PEMERINTAH KABUPATEN SUMENEP

KECAMATAN GANDING
DESA ROMBIYA TIMUR
RINCIAN PENGGUNAAN TENAGA KERJA DAN BAHAN
KEGIATAN : PENINGKATAN JALAN LINGKUNGAN
PEKERJAAN : JALAN RABAT BETON
LOKASI : DUSUN DAJA SONGAI DESA ROMBIYA TIMUR
VOLUME : 1,25 X 290 m
HARGA JUMLAH
NO URAIAN VOLUME SATUAN SATUAN TOTAL
(Rp) (Rp)
1.      UPAH
1 Pekerja 122.00 Hari 110,000 13,420,000
2 Tukang 25.00 Hari 127,000 3,175,000
3 Kepala Tukang 3.00 Hari 137,000 411,000

SUB TOTAL(I) 17,006,000


2.      BAHAN
1 Sirtu 23.00 M3 676,000 15,548,000
2 Papan Bekisting 4.00 M3 3,945,500 15,782,000
3 Paku Biasa 2’’-5’’ 18.00 Kg 25,000 450,000
4 Minyak Bekisting 6.00 Ltr 50,000 300,000
5 Semen 40 Kg 250.1 Zak 79,000 19,759,875
6 Pasir Hitam 24.00 M3 762,000 18,288,000
7 Batu Cor 28.00 M3 282,000 7,896,000
8 Air 8.00 M3 50,000 400,000
9 Prasasti 1.00 bh 250,000 250,000
SUB TOTAL (II) 78,673,875
3.      ALAT
1 Cetok 6.00 bh 50,000 300,000
2 Ember 10.00 bh 20,000 200,000
3 Sekop 2.00 bh 250,000 500,000
4 Cangkul 4.00 bh 150,000 600,000
5 Sapu Lidi 5.00 bh 15,000 75,000
6 Artco 2.00 bh 550,000 1,100,000
SUB TOTAL (II) 2,775,000
BIAYA OPERASIONAL 1,545,125
TOTAL BIAYA (I+II+II+BOP) 100,000,000
Sumenep

Mengatahui Diverifikasi Dibuat Oleh


Kepala Desa Rombiya Timur Sekretaris Desa Tim Pengelola kegiatan

………………………………………….. …………………………………………. ……………………………………………


Pajak Pajak

(PPn) 10% (PPh) 3%

732,000 6,000 116,000


173,182 6,927 133,927
22,418 7,473 144,473

Rp 1,554,800 Rp 424,036 Rp 1,978,836 86,036 762,036


Rp 1,578,200 Rp 430,418 Rp 2,008,618 502,155 4,447,655

Rp 1,975,988 Rp 538,906 Rp 2,514,893 10,055 89,055


Rp 1,828,800 Rp 498,764 Rp 2,327,564 96,982 858,982
Rp 789,600 Rp 215,345 Rp 1,004,945 35,891 317,891

Rp 7,727,388 Rp 2,107,469
Rp 9,834,857
Kabupaten : Sumenep
Kecamatan : GANDING TAKE OF SHEET
Desa : Desa Rombiya Timur
1. Galihan Tanah VOLUME

GALIAN = 290.0
= 36.25

1. Kebutuhan Tenaga
Pekerja = 36.25
= 27.19
2. Pekerjaan Urugan Sirtu Volume
Sirtu = 290.0
= 18.13

1. Kebutuhan Bahan
Sirtu = 1.20
= 21.75

2. Kebutuhan Tenaga
Pekerja = 18.13
= 4.53

3. Pasang Bekisting 2x Pakai Volume


Bekisting = 290.0
= 58.00

1. Kebutuhan Bahan
Kayu Beskiting = 58.00
Paku Biasa 2" - 5" = 58.00
Minyak Beskiting = 58.00

2. Kebutuhan Tenaga
Pekerja = 58.00
Tukang Kayu = 58.00
Kepala Tukang = 58.00

4. Pekerjaan Rabat Beton Volume


Beton mutu f'c=9,8 Mpa (125); slump (12 ± 2) Pekerja Rabat Beton = 290.0
cm;wc = 0,78 = 36.25

1. Kebutuhan Bahan
Portland Cement (PC) = 36.25
Pasir Beton (PB) = 36.25
Koral Beton ( Maksimu 30 n) = 36.25
Air = 36.25

2. Kebutuhan Tenaga
Pekerja = 1.650
Tukang Batu = 0.275
Kepala Tukang = 0.028
JENIS PRASARANA : Jalan rabat Beton
E OF SHEET Lokasi : Dusun daja songai
Volume 1.25 x 290 m
1. Galian Tanah
Panjang galian = 290 m
x 1.25 x 0.10 Lebar Galian = 1.25 M¹
m³ Dalam Galian = 0.10 M¹
Faktor Kebutuhan Tenaga
Pekerja = 27.19 hr
x 0.75
hr 2. URUGAN SIRTU
Faktor Kebutuhan Tenaga
x 1.25 x 0.05 Pekerja = 4.53 oh
m³ Faktor Kebutuhan Bahan
Sirtu = 21.75 m³

x 18.13

x 0.25
oh

3. BEKISTING
x 0.10 x 2.00 Faktor Kebutuhan Tenaga
m³ Pekerja = 30.16 oh
Tukang Kayu = 15.08 oh
Kepala Tukang = 1.51 oh
x 0.045 = 2.61 m³ Faktor Kebutuhan Bahan
x 0.300 = 17.40 kg Kayu Bakisting = 2.61 m³
x 0.100 = 5.80 ltr Paku Biasa 2''-5" = 17.40 kg
Minyak Bekisting = 5.80 ltr

x 0.520 = 30.16 oh
x 0.260 = 15.08 oh
x 0.026 = 1.51 oh

4. PERKERASAN JALAN RABAT BETON


x 1.25 x 0.10 Faktor Kebutuhan Tenaga
m³ Pekerja = 59.81 oh
Tukang Katu = 9.97 oh
Kepala Tukang = 1.02 oh
x 6.90 = 250.1 zak Faktor Kebutuhan Bahan
x 0.591 = 21.42 m³ Portland Cament (PC) = 250.1 zak
x 0.750 = 27.19 m³ Pasir Beton (PB) = 21.42 m³
x 0.215 = 7.79 m³ Koral Beton (Maksimum 3) = 27.19 m³
Air = 7.79 m³

x 36.25 = 59.81 oh
x 36.25 = 9.97 oh
x 36.25 = 1.02 oh