Anda di halaman 1dari 14

VOLUME PERHITUNGAN BANGUNAN

PerhitunganVolume Ruko 3 Lantai


No JENIS PEKERJAAN VOLUME
A. PEKERJAAN PERSIAPAN

1. Pembersihan Lahan Luas =p×l


= 14m × 5m
= 70 m2
2. Pembuatan Direksi Keet Luas =p×l
= 3m × 3m
= 9 m2
3. Bowplank Panjang = 6m + 15m + 6m + 15m
= 42 m
4. Gudang Bahan / Peralatan Luas =p×l
= 3m × 3m
= 9 m2
5. Pembuatan Pagar Keliling Keliling = 2 × (p + l)
= 2 × (14 + 5)
= 38 m
No JENIS PEKERJAAN VOLUME
6. Biaya Air Kerja 1 ls
7. Biaya Listrik Kerja 1 ls
B. PEKERJAAN TANAH
1. Pekerjaan Galian
Galian Pondasi Footplat
a. Pond. Footplat Tipe P1 Volume = (p × l × t) × Jumlah Tipe P1
= (1,6× 1,6 × 1,05) × 6
= 16,13 m3
b. Pond. Footplat Tipe P2 Volume = (p × l × t) × Jumlah Tipe P2
= (1,6 × 1,6 × 1,05) × 2
= 5,38 m3
Galian Pondasi Pasangan Batu Volume = (p × l × t) × Jumlah Tipe PB Gn
Gunung = (1× 1,5 × 1,1) × 1
= 1,65 m3
Sloof
a. Sloof 1 Volume = Luas S1 × Panjang S1
= (0,2 × 0,5) × 52,975
= 5,2975 m3
b. Sloof 2 Volume = Luas S2 × Panjang S2
= (0,2 × 0,3) × 4,55
= 0,273 m3
2. Timbunan
a. Footplat P1 0,6+0,8
Volume = ((( ) × 1,4 × 1,6) + (0,05 ×
2
1,05 × 1,6 )) × 6
= 7,23 m3 14,45
b. Footplat P2 0,6+0,8
Volume = ((( ) × 1 × 1,6) + (0,05 ×
2
1,05 × 1,6)) × 2
= 2,41 m3
c. Pasangan Batu Gunung 0,6+0,2
Volume =( ) × 1,1 × 1
2
= 0,44 m3
d. Dalam Denah (Sloof) Volume = ((5 – 0,15) × (14 – 0,15) × 0,3)
= 20,16 m3
No JENIS PEKERJAAN VOLUME
C. PEKERJAAN PENGECORAN
1. Cor Pondasi
a. Cor Pondasi P1 Tinggi 1+Tinggi 2
Volume = (( 2 ) )
× sisi × sisi +

(p
× l × t)) × Jumlah Pondasi
=

0,8+0,4
(( 2 ) )
× 1,4 ×1,6 +(0,2× 1,6× 0,4 5)¿× 6

= 8,5 m3
b. Cor Pondasi P2 Tinggi 1+Tinggi 2
Volume = (( 2 )
× sisi × sisi +
)
(p
× l × t)) × Jumlah Pondasi
=

(( 0,4+0,2
2 ) ×1,05 ×1,6)+(0,5 5 ×1,6 ×0,4 5) ¿ ×2
= 1,8 m3
c. Cor Pondasi Pasangan Batu Gunung a+b
Volume = (( ) )
2
× t ×l + (p × l × t ))

× Jumlah Pondasi
0,4+0,8
= (( 2 ) )
× 1 + (1 × 1,5 × 0,2)

