REALISASI VOLUME PEKERJAAN MINGGU KE-20 (TGL.

5 S/D 11 NOV 2021)


URAIAN

AC-BC LEVELING BETON KURUS BETON FS' 45


NO TANGGAL
LEBAR PANJANG VOLUME LEBAR PANJANG VOLUME LEBAR PANJANG VOLUME TIKET
KM KM KM
(M1) (M1) TIKET (TON) (M1) (M1) TIKET (M3) (M1) (M1) (M3)

1 5 NOVEMBER 2021 30+407 - 30+410 (KIRI-1) 3,75 3


(OPRIT AWAL)
30+410 - 30+510 (KIRI-1) 3,75 100 121
18+632 - 18+762 (KIRI-2) 3,75 130 152

2 6 NOVEMBER 2021 30+510 - 30+630 (KIRI-1) 3,75 120 140


18+762 - 18+867 (KIRI-2) 3,75 105 119

3 7 NOVEMBER 2021 19+039 - 19+049 (KIRI-2) 3,75 10 2,50 30+630 - 30+750 (KIRI-1) 3,75 120 143,50
18+867 - 18+982 (KIRI-2) 3,75 115 132,50

4 8 NOVEMBER 2021 20+783 - 20+786 (KIRI-2) 3,75 3


(LIDAH BETON)
20+786 - 20+886 (KIRI-2) 3,75 100 119
9+120 - 9+060 (KANAN-2) 3,75 60
9+480 - 9+415 (KANAN-2) 3,75 65 160,50
18+472 - 18+492 (KIRI-2) 3,75 20
18+982 - 19+059 (KIRI-2) 3,75 77 116,50

5 9 NOVEMBER 2021 20+886 - 20+986 (KIRI-2) 3,75 100 114


20+450 - 20+510 (KIRI-2) 3,75 60 72
9+415 - 9+325 (KANAN-2) 3,75 90
9+060 - 9+025 (KANAN-2) 3,75 35 151

6 10 NOVEMBER 2021 20+986 -21+056 (KIRI-2) 3,75 70 84


20+510 - 20+635 (KIRI-2) 3,75 125 154
9+000 - 9+025 (KANAN-2) 3,75 25
9+325 - 9+225 (KANAN-2) 3,75 100 157

7 11 NOVEMBER 2021 21+056 - 21+141 (KIRI-2) 3,75 85 96


9+225 - 9+135 (KANAN-2) 3,75 90 114
20+430 - 20+450 (KIRI-2) 3,75 20
20+635 - 20+680 (KIRI-2) 3,75 45
20+680 - 20+683 (KIRI-2) 3,75 3 86,5
(LIDAH)

SAMPAI DENGAN MINGGU LALU 14.185 7.841,10 2.623 972,90 14.046 16.340,00
MINGGU INI - - 10 2,50 1.866 2.232,50
SAMPAI DENGAN MINGGU INI 14.185 7.841,10 2.633 975,40 15.912 18.572,50
TOTAL VOLUME ADENDUM-2 9.428,23 1.517,25 22.123,00
SISA VOLUME ADENDUM-2 - 1.587,13 - 541,85 - 3.550,50