Anda di halaman 1dari 3

DAFTAR KUANTITAS DAN HARGA

NAMA PENYEDIA : PT. PP PRESISI. Tbk


NOMOR PAKET KONTRAK : HK.02.03/SPK-KTR/PPK 1.2 PJN I JBR/2021/02
TANGGAL KONTRAK : 13 JULI 2021
NAMA PAKET : REHABILITASI JALAN PAMANUKAN-SEWO-LOHBENER-JATIBARANG-PALIMANAN
PROVINSI : JAWA BARAT
Periode Minggu : (1 November sd 7 November 2021)
Pekan : 17

Progres Pekerjaan
No. Mata Perkiraan Harga Jumlah Bobot
Uraian Satuan
Pembayaran Kuantitas Satuan Harga-Harga (%)
S/D Minggu Lalu Minggu Ini S/D Minggu Ini
(Rupiah) (Rupiah)
a b c d e f f Kuantitas (Rupiah) (%) Kuantitas (Rupiah) (%) Kuantitas (Rupiah) (%)

DIVISI 1. UMUM
1.2 Mobilisasi LS 1.00 133,125,000.00 133,125,000.00 0.192% 0.70 93,187,500.00 0.134% - 0.000% 0.70 93,187,500.00 0.134%
1.8.(1) Manajemen dan Keselamatan Lalu Lintas LS 1.00 67,720,000.00 67,720,000.00 0.098% 0.25 16,930,000.00 0.024% - 0.000% 0.25 16,930,000.00 0.024%
1.17.(1a) Pengujian pH Buah 3.00 215,000.00 645,000.00 0.001% 1.00 215,000.00 0.000% - 0.000% 1.00 215,000.00 0.000%
1.17.(1b) Pengujian Oksigen Terlarut (DO) Buah 3.00 240,000.00 720,000.00 0.001% 1.00 240,000.00 0.000% - 0.000% 1.00 240,000.00 0.000%
1.17.(1c) Pengujian Zat Padat Terlarut (TDS) Buah 3.00 230,000.00 690,000.00 0.001% 1.00 230,000.00 0.000% - 0.000% 1.00 230,000.00 0.000%
1.17.(1d) Pengujian Zat Tersuspensi (TSS) Buah 3.00 230,000.00 690,000.00 0.001% 1.00 230,000.00 0.000% - 0.000% 1.00 230,000.00 0.000%
1.17.(1e) Pengujian Biological Oxygen Demand (BOD) Buah 3.00 245,000.00 735,000.00 0.001% 1.00 245,000.00 0.000% - 0.000% 1.00 245,000.00 0.000%
1.17.(1f) Pengujian Chemical Oxygen Demand (COD) Buah 3.00 305,000.00 915,000.00 0.001% 1.00 305,000.00 0.000% - 0.000% 1.00 305,000.00 0.000%
1.17.(1g) Pengujian Coliform Buah 3.00 400,000.00 1,200,000.00 0.002% 1.00 400,000.00 0.001% - 0.000% 1.00 400,000.00 0.001%
1.17.(1h) Pengujian E. Coli Buah 3.00 328,000.00 984,000.00 0.001% 1.00 328,000.00 0.000% - 0.000% 1.00 328,000.00 0.000%
1.17.(1i) Pengujian Destruksi Cu, Pb, Cd, Ni, Fe, Zn, Ag, Co, Mn Buah 3.00 470,000.00 1,410,000.00 0.002% 1.00 470,000.00 0.001% - 0.000% 1.00 470,000.00 0.001%
1.17.(1j) Pengujian Temperatur (Suhu) Buah 3.00 215,000.00 645,000.00 0.001% 1.00 215,000.00 0.000% - 0.000% 1.00 215,000.00 0.000%
1.17.(2a) Pengujian Vibrasi Lingkungan untuk Kenyamanan dan Kesehatan Buah 3.00 725,000.00 2,175,000.00 0.003% 1.00 725,000.00 0.001% - 0.000% 1.00 725,000.00 0.001%
1.17.(2b) Pengujian tingkat getaran kendaraan bermotor Buah 3.00 900,000.00 2,700,000.00 0.004% 1.00 900,000.00 0.001% - 0.000% 1.00 900,000.00 0.001%
1.17.(3a) Pengujian NoX Buah 3.00 413,666.67 1,241,000.00 0.002% - - 0.000% - 0.000% - - 0.000%
1.17.(3b) Pengujian Sulfurdioksida (SO2) Buah 3.00 493,333.33 1,480,000.00 0.002% 1.00 493,333.33 0.001% - 0.000% 1.00 493,333.33 0.001%
1.17.(3c) Pengujian Karbondioksida (CO2) Buah 3.00 533,333.33 1,600,000.00 0.002% 1.00 533,333.33 0.001% - 0.000% 1.00 533,333.33 0.001%
1.17.(3d) Pengujian Hidro Carbon (HC)-CH4 Buah 3.00 513,333.33 1,540,000.00 0.002% 1.00 513,333.33 0.001% - 0.000% 1.00 513,333.33 0.001%
1.17.(3f) Pengujian Total Partikulat (TSP) - Debu Buah 3.00 496,333.33 1,489,000.00 0.002% 1.00 496,333.33 0.001% - 0.000% 1.00 496,333.33 0.001%
1.17.(3g) Pengujian Timah Hitam (Pb) Buah 3.00 475,333.33 1,426,000.00 0.002% 1.00 475,333.33 0.001% - 0.000% 1.00 475,333.33 0.001%
1.19 Keselamatan dan Kesehatan Kerja LS 1.00 232,506,500.00 232,506,500.00 0.335% 0.59 136,016,302.51 0.196% 0.06 12,787,857.50 0.018% 0.64 148,804,160.01 0.214%
1.21 Manajemen Mutu LS 1.00 187,891,666.67 187,891,666.67 0.271% 0.59 109,916,625.00 0.158% 0.06 10,334,041.67 0.015% 0.64 120,250,666.67 0.173%

