DAFTAR UPAH PEKERJA BANGUNAN

HARGA UPAH SATUAN WAKTU


NO JENIS PEKERJA BANGUNAN
LUAR PULAU
Rp.

1 PEKERJA 90,000.00 1 ORANG/ HR/ 8 JAM


2 TUKANG BATU/GALI 120,000.00 1 ORANG/ HR/ 8 JAM
3 KEPALA TUKANG BATU 130,000.00 1 ORANG/ HR/ 8 JAM
4 TUKANG KAYU 120,000.00 1 ORANG/ HR/ 8 JAM
5 KEPALA TUKANG KAYU 130,000.00 1 ORANG/ HR/ 8 JAM
6 TUKANG CAT / PELITUR 120,000.00 1 ORANG/ HR/ 8 JAM
7 KEPALA TUKANG CAT / PELITUR 130,000.00 1 ORANG/ HR/ 8 JAM
8 TUKANG BESI BETON 120,000.00 1 ORANG/ HR/ 8 JAM
9 KEPALA TUKANG BESI BETON 130,000.00 1 ORANG/ HR/ 8 JAM
10 TUKANG BESI PROFIL 120,000.00 1 ORANG/ HR/ 8 JAM
11 KEPALA TUKANG BESI PROFIL 130,000.00 1 ORANG/ HR/ 8 JAM
12 MANDOR 130,000.00 1 ORANG/ HR/ 8 JAM
13 OPERATOR ALAT BESAR 130,000.00 1 ORANG/ HR/ 8 JAM
14 PEMBANTU OPERATOR / MEKANIK 120,000.00 1 ORANG/ HR/ 8 JAM
15 SUPIR TRUK 120,000.00 1 ORANG/ HR/ 8 JAM
16 KENEK TRUK 90,000.00 1 ORANG/ HR/ 8 JAM
17 PENJAGA MALAM 90,000.00 1 ORANG/ HR/ 8 JAM
DAFTAR HARGA BAHAN BANGUNAN
DKI JAKARTA

SATUAN HARGA SATUAN


NO JENIS BAHAN BANGUNAN
LUAR PULAU
Rp.
1 2 3 4

A AGREGAT KASAR, BAHAN PEREKAT & BAHAN JADINYA


1 Bata Merah Bakar bh 610.00
2 Batu Belah Pondasi m³ 244,830.00
3 Batu Koral Beton Kali m³ 290,820.00
4 Batu Pecah Mesin 1/2 m³ 276,960.00
5 Batu Pecah Mesin 2/3 m³ 276,960.00
6 Batu Pecah Mesin 5/7 m³ 257,900.00
7 Kanstin / Kerb Beton Pracetak P = 60 cm bh 62,000.00
8 Pasir Beton m³ 277,380.00
9 Pasir Pasang Kali m³ 282,530.00
10 Pasir Urug m³ 279,220.00
11 Semen PC / 50 kg zak 67,000.00
12 Semen Putih kg 2,180.00
13 Semen Warna kg 11,500.00
14 Tanah Urugan m³ 150,000.00
15 Air m3 1,250.00
-
B BAHAN FINISHING LABURAN, PENGISI DAN ALATNYA
1 Ampelas lbr 3,340.00
2 Bahan Plitur Kripik ( Sirlak India ) kg 87,200.00
3 Cat Besi/ Kayu Glotek kg 36,500.00
4 Cat Besi Duco Danaglos/ICI kg 84,000.00
5 Cat Bron kg 48,800.00
6 Cat Dasar ICI untuk Interior ( 2 Pelapis ) lt 31,000.00
7 Cat Kayu Seiv kg 44,440.00
8 Cat Marka / Spotlight kg 66,600.00
9 Cat Primer Marka kg 66,600.00
10 Cat Tahan Asam kg 26,400.00
11 Cat Tembok ICI Eksterior lt 54,000.00
12 Cat Tembok ICI Eksterior ( BETON ) lt 75,740.00
13 Cat Tembok ICI Interior ( PLAFOND DAN DINDING ) lt 54,000.00
14 Cat Tembok Sanlex kg 12,200.00
15 Cat Tembok Vinilex kg 18,000.00
16 Cat Tembok Vinilex gln 90,000.00
17 Dempul Duco kg 30,900.00
18 Dempul Halus / Imfra ( Wood Filler ) kg 28,800.00
19 Dempul Kayu Cap Kucing kg 24,400.00
20 Dempul Lilin kg 24,000.00
21 Dempul Plastik kg 26,900.00
22 Dempul Plitur kg 26,400.00
23 Kape Kayu bh 4,800.00
24 Kape Tembok bh 4,800.00
25 Karung Plastik bh 1,000.00
26 Kumpon kg 32,600.00
27 Kwas 1 1/2" bh 7,500.00
28 Kwas 3" bh 10,900.00
29 Melamik kg 37,500.00
30 Meni Kayu / Besi kg 16,000.00
31 Oker kg 21,100.00
32 Oten (Pewarna Plitur ) bks 3,700.00
33 Oyan bks 2,000.00
34 Pelapis Alkali ICI ( Cat Dasar Beton Ekterior ) lt 25,300.00
35 Pengawetan Kayu m³ 261,400.00
36 Pengopenan Kayu m³ 435,600.00
37 Plamir Tembok kg 12,400.00
1 2 3 4

38 Plincote kg 19,200.00
39 Rool Cat Tembok bh 16,000.00
40 Sincromat kg 32,600.00
41 Soligneum 1 blek 5 lt 28,000.00
42 Spirtus lt 4,000.00
43 Terpentin lt 5,000.00
44 Tiner A lt 14,900.00
45 Tiner B lt 16,300.00
46 Water Profing Emulsion kg 42,500.00
47 Water Profing Membrance ml 79,900.00

C BAHAN KAYU BERIKUT BAHAN JADINYA


1 Kayu Balok Borneo Super m³ 5,398,000.00
2 Kayu Balok Kamper Medan (kruing) m³ 9,523,750.00
3 Kayu Papan Kamper Samarinda m³ 10,798,330.00
4 Kayu Papan Borneo Super m³ 5,440,000.00
5 Kayu Papan Kamper Medan (Kruing) m³ 10,243,750.00
6 Kayu Papan Kamper Samarinda m³ 10,798,330.00
7 Kayu Papan Untuk Bekisting m³ 2,983,330.00
8 Kayu Terentang m³ 2,780,000.00
9 List profil kamper 1 cm m' 2,200.00

D BAHAN PENUTUP RANGKA PLAFOND


1 Gypsum 120 x 240 t = 9 mm ex DN lbr 64,000.00
2 GRC 4 mm lbr 54,000.00
3 GRC 9 mm lbr 125,000.00
4 List profil gypsum m' 4,500.00
5 Cotton plaster bh 16,500.00
6 Compoun zak 83,000.00

E BAHAN KAYU LAPIS


1 Multiplek 9 mm 120 x 240 lbr 150,700.00
2 Triplek 3 mm 120 x 240 lbr 52,910.00
3 Triplek 4 mm 120 x 240 lbr 62,350.00

F BAHAN LANTAI DAN PELAPIS DINDING


1 Keramik 25 x 45 (KM) KW I DN Corak / Warna / Anti Slip Roman bh 11,580.00
2 Keramik 20 x 20 (KM) KW I DN Corak / Warna / Anti Slip Roman bh 2,200.00
3 Keramik 20 x 20 (KM) KWI DN Putih Polos Roman bh 2,000.00
4 Keramik 20 x 25 Dinding KM KWI DN Corak Roman bh 3,200.00
5 Keramik 40 x 40 KW I DN Warna/Corak ( ANTI SLIP ) Roman bh 7,740.00
6 Floor hardener kg 29,000.00

G BAHAN SALURAN AIR KOTOR / BERSIH


1 Buis Beton Ø 30 cm ( 1 m' ) m1 50,600.00
2 Buis Beton Ø 40 cm ( 1 m' ) m1 56,100.00
3 Buis Beton Ø 50 cm ( 1 m' ) unit 67,100.00
4 Buis Beton Ø 60 cm ( 1 m' ) unit 117,100.00
5 Grafel U 20 cm' m1 23,900.00
6 Grafel U 30 cm' m1 29,700.00
7 Grafel U 40 cm' m1 55,000.00

I BAHAN LOGAM DAN BAHAN JADINYA


1 Baja Konstruksi U-39 / U-32 kg 9,950.00
2 Baja Tulangan Beton kg 12,020.00
3 Besi Beton U-24 Rata - Rata kg 12,020.00
4 Besi Beton U-39 / U-32 Rata - Rata kg 12,310.00
5 Besi Galvanisir kg 14,000.00
6 Besi Profil DN SII kg 10,300.00
7 Besi Profil Ex LN kg 12,300.00
8 Besi C Lip Chanel kg 10,300.00
9 Besi L 30.30.3 kg 11,000.00
5 Besi Strip kg 12,390.00
6 Daun Jendela Alumunium Natural ( Tanpa Kaca dan accessories ) m¹ 138,850.00
7 Daun Jendela Alumunium Warna ( Tanpa Kaca dan accessories ) m¹ 163,480.00
8 Daun Pintu Alumunium Natural ( tanpa kaca dan accessories ) m¹ 167,100.00
9 Daun Pintu Alumunium Warna ( tanpa kaca dan accessories ) m¹ 174,960.00
10 Handle Alumunium ( Tarikan Pintu Alumunium ) bh 403,700.00
45 Besi Hollow Block 20 X 20 26,000.00
46 Besi Hollow Block 40 X 40 kg 32,000.00
10 IWF Ex DN SII kg 9,950.00
1 2 3 4

11 Kawat Beton kg 18,910.00


12 Kawat Harmonika 4 cm m² 34,900.00
13 Kusen Alumunium Natural 1.3 mm t=1,3 mm ( 4 " ) m1 145,500.00
14 Kusen Alumunium Warna 1.3 mm t=1,3 mm ( 4 " ) m1 165,750.00
15 Kusen Alumunium Warna 1.3 mm t=1,3 mm ( 3 " ) m1 145,000.00
16 Lem Fox kg 29,830.00
17 Lem Kuning (aibond) kg 29,100.00
18 Pagar BRC m² 130,700.00
19 Wiremesh M8 m² 43,500.00
1 2 3 4

J BAHAN KACA
20 Glass Blead kg 22,000.00
21 Glass Block DN 20 x 20 ( Kedawung ) bh 23,000.00
22 Glass Block DN 20 x 20 Ex LN bh 88,600.00
23 Kaca 6 mm Gravver m² 1,306,800.00
24 Kaca Patri EX Luar negeri terpasang m² 3,746,200.00
25 Kaca Patri Lokal Terpasang ( ASAHI ) m² 1,379,400.00
26 Kaca Polos 2 mm ( ASAHI ) m² 43,600.00
27 Kaca Polos 3 mm ( ASAHI ) m² 63,400.00
1 Kaca Polos 5 mm ( ASAHI ) m² 93,600.00
Kaca Polos 8 mm ( ASAHI ) m² 180,000.00
2 Kaca Rayband 12 mm ( ASAHI ) m² 292,900.00
-
42 Kaca Rayband 5 mm ( ASAHI ) m² 104,000.00
43 Kaca Stopsol Panasat 8 mm m² 725,400.00
44 Thermo Plastik kg 34,700.00
44 Kaca Tempered 10 mm m² 398,000.00

K BAHAN PAKU DAN MUR BAUT


1 Besi Beugel kuda - kuda kg 12,100.00
2 Duk Angker kg 18,000.00
3 Mur Baut Biasa dia.19 s/d 16 (5 cm) bh 5,900.00
4 Mur Baut dia.19 / panjang 60 cm bh 53,900.00
5 Mur Baut HTB dia. 19 s/d 16 (5 cm) bh 9,900.00
6 Paku 1 cm s/d 3 cm kg 19,620.00
7 Paku 4 cm s/d 7 cm kg 17,300.00
8 Paku 8 cm s/d 12 cm kg 15,560.00
9 Paku Beton 2 cm s/d 5 cm bh 2,500.00
10 Paku Cacing kg 26,000.00
11 Paku Kait Lengkap bh 800.00
12 Paku Skrup kg 13,650.00
13 Paku Skrup 1 cm – 2,5 cm bh 190.00
14 Piser dia. 12 s/d 20 cm bh 4,800.00
15 Ramset / dina bolt bh 8,000.00

L BAHAN PERPIPAAN 1.²


1 Besi Pipa Hitam Ø 1" t=2 mm bt 108,200.00
2 Besi Pipa Hitam Ø 2" t=2 mm bt 217,800.00
3 Besi Pipa Hitam Ø 3" t=2 mm bt 393,500.00
4 Besi Pipa Hitam Ø 4" t=2 mm bt 519,900.00
5 Besi Pipa Hitam Ø 6" t=2 mm bt 726,000.00
6 Pipa PVC MASPION ABU Ø 1 1/2" (AW) bt 52,800.00
7 Pipa PVC MASPION ABU Ø 1 1/4" (AW) bt 40,000.00
8 Pipa PVC MASPION ABU Ø 1" (AW) bt 28,500.00
9 Pipa PVC MASPION ABU Ø 1/2" (AW) bt 18,400.00
10 Pipa PVC MASPION ABU Ø 2 1/2" (AW) bt 106,300.00
11 Pipa PVC MASPION ABU Ø 2" (AW) bt 76,700.00
12 Pipa PVC MASPION ABU Ø 3" (AW) bt 151,300.00
13 Pipa PVC MASPION ABU Ø 3/4" (AW) bt 22,400.00
14 Pipa PVC MASPION ABU Ø 4" (AW) bt 211,500.00
15 Pipa PVC 4" berlobang jenis AW m1 35,300.00
16 Pipa PVC RUCIKA type AW Ø 1 1/2" bt 86,300.00
17 Pipa PVC RUCIKA type AW Ø 1 1/4" bt 70,300.00
18 Pipa PVC RUCIKA type AW Ø 1" bt 52,800.00
19 Pipa PVC RUCIKA type AW Ø 1/2" bt 25,600.00
20 Pipa PVC RUCIKA type AW Ø 2 1/2" bt 148,600.00
21 Pipa PVC RUCIKA type AW Ø 2" bt 118,200.00
22 Pipa PVC RUCIKA type AW Ø 3" bt 218,900.00
23 Pipa PVC RUCIKA type AW Ø 3/4" bt 44,000.00
24 Pipa PVC RUCIKA type AW Ø 4" bt 335,500.00
25 Pipa PVC RUCIKA type AW Ø 6" bt 638,900.00
26 Pipa PVC RUCIKA type AW Ø 8" bt 926,400.00
27 Sambungan Pipa PVC Jenis AW 4 " TY bh 87,200.00
28 Solatip Leideng gl 3,700.00

M BAHAN SANITAIR
1 Saringan Air Lt KM Stainless Steel bh 58,100.00
2 Apooer Bath Tube bh 284,600.00
3 Kran stain less Lokal Kait bh 49,700.00
1 2 3 4

4 Shower Dengan Tiang bh 196,100.00


5 Shower Tanpa Tiang bh 108,900.00
6 Kran Tembok TOTO dia. 1/2 " bh 125,000.00
7 Kran Tembok ITAP dia. 1/2 " bh 34,900.00
8 Kran Bebek Sun Eui 1/2 " bh 156,900.00
9 Kran Bebek ITAP 1/2 " bh 52,300.00
10 Kran Panas Dingin San Eui Standard bh 217,800.00
1 2 3 4

11 Bath Cape Washteren unit 2,368,300.00


12 Tempat Sabun Poslin bh 50,100.00
13 Wastafel Lengkap TOTO LW 230 unit 1,134,100.00
14 Wastafel Lengkap INA unit 750,000.00
15 Closet Jongkok Poslin warna TOTO unit 217,800.00
16 Closet Jongkok Standard Putih Poslin TOTO unit 191,700.00
17 Closet Jongkok Lengkap Sistem Jet TOTO unit 1,986,400.00
18 Closet Duduk Warna Standard TOTO C 420 JP Lengkap unit 2,040,000.00
19 Wastafel Bulat Warna Standard Lengkap unit 1,283,600.00
20 Closet Duduk Warna Standard lengkap INA bh 1,430,300.00
21 Urinoir Lengkap TOTO Warna Standard lengkap U57M unit 2,050,000.00
22 Penyekat Poslin Urinoar TOTO lbr 523,500.00
23 Kitchen Zink Stainless Standard Lokal ( 1 Lobang ) bh 409,200.00
24 Kitchen Zink Stainless Non Standard Franke ( 1 Lobang ) bh 1,252,800.00
25 Kitchen Zink Stainless Non Standard Franke ( 2 Lobang ) bh 1,873,100.00
26 Sealtipe bh 750.00

N BAHAN PENUTUP ATAP


1 Bubungan Genteng Keramik bh 16,000.00
2 Genteng Keramik Glasur Premium 14,5 / m2 m² 145,000.00

Q BAHAN ALAT PENGANTUNG DAN KUNCI


1 Engsel Pintu Unilon Standard ps 17,200.00
2 Kunci 2 Slaag ISO bh 181,500.00
3 Kunci 2 Slaag Silinder SEIS Asli type 210 s/d type 226 bh 267,500.00
ANALISA HARGA SATUAN PEKERJAAN

