This configuration allows you to choose the plant for which you would want to activate SAP Material
Requirement Planning (SAP MRP). Activating MRP for the plant allows one to use the SAP MRP tool
for the plant. SAP Transaction code OMDU and the SAP path is Logistics > Production > MRP >
Planning File Entry > Activate MRP and Set up Planning File
Activating Planning file entry for the plant (through a variant that can be rescheduled) allows you to
collect all the material which has an MRP Type (other than XO) in the planning file, i.e., once the
planning file entry has been activated and MRP Types are assigned to the materials in the MRP 1
View, it collects all these maerials and adds them to the planning file list in SAP
The process of recording a planning file entry for a material, can be run periodically using a batch job
scheduling method. The transaction code to set up the variant and period scheduling is OMDO and the
Path for activating the planning file set up is Logistics > Production > MRP > Planning File Entry >
Activate MRP and Set up Planning File
All the entries in the planning file will have a “change indicator” specifying that a material has
undergone a change (change in receipts elements or issues elements). This indicator will help you to
choose only those materials that have undergone a change, through the use of planning key called
“Net Change Planning” when running MRP.
The planning file record for a material also has a “net change planning in the current horizon” field
which will be set if the change in the materials receipt or issue element is valid in the planning horizon.
This indicator will help you choose only those materials which have undergone a change in the
planning horizon; through the use of a planning key, in an MRP run, called “Net change planning in the
planning horizon”.
SAP MRP is run at plant level or at a group of plant level (called as scope of planning), thus the MRP
configuration is done at Plant level.
The configuration done for SAP MRP at Plant level would also be true for SAP Consumption Based
Planning (SAP CBP) settings.
Transaction code OPPQ takes you in to the SAP MRP configuration called as – Plant Parameters for
Material Requirement Planning. The Path which can be used is Logistics > Production > Material
Requirement Planning > Plant Parameters > Carry out Overall Maintenance of Plant Parameters.
The Transaction code for Consumption Based planning is OMI8 and the Path is Logistics > Materials
Management > Consumption Based Planning > Plant Parameters > Carry out Overall Maintenance of
Plant Parameters.
In the transaction code for Plant level parameters for SAP MRP, you should first input the plant and
press the maintain button.
If you have already maintained the configuration for the parameters, then it states so, if you haven’t
then it simply says – “To Maintain” next to the parameter
Fig MRP - Config 2
Following are the parameters that need to maintain as a part of SAP MRP/CBP Configuration:
a) Number ranges
The number range ID’s are maintained for the following objects:
In this section only the number range ID’s are maintained, while the actually number range configured
for the number range ID is maintained in the transaction code OMI2 for the above objects created in
the planning run (MRP Run) and in transaction code OMI3 for the objects created manually in the front
end.
Every number range interval, created using OMI2 and OM13, has an ID, which can be allocated to the
objects at plant level, i.e., every plant can have a different number range for the objects mentioned
above.
As per standard SAP, the Availability checking rule for the backorder processing is “PP”, though you
can have your own availability check rules created or configured.
Every Availability checks rule (availability checking scope defined) has a set of receipts (Purchase
orders, Production orders) and issues (Sales orders, dependent requirements, reservations, planned
independent requirements etc) which are to be considered or not to be considered during the SAP
availability checks.
To have the checking rule work along with the configuration, you should have the Availability checking
groups maintained in the material master. The Checking groups are configured to be associated with
the checking rules (checking scopes).
The availability checking rule (checking rule scope) has to be maintained, for a given SAP functionality
and it has to be assigned to the availability checking group maintained in the material master. The SAP
functionalities that use availability checks to check the availability of the header materials as well as
components at the plant at the time of sales order creation, the availability checks of the header
material at the time of sales order delivery, the availability checks for components in production – thus
reporting the missing parts list, the backorder processing etc.
c) Reporting
• To configure the objects, which are to be considered in the calculation of the “receipts days
supply” like the production orders/process orders, firmed planned orders, purchase orders,
assigned planned orders, firmed purchase requisitions, QM Inspection lots, reservations, safety
stocks
• To configure the reporting of “periods totals” in terms of a defined period (day, week, month,
periods as per planning calendar) of in Stock requirement list, MRP list, simulative MPR or
interactive MRP
d) MRP Controllers
This is a mandatory configuration. Here you can configure the list of MRP controllers for the plant. A
MRP Controller is a person or a group of people, which is responsible for planning a material or a given
list of materials.
