BQ Sumur Pantau+rmh Jenset
BQ Sumur Pantau+rmh Jenset
Halaman 1
VOLUME HARGA
NO. URAIAN PEKERJAAN
SATUAN VOLUME SATUAN (Rp) JUMLAH (Rp)
I. PEK. PERSIAPAN DAN MOB-DEMOBILISASI
1.1 Persiapan Peralatan Pengeboran dan Material Lokasi 24 869,000.00 20,856,000.00
1.2 Uji Potensi air Lokasi 24 5,417,500.00 130,020,000.00
Transportasi Peralatan Pengeboran, Material dan Personil
1.3 Paket 1 410,000,000.00 410,000,000.00
Halaman 2
VI. PERLENGKAPAN SARANA (spek. di isi dgn lengkap sesuai brosur)
6.1 Genset ….. KVA unit 24 78,523,500.00 1,884,564,000.00
- Merk : Highlander
- Model/Type : Silent
- Rated Output : 9.0 KVA
- Max Output : 10.5 KVA
- Celinder : 3 Buah
- Rated Rotation Speed : ......... rpm
- Starting System : electrict starter
- Cooling System : Water Coolled
- Voltage : 3 Pass (230-400 V)
- Bahan Bakar :Solar /Diesel
- Tool Kit : 1 Set
Aksesoris
- Elektroda : 3 Set
- Kabel Power : 130-140 m 4X2.5 mm NYYHY
- Kabel Elektroda : 130-140 M 3 X 1,5 mm NYYHY
- Kabel Sling Ø 5 mm : 130-140 M
- Panel Pompa : 3 Phasse Start Delta
- Switch Listrik PLN : Chint 2 P
dan Genset
6.3 Rumah Genset, Rumah Sumur Bor dan unit 24 81,655,400.00 1,959,729,600.00
Bak Penampungan Air
JUMLAH VI 4,596,333,600.00
VII. PENYUSUNAN LAPORAN Lokasi 24 850,000.00 20,400,000.00
JUMLAH VII 20,400,000.00
JUMLAH I s/d VII 9,922,996,800.00
PPN 10 % 992,299,680.00
JUMLAH KESELURUHAN 10,915,296,480.00
Terbilang : Sepuluh Milyar Sembilan Ratus Lima Lima Belas Juta Dua Ratus Sembilan Puluh Enam Ribu Empat Ratus Delapan
Puluh Rupiah
Kota, .....................
PT.
Direktur
DAFTAR KUANTITAS DAN HARGA
PEKERJAAN RUMAH GENSET, RUMAH SUMUR BOR, DAN BAK PENAMPUNG AIR
Kota, ................
PT.
Direktur
REKAPITULASI HARGA
PEKERJAAN RUMAH GENSET, RUMAH SUMUR BOR, DAN BAK PENAMPUNG AIR
Kota, ...............
PT.
