Anda di halaman 1dari 445

 

Silver Line 
ITP – The Rapid  Bus Rapid Transit 

 
Task I 
Visioning 
Report 
 
 
 
Submitted By:  
Wilbur Smith Associates 
 
 
 
 
January 21, 2011 
 

 
 
 

SILVER LINE BRT 
ITP – The Rapid 
 
 
 
 
 
 
 
 
 

Final 
Task I Vision Report 
 

January 21, 2011 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Prepared by: 
 
Silver Line BRT 

Table of Contents 
 
1.0  Introduction and Purpose ........................................................................................................................ 1 
 
2.0  Summary of Silver Line Reference Documents ............................................................................... 2 
 
3.0  Design Program for Stations and Roadway ...................................................................................... 4 
 
4.0  Stakeholder Meetings Summary ............................................................................................................ 5 
 
5.0  Station Concepts and Station Compotents ........................................................................................ 7 
 
6.0  Bus Operations and Station Locations ................................................................................................ 9 
 
7.0  Existing Traffic Signals and Modifications....................................................................................... 11 
 
8.0  Prototypical Pavement Marking Plans .............................................................................................. 11 
 
9.0  Communications Features and Interfaces ....................................................................................... 12 
 
10.0  Station Platform Concept Layouts ...................................................................................................... 13 
 
11.0  FTA’s Standard Cost Category (SCC) Workbook for Project Cost Estimate ....................... 14 
 
 
FIGURES 
 
Figure 1  Final Station Concept .................................................................................................................................. 8 
Figure 2   Proposed Station Locations ................................................................................................................... 10 
Figure 3  Final Station Locations ............................................................................................................................ 10 
 
 
APPENDICES 
 
Appendix A  Stakeholder Involvement Meeting Summaries 
Appendix B  Illustrations of Station Concepts 
Appendix C  Mapping of Dedicated/Non‐Dedicated Bus Lanes and Station Locations 
Appendix D  Prototypical Pavement Marking Plans, Roadway Concept Typical Sections and Plans, 
and Station Platform Layouts 
Appendix E  Survey Drawings 
Appendix F  Design Program – Stations Report 
Appendix G  Roadway Program Report 
Appendix H  Bus Operations, Traffic Signals, and Communications Concept Report 
Appendix I  Cost Estimate Report 

  
Task I Vision Report 
Page i 
 
Silver Line BRT 

Final Task I Vision Report 
 
1.0 Introduction and Purpose 
 
The purpose of this report is to summarize the findings of the analysis completed for the Silver Line 
BRT Task I Visioning process and provide information to Interurban Transit Partnership (ITP) – 
The Rapid and the Federal Transit Administration (FTA) to aid in moving the project forward into 
the final design phase.  The overall goal for the Task 1 Visioning was to take the design to a 
programmatic/conceptual level in order to clarify the elements below which will define the nature 
of the project that can be delivered for the budget: 
 
 BRT operations 
 specific station locations and BRT integration with general traffic on the streets 
 components of the station buildings and platforms including the level of quality of those 
components 
 communications between the BRT, stations, traffic signals, ITP, and the cities 
 confirm there are no fatal flaws to integrate the BRT with the ‘built environment” (meet 
ADA requirements at stations and crosswalks and meet roadway design requirements) 
 estimate the project cost 
 
Deliverables to illustrate the above will include: 
 
1. 3‐D visualization of the current VISSIM BRT operation analysis at several intersections to 
illustrate the BRT operation integrated with general traffic and pedestrians. 
2. Prototypical pavement marking plan to illustrate the station locations, lanes for BRT 
operation, and changes to the existing general traffic operation. 
3. Design Program report for Stations and Roadway and Conceptual Station illustrations of 
prototypical stations with catalogue cuts for components (2 or 3 prototypes depending on 
location; Central Business District or non‐Central Business District)   
4. Communication report conceptualizing how the various components (Automatic Vehicle 
Locator, emergency telephone, fare vending machines, Closed Circuit Television, and traffic 
signals) will interface.  
5. Roadway Concept Plans that meet design requirements integrated with existing. 
6. Update FTA’s SCC Workbook for project cost estimates. 
7. Written summary of the stakeholder involvement process. 
  
Level of completion of technical work (engineering and architecture) 
 
A. Architectural – Programmatic/Conceptual 
B. Traffic and Communication Engineering – Programmatic/Conceptual 
C. Roadway Engineering – 10% Level of completion 
 
The Silver Line Bus Rapid Transit (BRT) route runs through three cities; Grand Rapids, Wyoming, 
and  Kentwood  and  includes  33  proposed  Silver  Line  BRT  stations  along  a  9.6  mile  route  running 
from  the  ITP  central  station  to  60th  Street  on  Division  Avenue.    Refer  to  Figure  3  on  page  11  for 
details.    The  overall  vision  for  the  Silver  Line  BRT  is  to  provide  a  first  class  riding  experience  for 
users that is noticeably quicker than regular bus services.  
  
Task I Vision Report 
Page 1 
 
Silver Line BRT 

2.0 Summary of Silver Line Reference 
Documents 
 
2.1   Documents previously developed by ITP 
The Task I Visioning of the Silver Line BRT utilized information previously developed in prior 
stages of the project.  The goal was to pick up the final visioning phase where previous studies left 
off and prevent the need for rework.   Several documents where provided to the team for 
information; 
 
Environmental Assessment 
The Environmental Assessment (EA) for the Silver Line BRT was completed for The Rapid and FTA 
in August 2010.  This EA was prepared to disclose potential environmental effects and to provide 
an opportunity for agency and public comments to identify mitigation measures that would address 
impacts. The EA contains the results of the environmental analyses completed on this project. 
 
Transportation Technical Report 
The Transportation Technical Report was completed as part of the EA to document the detailed 
analysis of the transportation conditions for the Silver Line Study corridor.   The report was 
completed in March 2010. 
 
Operating Plan Detail 
The Operating Plan Detail document was prepared to outline the proposed route of the BRT and the 
high level details of how the system would operate and its interaction with other bus systems.  The 
document was developed at the request of the FTA and Project Management Office Certification 
(PMOC), completed on January 9, 2009. 
 
2.2  Documents Prepared by Wilbur Smith Associates for Task I 
This  team compiled some of the analysis into interim reports that are supplemental to the Task I 
Vision Report as listed below; 
 
Design Program – Stations 
The  purpose  of  this  technical  paper  was  to  prepare  a  design  guide,  to  be  applied  to  developing 
station concepts. It is located in Appendix F. 
 
Roadway Program 
The  purpose  of  this  technical  paper  was  to  identify  the  concept  design  program  for  roadway 
improvements.    This  provided  a  guide  for  the  team  to  follow  when  analyzing  roadway  and  non‐
station needs associated with construction of each station.  It is located in Appendix G. 
 
Bus Operations, Traffic Signals, and Communications Concept Report 
The purpose of this technical paper was to summarize the existing bus, traffic, and communications 
operations in the project area including;  
 
 Summarize the Silver Line BRT operation 
 Traffic and communication functions anticipated to be required for future operations 
  
Task I Vision Report 
Page 2 
 
Silver Line BRT 

 Identify  the  quantity  and  cost  of  new  infrastructure  and/or  equipment  needed  to  be 
included in the project to provide these functions 
 
This report is located in Appendix H. 
 
Cost Estimate Report 
The purpose of this technical paper was to summarize the cost estimating process and to explain 
the details of each component of the estimate as it relates to the BRT stations and systems.  It is 
located in Appendix I. 
 
Survey 
Base survey information was collected at each station location for topographies and utilities which 
are displayed in Appendix E.  It was important to begin analysis of each station and adjoining 
roadway conditions based on accurate data.  The survey provided coordinates and elevations for 
point data at key features, such as curb lines, drainage structures, buildings, and all above ground 
utilities within the vicinity of each station.  The survey was done approximately 100 ft either side of 
the proposed station locations.   
 
Note that the survey does not include legal alignments, ROW, or section corner information. 
 
REGIS Mapping 
The Team worked with REGIS to obtain 2009 aerials of the Silver Line BRT corridor which were 
incorporated into GIS mapping.  The GIS data also included parcel lines which gave the team a high 
level understanding of City right‐of‐way (ROW).  It is important to note that the parcel lines shown 
are not true ROW limits.  The Aerial images are displayed in Appendix C. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

  
Task I Vision Report 
Page 3 
 
Silver Line BRT 

3.0 Design Program for Stations and 
Roadway 
 
Design programs were compiled by the team for stations and roadway components to establish a 
set of design criteria for detailed analysis.  For full descriptions of the station and roadway 
programs refer to two technical papers developed by the team, Design Program – Stations, and 
Roadway Program as displayed in Appendix F and Appendix G.  
 
The station program details the requirements for all components associated with the shelter and 
station platform including the following: 
 
 Station passenger capacity 
 Furnishings inside the station shelter 
 Station shelter lighting 
 Furnishings and utilities on the station platform 
 Platform surface 
 Platform Lighting 
 Safety and security 
 Weather protection and roof drains 
 Station materials 
 Structural design 
 Platform height 
 Horizontal clearance 
 Platform slopes 
 ADA clearances 
 Minimum sidewalk widths 
 
The roadway program details the design requirements and criteria for all components relating to 
roadway and elements outside of the station platform including the following: 
 
 Design speed 
 Dedicated BRT lanes 
 Lane widths 
 Cross sections (number of lanes) 
 Horizontal alignment 
 ADA compliance 
 Horizontal and vertical clearance 
 
The design criteria identified in each design program was used as a base to ensure that each station 
and roadway element met local, state, and federal design standards, and that the functionality of the 
Silver Line BRT met the anticipated needs of the system.  
 
 

  
Task I Vision Report 
Page 4 
 
Silver Line BRT 

4.0 Stakeholder Meetings Summary 
 
As part of the overall visioning process the team reached out to stakeholders within the project 
area and the broader ITP service area in order to receive stakeholder input and communicate 
project benefits.  Meeting invite letters were prepared by the project team and then sent out to the 
stakeholders by ITP staff.  The overall approach was to review the BRT program and product with 
stakeholders through a series of four meeting sets scheduled in advance to coincide with specific 
project “Work Product” events. 
 
Four meetings (conducted in either one or two day periods) were held for each meeting at locations 
selected by ITP in the project service area.  The purpose of the meetings was to present decisions 
made at previous meetings, discuss how those decisions were folded into the project 
concept/vision, and receive stakeholder input.  The two locations for the meetings were Tommy 
Brann’s on south Division Avenue, and The Rapid Central Station.  The meeting topics were as 
follow: 
 
Meeting Set #1 – Overall BRT Route and BRT Operations, 3D VISSIM traffic model, Station 
Program, and Station Locations.  
 
Meeting Set #2 – Conduct Design Charrette centered around development of station 
concepts. 
 
Meeting Set #3 – Station Design Concept Development (presented to ITP staff, board and 
municipal stakeholders). 
 
Meeting Set #4 – Summary of design concept and overall process to stakeholders. 
 
As part of Meeting Set #2 a 3D traffic simulation was developed using VISSIM to illustrate traffic 
and bus operations at a couple of key intersections.  Future peak traffic was utilized with 
overpopulated buses and pedestrians to illustrate potential conflicts and operation issues under 
future peak conditions.  The analysis showed that the Silver Line BRT will not result in any 
additional adverse congestion or conflicts due to the proposed project. 
 
The following is a general summary of comments received regarding the overall development of the 
BRT Stations. 
 
General Shelter Structure Look & Feel 
The shelters should be a visually distinctive design which is simple, functional and easy to maintain.  
The shelter design should pick up on the ‘iconic’ look and feel already existing in Grand Rapids; in 
the ‘Le Grande Vatesse’ and in the rooflines of DeVos Place and the Rapid Central Station.  Shelters 
shall provide all required operational components while blending in with their surroundings yet 
still provide the branding and tall visual element to distinguish the shelter as a BRT station 
 
Weather Protection & Maintenance Concerns 
Provide ridership with protection from rain, wind and snow, salt/slush splash & icicles and 
maintain clean stations year around.  Discharge roof run‐off into the sewer system to avoid ice 
forming on the sidewalks. 

  
Task I Vision Report 
Page 5 
 
Silver Line BRT 

Sustainability Practices & Energy 
Take advantage of opportunities to incorporate ‘green’ design principals into the stations to keep in 
concert with the Green Grand Rapids initiative. 
 
Neighborhood Communication 
Station design should incorporate individual links to neighborhood via design expression, event 
announcement and/or artwork 
 
Visual, Audio and Surface Accommodations 
Shelters must be all inclusive in providing for riders needs using the latest audio and visual 
technology equipment, materials and surfaces. 
 
Advertisement & Naming Rights 
Take advantage of any marketing or advertizing opportunities with which funds could be used for 
station upkeep. 
 
Bicycle Advocacy & Accommodation  
Transit Vehicles and Stations as a leading part of the transportation network can and must 
acknowledge the place of bicycles as a viable alternative to the car.  Bike lanes, as part of the 
‘Complete Streets” movement, are envisioned in the future. All forms of at‐the‐station bike 
provisions should be available at appropriate station locations frequented by bicyclist.  The plan to 
allow riders to bring their bike on the transit vehicle was well received. 
 
Meeting Summaries were prepared for all four meeting sets and are included in Appendix A.  
Appendix A contains two lists of stakeholders and/or contacts.  The first list was the original 
stakeholder list that The Rapid used to notify stakeholders of upcoming meetings.  The second list 
was compiled from the original stakeholder list and all of those people that attended the meetings. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

  
Task I Vision Report 
Page 6 
 
Silver Line BRT 

5.0 Station Concepts and Station 
Components 
 
Following Meeting Set 2 the consultant team commenced development of the initial station 
concepts utilizing the information obtained from the stakeholder meetings along with input 
provided by ITP staff at prior meetings.  During the development of the station design concepts, the 
consultant team held a series of meetings with ITP staff and city staff from Grand Rapids, Wyoming, 
and Kentwood.  The purpose for the meetings was to guide the station concept development 
process and obtain valuable input in order for the team to create the proposed concepts as 
accurately as possible.  This iterative process allowed the team to get to a preferred concept much 
quicker and efficiently and provided the opportunity for the city stakeholders to provide input very 
early in the process.  The series of meetings held with ITP and city officials are listed below.  The 
meeting minutes are located in Appendix A.  Four draft concepts were prepared initially which 
were presented to ITP staff for review and comment.  One of these concepts was clearly favored by 
ITP staff which was then refined into a more detailed concept.  This concept was then brought back 
to ITP for further review and comment. 
 
October 20, 2010  ITP Staff 
October 26, 2010  ITP Staff 
October 27, 2010  ITP Staff and City Stakeholders 
October 27, 2010  ITP Board Members and members of public 
November 4, 2010  Wyoming and Kentwood City Staff 
November 5, 2010  Grand Rapids City Staff 
 
The final station concept shown in Figure 1 is a result of multiple meetings with stakeholders, ITP 
staff, and consultant team members.  The design reflects the identity of Grand Rapids and meets the 
requirements as outlined in the Station Program.  All of the concepts developed during this 
conceptual development process are shown in Appendix B. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
  
Task I Vision Report 
Page 7 
 
Silver Line BRT 

Figure 1 – Final Station Concept 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

  
Task I Vision Report 
Page 8 
 
Silver Line BRT 

6.0 Bus Operations and Station Locations 
 
The team assessed the operating needs of the Silver Line – BRT vehicles and the existing and 
proposed systems needs.   Specific station locations and dedicated lanes were analyzed and all are 
discussed in detail in the Bus Operations, Traffic Signals, and Communications Concept Report.  
Each of these components is critical to ensuring the Silver Line BRT provides first class and 
expedited service.  
 
Dedicated bus lanes are essential to an expedited service and were recommended at every location 
unless pavement widths negated additional lanage or if signal operations required shared lanes.  
Maps prepared to illustrate dedicated lane locations are located in Appendix C and the back of 
Appendix H.  The dedicated bus lanes allow only for BRT and regular buses to access the lane.  A 
preliminary recommendation to provide shared lanes at some signals (Burton, 28th, 36th, 44th, and 
54th) was made based on the EA traffic analysis and on field observations by the design team.  
Further traffic analysis will be required in the design phase to validate these recommendations. 
 
Each station was located based on the preliminary locations identified in the Environmental 
Assessment (EA) and adjusted to comply with the design program for stations and roadways.   The 
team looked at optimizing locations to avoid conflicts with existing driveways and some stations 
were relocated downstream of signals that were previously proposed upstream.  This is to allow 
Transit Signal Priority (TSP) to be affective (see Section 7.0). TSP provides an extended green time 
for buses drive through a signal if it is close before the signal turns red.  Several busy intersections 
were proposed not to include TSP to prevent additional delay to general purpose traffic. 
 
Figure 2 shows the proposed station locations including the changes made from the EA.  A few 
stations were shifted slightly to locate the station in a better location due to adjacent land use 
and/or building locations, while others were relocated entirely to allow better operational 
efficiencies for the proposed BRT system. At the south end of the project, it was determined only a 
northbound station would be provided on the east side of Division Street just north of 60th Street.  
Figure 3 shows the final station locations selected. 
 
Each Silver Line BRT Station will require a set of operating hardware devices: 
 
 Off‐board fare collection 
 “Next Bus” signs and audio 
 Audio station announcements on the bus 
 Ticket vending machine 
 Emergency telephone with CCTV camera 
 Fare validation device 
 Smart card reader 
 Passenger information sign and kiosk 
 
 
 
 
 
 
  
Task I Vision Report 
Page 9 
 
Silver Line BRT 

Figure 2 –Proposed Station Locations 
 
 
Legend   
Proposed BRT Alignment from EA
 

  Proposed BRT Station from EA 
 
BRT Station Relocation 

   
BRT Station Adjustment 
 

  BRT Station Removal 

Freeway 

  Major Road 
Highway 
Railroad 

 
 
 
 
  Downtown Inset

 
 
 
 
 
 
 
 
 
 
 
 
 
Figure 3 –Final Station Locations 
 

  
Task I Vision Report 
Page 10 
 
Silver Line BRT 

7.0 Existing Traffic Signals and 
Modifications 
 
The design team assessed each signal on the proposed Silver Line BRT route to ensure that Transit 
Signal Priority (TSP) would be possible and to identify the type of signals utilized at each location.  
OpticomTM is a communications device installed on each signal that allows vehicles installed with a 
transmitting devise (On‐board Equipment) to alter the signal timings.  Emergency vehicles use this 
system to preempt a signal to turn green at any time when approaching.  Silver Line BRT vehicles 
will be installed with OpticomTM On‐board Equipment to allow signal prioritization which operates 
similar to emergency vehicles TSP, only the difference being that the signal cannot be changed from 
red, instead the green can be extended until the BRT vehicle clears the signal.   Most existing signals 
on the Silver Line route have OpticomTM installed with the exception of signals on Ransom which 
will need to be installed as part of this project.   
 
The OpticomTM system is currently operational and works great, however technology is moving 
toward GPS based systems which would operate similarly to the existing system.  If this system is 
installed by each of the Cities then the Silver Line BRT would also need to upgrade the On‐board 
equipment.  At several intersections there are currently no countdown timers for pedestrian 
crossings. The design team assumed that up to 50 percent of signals would need to be upgraded to 
allow for safer pedestrian movements and to bring the crossings up to current design standards. 
 
The design team feels comfortable that the Silver Line BRT will be able to function as desired with 
the existing traffic signals and as new technology is introduced, modifications to On‐board 
Equipment will enable the system to continue operating well. 
 
8.0 Prototypical Pavement Marking 
Plans 
 
Pavement markings were preliminarily designed at each station location to illustrate how dedicated 
BRT lanes will interact with general purpose lanes, and to highlight changes in intersection 
operations such as dedicated bus lanes as displayed in Appendix D.  The striping plans show 
locations of dedicated bus lanes, non‐dedicated lanes and the lane transitions 
between them.  In addition the plans indicate the general condition of the 
roadway pavement and any proposed improvements planned by each of the 
cities, of Kentwood, Wyoming and Grand Rapids. 
 
The design team determined that the existing roadway conditions can safely 
accommodate the Silver Line BRT system with minor modifications to the 
roadway using pavement markings and signage.  The dedicated BRT lanes will 
be denoted with a six‐inch dashed white line and preferential lane‐use 
markings, as shown on the prototypical pavement marking plans.  Roadside 
signs will also denote the hours of operation of the dedicated BRT lanes. 
The prototypical pavement marking plans will be designed in more detail  Example of Buses 
during the design phase of this project.  Only roadside sign 
  
Task I Vision Report 
Page 11 
 
Silver Line BRT 

9.0 Communication Features and 
Interfaces 
 
Functional requirements for communications of station components, BRT vehicles, and the central 
office were identified as part of this study and are discussed in detail in the Bus Operations, 
Traffic Signals, and Communications Concept Report.    
 
Several key components of the communications system were analyzed as part of this project: 
 
 Technology / Topography ‐ Referred to as the “backbone” of the communications 
system and is the node that carries information between the various devices.    
 Bandwidth ‐ Defines the capacity of a system 
 Availability ‐ Availability of the bandwidth 
 Scalability ‐ Account for future needs 
 Quality of Service 
 Security 
 Reliability and Maintainability 
 Resilience, Survivability and Redundancy 
 Equipment Housing, Environmental Control and Electrical Power 
 
The communications devices needed for the Silver Line BRT are: 
 
 Emergency Telephone 
 Closed Circuit Television (CCTV) 
 Fare Validation 
 “Next Bus” Arrival Time Sign 
 Ticket Vending Machines 
 Smart Card Readers 
 Passenger Information Signs and Kiosk 
 
The design team determined the communication needs required to allow the the Silver Line BRT 
service to become operational and also provided a high level look at integrating the new service 
with existing systems.  It was identified that the existing Automatic Vehicle Locator (AVL) software 
will need to be upgraded to allow the next bus information to display accurately. Also, the fiber 
optic network, needed to carry information between the stations is currently incomplete.  
Additional segments of fiber optic cable need to be added for the Silver Line BRT system to be fully 
operational.  
 
 
 
 
 
 
 

  
Task I Vision Report 
Page 12 
 
Silver Line BRT 

10.0 Station Platform Concept Layouts 
 
Preliminary Engineering was performed at each station location to assess the potential impacts of 
constructing station platforms, pads, and shelters.  A set of detailed drawings of each station 
platform are located in Appendix D. 
 
The concept designs were based on surveyed topography and the REGIS mapping, and complied 
with the design criteria as discussed in Section 3.0.  The intent of the design effort for the Task I 
Visioning was to determine whether station construction at each location was feasible and look at 
potential construction issues associated with the platform, pad, and shelter.  The following items 
were analyzed at each station location: 
 
 Utility impacts based on survey data such as hydrants, power poles 
 Manholes 
 Grading of the station platform and ADA ramps 
 Impacted sidewalk construction 
 Station platform location and sizing 
 Transition curb to meet 14” elevated platform height 
 Concrete bus pad 
 Potential tree relocations 
 
In conjunction with the station platform design, roadway concepts were designed by the team to 
assure that each station location worked given constraints such as ROW, and physical constraints 
(preliminary design plans displayed in Appendix D).  The level of detail for the plans was enough 
to complete the final visioning phase, to provide a level of comfort on constructability and high 
potential construction costs prior to progressing to the final design phase.     
 
Based on the station platform locations, the team designed each bus pad and affected items 
surrounding each station as well as handicap accessible ramps to the elevated platform.  The plans 
show all areas of proposed construction and the relationship to existing roadway features and 
ROW.  The intent of this design was to avoid any ROW impacts and based on preliminary analysis 
this was achieved. 
 
Potential impacts to underground utilities are a significant concern for the local municipalities.  At 
this time, it is the intent to relocate existing utilities out from under the proposed stations, if 
possible.  Any utility information shown in the detailed drawings is only from above ground survey. 
 
 
 
 
 
 
 

  
Task I Vision Report 
Page 13 
 
Silver Line BRT 

11.0 FTA’s SCC Workbook for Project Cost 
Estimate 
 
A detailed cost estimate was completed by the team based on the Task I visioning process design 
for the BRT Silver line.   For a full description of the estimate and methodology refer to the Cost 
Estimate Report located in Appendix I. 
 
The intent of the estimate was to provide a preliminary cost to provide information to ITP and FTA 
confirming the project is within budget for a ‘very small starts’, and move the project forward to 
final design and the construction phase.  
 
As part of the estimate the team calculated detailed costs for each component of the design 
including; 
 
 Stations 
 Roadway 
 Signal prioritization upgrades to some intersections 
 Communications devices 
 Operating equipment for buses and stations 
 
Other cost items that were calculated during the EA phase were included in the estimate as place 
holders without recalculation. 
 
The detailed costs were summarized into the FTA cost estimating spreadsheet, which also 
calculates the year of expenditure costs based on predicted inflation.  The team assumed 
construction would begin in 2012 for two years and the year of revenue operations would begin in 
2014.   
 
The total year of expenditure costs in 2010 dollars is $35.7 million. 
 
 
 
 
 
 
 

  
Task I Vision Report 
Page 14 
 
 

 
APPENDICES 
 

  
Final Task I Vision Report 
 
 
 

 
Appendix A 
 
Stakeholder Involvement Meeting 
Summaries 

  
Final Task I Vision Report 
 
 
Proposed Stakeholders for the Silver Line Bus Rapid Transit (BRT)
The Rapid - Grand Rapids, MI
July 2010

Organization Name Phone # email Address Contact

Groups/Associations
Wyoming/Kentwood Chamber of Commerce 616-531-5990 sue@southkent.org 590 32nd Street SE, Wyoming, MI 49548-2345 Sue Bynum, Admin Assistant
West Michigan Hispanic Chamber of Commerce 616-452-4027 csanchez@hccwm.org 1251 Century Ave, Suite 200, Grand Rapids, MI 49503 Carlos Sanchez, Executive Director
Neighborhood Ventures 616-301-3929 lewism@neighborhoodventures.org 949 Wealthy St SE, Suite 200, Grand Rapids, MI 49506 Mark Lewis, Executive Director
Burton Heights Business District
Madison Square Business Dsitrict
Division South Business District
East Fulton Business District 616 776-7333 1041 E. Fulton Street, Grand Rapids, MI 49503
Heartside Business District/Neighborhood Assn 616-855-0435 jenn@heartsidegr.com Jenn Schaub
Division Avenue Business Association (28th to 54th) 616-452-8691 tommy@d-a-b-a.org 4157 Division Ave S., Grand Rapids, MI 49548 Tommy Brann, President
Heritage Hill Neighborhood Association (GR) 616-459-8950 heritage@heritagehillweb.org 126 College SE, Grand Rapids, MI 49503 Mike Clark, President
Garfield Park Neighborhood Association (GR) 616-241-2443 kwoudstra@gpnagr.org 334 Burton SE, Grand Rapids, MI 49507 Kathy Woudstra, Director
Grand Rapids Area Chamber of Commerce 616-771-0322 englehartj@grandrapids.org 111 Pearl Street NW, Grand Rapids, MI 49503 Jeanne Englehart, CEO

Mobil Metro Task Force


GR Downtown Development Authority abessette@grcity.us Ann Marie Bessette
Disabled Advocates of Kent County raebower@gmail.com Rae Bower
Inner City Christian Federation jbradford@iccf.org Jonathan Bradford
Crowe Horwath john.canepa@crowehorwath.com John Canepa
Kent County Administrator daryl.delabbio@kentcountymi.gov Daryl Delabbio
p Consumer Advisoryy Committee
Rapid y @
casey354@comcast.net Caseyy Dutmer
Frey Foundation ferrell@freyfdn.org Frey Foundation, 700 Bridgewater Place, GR MI 49503 Lynn Ferrell
Area Agency on Aging sandragj@aaawm.org Sandra Ghosten-Jones
Locus Development john@locusdevelopment.com John Green
Butterball Farms BTG@brandontgriffin.com Brandon Griffin
GVSU haynesl@gvsu.edu Lisa Haynes
WMEAC rhood@wmeac.org Rachel Hood
CB Richard Ellis Robert.horn@cbre.com Robert Horne
Grand Rapids Area Chamber of Commerce johnstona@grandrapids.org Andy Johnston
Cascade Engineering dirck.lyon@cascadeng.com Dirck Lyon
MI League of Conservation Voters bill@michiganlcv.org Bill Kirk
Kent Intermediate School District ronkoehler@kentisd.org Ron Koehler
Spectrum Hospital mark.lemoine@spectrum-health.org Mark Lemoine
Faith in Motion albertlewis@att.net Albert Lewis
GVSU moyerj@gvsu.edu James Moyer
Jade Pid Ventures mmraz@jadepigventures.com Mike Mraz
RoMan Manufacturing rroth@romanmfg.com Robert Roth
Grand Valley Metro Council stypulad@gvmc.org Don Stypula
Wyoming Deputy City Manager vandurenb@wyomingmi.gov Barb Van Duren
Rockford Construction mvangessel@rockfordconstruction.com Mike VanGessel
Community Leader panchovega13@aol.com Francisco Vega

Banks
Huntington Bank 230 E, Fulton, Grand Rapids, MI 49503
Huntington Bank 50 Monroe Ave., Grand Rapids. MI 49503
Chase Bank 200 Ottawa Ave. NW., Grand Rapids 49503 David Frey
Comerica Bank 99 Monroe Ave. NW., Grand Rapids 49546 Joe Davio
Fifth Third Bank 111 Lyon NW., Grand Rapids 49503 President/CEO

City Government
Grand Rapids, Deputy City Manager edelong@grcity.us Eric De Long
Grand Rapids mayor@grcity.us Mayor George Heartwell
Grand Rapids dshaffer@grcity.us Dave Shaffer Commissioner
Grand Rapids rbliss@grcity.us Rosalynn Bliss Commissioner
Grand Rapids jwhite@grcity.us James White, Sr. Commissioner
Grand Rapids jfowler@ci.grand-rapids.mi.us Jay Fowler
Grand Rapids sschulz@grcity.us Suzanne Schultz
Grand Rapids czull@ci.grand-rapids.mi.us Chris Zull
Grand Rapids mdeclercq@ci.grand-rapids.mi.us Mark DeClercq
Grand Rapids greimer@ci.grand-rapids.mi.us Gary Reimer
Wyoming mayor@wyomingmi.gov Mayor Jack Poll,
Wyoming wverhulst@wyomingmi.gov William VerHulst, Commissioner
Wyoming rpastoor@wyomingmi.gov Richard Pastoor, Commissioner
Wyoming dburrill@wyomingmi.gov Dan Burrill, Commissioner
Wyoming sbolt@wyomingmi.gov Sam Bolt, Commissioner
Wyoming cochrant@wyomingmi.gov Tim Cochran
City of Kentwood Planning Director schweitt@ci.kentwood.mi.us Terry Schweittzer
Kentwood mayor@ci.kentwood.mi.us Mayor Richard Root
Kentwood coughlinb@ci.kentwood.mi.us Robert Coughlin, Commissioner
Kentwood brownmi@ci.kentwood.mi.us Michael Brown, Commissioner
Kentwood brinkss@ci.kentwood.mi.us Sharon Brinks, Commissioner
Kentwood verwysr@ci.kentwood.mi.us Raymond VerWys, Commissioner
Kentwood cummingsf@ci.kentwood.mi.us Frank Cummings, Commissioner
Kentwood clantonr@ci.kentwood.mi.us Richard Clanton, Commissioner

Kent County Government - other


Kent County Road Commission rbelknap@kentcountyroads.net Roger Belknap
K
Kent C
County Road
R d Commission
C i i swarren@kentcountyroads.net
@k d Steve Warren
S W
vonkcommish@comcast.net Ted Vonk, Commissioner
toma@iserv.net Tom Antor, Comm.
g.rolls@comcast.net Gary Rolls, Comm.
sandiparrish@hotmail.com Sandi Frost Parrish, Comm.
roger@rockfordambulance.com Roger Morgan, Comm.
tanisart@comcast.net Arthur Tanis, Comm.
sjponstein@netzero.net Stan Ponstein, Comm.
hjvoorhees1@sbcglobal.net Harold Voorhees, Comm.
hirschfamily3@aol.com Bill Hirsch, Comm.
dagee@iserv.net Dean Agee, Comm.
p.hickey@prodigy.net Pete Hickey, Comm.
courtadek@aol.com Keith Courtade, Comm.

Other Institutions
Grand Action john.canepa@crowehorwath.com John Canepa
GVSU bachmeij@gvsu.edu Jim Bachmeier
Saint Mary's Hospital 200 Jefferson Ave. Grand Rapids, MI 49503 President
Grand Rapids Community College GRCC, 143 Bostwick Ave. NE, Grand Rapids, MI 49503 Dr. Steven Ender, President
J W Marriot JW Marriott 235 Lewis, Grand Rapids, 49503 Mr. George Aquino, GM
Amway Corp. Amway Hotel Corp. 7575 Fulton St. E. Ada, MI 49355 President/CEO
Van Andel Institute 333 Bostwick Ave. NE, Grand Rapids, MI 49503 Joe Gavan
Michigan Dept. of Transportation kinde@michigan.gov Eric Kind
Grand Valley Metro Council jay.hoekstra@gvmc.org Jay Hoekstra
MSU Medical College jerry.kooiman@ht.msu.edu Jerry Kooiman
DeVos Place/Van Andel Arena LIke@smggr.com Lynn Ike
The BOB gg@gilmorec.com Greg Gilmore
The BOB kcarey@comcast.net Kieth Carey
Metro Motors steve.metromotors@gmail.com
Silver Line Bus Rapid Transit (BRT)
Grand Rapids, Michigan

Technical Memorandum
Meeting Set #1
Summary of Stakeholder Engagement Meetings
(August 11 – 12, 2010)

August 25, 2010


STAKEHOLDER ENGAGEMENT MEETINGS

1.0 Public Meeting Details

Date of Meeting: August 11

Location: The Rapid Central Station


250 Grandville Ave SW
Grand Rapids

Time: 10:00 am – 1:00 pm and 3:00 pm – 6:00 pm

Total # of Meeting
Attendees: 13 signed in

Date of Meeting: August 12

Location: Tommy Brann’s


4157 S. Division Ave.
Wyoming

Time: 10:00 am – 1:00 pm

Total # of Meeting
Attendees: 11 signed in

1.1 Stakeholder Invitation

An invitation letter was set to stakeholders on July 27th, 2010. A copy of the invitation letter is
attached.

1.2 Meeting Format


The Stakeholder Engagement Meetings were conducted using an open-house format. Exhibits
were provided to explain the proposed Silver Line BRT system, the process that is being
followed, the benefits of a BRT system, the project history and schedule, and maps to illustrate
bus station locations and potential issues. A handout summarizing the exhibits was provided for
attendees to take home. A copy of the exhibits and handout are attached.

Attendees were encouraged to comment on the proposed station locations and BRT system.
Comments were noted on the large maps of the proposed station locations.

1
1.3 Summary of Comments Received
A summary of the comments received is attached.

1.4 Exhibits

Welcome
Why are you here?
What is a BRT? What are the benefits?
What is the Silver Line BRT? Why is it still being considered?
Silver Line BRT project history and schedule
Stakeholder Engagement: Next Steps

1.5 Meeting Register


The Meeting Registers from the Stakeholder Engagement Meetings held August 11 – 12 are
attached.

2
Stakeholder Invitation
Meeting Handout
Silver Line Bus Rapid Transit (BRT)
   
 
  Stakeholder Engagement Meeting 
 
 
 
 
  August 11‐12, 2010 
 
   
What is a Bus Rapid Transit?  What is the History and Future Schedule of the  
  Silver Line BRT Project? 
Bus Rapid Transit (BRT) is a form of public   
transportation that uses buses to provide faster, more  2003 –  Alternatives Analysis and Great Transit Grand 
Tomorrow (GT2) Study 
efficient service than a typical bus line. 
2007 –  Selection of Locally Preferred Alternative 
2009‐10 – Preparation of an Environmental Assessment 
What are the Benefits of a BRT? 
(EA), EA Public Hearing, and EA approval 
  2010‐11 – Final Design and Preliminary Engineering 
 A faster commute – fewer bus stops, quicker  2011 –  Project Capital Grant Agreement 
loading/unloading, signal priority  2012 –  Construction 
 Increased ridership   
 Increased capital cost effectiveness  What are the Next Steps for Stakeholder 
 Increased employment opportunities  Engagement? 
 Enhanced community cohesiveness   
A series of meetings have been scheduled to present 
 Enhanced economic development 
previous meeting decisions, discuss how decisions tie 
 Enhanced transit supportive land development  into the project vision, and to receive stakeholder input. 
 Improved operating cost efficiency   
 Improved environmental goals such as air quality  Meeting #2:  September 8‐9, 2010 
  Objective:  To foster workshops (charrettes) to 
What is the Silver Line BRT and why is it STILL  address station design concepts and 
communicate overall project 
being considered?  development process. 
 
The Silver Line BRT will offer an innovative, high 
Meeting #3:  Early November, 2010 (date TBD) 
capacity, higher speed, cost‐effective public 
Objective:  To provide a summary of station design 
transportation solution comparable to a light rail 
concepts, BRT and street operations, 
system, but at a significantly lower cost. 
benefits to riders and The Rapid 
The Silver Line BRT is still being considered because:  operations, and construction costs. 
 The current bus route along Division Avenue has the   
highest ridership in the Rapid System.  How can I find additional information about the 
 BRT is the most cost‐effective way of moving riders  Silver Line BRT or supply additional comments? 
and non‐riders along Division Avenue to downtown   
Grand Rapids.  You can visit the project’s website at: 
 The project continues to receive strong support  www.rapidsilverline.org; email the project team at 
from the Federal Transit Administration (FTA) and  planning@ridetherapid.org; or call the project hotline at 
the Michigan Dept. of Transportation (MDOT).  (616) 774‐1298. 
 The recent Transit Master Plan (TMP) outreach   
sessions indicate a continuing public support for the 
Thank You for your time and for 
project. 
visiting us today! 
Summary of Comments Received
Silver Line BRT
Stakeholder Engagement Meeting #1

Comment Summary
Location*

1. Central Station

- Grandville Avenue near the Central Station is being rebuilt in 2011. The city is to
decide if angle parking will remain or if it will be converted to parallel.

2. Monroe Avenue/Fulton Street

a. Northbound Station: The property owner has a development plan for this
area. The owner needs to be contacted to discuss the details (Greg
Gilmore.)
b. Southbound Station: Adjust the station location to avoid the loading dock.

3. Monroe Avenue/Lyon Street

a. Northbound Station: Possibly relocate the station south of the pedestrian


cross walk.
b. Southbound Station: The proposed station is located within the drop-off lane
of DeVos Place. There is 15-minute parking located here also.

4. Michigan Street

a. Westbound Station: Michigan Street development and entrance for the


medical school. Potentially relocate this station.

- Both stations on Michigan Street: Stations need to serve as transfer stations for routes
11 & 13. What time? Fare instrument? Weather protected?
- Potentially shift route east to service Lafayette/college.

5. Crescent Street

- Crescent Avenue at Bostwick : make Crescent Avenue three lanes at the « T » with
Bostwick ; Dedicated right and left turn lanes heading west on to Bostwick and a
through lane heading east on Crescent. The parking on the south side of Crescent
(across from the proposed westbound station) would have to be removed.

6. Ransom Avenue/Fountain Street

- Heavy left turns from Lyon on to Ransom during AM peak ; probably heading to
G.R.C.C. parking garage on the west side of Ransom between Fountain and Lyon.
Heavy left turns from Ransom in to G.R.C.C. parking garage during AM peak as well.
7. Jefferson Avenue/Wealthy Street

8. Division Avenue/Logan Street

a. Southbound Station: ICCF would prefer the station be located on Lyon Street
across from the northbound station. This would mean a left turn from Lyon on
to southbound Division.
b. Potentially relocate both stations on Lyon further east, closer to Sheldon. This
would mean potential land acquisition and possible reevaluation of the EA.

9. Division Avenue/Franklin Street

- Recommend running Bus Route #1 Division and #2 Kalamazoo more frequently,


clockwise on the route; split routing.

10. Division Avenue/Hall Street

11. Division Avenue/Cottage Grove Street

12. Division Avenue/Burton Street

13. Division Avenue/Alger Street

14. Division Avenue/28th Street

a. Northbound Station: Curb cut to business; possibly relocate station to the


north side of 20th Street on Division Avenue.
b. Southbound Station: A portion of the proposed station location covers the
driveway of the Walgreens.

- East and west transfers at 28th Street need to be properly accommodated.


- Possible park-n-ride lot for transfers to buses that go down 28th Street (Route #28 28th
Street) and/or shoppers.

15. Division Avenue/36th Street


a. Southbound Station: Station must not detract from businesses.

16. Division Avenue/43rd Street

- Why is there a station at 43rd and not 44th? 44th Street would be good for transfers
and easier for pedestrians to cross Division because 44th and Division is signalized.

17. Division Avenue/54th Street

- Park & Ride potential in the southeast quadrant of 54th and Division Avenue
intersection.
18. Division Avenue/60th Street
a. Northbound Station: Property owner thinks station would be better further
north, away from 60th Street.

- Need to define bus turnaround at end of route.


- Potential parking located north of 60th Street, north of creek, on the east side of
Division Avenue.
- Overhead walkway will it remain (Division & Bellevue)

**Other Comments**

- Disabled Considerations
o Braille Signage
o Accessible Signage
o Audio Messages
o Ticket vending must be ADA friendly
o ADA connection/transfers to other routes
- Need parking along route. Possibly lease from local businesses.
- Will pedestrian movements across Division be accommodated?
- Pedestrians crossing Division stops more access to signal crossings.
- Visibility/availability of public parking?
- Use accessible pedestrian traffic call signals with countdowns.
- Travel time concerns: Local bus = 1 hour vs. BRT = 34 minutes?

*Locations proposed in the Environmental Assessment


Exhibits
Silver Line Bus Rapid Transit
Stakeholder Engagement Meeting
Stakeholder Engagement Meeting
August 11‐12, 2010

W l
Welcome
Q:  Why are you here? 
A:  Because we need your input!

• What is a Stakeholder?
o Anyone who has an investment, share, or interest in the project including property owners businesses, institutions, 
and the general public served by the proposed BRT route.

• What is Stakeholder Engagement and why is it important?
o The process of engaging interested and affected parties in dialog to improve decision‐making and accountability of 
the project development process.
o Stakeholder engagement is very important because it allows the project team to gather information regarding how 
new BRT stations will look and how the system will operate.

• What do we expect from Stakeholders during these meetings?
o To provide input on desires, possible complications, areas of concern, ideas about station design, neighborhood 
context, and overall thoughts about the project.
What is a BRT?
What are the benefits?

• Bus Rapid Transit (BRT) is a form of public transportation that uses buses 
to provide faster, more efficient service than a typical bus line.

• Benefits of BRT include:
 A faster commute – fewer bus stops, quicker loading/unloading, 
signal priority
 Increased ridership
 Increased capital cost effectiveness
 Increased employment opportunities
 Enhanced transit supportive land development 
 Enhanced community cohesiveness
y
 Enhanced economic development
 Improved operating cost efficiency
 Improved environmental goals such as with air quality

Swift BRT vehicle and station from Everett WA


Swift BRT vehicle and station  from Everett, WA
What is the Silver Line BRT?
Why is it STILL being considered?

“Over
Over four fifths (83%) of residents 
four fifths (83%) of residents
• Silver Line BRT will offer an innovative, high capacity, higher speed, cost‐effective 
thought transportation  public transit solution comparable to a light rail system at a significant lower cost.
improvements are very urgent (37%) 
or somewhat urgent (46%).” • Silver Line BRT is still being considered because:
o Current bus route along Division Avenue has the highest ridership in the 
Community Study
Rapid System.
Jacokes & associates
Jacokes & associates
November, 2008 o A BRT is the most cost‐effective way of moving riders and non‐riders from 
Division Avenue to the area with the highest concentration of employment 
and activities in downtown Grand Rapids.
o The project continues to receive strong support from the Federal Transit 
( ) g p p
Administration (FTA) and the State of Michigan Department of Transportation 
(MDOT).
o Recent Transit Master Plan (TMP) outreach sessions indicate a continuing 
public support for the project.
Silver Line BRT project history 
and schedule

2003 2007 2009‐ 2010‐ 2011 2012


2010 2011* * *

Alternatives
Analysis

Final Design Federal 
Construction
Approval
Select Locally  Prepare 
Preferred  Environmental  Public
FONSI
Alternative  Assessment  Hearing
(
(LPA)) ( )
(EA)
Preliminary 
‐Purpose and Need ‐”Finding of No  Engineering
Great Transit  ‐Alternatives Significant 
Grand  ‐Impact Assessment Impact”/Approv
Tomorrow  ‐Mitigation al
Study

* Subject to FTA approval of The Rapid’s Operating Plan
Stakeholder Engagement:    
Next Steps

• A series of meetings have been scheduled to present decisions made at 
previous meetings, discuss how decisions have been folded into the project 
vision, and to receive stakeholder input:

• Meeting Set #2:
o September 8th and 9th, 2010
o Design Charrettes – workshops to address station design concepts and 
communicate overall project development process.

• Meeting Set #3:
o Early November, 2010
y ,
o Provide a summary of station design concepts, BRT and street  Stakeholders during a Design Charrette
operations, benefits to riders and The Rapid operations, and 
construction costs.
Meeting Register
Silver Line Bus Rapid Transit (BRT)
Grand Rapids, Michigan

Technical Memorandum
Meeting Set #2
Summary of Stakeholder Engagement Meeting
(September 30, 2010)

October 4, 2010
STAKEHOLDER ENGAGEMENT MEETINGS

1.0 Meeting Details

Date of Meeting: September 30, 2010

Location: Tommy Brann’s Restaurant


4157 S. Division Ave
Grand Rapids

Time: 9:00 am – 11:00 am

Total # of Meeting
Attendees: 14 signed in

Date of Meeting: September 30, 2010

Location: The Rapid Central Station


250 Grandville Ave. SW
Grand Rapids

Time: 1:30 am – 3:30 pm

Total # of Meeting
Attendees: 16 signed in

1.1 Stakeholder Invitation

An invitation letter was set to stakeholders on September 1, 2010. The Rapid followed up with
reminder e-mails to stakeholders each week leading up to the meetings. A copy of the invitation
letter is attached.

1.2 Meeting Format


The Stakeholder Engagement Meetings were conducted using a design workshop or charrette
format. A PowerPoint presentation was made to present the current status of the BRT Project,
provide updates since the first Stakeholder Meeting, and gather feedback based on several
example BRT station pictures and elements. Exhibits were provided to explain updates since
the first Stakeholder Meeting, station program elements, and present example BRT stations,
elements, and signage. A copy of the exhibits and presentation are attached.

1
Attendees were encouraged to provide input on the proposed station elements and design.
Comments were noted on large comment boards during the meeting, and a summary of the
comments are shown below.

1.3 Summary of Comments Received


General Shelter Structure Look & Feel
The shelters should be a visually distinctive design which is simple, functional and easy to
maintain. The shelter design should pick up on the ‘iconic’ look and feel already existing in
Grand Rapids; in the ‘Le Grande Vatesse’ and in the rooflines of DeVos Place and the Rapid
Central Station. Shelters shall provide all required operational components while blending in
with their surroundings yet still provide the branding and tall visual element to distinguish the
shelter as a BRT station

Weather Protection & Maintenance Concerns


Provide ridership with protection from rain, wind and snow, salt/slush splash & icicles and
maintain clean stations year around. Discharge roof run-off into the sewer system to avoid ice
forming on the sidewalks.

Sustainability Practices & Energy


Take advantage of opportunities to incorporate ‘green’ design principals into the stations to keep
in concert with the Green Grand Rapids initiative.

Neighborhood Communication
Station design should incorporate individual links to neighborhood via design expression, event
announcement and/or artwork

Visual, Audio and Surface Accommodations


Shelters must be all inclusive in providing for riders needs using the latest audio and visual
technology equipment, materials and surfaces.

Advertisement & Naming Rights


Take advantage of any marketing or advertizing opportunities with which funds could be used
for station upkeep.

Bicycle Advocacy & Accommodation


Transit Vehicles and Stations as a leading part of the transportation network can and must
acknowledge the place of bicycles as a viable alternative to the car. Bike lanes, as part of the
‘Complete Streets” movement, are envisioned in the future. All forms of at-the-station bike
provisions should be available at appropriate station locations frequented by bicyclist. The plan
to allow riders to bring their bike on the transit vehicle was well received.

A comprehensive, bulleted list of all comments received is attached.

1.4 Meeting Register


The Meeting Registers from the Stakeholder Engagement Meetings held September 30, 2010
are attached.

2
Stakeholder Invitation
September 1, 2010

Re: Invitation to attend Stakeholder Meeting 2 for the


Silver Line Bus Rapid Transit (BRT)

The Rapid, in cooperation with the cities of Grand Rapids, Kentwood, and Wyoming and the
Federal Transit Administration, is continuing the process of conducting preliminary engineering,
architecture, and coordination for the proposed Silver Line Bus Rapid Transit (BRT) system in
downtown Grand Rapids and along south Division Avenue to 60th Street.