NO. KEBUTUHAN INDEKS HARGA. SAT BIAYA BAHAN BIAYA UPAH JUMLAH
1 2 3 4 5 6 7=(4x6) 8=(4x6) 9=(7+8)
A PEKERJAAN PERSIAPAN
1 Memasang 1 m1 bouplank
Kayu Borneo Super 0.010 m³ 5,398,000.00 53,980.00 53,980.00
Bahan
Paku 5 - 7 0.038 kg 17,300.00 657.40 657.40
Tenaga kerja Ongkos Pasang 0.155 ls 54,637.40 8,468.80 8,468.80
Jumlah 54,637.40 8,468.80 63,106.20
Overhead + Profit 6,310.62
Jumlah 69,416.82
Dibulatkan 69,410.00
2 Membuat 1 m2 Kantor Direksi
Kayu Borneo Super 0.100 m³ 5,398,000.00 539,800.00 539,800.00
Paku 5 - 7 0.250 kg 17,300.00 4,325.00 4,325.00
Seng Glb BJLS 28 ( 80 x 180 cm ) 1.100 lbr 65,000.00 71,500.00 71,500.00
Triplex 3 mm 0.500 lbr 52,910.00 26,455.00 26,455.00
Bahan
PC (50 kg) 0.100 zak 67,000.00 6,700.00 6,700.00
Pasir pasang 0.250 m³ 282,530.00 70,632.50 70,632.50
Bata merah 70.000 bh 610.00 42,700.00 42,700.00
Peralatan 0.020 lot 762,112.50 15,242.25 15,242.25
Tenaga kerja Ongkos Pasang 0.150 ls 777,354.75 116,603.21 116,603.21
Jumlah 777,354.75 116,603.21 893,957.96
Overhead + Profit 89,395.80
Jumlah 983,353.76
Dibulatkan 983,350.00
3 Membuat 1 m2 Papan Nama Proyek
Kayu Borneo Super 0.065 m³ 5,398,000.00 350,870.00 350,870.00
Triplex 4 mm 1.000 m³ 62,350.00 62,350.00 62,350.00
Bahan Paku 5 - 7 0.250 kg 17,300.00 4,325.00 4,325.00
Cat Minyak 1.000 kg 44,440.00 44,440.00 44,440.00
Penulisan 0.125 ls 461,985.00 57,748.13 57,748.13
Tenaga kerja Ongkos Pasang 0.125 ls 519,733.13 64,966.64 64,966.64
Jumlah 519,733.13 64,966.64 584,699.77
Overhead + Profit 58,469.98
Jumlah 643,169.74
Dibulatkan 643,160.00
B PEKERJAAN TANAH (SNI 2835:2008)
1 Menggali 1 m3 tanah biasa sedalam 1 meter
Pekerja 0.750 OH 90,000.00 67,500.00 67,500.00
Tenaga kerja
Mandor 0.025 OH 130,000.00 3,250.00 3,250.00
Jumlah 70,750.00 70,750.00
Overhead + Profit 7,075.00
Jumlah 77,825.00
Dibulatkan 77,820.00
2 Menggali 1 m3 tanah biasa sedalam 2 meter
Pekerja 0.900 OH 90,000.00 81,000.00 81,000.00
Tenaga kerja
Mandor 0.045 OH 130,000.00 5,850.00 5,850.00
Jumlah 86,850.00 86,850.00
Overhead + Profit 8,685.00
Jumlah 95,535.00
Dibulatkan 95,530.00
3 Menggali 1 m3 tanah biasa sedalam 3 meter
Pekerja 1.050 OH 90,000.00 94,500.00 94,500.00
Tenaga kerja
Mandor 0.067 OH 130,000.00 8,710.00 8,710.00
Jumlah 103,210.00 103,210.00
Overhead + Profit 10,321.00
Jumlah 113,531.00
Dibulatkan 113,530.00
B009 Mengerjakan 1 m2 stripping tebing setinggi 1 meter
Pekerja 0.050 OH 90,000.00 4,500.00 4,500.00
Tenaga kerja
Mandor 0.005 OH 130,000.00 650.00 650.00
Jumlah 5,150.00 5,150.00
Overhead + Profit 515.00
Jumlah 5,665.00
Dibulatkan 5,660.00
4 Membuang 1 m3 tanah sejauh 15 meter
Pekerja 0.330 OH 90,000.00 29,700.00 29,700.00
Tenaga kerja
Mandor 0.010 OH 130,000.00 1,300.00 1,300.00
Jumlah 31,000.00 31,000.00
Overhead + Profit 3,100.00
Jumlah 34,100.00
Dibulatkan 34,100.00
NO. KEBUTUHAN INDEKS HARGA. SAT BIAYA BAHAN BIAYA UPAH JUMLAH
1 2 3 4 5 6 7=(4x6) 8=(4x6) 9=(7+8)
5 Mengurug kembali 1 m3 galian
Pekerja 0.250 OH 90,000.00 22,500.00 22,500.00
Tenaga kerja
Mandor 0.008 OH 130,000.00 1,083.33 1,083.33
Jumlah 23,583.33 23,583.33
Overhead + Profit 2,358.33
Jumlah 25,941.67
Dibulatkan 25,940.00
B012 Memadatkan 1 m3 tanah (per 20 cm)
Pekerja 0.500 OH 90,000.00 45,000.00 45,000.00
Tenaga kerja
Mandor 0.050 OH 130,000.00 6,500.00 6,500.00
Jumlah 51,500.00 51,500.00
Overhead + Profit 5,150.00
Jumlah 56,650.00
Dibulatkan 56,650.00
6 Mengurug 1 m3 pasir urug
Bahan Pasir Urug 1.200 m³ 279,220.00 335,064.00 335,064.00
Pekerja 0.300 OH 90,000.00 27,000.00 27,000.00
Tenaga kerja
Mandor 0.010 OH 130,000.00 1,300.00 1,300.00
Jumlah 335,064.00 28,300.00 363,364.00
Overhead + Profit 36,336.40
Jumlah 399,700.40
Dibulatkan 399,700.00
7 Mengurug 1 m3 sirtu padat untuk peninggian lantai bangunan
Bahan Sirtu ( Membeli Sirtu ) 1.200 m³ 320,490.00 384,588.00
Tukang Gali 0.250 org 120,000.00 30,000.00
Tenaga kerja
Mandor 0.025 org 130,000.00 3,250.00
Jumlah 417,838.00
Overhead + Profit 41,783.80
Jumlah 459,621.80
Dibulatkan 459,620.00
8 Mengurug 1 m3 tanah urug & Pemadatan (tiap 20 cm)
Pekerja 0.500 OH 90,000.00 45,000.00 22,500.00
Mandor 0.050 OH 130,000.00 6,500.00 3,250.00
Alat bantu 0.125 lot 205,750.00 25,718.75 12,859.38
Tanah urugan 1.200 m³ 150,000.00 180,000.00 180,000.00
Jumlah 180,000.00 77,218.75 218,609.38
Overhead + Profit 21,860.94
Jumlah 240,470.31
Dibulatkan 240,470.00
C PEKERJAAN PONDASI (SNI 2836:2008)
1 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 5 PP
Batu belah 15 cm/20cm 1.200 m³ 244,830.00 293,796.00 293,796.00
Bahan Portland Cement 136.000 kg 1,340.00 182,240.00 182,240.00
Pasir Pasang 0.544 m³ 282,530.00 153,696.32 153,696.32
Pekerja 1.500 OH 90,000.00 135,000.00 135,000.00
Tukang batu 0.600 OH 120,000.00 72,000.00 72,000.00
Tenaga kerja
Kepala tukang 0.060 OH 130,000.00 7,800.00 7,800.00
Mandor 0.075 OH 130,000.00 9,750.00 9,750.00
Jumlah 629,732.32 224,550.00 854,282.32
Overhead + Profit 85,428.23
Jumlah 939,710.55
Dibulatkan 939,710.00
D PEKERJAAN BETON (SNI 7394:2008)
1 Membuat 1 m3 lantai kerja 1PC : 3 PS : 5 KR
PC (50 kg) 218.000 kg 1,340.00 292,120.00 292,120.00
Bahan Pasir beton 0.520 m³ 277,380.00 144,237.60 144,237.60
Split Pecah mesin 2/3 0.870 m³ 276,960.00 240,955.20 240,955.20
Pekerja 1.650 HO 90,000.00 148,500.00 148,500.00
Tukang batu 0.250 HO 120,000.00 30,000.00 30,000.00
Tenaga kerja
Kepala tukang 0.025 HO 130,000.00 3,250.00 3,250.00
Mandor 0.080 HO 130,000.00 10,400.00 10,400.00
Jumlah 677,312.80 192,150.00 869,462.80
Overhead + Profit 86,946.28
Jumlah 956,409.08
Dibulatkan 956,400.00
D002 Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
PC (50 kg) 247.00 kg 1,340.00 330,980.00
Pasir beton 869.00 kg 198.13 172,173.73
Bahan
Split Pecah mesin 2/3 999.00 kg 205.16 204,950.40
Air 215.00 ltr 12.50 2,687.50
Pekerja 1.650 HO 90,000.00 148,500.00
Tukang batu 0.275 HO 120,000.00 33,000.00
Tenaga kerja
Kepala tukang 0.028 HO 130,000.00 3,640.00
Mandor 0.083 HO 130,000.00 10,790.00
Jumlah 906,721.63
Overhead + Profit 90,672.16
Jumlah 997,393.79
Dibulatkan 997,390.00
Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Bukling factor pasir = 20 %
D003 Membuat 1 m3 beton mutu f’c = 9,8 MPa (K 125), slump (12 ± 2) cm, w/c = 0,78
PC (50 kg) 276.00 kg 1,340.00 369,840.00
Pasir beton 828.00 kg 198.13 164,050.46
Bahan
Split Pecah mesin 2/3 1,012.00 kg 205.16 207,617.42
Air 215.000 ltr 12.50 2,687.50
Pekerja 1.650 HO 90,000.00 148,500.00
Tukang batu 0.275 HO 120,000.00 33,000.00
Tenaga kerja
Kepala tukang 0.028 HO 130,000.00 3,640.00
Mandor 0.083 HO 130,000.00 10,790.00
Jumlah 940,125.38
Overhead + Profit 94,012.54
Jumlah 1,034,137.92
Dibulatkan 1,034,130.00
D004 Membuat 1 m3 beton mutu f’c = 12,2 MPa (K 150), slump (12 ± 2) cm, w/c = 0,72
NO. KEBUTUHAN INDEKS HARGA. SAT BIAYA BAHAN BIAYA UPAH JUMLAH
1 2 3 4 5 6 7=(4x6) 8=(4x6) 9=(7+8)
PC (50 kg) 299.00 kg 1,340.00 400,660.00
Pasir beton 799.00 kg 198.13 158,304.73
Bahan
Split Pecah mesin 2/3 1,017.00 kg 205.16 208,643.20
Air 215.00 ltr 12.50 2,687.50
Pekerja 1.650 HO 90,000.00 148,500.00
Tukang batu 0.275 HO 120,000.00 33,000.00
Tenaga kerja
Kepala tukang 0.028 HO 130,000.00 3,640.00
Mandor 0.083 HO 130,000.00 10,790.00
Jumlah 966,225.43
Overhead + Profit 96,622.54
Jumlah 1,062,847.97
Dibulatkan 1,062,840.00
D005 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87
PC (50 kg) 230.00 kg 1,340.00 308,200.00
Pasir beton 893.00 kg 198.13 176,928.81
Bahan
Split Pecah mesin 2/3 1,017.00 kg 205.16 208,643.20
Air 200.00 ltr 12.50 2,500.00
Pekerja 1.200 HO 90,000.00 108,000.00
Tukang batu 0.200 HO 120,000.00 24,000.00
Tenaga kerja
Kepala tukang 0.020 HO 130,000.00 2,600.00
Mandor 0.060 HO 130,000.00 7,800.00
Jumlah 838,672.01
Overhead + Profit 83,867.20
Jumlah 922,539.22
Dibulatkan 922,530.00
2 Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66
PC (50 kg) 326.00 kg 1,340.00 436,840.00 436,840.00
Pasir beton 760.00 kg 198.13 150,577.71 150,577.71
Bahan
Split Pecah mesin 2/3 1,029.00 kg 205.16 211,105.07 211,105.07
Air 215.00 ltr 12.50 2,687.50 2,687.50
Pekerja 1.650 HO 90,000.00 148,500.00 148,500.00
Tukang batu 0.275 HO 120,000.00 33,000.00 33,000.00
Tenaga kerja
Kepala tukang 0.028 HO 130,000.00 3,640.00 3,640.00
Mandor 0.083 HO 130,000.00 10,790.00 10,790.00
Jumlah 801,210.28 195,930.00 997,140.28
Transportasi laut 200,302.57 200,302.57
Jumlah 1,001,512.85
Overhead + Profit 100,151.29 19,593.00 119,744.29
Jumlah 1,101,664.14 215,523.00 1,317,187.14
Dibulatkan 1,317,180.00
D007 Membuat 1 m3 beton mutu f’c = 16,9 MPa (K 200), slump (12 ± 2) cm, w/c = 0,61
PC (50 kg) 352.00 kg 1,340.00 471,680.00
Pasir beton 731.00 kg 198.13 144,831.99
Bahan
Split Pecah mesin 2/3 1,031.00 kg 205.16 211,515.38
Air 215.00 ltr 12.50 2,687.50
Pekerja 1.650 HO 90,000.00 148,500.00
Tukang batu 0.275 HO 120,000.00 33,000.00
Tenaga kerja
Kepala tukang 0.028 HO 130,000.00 3,640.00
Mandor 0.083 HO 130,000.00 10,790.00
Jumlah 1,026,644.86
Overhead + Profit 102,664.49
Jumlah 1,129,309.35
Dibulatkan 1,129,300.00
2 Membuat 1 m3 beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58
PC (50 kg) 371.00 kg 1,340.00 497,140.00 497,140.00
Pasir beton 698.00 kg 198.13 138,293.74 138,293.74
Bahan
Split Pecah mesin 2/3 1,047.00 kg 205.16 214,797.87 214,797.87
Air 215.00 ltr 12.50 2,687.50 2,687.50
Pekerja 1.650 HO 90,000.00 148,500.00 148,500.00
Tukang batu 0.275 HO 120,000.00 33,000.00 33,000.00
Tenaga kerja
Kepala tukang 0.028 HO 130,000.00 3,640.00 3,640.00
Mandor 0.083 HO 130,000.00 10,790.00 10,790.00
Jumlah 852,919.11 195,930.00 1,048,849.11
Overhead + Profit 104,884.91
Jumlah 1,153,734.02
Dibulatkan 1,153,730.00
D009 Membuat 1 m3 beton mutu f’c = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56
PC (50 kg) 384.00 kg 1,340.00 514,560.00
Pasir beton 692.00 kg 198.13 137,104.97
Bahan
Split Pecah mesin 2/3 1,039.00 kg 205.16 213,156.62
Air 215.00 ltr 12.50 2,687.50
Pekerja 1.650 HO 90,000.00 148,500.00
Tukang batu 0.275 HO 120,000.00 33,000.00
Tenaga kerja
Kepala tukang 0.028 HO 130,000.00 3,640.00
Mandor 0.083 HO 130,000.00 10,790.00
Jumlah 1,063,439.09
Dibulatkan 1,063,430.00
D010 Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275), slump (12 ± 2) cm, w/c = 0,53
PC (50 kg) 406.00 kg 1,340.00 544,040.00
Pasir beton 684.00 kg 198.13 135,519.94
Bahan
Split Pecah mesin 2/3 1,026.00 kg 205.16 210,489.60
Air 215.00 ltr 12.50 2,687.50
Pekerja 1.650 HO 90,000.00 148,500.00
Tukang batu 0.275 HO 120,000.00 33,000.00
Tenaga kerja
Kepala tukang 0.028 HO 130,000.00 3,640.00
Mandor 0.083 HO 130,000.00 10,790.00
Jumlah 1,088,667.04
Overhead + Profit 108,866.70
Jumlah 1,197,533.75
Dibulatkan 1,197,530.00
3 Membuat 1 m3 beton mutu f’c = 26,4 MPa (K 300), slump (12 ± 2) cm, w/c = 0,52
PC (50 kg) 413.00 kg 1,340.00 553,420.00 553,420.00
Pasir beton 681.00 kg 198.13 134,925.56 134,925.56
Bahan
Split Pecah mesin 2/3 1,021.00 kg 205.16 209,463.82 209,463.82
NO. KEBUTUHAN INDEKS HARGA. SAT BIAYA BAHAN BIAYA UPAH JUMLAH
Bahan
1 2 3 4 5 6 7=(4x6) 8=(4x6) 9=(7+8)
Air 215.00 ltr 12.50 2,687.50 2,687.50
Pekerja 1.650 HO 90,000.00 148,500.00 148,500.00
Tukang batu 0.275 HO 120,000.00 33,000.00 33,000.00
Tenaga kerja
Kepala tukang 0.028 HO 130,000.00 3,640.00 3,640.00
Mandor 0.083 HO 130,000.00 10,790.00 10,790.00
Jumlah 900,496.88 195,930.00 1,096,426.88
Transportasi laut 225,124.22 225,124.22
Jumlah 1,125,621.10
Overhead + Profit 112,562.11 19,593.00 132,155.11
Jumlah 1,238,183.21 215,523.00 1,453,706.21
Dibulatkan 1,453,700.00
D012 Membuat 1 m3 beton mutu f’c = 28,8 MPa (K 325), slump (12 ± 2) cm, w/c = 0,49
PC (50 kg) 439.00 kg 1,340.00 588,260.00
Pasir beton 670.00 kg 198.13 132,746.14
Bahan
Split Pecah mesin 2/3 1,006.00 kg 205.16 206,386.49
Air 215.00 ltr 12.50 2,687.50
Pekerja 2.100 HO 90,000.00 189,000.00
Tukang batu 0.350 HO 120,000.00 42,000.00
Tenaga kerja
Kepala tukang 0.035 HO 130,000.00 4,550.00
Mandor 0.105 HO 130,000.00 13,650.00
Jumlah 1,179,280.13
Overhead + Profit 117,928.01
Jumlah 1,297,208.14
Dibulatkan 1,297,200.00
D013 Membuat 1 m3 beton mutu f’c = 28,8 MPa (K 350), slump (12 ± 2) cm, w/c = 0,49
PC (50 kg) 448.00 kg 1,340.00 600,320.00
Pasir beton 667.00 kg 198.13 132,151.76
Bahan
Split Pecah mesin 2/3 1,000.00 kg 205.16 205,155.56
Air 215.00 ltr 12.50 2,687.50
Pekerja 2.100 HO 90,000.00 189,000.00
Tukang batu 0.350 HO 120,000.00 42,000.00
Tenaga kerja
Kepala tukang 0.035 HO 130,000.00 4,550.00
Mandor 0.105 HO 130,000.00 13,650.00
Jumlah 1,189,514.81
Overhead + Profit 118,951.48
Jumlah 1,308,466.29
Dibulatkan 1,308,460.00
D014 Membuat 1 m3 cor beton mutu K-175 (Ready Mix) Min. 6 m3 + slang
Bahan Adukan K-175 Ready Mix 1.00 m3 660,000.00 660,000.00
Pekerja 2.100 HO 90,000.00 189,000.00
Tukang batu 0.350 HO 120,000.00 42,000.00
Tenaga kerja
Kepala tukang 0.035 HO 130,000.00 4,550.00
Mandor 0.105 HO 130,000.00 13,650.00
Peralatan Alat bantu Slab + selang 0.045 lot 909,200.00 40,914.00
Jumlah 950,114.00
Overhead + Profit 95,011.40
Jumlah 1,045,125.40
Dibulatkan 1,045,120.00
D015 Membuat 1 m3 cor beton mutu K-225 (Ready Mix) Min. 6 m3 + slang
Bahan Adukan K-225 Ready Mix 1.00 m3 693,000.00 693,000.00
Pekerja 2.100 HO 90,000.00 189,000.00
Tukang batu 0.350 HO 120,000.00 42,000.00
Tenaga kerja
Kepala tukang 0.035 HO 130,000.00 4,550.00
Mandor 0.105 HO 130,000.00 13,650.00
Peralatan Alat bantu Slab + selang 0.045 lot 942,200.00 42,399.00
Jumlah 984,599.00
Overhead + Profit 98,459.90
Jumlah 1,083,058.90
Dibulatkan 1,083,050.00
D016 Membuat 1 m3 cor beton mutu K-250 (Ready Mix) Min. 6 m3 + slang
Bahan Adukan K-250 Ready Mix 1.00 m3 726,000.00 726,000.00
Pekerja 2.100 HO 90,000.00 189,000.00
Tukang batu 0.350 HO 120,000.00 42,000.00
Tenaga kerja
Kepala tukang 0.035 HO 130,000.00 4,550.00
Mandor 0.105 HO 130,000.00 13,650.00
Peralatan Alat bantu Slab + selang 0.045 lot 975,200.00 43,884.00
Jumlah 1,019,084.00
Overhead + Profit 101,908.40
Jumlah 1,120,992.40
Dibulatkan 1,120,990.00
D017 Membuat 1 m3 cor beton mutu K-300 (Ready Mix) Min. 6 m3 + slang
Bahan Adukan K-300 Ready Mix 1.00 m3 759,000.00 759,000.00
Pekerja 2.100 HO 90,000.00 189,000.00
Tukang batu 0.350 HO 120,000.00 42,000.00
Tenaga kerja
Kepala tukang 0.035 HO 130,000.00 4,550.00
Mandor 0.105 HO 130,000.00 13,650.00
Peralatan Alat bantu Slab + selang 0.045 lot 1,008,200.00 45,369.00
Jumlah 1,053,569.00
Overhead + Profit 105,356.90
Jumlah 1,158,925.90
Dibulatkan 1,158,920.00
D018 Membuat 1 m3 cor beton mutu K-350 (Ready Mix) Min. 6 m3 + slang
Bahan Adukan K-350 Ready Mix 1.00 m3 792,000.00 792,000.00
Pekerja 2.100 HO 90,000.00 189,000.00
Tukang batu 0.350 HO 120,000.00 42,000.00
Tenaga kerja
Kepala tukang 0.035 HO 130,000.00 4,550.00
Mandor 0.105 HO 130,000.00 13,650.00
Peralatan Alat bantu Slab + selang 0.045 lot 1,041,200.00 46,854.00
Jumlah 1,088,054.00
Overhead + Profit 108,805.40
Jumlah 1,196,859.40
Dibulatkan 1,196,850.00
D019 Membuat 1 m3 beton kedap air dengan strorox – 100
PC (50 kg) 400.00 kg 1,340.00 536,000.00

