Anda di halaman 1dari 9

Operating Reserves Provided by Distributed Generation

FRANCISCO D MOYA CH (a), DUVIER BEDOYA BEDOYA (b), Dr GILBERTO DE MARTINO


JANNUZZI (c), Dr LUIZ CARLOS PEREIRA DA SILVA (d),
FEM, FEEC, UNICAMP
Cidade Universitária "Zeferino Vaz", Campinas, São Paulo
BRAZIL
(a)
framo@fem.unicamp.br http://lattes.cnpq.br/6867376592649835
(b)
duvier@ieee.org http://lattes.cnpq.br/0918270598381687
(c)
jannuzzi@fem.unicamp.br http://www.fem.unicamp.br/~jannuzzi/index.html
(d)
lui@dsee.fee.unicamp.br http://www.dsee.fee.unicamp.br/~lui

Abstract: - Among the ancillary services, the operating reserves are important researching aspects, which deal
with supplying way and selling-buying prices. Currently, distributed generation (DG) rises as a new participant
in providing ancillary services, therefore, it is of main importance in operating reserves subject. This work
shows some advantages and technical drawbacks by using DG when operating reserves are supplied. Different
sceneries were computed where the electric generation was performed in a centralized and non-centralized way
respectively. A methodology for identifying the maximum DG, which can be allocated, is proposed; this
maximum level can be assessed without carrying out a negative impact in the network. Diverse DG technologies,
which present better performance in supplying such reserves, are also presented.

Key-Words: - Distributed Generation, Operating reserves, Ancillary services.