×1
= m3
2. Pelat Lantai (cor)
Pelat Lantai = Luas lantai × 0,05 × 2 – (luas void × 0,12 × 2)
= ((14 × 5) × 0,12 × 2) – (3,3 × 1 × 0,12 × 2)
= 16,8 – 0,792
= 16,008 m3
3. Kolom
Lantai 1
Kolom K1 = Tinggi kolom × luas kolom × jumlah kolom
= 4 × (0,15 × 0,3) × 8
= 1,44 m3
Kolom K2 = Tinggi kolom × luas kolom × jumlah kolom
= 4 × (0,15 × 0,15) × 5
= 0,45 m3
No JENIS PEKERJAAN VOLUME
Lantai 2
Kolom K1 = Tinggi kolom × luas kolom × jumlah kolom
= 3,6 × (0,15 × 0,3) × 8
= 1,296 m3
Kolom K2 = Tinggi kolom × luas kolom × jumlah kolom
= 3,6 × (0,15 × 0,15) × 3
= 0,243 m3
Lantai 3
Kolom K1 = Tinggi kolom × luas kolom × jumlah kolom
= 3,25 × (0,15 × 0,3) × 8
= 1,17 m3
Kolom K2 = Tinggi kolom × luas kolom × jumlah kolom
= 3,25 × (0,15 × 0,15) × 3
= 0,22 m3
4. Balok
Lantai 2
B1 = (luas balok B1) × panjang – pengurang
= (0,2 × 0,4) × (48 – ((0,15 × 0,3 × 8) + (0,15 ×
0,15 × 2)))
= 3,81 m3
B2 = (luas balok B2) × panjang – pengurang
= (0,15 × 0,3) × (24,45 – ((0,15 × 0,15 × 3) + (0,2
× 0,4 × 7) + (0,15 × 0,3 × 4)))
= 1,064 m3
Lantai 3
B1 = (luas balok B1) × panjang – pengurang
= (0,2 × 0,4) × (48 – ((0,15 ×0,3 × 8) + (0,15 ×
0,15 × 2)))
= 3,81 m3

No JENIS PEKERJAAN VOLUME


B2 = (luas balok B2) × panjang – pengurang
= (0,15 × 0,3) × (3,55 – (0,15 × 0,15 × 3))
= 0,16 m3
5. RingBalk
RB2 = (luas RB2) × Panjang – pengurang
= (0,15 × 0,15) (38 – (0,15 × 0,3 × 8))
= 0,85 m3
6. Talang
Talang = ( Luas Permukaan Talang depan × Tebal ) +
( Luas Permukaan Talang belakang × Tebal )
= ((5 × 1,2) × 0,1) + (5 × 1) × 0,1))
= 1,1 m3
D PEKERJAAN PEMBESIAAN
1. Pembesian Kolom
Pembesian Lantai 1
K1 D16 = Panjang × Jumlah Tulangan ×Jumlah
Kolom
= ( 4 + 6 (0,016)) × 8 × 8
= 262,144 m = 414,19 kg
Sengkang ø8 = Kel Sengkang x Jumlah Sengkang
= 0,9 x (4 : 0,15 + 1)
= 24,9 m = 9,72 kg
K2 D12 = Panjang × Jumlah Tulangan ×Jumlah
Kolom
= ( 4 + 6 (0,012)) × 4 × 5
= 81,44 m = 72,482 kg
Sengkang ø6 = Kel Sengkang x Jumlah Sengkang
= 0,6 x (4 : 0,15 + 1)
= 16,6 m = 3,66 kg
No JENIS PEKERJAAN VOLUME
Pembesian Lantai 2
K1 D16 = Panjang × Jumlah Tulangan ×Jumlah
Kolom
= ( 3,6 + 6 (0,016)) × 8 × 8
= 236,544 m = 373,74 kg
Sengkang ø8 = Kel Sengkang x Jumlah Sengkang
= 0,9 x (3,6 : 0,15 + 1)
= 22,5 m = 8,78 kg
K2 D12 = Panjang × Jumlah Tulangan ×Jumlah
Kolom
= ( 3,6 + 6 (0,012)) × 4 × 3
= 44,07 m = 39,22 kg
Sengkang ø6 = Kel Sengkang x Jumlah Sengkang
= 0,6 x (3,6 : 0,15 + 1)
= 15 m = 3,3 kg
Pembesian Lantai 3
K1 D16 = Panjang × Jumlah Tulangan ×Jumlah
Kolom
= ( 3,25 + 6 (0,016)) × 8 × 8
= 214,15 m = 338,357 kg
Sengkang ø8 = Kel Sengkang x Jumlah Sengkang
= 0,9 x (3,25 : 0,15 + 1)
= 20,4 m = 7,96 kg
K2 D12 = Panjang × Jumlah Tulangan ×Jumlah
Kolom
= ( 3,25 + 6 (0,012)) × 4 × 3
= 39,87 m = 35,49 kg
Sengkang ø6 = Kel Sengkang x Jumlah Sengkang
= 0,6 x (3,25 : 0,15 + 1)
= 13,6 m = 3 kg

