Data Warehouse Testing – Practical

Approach By Sharath
R Bhat
1

Table of Contents
............................................................................................................................................1
Data Warehouse Testing – Practical...................................................................................1
Approach By Sharath R Bhat ................................................................................1
1 ........................................................................................................................................2
Table of Contents ...............................................................................................................2
Introduction.........................................................................................................................3
2 Date warehouses Definition..............................................................................................3
3 Challenges of Data warehouse Testing.............................................................................3
4 Testing Methodology .......................................................................................................3
5 Testing Types....................................................................................................................4
5.1 Unit Testing...............................................................................................................4
5.2 Integration Testing.....................................................................................................5
5.3 Technical Shakedown Test........................................................................................5
5.4 System Testing .........................................................................................................6
5.5 User Acceptance Testing...........................................................................................7
5.6 Operational Readiness Testing (ORT).......................................................................7
6 Test Data...........................................................................................................................8
7 Conclusion........................................................................................................................8
Introduction
The characteristics of Data Warehouse applications pose a challenge for any
organization planning a Data Warehouse initiative: How can we be sure our data is
accurate and reliable when there are enormous amounts of it, and when it comes
from multiple systems with different data structures? The testing approach
described here combines practical experience implemented during testing Data
warehouse projects.

2 Date warehouses Definition


"A data warehouse is a subject oriented, integrated, time variant, non volatile
collection of data in support of management's decision making process".
There are three types of data warehouses:
1. Enterprise Data Warehouse - An enterprise data warehouse provides a central
database for decision support throughout the enterprise.
2. ODS (Operational Data Store) - This has a broad enterprise wide scope, but
unlike the real enterprise data warehouse, data is refreshed in near real time and
used for routine business activity.
3. Data Mart - Datamart is a subset of data warehouse and it supports a particular
region, business unit or business function.

3 Challenges of Data warehouse Testing


• Data selection from multiple source systems and analysis that follows pose great
challenge.
• Volume and the complexity of the data.
• Inconsistent and redundant data in a data warehouse.
• Inconsistent and Inaccurate reports.
• Non-availability of History data.

4 Testing Methodology
• Use of Traceability to enable full test coverage of Business Requirements
• In depth review of Test Cases
• Manipulation of Test Data to ensure full test coverage
Business Requirements
User Acceptance
Business Requirements System Requirements
Testing
Deployment Plan
Performance Requirement
Testing Business
Requirements
System Testing

Interface Design Intregration Testing Integration across


Functional Design
all designs

Software Components Testing against


Detailed Design Unit Testing
Design Detailed Design

Build

Fig 1 Testing Methodology (V- Model)


• Provision of appropriate tools to speed the process of Test Execution &
Evaluation
• Regression Testing

5 Testing Types
The following are types of Testing performed for Data warehousing projects.
1. Unit Testing.
2. Integration Testing.
3. Technical Shakedown Testing.
4. System Testing.
5. Operation readiness Testing
6. User Acceptance Testing.

5.1 Unit Testing


The objective of Unit testing involves testing of Business transformation rules, error
conditions, mapping fields at staging and core levels.
Unit testing involves the following
1. Check the Mapping of fields present in staging level.
2. Check for the duplication of values generated using Sequence generator.
3. Check for the correctness of surrogate keys, which uniquely identifies rows in
database.
4. Check for Data type constraints of the fields present in staging and core levels.
5. Check for the population of status and error messages into target table.
6. Check for string columns are left and right trimmed.
7. Check every mapping needs to implement the process abort mapplet which is
invoked if the number of record read from source is not equal to trailer count.
8. Check every object, transformation, source and target need to have proper
metadata. Check visually in data warehouse designer tool if every
transformation has a meaningful description.

5.2 Integration Testing


The objective of Integration Testing is to ensure that workflows are executed as
scheduled with correct dependency.
Integration testing involves the following
1. To check for the execution of workflows at the following stages
Source to Staging A.
Staging A to Staging B.
Staging B to Core.
2. To check target tables are populated with correct number of records.
3. Performance of the schedule is recorded and analysis is performed
on the performance result.
4. To verify the dependencies among workflows between source to staging,
staging to staging and staging to core is have been properly defined.
5. To Check for Error log messages in appropriate file.
6. To verify if the start jobs starts at pre-defined starting time. Example if the
start time for first job has been configured to be at 10:00AM and the Control-M
group has been ordered at 7AM, the first job would not start in Control-M until
10:00AM.
7. To check for restarting of Jobs in case of failures.