Bahan
NO. KEBUTUHAN INDEKS HARGA. SAT BIAYA BAHAN BIAYA UPAH JUMLAH
1 2 3 4 5 6 7=(4x6) 8=(4x6) 9=(7+8)
Pasir beton 0.480 m³ 277,380.00 133,142.40
Bahan Split Pecah mesin 2/3 0.800 m³ 276,960.00 221,568.00
Storox-100 1.200 kg 25,000.00 30,000.00
Air 210.00 ltr 12.50 2,625.00
Pekerja 2.100 HO 90,000.00 189,000.00
Tukang batu 0.350 HO 120,000.00 42,000.00
Tenaga kerja
Kepala tukang 0.035 HO 130,000.00 4,550.00
Mandor 0.105 HO 130,000.00 13,650.00
Jumlah 1,172,535.40
Overhead + Profit 117,253.54
Jumlah 1,289,788.94
Dibulatkan 1,289,780.00
D020 Memasang 1 m’ PVC Waterstop lebar 150 mm
Bahan Waterstop lebar 150 mm 1.050 m' 109,816.67 115,307.50
Pekerja 0.060 HO 90,000.00 5,400.00
Tukang batu 0.030 HO 120,000.00 3,600.00
Tenaga kerja
Kepala tukang 0.003 HO 130,000.00 390.00
Mandor 0.003 HO 130,000.00 390.00
Jumlah 125,087.50
Overhead + Profit 12,508.75
Jumlah 137,596.25
Dibulatkan 137,590.00
D021 Memasang 1 m’ PVC Waterstop lebar 200 mm
Bahan Waterstop lebar 200 mm 1.050 m' 203,650.00 213,832.50
Pekerja 0.070 HO 90,000.00 6,300.00
Tukang batu 0.035 HO 120,000.00 4,200.00
Tenaga kerja
Kepala tukang 0.004 HO 130,000.00 520.00
Mandor 0.004 HO 130,000.00 520.00
Jumlah 225,372.50
Overhead + Profit 22,537.25
Jumlah 247,909.75
Dibulatkan 247,900.00
D022 Membuat 1 m’ PVC Waterstop lebar 230 mm – 320 mm
Bahan Waterstop lebar 230 mm - 320 mm 1.050 m' 313,466.67 329,140.00
Pekerja 0.080 HO 90,000.00 7,200.00
Tukang batu 0.040 HO 120,000.00 4,800.00
Tenaga kerja
Kepala tukang 0.004 HO 130,000.00 520.00
Mandor 0.004 HO 130,000.00 520.00
Jumlah 342,180.00
Overhead + Profit 34,218.00
Jumlah 376,398.00
Dibulatkan 376,390.00
NO. KEBUTUHAN INDEKS HARGA. SAT BIAYA BAHAN BIAYA UPAH JUMLAH
1 2 3 4 5 6 7=(4x6) 8=(4x6) 9=(7+8)
3 Pembesian 10 kg dengan besi polos atau besi ulir
Besi beton (polos/ulir) 10.500 kg 9,950.00 104,475.00 104,475.00
Bahan
Kawat beton 0.150 kg 18,910.00 2,836.50 2,836.50
Pekerja 0.070 HO 90,000.00 6,300.00 6,300.00
Tukang besi 0.070 HO 120,000.00 8,400.00 8,400.00
Tenaga kerja
Kepala tukang 0.007 HO 130,000.00 910.00 910.00
Mandor 0.004 HO 130,000.00 520.00 520.00
Jumlah 107,311.50 16,130.00 123,441.50
Overhead + Profit 12,344.15
Jumlah 135,785.65
Dibulatkan 135,780.00
4 Memasang 1 m2 jaring kawat baja/wire mesh
Jaring kawat baja dilas 1.020 m2 43,500.00 44,370.00 44,370.00
Bahan
Kawat beton 0.050 kg 18,910.00 945.50 945.50
Pekerja 0.025 HO 90,000.00 2,250.00 2,250.00
Tukang besi 0.025 HO 120,000.00 3,000.00 3,000.00
Tenaga kerja
Kepala tukang 0.002 HO 130,000.00 260.00 260.00
Mandor 0.001 HO 130,000.00 130.00 130.00
Jumlah 45,315.50 5,640.00 50,955.50
Overhead + Profit 5,095.55
Jumlah 56,051.05
Dibulatkan 56,050.00
5 Memasang 1 m2 bekisting untuk pondasi
Kayu kelas III 0.040 m³ 2,780,000.00 111,200.00 111,200.00
Bahan Paku 5-10 cm 0.300 kg 17,300.00 5,190.00 5,190.00
Minyak bekisting 0.100 ltr 12,000.00 1,200.00 1,200.00
Pekerja 0.520 HO 90,000.00 46,800.00 46,800.00
Tukang kayu 0.260 HO 120,000.00 31,200.00 31,200.00
Tenaga kerja
Kepala tukang 0.026 HO 130,000.00 3,380.00 3,380.00
Mandor 0.026 HO 130,000.00 3,380.00 3,380.00
Jumlah 117,590.00 84,760.00 202,350.00
Overhead + Profit 20,235.00
Jumlah 222,585.00
Dibulatkan 222,580.00
6 Memasang 1 m2 bekisting untuk sloof
Kayu kelas III 0.045 m³ 2,780,000.00 125,100.00 125,100.00
Bahan Paku 5-10 cm 0.300 kg 17,300.00 5,190.00 5,190.00
Minyak bekisting 0.100 ltr 12,000.00 1,200.00 1,200.00
Pekerja 0.520 HO 90,000.00 46,800.00 46,800.00
Tukang kayu 0.260 HO 120,000.00 31,200.00 31,200.00
Tenaga kerja
Kepala tukang 0.026 HO 130,000.00 3,380.00 3,380.00
Mandor 0.026 HO 130,000.00 3,380.00 3,380.00
Jumlah 131,490.00 84,760.00 85,960.00
Overhead + Profit 8,596.00
Jumlah 94,556.00
Dibulatkan 94,550.00
7 Memasang 1 m2 bekisting untuk kolom
Kayu kelas III 0.040 m³ 2,780,000.00 111,200.00 111,200.00
Paku 5-10 cm 0.400 kg 17,300.00 6,920.00 6,920.00
Minyak bekisting 0.200 ltr 12,000.00 2,400.00 2,400.00
Bahan
Balok kayu kelas II 0.015 m³ 5,398,000.00 80,970.00 80,970.00
Plywood tebal 9 mm 0.350 lbr 150,700.00 52,745.00 52,745.00
Dolken kayu galam Ø (8-10 cm) pj. 4 m 2.000 bt 10,000.00 20,000.00 20,000.00
Pekerja 0.660 HO 90,000.00 59,400.00 59,400.00
Tukang kayu 0.330 HO 120,000.00 39,600.00 39,600.00
Tenaga kerja
Kepala tukang 0.033 HO 130,000.00 4,290.00 4,290.00
Mandor 0.033 HO 130,000.00 4,290.00 4,290.00
Jumlah 274,235.00 107,580.00 381,815.00
Overhead + Profit 38,181.50
Jumlah 419,996.50
Dibulatkan 419,990.00
8 Memasang 1 m2 bekisting untuk balok
Kayu kelas III 0.040 m³ 2,780,000.00 111,200.00 111,200.00
Paku 5-12 cm 0.400 kg 15,560.00 6,224.00 6,224.00
Minyak bekisting 0.200 ltr 12,000.00 2,400.00 2,400.00
Bahan
Balok kayu kelas II 0.018 m³ 5,398,000.00 97,164.00 97,164.00
Plywood tebal 9 mm 0.350 lbr 150,700.00 52,745.00 52,745.00
Dolken kayu galam Ø (8-10 cm) pj. 4 m 2.000 bt 10,000.00 20,000.00 20,000.00
Pekerja 0.660 HO 90,000.00 59,400.00 59,400.00
Tukang kayu 0.330 HO 120,000.00 39,600.00 39,600.00
Tenaga kerja
Kepala tukang 0.033 HO 130,000.00 4,290.00 4,290.00
Mandor 0.033 HO 130,000.00 4,290.00 4,290.00
Jumlah 289,733.00 107,580.00 397,313.00
Overhead + Profit 39,731.30
Jumlah 437,044.30
Dibulatkan 437,040.00
NO. KEBUTUHAN INDEKS HARGA. SAT BIAYA BAHAN BIAYA UPAH JUMLAH
1 2 3 4 5 6 7=(4x6) 8=(4x6) 9=(7+8)
9 Memasang 1 m2 bekisting untuk plat lantai
Kayu kelas III 0.040 m³ 2,780,000.00 111,200.00 111,200.00
Paku 5-12 cm 0.400 kg 15,560.00 6,224.00 6,224.00
Minyak bekisting 0.200 ltr 12,000.00 2,400.00 2,400.00
Bahan
Balok kayu kelas II 0.015 m³ 5,398,000.00 80,970.00 80,970.00
Plywood tebal 9 mm 0.350 lbr 150,700.00 52,745.00 52,745.00
Dolken kayu galam Ø (8-10 cm) pj. 4 m 6.000 bt 10,000.00 60,000.00 60,000.00
Pekerja 0.660 HO 90,000.00 59,400.00 59,400.00
Tukang kayu 0.330 HO 120,000.00 39,600.00 39,600.00
Tenaga kerja
Kepala tukang 0.033 HO 130,000.00 4,290.00 4,290.00
Mandor 0.033 HO 130,000.00 4,290.00 4,290.00
Jumlah 313,539.00 107,580.00 421,119.00
Overhead + Profit 42,111.90
Jumlah 463,230.90
Dibulatkan 463,230.00
10 Memasang 1 m2 bekisting untuk dinding
Kayu kelas III 0.040 m³ 2,780,000.00 111,200.00 111,200.00
Paku 5-12 cm 0.400 kg 15,560.00 6,224.00 6,224.00
Minyak bekisting 0.200 ltr 12,000.00 2,400.00 2,400.00
Bahan Balok kayu kelas II 0.020 m³ 5,398,000.00 107,960.00 107,960.00
Plywood tebal 9 mm 0.350 lbr 150,700.00 52,745.00 52,745.00
Dolken kayu galam Ø (8-10 cm) pj. 4 m 3.000 bt 10,000.00 30,000.00 30,000.00
Formite/penjaga jarak bekisting/spacer 4.000 bh 5,000.00 20,000.00 20,000.00
Pekerja 0.660 HO 90,000.00 59,400.00 59,400.00
Tukang kayu 0.330 HO 120,000.00 39,600.00 39,600.00
Tenaga kerja
Kepala tukang 0.033 HO 130,000.00 4,290.00 4,290.00
Mandor 0.033 HO 130,000.00 4,290.00 4,290.00
Jumlah 330,529.00 107,580.00 438,109.00
Overhead + Profit 43,810.90
Jumlah 481,919.90
Dibulatkan 481,910.00
11 Memasang 1 m2 bekisting untuk tangga
Kayu kelas III 0.030 m³ 2,780,000.00 83,400.00 83,400.00
Paku 5-12 cm 0.400 kg 15,560.00 6,224.00 6,224.00
Minyak bekisting 0.150 ltr 12,000.00 1,800.00 1,800.00
Bahan
Balok kayu kelas II 0.015 m³ 5,398,000.00 80,970.00 80,970.00
Plywood tebal 9 mm 0.350 lbr 150,700.00 52,745.00 52,745.00
Dolken kayu galam Ø (8-10 cm) pj. 4 m 2.000 bt 10,000.00 20,000.00 20,000.00
Pekerja 0.660 HO 90,000.00 59,400.00 59,400.00
Tukang kayu 0.330 HO 120,000.00 39,600.00 39,600.00
Tenaga kerja
Kepala tukang 0.033 HO 130,000.00 4,290.00 4,290.00
Mandor 0.033 HO 130,000.00 4,290.00 4,290.00
Jumlah 245,139.00 107,580.00 352,719.00
Overhead + Profit 35,271.90
Jumlah 387,990.90
Dibulatkan 387,990.00
E PEKERJAAN DINDING (SNI 6897:2008)
E008 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal ½ bata, campuran spesi 1 PC : 3 PP
Bata Merah 70.000 bh 610.00 42,700.00
Bahan Portland Cement 14.370 kg 1,340.00 19,255.80
Pasir Pasang 0.042 m³ 282,530.00 11,866.26
Pekerja 0.300 HO 90,000.00 27,000.00
Tukang batu 0.100 HO 120,000.00 12,000.00
Tenaga kerja
Kepala tukang 0.010 HO 130,000.00 1,300.00
Mandor 0.015 HO 130,000.00 1,950.00
Jumlah 116,072.06
Overhead + Profit 11,607.21
Jumlah 127,679.27
Dibulatkan 127,670.00
1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal ½ bata, campuran spesi 1 PC : 4 PP
Bata Merah 70.000 bh 610.00 42,700.00 42,700.00
Bahan Portland Cement 11.500 kg 1,340.00 15,410.00 15,410.00
Pasir Pasang 0.043 m³ 282,530.00 12,148.79 12,148.79
Pekerja 0.300 HO 90,000.00 27,000.00 27,000.00
Tukang batu 0.100 HO 120,000.00 12,000.00 12,000.00
Tenaga kerja
Kepala tukang 0.010 HO 130,000.00 1,300.00 1,300.00
Mandor 0.015 HO 130,000.00 1,950.00 1,950.00
Jumlah 70,258.79 42,250.00 112,508.79
Overhead + Profit 11,250.88
Jumlah 123,759.67
Dibulatkan 123,750.00
2 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal ½ bata, campuran spesi 1 PC : 5 PP
Bata Merah 70.000 bh 610.00 42,700.00 42,700.00
Bahan Portland Cement 9.680 kg 1,340.00 12,971.20 12,971.20
Pasir Pasang 0.045 m³ 282,530.00 12,713.85 12,713.85
Pekerja 0.300 HO 90,000.00 27,000.00 27,000.00
Tukang batu 0.100 HO 120,000.00 12,000.00 12,000.00
Tenaga kerja
Kepala tukang 0.010 HO 130,000.00 1,300.00 1,300.00
Mandor 0.015 HO 130,000.00 1,950.00 1,950.00
Jumlah 68,385.05 42,250.00 110,635.05
Overhead + Profit 11,063.51
Jumlah 121,698.56
Dibulatkan 121,690.00
NO. KEBUTUHAN INDEKS HARGA. SAT BIAYA BAHAN BIAYA UPAH JUMLAH
1 2 3 4 5 6 7=(4x6) 8=(4x6) 9=(7+8)
3 1 M2 Dinding Pemisah Gypsum t = 9 mm + rangka chanel C75 zinckalum
C75 TB=0,5 4.2000 m' 4,200.00 17,640.00 17,640.00
Gypsum ( 120 x 240 x 9 ) mm 0.7280 Lbr 54,000.00 39,312.00 39,312.00
Paku gypsum 0.2200 kg 86,850.00 19,107.00 19,107.00
Ramset / dina bolt 8.0000 Bh 8,000.00 64,000.00 64,000.00
Cotton plaster 0.1440 Bh 16,500.00 2,376.00 2,376.00
Compoun 0.2500 Zak 83,000.00 20,750.00 20,750.00
Pekerja 0.2000 Oh 90,000.00 18,000.00 18,000.00
Tukang kayu 0.1000 Oh 120,000.00 12,000.00 12,000.00
Kepala tukang 0.0100 Oh 130,000.00 1,300.00 1,300.00
Mandor 0.0100 Oh 130,000.00 1,300.00 1,300.00
Jumlah 163,185.00 32,600.00 195,785.00
Overhead + Profit 19,578.50
Jumlah 215,363.50
Dibulatkan 215,360.00
F PEKERJAAN PENGECATAN (SNI 2407:2008)
F001 Mengecat 1 m2 Beton ICI Eksterior
Cat tembok ICI 0.2500 lt 75,740.00 18,935.00
Alkali ICI sebelum pengecatan 0.1250 lt 25,300.00 3,162.50
Bahan
Rol cat 0.0100 bh 16,000.00 160.00
Ampelas 0.5000 lbr 3,340.00 1,670.00
Pekerja 0.1600 HO 90,000.00 14,400.00
Tukang cat 0.2800 HO 120,000.00 33,600.00
Tenaga kerja
Kepala tukang 0.0300 HO 130,000.00 3,900.00
Mandor 0.0100 HO 130,000.00 1,300.00
Alat Steger Werk 0.0250 lot 77,127.50 1,928.19
Jumlah 79,055.69
Overhead + Profit 7,905.57
Jumlah 86,961.26
Dibulatkan 86,960.00
F002 Mengecat 1 m2 Plafond dan Dinding Interior ICI
Cat tembok ICI 0.2600 lt 75,740.00 19,692.40
Cat dasar sebelum pengecatan 0.1000 lt 31,000.00 3,100.00
Bahan
Rol cat 0.0100 bh 16,000.00 160.00
Ampelas 0.3000 lbr 3,340.00 1,002.00
Pekerja 0.0200 HO 90,000.00 1,800.00
Tukang cat 0.0630 HO 120,000.00 7,560.00
Tenaga kerja
Kepala tukang 0.0060 HO 130,000.00 780.00
Mandor 0.0030 HO 130,000.00 390.00
Alat Steger Werk 0.0250 lot 34,484.40 862.11
Jumlah 35,346.51
Overhead + Profit 3,534.65
Jumlah 38,881.16
Dibulatkan 38,880.00
1 Mengecat 1 m2 Dinding Vinilex (3X)
Cat tembok Vinilex 0.1750 kg 18,000.00 3,150.00 3,150.00
Plamir tembok 0.1600 kg 12,400.00 1,984.00 1,984.00
Bahan
Rol cat 0.0100 bh 16,000.00 160.00 160.00
Ampelas 0.5000 lbr 3,340.00 1,670.00 1,670.00
Pekerja 0.0533 HO 90,000.00 4,800.00 4,800.00
Tukang cat 0.0933 HO 120,000.00 11,200.00 11,200.00
Tenaga kerja
Kepala tukang 0.0300 HO 130,000.00 3,900.00 3,900.00
Mandor 0.0100 HO 130,000.00 1,300.00 1,300.00
Alat Steger Werk 0.0450 lot 28,164.00 1,267.38 1,267.38
Jumlah 8,231.38 21,200.00 29,431.38
Overhead + Profit 2,943.14
Jumlah 32,374.52
Dibulatkan 32,370.00
2 Mengecat 1 m2 Plafond Vinilex (3X)
Cat tembok Vinilex 0.2000 kg 18,000.00 3,600.00 3,600.00
Plamir tembok 0.1600 kg 12,400.00 1,984.00 1,984.00
Bahan
Rol cat 0.0100 bh 16,000.00 160.00 160.00
Ampelas 0.5000 lbr 3,340.00 1,670.00 1,670.00
Pekerja 0.0533 HO 90,000.00 4,800.00 4,800.00
Tukang cat 0.0933 HO 120,000.00 11,200.00 11,200.00
Tenaga kerja
Kepala tukang 0.0300 HO 130,000.00 3,900.00 3,900.00
Mandor 0.0100 HO 130,000.00 1,300.00 1,300.00
Alat Steger Werk 0.0425 lot 28,614.00 1,216.10 1,216.10
Jumlah 8,630.10 21,200.00 29,830.10
Overhead + Profit 2,983.01
Jumlah 32,813.10
Dibulatkan 32,810.00
3 Mengecat 1 m2 Kayu (3X) Glotex berikut Meni
Meni kayu 0.1670 kg 16,000.00 2,672.00 2,672.00
Plamir kayu 0.0830 kg 24,400.00 2,025.20 2,025.20
Cat kayu merk GLOTEK 0.2000 kg 36,500.00 7,300.00 7,300.00
Bahan
Amplas kayu 0.4000 lbr 3,340.00 1,336.00 1,336.00
Minyak cat terpentin 0.1500 ltr 5,000.00 750.00 750.00
Kwas 3" 0.0500 bh 10,900.00 545.00 545.00
Pekerja 0.2000 HO 90,000.00 18,000.00 18,000.00
Tukang cat 0.3000 HO 120,000.00 36,000.00 36,000.00
Tenaga kerja
Kepala tukang 0.0300 HO 130,000.00 3,900.00 3,900.00
Mandor 0.0100 HO 130,000.00 1,300.00 1,300.00
Jumlah 14,628.20 59,200.00 73,828.20
Overhead + Profit 7,382.82
Jumlah 81,211.02
Dibulatkan 81,210.00
4 Mengecat 1 m2 Kayu Lama (2X) Glotex
Mengecat 1 m2 Kayu (3X) Glotex berikut Meni 2/3 X 81,210.00 54,140.00
Dibulatkan 54,130.00
5 Mengecat 1 m2 Plituran Meubulair
Dempul plitur (dempul kasar) 0.0300 kg 26,400.00 792.00 792.00