The Rapid is moving forward with this early design phase of the BRT in response to the
community outreach feedback received during the recent Transit Master Plan (TMP)
development. It was clear to us that the affected community wants to pursue the continued
evaluation of a BRT along Division Avenue. Additionally, we continue to receive the support of
the Federal Transit Administration for this phase of the proposed project.

You or your organization has been identified as a potential stakeholder in the BRT and,
accordingly, you are being invited to attend the project’s Meeting Set 2 – Design Charrette.
This meeting is intended to bring community members, professional architects and planners,
and decision-makers together to develop bus station concepts for the proposed Silver Line BRT
route.

The objective of this meeting is to present the BRT project goals, the Bus Station Design
Program, and existing information collected along with the advantages and disadvantages of
each station example. Stakeholders will be asked to identify and provide their likes and dislikes
of the station examples, identify opportunities for incorporating those preferences into the
project, and illustrate their preferences into a station vision. Based on input from the charette
participants, the station designers will then submit design options to The Rapid for their review,
consideration, and implementation as appropriate.

For those who attended the initial Meeting Set 1, held on August 11th and 12th, 2010 a one-page
project handout was provided that listed the charrettes as being held 8th and 9th, 2010 at The
Rapid’s Central Station and Tommy Brann’s restaurant. Due to adjustment in the project
development process, the dates of the charrettes have been changed to September 30th. There
will be two opportunities to attend, and stakeholders are invited to attend whichever time best
fits their schedule. The date, times, and locations of each meeting are listed below, and a
tentative meeting agenda is enclosed.

September 30, 2010 - 9:00 AM to 11:00 AM – Tommy Brann’s (4157 S. Division Ave.,
Wyoming). The focus for this workshop will be the Division Avenue corridor south of the
downtown Grand Rapids business district.

September 30, 2010 - 1:30 PM to 3:30 PM – The Rapid Central Station. The focus for this
workshop will be the downtown Grand Rapids business district.
If you are unable to attend either of the meetings, you may still submit your comments and
concerns to the Project Team at planning@ridetherapid.org or call the project hotline at
616.774.1298.

The proposed Silver Line BRT Project will provide enhanced transit access to downtown Grand
Rapids by providing reliable, frequent and speedy transit service along an approximately 10 mile
route that connects The Rapid’s Central Station in downtown Grand Rapids to 60th Street along
the Division Avenue corridor. The project will feature specialized stations with curbside level
boarding platforms, dedicated bus lanes for part of the route, and traffic signal priority for its
transit vehicles. While it will be important to maintain consistent “branding” among BRT stations,
the Rapid is looking for opportunities to include architectural features reflecting the
neighborhoods in which they reside.

We appreciate your involvement and look forward to meeting with you to discuss this very
important project.

Sincerely,

Taiwo Jaiyeoba
The Rapid Director of Planning
Silver Line Bus Rapid Transit (BRT) Project
Stakeholder Meeting 2 – Draft Agenda

Date: September 30, 2010

Time/Location: 9:00 - 11:00 am at Tommy Branns


1:30 - 3:30 pm at Rapid Central Station

1) Purpose and Objectives

2) Team Organization

3) Share with the Stakeholders


a. Definitions
b. The Project
c. BRT and Traffic Simulation Animation
d. The Station Program
e. Examples of Existing BRT Stations

4) Work as a Team to Identify Station Elements


a. Station Boundaries
b. Functional
c. Economical
d. Enhance the Neighborhood
e. Recommendations
Presentation
Silver Line BRT
Station Design Workshop
Interurban Transit Partnership – The Rapid
Agenda
… Purpose and Objectives
… Organization
… Share with the Stakeholders
† Definitions
† The Project
† Results of 1st Stakeholder Meeting
† Update Since 1st Stakeholder Meeting
† BRT and Traffic Simulation Animation
† The Station Program
† Station Design Framework
† Neighborhood Character
† Examples of Existing BRT Stations
… Work as a Team to Identify Station Elements
† Station Boundaries
† Functional
† Economical
† Enhance the Neighborhood
† Recommendations
Purpose and Objectives
… The Purpose of this Design Workshop:
† Project Overview,
† Design Program for the Silver Line BRT Stations and Platforms, and
† Examples of Existing BRT Stations so that stakeholders, the Rapid, and
designers can work as a team to identify station elements they prefer to include
in the Silver Line that will be functional, economical, and enhance the
neighborhoods

Las Vegas, NV – “Max”


What are the Benefits of BRT?
9 A faster commute – fewer stops, quicker
loading/unloading, signal priority
9 Increased ridership
9 Increased capital cost effectiveness
9 [Add jobs] Increased employment opportunities
9 Enhanced transit supportive land development
9 Enhanced community cohesiveness
9 Enhanced economic development
9 Improved operating cost efficiency
9 Improved environmental goals such as with air quality
Team Organization
The Rapid
Peter Varga
Taiwo Jaiyeoba

Wilbur Smith
Associates
Stakeholders
Ralph Trepal
Todd Davis

Isaac V. Norris
URS
Assoc
Theresa Petko
Isaac Norris
Mark Wrona
Roles and Responsibilities
… The Rapid – Owner and Operator of the Transit System in general
and the Silver Line in particular
… Stakeholders – The Community and Advisors
… Wilbur Smith Associates – Prime Consultant for the Silver Line
† Isaac V Norris Associates – Architect for the Stations
† URS – Urban Designer for the Stations

San Joaquin, CA – “Metro Express”


Definitions
… The Project – The Silver Line which is a Bus Rapid Transit (BRT)
that extends about 10 miles from Central Station via downtown
Grand Rapids to 60th and Division
… Bus Rapid Transit (BRT) – Think light rail (not trains) but use
buses
… Design Program – Technical requirements for what is in a station
that includes a shelter and a platform
… Station Elements – Components of the shelter, platform, and
aesthetics
… Functional – Make the station attractive, safe, convenient,
efficient, and comfortable
… Economical – Sustainable using quality materials to perform its
function, low maintenance, and not extravagant
The Project
… The Silver Line
† More service
† 10 min. peak period
† 15 min. off-peak
† Faster service – 60th St. to
Spectrum
† One seat ride
† Morning Northbound ~ 28
min.
† Afternoon Southbound ~ 26
min.

… Existing Conditions
† 30 min. headways
† Travel time 60th St. to Spectrum
via Central Station:
† Two seat ride
† Morning Northbound ~
50-55 min.
† Afternoon Southbound ~
75-80 min.
Results of Stakeholder Meeting #1
… Held August 11-12, 2010 at Tommy Brann’s and The Rapid Central
Station
… Approximately 24 stakeholders attended
… Major comments received:
† Why are proposed stations located where they are and how were they
determined (e.g. 43rd St. station)?
† How will future development near proposed stations affect BRT system (e.g.
The BOB)?
† Will proposed BRT stations accommodate existing bus routes and/or stations
(i.e. transfers)?
† Will 60th St. station accommodate a bus turn-around and/or park-n-ride?
† Will proposed BRT stations accommodate disabled persons?
† Will pedestrian movements along Division Ave. be accommodated?
Updates Since
Stakeholder
Meeting #1
BRT Station Relocations
† Crescent St.
† Fountain St.
† 43rd St.

BRT Station Adjustments


† Fulton St.
† Lyon St.
† Logan St.
† Franklin St.
† Cottage Grove St.
† Burton St.
† 60th St.
BRT and Traffic Simulation Animation:

……..at Division and Franklin


Station Design Framework
… Open Shelter design
… 10- or 14-inch high platforms
(precision docking)
… 60-foot platform lengths
(optimal)
… 14-foot platform width (optimal)
… Canopy Swift BRT Station (Everett, WA)

… Right-of-way limitations
… Adjacent land uses
… Sustainable
… Economical
… Specific station design will be
based upon station location
(downtown vs. Division Corridor)
HealthLine BRT Station (Euclid, OH)
Examples of Existing BRT Stations
… Curatiba, Brazil – “Rit” … Pittsburgh, PA – “South Busway”
Examples of Existing BRT Stations
… Los Angeles, CA – “Orange Line” … Pittsburgh, PA – “West Busway”
Examples of Existing BRT Stations
… Everett, WA – “Swift” … Kansas City, MO – “Max”
Examples of Existing BRT Stations
… Las Vegas, NV – “Max” … Phoenix, AZ – “Rapid”
Examples of Comparable Light Rail Stations
… Houston, TX – “METRORail” … Minneapolis, MN – “Hiawatha Line”
Branding / Vertical Element

Kansas City, MO – “Max” Everett, WA - “Swift”


Transit Shelter Equipment
… Fare Collection Station … Next Bus Message
Bike Storage Examples
Neighborhood Character
… Local Signage
Neighborhood Character
… Landscape/Streetscape
Neighborhood Character
… Integrated Art
Neighborhood Character
… Architecture / Design
More Example Stations
Northbound
Monroe
at Louis
Northbound
Monroe
at Louis
Northbound
Monroe
at Louis
Southbound
Monroe
at Louis
Southbound
Monroe
at Louis
Southbound
Monroe
at Louis
Southbound
Monroe
at Louis
Southbound
Monroe
at Louis
Southbound
Monroe
at Louis
Southbound
Monroe
at Louis
Southbound
Monroe
at Louis
Southbound
Monroe
at Louis
Southbound
Monroe
at Louis
Southbound
Monroe
at Louis
Southbound
Monroe
at Louis
Southbound
Monroe
at Louis
Southbound
Monroe
at Louis
Southbound
Monroe
at Louis
Southbound
Monroe
at Louis
36th Street
Southbound
36th Street
Southbound
36th Street
Southbound
36th Street
Southbound
36th Street
Southbound
36th Street
Southbound
36th Street
Southbound
36th Street
Southbound
What is important to you?
… Consider each Station Element of about 3 example stations and
evaluate how their Station Elements support, do not impact, or
detract from desirable station features
… After considering the preference of the various station elements
explore how might it fit into or be modified to a station design for
this project
Examples of Existing BRT Stations
… Los Angeles, CA – “Orange Line” … Pittsburgh, PA – “West Busway”
Examples of Existing BRT Stations
… Everett, WA – “Swift” … Kansas City, MO – “Max”
Examples of Existing BRT Stations
… Las Vegas, NV – “Max” … Phoenix, AZ – “Rapid”
Example Stations
Examples of Comparable Light Rail Stations
… Houston, TX – “METRORail” … Minneapolis, MN – “Hiawatha Line”
Next Steps
Summary of Comments Received
Silver Line BRT – The RAPID
Stakeholder Engagement Meeting 2
September 30, 2010

Summary of Comments Received

General Shelter Structure Look & Feel


The shelters should be a visually distinctive design which is simple, functional and easy to
maintain. The shelter design should pick up on the ‘iconic’ look and feel already existing in
Grand Rapids; in the ‘Le Grande Vatesse’ and in the rooflines of DeVos Place and the Rapid
Central Station. Shelters shall provide all required operational components while blending in
with their surroundings yet still provide the branding and tall visual element to distinguish the
shelter as a BRT station

Weather Protection & Maintenance Concerns


Provide ridership with protection from rain, wind and snow, salt/slush splash & icicles and
maintain clean stations year around. Discharge roof run-off into the sewer system to avoid ice
forming on the sidewalks.

Sustainability Practices & Energy


Take advantage of opportunities to incorporate ‘green’ design principals into the stations to keep
in concert with the Green Grand Rapids initiative.

Neighborhood Communication
Station design should incorporate individual links to neighborhood via design expression, event
announcement and/or artwork

Visual, Audio and Surface Accommodations


Shelters must be all inclusive in providing for riders needs using the latest audio and visual
technology equipment, materials and surfaces.

Advertisement & Naming Rights


Take advantage of any marketing or advertizing opportunities with which funds could be used
for station upkeep.

Bicycle Advocacy & Accommodation


Transit Vehicles and Stations as a leading part of the transportation network can and must
acknowledge the place of bicycles as a viable alternative to the car. Bike lanes, as part of the
‘Complete Streets” movement, are envisioned in the future. All forms of at-the-station bike
provisions should be available at appropriate station locations frequented by bicyclist. The plan
to allow riders to bring their bike on the transit vehicle was well received.
Exhibits
Updates Since
Stakeholder
Meeting #1
BRT Station Removals
and Relocations
† Crescent St.
† Fountain St.
† 43rd St.

BRT Station Adjustments


† Fulton St.
† Lyon St.
† Logan St.
† Franklin St.
† Cottage Grove St.
† Burton St.
† 60th St.
The Station Program
… Shelter Building … Platform
† High visibility and “Branding” † Lighting
† Lighting † Level or Nearly-level Boarding
† Roof and Wind Break † Way-finding Signage including visually
† Fare Collection Machine impaired

† Emergency Telephone † Route Map and Information Kiosk

† Next “Bus” message † Trash Receptacle

† Benches † Benches

† Closed Circuit TV † Integrated Art

† Integrated Art † Bike Racks

† Security † Plantings
Examples of Existing BRT Stations
… Everett, WA – “Swift” … Kansas City, MO – “Max”
Neighborhood Character
… Local Signage
Swift BRT vehicle and station from Everett, WA

Example Roadside marker
(lights up at night)
Station Name
Windscreens Leaning rail (on both windscreens)

Next bus arrival sign

of
Station
Elements

Information kiosk
(one on front, one on rear)
Seating
Rail at back of station
(at some stations only)
ORCA smart card readers Ticket vending machines
(one on each end of shelter) (two, side by side)
Meeting Register
Silver Line Bus Rapid Transit (BRT)
Grand Rapids, Michigan

Technical Memorandum
Meeting Set #3
Summary of Design Concept Meetings
(October 20, 26, 27, 2010)
Meetings with the Cities of Wyoming, Kentwood
and Grand Rapids
(November 4, 5, 2010)

November 8, 2010
DESIGN CONCEPT MEETINGS

1.0 Meeting Set 3

During the development of the station design concepts, the consultant team held a series of
meetings with ITP staff and city staff from Grand Rapids, Wyoming, and Kentwood. The
purpose for the meetings was to guide the station concept development process and obtain
valuable input in order for the team to create the proposed concepts as accurately as possible.
This iterative process allowed the team to get to a preferred concept much quicker and
efficiently and provided the opportunity for the city stakeholders to provide input very early in the
process. The series of meetings held with ITP and city officials are listed below. The meeting
minutes and the meeting registers are attached. The concepts developed during this process
are also attached.

1.1 Meeting Dates and Locations

Date of Meeting: October 20, 2010


Location: Interurban Transit Partnership – The Rapid Office
Time: 8:45 a.m.
Attendees: ITP Staff
**********************************************
Date of Meeting: October 26, 2010
Location: Interurban Transit Partnership – The Rapid Office
Time: 9:00 a.m.
Attendees: ITP Staff
**********************************************
Date of Meeting: October 27, 2010
Location: Interurban Transit Partnership – The Rapid Office
Time: 12:00 p.m.
Attendees: ITP Staff and City Stakeholders
**********************************************
Date of Meeting: October 27, 2010
Location: Interurban Transit Partnership – The Rapid Office
Time: 4:00 p.m.
Attendees: ITP Board Members and members of public
**********************************************
Date of Meeting: November 4, 2010
Location: City of Wyoming Engineering Dept.
Time: 2:30 p.m.
Attendees: Wyoming and Kentwood City Staff
**********************************************
Date of Meeting: November 5, 2010
Location: City of Grand Rapids Traffic and Safety
Time: 9:30 a.m.
Attendees: Grand Rapids City Staff

1
Meeting Minutes
ITP - The Rapid Silver Line BRT

Memorandum
TO: Attendees
File

FROM: Wilbur Smith Associates

DATE: October 20, 2010

SUBJECT: Station Design Concept “E” Meeting Minutes

PROJECT: Silver Line BRT Project

Date/Time: October 20, 2010 at 8:45 a.m.

Location: Interurban Transit Partnership – The Rapid Office


300 Ellsworth Avenue SW
Grand Rapids, MI 49503

Attendees:

7 Members of the Rapid staff (Peter, Conrad, Alan, Brian, Nick, Jennifer, Robin), Gary Scheuren, Todd
Davis, WSA, and Isaac Norris, IVNA

The following represents our understanding of the key points of discussion at the meeting with The Rapid
and other members of Project Team. Isaac presented revised station design Concept “E” in order to
obtain comments from the Rapid staff in advance of the upcoming board meeting. In general, the concept
was well received and the Rapid staff likes the overall concept. The following comments were made with
regard to the concept.

Comments:

1) Will the concept fit within the right-of-way and will the leaning pillars have any effect on
right-of-way? The back edge of the pillar will have to be moved forward to keep the leaning
pillar out of adjacent properties.
2) How much space is needed for pedestrians to pass by the station? In the downtown area the
clearance requirement is 6 feet.
3) A little concern over the metal supports for the benches as the Rapid would like to see
something solid under the benches to prevent cold air from blowing around the feet of riders.
4) Make sure Silver Line logo on vertical pillar remains above roof line of station.
5) There was some discussion about the need for the shelter roof to extend over the bus at the
stop. The Team will modify this concept to show a roof at the appropriate height and
extension to illustrate the issue. Is not a big concern though.
6) The station needs to have “The Rapid” logo someplace on the shelter. It was suggested that it
be etched on the glass ends of the shelter.

8164 Executive Court, Suite A – Lansing, Michigan 48917 517.622.2500 Fax: 517.622.2525
ITP - The Rapid Silver Line BRT
7) The name of the station of needs to be added to the concept. For now, place it on the back
beam facing the street.
8) ITP will provide Isaac with the actual colors for the Silver Line so he can use them in the
concepts.
9) A concern was raised about making sure there was adequate space for riders to move around
in front of the benches as riders get onto the transit vehicle.
10) Some discussion occurred regarding the location of the cameras within the shelter. Could be
placed near the Next Bus sign, or in the brow of the shelter.
11) If the fare machine is located at one end of the shelter, is there a preference to which end it
should be located from a rider’s point of view?
12) Where are the opportunities to incorporate neighborhood context or local art?
13) Would like to see option with a clear glass roof instead of the green color.
14) Need to add in some curves to the design somewhere to link to the overall theme of the
“Rapid”. The roof line was discussed as a potential location.
15) Can heat bars be provided in the shelter for use during the winter?
16) No paint should appear on the pillars below approximately 5-6 feet due to wear and tear
(scratching). Make the pillars stainless steel up to at least this point.
17) Some discussion about using concrete for the pillars up to this point as well.
18) Need to incorporate bike racks on the platform.
19) Remove bench near fare machine. Only two benches should be needed.

8164 Executive Court, Suite A – Lansing, Michigan 48917 517.622.2500 Fax: 517.622.2525
ITP - The Rapid Silver Line BRT

Memorandum
TO: Attendees
File

FROM: Wilbur Smith Associates

DATE: October 26, 2010

SUBJECT: Station Design Concept “E” Refinement Meeting Minutes

PROJECT: Silver Line BRT Project

Date/Time: October 26, 2010 at 9:00 a.m.

Location: Interurban Transit Partnership – The Rapid Office


300 Ellsworth Avenue SW
Grand Rapids, MI 49503

Attendees:

6 Members of the Rapid staff (Peter, Conrad, Brian, Nick, Jennifer, Robin), Gary Scheuren, Ralph Trepal,
WSA, Todd Davis, WSA, and Isaac Norris, IVNA

The following represents our understanding of the key points of discussion at the meeting with The Rapid
and other members of Project Team. Isaac presented the revised station design Concept “E” in order to
obtain comments from the Rapid staff for final refinements needed for the next day’s board meeting. The
following comments were made with regard to the concept. It was agreed that the Team would make the
final modifications to Concept “E” and rename it Concept “F” for presentation to the board.

Comments:

1) Rename example from Michigan Avenue – “Station Name”


2) Do not want step up to platform from sidewalk, make same height.
3) Peter sees three types of stations: prototypical (no space limitations), mid-size due to minor
space limitations, and smaller station due to limited space or location.
4) Recommend showing smaller station first, then larger.

8164 Executive Court, Suite A – Lansing, Michigan 48917 517.622.2500 Fax: 517.622.2525
ITP - The Rapid Silver Line BRT

Memorandum
TO: Attendees
File

FROM: Wilbur Smith Associates

DATE: October 27, 2010

SUBJECT: Presentation of Station Design Concepts to the BRT Stakeholders and ITP Staff

PROJECT: Silver Line BRT Project

Date/Time: October 27, 2010 at 12:00p.m.

Location: Interurban Transit Partnership – The Rapid Office


300 Ellsworth Avenue SW
Grand Rapids, MI 49503

Attendees:

5 Members of the Rapid staff (Peter, Conrad, Brian, Meegan, Taiwo)


Gary Scheuren
Ralph Trepal, WSA
Todd Davis, WSA
Isaac Norris, IVNA
Mark Wrona, URS
6 Stakeholders (Chris Zull, Terry Schweitzer, Tim Cochren, Eric Pratt, Jay Fowler, Suzanne Schulz)

The following represents our understanding of the key points of discussion at the meeting with The Rapid
and other members of Project Team.

Comments:

1) At 36th Street there is concern over the station blocking the vision of drivers pulling out of the
parking lot and onto Division.
2) Both Jay and Eric like the vertical element which has been integrated into the structure.
3) Suzanne would like to see the design details for the stations once they are prepared.
4) Chris asked about ADA regulations for ramps (i.e. are hand rails needed?)
5) Are truncated domes/precast cast iron a City standard?
6) Suzanne asked about lighting – 10 foot candles is standard – will they be flush mounted?
7) Tim asked about advertising opportunities
a. Suzanne will have to help with this due to local codes
b. Need to consider new technologies – LEDs, etc.
c. Naming rights are also an option
8) The “Next Bus” sign will have “Next 3 BRT Bus Arrivals” – what about cross-town routes?

8164 Executive Court, Suite A – Lansing, Michigan 48917 517.622.2500 Fax: 517.622.2525
ITP - The Rapid Silver Line BRT
9) Chris asked if The Team considered wireless? Ymax?
10) Suzanne discussed how meter boxes are graffiti magnets.
11) Meegan asked how snow removal will be handled.
12) Jay asked if there could be a canopy over the bus.
a. Chris stated it would have to be a 17’ high canopy minimum.
b. The higher the roof, the lower the weather protection it provides.
c. The roof needs to be 18” from the curb edge.
13) Suzanne wants her design team to go out to each station location to help site the shelters on
the platforms.
14) Tim asked about a snowmelt system (currently not in the budget.)
15) Tim asked about maintenance processes at each station and what ITP services will need to be
expanded.
16) Chris asked about management of the station information, communications, cameras, etc.
Will this be active?
17) Terry asked about the canopies having a wave feature
a. Roof glass
b. Seating (benches and glass)
c. Pavement
18) Underground utilities at each station location are a concern.

8164 Executive Court, Suite A – Lansing, Michigan 48917 517.622.2500 Fax: 517.622.2525
ITP - The Rapid Silver Line BRT

Memorandum
TO: Attendees
File

FROM: Wilbur Smith Associates

DATE: October 27, 2010

SUBJECT: Presentation of Station Design Concepts to the BRT Board

PROJECT: Silver Line BRT Project

Date/Time: October 27, 2010 at 4:00p.m.

Location: Interurban Transit Partnership – The Rapid Office


300 Ellsworth Avenue SW
Grand Rapids, MI 49503

Attendees:

Ralph Trepal, WSA


Todd Davis, WSA
Isaac Norris, IVNA
ITP Board Members
Members of the Public

The following represents our understanding of the key comments made by the board regarding the station
concepts.

Station Concept Comments:

1) Roof-to-floor glass at the benches may be desired for weather protection.


2) Will the shelters be heated? Will the shelters have a snow melt system?
a. Snow is a safety issue for the handicapped.
3) Can the roof mimic Central Station?
4) Can other colors be used instead of green on the pillar?
5) What is the cost of this system?
6) Everything looks very artistic and it is liked.
7) The concept is clever.

Peter Varga, ITP CEO, asked the ITP board to approve the general concept of the stations. The ITP board
approved.

8164 Executive Court, Suite A – Lansing, Michigan 48917 517.622.2500 Fax: 517.622.2525
ITP - The Rapid Silver Line BRT

Memorandum
TO: Attendees
File

FROM: Wilbur Smith Associates

DATE: November 4, 2010

SUBJECT: BRT Meeting with City of Wyoming and City of Kentwood

PROJECT: Silver Line BRT Project

Date/Time: November 4, 2010 at 2:30p.m.

Location: Wyoming Engineering Dept.


2660 Burlingame Avenue Southwest, Wyoming

Attendees:

Todd Davis, WSA


Isaac Norris, IVNA
Taiwo Jaiyeoba, The Rapid
Russ Henckell, City of Wyoming
Cayles Caceres, City of Wyoming
Tim Cochrau, City of Wyoming
Stephen Kepley, City of Kentwod
Terry Schweitzer, City of Kentwood
Patrick Hughes, City of Kentwood

The following represents our understanding of the key points of the meeting with both the City of
Wyoming and Kentwood.

Key comments and questions:

• Russ asked how many seconds will the green phase extend with the signal priority?
Concerned this may mess up other signal timing. Answer: this will not mess up overall
timing at signals as the signal will adjust the phase times to stay on the same overall timing
for that signal.
• The current Wyoming Opticom system is not maintained.
• Depth of platform question – 42” depth requirement for concrete platform.
• Snow plow equipment will need to be able to get under the canopy on the sidewalk – 10’
clearance needed
• Shelter roof edge needs to be 18” from back of curb (24” from face of curb).
• Utility relocation under the platform – who will be paying for that relocation? Utilities
should not be located under structures.
• Five feet of sidewalk clearance is required.

8164 Executive Court, Suite A – Lansing, Michigan 48917 517.622.2500 Fax: 517.622.2525
ITP - The Rapid Silver Line BRT
• How will platform drainage be handled?
• Can both cities provide the team with utility plan information? Carlos and Patrick are contact
persons. WSA will send them letters requesting information.
• Property line setback for canopy roof will be case by case if a building is adjacent; otherwise
okay to go to property line.
• Discussed curb drainage – integrated curb w/grate as potential solution.
• Question regarding shelter roof drainage – ice build-up, leaves, etc. Gravity may not be
enough.
• Will need to coordinate the construction schedule on Division with other projects scheduled
for the corridor.
• Who is responsible for station maintenance? A Memorandum of Understanding (MOU) is
being worked out between ITP and cities (Grand Rapids, Wyoming, Kentwood) to figure out
these issues.

8164 Executive Court, Suite A – Lansing, Michigan 48917 517.622.2500 Fax: 517.622.2525
ITP - The Rapid Silver Line BRT

Memorandum
TO: Attendees
File

FROM: Wilbur Smith Associates

DATE: November 5, 2010

SUBJECT: BRT Meeting with City of Grand Rapids

PROJECT: Silver Line BRT Project

Date/Time: November 5, 2010 at 9:30a.m.

Location: City of Grand Rapids, Traffic and Safety

Attendees:

Todd Davis, WSA


Matt Wendling, WSA
Isaac Norris, IVNA
Mark Wrona, URS
Eric Pratt, DDA
Taiwo Jaiyeoba, The Rapid
Chris Zull, City of GR
Rick DeVries, City of GR
Tom Drake, City of GR

The following represents our understanding the key points of the meeting with the City of Grand Rapids.

Key comments and questions:

• Current recommendation is to use Opticom


o Now is the time to go to GPS if needed
o Need to talk with the fire department to determine the correct direction and possible
funding and future plans (the fire department will begin by pursuing grants.)
o Preference is for one system
• Will bikes be allowed on the buses? Yes
• What is the approximate bus dwell time at a bus station? ~ 10 seconds.
• Water, sewer, gas, electric lines all under the sidewalk, thus under the station – what happens
if something breaks?
• Send utility requests to Rick.
• How will the station affect/integrate with the current street lights?
o Moving lights has been an issue in the past due to standards.
o South of 28th Street will be managed by Consumers Energy

8164 Executive Court, Suite A – Lansing, Michigan 48917 517.622.2500 Fax: 517.622.2525
ITP - The Rapid Silver Line BRT
• Will there be park-and-ride locations along corridor?
• The canopy needs to be 18” from back of curb (24” from face of curb)
• There is a possibility that a station could run into the location of a street light. Can the station
be modified to incorporate it? Moving a street light has been a challenge in the past.
However, the city is pretty inflexible on moving them. The city is only responsible for
Wealthy to 28th Street. BRT needs to work with independent cities.
• How close can the canopy be to the building face? Some of the buildings might have
canopies, lighting, etc. that could be affected by the bus station.
• How will the stations be powered? Stations will be powered by existing electrical services.
The stations will need fiber optic for communication.
• A cost analysis will need to be performed for an electric snow melt system. If there isn’t a
snow melt system for the stations, snow could be an issue and problem for riders.
• Dedicated lane issue: The city has a strong concern with regulation compliance. Minimizing
operating hours could be a solution. The city is currently looking into it. Eastbound
Michigan is fine, westbound Michigan should be shared.
• Burton Street NB should be dedicated, not shared as currently shown.
• 28th Street NB should be dedicated although there is a concern that the most congestion
occurs there. WSA followed what was in the EA.
• LOS D by movement NOT by intersection.

8164 Executive Court, Suite A – Lansing, Michigan 48917 517.622.2500 Fax: 517.622.2525
Meeting Register
Design Concepts
Silver Line Bus Rapid Transit (BRT)
Grand Rapids, Michigan

Technical Memorandum
Meeting Set #4
Summary of Stakeholder Engagement Meeting
(December 7, 2010)

December 8, 2010
STAKEHOLDER ENGAGEMENT MEETINGS

1.0 Meeting Details

Date of Meeting: December 7, 2010

Location: The Rapid Central Station


250 Grandville Ave. SW
Grand Rapids

Time: 10:00 am – Noon

Total # of Meeting
Attendees: 17 signed in

1.1 Stakeholder Invitation

An invitation letter was set to stakeholders on November 22, 2010. The Rapid followed up with
reminder e-mails to stakeholders each week leading up to the meetings. A copy of the invitation
letter is attached.

1.2 Meeting Format


The Stakeholder Engagement Meeting was conducted using a presentation style format. A
PowerPoint presentation was made to present the current status of the BRT project, provide
updates since the last Stakeholder Meeting, to review previously make public stakeholder
comments, present the preferred station design concept, and answer questions regarding the
project and proposed design. A copy of the presentation is attached. The meeting minutes are
also attached.

1.3 Summary of Comments Received


Stakeholders were encouraged to ask questions or leave written comment. A summary of the
discussion resulting from the questions asked and the written comments is attached.

1.4 Meeting Register


The Meeting Register from the Stakeholder Engagement Meeting held December 7, 2010 is
attached.

1
Stakeholder Invitation
Presentation
Stakeholder Engagement Meeting
Silver Line BRT Project
Interurban Transit Partnership – The Rapid
Agenda
… Introductions
… What we’ve done since we last met
… The Visioning and Preliminary Design
Process
… Station Concept Development - What we
heard from you
… Station Concepts
… Next Steps
What we’ve done since we last met
… Station Concept Development
† Iterative
Process with The Rapid
† Incorporated comments from stakeholder
meetings
† Coordinated with municipalities (Grand Rapids,
Wyoming, and Kentwood)
† Preliminary Cost Estimates

† Concept Evaluation

† ITP Board Meeting


The Visioning and Preliminary
Design Process
… Stakeholder meetings
… Design Program for Station and Roadway
… Traffic Simulation
… Bus Operations Report
… Survey of Station Locations
… Prototypical Pavement Marking Plans
… Communication Features and Interfaces Report
… Detailed Cost Estimate
… Station Platform and Pad Preliminary Design
Station Concept Development –
What we heard from you
… Comments on 8 areas of station design:
† General shelter structure appearance
† Weather protection and maintenance

† Sustainability practices and energy efficiency

† Integration of station with neighborhood/Art

† Visual, audio and surface accommodations

† Advertisement & naming rights for stations

† Bicycle accommodation/ADA compliance

† Station supporting elements


Let’s Revisit the Station Design
Framework
… Open Shelter design
… 10- or 14-inch high platforms
(precision docking)
… 60-foot platform lengths
(optimal)
… 14-foot platform width (optimal) Swift BRT Station (Everett, WA)

… Canopy
… Right-of-way limitations
… Adjacent land uses
… Sustainable
… Economical
… Specific station design will be
based upon station location HealthLine BRT Station (Euclid, OH)

(downtown vs. Division Corridor)


Preferred Design Conceptually
Approved by the ITP Board
Station Design Option A
Station Design Option B
Station Design Option C

Option C
Station Design Option D

Option D
Station Design Option E
Station Design Option F
Station Design Option F
Station Design Option F
Logan Street Station Southbound
Station Design Option F – Front
Elevation
Station Design Option F – Side
Elevation
Station Design Option F – Top
View
Station Design Option F -
Perspective
Sample Stations – Plan Views
Louis Street Station Northbound
Next Steps:
… Board informational presentation December 8, 2010
… Board consideration of conceptual A & E in January
2011
Questions?
Meeting Minutes
ITP - The Rapid Silver Line BRT

Memorandum
TO: Attendees
File

FROM: Wilbur Smith Associates

DATE: December 7, 2010

SUBJECT: Stakeholder Meeting #4 Minutes

PROJECT: Silver Line BRT Project

Date/Time: December 7, 2010, 10:00 am - Noon

Location: The Rapid Central Station

Attendees: See attached sign-in sheet

The following represents key comments and discussion from the meeting:

• Will fare machine and bike racks be at consistent locations at each station? Would like
consistency for ease of use. This has not been determined yet.

• Station looks more aesthetic when shorter. Worried about shelter being a barrier for adjacent
businesses.

• Likes idea that back of station is clear and sidewalk is open at rear.

• Have we considered a step at mid-point to allow access to the station? A: Can still be
considered.

• What happens to platform if station is reduced in size, can we keep raised platform (14”) to all
three doors of bus? A: Yes, optimal to allow access to all three doors even if station is
shorter.

• What consideration has been given to landscaping? A: Not much to date, but will engage
public more in design phase.

• Where is voice audio coming from at station and bus? A: Sound is at station and front door of
bus currently. Other door sound can be discussed.

• What intentions does Team/ITP have to work with local businesses to account for future
development? A: Some discussions have already occurred and more meetings will be held
during the subsequent design phase.

8164 Executive Court, Suite A – Lansing, Michigan 48917 517.622.2500 Fax: 517.622.2525
ITP - The Rapid Silver Line BRT
• Recommends reaching out to all businesses on upcoming development which may have an
effect on station locations.

• Please explain weather proofing systems for stations.


1) Canopy to catch water and drain down station column.
2) Windscreens for protection on either side depending on wind direction.
3) Snow – still discussing potential for snow melt system.

• 43rd Street station didn’t have crossing signal/light, how has team addressed this? A: Still
unresolved – this is documented and will be addressed in next phase.

• Looking at glass on either end of station:


1) Potential issue with sun glare – may be hard to see glass
2) Issue of cane under glass with user walking into glass
A: These issues will be looked at in final design – may need to add color to glass

• Have we considered rain barrels? A: It has been considered, but not resolved at this time.

• Recommend working with the downtown alliance for maintenance responsibilities – may use
water for other things.

• Is solar power being considered? A: It has been considered, but not resolved at this time.

• Monroe and Lewis – look at pedestrian crossing at this location.

Two written comments were received at the meeting:

Comment 1 - What is the anticipated pedestrian capacity on the platform? And if a bus pulls up
and I’m in line to get the ticket, does the bus wait or do I have to wait for the next bus? A: Bus
will wait.

Comment 2 - The site planning for our Wealthy Jefferson Development initiative is on a fast track
right now. The first construction is likely going to commence in June. We would like very much
to incorporate in our site planning the presence of the BRT stations. It would be very good for our
planner to get together with you ASAP.

A visually impaired discussion was held after the meeting between the consultant team and The Rapid.
The following represents the key points of the discussion:

• Very important to locate fare machines in consistent locations for easy access
• A concrete curb around glass screen would help guide visually impaired around
• Need a push button to activate next bus audio
• Keep landscaping heath low to avoid blocking station

8164 Executive Court, Suite A – Lansing, Michigan 48917 517.622.2500 Fax: 517.622.2525
Summary of Comments Received
Meeting Register
Contact List - Compiled from Stakeholder Lists and Meeting Attendees
Silver Line Bus Rapid Transit (BRT) Project
Contact Information for Team Members
Last Name First Name Organization Telephone Email Project Role Mailing Address Room (if applicable) City State Zip Fax

Design Team

Albaugh Lawrence Williams & Works (616) 224-1500 albaugh@williams-works.com 549 Ottawa Ave NE Grand Rapids MI 49503 (616) 224-1502
Connor Marlene Wilbur Smith Associates (413) 539-9005 mconnor@wilbursmith.com Transit Ops and Coordination 900 Chapel St Suite 1400 New Haven CT 06510 (203) 624-0484
Davis Todd Wilbur Smith Associates (517) 622-2503 TDAVIS@wilbursmith.com Project Director/Public Involvement 8164 Executive Dr Suite A Lansing MI 48917 (517) 622-2525
Dega Vinod Wilbur Smith Associates (614) 888-9440 VDEGA@wilbursmith.com Traffic/Traffic Control 1105 Schrock Rd Suite 200 Columbus OH 43229 (614) 888-6021
Goodreau Steve Wilbur Smith Associates (216) 875-2000 SGOODREAU@wilbursmith.com QA/QC 55 Public Square Suite 600 Cleveland OH 44113 (216) 875-2001
Holeman Eric Wilbur Smith Associates (773) 251-5001 eholeman@wilbursmith.com 801 Warrenville Rd Suite 260 Lisle IL 60532 (630) 434-8163
Hunter Matt Wilbur Smith Associates (517) 622-2508 mhunter@wilbursmith.com 8164 Executive Dr Suite A Lansing MI 48917 (510) 622-2525
Kelsch Sean URS Corporation (616) 574-8500 sean_kelsch@urscorp.com Site/Civil/Urban Design 3950 Sparks Dr SE Grand Rapids MI 49546 (616) 574-8542
Koenig Jim Wilbur Smith Associates (616) 622-2510 jkoenig@wilbursmith.com 8164 Executive Dr Suite A Lansing MI 48917 (517) 622-2525
Lee Truda Wilbur Smith Associates (804) 377-2300 TLEE@wilbursmith.com Scheduler 2112 West Laburnum Ave Suite 100 Richmond VA 23227 (804) 377-2301
Micheaux Theresa Wilbur Smith Associates (517) 622-2500 tmicheaux@wilbursmith.com 8164 Executive Dr Suite A Lansing MI 48917 (517) 622-2525
Norris Isaac Isaac V Norris & Associates (616) 452-3535 isaac.ivna@sbcglobal.net Station Design 1209 Kalamazoo SE Grand Rapids MI 49507 (616) 452-9913
Payseure Barney Clifton, Weiss & Associates (412) 8353957 bpayseure@cliftonweiss.com 524 Plymouth Rd Box 639 Gwynedd PA 19437 (215) 628-3165
Petko Theresa URS Corporation (616) 574-8500 Theresa_Petko@URSCorp.com Public/Stakeholder Involvement 3950 Sparks Dr SE Grand Rapids MI 49546 (616) 574-8542
Siniscalchi Debbie Wilbur Smith Associates (216) 875-2000 dsiniscalchi@wilbursmith.com 55 Public Square Suite 600 Cleveland OH 44113 (216) 875-2007
Talim Sushas Clifton, Weiss & Associates (215) 628-2640 x 25 stalim@cliftonweiss.com 524 Plymouth Rd Box 639 Gwynedd PA 19437 (215) 628-3165
Trepal Ralph Wilbur Smith Associates (216) 875-2000 RTREPAL@wilbursmith.com Project Manager 55 Public Square Suite 600 Cleveland OH 44113 (216) 875-2001
Vogelsang Phillip URS Corporation (616) 574-8500 Urban Design 3950 Sparks Dr SE Grand Rapids MI 49546 (616) 574-8542
Wendling Matt Wilbur Smith Associates (517) 622-2519 mwendling@wilbursmith.com Deputy Project Manager/Const Costs 8164 Executive Dr Suite A Lansing MI 48917 (517) 622-2525
Wrona Mark URS Corporation (616) 574-8500 Mark_E_Wrona@URSCorp.com Urban Design 3950 Sparks Dr SE Grand Rapids MI 49546 (616) 574-8542

Client

DeVries Judy ITP - The Rapid (616) 456-7514 jdevries@ridetherapid.org 300 Ellsworth Ave. SW Grand Rapids MI 49503 (616) 456-1941
Fedorowicz Mark ITP - The Rapid (616) 456-7514 mfedorowicz@ridetherapid.org Purchasing Manager 300 Ellsworth Ave. SW Grand Rapids MI 49503 (616) 456-1941
Jaiyeoba Taiwo ITP - The Rapid (616) 456-7514 tjaiyeoba@ridetherapid.org Project Manager 300 Ellsworth Ave. SW Grand Rapids MI 49503 (616) 456-1941
Kalczuk Jennifer ITP - The Rapid (616) 456-7514
456-7514 jkalczuk@ridetherapid.org External Relations Director 300 Ellsworth Ave. SW Grand Rapids MI 49503 (616) 456-1941
456-1941
Pouget Brian ITP - The Rapid (616) 456-7514 BPouget@ridetherapid.org Director of Operations 300 Ellsworth Ave. SW Grand Rapids MI 49503 (616) 456-1941
Scheuren Gary ITP - The Rapid (517) 582-5192 gary.scheuren@gmail.com Project Controls Consultant 830 N. Harrison Ave East Lansing MI 49504 (517) 332-3390
Schripper Steve ITP - The Rapid (616) 456-7514 Sschipper@ridetherapid.org Fleet and Facilities Manager 300 Ellsworth Ave. SW Grand Rapids MI 49503 (616) 456-1941
Varga Peter ITP - The Rapid (616) 456-7514 Pvarga@ridetherapid.org CEO 300 Ellsworth Ave. SW Grand Rapids MI 49503 (616) 456-1941
Venema Conrad ITP - The Rapid (616) 456-7514 Cvenema@ridetherapid.org Planning Manager 300 Ellsworth Ave. SW Grand Rapids MI 49503 (616) 456-1941

Stakeholders

Bachmeier Jim GVSU (616) 331-2188 bachmeij@gvsu.edu 1 Campus Drive Allendale MI 49401
Barton Chad (616) 285-6933 cbarton@rockfordconstruction.com 5540 Glenwood Hills Pkwy SE Grand Rapids MI 49512
Bessette Anne Marie Grand Rapids DDA (616) 456-3034 300 Monroe Ave NW Grand Rapids MI 49503
Bower Rae (616) 608-4718 raebower@gmail.com 475 Bruton Forest Ct SE Grand Rapids MI 49546
Bradford Jonathan ICCF (616) 336-9333 jbradford@iccf.org CEO 920 Cherry St SE Grand Rapids MI 49506 (616) 336-9323
Brann Tommy Brann's Restaurant (616) 690-7928 tombrann@branns.com
Bulkowski Dave DAKC (616) 949-1100 dave.b@dakc.org 3600 Camelot SE Grand Rapids MI 49546
Bulkowski Dick Steepletown Center (616) 451-4215 dick@steepletowncener.org 671 Davis Ave NW Grand Rapids MI 49504
Caceres Cayles City of Wyoming caceresc@wyomingmi.gov
Carey Keith kcarey@comcast.net
Champion Mark GRCC (231) 499-6042 mchampio@grcc.edu 143 Bostwick Ave NE Grand Rapids MI 49503
Cockran Tim City of Wyoming cockrant@wyomingmi.gov
D'Angelo Sam (616) 291-1365 samdangelo@hotmail.com 5301 S Division Ave Grand Rapids MI 49548
DeGood Jerry (616) 752-8691 jerrydegood@yahoo.com 2939 Division Wyoming MI 49548
Dressander Ron City of Wyoming (616) 249-3470 dressanr@wyomingmi.gov City Engineer 2660 Burlingame SW Wyoming MI 49509 (616) 249-3487
Duggan Joshua (616) 808-6585 joshuajduggan@gmail.com 619 Hawthorne St NE Grand Rapids MI 49503
Dutmer Casey (616) 534-0581 casey354@comcast.net 5930 Bayberry Farms Dr SW Grandville MI 49418
Earl Jan Heritage Hill Association (616) 459-8950 heritage@heritagehillweb.org 126 College SE Grand Rapids MI 49503 (616) 459-2409
Fluhartz Bill (616) 820-9425 bfluhartz@charter.net 2653 N 168th Ave Holland MI 49424
Fowler Jay Grand Rapids DDA (616) 456-3034 Executive Director 300 Monroe Ave NW Grand Rapids MI 49503
Graham Jennifer (616) 340-3310 jen.graham@sbcglobal.net 2298 Hidden Knoll Ave SE Caledonia MI 49316
Griffin Brandon (616) 485-0336 BTG@brandontgriffin.com 5021 Ciser Ave SW Wyoming MI 49548
Hartger Richard Cycle-Safe, Inc. (616) 954-9977 rhartger@cyclesafe.com President 478 Arrowhead SE Grand Rapids MI 49546
Hartger Susan Cycle-Safe, Inc. (616) 954-9977 shartger@cyclesafe.com 478 Arrowhead SE Grand Rapids MI 49546
Henckel Russ City of Wyoming henckelr@wyomingmi.gov
Hoekstra Jay GVMC (616) 459-8950 jay.hoekstra@gvmc.org Senior Planner 678 Front Ave NW Suite 200 Grand Rapids MI 49504 (616) 774-9292
Hood Rachel WMEAC (616) 451-3051 rhood@wmeac.org Executive Director 1007 Lake Dr SE Grand Rapids MI 49506 (616) 451-3054
Hughes Patrick City of Kentwood (616) 554-0739 hughesp@ci.kentwood.mi.us
Ingram Moss GRCC (616) 234-3067 mingram@grcc.edu 143 Bostwick Ave NE Grand Rapids MI 49503
Karnip Steve (616) 241-6304 steve.metromotors@gmail.com 3130 S Division Ave Wyoming MI 49548
Kepley Steve City of Kentwood (616) 554-0740 kepleys@ci.kentwood.mi.us City Engineer 4900 Breton Rd SE P.O. Box 8848 Kentwood MI 49518 (616) 698-7118
Kooiman Jerry MSU College of Human Med. (616) 234-2604 jerry.kooiman@hc.msu.edu Asst. Dean for Govt. Relations and Outreach 234 Division North Suite 400 Grand Rapids MI 49503
Kubicek Jim (616) 446-0547 jkubicek@iserv.net 3238 S Division Ave Wyoming MI 49548
Larobardiere Matt City of Grand Rapids (616) 456-3066 mlarobar@grcity.us 509 Wealthy SW Grand Rapids MI 49503
Leach, Jr. James (616) 538-1470 jimjr@hobartgr.com 4064 S Division Ave Wyoming MI 49548
Lewis Mark Neighborhood Venturer (616) 301-3929 lewism@neighborhoodventurer.org 1514 Wealthy #214 Grand Rapids MI 49502
Lockray Tim City of Wyoming (616) 530-7259 Wyoming MI 49548
MacKeigan Richard (616) 742-6189 rmackeigan@smggr.com 130 W Fulton Grand Rapids MI 49503
Mast Harold (616) 262-7268 hamast@comcast.net P.O. Box 8737 Kentwood MI 49518
McCormick Liz GRCC (616) 234-4081 lmccormick@grcc.edu 143 Bostwick Ave NE Grand Rapids MI 49503
Mullen Eric GRCC (616) 234-4164 emuller@grcc.edu Director of Student Activities 143 Bostwick Ave NE Grand Rapids MI 49503
Occhiping Nick WMEAC (616) 451-3051 nocchiping@wmeac.org 1007 Lane Drive S Grand Rapids Mi 49506
Oeverman Jon City of Grand Rapids (616) 456-3066 joeverman@grcity.us 509 Wealthy SW Grand Rapids MI 49503
Pomorski Tim (616) 262-3110 Timtech20@yahoo.com 240 Elwell Wyoming MI 49548
Pratt Eric Grand Rapids DDA (616) 456-3796 epratt@grcity.us Planner 300 Monroe Ave NW Grand Rapids MI 49503
Redmond Steve MDOT (616) 451-3091 redmonds@michigan.gov 1420 Front NW Grand Rapids MI 49504
Reeves Tim Kelloggsville Public Schools (616) 532-1570 treeves@kvilleps.org Middle School Principal 4560 S Division Ave Grand Rapids MI 49548
Schulz Suzanne City of Grand Rapids (616) 456-3646 sschulz@grcity.us Planning Director 1120 Monroe Ave NW Grand Rapids MI 49503
Schweitzer Terry City of Kentwood (616) 554-0710 schweitt@ci.kentwood.us Community Development Director 4900 Breton Ave SE Kentwood MI 49518 (616) 698-8199
Teles Paulo GRCC (616) 234-3754 pteles@grcc.edu Associate Director of Student Activities 143 Bostwick Ave NE Grand Rapids MI 49503
Terbush Ryan GVSU (810) 623-0749 terbushr@gvsu.edu 606 Valley Ave NW Grand Rapids MI 49504
Tilma Tom (616) 560-5705 thomastilma@gmail.com 1635 Hall St SE Grand Rapids MI 49506
VanElsacker Amy (906) 399-3330 vanelsa1@hotmail.com 120 S Division Ave Grand Rapids MI 49503
Vega Francisco (616) 245-5924 PanchVega@aol.com 1317 Giddings Ave SE Grand Rapids MI 49506
Victor Michael Neighborhood Venturer (616) 301-3929 michaelvictor@gmail.com 1514 Wealthy #214 Grand Rapids MI 49502
Warsen Greg Kelloggsville Public Schools (616) 538-7460 gwarsen@kvilleps.org Admin. Superintendent 242 52nd St SE Kentwood MI 49548 (616) 532-1597
Zull Chris City of Grand Rapids (616) 456-4639 czull@grcity.us City Traffic Engineer 300 Monroe Ave NW Grand Rapids MI 49503 (616) 456-3828

Updated 12/29/2010
 

 
Appendix B 
 
Illustrations of Station Concepts 
 
 

  
Final Task I Vision Report 
 
 
Final Station Concept
Final Station Concept
 

 
Appendix C 
 
Mapping of Dedicated/Non­Dedicated Bus 
Lanes and Station Locations 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
  
Final Task I Vision Report 
 
 
Legend
Final Proposed BRT Stations

New Crosswalk Proposed

AU
MP
Existing Bus Stop

CA Parcel Lines (from REGIS)


Lane Assignments During Peak Hours
7am - 9am & 4pm - 6pm
Dedicated Lane

Shared Lane

MONROE
Louis St (SB)

Louis St (NB)
S
UI
LO

BRT Base Mapping 0 20 40 Sheet

ER
NT
Louis Street Station

CE
Feet
1 of 17

E
O
NR
Monroe Avenue 1 inch = 40 feet

O
M
November 3, 2010
Legend
Final Proposed BRT Stations

New Crosswalk Proposed

Existing Bus Stop


Parcel Lines (from REGIS)
Lane Assignments During Peak Hours
7am - 9am & 4pm - 6pm
Dedicated Lane

Shared Lane

Van Andel (SB)


MONROE

Van Andel (NB)

BRT Base Mapping 0 20 40 Sheet


Van Andel Station Feet
2 of 17
Monroe Avenue 1 inch = 40 feet
November 3, 2010
Legend
Final Proposed BRT Stations

New Crosswalk Proposed

Existing Bus Stop


Parcel Lines (from REGIS)
Lane Assignments During Peak Hours
7am - 9am & 4pm - 6pm
Dedicated Lane

Shared Lane

MICHIGAN
Michigan St (WB)
Michigan St (EB)

BOSTWICK

BRT Base Mapping 0 20 40 Sheet


Michigan Street Station Feet
3 of 17
Michigan Street 1 inch = 40 feet
November 3, 2010
Legend
Final Proposed BRT Stations

New Crosswalk Proposed

Existing Bus Stop


Parcel Lines (from REGIS)
Lane Assignments During Peak Hours
7am - 9am & 4pm - 6pm
Dedicated Lane

Shared Lane

CRESCENT
LYON

RANSOM

G.R.C.C. (SB)

G.R.C.C. (NB)

BRT Base Mapping 0 20 40 Sheet


G.R.C.C. Station Feet
4 of 17
Ransom Street 1 inch = 40 feet
November 3, 2010
Legend
Final Proposed BRT Stations

New Crosswalk Proposed

Existing Bus Stop


Parcel Lines (from REGIS)
Lane Assignments During Peak Hours
7am - 9am & 4pm - 6pm
Dedicated Lane

Shared Lane

LA GRAVE

LIBRARY
Fulton St (SB) RANSOM
FULTON

Fulton St (NB)

BRT Base Mapping 0 20 40 Sheet


Fulton Street Station Feet
5 of 17
Ransom Street JEFFERSON 1 inch = 40 feet
November 3, 2010
GOODRICH
Legend
Final Proposed BRT Stations

New Crosswalk Proposed

Existing Bus Stop


Parcel Lines (from REGIS)
ALLEY LAGRAVE
Lane Assignments During Peak Hours
7am - 9am & 4pm - 6pm
Dedicated Lane

Shared Lane
GOODRICH

MAPLE
JEFFERSON

Wealthy St (SB)

Wealthy St (NB)

CESS
CESS

SAINT MARY’S AC
SAINT MARY’S AC

BRT Base Mapping 0 20 40 Sheet


Wealthy Street Station Feet
6 of 17
Jefferson Street 1 inch = 40 feet
November 3, 2010
Legend
Final Proposed BRT Stations

New Crosswalk Proposed

Existing Bus Stop


Parcel Lines (from REGIS)
Lane Assignments During Peak Hours

MCCONNELL
7am - 9am & 4pm - 6pm

LOGAN
Dedicated Lane

Shared Lane

DIVISION
Logan St (SB)

LOGAN

ALLEY DIVISION

Logan St (EB)

BRT Base Mapping 0 20 40 Sheet


Logan Street Station Feet
7 of 17
Division Street and Logan Street 1 inch = 40 feet
November 3, 2010
Legend
Final Proposed BRT Stations

New Crosswalk Proposed

Existing Bus Stop


Parcel Lines (from REGIS)
Lane Assignments During Peak Hours
7am - 9am & 4pm - 6pm
Dedicated Lane

Shared Lane

GRAHAM
DIVISION
Franklin St (SB)

Franklin St (NB)

FRANKLIN

BRT Base Mapping 0 20 40 Sheet


Franklin Street Station Feet
8 of 17
Division Street 1 inch = 40 feet
November 3, 2010
Legend
Final Proposed BRT Stations

New Crosswalk Proposed

Existing Bus Stop


Parcel Lines (from REGIS)
Lane Assignments During Peak Hours
7am - 9am & 4pm - 6pm
Dedicated Lane

Shared Lane

PUTNAM
CANTON

DIVISION
Green St (SB)

GREEN
Green St (NB)

BRT Base Mapping 0 20 40 Sheet


Green Street Station Feet
9 of 17
Division Street 1 inch = 40 feet
November 3, 2010
Legend
Final Proposed BRT Stations

New Crosswalk Proposed

Existing Bus Stop


Parcel Lines (from REGIS)
Lane Assignments During Peak Hours
7am - 9am & 4pm - 6pm
Dedicated Lane

Shared Lane

COTTAGE GROVE
DIVISION

Cottage Grove St (SB)

Cottage Grove St (NB)

COTTAGE GROVE
CROFTON

BRT Base Mapping 0 20 40 Sheet


Cottage Grove Street Station Feet
10 of 17
Division Street 1 inch = 40 feet
November 3, 2010
ALLEY QUIGLEY
ALLEY BURTON
Legend
Final Proposed BRT Stations

New Crosswalk Proposed


ALLEY DIVISION
ALLEY DIVISION Existing Bus Stop
Parcel Lines (from REGIS)
Lane Assignments During Peak Hours
7am - 9am & 4pm - 6pm
Dedicated Lane

Shared Lane

BURTON

QUIGLEY
Shared platform with existing bus stop.

