Anda di halaman 1dari 9

MANAGEMENT CASE

CREW MANAGEMENT IN INDIAN RAILWAYS:


A CASE OF DELHI DIVISION

Vandana Srivastava

Information Systems are used in most organizations to provide solutions to certain problems. Irrespective
of whether they are developed in-house or procured, information systems tend to evolve. The Crew
Management System, at the Delhi Division of Northern Railway, is one such example. This case is used to
bring out the problems faced by large, traditional and bureaucratic organizations in handling and setting
up information systems. While most Information System (IS) solutions require a complete overhaul of the
organizational structures and working systems, the best way to implement an IS in such organizations is
parallel introduction and evolutionary approach. It aims to bring to the fore, the implementation and
operational difficulties associated with IS and how organizations need to adopt an evolutionary approach
to building information systems.

INTRODUCTION Background
“HOW much is the forecast? For two?! Is one on a light Indian Railways, the largest railway network in the world,
engine….? Then get them from Jind…. It is a mess! had over 62,000 route kilometres of track. [http://sify.com/
Nobody has matched power crew requirements….” It news/]. It employed about 1.6 million people, carried over
was work as usual at the office of Mr. Gupta on a cold 11 million passengers and one million tonnes of freight
January morning. Mr. Gupta had a problem on his hands. everyday. The railways was operating about 13,000 trains
As a Chief Power Controller of the Division, he was daily and had 6,984 railway stations. In order to be able to
heading the mechanical power wing of the Delhi Division handle operations of such large magnitude, the railways
of Northern Railway. One of his prime responsibilities was divided into 16 zones. Each zone was again divided
was to ensure the availability of running staff into divisions. Though each division across all zones of
(Locomotive Drivers and Assistant Drivers) for the the railways had some unique operational requirements,
trains. And today he was short of two! There was not by and large, they were very similar.
enough crew data to forecast the requirements and match
The Delhi Division [Annexure 1] of Northern
them to availability. This was an everyday affair. The
Railways, dealt with the highest number of long distance
stress levels were high. Mr. Gupta had been at this post
trains on Indian Railways. It had been divided into six
for the last five years and he realized that things could
sections which were continuously monitored and
not go on like this ….something had to be done!
controlled from New Delhi Control Office.

This case has been prepared by Mrs. Vandana Srivastava, Faculty, IILM Institute for Higher Education, Gurgaon, India. The author is grateful to Mr.
Santosh Sinha, Senior Divisional Mechanical Engineer, Delhi Division of Northern Railway, Prof. Ishwar Dayal, Distinguished Professor and Ex-
Director, IIM-Lucknow and Mr. Sanjeev Kishore, General Manager, RITES India Ltd., for their valuable guidance and support. This case has been
prepared as a basis for class discussions and does not depict correct or incorrect handling of the situation.
88 Srivastava

