Anda di halaman 1dari 32

DAFTAR KUANTITAS DAN HARGA

Halaman 1
VOLUME HARGA
NO. URAIAN PEKERJAAN
SATUAN VOLUME SATUAN (Rp) JUMLAH (Rp)
I. PEK. PERSIAPAN DAN MOB-DEMOBILISASI
1.1 Persiapan Peralatan Pengeboran dan Material Lokasi 24 869,000.00 20,856,000.00
1.2 Uji Potensi air Lokasi 24 5,417,500.00 130,020,000.00
Transportasi Peralatan Pengeboran, Material dan Personil
1.3 Paket 1 410,000,000.00 410,000,000.00

1.4 Site Clearing Lokasi 24 869,000.00 20,856,000.00


1.5 Spoel Bak Lokasi 24 3,723,500.00 89,364,000.00
1.6 Rig Set-Up Lokasi 24 1,914,000.00 45,936,000.00
1.7 Papan Nama Proyek Lokasi 24 500,000.00 12,000,000.00
1.8 Biaya K3 dan Keselamatan Konstruksi Paket 1 76,000,000.00 76,000,000.00
JUMLAH I 805,032,000.00
II. PENGEBORAN
2.1 Pilot Hole dia. 6" : m' 2400 494,500.00 1,186,800,000.00
Jumlah 2.1. 1,186,800,000.00
2.2 Geophysical Well Logging + Interpretasi
2.2.1 Resistivity Log :
- Short Normal Log m' 2400 12,800.00 30,720,000.00
- Long Normal Log m' 2400 12,800.00 30,720,000.00
2.2.2 Self Potential Log m' 2400 12,800.00 30,720,000.00
Jumlah 2.2. 92,160,000.00
2.3 Reaming dia. 12" : m' 2400 358,200.00 859,680,000.00
Jumlah 2.3. 859,680,000.00
JUMLAH II 2,138,640,000.00
III. KONSTRUKSI SUMUR
3.1 Pipa Jambang dia. 6", GIP, m' 1968 487,900.00 960,187,200.00
3.2 Screen Low Carbon dia. 6" m' 432 913,600.00 394,675,200.00
3.3 Gravel Pack m3 60 490,600.00 29,436,000.00
3.4 Cement Grouting m3 72 1,015,600.00 73,123,200.00
3.5 Pipa Naik dia. 1,5", GIP m' 1728 180,500.00 311,904,000.00
3.6 Pipa Ukur MAT dia. 1" GIP m' 1728 129,000.00 222,912,000.00
JUMLAH III 1,992,237,600.00
IV. PEMBERSIHAN SUMUR
4.1 Water Circulation Lokasi 24 3,850,000.00 92,400,000.00
4.2 Air Lifting/Kompresor Lokasi 24 4,750,000.00 114,000,000.00
JUMLAH IV 206,400,000.00
V. UJI PEMOMPAAN
5.1 Uji Pemompaan Lokasi 24 6,231,400.00 149,553,600.00
5.2 Analisa Air Tanah Lokasi 24 600,000.00 14,400,000.00
JUMLAH V 163,953,600.00

Halaman 2
VI. PERLENGKAPAN SARANA (spek. di isi dgn lengkap sesuai brosur)
6.1 Genset ….. KVA unit 24 78,523,500.00 1,884,564,000.00
- Merk : Highlander
- Model/Type : Silent
- Rated Output : 9.0 KVA
- Max Output : 10.5 KVA
- Celinder : 3 Buah
- Rated Rotation Speed : ......... rpm
- Starting System : electrict starter
- Cooling System : Water Coolled
- Voltage : 3 Pass (230-400 V)
- Bahan Bakar :Solar /Diesel
- Tool Kit : 1 Set

6.2 Pompa Selam 3 PK + Aksesoris unit 24 31,335,000.00 752,040,000.00


- Merk : FRANKLIN
- Model/Type : 4GS22
- Total Head : 120 Meter
- Voltage : 3 Phasee 380 Volt

Aksesoris
- Elektroda : 3 Set
- Kabel Power : 130-140 m 4X2.5 mm NYYHY
- Kabel Elektroda : 130-140 M 3 X 1,5 mm NYYHY
- Kabel Sling Ø 5 mm : 130-140 M
- Panel Pompa : 3 Phasse Start Delta
- Switch Listrik PLN : Chint 2 P
dan Genset

6.3 Rumah Genset, Rumah Sumur Bor dan unit 24 81,655,400.00 1,959,729,600.00
Bak Penampungan Air
JUMLAH VI 4,596,333,600.00
VII. PENYUSUNAN LAPORAN Lokasi 24 850,000.00 20,400,000.00
JUMLAH VII 20,400,000.00
JUMLAH I s/d VII 9,922,996,800.00
PPN 10 % 992,299,680.00
JUMLAH KESELURUHAN 10,915,296,480.00
Terbilang : Sepuluh Milyar Sembilan Ratus Lima Lima Belas Juta Dua Ratus Sembilan Puluh Enam Ribu Empat Ratus Delapan
Puluh Rupiah

Kota, .....................
PT.

Direktur
DAFTAR KUANTITAS DAN HARGA
PEKERJAAN RUMAH GENSET, RUMAH SUMUR BOR, DAN BAK PENAMPUNG AIR

Harga Jumlah Total


No. Uraian Pekerjaan Volume
Satuan (Rp.) Jumlah (Rp.) (Rp.)
I PEKERJAAN PERSIAPAN
I.1 Pembersihan Lahan 1.000 ls 250,000.00 250,000.00
I.2 Pengukuran / Pasangan Bouwplank 26.000 m1 84,800.00 2,204,800.00
I.3 Administrasi dan Dokumentasi 1.000 ls 300,000.00 300,000.00
Sub Jumlah I 2,754,800.00
II PEMBUATAN RUMAH GENSET
II.1 PEKERJAAN GALIAN DAN URUGAN
II.1.1. Galian Tanah Untuk Pondasi dan Saluran 10.275 m3 78,400.00 805,560.00
II.1.2. Urugan Kembali Bekas Galian. Padat 4.780 m3 20,000.00 95,600.00
II.1.3. Urugan Pasir Dibawah Pondasi 0.940 m3 278,800.00 262,072.00
II.1 1,163,232.00
II.2 PEKERJAAN PONDASI / BETON
II.2.1 Pas. Aanstamping Batu Belah 1.200 m3 342,300.00 410,760.00
II.2.2 Pas. Pondasi Batu kali 2.925 m3 681,000.00 1,991,925.00
II.2.3 Sloof Beton Struktur 0.375 m3 6,433,500.00 2,412,562.50
II.2.4 Kolom Struktur 0.270 m3 5,924,600.00 1,599,642.00
II.2.5 Ring Balk Praktis 0.330 m3 6,383,800.00 2,106,654.00
II.2.6 Plat Lantai Beton Dudukan Mesin 0.786 m3 1,558,800.00 1,225,216.80
II.2.7 Pas. Lantai Kerja 0.300 m3 1,033,100.00 309,930.00
II.2 10,056,690.30
II.3 PEK.DINDING / PLESTERAN / PELAPISAN
II.3.1 Pas. Bata Merah ad. 1PC:3PS 25.000 m2 192,900.00 4,822,500.00
II.3.2 Plesteran ad. 1PC:3PS 50.000 m2 74,700.00 3,735,000.00
II.3.3 Pek. Acian 50.000 m2 69,000.00 3,450,000.00
II.3.4 Pek. Lubang Knalpot dia. 4" 1.000 ls 800,000.00 800,000.00
II.3 12,807,500.00
II.4 PEK. KUSEN DAN PINTU
II.4.1 Pas. Kusen Pintu Panel 0.050 m3 4,457,300.00 220,636.35
II.4.2 Pas. Daun Pintu Panel 2.000 bh 702,400.00 1,404,800.00
II.4.3 Pas. Rooster 2.000 bh 183,700.00 367,400.00
II.4.4 Angker-angker Kusen 10.000 bh 126,500.00 1,265,000.00
II.4.5 Dook & Neut Kusen Pintu 2.000 bh 87,800.00 175,600.00
II.4 3,433,436.35
II.5 PEK. KUNCI DAN PENGGANTUNG
II.5.1 Pas. Kunci Pintu Ganda 1.000 bh 160,800.00 160,800.00
II.5.2 Pas. Sloot Pintu Atas Bawah 2.000 bh 94,100.00 188,200.00
II.5.3 Pas. Engsel Pintu 4.000 bh 47,000.00 188,000.00
II.5 537,000.00
II.6 PEKERJAAN ATAP
II.6.1 Pas. Gording 6/12 0.180 m3 4,096,500.00 737,370.00
II.6.2 Pas. Atap Asbes Gelombang 22.500 m2 98,700.00 2,220,750.00
II.6.3 Pas. Listplank 3/20 24.500 m1 64,700.00 1,585,150.00
II.6 4,543,270.00
II.7 PEKERJAAN LANTAI DAN RABAT
II.7.1 Pek. Plesteran Lantai 6.000 m2 74,700.00 448,200.00
II.7.2 Pek. Acian Plesteran Lantai 6.000 m2 69,000.00 414,000.00
II.7.3 Pek. Pas. Lantai keramik 2.400 m2 197,900.00 474,960.00
II.7 1,337,160.00
II.8 PEKERJAAN PENGECATAN
II.8.1 Finishing Cat Tembok 50.000 m2 69,200.00 3,460,000.00
II.8.2 Finishing Cat Kayu 17.670 m2 72,200.00 1,275,774.00
II.8 4,735,774.00
II.9 PEKERJAAN SALURAN
II.9.1 Saluran Drainase 3.000 m1 302,700.00 908,100.00
II.9 908,100.00
Total Sub Jumlah II 39,522,162.65
Dibulatkan 39,522,100.00
Harga Jumlah Total
No. Uraian Pekerjaan Volume
Satuan (Rp.) Jumlah (Rp.) (Rp.)
III PEMBUATAN RUMAH SUMUR BOR
III.1 PEKERJAAN GALIAN DAN URUGAN
III.1.1 Galian Tanah Untuk Pondasi Rolag Bata 1.080 m3 78,400.00 84,672.00
III.1.2 Urugan Kembali Bekas Galian. Padat 0.612 m3 20,000.00 12,240.00
III.1.3 Urugan Pasir Dibawah Pondasi 0.716 m3 278,800.00 199,620.80
III.1 296,532.80
III.2 PEK.DINDING / PLESTERAN / PELAPISAN
III.2.1 Pas. Bata Merah Pondasi Rolag 0.641 m3 319,400.00 204,735.40
III.2.2 Pas. Bata Merah 1/2 ad. 1PC:3PS 4.210 m 2
192,900.00 812,109.00
III.2.3 Plesteran ad. 1PC:3PS 8.420 m2 74,700.00 628,974.00
III.2.4 Pek. Acian 8.420 m2 69,000.00 580,980.00
III.2 2,226,798.40
III.3 PEK. PENUTUP RUMAH SUMUR BOR
III.3.1 Pas. Penutup Besi 1.000 ls 1,318,600.00 1,318,600.00
III.3.2 Pas. Kunci Gembok 1.000 bh 24,000.00 24,000.00
III.3 1,342,600.00
III.4 PEKERJAAN LANTAI DAN RABAT
III.4.1 Pek. Plesteran Lantai 1.400 m2 74,700.00 104,580.00
III.4.2 Pek. Acian Plesteran Lantai 1.400 m2 69,000.00 96,600.00
III.4.3 Pek. Lantai Beton Tumbuk 0.152 m3 1,033,100.00 157,031.20
III.4 358,211.20
III.5 PEKERJAAN PENGECATAN
III.5.1 Finishing Cat Tembok 9.240 m2 69,200.00 639,408.00
III.5.2 Finishing Cat Besi 3.124 m2 68,000.00 212,432.00
III.5 851,840.00
III.6 ACCESSORIES INSTALASI RUMAH SUMUR BOR
III.6.1 Plate Top dan Plate Bottom 1.000 ps 504,600.00 504,600.00
III.6.2 Klem Pipa 1,5" 2.000 bh 208,100.00 416,200.00
III.6.3 L-Booh dia 1,5" 3.000 bh 137,500.00 412,500.00
III.6.4 Water Muur 2.000 bh 152,900.00 305,800.00
III.6.5 Manometer Pressure Gauge 1.000 bh 208,200.00 208,200.00
III.6.6 Check Valve 1.000 bh 450,200.00 450,200.00
III.6.7 Stop Kran dia 1,5" 1.000 bh 229,100.00 229,100.00
III.6.8 Water Meter dia 1,5" 1.000 bh 1,054,100.00 1,054,100.00
III.6 3,580,700.00
Total Sub Jumlah III 8,656,682.40
Dibulatkan 8,656,600.00
IV PEMBUATAN BAK PENAMPUNGAN AIR
IV.1 PEKERJAAN GALIAN DAN URUGAN
IV.1.1 Galian Tanah Untuk Pas. Batu Kali 5.605 m3 78,400.00 439,432.00
IV.1.2 Buangan Tanah Bekas Galian 5.605 m3 39,300.00 220,276.50
IV.1.3 Urugan Pasir Dibawah Pondasi 0.560 m3 278,800.00 156,128.00
IV.1 815,836.50
IV.2 PEKERJAAN PONDASI / BETON
IV.2.1 Pek. Aanstamping Batu Belah 1.619 m3 342,300.00 554,183.70
IV.2.2 Pek. Pondasi Batu Kali 8.214 m3 681,000.00 5,593,734.00
IV.2.3 Pek. Plat lantai Beton 1.200 m3 1,558,800.00 1,870,560.00
IV.2.4 Pek. Pas. Lantai Keramik 5.220 m2 197,900.00 1,033,038.00
IV.2.5 Pek. Pas. Dinding Keramik 5.670 m2 197,900.00 1,122,093.00
IV.2.6 Pek. Rabat Beton Tumbuk 1.055 m3 1,033,100.00 1,089,662.23
IV.2.7 Pek. Plesteran Dinding 17.490 m2 74,700.00 1,306,503.00
IV.2.8 Pek. Acian 17.490 m2 69,000.00 1,206,810.00
IV.2 13,776,583.93
IV.3 PEKERJAAN PENGADAAN DAN INSTALASI AIR
IV.3.1 Pas. Instalasi Inlet Pipa GIP dia. 1,5" 1.000 ls 2,529,400.00 2,529,400.00
IV.3.2 Pas. Bak Penampungan Air 5200 liter Fibre Glass 1.000 bh 7,260,000.00 7,260,000.00
IV.3.3 Pas. Instalasi Out-Let Pipa PVC dia. 3/4" 1.000 ls 459,500.00 459,500.00
IV.3.4 Pas. Stop Kran dia. 1" Jalur Distribusi 1.000 unit 179,300.00 179,300.00
IV.3.5 Pas. Stop Kran dia. 1" Jalur Pembuangan 1.000 unit 179,300.00 179,300.00
IV.3.6 Pas. Kran Air Bersih dia. 3/4" 6.000 unit 137,000.00 822,000.00
IV.3 11,429,500.00
IV.4 PEKERJAAN PEMBERSIHAN LAHAN
IV.4.1 BEKAS PEKERJAAN 1.000 ls 1,200,000.00 1,200,000.00
IV.4 1,200,000.00
IV.5 PEKERJAAN PEMASANGAN LOGO DI TORN
IV.5.1 Pekerjaan Pemasangan Signage Logo 1.000 ls 3,500,000.00 3,500,000.00
IV.5 3,500,000.00
Total Sub Jumlah IV 30,721,920.43
Dibulatkan 30,721,900.00