5.3 Technical Shakedown Test


Due to the complexity in integrating the various source systems and tools, there
are expected to be several teething problems with the environments. A Technical
Shakedown Test will be conducted prior to commencing System Testing, Stress &
Performance, User Acceptance testing and Operational Readiness Test to ensure
the following points are proven:
• Hardware is in place and has been configured correctly (including
Informatica architecture, Source system connectivity and Business
Objects).
• All software has been migrated to the testing environments correctly.
• All required connectivity between systems are in place.
• End-to-end transactions (both online and batch transactions) have been
executed and do not fall over.

5.4 System Testing


The objective of System Testing is to ensure that the required business functions
are implemented correctly. This phase includes data verification which tests the
quality of data populated into target tables.
System Testing involves the following
1. To check the functionality of the system meets the business specifications.
2. To check for the count of records in source table and comparing with the
number of records in the target table followed by analysis of rejected
records.
3. To check for end to end integration of systems and connectivity of the
infrastructure (e.g. hardware and network configurations are correct),
4. To check all transactions, database updates and data flows functions for
accuracy.
5. To validate Business reports functionality.

Reporting Ability to report data as required by Business using Business Objects


functionality
Report Structure Since the universe and reports have been migrated from previous
version of Business Objects, it’s necessary to ensure that the
upgraded reports replicate the structure/format and data
requirements (until and unless a change / enhancement has been
documented in Requirement Traceability Matrix / Functional Design
Document).
Enhancements Enhancements like reports’ structure, prompts ordering which were
in scope of upgrade project will be tested
Data Accuracy The data displayed in the reports / prompts matches with the actual
data in data mart.
Performance Ability of the system to perform certain functions within a prescribed
time.
That the system meets the stated performance criteria according to
agreed SLAs or specific non-functional requirements.
Security That the required level of security access is controlled and works
properly, including domain security, profile security, Data Security,
UserID and password control, and access procedures. That the
security system cannot be bypassed.
Usability That the system is useable as per specified requirements
User Accessibility That specified type of access to data is provided to users
Connection Test the connection
Parameters
Data provider Check for the right universe and duplicate data
Conditions/Selection Test the for selection criteria for the correct logic
criteria
Object testing Test the objects definitions
Context testing Ensure formula is with input or output context
Variable testing Test the variable for its syntax and data type compatible
Formulas or Test the formula for its syntax and validate the data given by the
calculations formula
Filters Test the data has filter correctly
Alerts Check for extreme limits Report alerts
Sorting Test the sorting order of Section headers fields, blocks
Totals and subtotals Validate the data results
Universe Structure Integrity of universe is maintained and there are no divergences in
terms of joins / objects / prompts

5.5 User Acceptance Testing


The objective of this testing to ensure that System meets the expectations of the
business users. It aims to prove that the entire system operates effectively in a
production environment and that the system successfully supports the business
processes from a user's perspective. Essentially, these tests will run through “a
day in the life of” business users. The tests will also include functions that involve
source systems connectivity, jobs scheduling and Business reports functionality.

5.6 Operational Readiness Testing (ORT)


This is the final phase of testing which focuses on verifying the deployment of
software and the operational readiness of the application. The main areas of
testing in this phase include:
Deployment Test
1. Tests the deployment of the solution
2. Tests overall technical deployment “checklist” and timeframes
3. Tests the security aspects of the system including user authentication and
authorization, and user-access levels.
Operational and Business Acceptance Testing
1. Tests the operability of the system including job control and scheduling.
2. Tests include normal scenarios, abnormal, and fatal scenarios
6 Test Data
Given the complexity of Data warehouse projects; preparation of test data is
daunting task. Volume of data required for each level of testing is given below.
Unit Testing - This phase of testing will be performed with a small subset (20%)
of production data for each source system.
Integration Testing - This phase of testing will be performed with a small subset
of production data for each source system.
System Testing – This phase of a subset of live data will be used which is
sufficient in volume to contain all required test conditions that includes normal
scenarios, abnormal, and fatal scenarios but small enough that workflow
execution time does not impact the test schedule unduly.

7 Conclusion
Data warehouse solutions are becoming almost ubiquitous as a supporting
technology for the operational and strategic functions at most companies. Data
warehouses play an integral role in business functions as diverse as enterprise
process management and monitoring, and production of financial statements.
The approach described here combines an understanding of the business rules
applied to the data with the ability to develop and use testing procedures that
check the accuracy of entire data sets. This level of testing rigor requires
additional effort and more skilled resources. However, by employing this
methodology, the team can be more confident, from day one of the
implementation of the DW, in the quality of the data. This will build the confidence
of the end-user community, and it will ultimately lead to a more effective
implementation.