You have to assign the MRP controller to the Material Master MRP 1 View, so as to delegate the
responsibility of the planning and evaluation of planning for that material.
e) Floats
Floats are buffers in the total lead time, that are provided in production/process order or in the planned
orders created manually or during an MRP run. The schedule margin key is used in the Material Master
MRP 2 View. It is used in MRP as well as in production order.
Opening period: Number of working days between the date that the order is created and the planned
start date. This time is available for the MRP controller to convert a planned order into a purchase
requisition or a production order.
Float after production: Number of working days between the scheduled finish date and the order finish
date; used as a float in production scheduling.
Float before production: Number of working days between the order start date and the scheduled start
date; used as a float in production.
Scheduling release period: Number of workdays between the planned start date and the date for
releasing the order. If the order release indicator is set, the production order is released by a
background program that takes all dates into account.
Plant Plant Margin Opening PeriodFl. Before ProductionFl. After ProductionRelease Period (In
Name Key (In Days) (In Days) (In Days) Days)
0001 0001 001 5 2 2 5
0001 0001 002 5 3 3 5
0001 0001 002 5 4 4 5
f) Special Procurement
The special procurement function helps you to configure and assign special procurement to the
materials which can be used during an MRP run while creating the procurement proposal.
The special procurement functions are withdrawal from alternate plant, production in alternate plant,
subcontracting, direct production, phantom item planning,
Create the Special procurement key (Key number = 12 as an example) in the plant C002 with the
procurement type as “F” and special procurement as “U” (Stock transfer) and the special procurement
plant as “C001”. Normally when creating the special procurement key use Z, Y or X to the Key number,
so instead of having Key number as 12, we could have something like Z2 or YA etc.
Similarly for Production in alternate plant, you could have a Configuration as below:
Fig MRP - Config 6
In this configuration parameter, you can maintain the production order type or the process order type,
which the system should use as default during the planned order conversion. Setting defaults in the
plant parameters configuration allows the system to fix and select the order type for a plant during the
conversion process.
Note: This can be a useful tool when you are using one production order type and one process order
type, but if you are using multiple production/process order types, then you should not be maintaining
defaults here.
Also for the purchase requisition conversion, you are given an option in the configuration to define the
maximum number of planned orders that can be converted in to Purchase requisition.
When carrying out the availability check for each of the components in a MRP BOM explosion, the
system needs to know the availability checking scope rule. Again we would maintain the standard
Checking rule as PP or you could alternatively configure one for yourselves.
h) BOM/Routing Selection ID
This configuration parameter is really important and it is mandatory to maintain one, since it helps
selection of BOM and task lists in the planned orders. Though there is one more place in the planned
order Scheduling parameters MRP configuration, where you can maintain the selection ID for selection
of the Task lists (Routing/Recipe/Rate Routing).
A selection procedure is set to select BOM or Routing/Recipe on priorities set for the BOM usage or for
the task list types and the task list status. Knowing the selection procedures allows the MRP run to
select the right BOM and task list for the planned orders.
In other words, you could have the BOM Selection being set for selection of the Production BOM
Usage first and if a BOM for the material with the Usage – production (Usage = 1), is not found, you
could have the system search for a BOM of universal Usage (Usage = 3).