DIVISION
Burton St (SB)

Burton St (NB)

ALLEY DIVISION

ALLEY DIVISION
ALLEY BURTON

BRT Base Mapping 0 20 40 Sheet


Burton Street Station Feet
11 of 17
Division Street 1 inch = 40 feet
November 3, 2010
Legend
Final Proposed BRT Stations

New Crosswalk Proposed

Existing Bus Stop


Parcel Lines (from REGIS)
Lane Assignments During Peak Hours
7am - 9am & 4pm - 6pm
Dedicated Lane

BLACKBURN
Shared Lane

SOUTHVIEW
DIVISION Southview St (SB)

SOUTHVIEW
Southview St (NB)

ALLEY DIVISION

44TH
BRT Base Mapping 0 20 40 Sheet
Southview Street Station Feet
12 of 17
Division Street 1 inch = 40 feet
November 3, 2010
Legend
Final Proposed BRT Stations

New Crosswalk Proposed

Existing Bus Stop


Parcel Lines (from REGIS)
Lane Assignments During Peak Hours
7am - 9am & 4pm - 6pm
Dedicated Lane

Shared Lane

HONEOYE

28th StN (SB)


DIVISIO

28th St (NB)

28TH
BRT Base Mapping 0 20 40 Sheet
28th Street Station Feet
13 of 17
Division Street 1 inch = 40 feet
November 3, 2010
Legend
Final Proposed BRT Stations

New Crosswalk Proposed

Existing Bus Stop


Parcel Lines (from REGIS)
Lane Assignments During Peak Hours
7am - 9am & 4pm - 6pm
Dedicated Lane

Shared Lane

36th St (SB)
DIVISION

36TH 36th St (NB)

WEXFORD
BRT Base Mapping 0 20 40 Sheet
36th Street Station Feet
14 of 17
Division Street 1 inch = 40 feet
November 3, 2010
Legend
Final Proposed BRT Stations

New Crosswalk Proposed

Existing Bus Stop


Parcel Lines (from REGIS)
Lane Assignments During Peak Hours
7am - 9am & 4pm - 6pm
Dedicated Lane

Shared Lane

FARNHAM

44th St (SB) DIVISION

44th St (NB)

44TH
BRT Base Mapping 0 20 40 Sheet
44th Street Station Feet
15 of 17
Division Street 1 inch = 40 feet
November 3, 2010
Legend
Final Proposed BRT Stations

New Crosswalk Proposed

Existing Bus Stop


Parcel Lines (from REGIS)
Lane Assignments During Peak Hours
7am - 9am & 4pm - 6pm
Dedicated Lane

Shared Lane

54TH
DIVISION
54th St (SB)

KELLOGG WOODS
54th St (NB)

BRT Base Mapping 0 20 40 Sheet


54th Street Station Feet
16 of 17
Division Street 1 inch = 40 feet
November 3, 2010
Legend
Final Proposed BRT Stations

New Crosswalk Proposed

Existing Bus Stop


Parcel Lines (from REGIS)
Lane Assignments During Peak Hours
7am - 9am & 4pm - 6pm
Dedicated Lane

Shared Lane

DIVISION

60th St (NB)

BRT Base Mapping 0 20 40 Sheet


60th Street Station Feet
17 of 17
Division Street 1 inch = 40 feet
November 3, 2010
 

 
Appendix D 
 
Prototypical Pavement Marking Plans, 
Roadway Concept Typical Sections and  
Plans, and Station Platform Layouts 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
   
  
Final Task I Vision Report 
 
 
SHEET
NUMBERS

TITLE

TYPICAL CROSS SECTIONS


1

2
THE RAPID
ROADWAY PLAN SHEETS 3-24

STATION DETAILS 25-43

PAVEMENT MARKING PROTOTYPES 44-48

SILVERLINE BUS RAPID TRANSIT

CONCEPTUAL PLAN
KENT
COUNTY
SUBMITTAL
1/18/2011

COUNTY KEY

PROPOSED SILVERLINE
BUS RAPID TRANSIT
ROUTE

DATE

01/18/11
Surface Transportation
Grand Rapids . Southfield .
SHEET
Traverse City

1
FINAL R.O.W.

AUTH DATE NO. REVISION

VARIES 2’ TO 2.5’

VARIES 9’ TO 12’ 8’ (TYPICAL) 6’ MIN.


BUS PAD STATION SIDEWALK

VARIES 2’ TO 2.5’
EXISTING GROUND
14" OR 10" 2% MAX. 2% MAX. VARIES 9’ TO 12’ 8’ (TYPICAL) 6’ MIN.
2% BUS PAD STATION SIDEWALK
AT EXISTING
EXISTING SIDEWALK GRADE
6" SIDEWALK
EXISTING ROAD 10" CONCRETE (TO BE REMOVED
AND REPLACED AS EXISTING GROUND

14"
MODIFIED CURB AND GUTTER
NEEDED) 2% MAX. 2% MAX.
2%
TYPICAL STATION CROSS SECTION
TO APPLY: EXISTING SIDEWALK
6" SIDEWALK
DEVOS PLACE SB STATION EXISTING ROAD 10" CONCRETE (TO BE REMOVED
GRCC NB STATION AND REPLACED AS
GRCC SB STATION MODIFIED CURB AND GUTTER
NEEDED)
WEALTHY NB STATION

DATE: 01/18/11
WEALTHY SB STATION TYPICAL STATION CROSS SECTION
DIVISION AND LOGAN NB STATION TO APPLY:
DIVISION AND FRANKLIN SB STATION LOUIS AND MONROE SB STATION
DIVISION AND GREEN NB STATION
DIVISION AND GREEN SB STATION
DIVISION AND COTTAGE GROVE NB STATION
DIVISION AND COTTAGE GROVE SB STATION
DIVISION AND BURTON NB STATION
DIVISION AND SOUTHVIEW NB STATION
DIVISION AND SOUTHVIEW SB STATION
DIVISION AND 28TH NB STATION
DIVISION AND 28TH SB STATION
DIVISION AND 36TH NB STATION
DIVISION AND 44TH NB STATION
DIVISION AND 44TH SB STATION
DIVISION AND 54TH NB STATION

WORKED ON BY: JSB


DIVISION AND 54TH SB STATION
DIVISION AND 60TH STATION

VARIES 2’ TO 2.5’

VARIES 9’ TO 12’ 8’ (TYPICAL) 6’ MIN.


BUS PAD STATION SIDEWALK
AT EXISTING
GRADE

01/18/11
EXISTING GROUND

14"
VARIES 2’ TO 2.5’ 2% MAX.
2% MAX.
2%
VARIES 9’ TO 12’ 8’ (TYPICAL) 6’ MIN.

DATE:
BUS PAD STATION SIDEWALK
6" SIDEWALK EXISTING SIDEWALK
EXISTING ROAD 10" CONCRETE (TO BE REMOVED
AND REPLACED AS
MODIFIED CURB AND GUTTER
NEEDED)
EXISTING GROUND
14" OR 10" 2% MAX. 2% MAX. TYPICAL STATION CROSS SECTION
2% TO APPLY:
LOUIS AND MONROE NB STATION
EXISTING SIDEWALK
6" SIDEWALK DEVOS PLACE NB STATION
EXISTING ROAD 10" CONCRETE (TO BE REMOVED
MICHIGAN AND BOSTWICK NB STATION
AND REPLACED AS
MODIFIED CURB AND GUTTER MICHIGAN AND BOSTWICK SB STATION
NEEDED)
DIVISION AND LOGAN SB STATION

TRW
DIVISION AND FRANKLIN NB STATION
TYPICAL STATION CROSS SECTION DIVISION AND BURTON SB STATION

CHECKED BY:
TO APPLY:
DIVISION AND 36TH SB STATION
FULTON AND RANSOM NB STATION
FULTON AND RANSOM SB STATION

42679_01_TYP.DGN
CONSTRUCTION SHEET

0 3 5 10 TYPICAL SECTIONS

FILE NAME:
Surface Transportation
DATE CONT. SEC. JOB NO. DESIGN UNIT SHEET NO.
Grand Rapids . Southfield .
10 SCALE R.O.W CONST.
Traverse City

01/18/11 2
FINAL R.O.W.
60TH ST
AUTH DATE NO. REVISION

SECTION 1 SECTION 36
T5N,R12W T6N,R12W
BYRON TWP CITY OF WYOMING

EX 66’ ROW
FAIR PAVEMENT CONDITION

DATE: 01/18/11
DIVISION AVE FROM 44TH ST TO 60TH ST

CITY OF WYOMING
PROPOSED RECONSTRUCTION & BOULEVARD BY THE CITY OF KENTWOOD - 2014

BYRON TWP
DIVISION AVE FROM 54TH ST TO 60TH ST

MICHIGAN MOBILE
HOME CONNECTION
NEW PAVEMENT MARKINGS GRIFFINS
BASED ON PROTOTYPICAL PLANS TRUCK CAPS
DIVISION AVE

TRAILER/RV SALES
BMW MOTORCYCLES

DIVISION AVE
SEE NEXT SHEET
EX 83’ ROW

EX ROW

EX 83’ ROW
BYRON TWP
100 105 CITY OF WYOMING 110 115
GAINES TWP
CITY OF KENTWOOD

WORKED ON BY: JSB


EX ROW
CROSSROADS HIGH SCHOOL
AAA AUTO SALES
DW3 ARNOLD’S
TOWNLINE ELEMENTARY MOTORCYCLES
DIVISION AND 60TH NB STATION

FAMILY DOLLAR AUTO DRIVEAWAY


CITY OF KENTWOOD

01/18/11
EX 60’ ROW
GAINES TWP

DATE:
DEDICATED BUS RAPID TRANSIT IN OUTSIDE LANES
DURING MORNING AND AFTERNOON PEAK PERIODS

EX 66’ ROW

TRW
SECTION 6 SECTION 31

CHECKED BY:
T5N,R11W T6N,R11W
GAINES TWP CITY OF KENTWOOD

42679_DIVISION_10000.DGN
60TH ST

KEY MAP

58TH ST

CONSTRUCTION
MAJESTIC ST SHEET

200 600 1000 DIVISION AVE STA 100+00 TO STA 116+00

FILE NAME:
0 400 800 Surface Transportation
SHEET NO.
DATE CONT. SEC. JOB NO. DESIGN UNIT
Grand Rapids . Southfield .
200 SCALE R.O.W CONST.
Traverse City

01/18/11 3
FINAL R.O.W.
56TH ST 54TH ST
AUTH DATE NO. REVISION

PROPOSED RESURFACING BY THE CITY OF WYOMING - 2012


SECTION 36
T6N,R12W
CITY OF WYOMING

54TH ST FROM CLYDE PARK TO DIVISION


FAIR PAVEMENT CONDITION
DIVISION AVE FROM 44TH ST TO 60TH ST
EX 105’ ROW

PROPOSED RECONSTRUCTION & BOULEVARD BY THE CITY OF KENTWOOD - 2014

DATE: 01/18/11
DIVISION AVE FROM 54TH ST TO 60TH ST

NEW PAVEMENT MARKINGS


BASED ON PROTOTYPICAL PLANS
EX 66’ ROW PROPOSED RESURFACING
BY THE CITY OF WYOMING - 2013
SHELL GAS DIVISION AVE FROM
DIVISION AND 54TH SB STATION
44TH ST TO 54TH ST

EX 89’ ROW
BROTHER’S MARINE & SUPERIOR TRANSIT HABITAT FOR HUMANITY JANSMA EYE CARE
MORE DOTTED RIGHT LANE PAVEMENT MARKING
100’ BEFORE INTERSECTION
SEE PREVIOUS SHEET
DIVISION AVE

DIVISION AVE
EX ROW

EX 100’ ROW
SEE NEXT SHEET
EX 83’ ROW

120 125 CITY OF WYOMING 130 135 140


CITY OF KENTWOOD

WORKED ON BY: JSB


EX ROW

AAA AUTO SALES

AAA AUTO SALES


MIDWAY RV CENTER MULTIPLE BUSINESSES GOODWILL BIG LOTS

NEW BEGINNINGS

673

673
.41

.82
DIVISION AND 54TH NB STATION
EX 70’ ROW

01/18/11
DOTTED RIGHT LANE PAVEMENT MARKING
100’ BEFORE INTERSECTION

DATE:
W
RO
80’
EX

DEDICATED BUS RAPID TRANSIT IN OUTSIDE LANES


DURING MORNING AND AFTERNOON PEAK PERIOD

SECTION 31

TRW
T6N,R11W
CITY OF KENTWOOD

CHECKED BY:
42679_DIVISION_11600.DGN
NANCY ST
KEY MAP

54TH ST

CONSTRUCTION SHEET

200 600 1000 DIVISION AVE STA 116+00 TO STA 141+00

FILE NAME:
0 400 800 Surface Transportation
SHEET NO.
DATE CONT. SEC. JOB NO. DESIGN UNIT
Grand Rapids . Southfield .
200 SCALE R.O.W CONST.
Traverse City

01/18/11 4
FINAL R.O.W.

AUTH DATE NO. REVISION

SECTION 36 SECTION 25
T6N,R12W T6N,R12W
CITY OF WYOMING CITY OF WYOMING

FAIR PAVEMENT CONDITION


DIVISION AVE FROM 44TH ST TO 60TH ST

DATE: 01/18/11
PROPOSED RESURFACING BY THE CITY OF WYOMING - 2013
DIVISION AVE FROM 44TH ST TO 54TH ST

SHELL GAS
HOME ACRES SILVER BULLET SOUTHSIDE STORAGE CAR WASH
USED CARS B&M AUTO SERVICE SIGNS NOW MUFFLER MAN

EX 125’ ROW
BUILDING SUPPLY AND RENTAL
ROXIE’S ANTIQUES
DOTTED RIGHT LANE PAVEMENT MARKING
100’ BEFORE INTERSECTION
SEE PREVIOUS SHEET
DIVISION AVE

DIVISION AVE
SEE NEXT SHEET
EX ROW
EX 100’ ROW

EX 100’ ROW
CITY OF WYOMING
145 150 155 160 165

CITY OF KENTWOOD

WORKED ON BY: JSB


EX ROW

BRYCE’S ROADBED MINISTRIES


MULTIPLE BUSINESSES
EXPERT SERVICE
MULTIPLE BUSINESSES WINDOW WORLD DIVISION TURF CITGO

MULTIPLE BUSINESSES

EX 66’ ROW

01/18/11
DATE:
DEDICATED BUS RAPID TRANSIT IN OUTSIDE LANES
DURING MORNING AND AFTERNOON PEAK PERIODS

SECTION 31
T6N,R11W SECTION 30

CITY OF KENTWOOD T6N,R11W


CITY OF KENTWOOD

TRW
CHECKED BY:
42679_DIVISION_14100.DGN
KEY MAP

52ND ST CONSTRUCTION SHEET

200 600 1000 DIVISION AVE STA 141+00 TO STA 166+00

FILE NAME:
0 400 800 Surface Transportation
SHEET NO.
DATE CONT. SEC. JOB NO. DESIGN UNIT
Grand Rapids . Southfield .
200 SCALE R.O.W CONST.
Traverse City

01/18/11 5
FINAL R.O.W.
60TH ST HOLLY ST JEAN ST ELWELL ST LEROY ST
AUTH DATE NO. REVISION

SECTION 25
T6N,R12W
CITY OF WYOMING

FAIR PAVEMENT CONDITION


DIVISION AVE FROM 44TH ST TO 60TH ST

PROPOSED RESURFACING BY THE CITY OF WYOMING - 2013

DATE: 01/18/11
DIVISION AVE FROM 44TH ST TO 54TH ST

EX 50’ ROW
EX 50’ ROW
EX 50’ ROW
EX 50’ ROW

GREAT LAKES KELLOGSVILLE MULTIPLE


BRANN’S CATERING GREAT LAKES EUROSPORTS THE DOCK CAR WASH
AUTO HIGH SCHOOL BRICKCRETE MOTEL BUSINESSES
DIVE LOCKER
DIVISION AVE

SEE PREVIOUS SHEET

SEE NEXT SHEET

DIVISION AVE
EX ROW
EX 100’ ROW

EX 97’ ROW
170 175 CITY OF WYOMING 180 185 190
CITY OF KENTWOOD

WORKED ON BY: JSB


EX ROW

STELTER’S LENTZ LA CORONA


UNCLE FRED’S ELECTRICAL AUTO WORLD BEST BUY
PET GROOMING HOBBY GONE MARATHON GAS ALL NIGHT RECOVERY AUTO SERVICE
PARTY STORE MATERIALS USED CARS
WILD PHOTOGRAPHY

EX 50’ ROW
EX 50’ ROW

01/18/11
EX 55’ ROW

EX 50’ ROW

DATE:
EX 68’ ROW

DEDICATED BUS RAPID TRANSIT IN OUTSIDE LANES

TRW
DURING MORNING AND AFTERNOON PEAK PERIODS

CHECKED BY:
SECTION 30
T6N,R11W
CITY OF KENTWOOD

42679_DIVISION_16600.DGN
SLUYTER ST DANIEL ST

KEY MAP

KELLOGSVILLE
MIDDLE SCHOOL

GARLAND ST 48TH ST 47TH ST CONSTRUCTION SHEET

200 600 1000 DIVISION AVE STA 166+00 TO STA 191+00

FILE NAME:
0 400 800 Surface Transportation
SHEET NO.
DATE CONT. SEC. JOB NO. DESIGN UNIT
Grand Rapids . Southfield .
200 SCALE R.O.W CONST.
Traverse City

01/18/11 6
FINAL R.O.W.
MONTABELLO ST FARNHAM ST 44TH ST MURRAY ST 43RD ST
AUTH DATE NO. REVISION

SECTION 25 SECTION 24
T6N,R12W T6N,R12W
CITY OF WYOMING CITY OF WYOMING

FAIR PAVEMENT CONDITION EXCELLENT PAVEMENT CONDITION


DIVISION AVE FROM 44TH ST TO 60TH ST DIVISION AVE FROM 36TH ST TO 44TH ST
EX 120’ ROW

PROPOSED RESURFACING BY THE CITY OF WYOMING - 2013 RESURFACED BY THE CITY OF WYOMING - SEPTEMBER 2010
DIVISION AVE FROM 44TH ST TO 54TH ST DIVISION AVE FROM 36TH ST TO 44TH ST

NEW PAVEMENT MARKINGS

DATE: 01/18/11
BASED ON PROTOTYPICAL PLANS DOTTED RIGHT LANE PAVEMENT MARKING
100’ BEFORE INTERSECTION

EX 66’ ROW
DIVISION AND 44TH SB STATION
EX 66’ ROW
EX 60’ ROW
EX 60’ ROW

WALGREEN’S

BP GAS STATION FIRESTONE


DEALER’S CHOICE ALL SEASONS FIRE DEPARTMENT MULTIPLE BUSINESSES CHASE
GEORGE’S
AUTO BODY AUTO BANK SALON
TRANSMISSION GORDY’S
AUTO
SEE PREVIOUS SHEET

CLASSIC FAMILY
SUPERMARKET
DIVISION AVE

DIVISION AVE
SEE NEXT SHEET
HAIR STUDIO PERFORMANCE
EX ROW

EX 103’ ROW
702
705

.95
.10
EX 98’ ROW

195 CITY OF WYOMING 200 205 210 CITY OF WYOMING 215


CITY OF KENTWOOD CITY OF KENTWOOD

WORKED ON BY: JSB


EX ROW

CASA VIA
EX 107’ ROW

CONEY SOUTH UNITED MULTIPLE BUSINESSES


MOTEL BUEKLER REALTY MULTIPLE GOLDEN

701
.62
ISLAND METHODIST CHURCH MULTIPLE BUSINESSES
BUSINESSES VINACOM BRIDGE PLAZA

ADVANCE
AUTO PARTS

EX 66’ ROW EX 66’ ROW EX 66’ ROW


EX 60’ ROW

01/18/11
RITE-AID

EX 55’ ROW

DIVISION AND 44TH NB STATION

DATE:
EX 70’ ROW

DOTTED RIGHT LANE PAVEMENT MARKING


100’ BEFORE INTERSECTION

DEDICATED BUS RAPID TRANSIT IN OUTSIDE LANES


DURING MORNING AND AFTERNOON PEAK PERIODS

TRW
CHECKED BY:
SECTION 30
T6N,R11W
CITY OF KENTWOOD SECTION 19
T6N,R11W
CITY OF KENTWOOD

42679_DIVISION_19100.DGN
MONTABELLO ST RIDGEWOOD ST

KEY MAP

43RD ST

FARNHAM ST 44TH ST MURRAY ST


CONSTRUCTION SHEET

200 600 1000 DIVISION AVE STA 191+00 TO STA 216+00

FILE NAME:
0 400 800 Surface Transportation
SHEET NO.
DATE CONT. SEC. JOB NO. DESIGN UNIT
Grand Rapids . Southfield .
200 SCALE R.O.W CONST.
Traverse City

01/18/11 7
FINAL R.O.W.
MAPLELAWN ST THURSTON ST BELLEVUE ST 41ST ST FLOYD ST WADSWORTH ST 39TH ST
AUTH DATE NO. REVISION

SECTION 24
T6N,R12W
CITY OF WYOMING

EXCELLENT PAVEMENT CONDITION


DIVISION AVE FROM 36TH ST TO 44TH ST

RESURFACED BY THE CITY OF WYOMING - SEPTEMBER 2010


DIVISION AVE FROM 36TH ST TO 44TH ST

DATE: 01/18/11
EX 66’ ROW
EX 66’ ROW

EX 66’ ROW
EX 80’ ROW EX 66’ ROW
EX 66’ ROW EX 60’ ROW

WASH WORLD
THV BRANN’S
AUTO HOLIDAY
FINANCIALS

DIVISION AVE
BURGER KING AUTO KING SHARP CAR
SEE PREVIOUS SHEET

CONSIDER COSTUMES GOLDEN GATE

SEE NEXT SHEET


DIVISION AVE

RESTAURANT
EX ROW

EX 100’ ROW
EX 103’ ROW

705
.94

235 240
220 225 230

WORKED ON BY: JSB


EX ROW

R&M
FAT MAN’S
LITTLE’S
FISH FRY CASH HOBART MICHIGAN TRAILER S & G IMPORTED JOSE’S RESTAURANT WINDOW TINTING
MULTIPLE DAIRY DEN CUSTOM CYCLES AUTO TOWING
ADVANCE PARIS MOTORS SALES & SERVICE PARTS CAR PARTS
BUSINESSES

MULTIPLE BUSINESSES

EX 66’ ROW EX 66’ ROW EX 66’ ROW


EX 66’ ROW EX 66’ ROW EX 66’ ROW
CITY OF KENTWOOD

CITY OF WYOMING

01/18/11
EX 66’ ROW

DATE:
DEDICATED BUS RAPID TRANSIT IN OUTSIDE LANES
DURING MORNING AND AFTERNOON PEAK PERIODS

TRW
CHECKED BY:
SECTION 19 SECTION 19
T6N,R11W T6N,R11W
CITY OF KENTWOOD CITY OF WYOMING

42679_DIVISION_21600.DGN
MAPLELAWN ST BELLEVUE ST

KEY MAP

WALTER AVE

WILBUR ST BURT AVE JANET AVE CONSTRUCTION SHEET

200 600 1000 DIVISION AVE STA 216+00 TO STA 241+00

FILE NAME:
0 400 800 Surface Transportation
SHEET NO.
DATE CONT. SEC. JOB NO. DESIGN UNIT
Grand Rapids . Southfield .
200 SCALE R.O.W CONST.
Traverse City

01/18/11 8
FINAL R.O.W.

JORDAN ST CALHOUN ST COOLIDGE ST 36TH ST AUTH DATE NO. REVISION

SECTION 24
T6N,R12W
CITY OF WYOMING

EX 82’ ROW

EXCELLENT PAVEMENT CONDITION FAIR/POOR PAVEMENT CONDITION


DIVISION AVE FROM 36TH ST TO 44TH ST DIVISION AVE FROM 28TH ST TO 36TH ST

DATE: 01/18/11
RESURFACED BY THE CITY OF WYOMING - SEPTEMBER 2010 PROPOSED RESURFACING BY THE CITY OF WYOMING - 2013
DIVISION AVE FROM 36TH ST TO 44TH ST DIVISION AVE FROM 28TH ST TO 36TH ST

DIVISION AND 36TH SB STATION DOTTED RIGHT LANE PAVEMENT MARKING


EX 50’ ROW 100’ BEFORE INTERSECTION
EX 50’ ROW EX 66’ ROW

GODWIN HEIGHTS MULTIPLE


JIM WILLIAM’S LEATHER MULTIPLE BUSINESSES SIERRA’S GENERAL SUBWAY ROMA KFC
MC DONALD’S SCHOOLS BUSINESSES
RESTAURANT RIT MUSIC GODWIN HARDWARE
DIVISION AVE

MOTEL EXPRESS MERCHANDISE MULTIPLE PIZZA


BUSINESSES
SEE PREVIOUS SHEET

SEE NEXT SHEET

DIVISION AVE
EX ROW
EX 100’ ROW

EX 100’ ROW
245 250 255 260 265

WORKED ON BY: JSB


EX ROW

PROPOSED RESURFACING BY THE CITY OF WYOMING - 2012


OLYMPIC KING
PHO BO
GODWIN A DONG GODWIN HEIGHTS MARKET RIBS
UNLIMITED WEPMAN’S TIMMER’S
JONATHAN STEVEN’S AUTOMOTIVE BODY SHOP MARKET SCHOOLS
LAKE MICHIGAN WENDY’S MARKS PHOTO INDIA HOUSE AUTO REPAIR BROKERS SERVICE
BEDDING EMPORIUM
CREDIT UNION & VIDEO

36TH ST FROM DIVISION TO EASTERN


EX 20’ ROW

EX 66’ ROW EX 66’ ROW


EX 60’ ROW EX 60’ ROW

01/18/11
DIVISION AND 36TH NB STATION

DATE:
EX ROW VARIES

DOTTED RIGHT LANE PAVEMENT MARKING


100’ BEFORE INTERSECTION

TRW
DEDICATED BUS RAPID TRANSIT IN OUTSIDE LANES

CHECKED BY:
DURING MORNING AND AFTERNOON PEAK PERIODS

SECTION 19
T6N,R11W
CITY OF WYOMING

42679_DIVISION_24100.DGN
ABBIE ST HIMES ST
KEY MAP

WEXFORD ST

36TH ST CONSTRUCTION SHEET

200 600 1000 DIVISION AVE STA 241+00 TO STA 266+00

FILE NAME:
0 400 800 Surface Transportation
SHEET NO.
DATE CONT. SEC. JOB NO. DESIGN UNIT
Grand Rapids . Southfield .
200 SCALE R.O.W CONST.
Traverse City

01/18/11 9
FINAL R.O.W.

35TH ST 34TH ST 33RD ST AVONLEA ST 32ND ST ONEIDA ST AUTH DATE NO. REVISION

SECTION 13
T6N,R12W
CITY OF WYOMING

FAIR/POOR PAVEMENT CONDITION


DIVISION AVE FROM 28TH ST TO 36TH ST

PROPOSED RESURFACING BY THE CITY OF WYOMING - 2013


DIVISION AVE FROM 28TH ST TO 36TH ST

DATE: 01/18/11
DOTTED RIGHT LANE PAVEMENT MARKING
NEW PAVEMENT MARKINGS
100’ BEFORE INTERSECTION
BASED ON PROTOTYPICAL PLANS
EX 66’ ROW
EX 60’ ROW EX 66’ ROW
EX 66’ ROW

EX 66’ ROW

EX 60’ ROW

RICH GAS VALUE 1


KFC GT AUTOS ALL AMERICAN AUTO ADMIRAL GAS STATION FUNERAL HOME
STATION AUTO SALES
SEE PREVIOUS SHEET
DIVISION AVE

SEE NEXT SHEET

DIVISION AVE
EX ROW
EX 100’ ROW

EX 101’ ROW
270 275 280 285 290

WORKED ON BY: JSB


EX ROW

LEE AUTO SERVICE B QUICK


JD BYRIDER DOC’S AUTO CAR WASH CHAN’S
GAS STATION EXPORT CENTER THE LEATHER MERRA MOTORS PRINTING
WILLIAMS CARS KUNG FU
FACTORY
SCHOOL

EX 60’ ROW
EX 60’ ROW
EX 60’ ROW

EX 66’ ROW VARIES

01/18/11
EX 60’ ROW EX 66’ ROW

EX 60’ ROW DOTTED RIGHT LANE PAVEMENT MARKING


100’ BEFORE INTERSECTION

DATE:
DEDICATED BUS RAPID TRANSIT IN OUTSIDE LANES
DURING MORNING AND AFTERNOON PEAK PERIODS

TRW
CHECKED BY:
SECTION 18
T6N,R11W
CITY OF WYOMING

42679_DIVISION_26600.DGN
35TH ST FREEDOM ST 34TH ST
KEY MAP

LEMYRA ST

CLEMENTS ST FRONTENAC ST EXCHANGE ST 32ND ST CONSTRUCTION SHEET

200 600 1000 DIVISION AVE STA 266+00 TO STA 291+00

FILE NAME:
0 400 800 Surface Transportation
SHEET NO.
DATE CONT. SEC. JOB NO. DESIGN UNIT
Grand Rapids . Southfield .
200 SCALE R.O.W CONST.
Traverse City

01/18/11 10
FINAL R.O.W.
MANCHESTER ST BUCKINGHAM ST CELIA ST COLRAIN ST CANTERBURY ST HONEOYE ST 28TH ST
AUTH DATE NO. REVISION

SECTION 13
T6N,R12W
CITY OF WYOMING
SECTION 12
T6N,R12W
CITY OF WYOMING

FAIR/POOR PAVEMENT CONDITION VERY GOOD PAVEMENT CONDITION


DIVISION AVE FROM 28TH ST TO 36TH ST DIVISION AVE FROM BURTON ST TO 28TH ST

PROPOSED RESURFACING BY THE CITY OF WYOMING - 2013


DIVISION AVE FROM 28TH ST TO 36TH ST

EX ROW
VARIES

DATE: 01/18/11
NEW PAVEMENT MARKINGS
BASED ON PROTOTYPICAL PLANS

RAILROAD
DIVISION AND 28TH SB STATION
EX 66’ ROW EX 66’ ROW

EX 66’ ROW EX 66’ ROW EX 66’ ROW


EX 66’ ROW WALGREEN’S

DOTTED RIGHT LANE PAVEMENT MARKING


VALUE 1
IMPERIAL LEASING SCOTTY’S AUTO
COFFMAN GAS STATION 100’ BEFORE INTERSECTION
AUTO SALES YOUNG’S ARMY OPHOFF
AUTO GLASS AUTO FINANCE
NAVY SURPLUS MOTOR SALES
MULTIPLE BUSINESSES
SEE PREVIOUS SHEET
DIVISION AVE

DIVISION AVE
EX ROW

SEE NEXT SHEET


EX 101’ ROW

EX 100’ ROW

WORKED ON BY: JSB


295 300 305 CITY OF WYOMING 310 315
CITY OF GRAND RAPIDS

EX ROW

AL & BOB’S MULTIPLE BIG RAY’S BELTLINE BAR


SPORTS BUSINESSES QUICK LUBE RENT A CENTER LEE’S MARKET MULTIPLE BUSINESSES VILLA
PIZZA

EX 66’ ROW

01/18/11
EX 66’ ROW DIVISION AND 28TH NB STATION
EX 66’ ROW

RAPIDS
EX 120’
ROW

DATE:
CITY OF WYOMING
DOTTED RIGHT LANE PAVEMENT MARKING

CITY OF GRAND
100’ BEFORE INTERSECTION

DEDICATED RAPID TRANSIT BUS IN OUTSIDE LANES


DURING MORNING AND AFTERNOON PEAK PERIOD

SECTION 18 SECTION 18 SECTION 7

TRW
T6N,R11W T6N,R11W T6N,R11W
CITY OF WYOMING CITY OF GRAND RAPIDS CITY OF GRAND RAPIDS

CHECKED BY:
42679_DIVISION_29100.DGN
WESLEY ST CELIA ST
KEY MAP

COLRAIN ST HONEOYE ST RAILROAD 28TH ST CONSTRUCTION SHEET

200 600 1000 DIVISION AVE STA 291+00 TO STA 316+00

FILE NAME:
0 400 800 Surface Transportation
SHEET NO.
DATE CONT. SEC. JOB NO. DESIGN UNIT
Grand Rapids . Southfield .
200 SCALE R.O.W CONST.
Traverse City

01/18/11 11
FINAL R.O.W.
CLAIRE ST KEN-O-SHA DR PLASTER CREEK BLVD SOUTHVIEW ST BLACKBURN ST
AUTH DATE NO. REVISION

SECTION 12
T6N,R12W
CITY OF WYOMING

SECTION 12
T6N,R12W
CITY OF GRAND RAPIDS

VERY GOOD PAVEMENT CONDITION


DIVISION AVE FROM BURTON ST TO 28TH ST

EX 33’ ROW

DATE: 01/18/11
DIVISION AND SOUTHVIEW SB STATION

RAPIDS
EX ROW VAR
IES

CITY OF WYOMING
EX 40’ ROW

CITY OF GRAND
EX 50’ ROW
EX 50’ ROW EX 72’ ROW

HERREMA S DIVISION
ABC STORAGE
PLUMBING OUTLET PARAGON LOG CABIN
SEE PREVIOUS SHEET
DIVISION AVE

DIVISION AVE
MORALES MOTORS
BOWLING COCKTAIL LOUNGE

SEE NEXT SHEET


EX ROW
EX 100’ ROW

EX 66’ ROW

WORKED ON BY: JSB


320 CITY OF WYOMING 325 330 335 340
CITY OF GRAND RAPIDS

EX ROW "LITTLE PLAZA" S&H DRY


ROSEMARY RAINBOW MOTEL
QUICK PRINTING SUPERMARKET CLEANING
TOSCANO’S AUTO REPAIR
COMPANY USED CARS
SPORTS BAR

DIVISION AND SOUTHVIEW NB STATION


EX 48’ ROW
EX 66’ ROW

01/18/11
EX 66’ ROW EX 66’ ROW

EX 66’ ROW EX 66’ ROW

DATE:
DOTTED RIGHT LANE PAVEMENT MARKING
100’ BEFORE INTERSECTION

DEDICATED BUS RAPID TRANSIT IN OUTSIDE LANES


DURING MORNING AND AFTERNOON PEAK PERIOD

SECTION 7
T6N,R11W

TRW
CITY OF GRAND RAPIDS

CHECKED BY:
42679_DIVISION_31600.DGN
EOLA ST MEERSE ST ROSEMARY ST KEN-O-SHA DR

KEY MAP

ALGER ST

SOUTHVIEW ST CONSTRUCTION SHEET

200 600 1000 DIVISION AVE STA 316+00 TO STA 341+00

FILE NAME:
0 400 800 Surface Transportation
SHEET NO.
DATE CONT. SEC. JOB NO. DESIGN UNIT
Grand Rapids . Southfield .
200 SCALE R.O.W CONST.
Traverse City

01/18/11 12
FINAL R.O.W.
WITHEY ST BAYLIS ST BANNER CT SUTTON ST KIRTLAND ST ANDRE ST CUTLER ST AUTH DATE NO. REVISION

BURTON ST

SECTION 12
T6N,R12W
CITY OF GRAND RAPIDS

SECTION 1
T6N,R12W
CITY OF GRAND RAPIDS

VERY GOOD PAVEMENT CONDITION GOOD PAVEMENT CONDITION


DIVISION AVE FROM BURTON ST TO 28TH ST DIVISION AVE FROM HALL ST TO BURTON ST

DATE: 01/18/11
DOTTED RIGHT LANE PAVEMENT MARKING
100’ BEFORE INTERSECTION
NEW PAVEMENT MARKINGS
BASED ON PROTOTYPICAL PLANS

DIVISION AND BURTON SB STATION

EX 66’ ROW EX 66’ ROW


EX 66’ ROW EX 66’ ROW EX 40’ ROW
EX 40’ ROW
EX 60’ ROW EX 66’ ROW
EX 50’ ROW

MAGNUM DURANT

DIVISION AVE
TATOOING ELECTRONIC BURTON HEIGHTS
BETO’S CAT PIMENTEL JALISCO NEW LAGO’S MULTIPLE CUSTOM
SEE PREVIOUS SHEET

IRON EAGLE SOUND USED CARS RODRIGUEZ SUPERMARKET MONTEGO BAY MULTIPLE BUSINESSES
DIVISION AVE

AUDIO & MULTIPLE SERVICES LAUNDROMAT MOON STORE BUSINESSES UPHOLSTERY AMY’S MULTIPLE
MOTORCYCLES

SEE NEXT SHEET


ACCESSORIES FASHION BUSINESSES

EX ROW

WORKED ON BY: JSB


EX 66’ ROW

EX 66’ ROW
345 350 355 360 365

EX ROW

TIRE GRAND VALLEY


DISCOUNT MULTIPLE BOTTLE POPEYE’S
MORNING MI TIERRA SHOP GR FAMILY SUPERMERCADO HEALTH INTERVENTION MULTIPLE BUSINESSES DENTAL CARE
RESTAURANT BUSINESSES HOUSE TAQUERIA SIERRA
GLORY RESTAURANT SERVICES DOLLAR GUADALAJARA SERVICES
SUPPLY

LOCK SHOP DIVISION AND BURTON NB STATION

01/18/11
EX 66’ ROW EX 66’ ROW EX 66’ ROW

EX 66’ ROW

DATE:
DOTTED RIGHT LANE PAVEMENT MARKING
100’ BEFORE INTERSECTION

DEDICATED BUS RAPID TRANSIT IN OUTSIDE LANES


DURING MORNING AND AFTERNOON PEAK PERIOD

SECTION 7 SECTION 6

TRW
T6N,R11W T6N,R11W
CITY OF GRAND RAPIDS CITY OF GRAND RAPIDS

CHECKED BY:
42679_DIVISION_34100.DGN
WITHEY ST MELVILLE ST

KEY MAP

BURTON ST

CONSTRUCTION SHEET
ANDRE ST

200 600 1000 DIVISION AVE STA 341+00 TO STA 367+00

FILE NAME:
0 400 800 Surface Transportation
SHEET NO.
DATE CONT. SEC. JOB NO. DESIGN UNIT
Grand Rapids . Southfield .
200 SCALE R.O.W CONST.
Traverse City

01/18/11 13
FINAL R.O.W.
QUIGLEY BLVD STEWART ST ROSE ST ELM ST GRIGGS ST BROWN ST DICKINSON ST CORINNE ST FOX ST AUTH DATE NO. REVISION

SECTION 1
T6N,R12W
CITY OF GRAND RAPIDS

GOOD PAVEMENT CONDITION


DIVISION AVE FROM HALL ST TO BURTON ST

DATE: 01/18/11
DOTTED RIGHT LANE PAVEMENT MARKING
NEW PAVEMENT MARKINGS
100’ BEFORE INTERSECTION
BASED ON PROTOTYPICAL PLANS
EX 66’ ROW EX 50’ ROW EX 50’ ROW
EX 40’ ROW EX 50’ ROW EX 50’ ROW
EX 66’ ROW
EX 66’ ROW

GARIBALDI’S

DIVISION AVE
TRAVEL BURTON HEIGHTS YESTER YEAR’S IN THE IMAGE AUTO
FAMILY OUTREACH SHORT STOP RESTAURANT
SEE PREVIOUS SHEET
DIVISION AVE

BODY SHOP LOUNGE REPAIR

SEE NEXT SHEET


AGENCY CENTER FOODS

EX ROW

EX 66’ ROW
EX 66’ ROW

380 385 390


370 375

WORKED ON BY: JSB


EX ROW

YOUTH TIENDA LA LA MEXICANA


QUISQUAYA PEST CONTROL
FAMILY MILLENIUM BAKERY & GROCERY
CENTER CONFIANZA GARAGE
TALK AUTO DETAIL FIRE DEPT

EX 66’ ROW
EX 50’ ROW
EX 50’ ROW EX 66’ ROW
DOTTED RIGHT LANE PAVEMENT MARKING

01/18/11
100’ BEFORE INTERSECTION

DATE:
DEDICATED BUS RAPID TRANSIT IN OUTSIDE LANES
DURING MORNING AND AFTERNOON PEAK PERIOD

SECTION 6
T6N,R11W

TRW
CITY OF GRAND RAPIDS

CHECKED BY:
42679_DIVISION_36700.DGN
KEY MAP

CONSTRUCTION SHEET
GRIGGS ST BROWN ST DICKINSON ST

200 600 1000 DIVISION AVE STA 367+00 TO STA 391+00

FILE NAME:
0 400 800 Surface Transportation
SHEET NO.
DATE CONT. SEC. JOB NO. DESIGN UNIT
Grand Rapids . Southfield .
200 SCALE R.O.W CONST.
Traverse City

01/18/11 14
FINAL R.O.W.