Kota, ................
PT.

Direktur
REKAPITULASI HARGA
PEKERJAAN RUMAH GENSET, RUMAH SUMUR BOR, DAN BAK PENAMPUNG AIR

NO. URAIAN PEKERJAAN JUMLAH HARGA

I PEKERJAAN PERSIAPAN Rp 2,754,800.00

II PEMBUATAN RUMAH GENSET Rp 39,522,100.00

III PEMBUATAN RUMAH SUMUR BOR Rp 8,656,600.00

IV PEMBUATAN BAK PENAMPUNGAN AIR Rp 30,721,900.00

JUMLAH ( I s.d IV ) Rp 81,655,400.00

Kota, ...............
PT.

0.00
Direktur
ANALISA HARGA SATUAN PEKERJAAN
Sub - Pekerjaan : Persiapan Peralatan Pengeboran dan Material 869,000.00
Nomor Urut Rab : 1.1
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Koefisien Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Driller hari 1.000 175,000.00 175,000.00 175,000.00
2 - Ass. Driller hari 1.000 150,000.00 150,000.00 150,000.00
3 - Operator hari 1.000 130,000.00 130,000.00 130,000.00
4 - Ass. Operator hari 1.000 100,000.00 100,000.00 100,000.00
5 - Welder hari 1.000 70,000.00 70,000.00 70,000.00
6 - Mekanik hari 1.000 85,000.00 85,000.00 85,000.00
7 - Helper hari 1.000 80,000.00 80,000.00 80,000.00
PERALATAN
1 - Peralatan Pengeboran ls 1.000 710,000.00 710,000.00 710,000.00
Jumlah Harga 790,000.00
Keuntungan max 10% 79,000.00
Jumlah 869,000.00
Dibulatkan 869,000.00

Sub - Pekerjaan : Uji Potensi Air 5,417,500.00


Nomor Urut Rab : 1.2
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Koefisien Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Ahli Geofisika hari 1.000 200,000.00 200,000.00 200,000.00
2 - Ass. Ahli Geofisika hari 1.000 175,000.00 175,000.00 175,000.00
3 - Helper 1 hari 1.000 80,000.00 80,000.00 80,000.00
4 - Helper 2 hari 1.000 80,000.00 80,000.00 80,000.00
BAHAN
1 - Alat Tulis ls 1.000 - - -
PERALATAN
1 - Peralatan uji potensi air ls 1.000 450,000.00 450,000.00 450,000.00
Jumlah Harga 985,000.00
Harga Satuan Bahan, Peralatan, dan Upah Pekerjaan Uji Potensi Air / hari 985,000.00
Jumlah titik 5.00
Harga Uji Potensi Air perlokasi 4,925,000.00
Keuntungan Max 10% 492,500.00
Jumlah 5,417,500.00
Dibulatkan 5,417,500.00

Sub - Pekerjaan : Site Clearing 1,144,000.00


Nomor Urut Rab : 1.4
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Koefisien Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Driller hari 2.000 175,000.00 350,000.00 350,000.00
2 - Welder hari 2.000 70,000.00 140,000.00 140,000.00
3 - Mandor hari 2.000 150,000.00 300,000.00 300,000.00
4 - Pekerja hari 2.000 80,000.00 160,000.00 160,000.00
5 - Tool Fusher hari 2.000 45,000.00 90,000.00 90,000.00
Jumlah Harga 1,040,000.00
Keuntungan max 10% 104,000.00
Jumlah 1,144,000.00
Dibulatkan 1,144,000.00

Sub - Pekerjaan : Spoel Bak 3,723,500.00


Nomor Urut Rab : 1.5
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Koefisien Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Driller hari 2.000 175,000.00 350,000.00 350,000.00
2 - Tukang hari 2.000 100,000.00 200,000.00 200,000.00
3 - Kepala Tukang hari 2.000 150,000.00 300,000.00 300,000.00
4 - Mandor hari 2.000 150,000.00 300,000.00 300,000.00
5 - Pekerja hari 2.000 80,000.00 160,000.00 160,000.00
BAHAN
1 - Pasir Pasang m3 4.000 200,000.00 800,000.00 800,000.00
2 - Semen PC @ 50 kg zak 15.000 85,000.00 1,275,000.00 1,275,000.00
Jumlah Harga 3,385,000.00
Keuntungan max 10% 338,500.00
Jumlah 3,723,500.00
Dibulatkan 3,723,500.00
Sub - Pekerjaan : Rig Set - Up 1,914,000.00
Nomor Urut Rab : 1.6
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Koefisien Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Driller hari 3.000 175,000.00 525,000.00 525,000.00
2 - Ass. Driller hari 3.000 150,000.00 450,000.00 450,000.00
3 - Operator hari 3.000 130,000.00 390,000.00 390,000.00
4 - Helper hari 3.000 80,000.00 240,000.00 240,000.00
5 - Tool Fusher hari 3.000 45,000.00 135,000.00 135,000.00
Jumlah Harga 1,740,000.00
Keuntungan max 10% 174,000.00
Jumlah 1,914,000.00
Dibulatkan 1,914,000.00

Sub - Pekerjaan : Pilot Hole dia. 6" 494,500.00


Nomor Urut Rab : 2.1
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Koefisien Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Driller hari 1.000 175,000.00 175,000.00 175,000.00
2 - Ass. Driller hari 1.000 150,000.00 150,000.00 150,000.00
3 - Operator hari 1.000 130,000.00 130,000.00 130,000.00
4 - Helper hari 1.000 80,000.00 80,000.00 80,000.00
BAHAN
1 - Solar liter 65.000 9,250.00 601,250.00 601,250.00
2 - Oli Hidrolis liter 5.000 22,500.00 112,500.00 112,500.00
3 - Oli Mesin liter 2.000 22,500.00 45,000.00 45,000.00
4 - Stempet kg 1.000 14,000.00 14,000.00 14,000.00
5 - Bentonit kg 40.000 17,000.00 680,000.00 680,000.00
PERALATAN
1 - Peralatan Pengeboran hari 1.000 710,000.00 710,000.00 710,000.00
Harga Satuan Bahan, Peralatan, dan Upah Pekerjaan Pilot Hole / hari 2,697,750.00
Kecepatan Pengeboran Perhari (meter) 6.00
Harga Satuan Bahan, Peralatan, dan Upah Pekerjaan Pilot Hole / meter 449,625.00
Keuntungan Max 10% 44,962.50
Jumlah 494,587.50
Dibulatkan 494,500.00

Sub - Pekerjaan : Geophysical Well Logging + Interpretasi 12,800.00


Nomor Urut Rab : 2.2 ( 2.2.1, 2.2.2)
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Koefisien Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Ahli Geofisika hari 2.000 200,000.00 400,000.00 400,000.00
2 - Ass. Ahli Geofisika hari 2.000 175,000.00 350,000.00 350,000.00
BAHAN
3 - Kertas Logging roll 1.000 143,900.00 143,900.00 143,900.00
4 - Tinta Logging botol 0.500 230,200.00 115,100.00 115,100.00
PERALATAN
5 - Peralatan Logging ls 1.000 450,000.00 450,000.00 450,000.00
Jumlah Harga 1,459,000.00
Harga Satuan Bahan, Peralatan, dan Upah Pekerjaan Geophysical Well Logging / hari 1,459,000.00
Kecepatan Geophysical Well Logging (meter) 125.00
Harga Satuan Bahan, Peralatan, dan Upah Pekerjaan Geophysical Well Logging / meter 11,672.00
Keuntungan Max 10% 1,167.20
Jumlah 12,839.20
Dibulatkan 12,800.00