Bahan
NO. KEBUTUHAN INDEKS HARGA. SAT BIAYA BAHAN BIAYA UPAH JUMLAH
1 2 3 4 5 6 7=(4x6) 8=(4x6) 9=(7+8)
Wood Filer (INFRA) 0.2000 kg 28,800.00 5,760.00 5,760.00
Melamik 0.3500 kg 37,500.00 13,125.00 13,125.00
Oker putih 0.0200 kg 21,100.00 422.00 422.00
Oker warna 0.0100 kg 21,100.00 211.00 211.00
Bahan
Batu Apung (gosok) 0.1000 kg 15,600.00 1,560.00 1,560.00
Sirlak ex India 0.2000 kg 87,200.00 17,440.00 17,440.00
Kwas 3" 0.0100 bh 10,900.00 109.00 109.00
Spirtus 0.2000 ltr 4,000.00 800.00 800.00
Ampelas kayu 0.1000 lbr 3,340.00 334.00 334.00
Pekerja 0.2500 HO 90,000.00 22,500.00 22,500.00
Tukang cat 0.2850 HO 120,000.00 34,200.00 34,200.00
Tenaga kerja
Kepala tukang 0.0400 HO 130,000.00 5,200.00 5,200.00
Mandor 0.0200 HO 130,000.00 2,600.00 2,600.00
Jumlah 40,553.00 64,500.00 105,053.00
Overhead + Profit 10,505.30
Jumlah 115,558.30
Dibulatkan 115,550.00
NO. KEBUTUHAN INDEKS HARGA. SAT BIAYA BAHAN BIAYA UPAH JUMLAH
1 2 3 4 5 6 7=(4x6) 8=(4x6) 9=(7+8)
6 Mengecat 1 m2 Permukaan baja zinchromat
Bahan Cat Zinchromat 0.3000 kg 32,600.00 9,780.00 9,780.00
Pekerja 0.0060 HO 90,000.00 540.00 540.00
Tukang cat 0.0600 HO 120,000.00 7,200.00 7,200.00
Tenaga kerja
Kepala tukang 0.0120 HO 130,000.00 1,560.00 1,560.00
Mandor 0.0060 HO 130,000.00 780.00 780.00
Jumlah 9,780.00 10,080.00 19,860.00
Overhead + Profit 1,986.00
Jumlah 21,846.00
Dibulatkan 21,840.00
G PEKERJAAN PENUTUP LANTAI DAN DINDING (SNI 7395:2008)
1 Memasang 1 m2 lantai keramik ukuran (20 x 20) cm DN Putih setara Roman
Ubin keramik 26.500 bh 2,000.00 53,000.00 53,000.00
Portland Cement 10.400 kg 1,340.00 13,936.00 13,936.00
Bahan
Pasir Pasang 0.045 m³ 282,530.00 12,713.85 12,713.85
Semen Warna 1.630 kg 11,500.00 18,745.00 18,745.00
Pekerja 0.700 HO 90,000.00 63,000.00 63,000.00
Tukang batu 0.350 HO 120,000.00 42,000.00 42,000.00
Tenaga kerja
Kepala tukang 0.035 HO 130,000.00 4,550.00 4,550.00
Mandor 0.035 HO 130,000.00 4,550.00 4,550.00
Jumlah 98,394.85 114,100.00 212,494.85
Overhead + Profit 21,249.49
Jumlah 233,744.34
Dibulatkan 233,740.00
2 Memasang 1 m2 lantai keramik ukuran (33 x 33) cm DN bercorak/berwarna setara Roman
Ubin keramik 10.000 bh 3,800.00 38,000.00 38,000.00
Portland Cement 8.190 kg 1,340.00 10,974.60 10,974.60
Bahan
Pasir Pasang 0.045 m³ 282,530.00 12,713.85 12,713.85
Semen Warna 1.620 kg 11,500.00 18,630.00 18,630.00
Pekerja 0.700 HO 90,000.00 63,000.00 63,000.00
Tukang batu 0.350 HO 120,000.00 42,000.00 42,000.00
Tenaga kerja
Kepala tukang 0.035 HO 130,000.00 4,550.00 4,550.00
Mandor 0.035 HO 130,000.00 4,550.00 4,550.00
Jumlah 80,318.45 114,100.00 194,418.45
Overhead + Profit 19,441.85
Jumlah 213,860.30
Dibulatkan 213,860.00
3 Memasang 1 m2 lantai keramik ukuran (40 x 40) cm DN bercorak/berwarna setara Roman
Ubin keramik 6.563 bh 7,740.00 50,793.75 50,793.75
Portland Cement 10.000 kg 1,340.00 13,400.00 13,400.00
Bahan
Pasir Pasang 0.045 m³ 282,530.00 12,713.85 12,713.85
Semen Warna 1.500 kg 11,500.00 17,250.00 17,250.00
Pekerja 0.700 HO 90,000.00 63,000.00 63,000.00
Tukang batu 0.350 HO 120,000.00 42,000.00 42,000.00
Tenaga kerja
Kepala tukang 0.035 HO 130,000.00 4,550.00 4,550.00
Mandor 0.035 HO 130,000.00 4,550.00 4,550.00
Jumlah 94,157.60 114,100.00 208,257.60
Overhead + Profit 20,825.76
Jumlah 229,083.36
Dibulatkan 229,080.00
4 Memasang 1 m2 lantai keramik ukuran (20 x 20) cm DN bercorak/berwarna setara Roman
Ubin keramik 26.500 bh 2,200.00 58,300.00 58,300.00
Portland Cement 10.400 kg 1,340.00 13,936.00 13,936.00
Bahan
Pasir Pasang 0.045 m³ 282,530.00 12,713.85 12,713.85
Semen Warna 1.630 kg 11,500.00 18,745.00 18,745.00
Pekerja 0.700 HO 90,000.00 63,000.00 63,000.00
Tukang batu 0.350 HO 120,000.00 42,000.00 42,000.00
Tenaga kerja
Kepala tukang 0.035 HO 130,000.00 4,550.00 4,550.00
Mandor 0.035 HO 130,000.00 4,550.00 4,550.00
Jumlah 103,694.85 114,100.00 217,794.85
Overhead + Profit 21,779.49
Jumlah 239,574.34
Dibulatkan 239,570.00
5 Memasang 1 m2 Floor Hardener
Floor Hardener 5.000 kg 29,000.00 145,000.00 145,000.00
Bahan
Pekerja 0.120 HO 90,000.00 10,800.00 10,800.00
Tukang batu 0.120 HO 120,000.00 14,400.00 14,400.00
Tenaga kerja
Kepala tukang 0.012 HO 130,000.00 1,560.00 1,560.00
Mandor 0.006 HO 130,000.00 780.00 780.00
Jumlah 145,000.00 27,540.00 172,540.00
Overhead + Profit 17,254.00
Jumlah 189,794.00
Dibulatkan 189,790.00
6 Memasang 1 m2 Waterprofing membran
Waterprofing membran 1.333 kg 79,900.00 106,530.67 106,530.67
Bahan
Alat bantu 0.015 ls 106,530.67 1,597.96 1,597.96
Pekerja 0.143 HO 90,000.00 12,870.00 12,870.00
Tukang batu 0.107 HO 120,000.00 12,840.00 12,840.00
Tenaga kerja
Kepala tukang 0.011 HO 130,000.00 1,365.00 1,365.00
Mandor 0.010 HO 130,000.00 1,300.00 1,300.00
Jumlah 108,128.63 28,375.00 136,503.63
Overhead + Profit 13,650.36
Jumlah 150,153.99
Dibulatkan 150,150.00
NO. KEBUTUHAN INDEKS HARGA. SAT BIAYA BAHAN BIAYA UPAH JUMLAH
1 2 3 4 5 6 7=(4x6) 8=(4x6) 9=(7+8)
7 Memasang 1 m2 dinding keramik ukuran (20 x 20) cm, DN bercorak/berwarna setara Roman
Keramik 26.500 m2 2,200.00 58,300.00 58,300.00
Portland Cement 9.300 kg 1,340.00 12,462.00 12,462.00
Bahan
Pasir Pasang 0.018 m³ 282,530.00 5,085.54 5,085.54
Semen Warna 1.940 kg 11,500.00 22,310.00 22,310.00
Pekerja 0.900 HO 90,000.00 81,000.00 81,000.00
Tukang batu 0.450 HO 120,000.00 54,000.00 54,000.00
Tenaga kerja
Kepala tukang 0.045 HO 130,000.00 5,850.00 5,850.00
Mandor 0.045 HO 130,000.00 5,850.00 5,850.00
Jumlah 98,157.54 146,700.00 244,857.54
Overhead + Profit 24,485.75
Jumlah 269,343.29
Dibulatkan 269,340.00
8 Memasang 1 m2 dinding batu andesit
Batu andesit 1.100 m2 215,000.00 236,500.00
Bahan Portland Cement 11.750 kg 1,340.00 15,745.00
Pasir Pasang 0.035 m³ 282,530.00 9,888.55
Pekerja 0.700 HO 90,000.00 63,000.00
Tukang batu 0.350 HO 120,000.00 42,000.00
Tenaga kerja
Kepala tukang 0.035 HO 130,000.00 4,550.00
Mandor 0.035 HO 130,000.00 4,550.00
Jumlah 376,233.55
Overhead + Profit 37,623.36
Jumlah 413,856.91
Dibulatkan 413,850.00
H PEKERJAAN PLESTERAN (SNI 2837:2008)
1 Membuat 1 m2 plesteran 1 PC : 3 PP, tebal 20 mm
Portland Cement 10.368 kg 1,340.00 13,893.12 13,893.12
Bahan
Pasir Pasang 0.031 m3 282,530.00 8,758.43 8,758.43
Pekerja 0.400 HO 90,000.00 36,000.00 36,000.00
Tukang batu 0.200 HO 120,000.00 24,000.00 24,000.00
Tenaga kerja
Kepala tukang 0.020 HO 130,000.00 2,600.00 2,600.00
Mandor 0.022 HO 130,000.00 2,860.00 2,860.00
Jumlah 22,651.55 65,460.00 88,111.55
Overhead + Profit 8,811.16
Jumlah 96,922.71
Dibulatkan 96,920.00
H015 Membuat 1 m2 plesteran 1 PC : 4 PP, tebal 20 mm
Portland Cement 8.320 kg 1,340.00 11,148.80
Bahan
Pasir Pasang 0.032 m3 282,530.00 9,040.96
Pekerja 0.400 HO 90,000.00 36,000.00
Tukang batu 0.200 HO 120,000.00 24,000.00
Tenaga kerja
Kepala tukang 0.020 HO 130,000.00 2,600.00
Mandor 0.022 HO 130,000.00 2,860.00
Jumlah 85,649.76
Overhead + Profit 8,564.98
Jumlah 94,214.74
Dibulatkan 94,210.00
2 Membuat 1 m2 plesteran 1 PC : 5 PP, tebal 20 mm
Portland Cement 6.912 kg 1,340.00 9,262.08 9,262.08
Bahan
Pasir Pasang 0.035 m3 282,530.00 9,888.55 9,888.55
Pekerja 0.400 HO 90,000.00 36,000.00 36,000.00
Tukang batu 0.200 HO 120,000.00 24,000.00 24,000.00
Tenaga kerja
Kepala tukang 0.020 HO 130,000.00 2,600.00 2,600.00
Mandor 0.022 HO 130,000.00 2,860.00 2,860.00
Jumlah 19,150.63 65,460.00 84,610.63
Overhead + Profit 8,461.06
Jumlah 93,071.69
Dibulatkan 93,070.00
3 Membuat 1 m2 Berapen 1 PC : 5 PP, tebal 15 mm
Portland Cement 5.184 kg 1,340.00 6,946.56 6,946.56
Bahan
Pasir Pasang 0.026 m3 282,530.00 7,345.78 7,345.78
Pekerja 0.150 HO 90,000.00 13,500.00 13,500.00
Tukang batu 0.075 HO 120,000.00 9,000.00 9,000.00
Tenaga kerja
Kepala tukang 0.008 HO 130,000.00 1,040.00 1,040.00
Mandor 0.008 HO 130,000.00 1,040.00 1,040.00
Jumlah 14,292.34 24,580.00 38,872.34
Overhead + Profit 3,887.23
Jumlah 42,759.57
Dibulatkan 42,750.00
4 Membuat 1 m2 finishing siar pasangan batu kali adukan 1 PC : 2 PP
Bahan Portland Cement 6.340 kg 1,340.00 8,495.60 8,495.60
Pasir Pasang 0.012 m3 282,530.00 3,390.36 3,390.36
Pekerja 0.300 HO 90,000.00 27,000.00 27,000.00
Tukang batu 0.150 HO 120,000.00 18,000.00 18,000.00
Tenaga kerja
Kepala tukang 0.015 HO 130,000.00 1,950.00 1,950.00
Mandor 0.015 HO 130,000.00 1,950.00 1,950.00
Jumlah 11,885.96 48,900.00 60,785.96
Overhead + Profit 6,078.60
Jumlah 66,864.56
Dibulatkan 66,860.00
5 Membuat 1 m2 acian
Bahan Portland Cement 3.250 m3 1,340.00 4,355.00 4,355.00
Pekerja 0.200 HO 90,000.00 18,000.00 18,000.00
Tukang batu 0.100 HO 120,000.00 12,000.00 12,000.00
Tenaga kerja
Kepala tukang 0.010 HO 130,000.00 1,300.00 1,300.00
Mandor 0.010 HO 130,000.00 1,300.00 1,300.00
Jumlah 4,355.00 32,600.00 36,955.00
Overhead + Profit 3,695.50
Jumlah 40,650.50
Dibulatkan 40,650.00
I PEKERJAAN KAYU (SNI 3434:2008)
1 Membuat dan memasang 1 m2 daun pintu panel, kayu kelas I atau II
NO. KEBUTUHAN INDEKS HARGA. SAT BIAYA BAHAN BIAYA UPAH JUMLAH
1 2 3 4 5 6 7=(4x6) 8=(4x6) 9=(7+8)
Papan Kayu 0.040 m3 4,290,000.00 171,600.00 171,600.00
Bahan
Lem kayu 0.500 kg 29,830.00 14,915.00 14,915.00
Pekerja 1.000 HO 90,000.00 90,000.00 90,000.00
Tukang Kayu 3.000 HO 120,000.00 360,000.00 360,000.00
Tenaga kerja
Kepala tukang 0.300 HO 130,000.00 39,000.00 39,000.00
Mandor 0.050 HO 130,000.00 6,500.00 6,500.00
Jumlah 186,515.00 495,500.00 682,015.00
Overhead + Profit 68,201.50
Jumlah 750,216.50
Dibulatkan 750,210.00
J PEKERJAAN BESI DAN ALUMINIUM (SNI 7393:2008)
J001 Memasang 1 kg besi profil
Bahan Besi profil 1.150 kg 10,300.00 11,845.00
Pekerja 0.060 HO 90,000.00 5,400.00
Tukang las konstruksi 0.060 HO 120,000.00 7,200.00
Tenaga kerja
Kepala tukang 0.006 HO 130,000.00 780.00
Mandor 0.003 HO 130,000.00 390.00
Jumlah 25,615.00
Overhead + Profit 2,561.50
Jumlah 28,176.50
Dibulatkan 28,170.00
1 Memasang 1 kg rangka kuda-kuda baja IWF
Bahan Besi baja IWF 1.150 kg 9,950.00 11,442.50 11,442.50
Pekerja 0.053 HO 90,000.00 4,770.00 4,770.00
Tukang las konstruksi 0.053 HO 120,000.00 6,360.00 6,360.00
Tenaga kerja
Kepala tukang 0.006 HO 130,000.00 715.00 715.00
Mandor 0.003 HO 130,000.00 390.00 390.00
Jumlah 11,442.50 12,235.00 23,677.50
Overhead + Profit 2,367.75
Jumlah 26,045.25
Dibulatkan 26,040.00
J003 Mengerjakan 100 kg pekerjaan perakitan
Solar 1.000 ltr 5,500.00 5,500.00
Bahan
Minyak pelumas 0.100 ltr 12,000.00 1,200.00
Pekerja 0.100 HO 90,000.00 9,000.00
Tukang las konstruksi 0.100 HO 120,000.00 12,000.00
Tenaga kerja
Kepala tukang 0.001 HO 130,000.00 130.00
Mandor 0.005 HO 130,000.00 650.00
Alat Sewa alat 0.800 jam 28,480.00 22,784.00
Jumlah 44,564.00
Overhead + Profit 4,456.40
Jumlah 49,020.40
Dibulatkan 49,020.00
J004 Membuat 1 m2 pintu besi plat baja tebal 2 mm rangkap, rangka baja siku
Besi siku L 30.30.3 15.000 kg 11,000.00 165,000.00
Bahan Besi plat baja 32.800 kg 11,100.00 364,080.00
Kawat las 0.050 kg 18,400.00 920.00
Pekerja 1.050 HO 90,000.00 94,500.00
Tukang las konstruksi 1.050 HO 120,000.00 126,000.00
Tenaga kerja
Kepala tukang 0.105 HO 130,000.00 13,650.00
Mandor 0.052 HO 130,000.00 6,760.00
Jumlah 770,910.00
Overhead + Profit 77,091.00
Jumlah 848,001.00
Dibulatkan 848,000.00
J005 Mengerjakan 10 cm pengelasan dengan las listrik
Kawat las listrik 0.400 kg 18,400.00 7,360.00
Bahan Solar 0.300 ltr 5,500.00 1,650.00
Minyak pelumas 0.040 ltr 12,000.00 480.00
Pekerja 0.040 HO 90,000.00 3,600.00
Tukang las konstruksi 0.002 HO 120,000.00 240.00
Tenaga kerja
Kepala tukang 0.002 HO 130,000.00 260.00
Mandor 0.170 HO 130,000.00 22,100.00
Jumlah 26,680.00
Overhead + Profit 2,668.00
Jumlah 29,348.00
Dibulatkan 29,340.00
J006 Membuat 1 m2 rangka jendela besi scuare tube (25 x 5) cm
Besi scuare tube 4.760 m' 22,000.00 104,720.00
Bahan Besi lis kaca (1 x 1) cm 4.522 m' 20,000.00 90,440.00
Pintu gulung besi 20.000 cm 4,500.00 90,000.00
Pekerja 0.650 HO 90,000.00 58,500.00
Tukang las biasa 0.650 HO 120,000.00 78,000.00
Tenaga kerja
Kepala tukang 0.065 HO 130,000.00 8,450.00
Mandor 0.032 HO 130,000.00 4,160.00
Jumlah 239,110.00
Overhead + Profit 23,911.00
Jumlah 263,021.00
Dibulatkan 263,020.00
J007 Memasang 1 m2 pintu rolling door besi
Bahan Pintu gulung besi 1.000 m2 4,500.00 4,500.00
Pekerja 1.200 HO 90,000.00 108,000.00
Tukang las biasa 1.200 HO 120,000.00 144,000.00
Tenaga kerja
Kepala tukang 0.120 HO 130,000.00 15,600.00
Mandor 0.006 HO 130,000.00 780.00
Jumlah 272,880.00
Overhead + Profit 27,288.00
Jumlah 300,168.00
Dibulatkan 300,160.00
J008 Memasang 1 m2 pintu lipat (Folding door) bahan plastik/PVC
Bahan Pintu lipat 1.000 m2 450,000.00 450,000.00
Pekerja 0.440 HO 90,000.00 39,600.00
Tukang 0.440 HO 120,000.00 52,800.00
Tenaga kerja
NO. KEBUTUHAN INDEKS HARGA. SAT BIAYA BAHAN BIAYA UPAH JUMLAH
1 2 3 4 5 6 7=(4x6) 8=(4x6) 9=(7+8)
Tenaga kerja
Kepala tukang 0.044 HO 130,000.00 5,720.00
Mandor 0.220 HO 130,000.00 28,600.00
Jumlah 576,720.00
Overhead + Profit 57,672.00
Jumlah 634,392.00
Dibulatkan 634,390.00
J009 Memasang 1 m2 sunscreen alluminium
Bahan Sunscreen alluminium 1.000 m2 350,000.00 350,000.00
Pekerja 0.088 HO 90,000.00 7,920.00
Tukang 0.800 HO 120,000.00 96,000.00
Tenaga kerja
Kepala tukang 0.080 HO 130,000.00 10,400.00
Mandor 0.004 HO 130,000.00 520.00
Jumlah 464,840.00
Overhead + Profit 46,484.00
Jumlah 511,324.00
Dibulatkan 511,320.00
J010 Memasang 1 m2 rolling door alluminium
Bahan Rolling door alluminium 1.000 m2 600,000.00 600,000.00
Pekerja 1.000 HO 90,000.00 90,000.00
Tukang 1.000 HO 120,000.00 120,000.00
Tenaga kerja
Kepala tukang 0.100 HO 130,000.00 13,000.00
Mandor 0.050 HO 130,000.00 6,500.00
Jumlah 829,500.00
Overhead + Profit 82,950.00
Jumlah 912,450.00
Dibulatkan 912,450.00
21 Memasang 1 m kusen pintu alluminium warna
Profil alluminium 1.100 m' 165,750.00 182,325.00
Bahan Skrup fixer 2.000 bh 3,000.00 6,000.00
Sealant 0.060 tube 25,000.00 1,500.00
Pekerja 0.043 HO 90,000.00 3,870.00
Tukang khusus alluminium 0.043 HO 120,000.00 5,160.00
Tenaga kerja
Kepala tukang 0.0043 HO 130,000.00 559.00
Mandor 0.0021 HO 130,000.00 273.00
Jumlah 199,687.00
Dibulatkan 199,680.00
J012 Memasang 1 m2 pintu alluminium strip lebar 8 cm
Profil alluminium 4.400 m' 165,750.00 729,300.00
Bahan
Alluminium strip 14.600 m' 40,000.00 584,000.00
Pekerja 0.085 HO 90,000.00 7,650.00
Tukang khusus alluminium 0.085 HO 120,000.00 10,200.00
Tenaga kerja
Kepala tukang 0.0085 HO 130,000.00 1,105.00
Mandor 0.0042 HO 130,000.00 546.00
Jumlah 603,501.00
Overhead + Profit 60,350.10
Jumlah 663,851.10
Dibulatkan 663,850.00
22 Memasang 1 m2 pintu kaca rangka alluminium
Pintu alluminium 4.400 m' 174,960.00 769,824.00
Bahan Profil kaca 4.500 m' 4,500.00 20,250.00
Sealant 0.270 tube 25,000.00 6,750.00
Pekerja 0.085 HO 90,000.00 7,650.00
Tukang khusus alluminium 0.085 HO 120,000.00 10,200.00
Tenaga kerja
Kepala tukang 0.009 HO 130,000.00 1,170.00
Mandor 0.005 HO 130,000.00 650.00
Jumlah 816,494.00
Overhead + Profit 81,649.40
Jumlah 898,143.40
Dibulatkan 898,140.00
J014 Memasang 1 m2 venetions blinds dan Vertical blinds
Bahan Venetions blinds dan vertical blinds (tirai) 1.000 m2 275,000.00 275,000.00
Pekerja 0.350 HO 90,000.00 31,500.00
Tukang 0.350 HO 120,000.00 42,000.00
Tenaga kerja
Kepala tukang 0.035 HO 130,000.00 4,550.00
Mandor 0.018 HO 130,000.00 2,340.00
Jumlah 355,390.00
Overhead + Profit 35,539.00
Jumlah 390,929.00
Dibulatkan 390,920.00
J015 Memasang 1 m2 terali besi strip (2 x 3) mm
Besi strip 6.177 kg 12,390.00
Bahan
Pengelasan 27.080 cm 2,668.00 72,249.44
Pekerja 1.670 HO 90,000.00 150,300.00
Tukang las 1.670 HO 120,000.00 200,400.00
Tenaga kerja
Kepala tukang 0.167 HO 130,000.00 21,710.00
Mandor 0.083 HO 130,000.00 10,790.00
Jumlah 455,449.44
Overhead + Profit 45,544.94
Jumlah 500,994.38
Dibulatkan 500,990.00
NO. KEBUTUHAN INDEKS HARGA. SAT BIAYA BAHAN BIAYA UPAH JUMLAH
1 2 3 4 5 6 7=(4x6) 8=(4x6) 9=(7+8)
2 Memasang 1 m2 kawat harmonika
Kawat harmonika 1.100 m2 34,900.00 38,390.00 38,390.00
Bahan Pengelasan 11.110 cm 2,668.00 29,641.48 29,641.48
Baja strip (0,2X2)cm 1.716 kg 12,390.00 21,261.24 21,261.24
Pekerja 0.100 HO 90,000.00 9,000.00 9,000.00
Tukang las 0.100 HO 120,000.00 12,000.00 12,000.00
Tenaga kerja
Kepala tukang 0.010 HO 130,000.00 1,300.00 1,300.00
Mandor 0.005 HO 130,000.00 650.00 650.00
Jumlah 89,292.72 22,950.00 112,242.72
Overhead + Profit 11,224.27
Jumlah 123,466.99
Dibulatkan 123,460.00
3 Memasang 1 m’ talang datar/ jurai seng bjls 28 lebar 90 cm
Seng plat 1.050 m' 25,888.89 27,183.33 27,183.33
Bahan Paku 1 cm – 2,5 cm 0.015 kg 19,620.00 294.30 294.30
Papan kayu kelas II atau III 0.019 m3 2,780,000.00 52,820.00 52,820.00
Pekerja 0.200 HO 90,000.00 18,000.00 18,000.00
Tukang 0.100 HO 120,000.00 12,000.00 12,000.00
Tenaga kerja
Kepala tukang 0.250 HO 130,000.00 32,500.00 32,500.00
Mandor 0.010 HO 130,000.00 1,300.00 1,300.00
Jumlah 80,297.63 63,800.00 144,097.63
Overhead + Profit 14,409.76
Jumlah 158,507.40
Dibulatkan 158,500.00
J020 Memasang 1 M2 atap baja ringan Setara Maxitop Bluescope lysaght bentang max. 8m + rangka dan reng
Bahan dan Upah 1.000 m2 165,000.00 165,000.00
Jumlah 165,000.00
Overhead + Profit 16,500.00
Jumlah 181,500.00
Dibulatkan 181,500.00