COTTAGE GROVE ST RAILROAD STEVENS ST LA BELLE ST HOME ST RENA ST ZENO ST AUTH DATE NO. REVISION

HALL ST

SECTION 1
T6N,R12W
CITY OF GRAND RAPIDS

GOOD PAVEMENT CONDITION


DIVISION AVE FROM HALL ST TO BURTON ST

DATE: 01/18/11
DIVISION AND COTTAGE GROVE SB STATION

EX 60’ ROW
EX 68’ ROW

EX 50’ ROW EX 50’ ROW EX 50’ ROW


EX 66’ ROW EX 66’ ROW

CONSTRUCTIVE
NEMIC INUDSTRIAL
SHEET METAL

DIVISION AVE
SUPPLY SALVATION ARMY SERENITY
SALON

SEE NEXT SHEET


PRIDGEON BUILDING
AND CLAY
SEE PREVIOUS SHEET

FOR SALE

EX 83’ ROW
EX ROW
DIVISION AVE

415
410
EX 66’ ROW

405
400
395

WORKED ON BY: JSB


EX ROW

EX 80’ ROW

EX 76’ ROW
EX 76’ ROW
EX 70’ ROW
ST VINCENT MULTIPLE
BOY’S MY PLACE CHURCH USED CARS MC DONALD’S AUTO ZONE
DETENTION BASIN DE PAUL BUSINESSES
AUTO REPAIR BAR
PARKING LOT

EX 66’ ROW EX 66’ ROW


EX 66’ ROW EX 78’ ROW
EX 66’ ROW
EX 66’ ROW
EX 66’ ROW

DIVISION AND COTTAGE GROVE NB STATION

01/18/11
DOTTED RIGHT LANE PAVEMENT MARKING
100’ BEFORE INTERSECTION

DATE:
DEDICATED BUS RAPID TRANSIT IN OUTSIDE LANES
DURING MORNING AND AFTERNOON PEAK PERIOD

SECTION 6
T6N,R11W
CITY OF GRAND RAPIDS

TRW
CHECKED BY:
42679_DIVISION_39100.DGN
CROFTON ST COTTAGE GROVE ST RAILROAD GARDEN ST

KEY MAP

HALL ST

FAIR ST LA BELLE ST HOME ST CONSTRUCTION SHEET

200 600 1000 DIVISION AVE STA 391+00 TO STA 416+00

FILE NAME:
0 400 800 Surface Transportation
SHEET NO.
DATE CONT. SEC. JOB NO. DESIGN UNIT
Grand Rapids . Southfield .
200 SCALE R.O.W CONST.
Traverse City

01/18/11 15
FINAL R.O.W.
HALL ST CANTON ST PUTNAM ST SHELBY ST ALBANY ST DELAWARE ST ANTOINE ST DATE NO.
AUTH REVISION

SECTION 36
T7N,R12W
CITY OF GRAND RAPIDS

VERY GOOD PAVEMENT CONDITION

DATE: 01/18/11
DIVISION AVE FRANKLIN ST TO HALL ST

DOTTED RIGHT LANE PAVEMENT MARKING


DOTTED RIGHT LANE PAVEMENT MARKING 100’ BEFORE INTERSECTION
100’ BEFORE INTERSECTION
NEW PAVEMENT MARKINGS
BASED ON PROTOTYPICAL PLANS
EX 68’ ROW
DIVISION AND GREEN SB STATION
EX 68’ ROW
EX 66’ ROW
EX 66’ ROW
EX 66’ ROW
EX 66’ ROW
EX 66’ ROW
DIVISION AVE

J-N-J
SEE PREVIOUS SHEET

BP GAS TIRE SHOP NORTHWESTERN M&N T&W


KFC FISH & CHICKEN

DIVISION AVE
AUTO SUPPLY MOTORS ELECTRONICS

SEE NEXT SHEET


EX ROW
EX 83’ ROW

EX 83’ ROW

WORKED ON BY: JSB


420 425 430 435 440

EX ROW

CHICKEN COOP HOME REPAIR


BIG BABIES GLT SERVICES AUTO REPAIR
BBQ

DOTTED RIGHT LANE PAVEMENT MARKING


100’ BEFORE INTERSECTION
EX 66’ ROW EX 43’ ROW
EX 55’ ROW

01/18/11
DIVISION AND GREEN NB STATION

DATE:
DEDICATED BUS RAPID TRANSIT IN OUTSIDE LANES
DURING MORNING AND AFTERNOON PEAK PERIOD

TRW
SECTION 31

CHECKED BY:
T7N,R11W
CITY OF GRAND RAPIDS

42679_DIVISION_41600.DGN
HALL ST GREEN ST HIGHLAND ST

KEY MAP

DELAWARE ST CONSTRUCTION SHEET

200 600 1000 DIVISION AVE STA 416+00 TO STA 440+00

FILE NAME:
0 400 800 Surface Transportation
SHEET NO.
DATE CONT. SEC. JOB NO. DESIGN UNIT
Grand Rapids . Southfield .
200 SCALE R.O.W CONST.
Traverse City

01/18/11 16
FINAL R.O.W.
FRANKLIN ST BUCKLEY ST AUTH DATE NO. REVISION

SECTION 36
T7N,R12W
CITY OF GRAND RAPIDS

VERY GOOD
PAVEMENT CONDITION FAIR PAVEMENT CONDITION

DIVISION AVE FROM DIVISION AVE FROM WEALTHY ST TO FRANKLIN ST


FRANKLIN ST TO HALL ST

DOTTED RIGHT LANE PAVEMENT MARKING


100’ BEFORE INTERSECTION

DATE: 01/18/11
DIVISION AND FRANKLIN SB STATION

73.04’ EX 66’ ROW


EX 66’ ROW
EX 66’ ROW

AMERICAN
MEDICAL RESPONSE
AMIGOS A TO Z MULTIPLE BUSINESSES
SEE PREVIOUS SHEET

AZUCAR
AUTO SALES NIGHT CLUB RADIATOR SHOP

SEE NEXT SHEET


LIQUOR STORE
DIVISION AVE

DIVISION AVE
EX ROW

EX 83’ ROW
EX 83’ ROW

440 445 450 455 460

WORKED ON BY: JSB


EX ROW

TEQUILA
NIGHT CLUB PERFIT CORPORATION
AUTO REPAIR BURGER
MEDBIO MULTIPLE FAMILY DOLLAR
KING
DOTTED RIGHT LANE QMED BUSINESSES

PAVEMENT MARKING
100’ BEFORE INTERSECTION DIVISION AND FRANKLIN NB STATION

01/18/11
EX 66’ ROW

EX 57’ ROW
NEW PAVEMENT MARKINGS EX 66’ ROW
BASED ON PROTOTYPICAL PLANS

DATE:
EX ROW VARIES

DEDICATED BUS RAPID TRANSIT IN OUTSIDE LANES


DURING MORNING AND AFTERNOON PEAK PERIOD

TRW
SECTION 31

CHECKED BY:
T7N,R11W
CITY OF GRAND RAPIDS

42679_DIVISION_44000.DGN
FRANKLIN ST HAIFLEY ST

KEY MAP

CONSTRUCTION SHEET
PLEASANT ST BUCKLEY ST

200 600 1000 DIVISION AVE STA 440+00 TO STA 460+00

FILE NAME:
0 400 800 Surface Transportation
SHEET NO.
DATE CONT. SEC. JOB NO. DESIGN UNIT
Grand Rapids . Southfield .
200 SCALE R.O.W CONST.
Traverse City

01/18/11 17
FINAL R.O.W.
LOGAN ST MC CONNELL ST WEALTHY ST
AUTH DATE NO. REVISION

FAIR PAVEMENT CONDITION

DIVISION AVE FROM WEALTHY ST TO FRANKLIN ST

DEDICATED BUS RAPID TRANSIT IN OUTSIDE LANES DEDICATED BUS RAPID TRANSIT IN SOUTHBOUND OUTSIDE LANE

DURING MORNING AND AFTERNOON PEAK PERIOD DURING MORNING AND AFTERNOON PEAK PERIOD

DIVISION AND LOGAN SB STATION

EX 72’ ROW
EX 50’ ROW

DIVISION AND LOGAN EB STATION EX 66’ ROW


DIVISION AVE

DIVISION AVE
MULTIPLE BUSINESSES MULTIPLE BUSINESSES SHELL GAS MULTIPLE BUSINESSES

SEE PREVIOUS SHEET


SECTION 31
T7N,R11W
CITY OF GRAND RAPIDS

460 465 470

620
600
AUTO PARTS EMPTY LOT EMPTY LOT

DIOCESE OF GRAND RAPIDS

645
645
.33
.73

645 645
.80 .60
SHELDON AVE

DATE: 01/18/11
SHARED BUS RAPID TRANSIT/VEHICULAR WESTBOUND LANE

WEALTHY ST FROM JEFFERSON AVE TO DIVISION AVE


SHARED BUS RAPID TRANSIT/VEHICULAR EASTBOUND LANE

EX 66’ ROW

EX 66’ ROW

DURING MORING AND AFTERNOON PEAK PERIOD


LOGAN ST FROM JEFFERSON AVE TO DIVISION AVE

DURING MORING AND AFTERNOON PEAK PERIOD

FAIR PAVEMENT CONDITION


EX 16’ ROW
EX 16’ ROW
FAIR PAVEMENT CONDITION

625
605
LAGRAVE AVE

WORKED ON BY: JSB


EX 66’ ROW

EX 66’ ROW

LAGRAVE AVE
EX 16’ ROW

EX 16’ ROW

01/18/11
DATE:
SEE JEFFERSON SHEET
PARKING LOT
JEFFERSON AVE

JEFFERSON AVE
EX ROW
EX 66’ ROW

EX 66’ ROW
545 550

630
610

EX ROW

PARKING LOT

TRW
CHECKED BY:
EX 50’ ROW

SHARED BUS RAPID TRANSIT/VEHICULAR NORTHBOUND LANE SHARED BUS RAPID TRANSIT/VEHICULAR LANES
DURING MORNING AND AFTERNOON PEAK PERIOD DURING MORNING AND AFTERNOON PEAK PERIOD

42679_JEFFERSON_LOGAN.DGN
FAIR PAVEMENT CONDITION VERY GOOD PAVEMENT CONDITION
JEFFERSON AVE FROM WEALTHY ST TO LOGAN ST JEFFERSON AVE FROM CHERRY ST TO WEALTHY ST

KEY MAP

CONSTRUCTION SHEET
LOGAN ST WEALTHY ST

200 600 1000 DIVISION, LOGAN, WEALTHY, AND JEFFERSON

FILE NAME:
0 400 800 Surface Transportation
SHEET NO.
DATE CONT. SEC. JOB NO. DESIGN UNIT
Grand Rapids . Southfield .
200 SCALE R.O.W CONST.
Traverse City

01/18/11 18
FINAL R.O.W.
GOODRICH ST CHERRY ST
AUTH DATE NO. REVISION

SECTION 31
T7N,R11W
CITY OF GRAND RAPIDS

VERY GOOD PAVEMENT CONDITION GOOD PAVEMENT CONDITION


JEFFERSON AVE FROM CHERRY ST TO WEALTHY ST JEFFERSON AVE FROM FULTON ST TO CHERRY ST

DATE: 01/18/11
EX 66’ ROW

WEALTHY SB STATION

SEE FULTON AND RANSOM SHEET


RIVER AMERICAN
SEE PREVIOUS SHEET
JEFFERSON AVE

JEFFERSON AVE
CITY PARKING LOT CANCER
STUDIOS SOCIETY

BUILDING
EX ROW
EX 66’ ROW

EX 66’ ROW
555 560 565

WORKED ON BY: JSB


EX ROW

ST. MARY’S DOCTORS OFFICE

HOSPITAL

WEALTHY NB STATION

EX 66’ ROW

01/18/11
SHARED BUS RAPID TRANSIT/VEHICULAR LANES

DATE:
DURING MORNING AND AFTERNOON PEAK PERIOD

TRW
42679_WEALTHY_JEFFERSON.DGN CHECKED BY:
KEY MAP

CONSTRUCTION SHEET
CHERRY ST

200 600 1000 JEFFERSON

FILE NAME:
0 400 800 Surface Transportation
SHEET NO.
DATE CONT. SEC. JOB NO. DESIGN UNIT
Grand Rapids . Southfield .
200 SCALE R.O.W CONST.
Traverse City

01/18/11 19
FINAL R.O.W.
WESTON ST FULTON ST LIBRARY ST FOUNTAIN ST
AUTH DATE NO. REVISION

SECTION 30
T7N,R11W
CITY OF GRAND RAPIDS

GOOD PAVEMENT CONDITION GOOD PAVEMENT CONDITION


JEFFERSON AVE FROM FULTON ST TO CHERRY ST RANSOM AVE FROM FULTON ST TO LYON ST

SHARED BUS RAPID TRANSIT/VEHICULAR LANES

DEDICATED BUS RAPID TRANSIT IN OUTSIDE LANES


DURING MORNING AND AFTERNOON PEAK PERIOD

DURING MORNING AND AFTERNOON PEAK PERIOD

DATE: 01/18/11
FULTON ST FROM JEFFERSON AVE TO RANSOM AVE
VERY GOOD PAVEMENT CONDITION

DOTTED RIGHT LANE PAVEMENT MARKING


100’ BEFORE INTERSECTION

635
EX 82’ ROW EX ROW VARIES
FULTON AND RANSOM SB STATION
LA GRAVE AVE

EX 66’ ROW

EX 66’ ROW
GR PUBLIC

SEE GRCC-RANSOM SHEET


GR PUBLIC
LIBRARY

RANSOM AVE
LIBRARY

WORKED ON BY: JSB


EX ROW

EX 66’ ROW
60 65

EX 63’ ROW EX ROW


FOUNTAIN
PARK ST ST
FOUNTAIN
ST CECELIA PARK
PLACE CHURCH
CHURCH
MUSIC SOCIETY PLACE
SEE WEALTHY AND JEFFERSON SHEET

FULTON AND RANSOM NB STATION

DOTTED RIGHT LANE PAVEMENT MARKING

01/18/11
MULTIPLE BUSINESSES
JEFFERSON AVE

100’ BEFORE INTERSECTION


APARTMENT BUILDING

EX 66’ ROW
575
EX 66’ ROW

DATE:
NEW PAVEMENT MARKINGS
EX 66’ ROW

570

640
BASED ON PROTOTYPICAL PLANS
565

EX 78’ ROW

TRW
CHECKED BY:
42679_FULTON_RANSOM.DGN
STATE ST FULTON ST

KEY MAP

FOUNTAIN ST

CONSTRUCTION SHEET

200 600 1000 FULTON AND RANSOM

FILE NAME:
0 400 800 Surface Transportation
SHEET NO.
DATE CONT. SEC. JOB NO. DESIGN UNIT
Grand Rapids . Southfield .
200 SCALE R.O.W CONST.
Traverse City

01/18/11 20
FINAL R.O.W.

FOUNTAIN ST LYON ST CRESCENT ST AUTH DATE NO. REVISION

SECTION 29
T7N,R11W
CITY OF GRAND RAPIDS

GOOD PAVEMENT CONDITION POOR PAVEMENT CONDITION


RANSOM AVE FROM FULTON ST TO LYON ST RANSOM AVE FROM CRESCENT ST TO LYON ST

SEE MICHIGAN AND BOSTWICK SHEET


EX 66’ ROW

BOSTWICK AVE
BOSTWICK AVE

EX 66’ ROW
EX 66’ ROW
EX ROW VARIES 40 45

640

DATE: 01/18/11
RANSOM AVE TO BOSTWICK AVE
EX 66’ ROW

FAIR PAVEMENT CONDITION


CRESCENT ST FROM
GRAND RAPIDS GRAND RAPIDS
COMMUNITY COLLEGE COMMUNITY COLLEGE

SEE FULTON AND RANSOM SHEET


GR PUBLIC
LIBRARY GRAND RAPIDS GRAND RAPIDS GRCC SB STATION
SPECTRUM
COMMUNITY COLLEGE COMMUNITY COLLEGE
HEALTH
RANSOM AVE

PARKING RAMP

EX 55’ ROW
EX 66’ ROW

EX ROW

70 75 80

WORKED ON BY: JSB


DURING MORNING AND AFTERNOON PEAK PERIOD
SHARED BUS RAPID TRANSIT/VEHICULAR LANES
EX 66’ ROW
PARK FOUNTAIN ST EX ROW

PLACE CHURCH

GRAND RAPIDS
PARKING RAMP PARKING RAMP SPECTRUM HEALTH
COMMUNITY COLLEGE

GRCC NB STATION

EX 66’ ROW

01/18/11
EX 66’ ROW

DATE:
SHARED BUS RAPID TRANSIT/VEHICULAR LANES
DURING MORNING AND AFTERNOON PEAK PERIOD

TRW
CHECKED BY:
FOUNTAIN ST

42679_GRCC_RANSOM.DGN
KEY MAP

CONSTRUCTION SHEET
CRESCENT ST

200 600 1000 GRCC - RANSOM

FILE NAME:
0 400 800 Surface Transportation
SHEET NO.
DATE CONT. SEC. JOB NO. DESIGN UNIT
Grand Rapids . Southfield .
200 SCALE R.O.W CONST.
Traverse City

01/18/11 21
FINAL R.O.W.

AUTH DATE NO. REVISION

SECTION 30
T7N,R11W
CITY OF GRAND RAPIDS

FAIR PAVEMENT CONDITION


MICHIGAN ST FROM MONROE AVE TO BOSTWICK AVE

DATE: 01/18/11
GRAND RAPIDS PRESS

MICHIGAN AND BOSTWICK WB STATION NEW PAVEMENT MARKINGS


BASED ON PROTOTYPICAL PLANS
OLDS MANOR

EX 100’ ROW
EX 100’ ROW
OLDS MANOR GRAND RAPIDS PRESS

SPECTRUM HEALTH
MICHIGAN ST

MICHIGAN ST
EX ROW
EX 106’ ROW

EX ROW VARIES
665 670

WORKED ON BY: JSB


655 660

EX ROW

DURING MORNING AND AFTERNOON PEAK PERIODS


SHARED BUS RAPID TRANSIT/VEHICULAR LANES
520
VAN ANDEL
SPECTRUM HEALTH

50
INSTITUTE

EXCELLENT PAVEMENT CONDITION


IMMANUEL CHURCH

CRESCENT ST TO MICHIGAN ST
DEVOS PLACE
MICHIGAN AND BOSTWICK EB STATION
100’ BEFORE INTERSECTION
LANE PAVEMENT MARKING

BOSTWICK AVE FROM

01/18/11
CITY-COUNTY COMPLEX &
PARKING STRUCTURE
DOTTED RIGHT
DEVOS PLACE

CITY-COUNTY COMPLEX & PARKING STRUCTURE


25

DATE:
SEE DEVOS PLACE SHEET SEE GRCC-RANSOM SHEET

EX 66’ ROW
DOTTED RIGHT LANE PAVEMENT MARKING
100’ BEFORE INTERSECTION

DEDICATED BUS RAPID TRANSIT IN OUTSIDE LANES


DURING MORNING AND AFTERNOON PEAK PERIOD

TRW
42679_MICHIGAN_BOSTWICK.DGN CHECKED BY:
DIVISION AVE BOSTWICK AVE

KEY MAP

CONSTRUCTION SHEET

200 600 1000 MICHIGAN AND BOSTWICK

FILE NAME:
0 400 800 Surface Transportation
SHEET NO.
DATE CONT. SEC. JOB NO. DESIGN UNIT
Grand Rapids . Southfield .
200 SCALE R.O.W CONST.
Traverse City

01/18/11 22
FINAL R.O.W.

LYON ST BRIDGE ST AUTH DATE NO. REVISION

SECTION 25
T7N,R12W
CITY OF GRAND RAPIDS

FAIR PAVEMENT CONDITION GOOD/FAIR PAVEMENT CONDITION


MONROE AVE FROM LYON ST TO MARKET ST MONROE AVE FROM MICHIGAN ST TO LYON ST

DATE: 01/18/11
EX 102’ ROW

EX 66’ ROW

EX 142’ ROW
DOTTED RIGHT LANE PAVEMENT MARKING
DEVOS PLACE SB STATION
100’ BEFORE INTERSECTION
SEE LOUIS AND MONROE SHEET

AMWAY GRAND
DEVOS PLACE DEVOS PLACE DEVOS PLACE OLDS MANOR
PLAZA HOTEL

MONROE AVE
MONROE AVE

EX ROW

EX 92’ ROW

WORKED ON BY: JSB


EX 100’ ROW

25 30
20
15

655
EX ROW

MULTIPLE
FIFTH THIRD
BUSINESSES MILLER & JOHNSON
BUILDING
CITY-COUNTY COMPLEX & PARKING STRUCTURE

DOTTED RIGHT LANE PAVEMENT MARKING GRAND RAPIDS PRESS

01/18/11
DOTTED RIGHT LANE PAVEMENT MARKING 100’ BEFORE INTERSECTION
DEVOS PLACE NB STATION
100’ BEFORE INTERSECTION SEE MICHIGAN AND BOSTWICK SHEET
EX 66’ ROW

EX 102’ ROW

DATE:
DEDICATED BUS RAPID TRANSIT IN OUTSIDE LANES
DURING MORNING AND AFTERNOON PEAK PERIODS

TRW
42679_DEVOSPLACE_MONROE.DGN CHECKED BY:
LYON ST
KEY MAP

MICHIGAN ST CONSTRUCTION SHEET

200 600 1000 DEVOS PLACE

FILE NAME:
0 400 800 Surface Transportation
SHEET NO.
DATE CONT. SEC. JOB NO. DESIGN UNIT
Grand Rapids . Southfield .
200 SCALE R.O.W CONST.
Traverse City

01/18/11 23
FINAL R.O.W.

CAMPAU AVE PEARL ST LYON ST AUTH DATE NO. REVISION

SECTION 25
T7N,R12W
CITY OF GRAND RAPIDS

FAIR PAVEMENT CONDITION


MONROE AVE FROM LYON ST TO MARKET ST

DEDICATED BUS RAPID TRANSIT IN OUTSIDE LANES


DURING MORNING AND AFTERNOON PEAK PERIOD

DOTTED RIGHT LANE PAVEMENT MARKING

DATE: 01/18/11
MONROE AVE

100’ BEFORE INTERSECTION

W
EX

O
RO

’R
W
V
A

90
RI
ES

EX
COURTYARD
BY MARRIOT

EX 66’ ROW
THE BOB PARKING RAMP
LOUIS AND MONROE SB STATION
DOTTED RIGHT LANE PAVEMENT MARKING
5
100’ BEFORE INTERSECTION

COMERICA BUILDING AMWAY GRAND


NATIONAL CITY PLAZA HOTEL
AMWAY GRAND AMWAY GRAND
BUILDING
PLAZA HOTEL PLAZA HOTEL

SEE DEVOS PLACE SHEET

WORKED ON BY: JSB


HUNTINGTON
EX ROW
BUILDING

MONROE AVE
EX 100’ ROW
E
X
66

R 10 15
O
W

PARKING LOT

EX ROW

MULTIPLE MULTIPLE
BUSINESSES BUSINESSES
LOUIS AND MONROE NB STATION ROSA PARKS CIRCLE

01/18/11
GRAND RAPIDS
E ART MUSEUM
X
66

R

DATE:
O
W
DOTTED RIGHT LANE PAVEMENT MARKING
100’ BEFORE INTERSECTION

DOTTED RIGHT LANE PAVEMENT MARKING


EX 66’ ROW
100’ BEFORE INTERSECTION

TRW
CHECKED BY:
LOUIS ST

42679_LOUIS_MONROE.DGN
KEY MAP

MONROE CENTER PEARL ST LYON ST CONSTRUCTION SHEET

200 600 1000 LOUIS AND MONROE

FILE NAME:
0 400 800 Surface Transportation
SHEET NO.
DATE CONT. SEC. JOB NO. DESIGN UNIT
Grand Rapids . Southfield .
200 SCALE R.O.W CONST.
Traverse City

01/18/11 24
FINAL R.O.W.
NOTE: 1) THIS PROTOTYPICAL PAVEMENT MARKING PLAN SHOWING DEDICATED
BUS RAPID TRANSIT LANES DURING PEAK TRAFFIC PERIODS IS AUTH DATE NO. REVISION
OVLY COLD PLASTIC
CONSISTENT WITH THE FINDINGS OF THE ENVIRONMENTAL ASSESSMENT.
24" STOP BAR THERMOPLASTIC, 6 INCH
2) DEDICATED BUS RAPID TRANSIT LANES WILL BE MARKED WITH 6" WIDE
BROKEN WHITE LANE LINE
BROKEN LANE LINES AND DEDICATED LANE SYMBOLS. THERMOPLASTIC, 4 INCH
12’-6" MARK, 37’-6" GAP
DOUBLE SOLID YELLOW LANE LINE

OVLY COLD PLASTIC OVLY COLD PLASTIC


DEDICATED LANE SYM 12 INCH CROSSWALK
MONROE AVE

200’ SPACING 8’ LONG, 2’ GAP


EX
RO
W

S
IE
R
A
V
W
O
R
X
E
EX RO
W

DATE: 01/18/11
E
IN
H

L
C
E

EX
N

N
IT 6 I
A

R
O
L

W
W HT

E
IN 60
IG

H
6+

R
D
A

E
ST

G
T
E
T
B
O

MONROE AVE
D

OVLY COLD PLASTIC

EX 100’ ROW
24" STOP BAR

WORKED ON BY: AVP


8

TS THERMOPLASTIC, 4 INCH
SOLID WHITE LANE LINE

THERMOPLASTIC, 4 INCH
DOUBLE SOLID YELLOW LANE LINE

01/18/11
NE
LI
NE
CH
THERMOPLASTIC, 6 INCH

LA
IN
DOTTED WHITE LANE LINE OVLY COLD PLASTIC

DATE:
TE
T6

2’ MARK, 4’ GAP 12 INCH CROSSWALK


HI

8’ LONG, 2’ GAP
60
GH
W
7+

ED
RI
A
D
TT
ST
EN
DO

PROPOSED LOUIS AND MONROE NB


RAPID TRANSIT STATION
EX
R
O
W

OVLY COLD PLASTIC

TRW
12 INCH CROSSWALK
8’ LONG, 2’ GAP

CHECKED BY:
42679_01_LOUIS_NB_PVTMRKG.DGN
E
X
66

R
O
W
PROTOTYPICAL
PERMANENT PAVEMENT MARKINGS
LOUIS ST

0 3 5 10 3-LEG INTERSECTION APPROACH (MONROE/LOUIS)

FILE NAME:
= BRT FLOW PATH
Surface Transportation
DATE CONT. SEC. JOB NO. DESIGN UNIT SHEET NO.
Grand Rapids . Southfield .
10 SCALE R.O.W CONST.
TS = TRAFFIC SIGNAL Traverse City

01/18/11 44
FINAL R.O.W.
NOTE: 1) THIS PROTOTYPICAL PAVEMENT MARKING PLAN SHOWING DEDICATED
BUS RAPID TRANSIT LANES DURING PEAK TRAFFIC PERIODS IS
MICHIGAN ST AUTH DATE NO. REVISION
CONSISTENT WITH THE FINDINGS OF THE ENVIRONMENTAL ASSESSMENT. THERMOPLASTIC, 4 INCH

2) DEDICATED BUS RAPID TRANSIT LANES WILL BE MARKED WITH 6" WIDE SOLID WHITE LANE LINE

BROKEN LANE LINES AND DEDICATED LANE SYMBOLS. EX 100’ ROW

THERMOPLASTIC, 4 INCH
THERMOPLASTIC, 6 INCH DOUBLE SOLID YELLOW LANE LINE
DOTTED WHITE LANE LINE
2’ MARK, 4’ GAP

OVLY COLD PLASTIC,

669
ONLY

EX ROW
PROPOSED MICHIGAN AND BOSTWICK WB
PROPOSED MICHIGAN AND BOSTWICK EB
RAPID TRANSIT STATION
RAPID TRANSIT STATION ONLY
THERMOPLASTIC, 6 INCH

EX ROW
BROKEN WHITE LANE LINE
12’-6" MARK, 37’-6" GAP

OVLY COLD PLASTIC


LEFT TURN ARROW SYMBOL

OVLY COLD PLASTIC


OVLY COLD PLASTIC RIGHT TURN ARROW SYMBOL

DATE: 01/18/11
24" STOP BAR

THERMOPLASTIC, 4 INCH
SOLID WHITE LANE LINE

STA 669+75 STA 669+75

WORKED ON BY: AVP


END 6 INCH DOTTED WHITE LANE LINE BEGIN 4 INCH
END 4 INCH SOLID WHITE LANE LINE SOLID WHITE LANE LINE
EX ROW

THERMOPLASTIC, 4 INCH OVLY COLD PLASTIC


DOUBLE SOLID YELLOW LANE LINE 12 INCH CROSSWALK
8’ LONG, 2’ GAP

OVLY COLD PLASTIC


12 INCH CROSSWALK

01/18/11
8’ LONG, 2’ GAP

670
BOSTWICK AVE

DATE:
ONLY
EX 66’ ROW

50 51

TS

TRW CHECKED BY:


42679_05_MICHIGAN_EB_PVTMRKG.DGN
SOLID WHITE LANE LINE

EX ROW
EX ROW
SOLID WHITE LANE LINE

END 4 INCH

OVLY COLD PLASTIC


STA 50+69

LEFT TURN ARROW SYMBOL


BEGIN 4 INCH
STA 50+04

EX 100’ ROW PROTOTYPICAL


OVLY COLD PLASTIC
24" STOP BAR MICHIGAN ST PERMANENT PAVEMENT MARKINGS

THERMOPLASTIC, 4 INCH
= BRT FLOW PATH 0 3 5 10 3-LEG INTERSECTION APPROACH (MICH./BOSTWICK)

FILE NAME:
SOLID WHITE LANE LINE

Surface Transportation
DATE CONT. SEC. JOB NO. DESIGN UNIT SHEET NO.
OVLY COLD PLASTIC, 10 SCALE Grand Rapids . Southfield .
TS = TRAFFIC SIGNAL ONLY Traverse City
R.O.W CONST.

01/18/11 45
FINAL R.O.W.
NOTE: 1) THIS PROTOTYPICAL PAVEMENT MARKING PLAN SHOWING DEDICATED
BUS RAPID TRANSIT LANES DURING PEAK TRAFFIC PERIODS IS
FULTON ST AUTH DATE NO. REVISION
CONSISTENT WITH THE FINDINGS OF THE ENVIRONMENTAL ASSESSMENT.
2) DEDICATED BUS RAPID TRANSIT LANES WILL BE MARKED WITH 6" WIDE
BROKEN LANE LINES AND DEDICATED LANE SYMBOLS.

EX 82’ ROW

EX ROW

637
OVLY COLD PLASTIC,
ONLY

STA 60+52
END 4 INCH
SOLID WHITE LANE LINE

STA 61+27
BEGIN 4 INCH
SOLID WHITE LANE LINE
THERMOPLASTIC, 4 INCH

DATE: 01/18/11
SOLID WHITE LANE LINE

PROPOSED FULTON AND RANSOM SB


RAPID TRANSIT STATION

EX ROW
EX ROW

OVLY COLD PLASTIC


12 INCH CROSSWALK
8’ LONG, 2’ GAP

ONLY

RANSOM AVE

WORKED ON BY: AVP


OVLY COLD PLATSIC
12 INCH CROSSWALK
TS

EX 66’ ROW
8’ LONG, 2’ GAP

60 61 62

01/18/11
DATE:
638

THERMOPLASTIC, 4 INCH
BROKEN YELLOW LANE LINE
12’-6" MARK, 37’-6" GAP

STA 638+10 OVLY COLD PLASTIC,


END 4 INCH LEFT TURN ARROW SYMBOL
DOTTED WHITE LANE LINE EX ROW
EX ROW

OVLY COLD PLASTIC, THERMOPLASTIC, 4 INCH


24" STOP BAR DOUBLE SOLID YELLOW LANE LINE PROPOSED FULTON AND RANSOM NB

TRW
RAPID TRANSIT STATION
EX ROW

CHECKED BY:
OVLY COLD PLASTIC
12 INCH CROSSWALK
8’ LONG, 2’ GAP

42679_10_FULTON_SB_PVTMRKG.DGN
OVLY COLD PLASTIC,
24" STOP BAR

THERMOPLASTIC, 6 INCH
DOTTED WHITE LANE LINE
EX 78’ ROW 2’ MARK, 4’ GAP

PROTOTYPICAL
PERMANENT PAVEMENT MARKINGS

0 3 5 10 3-LEG BOULEVARD INTERSECTION (FULTON/RANSOM)

FILE NAME:
= BRT FLOW PATH
Surface Transportation
DATE CONT. SEC. JOB NO. DESIGN UNIT SHEET NO.
FULTON ST 10 SCALE Grand Rapids . Southfield .
Traverse City
R.O.W CONST.
TS = TRAFFIC SIGNAL
01/18/11 46
FINAL R.O.W.
NOTE: 1) THIS PROTOTYPICAL PAVEMENT MARKING PLAN SHOWING DEDICATED
BUS RAPID TRANSIT LANES DURING PEAK TRAFFIC PERIODS IS LOGAN ST AUTH DATE NO. REVISION
CONSISTENT WITH THE FINDINGS OF THE ENVIRONMENTAL ASSESSMENT.
2) DEDICATED BUS RAPID TRANSIT LANES WILL BE MARKED WITH 6" WIDE
BROKEN LANE LINES AND DEDICATED LANE SYMBOLS.

EX 66’ ROW

STA 463+40
END RIGHT 4 INCH
SOLID WHITE EDGE LINE
PROPOSED DIVISION AND LOGAN SB
RAPID TRANSIT STATION

EX ROW

DATE: 01/18/11
THERMOPLASTIC, 4 INCH
SOLID WHITE EDGE LINE
OVLY COLD PLASTIC
DEDICATED LANE SYM
200’ SPACING
OVLY COLD PLASTIC
DEDICATED LANE SYM
200’ SPACING
DIVISION AVE

THERMOPLASTIC, 4 INCH
DOUBLE SOLID YELLOW LANE LINE

DIVISION AVE
462 463

600

EX 83’ ROW
EX 83’ ROW

THERMOPLASTIC, 6 INCH
BROKEN WHITE LANE LINE

WORKED ON BY: AVP


12’-6" MARK, 37’-6" GAP

THERMOPLASTIC, 6 INCH
BROKEN WHITE LANE LINE
12’-6" MARK, 37’-6" GAP

01/18/11
OVLY COLD PLASTIC
DEDICATED LANE SYM
200’ SPACING

DATE:
EX ROW EX ROW

TRW
THERMOPLASTIC, 4 INCH
DOUBLE SOLID YELLOW LANE LINE

CHECKED BY:
42679_14_LOGAN_SB_PVTMRKG.DGN
OVLY COLD PLASTIC,
24" STOP BAR

EX ROW VARIES
PROTOTYPICAL
PERMANENT PAVEMENT MARKINGS
LOGAN ST

= BRT FLOW PATH 0 3 5 10 3-LEG UNSIGNALIZED INTERSECTION (DIV./LOGAN)

FILE NAME:
Surface Transportation
DATE CONT. SEC. JOB NO. DESIGN UNIT SHEET NO.
Grand Rapids . Southfield .
TS = TRAFFIC SIGNAL 10 SCALE R.O.W CONST.
Traverse City

01/18/11 47
FINAL R.O.W.
NOTE: 1) THIS PROTOTYPICAL PAVEMENT MARKING PLAN SHOWING DEDICATED
BUS RAPID TRANSIT LANES DURING PEAK TRAFFIC PERIODS IS AUTH DATE NO. REVISION
CONSISTENT WITH THE FINDINGS OF THE ENVIRONMENTAL ASSESSMENT.
2) DEDICATED BUS RAPID TRANSIT LANES WILL BE MARKED WITH 6" WIDE
BROKEN LANE LINES AND DEDICATED LANE SYMBOLS.

OVLY COLD PLASTIC 44TH ST


DEDICATED LANE SYM
200’ SPACING

PROPOSED DIVISION AND 44TH SB


RAPID TRANSIT STATION
OVLY COLD PLASTIC
12 INCH CROSSWALK
8’ LONG, 2’ GAP
THERMOPLASTIC, 4 INCH
DOUBLE SOLID YELLOW LANE LINE

OVLY COLD PLASTIC


24" STOP BAR

EX ROW
EX ROW

OVLY COLD PLASTIC


LEFT TURN ARROW SYMBOL

THERMOPLASTIC, 6 INCH
BROKEN WHITE LANE LINE
12’-6" MARK, 37’-6" GAP

DATE: 01/18/11
DIVISION AVE
EX 98’ ROW

ONLY
OVLY COLD PLASTIC 203
204
DEDICATED LANE SYM 205
200’ SPACING

WORKED ON BY: AVP


01/18/11
DATE:
OVLY COLD PLASTIC,
ONLY

THERMOPLASTIC, 4 INCH

SOLID WHITE LANE LINE


SOLID WHITE LANE LINE

DOTTED WHITE LANE LINE

DOTTED WHITE LANE LINE

SOLID WHITE LANE LINE


EX ROW
EX ROW

BEGIN 6 INCH
THERMOPLASTIC, 4 INCH THERMOPLASTIC, 6 INCH
STA 203+81

DOULBE SOLID YELLOW LANE LINE DOTTED WHITE LANE LINE

BEGIN 6 INCH
2’ MARK, 4’ GAP

STA 204+31

TRW
STA 205+31
END 6 INCH

END 4 INCH

CHECKED BY:
75’ GAP

THERMOPLASTIC, 6 INCH
BROKEN WHITE LANE LINE

42679_30_44TH_NB_PVTMRKG.DGN
12’-6" MARK, 37’-6" GAP

PROPOSED DIVISION AND 44TH NB


PROTOTYPICAL
RAPID TRANSIT STATION
44TH ST
PERMANENT PAVEMENT MARKINGS

0 3 5 10 5-LANE INTERSECTION APPROACH (DIV./44TH)

FILE NAME:
= BRT FLOW PATH
Surface Transportation
DATE CONT. SEC. JOB NO. DESIGN UNIT SHEET NO.
Grand Rapids . Southfield .
10 SCALE R.O.W CONST.
Traverse City
TS = TRAFFIC SIGNAL
01/18/11 48
 

 
Appendix E 
 
Survey Drawings 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

  
Final Task I Vision Report 
 
 
Survey
Silver Line BRT
61
4 .7
7

DOORWAY

BUILDING
COMERICA
Louis Street Station

DOOR
CONC
RET E

POST

VALVE
61

INDICATOR
64
14
. .4
6
422
61 1 2
61 2 .2.6 8
2 .2 3
4

61 61

POST IND VALVE


5 4 .5
.0 2
6 5

CO
611 4 .5
6611 5 .0 4
6 6611 4

NC
44.9.4 4 .6
.6
75 61 33

E
61 61
64 4

RE
14
. .7 61 4 .8
.9 9 661 4 .4 66

U
0 14
999 144

TE
61.3.3 .3
61
3
LANDSCAPING

42.74
2.0
6161 8 61 61
4
4614.
4 .14 .7 .5 4 .8
3 STORY

U
6
BUILDING

2.7 2 61 6
& ’ CU 755
4 .561 6161
4
DOORWAY

1 .4 4 .5
4 .0
GU R
6 3 61 77 61
TT B 611 2 61
LANDSCAPING 4 3
5 .4
LANDSCAPING

.0 61 .9 7

SIGN
61 2 .4.4 6 61 0
61
8 3 .4
ER 2 .3 1 LAN DS 616 61 61
9 61 6161 61 61 46.8
1644161 661
4 .4 4 .1 5
4 4 144
11 .444
4614.
.1
4 .1 4 .44
C APIN
G .1 .8 .3.8 8 2 1
61 61 6.7
4175.3.33 61
U

1 6.4 3 4 4 5 95
64
11
14 .3
4 .7.74 4.2 61 4 .3
M 61
4
. .7 3 41 4 .8 5 61

U
.1 0
766 6161 4 61

SIGN
2 61
4 6 616 61 4 .0 3
.6 61 6141 4 3 .8.3 3 .6 0 .6
ON
61 5 4 66161 4 61 4 61 611 4 .8 4.6.15.2 61 50 2 7
1 .9 R .1 144.4 .4 4 614 .4 8 32 4
2 .0.07 9 .3 61 .9 4
6 O 04 7 4 .46
DOOR

4 .4 6611
2 61
6161 2
BI 4 3 44.7.3
.2 55
2 .56.01 9 61

CONCRETE
4
TU E A

E
2 28.2 V 61 .1 6161
3

LANDSCAPING
2 7
CONC
.5 4 .8
4 .3

E
MI 6161 2 4 8 7
NO E N 2 .9
RET E
CONCRETE

61 .4 65 61 61
2 .4 4 .0
9 66116 1
US UE 4614.
61 331.8.74 .1
61
U

61
100
3 .6 4.22 8 3 .9 61 4
4 .0 BRICK 6 6
2.0
3 61 4
61 61 8

F
3 61 61
.6 3 .9 61 .1 6 6 614 661161 4 6 61 61616114 .1 6166111 3
PARKING METE

66116 0 1414 4 .2
9 61.3 1 44.7 4 .344.2.2.761
F

.78 3

OVERHANG
3613. 61 61
6 .7 .6 .1 61 61 4.1.6
4 0
44.8.8 4 66 4 .2 4 .7
& ’ CU 341.6461 61 3 06611 61 34 .9
61
61 6 4 3 3 3 3 3343.8 6.4611 6661161 9 1 54 1 55 4 .1

U
6.1169.13 .6 616134 .4 7 3 4 .4
2

2IN
8
611 3 6116613 14 32.7 2
711 .3 2 .861 .8
.1 .2 6.4 .0.63 34.7.9.3 9 BRICK 83 7 6611 .9 561 8 5 6113461314444.4.4 61 66116141444.3.34 .8 6 61
3613.
9 361.4 .8 61 61
61
GU R
2 61 2 .7 3 1
13313.9.9 77 558 .8 44 4 661 .0.0.4.530 4 .3 614 .4 4.4 .887 7 631 2 61
.7

2"
1 61 6 1 2 .861
2"

61 616 61 3 .7 .9 2
U

.2 53.35.80 61 134.00000 2
811 641 .80088
2 .8 5 661 3 .3 9 61 61 61 .3.559 .6 0 .34 2 .91 2 4 .3
61 6 61 6 6 .4
861
TT B 87 6 61 3 .7 31.83 61 3 3.3
1 61 6 61 6 143
6
2 .9.32
7 6.8 6 7 .4 1 61 1

2IN
.3.86 61 1 3 .2 3 .7 631.7
2 .6 13 3 .3 66 4.3 6 61 61 8 4 .9 1 4 4 .3 1 5
9 3 .8 4 61 61 2 61 7 112
GAS

.2 61 3 .91 3 661 3 .7 1 3 915 61 2 .3


4 4

2IN
8 .7
ER
2

2"
3 3 61 2 1 3 3 .3 61 26 113 .6 .4 2 .4 .4

BRICK
0 6147.2 3 .9 1 8 .0 6 4 61 3 .0
2IN

9 .8 4
2IN

7 .4 8 616 661 143.0 8


61 2 3 .36 1 3 619 6 61 6

BRICK
3 61 61 616 6.7 4 .3 0 3 .3 .3 3 631 .55 9 6.6 2
.7 61 2 .56132 6 6 6

2"
1431 34 .66 3
6 3 .4 4 103 .2 3 43.2 661 4 661 613 1 3 3 .8 1 3
.4 .0.5 .5.0 5 1
6 3 .6 616661114 31.63 1 3 61.2 641 .7

TRAFF
61 1 .2 143 3 .5 2
8

OVERHANG
611 2 2 4 61 .0.4

OVERHANG
6129681 1 3 61 2613 .644.1.0 1 1633 .6 61 3.7.29 6.81611 1 .0619
.9 61 614 61 9.2 7 .2 9 38.2 3 .20661 .6 4 13

0
2 .7.3 1
8 3 .0 3 .5.4 3 .1 3 61 61 3 3 .6621.1119
6 3.2 631 761 6 1 33 .6 611 3 56 631.2 5 3 .12 6 2 .5
61 7 1 .1 3
61 5.6 18 2 7
61 2 4 0 861 1 3 .5 .5 93
.5 611 3 .607 .6 3 .2 3 .2 .2 8 6 3 .2.6 6 6211.7 .6
2 .8 6 3 8 3 8
5 1 3 2

BRICK
3 .0 .6 61 .23 1 8 2 1.7
.8 9 8
61 .1 5 3 3 .2
8
.2

20.5’ HIGH
3 3 .2 8
7 9

TRAFFIC
0

LIGHT ARM
61 61
2
CO
.5
8
2612.
.5
NC

U
588 2.0’ CURB

10
6

CROSSWALK
RE

BRICK
611 2

Feet
TE61 3 .1.6 3
& GUTTER
PARKING

0
METERS

3 .1 61
61 61 8 3 .2
2 .9 3 1
2 .2 61
6 61 3
3 .3 .2
2 6 MONROE AVENUE

1 inch = 40 feet
6 503+00
6 12

OVERHANG

BRICK
502+00

20
61 6 1 2 .8

LANDSCAPING

BRICK
3 .3 1 3 .3.8 8 7 501+00 BITUMINOUS

3"
20.2’ HIGH
500+00 3 0

TRAFFIC
61 6

LIGHT ARM
3 .31 3
LANDSCAPING

61 7 .3
2
61 9
.8 3 .4
6 4 6
611 2 61
3

BRICK
3 .4.9 9
4 .0
2

BENCH
61 61
3 3 .5 6
.6 3
1 611 3 61
3 .5.0 9 3
61 4 61 .11

BRICK
3 .3 61 3 .5
6 3 .6 9
5
61
3 6
LA 61 .6 61 3 61 61
3 .6 .3 6
8 631.3 3 .3

BRICK
3
ND 61 3 .41 6
61
61
3

BRICK
.7 3 .7 11 3 6
5 .4 1
SC
61 4 61 61
3
3 61 5 3 .7
61 6313..99
.6

U
.7

BRICK
00
4
AP 3 .7 73 .7 2.0’ CURB
7
9 6 6
3613.
.7

BRICK
BI IN 61 1 3

U
TU G 61
788
3 6611 3 .4 .4 3
61
.8
6
33.8.8 3 & GUTTER
96
MI
3 .8 61
3 3 .8 61
NO
61 3 3 .8 61
3 0 61 3
61 .8 3 61 .8 61
US 61
3 61 3 3 .7 3 4 .43 61 61
3
.6 3 61 .8 9 .8 61 61 61 3 .1
2 .8 3 2 61 1 3 2 4 4 .6

BRICK
2 .8 61 .4 .2 9
.8 3 4 9
61
.8 3 66161 63 .6 6 7
0 0

3"
631 61 1 33 .73 .3 13
63 3 .86 .7 99 3 . .7

U
13 61 13

BRICK
755
. 3

BRICK
.8 61 0 .5
3 .7
.7 061 3

U
9
833
9 .2
5 61
4 .5
1
32

61 61 61
3 3 .7
.8 8 61
3613.
8 .8 3 61
.5

U
3
800
96 .3
61 13 0
3 .8 .5
63 6 61
3 6
.4
61641 1 3 .0 61
33.4.4 0 61
4

BRICK
.0

BRICK
BRICK
6012
3613.
.4 5

U
61 2 .9 477
3 .4 9
6

BIT
LOU
61 61
3 3

UM
.7

IS
.7

CONTROL BOX
0 0

STREET LIGHTING
61

IN
3

BRICK
61.6 4
3 .6 61 61
2 3 .0 2 .7

OU
61
3
S TR
.5 61 6 9 0

S
0 21 61 6

CONCRETE
3 1.1361
3
0.0 2.5
61613 612.6.624.76
2612..03 8 3
EET
.5
CROSSWALK

BRICK
533
6611
61 33.4.4
3 .4 50
7 61
61 3 .4
3 .4 1
2

BRICK

WIRES IN THE AREA


61
631
.1

BRICK
261.6
72
7.6
8

NOTE: THERE ARE NO OVERHEAD


2.0’ CURB
& GUTTER

Sheet

1 of 21
Survey
Silver Line BRT
FIRE
LIGHT POLE

F.F.=613.58
Van Andel Station

ORNAMENTAL

DOORWAY

LIGHT POLE

PLACE
DEVOS
ORNAMENTAL
FIRE DOOR

FIRE DOOR

F.F.=613.26
F.F.=613.24
F.F.=613.29
61 61
6611 3 3 .5

DOORWAY
33.4.3 6161 6611 61 .5 5
5

DOORWAY
07

DOORWAY
33.4 33.4 3 .5
.54 .47

OVERHANG
DOOR
7 8 2 61

ORNAMENTAL LIGHT E
ORNAMENTAL LIGHT E
3 .4

ORNAMENTAL
61
3 8
.4

AREA
5

61 61 61
3 61 3 3

ORNAMENTAL LIGHT
.2 .3 .3

E LIGHT
3

AREA LIGHT
AREA LIGHT
8 0 7

AREA LIGHT
AREA LIGHT
.2

AREA LIGHT

AREA LIGHT

AREA LIGHT
7

LIGHT

DOOR
61
3 .2

DOOR
61
8 3 .2

DOOR
9
61
61 3 .2
3 6

6 6"
6"
6"
.1
0 61 61
3 3
AN .0
CONC RETE.1
61 G 61 8 61 8
612 61 2 3 .1

MONUMENT
61

ORNAMENTAL

ORNAMENTAL
2.7.3 2 .3 .8 3 4
2

DOORWAY
95 66 61 61
2 .8 6161
3 DECORATIVE TILE 61 2
72 63 3 2 .82 .8 611122 .1 61 2 .9
1 7 79 2 .4.4.494 66116122 66611 0 61 2 .9 7
8
1333
2 .8 7