Sub - Pekerjaan : Reaming Hole dia. 12" 358,200.00


Nomor Urut Rab : 2.3
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Koefisien Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Driller hari 1.000 175,000.00 175,000.00 175,000.00
2 - Ass. Driller hari 1.000 150,000.00 150,000.00 150,000.00
3 - Operator hari 1.000 130,000.00 130,000.00 130,000.00
4 - Helper hari 1.000 80,000.00 80,000.00 80,000.00
BAHAN
1 - Solar liter 55.000 9,250.00 508,750.00 508,750.00
2 - Oli Hidrolis liter 5.000 22,500.00 112,500.00 112,500.00
3 - Oli Mesin liter 2.000 22,500.00 45,000.00 45,000.00
4 - Stempet kg 1.000 14,000.00 14,000.00 14,000.00
5 - Bentonit kg 40.000 17,000.00 680,000.00 680,000.00
PERALATAN
6 - Peralatan Pengeboran hari 1.000 710,000.00 710,000.00 710,000.00
Jumlah Harga 2,605,250.00
Harga Satuan Bahan, Peralatan, dan Upah Pekerjaan Reaming Hole / hari 2,605,250.00
Kecepatan Reaming Hole Perhari / meter 8.00
Harga Satuan Bahan, Peralatan, dan Upah Pekerjaan Reaming Hole / meter 325,656.25
Keuntungan Max 10% 32,565.63
Jumlah 358,221.88
Dibulatkan 358,200.00
Sub - Pekerjaan : Pengadaan dan Pemasangan Pipa Jambang dia. 6" Pipa GIP 487,900.00
Nomor Urut Rab : 3.1
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Koefisien Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Driller hari 2.000 175,000.00 350,000.00 350,000.00
2 - Ass. Driller hari 2.000 150,000.00 300,000.00 300,000.00
3 - Operator hari 2.000 130,000.00 260,000.00 260,000.00
4 - Mekanik hari 2.000 85,000.00 170,000.00 170,000.00
5 - Helper hari 2.000 80,000.00 160,000.00 160,000.00
6 - Welder hari 2.000 70,000.00 140,000.00 140,000.00
BAHAN
1 - Pipa GIP dia. 6" m1 104.000 397,500.00 41,340,000.00 41,340,000.00
2 - Solar liter 110.000 9,250.00 1,017,500.00 1,017,500.00
3 - Oli Hidrolis liter 5.000 22,500.00 112,500.00 112,500.00
4 - Oli Mesin liter 2.000 22,500.00 45,000.00 45,000.00
5 - Stempet kg 1.000 14,000.00 14,000.00 14,000.00
PERALATAN
1 - Peralatan Pengeboran hari 2.000 710,000.00 1,420,000.00 1,420,000.00
2 - Peralatan Pengelasan hari 2.000 400,000.00 800,000.00 800,000.00
Jumlah Harga 46,129,000.00
Harga Satuan Bahan, Peralatan, dan Upah Pek. Jambang dia. 6" Pipa GIP / 104 meter 46,129,000.00
Kecepatan Pemasangan Pipa Jambang 6" Perhari / meter 104.00
Harga Satuan Bahan, Peralatan, dan Upah Pek. Jambang dia. 6" Pipa GIP / 1 meter 443,548.08
Keuntungan Max 10% 44,354.81
Jumlah 487,902.88
Dibulatkan 487,900.00

Sub - Pekerjaan : Pengadaan dan Pemasangan Screen Low Carbon dia. 6" 913,600.00
Nomor Urut Rab : 3.2
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Koefisien Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Driller hari 1.000 175,000.00 175,000.00 175,000.00
2 - Ass. Driller hari 1.000 150,000.00 150,000.00 150,000.00
3 - Operator hari 1.000 130,000.00 130,000.00 130,000.00
4 - Mekanik hari 1.000 85,000.00 85,000.00 85,000.00
5 - Helper hari 1.000 80,000.00 80,000.00 80,000.00
6 - Welder hari 1.000 70,000.00 70,000.00 70,000.00
BAHAN
1 - Screen Low Carbon dia 6" m1 21.000 678,500.00 14,248,500.0 14,248,500.00
2 - Besi Plat Strip m1 51.200 15,600.00 798,720.0 798,720.00
3 - Solar liter 55.000 9,250.00 508,750.00 508,750.00
4 - Oli Hidrolis liter 2.500 22,500.00 56,250.00 56,250.00
5 - Oli Mesin liter 1.000 22,500.00 22,500.00 22,500.00
6 - Stempet kg 0.500 14,000.00 7,000.00 7,000.00
PERALATAN
1 - Peralatan Pengeboran hari 1.000 710,000.00 710,000.00 710,000.00
2 - Peralatan Pengelasan hari 1.000 400,000.00 400,000.00 400,000.00
Jumlah Harga 17,441,720.00
Harga Sat. Bahan, Peralatan, dan Upah Pek. Screen Low Carbon dia. 6" / 21 meter 17,441,720.00
Kecepatan Pemasangan Pek. Screen Low Carbon dia. 6" Perhari / meter 21.00
Harga Sat. Bahan, Peralatan, dan Upah Pek. Sreen Low Carbon dia. 6" / 1 meter 830,558.10
Keuntungan Max 10% 83,055.81
Jumlah 913,613.90
Dibulatkan 913,600.00

Sub - Pekerjaan : 1m3 Pengadaan dan Pemasangan Gravel Pack 490,600.00


Nomor Urut Rab : 3.3
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Koefisien Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Driller hari 1.000 175,000.00 175,000.00 175,000.00
2 - Ass. Driller hari 1.000 150,000.00 150,000.00 150,000.00
3 - Mekanik hari 1.000 85,000.00 85,000.00 85,000.00
4 - Helper hari 1.000 80,000.00 80,000.00 80,000.00
BAHAN
1 - Gravel Pack m3 2.500 250,000.00 625,000.00 625,000.00

Jumlah Harga 1,115,000.00


Harga Satuan Bahan, Peralatan, dan Upah Pek. Gravel Pack m3 1,115,000.00
Jumlah Satuan Per Keperluan 2.50
Harga Satuan Bahan, Peralatan, dan Upah Pek. Gravel Pack 1 m3 446,000.00
Keuntungan Max 10% 44,600.00
Jumlah 490,600.00
Dibulatkan 490,600.00

Sub - Pekerjaan : 1m3 Pengadaan dan Pemasangan Cement Grouting


Nomor Urut Rab : 3.4
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Koefisien Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Driller hari 1.000 175,000.00 175,000.00 175,000.00
2 - Ass. Driller hari 1.000 150,000.00 150,000.00 150,000.00
3 - Mekanik hari 1.000 85,000.00 85,000.00 85,000.00
4 - Helper hari 1.000 80,000.00 80,000.00 80,000.00
BAHAN
1 - Pasir Beton m3 3.000 250,000.00 750,000.00 750,000.00
2 - Semen PC @ 50 Kg zak 18.000 85,000.00 1,530,000.00 1,530,000.00

Jumlah Harga 2,770,000.00


Harga Satuan Bahan, Peralatan, dan Upah Pekerjaan Cement Grouting 2,770,000.00
Jumlah Satuan Per Keperluan 3.00
Harga Satuan Bahan, Peralatan, dan Upah Pekerjaan Cement Grouting 923,333.33
Keuntungan Max 10% 92,333.33
Jumlah 1,015,666.67
Dibulatkan 1,015,600.00
Sub - Pekerjaan : Pengadaan dan Pemasangan Pipa Naik dia. 1,5" Pipa GIP 180,500.00
Nomor Urut Rab : 3.5
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Koefisien Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Driller hari 1.000 175,000.00 175,000.00 175,000.00
2 - Ass. Driller hari 1.000 150,000.00 150,000.00 150,000.00
3 - Operator hari 1.000 130,000.00 130,000.00 130,000.00
4 - Mekanik hari 1.000 85,000.00 85,000.00 85,000.00
5 - Helper hari 1.000 80,000.00 80,000.00 80,000.00
BAHAN
1 - Pipa GIP dia 1,5" m1 90.000 139,500.00 12,555,000.00 12,555,000.00
2 - Soket Pipa GIP 1,5" bh 15.000 28,750.00 431,250.00 431,250.00
3 - Seal Tape roll 5.000 7,000.00 35,000.00 35,000.00
4 - Solar liter 35.000 9,250.00 323,750.00 323,750.00
5 - Oli Hidrolis liter 3.000 22,500.00 67,500.00 67,500.00
6 - Oli Mesin liter 1.000 22,500.00 22,500.00 22,500.00
7 - Stempet kg 0.500 14,000.00 7,000.00 7,000.00
PERALATAN
1 - Peralatan Pengeboran hari 1.000 710,000.00 710,000.00 710,000.00
Jumlah Harga 14,772,000.00
Harga Satuan Bahan, Peralatan, dan Upah Pek. Pipa Naik dia. 1,5" Pipa GIP / 90 meter 14,772,000.00
Kecepatan Pemasangan Pipa Naik dia. 1,5" Perhari / meter 90.00
Harga Satuan Bahan, Peralatan, dan Upah Pek. Pipa Naik dia. 1,5" Pipa GIP / 1 meter 164,133.33
Keuntungan Max 10% 16,413.33
Jumlah 180,546.67
Dibulatkan 180,500.00

Sub - Pekerjaan : Pengadaan dan Pemasangan Pipa Ukur MAT dia. 1" Pipa GIP
Nomor Urut Rab : 3.6
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Koefisien Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Driller hari 1.000 175,000.00 175,000.00 175,000.00
2 - Ass. Driller hari 1.000 150,000.00 150,000.00 150,000.00
3 - Operator hari 1.000 130,000.00 130,000.00 130,000.00
4 - Mekanik hari 1.000 85,000.00 85,000.00 85,000.00
5 - Helper hari 1.000 80,000.00 80,000.00 80,000.00
BAHAN
1 - Pipa GIP dia. 1" m1 90.000 93,500.00 8,415,000.00 8,415,000.00
2 - Soket Pipa GIP 1" bh 15.000 23,700.00 355,500.00 355,500.00
3 - Seal Tape roll 5.000 7,000.00 35,000.00 35,000.00
4 - Solar liter 35.000 9,250.00 323,750.00 323,750.00
5 - Oli Hidrolis liter 3.000 22,500.00 67,500.00 67,500.00
6 - Oli Mesin liter 1.000 22,500.00 22,500.00 22,500.00
7 - Stempet kg 0.500 14,000.00 7,000.00 7,000.00
PERALATAN
1 - Peralatan Pengeboran hari 1.000 710,000.00 710,000.00 710,000.00
Jumlah Harga 10,556,250.00
Harga Satuan Bahan, Peralatan, dan Upah Pek. Pipa Naik dia. 1" Pipa GIP / 90 meter 10,556,250.00
Kecepatan Pemasangan Pipa Naik dia. 1" Perhari / meter 90.00
Harga Satuan Bahan, Peralatan, dan Upah Pek. Pipa Naik dia. 1" Pipa GIP / 1 meter 117,291.67
Keuntungan Max 10% 11,729.17
Jumlah 129,020.83
Dibulatkan 129,000.00

Sub - Pekerjaan : Uji Pemompaan 6,231,400.00


Nomor Urut Rab : 5.1
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Koefisien Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)

1 Step Drawdown Test hari 1.000 1,839,700.00 1,839,700.00 1,839,700.00


2 Recovery Test hari 1.000 1,083,500.00 1,083,500.00 1,083,500.00
3 Constant Rate Test hari 1.000 3,308,200.00 3,308,200.00 3,308,200.00
Jumlah Harga 6,231,400.00
Dibulatkan 6,231,400.00