Jumlah Harga Pekerjaan DIVISI 1 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 643,528,166.67 0.927% 363,065,094.18 0.523% 23,121,899.17 0.033% 386,186,993.34 0.557%

DIVISI 2. DRAINASE
2.3.(16) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 120 x 120 cm M1 18.0 2,205,400.0 39,697,200.00 0.057% - - 0.000% - 0.000% - - 0.000%
2.3.(26) Saluran berbentuk U Tipe DS 3 M1 3,490.00 1,013,785.00 3,538,109,650.00 5.099% 517.20 524,329,602.00 0.756% 265.20 268,855,782.00 0.387% 782.40 793,185,384.00 1.143%

Jumlah Harga Pekerjaan DIVISI 2 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 3,577,806,850.00 5.156% 524,329,602.00 0.756% 268,855,782.00 0.387% 793,185,384.00 1.143%

DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK


3.1.(7) Galian Perkerasan Beraspal dengan Cold Milling Machine M3 2,653.75 183,700.00 487,493,875.00 0.703% 2,653.75 487,493,875.00 0.703% - 0.000% 2,653.75 487,493,875.00 0.703%
3.1.(8) Galian Perkerasan Beraspal tanpa Cold Milling Machine M3 87.60 178,600.00 15,645,360.00 0.023% - - 0.000% - 0.000% - - 0.000%
3.1.(10) Galian Pekerasan Beton M3 34.00 314,400.00 10,689,600.00 0.015% - - 0.000% - 0.000% - - 0.000%

Jumlah Harga Pekerjaan DIVISI 3 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 513,828,835.00 0.741% 487,493,875.00 0.703% 0.000% 487,493,875.00 0.703%

DIVISI 4. PEKERJAAN PREVENTIF

Jumlah Harga Pekerjaan DIVISI 4 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) - - 0.000% 0.000% - 0.000%

DIVISI 5. PERKERASAN BERBUTIR


5.1.(3) Lapis Pondasi Agregat Kelas S M3 7,986.95 233,900.00 1,868,147,605.00 2.692% 561.28 131,283,392.00 0.189% 195.00 45,610,500.00 0.066% 756.28 176,893,892.00 0.255%
5.3.(1.c) Perkerasan Beton Semen Fast Track 24 Jam M3 554.63 1,767,849.20 980,493,362.55 1.413% 254.69 450,257,932.37 0.649% 281.72 498,036,266.81 0.718% 536.41 948,294,199.18 1.367%
SKh.1.5.3.(3) Perkerasan Beton Semen untuk Pembukaan Lalu Lintas Umur Beton > 3 hari < M3 23,871.52 1,407,919.96 33,609,193,073.74 48.437% 10,868.90 15,302,542,133.19 22.054% 2,167.04 3,051,011,830.52 4.397% 13,035.94 18,353,553,963.71 26.451%

