REKAPITULASI ANGGARAN BIAYA ( RAB)

PEKERJAAN : REHAB RUMAH TYPE 45


LOKASI : PONTIANAK
TAHUN ANGGARAN : 2021

NO. URAIAN PEKERJAAN SUB JUMLAH HARGA (Rp.) JUMLAH HARGA (Rp.) BOBOT PEKERJAAN %

1 2 3 4 5
0.39
I. PEKERJAAN PENDAHULUAN 500,000.00

II. PEKERJAAN REHAB RUMAH TYPE 45 126,256,082.79


A Pekerjaan Pondasi 16,343,960.00 12.89
B Pekerjaan Struktur Beton Bertulang 49,307,180.00 38.90
C Pekerjaan Lantai, Dinding dan Plafond 38,331,053.02 30.24
D Pekerjaan Pintu dan Ventilasi 1,750,000.00 1.38
E Pekerjaan Kuda-Kuda & Penutup Atap 9,360,000.00 7.38
F Pekerjaan Pengecatan 6,038,889.77 4.76
G Pekerjaan Elektrikal 1,265,000.00 1.00
H Pekerjaan Lain- Lain 3,860,000.00 3.05

J U M L A H …………………….. Rp 126,756,082.79 100.00


DIBULATKAN …………………… Rp 126,756,000.00

TERBILANG : Seratus Dua Puluh Enam Juta Tujuh Ratus Lima Puluh Enam Ribu Rupiah
DAFTAR KUANTITAS HARGA
PEKERJAAN : REHAB RUMAH TYPE 45
LOKASI : PONTIANAK
TAHUN ANGGARAN : 2021