1 Introduction services, when they take part into the electricity


The reliability concept deals with different elements market. In California there is a reserve market
in electric power systems: security and sufficiency. independent and parallel to the electricity market. In
Security is described as the capacity of the system to New England, there is a capacity market, similar to
face different disturbs, this is used combined with an operative reserve market. In Brazil, the regulatory
protection devices, power dispatch and other agency establishes an operating reserve total for the
auxiliary services. Sufficiency represents the whole system, equal to the capacity of the major
capability of the system for attending the demand generator unit. Thus the Itaipu power plant with 6,3
requirements in any time. GW sets up the maximum level of the operating
In economical terms, security concept can be defined reserves. The current capacity of the Brazilian Power
as a public good. Transit systems, national defense System is 91,17 GW, being the operative reserve
infrastructure, laws, etc, are considered as public 6,7% of the total installed capacity.
goods also. Some authors consider the system Currently, electric systems are changing and with the
security as a public good [1], being operating reserves distributed generation (DG) growing up, the
of an electric system a key security element. distribution systems are turning into from passive to
As other public goods, power system security has no active entities [2]. The new and future DG schemes
clear indications of its cost per user. Some users can are allowing a wide possibility of new energy
disagree paying the operating reserves when they suppliers and complementary services such as
don’t utilize such reserves and also if they are paying auxiliary services in which the operating reserves
for extra security which is provided for other users. takes part into. DG is a new participant in the current
The difficulty is defining the optimal acquisition level and future electric systems related to programming
for every user and develops a methodology for and the operating reserves dispatch [3], [4].
carrying out this acquisition as well as its costs. Dispatch of centralized units requires a higher
The electricity markets in different countries are generation level, which should supply energy to all
discriminated mainly in the methodologies or the network points, including all the load power and
procedures in the operative reserve management. For the network losses in the whole system, the
instance, in Britain the reserves are obtained by long- transmission system and the final points related to the
term contracts. In the Nord Pool market, the energy distribution system [5].
utilities, are required to supply specific auxiliary On the other hand, delivering active power by the
generators in the distribution system, close to the
load, reduces the losses and consequently, improves transmission, sub transmission and distribution
the voltage levels and increases the system security. systems.
This work shows some technical advantages when
DG is used in the dispatch of active and reactive
power reserves. In the following section, the 2.1 The DG and its role with the Operating
formulation of the problem is described. Afterwards, reserves
it is showed and explanation of the methodology After presenting the DG advantages and drawbacks,
used. It is also proposed a methodology for it is possible to note that the operating reserves with
establishing the maximum DG level that can be DG present different implications; therefore, it is also
installed and at the same time, caring of the negative necessary assessing the advantages and
impacts in the network and consequently the disadvantages. With this aim, in the second part of
maximum DG level that can be provided for the this work is presented an analysis related to the active
supply of operating reserves. and reactive energy supplied by DG when centralized
An application is also showed; it is presented an generators outages occur.
analysis when DG is used for supplying operating
reserves. Furthermore, the DG technologies that
attend more efficiently the reserves management is 3 Methodology
described. Finally the conclusions of this work are
The development of a methodology that lets know the
presented.
DG energy production limits, allows assessing
directly the DG maximum capacity for providing
operating reserves. In some works such as [8] and [9],
2 Problem Formulation it is described the importance of the DG allocation
The connection of energy supplies to the distribution and establishing the necessary capacity for DG
systems modifies the traditional hierarchical installation in order to reduce the distribution system
generation way before known. The energy injection losses. However, its neglects the analysis of possible
in the distribution networks modifies the power flow impacts like overvoltages produced by DG
and can develop several impacts such as: losses, installation.
investments, voltage profile, maintenance people For knowing the effects on determined electric
security, power quality, short circuit power, and system when DG is studied, it is convenient to know
system operation. This work analyzes the impact on the electric parameters of such system when
the active and reactive power losses, and the voltage centralized generators are used. For instance, when a
profile impact on the network. load flow is computed it is possible to know some of
the most important electric parameters (such as:
voltage profile and the losses level) without using DG
on the system. After that, it is possible obtaining the
2.1 Loses modification when DG is used
base case for comparing with the alterations in the
The problematic associated to the DG impact has
presence of generators connected to the distribution
several implications (economic, technical and
system. The base case allows also verifying the
environmental). For this reason, in the last years
buses, which presents greater voltage drops and the
researchers have began to take it into account.
areas and branches where the losses are more critical.
Currently due to the multiple studies, it is known that
This buses and areas are the best locations for the DG
DG presents limited advantages related to the losses
installation. After the DG installation in such
reduction. In [6] and [7] it is known the importance of
sceneries, the possible presence of overvoltages is
the active and reactive energy supplied by the DG. In
lower and the losses reduction is more effective.
these works it is also demonstrated that with higher
This section is based on the procedure presented in
levels of DG the losses may increase. Thus it is
[8]. After assessing the DG units to be installed in the
necessary known the DG capacity that can be
distribution system, it is necessary to compute load
installed without increasing the losses and not
flows by increasing the generators capacity and
affecting the voltage profile. It is required to know
assessing the new electric parameters in order to
the energy generation limits through DG, it makes
evaluate the overvoltage levels produced.
essential to know the maximum DG capacity for
This methodology is presented in Fig. 1.
supplying the operating reserves.
In the first part of this work, a methodology for
determining the DG installation limits is presented. It
is also studied the influence on the losses in the
power system analysis MATPOWER [14] was
utilized.

Fig. 2 Distribution circuit used.