Similarly, you could have a task list of type Routing or Recipe or reference operation sets selected and
set in priorities of selection (1st – Routing, 2nd – Reference operation sets, 3rd, which has a Status
Released for all purposes or released for costing) etc.
h) Scheduling of Planned orders
This configuration parameter is really important and it is mandatory to maintain one. It allows you to set
the control parameters for scheduling of planned orders of type LA at a given plant and for a given
MRP Controller. You can leave the MRP controller as “*” to have the scheduling parameters true for all
the planned orders across all the MRP controllers.
• The Routing/Recipe Selection ID, specifying the routing/recipe that would be selected for
detailed scheduling, as per the priorities set for task list type and task list status.
• The Detailed scheduling, using the task list is only carried for the scheduling Horizon
mentioned, i.e., if the planned orders dates lie beyond the scheduling horizon, then the basic date
scheduling is used where the in house production times from the material master is used.
• Allow Scheduling Indicator allows the planned orders to be scheduled using the detailed
scheduling or basic date scheduling, either of the two, depending upon the availability of the task list
and scheduling type selected for the MRP run.
• Generate Capacity requirements indicator allows generation of the capacity requirements for
the work centers and loads them accordingly. The loading of the work centers is as per the use of
the work center determined through the scheduling carried out.
• The Task list selection, scheduling horizon, scheduling indicator and the capacity indicator can
also be set for rough cut planning used for Long term planning purposes.
• The next configuration parameter talks about the configuration of the selection of the type of
scheduling level that should be used for adjusting the basic dates of planned orders. The various
options available are rate based scheduling, lead time scheduling, scheduling using takt times.
• The Adjust planned order dates configuration option allows you to readjust the scheduling
results or the basic dates every time you carry out Scheduling. Though there is one more
scheduling configuration option provided by the system for overwriting/adjusting the existing basic
dates by the new dates arrived at, through rescheduling (using the scheduling level as mentioned).
The system not only offers an option to adjust the basic dates for the planned order arrived at by
using the scheduling level set, but it also setting the dates of the dependent requirements to the
operation start date or the order start date.
This configuration not only adjusts or sets the dates of the header planned order and the dependent
planned orders, but it also generates capacity requirements for the same.
See below for the details of adjusting dates in scheduling and adjusting dates for capacity
requirement generation:
• You can adjust the Basic Dates of the header planned order using the scheduling level
and adjust (or set) the dependent requirements to the start of the header planned order
• You can adjust the Basic Dates of the header planned order using the scheduling level
and adjust (or set) the dependent requirements to the start of the respective operation to
which the dependent requirements are assigned to
• You can decide not to adjust the Basic Dates of the header planned order arrived at by
using the scheduling level and at the same time not-adjust (or not set) the dependent
requirements to the start of the header planned order
• You can decide not to adjust the Basic Dates of the header planned order arrived at by
using the scheduling level and at the same time not-adjust (not set) the dependent
requirements to the start of the respective operations to which the dependent requirements
are assigned to
• You are also provided an option to configure the scheduling type – whether forward or
backward scheduling. It is a normal behavior for the standard system to have this configured as
“backward scheduling” so that SAP MRP (material requirement planning) never misses the
customer delivery date or order availability date. An option is also provided to not-to-schedule, any
orders during the breaks set in the factory calendar.
• Start date in the in the past options allows you to push the start date of the planned orders to
a certain number of days in past. If the order start date goes beyond the number of days allowed,
then the system uses the concept of ‘today’s scheduling” and sets the start date of the planned
order to today’s date and carrying out forward scheduling there-after.
• One of the scheduling parameters is “reduction measures”, used to reduce the total order lead
time in circumstances designed. You can avoid configuration of reduction measures, if you are not
using it.
For external purchasing, one can maintain the default lead time required for conversion of Purchase
requisition into purchase order, using the planned delivery lead times from the purchase info record or
purchasing agreement. So as to use the planned delivery times from the purchase info record, one
should also maintain the source list for the material, with the same vendor in the source list and the
purchase info record.