0.00
Direktur
ANALISA HARGA SATUAN PEKERJAAN
Sub - Pekerjaan : Persiapan Peralatan Pengeboran dan Material 869,000.00
Nomor Urut Rab : 1.1
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Koefisien Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Driller hari 1.000 175,000.00 175,000.00 175,000.00
2 - Ass. Driller hari 1.000 150,000.00 150,000.00 150,000.00
3 - Operator hari 1.000 130,000.00 130,000.00 130,000.00
4 - Ass. Operator hari 1.000 100,000.00 100,000.00 100,000.00
5 - Welder hari 1.000 70,000.00 70,000.00 70,000.00
6 - Mekanik hari 1.000 85,000.00 85,000.00 85,000.00
7 - Helper hari 1.000 80,000.00 80,000.00 80,000.00
PERALATAN
1 - Peralatan Pengeboran ls 1.000 710,000.00 710,000.00 710,000.00
Jumlah Harga 790,000.00
Keuntungan max 10% 79,000.00
Jumlah 869,000.00
Dibulatkan 869,000.00
Sub - Pekerjaan : Pengadaan dan Pemasangan Screen Low Carbon dia. 6" 913,600.00
Nomor Urut Rab : 3.2
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Koefisien Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Driller hari 1.000 175,000.00 175,000.00 175,000.00
2 - Ass. Driller hari 1.000 150,000.00 150,000.00 150,000.00
3 - Operator hari 1.000 130,000.00 130,000.00 130,000.00
4 - Mekanik hari 1.000 85,000.00 85,000.00 85,000.00
5 - Helper hari 1.000 80,000.00 80,000.00 80,000.00
6 - Welder hari 1.000 70,000.00 70,000.00 70,000.00
BAHAN
1 - Screen Low Carbon dia 6" m1 21.000 678,500.00 14,248,500.0 14,248,500.00
2 - Besi Plat Strip m1 51.200 15,600.00 798,720.0 798,720.00
3 - Solar liter 55.000 9,250.00 508,750.00 508,750.00
4 - Oli Hidrolis liter 2.500 22,500.00 56,250.00 56,250.00
5 - Oli Mesin liter 1.000 22,500.00 22,500.00 22,500.00
6 - Stempet kg 0.500 14,000.00 7,000.00 7,000.00
PERALATAN
1 - Peralatan Pengeboran hari 1.000 710,000.00 710,000.00 710,000.00
2 - Peralatan Pengelasan hari 1.000 400,000.00 400,000.00 400,000.00
Jumlah Harga 17,441,720.00
Harga Sat. Bahan, Peralatan, dan Upah Pek. Screen Low Carbon dia. 6" / 21 meter 17,441,720.00
Kecepatan Pemasangan Pek. Screen Low Carbon dia. 6" Perhari / meter 21.00
Harga Sat. Bahan, Peralatan, dan Upah Pek. Sreen Low Carbon dia. 6" / 1 meter 830,558.10
Keuntungan Max 10% 83,055.81
Jumlah 913,613.90
Dibulatkan 913,600.00
Sub - Pekerjaan : Pengadaan dan Pemasangan Pipa Ukur MAT dia. 1" Pipa GIP
Nomor Urut Rab : 3.6
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Koefisien Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Driller hari 1.000 175,000.00 175,000.00 175,000.00
2 - Ass. Driller hari 1.000 150,000.00 150,000.00 150,000.00
3 - Operator hari 1.000 130,000.00 130,000.00 130,000.00
4 - Mekanik hari 1.000 85,000.00 85,000.00 85,000.00
5 - Helper hari 1.000 80,000.00 80,000.00 80,000.00
BAHAN
1 - Pipa GIP dia. 1" m1 90.000 93,500.00 8,415,000.00 8,415,000.00
2 - Soket Pipa GIP 1" bh 15.000 23,700.00 355,500.00 355,500.00
3 - Seal Tape roll 5.000 7,000.00 35,000.00 35,000.00
4 - Solar liter 35.000 9,250.00 323,750.00 323,750.00
5 - Oli Hidrolis liter 3.000 22,500.00 67,500.00 67,500.00
6 - Oli Mesin liter 1.000 22,500.00 22,500.00 22,500.00
7 - Stempet kg 0.500 14,000.00 7,000.00 7,000.00
PERALATAN
1 - Peralatan Pengeboran hari 1.000 710,000.00 710,000.00 710,000.00
Jumlah Harga 10,556,250.00
Harga Satuan Bahan, Peralatan, dan Upah Pek. Pipa Naik dia. 1" Pipa GIP / 90 meter 10,556,250.00
Kecepatan Pemasangan Pipa Naik dia. 1" Perhari / meter 90.00
Harga Satuan Bahan, Peralatan, dan Upah Pek. Pipa Naik dia. 1" Pipa GIP / 1 meter 117,291.67
Keuntungan Max 10% 11,729.17
Jumlah 129,020.83
Dibulatkan 129,000.00
Harga Satuan Bahan, Peralatan, dan Upah Pengadaan dan Pemasangan Genset 71,385,000.00
Keuntungan Max 10% 7,138,500.00
Jumlah 78,523,500.00
Dibulatkan 78,523,500.00
Harga Satuan Bahan, Peralatan, & Upah Pengadaan & Pemasangan Pompa Selam 31,335,000.00
Keuntungan Max 10% 3,133,500.00
Jumlah 31,335,000.00
Kota, ...........