K PEKERJAAN LANGIT-LANGIT (SNI 2839:2008)
K001 Memasang 1 m2 langit-langit asbes semen, tebal 4 mm, 5 mm, dan 6 mm
Asbes semen 1.100 m2 18,600.00 20,460.00
Bahan
Paku tripleks 0.010 kg 19,620.00 196.20
Pekerja 0.030 HO 90,000.00 2,700.00
Tukang kayu 0.070 HO 120,000.00 8,400.00
Tenaga kerja
Kepala tukang 0.007 HO 130,000.00 910.00
Mandor 0.004 HO 130,000.00 520.00
Jumlah 33,186.20
Overhead + Profit 3,318.62
Jumlah 36,504.82
Dibulatkan 36,500.00
K002 Memasang 1 m2 langit-langit akustik ukuran (30 x 30) cm
Akustik 12.000 lbr 15,437.50 185,250.00
Bahan
Paku tripleks 0.050 kg 19,620.00 981.00
Pekerja 0.120 HO 90,000.00 10,800.00
Tukang kayu 0.120 HO 120,000.00 14,400.00
Tenaga kerja
Kepala tukang 0.012 HO 130,000.00 1,560.00
Mandor 0.006 HO 130,000.00 780.00
Jumlah 213,771.00
Overhead + Profit 21,377.10
Jumlah 235,148.10
Dibulatkan 235,140.00
K003 Memasang 1 m2 langit-langit akustik ukuran (30 x 60) cm
Akustik 5.800 lbr 30,875.00 179,075.00
Bahan
Paku tripleks 0.050 kg 19,620.00 981.00
Pekerja 0.100 HO 90,000.00 9,000.00
Tukang kayu 0.100 HO 120,000.00 12,000.00
Tenaga kerja
Kepala tukang 0.010 HO 130,000.00 1,300.00
Mandor 0.005 HO 130,000.00 650.00
Jumlah 203,006.00
Overhead + Profit 20,300.60
Jumlah 223,306.60
Dibulatkan 223,300.00
K004 Memasang 1 m2 langit-langit akustik ukuran (60 x 120) cm
Akustik 1.500 lbr 123,500.00 185,250.00
Bahan
Paku tripleks 0.050 kg 19,620.00 981.00
Pekerja 0.100 HO 90,000.00 9,000.00
Tukang kayu 0.100 HO 120,000.00 12,000.00
Tenaga kerja
Kepala tukang 0.010 HO 130,000.00 1,300.00
Mandor 0.005 HO 130,000.00 650.00
Jumlah 209,181.00
Overhead + Profit 20,918.10
Jumlah 230,099.10
Dibulatkan 230,090.00
K005 Memasang 1 m2 langit-langit tripleks ukuran (120 x 240) cm, tebal 3 mm, 4 mm dan 6 mm
Tripleks 0.375 lbr 62,350.00 23,381.25
Bahan
Paku tripleks 0.030 kg 19,620.00 588.60
Pekerja 0.100 HO 90,000.00 9,000.00
Tukang kayu 0.100 HO 120,000.00 12,000.00
Tenaga kerja
Kepala tukang 0.010 HO 130,000.00 1,300.00
Mandor 0.005 HO 130,000.00 650.00
Jumlah 46,919.85
Overhead + Profit 4,691.99
Jumlah 51,611.84
Dibulatkan 51,610.00
K006 Memasang 1 m2 langit-langit lambriziring kayu, tebal 9 mm
Kayu papan 0.015 m3 4,290,000.00 64,350.00
Bahan
Paku tripleks 0.010 kg 19,620.00 196.20
Pekerja 0.080 HO 90,000.00 7,200.00
Tukang kayu 0.080 HO 120,000.00 9,600.00
Tenaga kerja
Kepala tukang 0.080 HO 130,000.00 10,400.00
Mandor 0.040 HO 130,000.00 5,200.00
NO. KEBUTUHAN INDEKS HARGA. SAT BIAYA BAHAN BIAYA UPAH JUMLAH
1 2 3 4 5 6 7=(4x6) 8=(4x6) 9=(7+8)
Jumlah 96,946.20
Overhead + Profit 9,694.62
Jumlah 106,640.82
Dibulatkan 106,640.00
K007 Memasang 1 m2 langit-langit gypsum board ukuran (1200x2400x9) mm
Gypsum board 0.364 lbr 64,000.00 23,296.00
Bahan
Paku skrup 0.110 kg 13,650.00 1,501.50
Pekerja 0.100 HO 90,000.00 9,000.00
Tukang kayu 0.050 HO 120,000.00 6,000.00
Tenaga kerja
Kepala tukang 0.005 HO 130,000.00 650.00
Mandor 0.005 HO 130,000.00 650.00
Jumlah 41,097.50
Overhead + Profit 4,109.75
Jumlah 45,207.25
Dibulatkan 45,200.00
23 Memasang 1 m’ list plafond gypsum profil
List gypsum profil 1.050 m' 4,500.00 4,725.00
Bahan
Tepung gypsum 0.150 kg 2,180.00 327.00
Pekerja 0.060 HO 90,000.00 5,400.00
Tukang kayu 0.060 HO 120,000.00 7,200.00
Tenaga kerja
Kepala tukang 0.006 HO 130,000.00 780.00
Mandor 0.003 HO 130,000.00 390.00
Jumlah 18,822.00
Overhead + Profit 1,882.20
Jumlah 20,704.20
Dibulatkan 20,700.00
K009 Memasang 1 m2 langit-langit GRC board ukuran (1200x2400x4) mm
Gypsum board 0.364 lbr 54,000.00 19,656.00
Bahan
Paku skrup 0.110 kg 13,650.00 1,501.50
Pekerja 0.100 HO 90,000.00 9,000.00
Tukang kayu 0.050 HO 120,000.00 6,000.00
Tenaga kerja
Kepala tukang 0.005 HO 130,000.00 650.00
Mandor 0.005 HO 130,000.00 650.00
Jumlah 37,457.50
Overhead + Profit 3,745.75
Jumlah 41,203.25
Dibulatkan 41,200.00
K010 Memasang 1 m2 langit-langit GRC board ukuran (1200x2400x6) mm
Gypsum board 0.364 lbr 90,000.00 32,760.00
Bahan
Paku skrup 0.110 kg 13,650.00 1,501.50
Pekerja 0.100 HO 90,000.00 9,000.00
Tukang kayu 0.050 HO 120,000.00 6,000.00
Tenaga kerja
Kepala tukang 0.005 HO 130,000.00 650.00
Mandor 0.005 HO 130,000.00 650.00
Jumlah 50,561.50
Overhead + Profit 5,056.15
Jumlah 55,617.65
Dibulatkan 55,610.00
K011 Memasang 1 m2 langit-langit GRC board ukuran (1200x2400x9) mm
Gypsum board 0.364 lbr 125,000.00 45,500.00
Bahan
Paku skrup 0.110 kg 13,650.00 1,501.50
Pekerja 0.100 HO 90,000.00 9,000.00
Tukang kayu 0.050 HO 120,000.00 6,000.00
Tenaga kerja
Kepala tukang 0.005 HO 130,000.00 650.00
Mandor 0.005 HO 130,000.00 650.00
Jumlah 63,301.50
Overhead + Profit 6,330.15
Jumlah 69,631.65
Dibulatkan 69,630.00
K012 Memasang 1 m2 langit-langit akustik ukuran (60 x 120) cm + rangka alluminium
Profil Alluminium "T" 3.600 m' 85,000.00 306,000.00
Kawat diameter 4 mm 0.150 kg 19,800.00 2,970.00
Bahan
Ramset 1.050 bh 9,800.00 10,290.00
Akustik 60 cm x 120 cm 1.500 lbr 123,500.00 185,250.00
Pekerja 0.500 HO 90,000.00 45,000.00
Tukang besi 0.500 HO 120,000.00 60,000.00
Tenaga kerja
Kepala tukang 0.050 HO 130,000.00 6,500.00
Mandor 0.025 HO 130,000.00 3,250.00
Jumlah 619,260.00
Overhead + Profit 61,926.00
Jumlah 681,186.00
Dibulatkan 681,180.00
K013 Memasang 1 m’ list langit-langit kayu profil 5 cm
List kayu profil 1.050 m' 29,930.00 31,426.50
Bahan
Paku 0.010 kg 17,300.00 173.00
Pekerja 0.050 HO 90,000.00 4,500.00
Tukang kayu 0.050 HO 120,000.00 6,000.00
Tenaga kerja
Kepala tukang 0.005 HO 130,000.00 650.00
Mandor 0.003 HO 130,000.00 390.00
Jumlah 43,139.50
Overhead + Profit 4,313.95
Jumlah 47,453.45
Dibulatkan 47,450.00
K013 Memasang 1 m’ list langit-langit kayu 1/4
List kayu 1/4 1.050 m' 3,000.00 3,150.00
Bahan
Paku 0.010 kg 17,300.00 173.00
Pekerja 0.050 HO 90,000.00 4,500.00
Tukang kayu 0.050 HO 120,000.00 6,000.00
Tenaga kerja
Kepala tukang 0.005 HO 130,000.00 650.00
Mandor 0.003 HO 130,000.00 390.00
Jumlah 14,863.00
Overhead + Profit 1,486.30
Jumlah 16,349.30
NO. KEBUTUHAN INDEKS HARGA. SAT BIAYA BAHAN BIAYA UPAH JUMLAH
1 2 3 4 5 6 7=(4x6) 8=(4x6) 9=(7+8)
Dibulatkan 16,340.00
K014 Memasang 1 m2 rangka langit-langit uk. 1 m x 1 m, kayu kelas II
Kayu gergajian kelas II, balok 0.0120 m³ 5,398,000.00 64,776.00
Bahan
Paku berbagai ukuran (4 - 7 cm) 0.1000 kg 17,300.00 1,730.00
Pekerja 0.1500 HO 90,000.00 13,500.00
Tukang kayu 0.2500 HO 120,000.00 30,000.00
Tenaga kerja
Kepala tukang 0.0250 HO 130,000.00 3,250.00
Mandor 0.0750 HO 130,000.00 9,750.00
Jumlah 123,006.00
Overhead + Profit 12,300.60
Jumlah 135,306.60
Dibulatkan 135,300.00
K014 Memasang 1 m2 rangka langit-langit kayu lama pasang kembali
Bahan
Paku berbagai ukuran (4 - 7 cm) 0.1000 kg 17,300.00 1,730.00
Pekerja 0.1500 HO 90,000.00 13,500.00
Tukang kayu 0.2500 HO 120,000.00 30,000.00
Tenaga kerja
Kepala tukang 0.0250 HO 130,000.00 3,250.00
Mandor 0.0750 HO 130,000.00 9,750.00
Jumlah 58,230.00
Overhead + Profit 5,823.00
Jumlah 64,053.00
Dibulatkan 64,050.00
K015 Memasang 1 m2 rangka langit-langit uk. 30 cm x 60 cm, kayu kelas II
Kayu gergajian kelas II, balok 0.0230 m³ 5,398,000.00 124,154.00
Bahan
Paku berbagai ukuran (4 - 7 cm) 0.1500 kg 17,300.00 2,595.00
Pekerja 0.2000 HO 90,000.00 18,000.00
Tukang kayu 0.3000 HO 120,000.00 36,000.00
Tenaga kerja
Kepala tukang 0.0300 HO 130,000.00 3,900.00
Mandor 0.0100 HO 130,000.00 1,300.00
Jumlah 185,949.00
Overhead + Profit 18,594.90
Jumlah 204,543.90
Dibulatkan 204,540.00
K016 Memasang 1 m2 rangka langit-langit uk. 30 cm x 30 cm, kayu kelas II
Kayu gergajian kelas II, balok 0.0270 m' 5,398,000.00 145,746.00
Bahan
Paku berbagai ukuran (4 - 7 cm) 0.2000 kg 17,300.00 3,460.00
Pekerja 0.2500 HO 90,000.00 22,500.00
Tukang kayu 0.3500 HO 120,000.00 42,000.00
Tenaga kerja
Kepala tukang 0.0350 HO 130,000.00 4,550.00
Mandor 0.0125 HO 130,000.00 1,625.00
Jumlah 219,881.00
Overhead + Profit 21,988.10
Jumlah 241,869.10
Dibulatkan 241,860.00
K017 Memasang 1 m2 rangka langit-langit uk. 60 cm x 60 cm, besi hollow
Besi hollow 40x40 mm 1.6500 m' 26,000.00 42,900.00
Bahan Besi hollow 20x20 mm 2.3000 m' 32,000.00 73,600.00
Paku skrup 30.0000 bh 190.00 5,700.00
Pekerja 0.1500 HO 90,000.00 13,500.00
Tukang kayu 0.2500 HO 120,000.00 30,000.00
Tenaga kerja
Kepala tukang 0.0250 HO 130,000.00 3,250.00
Mandor 0.0075 HO 130,000.00 975.00
Jumlah 169,925.00
Overhead + Profit 16,992.50
Jumlah 186,917.50
Dibulatkan 186,910.00
1 Memasang 1 m2 langit-langit GRC 4 mm + rangka besi hollow
Besi hollow 40x40 mm 0.4150 btg 32,000.00 13,280.00 13,280.00
Besi hollow 20x20 mm 0.1500 btg 26,000.00 3,900.00 3,900.00
Bahan GRC ( 120 x 240 x 4 ) mm 0.3640 lbr 54,000.00 19,656.00 19,656.00
Paku sekrup 25.0000 bh 190.00 4,750.00 4,750.00
Ramset / dina bolt 4.0000 bh 8,000.00 32,000.00 32,000.00
Cotton plaster 0.0720 bh 16,500.00 1,188.00 1,188.00
Compoun 0.1250 zak 83,000.00 10,375.00 10,375.00
Pekerja 0.1000 HO 90,000.00 9,000.00 9,000.00
Tukang kayu 0.0500 HO 120,000.00 6,000.00 6,000.00
Tenaga kerja
Kepala tukang 0.0050 HO 130,000.00 650.00 650.00
Mandor 0.0050 HO 130,000.00 650.00 650.00
Jumlah 85,149.00 16,300.00 101,449.00
Overhead + Profit 10,144.90
Jumlah 111,593.90
Dibulatkan 111,590.00
2 Memasang 1 m2 langit-langit Gypsum 9 mm + rangka besi hollow
Besi hollow 40x40 mm 0.4150 btg 32,000.00 13,280.00 13,280.00
Besi hollow 20x20 mm 0.1500 btg 26,000.00 3,900.00 3,900.00
Bahan Gypsum ( 120 x 240 x 9 ) mm 0.3640 lbr 64,000.00 23,296.00 23,296.00
Paku sekrup 25.0000 bh 190.00 4,750.00 4,750.00
Ramset / dina bolt 4.0000 bh 8,000.00 32,000.00 32,000.00
Cotton plaster 0.0720 bh 16,500.00 1,188.00 1,188.00
Compoun 0.1250 zak 83,000.00 10,375.00 10,375.00
Pekerja 0.1000 HO 90,000.00 9,000.00 9,000.00
Tukang kayu 0.0500 HO 120,000.00 6,000.00 6,000.00
Tenaga kerja
Kepala tukang 0.0050 HO 130,000.00 650.00 650.00
Mandor 0.0050 HO 130,000.00 650.00 650.00
Jumlah 88,789.00 16,300.00 105,089.00
Overhead + Profit 10,508.90
Jumlah 115,597.90
Dibulatkan 115,590.00
L PEKERJAAN PENUTUP ATAP
1 Memasang 1 m2 penutup atap genteng keramik glasur
Bahan Atap Genteng Keramik Glasur 14.500 bh 8,386.21 121,600.00 121,600.00
Pekerja 0.010 org 90,000.00 900.00 900.00
Tenaga kerja
NO. KEBUTUHAN INDEKS HARGA. SAT BIAYA BAHAN BIAYA UPAH JUMLAH
1 2 3 4 5 6 7=(4x6) 8=(4x6) 9=(7+8)
Tukang kayu 0.010 org 120,000.00 1,200.00 1,200.00
Tenaga kerja
Kepala tukang 0.200 org 130,000.00 26,000.00 26,000.00
Mandor 0.010 org 130,000.00 1,300.00 1,300.00
Jumlah 121,600.00 29,400.00 151,000.00
Overhead + Profit 15,100.00
Jumlah 166,100.00
Dibulatkan 166,100.00
Memasang 1 m2 penutup atap spandek 0,45
Bahan Atap spandek 1.050 m2 104,000.00 109,200.00
Paku cacing 0.120 kg 26,000.00 3,120.00
Pekerja 0.140 org 90,000.00 12,600.00
Tukang kayu 0.067 org 120,000.00 8,040.00
Tenaga kerja
Kepala tukang 0.007 org 130,000.00 910.00
Mandor 0.007 org 130,000.00 910.00
Jumlah 134,780.00
Overhead + Profit 13,478.00
Jumlah 148,258.00
Dibulatkan 148,250.00
2 Memasang 1 m' bubungan atap genteng keramik glasur
Bahan Bubungan Genteng Keramik Glasur 4.0000 bh 16,000.00 64,000.00 64,000.00
PC (50 kg) 6.5200 kg 1,340.00 8,736.80 8,736.80
Pasir pasang 0.2100 m3 282,530.00 59,331.30 59,331.30
Pekerja 0.1500 org 90,000.00 13,500.00 13,500.00
Tukang kayu 0.2000 org 120,000.00 24,000.00 24,000.00
Tenaga kerja
Kepala tukang 0.0100 org 130,000.00 1,300.00 1,300.00
Mandor 0.0050 org 130,000.00 650.00 650.00
Jumlah 132,068.10 39,450.00 171,518.10
Overhead + Profit 17,151.81
Jumlah 188,669.91
Dibulatkan 188,660.00
NO. KEBUTUHAN INDEKS HARGA. SAT BIAYA BAHAN BIAYA UPAH JUMLAH
1 2 3 4 5 6 7=(4x6) 8=(4x6) 9=(7+8)
N PEKERJAAN KUNCI/ALAT GANTUNG & KACA
1 Memasang 1 buah kunci tanam 2 Slaag ISO
Bahan Kunci 2 Slaag ISO 1.000 bh 181,500.00 181,500.00 181,500.00
Tenaga kerja Tukang kayu 0.5000 org 120,000.00 60,000.00 60,000.00
Jumlah 181,500.00 60,000.00 241,500.00
Overhead + Profit 24,150.00
Jumlah 265,650.00
Dibulatkan 265,650.00
2 Memasang 1 buah kunci tanam 2 Slaag Silinder SEIS Asli type 210 s/d type 226
Bahan Kunci 2 Slaag Silinder SEIS 1.000 bh 267,500.00 267,500.00 267,500.00
Tenaga kerja Tukang kayu 0.5000 org 120,000.00 60,000.00 60,000.00
Jumlah 267,500.00 60,000.00 327,500.00
Overhead + Profit 32,750.00
Jumlah 360,250.00
Dibulatkan 360,250.00
3 Memasang 1 buah Engsel Pintu Unilon Standard
Bahan Engsel Pintu Unilon Standard 1.000 bh 17,200.00 17,200.00 17,200.00
Tenaga kerja Tukang kayu 0.1500 org 120,000.00 18,000.00 18,000.00
Jumlah 17,200.00 18,000.00 35,200.00
Overhead + Profit 3,520.00
Jumlah 38,720.00
Dibulatkan 38,720.00
4 Memasang 1 m2 Kaca Polos tebal 5 mm
Bahan Kaca Polos tebal 5 mm 1.000 bh 93,600.00 93,600.00 93,600.00
Pekerja 0.1500 org 90,000.00 13,500.00 13,500.00
Tenaga kerja
Tukang kayu 0.2000 org 120,000.00 24,000.00 24,000.00
Jumlah 93,600.00 37,500.00 131,100.00
Overhead + Profit 13,110.00
Jumlah 144,210.00
Dibulatkan 144,210.00
4 Memasang 1 m2 Kaca Rayban tebal 6 mm
Bahan Kaca Rayban tebal 6 mm 1.000 bh 104,000.00 104,000.00 104,000.00
Pekerja 0.1500 org 90,000.00 13,500.00 13,500.00
Tenaga kerja
Tukang kayu 0.2000 org 120,000.00 24,000.00 24,000.00
Jumlah 104,000.00 37,500.00 141,500.00
Overhead + Profit 14,150.00
Jumlah 155,650.00
Dibulatkan 155,650.00
N015 Memasang 1 m2 Kaca Warna Biru tebal 8 mm
Bahan Kaca Stopsol Panasat tebal 8 mm 1.000 bh 725,400.00 725,400.00
Pekerja 0.1500 org 90,000.00 13,500.00
Tenaga kerja
Tukang kayu 0.2000 org 120,000.00 24,000.00
Jumlah 762,900.00
Overhead + Profit 76,290.00
Jumlah 839,190.00
Dibulatkan 839,190.00
N015 Memasang 1 m2 Kaca Tempered tebal 10 mm
Bahan Kaca Tempered tebal 10 mm 1.000 m2 398,000.00 398,000.00
Pekerja 0.1500 org 90,000.00 13,500.00
Tenaga kerja
Tukang kayu 0.2000 org 120,000.00 24,000.00
Jumlah 435,500.00
Dibulatkan 435,500.00
O PEKERJAAN SANITAIR
1 Memasang 1 buah Wastafel
Wastafel Lengkap TOTO 1.0000 umit 1,134,100.00 1,134,100.00 1,134,100.00
Bahan Semen Portland 6.0000 kg 1,340.00 8,040.00 8,040.00
Pasir Pasang 0.0100 m³ 282,530.00 2,825.30 2,825.30
Pekerja 1.2000 org 90,000.00 108,000.00 108,000.00
Tukang batu 1.4500 org 120,000.00 174,000.00 174,000.00
Tenaga kerja
Kepala tukang 0.1500 org 130,000.00 19,500.00 19,500.00
Mandor 0.1000 org 130,000.00 13,000.00 13,000.00
Jumlah 1,144,965.30 314,500.00 1,459,465.30
Overhead + Profit 145,946.53
Jumlah 1,605,411.83
Dibulatkan 1,605,410.00
2 Memasang 1 buah Bank mandi bata merah volume 0,3 m3
Bata Merah 200.0000 bh 494.00 98,800.00 98,800.00
Bahan PC (50 kg) 144.0000 kg 1,340.00 192,960.00 192,960.00
Pasir pasang 0.3000 m³ 282,530.00 84,759.00 84,759.00
Pekerja 6.0000 org 90,000.00 540,000.00 540,000.00
Tukang batu 3.0000 org 120,000.00 360,000.00 360,000.00
Tenaga kerja
Kepala tukang 0.3000 org 130,000.00 39,000.00 39,000.00
Mandor 0.3000 org 130,000.00 39,000.00 39,000.00
Jumlah 376,519.00 978,000.00 1,354,519.00
Overhead + Profit 135,451.90
Jumlah 1,489,970.90
Dibulatkan 1,489,970.00
3 Memasang 1 buah Closet Jongkok Standard Putih Poslin TOTO
Bahan Closet Jongkok TOTO 1.0000 unit 217,800.00 217,800.00 217,800.00
Pekerja 1.0000 org 90,000.00 90,000.00 90,000.00
Tukang batu 1.5000 org 120,000.00 180,000.00 180,000.00
Tenaga kerja
Kepala tukang 0.1500 org 130,000.00 19,500.00 19,500.00
Mandor 0.1600 org 130,000.00 20,800.00 20,800.00
Jumlah 217,800.00 310,300.00 528,100.00
Overhead + Profit 52,810.00
Jumlah 580,910.00
Dibulatkan 580,910.00
4 Memasang 1 buah Closet Duduk Standard Putih Poslin TOTO
Bahan Closet duduk TOTO 1.0000 unit 2,040,000.00 2,040,000.00 2,040,000.00
Perlengkapan 0.0600 lot 2,040,000.00 122,400.00 122,400.00
Pekerja 1.0000 org 90,000.00 90,000.00 90,000.00
Tukang batu 1.5000 org 120,000.00 180,000.00 180,000.00
Tenaga kerja
Kepala tukang 0.1500 org 130,000.00 19,500.00 19,500.00
NO. KEBUTUHAN INDEKS HARGA. SAT BIAYA BAHAN BIAYA UPAH JUMLAH
Tenaga kerja
1 2 3 4 5 6 7=(4x6) 8=(4x6) 9=(7+8)
Mandor 0.1600 org 130,000.00 20,800.00 20,800.00
Jumlah 2,162,400.00 310,300.00 2,472,700.00
Overhead + Profit 247,270.00
Jumlah 2,719,970.00
Dibulatkan 2,719,970.00
NO. KEBUTUHAN INDEKS HARGA. SAT BIAYA BAHAN BIAYA UPAH JUMLAH
1 2 3 4 5 6 7=(4x6) 8=(4x6) 9=(7+8)
5 Memasang 1 m' pipa hitam ø3"
Pipa hitam ø 3" 1.2000 m' 65,583.33 78,700.00 78,700.00
Bahan
Perlengkapan (dari harga pipa) 35.0000 % 65,583.33 22,954.17 22,954.17
Pekerja 0.0540 Oh 90,000.00 4,860.00 4,860.00
Tukang batu 0.0900 Oh 120,000.00 10,800.00 10,800.00
Tenaga kerja
Kepala tukang 0.0090 Oh 130,000.00 1,170.00 1,170.00
Mandor 0.0270 Oh 130,000.00 3,510.00 3,510.00
Jumlah 101,654.17 20,340.00 121,994.17
Overhead + Profit 12,199.42
Jumlah 134,193.58
Dibulatkan 134,190.00
6 Memasang 1 m' pipa hitam ø 4"
Pipa hitam ø 4" 1.2000 m' 86,650.00 103,980.00 103,980.00
Bahan
Perlengkapan (dari harga pipa) 35.0000 % 86,650.00 30,327.50 30,327.50
Pekerja 0.0540 Oh 90,000.00 4,860.00 4,860.00
Tukang batu 0.0900 Oh 120,000.00 10,800.00 10,800.00
Tenaga kerja
Kepala tukang 0.0090 Oh 130,000.00 1,170.00 1,170.00
Mandor 0.0270 Oh 130,000.00 3,510.00 3,510.00
Jumlah 134,307.50 20,340.00 154,647.50
Overhead + Profit 15,464.75
Jumlah 170,112.25
Dibulatkan 170,110.00