Using the planned delivery times from the material master or from purchase info record, is totally a
decision of the consultant. It is indeed a nice additional option provided by SAP for using the lead time
from info records.
j) Planning Horizon
Maintaining a planning horizon helps the system to plan only those demands, which fall in the planning
horizon starting from today. When an MRP Run is taken, the planning horizon is number of work days
as mentioned (let’s say 180 days) from today’s date; the system would not plan any orders whose start
date lies beyond this horizon.
SAP MRP offers you a choice to select the most controversial stock types, in its net requirement
calculations. The stock types are – stock in transfer (stock in transfer is considered as stock at the
receiving plant as it is already issued from the sending plant), blocked stock, restricted batch stock
(stock of batches marked with restricted batch)
The entire configuration that is created as a part of SAP MRP Plant level parameter in the above steps
can be also set for an MRP Group. You can group materials using MRP Groups. Each of the MRP
Group can have its own MRP Parameter set. You can set the MRP group in the material master MRP 1
View.
MRP Group can be maintained using transaction code OPPR or the transaction path – Logistics >
Production > MRP > MRP Groups >
Strategy group,
Conversion order types,
Planning horizon,
Planning time fence and roll forward periods,
BOM and task list selection ID’s,
Direct procurement parameters,
Planned order scheduling parameters,
Start number of days allowed in the past
Availability checking groups,
Strategy Groups
The strategy groups can be set for a given MRP group at a given plant. The strategy group consists of
a number of planning strategies assigned in a sequence of priorities. In other words, the strategy
groups, groups together the relevant planning strategies of a material. If you don’t see the default
strategy groups, then we would have to manually maintain the strategy groups on the materials MRP 3
view. Defaulting the strategy groups is a nice idea when the strategy groups would remain the same
across all the materials which would be assigned with a given strategy group.
For example:
A material can have the priority 1 strategy as Made-to-Stock (planning strategy 40) and then priority 2
planning strategy as Made-to-Order (planning strategy 20). Assigning this “strategy group” for a MRP
group in the MRP Group Parameters configuration and then subsequently assigning the MRP Group to
the material master would make the material work on a planning strategy 40 and planning strategy 20
in a sequence of priority.
The primary strategy for the material is 40 – Made-to-stock while the secondary strategy is 20 – Made-
to-order, which means that every time you plan or produce a material or create a sales order for the
material it will always primarily work as a made-to-stock material. Nevertheless, you can also make to
material work as a made-to-order material, by changing the requirement type – “KE” of the material in
the sales order procurement tab, to suit for made-to-order, which the system would allow since the
material’s secondary planning strategy is made-to-order.
In all probabilities, MRP Types is not something which one should configure in SAP; it is used as a
standard configuration. Nevertheless, a consultant should know the importance of MRP types and the
involved pre-configured parameters.
a) MRP Procedures
MRP Procedures defines the type of MRP to be used – Reorder point planning methods, Material
requirement planning or demand based planning methods, Forecast based planning methods, Time
phased planning methods, MPS and the no planning procedures to mark a material with a MRP types
that does not plan a material at all.
b) Firming Type
In the category of MRP procedure called – MRP or demand based planning method and MPS, SAP
offers 8 different MRP types with Firming namely P1, P2, P3, P4 and M0, M1, M2, M3, M4.
When working with the planning time fence, one needs to set the firming methods & the scheduling
methods of the procurement proposals within the planning time fence.
0 1 2 3 4
Firming type
M0 P1 P2 P3 P4
MRP Types M1 M2 M3 M4
The inclusion of external requirements in net requirement calculations is available to be set, when you
are working with reorder point planning based MRP types. Actually there are 2 options in this field, i.e.,
include external requirements in the total planning horizon or restrict the inclusion of the external
requirements only within the replenishment lead time.
For example:
If the external requirements are set to be considered in the total horizon (of 7 weeks) then in the
today’s MRP run, the Customer demand will be considered as it falls in the planning horizon and it will
reduce the warehouse stock proportionately which would trigger the reorder point planning
procurement once the stock falls below the reorder point.