Jumlah Harga Pekerjaan DIVISI 5 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 36,457,834,041.29 52.543% 15,884,083,457.57 22.892% 3,594,658,597.33 5.181% 19,478,742,054.90 28.073%

DIVISI 6. PERKERASAN ASPAL

6.1 (2a) Lapis Perekat - Aspal Cair/Emulsi Liter 27,896.4 14,000.0 390,549,600.00 0.563% 27,896.40 390,549,600.00 0.563% - 0.000% 27,896.40 390,549,600.00 0.563%
6.1 (2a) Lapis Perekat - Aspal Cair/Emulsi Liter 26,383.1 11,161.8 294,482,885.58 0.424% 25,064.89 279,769,241.76 0.403% - 0.000% 25,064.89 279,769,241.76 0.403%
6.3(5b) Laston Lapis Aus Modifikasi (AC-WC Mod) Ton 3,237.4 1,365,200.0 4,419,669,546.29 6.370% 2,844.17 3,882,866,298.33 5.596% - 0.000% 2,844.17 3,882,866,298.33 5.596%
6.3(6a) Laston Lapis Antara (AC-BC) Ton 9,057.9 909,100.0 8,234,530,185.39 11.868% 9,165.34 8,332,207,948.52 12.008% - 0.000% 9,165.34 8,332,207,948.52 12.008%
6.3(6b) Laston Lapis Antara Modifikasi (AC-BC Mod) Ton 4,432.7 1,294,300.0 5,737,217,957.94 8.268% 3,937.95 5,096,889,845.64 7.346% - 0.000% 3,937.95 5,096,889,845.64 7.346%
6.3(7b) Laston Lapis Fondasi Modifikasi (AC-Base Mod) Ton 3,781.7 1,259,500.0 4,763,052,409.50 6.864% 3,742.33 4,713,465,594.74 6.793% - 0.000% 3,742.33 4,713,465,594.74 6.793%
6.3.(8) Bahan anti pengelupasan Kg 1,110.4 77,400.0 85,941,284.13 0.124% 292.54 22,642,737.02 0.033% - 0.000% 292.54 22,642,737.02 0.033%

Jumlah Harga Pekerjaan DIVISI 6 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 23,925,443,868.84 34.481% 22,718,391,266.00 32.742% - 0.000% 22,718,391,266.00 32.742%
DIVISI 7. STRUKTUR
7.1 (7a) Beton strukur, fc’20 MPa M3 349.00 938,700.00 327,606,300.00 0.472% 61.60 57,823,920.00 0.083% 11.00 10,325,700.00 0.015% 72.60 68,149,620.00 0.098%
7.1 (8) Beton , fc’15 Mpa M3 1,625.00 880,100.00 1,430,162,500.00 2.061% 270.17 237,776,617.00 0.343% - - 0.000% 270.17 237,776,617.00 0.343%
7.3 (8) Anyaman Kawat Yang Dilas (Welded Wire Mesh) Kg 7,433.70 13,500.00 100,354,950.00 0.145% 1,192.80 16,102,800.00 0.023% 213.00 2,875,500.00 0.004% 1,405.80 18,978,300.00 0.027%
7.9.(1) Pasangan Batu M3 673.82 651,200.00 438,791,584.00 0.632% 78.00 50,793,600.00 0.073% - - 0.000% 78.00 50,793,600.00 0.073%

Jumlah Harga Pekerjaan DIVISI 7 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 2,296,915,334.00 3.310% 362,496,937.00 0.522% 13,201,200.00 0.019% 375,698,137.00 0.541%

DIVISI 8. REHABILITASI JEMBATAN

Jumlah Harga Pekerjaan DIVISI 8 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) - - 0.000% 0.000% - 0.000%