Fig. 1 Methodology for establishing the
maximum DG installation level. Below the process for the sceneries studied is
presented as follows:
Phase I: Load flow without DG (base case): for this
This methodology allows computing the maximum
case the active energy generation (P) and the reactive
DG installation level without damaging the network.
(Q) were delivered in a centralized way without DG.
It is also possible to establish the maximum DG level
In this case it is considered that the centralized
for the operating reserves. Some works such as [10]
generators supply all the active and reactive demand,
and [11] have presented a methodology for
supposing that the generators are delivering the
computing the amount of operating reserves which
operating reserves scheduled previously. In this work
can be established for an electric system, but
the reserves classified in accordance with the
currently there are no studies related to the evaluation
response were not considered.
of such reserves in DG. The methodology proposed
Phase II: Losses and voltage profile analysis: After
in this work arises in response to the necessity of
computing the base case, it is possible to obtain the
determining the maximum DG admissible level for
areas where the higher losses level is presented. The
supplying operating reserves.
results for the case analyzed in this work, in only one
of the distribution circuits and determined areas that
are represented with the gross line Fig. (2).
3.1 Study Case In addition, Fig. (3) shows losses level in the
In this work it is implemented a simulation for distribution circuit circuit which has more losses. It is
different sceneries with the aim of comparing important to emphasize that only one distribution
technical centralized generation aspects and non- circuit presents the higher losses level
centralized generation when DG is involved. Fig. (4) shows the voltage profile (V) for each
These sceneries were computed by using a load flow voltage level: transmission, sub transmission and
(static model) for an electric system which takes into distribution (gross line) at base case. The load flow
account voltage levels for transmission, sub results show that the voltage levels decrease from the
transmission and distribution in order to assess the transmission level until the more distant buses in the
DG impact in every voltage level. The IEEE30 bus distribution system. These areas are represented with
system was used [12] for carrying out the study. Two circles and they are named V1 to V7 Fig. (2).
buses on the medium voltage level were separated for Phase III: Selection of the more appropriate buses for
generating the distribution network (low voltage the DG installation: After obtaining the areas with
level). At the buses 30 and 24 it was connected a major losses, it is possible to establish the areas
distribution system of 70 buses TS2 [13] that is where the generators can be allocated in the
presented in Fig. (2). distribution system.
For computing the optimal flow the Newton-Raphson Phase IV: For determining the possible DG impacts
and Fast-Decoupled Newton methods were used. In affecting the voltage level, the smaller generators
order to develop the simulations, the program for should be connected only to one of the distribution
circuits and assess the impact when compared with Phase V: After installing the generators, several load
the distribution circuit without DG presence. For the flows were computed increasing the DG installed
case studied, four generators in the first distribution capacity, with the aim of obtaining the impact on the
system were installed. The first distribution system different voltage levels of the system that is being
corresponds to the areas V5, V4 and V7 (allocated in studied.
the bus 30) Fig. (2). The generators selected were allocated for a operation
Table 1 shows all the generators of the system with with a power factor of 0,9 in capacitive or inductive
their basic features. way.
Phase VI: Verification of the electric parameters
after DG installation: in this part of the procedure it is
compared the voltage level and the losses presented
when DG is used related to the base case.
a) Losses analysis: in Fig. (5), it is possible to analyze
the losses behavior in the transmission, sub
transmission and distribution branches by increasing
the DG from zero up to 3,73 % of the total system
load. This is known as DG Penetration Level
(DGPL).

