TUGAS
Laporan ini disusun untuk memenuhi salah satu syarat menyelesaikan pendidikan
Diploma IV Program Studi Teknik Perawatan dan Perbaikan Gedung
Jurusan Teknik Sipil
Oleh:
2020
PERENCANAAN METODE PELAKSANAAN PONDASI
TIANG PANCANG PATRA HOTEL & CONVENTION
CJREBON
Oleh:
Pembimbing I Pembimbing II
~
Antonius Siswanto, Drs., SST., MT.
NIP. 19610118 198603 1 001
Djuwadi, Drs., MT.
NIP. 19571107 198403 1 001
ABSTRAK
iv
ABSTRACT
Patra Cirebon Hotel & Convention building is located on Jl. Tuparev No.11,
Sutawinangun, Kedawung, Cirebon, West Java. This building is a type of
residential building. This building has a total of twelve floors with one besment
floor. The foundation used in this building is a reinforced concrete pile foundation
with a size of 40 x 40 cm.
Based on the data it is known that the required number of piles is 481 piles
with 15 types of pile caps. During the implementation, heavy equipment such as
excavators, dump trucks, hydraulic static pile driver (HSDP), crawler crane and
concrete pump were used. From the calculation results, it is found that the erection
and pile cap work time is 136 working days at a cost of Rp. 52,439,937,691 (Fifty-
two billion four hundred and thirty-nine million nine hundred thirty-seven thousand
six hundred and ninety-one rupiah).
v
KATA PENGANTAR
Puji syukur kami panjatkan kehadirat Allah SWT. Kerena atas ridha-Nya
penulisan tugas akhir yang berjudul “Perencanaan Metode Pelaksanaan Pondasi
Tiang Pancang Patra Hotel & Convention Cirebon” dapat berjalan dengan lancar.
Shalawat serta salam kami curahkan kepada baginda Rasulullah Muhmmad SAW,
keluarga dan para sahabat.
1. Tuhan Yang Maha Esa Allah SWT yang telah meridhai dalam penulisan
laporan tugas akhir ini,
2. Kedua orang tua dan keluarga yang senantiasa memberikan dukungan moril
ataupun materil,
3. Bapak Siswanto selaku dosen pembimbing pertama dan Bapak Djuwadi selaku
dosen pembimbing kedua yang senantiasa membimbing kami dalam penulisan
laporan tugas akhir ini,
4. Bu Ery selaku dosen punguji dalam pelaksanaan pekerjaan laporan tugas akhir
ini,
5. Bapak Ujang Ruslan selaku dosen penguji dalam pelaksanaan laporan tugas
akhir ini,
6. Seluruh dosen, teknisi dan staff jurusan Teknik Sipil Politeknik Negeri
Bandung yang telah membimbing kami dari awal perkuliahan hingga saat ini.
Kritik dan saran kami terima sabagai masukan untuk penulisan laporan tugas
akhir ini. Semoga laporan tugas akhir ini dapat bermanfaat bagi kita semua.
vi
Akhir kata kami ucapkan terimakasih banyak kepada semua pihak yang
telah membimbing selama penulisan tugas akhir ini. Semoga Allah SWT membalas
semua kebaikan yang telah diberikan.
vii
DAFTAR ISI
LEMBAR PENGESAHAN................................................................................... i
ABSTRAK ......................................................................................................... iv
ABSTRACT ........................................................................................................ v
I. 2. Rumusan Masalah.................................................................................. 1
I. 3. Tujuan ................................................................................................... 2
viii
III. 3. Analisis Perancangan Biaya Pelaksanaan ......................................... 46
ix
IV. 6. 7. Pekerjaan Pemasangan Bekisting Pile Cap .............................. 126
x
DAFTAR LAMPIRAN
xi
DAFTAR GAMBAR
Gambar I.1 Gambar Tampak Bangunan Gedung Patra Hotel & Convention
Cirebon ................................................................................................................ 3
Gambar II.1 Ilustrasi Pekerjaan Surveying Kolom. ............................................. 8
Gambar II.2 Ilustrasi Pekerjaan Pembesian Kolom. ............................................ 9
Gambar II.3 Ilustrasi Pekerjaan Pemasangan Bekisting Kolom. ......................... 9
Gambar II.4 Ilustrasi Pekerjaan Pengecoran Kolom. ....................................... 10
Gambar II.5 Gambar Ilustrasi Pekerjaan Pembuatan Balok.............................. 11
Gambar II.6 Gambar Ilustrasi Pekerjaan Pembuatan Plat Lantai. ..................... 12
Gambar II.7 Gambar Ilustrasi Pekerjaan Pembuatan Tangga. .......................... 13
Gambar II.8 Gambar Ilustrasi Dinding Penahan Tanah Massa. ........................ 15
Gambar II.9 Gambar Ilustrasi Dinding Penahan Tanah Turap.......................... 16
Gambar II.10 Gambar Ilustrasi Dinding Penahan Tanah Diaphragm Wall. ...... 16
Gambar II.11 Gambar Ilustrasi Dinding Penahan Tanah Contiguous Bored Pile.