Crew Management maintained and provided running rooms for the running
staff. While most crew lobbies had living quarters for
Crew Management was a vital function performed in
the staff, some lobbies were transit lobbies, i.e., the
train operations on Indian Railways. It aimed at efficient
running staff did not have living quarters here. The clerk
deployment of running staff (Loco Drivers and Traffic
at the crew lobby maintained the record of the crew
Guards), ensuring availability wherever and whenever
signing in or signing off. Apart from this, crew members
required. The running staff was divisionally managed
would undergo breath- analyzer test at the lobbies and
but worked under three separate functional departments
the results were recorded. Any important message to be
viz., Traffic department (guards), Mechanical department
relayed to the running staff was handed over at the crew
(drivers, assistants, fireman for steam/diesel locomotives)
lobby. Therefore, the crew lobbies had all the information
and Electrical traction department (drivers and assistants
for the running staff.
for electric locomotives). Performance of staff had to be
monitored to ensure safety and reliability in the running Mr. Gupta had the administrative control over six
of trains. The running staff was governed by the out of eight crew booking lobbies of the division
provisions of hours of employment regulations. These [Annexure 1]. Of these six lobbies, all lobbies except
regulations laid down the rules for hours of duty DLI catered to crew for diesel engines only. Keeping in
performed per fortnight and the requirements of rest at mind the magnitude of operations, work had been
home station and outstation [Annexure 3]. allocated among lobbies.
Efficient crew and power management were The Old Delhi Crew Lobby (DLI) was the main Crew
essential for sufficient fluidity in train operations. Due Lobby for Mail/Express and Passenger trains. All major
to the higher priority and hence fixed schedule of Diesel and Electric Mail/Express and Passenger links
passenger trains, crew management for passenger trains allocated to the division were operated from here, with
was a streamlined process. Freight operations (goods all other lobbies being minor lobbies. The major freight
trains) were scheduled on the basis of requirement and lobbies were SSB (Shakur Basti) and JHI (Jind). Between
availability of slots and therefore, crew management them, DLI, SSB and JHI accounted for a total of 750
for freight operations had to be done as and when running staff, that is, about 250 running staff each! Apart
required. An improper crew forecasting for freight from handling through traffic, these lobbies were
trains would lead to non-availability of running staff responsible for placement and withdrawal of rakes (goods
for freight trains. This would create problems in the wagons) for loading by the division.
freight train scheduling and result in loss of revenue
for the railways. Moreover, the number of passenger Crew Management at Delhi Division: The Past
trains and magnitude of freight operations would
increase every year. This added strain to an already Crew Management formed just a part of Mr. Gupta’s
stretched system. Hence, efficient crew management work. He not only had to be aware of crew status but
has become even more important. also be able to forecast the requirements and match the
crew availability to the forecast. This required complete
control: knowing and monitoring the running staff
Some Facts about the Crew Scenario at Mechanical
movement over geographically separated lobbies of the
Power Wing of Delhi Division
division.
Mr. Gupta was heading the mechanical power wing
[Annexure 2] of the Delhi Division, which looked after
the maintenance and operation of seven Running The Manual System
Rooms1, six crew booking lobbies2, three Rail Diesel Crews were booked manually from either various lobbies
Installations3, one ‘A’ class Accident Relief Train where they were headquartered or from outstation lobbies
including 140 tonne crane and the Heritage Steam Care touched during train operations. The manual system
Centre4 at Rewari. Managing freight and crew operations operated as follows: on reporting arrival crews were
was the main activity of the Power Wing. granted home rest or outstation rest, as the case may be.
The running staff strength for the power wing of the After completion of scheduled rest, these crews were
Delhi Division was 1200. They would report for duty at made available for freight operations. Crew availability
various crew lobbies over the division. The division was calculated on the basis of reported arrivals. All

VISION—The Journal of Business Perspective Vol. 10 No. 3 July-September 2006


● ● ●
Crew Management in Indian Railways: A Case of Delhi Division1 89●

information about crew availability status was recorded and taken up for resolution as part of MIS project
manually at the lobbies and reported manually to the sanctioned by Railway Board in August.
Power Control at Delhi.
The modules for computerized crew management
were developed as a part of Mechanical MIS for Southern
Some of the Problems with the Manual System Railway by M/S BITECH, Chennai. It had been tested
● It was very difficult to ascertain the location of each successfully in various divisions of Southern and South
crew at any given moment. Complete crew picture Western Railways (SR and SWR, henceforth). In
was rarely available. The Divisional Power Control September, Mr. Gupta was nominated to monitor the
(PRC, henceforth), operating under Mr. Gupta’s implementation of the Mechanical MIS modules in the
directions, would take regular telephonic feedback DLI division.
from various lobbies for monitoring.
Crew Management: The Present
● Depending upon Traffic forecasts, crew balancing,
i.e., spare crew movement between various lobbies
was finalized by PRC. Since PRC’s crew position Crew Management System at the Lobbies
was also based on reported arrivals, accurate crew The system was a client-server software. The server
position was not available. Sometimes in an eight- software was developed in Oracle 8i whereas the client
hour shift PRC was not be able to talk even once end had the software in Oracle 6i. The front end was
every hour to each Crew Lobby. Consequently, not designed in Visual Basic. The system aimed to streamline
only would matching of crew with traffic forecasts the manual work by providing a computerized solution.
suffer rather proper traffic planning would become
Even though the software was network-enabled, yet
a casualty leading to detentions of freight trains.
no networking with Divisional Control had been done
● Divisional control was not on real time basis and in any lobbies of Southern and South Western railways,
there was always an element of delay. Even the 10- where it was installed earlier. All lobbies in SR and SWR
hour position, when required, took at least two days were working on a stand-alone basis. When the system
to be compiled from all lobbies. was implemented at the DLI division it was again setup
● It was frequently seen that mileage earnings were as stand-alone system in the various lobbies. Such an
not equal between all crews. While some crews were implementation computerized the work at the lobbies.
over-utilized, there were others who were To meet software/networking requirements one
underutilized. server (Intel Xeon 2.8 GHz) at NDLS Control and
● Updated Current Crew Refresher and Leave Reserve sufficient number of client end Personal Computers (PC,
details were not available in the division. henceforth) (P4- 3.0 GHz) were procured and were
distributed to all lobbies, Power control, Operating and
● Crew revenue calculations were done manually Headquarter. The hardware procurement was completed
which would at times be inaccurate and delayed. in May next year.
● On the safety front, while breath-analyzer test was
mandatory, its enforcement remained sluggish. Advantages of the System
Moreover, Mr. Gupta knew that the DLI division At the lobbies, the system could generate the reports
was set for an increase in running staff by about 200 in regarding sign-on details for all services, daily crew
the coming few months. This would have increased performance including rest details, crew absence details,
pressure on the manual system. over-due details, consolidated biodata, and payment
reports, etc.. Optimized crew-utilization and mileage
equalization among the crew became possible. It became
Systems Solution: The Crew Management System
easier to manage crew data, training backlogs, etc. The
The problems with the manual crew booking and problems associated with manual calculation of payment
monitoring system were not confined to DLI division were also ruled out. All allowance calculations were
alone but were prevalent all over the Indian Railways. accurate and payments were timely, which saved
Crew Management System was identified as the solution substantial time and effort of the staff.
VISION—The Journal of Business Perspective Vol. 10 No. 2 July-September 2006
● ● ●
90 Srivastava