Fig. 3 Losses level in the distribution


system

Fig. 5 Losses increasing the DG


penetration
In this case, the active losses level of the transmission
system decreases by 14% and for the sub
transmission system the losses where reduced by 29%
when the DGPL is 10%.
In relation to the distribution system, the losses
decrease up to determined level, after this DGLP
Fig. 4 Voltage profile at base case level the losses rises highly. At the base case, when
the DGLP is 0,78%, a limit for the reduction of the
P max Power
Generator Type
(MW) Factor
active losses is obtained. For the reactive limit, it is
G1 Centralized 200 Free
presented a DGLP different of the active one due to
G2 Centralized 80 Free
the reduction of active energy. Table 2 shows the
G3 Centralized 50 Free numerical results that the load flow provided for three
G4 Centralized 40 Free DGPL levels. Thus, DG presents more advantages in
G5 Centralized 30 Free the active and reactive losses reduction in
G6 Centralized 40 Free transmission and sub transmission levels and with a
G7 Distributed 2,53 0,9 limit in through the distribution levels. However, it is
G8 Distributed 2,53 0,9 possible to reduce the losses in a greater rate in the
G9 Distributed 2,53 0,9 distribution circuit than in the other circuits.
G10 Distributed 2,53 0,9 For instance, at base case, it was possible to reduce
the losses in the distribution system by 33% with only
Table 1 Generators features a 0,78 DGPL level.
than when DG is not used, producing a minor voltage
DGPL(%) drop. In addition, the active and reactive power
Net Power 0 0,38 1,23 injection increase the voltage profile. In Fig. (4) is
Transmission
P (MW) 2,65 2,57 2,28 showed a voltage profile for the base case and when
Q(MVAr) 9,41 9,14 8,12 the DGPL is 1,23%. In Brazil, the technical
P (MW) 1,33 1,19 0,95 regulation establishes that the minimum and
Sub transmission
Q(MVAr) 10,44 9,85 8,68 maximum values for systems with voltages level up
P (MW) 0,12 0,08 0,60 to 231 kV should not be minor and major than 95%
Distribution
Q(MVAr) 0,23 0,15 0,47 and 105% respectively.
Table 2 Losses in different system Fig. (6) shows that the voltage levels in the base case
levels don’t infringe the limits, however, the upper limits
are infringed when the DGPL is greater than 1,23%.
For analyzing the possible impact that DG can After increasing the active and reactive power output
develop in other distributed systems where initially in the distribution network, overvoltages can occur,
DG was not installed, it is necessary assessing the mainly in the distribution system, and with less
losses behavior, they are showed in Fig. (6). importance in the sub transmission and transmission
The losses in the distribution system where DG has systems. An alternative for avoiding such violations
no been installed, present a similar behavior in the is increase the number of smaller generators in the
transmission and distribution systems. The reduction distribution networks, this is known as an augment in
losses curve presents a linear behavior in the the DG dispersion level of lower power, it is shown
distribution system, whereas, the reduction losses for in [7] and [16].
the transmission system is concave. This feature for The methodology proposed in this work recommends
distribution systems is also shown in [7]. increasing the DGPL and verifying at which values
In a persuasive way, the DG decreases the active and the generation be on the voltage network limit. Fig.
reactive losses in distribution systems where DG is (4) shows that the maximum voltage values are
not intall. As was explained earlier (see Phase IV), presented exactly in the distribution system where the
four generators in the first distribution system only DG has been installed. In this case, when the DGPL
were installed. In addition, when the DGPL is 0.78%, is 1,23 % the maximum value is obtained when the
in the second distribution circuit a losses reduction of voltage limits are not violated (in Brazil for systems
0,36% is obtained, see Fig. (6). The DG presents also up to 231 kV).
advantages in the active and reactive losses reduction The penetration value is showed in Fig. (6) for GD3,
in others distribution circuits of electrical system. this means that respecting the maximum voltage
The total losses reduction in the system can be to limit, the maximum losses reduction value is not
measure and compensate economy to DG for this reached, however, the advantage is obtained with a
contributions. major losses reduction in other branches of the
system (transmission, sub transmission and other
distribution networks). All the results are shown in
Table 2.
Phase VII) With the identification of the maximum
penetration level, the electric parameters established
are respected so, it is possible to obtain the maximum
DG value without carrying out a negative impact on
the system, as was explained earlier, in this case
when the DGPL is 1,23 %. Therefore, with this
methodology it is also possible to obtain the
maximum level that DG can deliver in relation to the
operating reserves.
Fig. 6 losses in the distribution system
b) Voltage analysis:
The DG energy production in the distribution system 4 DG as an Operating Reserve Supplier
carries out an increase in the voltage profile of the With the aim of verifying the DG performance and its
system [15], [16]. This impact is due to the local impacts in operating reserves deliver, it is necessary
energy supplied and to the injection or consumption analyzing situations for possible outages of
of energy in the system. In the first place, the active centralized generators. For this analysis it is studied
demand reduction that the generator delivers is lower the base case where all the centralized generators are
supplying active and reactive power for all the scenery, this happens when the generator G3 is out,
system. as mentioned before.
In the second part of this work, other cases were It is possible to prove that by using DG a minor
simulated turning off a centralized generator in each losses level is presented when a centralized generator
case and the DG deliver operating reserves. The is out. For the studied case, the losses reduction
DGPL is also increased with the aim of assessing the related to the base case where G3 is out and there is
electric parameters in the system with the output of a no DG, the losses level decreased by 7,45% for active
centralized generator and the entry of DG. power and by 7,33% for reactive power. In the sub
transmission area, the reduction was by 14,7% and by
7,48% for active and reactive power respectively. In
4.1 Voltage Analysis the distribution system, there are major advantages;
For the analyzed system, the results showed that the the losses reduction is 23% for active power and
voltage profiles in every one of the subsystems were 42.3% for reactive power. These results are illustrated
not modified in an important way with the outage of in Table 2.
the centralized generators at base case. This means,
without the DG presence, the centralized generators DGPL(%)
supplied in an effective way the active and reactive Net Power 0* 0** 1,23
power demand with the outage of any centralized P(MW) 2,646 6,90 6,70
Transmission
generator. Q(MVAr) 9,407 23,92 23,23
The load flow results showed also that the voltage P(MW) 1,334 1,37 1,17
Sub transmission
profiles are not modified seriously when DGPL is Q(MVAr) 10,44 10,49 9,71
increase, being almost the same voltage profiles as P(MW) 0,123 0,12 0,09
Distribution
showed in Fig. (4) Section (3.1 b.) Q(MVAr) 0,229 0,23 0,13