PT.
Direktur
ANALISA HARGA SATUAN PEKERJAAN RUMAH GENSET, RUMAH SUMUR BOR, DAN BAK
PENAMPUNG AIR
Sub - Pekerjaan : 1 m1 Instalasi Inlet Pipa GIP dia. 1,5" Bak Air 2,529,400.00
Nomor Urut Rab : IV.3.1
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Ongkos pasang ls 1.000 100,000.00 100,000.00 100,000.00
BAHAN
1 - Pipa GIP dia. 1,5" m1 15.000 139,500.00 2,092,500.00 2,092,500.00
2 - L-Booh 1,5" bh 3.000 18,000.00 54,000.00 54,000.00
3 - Water Muur dia. 1,5" bh 1.000 20,700.00 20,700.00 20,700.00
4 - Sock Drat Luar dia. 1,5" bh 2.000 5,650.00 11,300.00 11,300.00
5 - Seal Tape bh 3.000 7,000.00 21,000.00 21,000.00
Jumlah Harga 2,299,500.00
Keuntungan max 10% 229,950.00
Jumlah 2,529,450.00
Dibulatkan 2,529,400.00
Sub - Pekerjaan : Pas. Pipa PVC jalur distribusi dia. 1" 459,500.00
Nomor Urut Rab : IV.3.3
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Ongkos pasang ls 1.000 100,000.00 100,000.00 100,000.00
BAHAN
1 - Pipa PVC dia.1" m1 8.000 21,500.00 172,000.00 172,000.00
2 - Lem Paralon tube 1.000 15,000.00 15,000.00 15,000.00
3 - Knie PVC dia. 1" bh 4.000 12,000.00 48,000.00 48,000.00
4 - T PVC dia.1" bh 1.000 6,000.00 6,000.00 6,000.00
5 - T PVC dia.1" ke 3/4" bh 6.000 7,000.00 42,000.00 42,000.00
6 - Sock Drat Dalam PVC dia. 1" bh 6.000 5,800.00 34,800.00 34,800.00
PERALATAN
Jumlah Harga 417,800.00
Keuntungan max 10% 41,780.00
Jumlah 459,580.00
Dibulatkan 459,500.00
Kota, ..............
PT.
Direktur
DAFTAR HARGA BAHAN
1 2 3 4
1 2 3 4
43 Bak Penampung 5000 liter Fibre Glass buah 6,500,000.00
44 Lem Paralon Tube 15,000.00
45 Seal Tape roll 7,000.00
46 Isolatif roll 6,000.00
47 Stop Kran 1" buah 46,000.00
48 Stop Kran 1,5" buah 90,000.00
49 Kran Tembok dia. 3/4" buah 17,000.00
50 Knie GIP dia. 1,5" buah 14,000.00
51 Knie PVC dia. 1" buah 12,000.00
52 L-Booh GIP dia. 1,5" buah 18,000.00
53 T GIP dia. 1,5" buah 19,000.00
54 T GIP dia. 1,5" ke 3/4 buah 21,500.00
55 T PVC dia. 1" buah 6,000.00
56 T PVC dia. 1" ke 3/4" buah 7,000.00
57 Check Valve buah 291,000.00
58 Socket Drat Dalam PVC dia. 3/4" buah 5,800.00
59 Sock Drat Dalam, PVC dia. 1" buah 5,000.00
60 Sock Drat Luar, PVC dia. 1" buah 5,000.00
61 Sock Drat Luar GIP dia. 1" buah 5,000.00
62 Sock Drat Dalam, GIP dia. 1,5" buah 5,600.00
63 Sock Drat Luar, GIP dia. 1,5" buah 5,650.00
64 Soket GIP dia 1,5" buah 28,750.00
65 Soket GIP dia 1" buah 23,700.00
