Tingkat
Bobot (%) Kerusakan
N Komponen
Sub Komponen Bangunan Terhada Bobo Nilai
o Bangunan Kerusakan
p t (%)
Ruang Maksimum (%) (4x6)
(1) (2) (3) (4) (5) (6) (7)
1 Atap a. Penutup Atap 10,56% 100% 35 3,70%
b. Rangka Atap 11,62% 100% 40 4,65%
c. Lis Plang & Talang 2,06% 100% 100 2,06%
2 Plafon a. Rangka Plafon 4,67% 100% 50 2,34%
b. Penutup & Lis Plafon 5,06% 100% 25 1,27%
c. Cat 1,41% 100% 40 0,56%
3 Dinding a. Kolom & Balok Ring 9,66% 100% 25 2,42%
b. Bata / Dinding Pengisi 13,68% 100% 25 3,42%
c. Cat 1,65% 100% 80 1,32%
4 Pintu & Jendela a. Kusen 2,70% 100% 35 0,95%
b. Daun Pintu 2,47% 100% 50 1,24%
c. Daun Jendela 5,15% 100% 50 2,58%
5 Lantai a. Struktur Bawah 2,89% 100% 20 0,58%
b. Penutup Lantai 8,96% 100% 35 3,14%
6 Pondasi a. Pondasi 11,15% 100% 30 3,35%
b. Sloof 3,30% 100% 35 1,16%
7 Utilitas a. Listrik 1,79% 100% 30 0,54%
b. Instalansi Air Hujan & 100 1,22%
pasang rabat beton 1,22% 100% 0 0,00%
keliling bangunan 0
JUMLAH 100,00% 0 36,45%