BUILDING
.0
61
2 .5.5.5 .0.0 .8 0
OVER HANG
61

SUPPORT
42861 301 6
2. 2 .5 3 .0
7 66161 2

E
57

6"
1223

AREALIGHT

AREALIGHT
.9.5.0 0 66161

AREA LIGHT
95

AREA LIGHT
AREA LIGHT
AREA LIGHT
122.9

AREA LIGHT
6"AREA LIGHT
2 .9

LIGHT
LIGHT
.8.5 61
6091 0 2 .9 61
26.4 6
162 1 7 2 .8 6611
21.4621 8 22.9.8
25.4.8 09 61 61
6212.8
2 2 2
61 61

6
61 61 61 .8 .7 2 .6 2
2 2 .2
61 2 2.7 61 5 61 3 .6
2 .8 4

6"
6"
.1 0 2 .3 8 2 3

OVERHANG
1 8 61
2 .7 61 .7
1

6"
61 2 61 61 61 2 61 7 2 .9
2 .3 61621.82 2 .4 .5 4
66 610.7 2 .4
8 6 2 .7 61 61
611122 5 2 .3 661611 2 9 8 61
62 .36 2 .8 2 .7
4
61 2 .3.3.3
63 0 22.7.7
6.76118 661 61 61 9 2 .5
2 6

F
2 .2 3 99622.31 22 .32 .3 .3
61 6
26 1 66611 5
8 .23 .3 1 2
7 1 2 .21 2 2 .2 61 112222.6.6
9.2 9 2 .6.686
5 61 .1 8 67 61 61 61
2 .2 2 2 2 .3
1 61 .0 8 .5 1
61
7
61 66112.5 2
2 .1 62 2 61 61 .9 61
3 1 2 .0 31 1 2 .3
61 6 3 61 61
61 .9 9 2 .4
61 .0 3 3 61
2 5 .1 .2 3
..008
0 .9 .2

E
8 1 .91
0 32 7 6
5 61
61
611 61 61
61 1 .7 1..6 2 2 .8
1 .7 1 .2 61 61 61 4
1 0 2 2
633
MONROE AVENUE 611 .7 .2 61 61 .7
1 .74 7 2 8
5
1 .8 .3 61 61 61 61
3 3 2 2 2
61
2
.5 .1 .0 2 .5
61 .7
1 2 9 2 .6 1
8
7
BITUMINOUS
516+00

LIGHT POLE
515+00

0
513+00 514+00

ORNAMENTAL

10

Feet
CRO

MONROE AVE

1 inch = 40 feet
20
S SW

61
2
BITUMINOUS
.4 61
5 2 61
.4
ALK

9 2 .1
7
6611
22.2.2
44
61
2 .5 61
6 2 61
2 61
.4 .1 2 61 61
8 2 .1 2 .42 61
1 2 .0
61
2.4 1 9 61
1 611
61 6 .8 1..9
6111 .8 4
1 .9
61
U

2 .2 0 61
933 61
0 611 612
61
0 1..4 611 .6 61 61 61
61 6 2.2.72
611 .5 0 61 2 .2 611 2 61
.3 2 1
466 61 1 .7
2. 2 .1
2 .06 61 2 .161
9
612 .2 8 2 .7 1 .8
611 .7 9 61 0
E

2 8
2 .13 611 661 61 61 61621.1 6 2 .1
19 2 .78
2 .2 22.55.5 6 4
7 2 .2 61

GAS
61 61 2.9.34 122.5
2 62 7 .52 6 1 61 3 58 62
61 .1 61 1 2.1 5 4 12 61 1.6 25 61 61
2 3 61 61 .4
2 .4 61 2 2 .8
61 61 2 .7 .7 0 .7

F
.2 2 .2 .2
2 2 2 2 0 7 2 .6 1
2 62 1 .3 .4 .5 1 5
61
61
12
. 2 3 9 8
.2 .2 61
0 62
12 61
1 2 2

U
233
.2
. .4 61
2 61 61 61 61 61
2 .8
2
U

9 .4 2 .7 7
400
6 .5 2 .6 2 .6 .7 6
9 9 9 7
61 61
2 61
2 61
61
.2 2 .2 .4 2 61
1 6 61 1 .5 61 61
2 3
2 .0
3613.
2 4 .7 .8 61 .0 7
.4 61 5 0 2
STREEL LIGHT U

3
066
.9

GAS
2 .4 61 61 61
2
2 61 61
2 .8 9
5 .6 2 2 .9
2 .7 .8 0 46
2 4 61
61 61
62 3613.
1 2. 61 .1
2612.
.6 .9 2
122
.9
U
U

611
SA

944
5
GAS
GAS

61
61 3 .4
61 3 0
LAWN .1
3 .0 9
5
61 CONCRETE
63
13
. .2
299
SA

61
6

3
6

.1
4
61 61
61 61
3 2 .9
61 3 3 .1 .1 8
3 .2 .1 8 3
4 5
DOOR

DOOR

WIRES IN THE AREA


NOTE: THERE ARE NO OVERHEAD
34.0’ WIDE
OPENING TO

STRUCTURE
LEVEL OF PARKING
MONROE AVENUE

Sheet

2 of 21
12+00
RETAINING WALL
69 6969 8 69
7 .4 7 .4 .1 8 .1
8 006 3
6969 98
7 .27 .1 .0 69 69 69
39 3 7 .8 7 8 .0
.9 3
6 4

LANDSCAPING
6696 6699
69 99888.6.7 868.79.7 6969

Survey
8 .1.7600 854.2 8 .48 .4
2 7 32
6969
8 .68 .6
66

69
69 8 .7 69
8 .3 7 9 .0

BUS STOP SIGN


9 3

COVERED BUS STOP

Silver Line BRT


69
8 .7
69
1 9 .2 69
69 3 69 9 .1
9 .4 9 69 6
0 .3 9
5 .3
4

CONCRETE
70 69

1.5’ CURB & GUTTER


700 .0 69 9 .8
69 7 0 .00 9 .9 8
9 .60 0
8 8
5 .1 8
70
0 .4

23.2’ HEIGHT
1

70 70 7 70
0 .3 70
700 0 .7 70 0 .5
1 00
. 0 .8 2 0 .6 9
.8 1 7
4

U
84
70

OVERHEAD WALKWAY
1 .1 70
4 1 .0
8
Michigan Street Station

70 70
70
70 1 .01 .6 71
01
70 170.270 8 0 . .5

U
1 .313.31 .7
577
4 0706 7
1 .9 0 2
70 6 .0 70
2 .1 3 1
2 .9
8

BUILDING
70
70 2 .5
7070 70 2 .6 6
2 .72 .22 .2 5
70 25 9
70 3 .8
3 .9 0
2
70
3 .7
2
70
70 70 70 730.4
3 .9 3 .9 3 .8
3 .53
7 8 9 7
70
4 .0
9 7070 70
3 .5
3 .5 4 .1
70 5 70
70 7070 7 70 7 7 4 7070
3 .8 3 4 7 0774070 4 .3 70077045 0.3 .4 4 .4
704 .4
05.0 1 4 .5
70 55.0.0 0
4 .7 8.2 7 0 40 5.3 8 0
74
04 .4 .05 32 5.0.1554 .41
56
82
7

13+00
..887005

U
0.03 70
4 .8
7070
70 70 5 4 .85 .4
5 5 13
.3 .2

F
1 2

70
4 .9

LAWN
70
5 7070
7070
4704. 70 70 5 .56 .1
.9 5 .15 4 770 6 .25 .5
2.5 77 70

U
707 5
7070 7
999 6 .0
5 .7
5 .8
5 .55 0.05
5 1
0 8.1 7

LANDSCAPING

CONCRETE
70 7070

8IN 8"
70
70 6 .1
75
05 6 .26 .1
6 2 ..5758 7070 18
.5

U
7070
7 087505.663.15 6 .46 .5
70 5. 40
6 .9 70 7070.774
5 6 .9
5 .96 .44
12
75 0
70

0
7 .2
6706.
70
7 .9 707070 7070 7070
7 7

U
6 .77 .3 7 .46 .8
.7
97 6 .56 .16 .2
3 70 70 941 59 60
7 .4 7 .2
0 1
70
70 7070 70 7 7 .4 70
6 .7 6 .77 .1 .1 2 7 .3

LANDSCAPING
6 16 4 7
70 70

10
70 70 7 .3 7
8 7 .3
.0 .6 9 2

Feet
6 9

CONCRETE WALL
70
70
8 7 .8

BITUMINOUS
LANDSCAPING

.6 4
4 707070
70 7 .87 .47 .3
8 .6 70
70 23 9 70 70 7070

1 inch = 40 feet
7
RETAINING WALL

8 .0 8 .78

LAWN
8 .8 7070 8 .38 .3
7 3 8.1 5 13

MICHIGAN AVENUE
8 .18 .7

20
71 70 8 70 701 8 70 7070 75 7070
7071 .4 8 .37771100 .2 .1 7 .8 7 8 8 .58 .5
0.108 7 70 70
70 4.1.6 4 008.1.1.419 0 .775.2 6 8 .5 17
9 58 006 08 8 .7

LIGHTING CONTROL BOX


2.0’ CURB & GUTTER
70 70 4
9 .2 .4 9 70
.5 4 8 .7 8
1 0
8 .7
8

1.5’ CURB & GUTTER

CONCRETE
70
8 .7
CONCRETE

6
7710 770 70 70
71 09.1.1 7 7711080.9.1 8 .8
70 0 .170419 0 97.40 909.1.092 4 9.
9 .9 4 .7
4 6 .1 2307 7 7070
0 0 9 0 9 8 .58 .5
27
.2 .0 5 5
6 9
71 70 70 707
71 0 .2 9 .7 8 .9 80 9
0 .3 2 7 3 .9 0.3 77071
6 9 .50 .2 7170
51

4IN
71 0 .39 .7
0 .6
70 74
0 9 .9

LAWN 4"
5

E
70 7171
71 71 0 .00 .0
0 .8
97.971 77 87
0 001.6 0 .4717117011 0
70179317.9 71
71 07.019.6 0 .0
0 3.6 711 00 .7.7 0 .2
7171
0

ELEV=26.0’
03.17 8 0 .1.7 86.11 66 0 .30 .3
.4 9 23
71
1 .1 5 71 0 7
71
5 0 .1
1 .5
84

LOWEST WIRE
71
1 0 .8
ELEV=23.9’

0 71 7171
71 7 0 .5
0 .0 0 .0
701.41 8 50
LOWEST WIRE

0 6.00 .0
87
71 71 77111
1 .9 1 .9 1 .8.8 71 71
7 1 98
1 .1 71 71 1 .1
8 1 .0 1 .1
9
7171701.805.4 71 4 5
71 1 .1
7 7

LAWN
71 2 .0 71 11 70
1 0 731711 11711
71 2 .1 5 1 .9 .9 7711 7 0..55 1 .1.2 .2 78 .2
2 .2 7 1 714 2 11 1 171 ELECTRIC (AERIAL) 32 11 9
71 .1.1 0 .6 1 0
71 71 711 1 2 1 .7 77 711 7
1 .8 0 00 1 .7 71 71 71 .4 0
9
3
71
2 .32 .2 .1 6 0 111.3.3 .6171
.1 1 1 .0 1 .2 2 .0
71
.3 3 3 2 4 71
4 71 24 717 4 77
71 1 .7
1.
7171
11
71 1 .3 11
1.
1 .5 .8 5 1 .81 .8
U

71 9 711 .2.117
75
5

U
7 76
1. 39
1 .9 71 .2 6
CONCRETE 8 77111 71 71 711 71 71

U
1 .3 1 2
71 71
98 2 .1 2 .6
2 .4 2 .3 71 7 71 .4.3 9 .0 271 2 .2 .9 9 3 1
9 CROSSWALK 1 .52 71 2 3
8 1 .7
7 1 2 .17 .2 7
14+00

71 91 2 71
71 7171 .0 2 .4 71
71 2 .0 1
LAWN 71 2 2 1 .7 1 .71 .7 7 2 .2
7171 2 .8 71 .2 7 5 38 8
7 33 71 0 2 .2
71711 2 .6 .1.121 2 .4 8
2 .7
2 .7 8 6
43

Sheet

3 of 21
15+
Survey
Silver Line BRT
G.R.C.C. Station SB

MTER

CONCRETE
ELECTRIC
ELECTRIC
73 77330 73
72 7272 72 72
0 .1 0.1.1 0 .2
72 72 4 9 99.7.7 9 .6 9 8
4 .1 .3 .2 31 8 .5 4 4 01
4 6 3 72 72
9 .7 9 73 7
.6 0

(TYPICAL)
0 .2 73 3 0
9

ELEC METER
6 0 .2 .2 6 TREE BOX
72 LANDSCAPING 72 LANDSCAPING 73 2

TRANSFORMERETBETB
72 72
4 .7 72 72 8 8 9 .3 0 .0 73 73
0 6 7 .3 .9 8 7
73 73

0
.7 .4 1 0 0 73 0 .2 0 73 0 .5
0 9 73 73 .1 0 73 7 .4 0 1
0 0 3 .2 0 2 .6
.1 .3 0 .3 4
4 1 2
2IN

ETB 2IN
2IN
73 73 73
LAWN 0 0 0 .6
.1 .2 0
72 73 4 9
72 0
2"

72 72 9
72 8 9 .5 .0

2"
2"
7 .0

PARKING
6 .4 .2 1 6 0
.4 0 2
5

10

Feet
73 73 73
72 72
0 0 .5 0 .6
72 72
8 9 9 .8 .2
72
CONCRETE728
72 6 7 .1 .8 .3 3 5 8
2 .3 .2 7 5 6 3
.2 4 8 73
4 72 1 .4
9
METER
4
10IN

72 .8 73 73
8 4

10IN
0 0

PARKING METER
.2 .4 .6

1 inch = 40 feet
7

14IN
72

10"

PARKING METER
72 7 8 LAWN 5 5 73
6 .2

14"
10"

73
.7 2 6 .8 7 72 72

20
72 1 5
72 728 729 720 73 0 .8
0
727 8.9.4 8.4.95 9.0.51
726 .2 7 0
730 .5
5 .77 6.2.73
72 7 3 72
9
72 0 .59
72 9 72 5 7 .0 9 .5
9
5 .8 6 .8 .8 1 4
1 7
1

514+00 515+00
512+00 513+00
METER
PARKING

METER
PARKING

METER
PARKING
RANSOM AVENUE
BITUMINOUS
73
72 73 72 72 1 .7
72 72
9 0 .0 9 .6 9 .9 2
72
6 7 8 .4 .2 1 6
.2 .4 5 8
4 0 6

72
1 .7
2

Sheet

4 of 21
Survey
Silver Line BRT
G.R.C.C. Station NB

72 72 4
4 .1 .3
4 6

72 L
4 .7 72
0 6 .7
0

72
6 .4
5

72
72 6 .3
2 .2
71 4
3 4
.4
89

45
72 7
6 .7
72 1
726
71 71 72 5.2.77
70 71 71 6 8 0 .4 72 9
6 4 .1 .3 .3 5
.5
1 .7
5 2 7 5 .8
4 8 1

RANSOM AVENUE 512+00 513+00


510+00 511+00
BITUMINOUS

71 71
71 71 3 5 .2
70 0 1 .8 .6 4
8 .1 1 0
.9 0

PARKING
PARKING
1

0
71 71
71
5 6 .6
9 .0 72
CONCRETE .37 7 5 6
70 70 5 2 71 711 871 .2
9
711 5 .4 71 6 .9 .99 4
8 .9
.0 7 5 .8 3 7 .4 2 9 .4 7
70 0 89 7 71
5 2.4 1
70 8 .8 711 0 .6 71 2 .0 71 711 4 .0 4

METER METER
9 .3 6 1 .1 8 4 .5 1 71
721.4 571 2 .6 71 9

PARKING METER
0 71

PARKING METER
7 4 7 7 .9

CLEAN OUT
71 71

CLEAN OUT
71 71 274.5 721.6 7 .0 .2 0
8"

71 1 .2 71 4 71
9
8IN

0 1 .4 2 .5 6 29.6 3 .2 4 2

8"
LAWN

10
8IN
.6 0 1 3 9 .6 7 .5
6

8IN
2 2 72

Feet
8"
8IN
71 71 71 0

8"
LAWN 71 71
2 4 6 7 .7 .4
70
.6 .8 .1 0 7
9 .8
1 .1
5 1 8
9 3
71
4 .3 71 72
CONCRETE 3 71 71 71
7 0

1 inch = 40 feet
.7

U
71 71 5
71 71 5 .0 .7 .7 3
0
1 .1 2 .6 714 .7
9 5 5 6 7
.0 9 9

HANDRAIL

20
HANDRAIL
3 71
71 5 .0 71 .1 3 71
0
5 .1 1 5 .1 5 .6 71 71 72 72
.6 71 71 6
71
5 7 LAWN 9 0 1 .7
0 2 71
771 8 7711 4
.9 .9 .6 .9 2
LAWN 8

3X5
1 .1 .6 166 66.3.3 7

8IN
HANDRAIL
1 2

8"
6
DRAIN

6 .3.3

HANDRAIL
7 .3 535

HANDRAIL
70 71 43
9 5
.7 6 .3
0 4

71
6 .3

4FT
5

DOOR DOOR

METER
PARKING

METER
PARKING
RAMP

CLEANOUTS
PARKING
ROOF DRAIN

HANDRAIL

F.F.=716.35
DOORWAY

Sheet

5 of 21
Survey
Silver Line BRT
Fulton Street Station

-BITUMINOUS PARKING
LOT-

BRICK
PILLAR (TYP.)
65 65
4 4

BITUMINOUS
.5 .4

METER
5 2

PARKING
METER
65

PARKING
4 .0
65 65 8 6 65
3 .9 3
65
4 4
1 .9 655 4 .0
.1 65 65 65 .5
4 3 .9 4
4 4 4 .1 65 4 0
7 .2 4 4 .4

43
2 .2 65 65 9

6
5 4 .3 66455.3
65 7 65

6
3 44.42.3
.7 65 18 4 .4
65
4
65 9 3 .9 65 2 .4
3 4 4 65 7
.6 .1 4
0 65

CONC
.3

F
0 4 65
3
.1 4 65

CONC
8 .1 4 65

PARKING METER
7 .1 65 4

CONC
65 65 7 4 .2

PARKING METER
65 3 65 3 65 .1 7
3 .5 .9 9

CONC
635 4 CONC RETE
.63 65 4

CONC
9.2 65
65 .0 64 6 .0 4

CONC
65 3 .7

CONC
3 .2 65 0 3 9 655 3 5 .0
2 3 .2 65 .3 2 3 .4.9 4 7 65
9 3 .4 65 6 653 .9 6 6
3 3 .5 3 5 655 3 .9 5 3
65 .5 0 65 65 6
7 3 .6
3 .4 1 .5 1 3 .4 3 655 3 .8
65 2 4 .8 2
1 3 .5 3 7
65 .3 8
4 3 .4
4

RANS OM AVENUE 496+00 497+00


495+00

0
BITUMINOUS

10

Feet

1 inch = 40 feet
20
65
3 65
6 .9 5 3 65
65 655 3 .8 6 .8 8 4 .0 65
4 .3 4 3 655 3 .8 6 0 65
4 .0
4 .2 8 4 .3 8 655 3
.9 65 0 4 .1

PARKING METER
65 65 4 4 .4 8 654 65 8 65
4 4 .3 65 5 4.0.53 4 .0 65
.5 5 1
654 .1 656 3

PARKING METER
1 9 .0 4 .65 544 65 4 65 5
65 65 4 65 65 5 .7.5 3 .9 65 .7 9
4 .5 4 4 .5 4 .4 07 .0 7 65 65

10"
7 653 .7

10
0 .4 65 1 5 65 65 3 .8 4 4 .27
6 4 65 4 5 .2 7 .2 6
.5 65 4 .5 6
9 4 .6 6
.6 6
6 655 10"
10
4 .8 65
65 7 4
4 .6
65 CONCRETE .5
4 .6 7
8 65
8 4 .6 65
7 4 .8 65
65 6 4
4 .8 65 65
.9 65 65 2 4 .7 4
6 5 5 6 .4
.3 .1 65 65 9
3 1 4 5
.9 .1 65
0 8

12
65 4 65
5 .6 4

8
LAWN 65 .0 0 .6

14
5 7 65
.4 5 7
4 .0
4

8"

12"
10

14"
65
5 .3

METER
9

10"

PARKING
METER
CONC RETE
CONC RETE

PARKING
65 65
5 5 .0
.4 3
7

Sheet

6 of 21
Survey
Silver Line BRT
Wealthy Street Station

BRICK
2 STORY

BUILDING

LAWN
DOORWAY
CONCRETE

BITUMINOUS
65
2 .6
3 65 65
4 1 .3
.5 6565
2
65 7 1 .40 .9
2 .8 65 6 3654
3 1 5.40 1
BITUMINOUS

65 65 65 0.9 6 .0 2
2 6655 656
.2
65665 65
2
65
4
65 65
4
65 65 65
4
65 1 .5 1 .3
4
22.3.3 5242
.4.6 .3 .6 2 .8 2 2 .3 1 .9
541
.1.8 9 4
44 .411 9 9 .6 1 .5 .1 3 7 66
MAPLE STREET

1 8 2 7 65
1 .0 65
0 0 .9
65 4
65 65 2 .1
65
2 65
2 2 .4 4 .0
.5 7 6
2 65 2 .0 65
16.9 5
65
65
1 1 .0
531
.9 1
65 .5 1
CONCRETE .7 1 .7 9 65
0 1

F
65 65 65 65 65 65 65 65 7 3 6565 .2
1 1 1 .9 1 1 65 2 2 65 2 11.4 9
.2 .6 2 .4 .5 1 65 .2 .2 2 65 .4
2 4 65 3 .9 2 0 6 .4 2
65.04 65 41
65 .0
F

65 7 1 7 65 65 9 .4
0 .8 1 .3 .5 1 8 2 65 1 65 61
51 65 6 1 .0
5 1 2 .5 665 .1 3 65 2 2 . .9
1 .4 5 1 6
9 511 2 .2 .2 .0 65
U

9 65 9 .4 8 65 1
4 1
.6.6 65
900
65 .1

0
0 .8 6
65 665 65
15 2 .2
65 656 65 65 652 .2 65 6 65 65 1 .0 0
65 3 65 2 .1522.1.1 1 .7 65 1 652 .0 655 2 65 2 .1 2 .1 3 655 1 5
1 .7 2 .19 1 .7
1651.511.66.5501 1.09 6 66
1 .8
16.7 8 95 666555 3 .7 3 9 1 .69 65
1 .5.3 6 1 .3 5 65 1 .2 4 65 .1
1
521 2 1 1 6 2 1 5 1
1008 .08 5155.111.1.1
.7 111.7.7.7 .6 .3 .2 5 01
8 551 9 6 0
65
BITUMINOUS 476+00
1651.
.2
475+00 CONCRETE
U

474+00 266

10
473+00

Feet
65 65 65 65
6655
1 1 1 1 .2
11.9.9 .9 .7 .5 7
88 4 4 0

1 inch = 40 feet
20
65 65 65 65
1 1 1 1 .9
.1 .4 .7 6
9 7 3

JEFFERSON AVENUE BITUMINOUS


CONCRETE
65 65 65 65 6655 65 65 65
1 65 0
.0 6 65 1 .3 65 65
1 .5 65 1 .7 65 11.7.7 6 6 6 1 .5 1 1 .0 .8
6 655 1 6516 3 651 4 651 65 65 65 97 65 65 65
65 65 .4 4 9
6655 1 .2 2.6
654 65 1 .7 655 1 .7 655 1 .5 65 6551 .4 1
1 1
1 .0 1 6
65 2 1 1
1 .5.0 2 1.25.716 22.1.1 8 2.4.37 65 .580 2 .3 2 .2 0 .3 .8 1 .8 2 .2 2 .7 1 .5 2 1 .56 1 .99
5 .8 .5 2 .4 2
2 65 6.7 8 20 1
2. 2 .5 2 3 1 65 1 1 65 0 0 6 8 1 .9 4 3 9
1 0 65 65 1 .9 2 .1 3
2

U
65 6 .6 7 65 65
50
2 2 2 .4 2 0 65
2
1 .75 1
.4 .5 .5 0 .1
5 .8 2 0 4 7 6 65 65
LAWN LAWN 1 .9 1
8 .8
65 65 6565 65 65 65 9
65 65 2
1 1 2 .3 2 2 .52 2 .3 .2 2 .1
.7 .9 .6
CONCRETE CONCRETE
65
5 8 7 4.5 3 2 1 7
0 2652.
.5

U
522
65
66565 6 65 65 65 6565 65
65 65 65 6565 6655
1 2 2 2 .7
5 2622 5 2
5.72 .7 .7 2 .1 2 .12 22.0.0 2 .0 1 .9 1 .91 .9 2 .0
.8 .0 .3 3 5 6 66 8
2 1 6 1.1 0 97
.5.7752 4 65 7

U
65 2 65 2 .2
2. 62
52 6
12 . .2

12IN
12IN

12IN
U
65
299
65 2 .2
2 .0 1
65
2
65 LAWN 7 LAWN .2 65
2 6
LAWN 2
.1 .1 6565 6
0 4 2 .62 .15 2
1 0.0 8 65 65 2
2 .1 65.0
0 2 .54
5
LAWN
BITUMINOUS
BITUMINOUS

BUS STOP SIGN

WOOD CHIPS
WOOD CHIPS
WOOD CHIPS

Sheet

7 of 21
FIRE SERVICE
DOORWAY

DOORWAY
DOORWAY
DOORWAY

DOORWAY

CONNECTION
DOORWAY
2-3 STORY
DOORWAY

BRICK BUILDING

F.F. ELEV.=644.14
DOORWAY
64

DOORWAY
64
2642.
64 .9 64 3
2 .1

DOORWAY
64

U
3
944
.8 .0 7 3 64

HEIGHT=25.4’
6 2 .4 4
5 .2
3

LOWEST WIRE
64
2 64

BITUMINOUS
.8 4

Survey
6 .1
0
64 6 64 64
3 .34 2 3 .2 2
6 .8 5 4 .4 6
94 64
3 .0 3
64 64 64

POST IND VALVE


1 .1 2 3 3
64
3
6 .4 .8 3 .9 .7
644 3 646 5 8 4 7

CONCRETE
3 .1.1 0 64 64 664644 6464 64 64 64 64 64 64 64 64 6 64 64
34.43 3 4 64 4 4 4 64 64
4 4 4 5

4IN 6IN
644 3 .4
.9 44.0
4.0.0 4 .14 .1 .3 4 .4 .4 .5 .6 .6 .7 .7 5 .0 4 5 5 .0 5 .1 5 .2 .3
2 .9 9.4 0 9 6 012 54 7 7 9 1 9 9

8X8
9 3 6 7 .0 8 4 5 4

Silver Line BRT


GAS
GAS

OVERHANG OVERHANG
OVERHANGOVERHANG
OVERHANG
OVERHANGOVERHANG

OVERHANG
642
2

OVERHANG
64
.9 64
93 .1 64

OVERHANG
OVERHANG
OVERHANG
OVERHANG
OVERHANG

GAS
OVERHANG
2 64 3 3 .9 64 64 64
.6
64 CONCRETE4.20 4 4
6644 5
64 3 3 .7 6 .6 .9 .0
3 5 64 64 7 1 3
.5

GAS
GAS
33. .
1 3 3

GAS
AERIAL UTILITY LINES

RISER
AERIAL UTILITY LINES

RISER
7722 64 .8614 .8 2

GAS
3 .7 3 .7
64 2 4

F
6
64
64 64 64 64
4
643 .7 63 6 3

GAS
643 .9 644 644 4
.0 43 .8

GAS
3 .41 .
4 3 .2 3 .76 4.4.22 4 .6 9
0 4 8
222 43.6.229

CURB ONLY
Logan Street Station

461+00 462+00 463+00 464+00


HEIGHT=30.0’
LOWEST WIRE

DIVISION AVENUE
BITUMINOUS

AERIAL
UT ILI
6
644 3 64 64 64 64
3 .7.5 1 64 3 .8 4 4 4
8 3 1 .0 .4 .7
.6 66 5 0 3
7 4433
64 64 .6.6 6464
3 53 3 3

TY LINES
3 .7 64
.9 7
.4.4 64
78 3
7 3 .4 .7
9 9

64 64
64 643
4 .0 3 36.44.52
8 .9 64
9 4 31.6
.0 64 5
1 3 .7
5 6464
64 3 .3
3 .6
3 .9 64 9
67
9 3 .8 4 3
8 .7
1 64
3 .3
7
64
3 .4
4
64

0
3643.
.1 155
6464
3 .63 .1
48

10
64

Feet
4.
65
64
64 4 .2
64 4 .1 0
4 .3 7

1 inch = 40 feet
6

LA
O

20
WN

NC
28

RE
TE
64
4 .1
7

BITUMINOUS
64
4 6
.5 6 64 4 4 4
7 4 64.5 .1
4 .5 4 1 8
8 .3 7
64
4 .5
64 8 64
4 .6 4
4 64.2 2
4
6 664.3
646 4 44.6440.3.2
66 4 8
64 6644 4 644444.7.764 4 4.6.32 0 1
4 .8 4 .8.8 4 .7 34 .5 8
8 36 3 7

HEIGHT=24.6’
64
4 .4

LOWEST WIRE
5

64 64
64 5 .0
5 .2 6
05 .1 9 66444464 4 6
.9 .8 4 4
GUY POLE

3 54.0
.94 6246.6
HEIGHT=18.3’

29 44 42 64 64 5
644.7 .0
64.9 2.6 3
LOWEST WIRE

5 .06 3
5 .0 6
9 GUY WIRES
6464
5 .0
4 .7
7 0

64
64 5 .1
5 .1 9
1
64 64
5 .0 5
64 64 5 .1
66 5 .3 .3 6 6 8
45
64 4455.5.5 4 8 .0
5 .5 10 9
2
E
64
5 .0
64
5
64 6 .2
64 5 3
5 .3
.7 3
3
64
65 64 64
45
.
.5 5 5 .0
.3 0
0
588
GRAVEL
64 646
5 .8 455.6 664 5 6644
0 .60 4 5 .5 3 55.4.2 64
5 .5 06 5 AERIAL UTILITY LINES
8 .0
8

64
6 .2
3 6
644 5
5 .4.4 7
64 64 0
5 .8 5 .7
2 5

64 64
5 .9 5 .8
64
5
9 9 .5
4

64
5 .8
9
HEIGHT=19.3’
BITUMINOUS

64
6 .1
LOWEST WIRE

8
LOGAN STREET

64
64 5 .7
8 .0 9
6
6
64 4 5
6 .2 .8 2
64 1
7 .4
CONCRETE

64
8 .7
0

64
7 .0
64 64 6 64
3 6 6 .3
6 .9 .7 64
8 476 2 6 .5
.3 5

Sheet
3

8 of 21
Survey
Silver Line BRT
Franklin Street Station

65 65
8 7 .1
.0 5
1
65 65 LAWN 65
8 8 .1 6 65
.4 1 .7 65 6 .2
0 65 9 6
7
65 .5 9
.7 8 .0 4
8 7 65
6
65
65 .5 5 .8
7 65 5 5
.0 6
65
65 3 .8 65 65 6 .2
8 .0 1 6 .3 5 .9 5

U
2 65 3 1
6

CONCRETE
65 65 65
7 .4 7 .4 7 .2
65 65 65 .6 2
5 0 6
7 .0 6 .9 6

4X4
6 .6 65 5 6 65 65
65 65 65 0 5 6 5 .9 5 .9
7 7 6 .4 .0

SIG
.0 .0 6 .9 2 3 5
7 5 7 46655 6
6 .3.4 LOWE ST WIRE
65 65 65 71
6 6 6 .6 65 65 6
.9 .6 2 66.3 6 .4 5 6
4 9 56265 AT SAG=22.0’ 655 .4 0
6 .4

SIG
65 .16 7.1
65 3 0
665.0
65 6 65 65
65 6 .4
.36 6 .1 6 .16 6 .0
65 65 65 CONCRETE
6 .5 5
586 5 1 3
6 6 6 .1
.6 .6 .5 2 9
2 0 6 65

CONC
65 6 6 .1

CONC
7

CONC
6 .35 6
.0
656 65 65 65 65 65 4 3
65.45 6 .4
6 .3 6 65 65 65 6 .2 65 6 .0
0 165.3 4 5 .8 65 5 .7 5 .7 5 .9
65 6.9 6
8
65 8 8
6 5 .9 9 5 .8 8 2 65
6
65
.1 9 8
5 .9
.2 5 .4
0 0 2 3

442+00 443+00 444+00

0
10

Feet
DIVISION AVENUE

AT SAG=22.0’

AT SAG=22.0’

1 inch = 40 feet
BITUMINOUS

LOWEST WIRE
LOWEST WIRE

20
65 65 65 65 65 65 65
65 .5 655
5 .8 6 65 5 .7 65 5 .4 65 65 5 .3 .3 655 .3
65 2 655 5 65 5 2 655 5 9
.5 655 .4 9 5 .3
655.4 8 65 5 .32 655.24
65 6 65 6 .2.7 1 6 .6
.2 7
6 .0 2 5 .55 8 53.5 5 .4 4 5 .47
6 .3 655.7 7 1 65 65 5 7 3 5 6
.3 0 6 .35
5 6
6 .1 6 .0
65 65 565 8
6 .3 6 .1 6 .1 65 65 65
65
6
65
2 8 5 5 .7
65
5 5
.0 .0
65 5 .6 .6 .6
65 6 5 .9 0 7 9
2 65 65 3
65 6 .06 0
6 6 9
CONCRETE 5 586 65 .3 .2 CONCRETE
CONC
CONC

.8 9
CONC

9
CONC

.1 6 .2
U

8
CONC

6 4
6
65 655 6 65 65 65 65 65 6 65
6 6
CONC

6 5 65665565 65 65
6 6 .1.0
655 65 .3 .4 .3 .9 555 5 5 5 .9 5 5 6 5 .9
65 .6651 6655 06 6 9 65 8 5 3 65 .6.63.674.6 3 .9 2 .9 7 .0 5
6 .5 6 .5 .4 .4 3 6 65 6 4
66.5.2 0 65 65 6 .0
4 8 LOWEST WIRE 02 65 65 .5 0 6 .0 5 65 6 .5 65 65
65 6 .4 6 .6

SIG
6 .3 6 .4 65 1 66565.1 6 .5 0
0 5 65 6 .2 65 6 6 .1 5 5.79 7 65 6
6 .6
65 7 65 6 .76 605
7
SIG

AT SAG=22.0’ 0 .0 665.1 6 .25 5 65 5 6 .5 6 .8


65 5 65 655 9 6 .7 65 .7 4 1
5.9 65 LAWN 6 6 5.7.74 7 LAWN
6 1 65
65 5 .8 655 5 .7.2 3
6
6 .5 9 65 5 .7 3 .8
4 6656 2 6
65 .1
5 .7
56.7
5 .9 00
5
65 65
6 .6 7 .2
65 0 7
6 .1 BITUMINOUS
4
CONCRETE

65
SIGN

65 65 7 .3
6 .8 6 .9 7
7 4
BITUMINOUS
FRANKLIN STREET

Sheet

9 of 21
Survey
Silver Line BRT
Green Street Station

BLDG
BLDG

BLDG
BLDG
BLDG

"KFC"
1 STORY
BUILDING
65 65
8 6 .5

OVERHANG
.3

BLDGOVERHANG
2 0

OVERHANG

OVERHANG
BLDGOVERHANG
BLDGOVERHANG
OVERHANG

OVERHANG
65 65
4 .9 65 5
1
6565
5 .6
5 .05 .4 1
1.4 3 2

65
6 .2
65 65
65 65 7 .0
65
5 5 65
5 1 7 65 .9 .8 5
.7 .0 8 5

POST
2 5 .9 6 5 .8 65
8 5 6 5 .1
65 55 3

BITUMINOUS
BITUMINOUS

6 .0 .8
65
1 8 6565
5 .9 65 65 5 .25
65 4 65 1.8 0
5
6565 5 .8
65
5
5 .7 5
65
.2 6 65

CONCRETE
8
5 .05 .5 65 1 .7 2 .9 .9 65 5
84 65 5 9 6655

CANTON STREET
1 6
PUTNAM STREET

5 5 .8 .6 55.8.3 65.3 2
.5 7 2 32

LANDSCAPING
3 5 .8
0

BUILDING
LAWN

POST
65

BITUMINOUS
5 65

OVERHANG
.5 65
65

LAWN
5 65 5 .1
2
65
65 .4 5 .7 9 65
3 65 65
5. LANSCAPING
655.4 65 5 6 5 .7 65
5655. 65 0
58.4 5 .4 .6 5 .6
5
.3 6 2
76 4 65
.2

U
65 65655.6 65 6655565 1
.0 5
433 65
65 4 3 5
55 65
5
65 5 .35 2 4 5 .2
44.9 7 .2
5 .5 .4 .3 .3 5 .1 1.0 2 .9 .913 0 7
5 .0
1 1 5 5 1 55 65
4
65 6 4 .8
4

GAS
GAS
GAS
.7 5

GAS
GAS
6

GAS
5 655 5 65
65 65 65 65 65
4 .9.0 1
5
65
5 4 4 4 .9 5 5
.3 .8 .7 .0 .0
65
7 65 .3 1 7 2 7
64
54 4 3 1 DRIVE ENTRANCE CONCRETE 2
. .9 .9
6 65
5

U
999 65 65
CONCRETE 6 6 65 65 4 65 6 65 6565 4 65 65 65 6 65 65 .3

2" 2IN
2" 2IN

65 65
65 5 65 65
65 5
4 .2 5 5 6555 65 5 4 4 .2 655 4 4 4 .8 4 .9 4 655 4 5 .1 .3 9
.9 3
655 .3 .1 .1 4.2
654 .8 65 4 .5 .5
.1 0 4 .3 .3 4 .8.9
2 64
54 9 0 .9 2 3
8 4 .80 8 6 65 4 .19
4 .04
4. 7 8 6 65 .2 63 1 66575 . .3 0 4 .4.9 2
3
65 65 .582 4 .0 5
4 4 .2 7 8 4 .3 44.4.4 65
377
.8 4 .5 4
08
1 4 011 .5

0
3 8 0
65
64
54
65 2.0’ CURB & GUTTER .
5 CONCRETE .4
.0

U
2
411
65 65 65 65 65
5 4 .9 4 4 4 .6 421+00 422+00
419+00 .1 0 420+00 .5 .5 2
2 4 6

10

Feet

1 inch = 40 feet
65 65 656
5

20
5 .6 6555.65
.7 5 5 .65.6
6 42
65
5 .9
1
65 65
6 5 .8
.0 1
3
DIVISION AVENUE

65 65
4 .8 4
65
3 .8 4 .8
65 65 65
3 5 .1 5 5
1 4 .1 .1
6 7 BITUMINOUS
BITUMINOUS
2.0’ CURB & GUTTER
2.0’ CURB & GUTTER
65
65 4 .4
65 665 6
555 5
4 6 6 654 .8 65.0.06 56.05
.4 665 4 655 4 .6 6565 4 .85
7 5 .3 5 .4 7 65 565.024565 75 .0
4 .7365 5 .55 .5 3 5 .7 653 5.055 658
965 4 .86565 4 0 22 5
65 2 .750.6.0 7 5 .1
CONCRETE 65 4 .7
5 .4 6755 .9 65 365 6
5 56.55.5042 5 .5 565 0 5 5 65 65 65
65 5 .3 8
3.9 4
4 .1 65 6 1 9 65 8 .0641.9 .0 65 4 .9 654 .8 65 .6 8
8 65 5 .5
55 7 4 .965 2 4 .78 65 65 65 4 6
65 65 65 65 65 65 4 .665654
5 .7 5 65
9
65 .4 9 5 5 66 5 .6
4 5 5 5 4 656 .1 5 5 4 5 .3 .2 .2 6 5655 5 65
2"

645.2 5 .7 .1 1655 5 .1
.9 .0 .2 .0 .6 4 65659 55.2.27 55 8 65 65 5 .5 1 1 5 2 6 5 55 5.2 .2 2 5 0 5
2IN

0 4 9 7 32 8.2 45.76.25 89 6565 6565 65 .5 .0 2 65 65


3 65555 6 56 65 5 .36 .4
5 5 65 65 5 .7 9.84 2 65
5 .8 2 5 5
65 .6 656565 6 .0 6
65 655 .55 .5 5 .08 3 5 .2 7 5 .40 CONCRETE .7 5 .3
.6 .8 5 3 5 .655.1.1 5 5
0 21 .1
3IN

4 65 4 .7.2 3 5 45.2546.2.8
4
5 .4
466 6 65.56 1
3"

.3 2 .7 82 5 .00 8 1
0 3 9 65 65 0 65
FLOWERS 0
7
4 .2 65 8 3 5 5
65 5 5 .8
5
5 5.75
5 65 .3 .3 5 .3 4 .2 0.2 1
65 4 .4
4. 9 8 7 8
4 .3 8 65
U

65 5
48
8 .0
4 .2 65 65 5 65 65 65 65 65
5
65 65
7 5 5 5 5 .7 5 5 .4
BLDG OVERHANG
BLDG OVERHANG

65 4 .8 4 .9 .0 .5 .6 .7 9 .4
BLDG OVERHANG

65 4 .5 4 5 6 7 6 2 8 65 96
65 5 .4 5 5
4 .5 1 6 .1 65 8 .5 1
6 3 65 5 .8
6
BLDG OVERHANG

LANDSCAPING .0 4 65
5
2 65 .7
4
66554.2654.5 65
64 6 65 5 .8
5 44 8 65 .0 6 65 7
65 . 5 .8 6 .1 6 65 65
4
65 .008
1 65 5 .1 5 5
.3 4 .0 8 5 65 8 .9 .9
0 .9 3 7
8 3
6 .1 65
LAWN

65 8 6 .3
5 .1 0
3 65
65 65 65 65 65 5 .8 65
4 .6 4 .2 4 65 5 5 65 65
6
22

8 9 .6 4 .7 .7 5 9 65 6 .2
3 .6 65 2 7 .8 6 .2 7
9 4 4 .2 65 4
.3 2 6
LAWN

.1
SIGN

65465 4
LAWN

4 .14 .6
8IN 8"
BUILDING
1.5 STORY

73 65 6
CONCRETE
CONCRETE

5 .0 5 5 65 65 65 65
.2 5 5 6 65
65 065 0 5 .2 .3 .6 .3 6 .3
5 .2 5 .3 7 1 9 6 9
0 1
BITUMINOUS
OVERHANG

BITUMINOUS
GREEN STREET

Sheet

10 of 21
Survey
Silver Line BRT
65
6 .4
210

21
65 665
675 5 77
.2
7 .27 .0
.0 0
0

SI9
8

397+00
Cottage Grove Street Station NB

396+00

LOWEST WIR
SAG=17.1’
E AT

E S
LO SA
W G=
W
65

2
65

IR
65 65 8 .0
65 665 7 .8 658 7
67 .5

E
65 578.7 3 8.0.56
6 7 .0

T 1.7’
65 655 75 .25
65 6 7 .0 6 655 7 8 7 .9.4 7 5 0
6 655 6 3 5 6 .0 2

AT
65 65 6 .9 7 .5 7
6 .7 65 6 2 7 .4.9 3 .9
4 7 65 65 65
65 6 .565 655 6 4 7 .8
.3 5 5 65 8 8 65
8 8
656 4 6 .3 7 65 .1 65 .0 65 .2 .4
7 .1.6 6
0 7 1 8
2"

7 1
F
6.4.92 9 7 65 65 7 .7 .9 65 .2 8
U

7 65 7 65 .5 2 7 0

0
7 .5 7 7 .8 3 8 .9 LAWN 65
.3 65 .7 1

2"
65 8 1
2"

8
2

65 7 65 6 65
65 65 7 7 8 .5 7 8 .8

U
.5 .0 2

2
.1 .5

2"
66.4 6 .9 65 3 3 65 65 65
7 9 7 7 5 8
2

5665
46 65 2 .3 65 .9 8 .3 .5 6565
.8 8 6 7

2"
6 .9 LAWN 7 8

2
66655 .3 9 .09 .0
.8

2
5666 8 7 65 0 65
65
7 8 CONCRETE 65 55
.4.4.56
9752 6 65 6 .8 65 7 .8 65 8 .9
7 .6 0 65 5
.3

U
.7 6 .8 8
1 0 65 6565 86.05 65
8 8
65 1 9 8 .1
8 .38 .4 86.3 .5 .7
6 .46565
6 66 65 65 65 0 22 1 3 1 AERIAL UTILITY LINE
65 7 8 .0 8
6565 65 25 6 .4.4 4.5652 7 .9 1 .0
6 65 6 5

10
6 .76 656 .9 65
65 65 CONCRETE 7 .7 0
65
8
5.7 5 6.3.8 8 .7 1
6 7 8

Feet
6 .4 4 .6 .8
7 .1
6 5 65 5 4
1 8
AERIAL UT 65
65
7
65665 5 7
7 .7 .5
0
6

ILITY LINE
.5

6
7 .4 75.7 65
66 9
7 .8.7 5 5 65

FO
4 65 9

6"
6"

65 565577.46.45 26 65 9 .1 8 .9
65 7 .47 .3457 .5 9 .2 .4 0 9
6 AERIAL UTILITY LINE 5 0
65 6565.2 0 65 8 9 2 65

1 inch = 40 feet
6 .3 6 6 7 .5 8 65 LAWN LAWN
3 .2 0.7 5 1 65 .7 0 65
8 8 65
65
9
.9 .9 .4

20
65 8 .7 8
65 65 8 1 9 2 .9 2
65
7 8 .3 9
7 .9 65 .2 LAWN 3
.8 0 9 1
5 .3

U
65
7 .9 6
3
65
9 .3
65 5

BITUMINOUS
9 .0
4
SAG=16.4’
LOWEST WIRE AT

SAG=17.7’
LOWEST WIRE AT

LOWES
SAG=20

SAG=20.1’
.1 ’
T WIRE

LOWEST WIRE AT
AT
65 65
685.5 8 .6
8 8.5 6
9

Sheet

11 of 21
Survey
Silver Line BRT
Cottage Grove Street Station SB

1 STORY

BUILDING
BRICK & STEEL
F.F.=658.26
DOOR

65
66 6 .4
1 .4 210
5
21

0
65
66 8 .7
0 8 65 65
.7 8 65
7 7 .3
6565 6
9 65 .2 .9 6 .25 6
DOOR 36

66 9 6 9 5 6 .7
0 .6 .8 65 5 8 .3 0
8 9

6"

6
8 65
.6

6"
65 3 9 .2
9 0 65

6"
.9 65
.78 CONCRETE
9

6"
7 .2 3
65

6"
LAWN LAWN 8

10
4 65
LAWN

.4

6"
65
66 9 8 8 .3 65 65

6"
65

Feet
6
1 65 .3 8 5 8 675
.1 4 .4 .1 .2

6
7 66 9 .7 9 0 7 .27
0
SI9

1 665565 8
SAG=2
.1

6
2 6565 65 65 66.7.86 5.3
5.0’
CONC

CONC

6
76.8
7 .8 6 .9 6 .866 23 67.3

6
556
LOWE
65 57 9 3 6.5 9
8 65 4.63

6
65
9 .7 8 .56
SIG

9 0
ST WIR
65 .4
9 .2 7
E AT
66 0 5 65

1 inch = 40 feet
66 0 .7
66 0 .2 5 6 .9 65
1 .8 2 65
7
653 6 .5
.3 1

20
6565
2 65
65
8 65 65
8 7 .67 .6 65 6 .0 65 65 6 .9 7
65 9 .6 8 .1 76 7 655 61 6 .9665.6 3
.4
U

9 .0 1 65 9 65
7
6 .7.9 4 6 63
66
CONCRETE .6 5 1 65
.9 665.2 6
6 .6
66 0 .1 65 65 65 65 8 .1
7 .9
5 6 6 4
66
1 0 36 65 8 8 .4 8 .1 65757.0
.6 8 .8 8 .3 0 36 .0
3"