Problems with the System in Delhi Area and Remote Location Networking. He
decided to develop an exclusive WAN for the four
Though the Crew Management System streamlined work
locations in Delhi area (DLI, NDLS, SSB and DEE).
at the lobbies of the Delhi Division, yet, Mr. Gupta’s
Remote areas were decided to be connected through
troubles were not over. Due to lack of networking, the
VPN, VSAT or ISDN etc to the WAN.
crew availability across the various crew lobbies of the
division was still calculated manually. Hence, forecasting
and most of the control work was still done manually Wireless Networking in Delhi Area
and continued to be problematic. “Connecting the lobbies in Delhi area is not a problem”,
thought Mr. Gupta. He decided to take advantage of
The Next Step: Implementation of Networked Crew delicensing of 2.4 GHz bandwidth by DOT and went in
Management Modules for Wireless Networking in DLI Area. Towers were
erected at the four locations in DLI area (DLI, NDLS,
The main task was now to network the division.
SSB and DEE) and radio transmitters installed. NDLS
Networking the division was a challenge since Crew
was the central location with direct access to DLI and
Lobby networking over large distances had not been tried
DEE. A repeater for SSB was installed at DEE because
anywhere else over the Indian Railways. Mr. Gupta
no direct line of sight was available.
chalked-out a step-wise plan.
Remote location networking still continued to pose
The First phase involved verifying the software’s
greater challenges. The aim was to have uninterrupted
network connectivity and adaptability features before
connectivity at required bandwidth with minimal, if not
proceeding with hardware purchase. The connectivity
fixed, running costs. The following options were tried:
was verified on railnet, the leased line for the railways,
between Shakur Basti (SSB) and Power Control, New 1. Virtual Private Network (VPN) - Connectivity could
Delhi, using the existing hardware. The server was placed be established through VPN on dialup internet but
at PRC, NDLS (New Delhi) and client at Shakur Basti. the bandwidth available was insufficient.
2. VSAT installations were set up at on a trial basis at
The Big Challenge JHI in association with M/s HCL Comnet. This
With the first phase successfully over, Mr.Gupta decided technology was the same as that being used for
to go ahead to the Second Phase: Lobby Networking. nationwide ATMs. Years of successful use had made
The biggest challenge was networking: it a viable option. Though connectivity was
established, sufficient bandwidth could not be
1. Railnet was not a viable option because of obtained.
insufficient bandwidth. Trials between SSB-NDLS
indicated a severe bandwidth restriction and 3. Available DOT telephone lines at JHI and MTC
inordinately high time was taken in data transfer. It were converted into ISDN lines. Connectivity was
was observed that a minimum of 64 kbps was established and workable bandwidth was available
required for a workable speed of data transfer. on which crew booking modules could operate
Moreover, railnet was available only at New Delhi, satisfactorily. To reduce costs, one PC each at JHI
Old Delhi and Shakur Basti. JHI, MTC and DEE and MTC were converted into local servers. Now,
[Annexure 1] were not connected on Railnet. It ISDN connectivity was used only for viewing reports
seemed that a sturdier option was required. for monitoring purposes. All time connectivity was
not provided in order to cut down costs. The system
2. Cost of networking was another constraint. Solutions allowed periodical reports to be stored in the local
with fixed and low periodic costs were preferred server, to be downloaded as per requirement.
because amount of data transfer would be huge and
network engagement would be high.
Present Status and Further Action to be Taken
Networking the Division Another six months had passed. The mechanical power
In order to handle this, Mr. Gupta’s boss advised him to wing now had a network with a bandwidth of 2 Mbps
break the problem into two parts: Wireless Networking exclusively for its use. The entire networking was