.......................................................................................................................... 17
Gambar II.12 Gambar Ilustrasi Pondasi Tapak. .............................................. 18
Gambar II.13 Gambar Ilustrasi Pondasi Menerus. ........................................... 18
Gambar II.14 Gambar Ilustrasi Pondasi Rakit. ................................................ 19
Gambar II.15 Gambar Ilustrasi Pondasi Sumuran. ........................................... 19
Gambar II.16 Gambar Ilustrasi Pondasi Bored Pile. ........................................ 20
Gambar II.17 Tiang Pancang Kayu. ................................................................ 21
Gambar II.18 Gambar Ilustrasi Maxipile dan Minipile. .................................... 22
Gambar II.19 Tiang Pancang Beton................................................................. 22
Gambar II.20 Tiang Pancang Baja................................................................... 23
Gambar II.21 Tiang Pancang Komposit........................................................... 24
Gambar II.22 Gambar Ilustrasi Drop Hammer. ............................................... 24
Gambar II.23 Gambar Ilustrasi Diesel Hammer. .............................................. 25
Gambar II.24 Gambar Ilustrasi Hydraulic Static Pile Driver. .......................... 26
Gambar II.25 Gambar Ilustrasi Vibratory Pile Driver. ..................................... 26
Gambar II.26 Gambar Ilustrasi Axial Load Test Tekan ..................................... 27
Gambar II.27 Gambar Ilustrasi Axial Load Test Tarik ...................................... 28
Gambar II.28 Gambar Ilustrasi Lateral Load Test Metode Kentledge ............... 29
xii
Gambar II.29 Gambar Ilustrasi Lateral Load Test Metode Pile to Pile.............. 29
Gambar II.30 Gambar Ilustrasi Pile Driving Analyzer (PDA) ........................... 30
Gambar II.31 Gambar Macam-macam Bentuk Pile Cap................................... 31
Gambar III.1 Diagram Alir Pengerjaan Tugas Akhir. ....................................... 44
Gambar IV.1 Denah Pondasi Patra Hotel & Convetion Cirebon....................... 49
Gambar IV.2 Detail dan Potongan Pondasi pada Pile Cap TP-1A.................... 50
Gambar IV.3 Detail dan Potongan Pondasi pada Pile Cap TP-1. ...................... 51
Gambar IV.4 Detail dan Potongan Pondasi pada Pile Cap TP-2A..................... 51
Gambar IV.5 Detail dan Potongan Pondasi pada Pile Cap TP-2. ...................... 52
Gambar IV.6 Detail dan Potongan Pondasi pada Pile Cap TP-3. ...................... 52
Gambar IV.7 Detail dan Potongan Pondasi pada Pile Cap TP-4. ...................... 53
Gambar IV.8 Detail dan Potongan Pondasi pada Pile Cap TP-5. ...................... 53
Gambar IV.9 Detail dan Potongan Pondasi pada Pile Cap TP-6. ...................... 53
Gambar IV.10 Detail dan Potongan Pondasi pada Pile Cap TP-8A................... 54
Gambar IV.11 Detail dan Potongan Pondasi pada Pile Cap TP-8. .................... 54
Gambar IV.12 Detail dan Potongan Pondasi pada Pile Cap TP-9. .................... 55
Gambar IV.13 Detail dan Potongan Pondasi pada Pile Cap TP-11. .................. 55
Gambar IV.14 Detail dan Potongan Pondasi pada Pile Cap TP-16. ................. 56
Gambar IV.15 Detail dan Potongan Pondasi pada Pile Cap TP-48. .................. 56
Gambar IV.16 Detail dan Potongan Pondasi pada Pile Cap TP-96. .................. 57
Gambar IV.17 Lokasi Penyelidikan Tanah. ...................................................... 58
Gambar IV.18 Data Pengujian Tanah BH-1. ..................................................... 59
Gambar IV.19 Data Pengujian Tanah BH-2. ..................................................... 60
Gambar IV.20 Statigrafi Tanah berdasarkan Gambar BH-1 dan BH-2. ............. 61
Gambar IV.21 Gambar Ilustrasi Kebutuhan Tiang Pancang yang Tertanam. ..... 62
Gambar IV.22 Pembagian Zona Pekerjaan Pondasi Tiang Pancang .................. 63