59
.2 9 635 .9 5 2 6 4 7 65 65 5 76.555 7
.5

3"
65 .3 656 .910
66 9 9 7 655 7 7 7 .06 77 .0 9

3"
662 0
66 .9 .5 9 6 .9 .1
3

655 8 .3 6 .90
.2 0 2 6
LAWN 655 8 657 .4 3 5 95 7 7

3"
.3 5 .2 6

3
1 .0 8 .8
9 6 6 59 657 .8 6

3
7 36 7 .46 2

3"
655 9 5 .2 65 .3 86
66 65 9 .7
7 .86 8

3
656 0 .3 65 8 .8 7 5
9 8 .4

3
660 .9
65 9 .8 3 .5 65 .2 97 8 .9 6 5
66 0 .59 7 9 .2 1
9 .8 7 9
0 .5 5 8
2
LOWE
LO SA
W G

SAG=1
ST WIR
9.6’
E AT

65
65 6 8 .2
65 6 8 .8 655 8 .2 7
8 655 8 5 8 .7 2 65
65 65.9 8 9 .2.7 8 0 657 .1
8 .9 9 .3 6 7 .19
2 4 9
SIG

65
9 65 6565
65 .0 6 9 .4 6 .7
6 .7
659 9 5 5
9.0.18
3
AERIAL UT
65
65 9 .2
96.2565 8
96.29 .7
02

65 6565
9 .7
9 .2 9 .1
66 9 74
1 .0
234

20

Sheet

12 of 21
Survey
Silver Line BRT
F.F.=687.58
DOORWAY

F.F.=687.23
Burton Street Station NB

DOORWAY
6868

DOOR 60 INCH
6 .66 .1

DOOR 36 IN
68 68
68 7 .5
7 .2 8 6868
3 6 .76
68 6.3 5
68 66.78
68 7 .1
68 .9 6 68636 .6

3"
86 6 E 2 68.46 1
.8 68 .8 7
CONCRET 68
7 6 68 4 6 .7 9.4 3

CONC
.6 68
1 6 68 68 680
668 6 .7 6 6 .8 7
6 .9 6 .6
86 68 688 6 .6 688 6 .0

U
68866.7 8
4 68 3 2
.8 6 .7 8

CONC U
6 .2 6 .1 1

3
6 .2.6666
0 68 .3421 628 7 8 6 .8 6
68 6 86
6 .3 6 .2 68 6 6 .7
.3 4 6 .7 866.6
9 8 1 68 5 .523
6868 6 687 .0
6 .4.8 68 6 6 .54
2648 66 .9 688 6 6
.5 2 6 .5.9 8
1 1

0
68
68 6 7 .1
68 7 .0 68 688 7 .1 5
68 7 .1 7 .61
68 7 .0 4 9 0
68 7 .0 7 .0 0
68 686 4 68 9
68 6 6 .9 7.9.45 7 .1

10
68 4
68
6 6 .7
68 6 .8 68 68 688 6 .8 6 8

Feet
68 68 68 686 2 7
6 6 686 .5 688 6 1 68
7 7.7.36 7 .3 .4
7 .4 8
68 6 .59 68 68 7 .2 .2 89 7 5 2 4
68 .3 4 68 68 .4 7
68 68 7 7 .0
7 .1.6 7
7 7 2 .3 68
686 .3 66.28 6 .3
6 6
7 .0 7 .1 1 68
6 7 .3
6 .9 4
4 .9 .9 5 3 68 7 68 7 .1
68 6 .82
0 1 68 3 6 7 2
686 .2 4 6 .9 .1 9 68 68 68 68
.8 68 8 68 4
68
7 7 7 .4 7 68 7
68 6 .73
7 68 7 7 .3 .4 68 9 .5 68 7 .7 .8
6 8.1 4 68
7 .2 .2 5 1 7 5 7 CONCRET 0 E 4
6 .0 0 .4 .6 68

1 inch = 40 feet
6683 .9 0 9 7
6 .2 68 8 4 8 .9
CONC

68 .1 5 7 1

1 1"
CONC

3 68 68
.0 7

2 2"
6 .2

20
7
CONC
.3

CONC
68

2 2"
68 56 68 CONCRET E 3 .2 3 668 68 668
.3 6 2

2 2"
6688 8 .38 77 .9 68
6 8.16 2 .7 66
68878.6 7

CONC
3 68 78.4 628 .8 07 .9
68 6 66 6 687 .2 2

CONC
.2 6 68 688877 9

CONC
685.0 68 7 .5.062 7 .89
7

SIG
68 86886778.18 7 .8 7.7.722
6 .29 2 8 6 .3 .1 687 .67.178.17546 6 68 7 .4.8.257 7 .5 5 7 5
68 6
8 1 2 7 .38.2 389 7 7 .4 1
6
6 .28668
5 .2 2
0 .16 4.5 68 5
4 7
69 68 .3
7 .2 7 2
68 6 .5
6 3
.5 68
1

U
68 5 .2 68 68 68
7 1 5 5 7 .9
68 .2 .5 .7

BIT
6 3 6 6 2 1
.7
BIT

BIT

BIT
2 97
69 .1 68
7 9 68 7 .3
66 .1
68 8 58 6 68 3 7 .1 7
5 .9 .9 .4 3 7 3
5 .0 -BITUMINOUS PARKING LOT-
8 0
68
6 .4
2
68 68
6 .7
668.9
6784
1 .1 68
6 .8
16 5 .0
9

BIT

HEIGHT=24.4’
LOWEST WIRE

Sheet

13 of 21
Survey
Silver Line BRT
Burton Street Station SB

BRICK
2 STORY

BUILDING
MULTIPLE
STOREFRONTS
F.F.=687.58

0
DOORWAY

F.F.=687.23

F.F.=687.25
F.F.=687.49

F.F.=687.01

F.F.=687.05

F.F.=687.11
DOORWAY

DOORWAY
DOORWAY

F.F.=686.42
F.F.=686.83

F.F.=686.17
F.F.=686.33
DOORWAY

DOORWAY

F.F.=686.97

10
DOORWAY

Feet
DOORWAY
DOORWAY
DOOR 36 IN

DOORWAY
DOORWAY
DOORWAY
6868
DOOR 60 INCH

68
7 .2 DOOR 36 IN 68
6 .66 .1
68

DOOR 36 IN
5 7

DOOR 36 IN
DOOR 36 IN
68

DOOR 36 IN
6698 68 7 .5
68 68 .2 8

DOOR 60 IN
DOOR 36 IN

DOOR 36 IN
68 669689 7 .4 6868
7 7

DOOR 36 IN
6668 7 6967.6.0 3

DOOR 36 IN
.1 .0

DOOR 36 IN
68 68 68 .0 56.5
6.9.7 9 6 .76
68 68 68
6 6698 6 6 89775 1 5 1
6 .699 68 6.3 5

1 inch = 40 feet
6 .8 .9 .0.5
68
6 6 6 .4 6969 6 783 2

OVERHANG
6 .1
6 .2.6 3 68 66.78

OVERHANG
.7 .1 .3 68 6 2 7 69 .0 135

OVERHANG
16
5 .5.6 68 7

OVERHANG
4 5 7 3 .1 68
6 .1

OVERHANG
4 69 65 .5 68 56 68 6 68 .9
68636 .6

20
69 6 68
3"

OVERHANG
6 .9 6 2

OVERHANG
6
68.46 1
69 .9 7 E

OVERHANG
6 .0 69 68 6 .4 8 63 .9 4 .8 .8 CONCRET 68
6 6 68

OVERHANG
6 .3 368 .9 0 68 4 7
9.4 3
.8 6 68 4

3"
1"
68 6 .7
CONC

9 668.0 68 68 68
6 68 1 5 6 .8 .6

OVERHANG
6 .8
6 6

OVERHANG
6 68 680

PARKING METER
CONC
68 .4 6868 1 6 68
6 .56 1 .9 .8 6 .9

CONC
68 6 668 6 .7 7

OVERHANG

PARKING METER
6 .5

CONC
68 2 68 6 68 E 68

CONC
1 6 .8 6 .6

OVERHANG
668.1 CONCRET E 5 6 6 CONCRET
6 1 6 .86 .8 68 8 6 68 688 6 .6 688 6 .0
U

0 68 68 6
6 .8 8 6 68866.7 8
4 68 3 2

CONC
68 .7 .6 68 .8 .8 6 .7 8
6 6
CONC U

6 68 6 6 86 6 .2 6 .1 1
6 6 768 66 .9
3

6 0.0 6 .2.6666
.6 .6 1 6 .8 688 6 2 .8 0 5 8 .9 0 628 7 8 6 .8 6

CONC
2 68 .3 9 68 6 2
6 .7 .8 68 .3421 68 6 86

PARKING METER
68 68 0 688 6 .6 68 .5 01 68 6 6 .7
.5 3 3 68 6 .4 3 6 .2

CONC
68 68 6 68 6 .3 0 6 .3

1
6 .0
5
6 .4 .5 6 686 .1 2 6 .4 8 6 .5
9 8
.3 4
1 68
6 .7 866.6
3 .9 4 686 .0 3 6 .4 7 5 5 .523

3
6 9 6 .12
6 .27
1 8 6868 6 687 .0
5 6 6 .54
688 6 .0 3 6 .4.8 68
68 5 .5 4 2648 66 .9 688 6 6
5 .6 6 .5 2 6 .5.9 8
0 1 1

METER
PARKING
OVERHANG

OVERHANG

METER
PARKING
OVERHANG

METER
PARKING
68
68 68
6 6 6 .5
68 668 6 .4 688 6 .59 68
68 .3 4
6 .28 66 .3 7 68 68 7 .0 7 7 .1
686 .3 6 6 .9 3
68 6 .82 4.9 04 .9 3 5 68
4 1 68 6 .9
686 .2 6 .8
68 6 .73
7
68 8
6 8.1 4 68 68
7 7 .2
6683 6 .9 .0 0
68 68 .1 6 .2 68 8 4
6 .0 7 68
.3
.4 6 .25 3
7
09 685
2 2"

68 6 .3 68 CONCRET E 3 .2
6 2
2 2"

.7

36
6 8.16 2 66
CONC

68 6 3 68 66 6 6888
.2 6
CONC

685.0 7
SIG

6866868888767778.18 7 68
6 .29 2 8 6 .3 .1 687 .67.1.1.1 7 7.8
68
8 1 2 7 .38.285.14368976
66.2868
6 5 .2
0 .16 .5 68 5
44 7
69 68 .3
7 .2 7 2
68 6 .5
6 3
.5 68
1 5
U

68 .2
68 7 .2 1
BIT

6 3
.7 69
2 7
69 .1 68
7 9 68 7 .3
6 .1
68 68 58 6 68 3 7 .1 7
5 .9 .9 .4 3 7 3
8 5 .0
0
68
6 .4
2
68 68
6 .7
66.9
8687
1 46.1 68
.81 5 .0
6 9
BIT

HEIGHT=24.4’
LOWEST WIRE

Sheet

14 of 21
Survey
Silver Line BRT
66 6 6
5 .1 6 56 5
BRICK

9 .1 2.5 5
1 STORY

BUILDING

WATER VALVES
SHRUB

BITUMINOUS
Southview Street Station

66 6666 66
5 .7 6666666666 6666668668 666666
5 .1 4 5 66
1 .9.40 4 5 .6 2 5 .757.9.277.3.2 7 .2.48.5.4 89.59.0.0
1 9 43 14 74 03 128

SOUTHVIEW STREET
F
66 66 6 66
66 7 .1 7 6.38 8
5 .1 5 4.3 7 .5
9 0
6667 6677
90 00
66 66
5

ELEV. N=22.3’
64
64
. .3 6666 6
LAWN
6 66
LAWN
66666
689 6666667 66 66 66 66
9
6667.9.749 67670
90.9.7
.8 9 57.5.2 6 7 67 8 7.3.8.0 .7
87.7 7 8 66 66 9 .5 .8 67
811665.39 .3 .4.4 9 .7 .8 9 9 7 6
12 0 3
810 .511
6 1 8

LOWEST WIRE
666 .0 4 .0 5
86.89
66 9.1 7 66 LAWN
66 66 7 .6 8 .8
5 6 .7 5 66 66 LAWN 3
.3 4 7 8
8 .7 .1
2 9 66
6 66 8
66 66666 5 6 .9
AERIA L UT 7
4 .3 6
5 .05 .4 66 .5 2
.9 95 6 5
ILITY LINES 66
5 561 .1 9 5 .6
65 .6 4
.1 2
66 1
5 .0 66
3 66 66 8 .7
5 .3 7 3 66
66
7 66 66 6666 5 .4 9
4
66
CONCRETE 666.5 67 .4
66 5 .7 5 .8 5 .8 .9 6 66 67
3
5 .16
67656 5 .7 9 3 82 66 7 .2
.
.7
6
U

.6 1
755
.5 5 6
2IN

5 .6
5
2"

35
6 666 8 .5
3IN

66 LAWN
3"

6666 666
66 666 7
5 .1 666665666 6 .2 686.1 6
7 55.6.76 55 .3 566.5
.5555.8.9 66 66 .7 62 80.1
66 93 .3 99 1
5. 6 .8
66 3 .9
896.46241 5 .4
5 .5 3 0
2
66
43
66 1 .6 2 1
0 .9 4
65 .7 3
8 1
.9
8

2.0’ CURB
& GUTTER 2.0’ CURB BITUMIN
& GUTTER

AERIA L UTILITY LINES


DIVISION AVENUE 336+00
ELEV. S=18.7’
ELEV. N=17.0’

335+00
334+00
LOWEST WIRE
LOWEST WIRE

66
333+00 6666 6 7
666666 66 6 7 .3 1
666666.2.2
.2.344 7 .8 .3 3
66.8
.8820 2

0
0 66 66 66
7 .87
7. 665.4 0
6666 66 7 .4
5
6 .1
6 .26 .7
15
50 5 66
6 66 7
66 666 6 66 7 .8
.3 5
666 .2.7 3 7 .3 8
6 .20 1
4664.
.7 1

U
755

10

Feet
DIVISION AVENUE

1 inch = 40 feet
20
2.0’ CURB
BITUMINOUS & GUTTER
2.0’ CURB
66 66 66 66 9 6666
& GUTTER 8 7 .9
8 .9 .2 99.3.2
66
66 66 .2 8 6 2 39
66 6 4 .3
466 66 66 66 66 66 6 9
66 6 4. 66 5 .9
1 66 3 .2 66 66 66 666 4 8 66 6 4 .5 5 .4 5 .6 5 .3 5 .4 5 .8 6
66
6 .6 .4 4 .5 2 .0 6 0 6 7 7
52
4 .7 0 .9
65
66 6666 6366.26 33 66 4 .2 4 .54 .7 1 8
65 65 9 .5
66 0 .6 666 1 9 33.3.3 31.4.3 4 .3 8 5 2 9 5
8 660 6 2 .1.6 4 66
0660.
669 .5 4 .0 41 09 1 4
66
65 .3 9 65 1.6.01 2 .7 66
9 7
0 .02
099 63
65 8 .3 65
.5 0
63
. 7 66 66 9 .6
.9 4 5

F
8 .7 2 8 .8 6 .9 .0
6 3

U
911 LAWN 2 3

2IN

3IN
66
66 66 4

2"
1 2 .9 66
.2 .6 5 66

3"
6 1 5 5 .1
66 LAWN 66 .0 7
0 .1 3
66 7
.9

17
4 6 64
64
65 6666 66
9 6666 6. 5
.1 6.74 5 .05 .0 .1

U
6 66
73 3.5
66 2
33.9.9
2 46 7
1 .5 89
65 6666 66 .3 5
65
9
6655 9 0 .2 4
.4 99.5.4 .7 00.0.0
4
0 39 5 54
66 666666 66
CONCRETE 666 6 66 66 66
4 5 .1 5 55.2.2 5 .2
66 634 6 4 4 4 .1 .6 7 .2 1 13 1
66 66 2 .7
.9.0 .0 .0 6
0 1 .4 1
96 4 5 4
65 65 .8 2 66
9 .4 9 .6 66 1 66 5
7 2 66
0 0
4 .6 .966
46
.7 .7 9 .3
65 65 9 2 66 1
9 .8 9 66 66 65
.8 0 0 65
66 664
5 7 .1 .6 6 . .5
6

4IN
4 64
6645.7 1 522

4IN
65
..77.199
9 9

4"
.8 CONCRETE

4IN
2

4"

4"
LAWN 66
6 .7
66 6666
6 .16 6 3
66 6
66 5 .3 66 6656 5.1.63 6
4 .6 9 5 .8 .35
BITUMINOUS
6
66 3 3 .4 3
66 0 .6
0 .0
65 8
9 0
.9
0
65 65
9 .8 9
6 .9
2 LANDSCAPING

Sheet

15 of 21
F. ELEV.=654.32
DOORWAY

Survey
Silver Line BRT
28th Street Station

64 64
9 .6
6 649.47
64
9
8648
.6 64 ..9 9
2 8 .9 44
0
64
9 .4
CONCRETE

64 64 6
649 .2 64 9 4.1 8
9 .39 9 .2 .2 61.7 3
7 1
BITUMINOUS
PARKING 64
9 .0
8
64
65 64 8 .9
6565 3 .8 8 4
4 .44
0 6565 .8
8.0 4 4 64
3 .43 .9 9
TRAFFIC

20 65 .0
2 7
LAWN

65 65
3 .2 64
4 .3 .6 6 8
5 6 .3
0
CONTROL BOX

65 65 65 64
7 65 8

HEIGHT=21.7’
.8 6466
65 657 7 .77 .4
7

HEIGHT=18.6’
66 .3 9 0 7 .4 65 65 .6 84.6488
56 8 65 2 6644 3
.4

LOWEST WIRE
. 0 65 3 .5
F

LOWEST WIRE
88.4 64 646 5.6.602
65 .774 4 .5 6565 .4 1 .44
6 .8 4 6565
3 3 .7
4 .2 65 65 0 7
64 5 8 .2 487
4 .94 3 .1.939
3 5.7 0
65
4 7655 3 .8 3 65 64 68
.2 4 .2 3 .5 4 3 .5 8 48
.
9 6 8
65 65 .5 .5
3 3 0 5
E

65 .8
55

LAWN
.6 65 65 64 64
7 .6 65 65 65 8 3 3 65 64
8 8 7
7 65 5 65 4 5 .5 .5 2 64 .3
1 .6 7 .9 5 .0 6 6 4
65
3 .7 8 9
64 6.047 .9 6
4 6 .1 7 .26565 6 3 5 .4 0 .3 8 .3 .8
65 57 1 4 5 .14 .6 5 4 36.8 8 65 65 9 64 0
65 3 7 .7 3 3

LAWN
7 .1 7 .2
65.1 2
5 47 65 .4 .2 65
.2 65 65
3
64
2 7 .16
5 4 3 2 1 .0 3
65
2
65
65 65 4 .0 65
64 667
1 .0 7 .0 .8 2
652 .6 64 447
WATERLINE

F
6 .77 .165
7 65 65
4 0 LANDSCAPING 0 0 .7 2 .34 68
48 8 .2
7..7.7 AERIAL UTILITY LINES
4 9 .2 7 0

CP 16
2 .0 .1 1 . .2 6

LAWN
64
7022
7 7 8
SIGNALE

BITUMINOUS
277
65 65 65 65 .4 64 664464
7 .165 7 4 65 65 7 864.0 88.2.37
.0
64
47 5
5 .2 65 65 .2 3 .8 3 77.9 91.8 2
.2 4 3 .6 0 .1 9
8
86
.3 9 3 65
2 64
65 64
7647.
65
65 55 5 9 65 .5 2 65 9 9 6 .9
65 .0 .0 .5 .0
U

65 4 .9 6565 3 1 65
6 0
977
6 .6 .7 4 2 65 363.9 .8 4 65 4 1 .4 4 7 644 8
1 65 5 .7 6655 5
3 5.73 65
3
65 2 .0 .2 2 8 .2684 64
8
4 6 .7 3 6
AERIAL UTILITY LINES
78.5
65
65 65 65 6 .6 56 6569 5 .5.5
00 6 3 .6 .3 4 64 64 .36 2 .2 8

BUSSTOP
.2 5 .3 8 3 8 8 .64 8 5 .1 2
6 .6 4 5 .2 .5

WATERLINE
6 .7
0
65665.8
0. 64
4 30 65 6 64 1 .5 64

ELEC
6 .568.86 6
5 635 65 8 .1
64

W
635.3
75 64 6464 8 8648.
6 51 6 6 .4 6 .6 6 .6 65 6565 3 6655 CONCRETE 6 64 9 4 67 .0
.4 9 1 3 5 3 6.2 65 665 4 9 .4 9 .0.9
9 64
U

00.3 .4 1
4 7.
2 3 .3 .3 5 11
.3 65 6
077
65 84 7 65 6 65 65 1 .8 .1 .36
7 64 1 64 6 8 .8 .9
2 5 55 2

WATER
.2 4 9
U

65

ELEC
3 .1655 .9 0
933
CONCRETE .2 .2 8
65 1 .8 6
9.
65 6 .16 6555.5 7 8 .3 8 .6 64 694.0
6 .1 65 65 6 8 1 33 .3 7 65 69 64 89.5
E

.3 561 65
688
7 6 .1 656 .3 5 5.9 .4 5 4 65 173 65 65 650 .2 64 4.49 4 694.3 3
.0 65 65 6 BITUMINOUS

ELEC
.42 65 635.0
6 640 2 80.8
MDOT

6 6 2 65 63 9 65
6
1 .8 9 .0.4 2
65

E
.365 6 .15 9 65 5 .2 3 2 .94 2 .6 3 .0 655 11 .0 9.1.78 0 2
65 25 35 .6 1 4 655 2 655 1 .86655 655 0 .6.0 7
46 2 7 1 64

E
.8 4 65 4 .9 65 .6 8 2 .5 1 .2 511 1 .2 3 9
1.
5 .9 1 65 7 3 .5 52
9 .2.211 7 .3
3 65
5 .4
8 .3 65 .1 06 21 0
9
4 .9 9 2 .0
5 .6 65 1 65
3 8
4 5 .4 .9
3 9

2.5’ CURB & GUTTER

0
HEIGHT=21.4’
LOWEST WIRE

10
312+00

Feet
311+00
310+00
309+00

1 inch = 40 feet
20
DIVISION AVENUE
AER IAL UTILIT

64
67
47
. .5
U

599
Y LINES

2.5’ CURB & GUTTER 64


8 .8 64
6
64 1 648
UNDER

65 64 9 .0
65 6 66554 9 64 64 8.4.563464 8
8 64
65 65 655615 605 00 .8 9 9 .2 7
64 68 .6 2 .7 .8 7
65 65 652 .2 65 .619 1 .9

AERIAL UTILITY LINES


65 .3.3758 .9 4
4 653 6653 .165 2 .37 1 .6 1.41.7.81 8 .6 4 8364 8 8 0 8
.1 4.9
65533 .54 3 .2
9
1 .0.1 2 0 .4
4 .7 .8
7 3.5.54 2 65 6501 35 7 6 3 5
65 65645.4645.985
.0 65 .453 6 64
CONSTRUCTION

656 65 02 2 .0 .8 64
50 65 8
45 55 4 .4 65 1 9 6 0 CONCRETE
64 6644 648 .6 .1
65 . 32 64
8 .4
F

65 .855.2 65 .227 36.4 65 65 BITUMINOUS65.5 8 6565 9 88.8.8 8 .74 7


66 4
5 .7
E

U
565 5 8 5 7 LAWN 65 5 6 656655 2 .2 2 .0 655 1 .2 0 .6
00.3.3
0 66 4
64 8 .3 4 7 67
6 5. 65 3 65 1 .3 5 043 8 .1 2

E
5 .0 65 .3 3 65 .2 65 .8 65 36.3 6553365 CONCRETE 2 .3
22.3 4 7 2 .44 7.
6 .4

ELEC
654 .4 2
2 .9 4 3

BUSSTOP
03
6655 655.5 03 5 .3 3 655 3 .5 9 .4.43 .4 9.384
5 .4 65 .15 1 6464 7 164
4 .58 24 6
41
55.3 5 6.2 2 5 .3 0 5.1 6
.33 6
0 5 6 7 64
7
7 .7.8 7 .3
64 .6 09 640
656 64 6466464 64
CONCRETE 65 64 9 .3 7 9 64 7664.64
5 .4
5 .5 65 0 9 .8
8 .9 846884.8
8 .8
.8
1 1 .5 9 6 .88 4 2
96 .9 8
7 .2 737.1.1
45
4 65 65 .7 65 0 9 1
65 3 2 65 2 0
4 9459 7.8 5
65
65 652.6 64
665 65 5 4 .6 .5 .82675 9 2 .8 .0 .463 64
7
5 55 5 .2 9 65 .1 3 4 4
9 8 .4
.7
.7 0 .5 4 4 65
4 2..8 2 2 .3 .5 2
65 65 6 8 9 .1 .9 2 9 664464 6

U
65 1 65 2 664.7.7 .5
89965 64
5 .6 .1 5 .2 3 .0 2 .9 64 6 622.8 1
7 2 9 7 1 674.7 .6

TELE
64 5 64 4
9 .6
7 .57 64 6 .5
8 2 6 .3 1
65 5 64
65 64
6 6 .5
64 6 .3
.5 7 .1 64 6 .2 64
3 5 6
6644 7
65 BITUMINOUS 8 6 .2 9 .0 55.864
6 .3 3 7 .70 5
64 8 .5
65 65 6 64
6 7
66.056 .5 .2
9.
69.82 PARKING 64 64 7
4 6 6
23
.7 .4 64
65 4 8 64
4 .2 65 65 5 654.4
8 3 2 64 64 .9 5 78.7
.2 .4 65
6 6 0 0
9 1 .1 6644

SIGN
7 .5 .2 64 6 8
TS

66 8 9 .0 66.0.0
65 5566 64 6 9 73 64
6 .3 .8.8
44 65 9 .95 065 64 4 .9
465 6 65 5 .5
65
4
65 65 65 65 65 65 65 65
.8 6 6 .2 3 3 3 2 2 1 1 0
2.408.3
1
64 5 .4 2
64 64
8 .1 0 .7 .3 .0 .6 .1 .7 .3 .9 9 3
5 3 8 0 7 8 7 7 4 .0
3
5645. 654
65 64 .8
0 6
U

.2
U

.6 64
855 5..7788
65 65 2 5
665 6 4 .8
.56 .6 4
3.6 5
0
LAWN

65
0 .9 64 646
64
3 64 6 .4
54.75 64
9 5 4.4 6 5 .3 4 .4
9 8

HEIGHT=21.1’
.0
1 64
5
64
.3

LOWEST WIRE
4 .9
8 6

65 65 64
4 1 65 65 65 65
1
64
6 5 .2
.3 .4 1 .8 1 .2 1 .1 .1 .2 2
1 7 0 7 7 65 5 8
1 .1
0 64
6655 65 9 .3 64
44.5.5 1 .9 5 4
45 5 65 65 64 .8 8664464
0 .7 16.2 4 .5 44.5.54 .0
DOORWAY

DOORWAY

DOORWAY
DOORWAY

2 5 12 64 64 9 35 0
65 65 .4 9 6 .0
1 1 0 .1 9
64
.8 6 4 .6
1 65 65.2 6 64 9 64
DOORWAY

65 0 .7 1 .5 4 .4 4
1 .9 2 9 .3
7 8 6
64
5
AERIAL UTILITY LINES

.4 6
2 44
CONCRETE

65 .3
1 6 64
.7 3 .6
9 0
BUILDING
OVERHANG
F.F. ELEV.=652.01
DOORWAY
F.F. ELEV.=651.98

F.F. ELEV.=653.91
DOORWAY

DOORWAY
F.F. ELEV.=653.39

#2800
DOORWAY

F.F. ELEV.=653.89
1 STORY

DOORWAY
"BELTLINE BAR"
FRAME BUILDING

Sheet

16 of 21
Survey
Silver Line BRT
6767
667 67 7
67 7 .8
7 88 8
.4 7 .4 0
.5 96 .3 6 67 .8 35
27 7 .5
8 .3
4 1
67
67 67 7
8 .4 8 .2 676 .5 2
3 9 77.87
97.3 9

TRAF SIG
50 6 6 67
78 78 78 8 .1
.4 .4 67.3
0 83
3 67 67 2

E
.2 8 .28 .0
1
67 1 26677
8 .2 667 77.8.8
6 777

GAS
67 67 .6.5 28
7 .8 7 .8 24 6
6767 7 67 677 8
69 0 7 .2 .7 7 .7.1 6
6677 7 7 6 67 8 .1
6777 .5 02 666777788 7 .6 6 3
7.9.8.4 5
39 6 6767 7 77.5.0.03 67 9
5 677 7 .8 6
67 7 .4.8
.534
4 7
.8
7 .2 3 07 0
36th Street Station NB

677 7 .767
2 7 .1 6 7
7.
5 .1 3
13

CONCRETE

19.0’ HIGH
BRICK TEXTURED

TRAFFIC ARM
262+00

TRAFFIC LIGHT ARM


261+00

BOTTOM STOP
260+00

(18.5’ MINIMUM CLEARANCE)


259+00

LOWEST WIRE
BOTTOM

HEIGHT=S 21.0 FEET


LIGHT
69
5 .7

STOP
2

BOTTOM
LIGHT
69
5 .6 DIVISION AVENUE
3
CONCRETE

9’ HIGH +/-
GLASS

STOP LIGHT
BUS STOP

PI 259+18.513
69

CONCRETE
5
METAL WALKWAY

.4
3 67
6

BRICK TEXTURED
OVER DIVISION AVENUE

8 .0 67
67 67 8 67 8 66777 7 .9
67 8
67 6 678 .1 8 .1
.5 3
88.3.3 2
67 67 8 .0 8 .07 8 678 .51 7 36
67 7 7 .9 .0 67 6 8 4.5 4
.9 6 4 9 8 78 8 .57 67
8
7 .7 .2
67 67 67 67
67 6 67 7 67 0
6677 7 5 677 8 .0 1 .6 2 67 67 2 67.7 9
8
67 67 7 7 7 .5 7 .9
.9 6 8 .0 2 687.6 8 .6 8 .4 8 .9
.4 7 2
7 .2
7.
67 677 .1 677 .1 .1 4
0
67 CONCRETE 67 7 .7 2 67 4 67 67 8 6 68 2 .6 3
8 67 7 8
E

67 67 7 .6 2 7 .73
67 7 .5 7 .6 3 678 .1 .7 8 .7 6.6 2 7 8 7 8 .7
28 67 67
7.2.34 .5 39 67 3 7 7 6767.5 67 7 7 67 8 .66 9 67 67 671 67 .7 0 1
67 7 7.1.25 676 6767 .8 8.4 9 73 7 6 8 8 .7
6677 8 .8 8 .767
7 .5 9 7 .9 7 .8 67 7 .5.5 4 7 .6 .9 .7 7 6878.7.7 678 8
2
7 .9
8 .0 6 9 67 9

0
67 7
BUS STOP
2 67 88 67 7 .7 5 869.876 6 86.7 67 9 .7 9
24

67 7 .1 BITUMINOUS 67 67 687.2
67 7 .8 67 8 .1 0 80.87 8 748 8 .8
7 2.5’ CONCRETE CURB & GUTTER 8 8 .83

E
67 67 7.3.56
6 3 .8 5 67 67 6 .1 67 67 8 .2 1 3.8 6 .8 8 5 BITUMINOUS
7 .167 .7 0 67 6 8 .1 7 .7 67 77 8 8 .7 5 67 6 67
8 4 7 .9 .8 667 67 8 .2 8 9
74 7 0 7 .9 67 79
.1

BUS STOP
67 67 678 .0 67 0 6 6 8 .7 9 .1
7
677 88.1.2 67 0 8 .9 3
CP 12

7 7 67 .7 7 67 8 .10 677 8 8 .6 80 8 8 8 4

TRAFFIC SIGNALTS E
.767 67
67 .2 2.6 8 7 .7 8 .0 4 67 68 67 8 .6.0
7 7 .9
67 .3 0
67 7 .8
67 1 687.1 4 8 1
GAS

67 7 7.6 31 67 667 7 BRICK 87.1 3 .4


7 .8 .9 8 .0 3
7.
7 .2 .4 9 8

GAS
67

CP 11
4 1 7 CONCRETE

WATER
67 4
90 67 67 67 67
67 7 7.1 4 8 8 67 9 9

10
.2 .5 CONCRETE 67 8 .0 .1

GAS
7 .1 .2 4 8 .9 3
6 3 67 7

Feet
1 3 67 .7 31
67 67 8
8 .6 3
67 67 67
8 8 .4 7
7 6677 67 8 .2 .2 6
6 .27 .3 4
.4 9
8
6767777 63 1 77.8.8 .1 4
67 8 .0
7 .0 .5.5 6 7 7 12 67 8 8 .1 1
.0 3 67

38 OAK
3 9 .7 5 9 9 .4
6

1 inch = 40 feet
67 67
6767 8 9

20
36 OAK
.4 67 67
7 .5
7 .0 67 6
67 8’ HIGH CHAIN LINK FENCE 9 .3 9
18 8 67 9 .1 8 .8
67 .4 8 LAWN .0 1 LAWN 4
67 8 6 .7 6
7 .8 .2 8
4
0 67
6767 9 .7
7 .07 0
67 2.5 6 67
7 .5 6 67 8
2
67 67 7 8 .3 8 .6
.667
68
7 .8 8 .4 2 8 .7
6 0

CONCRETE
67 67
6 8
674
.9 68 .7
78 1 67
67 2 . .1 6
1 7
67 9 .3
7 .4 9

U
11 8 67
8 .3 9 .1 8
2 .1 0
67 4
7 .3
8

67
9 .8

36TH STREET
5

TRAFFIC
CONTROL BOX
68 68
1 1 .9
.3 2
6 68
1 .2
5
DOOR

68
1 .3
7

Sheet
68
0 .6
7

16 of 21
Survey
Silver Line BRT
36th Street Station SB

1 STORY
BRICK BUILDING

ELEV.:679.05’
ELEV.:678.76’

ELEV.:679.04’
FINISHED FLOOR
FINISHED FLOOR

OVERHANG

ELEV.:678.78’

FINISHED FLOOR
OVERHANG

0
FINISHED FLOOR
STEPS

10
67 6 67
7

Feet
677 7 .8
67 67 6677 67 8
67 7 .4 0
6786 8 88 .5
8678.
67 67 .7 .4 .3 6 67 .8 53
967 . 2967
8
67 6677 8 .7.7 8 6677 .7 3 67
9 .0 67 8 67 7 .5
756
67 67 8.7 88.7.7 8 88 8 8 .3
1
67
05 67 .7 4
74 .784 6
667 8 0 .6 7 .7 7 4
67
9. 9 .0 66 6767
7 778 6677 8 .4 .7 8 89 8 .6 68
67 .7.733 67 .7 9
8
.4 .4.1 88 4 7798 7 .9
87 .9 92 8 .6

OVERHANG
.0.3 0 67 8 67 3 7 8.7
BITUMINOUS 04
5 67 .2 67 .7 0

METER
64 .2.9 .72 7 67
04 67 05 67 8 .7 8 .7 7
7 .8 01 2 0 8 .7 67 67

OVERHANG
67 67 9 .0 8 3 1 67
8

STEP
67

1 inch = 40 feet
67

STEP
STEP
67 .3 6 0 .2 676 .5 2
7 7 .4 86.1
5 8 .6 8 8 .5 8 .4

OVERHANG
0 67 67
.3 3 7 82 67
6
67 .7 67 7 3 9 77.87
5 .7 8 .2 8 .8 67 7 .9 8 7 79.3 9

20
67 .7 CONCRETE

OVERHANG
.2 7 8 .5
8
TRAF SIG

.0 7 4 4 6767
6677 9 8 .2 9
.6 4 6 67
87.1.7 0 0

STEP
67 0 67 8 7 8

STEP
67 77.9
.3.9 33 CONCRETE 8 .4 .4 6 .3 8 .1

STEP
7 .3 .2 9808 AERIAL UTILITY LINE 67
67 8 67 3 0 7 83 67 67 2

STEP
687 6767
E

7 5 .5 .2

STEP
.0 67 8 .3 8 .28
80.4
0 .8 6 9 678 .28 .3 1

BUS STOP
69 8 678 .5 1.0 26677
E
67 7 .86 2 7 67
4 93
67
.5 67 67 67 8 .4 677 8 .3 8 .09 67 6 8 .2 667 77.8.8
14

3 7 8 7 .8 0 7 .8 5 67 7 7 .8
687 67 7 8
6
777
.8 .6.5 28
7677.
GAS

.9

WATER
6677 .1 3 67 6 0 7 .7 7 .8.3
0 67 67
67 6 867
7
8 .0
9 3
24
3.3FT DIA U

67 7 .8 7 .8 7 .8
6788 .0 0
966 6767 7
7 .1 67 7.0.547 7 .9 3 69 0
4 7 .7 0 67 67 7 .2 .7
67 .9 67 4 2 7 8 66677 7 7 .5 02
7 67 9 67
.9 .2 7777 5
.2 7
7 .4 7 .8 6
67666778 8 .9.8.4 6
9
67
.7 6767 5 0
7 78.2.2 395
2 677 7 .8 6
6677 7 .8 6677 7 .7.73312
67
7.8 7 .2 3
7. 7 .3 4 67 677 7 6
7
.34 67 7
677 .6.6
2 .7
67 79 7 .6 7 .687 67 7 .1 6
44BITUMINOUS
67 67 .8 6 67 8 5
67 7 .3 7
.7
67 3 67 7 .0
67 7 .3 7 7 .4 67 0 7 .6 7 .6 .6 2
677
6
67 2 7 .8 3 6 1
6 7.6.26 67 9 7 .7 2
67
67 6 .7
67 6 6677
6 .97 6 77.3.3
677 7
.5
7 .0 1
67
7 .1
7
7 .4
5
1 CONCRETE WATER
6 .6 6 5.8 2 22 1 2
3

BRICK TEXTURED

LOWEST WIRE
HEIGHT=N 12.3 FEET
CONCRETE
CONCRETE

19.0’ HIGH
BRICK TEXTURED

TRAFFIC ARM
TRAFFIC LIGHT ARM

CONCRETE
BOTTOM STOP

(18.5’ MINIMUM CLEARANCE)

259+00
LOWEST WIRE
BOTTOM

258+00
HEIGHT=S 21.0 FEET

257+00

LOWEST WIRE
LIGHT

HEIGHT=S 12.3 FEET


256+00
69
5 .7
STOP

2
BOTTOM
LIGHT

69
5 .6
3
STOP LIGHT

PI 259+18.513

DIVISION AVENUE 69
CONCRETE

5 .4
3
BRICK TEXTURED

67
67 67
67 7.
67 677 .1 7 .2
67 677 .2 7 .6 2 8
67
28 667777.1.737.14 67 67
67 67 67 7 7.1.25 7 .346 .5 39 67 3 7 7
7 7 .6 67 7 6767 .8 8.4 9
67 .5 4
7 .5 9 .9
7 .8 8 .0
7 1 67 7 2 67 2 7 .9
88
67 .1 6767 .1
6 3 7 .8 67
.7 7 .3
E

67 67 7 .56 3 7 .8
9 7 .167 .7 60 67 6
747 0
67 67 678 .0
7 7 67 .7 7 67 8 .10
TRAFFIC SIGNALTS E

6677 .2 2.6 8 7 .7 67 8 .0 4 67
77
67 67 67 7.6.631 67 667 7 67 1
7 7 .8 .9
7. 8 .0
BRICK687.187.1
.7 67 7 .2 .4
CP 11

1 7 4 9 4 1 90 7 8
67 67.1 67 67
8 .2
GAS

7 .17 .24
1 43 6
67 6 67 67 67
77 67 678 8 .2 .2
8 .4
6 .27 .3 7 .8 67 8.0.14 4 89
67 67777 63 1 21 67 8 .1 1
7 .0 .5.5 67 7
3
9 .7 8 .0 3
5 9

67
6767 8 .4
7 .07 .5 67 6
18 67 8 .4
67 8 6
7 .8 .2
0 4
6767
7 .07
67 2.5 6 67
7 .5 6 67 8
2
67 67 7 8 8 .6
.667
68
7 .8 8 .4 .3 2 8 .7
4 6 0
CONCRETE

67 67
6 8
67
.9 .7
2 8678. 1
67 .1 6
1 7
U

7 .4 11 8
8 .3
2
67
7 .3
8
36TH STREET
TRAFFIC

Sheet
CONTROL BOX

18 of 21
NG
1 .0
0
1 .0
0

Survey
67
9 .9
8

Silver Line BRT


44th Street Station
LOWEST WIRE=23.0’

LOWEST WIRE=20.5’

68 68

LOWEST WIRE=22.5’
1 .2 1 .1 68
7 8 1 .8
68 6 5
68 8 1

LOWEST WIRE=20.4’
68 681 .1 68 1 .3 .3 8
0 LAWN 1 .3 1
68 .8 0 .90
3
1 5 6 68

SL-44.39
.0 68
1 1 .2
68
1 .1 6
BITUMINOUS 68
68 1 .1
68 4 6868 68 1 .2
1 68 1 0 .5 9
.3 1 .4 6688 1 .9.5 2 1 .5 0
7
3 3 68 68 3 1
68 686811.7.8
68 1 1 .3 618.3 68
68 1 .3 3 1 1 .3
11.3.498
68
68 1 .2 1 2.3
7 88 1
1 .2 1 2 .4 LAWN 68 68
.1 6 6 1
68 1 .0
7 68 6
68
1 .4 61 7
668 68 5

PLANTER
PLANTER
68 811.1 1 .2 1 .2 86861811 .4 81
.
CONCRETE
68 1 .13 2 0 .5 6
.2
68 681.0 7 6688 1 .3.33.232
68 1 1 7
E

522
1 .0 61 .6
1 .7 668 8 0
SA

68
12IN

81 3
1 .1 3 23
801 .6
.1 6 68 68 .9.0 0
..009 68
3 9 1 .4 0 1
00

PLANTER
PLANTER
68 .8

SA
1 .1 8 2 .3
68 7 7
1 .1 68 68
2 68 68 1 .0 68 1 .0
LAWN
1 1 6 0 2 68

F
.1 .1 68
6 1 3 .9 68 68 0 68 1 .4
.7

BOXBOX
BOXBOX
68 7 68 68
0 0 1 5
68 8 0 1 0 .6 1 .5
.8 BITUMINOUS .2 .6
0 .6 68 .5 8 9 2

8IN
68 0 .4 6 68 2 9 68 4 0 .5

8"
0 .4 1 68 06.9
688 0 .5
4 68 68 680 68 6

2IN
68 68 0 .8 0.8 050 68 8 0 .6
68 .5.427
680 .9 0 .3 1 68.414 0 .6 8
0680.
0 68 4 .1 0 .5
0 .5
1
68 .551 9 2.0’ CURB
188
0 .3 1

SQUARE
0 .5
0 6
& GUTTER
2.0’ CURB
& GUTTER

0
205+00
204+00
203+00
202+00

10

Feet

1 inch = 40 feet
ELECTRIC (AERIAL)

20
DIVISION AVENUE
BITUMINOUS
2.0’ CURB
2.0’ CURB & GUTTER
& GUTTER
68 68
68 68 1 1
68 68 1 1 68.2 1 .2 68
68 68
0 .9 068.9 68 68 .0 5 6 .0 681 9 1
68
68 68 680 .8 6 68 68 66 0 688 1 .09 .3 1 .3
68 0 608.8 3 68 8 08.80 .8 68 68 05.9 68 .9 1 .0 68 1 .5 3
1.2.61 6 68 3
2
68
68 0 .80 68 688 0 0 .8
68 0 0 0 .6 68 .7 2 68
0
680 .7 68 1 .0 9 0 1 .5 5
68 0 .6 .5 68 6 68 68 0 .71 68 0 0 .9
.8686 57
0 .9 58 1 .28 1 .3 867 0 0 .9 1
2
1 .3
GAS

0 2 68 9 68 0 680 1 .1 7 .7 68 0 .8
2 9 668 18 0 .9 3 7 1 .1 6 62
0.
.7 6 68 .860 0
0 .568 0 0 .4 680 1.6.02 6 8 0 .9 3 1 0 .81 .3
6 68 7 6688 1 .3
9 680 .78 0 .6 18 0.4 3 3
.8
43 0.4.8
0 8
.3 .9 3
1 68 811685
688 0 .6 0 68 4 68 2 6868 3
1
1 .6 .8.7 1

SQUARE
1 .17 .7 5 6 0 68
6
SL-44.40

68 .2
1 .0 2
3 0
680 1 .4 0 .91 6868
2 1 .8
42 .4
4
9 68 688 0 .7 0.6 0 1.3 0 1 .30 68
1 0 .8 9
68 LAWN 68 1 2
.3 .8 5 68 .787 1 .1 68 8.9 9 1 .8
5 68 4 68 0 .9
8 68 .7 LAWN 2 68
1 .0 1 .4 0 68 68 68 66188.31 6688 618.4 9 1
9 1
68 1 CONCRETE CONCRETE .7
5 1 .3 0 .913.2 11.3.3 1 .17 6868 1 1
2IN

.0 .2 0 9.1 66 91 5 1 .7.6
8 6 6866 68 68 68
GAS

68 68 LAWN 5 76 68 1 1 1 .7
1 .2 1 .4 CONCRETE 6688 6 188.3
11.3 81 68 1 .8 .9 2
5 3 68 8 1 1.398 .6 1 .6 3 3 68
LAWN 68 61186.78.8 .3 68 68 68 8 .5 7 1 .7
6 68 681 .4 6686 6
1 8 9 1
6 68 1
113.391.3.4 8 1 .1 1 .21
.4
688 118.3
6 68 68 6868 8 1 .8
1 .4 1 .43 8691 3 684.3 1 .4.4 .24 71 .2
6
68 6 668
GAS

688618.9
1 .4 7 2 4 5 1 .48 18 11 68 68 68 68
GAS

68 .3
1 .3 1 .51 .4 8 81 1 .671 68
1
1 .41831 .5
8 17 2 .4 .4 .5.4 68CONCRETE 2 2 1
.4 2.4 5 0 8 2 9 66889 4 45 68 1 .7 1 .0 68 .0 8 68 1 .7 .7 6
05 5 68 68 686688 6868 11.9.8 1 .7 2 .8 2 68 6
68 668 6 1 1 .71 2 2 .2 2 .0 168
E

68 1 CONCRETE 1 .5 1 .4
88 .3 50 1 0 3 1 .9 1 .8 8
1 .5 1 8 618.2618.6.8 68 2 7
68 68 6 6868 .5 1
66181.2.41 .3 1 .49618921 9 4 68 2 .1 68
68
CONCRETE 668868 1 9
81171 3 2 .0 2
1 1.4
6811.4 .3 1 .468 1 1 .41 .4 2.8 7.4 8 0 .1
.5 5
8 1.4
2 .92 5 6 68 .5.841 3 8
01 3 1 .8.4950
0 68 618.7
687 6 68 68
1 .4 1 1 .8
17.2
68 8 2 68 .8 4
1 .8
4 6868
68 9 1 .5 .0 6 1 2 3 1 .4
1 .5 68 8 .6
1 .8
1 9 0 4
9 .7 6868
LAWN
7 5 2 .11 .6 6868
00 1 .72 .1
BITUMINOUS 58
LAWN 68
2
LAWN BITUMINOUS .1
4
68
1
CONCRETE

LOWEST WIRE=27.7’

1 .0
1 .0 0
0

68
1 .6
7

Sheet

19 of 21
BUILD
Survey
Silver Line BRT
67
2 .1
8
54th Street Station

67
2 .0 67
4 2 67
67 .3 2 .2
67
2 1 2 .1
6767
.0 5 2 .11
4 5 4.6 6

6767
67 67 67 2 .21 .7
2 2 .2 2 77
.4 9 .4
0 2
67 67 67
2 .1 2 2
2 .4 .3
4 6
67
2 .0 67
4 2
67 67 .5
2 .2
67
2 2 67
.6
1.
1 7 2 67
2
67 67 .4 .4
3
98
2 .0 67 2 .6 3
8 2 3

7
.3
7 67
3
67
67 .0 2 .5
2 .2 3 0
8 6677
67
3 .8
22.6.5
67 67 7 32 676
4

TEXTURED
3 .4 67 27.5

8 CONCRETE
67 .1 5
2 .0
0

WATER
2 2 2 .6 2
.9 67 67 8
9 2

TRAFFIC SIG
67 .9 67 2
2 2 2 .8 .6 7 67
.6 3
0 67
3
67
.0 6 6
2
LAWN 67 .2 LAWN 0 72 .9

E
2 7 6677 .7 0
.3
8
967 6

LOWEST WIRE
33.7.7

POST
77 67 2 .6 7 2
.6
3 7

POST
.6 3

CONNECTION AT 19.0’
4 67

8IN ELM
TSTAKE
67

8IN ELM

8IN ELM
1

8IN ELM
2 .3
.9 BRUSH 67
1
6 3 .0

WIRE HEIGHT WEST


67
0 627
67 67 67 .3
2 .24
67 67 3 2 67
67 67 2 3 .0 6677 69.9 2 2 .8 66 2 .3 3
67 67 2 2 .9 .0 1 22.9.9 4
67 67 67
2 2 .6 .8 .8 6 0 88
4 .3 5 7722
2 2 .4 0 8 4

GAS
.7.7 1
2 .1 .2 .3 4 4 67 1
5 5 5 67
2 .9
2 .8
67 67 3 7
67 CONCRETE SIDEWALK 67 67 2 2 .8 67
6677 67 6677 2 2 2 .8
67 67 2 22 .5 .5 .7 .7 8 9 67 672
1 2 22.2.2 .3 8 2 5 3 2.7.24

GAS
.4 1
.9 .0 67 0 9 67 .0 8

OVERHEAD ANCHOR WIRE


3 7 CONCRETE 2
67
2
67
2 2
67 67 .6 .7 .7
1
67 67 2 6 1 8
.8 BITUMINOUS 2 .0 2 .0 69 .2 LAWN 6
AERIAL UTILITY LINE 5 1 9 1 67 67 6 67 67 677 2
6657.9 67 67 6677 672 2 .5
6 67 711 5 1 67 1 .8 6722.0.1 6677 2 2 .57 2 .5 2 .1
9
2 .1 7
.2
BOTTOM TRAFFIC LIGHT

6677 1 677 1 1 .867 6.8.773 .6 7 67 1 .7


7 1 .797
1 .7 1.4.93 2 .0 8 6 7
.6
1 .1 1 .3.8 3 5 1 .4 19.5 1 .6 3 7 51 8
65 4 6 2 1

69
1 .2
2.5’ CONCRETE CURB & GUTTER 8
TRAFFIC SIGNAL
ARM HEIGHT=19.0’

139+00 140+00

0
137+00 138+00

10

Feet

1 inch = 40 feet
20
DIVISION AVENUE
BITUMINOUS

OVERHEAD
GUY WIRE
2.5’ CONCRETE CURB & GUTTER
67 67 67 6677
67 66 67 672 .0 672
61 677 17 1 617 2.2.776 67 22.6.3
6 71 67 66771 .6 .7.6 24 2 .51 67 7 3 86 6
. .0 671 .2 6767 1
1 .4
67 .8 67 4 .0
677 1 .0 088 1 .60 .11
22 .4 672 .1 0 6 2 .5.3 5 3 36.0 672 2 .9 1 67 677 2
12 .1 72
671 .4 0 67 .9 11 67 2 .656 6 2 .7 4 3 2 .6.2 8
67
1 .99 8 2 .2 2 5 5 .7
67 .2 9
0 67 1 67 .7 8 1 67 8 67 6
3 67 2
2 3
2.
2 2 .8 .7 3 .2 .3 .3 66767 2
.1 2 6
67 LAWN 3 0 8
5 2 67 6 7 26 .3
W

40

ANCHOR WEST
67 LAWN
.9 3 .3 3 .3 67 7 2 2 .7 .77 2 4
67 2 8
1 LAWN 69 3 67 2 .9 .9 3 67 32.4 2
.9 67 5 67 3 4 2
7 2 .2 67 .2
TRAFFIC SIGNAL E

.5 8 67 676 67 3 .2 1 67 .7 6
5 2 66667777 672 .9 6677 733 2 .6 67 67
67 67 .7 9 23.9.2 .1.2 3 .0 6 4
67 6677 2
2 2 .6 2222.9.9 2 .71
46 01 8 2 .4 2 .3
1 .0 .2 .7.763 9
GAS

1 .8 2 22 6 9
TRAFFIC SIGNAL

.6 4
ARM HEIGHT=18.8’

92
WATER

3
TRAFFIC SIGNAL

6 67 67 67
67
67
66377 67 6 67 7 3 .1
67
3 3 2 .967 3 667 67 26.56
.1
67 67 .122 2 .9 7 3
CONCRETE SIDEWALK 673.0 67 3 .4 2 67 .1 6 7 .17 3 2
7 277 2
67 2 67 2 7.8.8 6 .2 6 3 9 .7 .3
ELEC

.3 67 2 .7 34 .6 67 4 3 .5 676 22
1 .0 2 67
9 67 67 4 67
5 3 6
73 .2.1 9 .8 7
8
.7 67 .4 2 .6 3 3 .1 5
3 3 .6 .5 37.33
6 2
0 67 9 2 .1 2 .4 8 1
.4 2 3 67 3.3 167 3
CP 6

7 .6 3 67
6 67 67 67
3 .3 .2 2
67 67 3 .7 3 3 6 4 67 .8 1
67 4 .0 .3 3 .2
2
67 673 .9 2 1 .3 5 67 7 3
.7 3 .1
67 67 3 .8
5 67 9 67
3 .97 4 .2 4 .0 7
67 LAWN 2 67 3 2 5 LAWN 4
3 .9 3 .6 67 676677 2
.5 8 .7 3
2 9
67
3 .1 2 .6.1
672 .6
52 .8 2 .60 18

2/6 CA
67 1 2
67 4 67 67

2/6 CA
67
3 .5
67 .3 4 .3 4 .8 67 2 .6
67
3 7 4 .0 8 5 1 4 LAWN
.2 9 .4 67 9
7 9 3
SIGN

8 MAP

67 67 .7 67
4 4 .1 2 3
.0 0 .0
0 67
3
67 9 6767 2
.0 4 .5 67 2 .6.1
4 8 4 26
.4
7
HEIGHT=29.0’

67
67 3 67
LOWEST WIRE

4 .3 67 3

HEIGHT W=22.1’

SIGN
.0 1 3 .1

LOWEST WIRE
7 .5 3
5
POST IND VALVE

67
ELEC

67
3
1.
.2
6
90 67 6 676
676 2 .7 7 2 27 2

CP 5 5
37.22 4 .6.59.04 5
4.8 7
54TH STREET

Sheet

20 of 21
.=670.34 CL DOOR

1 STORY
FRAME BUILDING
67

DOOR CL 6X7
0.