No JENIS PEKERJAAN VOLUME


2. Pembesian Balok
Pembesian Lantai 2
B1 4,5 m D16 tump = (1,125 + 0,175 + (12 (0,016)) + (6
(0,016)) + 1) × 16 × 4
= 165,64 m = 261,72 kg
Sengkang ø8 = 1,2 × ((4,5 : 0,15) + 1)
= 37,2 m = 14,51 kg
D16 Lap = (2,25 + 1) × 8 × 4
= 104 m = 164,32 kg
Sengkang ø8 = 1,2 × ((4,5 : 0,2) + 1)
= 28,2 m = 11 kg
B1 5 m D16 tump = (1,25 + 0,175 + (12 (0,016)) + (6
(0,016)) + 1) × 16 × 6
= 260,45 m = 411,52 kg
Sengkang ø8 = 1,2 × ((5 : 0,15) + 1)
= 41,2 m = 16,07 kg
D16 Lap = (2,5 + 1) × 8 × 6
= 168 m = 265,44 kg
Sengkang ø8 = 1,2 × ((5 : 0,2) + 1)
= 31,2 m = 12,17 kg
B2 1,2 m D16 tump = (0,3 + 0,175 + (12 (0,016)) + (6
(0,016)) +1) × 8 × 1
= 14,11 m = 22,3 kg
Sengkang ø8 = 0,9 × ((1,2 : 0,1) +1)
= 11,7 m = 4,57 kg
D16 lap = (0,6 + 1) × 4 × 1
= 6,4 m = 10,12 kg
D12 lap = (0,6 + 1) × 2 × 1
= 3,2 m = 2,85 kg

No JENIS PEKERJAAN VOLUME


Pembesian Balok
Pembesian Lantai 2
B2 1,2 m (Lanjutan) Sengkang ø8 = 0,9 × ((1,2 : 0,2) +1
= 6,3 m = 2,46 kg
B2 3,8 m D16 tump = (0,95 + 0,175 + (12 (0,016)) + (6
(0,016)) +1) × 8 × 3
= 57,92 m = 91,52 kg
Sengkang ø8 = 0,9 × ((3,8 : 0,1) +1)
= 35,1 m = 13,69 kg
D16 lap = (1,9 + 1) × 4 × 3
= 34,8 m = 54,99 kg
D12 lap = (1,9 + 1) × 2 × 3
= 17,4 m = 15,47 kg
Sengkang ø8 = 0,9 × ((3,8 : 0,2) +1
= 18 m = 7,02 kg
B2 5 m D16 tump = (1,25 + 0,175 + (12 (0,016)) + (6
(0,016)) +1) × 8 × 2
= 43,41 m = 68,59 kg
Sengkang ø8 = 0,9 × ((5 : 0,1) +1)
= 45,9 m = 17,91 kg
D16 lap = (2,5 + 1) × 4 × 2
= 28 m = 44,24 kg
D12 lap = (2,5 + 1) × 2 × 2
= 14 m = 12,46 kg
Sengkang ø8 = 0,9 × ((5 : 0,2) +1
= 23,4 m = 9,13 kg
Pembesian Lantai 3
B1 4,5 m D16 tump = (1,125 + 0,175 + (12 (0,016) + (6
(0,016) + 1) × 16 × 4
= 165,64 m = 261,72 kg
No JENIS PEKERJAAN VOLUME
Pembesian Balok
Pembesian Lantai 3
B1 4,5 m (Lanjutan) Sengkang ø8 = 1,2 × ((4,5 : 0,15) + 1)
= 37,2 m = 14,51 kg
D16 Lap = (2,25 + 1) × 8 × 4
= 104 m = 164,32 kg
B2 1,2 m D16 tump = (0,3 + 0,175 + (12 (0,016) + (6
(0,016) +1) × 8 × 1
= 14,11 m = 22,3 kg
Sengkang ø8 = 0,9 × ((1,2 : 0,1) +1)
= 11,7 m = 4,57 kg
D16 lap = (0,6 + 1) × 4 × 1
= 6,4 m = 10,12 kg
D12 lap = (0,6 + 1) × 2 × 1
= 3,2 m = 2,85 kg
Sengkang ø8 = 0,9 × ((1,2 : 0,2) +1
= 6,3 m = 2,46 kg
B2 2,35 m D16 tump = (0,59 + 0,175 + (12 (0,016) + (6
(0,016) +1) × 8 × 1
= 16,43 m = 25,96 kg
Sengkang ø8 = 0,9 × ((2,35 : 0,1) +1)
= 22,05 m = 8,6 kg
D16 lap = (1,18 + 1) × 4 × 1
= 8,72 m = 13,78 kg
D12 lap = (1,18 + 1) × 2 × 1
= 4,36 m = 3,89 kg
Sengkang ø8 = 0,9 × ((2,35 : 0,2) +1
= 11,48 m = 4,48 kg