Sub - Pekerjaan : Step Drawdown Test 1,839,700.00


Nomor Urut Rab : 5.1
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Koefisien Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Ahli Hidrogeologi hari 1.000 200,000.00 200,000.00 200,000.00
2 - Ass. Ahli Hidrogeologi hari 1.000 175,000.00 175,000.00 175,000.00
3 - Operator hari 1.000 130,000.00 130,000.00 130,000.00
4 - Helper hari 1.000 80,000.00 80,000.00 80,000.00
BAHAN
1 - Solar liter 50.000 9,250.00 462,500.00 462,500.00
2 - Oli Mesin liter 10.000 22,500.00 225,000.00 225,000.00
PERALATAN
1 - Mesin Pumping Test, EC Meter, PH meter, hari 1.000 400,000.00 400,000.00 400,000.00
Termometer dan Water Circulation
2 - Alat Tulis ls 1.000 - - -
Jumlah Harga 1,672,500.00
Harga Satuan Bahan, Peralatan, dan Upah Pekerjaan Step Down Test 1,672,500.00
Keuntungan Max 10% 167,250.00
Jumlah 1,839,750.00
Dibulatkan 1,839,700.00
Sub - Pekerjaan : Recovery Test
Nomor Urut Rab : 5.2
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Koefisien Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Ahli Hidrogeologi hari 1.000 200,000.00 200,000.00 200,000.00
2 - Ass. Ahli Hidrogeologi hari 1.000 175,000.00 175,000.00 175,000.00
3 - Operator hari 1.000 130,000.00 130,000.00 130,000.00
4 - Helper hari 1.000 80,000.00 80,000.00 80,000.00
PERALATAN
1 - Mesin Pumping Test, EC Meter, PH meter, hari 1.000 400,000.00 400,000.00 400,000.00
Termometer dan Water Circulation
2 - Alat Tulis ls 1.000 - - -
Jumlah Harga 985,000.00
Harga Satuan Bahan, Peralatan, dan Upah Pekerjaan Recovery Test 985,000.00
Keuntungan Max 10% 98,500.00
Jumlah 1,083,500.00
Dibulatkan 1,083,500.00

Sub - Pekerjaan : Constant Rate Test 3,308,200.00


Nomor Urut Rab : 5.3
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Koefisien Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Ahli Hidrogeologi hari 2.000 200,000.00 400,000.00 400,000.00
2 - Ass. Ahli Hidrogeologi hari 2.000 175,000.00 350,000.00 350,000.00
3 - Operator hari 2.000 130,000.00 260,000.00 260,000.00
4 - Helper hari 2.000 80,000.00 160,000.00 160,000.00
BAHAN
1 - Solar liter 100.000 9,250.00 925,000.00 925,000.00
2 - Oli Mesin liter 5.000 22,500.00 112,500.00 112,500.00
PERALATAN
1 - Mesin Pumping Test, EC Meter, PH meter, hari 2.000 400,000.00 800,000.00 800,000.00
Termometer dan Water Circulation
2 - Alat Tulis ls 2.000 - - -
Jumlah Harga 3,007,500.00
Harga Satuan Bahan, Peralatan, dan Upah Pekerjaan Constant Rate Test 3,007,500.00
Keuntungan Max 10% 300,750.00
Jumlah 3,308,250.00
Dibulatkan 3,308,200.00

Sub - Pekerjaan : Pengadaan dan Pemasangan Genset 78,523,500.00


Nomor Urut Rab : 6.1
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Koefisien Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Ongkos Pasang ls 1.000 100,000.00 100,000.00 100,000.00
2 - Mekanik Orang 1.000 85,000.00 85,000.00 85,000.00
BAHAN
1 - Mesin Genset unit 1.000 71,200,000.00 71,200,000.00 71,200,000.00

Harga Satuan Bahan, Peralatan, dan Upah Pengadaan dan Pemasangan Genset 71,385,000.00
Keuntungan Max 10% 7,138,500.00
Jumlah 78,523,500.00
Dibulatkan 78,523,500.00

Sub - Pekerjaan : Pengadaan dan Pemasangan Pompa Selam 3 PK (100.00)


Nomor Urut Rab : 6.2
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Koefisien Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Ongkos Pasang ls 1.000 100,000.00 100,000.00 100,000.00
2 - Mekanik Orang 1.000 85,000.00 85,000.00 85,000.00
BAHAN
1 - Mesin Pompa Selam unit 1.000 15,200,000.00 15,200,000.00 15,200,000.00
2 - Sling Baja 5mm m' 105.000 80,000.00 8,400,000.00 8,400,000.00
3 - Panel Pompa & accessories unit 1.000 7,550,000.00 7,550,000.00 7,550,000.00

Harga Satuan Bahan, Peralatan, & Upah Pengadaan & Pemasangan Pompa Selam 31,335,000.00
Keuntungan Max 10% 3,133,500.00
Jumlah 31,335,000.00

Kota, ...........
PT.

Direktur
ANALISA HARGA SATUAN PEKERJAAN RUMAH GENSET, RUMAH SUMUR BOR, DAN BAK
PENAMPUNG AIR

Sub - Pekerjaan : 1 m1 Pasang Bouwplank 84,800.00


Nomor Urut Rab : I.1.2.
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Pekerja org 0.125 80,000.00 10,000.00 10,000.00
2 - Tukang org 0.125 100,000.00 12,500.00 12,500.00
3 - Kepala Tukang org 0.013 150,000.00 1,950.00 1,950.00
4 - Mandor org 0.006 150,000.00 900.00 900.00
BAHAN
1 - Kayu Terentang/Albasia (Balok) m3 0.014 2,250,000.00 31,500.00 31,500.00
2 - Kayu Terentang/Albasia (papan) m3 0.008 2,500,000.00 20,000.00 20,000.00
3 - Paku 4 cm s/d 7 cm (Paku Sedang) kg 0.023 13,500.00 310.50 310.50
Jumlah Harga 77,160.50
Keuntungan max 10% 7,716.05
Jumlah 84,876.55
Dibulatkan 84,800.00

Sub - Pekerjaan : 1 m3 Galian Tanah Biasa 78,400.00


Nomor Urut Rab : II.1.1 ,III.1.1 dan IV.1.1
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Pekerja org 0.695 80,000.00 55,600.00 55,600.00
2 - Mandor org 0.105 150,000.00 15,750.00 15,750.00
PERALATAN
Jumlah Harga 71,350.00
Keuntungan max 10% 7,135.00
Jumlah 78,485.00
Dibulatkan 78,400.00

Sub - Pekerjaan : 1 m3 Urugan Tanah Kembali 20,000.00


Nomor Urut Rab : II.1.2 dan III.1.3
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Pekerja org 0.192 80,000.00 15,360.00 15,360.00
2 - Mandor org 0.019 150,000.00 2,850.00 2,850.00
PERALATAN
Jumlah Harga 18,210.00
Keuntungan max 10% 1,821.00
Jumlah 20,031.00
Dibulatkan 20,000.00

Sub - Pekerjaan : 1 m3 Urugan Pasir 278,800.00


Nomor Urut Rab : II.1.3, III.1.3. dan IV.1.3.
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Pekerja org 0.150 80,000.00 12,000.00 12,000.00
2 - Mandor org 0.010 150,000.00 1,500.00 1,500.00
BAHAN
1 - Pasir Pasang m3 1.200 200,000.00 240,000.00 240,000.00
Jumlah Harga 253,500.00
Keuntungan max 10% 25,350.00
Jumlah 278,850.00
Dibulatkan 278,800.00

Sub - Pekerjaan : 1 m3 Pasangan Aanstamping Batu Kali 342,300.00


Nomor Urut Rab : II.2.1. dan IV.2.1.
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Pekerja org 1.500 80,000.00 120,000.00 120,000.00
2 - Mandor org 0.075 150,000.00 11,250.00 11,250.00
BAHAN
1 - Batu Belah / Batu Kali m3 1.200 150,000.00 180,000.00 180,000.00
Jumlah Harga 311,250.00
Keuntungan max 10% 31,125.00
Jumlah 342,375.00
Dibulatkan 342,300.00

Sub - Pekerjaan : 1 m3 Pasangan Batu Kali 681,000.00


Nomor Urut Rab : II.2.2. dan IV.2.2.
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Kepala Tukang org 0.113 150,000.00 16,950.00 16,950.00
2 - Tukang org 0.500 100,000.00 50,000.00 50,000.00
3 - Mandor org 0.017 150,000.00 2,550.00 2,550.00
4 - Pekerja org 1.250 80,000.00 100,000.00 100,000.00
BAHAN
1 - Batu Belah / Batu Kali m3 1.200 150,000.00 180,000.00 180,000.00
2 - Semen PC @ 50 Kg zak 2.160 85,000.00 183,600.00 183,600.00
3 - Pasir Pasang m3 0.430 200,000.00 86,000.00 86,000.00
Jumlah Harga 619,100.00
Keuntungan max 10% 61,910.00
Jumlah 681,010.00
Dibulatkan 681,000.00

Sub - Pekerjaan : 1 m3 Sloof Beton 6,433,500.00


Nomor Urut Rab : II.2.3.
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
1 - Besi Beton U-24 Kualitas KS-Sj kg 60.000 27,100.00 1,626,000.00 1,626,000.00
2 - Pasangan Bekisting (papan) u beton m2 17.770 167,000.00 2,967,590.00 2,967,590.00
3 - Cor Adukan Beton K-175 m3 1.000 1,255,100.00 1,255,100.00 1,255,100.00
Jumlah Harga 5,848,690.00
Keuntungan max 10% 584,869.00
Jumlah 6,433,559.00
Dibulatkan 6,433,500.00

Sub - Pekerjaan : 1 m3 Kolom Beton 5,924,600.00


Nomor Urut Rab : II.2.4.
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
1 - Besi Beton U-24 Kualitas KS-Sj kg 60.000 27,100.00 1,626,000.00 1,626,000.00
2 - Pasangan Bekisting (papan) u beton m2 13.330 167,000.00 2,226,110.00 2,226,110.00
3 - Cor Adukan Beton K-175 m3 1.000 1,255,100.00 1,255,100.00 1,255,100.00
4 - Pasangan Stootwerk u/ Beton m2 1.000 278,800.00 278,800.00 278,800.00
Jumlah Harga 5,386,010.00
Keuntungan max 10% 538,601.00
Jumlah 5,924,611.00
Dibulatkan 5,924,600.00
0.15 0.200 0.2 33.3333333333333
Sub - Pekerjaan : 1 m3 Ring Balk Praktis 6,383,800.00
Nomor Urut Rab : II.2.5.
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
1 - Besi Beton U-24 Kualitas KS-Sj kg 60.000 27,100.00 1,626,000.00 1,626,000.00
2 - Pasangan Bekisting (papan) u beton m2 15.830 167,000.00 2,643,610.00 2,643,610.00
3 - Cor Adukan Beton K-175 m3 1.000 1,255,100.00 1,255,100.00 1,255,100.00
4 - Pasangan Stootwerk u/ Beton m2 1.000 278,800.00 278,800.00 278,800.00
Jumlah Harga 5,803,510.00
Keuntungan max 10% 580,351.00
Jumlah 6,383,861.00
Dibulatkan 6,383,800.00
Sub - Pekerjaan : 1 m3 Plat Lantai beton 1,558,800.00
Nomor Urut Rab : II.2.6. dan IV.2.3.
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
1 - Cor Adukan Beton K-175 m3 1.000 1,255,100.00 1,255,100.00 1,255,100.00
2 - Angker Besi Baut+Mur 16mm bh 4.000 40,500.00 162,000.00 162,000.00
Jumlah Harga 1,417,100.00
Keuntungan max 10% 141,710.00
Jumlah 1,558,810.00
Dibulatkan 1,558,800.00