"BMW MOTORCYCLES"
67 67
0
31
.3 0 .2
4 8

CP 4 2
67 67

Survey
0 .0 0 .0
67 5 0
67 0
0 .5
67 .5 4 66
9 0 .4
67 67 9 .9
8 1067.9 4
.211 .9
73.9 7
8

POST

Silver Line BRT


67 6677
10 10.9 66 66
.9 .14
3 9 9
.3 78
5 .5 .4
66 4 8
66
9 9 .6 66
.7 0 9
0 .3
3 66
9 .2
2
66
9 .5
66
66 8 .2
9 7
67 .5 8
0 BITUMINOUS 4
.0
60th Street Station

66

HEIGHT=E 21.2’
1 9
66
67 .4 .3 9 66

LOWEST WIRE
0 3 7 9 .4
.2 3

WATER
BITUMINOUS 9 66 66 66
8 .8
67 66 67 9 .5 9 .5 66 9
0 9 .4 66 0 .4 4 9 9
66
9
.2 4 9 4 .3 .4 66
8 .6 9 8 9 .5
9 4
66
67 9 .4
0 .1 66 1
3 9

6IN
67 .8
0 2 66

SIGN
.1 67 8 .7
8 5
66
9
LAWN 670 .367 LAWN

BUILDING OVERHANG
.4 66 0 .10 0 .1 66 66

SIGN
66 66 1 6 7 9
67 67 9 9

DRIVE ENTRANCE
DRIVE ENTRANCE
67 0 0 9 .8 9 .6 .7 .3 66
0 .1 .1 .7 6
66
9 1 0 8 .8
.1 8 3 1 5 67 67
.5
3 0 0 7
WIRE HEIGHT 19.8’

.3 67 8
.5 2 0 66
67 3 .0 9
66
66 67 0 .0 2 .8
9 0
LAWN 1 66 0
.9 .0 9
9.
.6

WIRE HEIGHT
2 8 97 0 66 69
66 9 2
9

F
.4 .5 .7
66
8 2 1
9 6
6 66 66 66.4 5 66 66 6666 666 9 6666 6 6666 666 6666 9
66
66 9
6666696
66.69
66 AERIAL UTILITY LINE
666 9 696 9 .19 669 696.1 99.4.5 9 .7
9 .5 66 66 6 6
9 .8

4X4
9 .29 .3699.5

WATER
9 .5.5 366 99.1.2 666 9 .2 69 69 9 6 6
8 .8.3 4 .48 3.0
1.9 2
9.1.06 9 9.1 82
5 9 .0 61
9 .4.9 .4 9 8 .30 0 69 6
6 3 6 3 9
9 .1 1 4 6 .198 20 5 6 . .3 6
8 344 69.5.308.589.97 9.97 667 0 .0
9 .5 2 667 0 .0 LOWEST WIRE 19.8’

WATER
3 9 .6 8
0

66
69
69
. .9

AER
U
977

T WIR
103+00 104+00
101+00 102+00

E 14 .8
LOWES IA L UTILITY
’ @ RO
LINE
A D CL
DIVISION AVENUE
BITUMINOUS

6
66
69 676 9 .6

0
666
66 6 6 99. 0 .0 1
66 6666 66 66 66 66 66 66 66 66 7 0 .5.59 67 8
6 6 6 6 9 9 9 6 9 676 9 .6 .1 4 0
67
59 67
66 9 .3 667699.5 6 9 .4 6 9 .4 .5 66 9 .566 9 .5 666669 .6 96.67 697.60
0 0 .1
9669.6669
.1 666 9 .1 666 9 .1 666 9 .3
9 .8 9
6709 .5 7 0 6 9 .56 66 7 666696.5 6 646 4 6740 67
0
0 .1 2
.2 0 .4 4
9 .6 7 9 .7 8 0.0.4
.9010 .0 37 0 66 6 .6 5 66 9 .469.5.52 67 1 0.1 54.1 4 .2 6 67 9 66
0
106069.1.64 669 .8 1
0 8 09 4 .0 9 .5 66 9 .59 6.4 9 .5 .6 1 9 .6 9 69 67 .378 6 .6
67 2
0 66
69 6 66 7 9 .91 7 4 5 .6 7 5.6 0 .1
1
66 9 .6 9
.9 9 .9 67 5
6 67 9 .5 7 0
6 2 0 7 607.0 9 1 .4
5 9 0
67
0 67 0 .0 76 9 068.6 66 .1 5 .4 3
.0 .4 67 67 0 70 67 67 9 .5 8
9 6 0 .3 9 .6 0 0 .0 .1 4.3 0 .4 06.16 0
67 5 66 67 6 2 98.4
0 467 3
66 9 .4
67 .3 6 66 607 0 .4 3
67 67 0 3 66
9 3 .4 5
67
0
66
9 66 66
.6 9
0 .38 9

10
9. 67 6 9 .6 66
67 0 .2 0 3 67 67 .6 .4 9 .2 66 .2 9 .2
0 .1 67 0 0 0 .1 2 9 .6
2 4 9 6 .2 2

Feet
3 67 2 LAWN LAWN 1 66 .2 6
97
.0 0 0 .1 .1 67 5 3 BITUMINOUS 9 66 7
1 .0 .2 2 0 .7 9
5 0 .3 6

CP 3 3
2 67 66 0 .3
0

WIRE HEIGHT
4 66 6 9 66 2
.0 9 .9 .5 9 66
3 67
6 3 666 66 9 .9 66 9
USDT

67 0
66 666 .6 367 0 .3
0 66 .0 66 6 66 66 66 66 9 96 .0 6 99 .8 9 .5 6 669 .7 4 66
.2 9 .9 1 66 9 .2 66 66.2 1 .590.4
9 .2 2 .7 2 66 6 66 8
8 6666 9 .5 6669 96.46 9 .3
9 9 3 2 9 9 9 .20 .3
67 66 4 6666 9 9 .2 8 09 .2 .3 .3 .3 7 6
9 3

1 inch = 40 feet
67 66 660 .9
.5
99.5.4 9 .5.46 90.3 6
1 6 2 1 0 2 66
9 9.0.70 9 .5
82 09 9
660 .1 .7 0 6 .2
5

20
9 .72 66 3 66
8
9 6 66 66 66
9 9 66 .8
66 6
9 9 .1 9 1

WIRENORTH
CONCRETE SIDEWALK 66 6666 66 66 9 66 6 9 .1 .1 .0
6 9
9 6.29 .1 6 4 4 0
99.3.3 9 .0 .2 9
WIRE HEIGHT

66 66 66 .4 66 9 .2 .2 66
66
9 66
9
66 6 9 .4 66 6 76 6 9 6.2 1
3 5 3
1 6
9
68
9

HEIGHT
66 .6 .6 66 9 .5 9 .5 66 9 66 .6 69
.1 6
9 3 .5 9 .567 8
9
67 .4 686 66 6 9 .7
9 9 66 6 .4 7 .9
.7 66 665 6 9 .4 7 66 1 9 0 .0 .8 0 .1 6 98.57 9 .8 0 .9 8 .8 6 8 1 66 9
2 9 .7 9 .6 6 9 66 4 66 7 9 .4 1 7 2 5.1 9 2 7 0 .8 4 8 .8
9 .4
0 1 .7 9 9 .5 2 67 66
8 8
8 1 0 .9
.1 66
6
66 66 1 9 .3
66 9 .9 9 .6
66 66 66
66 9 AERIAL UTILITY LINE 4 8
9 .6 66
9 3 1 .9 9 .2 .7
5 9 .5 .6 66 LAWN 66 4 66 8 66 4
8 4 9 9 .8
66 8
66 .3 66 66 7
9 .4 66 9 .4 .9
67 9 0 9 9 6 66
67 0 .6 .6 .6 3 9 .6 663
9
0 .3 3 66 0 2 0 .2

SIGN
9 8 .9
.2 5 .5
66
8
66 66 5
0 66 66 9
SIGN

66 8
66 7 9 9 9 8 .8
.0 66 .4
.2 .2 .2 9 0
CP 4 4

9 .6 7 3 2 8 .4 9 66
2 4 66 8
66 66 8 .6 LAWN .8
699 9 4 8
.6.6 .6 66 66
35 6 66 66 9 .5 9 .0

PLANTER
9 .6 9 8 8
6 .5
8

66 66 66 66
69
9 9 9 9 .4
.8 .8 .9 .8 5
1 5 3 9

DOOR
DOOR

DOOR
HEIGHT=9.6’
HEIGHT=S 18.0’

HEIGHT=N 17.3’
BITUMINOUS
LOWEST WIRE

GUY ANCHOR

HEIGHT=W 19.6’
LOWEST WIRE

LOWEST WIRE
BITUMINOUS

"DW3" 1 STORY

BUILDING #5990
BRICK & FRAME
F.F.=669.89 CL DOOR

F.F.=669.93 CL DOOR

F.F.=669.85 CL DOOR

Sheet

21 of 21
 

 
Appendix F 
 
Design Program – Stations Report  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 
 
 
 
 
 
 
 
  
Final Task I Vision Report 
 
 
SILVER LINE BRT

DESIGN PROGRAM - STATIONS

Task 2.0

September 24, 2010

Prepared by:
Wilbur Smith Associates
Table of Contents
1.0 INTRODUCTION ...................................................................................................................... 1-1
2.0 STATION CAPACITY................................................................................................................... 2-1
2.1 Station Shelters ............................................................................................................. 2-1
2.1.1 Station Passenger Capacity .................................................................................. 2-1
2.1.2 Furnishings Inside the Station Shelter .................................................................. 2-1
2.1.3 Station Shelter Lighting ........................................................................................ 2-1
2.2 Station Platforms ........................................................................................................... 2-1
2.2.1 Furnishings and Utilities on the Station Platform.................................................. 2-1
2.2.2 Platform Surface .................................................................................................. 2-2
2.2.3 Platform Lighting ................................................................................................. 2-2
3.0 STATION BUILDING FEATURES .................................................................................................. 3-1
3.1 Safety and Security ........................................................................................................ 3-1
3.2 Weather Protection and Roof Drains ............................................................................. 3-1
3.3 Station Materials ........................................................................................................... 3-1
3.4 Structural Design ........................................................................................................... 3-1
4.0 OTHER DIMENSIONAL REQUIREMENTS .................................................................................... 4-1
4.1 Platform Height ............................................................................................................. 4-1
4.2 Horizontal Clearance ..................................................................................................... 4-1
4.3 Platform Slopes ............................................................................................................. 4-1
4.4 ADA Clearances ............................................................................................................. 4-1
4.5 Minimum Sidewalk Width.............................................................................................. 4-1

i
1.0 INTRODUCTION
The purpose of this technical paper is to identify the concept design program for the transit stations in
order to guide the visualization task of the project in developing concept level illustrations of the
stations. Following the visualization task, at the beginning of the design phase, Design Criteria for the
stations will be prepared by the Design Team to be used for final design.

This Design Program – Stations contains the following components:

• Station capacity
o Buildings
o Platforms
o Utilities
o Equipment included
o Amenities included
• Expectations for Weather Protection
• Dimensional Requirements

Introduction
1-1
2.0 STATION CAPACITY
2.1 Station Shelters
2.1.1 Station Passenger Capacity
• Coaches have a 40 seat capacity
• Inbound coaches will board passengers uniformly over the ten stations from 60th and
Division to Franklin Street; about four passengers per station. Use six passengers
(standing and seated) as the capacity for the typical station.
• Outbound coaches will board passengers uniformly over the 5 stations from Fulton
Street to Fountain Street; about eight passengers per station. Use 10 passengers
(standing and seated) as the capacity for these five outbound stations in the CBD.

2.1.2 Furnishings Inside the Station Shelter


• Two to three seats (one bench)
• One wheelchair space
• Ticket Vending Machine (assumed dimensions: 30” wide x 12” deep x 42” high with
30”x30” clear space in front for maintenance)
• Free standing Ticket Validator (assumed dimensions: 10” wide x 10” deep x 42” high)
• Free standing Emergency Telephone (Blue Light) with camera (assumed dimensions:
12” wide x 12” deep x 72” high)
• Wall mounted “Next Bus” Variable Message Sign with audio (assumed dimensions: 24”
wide x 8” deep x 16” high)
• Security cameras (one or two wall mounted in addition to the camera with the
emergency telephone)
• Signage
• Art (or something related to local context)
• Signage for the visual and hearing impaired customers

2.1.3 Station Shelter Lighting

Station shelters shall be lighted with an averaged maintained level of 10 fc.

2.2 Station Platforms


2.2.1 Furnishings and Utilities on the Station Platform
• Three seats (one bench)
• One trash receptacle
• Bike racks
• Cigarette disposal
• Kiosk for Route Maps and opportunities to post other information (assumed
dimensions 48” high x 36” wide x 24” deep with 36”x36” clear space in front and back
for maintenance.)
• Signage for the visual and hearing impaired customers

Station Capacity
2-1
• Art (or something related to local context)
• Free-standing NEMA electrical panel with GFI outlet (assumed dimensions 36” high x
24” wide x 12” deep with 48”x48” clear space in front for maintenance.)
• Tree Plantings may be included on the platform

2.2.2 Platform Surface

Hard impervious durable surface that allows for easy maintenance, snow removal and water drainage.
Examples include stamped concrete, scored concrete, pavers, etc.. Provide ADA tactile surface at the
curb.

2.2.3 Platform Lighting

Platforms shall be lighted with an average maintained level of 2 fc.

Station Capacity
2-2
3.0 STATION BUILDING FEATURES
3.1 Safety and Security
• Station buildings shall not provide locations to hide people or packages.
• Stations are not to be enclosed
• The interiors of stations buildings must be clearly visible from the outside.
• Maximize use of transparent materials where possible.
• All station buildings must be designed to eliminate conditions where a person could be
contained
• Measures to prevent loitering (signage, bench design, etc)

3.2 Weather Protection and Roof Drains


Station buildings shall have a roof and appropriate wind breaks. No heating is provided. Roof storm
water shall be collected and disposed per local requirements but shall not be discharged onto the
platform walking surface where it can freeze.

In most cases it is expected that the canopy will be about 25 feet long to cover both doors of a 40 foot
coach and set back 24” from the face of curb to protect the boarding passengers from rain. The 25 foot
length may be reduced if site constraints do not permit. If the roof extends over the bus, the clear height
of the roof is to be 14’-6” above the pavement.

3.3 Station Materials


Structures shall be made of materials that are durable and easy to clean such as glass, stainless steel,
ceramic or porcelain tile, and concrete.
Maximize inter-changeability of components to minimize attic stocks and ease in replacement of
damaged parts.
Maximize transparency.
Incorporate design elements or art that relate to the context of the neighborhood
Signage/branding of the Silver Line BRT

3.4 Structural Design


Stations shall meet all building code requirements for structural design except that the bottom of the
foundations shall be at approximately the same depth as the roadway pavement.

Incorporate large vertical feature at each location that allow stations to be visible up to 2 blocks away
Optimize the ability to manufacture the stations off-site.

Station Building Features


3-1
4.0 OTHER DIMENSIONAL REQUIREMENTS
4.1 Platform Height
The platforms shall be placed 14” above the pavement for BRT Vehicles and 10” above the pavement
where BRT will share stations with other local route stops. The BRT will share the platform with local
routes at the following stations:
• Michigan WB
• Ransom NB at Fulton
• Burton NB and SB
• 28th NB and SB
• 36th NB and SB
• 44th NB and SB

4.2 Horizontal Clearance


All elements of the station shall be placed not less than 24” from the face of curb. With prior approval
from the City, the horizontal clearance may be reduced to 18”. Where the platform is 10” high there
must be 96” clear perpendicular to the curb for the bus to deploy the ADA ramp.

4.3 Platform Slopes


All slopes of the platform will be designed and constructed to meet ADA requirements.

4.4 ADA Clearances


All clearances required by ADA shall be provided.

4.5 Minimum Sidewalk Width


The minimum sidewalk width behind the station building shall be 5’-0 clear.

Other Dimensional Requirements


4-1
 

 
Appendix G 
 
Roadway Program Report 

  
Final Task I Vision Report 
 
 
 
 
 
 
 
SILVER LINE BRT  
 
 
TECHNICAL MEMORANDUM 
 
Task 2.0 Roadway Program 
 
September 1, 2010 
 
 
 
Prepared by: 
Wilbur Smith Associates 
and 
URS Corporation 
 
 

Table of Contents 
 

TECHNICAL MEMORANDUM 
 
1.0 INTRODUCTION ............................................................................................................. 1‐1 
2.0 DESIGN SPEED ............................................................................................................... 2‐1 
3.0 DEDICATED BRT LANES .................................................................................................. 3‐1 
4.0 LANE WIDTH.................................................................................................................. 4‐1 
5.0 CROSS SECTION ............................................................................................................. 5‐1 
6.0 HORIZONTAL ALIGNMENT ............................................................................................. 6‐1 
7.0 ADA COMPLIANCE ......................................................................................................... 7‐1 
8.0 HORIZONTAL AND VERTICAL CLEARANCE....................................................................... 8‐1 
9.0 REFERENCES .................................................................................................................. 9‐1 
10.0 APPENDIX...................................................................................................................... 10‐1 
 

 
 
 
 
 
 
 
 
 

 
Table of Contents 

TECHNICAL MEMORANDUM 
 
1.0 INTRODUCTION 
 
The Silver Line Bus Rapid Transit (BRT) will provide a state of the art transit option for the greater 
Grand Rapids area.  The main route for the BRT includes the following roadways: 

• Grandville Avenue – Central Station to Monroe 
• Monroe Avenue – Weston to Michigan 
• Michigan Street – Monroe to Bostwick 
• Ransom Avenue – Crescent to Fulton 
• Logan Avenue – Jefferson to Division 
• Jefferson Avenue – Fulton to Logan 
• Wealthy Street – Jefferson to Division 
• Division Avenue – Wealthy to 60th 

In  preparation  for  the  roadway  design,  this  technical  paper  will  identify  the  concept  design 
program for the roadway improvements associated with the Silver Line BRT.  An initial review of 
the existing  roadways has been completed. Based on this review, initial design criteria  have  been 
identified for the proposed work.  It should be noted that, after station location and dedicated BRT 
lanes have been finalized, more detailed information will be included. 

As  discussed  in  the  environmental  assessment,  improvements  to  the  existing  roadways  will 
generally  be  spot  improvements  associated  with  the  proposed  stations.    This  will  include 
construction  of  concrete  pavement  with  new  curb  and  gutter  in  front  of  the  stations  to  minimize 
‘rutting’ from the stopping and starting of the proposed BRT.   In addition, auxiliary/turning lanes 
may be added at intermittent locations to accommodate the proposed BRT route. Finally, portions 
of the route may be cold milled (i.e. top layer of asphalt removed) and resurfaced with asphalt to 
improve overall ride quality. The cold milling depth will likely be 1.5 inches to 2 inches. This should 
be deep enough to remove existing surface deterioration and wheel rutting. 
 
In  coordination  with  the  layout  of  the  proposed  stations  and  dedicated  BRT  lanes,  the  pavement 
markings and signing will be modified along the corridor. The markings and signing will delineate 
lane assignments, parking, turn lanes, etc… 
 
Exact locations for concrete pavement and cold milling and resurfacing will be determined once the 
final station locations and dedicated BRT lane locations are set. 
 

 
Introduction 
1­1 
2.0 Design Speed 
 
The  design  speed  for  the  roadways  shall  be  typically  designed  at  five  miles‐per‐hour  over  the 
posted speed limit.  Posted speed may be used for portions of this project as this section of roadway 
is a non‐freeway and non‐NHS (National Highway System) route.  Existing posted speed limits and 
appropriate design speeds are shown in the following table. 
 
Table 2.1 Existing Posted Speed Limits and Design Speeds 
Roadway  Start  End   Speed  Limit  Design  Speed 
(mph)  (mph) 
Grandville Avenue  Central Station  Monroe Avenue  25  30 
Monroe Avenue  Weston  Michigan Street  25  30 
Michigan Street  Monroe Avenue  Bostwick Avenue  30  35 
Ransom Avenue  Crescent Street  Fulton Street  25  30 
Jefferson 
Logan Avenue  Division Avenue  25  30 
Avenue 
Jefferson Avenue  Fulton Street  Wealthy Street  25  30 
Jefferson 
Wealthy Street  Division Avenue  25  30 
Avenue 
Division Avenue  Wealthy Street  Alger Street  30  35 
Division Avenue  Alger Street  28  Street 
th 35  40 
Division Avenue  28th Street  54th Street  40  45 
Division Avenue  54th Street  60th Street  45  50 
 

 
Design Speed 
2­1 
3.0 Dedicated BRT Lanes 
 
In order to maximize efficiency of the Silver Line, dedicated BRT lanes will be provided wherever 
possible.  After  the  exact  locations  of  the  dedicated  BRT  lanes  are  determined,  a  summary  table 
identifying these areas will be listed. It is anticipated that dedicated BRT lanes will have an 11‐foot 
width. 

 
Dedicated BRT Lanes 
3­1 
 
4.0 Lane Widths 
 
The  existing  roadway  typically  has  11‐foot  to  12‐foot  wide  lanes.    However,  intermittent 
auxiliary/turning  lanes  appear  to  be  as  narrow  as  10‐foot.    Proposed  through  lane  widths  will 
typically be 11‐foot lanes as recommended in the AASHTO ‘Green Book’.  Auxiliary lanes will also be 
11‐feet  wide,  however,  10‐foot  lanes  will  be  considered  where  space  is  limited.  As  previously 
mentioned, the dedicated BRT Lane will be a minimum of 11‐feet. 

 
Lane Widths 
4­1 
5.0 Cross Sections 
 
The existing roadway cross section varies throughout the Silver Line BRT route.  Listed below is a 
general  summary  of  the  roadway  cross  section  by  street.  It  should  be  noted  that  the  number  of 
lanes column includes center left turn lanes. 
 
Table 5.1 Summary of Roadway Cross Sections 
Roadway  Start  End  Number of Lanes  Parking 
Grandville Avenue  Central Station  Monroe Avenue  2‐3  Yes 
Monroe Avenue  Weston  Michigan Street  5  None 
Michigan Street  Monroe Avenue  Bostwick Avenue  6  None 
Ransom Avenue  Crescent Street  Fulton Street  2  Yes 
Jefferson Avenue  Fulton Street  Wealthy Street  2‐3  Yes 
Jefferson 
Wealthy Street  Division Avenue  5  No 
Avenue 
Division Avenue  Wealthy Street  Alger Street  4  Yes 
Division Avenue  Alger Street  44th Street  5  No 
Division Avenue  44  Street 
th 56  Street 
th 4  Varies 
Division Avenue  56th Street  60th Street  5  No 
 

 
Cross Sections 
5­1 
6.0 Horizontal Alignment 
 
Since  the  roadway  will  not  be  reconstructed,  the  horizontal  alignment  will  not  be  modified.  
However, lane shifts may be required at certain locations to accommodate additional auxiliary/turn 
lanes.  Shown below is a table that shows distances required for a lane shift.  After the final layout of 
the  stations  and  dedicated  BRT  lanes  is  determined,  specific  locations  for  lanes  shifts  will  be 
identified. Please note that the table assumes an 11‐foot shift distance (equal to one lane). 
 
Table 6.1 Summary of Lane Shifts 
Design Speed  Shift Distance 
30  165 
35  225 
40  295 
45  495 
50  550 

 
Horizontal Alignment 
6­1 
 
7.0 ADA Compliance 
 
As mentioned in the Stations Design Program, all station areas will be ADA compliant. This will 
include upgrading sidewalk ramps within the station influence area that are not compliant. These 
modifications will include design of ADA compliant ramps with detectable warning strips. Each City 
within the project area does not have unique ADA standards, instead they follow the Americans 
with Disabilities Act Guidelines and the Michigan Department of Transportation Sidewalk 
Guidelines (see Appendix). 

 
ADA Compliance 
7­1 
8.0 Horizontal and Vertical Clearance 
 
Horizontal clearance shall meet minimum offset distance as identified in the AASHTO ‘Green Book’. 
For urban arterials, collectors and local streets, the offset to an obstruction can be as small as 18 
inches (1.5 feet) from the face of curb. However, the preferred minimum would be 24 inches (2 
feet). Where practical, additional offset distance should be provided. 
 
Vertical clearance shall meet minimum underclearance requirements identified in the Michigan 
Bridge Design Manual. For arterials, collectors and local roads, the minimum vertical clearance is 
14’‐6”. However, the preferred minimum would be 14’‐9”. This allows the 14’‐6” mimimum to be 
maintained if a 3 inch asphalt overlay takes place in the future. 
 

 
Horizontal and Vertical Clearance 
8­1 
9.0 References 
 
AASHTO ‐ A Policy on Geometric Design of Highways and Streets, 2004. 
 
Americans  with  Disabilities  Act  and  Architectural  Barriers  Act  Accessibility  Guidelines.  July  23, 
2004. 
 
Draft Public Rights‐of‐Way Accessibility Guidelines. November 23, 2005. 
 
Michigan Department of Transportation Standard Plans 
 
 
Michigan Department of Transportation Bridge Design Manual 

 
References 
9­1 
10.0 Appendix 
 
 
 
   
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 
Appendix 
10­1 
 

 
Appendix H 
 
Bus operations, Traffic Signals, and 
Communications Concept Report 

  
Final Task I Vision Report 
 
 
 
 
 
 
 

SILVER LINE BRT  
 
 
 

Bus Operations, Traffic Signals, and 
Communications Concept Report 
 

Tasks 5.1, 5.2, 5.4, 5.5 and 5.6 
Tasks 6.1 and 6.6 thru 6.10 
 
 

 
October 21, 2010 
 
 
 
Prepared by: 
Wilbur Smith Associates 
And  
Clifton, Weiss and Associates 
 
Table of Contents 
 

Bus Operations, Traffic Signals, and 
Communications Concept Report 
 
1.0  INTRODUCTION AND PURPOSE ................................................................................................. 1 
 
2.0  EXISTING CONDITIONS .............................................................................................................. 1 
 
2.1  Existing Bus Operations .................................................................................................. 1 
2.2  Existing Traffic Signals .................................................................................................... 2 
2.3  Existing Communications Infrastructure ......................................................................... 3 
 
3.0  COMMUNICATIONS SYSTEMS ................................................................................................... 3 
 
3.1  Introduction ................................................................................................................... 3 
3.2  Technology/ Topography ................................................................................................ 3 
3.3  Bandwidth ...................................................................................................................... 5 
3.4  Availability ..................................................................................................................... 5 
3.5  Scalability ....................................................................................................................... 6 
3.6  Quality of Service ........................................................................................................... 6 
3.7  Security .......................................................................................................................... 7 
3.8  Reliability and Maintainability ........................................................................................ 7 
3.9  Resilience, Survivability and Redundancy ....................................................................... 8 
3.10  Equipment Housing, Environmental Control and Electrical Power ................................... 8 
 
4.0  BRT FUNCTION REQUIREMENTS ................................................................................................ 9 
 
4.1  BRT Operations .............................................................................................................. 9 
  4.1.1  Introduction ....................................................................................................... 9 
  4.1.2  BRT Operations Overview .................................................................................. 9 
  4.1.3  Dedicated Lanes ................................................................................................. 9 
  4.1.4  Station Locations and Transit Signal Priority ..................................................... 10 
  4.1.5  Off‐Board Fare Collection ................................................................................. 10 
  4.1.6  “Next Bus” Display ........................................................................................... 10 
  4.1.7  3‐D VISSIM Simulations .................................................................................... 10 
4.2  Traffic Operations ......................................................................................................... 12 
4.2.1  Intersections To Have Transit Signal Priority ..................................................... 12 
4.2.2  Transit Signal Priority Functional Devices ......................................................... 12 
4.2.3  Detection System ............................................................................................. 13 
4.2.4  Signal Controller Interface Unit (SCIU) .............................................................. 15 
4.2.5  Remote Data Management System (RDMS) ..................................................... 15 
4.2.6  Traffic Signal Heads .......................................................................................... 15 
  
Bus Operations, Traffic Signals, and Communications Concept Report 
Page i 
 
4.3  Silver Line BRT Communications Requirements ............................................................ 16 
4.3.1  Communications Systems ................................................................................. 16 
4.3.2  Emergency Telephone ...................................................................................... 16 
4.3.3  CCTV ................................................................................................................ 16 
4.3.4  Connectivity ..................................................................................................... 16 
4.3.5  Bandwidth ....................................................................................................... 17 
4.4  Communications Options and Recommendations ......................................................... 18 
4.4.1  Technology / Topography ................................................................................. 18 
4.4.2  Bandwidth ....................................................................................................... 22 
4.4.3  Other Design Approach Items ........................................................................... 22 
 
5.0  ADDITIONAL INFRASTRUCTURE NEEDED TO PROVIDE BRT FUNCTIONS ................................... 23 
 
5.1  Operations ................................................................................................................... 23 
5.2  Traffic Signals ............................................................................................................... 23 
5.3  Communications .......................................................................................................... 24 
 
6.0  BRT OPERATIONS,TRAFFIC SIGNALS, AND COMMUNICATIONS COST ESTIMATE ...................... 24 
 
 
APPENDICES 
 
Appendix A  Meeting Minutes 
Appendix B  Existing Bus Routes 
Appendix C  Dedicated Lane Base Maps and Station Locations 
Appendix D  VISSIM Simulation CD 
Appendix E  Traffic Signal priority, Transit Operations, and Communications Cost Estimate

  
Bus Operations, Traffic Signals, and Communications Concept Report 
Page ii 
 
 

Bus Operations, Traffic Signals, and 
Communications Concept Report 
 
1.0 INTRODUCTION AND PURPOSE 
 
The  Silver  Line  Bus  Rapid  Transit  (BRT)  route,  as  defined  in  the  Environmental  Assessment  (EA) 
report  prepared  in  2010,  runs  through  three  cities;  Grand  Rapids,  Wyoming,  and  Kentwood  and 
includes 33 proposed Silver Line BRT stations along a 9.6 mile route.   
 
The  purpose  of  this  technical  paper  is  to  summarize  the  existing  bus,  traffic,  and  communication 
operations in the project area; summarize the Silver Line BRT operation, traffic and communication 
functions anticipated to be required for future operations; and identify the quantity and cost of new 
infrastructure and/or equipment needed to be included in the project to provide these functions. 
 
To  identify  existing  conditions  the  study  team  met  with  representatives  from  each  of  the  three 
cities, and the Interurban Transit Partnership (ITP) – The Rapid, to discuss, existing and proposed 
bus  operations,  existing  signal  operations,  and  communication  infrastructure.    The  meeting  notes 
are attached in Appendix A. 
 
 

2.0 EXISTING CONDITIONS 
 
2.1  Existing Bus Operations 
 
Several existing bus routes operate in the area of the proposed Silver Line BRT.  These routes will 
continue their current operations after the Silver Line is operational:  Route # 1 along Division from 
60th to Wealthy, Route #3 overlaps for a short section on Jefferson, Route #11 overlaps from The 
Rapid station downtown until the BRT route turns from Michigan onto Bostwick.  The existing bus 
routes  are  included  in  Appendix  B.  Other  bus  routes  have  minor  interaction  with  the  BRT  route 
such as route #4, #12, #13, #14, #15.   
 
 There are no dedicated lanes for buses on any existing routes located along the proposed 
Silver Line BRT route. 
 The current equipment and software is developed by AVL Technologies in Colorado and the 
stop annunciators are from McKenzie Corporation.  The current system appears to have 
some existing issues with the functioning of their Automatic Vehicle Locator (AVL) System.  
The reporting features are not yet meeting their expectations.    
 The “next bus” sign currently gives a scheduled time which is not linked to actual bus 
arrivals 
 Currently using Odyssey GFI Genfare fare boxes which have smart capabilities but have not 
been implemented or utilized.  They were installed in 2003 – 2004.   
  
Bus Operations, Traffic Signals, and Communications Concept Report 
Page 1 
 
 

 
It is anticipated that the AVL system shortcomings will be corrected to support BRT operations and 
provide real time bus information for variable message signs. 
 
2.2  Existing Traffic Signals 
 
An  assessment  was  made  in  determining  the  type  of  equipment  that  is  available  in  the  field  to 
provide  Transit  Signal  Priority  (TSP).    Existing  traffic  signal  information  for  the  28  signals  on  the 
proposed Silver Line BRT route was collected from each of the three cities within the project limits 
and is summarized in Table 2.1.  The information will be used to design the proposed BRT system 
to be compatible with existing systems.   
 
Based on information from engineering staff at the cities of Grand Rapids, Wyoming, and Kentwood, 
all intersections are equipped with Eagle EPAC signal controllers.  These controllers are capable of 
providing  TSP.    In  addition,  it  was  also  found  that  the  majority  of  the  signalized  intersections 
already have OpticomTM detection systems installed for Emergency Vehicle Preemption.  This same 
detection equipment can be used to detect transit vehicles to provide TSP.   The OpticomTM system 
will allow the BRT buses to have signal prioritization where applicable. 
 
 
 Table 2.1 Existing Traffic Signals  
SIGNAL CONTROLLER TYPE OPTICOM PRESENT
MAJOR ROUTE CROSS STREET MAKE
Market Fulton Eagle EPAC yes
Monroe Loius Eagle EPAC yes
Monroe Pearl Eagle EPAC yes
Monroe Lyon Eagle EPAC yes
Monroe Michigan Eagle EPAC yes
Michigan Ottawa Eagle EPAC yes
Michigan Ionia Eagle EPAC yes
Michigan Bostwick Eagle EPAC yes
Ransom Lyon Eagle EPAC no
Ransom Fountain Eagle EPAC no
Ransom Fulton Eagle EPAC no
Fulton Jefferson Eagle EPAC yes
Wealthy Division Eagle EPAC yes
Division Franklin Eagle EPAC yes
Division Deleware Eagle EPAC yes
Division Hall Eagle EPAC yes
Division Cottage Grove SE Eagle EPAC yes
Division Cottage Grove SW Eagle EPAC yes
Division Griggs Eagle EPAC yes
Division Burton Eagle EPAC yes
Division Alger Eagle EPAC yes
Division 28th Eagle EPAC yes
Division 32nd Eagle EPAC yes
Division 36th Eagle EPAC yes
Division 44th Eagle EPAC yes
Division 48th Eagle EPAC yes
Division 54th Eagle EPAC yes
Division 60th Eagle EPAC yes  
                                                
 
  
Bus Operations, Traffic Signals, and Communications Concept Report 
Page 2 
 
 

2.3  Existing Communications Infrastructure 
 
Existing fiber optic cable is available between Central Station and 28th Street.  There are plans for 
extending the fiber optic cable along Division south of 28th Street but that work is not anticipated 
until after the Silver Line BRT is intended to be operational. 
 
Leased facilities are available in the project area at a monthly lease cost of approximately $10,000 
per month. 
 
 

3.0 COMMUNICATIONS SYSTEMS 
 
3.1  Introduction 
 
It is difficult at times to draw the boundary between a communications system and its user systems 
or  clients.    As  an  example,  Internet  browser  software  on  a  computer  performs  critical 
communications  tasks,  but  would  be  considered  a  user  system  and  not  part  of  a  communications 
system.    The  term  Communications  System  will  be  used  herein  to  describe  the  basic 
communications  transmission  system  that  will  serve  the  proposed  Silver  Line  BRT.    The 
Communications System will host several sub‐networks that serve specific client systems. 
 
In  addition  to  the  client  systems  already  planned  for  the  proposed  Silver  Line  BRT,  likely  future 
uses and demand for communications can be anticipated by examining other transit agencies.  It is 
important  for  a  communications  system  to  be  equipped  to  respond  to  evolving  demands  for 
different  types  of  services.    Typical  types  and  quantities  of  services  demanded  have  grown 
dramatically in recent times and have moved from the fixed dedicated bandwidth of time division 
multiplex (TDM) to shared resources using network‐based technologies. 
 
To address the requirements of the Communications System there are several system attributes to 
be considered: 
 
 Technology / Topography 
 Bandwidth 
 Availability 
 Scalability 
 Quality of Service 
 Security 
 Reliability and Maintainability 
 Resilience, Survivability and Redundancy 
 Equipment Housing, Environmental Control and Electrical Power 
 
3.2  Technology / Topography 
 
The  backbone  is  the  portion  of  the  communications  network  that  carries  the  bulk  of  information.  
Ideally the backbone must extend over the entire territory and will serve all of the communications 
  
Bus Operations, Traffic Signals, and Communications Concept Report 
Page 3 
 
 

based applications.  Any application should be able to connect to any backbone node and be able to 
communicate  with  all  other  application  elements  connected  to  other  nodes  as  required.    The 
technology  used  to  form  the  backbone  as  well  as  the  topology,  or  shape  of  the  backbone  will 
determine many of the other attributes of the system.  Technology and topology are closely related 
in that certain technologies are designed to function in a certain type of topology.  Geography and 
other physical limitations of a system will determine the available topology choices. 
 
Fiber Optic:  In a fiber optic based backbone, fiber optic cable is installed over the entire length of 
the area served. At each location to be served, some or all of the fibers in the cable are terminated in 
a  distribution  panel.    With  fiber  optic  cable  comprising  the  physical  layer,  it  is  also  necessary  to 
provide  transmission  equipment  to  serve  applications  that  are  not  equipped  for  optical 
transmission.    The  two  main  technologies  provided  by  fiber‐based  transmission  equipment  are 
Synchronous Optical Network (SONET) and Ethernet.  Multi‐service platforms (MSPs) provide both 
technologies, supporting  both traditional  Time Division Multiplex (TDM) interconnections as well 
as Ethernet capabilities. 
 
Microwave:  There is considerable use of licensed and unlicensed microwave data communication 
technology on commuter rail and transit properties in the United States.  Line‐of‐sight is required 
between nodes.  This often requires the use of high towers. 
 
Leased Facilities:  There are multiple technologies available as leased services such as:  frame relay, 
Multi‐protocol Label Switching (MPLS), point‐to‐point TDM, and Digital Subscriber Line (DSL).  It is 
also  possible  to  lease  individual  voice  or  serial  data  circuits.    Leased  services  can  be  either 
conventional  hard‐wired  lease  lines,  or  wireless  leased  circuits.    Initial  capital  outlay  for  this 
alternative  is  relatively  low,  consisting  only  of  the  initial  installation  costs  for  the  service  and  the 
required  interface  equipment.    The  ongoing  maintenance  cost  varies  with  attributes  such  as 
bandwidth.    It  should  be  noted,  that  in  the  aftermath  of  both  September  11,  2001  and  Hurricane 
Katrina,  many  telecommunications  experts  concluded  that  mission  critical  applications,  in 
particular  applications  that  involve  public  safety,  should  not  rely  entirely  on  communications 
networks based on leased services.   
 
Wireless  Local  Area  Networking:    Wireless  Local  Area  Networks  (WLAN)  have  become 
commonplace since the ratification of the first IEEE 802.11 standard in 1996.  Now known as WiFi, 
this standard continues to improve as its popularity continues.  These networks permit un‐tethered 
access  to  the  Internet  and  corporate  files  in  support  of  data,  voice,  and  video  applications.    Their 
implementation  ranges  from  simple  residential  installations  to  complex  meshed  urban  and  even 
statewide networks.   
 
Wireless  Mesh:    This  approach  places  wireless  network  nodes  usually  mounted  on  poles  at  a 
distance of approximately seven‐tenths of a mile apart along the territory to be served.  Each node 
covers  an  area  with  WiFi  signal.    Each  Node  passes  information  on  to  its  neighbor,  relaying 
information  to  a  point  where  the  mesh  accesses  a  central  center  or  high‐speed  network.    This 
approach provides scalability since a new site can be added relatively easily at any time in nearly 
any  location.    The  overall  bandwidth  provided  is  the  lowest  of  the  alternatives  considered.    The 
alternative also requires user system interfaces to be WiFi.   
 
WiMAX:  WiMAX is a next generation technology that improves upon WiFi.  This new technology is a 
dual‐use  technology  that  supports  4th  generation  cellular  data  service  from  providers  such  as 

  
Bus Operations, Traffic Signals, and Communications Concept Report 
Page 4 
 
 

Clearwire and Sprint/Nextel as well as customer‐owned wireless networks that have much larger 
coverage areas than the localized coverage typically provided by a WiFi access point. 
 
Cellular Data Services:   The cellular  data services industry continues to  progress the performance 
levels  of  their  networks.    The  use  of  this  technology  is  considered  a  viable  alternative  to  building 
completely new wireless networks in support of wide‐area data or voice applications. 
 
Free  Space  Optics:    Free  Space  Optics  (FSO)  uses  light  propagating  in  free  space  to  transmit  data 
between two points.  FSO is often used in locations where physical connection is difficult, such as in 
cities where installing fiber optic cables is expensive or impossible.  FSO products range from 0.5 to 
2 kilometers in distance and from 25 Mbps to 1.25 Gbps in bandwidth capacity.  Advantages include 
fast installation times, no license requirements, high degree of security, and lower installation and 
maintenance  costs  than  that  of  a  fiber  based  system.    The  main  disadvantage  is  susceptibility  to 
weather conditions and physical obstructions.   
 
3.3  Bandwidth 
 
Bandwidth,  or  digital  data  rate  expressed  in  bits  per  second,  is  a  critical  requirement  of  a 
communications  system.    It  defines  the  size  or  capacity  of  the  system.    Application  bandwidth 
requirements  are  prime  considerations  in  network  planning.    Bandwidth  requirement  estimates 
and  forecasts  are  by  nature  complex.    In  a  time‐division  multiplexing  (TDM)  based  network  each 
user  component  is  assigned  a  dedicated  channel  with  an  assigned  bandwidth.    As  an  example,  a 
telephone is generally  assigned a  64  kbps channel.  This bandwidth is dedicated to the telephone 
whether or not the phone is in use.  In a packet‐based network environment, the packets containing 
the audio signal from the telephone are mixed or alternated with packets from other applications.  
Estimating  and  forecasting  the  bandwidth  requirements  of  a  communications  system  carrying 
packet‐based  traffic  generated  by  many  different  types  of  applications  is  more  complex.    The 
complexity increases with the disparity of the transported traffic.  Packet‐based networks are able 
to retransmit packets that are blocked, allowing the information to be transmitted, but introducing 
latency.    The  degree  of  latency  that  is  tolerable  is  dependent  upon  the  application,  introducing 
additional complexity in predicting required bandwidth. 
 
3.4  Availability 
 
One of the factors in bandwidth requirement calculations is the principle of system availability.  In a 
system  with  high  availability,  portions  of  the  network  will  not  be  denied  full  functionality  due  to 
other portions of the network with less bandwidth.  Access to the full system bandwidth is available 
wherever  necessary,  with  a  minimum  of  wiring  and/or  administrative  changes.    Generally  this 
quality requires a high‐bandwidth communications backbone.  As much of the system bandwidth as 
possible  is  available  for  use  by  applications.    Unnecessary  redundancy,  mirroring  or  carrying 
information other than that required for resilience is avoided. 
 
The  term  availability  is  often  used  in  another  sense,  i.e.  the  proportion  of  time  a  system  is  in  a 
functioning condition.  For purposes of clarity, the term availability will not be used in that sense in 
this report. 
 
 

  
Bus Operations, Traffic Signals, and Communications Concept Report 
Page 5 
 
 

3.5  Scalability 
 
A  sound  basis  for  meeting  the  needs  of  the  future  is  to  plan  an  architecture  that  is  scalable  and 
modular,  so  that  as  demands  increase,  new  building  blocks  can  be  added  to  accommodate  the 
increased needs.  Often, a scalable and modular system is more costly initially than a fixed system, 
requiring extra components that will permit future expansion, but will provide a positive return on 
investment  against  the  increased  initial  capital  costs  when  the  inevitable  demands  upon  the 
communications systems are made on an unpredictable schedule. 
 