O 012 Memasang 1 m' pipa PVC tipe AW ø 1/2"


PVC tipe AW ø 1/2" 1.2000 m' 4,600.00 5,520.00
Bahan
Perlengkapan (dari harga pipa) 35.0000 % 4,600.00 1,610.00
Pekerja 0.0540 Oh 90,000.00 4,860.00
Tukang batu 0.0900 Oh 120,000.00 10,800.00
Tenaga kerja
Kepala tukang 0.0090 Oh 130,000.00 1,170.00
Mandor 0.0270 Oh 130,000.00 3,510.00
Jumlah 27,470.00
Overhead + Profit 2,747.00
Jumlah 30,217.00
Dibulatkan 30,210.00
O 013 Memasang 1 m' PVC tipe AW ø 3/4"
PVC tipe AWs ø 3/4" 1.2000 m' 5,600.00 6,720.00
Bahan
Perlengkapan (dari harga pipa) 35.0000 % 5,600.00 1,960.00
Pekerja 0.0540 Oh 90,000.00 4,860.00
Tukang batu 0.0900 Oh 120,000.00 10,800.00
Tenaga kerja
Kepala tukang 0.0090 Oh 130,000.00 1,170.00
Mandor 0.0270 Oh 130,000.00 3,510.00
Jumlah 29,020.00
Overhead + Profit 2,902.00
Jumlah 31,922.00
Dibulatkan 31,920.00
O 014 Memasang 1 m' PVC tipe AW ø 1"
PVC tipe AW ø 1" 1.2000 m' 7,125.00 8,550.00
Bahan
Perlengkapan (dari harga pipa) 35.0000 % 7,125.00 2,493.75
Pekerja 0.0540 Oh 90,000.00 4,860.00
Tukang batu 0.0900 Oh 120,000.00 10,800.00
Tenaga kerja
Kepala tukang 0.0090 Oh 130,000.00 1,170.00
Mandor 0.0270 Oh 130,000.00 3,510.00
Jumlah 31,383.75
Overhead + Profit 3,138.38
Jumlah 34,522.13
Dibulatkan 34,520.00
7 Memasang 1 m' PVC tipe AW ø2"
PVC tipe AW ø 2" 1.2000 m' 19,175.00 23,010.00 23,010.00
Bahan
Perlengkapan (dari harga pipa) 35.0000 % 19,175.00 6,711.25 6,711.25
Pekerja 0.0540 Oh 90,000.00 4,860.00 4,860.00
Tukang batu 0.0900 Oh 120,000.00 10,800.00 10,800.00
Tenaga kerja
Kepala tukang 0.0090 Oh 130,000.00 1,170.00 1,170.00
Mandor 0.0270 Oh 130,000.00 3,510.00 3,510.00
Jumlah 29,721.25 20,340.00 50,061.25
Overhead + Profit 5,006.13
Jumlah 55,067.38
Dibulatkan 55,060.00
8 Memasang 1 m' PVC tipe AW ø3"
PVC tipe AW ø 3" 1.2000 m' 37,825.00 45,390.00 45,390.00
Bahan
Perlengkapan (dari harga pipa) 35.0000 % 37,825.00 13,238.75 13,238.75
Pekerja 0.0540 Oh 90,000.00 4,860.00 4,860.00
Tukang batu 0.0900 Oh 120,000.00 10,800.00 10,800.00
Tenaga kerja
Kepala tukang 0.0090 Oh 130,000.00 1,170.00 1,170.00
Mandor 0.0270 Oh 130,000.00 3,510.00 3,510.00
Jumlah 58,628.75 20,340.00 78,968.75
Overhead + Profit 7,896.88
Jumlah 86,865.63
Dibulatkan 86,860.00
9 Memasang 1 m' PVC tipe AW ø 4"
PVC tipe AW ø 4" 1.2000 m' 52,875.00 63,450.00 63,450.00
Bahan
Perlengkapan (dari harga pipa) 35.0000 % 52,875.00 18,506.25 18,506.25
Pekerja 0.0540 Oh 90,000.00 4,860.00 4,860.00
Tukang batu 0.0900 Oh 120,000.00 10,800.00 10,800.00
Tenaga kerja
Kepala tukang 0.0090 Oh 130,000.00 1,170.00 1,170.00
Mandor 0.0270 Oh 130,000.00 3,510.00 3,510.00
Jumlah 81,956.25 20,340.00 102,296.25
Overhead + Profit 10,229.63
Jumlah 112,525.88
Dibulatkan 112,520.00
10 Memasang 1 bh kran air ø 3/4" atau 1/2"
Kran air ø 3/4" atau 1/2" 1.0000 bh 125,000.00 125,000.00 125,000.00
Bahan
Sealtape 0.0250 bh 750.00 18.75 0.19
NO. KEBUTUHAN INDEKS HARGA. SAT BIAYA BAHAN BIAYA UPAH JUMLAH
1 2 3 4 5 6 7=(4x6) 8=(4x6) 9=(7+8)
Pekerja 0.0100 Oh 90,000.00 900.00 900.00
Tukang batu 0.1000 Oh 120,000.00 12,000.00 12,000.00
Tenaga kerja
Kepala tukang 0.0100 Oh 130,000.00 1,300.00 1,300.00
Mandor 0.0050 Oh 130,000.00 650.00 650.00
Jumlah 125,018.75 14,850.00 139,850.19
Overhead + Profit 13,985.02
Jumlah 153,835.21
Dibulatkan 153,830.00
11 Memasang 1 bh floor drain
Bahan Floor drain 1.0000 bh 58,100.00 58,100.00 58,100.00
Pekerja 0.0100 Oh 90,000.00 900.00 900.00
Tukang batu 0.1000 Oh 120,000.00 12,000.00 12,000.00
Tenaga kerja
Kepala tukang 0.0100 Oh 130,000.00 1,300.00 1,300.00
Mandor 0.0050 Oh 130,000.00 650.00 650.00
Jumlah 58,100.00 14,850.00 72,950.00
Overhead + Profit 7,295.00
Jumlah 80,245.00
Dibulatkan 80,240.00
Q PEKERJAAN JALAN LINGKUNGAN DAN DRAINASE
Q 002 1 M2 PAS. ONDERLAG BATU BELAH T = 20 CM
Pasir Pasang 0.1500 m³ 282,530.00 42,379.50
Bahan
Batu Belah + Batu Kancing/Tepi 0.2500 m³ 145,000.00 36,250.00
Peralatan 0.3200 lot 38,500.00 12,320.00
Peralatan
Peralatan (Sewa Wales) = 1/75000 (W4) 0.0133 lot 93,500.00 1,246.67
Pekerja Trampil (Gali + Urug + Ampar) 0.2000 OH 90,000.00 18,000.00
Tenaga Kerja
Mandor 0.0200 OH 130,000.00 2,600.00
Jumlah 70,416.67
Overhead + Profit 7,041.67
Jumlah 77,458.33
Dibulatkan 77,450.00
Q 003 1 M2 AMPARAN BATU PECAH MESIN 5/7 t=10 cm
Bahan Batu Pecah Mesin 5/7 0.1200 m³ 257,900.00 30,948.00
Peralatan 0.1600 lot 399,300.00 63,888.00
Peralatan
Peralatan (Sewa Wales) = 1/75000 (W4) 0.0267 lot 93,500.00 2,493.27
Pekerja Trampil (Gali + Urug + Ampar) 0.1100 OH 90,000.00 9,900.00
Tenaga Kerja
Mandor 0.0110 OH 130,000.00 1,430.00
Jumlah 97,329.27
Overhead + Profit 9,732.93
Jumlah 107,062.20
Dibulatkan 107,060.00
Q 008 1 LITER LAPIS PEREKAT (TACK COAT)
Aspal Bitumen 1.1840 kg 10,800.00 12,787.20
Bahan Minyak Tanah 0.3387 kg 3,300.00 1,117.60
Alat Bantu 0.0003 m³ 38,500.00 12.83
Pekerja 0.0033 org 90,000.00 297.00
Tenaga Kerja
Mandor 0.0002 org 130,000.00 26.00
Jumlah 14,240.63
Overhead + Profit 1,424.06
Jumlah 15,664.70
Dibulatkan 15,660.00
Q 013 1 M2 HOTMIX PAKAI ALAT BESAR T=5 cm KLS JALAN 8 TON LEBIH
Hotmix HRS 0.1110 ton 1,200,000.00 133,200.00
Bahan
Peralatan 0.0238 hr 100,000.00 2,380.00
Pekerja 0.0050 90,000.00 450.00
Tenaga Kerja Pekerja Trampil 0.0009 org 130,000.00 117.00
Mandor 0.0004 org 130,000.00 52.00
Jumlah 136,199.00
Overhead + Profit 13,619.90
Jumlah 149,818.90
Dibulatkan 149,810.00
Q 014 1 M2 LAPISAN PENETRASI (LAPEN)
Batu Pecah 3 - 5 cm 0.0480 m² 200,000.00 9,600.00
Batu Pecah 1 - 2 cm 0.0220 m² 276,960.00 6,093.12
Bahan
Abu Batu / Screnn 0.5 - 1 cm 0.0080 m² 185,000.00 1,480.00
Aspal Curah/ Aspal Bitumen 5.0000 kg 10,800.00 54,000.00
Peralatan 0.0500 lot 38,500.00 1,925.00
Pekerja 0.0667 org 90,000.00 6,003.00
Tenaga Kerja
Tukang Batu Terampil 0.0100 org 130,000.00 1,300.00
Mandor 0.0033 org 130,000.00 429.00
Jumlah 80,830.12
Overhead + Profit 8,083.01
Jumlah 88,913.13
Dibulatkan 88,910.00
NO. KEBUTUHAN INDEKS HARGA. SAT BIAYA BAHAN BIAYA UPAH JUMLAH
1 2 3 4 5 6 7=(4x6) 8=(4x6) 9=(7+8)
Q 015 1 M1 SALURAN BUIS BETON 1/2 DIA 20 CM + PASANGAN BATA MERAH
Galian Tanah 0.1500 m³ 77,820.00 11,673.00
Grefel Beton 20 Cm 1.0000 bh 41,200.00 41,200.00
Pas . Bata 1 : 4 0.4000 m2 237,060.00 94,824.00
Plesteran 1 : 3 0.7000 m2 72,390.00 50,673.00
Upah kerja 0.1500 ls 105,139.68 15,770.95
Jumlah 214,140.95
Overhead + Profit 21,414.10
Jumlah 235,555.05
Dibulatkan 235,550.00
Q 017 1 M1 PASANGAN DRANASE BUIS BETON BULAT DIA 20 UNTUK SODETAN
Galian Tanah 0.1500 m³ 77,820.00 11,673.00
Urugan Tanah Kembali Dipadatkan 0.0750 m³ 56,650.00 4,248.75
Buis Beton Dia 20 Cm 1.0000 bh 41,200.00 41,200.00
Cor Beton Tumbuk 0.0600 m³ 956,400.00 57,384.00
Jumlah 114,505.75
Overhead + Profit 11,450.58
Jumlah 125,956.33
Dibulatkan 125,950.00
Q 022 1 M2 PASANGAN PAVING BLOCK NATURAL 8 CM K-225
Paving Block nATURAL 8 cm K-225 1.0100 m² 120,000.00 121,200.00
Bahan
Pasir Beton 0.1000 m³ 277,380.00 27,738.00
Pekerja Setengah Terampil 0.2500 org 30,000.00 7,500.00
Tukang Batu Setengah Terampil 0.5000 org 55,000.00 27,500.00
Tenaga Kerja
Kepala Tukang Batu 0.0250 org 130,000.00 3,250.00
Mandor 0.0030 org 130,000.00 390.00
Stamper 0.2400 jam 15,000.00 3,600.00
Peralatan
Peralatan Bantu 1.0000 ls 1,000.00 1,000.00
Jumlah 192,178.00
Overhead + Profit 19,217.80
Jumlah 211,395.80
Dibulatkan 211,390.00
1 M2 PASANGAN ALLUMUNIUM COMPOSITE

Allumunium Composite 1.0000 m2 350,000.00 350,000.00

Bahan Rangka Hollow Allumunium dan asesorie 1.0000 m2 150,000.00 150,000.00

Sealend back up 1.0000 ls 35,000.00 35,000.00

Tenaga Kerja Upah pasang 1.0000 m2 79,000.00 79,000.00

Jumlah 614,000.00

Overhead + Profit 61,400.00

Jumlah 675,400.00

Dibulatkan 675,000.00
HARGA SATUAN PEKERJAAN
NO URAIAN JUMLAH (Rp)
1 2 3

A PEKERJAAN PERSIAPAN
1 Memasang 1 m1 bouplank 69,410.00
2 Membuat 1 m2 Kantor Direksi 983,350.00
3 Membuat 1 m2 Papan Nama Proyek 643,160.00

B PEKERJAAN TANAH (SNI 2835:2008)


1 Menggali 1 m3 tanah biasa sedalam 1 meter 77,820.00
2 Menggali 1 m3 tanah biasa sedalam 2 meter 95,530.00
3 Menggali 1 m3 tanah biasa sedalam 3 meter 113,530.00
4 Mengerjakan 1 m2 stripping tebing setinggi 1 meter 5,660.00
5 Membuang 1 m3 tanah sejauh 15 meter 34,100.00
6 Mengurug kembali 1 m3 galian 25,940.00
7 Memadatkan 1 m3 tanah (per 20 cm) 56,650.00
8 Mengurug 1 m3 pasir urug 399,700.00
9 Mengurug 1 m3 sirtu padat untuk peninggian lantai bangunan 459,620.00
10 Mengurug 1 m3 tanah urug & Pemadatan (tiap 20 cm) 240,470.00

C PEKERJAAN PONDASI (SNI 2836:2008)


1 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 5 PP 939,710.00
C 009 Memasang 1 m3 batu kosong (anstamping) 595,710.00

D PEKERJAAN BETON (SNI 7394:2008)


1 Membuat 1 m3 lantai kerja 1PC : 3 PS : 5 KR 956,400.00
2 Membuat 1 m3 beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58 1,153,730.00
3 Pembesian 10 kg dengan besi polos atau besi ulir 135,780.00
4 Memasang 1 m2 jaring kawat baja/wire mesh 56,050.00
5 Memasang 1 m2 bekisting untuk pondasi 222,580.00
6 Memasang 1 m2 bekisting untuk sloof 94,550.00
7 Memasang 1 m2 bekisting untuk kolom 419,990.00
8 Memasang 1 m2 bekisting untuk balok 437,040.00
9 Memasang 1 m2 bekisting untuk plat lantai 463,230.00
10 Memasang 1 m2 bekisting untuk dinding 481,910.00
11 Memasang 1 m2 bekisting untuk tangga 387,990.00

E PEKERJAAN DINDING (SNI 6897:2008)


1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal ½ bata, campuran spesi 1 PC : 3 PP 127,670.00
2 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal ½ bata, campuran spesi 1 PC : 4 PP 123,750.00
3 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal ½ bata, campuran spesi 1 PC : 5 PP 121,690.00
4 1 M2 Dinding Pemisah Gypsum t = 9 mm + rangka chanel C75 zinckalum 215,360.00

F PEKERJAAN PENGECATAN (SNI 2407:2008)


1 Mengecat 1 m2 Dinding Vinilex (3X) 32,370.00
2 Mengecat 1 m2 Plafond Vinilex (3X) 32,810.00
3 Mengecat 1 m2 Kayu (3X) Glotex berikut Meni 81,210.00
4 Mengecat 1 m2 Plituran Meubulair 115,550.00
5 Mengecat 1 m2 Permukaan baja zinchromat 21,840.00

G PEKERJAAN PENUTUP LANTAI DAN DINDING (SNI 7395:2008)


1 Memasang 1 m2 lantai keramik ukuran (20 x 20) cm DN Putih setara Roman 233,740.00
2 Memasang 1 m2 lantai keramik ukuran (33 x 33) cm DN bercorak/berwarna setara Roman 213,860.00
3 Memasang 1 m2 lantai keramik ukuran (40 x 40) cm DN bercorak/berwarna setara Roman 229,080.00
4 Memasang 1 m2 lantai keramik ukuran (20 x 20) cm DN bercorak/berwarna setara Roman 239,570.00
5 Memasang 1 m2 Floor Hardener 189,790.00
6 Memasang 1 m2 Waterprofing membran 150,150.00
7 Memasang 1 m2 dinding keramik ukuran (20 x 20) cm, DN bercorak/berwarna setara Roman 269,340.00
8 Memasang 1 m2 dinding batu andesit 413,850.00

H PEKERJAAN PLESTERAN (SNI 2837:2008)


1 Membuat 1 m2 plesteran 1 PC : 3 PP, tebal 20 mm 96,920.00
1 Membuat 1 m2 plesteran 1 PC : 5 PP, tebal 20 mm 93,070.00
2 Membuat 1 m2 Berapen 1 PC : 5 PP, tebal 15 mm 42,750.00
3 Membuat 1 m2 finishing siar pasangan batu kali adukan 1 PC : 2 PP 66,860.00
4 Membuat 1 m2 acian 40,650.00

I PEKERJAAN KAYU (SNI 3434:2008)


1 Membuat dan memasang 1 m2 daun pintu panel, kayu kelas I atau II 750,210.00
NO URAIAN JUMLAH (Rp)
1 2 3
NO URAIAN JUMLAH (Rp)
1 2 3
J PEKERJAAN BESI DAN ALUMINIUM (SNI 7393:2008)
1 Memasang 1 kg rangka kuda-kuda baja IWF 26,040.00
2 Memasang 1 m2 kawat harmonika 123,460.00
3 Memasang 1 m’ talang datar/ jurai seng bjls 28 lebar 90 cm 158,500.00
4 Memasang 1 M2 atap baja ringan Setara Maxitop Bluescope lysaght bentang max. 8m + rangka dan reng 181,500.00

K PEKERJAAN LANGIT-LANGIT (SNI 2839:2008)


1 Memasang 1 m2 langit-langit GRC 4 mm + rangka besi hollow 111,590.00
2 Memasang 1 m2 langit-langit Gypsum 9 mm + rangka besi hollow 115,590.00

L PEKERJAAN PENUTUP ATAP


1 Memasang 1 m2 penutup atap genteng keramik glasur 166,100.00
2 Memasang 1 m' bubungan atap genteng murando glazur 163,910.00
3 Memasang 1 m2 penutup atap spandek 0,45 148,250.00

M PEKERJAAN KUNCI/ALAT GANTUNG & KACA


1 Memasang 1 buah kunci tanam 2 Slaag ISO 265,650.00
2 Memasang 1 buah kunci tanam 2 Slaag Silinder SEIS Asli type 210 s/d type 226 360,250.00
3 Memasang 1 buah Engsel Pintu Unilon Standard 38,720.00
4 Memasang 1 m2 Kaca Polos tebal 5 mm 144,210.00
Memasang 1 m2 Kaca Rayban tebal 6 mm 155,650.00

N PEKERJAAN SANITARI
1 Memasang 1 buah Wastafel 1,605,410.00
2 Memasang 1 buah Bank mandi bata merah volume 0,3 m3 1,489,970.00
3 Memasang 1 buah Closet Jongkok Standard Putih Poslin TOTO 580,910.00
4 Memasang 1 buah Closet Duduk Standard Putih Poslin TOTO 2,719,970.00
5 Memasang 1 buah Urinoir Lengkap TOTO Warna Standard lengkap 2,298,160.00
6 Memasang 1 m' pipa hitam ø3" 134,190.00
7 Memasang 1 m' pipa hitam ø 4" 170,110.00
8 Memasang 1 m' pipa PVC tipe AW ø 1/2" 30,210.00
9 Memasang 1 m' PVC tipe AW ø 3/4" 31,920.00
10 Memasang 1 m' PVC tipe AW ø 1" 34,520.00
11 Memasang 1 m' PVC tipe AW ø2" 55,060.00
12 Memasang 1 m' PVC tipe AW ø3" 86,860.00
13 Memasang 1 m' PVC tipe AW ø 4" 112,520.00
14 Memasang 1 bh kran air ø 3/4" atau 1/2" 153,830.00
15 Memasang 1 bh floor drain 80,240.00

