BILL OF QUANTITIES

Sr. Rate Amount


Particulars Qty. Unit
No. In Figure In Words (Rs.)
1 Excavation for building foundation in all kinds of
soils (soft, hard, gravelly, murum etc.) including
trimming and dressing sides to true alignment /
design section / profile and grade, bailing out sub-
soil water or water from any other source,
timbering, strutting where required, backfilling the
trenches in 6" layers, and disposal of surplus
earth after backfilling the trenches at specified
location as directed by the Engineer In charge
including all leads and lifts, providing fence guard,
lights, flags and temporary crossings for non
vehicular traffic where ever required.

25 Cu.m

2 Providing & laying soling stones 6" to 9" size


under floors including packing with spawls, chips
& consolidating etc complete including all leads
and lifts up to site of works.
80 Sq.m

3 Cement concrete plain including placing


compacting, finishing and curing, complete
(including screening and washing of stone
aggregate) without shuttering .
Ratio 1:4:8. 5.00 Cu.m

4 Cement concrete plain including placing


compacting, finishing and curing, complete
(including screening and washing of stone
aggregate) without shuttering .
Ratio 1:3:6. 25.00 Cu.m

5 Supplying earth from approved outside sources


including digginhg, loading and unloading and
filling in foundatin trenches, plinth or under floor
etc. includig breaking clods, dressing, watering
and consolidation by ramming in layers not
ecxceeding 9 " in depth to full compaction
complete with all leads and lifts up to work site.

25.00 Cu.m

6 Providing & laying Reinforced cement concrete


work using graded crushed stone 3/4" (19 mm)
and down gauge having minimum works cube
crushing strength of 3000 psi @ 28 days with the
mix not leaner than 1:2:4. This rate also includes
all kinds of forms, moulds, lifting of shuttering,
curing rendering and finishing the exposed
surface including screening the crush, etc.
complete.(for culumns, footings , lintles, beams
and roof slabs)
30.00 Cu.m
Sr. Rate Amount
Particulars Qty. Unit
No. In Figure In Words (Rs.)

7 Providing reinforcement with & including the cost


of straightening, cutting, bending, binding,
wastage and placing on CC precast or MS chairs
and binding with binding wire, cost of chairs and
binding wire, including removal of rust etc.
complete in all respects.

(a) (i) MS Plain round bar 350 Kg.

(b) (ii) Tor bars with strength of 60000 psi 2015 Kg.

8 Providing and laying first class solid burnt brick


masonry set in cement mortar 1:6 in straight or
curved wall including scaffolding, raking out joints
and curing etc. complete in foundation, plinth and
ground floor super structure.
65.00 Cu.M

9 Providing & laying 1:9 cement concrete using


graded stone crushed 3/4" and down gauge in
terracing 3" avg. thickness to required slope in
pannels including form work consolidation,
finishing and curing etc and painting the surface
with Plastic bitumen no. 4 @ 15 lbs per 100 sft
blended with sand @ 2 cft per 100 sft, complete
on ground floor roof.
70.00 Sq.M

10 3/4" thick Cement Plaster 1:4 on walls and


columns etc. in basement, plinth, mezzanine and
ground floor including making edges, corners, and
curing etc., complete.
400.00 Sq.M

11 Providing and fixing 1-1/2" thick best quality


deodar wood shutter fully glazed with plain glass
panes 24 oz (7.3 kg./s.m) approved iron hinges,
tower bolts, deodar wood beading and putty
packing to glasses etc., complete.
20.00 Sq.m

12 Providing & laying floors of 3" thick 1:2:4 cement


concrete using graded crushed stone 3/4" and
down gauge in ground floors laid in pannels
including form works, consolidation, finishing and
providing and laying 3mm glass patties 1" depth,
curing etc complete.
160.00 Sq.m

13 Providing & fixing CC Jali of approved quality


jointing with 1:3 CC mortar complete in all respect.
10.00 Sq.m
Sr. Rate Amount
Particulars Qty. Unit
No. In Figure In Words (Rs.)
14 Distempering with vinyle distemper of approved
make and shade in 2 coats over and including the
cost of one priming coat of lime wash including
sand papering, dusting and filling the holes &
inequalities, in ground floor.
400.00 Sq.m

15 Preparing the surface & painting two coats on new


surface with weather coat including the rubbing
the surface with rubbing brick / sand paper, filling
the voids with chalk / plaster of Paris and then
painting with weather coat of approved make.

215.00 Sq.m

16 Primer coat on new work, such as timber work,


ceiling and timber boarding etc., of any
description, as specified. 10.00 Sq.m

17 2 coats of painting on new work, such as timber


work, ceiling and timber boarding etc. of any
description with synthetic enamel paint.
10.00 Sq.m

Total Rs.

(Rupees ________________________________________________________________________)
(In Words)

___________________ _________________________________________
CONTRACTOR