Anda di halaman 1dari 1

PMTCover0208-1.

qxd 3/2/08 17:39 Page 35

Assume nothing, challenge everything!

© 2008 Project Manager Today All rights reserved. By downloading this pdf file the recipient agrees to use this information for personal use only and may print one copy.
This pdf may not be copied, altered, or distributed to other parties without the permission of the publishers. First published in this form in Project Manager Today.
Dr David Hillson, director, Risk Doctor & Partners

No-one knows the future with perfect certainty, simple approach can be used to turn project flexibility at all. How can we know which
which of course is why we need risk assumptions into risks. Where an assumption is constraints are set in stone, and which might be
management. But sometimes we try to guess what assessed as likely to be false and it could have a worth changing, if possible?
might happen, and use that information as a basis significant effect on one or more project In the same way that assumptions can be tested
for planning or decision-making. The proper objectives, that assumption should be considered to expose threats, a similar IF-THEN test can be
name for such a guess is an ‘assumption’, and these as a candidate risk. applied to constraints to identify possible
are an important source of risk, for projects, This type of Assumptions Analysis is a powerful opportunities.This starts by listing the constraints,
businesses and life in general. way of exposing project-specific risks, since it then writing statements saying:
Making assumptions is a good way of dealing addresses the particular assumptions made about a ‘IF this constraint could be relaxed or removed,
with an uncertain future when there are a number given project. There are, however, two dangers THEN the effect on the project would be …’
of possible options. It certainly simplifies matters with this technique: We are looking for constraints that could
and allows us to get on with things instead of 1. The first weakness is that this technique can possibly be changed (the IF side has a positive
spending a long time analysing all the possibilities. only consider explicit assumptions, which have probability), and where such a change would be
In its most basic form, an assumption is a decision been consciously made and openly beneficial to the project (a positive impact on the
to proceed on the basis that one option will turn communicated. There are, however, many THEN side). These constraints then present an
out to be correct and the others will not happen. implicit assumptions which we all make every opportunity to the project where something
Projects make a lot of assumptions, especially day, some of which are very risky.Assumptions might be changed in order to promote the
during the planning phase. For example, we might Analysis can’t analyse assumptions that remain achievement of one or more objectives. We can
assume that we fully understand the specification hidden. find them through a simple process of Constraints
and scope, or that our suppliers will deliver on 2. Secondly this approach tends only to identify Analysis that matches Assumptions Analysis, but
time, or that our client will sign-off all approvals downside risks, threats that a particular which tests those imposed restrictions to see if any
within two weeks, or that all key members of our assumption may prove false and result in a might usefully be challenged.
project team will remain for the duration of the problem for the project. Assumptions Analysis Instead of making blind assumptions about the
project. But what happens if we assumed the is not good at identifying opportunities future, or accepting that stated constraints are
wrong thing? In most cases a false assumption because most of our underlying assumptions unchangeable, we should be prepared to challenge
would lead to a problem for the project, since we are optimistic. assumptions and constraints. Asking simple
usually tend to assume that things will go the way The first shortcoming can be overcome by a questions about what might happen in the
we want. facilitated approach to identifying and recording uncertain future can expose significant threats and
Of course, not all assumptions matter equally. assumptions, using someone independent and opportunities, which can then be addressed
There are some assumptions which might prove external to the project to challenge established through the risk process, leading to increased
false without having a significant effect on the thinking. To be fully effective, Assumptions chances of success.
overall project, but there are others where a Analysis needs full disclosure. © February 2008, Dr David Hillson PMP FAPM FIRM FRSA
different outcome could be serious. So we may be For opportunity identification, the technique
assuming that our design team will produce draft can be extended to address and challenge About the author
designs within a month, but we have enough float constraints. These are restrictions on what the Dr David Hillson, PMP, FAPM, FIRM,
in the schedule to cope if it takes two months – project can or cannot do, how it must or must not is an international risk management
the assumption could be false but it wouldn’t proceed, and they are often imposed from outside consultant, and Director of Risk Doctor &
matter too much. On the other hand, if we make the project, for example by management, clients Partners (www.risk-doctor.com). He is a
an assumption that regulatory requirements won’t or regulators. But some of these constraints may popular conference speaker and award-
change before our product is released into the not be as fixed as they first appear – indeed some winning author on risk. He is recognised
market, but in fact they do change, then we could of them might be assumed constraints. In fact it internationally as a leading thinker and
be in real trouble. might be possible for a constraint to be relaxed or practitioner in the risk field, and has made several innovative
contributions to improving risk management.
Fortunately there is a simple process for testing perhaps even removed completely. Sometimes
David is an active member of the global Project
how risky our assumptions might be, and for changing a constraint might not help much, but
Management Institute (PMI) and received the PMI
including them in the risk process if necessary. It’s in other cases it might create the possibility of Distinguished Contribution Award for his work in
called Assumptions Analysis.The first step is to list working more efficiently. developing risk management over many years. He is also a
all the assumptions we have made about our For example, management may have classified Fellow of the UK Association for Project Management
project. A simple IF-THEN statement can be our project as low-priority, resulting in inadequate (APM) and a Fellow of the UK Institute
written for each assumption, in the form: resourcing. But might we be able to get our of Risk Management (IRM).
‘IF this assumption proved to be false, project reclassified and so gain access to better
THEN the effect on the project would be …’ resources? Or perhaps you’ve been told that all david@risk-doctor.com
We can then assess both sides of this statement. detailed design must be completed before any www.risk-doctor.com
On the IF side, we ask how likely the assumption implementation can start? If it was possible to
is to be unsafe. Considering the THEN side tells relax this constraint to permit parallel
us whether it would matter if the assumption was development of low-risk elements, that
wrong. Another way of describing this is to see might be very beneficial to the project
the IF statement as reflecting probability, whereas schedule and save time. On the other hand,
the THEN phrase is about impact.And probability if the project end-date coincides with a major
and impact are the two dimensions of risk. This product launch event, there may be no schedule

RISK DOCTOR
FEBRUARY 2008 35

Anda mungkin juga menyukai