DIVISI 9. PEKERJAAN HARIAN & PEKERJAAN LAIN-LAIN


9.2.(1) Marka Jalan Termoplastik M2 3,912.60 205,600.00 804,430,560.00 1.159% - - 0.000% 100.00 20,560,000.00 0.030% 100.00 20,560,000.00 0.030%
9.2.(6a) Patok Kilometer Buah 6.00 372,300.00 2,233,800.00 0.003% - - 0.000% 0.000% - - 0.000%
9.2.(6b) Patok Hektometer Buah 76.00 85,700.00 6,513,200.00 0.009% - - 0.000% 0.000% - - 0.000%
9.2.(10b) Kereb Pracetak Jenis 2 (Penghalang/Barrier) M1 9,680.00 87,000.00 842,160,000.00 1.214% 2,151.60 187,189,200.00 0.270% - 0.000% 2,151.60 187,189,200.00 0.270%
9.2.(10f) Kereb Pracetak Jenis 6 (Kereb dengan Bukaan) Buah 144.80 127,200.00 18,418,560.00 0.027% - - 0.000% 0.000% - - 0.000%

Jumlah Harga Pekerjaan DIVISI 9 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 1,673,756,120.00 2.412% 187,189,200.00 0.270% 20,560,000.00 0.030% 207,749,200.00 0.299%

DIVISI 10. PEKERJAAN PEMELIHARAAN KINERJA


10.1.(9) Perbaikan Campuran Aspal Panas M3 122.93 2,424,000.00 297,975,048.00 0.429% 87.86 212,972,494.56 0.307% 0.000% 87.86 212,972,494.56 0.307%

Jumlah Harga Pekerjaan DIVISI 10 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 297,975,048.00 0.429% 212,972,494.56 0.307% 0.000% 212,972,494.56 0.307%

JUMLAH HARGA KONSTRUKSI 69,387,088,263.79 100% 40,740,021,926.31 58.714% 3,920,397,478.50 5.650% 44,660,419,404.80 64.364%

PPN 6,938,708,826.38 REALISASI SD MINGGU INI 64.364%


KONSTRUKSI + PPN 76,325,797,090.17 RENCANA SD MINGGU INI 69.697%
DEVIASI -5.333%

Disetujui oleh, Diperiksa oleh, Dibuat Oleh,


Pengguna Jasa Konsultan Pengawas Penyedia Jasa
PPK 1.2 Provinsi Jawa Barat PT Surya Praga PT Nasuma Putra KSO PT PP Presisi Tbk

Sendy Reza Davian, S. MT. Barkah Hidayat, ST Djoko Istamar


Koordinator Pengawas Lapangan Quantity Engineer Asisten Produksi Lapangan
LAPORAN KEMAJUAN FISIK MINGGUAN
PERIODE MINGGU KE 17

Nama Paket : Rehabilitasi Jalan Pamanukan-Sewo-Lohbener-Jatibarang-Palimanan Unit Kerja : PK 1.2 Provinsi Jawa Barat
Kontrak No : HK.02.03/SPK-KTR/PPK 1.2 PJN I JBR/2021/02 Kontraktor Pelaksana : PT PP Presisi Tbk
Tanggal Kontrak : 13-Jul-21 Konsultan Supervisi : PT Surya Praga PT Nasuma Putra KSO

KRONOLOGIS KONTRAK
Masa Pelaksanaan Minggu Ke Pelaksanaan Sisa Masa Pelaksanaan
- Nilai Kontrak : Rp 69,387,088,263.79
- Bobot Bobot
Jumlah Hari Kerja Jumlah Hari Kerja
- (%) (%)
a. NK : Rp 69,387,088,263.79 172 HK 31-Dec-21 17 117 HK 64.364 55 HK 35.636
- Rencana PHO : ###
- Rencana FHO : ###

Progress Pekerjaan
LINGKUP PEKERJAAN
S/D Mg Lalu Mg Ini S/D Mg Ini

BOBOT RENCANA (%) 63.927 5.771 69.697

BOBOT REALISASI (%) 58.714 5.650 64.364

DEVIASI (%) -0.120 -5.333

Disetujui oleh, Diperiksa oleh, Dibuat Oleh,


Pengguna Jasa Konsultan Pengawas Penyedia Jasa
PPK 1.2 Provinsi Jawa Barat PT Surya Praga PT Nasuma Putra KSO PT PP Presisi Tbk

Sendy Reza Davian, S. MT. Barkah Hidayat, ST Djoko Istamar


Koordinator Pengawas Lapangan Quantity Engineer Asisten Produksi Lapangan