Sub - Pekerjaan : 1 m3 Lantai Kerja/Beton Tumbuk 1,033,100.00


Nomor Urut Rab : II.2.7., III.4.3, dan IV.2.6
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Kepala Tukang org 0.050 150,000.00 7,500.00 7,500.00
2 - Tukang org 0.500 100,000.00 50,000.00 50,000.00
3 - Mandor org 0.010 150,000.00 1,500.00 1,500.00
4 - Pekerja org 2.000 80,000.00 160,000.00 160,000.00
BAHAN
1 - Semen PC @ 50 Kg zak 3.956 85,000.00 336,260.00 336,260.00
2 - Pasir Beton m3 0.540 250,000.00 135,000.00 135,000.00
3 - Kerikil 1/2 (Pecah Mesin) m3 0.830 300,000.00 249,000.00 249,000.00
Jumlah Harga 939,260.00
Keuntungan max 10% 93,926.00
Jumlah 1,033,186.00
Dibulatkan 1,033,100.00

Sub - Pekerjaan : 1 m2 Pasangan 1/2 Bata Merah 192,900.00


Nomor Urut Rab : II.3.1. dan III.2.2
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Kepala Tukang org 0.021 150,000.00 3,150.00 3,150.00
2 - Tukang org 0.214 100,000.00 21,400.00 21,400.00
3 - Mandor org 0.011 150,000.00 1,650.00 1,650.00
4 - Pekerja org 0.429 80,000.00 34,320.00 34,320.00
BAHAN
1 - Bata Merah bh 70.000 850.00 59,500.00 59,500.00
2 - Semen PC @ 50 Kg zak 0.525 85,000.00 44,625.00 44,625.00
3 - Pasir Pasang m3 0.054 200,000.00 10,800.00 10,800.00
Jumlah Harga 175,445.00
Keuntungan max 10% 17,544.50
Jumlah 192,989.50
Dibulatkan 192,900.00

Sub - Pekerjaan : 1 m2 Plesteran ad. 1Pc : 3Ps 74,700.00


Nomor Urut Rab : II.3.2. , III.4.1 dan IV.2.7.
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Kepala Tukang org 0.021 150,000.00 3,150.00 3,150.00
2 - Tukang org 0.214 100,000.00 21,400.00 21,400.00
3 - Mandor org 0.021 150,000.00 3,150.00 3,150.00
4 - Pekerja org 0.286 80,000.00 22,880.00 22,880.00
BAHAN
1 - Semen PC @ 50 Kg zak 0.160 85,000.00 13,600.00 13,600.00
2 - Pasir Pasang m3 0.019 200,000.00 3,800.00 3,800.00
Jumlah Harga 67,980.00
Keuntungan max 10% 6,798.00
Jumlah 74,778.00
Dibulatkan 74,700.00

Sub - Pekerjaan : 1 m2 Pek. Acian 69,000.00


Nomor Urut Rab : II.3.3. , III.2.3 ,III.4.2 dan IV.2.8
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Kepala Tukang org 0.021 150,000.00 3,150.00 3,150.00
2 - Tukang org 0.210 100,000.00 21,000.00 21,000.00
3 - Mandor org 0.020 150,000.00 3,000.00 3,000.00
4 - Pekerja org 0.275 80,000.00 22,000.00 22,000.00
BAHAN
1 - Semen PC @ 50 Kg zak 0.160 85,000.00 13,600.00 13,600.00
Jumlah Harga 62,750.00
Keuntungan max 10% 6,275.00
Jumlah 69,025.00
Dibulatkan 69,000.00

Sub - Pekerjaan : 1 m3 Kusen Pintu 4,457,300.00


Nomor Urut Rab : II.4.1
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Kepala Tukang org 1.512 150,000.00 226,800.00 226,800.00
2 - Tukang org 3.628 100,000.00 362,800.00 362,800.00
3 - Mandor org 0.228 150,000.00 34,200.00 34,200.00
4 - Pekerja org 3.628 80,000.00 290,240.00 290,240.00
BAHAN
1 - Kayu Balok Kelas II m3 1.100 2,850,000.00 3,135,000.00 3,135,000.00
2 - Paku 4 cm s/d 7 cm (Paku Sedang) kg 0.100 13,500.00 1,350.00 1,350.00
3 - Lem putih kg 0.200 8,800.00 1,760.00 1,760.00
Jumlah Harga 4,052,150.00
Keuntungan max 10% 405,215.00
Jumlah 4,457,365.00
Dibulatkan 4,457,300.00

Sub - Pekerjaan : 1 buah Daun Pintu Panel 702,400.00


Nomor Urut Rab : II.4.2.
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Kepala Tukang org 0.320 150,000.00 48,000.00 48,000.00
2 - Tukang org 2.400 100,000.00 240,000.00 240,000.00
3 - Mandor org 0.032 150,000.00 4,800.00 4,800.00
4 - Pekerja org 0.480 80,000.00 38,400.00 38,400.00
BAHAN
1 - Kayu Balok Kelas II m3 0.046 2,850,000.00 131,100.00 131,100.00
2 - Kayu Papan Kelas II m3 0.060 2,850,000.00 171,000.00 171,000.00
3 - Lem putih kg 0.010 8,800.00 88.00 88.00
4 - Paku 1 cm s/d 3 cm (Paku Kecil) kg 0.400 13,000.00 5,200.00 5,200.00
Jumlah Harga 638,588.00
Keuntungan max 10% 63,858.80
Jumlah 702,446.80
Dibulatkan 702,400.00

Sub - Pekerjaan : 1 buah Rooster 183,700.00


Nomor Urut Rab : II.4.3.
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Kepala Tukang org 0.120 150,000.00 18,000.00 18,000.00
2 - Tukang org 0.900 100,000.00 90,000.00 90,000.00
3 - Mandor org 0.012 150,000.00 1,800.00 1,800.00
4 - Pekerja org 0.180 80,000.00 14,400.00 14,400.00
BAHAN
1 - Kayu Papan Kelas II m3 0.015 2,850,000.00 42,750.00 42,750.00
2 - Paku 1 cm s/d 3 cm (Paku Kecil) kg 0.010 13,000.00 130.00 130.00
Jumlah Harga 167,080.00
Keuntungan max 10% 16,708.00
Jumlah 183,788.00
Dibulatkan 183,700.00
Sub - Pekerjaan : 1 buah Angker-angker kusen 126,500.00
Nomor Urut Rab : II.4.4.
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Ongkos pasang ls 1.000 100,000.00 100,000.00 100,000.00
BAHAN
1 - Besi Beton Polos kg 1.000 15,000.00 15,000.00 15,000.00
PERALATAN
Jumlah Harga 115,000.00
Keuntungan max 10% 11,500.00
Jumlah 126,500.00
Dibulatkan 126,500.00

Sub - Pekerjaan : 1 buah Dook & Neut Kusen Pintu 87,800.00


Nomor Urut Rab : II.4.5.
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
1 - Cor Adukan Beton K-175 m3 0.002 1,255,100.00 2,510.20 2,510.20
2 - Bekisting m2 0.050 167,000.00 8,350.00 8,350.00
3 - Acian ls 1.000 69,000.00 69,000.00 69,000.00
Jumlah Harga 79,860.20
Keuntungan max 10% 7,986.02
Jumlah 87,846.22
Dibulatkan 87,800.00

Sub - Pekerjaan : 1 buah Kunci Pintu Ganda 160,800.00


Nomor Urut Rab : II.5.1
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Kepala Tukang org 0.600 150,000.00 90,000.00 90,000.00
2 - Mandor org 0.005 150,000.00 750.00 750.00
BAHAN
1 - Kunci pintu bh 1.000 55,500.00 55,500.00 55,500.00
Jumlah Harga 146,250.00
Keuntungan max 10% 14,625.00
Jumlah 160,875.00
Dibulatkan 160,800.00

Sub - Pekerjaan : 1 buah Slot Pintu Atas Bawah 94,100.00


Nomor Urut Rab : II.5.2
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Kepala Tukang org 0.400 150,000.00 60,000.00 60,000.00
2 - Mandor org 0.004 150,000.00 600.00 600.00
BAHAN
1 - Slot Pintu Atas Bawah bh 1.000 25,000.00 25,000.00 25,000.00
Jumlah Harga 85,600.00
Keuntungan max 10% 8,560.00
Jumlah 94,160.00
Dibulatkan 94,100.00

Sub - Pekerjaan : 1 buah Engsel Pintu 47,000.00


Nomor Urut Rab : II.5.3.
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Kepala Tukang org 0.150 150,000.00 22,500.00 22,500.00
2 - Mandor org 0.002 150,000.00 300.00 300.00
BAHAN
1 - Engsel Pintu bh 1.000 20,000.00 20,000.00 20,000.00
Jumlah Harga 42,800.00
Keuntungan max 10% 4,280.00
Jumlah 47,080.00
Dibulatkan 47,000.00

Sub - Pekerjaan : 1 m2 Gording Kayu 6/12/m3 4,096,500.00


Nomor Urut Rab : II.6.1.
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Kepala Tukang org 1.000 150,000.00 150,000.00 150,000.00
2 - Tukang org 2.500 100,000.00 250,000.00 250,000.00
3 - Mandor org 0.200 150,000.00 30,000.00 30,000.00
4 - Pekerja org 1.500 80,000.00 120,000.00 120,000.00
BAHAN
1 - Kayu Balok Kelas II m3 1.100 2,850,000.00 3,135,000.00 3,135,000.00
2 - Paku 4 cm s/d 7 cm (Paku Sedang) kg 2.900 13,500.00 39,150.00 39,150.00
Jumlah Harga 3,724,150.00
Keuntungan max 10% 372,415.00
Jumlah 4,096,565.00
Dibulatkan 4,096,500.00

Sub - Pekerjaan : 1 m2 Atap Asbes Gelombang/m2 98,700.00


Nomor Urut Rab : II.6.2.
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Ongkos Pasang ls 0.500 80,000.00 40,000.00 40,000.00
BAHAN
1 - Asbes Gelombang kecil lmbr 0.417 93,000.00 38,781.00 38,781.00
2 - Paku Asbes kg 0.500 22,000.00 11,000.00 11,000.00
Jumlah Harga 89,781.00
Keuntungan max 10% 8,978.10
Jumlah 98,759.10
Dibulatkan 98,700.00

Sub - Pekerjaan : 1 m1 Lystplank Kayu Kelas II (Papan) 3/20 /m' 64,700.00


Nomor Urut Rab : II.6.3.
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Kepala Tukang org 0.016 150,000.00 2,400.00 2,400.00
2 - Tukang org 0.160 100,000.00 16,000.00 16,000.00
3 - Mandor org 0.003 150,000.00 450.00 450.00
4 - Pekerja org 0.056 80,000.00 4,480.00 4,480.00
BAHAN
1 - Kayu Papan Kelas II m3 0.012 2,850,000.00 34,200.00 34,200.00
2 - Paku 4 cm s/d 7 cm (Paku Sedang) kg 0.100 13,500.00 1,350.00 1,350.00
Jumlah Harga 58,880.00
Keuntungan max 10% 5,888.00
Jumlah 64,768.00
Dibulatkan 64,700.00