Gambar IV.23 Gambar Diagram Alir Pekerjaan Pemancangan. ........................ 70
Gambar IV.24 Lokasi Penyimpanan Tiang Pancang. ........................................ 73
Gambar IV.25 Gambar Penempatan Tiang Pancang. ........................................ 74
Gambar IV.26 Ilustrasi Pekerjaan Surveying. ................................................... 75
Gambar IV.27 Alur Pekerjaan Pemancangan. ................................................... 76
Gambar IV.28 Gambar Ilustrasi Pemasukan Tiang Pancang ke Clamping Box . 77
xiii
Gambar IV.29 Gambar Ilustrasi Penekanan Tiang Pancang .............................. 77
Gambar IV.30 Gambar Ilustrasi Pengelasan Tiang Pancang ............................. 78
Gambar IV.31 Denah Lokasi Test Pile. ............................................................ 79
Gambar IV.32 Gambar Ilustrasi Pemasangan Transducer dan Accelerometer. .. 80
Gambar IV.33 Gambar Ilustrasi Proses Penumbukan Pile Driver Test (PDA)... 81
Gambar IV.34 Diagram Alir Pekerjaan Pile Cap. ............................................. 85
Gambar IV.35 Gambar Ilustrasi Penggalian untuk Pile Cap. ............................ 86
Gambar IV.36 Gambar Ilustrasi Pemotongan dan Pembobokan Tiang. ............. 87
Gambar IV.37 Gambar Ilustrasi Pekerjaan Pembesian. ..................................... 88
Gambar IV.38 Gambar Ilustrasi Pekerjaan Pengecoran..................................... 89
Gambar IV.39 Gambar Work Breakdown Structure. ......................................... 90
Gambar IV.40 Menghitung Volume Galian Pile Cap TP 1-A. .......................... 93
Gambar IV.41 Menghitung Volume Urugan Pasir Pile Cap TP 1-A. ................ 95
Gambar IV.42 Menghitung Volume Lantai Kerja Pile Cap TP 1-A. ................. 97
Gambar IV.43 Gambar Detail Pile Cap TP-1A................................................. 98
Gambar IV.44 Gambar Untuk Perhitungan Volume Tulangan .......................... 99
Gambar IV.45 Menghitung Quantity Bekisting Batako Pile Cap TP 1-A. ....... 101
Gambar IV.46 Menghitung Volume Lantai Kerja Pile Cap TP 1-A. ............... 103
Gambar IV.47 Gambar Input Uraian Pekerjaan .............................................. 171
Gambar IV.48 Gambar Input Durasi Pekerjaan............................................... 172
Gambar IV.49 Gambar Input Hubungan Pekerjaan. ........................................ 172
Gambar IV.50 Gambar Hasil Waktu Pelaksanaan. .......................................... 173
xiv
DAFTAR TABEL
xv
Tabel IV.22 Analisa Harga Satuan Pekerjaan 1 m³ Beton Mutu, f’c = 10 MPa
Menggunakan Ready Mixed dan Pompa Beton. ................................................ 142
Tabel IV.23 Tabel Analisa Harga Satuan Pekerjaan Pembesian 10 Kg dengan Besi
Polos atau Ulir. ................................................................................................ 143
Tabel IV.24 Tabel Analisa Harga Satuan Pekerjaan 1 m2 Pasangan Batako (10 x
20 x 40) cm tebal batu campuran 1SP : 3PP. ................................................... 147
Tabel IV.25 Tabel Analisa Harga Satuan Pekerjaan 1 m³ Beton Mutu, f’c = 35 MPa
Menggunakan Ready Mixed dan Pompa Beton. ................................................ 149
Tabel IV.26 Bill of Quantity. ........................................................................... 150
Tabel IV.27 Tabel Rencana Anggara Biaya Pelaksanaan. ................................ 160
Tabel IV.28 Rekap Durasi Pekerjaan. .............................................................. 170
xvi
Daftar Pustaka
H. S, Sardjono. 1988. “Pondasi Tiang Pancang Jilid Satu”. Surabaya: Sinar Wijaya.
PT. Wijaya Karya. 2019. “Buku Manual Produk Pc Spun Pile”. Jakarta.
http://www.cranesxcmg.com/XCMG-25-ton-Telescopic-Crawler-Crane-
XGC25T-pd814834.html (diakses pada 31 Agustus 2020 pukul 22.40 WIB)
https://www.oto.com/en/truk-baru/hino/ranger-dump-fm-260-jd/spesifikasi
(diakses pada 1 September 2020 pukul 00.22 WIB)
I
https://nikifour.co.id/4-jenis-alat-pemasang-tiang-pancang/ (diakses pada 27
Agustus 2020 pukul 22.02 WIB)
II