REALISASI VOLUME PEKERJAAN MINGGU KE-14 (TGL.

24 S/D 30 SEPTEMBER 2021)


URAIAN

AC-BC LEVELING BETON KURUS BETON FS' 45


NO TANGGAL
LEBAR PANJANG VOLUME LEBAR PANJANG VOLUME LEBAR PANJAN VOLUME TIKET
KM KM KM
(M1) (M1) TIKET (TON) (M1) (M1) TIKET (M3) (M1) G (M1) (M3)

1 24 SEPTEMBER 2021 30+407 - 30+415 (KANAN-1) 3,6 8 29+578 - 29+581 (KIRI-1) 3,75 3
30+407 - 30+736 (KANAN-2) 3,6 329 172,75 (OPRIT AWAL)
29+581 - 29+661 (KIRI-1) 3,75 80 95

9+315 - 9+450 (KIRI-1) 3,75 135 155,5

2 25 SEPTEMBER 2021 12+177 - 11+940 (KANAN-1) 4 237 123,72 29+661 - 29+756 (KIRI-1) 3,75 95 117
9+450 - 9+525 (KIRI-1) 3,85 75
9+525 - 9+528 (KIRI-1)-LIDAH 3,75 3 93,5

3 26 SEPTEMBER 2021 12+177 - 12+035 (KANAN-2) 3,6 142 96,94 29+756 - 29+856 (KIRI-1) 3,75 100 126,5

4 27 SEPTEMBER 2021 12+035 - 11+603 (KANAN-2) 3,6 200 432

5 28 SEPTEMBER 2021 11+940 - 11+662 (KANAN-1) 3,7 278 158,64

6 29 SEPTEMBER 2021 23+150 - 23+275 (KANAN-1) 4,1 124 66,92


TRIAL COMPACT

7 30 SEPTEMBER 2021 11+662 - 11+444 (KANAN-1) 3,9 218 130,06 29+856 - 29+961 (KIRI-1) 3,75 105 126,5
17+075 - 17+130 (KIRI-1) 3,75 55 60
9+015 - 9+110 (KIRI-2) 3,75 95 95,5

SAMPAI DENGAN MINGGU LALU 9.242 4.772,81 2.142 809,50 4.639 5.550,00
MINGGU INI 1.536 1.181 - 0,00 746 870
SAMPAI DENGAN MINGGU INI 10.778 5.953,84 2.142 809,50 5.385 6.420
TOTAL VOLUME ADENDUM 10.042,42 1212,30 22.538,48
SISA VOLUME ADENDUM - 4.088,58 - 402,80 - 16.118,98