66 Water Mur 1,5" buah 20,700.00
67 Manometer Pressure Gauge buah 49,500.00
68 Water Meter dia. 1,5" buah 840,000.00
69 Pipa PVC dia. 1" m1 21,500.00
70 Pipa GIP dia. 1" m1 93,500.00
71 Pipa GIP dia. 1,5" m1 139,500.00
72 Pipa GIP dia. 6" m1 397,500.00
73 Screen Low Carbon dia. 6" m1 678,500.00
74 Sling Baja 5 mm m1 80,000.00
75 Plate Top buah 145,000.00
76 Plate Bottom buah 145,000.00
77 Bentonit kg 17,000.00
78 Oli Mesin liter 22,500.00
79 Oli Hidrolis liter 22,500.00
80 Stempet kg 14,000.00
81 Solar liter 9,250.00
82 Bensin liter 7,800.00
83 Water Circulation unit 3,850,000.00
84 Air Lifting/Kompresor unit 4,750,000.00
85 Tinta Logging botol 230,200.00
86 Kertas Kerja Logging roll 143,900.00
87 Mesin Genset .... KVA unit 71,200,000.00
88 Pompa Selam 3 PK unit 15,200,000.00
89 Panel Pompa & Accessories unit 7,550,000.00
90 Klem Pipa 1,5" buah 10,200.00
91 Baut + Mur 12mm buah 17,200.00
92 Angker Besi Baut + Mur 16mm buah 40,500.00
NO URAIAN VULOME HARGA SATUAN (Rp)
1 2 3 4
Kota, ......
PT.
Direktur
DAFTAR HARGA UPAH DAN SEWA
HARGA UPAH
NO. URAIAN SATUAN
(Rp)
1 2 3 4
Kota, ...............
PT.
Direktur
TIME SCHEDULE
BULAN
Bobot Skala
NO. URAIAN PEKERJAAN HARGA (Rp) Pekerjaan BULAN KE 1 BULAN KE 2 BULAN KE 3 BULAN KE 4 BULAN KE 5 BULAN KE 6 BULAN KE 7 BULAN KE 8 Bobot Keterangan
(%) (%)
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
I. PEK.PERSIAPAN & MOB - DEMOBILISASI
1.1 Persiapan Peralatan Pengeboran dan Material 20,856,000.00 0.210 0.063 0.063 0.042 0.042 100
1.2 Uji Potensi air 130,020,000.00 1.310 0.393 0.393 0.262 0.262
1.3 Transportasi Peralatan Pengeboran dan Material 410,000,000.00 4.132 0.826 0.826 0.826 0.413 0.413 0.413 0.413
1.4 Site Clearing 20,856,000.00 0.210 0.070 0.070 0.070
1.5 Spoel Bak 89,364,000.00 0.901 0.270 0.270 0.180 0.180
1.6 Rig Set-Up 45,936,000.00 0.463 0.154 0.154 0.154
1.7 Papan Nama Proyek 12,000,000.00 0.121 0.040 0.040 0.040
1.7 Biaya K3 dan Keselamatan Konstruksi 76,000,000.00 0.766 0.230 0.230 0.153 0.153
II. PENGEBORAN -
2.1 Pilot Hole dia. 6" : 1,186,800,000.00 11.960 1.196 1.196 1.196 1.196 1.196 1.196 0.797 0.797 0.797 0.797 0.797 0.797 75
2.2 Geophysical Well Logging + Interpretasi -
2.2.1 Resistivity Log : -
- Short Normal Log 30,720,000.00 0.310 0.103 0.103 0.103
- Long Normal Log 30,720,000.00 0.310 0.103 0.103 0.103