Sub - Pekerjaan : 1 m2 Pasangan Lantai Keramik uk. 30 x 30 cm 197,900.00


Nomor Urut Rab : II.7.2. dan IV.2.5.
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Kepala Tukang org 0.100 150,000.00 15,000.00 15,000.00
2 - Tukang org 0.500 100,000.00 50,000.00 50,000.00
3 - Mandor org 0.025 150,000.00 3,750.00 3,750.00
4 - Pekerja org 0.250 80,000.00 20,000.00 20,000.00
BAHAN
1 - Keramik (30x30) dooz 1.100 65,000.00 71,500.00 71,500.00
2 - Semen PC @ 50 Kg zak 0.160 85,000.00 13,600.00 13,600.00
3 - Pasir Pasang m3 0.030 200,000.00 6,000.00 6,000.00
4 - Semen Warna kg 0.013 9,500.00 123.50 123.50
Jumlah Harga 179,973.50
Keuntungan max 10% 17,997.35
Jumlah 197,970.85
Dibulatkan 197,900.00

Sub - Pekerjaan : 1 M2 Pengecatan Dinding Dengan Cat Vinilex 69,200.00


Nomor Urut Rab : II.8.1. dan III.5.1.
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Kepala Tukang org 0.038 150,000.00 5,700.00 5,700.00
2 - Tukang org 0.182 100,000.00 18,200.00 18,200.00
3 - Mandor org 0.013 150,000.00 1,950.00 1,950.00
4 - Pekerja org 0.125 80,000.00 10,000.00 10,000.00
BAHAN
1 - Cat Tembok Vinilex kg 0.350 57,000.00 19,950.00 19,950.00
2 - Plamur/Dempul Tembok kg 0.160 28,000.00 4,480.00 4,480.00
3 - Hampelas lmbr 0.500 4,000.00 2,000.00 2,000.00
4 - Roll Cat bh 0.050 14,000.00 700.00 700.00
Jumlah Harga 62,980.00
Keuntungan max 10% 6,298.00
Jumlah 69,278.00
Dibulatkan 69,200.00

Sub - Pekerjaan : 1 m2 Pengecatan Kayu Dengan Cat Kayu 72,200.00


Nomor Urut Rab : II.8.2.
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Kepala Tukang org 0.046 150,000.00 6,900.00 6,900.00
2 - Tukang org 0.250 100,000.00 25,000.00 25,000.00
3 - Mandor org 0.016 150,000.00 2,400.00 2,400.00
4 - Pekerja org 0.150 80,000.00 12,000.00 12,000.00
BAHAN
1 - Cat Kayu SEIV kg 0.200 33,500.00 6,700.00 6,700.00
2 - Menie Kayu kg 0.167 21,000.00 3,507.00 3,507.00
3 - Plamur/Dempul Kayu kg 0.200 28,000.00 5,600.00 5,600.00
4 - Kuas 3" bh 0.050 10,000.00 500.00 500.00
5 - Hampelas lmbr 0.400 4,000.00 1,600.00 1,600.00
6 - Minyak Cat / Terpentin ltr 0.150 10,000.00 1,500.00 1,500.00
Jumlah Harga 65,707.00
Keuntungan max 10% 6,570.70
Jumlah 72,277.70
Dibulatkan 72,200.00

Sub - Pekerjaan : 1 m1 Pek. Saluran Drainase 302,700.00


Nomor Urut Rab : II.9.1.
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Galian Tanah Biasa m3 0.217 78,400.00 16,986.67 16,986.67
2 - Beton tumbuk 1:3:5 m3 0.250 1,033,100.00 258,275.00 258,275.00

Jumlah Harga 275,261.67


Keuntungan max 10% 27,526.17
Jumlah 302,787.83
Dibulatkan 302,700.00

Sub - Pekerjaan : 1 m2 Pasangan Rolaag Bata Merah 319,400.00


Nomor Urut Rab : III.2.1.
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Kepala Tukang org 0.021 150,000.00 3,150.00 3,150.00
2 - Tukang org 0.214 100,000.00 21,400.00 21,400.00
3 - Mandor org 0.011 150,000.00 1,650.00 1,650.00
4 - Pekerja org 0.429 80,000.00 34,320.00 34,320.00
BAHAN
1 - Bata Merah bh 140.000 850.00 119,000.00 119,000.00
2 - Semen PC @ 50 Kg zak 1.050 85,000.00 89,250.00 89,250.00
3 - Pasir Pasang m3 0.108 200,000.00 21,600.00 21,600.00
Jumlah Harga 290,370.00
Keuntungan max 10% 29,037.00
Jumlah 319,407.00
Dibulatkan 319,400.00

Sub - Pekerjaan : 1 m2 Pasangan Dinding Keramik uk. 30 x 30 cm 197,900.00


Nomor Urut Rab : IV.2.5.
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Kepala Tukang org 0.100 150,000.00 15,000.00 15,000.00
2 - Tukang org 0.500 100,000.00 50,000.00 50,000.00
3 - Mandor org 0.025 150,000.00 3,750.00 3,750.00
4 - Pekerja org 0.250 80,000.00 20,000.00 20,000.00
BAHAN
1 - Keramik (30x30) dooz 1.100 65,000.00 71,500.00 71,500.00
2 - Semen PC @ 50 Kg zak 0.160 85,000.00 13,600.00 13,600.00
3 - Pasir Pasang m3 0.030 200,000.00 6,000.00 6,000.00
4 - Semen Warna kg 0.013 9,500.00 123.50 123.50
Jumlah Harga 179,973.50
Keuntungan max 10% 17,997.35
Jumlah 197,970.85
Dibulatkan 197,900.00

Sub - Pekerjaan 1 buah Pasangan Penutup Rumah Sumur Bor 1,318,600.00


Nomor Urut Rab III.3.1 dan III.5.1
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Koefisien Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Welder org 0.600 70,000.00 42,000.00 42,000.00
2 - Pekerja org 1.200 80,000.00 96,000.00 96,000.00
3 - Mandor org 0.050 150,000.00 7,500.00 7,500.00
BAHAN
1 - Besi Plat lmbr 0.525 559,000.00 293,245.81 293,245.81
2 - Besi Siku 4x4cm m1 11.200 25,000.00 280,000.00 280,000.00
3 - Engsel Pintu Besi bh 2.000 25,000.00 50,000.00 50,000.00
4 - Besi Beton Polos U-24 Kualitas SII kg 2.000 15,000.00 30,000.00 30,000.00
PERALATAN
1 - Peralatan Las ls 1.000 400,000.00 400,000.00 400,000.00
Jumlah Harga 1,198,745.81
Keuntungan max 10% 119,874.58
Jumlah 1,318,620.39
Dibulatkan 1,318,600.00

Sub - Pekerjaan : 1 m2 Pengecatan Besi Dengan Cat Besi 68,000.00


Nomor Urut Rab : III.5.2
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Kepala Tukang org 0.046 150,000.00 6,900.00 6,900.00
2 - Tukang org 0.250 100,000.00 25,000.00 25,000.00
3 - Mandor org 0.016 150,000.00 2,400.00 2,400.00
4 - Pekerja org 0.150 80,000.00 12,000.00 12,000.00
BAHAN
1 - Cat Besi SEIV kg 0.200 40,000.00 8,000.00 8,000.00
2 - Menie Besi kg 0.167 24,000.00 4,008.00 4,008.00
3 - Kuas 3" bh 0.050 10,000.00 500.00 500.00
4 - Hampelas lmbr 0.400 4,000.00 1,600.00 1,600.00
5 - Minyak Cat / Terpentin ltr 0.150 10,000.00 1,500.00 1,500.00
Jumlah Harga 61,908.00
Keuntungan max 10% 6,190.80
Jumlah 68,098.80
Dibulatkan 68,000.00

Sub - Pekerjaan : Pas. Plate Top dan Plate Botttom


Nomor Urut Rab : III.6.1
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Ongkos pasang ls 1.000 100,000.00 100,000.00 100,000.00
BAHAN
1 - Plate Top bh 1.000 145,000.00 145,000.00 145,000.00
2 - Plate Bottom bh 1.000 145,000.00 145,000.00 145,000.00
3 - Muur Baut bh 4.000 17,200.00 68,800.00 68,800.00
PERALATAN
Jumlah Harga 458,800.00
Keuntungan max 10% 45,880.00
Jumlah 504,680.00
Dibulatkan 504,600.00

Sub - Pekerjaan : Pas. Klem Pipa 1,5"


Nomor Urut Rab : III.6.2
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Ongkos pasang ls 1.000 100,000.00 100,000.00 100,000.00
BAHAN
1 - Klem Pipa bh 2.000 10,200.00 20,400.00 20,400.00
2 - Muur Baut rol 4.000 17,200.00 68,800.00 68,800.00
PERALATAN
Jumlah Harga 189,200.00
Keuntungan max 10% 18,920.00
Jumlah 208,120.00
Dibulatkan 208,100.00

Sub - Pekerjaan : I buah Pas. L-Booh dia. 1,5"


Nomor Urut Rab : III.6.3
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Ongkos pasang ls 1.000 100,000.00 100,000.00 100,000.00
BAHAN
1 - L-Booh dia. 1,5" bh 1.000 18,000.00 18,000.00 18,000.00
2 - Seal Tape rol 1.000 7,000.00 7,000.00 7,000.00
PERALATAN
Jumlah Harga 125,000.00
Keuntungan max 10% 12,500.00
Jumlah 137,500.00
Dibulatkan 137,500.00

Sub - Pekerjaan : 1 buah Pas. Water Muur


Nomor Urut Rab : III.6.4
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Ongkos pasang ls 1.000 100,000.00 100,000.00 100,000.00
BAHAN
1 - Water Muur bh 1.000 20,700.00 20,700.00 20,700.00
2 - Sock Drat Luar dia. 1,5" bh 2.000 5,650.00 11,300.00 11,300.00
2 - Seal Tape rol 1.000 7,000.00 7,000.00 7,000.00
PERALATAN
Jumlah Harga 139,000.00
Keuntungan max 10% 13,900.00
Jumlah 152,900.00
Dibulatkan 152,900.00

Sub - Pekerjaan : I buah Pas. Manometer Pressure Gauge


Nomor Urut Rab : III.6.5
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Ongkos pasang ls 1.000 100,000.00 100,000.00 100,000.00
BAHAN
1 - Manometer Pressure Gauge bh 1.000 49,500.00 49,500.00 49,500.00
2 - T- dia. 1,5 " ke 3/4" bh 1.000 21,500.00 21,500.00 21,500.00
3 - Sock Drat Luar dia. 1,5" bh 2.000 5,650.00 11,300.00 11,300.00
4 - Seal Tape rol 1.000 7,000.00 7,000.00 7,000.00
PERALATAN
Jumlah Harga 189,300.00
Keuntungan max 10% 18,930.00
Jumlah 208,230.00
Dibulatkan 208,200.00

Sub - Pekerjaan : 1 buah Pas. Check Valve


Nomor Urut Rab : III.6.6
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Ongkos pasang ls 1.000 100,000.00 100,000.00 100,000.00
BAHAN
1 - Check Valve bh 1.000 291,000.00 291,000.00 291,000.00
2 - Sock Drat Luar dia. 1,5" bh 2.000 5,650.00 11,300.00 11,300.00
3 - Seal Tape rol 1.000 7,000.00 7,000.00 7,000.00
PERALATAN
Jumlah Harga 409,300.00
Keuntungan max 10% 40,930.00
Jumlah 450,230.00
Dibulatkan 450,200.00

Sub - Pekerjaan : 1 buah Pas. Stop Kran dia. 1,5"