Q PEKERJAAN JALAN LINGKUNGAN DAN DRAINASE


1 1 M2 PAS. ONDERLAG BATU BELAH T = 20 CM 77,458.33
2 1 M2 AMPARAN BATU PECAH MESIN 5/7 t=10 cm 107,062.20
3 1 LITER LAPIS PEREKAT (TACK COAT) 15,664.70
4 1 M2 HOTMIX PAKAI ALAT BESAR T=5 cm KLS JALAN 8 TON LEBIH 149,818.90
5 1 M2 LAPISAN PENETRASI (LAPEN) 88,913.13
6 1 M1 SALURAN BUIS BETON 1/2 DIA 20 CM + PASANGAN BATA MERAH 235,550.00
7 1 M1 PASANGAN DRANASE BUIS BETON BULAT DIA 20 UNTUK SODETAN 125,950.00
8 1 M2 PASANGAN PAVING BLOCK NATURAL 8 CM K-225 211,390.00
9 PEK. KERB / KANSTIN / PITA BETON PER M1 159,550.00
10 1 M2 PASANGAN ALLUMUNIUM COMPOSITE 675,000.00
ANALISA HARGA SATUAN BETON GEDUNG KANTOR
NO. URAIAN SAT. KOEF. HARGA SAT. JUMLAH
1 2 3 4 5 6=4X5
LANTAI 1
1 M3 KOLOM 600/600 SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 310.76 13,578.00 4,219,563.24
Pasang Bekisting untuk kolom m2 6.67 419,990.00 2,799,933.33
Jumlah 8,173,226.57
Dibulatkan 8,173,220.00
1 M3 KOLOM K1 300/700 SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 257.00 13,578.00 3,489,546.00
Pasang Bekisting untuk kolom m2 9.52 419,990.00 3,999,904.76
Jumlah 8,643,180.76
Dibulatkan 8,643,180.00
1 M3 KOLOM K1A 300/500 SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 257.00 13,578.00 3,489,546.00
Pasang Bekisting untuk kolom m2 10.67 419,990.00 4,479,893.33
Jumlah 9,123,169.33
Dibulatkan 9,123,160.00
NO. URAIAN SAT. KOEF. HARGA SAT. JUMLAH
1 2 3 4 5 6=4X5
1 M3 KOLOM (SIRIP) 300/700 SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 110.00 13,578.00 1,493,580.00
Pasang Bekisting untuk kolom m2 9.52 419,990.00 3,999,904.76
Jumlah 6,647,214.76
Dibulatkan 6,647,210.00
1 M3 KOLOM 12/12 SITE MIX K-175
Beton Site Mix K-175 m3 1.00 1,317,180.00 1,317,180.00
Besi Beton kg 260.00 13,578.00 3,530,280.00
Pasang Bekisting untuk sloof ( 2 x pakai ) m2 27.78 94,550.00 1,313,194.44
Jumlah 6,160,654.44
Dibulatkan 6,160,650.00
1 M3 BALOK B1 300/700 SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 257.00 13,578.00 3,489,546.00
Pasang Bekisting untuk balok m2 8.10 437,040.00 3,537,942.86
Jumlah 8,181,218.86
Dibulatkan 8,181,210.00
1 M3 BALOK B2 300/600 SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 257.00 13,578.00 3,489,546.00
Pasang Bekisting untuk balok m2 8.67 437,040.00 3,787,680.00
Jumlah 8,430,956.00
Dibulatkan 8,430,950.00
1 M3 BALOK B3 200/400 SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 188.00 13,578.00 2,552,664.00
Pasang Bekisting untuk balok m2 12.50 437,040.00 5,463,000.00
Jumlah 9,169,394.00
Dibulatkan 9,169,390.00
1 M3 BALOK B4 150/300 SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 193.00 13,578.00 2,620,554.00
Pasang Bekisting untuk balok m2 20.00 437,040.00 8,740,800.00
Jumlah 12,515,084.00
Dibulatkan 12,515,080.00
1 M3 LISTPLANK 100/700 SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 82.00 13,578.00 1,113,396.00
Pasang Bekisting untuk sloof m2 21.43 94,550.00 2,026,071.43
Jumlah 4,293,197.43
Dibulatkan 4,293,190.00
1 M3 BALOK LINTEL 11/15 SITE MIX K-175
Beton Site Mix K-175 m3 1.00 1,317,180.00 1,317,180.00
Besi Beton kg 211.00 13,578.00 2,864,958.00
Pasang Bekisting untuk sloof m2 24.85 94,550.00 2,349,424.24
Jumlah 6,531,562.24
Dibulatkan 6,531,560.00
1 M3 PLAT BETON T=13 CM SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Pasang Bekisting untuk plat m2 7.69 463,230.00 3,563,307.69
Jumlah 4,717,037.69
Dibulatkan 4,717,030.00
1 M3 PLAT BETON T=12 CM SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Jumlah 1,153,730.00
Dibulatkan 1,153,730.00
1 M3 PLAT BETON ATAP T=12 CM SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Pasang Bekisting untuk plat m2 8.33 463,230.00 3,860,250.00
Jumlah 5,013,980.00
Dibulatkan 5,013,980.00
1 M3 PLAT BETON LUIVEL T=10 CM SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 118.00 13,578.00 1,602,204.00
Pasang Bekisting untuk plat m2 10.00 463,230.00 4,632,300.00
Jumlah 7,388,234.00
Dibulatkan 7,388,230.00
1 M3 PLAT BETON T=10 CM SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 86.00 13,578.00 1,167,708.00
Pasang Bekisting untuk plat m2 10.00 463,230.00 4,632,300.00
NO. URAIAN SAT. KOEF. HARGA SAT. JUMLAH
1 2 3 4 5 6=4X5
Jumlah 6,953,738.00
Dibulatkan 6,953,730.00
1 M3 BALOK 20/40 SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 178.00 13,578.00 2,416,884.00
Pasang Bekisting untuk balok m2 12.50 437,040.00 5,463,000.00
Jumlah 9,033,614.00
Dibulatkan 9,033,610.00
1 M3 PLAT BETON T=17 CM SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 231.00 13,578.00 3,136,518.00
Pasang Bekisting untuk tangga m2 5.88 387,990.00 2,282,294.12
Jumlah 6,572,542.12
Dibulatkan 6,572,540.00
1 M3 ANAK TANGGA SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 100.00 13,578.00 1,357,800.00
Pasang Bekisting untuk sloof m2 6.67 94,550.00 630,333.33
Jumlah 3,141,863.33
Dibulatkan 3,141,860.00
1 M3 BETON PONDASI FITE LIFT SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 140.00 13,578.00 1,900,920.00
Pasang Bekisting untuk pondasi m2 2.00 222,580.00 445,160.00
Jumlah 3,499,810.00
Dibulatkan 3,499,810.00
1 M3 BETON DINDING FITE LIFT T=20 CM SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 116.00 13,578.00 1,575,048.00
Pasang Bekisting untuk pondasi m2 1.00 481,910.00 481,910.00
Jumlah 3,210,688.00
Dibulatkan 3,210,680.00
LANTAI 2

1 M3 KOLOM K1 300/700 SITE MIX K-225


Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 202.00 13,578.00 2,742,756.00
Pasang Bekisting untuk kolom m2 8.10 419,990.00 3,399,919.05
Jumlah 7,296,405.05
NO. URAIAN SAT. KOEF. HARGA SAT. JUMLAH
1 2 3 4 5 6=4X5
Dibulatkan 7,296,400.00
1 M3 KOLOM (SIRIP) 300/700 SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 110.00 13,578.00 1,493,580.00
Pasang Bekisting untuk kolom m2 9.52 419,990.00 3,999,904.76
Jumlah 6,647,214.76
Dibulatkan 6,647,210.00
1 M3 KOLOM 12/12 SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 260.00 13,578.00 3,530,280.00
Pasang Bekisting untuk sloof ( 2 x pakai ) m2 27.78 94,550.00 1,313,194.44
Jumlah 5,997,204.44
Dibulatkan 5,997,200.00
1 M3 BALOK B1 300/700 SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 170.00 13,578.00 2,308,260.00
Pasang Bekisting untuk balok m2 9.52 437,040.00 4,162,285.71
Jumlah 7,624,275.71
Dibulatkan 7,624,270.00
1 M3 BALOK B2 250/400 SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 148.00 13,578.00 2,009,544.00
Pasang Bekisting untuk balok m2 10.50 437,040.00 4,588,920.00
Jumlah 7,752,194.00
Dibulatkan 7,752,190.00
1 M3 BALOK 300/500 SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 182.00 13,578.00 2,471,196.00
Pasang Bekisting untuk balok m2 8.67 437,040.00 3,787,680.00
Jumlah 7,412,606.00
Dibulatkan 7,412,600.00
1 M3 BALOK 200/400 SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 158.00 13,578.00 2,145,324.00
Pasang Bekisting untuk balok m2 12.50 437,040.00 5,463,000.00
Jumlah 8,762,054.00
Dibulatkan 8,762,050.00
1 M3 BALOK 150/300 SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 258.00 13,578.00 3,503,124.00
Pasang Bekisting untuk balok m2 20.00 437,040.00 8,740,800.00
Jumlah 13,397,654.00
Dibulatkan 13,397,650.00
1 M3 BALOK B5A 200/300 SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 312.00 13,578.00 4,236,336.00
Pasang Bekisting untuk balok m2 13.33 437,040.00 5,827,200.00
Jumlah 11,217,266.00
Dibulatkan 11,217,260.00
1 M3 BALOK B5A 200/350 SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 341.00 13,578.00 4,630,098.00
Pasang Bekisting untuk balok m2 12.86 437,040.00 5,619,085.71
Jumlah 11,402,913.71
Dibulatkan 11,402,910.00
NO. URAIAN SAT. KOEF. HARGA SAT. JUMLAH
1 2 3 4 5 6=4X5
1 M3 BALOK BK2A 200/400 SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 287.00 13,578.00 3,896,886.00
Pasang Bekisting untuk balok m2 12.50 437,040.00 5,463,000.00
Jumlah 10,513,616.00
Dibulatkan 10,513,610.00
1 M3 PLAT BETON T=13 CM SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Pasang Bekisting untuk plat m2 7.69 463,230.00 3,563,307.69
Jumlah 4,717,037.69
Dibulatkan 4,717,030.00
1 M3 BETON SUNCREEN 100/600 SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 102.00 13,578.00 1,384,956.00
Pasang Bekisting untuk sloof m2 23.33 94,550.00 2,206,166.67
Jumlah 4,744,852.67
Dibulatkan 4,744,850.00
1 M3 LISTPLANK 100/700 SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 82.00 13,578.00 1,113,396.00
Pasang Bekisting untuk sloof m2 21.43 94,550.00 2,026,071.43
Jumlah 4,293,197.43
Dibulatkan 4,293,190.00
1 M3 BALOK LINTEL 11/15 SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 211.00 13,578.00 2,864,958.00
Pasang Bekisting untuk sloof m2 24.85 94,550.00 2,349,424.24
Jumlah 6,368,112.24
Dibulatkan 6,368,110.00
1 M3 PLAT BETON LUIVEL T=10 CM SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 118.00 13,578.00 1,602,204.00
Pasang Bekisting untuk plat m2 10.00 463,230.00 4,632,300.00
Jumlah 7,388,234.00
Dibulatkan 7,388,230.00
1 M3 PLAT BETON T=10 CM SITE MIX K-225
Beton Site Mix K-225 m3 1.00 1,153,730.00 1,153,730.00
Besi Beton kg 118.00 13,578.00 1,602,204.00
Pasang Bekisting untuk plat m2 10.00 463,230.00 4,632,300.00
Jumlah 7,388,234.00
Dibulatkan 7,388,230.00
CONTOH PERHITUNGAN BETON BERTULANG
TAHUN ANGGARAN 2013
NOMOR HASIL HARGA BERIKUT
NO. URAIAN HASIL ANALISA
ANALISA KEUNTUNGAN

1 Hasil Analisa Pekerjaan 1 m3 beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87 D 002 997,390.00
2 Hasil Analisa Pekerjaan 1 m3 beton mutu f’c = 9,8 MPa (K 125), slump (12 ± 2) cm, w/c = 0,78 D 003 1,034,130.00
3 Hasil Analisa Pekerjaan 1 m3 beton mutu f’c = 12,2 MPa (K 150), slump (12 ± 2) cm, w/c = 0,72 D 004 1,062,840.00
4 Hasil Analisa Pekerjaan 1 m3 beton mutu f’c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66 D 006 1,317,180.00
5 Hasil Analisa Pekerjaan 1 m3 beton mutu f’c = 16,9 MPa (K 200), slump (12 ± 2) cm, w/c = 0,61 D 007 1,129,300.00
6 Hasil Analisa Pekerjaan 1 m3 beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58 2 1,153,730.00
7 Hasil Analisa Pekerjaan 1 m3 beton mutu f’c = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56 D 009 1,063,430.00
8 Hasil Analisa Pekerjaan 1 m3 beton mutu f’c = 24,0 MPa (K 275), slump (12 ± 2) cm, w/c = 0,53 D 010 1,197,530.00
9 Hasil Analisa Pekerjaan 1 m3 beton mutu f’c = 26,4 MPa (K 300), slump (12 ± 2) cm, w/c = 0,52 2 1,453,700.00
10 Hasil Analisa Pekerjaan 1 m3 beton mutu f’c = 28,8 MPa (K 325), slump (12 ± 2) cm, w/c = 0,49 D 012 1,297,200.00
11 Hasil Analisa Pekerjaan 1 m3 beton mutu f’c = 28,8 MPa (K 350), slump (12 ± 2) cm, w/c = 0,49 D 013 1,308,460.00
12 Hasil Analisa Pekerjaan 1 m3 beton mutu K-175 (Ready Mix) D 014 1,045,120.00
13 Hasil Analisa Pekerjaan 1 m3 beton mutu K-225 (Ready Mix) D 015 1,083,050.00
14 Hasil Analisa Pekerjaan 1 m3 beton mutu K-250 (Ready Mix) D 016 1,120,990.00
15 Hasil Analisa Pekerjaan 1 m3 beton mutu K-300 (Ready Mix) D 017 1,158,920.00
16 Hasil Analisa Pekerjaan 1 m3 beton mutu K-350 (Ready Mix) D 018 1,196,850.00
17 Hasil Analisa Pekerjaan Pembesian 10 kg dengan Besi Beton (polos/ulir) D 019 135,780.00
18 Hasil Analisa Pekerjaan Bekisting untuk Pondasi D 020 222,580.00
19 Hasil Analisa Pekerjaan Bekisting untuk Sloop D 021 94,550.00
20 Hasil Analisa Pekerjaan Bekisting untuk Kolom D 022 419,990.00
21 Hasil Analisa Pekerjaan Bekisting untuk Balok 3 437,040.00
22 Hasil Analisa Pekerjaan Bekisting untuk Plat lantai D 024 463,230.00
23 Hasil Analisa Pekerjaan Bekisting untuk Dinding 4 481,910.00
24 Hasil Analisa Pekerjaan Bekisting untuk Tangga 5 387,990.00

1. 1 M3 PEKERJAAN PONDASI (Cor Beton mutu K 175 Ready Mix Besi 150 kg + Bekisting)
- Hasil Analisa Pekerjaan 1 m3 beton mutu K-175 (Ready Mix) 1,045,120.00
- Pembesian 15 kg dengan Besi Beton (polos/ulir) ; 15 x Hasil Analisa (D 018) 2,036,700.00
- Bekisting untuk pondasi 5 x Hasil Analisa (D 021) 1,112,900.00

Jumlah 4,194,720.00

2. 1 M3 PEKERJAAN SLOOP (Cor Beton mutu K 225 Ready Mix Besi 300 kg + Bekisting)
- Hasil Analisa Pekerjaan 1 m3 beton mutu K-225 (Ready Mix) 1,083,050.00
- Pembesian 20 kg dengan Besi Beton (polos/ulir) ; 20 x Hasil Analisa (D 018) 2,715,600.00
- Bekisting untuk sloop 5 x Hasil Analisa (D 022) 472,750.00

Jumlah 4,271,400.00

3. 1 M3 PEKERJAAN KOLOM (Cor Beton mutu K 300 Ready Mix Besi 300 kg + Bekisting)
- Hasil Analisa Pekerjaan 1 m3 beton mutu K-300 (Ready Mix) 1,158,920.00
- Pembesian 30 kg dengan Besi Beton (polos/ulir) ; 30 x Hasil Analisa (D 018) 4,073,400.00
- Bekisting untuk kolom 5 x Hasil Analisa (D 023) 2,099,950.00

Jumlah 7,332,270.00

4. 1 M3 PEKERJAAN BALOK (Cor Beton mutu K 300 Ready Mix Besi 200 kg + Bekisting)
- Hasil Analisa Pekerjaan 1 m3 beton mutu K-300 (Ready Mix) 1,158,920.00
- Pembesian 20 kg dengan Besi Beton (polos/ulir) ; 20 x Hasil Analisa (D 018) 2,715,600.00
- Bekisting untuk balok 5 x Hasil Analisa (D 024) 2,185,200.00

Jumlah 6,059,720.00

5. 1 M3 PEKERJAAN PLAT LANTAI (Cor Beton mutu K 300 Ready Mix Besi 150 kg + Bekisting)
- Hasil Analisa Pekerjaan 1 m3 beton mutu K-300 (Ready Mix) 1,158,920.00
- Pembesian 15 kg dengan Besi Beton (polos/ulir) ; 15 x Hasil Analisa (D 018) 2,036,700.00
- Bekisting untuk plat lantai 5 x Hasil Analisa (D 025) 2,316,150.00

Jumlah 5,511,770.00

6. 1 M3 PEKERJAAN DINDING (Cor Beton mutu K 175 Ready Mix Besi 150 kg + Bekisting)
- Hasil Analisa Pekerjaan 1 m3 beton mutu K-175 (Ready Mix) 1,045,120.00
- Pembesian 15 kg dengan Besi Beton (polos/ulir) ; 15 x Hasil Analisa (D 018) 2,036,700.00
- Bekisting untuk dinding 5 x Hasil Analisa (D 026) 2,409,550.00

Jumlah 5,491,370.00

7. 1 M3 PEKERJAAN DINDING (Cor Beton mutu K 225 Ready Mix Besi 200 kg + Bekisting)
- Hasil Analisa Pekerjaan 1 m3 beton mutu K-225 (Ready Mix) 1,083,050.00
- Pembesian 20 kg dengan Besi Beton (polos/ulir) ; 20 x Hasil Analisa (D 018) 2,715,600.00
- Bekisting untuk tangga 5 x Hasil Analisa (D 027) 1,939,950.00

Jumlah 5,738,600.00

KETERANGAN :
Untuk Pekerjaan Plat Lantai Beton, Balok Beton dan Pekerjaan Beton lainnya disesuaikan dengan kondisi penempatan
Apabila terletak diatas dan membutuhkan penyangga maka ditambah Pekerjaan Stoot Werk

Contoh Perhitungan Beton Hal.74


CONTOH PERHITUNGAN BERAT BESI BETON DALAM 1 M3

BESI BETON POLOS BESI BETON SPIRAL

No Diameter Berat Besi No Diameter Berat Besi No. Diameter


mm Kg / m1 mm Kg / m1 mm

1 4.0 0.13 11 12 0.89 1 10.00


2 5.0 0.12 12 13 1.04 2 13.00
3 5.5 0.19 13 14 1.21 3 16.00
4 5.7 0.20 14 16 1.58 4 19.00
5 6.0 0.22 15 19 2.23 5 22.00
6 6.5 0.31 16 22 2.98 6 25.00
7 8.0 0.40 17 23 3.26 7 29.00
8 9.0 0.53 18 25 3.85 8 32.00
9 10.0 0.62 19 28 4.83 9 36.00
10 11.0 0.75 20 31 5.93
21 32 6.31

MENGHITUNG BERAT BESI BETON DALAM 1 M3

1. Kolom Praktis 12 X 12 cm' pakai tulangan 4 batang dia. 12 beugel dia. 8 jarak 20 cm
Panjang 1 m3 ukuran 12 x 12 cm = ( 1 : 0.12 : 0.12 ) = 69.44
Besi 4 batang dia. 12 = 4 x 69,44 x 0,89 kg = 247.22
Besi beugel dia. 8 jarak 20 mm = ( 69,44 : 0,20 ) x ( 4 x 0,12 ) x 0, 40 kg = 66.67

BERAT BESI BETON UNTUK UKURAN 12 x 12 CM1 DALAM 1 M3 = 313.89

2. Kolom praktis 15 X 15 cm' pakai tulangan 4 batang dia. 12 beugel dia. 8 jarak 20 cm
Panjang 1 m3 ukuran 15 x 15 cm = ( 1 : 0.15 : 0.15 ) = 44.44
Besi 4 batang dia. 12 = 4 x 44,44 x 0,89 kg = 158.22
Besi beugel dia. 8 jarak 20 mm = ( 44,44 : 0,20 ) x ( 4 x 0,15 ) x 0, 40 kg = 71.11

BERAT BESI BETON UNTUK UKURAN 15 x 15 CM1 DALAM 1 M3 = 229.33

3. Sloof praktis 15 X 20 cm' pakai tulangan 4 batang dia. 12 beugel dia. 8 jarak 15 cm
` = ( 1 : 0.15 : 0.20 ) = 33.33
Besi 4 batang dia. 12 = 4 x 33,33 x 0,89 kg = 118.67
Besi beugel dia. 8 jarak 15 mm = ( 33,33 : 0,15 ) x ( 2 x 0,15 ) + ( 2 x 0,2 ) x 0, 40 kg = 62.22

BERAT BESI BETON UNTUK 15 x 20 CM1 DALAM 1 M3 = 180.89

4. Kolom Beton 20 X 30 cm' pakai tulangan 4 batang dia. 12 + 2 batang dia. 10 beugel dia. 8 jarak 15 cm
Panjang 1 m3 ukuran 20 x 30 cm = ( 1 : 0.20 : 0.30 ) = 16.67
Besi 4 batang dia. 12 = 4 x 16,67 x 0,89 kg = 59.33
Besi 2 batang dia. 10 = 2 x 16.67 x 0.62 kg = 73.57
Besi beugel dia. 8 jarak 15 mm = ( 16,67 : 0.15 ) x (( 2 x 0.2 ) + ( 2 X 0,3 )) X 0,40 kg = 44.44

BERAT BESI BETON UNTUK UKURAN 20 x 30 CM DALAM 1 M3 = 177.35

Contoh Perhitungan Besi Hal. 75


DALAM 1 M3

BESI BETON SPIRAL

Berat Besi
Kg / m1

0.62
1.04
1.58
2.23
2.98
3.85
5.19
6.31
7.99

1 M3

m1
kg ( A)
kg ( B )

kg/m3 ( A + B )

m1
kg ( A)
kg ( B )

kg/m3 ( A + B )

m1
kg ( A)
kg ( B )

kg/m3 ( A + B )

m1
kg ( A)
kg ( B)
kg ( C )

kg/m3 ( A + B + C )