VISION—The Journal of Business Perspective Vol. 10 No. 3 July-September 2006


● ● ●
Crew Management in Indian Railways: A Case of Delhi Division1 91 ●

completed in just Rs.4,00,000. The running cost was left for him at this post, since in the Railways officers
almost nil with no recurring costs such as rental, etc. had tenured postings. He wondered whether his successor
would be able to upgrade the system further. He
All lobbies were now computerized and networked
wondered how he could make the system robust enough
with PRC, New Delhi. Jakhal was the only exception
to endure people and technology changes.
since no crew was headquartered there and therefore a
crew database could not be created. The modules for crew
booking were working smoothly and were connected to Questions
the PRC. Even after providing bandwidth for crew 1. Was getting the MIS such a good idea?
booking module, sufficient space was available. At a
minimal cost increase video conferencing facility could 2. What should Mr. Gupta do next to improve the
be incorporated. Surprise breath analyzer tests could now results and to enhance the system?
be conducted in full view and this had bolstered safety 3. If Crew Lobby networking was the solution, what
aspects. Cameras were installed in all lobbies and PRC were the challenges facing Mr. Gupta?
and full duplex video-conferencing facility was made
available. This was the first case of such long-distance 4. Which networking technology would best suit future
wireless network including video-conferencing over requirements?
Indian Railways. 5. What were the difficulties faced by Mr. Gupta in
Mr. Gupta was in a dilemma. He had achieved a lot. setting up an IS?
But he also knew that the introduction of Information 6. Based on this case, comment on the organizational
System in any organization was not a one-time task. With culture of the Railways.
ever-changing technology, anything that was new today
would very soon become obsolete. Only one year was 7. How can Information Systems sustain technological
and human changes?

ANNEXURE 1

HISTORY OF DELHI DIVISION


The DRM (Divisional Railway Manager) heads the Delhi Division. Serving Haryana, Delhi and Uttar Pradesh,
Delhi Division has a route kilometerage of 1192.95 Kms with 158 stations. It handles 496 Passenger carrying
trains and 210 Freight trains everyday. The original station to serve the capital of India, Delhi Junction came into
existence in April 1864 when a temporary building was constructed. At that time nobody could have imagined
that the station designed to deal with 100 passengers a day would ultimately have to deal with 1,00,000 passengers
per day. Planning for construction of the present building commenced in 1890. The station was built in the style
of the Mughal period, resembling both mosque and fortress. It could be used a hotel as well as a shelter during
emergencies, with provision for security personnel gaining rapid access to the top in order to take up defensive
positions. This was an important consideration for the British as the neighboring Chandni Chowk area was the
epicenter of political activity.
Delhi Division generates the highest revenue of all the Divisions of Northern Railway, amounting to around
Rs. 746 lakhs everyday. Of this Rs. 456 lakhs comes from the 7.4 lakhs passengers booked every day while Rs.
222 lakhs comes from freight.

Crew Lobbies under administrative control of Delhi Division


JHL Jakhal DEE Delhi Sarai Rohilla
JHI Jind DLI Old Delhi
SSB Shakur Basti MTC Meerut City

VISION—The Journal of Business Perspective Vol. 10 No. 2 July-September 2006


● ● ●
92 Srivastava

ANNEXURE 2

ORGANIZATIONAL CHART

General Manager
DRMs
Delhi
Addl.General Manager
DRMs
Lucknow
SDGM CDM CCM COS CSO
DRMs
Vigliance Operating Commercial Stores Safety
Moradabad

CE CME CEE DRMs


Civil Engineering Mechanical Engineering Electrical Engineering Firozpur

DRMs
Ambala
CSC CMD CAD(C) FA&C&O CPO
Security Medical Construction Accounts Personnel

CSTE CPRO
Signal & Telecommunication Public Relations

Divisional Rly. Manager

Add. Divisional Rly. Add. Divisional Rly.