Table 3 Losses in different DG levels


* base case, all centralized generators on
4.2 Losses Analysis ** base case and G3 is out
Fig. (7) shows the losses level in the transmission and
sub transmission branches when compared with the Fig. (8) illustrates the curves for the active losses for
base case in the worst case, which is when G3 is out the distribution circuits in each case when the
operation. In this case, for the transmission system generators are out of operation.
the losses increase up to 261% for active power and Curves PLC21, PLC22, PLC23 and PLC24, represent
254% for reactive power. when the generators G1, G2, G3, y G4 are out
The impact in the sub transmission and distribution respectively. It is observed that for the distribuited
networks is minor when G3 is out, the total losses circuit (1) where DG is installed, there are no changes
increases by 2,7% and by 0,7% for active and in the losses level when the centralized generators are
reactive power respectively. out.

Fig. 8 Distribution losses increasing the


Fig. 7 Transmission and sub DG penetration when G3 is out of
transmission losses increasing the DG operation
penetration and with G3 out of operation
As explained before (Section 3.1. a.), the losses in the
Fig. (7) also shows the losses behavior when DGPL distribution circuit where DG is not installed present
is increased form zero up to 3,73%. This is done with a linear behavior. Whereas, the curve for the other
the objective of analyzing the DG impact in the worst distribution circuit presents a concave behavior, a
feature of the distribution systems where DG is operating reserve difference each electricity markets.
installed. In Fig. (8) the area under the curve PLC23 Normally, Spinning Reserve (also is known as
between 0 and GD3 represents the maximum losses primary reserves) is the use of generating equipment
reduction that the DG installation can obtain when that is online and synchronized to the grid such that
G3 is out. In Section 3.1. b. it was explained that the generating equipment can begin to increase output
GD3 represents the maximum DGPL where there are delivery immediately in response to changes to
no violations on the voltage limits, that means, this interconnection frequency, and be fully utilized
point represents the maximum penetration value and within seconds to <10 minutes to correct for
therefore the maximum operating reserves value. This generation/load imbalances caused by generation or
is the maximum operating reserves value that DG can transmission outages. Most on-line DG could perform
contribute without originating negative impacts on spinning reserve and respond in less than 10 seconds.
the system. This work shows a individual case, is Supplemental reserve (non-spinning also is known as
necessary to apply this methodoly for peak hours, low secundary and third reserves) differs from spinning
hours and for summer and winter period. reserve because supplemental does not need to
respond to an outage immediately. Traditional non-
spinning reserve needs to be available within 10
4.3 DG Technologies for providing operating minutes.
reserves
There are different technologies that can be used for Supply Demand Operating
Technologies following Reserves
DG applications (wind generation, photovoltaic, co-
generation, etc). Every technology presents a Natural Gas Turbine øøø øøø

