UTS Mo 2 No 5 Nur Salimah
UTS Mo 2 No 5 Nur Salimah
Nim : 181310327
Kelas : 01
Averagerequirement=totalexpeveteddemand
Bulan Demand Day Demand/day
Januari 1.500 20 75
Februari 1.500 19 79
Maret 1.400 22 64
April 1.700 21 81
Mei 1.700 22 86
Juni 2.000 21 95
10.000 125
Numberofproductionday
=10.000
125
=80 unit/hari
strategylevel
=1.480
workforcerequiredtoproduce80unitper/hari
workercost
inventorycarrying=1.480unitxRp.1.000
=Rp.1.480.000
Reguler-timerlabor=20workesxRp.20.000/harix125 hari
=Rp.50.000,000
TotalCost =Rp.51.480.000
- MixedStrategy
MinimumRequiment = 64 unit/
hariInhous production =64 unit/hari
=8000 unit
Subcontractunit =10.000 unit–8000unit
=2000 unit
64 unitX2 jam/unit =128jam/8 jam perworker
=16 workesperhari
Cost
Regulartime labor = 16 workerxRp20.000perday x125day
=Rp40.000.0000
Subcontracting =2000 unitx5000
=Rp10.000.000
TotalCost =Rp50.000.000
- ChaseStrategy
Month Fore cash Daily BasicProdu Thiring Layoffcost TotalCost
prodra ct Cost
te cost
Januari 1500 75 7.500.000 - - 7.500.000
Februari 1500 79 7.500.000 14x50.000 - 7.700.000
=200.000
Maret 1400 64 7.000.000 - 15x100.000 8.500.000
=1.500.000
April 1700 81 8.500.000 850.000 - 9.350.000
Mei 1900 86 9.500.000 250.000 - 9.750.000
Juni 2000 95 10.000.000 4.50.000 - 10.450.000
- 50.000.000 1.750.000 1.500.000 53.250.000
Alternatif strategi yang terbaik dengan menerikan biaya yang terendah adalah
menggunakanmixedstrategi denganmengeluarkantrotal biaya Rp50.000.000.