Contoh Perhitungan Besi Hal. 75


ANALISA HARGA SATUAN GEDUNG
No Uraian Pekerjaan Volume Sat. Harga Sat. Total Harga
Rp. Rp.
1 PEKERJAAN KUSEN PINTU, JENDELA KACA ( PJ1)
1 Pek. Kusen alumunium warna 3" 30.00 m' 145,000.00 4,350,000.00
2 Pek. Rangka pintu alumunium 11.64 m' 174,960.00 2,036,534.40
3 Pek. Rangka jendela alumunium 37.52 m' 163,480.00 6,133,769.60
4 Pek. Kaca rayban 6 mm 12.29 m2 155,650.00 1,912,938.50
5 Pek. Assesories 5% dari pek. Alumunium dan kaca 1.00 ls 721,662.13 721,662.13
6 Pek. Kunci cylinder set. SEIS 2.00 bh 360,250.00 720,500.00
7 Pek Floor Hank set. Dorma 2.00 bh 3,000,000.00 6,000,000.00
8 Pek. Engsel jendela ( casement ) 20.00 bh 37,000.00 740,000.00
9 Pek. Grendel jendela( rambuncis ) 10.00 bh 25,000.00 250,000.00
10 Pek. Handel pintu 4.00 bh 350,000.00 1,400,000.00
Jumlah PJ1 24,265,404.63
2 PEKERJAAN KUSEN PINTU KACA ( P1)
1 Pek. Kusen alumunium warna 3" 5.98 m' 145,000.00 867,100.00
2 Pek. Rangka pintu alumunium 11.64 m' 174,960.00 2,036,534.40
3 Pek. Kaca polos 6 mm 3.36 m2 155,650.00 522,984.00
4 Pek. Assesories 5% dari pek. Alumunium dan kaca 1.00 ls 171,330.92 171,330.92
5 Pek. Kunci cylinder set. SEIS 1.00 bh 360,250.00 360,250.00
6 Pek. Engsel pintu 6.00 bh 38,720.00 232,320.00
7 Pek. Expagnolet tanam 1.00 set 150,000.00 150,000.00
8 Pek. Handel pintu 4.00 bh 350,000.00 1,400,000.00
Jumlah P1 5,740,519.32
3 PEKERJAAN KUSEN PINTU, JENDELA KACA ( P2)
1 Pek. Kusen alumunium warna 3" 9.34 m' 145,000.00 1,354,300.00
2 Pek. Rangka pintu alumunium 11.64 m' 174,960.00 2,036,534.40
3 Pek. Rangka jendela alumunium 5.28 m' 174,960.00 923,788.80
4 Pek. Kaca polos 6 mm 0.82 m2 155,650.00 127,633.00
5 Pek. Assesories 5% dari pek. Alumunium dan kaca 1.00 ls 222,112.81 222,112.81
6 Pek. Kunci cylinder set. SEIS 1.00 bh 265,650.00 265,650.00
7 Pek. Engsel pintu 6.00 bh 360,250.00 2,161,500.00
8 Pek. Expagnolet tanam 1.00 set 150,000.00 150,000.00
9 Pek. Engsel jendela ( casement ) 4.00 bh 37,000.00 148,000.00
10 Pek. Grendel jendela( rambuncis ) 1.00 bh 25,000.00 25,000.00
11 Pek. Handel pintu 2.00 bh 350,000.00 700,000.00
Jumlah P2 8,114,519.01
4 PEKERJAAN KUSEN PINTU ( P3)
1 Pek. Kusen alumunium warna 3" 5.00 m' 145,000.00 725,000.00
2 Pek. Assesories 5% dari pek. Alumunium dan kaca 1.00 ls 36,250.00 36,250.00
3 Pek. Daun pintu panel kayu kamper oven 1.68 m2 750,210.00 1,260,352.80
3 Pek. Kunci cylinder set. SEIS 1.00 bh 360,250.00 360,250.00
4 Pek. Engsel pintu 3.00 bh 360,250.00 1,080,750.00
Jumlah P3 3,462,602.80
5 PEKERJAAN KUSEN PINTU ( P5)
1 Pek. Kusen Pintu PVC pabrikasi 1.00 unit 1,250,000.00 1,250,000.00
2 Pek. Upah pasang 1.00 ls 250,000.00 250,000.00
Jumlah P4 1,500,000.00
3 PEKERJAAN KUSEN PINTU ( P4)
1 Pek. Kusen alumunium warna 3" 5.98 m' 145,000.00 867,100.00
2 Pek. Assesories 5% dari pek. Alumunium dan kaca 1.00 ls 171,330.92 171,330.92
3 Pek. Daun pintu panel kayu kamper oven 3.36 m2 750,210.00 2,520,705.60
4 Pek. Kunci cylinder set. SEIS 1.00 bh 360,250.00 360,250.00
5 Pek. Engsel pintu 6.00 bh 38,720.00 232,320.00
6 Pek. Expagnolet tanam 1.00 set 150,000.00 150,000.00
7 Pek. Handel pintu 4.00 bh 350,000.00 1,400,000.00
Jumlah P1 5,701,706.52
6 PEKERJAAN KUSEN JENDELA KACA (J1)
1 Pek. Kusen alumunium warna 3" 8.76 m' 145,000.00 1,270,200.00
2 Pek. Rangka jendela alumunium 10.92 m' 174,960.00 1,910,563.20
3 Pek. Kaca polos 6 mm 1.82 m2 155,650.00 283,283.00
4 Pek. Assesories 5% dari pek. Alumunium dan kaca 1.00 ls 173,202.31 173,202.31
5 Pek. Engsel jendela ( casement ) 8.00 bh 37,000.00 296,000.00
6 Pek. Grendel jendela( rambuncis ) 4.00 bh 25,000.00 100,000.00
Jumlah J1 4,033,248.51
7 PEKERJAAN KUSEN JENDELA KACA (J2)
1 Pek. Kusen alumunium warna 4" 5.39 m' 145,000.00 781,550.00
2 Pek. Rangka jendela alumunium 5.82 m' 174,960.00 1,018,267.20
3 Pek. Kaca polos 6 mm 1.05 m2 155,650.00 163,432.50
4 Pek. Assesories 5% dari pek. Alumunium dan kaca 1.00 ls 98,162.49 98,162.49
5 Pek. Engsel jendela ( casement ) 4.00 bh 37,000.00 148,000.00
No Uraian Pekerjaan Volume Sat. Harga Sat. Total Harga
Rp. Rp.
6 Pek. Grendel jendela( rambuncis ) 2.00 bh 25,000.00 50,000.00
Jumlah J2 2,259,412.19
No Uraian Pekerjaan Volume Sat. Harga Sat. Total Harga
Rp. Rp.
8 PEKERJAAN KUSEN JENDELA KACA (J3)
1 Pek. Kusen alumunium warna 3" 9.90 m' 145,000.00 1,435,500.00
2 Pek. Rangka jendela alumunium 12.44 m' 174,960.00 2,176,502.40
3 Pek. Kaca polos 6 mm 2.41 m2 155,650.00 375,116.50
4 Pek. Assesories 5% dari pek. Alumunium dan kaca 1.00 ls 199,355.95 199,355.95
5 Pek. Engsel jendela ( casement ) 8.00 bh 37,000.00 296,000.00
6 Pek. Grendel jendela( rambuncis ) 4.00 bh 25,000.00 100,000.00
Jumlah J3 4,582,474.85
9 PEKERJAAN KUSEN JENDELA KACA (J4)
1 Pek. Kusen alumunium warna 3" 5.80 m' 145,000.00 841,000.00
2 Pek. Kaca polos 6 mm 1.27 m2 155,650.00 197,675.50
3 Pek. Assesories 5% dari pek. Alumunium dan kaca 1.00 ls 51,933.78 51,933.78
Jumlah J4 1,090,609.28
10 PEKERJAAN KUSEN BOUVENLIGHT (BV1)
1 Pek. Kusen alumunium warna 3" 2.54 m' 145,000.00 368,300.00
2 Pek. Kaca polos 6 mm 0.46 m2 155,650.00 71,599.00
3 Pek. Assesories 5% dari pek. Alumunium dan kaca 1.00 ls 21,994.95 21,994.95
Jumlah BV1 461,893.95

16 PEKERJAAN KUDA-KUDA TYPE K1


WF. 250 125 6 9 637.52 kg 26,040.00 16,601,042.50
Plat tb=16 mm 12.52 kg 26,040.00 325,936.91
Plat tb=12 mm 62.95 kg 26,040.00 1,639,296.64
Plat tb=10 mm 42.31 kg 26,040.00 1,101,806.58
Cat zingkromat 23.92 m2 21,840.00 522,412.80
Jumlah K1 20,190,495.43
17 PEKERJAAN KUDA-KUDA TYPE K2
WF. 250 125 6 9 630.13 kg 26,040.00 16,408,455.00
Plat tb=16 mm 12.52 kg 26,040.00 325,936.91
Plat tb=12 mm 62.95 kg 26,040.00 1,639,296.64
Plat tb=10 mm 42.31 kg 26,040.00 1,101,806.58
Cat zingkromat 23.92 m2 21,840.00 522,412.80
Jumlah K2 19,997,907.93
18 PEKERJAAN KUDA-KUDA TYPE K3
WF. 200 100 5,5 8 239.79 kg 26,040.00 6,244,044.80
Plat tb=16 mm 11.27 kg 26,040.00 293,343.22
Plat tb=12 mm 15.03 kg 26,040.00 391,473.83
Plat tb=10 mm 14.10 kg 26,040.00 367,268.86
Cat zingkromat 9.85 m2 21,840.00 215,124.00
Jumlah K2 7,511,254.71
19 PEKERJAAN KUDA-KUDA JURAI TYPE J1
WF. 250 125 6 9 303.82 kg 26,040.00 7,911,494.50
Plat tb=16 mm 6.26 kg 26,040.00 162,968.46
Plat tb=12 mm 15.97 kg 26,040.00 415,940.94
Plat tb=10 mm 21.16 kg 26,040.00 550,903.29
Cat zingkromat 10.45 m2 21,840.00 228,228.00
Jumlah J1 9,269,535.18
20 PEKERJAAN KUDA-KUDA JURAI TYPE J2
WF. 250 125 6 9 373.34 kg 26,040.00 9,721,817.00
Plat tb=16 mm 6.26 kg 26,040.00 162,968.46
Plat tb=12 mm 15.97 kg 26,040.00 415,940.94
Plat tb=10 mm 21.16 kg 26,040.00 550,903.29
Cat zingkromat 13.60 m2 21,840.00 297,024.00
Jumlah J2 11,148,653.68
21 PEKERJAAN KUDA-KUDA JURAI TYPE J3
WF. 200 100 5,5 8 121.60 kg 26,040.00 3,166,464.00
Plat tb=16 mm 6.26 kg 26,040.00 162,968.46
Plat tb=12 mm 15.03 kg 26,040.00 391,473.83
Plat tb=10 mm 10.97 kg 26,040.00 285,653.56
Cat zingkromat 5.26 m2 21,840.00 114,878.40
Jumlah J2 4,121,438.24
REKAPITULASI
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : PEMBANGUNAN GEDUNG RUMAH SAKIT CITRA MEDIKA LT.4 & ROOFTOP
LOKASI : Jalan Kalimjulya No.58 Cilodong Kota Kembang Depok

No Uraian Pekerjaan

I PEKERJAAN KANTOR
A PEKERJAAN LANTAI 4
I PEKERJAAN PERSIAPAN
III PEKERJAAN BETON
IV PEKERJAAN PASANGAN
V PEKERJAAN ATAP DAN PLAFOND
VI PEKERJAAN KUSEN DAN PENGGANTUNG
VII PEKERJAAN SANITAIR
VIII PEKERJAAN PENGECATAN
IX PEKERJAAN ATAP

B PEKERJAAN LANTAI ROOFTOP


I PEKERJAAN BETON
II PEKERJAAN PASANGAN
III PEKERJAAN ATAP DAN PLAFOND
IV PEKERJAAN KUSEN DAN PENGGANTUNG

D PEKERJAAN M/E

Jumlah
PPN 10%
Jumlah Total
Dibulatkan

TERBILANG

Jakarta, 2021
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : PEMBANGUNAN GEDUNG RUMAH SAKIT CITRA MEDIKA LT.4 & ROOFTOP
LOKASI : Jalan Kalimjulya No.58 Cilodong Kota Kembang Depok

Harga Sat.
No Uraian Pekerjaan Volume Sat.
Rp.
A PEKERJAAN LANTAI 4
I PEKERJAAN PERSIAPAN
1 Pek. Bouwplank dan pengukuran 164.80 m' 69,410.00
2 Pek. Direksi keet 9.00 m2 983,350.00
3 Pengadaan air kerja 1.00 ls 10,000,000.00
4 Pengadaan listrik kerja 1.00 ls 10,000,000.00
5 Sewa Lift barang 3.00 bln 18,000,000.00
6 Pek. Mobilisasi dan demobilisasi 1.00 ls 30,000,000.00
7 Pek. Bongkaran bangunan di lantai atap & Beton overstek 1.00 ls 25,000,000.00
8 Pek. Pemindahan Tangki 5 bh ke rooftop baru 1.00 ls 5,000,000.00
9 Pek. Pemindahan Mesin Lift ke Raung Mesin Lift Baru berikut panel control dan Panel l 1.00 ls 75,000,000.00
10 Pek. Penggantian Seling Lift 1.00 ls 50,000,000.00
11 Pek. Modifikasi sangkar Lit 1.00 ls 15,000,000.00

Jumlah I
III PEKERJAAN BETON
1 Pek. Beton kolom 600/600 mm, 200 kg/m3 35.50 m3 8,173,220.00
1 Pek. Beton kolom 300/600 mm, 200 kg/m3 1.22 m3 8,173,220.00
2 Pek. Beton kolom praktis 12/12 cm, 260 kg/m3 6.84 m3 6,160,650.00
3 Pek. Beton balok B1 300/600 mm, 170 kg/m3 47.23 m3 8,430,950.00
4 Pek. Beton balok B2 300/500 mm, 182 kg/m3 30.15 m3 8,430,950.00
5 Pek. Beton balok B3 200/400 mm, 188 kg/m3 3.22 m3 9,169,390.00
6 Pek. Beton balok B4 150/300 mm, 193 kg/m3 3.24 m3 12,515,080.00
7 Pek. Plat beton lantai tbl=13 cm ( ram ) 89.18 m3 4,717,030.00
8 Pek. Plat beton lantai atap tbl=12 cm 71.40 m3 5,013,980.00
9 Pek. Pasangan Wire mash M8, 2 lapis untuk lantai atap 594.50 m2 56,050.00
10 Pek. Beton luivel t=10 cm 7.41 m3 7,388,230.00
11 Pek. Beton listplank 100/700 mm, 82 kg/m3 0.91 m3 4,293,190.00
12 Pek. Beton lintel 11/15 cm, 211 kg/m3 1.44 m3 6,531,560.00
13 Pek.Waterprofing Membran 594.50 m2 99,500.00
14 Pek. Beton tangga
- balok tangga 20/40 cm, 178 kg/m3 0.96 m3 9,033,610.00
- plat tangga dan bordes tbl=17 cm, 231 kg/m3 11.22 m3 6,572,540.00
- beton anak tangga, 101 kg/m3 3.69 m3 3,141,860.00
Jumlah III
Harga Sat.
No Uraian Pekerjaan Volume Sat.
Rp.
IV PEKERJAAN PASANGAN
1 Pek. Pasangan bata merah 1 : 5 1,345.00 m2 121,690.00
2 Pek. Plesteran + acian 1 : 5 2,690.00 m2 93,070.00
3 Pek. Plesteran + acian 1 : 5 beton 503.60 m2 93,070.00
4 Pek. Revair tangga dan topi beton dengan acian 140.10 m2 40,650.00
5 Pek. Plesteran + acian 1 : 5 opening kusen 56.43 m2 93,070.00
6 Pek. Leveling lantai 927.75 m2 46,535.00
7 Pek. Lantai Granit tile 60/60 cm polos set. Garuda 807.50 m2 229,080.00
8 Pek. Lantai keramik 20/20 cm corak km/wc set. Roman 61.80 m2 239,570.00
9 Pek. Plin keramik 10/40 cm 355.20 m' 57,270.00
10 Pek. Dinding keramik 20/25 cm corak set. Roman 192.64 m2 269,340.00
11 Pek. Keramik tangga luar 30/60 cm type kasar 19.00 m2 213,860.00
12 Pek. Keramik tangga dalam 88.80 m2 229,080.00
13 Pek. Nosing tangga luar 36.00 m' 76,360.00
14 Pek. Nosing tangga dalam 132.20 m' 76,360.00
15 Pek. Railling tangga dalam besi hollow 40/40 + 20/40 tb=0,6 mm + pipa finish cat 42.00 m' 600,000.00
Jumlah IV
V PEKERJAAN ATAP DAN PLAFOND
1 Pek. Plafond GRC 4 mm + rangka hollow galvalum 61.80 m2 111,590.00
2 Pek. Plafond Gypsum 9 mm + rangka hollow galvalum 807.50 m2 115,590.00
3 Pek. List pinggir V. Channel 682.00 m' 22,500.00
Jumlah V
VI PEKERJAAN KUSEN DAN PENGGANTUNG
1 Pek. Kusen Pintu Type P1 3.00 unit 5,740,519.32
2 Pek. Kusen Pintu Type P2 15.00 unit 8,114,519.01
3 Pek. Kusen Pintu, Jendela kaca Type P3 2.00 unit 3,462,602.80
4 Pek. Kusen Pintu PVC Type P5 21.00 unit 1,500,000.00
5 Pek. Kusen Jendela kaca Type J1 20.00 unit 4,033,248.51
6 Pek. Kusen Bouvenlight Type BV1 6.00 unit 461,893.95
Jumlah VI
VII PEKERJAAN SANITAIR
1 Pek. Kloset duduk set. TOTO 21.00 bh 2,719,970.00
2 Pek. Wastafel set. TOTO 18.00 bh 1,605,410.00
3 Pek. Kran 10.00 bh 153,830.00
4 Pek. Hand Shower set. TOTO 21.00 bh 275,000.00
5 Pek. Floor Drain 21.00 bh 80,240.00
Jumlah VII
Harga Sat.
No Uraian Pekerjaan Volume Sat.
Rp.
VIII PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding, kolom 2,661.18 m2 32,370.00
2 Pek. Pengecatan plafond 868.40 m2 32,810.00
3 Pek. Pengecatan daun pintu dengan melamix 6.72 m2 115,550.00
Jumlah VIII
Harga Sat.
No Uraian Pekerjaan Volume Sat.
Rp.
IX PEKERJAAN ATAP
1. Pek. Kuda-kuda Type K1 5.00 unit 20,190,495.43
3. Pek. Angkur baut dia. 16 mm, pj. 50 cm 80.00 bh 65,000.00
4. Pek. Gording baja C 150 65 20 3,2 6,656.86 kg 26,040.00
5. Pek. Dudukan gording plat t=6 mm 361.72 kg 26,040.00
6. Pek. Mur baut dia. 16 mm HTB 516.00 bh 6,000.00
7. Pek. Mur baut dia. 10 mm HTB 1,024.00 bh 5,000.00
8. Pek. Ikatan angin dia. 16 mm 486.64 kg 26,040.00
9. Pek. Trekstang dia. 12 mm 382.90 kg 26,040.00
10. Pek. Water moor dia. 16 mm 40.00 bh 35,000.00
11. Pek. Rangka atap baja ringan ( kaso + reng ) jarak kaso 80 cm 512.10 m2 110,000.00
12. Pek. Penutup atap Biumen 512.10 m2 236,109.48
13. Pek. Bubungan genteng betumen 28.45 m' 159,704.88
14. Pek. Listplank GRC 142.80 m' 125,000.00
15. Pek. Talang tegak PVC dia. 4" 240.00 m' 112,520.00
16. Pek. Roof drain 24.00 bh 125,000.00

Jumlah IX
Total Harga
Rp.

294,288,918.00
2,097,883,333.39
849,486,136.95
115,580,187.00
260,800,882.61
95,015,090.00
115,411,096.60
550,816,189.35

624,682,346.20
289,243,401.10
13,258,860.00
43,694,299.22

1,757,763,000.00

7,107,923,740.42
710,792,374.04
7,818,716,114.46
7,818,716,000.00
Total Harga
Rp.

11,438,768.00
8,850,150.00
10,000,000.00
10,000,000.00
54,000,000.00
30,000,000.00
25,000,000.00
5,000,000.00
75,000,000.00
50,000,000.00
15,000,000.00

294,288,918.00

290,116,617.12
10,004,021.28
42,138,846.00
398,210,630.40
254,193,142.50
29,488,758.24
40,548,859.20
420,641,150.25
357,998,172.00
33,321,725.00
54,746,784.30
3,906,802.90
9,405,446.40
59,152,750.00

8,672,265.60
73,743,898.80
11,593,463.40
2,097,883,333.39
Total Harga
Rp.

163,673,050.00
250,358,300.00
46,870,052.00
5,695,065.00
5,251,940.10
43,172,846.25
184,982,100.00
14,805,426.00
20,342,304.00
51,885,657.60
4,063,340.00
20,342,304.00
2,748,960.00
10,094,792.00
25,200,000.00
849,486,136.95

6,896,262.00
93,338,925.00
15,345,000.00
115,580,187.00

17,221,557.96
121,717,785.15
6,925,205.60
31,500,000.00
80,664,970.20
2,771,363.70
260,800,882.61

57,119,370.00
28,897,380.00
1,538,300.00
5,775,000.00
1,685,040.00
95,015,090.00
Total Harga
Rp.

86,142,396.60
28,492,204.00
776,496.00
115,411,096.60
Total Harga
Rp.

100,952,477.17
5,200,000.00
173,344,634.40
9,419,188.80
3,096,000.00
5,120,000.00
12,672,105.60
9,970,716.00
1,400,000.00
56,331,000.00
120,911,663.68
4,543,603.69
17,850,000.00
27,004,800.00
3,000,000.00

550,816,189.35