MINGGU PERTAMA
1 SENIN
25 OKTOBER
2 SELASA 8 Jam
26 OKTOBER
7 MINGGU
01-Nov-21
JUMLAH
NO BAHAN DAN ALAT MATERIAL SAT PEMASUKAN BAHAN MATERIAL MINGGU
INI
SENIN SELASA RABU KAMIS JUMAT SABTU MINGGU
25-OKT 26-OKT 27-OKT 28-OKT 29-OKT 30-OKT 01-Nov
1 BESI DIA 10 Btg 48 48
2 BESI DIA 8 Btg 16 16
3 KAYU KASO 4/6 Btg 6 6
4 KAYU RENG 3/4 Btg 3 10 13
5 PAKU 5 Kg 1 1
6 PAKU 7 Kg 1 1
7 PAKU 10 Kg 1 1
8 KUNCI BESI 10 Pc 1 1
9 KUNCI BESI 8 Pc 1 1
10 KAWAT Rol 1 1
11 BONDEK 0,75 P.5M m 8 8
12 BAMBU Btg 3 10 13
13 Linggis Besar Pc 1 1
14 Linggis Kecil Pc 1 1
15 Bor Modern Pc 1 1
16 Pahat Beton Pc 1 1
17 Kabel 50m Rol 1 1
18 Steker Pc 1 1
19 Jack Pc 1 1
20 Obeng Pc 1 1
21 Mata gerinda Pc 10 10
22 Mata roofing Pc 1 1
23 Batu split m3 1,5 0
24 Papan 9mm Lbr 5 5
25 kaso Ikat 1 1
26 Pin Besi Pc 1 1
LAPORAN BAHAN DAN ALAT
NAMA PEKERJAAN : RENOVASI RUMAH TINGGAL
LOKASI : JL.RAJAWALI BLOK D3/12 GRIYA CINERE, LIMO, DEPOK
PERIODE : 25 OKTOBER - 02 NOVEMBER
27 Semen Zak 20 20
28 Pipa besi Pc 1 1
29 Paku triplek Kg 1 1
30 Ember Cor Pc 20 20
31 Plastik cor m 15 10 25
32 Pasir m3 6,5 0
33 Selotip Listrik Pc 1 1
34 Kunci inggris Pc 1 1
35 Pacul 2 2
36 Sekop pasir 1 1
LAPORAN TENAGA KERJA
NAMA PEKERJAAN : RENOVASI RUMAH TINGGAL
LOKASI : JL.RAJAWALI BLOK D3/12 GRIYA CINERE, LIMO, DEPOK
PERIODE : 25 OKTOBER - 02 NOVEMBER
A. PROGRESS
Chart Title
REALISASI 13.99
SCHEDULE 7.17
1 2 3
DEVIASI 6.82
B. WAKTU PELAKSANAAN
6.82 %
JANGKA WAKTU PELAKSANAAN 45 Hari Kalender
WAKTU BERJALAN 5 Hari Kalender
13.99 % SISA WAKTU 40 Hari Kerja
7.17 %
MATERIAL ONSITE
LAPORAN VISUAL PEKERJAAN MINGGUAN
Project Renovasi
Jl.Rajawali Blok D3/12, Griya Cinere, Limo.
26 Okt 2021
BONGKAR ATAP
LAPORAN VISUAL PEKERJAAN MINGGUAN
Project Renovasi
Jl.Rajawali Blok D3/12, Griya Cinere, Limo.
27 Okt 2021
PEMBESIAN BALOKAN