Nomor Urut Rab : III.6.7
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Ongkos pasang ls 1.000 100,000.00 100,000.00 100,000.00
BAHAN
1 - Stop Kran dia. 1,5" bh 1.000 90,000.00 90,000.00 90,000.00
2 - Sock Drat Luar dia. 1,5" bh 2.000 5,650.00 11,300.00 11,300.00
3 - Seal Tape rol 1.000 7,000.00 7,000.00 7,000.00
PERALATAN
Jumlah Harga 208,300.00
Keuntungan max 10% 20,830.00
Jumlah 229,130.00
Dibulatkan 229,100.00

Sub - Pekerjaan : 1 buah Pas. Water Meter dia. 1,5"


Nomor Urut Rab : III.6.8
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Ongkos pasang ls 1.000 100,000.00 100,000.00 100,000.00
BAHAN
1 - Water Meter dia. 1,5" bh 1.000 840,000.00 840,000.00 840,000.00
2 - Sock Drat Luar dia. 1,5" bh 2.000 5,650.00 11,300.00 11,300.00
3 - Seal Tape rol 1.000 7,000.00 7,000.00 7,000.00
PERALATAN
Jumlah Harga 958,300.00
Keuntungan max 10% 95,830.00
Jumlah 1,054,130.00
Dibulatkan 1,054,100.00

Sub - Pekerjaan : 1 m1 Instalasi Inlet Pipa GIP dia. 1,5" Bak Air 2,529,400.00
Nomor Urut Rab : IV.3.1
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Ongkos pasang ls 1.000 100,000.00 100,000.00 100,000.00
BAHAN
1 - Pipa GIP dia. 1,5" m1 15.000 139,500.00 2,092,500.00 2,092,500.00
2 - L-Booh 1,5" bh 3.000 18,000.00 54,000.00 54,000.00
3 - Water Muur dia. 1,5" bh 1.000 20,700.00 20,700.00 20,700.00
4 - Sock Drat Luar dia. 1,5" bh 2.000 5,650.00 11,300.00 11,300.00
5 - Seal Tape bh 3.000 7,000.00 21,000.00 21,000.00
Jumlah Harga 2,299,500.00
Keuntungan max 10% 229,950.00
Jumlah 2,529,450.00
Dibulatkan 2,529,400.00

Sub - Pekerjaan : Pas. Bak Penampung 5200 liter 7,260,000.00


Nomor Urut Rab : IV.3.2
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Ongkos pasang ls 1.000 100,000.00 100,000.00 100,000.00
BAHAN
1 - Bak Penampung 5200 liter Fibre Glass bh 1.000 6,500,000.00 6,500,000.00 6,500,000.00
Jumlah Harga 6,600,000.00
Keuntungan max 10% 660,000.00
Jumlah 7,260,000.00
Dibulatkan 7,260,000.00

Sub - Pekerjaan : Pas. Pipa PVC jalur distribusi dia. 1" 459,500.00
Nomor Urut Rab : IV.3.3
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Ongkos pasang ls 1.000 100,000.00 100,000.00 100,000.00
BAHAN
1 - Pipa PVC dia.1" m1 8.000 21,500.00 172,000.00 172,000.00
2 - Lem Paralon tube 1.000 15,000.00 15,000.00 15,000.00
3 - Knie PVC dia. 1" bh 4.000 12,000.00 48,000.00 48,000.00
4 - T PVC dia.1" bh 1.000 6,000.00 6,000.00 6,000.00
5 - T PVC dia.1" ke 3/4" bh 6.000 7,000.00 42,000.00 42,000.00
6 - Sock Drat Dalam PVC dia. 1" bh 6.000 5,800.00 34,800.00 34,800.00
PERALATAN
Jumlah Harga 417,800.00
Keuntungan max 10% 41,780.00
Jumlah 459,580.00
Dibulatkan 459,500.00

Sub - Pekerjaan : 1 buah Pas. Stop Kran dia. 1" 179,300.00


Nomor Urut Rab : IV.3.4
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Ongkos pasang ls 1.000 100,000.00 100,000.00 100,000.00
BAHAN
1 - Stop Kran 1" bh 1.000 46,000.00 46,000.00 46,000.00
2 - Sock Drat Luar dia. 1" bh 2.000 5,000.00 10,000.00 10,000.00
3 - Seal Tape rol 1.000 7,000.00 7,000.00 7,000.00
PERALATAN
Jumlah Harga 163,000.00
Keuntungan max 10% 16,300.00
Jumlah 179,300.00
Dibulatkan 179,300.00

Sub - Pekerjaan : 1 buah Pas. Kran dia. 3/4" 137,000.00


Nomor Urut Rab : IV.3.8
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Ongkos pasang ls 1.000 100,000.00 100,000.00 100,000.00
BAHAN
1 - Kran Tembok dia. 3/4 bh 1.000 17,000.00 17,000.00 17,000.00
2 - Socket Drat Dalam PVC dia. 3/4" bh 1.000 5,800.00 5,800.00 5,800.00
3 - Seal Tape rol 0.250 7,000.00 1,750.00 1,750.00
PERALATAN
Jumlah Harga 124,550.00
Keuntungan max 10% 12,455.00
Jumlah 137,005.00
Dibulatkan 137,000.00

Sub - Pekerjaan : 1 m3 Buangan Tanah bekas galian ditempat 39,300.00


Nomor Urut Rab : IV.2.1
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Volume Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Pekerja org 0.348 80,000.00 27,840.00 27,840.00
2 - Mandor org 0.053 150,000.00 7,950.00 7,950.00
PERALATAN
Jumlah Harga 35,790.00
Keuntungan max 10% 3,579.00
Jumlah 39,369.00
Dibulatkan 39,300.00

Sub - Pekerjaan 1 kg Besi Beton U-24 Kualitas KS-SJ 27,100.00


Nomor Urut Rab
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Koefisien Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Kepala Tukang org 0.010 150,000.00 1,500.00 1,500.00
2 - Tukang org 0.005 100,000.00 500.00 500.00
3 - Mandor org 0.030 150,000.00 4,500.00 4,500.00
1 - Pekerja org 0.035 80,000.00 2,800.00 2,800.00
BAHAN
2 - Besi Beton U-24 kg 1.010 15,000.00 15,150.00 15,150.00
3 - Kawat Beton bh 0.010 25,000.00 250.00 250.00
PERALATAN
Jumlah Harga 24,700.00
Keuntungan max 10% 2,470.00
Jumlah 27,170.00
Dibulatkan 27,100.00

Sub - Pekerjaan 1 m2 Pasangan Bekisting (Papan) u/ Beton Praktis 167,000.00


Nomor Urut Rab
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Koefisien Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Kepala Tukang org 0.090 150,000.00 13,500.00 13,500.00
2 - Tukang org 0.130 100,000.00 13,000.00 13,000.00
3 - Mandor org 0.030 150,000.00 4,500.00 4,500.00
4 - Pekerja org 0.082 80,000.00 6,560.00 6,560.00
BAHAN
1 - Kayu Balok Kelas II m3 0.024 2,850,000.00 68,400.00 68,400.00
2 - Kayu Terentang/Albasia (Papan) m3 0.017 2,500,000.00 42,500.00 42,500.00
3 - Paku 4 - 7 Cm (paku sedang) Kg 0.250 13,500.00 3,375.00 3,375.00
Jumlah Harga 151,835.00
Keuntungan max 10% 15,183.50
Jumlah 167,018.50
Dibulatkan 167,000.00

Sub - Pekerjaan 1 m3 Pasangan Stootwerk u/ Beton 278,800.00


Nomor Urut Rab
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Koefisien Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Kepala Tukang org 0.200 150,000.00 30,000.00 30,000.00
2 - Tukang org 0.200 100,000.00 20,000.00 20,000.00
3 - Mandor org 0.017 150,000.00 2,550.00 2,550.00
4 - Pekerja org 0.150 80,000.00 12,000.00 12,000.00
BAHAN
1 - Kayu Balok Kelas II m3 0.016 2,850,000.00 45,600.00 45,600.00
2 - Kayu Terentang/Albasia (Papan) m3 0.056 2,500,000.00 140,000.00 140,000.00
3 - Paku 4 - 7 Cm (paku sedang) Kg 0.250 13,500.00 3,375.00 3,375.00
Jumlah Harga 253,525.00
Keuntungan max 10% 25,352.50
Jumlah 278,877.50
Dibulatkan 278,800.00

Sub - Pekerjaan 1 m3 Cor Adukan Beton K-175 1,255,100.00


Nomor Urut Rab
Jumlah Harga (Rp) Harga Satuan
No. Uraian Bahan dan Upah Satuan Koefisien Harga Satuan
Bahan / Alat Upah Pekerjaan
1 2 3 4 5 6=(4x5) 7=(4x5) 8=(6+ 7)
UPAH
1 - Kepala Tukang org 0.050 150,000.00 7,500.00 7,500.00
2 - Tukang org 0.500 100,000.00 50,000.00 50,000.00
3 - Mandor org 0.010 150,000.00 1,500.00 1,500.00
4 - Pekerja org 1.500 80,000.00 120,000.00 120,000.00
BAHAN
1 - Semen PC @ 50 kg zak 6.800 85,000.00 578,000.00 578,000.00
2 - Pasir Beton m3 0.540 250,000.00 135,000.00 135,000.00
3 - Kerikil 1/2 (pecah mesin) m3 0.830 300,000.00 249,000.00 249,000.00
PERALATAN
Jumlah Harga 1,141,000.00
Keuntungan max 10% 114,100.00
Jumlah 1,255,100.00
Dibulatkan 1,255,100.00

Kota, ..............
PT.

Direktur
DAFTAR HARGA BAHAN

NO URAIAN VULOME HARGA SATUAN (Rp)

1 2 3 4

1 Batu Belah / Batu Kali m3 150,000.00


2 Kerikil 1/2 (Pecah Mesin) m3 300,000.00
3 Kerikil 2/3 (Pecah Mesin) m3 300,000.00
4 Pasir Pasang m3 200,000.00
5 Pasir Beton m3 250,000.00
6 Gravel Pack m3 250,000.00
7 Bata Merah buah 850.00
8 Semen PC @ 50 Kg zak 85,000.00
9 Semen Warna kg 9,500.00
10 Kayu Terentang/Albasia (Balok) m3 2,250,000.00
11 Kayu Terentang/Albasia (Papan) m3 2,500,000.00
12 Kayu Balok Kelas II m3 2,850,000.00
13 Kayu Papan Kelas II m3 2,850,000.00
14 Asbes Gelombang Kecil/Seng gelombang* lembar 93,000.00
15 Keramik (30x30) dooz 65,000.00
16 Besi Beton Polos U-24 Kualitas KS-SJ kg 15,000.00
17 Besi Beton Polos U-24 Kualitas SII kg 15,000.00
18 Kawat Beton kg 25,000.00
19 Besi Plat Eser tebal 3mm lembar 559,000.00
20 Besi Siku 4x4cm m1 25,000.00
21 Besi Plat Strip 4mm m1 15,600.00
22 Paku 1 cm s/d 3 cm (Paku Kecil) kg 13,000.00
23 Paku 4 cm s/d 7 cm (Paku Sedang) kg 13,500.00
24 Paku 8 cm s/d 12 cm (Paku Besar) kg 11,500.00
25 Paku Asbes kg 22,000.00
26 Plamur/Dempul Tembok kg 28,000.00
27 Menie Kayu kg 21,000.00
28 Menie Besi kg 24,000.00
29 Cat Tembok kg 57,000.00
30 Cat Kayu kg 33,500.00
31 Cat Besi kg 40,000.00
32 Roll Cat buah 14,000.00
33 Kuas 3" buah 10,000.00
34 Minyak Cat / Terpentin liter 10,000.00
35 Thiner - B liter 20,000.00
36 Lem Putih kg 8,800.00
37 Hampelas lembar 4,000.00
38 Kunci Pintu buah 55,500.00
39 Kunci Gembok buah 24,000.00
40 Engsel Pintu buah 20,000.00
41 Engsel Pintu Besi buah 25,000.00
42 Slot Pintu Atas Bawah buah 25,000.00
NO URAIAN VULOME HARGA SATUAN (Rp)