Chief Traffic Manager Chief Medical Spuds.
Manager (Operation) Manager (Technical)

Sr. Divisonal Sign. & Sr. Divisonal


Sr. Divisional
Telecom Engineer Personal Officer Sr. Divisonal
Operational Manager
Commercial Manager
Sr. Divisonal Sr. Divisonal
Sr. Divisional Mechanical Engineer/ Account Officer
Operational Manager C&W, Goods, liason DTM/ Shatabdi
(Planning) Sr. Divisonal Security
Divisonal Sign. Engineer/ Commissioner
Divisional Mechanical I, II, III, IV, E, C DCM/ Catering
Engineer (Operation)
Sr. Divisonal Electrical Eng-
Sr. Divisional Elec- ineer TRD., Chg., G, EMU, Loco
trical Engineer (RSO)
Sr. Divisonal
Controller of Stores

Sr. Divisonal Mechanical


Engineer/ SSB, TKD

VISION—The Journal of Business Perspective Vol. 10 No. 3 July-September 2006


● ● ●
Crew Management in Indian Railways: A Case of Delhi Division1 93 ●

ANNEXURE 3

HOURS OF EMPLOYMENT REGULATIONS FOR RUNNING STAFF

Salient Features of Hours of Employment Regulation for Running Staff (Traffic and Loco)
a. Hours of work –As a general rule, duties of running staff are classified as continuous. Statutory limit for hours
of employment of such staff has been fixed at 54 hrs a week on an average in a month
b. Duty Hours – Duty hours of running staff is counted from Signing On to Signing off. Time allowed for taking
over and making over forms part of their duty hours.
c. The overall duty at a stretch for running staff from signing on should not ordinarily exceed 12 hrs and they are
entitled to claim relief thereafter. The running duty should not ordinarily exceed 10 hrs from the departure of
the train and the staff should be entitled to claim relief thereafter. However, in operational and exceptional
exigencies (Accidents, floods, agitations, equipment failures etc) staff may work beyond these limits.
d. Rest for Running Staff – Rest is based on total duty performed on a particular trip.
i. Rest at Headquarters
1. 12 hrs when duty performed is less than 8 hrs.
2. 16 hrs when duty performed is 8 hrs or more.
ii. Rest at Outstation:
1. 06 hrs when duty performed is less tan 9 hrs.
2. 08 hrs when duty performed is 9 hours or more
e. Periodic Rest – In one calendar month, periodic rest may be given to running staff in the following manner:
4 periods of rest of not less than 30 consecutive hrs each, or 5 periods of rest of not less than 22
consecutivehrs each.
Such rest should be given at headquarters and must include a full night in bed (2200hrs to 0600hrs).
f. Away from headquarters – Running staff should not normally be away from headquarters for more than 3 to
4 days at a stretch.
g. Waiting for duty – The time during which a running staff is waiting for duty, and not resting, should be
included in the hours of employment
h. Continuous night duty – Night duty should not exceed six nights at a stretch.
i. Overtime –Normally a staff should be made to perform 104 cumulative hours of duty in a 14 day fortnightly
period. In case his duty hours exceed 104 hrs he is entitled to overtime allowance.
j. If a person is sent as spare on jobs, only the duration from train arrival to train departure is to be include in his
HOER list whereas in normal duty sign on to sign off duration is considered.
k. If a staff has to stay outstation for more than 16 hrs, he is entitled to one unit of overrest allowance which is
equal to a credit of 70 kms. Progressively, for every additional twenty four hrs, he is entitled for one more unit
of overrest allowance.
l. A Shunter, if sent outstation for shunting duty purposes gets one unit of outstation allowance (70 kms) if he is
stopped at the outstation administratively for every additional day of stay.

VISION—The Journal of Business Perspective Vol. 10 No. 2 July-September 2006


● ● ●
94 Srivastava

NOTES
1. Running rooms—waiting rooms for the running staff to rest between shifts.
2. Crew booking lobbies—offices where the running staff sign-in or sign-off from their duty.
3. Locations within the division where fuelling of diesel locomotives took place.
4. The division had a few steam engines for running the Heritage Steam Trains over short distances for tourists.
These trains and locomotives were maintained at the Heritage Steam Care Centre at Rewari.

Vandana Srivastava, (vandana.srivastava@iilm.in) is associated with IILM Institute for almost two years, teaching various courses
of Information Management to students of PGDM. She has over seven years experience in teaching Physics and Computer Science at
undergraduate and postgraduate levels at Punjab, K.C College, Mumbai and Ansal Institute of Technology, Gurgaon. Her areas of
interest include Analysis and Design of Information Systems, Artificial Intelligence and Neural Networks. Her research interests lie in
Quality in IT enabled services and Inter-organizational Information Systems.

VISION—The Journal of Business Perspective Vol. 10 No. 3 July-September 2006


● ● ●

Anda mungkin juga menyukai