N URAIAN PEKERJAAN UNI PERKIRAAN BIAYA BOBOT


O T HARGA SATUAN JUMLAH BIAYA PEKERJAAN
( Rp. ) VOLUME ( Rp. ) %
1 2 4 5 6 7 8
I. PEKERJAAN PENDAHULUAN Lsm 500,000.00 1.00 500,000.00 0.39
1 Pengukuran Dan Pembersihan Lokasi Sub Jumlah I 500,000.00 0.39
II PEKERJAAN REHAB RUMAH TYPE 45
A Pekerjaan Pondasi
1 Galian Tanah M3 54,000.00 12.64 682,560.00 0.54
2 Urugan Pasir Alas Pondasi M3 125,000.00 1.94 242,500.00 0.19
3 Lantai Kerja M3 675,000.00 0.49 330,750.00 0.26
4 Cerucuk Ø 8/10 - 4 m + Pemancangan M' 20,000.00 240.00 4,800,000.00 3.79
5 Cerucuk Ø 8/10 - 4 m + Pemancangan M' 20,000.00 108.00 2,160,000.00 1.70
6 Pondasi P1 (Setempat Uk. 0,90 x 0,90 m)
- Camp. 1 : 2 : 3 M3 890,000.00 1.72 1,530,800.00 1.21
- Tulangan Kg 15,000.00 210.06 3,150,900.00 2.49
- Bekisting M2 98,000.00 3.24 317,520.00 0.25
7 Kolom Pondasi Uk. 20x20 cm
- Camp. 1 : 2 : 3 M3 890,000.00 0.50 445,000.00 0.35
- Tulangan Kg 15,000.00 147.19 2,207,850.00 1.74
- Bekisting M2 98,000.00 3.02 295,960.00 0.23
8 Urugan Kembali M3 19,000.00 9.48 180,120.00 0.14
Sub Jumlah A 16,343,960.00 12.89
B Pekerjaan Struktur Beton Bertulang
1 Balok Lantai Uk. 20/50 cm
- Camp. 1 : 2 : 3 M3 890,000.00 4.10 3,649,000.00 2.88
- Tulangan Kg 15,000.00 285.07 4,276,050.00 3.37
- Bekisting M2 98,000.00 14.90 1,460,200.00 1.15
2 Balok Lantai Uk. 15/30 cm
- Camp. 1 : 2 : 3 M3 890,000.00 0.10 89,000.00 0.07
- Tulangan Kg 15,000.00 22.54 338,100.00 0.27
- Bekisting M2 98,000.00 0.79 77,420.00 0.06
3 Plat Lantai t = 10 cm
- Camp. 1 : 2 : 3 M3 890,000.00 4.68 4,165,200.00 3.29
- Wire Mesh 2 x M5 Kg 18,000.00 99.68 1,794,240.00 1.42
4 Kolom Uk. 20x20 cm
- Camp. 1 : 2 : 3 M3 890,000.00 1.92 1,708,800.00 1.35
- Tulangan Kg 15,000.00 229.61 3,444,150.00 2.72
Bekisting M2 98,000.00 11.52 1,128,960.00 0.89
5 Kolom Praktis Uk. 10x10 cm -
- Camp. 1 : 2 : 3 M3 890,000.00 0.16 142,400.00 0.11
- Tulangan Kg 15,000.00 33.36 500,400.00 0.39
- Bekisting M2 98,000.00 1.92 188,160.00 0.15
6 Kolom Lt 2 Uk. 15x15 cm
- Camp. 1 : 2 : 3 M3 890,000.00 1.08 961,200.00 0.76
- Tulangan Kg 15,000.00 66.68 1,000,200.00 0.79
- Bekisting M2 98,000.00 8.64 846,720.00 0.67
6 Balok Anak Uk. 10/20 cm -
- Camp. 1 : 2 : 3 M3 890,000.00 0.10 89,000.00 0.07
- Tulangan Kg 15,000.00 15.12 226,800.00 0.18
- Bekisting M2 98,000.00 0.46 45,080.00 0.04
7 Balok Lt 2 Uk. 20/30 cm
- Camp. 1 : 2 : 3 M3 890,000.00 2.50 2,225,000.00 1.76
- Tulangan Kg 15,000.00 193.09 2,896,350.00 2.28
- Bekisting M2 98,000.00 9.94 974,120.00 0.77
8 Plat Lantai 2 t = 10 cm
- Camp. 1 : 2 : 3 M3 890,000.00 4.08 3,631,200.00 2.86
- Wire Mesh 2 x M5 Kg 15,000.00 199.36 2,990,400.00 2.36
- Bekisting M2 98,000.00 14.04 1,375,920.00 1.09
9 Ring Balok Uk. 15/30 cm
- Camp. 1 : 2 : 3 M3 890,000.00 1.90 1,691,000.00 1.33
- Tulangan Kg 15,000.00 193.09 2,896,350.00 2.28
- Bekisting M2 98,000.00 9.32 913,360.00 0.72
10 Tangga
- Camp. 1 : 2 : 3 M3 890,000.00 2.36 2,100,400.00 1.66
- Tulangan Kg 15,000.00 41.20 618,000.00 0.49
- Bekisting M2 200,000.00 4.32 864,000.00 0.68
Sub Jumlah B 49,307,180.00 38.90
N PERKIRAAN BIAYA
O HARGA JUMLAH BOBOT
URAIAN PEKERJAAN UNIT VOLUM
SATUAN BIAYA PEKERJAAN
E
( Rp. ) ( Rp. ) %
1 2 4 5 6 7 8
C Pekerjaan Lantai, Dinding dan Plafond
1 Dinding Batako Uk. 15/30/7 M2 98,000.00 172.46 16,901,291.41 13.33
2 Plesteran Dinding Batako M2 56,000.00 323.92 18,139,761.61 14.31
3 Plesteran Kolom Dan Balok M2 56,000.00 58.75 3,290,000.00 2.60
Sub Jumlah C 38,331,053.02 30.24
D Pekerjaan Pintu dan Ventilasi
1 Pintu BH 600,000.00 1.00 600,000.00 0.47
2 Jendela BH 450,000.00 2.00 900,000.00 0.71
3 KR2 (Batako Kerawang 2) BH 250,000.00 1.00 250,000.00 0.20
Sub Jumlah D 1,750,000.00 1.38
E Pekerjaan Kuda-Kuda & Penutup Atap
1 Rangka Baja Ringan M2 125,000.00 46.80 5,850,000.00 4.62
2 Atap Spandek M2 75,000.00 46.80 3,510,000.00 2.77

Sub Jumlah E 9,360,000.00 7.38


F Pekerjaan Pengecatan
1 Cat Tembok M2 45,000.00 134.20 6,038,889.77 4.76
Sub Jumlah F 6,038,889.77 4.76
G Pekerjaan Elektrikal
1 Instalasi Titik Lampu Ttk 100,000.00 5.00 500,000.00 0.39
2 Instalasi Stop Kontak Ttk 100,000.00 5.00 500,000.00 0.39
3 Stop Kontak Bh 25,000.00 5.00 125,000.00 0.10
4 Saklar Ganda Bh 35,000.00 4.00 140,000.00 0.11
Sub Jumlah G 1,265,000.00 1.00

G Pekerjaan Lain- Lain


1 Closet Duduk + Aksesoris Bh 1,500,000.00 1.00 1,500,000.00 1.18
2 Kran + aksesoris Bh 55,000.00 2.00 110,000.00 0.09
3 Gorong-gorong Septictank + aksesoris Bh 200,000.00 3.00 600,000.00 0.47
4 Instalasi Pipa Set 250,000.00 6.00 1,500,000.00 1.18
5 Atap Bening Lsm 150,000.00 1.00 150,000.00 0.12
Sub Jumlah G 3,860,000.00 3.05
Sub Jumlah IV 126,756,082.79 100.00