1 2 3 4
43 Bak Penampung 5000 liter Fibre Glass buah 6,500,000.00
44 Lem Paralon Tube 15,000.00
45 Seal Tape roll 7,000.00
46 Isolatif roll 6,000.00
47 Stop Kran 1" buah 46,000.00
48 Stop Kran 1,5" buah 90,000.00
49 Kran Tembok dia. 3/4" buah 17,000.00
50 Knie GIP dia. 1,5" buah 14,000.00
51 Knie PVC dia. 1" buah 12,000.00
52 L-Booh GIP dia. 1,5" buah 18,000.00
53 T GIP dia. 1,5" buah 19,000.00
54 T GIP dia. 1,5" ke 3/4 buah 21,500.00
55 T PVC dia. 1" buah 6,000.00
56 T PVC dia. 1" ke 3/4" buah 7,000.00
57 Check Valve buah 291,000.00
58 Socket Drat Dalam PVC dia. 3/4" buah 5,800.00
59 Sock Drat Dalam, PVC dia. 1" buah 5,000.00
60 Sock Drat Luar, PVC dia. 1" buah 5,000.00
61 Sock Drat Luar GIP dia. 1" buah 5,000.00
62 Sock Drat Dalam, GIP dia. 1,5" buah 5,600.00
63 Sock Drat Luar, GIP dia. 1,5" buah 5,650.00
64 Soket GIP dia 1,5" buah 28,750.00
65 Soket GIP dia 1" buah 23,700.00
66 Water Mur 1,5" buah 20,700.00
67 Manometer Pressure Gauge buah 49,500.00
68 Water Meter dia. 1,5" buah 840,000.00
69 Pipa PVC dia. 1" m1 21,500.00
70 Pipa GIP dia. 1" m1 93,500.00
71 Pipa GIP dia. 1,5" m1 139,500.00
72 Pipa GIP dia. 6" m1 397,500.00
73 Screen Low Carbon dia. 6" m1 678,500.00
74 Sling Baja 5 mm m1 80,000.00
75 Plate Top buah 145,000.00
76 Plate Bottom buah 145,000.00
77 Bentonit kg 17,000.00
78 Oli Mesin liter 22,500.00
79 Oli Hidrolis liter 22,500.00
80 Stempet kg 14,000.00
81 Solar liter 9,250.00
82 Bensin liter 7,800.00
83 Water Circulation unit 3,850,000.00
84 Air Lifting/Kompresor unit 4,750,000.00
85 Tinta Logging botol 230,200.00
86 Kertas Kerja Logging roll 143,900.00
87 Mesin Genset .... KVA unit 71,200,000.00
88 Pompa Selam 3 PK unit 15,200,000.00
89 Panel Pompa & Accessories unit 7,550,000.00
90 Klem Pipa 1,5" buah 10,200.00
91 Baut + Mur 12mm buah 17,200.00
92 Angker Besi Baut + Mur 16mm buah 40,500.00
NO URAIAN VULOME HARGA SATUAN (Rp)

1 2 3 4
Kota, ......
PT.

Direktur
DAFTAR HARGA UPAH DAN SEWA

HARGA UPAH
NO. URAIAN SATUAN
(Rp)

1 2 3 4

HARGA UPAH PERSONIL


1 Pekerja 80,000 Orang / hari
2 Tukang 100,000 Orang / hari
3 Kepala Tukang 150,000 Orang / hari
4 Mandor 150,000 Orang / hari
5 Ahli Geofisika 200,000 Orang / hari
6 Ass. Ahli Geofisika 175,000 Orang / hari
7 Ahli Geologi 200,000 Orang / hari
8 Ass. Ahli Geologi 175,000 Orang / hari
9 Ahli Hidrogeologi 200,000 Orang / hari
10 Ass. Ahli Hidrogeologi 175,000 Orang / hari
11 Driver 70,000 Orang / hari
12 Driller 175,000 Orang / hari
13 Ass. Driller 150,000 Orang / hari
14 Operator 130,000 Orang / hari
15 Ass. Operator 100,000 Orang / hari
16 Helper 80,000 Orang / hari
17 Mekanik 85,000 Orang / hari
18 Tool Fusher 45,000 Orang / hari
19 Welder 70,000 Orang / hari

HARGA SEWA PERALATAN OPERASIONAL


1 Kendaraan Roda 6 700,000 Unit / hari
2 Kendaraan Roda 4 500,000 Unit / hari
2 Peralatan Pengeboran 710,000 Unit / hari
3 Peralatan Logging/Uji potensi air 450,000 Unit / hari
4 Mesin Pumping Test, EC Meter, PH meter, 400,000 Unit / hari
Termometer, TDS Meter, Water Circulation dan GPS
5 Mesin Las 400,000 Unit / hari

Kota, ...............
PT.

Direktur
TIME SCHEDULE

BULAN
Bobot Skala
NO. URAIAN PEKERJAAN HARGA (Rp) Pekerjaan BULAN KE 1 BULAN KE 2 BULAN KE 3 BULAN KE 4 BULAN KE 5 BULAN KE 6 BULAN KE 7 BULAN KE 8 Bobot Keterangan
(%) (%)
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
I. PEK.PERSIAPAN & MOB - DEMOBILISASI
1.1 Persiapan Peralatan Pengeboran dan Material 20,856,000.00 0.210 0.063 0.063 0.042 0.042 100
1.2 Uji Potensi air 130,020,000.00 1.310 0.393 0.393 0.262 0.262
1.3 Transportasi Peralatan Pengeboran dan Material 410,000,000.00 4.132 0.826 0.826 0.826 0.413 0.413 0.413 0.413
1.4 Site Clearing 20,856,000.00 0.210 0.070 0.070 0.070
1.5 Spoel Bak 89,364,000.00 0.901 0.270 0.270 0.180 0.180
1.6 Rig Set-Up 45,936,000.00 0.463 0.154 0.154 0.154
1.7 Papan Nama Proyek 12,000,000.00 0.121 0.040 0.040 0.040
1.7 Biaya K3 dan Keselamatan Konstruksi 76,000,000.00 0.766 0.230 0.230 0.153 0.153
II. PENGEBORAN -
2.1 Pilot Hole dia. 6" : 1,186,800,000.00 11.960 1.196 1.196 1.196 1.196 1.196 1.196 0.797 0.797 0.797 0.797 0.797 0.797 75
2.2 Geophysical Well Logging + Interpretasi -
2.2.1 Resistivity Log : -
- Short Normal Log 30,720,000.00 0.310 0.103 0.103 0.103
- Long Normal Log 30,720,000.00 0.310 0.103 0.103 0.103
2.2.2 Self Potential Log 30,720,000.00 0.310 0.103 0.103 0.103
2.3 Reaming Hole dia. 12" 859,680,000.00 8.664 1.444 1.444 1.444 1.083 1.083 1.083 1.083
III. KONSTRUKSI SUMUR -
3.1 Pipa Jambang dia. 6", GIP, 960,187,200.00 Jangka Waktu
9.676 1.451 1.451 1.451 1.451 0.645 0.645 0.645 0.645 0.645 0.645
Pelaksanaan
3.2 Screen Low Carbon dia. 6" 394,675,200.00 3.977 0.795 0.795 0.795 0.795 0.795 50 240 (Dua Ratus
Empat Puluh)
3.3 Gravel Pack 29,436,000.00 0.297 0.099 0.099 0.099 hari kalender
3.4 Cement Grouting 73,123,200.00 0.737 0.184 0.184 0.184 0.184
3.5 Pipa Naik dia. 1,5", GIP 311,904,000.00 3.143 0.524 0.524 0.524 0.524 0.524 0.524
3.6 Pipa Ukur MAT dia. 1" GIP 222,912,000.00 2.246 0.562 0.562 0.562 0.562
IV. PEMBERSIHAN SUMUR -
4.1 Water Circulation 92,400,000.00 0.931 0.233 0.233 0.233 0.233
4.2 Air Lifting/Kompresor 114,000,000.00 1.149 0.230 0.230 0.230 0.230 0.230
V. UJI PEMOMPAAN -
5.1 Uji Pemompaan 149,553,600.00 1.507 0.377 0.377 0.377 0.377 25
5.2 Analisa Air Tanah 14,400,000.00 0.145 0.048 0.048 0.048
VI. PERLENGKAPAN SARANA -
6.1 Genset Mesin Genset ... KVA 1,884,564,000.00 18.992 2.216 2.216 2.216 2.216 2.216 2.216 1.424 1.424 1.424 1.424
6.2 Pompa Selam 3 PK 752,040,000.00 7.579 1.516 1.516 1.516 1.516 1.516
Beserta Panel & Accessories -
6.3 Rumah Genset, Rumah Sumur Bor, dan 1,959,729,600.00 19.749 1.975 1.975 1.975 1.975 1.975 1.975 1.975 1.975 1.975 1.975
Bak Penampungan Air
-
VII. PENYUSUNAN LAPORAN 20,400,000.00 0.206 0.103 0.103 0

JUMLAH 9,922,996,800.00 100.00


JUMLAH BOBOT 100%

RENCANA BOBOT PERMINGGU (%) 0.103 1.512 1.449 2.363 3.595 4.790 4.893 8.346 6.307 5.111 4.695 5.208 3.949 1.315 1.085 0.901 0.880 0.869 1.305 2.087 3.321 4.331 5.130 2.400 2.430 1.273 2.190 3.321 7.528 5.130 2.078 0.103
KUMULATIF RENCANA BOBOT PERMINGGU (%) - 0.103 1.616 3.065 5.427 9.023 13.813 18.706 27.052 33.359 38.470 43.166 48.374 52.323 53.638 54.724 55.625 56.505 57.374 58.679 60.765 64.086 68.417 73.547 75.947 78.377 79.651 81.840 85.161 92.690 97.819 99.897 100.000

Kota, ...............
PT.

0.00
Direktur
JADWAL PELAKSANAAN

BULAN I BULAN II BULAN III BULAN IV BULAN V BULAN VI BULAN VII BULAN VIII
NO. URAIAN PEKERJAAN KETERANGAN
MG-1 MG-2 MG-3 MG-4 MG-1 MG-2 MG-3 MG-4 MG-1 MG-2 MG-3 MG-4 MG-1 MG-2 MG-3 MG-4 MG-1 MG-2 MG-3 MG-4 MG-1 MG-2 MG-3 MG-4 MG-1 MG-2 MG-3 MG-4 MG-1 MG-2 MG-3 MG-4

I. PERSIAPAN DAN MOB-DEMOB

II. PENGEBORAN

III. KONSTRUKSI SUMUR Jangka Waktu


Pelaksanaan
240 (Dua Ratus
IV. PEMBERSIHAN SUMUR Empat Puluh)
hari kalender

V. UJI PEMOMPAAN

VI. PERLENGAKAPAN SARANA

VII. PENYUSUNAN LAPORAN

Kota, ...............
PT.

Direktur

Anda mungkin juga menyukai