No JENIS PEKERJAAN VOLUME


3. Pembesian Ring Balok
RB2 4,5 m D10 tump = (1,125 + 0,175 + (12 (0,01) + (6
(0,01) +1) × 4 × 4
= 39,68 m = 24,61 kg
Sengkang ø6 = 0,6 × ((4,5 : 0,15) +1)
= 18,6 m = 4,1 kg
D10 lap = (2,25 + 1) × 4 × 4
= 52 m = 32,24 kg
Sengkang ø6 = 0,6 × ((4,5 : 0,2) +1
= 14,1 m = 3,11 kg
RB2 5 m D10 tump = (1,25 + 0,175 + (12 (0,01) + (6
(0,011) +1) × 4 × 4
= 41,68 m = 25,85 kg
Sengkang ø6 = 0,6 × ((5 : 0,15) +1)
= 20,6 m = 4,54 kg
D10 lap = (2,5 + 1) × 4 × 4
= 56 m = 34,72 kg
Sengkang ø6 = 0,6 × ((5 : 0,2) +1
= 15,6 m = 3,44 kg
4. Pembesian Sloof
S1 1 m 2 (20 x 50) 1,4 D16 tump = (0,25 + 0,175 + (12 (0,016)) + (6
(0,016)) + 1) × 10 × 2
= 34,26 m = 54,13 kg
Sengkang ø8 = 1,4 × ((1 : 0,1) + 1)
= 15,4 m = 6,01 kg
D16 Lap = (0,5 + 1) × 10 × 2
= m = kg
Sengkang ø8 = 1,4 × ((1 : 0,2) + 1)
= 8,4 m = 3,28 kg

No JENIS PEKERJAAN VOLUME


Pembesian Sloof
S1 1,2 m 1 D16 tump = (0,3 + 0,175 + (12 (0,016)) + (6
(0,016)) + 1) × 10 × 1
= 17,63 m = 27,86 kg
Sengkang ø8 = 1,4 × ((1,2 : 0,1) + 1)
= 18,2 m = 7,1 kg
D16 Lap = (0,6 + 1) × 10 × 1
= 16 m = 25,28 kg
Sengkang ø8 = 1,4 × ((1,2 : 0,2) + 1)
= 9,8 m = 3,83 kg
S1 3,8 m 1 D16 tump = (0,95 + 0,175 + (12 (0,016)) + (6
(0,016)) + 1) × 10 × 1
= 24,13 m = 38,13 kg
Sengkang ø8 = 1,4 × ((3,8 : 0,1) + 1)
= 54,6 m = 21,3 kg
D16 Lap = (1,9 + 1) × 10 × 1
= 29 m = 45,82 kg
Sengkang ø8 = 1,4 × ((3,8 : 0,2) + 1)
= 28 m = 10,92 kg
S1 4 m 2 D16 tump = (1 + 0,175 + (12 (0,016)) + (6
(0,016)) + 1) × 10 × 2
= 49,26 m = 77,83 kg
Sengkang ø8 = 1,4 × ((4 : 0,1) + 1)
= 57,4 m = 22,39 kg
D16 Lap = (2 + 1) × 10 × 2
= 60 m = 94,8 kg
Sengkang ø8 = 1,4 × ((4 : 0,2) + 1)
= 29,4 m = 11,47 kg

No JENIS PEKERJAAN VOLUME


Pembesian Sloof
S1 4,5 m 4 D16 tump = (1,125 + 0,175 + (12 (0,016)) + (6
(0,016)) + 1) × 10 × 4
= 103,52 m = 163,57 kg
Sengkang ø8 = 1,4 × ((4,5 : 0,1) + 1)
= 64,4 m = 25,12 kg
D16 Lap = (2,25 + 1) × 10 × 4
= 130 m = 205,4 kg
Sengkang ø8 = 1,4 × ((4,5 : 0,2) + 1)
= 32,9 m = 12,84 kg
S1 5 m 4 D16 tump = (1,25 + 0,175 + (12 (0,016)) + (6
(0,016)) + 1) × 10 × 4
= 108,52 m = 171,47 kg
Sengkang ø8 = 1,4 × ((5 : 0,1) + 1)
= 71,4 m = 27,85 kg
D16 Lap = (2,5 + 1) × 10 × 4
= 140 m = 221,2 kg
Sengkang ø8 = 1,4 × ((5 : 0,2) + 1)
= 36,4 m = 14,2 kg
S2 1,2 m 2 (20 x 30) 1 D16 tump = (0,3 + 0,175 + (12 (0,016)) + (6
(0,016)) + 1) × 8 × 1
= 14,11 m = 22,3 kg
Sengkang ø8 = 1 × ((1,2 : 0,1) + 1)
= 13 m = 5,07 kg
D16 Lap = (0,6 + 1) × 8 × 1
= 12,8 m = 20,23 kg
Sengkang ø8 = 1 × ((1,2 : 0,2) + 1)
= 7 m = 2,73 kg