different production profile, therefore, the load flows Micro-turbine øøø øøø
Steam Turbine øøø øøø
and losses impact depends on each technology.
Combined Cycle øøø øøø
Generally, the DG profile varies constantly. This
Electrochemical Devices øøø øøø
variation can be produced by the primary resource
Small hydro ▲▲▲ ▲
(wind, sun, water, etc) or due to the process features
Wind turbines ▲▲▲ ▲▲▲
(e.g. co-generation process).
Mini-Wind ▲▲▲ ▲▲▲
As the DG production profile is adapted to the
PhotoVoltaic ▲▲▲ ▲▲▲
demand profile of the buses where the DG is
PhotoThermal øø ▲
installed, the electric parameters will be better or
Fuel Cell øø ▲▲
worse. For instance, if the DG production in each bus
is exactly equal to the demand in each bus, the losses Table 4 DG technologies behaviors for
will be annulated since all the demand is supplied operating reserves supplying [17]
locally and there are no flows in the network. øøø: very good
Therefore, the GD more appropriate technologies for øø: good
supplying operating reserves are with constant ▲: normal
production profiles. ▲▲: bad
In this category can be classified the generators ▲▲▲: very bad
which supply almost constant power all the time
(higher utilization factor, generally classified from 0
up to 1, where 1 is the maximum value). In some
cases the DG production can be practically constant, 5 Conclusion
which is the case of combustible-cells, biomass plants Providing operating reserves by DG makes that the
and the gas micro-turbines. These technologies are large centralized generators reduces the schedule
well conditioned to the demand profile. In [7] was energy for delivering reserves. Therefore, these large
shown that the wind and photovoltaic generation are generators can have more available power for the
ill conditioned for the demand profile. Table 4 shows basic energy supplied to the system.
the technologies behavior related to the demand and By using DG, overvoltage levels can appear, mainly
the operating reserves delivery. in the distribution network and with less impact in the
sub transmission and transmission systems. An
As was explained earlier, the electricity markets in alternative for avoiding these overvoltages is
different countries are discriminated mainly in the increasing the DG penetration level with low power
methodologies or procedures in the operative reserve generators, it means with a greater DG dispersion.
management. In general, the maximum level of The DG contribution to the operating reserves
operating reserves and the time for the entry presents more advantages related with losses in sub
transmission and sub transmission systems, in the [10] C.W. Yu, X.S. Zhao, F.S. Wen, C.Y. Chung,
distribution systems the losses reduction is more T.S. Chung, M.X. Huang, Princing and
conservative since it depends on the technical system procurement of operating reserves in competitive
variables and can be manage with a major DG pool-based electricity markets, Electrical Power
dispersion. Systems Research, N° 73, 2005, pp. 37-43.
The DG impact on the system depends generally on [11] Kun-Yuan Huang, Yann-Chang Huang,
the production profile and how it is adaptable to the Integrating Direct Load Control With
demand profile. The DG technologies that can Interruptible Load Management to Provide
accomplish a better role in the operating reserves Instantaneous Reserves for Ancillary services,
delivery are those with a constant production profile IEEE Transactions on Power Systems, Vol. 19,
and also those that can begin to increase output No. 3, pp. 1626-1634, August 2004
delivery immediately in response to changes to [12] Power Systems, Test Case Archive,
interconnection frequency to correct for http://www.ee.washington.edu/research/pstca/pf3
generation/load imbalances caused by generation or 0/pg_tca30bus.htm
transmission outages. [13] Mesut E. Baran, Felix F. Wu, Optimal
Capacitor Placement On Radial Distribution
Systems, Copyright Material IEEE Transactions
References: on Power Delivery, Vol4, N°1, pp. 725-734.
[14] PSERC, Matpowe, A Matlab Power System