If the external requirements are set to be considered in the Replenishment lead time, let’s say the
Replenishment lead time is 1 week, then in that case, only in a MRP run triggered one week before the
start date of the external demand, this customer demand will be considered, thus triggering reduction in
warehouse stocks.
SAP also offers an option to select the additional external requirements that should also be included in
the net requirement planning calculations like the - components supplied to the vendor in a
subcontracting case, reservations set for the components in a production order, reservations of
components in plant maintenance orders, requirements to satisfy the Stock transfer order to another
plant, stock transfer requisitions created for Stock transfer orders, requirements raised because of
stock transfer delivery schedules.
Forecasting MRP Types have a “forecasting indicator” as obligatory, unlike other MRP types which
normally have the forecasting indicator set to optional.
Also the historical data is updated in the material master as total consumption (planned consumption
plus unplanned consumption) or unplanned consumption. When the consumption is planned as per the
MRP reservations, planned consumption is updated and when the consumption is not planned as per
the reservation or is greater than the reservation quantities, then unplanned consumption is updated.
In MRP type configuration, you have an option of choosing the type of historical consumption of a
material to be used for planning whether total consumption (planned + unplanned consumption) or
unplanned consumption.
After choosing the historical date type, you should configure, the type of forecast requirements to be
considered in MRP planning run, whether total consumption (planned + unplanned consumption) or
unplanned consumption.
The reduction method for forecast requirements is also configurable. The default is reduction by
consumption.
d) Planning method
The MRP type offers you to plan the materials in an external system, like the MRP Type X0. The
indicator called the planning method allows you to choose external planning so as to plan materials in
the external system.
e) Automatic Calculations
You can have the safety stock and the reorder point calculated automatically by the system, when you
are using the automatic reorder point planning methods. In the automatic calculations the system uses
the forecast data.
Configuring SAP MRP Scope of Planning for the Total Planning Run
SAP provides an option to plan multiple plants together or multiple MRP areas in one planning run in a
sequence. Transaction code OM0E can be used for configuration or the logical SAP path – SAP
Customizing Implementation Guide > Production > MRP > Planning > Define Scope of Planning for
Total Planning, can be used to configure.
Step 2 – Define the plants or MRP areas to be included in the planning run arranged in a sequence.
The sequence is defined by the first field called
Configuring SAP MRP Planning time fence and Roll Forward Period
The transaction path to configure the planning time fence and roll forward period is: SAP Customizing
Implementation Guide > Production > Material Requirements Planning > Planning > MRP Areas > MRP
Calculation > Define Planning Time Fence and Roll Forward Period
In other words, in the planning time fence, the system does not create or delete any procurement
proposals nor does it changes the existing proposals.
The system calculates the time fence from today’s date plus the “number of days mentioned as
planning time fence” in the material master or in the MRP configuration (where you can define the
planning time fence for plant or for a given MRP group). It is needless to say that any new
requirements are not included in this time period nor the existing requirements are changed. MRP
carries its usual planning outside this fence without interrupting this fenced period.
It is logical that any procurement proposal lying outside this fence would start moving in to the fence
one by one; when the fence moves ahead on the time scale. When they move in to this fence, they are
automatically firmed for protection.
The automatically created procurement proposals in the MRP Run are not firmed by the system, so
that they are available for adjusting dates and quantities in the next planning run, in cases where there
is change in BOM or task list.
You can though manually firm the planned orders individually or collectively using transaction code
MD19
Note - Automatically created planned orders in the planning time fence are only remain firm till they are
in the planning run.
For manually created or changed procurement proposals or even when you reschedule the planned
order in the graphical planning table, the system always marks them with a firming indicator. Though
you can remove or delete this firming indicator.
In case of a planned order, you can manually firm it by selecting the “firming planned order Indicator” in
the planned order header. And in order to make sure that the BOM levels below are not exploded or
changed in a planning run, you have to set the “firming components indicator”
The Roll Forward Period adds the functionality of automatic deletion of firmed planned orders, from the
master plan. It also creates new proposals to cover any requirements pending during the MRP run.