2.2.2 Self Potential Log 30,720,000.00 0.310 0.103 0.103 0.103
2.3 Reaming Hole dia. 12" 859,680,000.00 8.664 1.444 1.444 1.444 1.083 1.083 1.083 1.083
III. KONSTRUKSI SUMUR -
3.1 Pipa Jambang dia. 6", GIP, 960,187,200.00 Jangka Waktu
9.676 1.451 1.451 1.451 1.451 0.645 0.645 0.645 0.645 0.645 0.645
Pelaksanaan
3.2 Screen Low Carbon dia. 6" 394,675,200.00 3.977 0.795 0.795 0.795 0.795 0.795 50 240 (Dua Ratus
Empat Puluh)
3.3 Gravel Pack 29,436,000.00 0.297 0.099 0.099 0.099 hari kalender
3.4 Cement Grouting 73,123,200.00 0.737 0.184 0.184 0.184 0.184
3.5 Pipa Naik dia. 1,5", GIP 311,904,000.00 3.143 0.524 0.524 0.524 0.524 0.524 0.524
3.6 Pipa Ukur MAT dia. 1" GIP 222,912,000.00 2.246 0.562 0.562 0.562 0.562
IV. PEMBERSIHAN SUMUR -
4.1 Water Circulation 92,400,000.00 0.931 0.233 0.233 0.233 0.233
4.2 Air Lifting/Kompresor 114,000,000.00 1.149 0.230 0.230 0.230 0.230 0.230
V. UJI PEMOMPAAN -
5.1 Uji Pemompaan 149,553,600.00 1.507 0.377 0.377 0.377 0.377 25
5.2 Analisa Air Tanah 14,400,000.00 0.145 0.048 0.048 0.048
VI. PERLENGKAPAN SARANA -
6.1 Genset Mesin Genset ... KVA 1,884,564,000.00 18.992 2.216 2.216 2.216 2.216 2.216 2.216 1.424 1.424 1.424 1.424
6.2 Pompa Selam 3 PK 752,040,000.00 7.579 1.516 1.516 1.516 1.516 1.516
Beserta Panel & Accessories -
6.3 Rumah Genset, Rumah Sumur Bor, dan 1,959,729,600.00 19.749 1.975 1.975 1.975 1.975 1.975 1.975 1.975 1.975 1.975 1.975
Bak Penampungan Air
-
VII. PENYUSUNAN LAPORAN 20,400,000.00 0.206 0.103 0.103 0
RENCANA BOBOT PERMINGGU (%) 0.103 1.512 1.449 2.363 3.595 4.790 4.893 8.346 6.307 5.111 4.695 5.208 3.949 1.315 1.085 0.901 0.880 0.869 1.305 2.087 3.321 4.331 5.130 2.400 2.430 1.273 2.190 3.321 7.528 5.130 2.078 0.103
KUMULATIF RENCANA BOBOT PERMINGGU (%) - 0.103 1.616 3.065 5.427 9.023 13.813 18.706 27.052 33.359 38.470 43.166 48.374 52.323 53.638 54.724 55.625 56.505 57.374 58.679 60.765 64.086 68.417 73.547 75.947 78.377 79.651 81.840 85.161 92.690 97.819 99.897 100.000
Kota, ...............
PT.
0.00
Direktur
JADWAL PELAKSANAAN
BULAN I BULAN II BULAN III BULAN IV BULAN V BULAN VI BULAN VII BULAN VIII
NO. URAIAN PEKERJAAN KETERANGAN
MG-1 MG-2 MG-3 MG-4 MG-1 MG-2 MG-3 MG-4 MG-1 MG-2 MG-3 MG-4 MG-1 MG-2 MG-3 MG-4 MG-1 MG-2 MG-3 MG-4 MG-1 MG-2 MG-3 MG-4 MG-1 MG-2 MG-3 MG-4 MG-1 MG-2 MG-3 MG-4
II. PENGEBORAN
V. UJI PEMOMPAAN
Kota, ...............
PT.
Direktur