[1] L. Wang, C.W. Yu, F.S. Wen, Economic Theory Simulation Packege, V 3,
And The Aplication Of Incentive Contracts To www.pserc.edu/matpower/
Procure Operation Reserves”, Copyright [15] S. Conti, S. Raiti and G. Tina, Small-scale
Material Electric Power Systems Research, 2007, embedded generation effect on voltage profile: an
N°77, pp. 518-526. analytical method, IEE Proceedings Generation,
[2] Bayegan, M., A Vision of the Future Grid, IEEE Transmission and Distribution, Vol. 150, No. 1,
Power Engineering Review, Vol. 21, pp. 10-12, 2003, pp. 78-86.
December 2001. [16] C.L. Masters, Voltage rise, the big issue
[3] Fang Z, Editorial Special Issue on Distributed when connecting embedded generation to long 11
Power Generation, IEEE Transactions on Power kV overhead lines, Power Engineering Journal,
Electronics, V 19, N° 5, September 2004. February 2002, pp. 5-12
[4] Y. Xiaoyan, T. Leon, Ancillary Services Provided [17] V.H. Méndez, J. River, J.I. de la Fuente, T.
from DER with Power Electronics Interface, Gómez, J. Arceluz, J. Marín, Amadurga, Impac
IEEE Power Engineering Review, Vol. 21, of distributed generation on distribution
December 2006, pp. 10-12. investment deferral", Electrical Power and
[5] Pepermans G., Driesen J., Haeseldonckx D., Energy Systems, N° 28, 2006, pp. 244-252
Belmans R., D’haeseleer W., Distributed
generation: definition, benefits and issues,
Energy Policy, N° 33, 2005. Biographies
[6] S. Persaud, B. Fox and D. Flynn, Impact of Francisco D. Moya Ch received the P.E. in Electrical
Remotely Connected Wind Turbines on Steady Engineering from the National University of
State Operation of Radial Distribution Networks, Colombia and the M.S. in electrical Engineering
IEE Proceedings. Generation, Transmission and from University Los Andes, Colombia, in 2000 and
Distribution, Vol. 147, No. 3; pp. 157-163; 2000. 2005, respectively. He presently is a Ph.D. student in
[7] V.H. Méndez, J. River, J.I. de la Fuente, T. electrical engineering at UNICAMP (University of
Gómez, Assessment of Energy Distribution Campinas), Brazil. His main research interests are in
Losses for Increasing Penetration of Distributed power quality, distributed energy systems, energy
Generation, IEEE Transactions on Power efficiency and conservation, renewables, energy and
Electronics, V 21, N° 2, May 2006, pp. 533-540. environmental policy.
[8] T. Griffin, K. Tomsovic, D. Secrest and A. Law,
Placement of Dispersed Generations Systems for Duvier B. Bedoya areceived the P.E. in Electrical
Reduced Losses, 33rd Hawaii International Engineering with first class honours from the
Conference on System Sciences; 2000. National University of Colombia, Manizales,
[9] A. Naesh, M. Pukar, N. Mithulananthan, An Colombia, in 2004, the M.S. in Electrical Engineering
analytical approach for DG allocation in primary from UNICAMP (University of Campinas), in 2007,
distribution network, N° 28, 2006, pp. 669-678 where he is currently researcher. His main research
interests are in voltage stability, high voltaje and
embedded generation studies.

Gilberto de Martino Jannuzzi received Ph.D. degree


from Cambridge University, U.K. (Energy Research
Group, Cavendish Laboratory). He is an Associate
Professor of Energy Systems at the Department of
Energy, Mechanical Engineering Faculty, UNICAMP
(University of Campinas), He is Executive Director
of the International Energy Initiative , a Southern-
conceived, Southern-led and Southern-located South-
South-North partnership. My interests are related to
energy planning, with special emphasis on energy
efficiency and conservation, renewables, energy and
environmental policy, and technology transfer issues.

Luiz Carlos P. Silva received the B.S. degree in


Electrical Engineering from Goias Federal University
(UFG), Goiania, Brazil, in 1995, and the M.S. and
Ph.D. degrees from UNICAMP, in 1997 and 2001,
respectively. Currently, he is an Assistant Professor at
UNICAMP (University of Campinas), where he has
been with since 2002. His research interests include
dynamic and static voltage stability analysis and
generation distribution systems.

Anda mungkin juga menyukai