This period can be defined for number of days in past or future. The system deletes all the firmed
planned orders that lie before the roll forward period.
Using the roll forward period, you can have the system delete all useless old firmed planned orders,
which otherwise the system would never had deleted, since they were firmed. This allows for
reorganizing the planned orders.
Long ago, SAP MRP was only at the plant level or at MRP controller level (activated through a user
exit). Then SAP came up with the concept of running MRP at MRP areas. You can define your own
area for which you want to run MRP without disturbing other areas.
Running MRP for MRP Areas: For running MRP at a MRP area, you would have to create a scope of
planning in MRP configuration, which contain the MRP area or a set of MRP areas arranged in
sequence of planning.
Assigning MRP areas: To have the “MRP Areas” work, you have to activate the MRP areas and then
create them and then assign them to the material master MRP 1 view. If a MRP area is not assigned to
the material, then it will work as per the plant level MRP area.
Step 1: Activate MRP Area: Use the transaction path: SAP Customizing Implementation Guide >
Production > Material Requirements Planning > Master Data > MRP Areas > Activate MRP for MRP
Areas
Step 2: Define MRP Areas: Use transaction path: SAP Customizing Implementation Guide >
Production > Material Requirements Planning > Master Data > MRP Areas > Define MRP Areas
Plant MRP Areas: You can create one MRP area for several plants, so that when you run the MRP for
this MRP area, the run is for all the plants configured in the MRP area.
Storage Location MRP Areas: You can create MRP areas for several storage locations at a plant. You
cannot use one storage location in multiple MRP areas.
Subcontractors MRP Areas: You can create MRP areas for several subcontractors for a plant. You
cannot use one subcontractor in multiple MRP areas.
The Range of coverage profile is configured for the use of Dynamic safety stock for a given material.
The range of coverage configuration contains the parameters for the calculation of the dynamic safety
stock. The dynamic safety stock is a stock calculated based on the average daily requirements for a
period rather than the actual requirements over the period, therefore it is more statistical value rather
than an absolute value.
Safety stock as we know is used to cover the fluctuations in the requirements, so is the dynamic safety
stock, the only difference being, the safety stock is an absolute value provided directly for a material
whereas the dynamic safety stock is calculated by the system on the basis of the coverage period and
average daily stock calculated internally by the system.
The transaction path is: SAP Customizing Implementation Guide > Production > Material Requirements
Planning > Planning > MRP Calculations > Define Range of Coverage Profile (Dynamic Safety Stock)
Period indicator - Indicate the type of period, whether week or month or according to PP planning
calendar. (Let’s say it is W – Week)
Number of Periods – Number of periods used to calculate the average daily requirements (Let’s say it
is 13 Weeks)
Type of Period length – It defines the number of days in the period, if the period length is in terms of
workdays, then the factory calendar work days are considered, if the period length is in terms of
calendar days then it is considered in terms of Gregorian calendar, and if it is terms of standard days,
then you would have to enter the number of days in a period in the configuration (Let’s say that the
configuration was done with workdays and the factory calendar has 7 days per week)
= Requirements in the period (Requirements in 13 Weeks – Lets say 910 Units) / (Number of Periods –
Lets say 13 Weeks) * (Number of days in the period – Lets say 7 days)
= 910 / (13*7)
= 10 Units
Configuration parameters for calculation of Dynamic Safety Stock for the Range of Coverage
You can define 3 different range of coverage – minimum, maximum, and target range of coverage,
which is used to calculate 3 different stocks using the average daily requirements (range of coverage
multiplied by the period length). The Target range of coverage defined here would be used to calculate
the Dynamic Safety Stock for the period of the coverage.
The Period of the coverage is specified in the configuration. The coverage’s and the periods for which
they should work for, are defined for 2 separate period lengths and the 3 rd period length is for the rest of
horizon.
In the example, we have defined the safety stock to cover a period of 7 days (minimum, target and the
maximum range of coverage). The minimum, target and the maximum stock is calculated for the
average daily requirement over the respective coverage periods.