No JENIS PEKERJAAN VOLUME


Pembesian Sloof
S2 2,15 m 1 D16 tump = (0,54 + 0,175 + (12 (0,016)) + (6
(0,016)) + 1) × 8 × 1
= 16,03 m = 25,33 kg
Sengkang ø8 = 1 × ((2,15 : 0,1) + 1)
= 22,5 m = 8,76 kg
D16 Lap = (1,08 + 1) × 8 × 1
= 16,64 m = 26,3 kg
Sengkang ø8 = 1 × ((2,15 : 0,2) + 1)
= 11,75 m = 4,59 kg
5. Pembesian Pondasi
Pondasi Footplat P1 D16 – 0,15 m = 6 × ((1,5 : 0,15) + 1) × 2
= 132 m = 208,56 kg
D16 – 0,2 m = (1,5 + 1,22 + 0,3 + 1,22) ×
((1,5 : 0,2) + 1) × 2
= 72,08 m = 113,89 kg
Pondasi Footplat P2 D16 – 0,15 m = 6 × ((1,5 : 0,15) + 1) × 2
= 132 m = 208,56 kg
D16 – 0,2 m(X) = (1,5 + 0,2 + 0,3 + 1,22) ×
((1,5 : 0,2) + 1)
= 27,37 m = 43,25 kg
D16 – 0,2 m(Y) = (1,5 + 1,22 + 0,3 + 1,22) ×
((1,5 : 0,2) + 1)
= 36,04 m = 56,95 kg
6. Pembesian Pelat
Pembesian plat Lt. 2
Arah X (1,2 m) 2 Jumlah tul. = 2 × (1200/150 + 1) = 18
Panjang total = 18 × (1200 mm + 2 × 6(10)) × 2
= 47,52 m = 29,46 kg

No JENIS PEKERJAAN VOLUME


Pembesian plat Lt. 2
Arah X (2,6 m) 2 Jumlah tul. = 2 × (2600/150 + 1) = 36,67
Panjang total = 36,67 ×(2600 mm + 2 × 6(10)) × 2
= 199,47 m = 123,67 kg
Arah X (3,8 m) 1 Jumlah tul. = 2 × (3800/150 + 1) = 52,67
Panjang total = 52,67 ×(3800 mm + 2 × 6(10)) × 1
= 206,45 m = 128 kg
Arah X (5 m) 4 Jumlah tul. = 2 × (5000/150 + 1) = 68,67
Panjang total = 68,67 ×(5000 mm + 2 × 6(10)) × 4
= 1757,87 m = 1089,88 kg
Arah Y (1,15 m) 1 Jumlah tul. = 2 × (1150/150 + 1) = 17,33
Panjang total = 17,33 ×(1150 mm + 2 × 6(10)) × 1
= 22,01 m = 13,65 kg
Arah Y (1,2 m) 2 Jumlah tul. = 2 × (1200/150 + 1) = 18
Panjang total = 18 × (1200 mm + 2 × 6(10)) × 2
= 47,52 m = 29,46 kg
Arah Y (2,15 m) 1 Jumlah tul. = 2 × (2150/150 + 1) = 30,67
Panjang total = 30,67 ×(2150 mm + 2 × 6(10)) × 1
= 69,61 m = 43,16 kg
Arah Y (2,25 m) 2 Jumlah tul. = 2 × (2250/150 + 1) = 32
Panjang total = 32 × (2250 mm + 2 × 6(10)) × 2
= 151,68 m = 94,04 kg
Arah Y (2,35 m) 1 Jumlah tul. = 2 × (2350/150 + 1) = 33,33
Panjang total = 33,33 ×(4500 mm + 2 × 6(10)) × 1
= 82,33 m = 51,051 kg
Arah Y (2,5 m) 2 Jumlah tul. = 2 × (2500/150 + 1) = 35,33
Panjang total = 35,33 ×(2500 mm + 2 × 6(10)) × 2
= 185,15 m = 114,79 kg

No JENIS PEKERJAAN VOLUME


Pembesian plat Lt. 3