You can check the minimum, maximum, target stock levels, minimum range of coverage, maximum
range of coverage, target range of coverage in the MRP List or Stock requirements list’s “Period Total
Display” Section.
As per our example, for the first period of 13 weeks, all the 3 stocks levels – minimum, maximum, and
target stock levels would be 70 Units and for the next period of 26 weeks it will be 70 units as well and
for the rest of the horizon it will be 70 units again.
Normally when the available stock falls below the minimum stock level, SAP planning run, would
immediately create planned orders to suffice at least the target stock level. For example if the minimum
stock level is 30 and the maximum is 80 and the target stock is 50 units, then if the available stocks fall
below the 30 units mark, SAP creates a procurement proposal for 50 units to reach back to the target
stock level. Whereas in the example below, all the 3 stocks types are 70 units, therefore when the
stocks fall below the 70 units, the system will try to raise a procurement proposal to reach back to 70
units.
For the first period, when the stock falls below 32 units (minimum Stock Level), the SAP MRP run
would create the procurement proposals (Let’s Say planned order) for a quantity to suffice at least the
target safety stock level or the dynamic safety stock level = 8 Units.
Dynamic safety stock Dynamic safety stocks Dynamic safety stocks for Dynamic safety stocks for
formula summarized as = for the 1st period of 8 the 2nd period of 8 weeks the rest of the Horizon
Average Daily Stock * weeks
Range of coverage
= 2 * 16 = 32 = 2 * 16 = 32 = 2 * 16 = 32
Minimum safety stock
= 5 * 16 = 80 = 5 * 16 = 80 = 5 * 16 = 80
Target safety stock
SAP offers 2 types of evaluations in SAP, the days supply and the receipt day’s supply.
In the SAP MRP Evaluation transactions such as stock requirement list or MRP list, the days supply
would calculate the number of days on the time axis, till the material requirements can be satisfied
purely by the current available stock.
While the Receipt Day’s supply would indicate how long would the current stock and the expected
receipts would cover the requirements. There are 2 receipt day’s supply evaluations offered by SAP
called as the receipt day’s supply 1 and receipt days supply 2. SAP offers a configuration to select the
receipts elements for receipt day supply 1 and 2 evaluations. There is also an option to have the
receipt day’s supplies to be calculated when the stocks fall below the safety stock or below the current
available stocks.
The days supply values or the receipt days supply values can be correlated with the range of coverage
concept. These tools comes with traffic lights – red, yellow and green which offer warnings to the MRP
Controllers/users and lets him/her strategically know when the material stock would be totally
consumed out, which would help the planner to foresight and take necessary actions in advance.
The transaction path for the same is SAP Customizing Implementation Guide > Production > Material
Requirements Planning > Evaluations > Define Receipt Elements for Receipt Days' Supply
X
Only Consider Current available Stocks to cover
Requirements
Consider Receipts also along with Current Stock in Calculation of Days Supply
Firmed Planned orders, Planned orders assigned with Production versions, Purchase orders, Schedule lines,
Firmed Purchase Requisitions, Receipt Reservations, Shipping Notifications
X
Consider all the possible receipt elements along with the
plant stock
X
Consider all the Most Certain receipt elements along with
the plant stock
Days’ Supply on Today = Coverage’s Considering without the receipts = 3 Days Exactly
Receipts Days’ Supply for Material M1 on Today = A little more than 4 days
(Receipts are also considered – This example can be for Receipt Days supply 1 or 2)
2nd - 30 (95 + 0 ) – 30 = 65
Day Total Receipts on day = 0 Available = 95
4th - 47
Day Planned order = 8 Available = 40 (40 + 13) – 47 = 6
Production order = 5
Total Receipts on day = 13
5th - 40 Available = 6 (1 + 5) – 40 = - 34
Day Planned order = 5 Shortage
Total Receipts on day = 0
6th - 20
Day