The  communications  marketplace  will  respond  to  the  needs  of  the  large  carrier  and  telephone 
companies.    Therefore,  one  key  to  a  successful  strategy  is  to  keep  current  with  and  follow  the 
strategies  and  technological  trends  of  the  communications  marketplace,  and  in  particular,  the 
marketplace for large carriers and telephone companies. 
 
The architectures found in the marketplace are based upon meeting changing customer demands, 
leveraging capital investments and building networks that can evolve based upon scalable building 
blocks.    A  prime  example  is  the  manner  in  which  major  telephone  companies  have  evolved  their 
Synchronous  Optical  Network  (SONET)  plant.    The  carriers  have  found  that  their  customers 
demand the reliability associated with SONET standards regardless of the end service they need.  In 
particular,  customers  demand  the  50‐msec  automatic  protection  switching  and  the  resiliency 
associated with ring‐based networks.  These levels of reliability and resiliency are based upon well‐
defined  and  well‐known  industry  standards.    Newer  services  often  rely  on  the  SONET  layer  to 
overcome  their  shortcomings  in  reliability  and  resiliency.    Widely  deployed  and  well  understood, 
the use of SONET by major carriers will continue in the near term. 
 
Initially  deployed  as  TDM  architecture,  the  core  SONET  systems  deployed  by  the  telephone 
companies  have  evolved  to  support  cell  based  technologies  (ATM,  Frame  Relay,  IP  Ethernet)  and 
more  recently  to  Wave  Division  Multiplex  (WDM)  and  Multi‐protocol  Label  Switching  (MPLS).  
These technologies are built upon the foundations established in earlier years, but have continued 
to evolve using incremental building blocks to meet increased demand for newer services, in most 
cases by moving traffic from dedicated TDM services to IP based shared resources, such as Ethernet 
and MPLS. 
 
A scalable and flexible communications system is one where network capacity may be changed in 
response to changes in demand, without significant redesign or abandonment of existing resources.  
The network may be extended to serve new geographic locations by installing additional elements 
of the same type used in the existing network.  This requires standardization of system elements.   
 
3.6  Quality of Service 
 
Time‐division multiplexing (TDM) communications systems dedicate bandwidth for each circuit or 
channel allocated.  By doing so, maximum quality of service is delivered for every circuit.  The price 
that  is  paid  is  in  efficiency,  because  bandwidth  is  used  for  idle  circuits.    Packet‐based  systems 
deliver  a  higher  rate  of  efficiency  by  only  sending  packets  when  required,  however  there  may  be 
times  when  the  demand  for  bandwidth  exceeds  capacity,  delaying  packets  or  causing  them  to  be 
retransmitted or discarded. 
 

  
Bus Operations, Traffic Signals, and Communications Concept Report 
Page 6 
 
 

In  networking,  Quality  of  Service  (QoS)  refers  to  resource  reservation  control  mechanisms  rather 
than service quality.  The QoS mechanism provides different priority levels to guarantee a certain 
level of performance to an application.  This can be important to delay sensitive real‐time streaming 
multimedia applications such as Voice over IP (VoIP) and video.  QoS mechanisms are not required 
when there is no network congestion. 
 
Several network communications protocols provide QoS  mechanisms, including frame relay, ATM 
and MPLS.  QoS generally functions at higher Open System Interconnection (OSI) layers than those 
provided by a communications system, however it is important that physical and transport systems 
do not preclude the desired QoS mechanism. 
 
3.7  Security 
 
Many  applications  have  built  in  security  measures,  such  as  the  Payment  Card  Industry  (PCI) 
protocol  used  by  most  Ticket  Vending  Machine  (TVM)  Systems.    Once  the  critical  information  is 
encrypted,  it  may  be  transmitted  over  the  Internet  or  the  public  switched  telephone  network.  
Other  applications  rely  on  the  communications  transmission  system  being  secure.    There  is 
inherent degree of insecurity whenever wireless transport is used.  This may be mitigated through 
the use of encryption or other security measures. 
 
3.8  Reliability and Maintainability 
 
For  a  well  operating,  functional  system  that  is  meeting  needs,  age  alone  is  not  necessarily  a 
requirement  for  replacement  or  upgrade.    However  when  new  functions  are  required  that  the 
current  system  cannot  supply,  or  the  age  of  a  device  in  a  rapidly  changing  marketplace  results  in 
loss  of  support  and  replacement  parts  from  the  vendor  community,  then  consideration  must  be 
given to the risk of continuing with a system that does not meet needs or cannot be maintained. 
 
Applications have varying degrees  of tolerance to reliability.   A brief communications failure may 
have a small effect to a passenger information system, only delaying the arrival of new information.  
However,  a  brief  communications  failure  could  more  drastically  affect  safety  or  control 
applications.   
 
A state of good repair of the current systems is mandatory, irrespective of whether a system is kept 
in service as is, or migrated to a newer platform or system.  A state of good repair is not achieved 
only  by  performing  routine  maintenance  and  repair.    In  some  instances  it  requires  immediate 
replacement  of  aged  components.    In  other  cases,  maintaining  a  state  of  good  repair  requires 
periodic  updates  of  software,  often  on  a  quarterly  or  even  monthly  basis.    Manufacturers  of 
equipment typically will not support customers during routine or emergency diagnostics or repair 
unless the latest version of software has been deployed. 
 
Deployment  of  remote  diagnostics  to  complement  the  new  systems  will  enhance  current 
maintenance practices by reporting the precise nature of any technical issue before technicians are 
deployed.    Remote  diagnostics  and  improved  network  management  may  allow  re‐routing  of 
disrupted  services  to  alternate  channels  until  normal  business  hours,  thus  avoiding  unnecessary 
overtime costs. 
 

  
Bus Operations, Traffic Signals, and Communications Concept Report 
Page 7 
 
 

It  is  important  to  maintain  a  periodic  replacement  cycle  of  Communications  System  components 
that  acknowledges  limits  on  capital  budgets  and  service  life  expectations  for  current  systems 
deployed in phases over the years.  These cycles are based upon deployed systems in‐service dates 
and  geographies.    It  is  important  to  note  that  communications  systems,  and  for  that  matter  any 
microprocessor  or  software  based  system,  now  faces  accelerated  replacement  cycles  compared 
with older technologies, and it is highly probable that communications and signal systems may each 
exhibit significantly different replacement cycles based upon their respective technologies. 
 
3.9  Resilience, Survivability and Redundancy 
 
In a resilient communications system, as much of the network as possible will continue to function 
in  the  event  of  localized  events  or  failures,  such  as  cable  cuts  or  equipment  failures.    For  true 
resilience,  the  alternate  communications  paths  must  be  constantly  and  automatically  tested  to 
assure they are functioning and may be depended upon in the event of a failure. 
 
In  a  survivable  communications  system  the  network  is  able  to  maintain  or  restore  an  acceptable 
level  of  performance  after  a  catastrophic  network  failure  by  applying  various  preventative  and 
restoration techniques.  This requires having restoration plans in place and the resources available 
to implement the plans. 
 
Redundancy is closely tied to these requirements for resilience and survivability.  Having multiple 
communications paths that are constantly and automatically verified is necessary for the backbone 
system.    Traditionally,  network  infrastructures  have  been  designed  for  single  failure  redundancy.  
This, for instance, is the basis of a SONET ring infrastructure.  The ring provides two paths around a 
failure.   
 
3.10  Equipment Housing, Environmental Control and Electrical 
Power 
 
It is important to provide space and environmental controls for existing and future communications 
equipment.  For availability, resilience and survivability it is essential that each location type have a 
standardized electrical power treatment.  This includes lightning protection, surge protection and 
UPS or other means for providing power during a commercial power failure. 
 
 
 
 
 
 
 
 
 
 
 
 

  
Bus Operations, Traffic Signals, and Communications Concept Report 
Page 8 
 
 

4.0 BRT FUNCTION REQUIREMENTS 
 
4.1  BRT Operations 
 
4.1.1   Introduction 
 
The  proposed  Silver  Line  BRT  system  will  need  to  integrate  with  the  existing  Automatic  Vehicle 
Location (AVL) system and other systems currently utilized by ITP. 

The  following  represents  a  list  of  requirements  for  the  proposed  operating  system  that  should 
allow the riders of the BRT system to seamlessly transfer from the Silver Line BRT to other routes 
and operate seamlessly with the existing ITP systems. 
 
4.1.2  BRT Operations Overview 
 
Improved  operating  times  of  the  BRT  are  dependent  on  Dedicated  Lanes,  Station  Locations  and 
Transit Signal Priority (TSP), and Off‐Board Fare Collection.  Two other amenities to make the BRT 
a  first‐class  service  is  to  provide  passengers  with  a  “Next  Bus”  Display  and  Level  Boarding.    The 
“Next Bus” Display will be driven by information collected from ITP’s existing AVL system. 
 
The Level Boarding will set the platform 14 inches above the top of pavement.  This platform height 
will require that the vehicles are equipped with precision docking devices.   Platforms that provide 
service to both BRT and local buses will be set at 10 inches above the top of pavement.  
 
4.1.3   Dedicated Lanes 
 
 The BRT vehicles would run in the existing travel lanes closest to the curb in each direction 
with 10‐minute headways in peak hours and 15‐minute headways in off‐peak hours. During 
peak  hours,  portions  of  the  bus  travel  lanes  would  be  exclusively  for  transit  use.  Only 
right‐turn  general  traffic  at  intersections  or  the  various  driveways  along  Division  Avenue 
would  be  allowed  to  utilize  this  lane  in  the  immediate  area  of  their  turn.  Outside  of  peak 
hours, the transit vehicles would travel in mixed traffic.  See Appendix C for locations of the 
dedicated lanes along the BRT corridor. 
 The  following  locations  are  where  it  is  recommended  that  the  BRT  travel  lane  be  shared 
with northbound general through traffic to increase northbound throughput along Division 
Avenue. The travel lane restriction could be lifted a relatively short distance in advance of 
the  intersection,  and  then  put  back  in  place  a  short  distance  downstream  from  the 
intersection. 
o Burton Street and Division Avenue 
o 28th Street and Division Avenue 
o 36th Street and Division Avenue 
 The  following  locations  are  where  it  is  recommended  that  the  BRT  travel  lane  be  shared 
with  northbound  and  southbound  general  through  traffic  to  increase  throughput  along 
Division  Avenue.  The  travel  lane  restriction  could  be  lifted  a  relatively  short  distance  in 
advance  of  the  intersection,  and  then  be  put  back  in  place  a  short  distance  downstream 
from the intersection. 
o 44th Street and Division Avenue 
  
Bus Operations, Traffic Signals, and Communications Concept Report 
Page 9 
 
 

o 54th Street and Division Avenue 
 The BRT vehicle is allowed, traffic permitting, to leave the dedicated lane to pass local buses 
or vehicles making right turns. 
 
4.1.4   Station Locations and Transit Signal Priority 
 
The  benefit  of  TSP is dependent  on  the stations  being located on the  far  side of the intersections.   
Unfortunately, the EA located some stations where they cannot benefit from TSP.  As a result, some 
stations have been relocated and are shown in Appendix C. 
 
Other technical aspects of TSP are developed in Section 4.2 Traffic Operations of this report. 
 
4.1.5   Off­Board Fare Collection 
 
 Smart Card Readers are desirable but may be too expensive; however, the existing Odyssey 
GFI Genfare fare boxes have smart capabilities which has not been implemented or utilized 
to date. They were installed in 2003‐2004. 
 Ticket Vendor Machines ‐ Pre‐paid boarding is a desired attribute for the Silver Line BRT 
service as a feature to reduce dwell time at stations. 
 Random fare verification and the honor system currently used have been effective at 
safeguarding against fare payment avoidance.   It is expected they will be just as effective in 
the proposed BRT system.  
 
The consultant team will make a recommendation on the fare system and technology during final 
design.  The recommended system must be fully ADA compliant. 
 
4.1.6   “Next Bus” Display 
 
 The proposed “next bus” system should include audio for persons with disabilities. 
 User’s should be able to easily differentiate between the BRT system and the regular fixed 
route system. 
 BRT needs to be integrated into the existing AVL system to support the “Next Bus” display. 
 
4.1.7   3­D VISSIM Simulations 
 
Three intersections, as illustrated in Figures 4.1, 4.2 and 4.3, were selected to simulate the traffic 
operations: 
 
 Michigan and Bostwick (Transit turning , dedicated east bound transit, mixed use 
westbound) 
 Franklin and Division (Dedicated transit in both directions) 
 36th and Division (Dedicated southbound transit and mixed use north bound) 
 
The  simulation  includes  traffic  volumes  based  on  2035  projections  except  that  transit  and 
pedestrian traffic was significantly increased to visually confirm that these modes would not reduce 
the LOS. 
 
 
  
Bus Operations, Traffic Signals, and Communications Concept Report 
Page 10 
 
 

 
The simulation demonstrated that: 
 
 Pedestrians had adequate time to cross the street safely 
 Bus Operations did not adversely impact the intersection LOS 
 Mixed traffic turning movements were accommodated even with the dedicated transit lanes 
 
A CD of the AVI (movie clip) files is included as Appendix D. 
  

 
  Figure 4.1 Michigan and Bostwick 
 

 
  Figure 4.2 Franklin and Division 
  
Bus Operations, Traffic Signals, and Communications Concept Report 
Page 11 
 
 

 
  Figure 4.3   36th and Division 
 
 
4.2  Traffic Operations 
 
4.2.1   Intersections To Have Transit Signal Priority 
 
The  Silver  Line  Rapid  Transit  System  EA  document,  proposed  to  provide  Transit  Signal  Priority 
(TSP)  at  all  of  the  signalized  intersections  along  the  proposed  Silver  Line  BRT  route  except  the 
following: 
 
 Division Avenue and Burton Street 
 Division Avenue and 28th Street 
 Division Avenue and 44th Street 
 
4.2.2  Transit Signal Priority Functional Devices 
 
The  TSP  system  provides  specialized  treatment  of  transit  vehicles  at  signalized  intersections  and 
requires four basic functional devices: 
 
 A mechanism to communicate transit vehicle arrival to the signal controller (On‐Board 
Equipment), 
 A mechanism to detect the transit vehicle presence (Roadside Equipment), 
 A mechanism to communicate/execute the TSP logic to the controller (Signal Controller 
Interface Unit), and 
 A mechanism to monitor the TSP system performance (Remote Data management System). 
 
Figure 4.4 describes the basic functional components of the TSP system.  The On‐Board Equipment 
(OBE)  emits  a  signal  to  the  Road‐side  Equipment  (RSE).    The  RSE  detects  the  transit  vehicle  and 
  
Bus Operations, Traffic Signals, and Communications Concept Report 
Page 12 
 
 

transmits the information to a Signal Controller Interface Unit (SCUI).  The SCUI responds with the 
appropriate  signal  timing.      The  TSP  system  performance  is  monitored  by  Remote‐Data 
Management System (RDMS). 
 
 
 
 
 
  Transit
  Priority
 
 
  Confirmation
Device
  TA

 
 
 
  OBE RSE
 
 
 
 
  FD

 
 
  EV
 
Preëmption
 
SCIU
 
 
 
  Figure 4.4  Functional Components of TSP 
 
In  so  far  as  the  on‐board  and  roadside  equipment  must  be  compatible  these  are  generally 
purchased as a package Detection System from a single vendor. 
 
4.2.3  Detection System 
 
On­Board  Equipment  (OBE):    OBE  is  a  device  that  is  mounted  on  the  transit  vehicle  and  is 
continuously emitting the signal conveying the presence of the transit vehicle.  It is the intent of the 
ITP that TSP is required only for Silver Line BRT vehicles. 
 
Typically,  the  on‐board  equipment  is  mounted  on  the  roof  of  the  transit  vehicles  or  inside  the 
transit vehicle on the dashboard or the electronic number plate housing.   OpticomTM  emitters  are 
typically  mounted  on  the  roof  of  the  transit  vehicle  for  better  line‐of‐sight  to  communicate  with 
OpticomTM detectors at the signals.  The on‐board equipment derives power from the vehicle power 
source  and  can  be  automated  with  the  vehicle  ignition  process.    Activation  of  the  signal  can  be 

  
Bus Operations, Traffic Signals, and Communications Concept Report 
Page 13 
 
 

linked to the door opening or closing.  In the case of near‐side stops or when the transit vehicle is 
stopped and its doors are open; TSP request to the signal should be stopped. 
 
Road­side Equipment (RSE):  RSE is a device that can detect the signal emitted by the OBE; detecting 
the  presence  of  the  transit  vehicle.  In  some  TSP  technologies,  the  detectors  are  installed  in  the 
roadway pavement or on the curbside at an advanced distance from the intersection.  
 
The  existing  Detection  System  is  OpticomTM  equipment  mounted  on  the  signal  mast  arm  or  span 
wire  is  hardwired  to  the  SCIU  that  is  secured  within  the  local  signal  controller  cabinet  and  is 
currently being used for Emergency Vehicle Preemption.  The same equipment can be used for TSP 
for the proposed Silver Line BRT.  The RSE detects the presence of the transit vehicle and conveys 
the presence signal to the SCIU to execute the TSP logic.  
 
The choice of strategies, technology, and the existing hardware in the field determine or dictate the 
functional  requirements  for  TSP  system  components.      Given  the  presence  of  the  existing  3M 
OpticomTM  system  in  the  field,  it  is  recommended  to  utilize  existing  field  equipment  for  TSP 
purposes  and  add  necessary  components  to  the  Silver  Line  BRT  vehicles.      New  RSE’s  would  be 
provided at intersections that do not have existing OpticomTM equipment. 
 
The 3M OpticomTM components consist of an OBE that is an infrared strobe emitter, an RSE that is 
an infrared detector directionally mounted at intersections, and an interface to the signal controller. 
The emitter sends a cone of infrared and visible strobe light in the forward direction.   
                                                                                                                               
Within  the  strobe’s  flashing  pattern  and  frequency  is  a  coded  message  consisting  of  the  vehicle 
identification number.  At each intersection approach for which priority is desired, 3M OpticomTM 
detectors  are  mounted  facing  approaching  traffic.    Figure  4.5  shows  the  3M  OpticomTM  TSP 
system’s vehicle on‐board and intersection‐mounted components.  OpticomTM supports two or four 
channels, providing detection capability on two or four approaches respectively.  The detectors are 
connected  by  wire  to  the  OpticomTM  phase  selector  card  installed  in  the  signal  controller  cabinet.  
The  phase  selector  (and  card  rack  for  some  controllers)  provides  the  interface  between  the 
detectors and the preemption inputs of the signal controller.  This interface provides authentication 
and  authorization  of  priority  phases  using  predefined  logic  and  acts  through  standard  controller 
functions.  In  addition,  the  phase  selector  supports  user  classification  and  operating  priorities  for 
vehicle  types  overriding  other  vehicle  types.      The  3M  OpticomTM  system  is  able  to  communicate 
with both centralized and closed loop systems. 
 
 
 
 
 
 
 
 
 
 
 
 
 

   Figure 4.5  3M OpticomTM – Emitter and Detector  
Bus Operations, Traffic Signals, and Communications Concept Report 
Page 14 
 
 

4.2.4  Signal Controller Interface Unit (SCIU) 
 
The  SCIU  is  the  most  important  and  complex  component  of  any  TSP  system.  The  SCIU’s 
responsibility  is  to  ensure  that  the  detected  vehicle  is  authorized  to  get  TSP,  determine  if  the 
detected vehicle is a transit vehicle or an emergency vehicle, and execute the TSP logic to send the 
appropriate signal timing plans to the signal controller.  The SCIU is typically an interface card that 
communicates with the traffic signal controller at the local intersection level. Depending on the TSP 
strategy  selection,  the  SCIU  ensures  that  predefined  TSP  logic  is  deployed  seamlessly  and  the 
controller can return to the normal operations once the detected vehicle is served. 
 
The physical composition and the functional requirements of the SCIU are different and unique for 
each  type  of  controller  owing  to  the  controller  design  and  communications  requirements. 
Sometimes, the SCIU design can be extremely complicated to ensure the performance  of different 
types of  TSP strategies.  The SCIU functional requirements often provide  limitations on or dictate 
which TSP strategies can be deployed in the field.   However, based on the existing conditions data, 
all  intersections  along  the  proposed  Silver  Line  BRT  route  are  equipped  with  Eagle  EPAC  signal 
controllers.    These  controllers  are  capable  of  providing  TSP  and  can  communicate  with  the 
OpticomTM system.     
 
The Final EA document recommended Early Green and Green Extensions as part of the TSP.   This 
active  priority  strategy  can  give  an  early  green  signal  or  hold  a  green  signal  that  is  already  being 
displayed allowing free passage of the authorized vehicle. 
 
4.2.5  Remote Data Management System (RDMS) 
 
RDMS  is  a  data  management  system  that  enables  the  transit  as  well  as  traffic  engineers  and 
planners to monitor the performance of the TSP system. 
 
The  RDMS  system  can  be  a  single  location  system  or  a  web‐based  system  accessible  to  all  the 
stakeholders interested in monitoring the performance of the TSP system. 
 
Currently,  the  City  of  Grand  Rapids  has  the  central  control  system  and  uses  ACTRA®.    Except  for 
Division  Avenue  and  32nd  Street  intersection,  all  intersections  communicate  with  the  system.  
ACTRA® is capable of generating reports on TSP activations.  It can generate reports by intersection 
and by vehicle identification number (ID).  Each OpticomTM emitter which is mounted on the transit 
vehicles  would  have  a  unique  ID.    This  information  can  be  reviewed  by  city  traffic  staff  and  the 
Interurban Transit Partnership (ITP) to refine the Early Green and Green Extension times based on 
the delays to the general traffic and to BRT vehicles. 
 
4.2.6  Traffic Signal Heads 
 
It is anticipated to use all of the existing traffic signal heads.  If new traffic signal heads are required 
they will be the standard (red, amber, green) signal in a yellow enclosure.   In so far as the transit 
lanes  are  dedicated  only  during  peak  periods  it  is  not  appropriate  to  use  special  transit  signal 
heads. 
 
 
 

  
Bus Operations, Traffic Signals, and Communications Concept Report 
Page 15 
 
 

4.3  Silver Line BRT Communications Requirements 
 
4.3.1  Communication Systems 
 
To plan a communications system it is necessary to consider the requirements of the various user 
systems  or  clients,  both  those  currently  planned  and  those  that  may  be  added  in  the  future.    The 
following Communications System clients are planned for the proposed Silver Line BRT; now or in 
the future: 
 
 Emergency Telephone 
 Closed Circuit Television (CCTV) 
 Fare Validation 
 “Next Bus” Arrival Time Sign 
 Ticket Vending Machines 
 Smart Card Readers 
 Passenger Information Signs and Kiosk 
 
4.3.2  Emergency Telephone 
 
Emergency telephone service is planned for each platform at every station.  At this time the most 
likely  arrangement  for  the  emergency  phones  is  a  free  standing  stanchion.    Stanchions  clearly 
indicate the presence of an emergency phone to patrons through color, graphics and by displaying 
the standard blue light.   
 
4.3.3  CCTV 
 
Emergency  telephone  stanchions  also  provide  convenient  mounting  locations  for  CCTV  cameras.  
Two cameras are planned for each stanchion.  The first is a fixed camera that will capture the image 
of  an  emergency  phone  user.    The  second  is  a  pan‐tilt‐zoom  dome  camera  that  is  mounted  on  an 
extension pole above the stanchion.  This camera will provide surveillance capability of the entire 
platform area. 
 
4.3.4  Connectivity 
 
Each  of  the  user  applications  will  require  connectivity  to  a  central  facility.    Communications 
between  stations  will  be  minimal.    Table  4.1  depicts  the  expected  connectivity  requirement  for 
each of the applications. 
 
 
 
 
 
 
 
 
 
 

  
Bus Operations, Traffic Signals, and Communications Concept Report 
Page 16 
 
 

Table 4.1  Connectivity Requirements 
Application  Connectivity Requirement 
Emergency Telephone  PBX or VoIP Server
CCTV Viewing and Storage 
CCTV 
Facility 
Fare Validation  System Host via Public Network
“Next Bus” Arrival  System Host via Public Network
System Host via Public Network 
Ticket Vending  
or On‐Site Server 
System Host via Public Network 
Smart Card Readers  
or On‐Site Server 
System Host via Public Network 
Passenger Information  
or On‐Site Server 
  

 
It  is  assumed  that  each  of  these  central  facilities  will  be  located  at  the  Central  Station  location.  
However, the Communications System must be capable of providing connectivity to other locations 
if required. 
 
4.3.5  Bandwidth 
 
In approximating the bandwidth requirements for the Communications System a reasonable value 
for  each  application  at  each  location  has  been  estimated.    It  is  assumed  that  every  station  on  the 
Silver Line BRT will have the same user applications.  The bandwidths are then added to obtain a 
maximum value that would apply to all applications at all locations transmitting information.  The 
bandwidth needs for the planned and future applications are summarized in Table 4.2. 
 
Table 4.2  Approximate Bandwidth Requirements   
Application  Approximate Bandwidth   
Requirement   
 
Emergency Telephone  128 kbps
 
CCTV  25 Mbps
 
Fare Validation  128 kbps  
“Next Bus” Arrival  1.5 Mbps  
Ticket Vending   1.5 Mbps  
Smart Card Readers   1.5 Mbps  
Passenger Information   256 kbps  
Total  30 Mbps  
  
 
 
Note  that  CCTV  is  particularly  bandwidth  intensive.    The  bandwidth  required  at  each  station  for 
CCTV  depends  on  numerous  factors.    Key  factors  are  listed,  showing  the  assumptions  made  for  a 
Silver Line BRT station: 
 
 Number of Cameras –  Two for each of the 33 directional stations 
 Frames Per Second – 15 
 Type of Cameras – IP 
  
Bus Operations, Traffic Signals, and Communications Concept Report 
Page 17 
 
 

 Resolution – 640 x 480 
 Video Format – Mjpeg 
 Live Viewing – Yes 
 Recording Method – Network Storage at Central Location 
 
A key factor in the bandwidth stated for CCTV is the use of networked storage.  Networked storage 
eliminates  the  need  for  a  local  recorder  or  storage  device,  but  requires  a  large  amount  of 
bandwidth.  By recording locally, the Communications System bandwidth is reduced to that needed 
for live viewing. 
 
Bandwidth  requirements  for  all  other  applications  both  planned  and  future  are  significantly  less 
than  that  required  for  CCTV  using  network  storage.    For  this  reason,  future  expansion  of  CCTV 
coverage at stations must be identified early in the design in order to provide sufficient bandwidth.   
 
4.4  Communications Options and Recommendations 
 
4.4.1  Technology / Topography 
 
Of  the  physical  media  available  for  communications  transmission,  fiber  optic  cable  has  many 
advantages,  including  very  high  bandwidth  capabilities,  high  reliability,  and  intrinsic  security 
attributes.  The major disadvantage of fiber is the high cost of installation.  The City of Grand Rapids 
has indicated that existing fiber optic cable is available between Central Station and 28th Street.  The 
existence of fiber optic cable makes the choice of physical media simple for this area.  Some work 
will be required at each station to access the existing cable and extend fibers to the communications 
equipment at each platform. 
 
Installation of fiber optic cable is also planned along Division south of 28th Street; however, it will 
likely  be  three  to  five  years  or  longer  before  this  plan  is  implemented.    One  option  for  the  area 
between  28th  Street  and  60th  Street  is  to  install  fiber  optic  cable  as  part  of  the  Silver  Line  BRT 
Project.  Cost is a  major  consideration of this option.  Estimating the cost  of installing  aerial  fiber 
optic  cable  highly  depends  on  local  conditions.    The  cost  can  vary  from  $25,000  to  $100,000  per 
mile. 
 
Considering  the  other  options  for  this  area,  there  are  some  that  can  be  easily  eliminated.  
Microwave and Free Space Optics both require line‐of‐sight, and for that reason would most likely 
require towers that are difficult to site and are often disliked by neighbors.  Wireless Mesh would 
require a large number of node installations, and would provide inadequate bandwidth.  Wireless 
LANs  would  serve  a  station  area,  but  would  not  provide  the  connectivity  back  to  the  central 
location.  The remaining options are examined in more detail. 
 
WiMAX:    WiMAX  products  are  becoming  available,  such  as  the  RuggedMAX  line  of  products 
manufactured by Ruggedcom, Inc.  Base station units are mounted on utility poles and cover a much 
larger  area  than  WiFi  access  points.    FCC  licensing  is  required  to  deploy  these  wireless  devices; 
however, the licenses are generally easy to obtain and are inexpensive.  To cover the area from 28th 
Street to 60th Street, base station units would be installed on utility poles at the 28th Street Station 
area.    Bandwidth  is  an  important  consideration.    Effective  bandwidth  decreases  as  the  coverage 
distance increases.   
 
  
Bus Operations, Traffic Signals, and Communications Concept Report 
Page 18 
 
 

Leased Facilities:  The use of leased services is an attractive option for the area not equipped with 
fiber optic cable.  The prospect of fiber optic cable becoming available in the future also makes the 
use  of  lease  services  attractive,  since  it  eliminates  the  installation  of  infrastructure  that  will 
eventually  be  replaced.    In  particular,  Multi‐protocol  Label  Switching  (MPLS)  service  provides  a 
network  solution  that  readily  interfaces  other  IP‐based  networks  and  systems.    Service  Level 
Agreements are available with MPLS to assure a level of reliability.  The service is scalable, allowing 
selection  of  bandwidth  to  serve  only  the  current  equipment  and  allowing  changes  to  port 
bandwidths if additional equipment is installed in the future.  Bandwidths as high as 12 Mbps are 
available.  A disadvantage of MPLS is the relatively high recurring cost.  Monthly lease cost for MPLS 
service to the stations in this area is roughly approximated to be $10,000 per month.   
 
Each of these options remains viable and will be considered as the proposed Silver Line BRT design 
progresses.    However  MPLS  service  offers  distinct  advantages  in  terms  of  bandwidth,  scalability, 
reliability and security, and is considered to be the most likely option at this time.   
 
As  previously  stated,  communications  technology  has  moved  in  recent  years  from  the  fixed 
dedicated bandwidth of time‐division multiplexing (TDM) to shared resources using network‐based 
technologies.  Ethernet/IP has become nearly ubiquitous throughout the industry.  Devices such as 
telephones  and  video  cameras  have  evolved  into  Internet  Protocol  (IP)  devices.    Nearly  all  data 
based  systems,  such  as  Automatic  Vehicle  Location  and  Fleet  Management  Systems  require 
Ethernet/IP communications between elements.  Communications transmission equipment for the 
Silver Line BRT will provide Ethernet/IP service to each station.   
 
The topology of the system is a key factor in redundancy.  SONET based systems provide excellent 
self‐healing  redundancy  characteristics  when  deployed  in  a  ring  topology.    When  a  node  or  path 
ceases to function, the Synchronous Optical Network (SONET) automatically reroutes traffic around 
the failure using other nodes and connections, making the transition in less than 50 microseconds.  
The Division Avenue corridor does not lend itself to a ring topology, being essentially a straight line.  
A  SONET  system  could  still  be  deployed,  using  a  collapsed  ring,  i.e.  fibers  contained  in  the  same 
cable  sheath.    A  collapsed  ring  does  not  provide  the  same  degree  of  protection  that  a  spatially 
diverse  ring  does.    If  a  fiber  cable  is  cut,  it  is  likely  that  all  fibers  in  the  cable  will  be  severed  or 
damaged.    SONET  nodes  are  more  costly  than  routers.    The  additional  cost  plus  the  necessity  of 
using a collapsed ring make the use of SONET less appealing for the proposed Silver Line BRT. 
 
IP protocols such as Open Shortest Path First (OSPF) also provide protection against equipment and 
link failures.  OSPF quickly detects changes in the network topology, such as those caused by node 
or link failures, and changes the affected packet routing in a matter of seconds.  While not as fast as 
the protection provided by SONET, OSPF still provides a high degree of  protection when multiple 
paths are available. 
 
SONET  nodes  will  continue  to  be  considered  in  the  project  design,  but  it  is  expected  that 
environmentally  hardened,  Gigabit  Ethernet  layer  three  switches/routers  will  provide  the  best 
basis  for  the  Silver  Line  BRT  Communications  System.    Figure  4.6  depicts  a  typical  station  using 
this approach. 
 
 

  
Bus Operations, Traffic Signals, and Communications Concept Report 
Page 19 
 
 

 
 
  Figure 4.6 Typical Station Communications 
 
Using  this  approach,  all  user  applications  will  interface  the  Communications  System  via 
Ethernet/IP, including IP CCTV Cameras and VoIP Emergency Telephones. 
 
Figures 4.7 and 4.8 show two possible approaches to the network arrangement.  In Approach 1, 
depicted in Figure 4.7, each Switch/Router in the area served by fiber will have a dedicated pair of 
fibers  back  to  the  central  office.    This  maximizes  the  amount  of  bandwidth  available  to  each 
location.  Fiber connections are also provided to the next station.  The last station served by fiber, 
28th Street, will also be served by MPLS.  Using this arrangement, if the fiber optic cable is severed 
in  any  location,  each  Switch/Router  will  have  an  alternate  path  back  to  the  central  location.    The 
disadvantage to this arrangement is the number of fiber pairs required. 
 

  
Bus Operations, Traffic Signals, and Communications Concept Report 
Page 20 
 
 

 
 
Figure 4.7 Topology Approach 1 
 
 
Approach 2 depicted in Figure 4.8 requires fewer fiber pairs than Approach 1 by “daisy chaining” 
several  Switch/Routers.    The  price  paid  is  in  bandwidth,  with  the  daisy  chained  Switch/Routers 
sharing  the  Gigabit  bandwidth.    Approach  2  provides  alternate  paths  in  a  similar  manner  to 
Approach 1. 
 

 
 
Figure 4.8 Topology Approach 2 
  
Bus Operations, Traffic Signals, and Communications Concept Report 
Page 21 
 
 

4.4.2  Bandwidth 
 
As  previously  discussed,  each  station  will  require  approximately  30  Mbps  of  bandwidth  if 
networked  video  storage  is  used.    Approach  1  will  easily  meet  this  requirement  for  the  stations 
served  by  fiber,  with  the  full  Gigabit  Ethernet  bandwidth  available  to  each  Switch/Router.  
Approach 2 will also meet bandwidth needs in the fiber area, since no more than five stations are 
chained on any one pair of fibers, requiring a total of approximately 150 Mbps of the Gbps capacity. 
 
The area not served by fiber optic cable is a much different bandwidth scenario.  Due to the much 
more limited bandwidth capacity of leased facilities or any of the other non‐fiber options, it would 
be required that CCTV data be stored locally.  This requires a digital video recorder at each location 
and heating/cooling ability of the equipment housing.  Therefore, due to the bandwidth limitations, 
the  need  for  expensive  digital  recorders,  and  the  significant  recurring  leasing  costs  it  is 
recommended  to  provide  fiber  optic  for  the  full  length  of  the  project  as  described  in  Approach  2 
except that new aerial fiber is recommended south of 28th Street in lieu of leased (MPLS) fibers. 
 
4.4.3  Other Design Approach Items 
 
Availability:  To assure the greatest amount of availability, Approach 1 will be preferred. However, 
it  is  unlikely  that  as  many  as  34  fibers  will  be  available  to  be  dedicated  to  this  system.  The  daisy 
chaining  of  Approach  2  will  therefore  be  used  as  required  by  the  number  of  available  fiber  pairs.  
Availability will also be considered in the selection Switch/Routers. 
 
Scalability:    Scalability  is  achieved  by  planning  for  future  user  applications,  providing  spare 
bandwidth  capacity  and  Switch/Router  ports.    Future  applications  will  also  be  considered  in 
allocating space, environmental treatment and electrical power for equipment housings. 
 
Quality of Service:  The Switch/Routers chosen, as well as the MPLS service provided will support 
QoS.  This will be an important system feature since primary use of the system will be by VoIP and 
video. 
 
Security:  As previously discussed, a degree of security is inherent in fiber‐based communications 
systems.  The LAN/WAN network approach also lends itself to using modern security methods. 
 
Reliability and Maintainability:  Network management and remote diagnostics will be provided for 
the  Communications  System  as  well  as  the  Emergency  Telephone  and  CCTV  user  applications.  
Hardened  units  will  also  be  employed  to  the  greatest  extent  possible.    Maintenance  will  be 
considered in the arrangement of equipment in housings. 
 
Resilience,  Survivability  and  Redundancy:    This  subject  has  been  considered  and  discussed  in  the 
Technology/Topology  section.    The  Communications  System  will  be  arranged  to  provide  as  much 
resilience as possible while not driving up cost using approaches such as hot standby  equipment.  
UPS will be used to provide limited protection during commercial power failures. 
 
Equipment  Housing,  Environmental  Control  and  Electrical  Power:    Many  of  the  characteristics 
discussed  above  depend  upon  the  housings  and  environmental  controls  used  to  house  the 
equipment.  This will be a primary consideration during project design. 
 

  
Bus Operations, Traffic Signals, and Communications Concept Report 
Page 22 
 
 

5.0 ADDITIONAL INFRASTRUCTURE NEEDED 
TO PROVIDE BRT FUNCTIONS 
 
5.1  Operations 
 
Each Silver Line BRT Station will require a set of operating hardware devices:  
 
 “Next bus” signs with audio 
 Audio station announcements on the bus 
 Ticket Vending Machine 
 Emergency Telephone with CCTV camera 
 One additional CCTV camera 
 Fare Validation Device 
 Smart Card Reader 
 Passenger Information sign and Kiosk 
 
Each  of  the  systems  will  utilize  the  communications  infrastructure  and  will  tap  into  the  electrical 
supply constructed at each station. 
 
The ITP must make their current AVL System functional to support BRT operations. 
 
 
5.2  Traffic Signals 
 
Signal  Replacement/Modification:    Based  on  the  existing  infrastructure  capabilities  and  the 
requirements to implement TSP, there is no need to replace or significantly modify any signalized 
intersections. 
 
Transit Signal Priority (TSP) Equipment:  It is recommended that this project utilize the existing 3M 
OpticomTM  system  for  TSP  communication  at  signalized  intersections;  the  following  equipment  is 
required to deploy TSP using OpticomTM technology: 
 
 Signal Requirements (Per signalized intersection where not existing) 
o Confirmation Light Kit 
o Detector 
 Two Channel/Two direction, or 
 One Channel/ One Direction 
o Phase Selector (Four Channel) 
o Span Wire Clamp 
o Card Rack with P1 Harness Assembly 
 
 Bus Requirements (Per bus) 
o Emitter (Low Priority with Visible Light Filter) 

  
Bus Operations, Traffic Signals, and Communications Concept Report 
Page 23 
 
 

 Software Requirements (One cost for system wide ) 
o User configuration software with Communication Cable 
o 700 Series Emitter User Configuration software and Communication Cable 
 
5.3  Communications 
 
The  following  is  a  summary  of  the  infrastructure  needed  based  on  the  communications  systems 
options and recommendations.  
 
 Aerial Fiber on Division from 28th to 60th street 
 Approach 2 Switches and Routers 
 Switches and routers at each station pair 
 Equipment housing at each station pair 
 Underground  conduit  between  station  pairs  and  tie‐in  to  existing  fiber  optic  and  electric 
utilities 
 
 

6.0 BRT OPERATIONS, TRAFFIC SIGNALS, 
AND COMMUNICATIONS COST ESTIMATE 
 
The Construction Cost Estimate for BRT Operations, Traffic Signals, and Communication is detailed 
in  Appendix  E.      The  cost  estimate  is  based  on  2010  dollars  and  does  not  contain  vehicles, 
escalation, contingency or professional services.   
 
The project cost estimate will utilize FTA’s Standard Cost Categories (SCC) spreadsheet was used to 
summarize costs.  The total cost will be summarized in the Cost Estimate Report and will include 
escalation  to  year  of  expenditure,  a  33  percent  contingency  on  all  cost  items,  and  professional 
services.   The most recent total cost for the project excluding vehicle cost (as of October 11, 2010) 
is $28.6 million and within budget. 
 
 
 
 
 
 
 

  
Bus Operations, Traffic Signals, and Communications Concept Report 
Page 24 
 
 

 
 
APPENDICES 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
  
Bus Operations, Traffic Signals, and Communications Concept Report 
 
 
 

 
 
Appendix A 
 
Meeting Minutes 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
  
Bus Operations, Traffic Signals, and Communications Concept Report 
 
 
Wilbur Smith Associates Inc., Michigan

Memorandum
TO: Attendees
File

FROM: Wilbur Smith Associates

DATE: August 9, 2010

SUBJECT: Traffic Operations Meeting

PROJECT: Silver Line BRT

Date/Time: August 9, 2010 at 2:00 p.m.

Location: Interurban Transit Partnership – The Rapid Office


300 Ellsworth Avenue SW
Grand Rapids, MI 49503

Attendees:

Taiwo Jaiyeoba, The Rapid


Conrad Venema, The Rapid
Gary Scheuren, The Rapid
Russ Henckel, City of Wyoming
Ron Dressander, City of Wyoming
Chris Zull, City of Grand Rapids
Terry Schweiterzer, City of Kentwood
Mike Devries, URS
Barney Payseure, CWA
Marlene Connor, WSA
Vinod Dega, WSA
Matt Hunter, WSA

The following represents our understanding of the key points of discussion at the traffic
operations meeting. If anything appears misrepresented, please let us know.

Meeting Purpose: Understand Cities traffic signal systems as well as how the Transit
Signal Priority equipment will interact with the traffic signal controllers.

Introduction
• The EA for the Silver Line is complete
Signals
• Existing signals are Eagle EPAC (models 30, 50 and 60 coming soon)
• The proposed transit signal prioritization in the EA document includes early green and
green extension. Pre-emptive signals are not proposed

8164 Executive Court, Suite A – Lansing, Michigan 48917 517.622.2500 Fax: 517.622.2525
Wilbur Smith Associates Inc., Michigan
• Cities concerned that extending green to Division when is the secondary traffic volume
could cause problem for heavy volume on some of side streets. The EA document
excludes the following heavy volume intersections along Division Avenue from
implementing transit signal prioritization – Burton St, 28th St, and 44th St. Group
suggested to exclude 36th St and 54th St also from implementing transit signal priority.
However, the study as part of the EA document shows 36th St and 54th St would still
operate within acceptable level of service even with transit signal priority.
• The City of Wyoming controls the signals at 32nd, 36th, 44th, 48th, and 54th which are
shared with the City of Kentwood. They all follow standards set by the City of Grand
Rapids
• The Opticom system is used to allow communication with the signals i.e emergency
vehicles. Currently the Fire department are the only group authorized. City of Wyoming
portion of Opticom is not being used.
• The City of Grand Rapids will provide a list of signals that have Opticom
• If other than Opticom is proposed, Cities indicated that The Rapid will be responsible to
change the hardware at signals and also on the Emergency vehicles. Group agreed that
the Opticom remain the system for the Silver Line to keep consistency and avoid
additional cost
• The system is currently optimized for progression which the city is hopeful will suffice for
the transit progression along the corridor.
• The consultant team needs to consider delay to the general public and ensure that
additional green time is only given when needed
• The average cycle length is currently 90 seconds
• The consultant team will request necessary synchro files for the existing signal network
from the City of Grand Rapids
• The existing detection systems include micro, loops, video and a few pucks
o If any improvements are done at signals, cities are changing them to Video
detection
o The City of Grand Rapids will provide a list of detection types at each signal
• City’s central control system currently uses ACTRA, however, will be changing to
TACTICS. Except 32nd St, all other intersections communicate with Central control
system.

Maintenance
• The Cities are concerned about the maintenance requirements as they are responsible
o The Memorandum of Understanding (MOU) is currently drafted will layout all
components of the system including the maintenance requirements
o The MOU has been reviewed by City management prior to this technical
coordination
o The MOU will address issues communicated at two levels, to City Managers at
one level and to engineering and operations at the next level
o The MOU will be a living document that can be revised over time
• A quarterly technical report is proposed to look at safety, detour routes and maintenance
schedule

Communication Infrastructure
• The Current communication infrastructure has either radio, copper or fiber
o Fiber is installed from 28th to Wealthy, with none south of 28th
o No ductwork is available for running fiber or cable
o The existing fiber network has 48 lines with approximately 50% dark
o The City owns all lines and may look at leasing in the future

8164 Executive Court, Suite A – Lansing, Michigan 48917 517.622.2500 Fax: 517.622.2525
Wilbur Smith Associates Inc., Michigan
• The City of Grand Rapids will send a fiber map
• The Silver Line will likely need 2 lines for traffic, and 2 or more for other uses such as
CCTV

Other
• Note that Division is an incident management route for US-131
• 28th street is an M-route that crosses division but it is not recommended for signal
prioritization so not an issue
• ITP will coordinate with MDOT (Eric Kind - TSC Manager, and Paul Errand – Traffic
Management Center)
• The cities would like to see what other cities have done with signage when lanes
transition from exclusive bus lane to shared lane.
• The speed limit on Division from 28th to 54th will increase to 40 mph from 35 mph

Action Items
• The City of Grand Rapids will provide a list of signals that have Opticom
• The consultant team will request necessary synchro files for the existing signal network
from the City of Grand Rapids
• The City of Grand Rapids will provide a list of detection types at each signal
• The City of Grand Rapids will send a fiber map

The meeting was adjourned at 4:00 p.m.

8164 Executive Court, Suite A – Lansing, Michigan 48917 517.622.2500 Fax: 517.622.2525
Wilbur Smith Associates Inc., Michigan

Memorandum
TO: Attendees
File

FROM: Wilbur Smith Associates

DATE: August 10, 2010

SUBJECT: Bus Operations Minutes

PROJECT: Silver Line BRT

Date/Time: August 10, 2010 at 10:00 a.m.

Location: Interurban Transit Partnership – The Rapid Office


300 Ellsworth Avenue SW
Grand Rapids, MI 49503

Attendees:

Taiwo Jaiyeoba, The Rapid


Brian Pouget, The Rapid
Conrad Venema, The Rapid
Meegan Joyce, The Rapid
Ronald Webber, The Rapid
Steve Schnipper, The Rapid
Gary Scheuren, The Rapid
Barney Payseure, CWA
Kyle Reidsma, URS
Marlene Connor, WSA
Vinod Dega, WSA
Matt Hunter, WSA

The following represents our understanding of the key points of discussion at the bus operations
meeting. If anything appears misrepresented, please let us know.

Meeting Purpose: Understand all of ITP’s operations and expectations that will interface
with the Silver Line and how those will be communicated.

Introduction
• The team would like to understand what systems are currently in place and how they
can be implemented into the Silverline BRT.
• ITP would like to ensure that their current ITS system will be compatible with the
proposed system

8164 Executive Court, Suite A – Lansing, Michigan 48917 517.622.2500 Fax: 517.622.2525
Wilbur Smith Associates Inc., Michigan
Integrate the BRT with AVL system/other systems in ITP
• The current equipment and software is developed by AVL Technologies in Colorado and
the stop annunciators are McKenzie. They appear to have some existing issues with the
current functioning of their AVL systems. The reporting features are not yet meeting their
expectations. The Rapid staff needs to resolve this with their vendor.
• The next bus sign currently gives a scheduled time which is not linked to actual bus
arrivals
• The proposed next bus system should include audio for persons with disabilities, on
board the vehicles and at stations.
• ITP would like the system to make it easy for users to differentiate the BRT and regular
fixed route system.
• BRT needs to be integrated into the existing system
• Transferring between the BRT and other services needs to be seamless

Fare Collection
• Smartcards are desirable but may be too expensive
o Currently using GFI Genfare fareboxes, the Odyssey model which has smart
capabilities which has not been implemented or utilized. They were installed in
2003-2004
• Pre-paid boarding is a desired attribute for the Silverline service, as a feature to reduce
dwell time at stations. Questions were raised regarding how to safeguard fare payment
avoidance
• The consultant team is to make a recommendation on the fare system and technology. .
o Options include: one card that can be used on both BRT and regular service
o Issues raised: premium fare for BRT, shared stations

Emergency Telephones
• Currently no system in place
• Emergency calls should go to the security office which is manned 24/7
• ITP would like the emergency telephone to automatically trigger a camera at that
location so that security can instantly see the incident
• Calls need to be recorded for later use

CCTV
• Existing cameras on buses are Apollo, Washington
• Central station currently has cameras
• The current security system has 64 cameras that are monitored 24/7
• The proposed system should include cameras at other stations that will tie to the main
system
• The goal is not to have all cameras visible at once but to have easy access to camera
footage when needed.
• The initial camera locations need to be prioritized at the worst crime locations
• ITP should explore the potential of tying into the City of Grand Rapids Traffic
Management Center

General System
• ITP would like the system to be as intermodal as possible allowing easy transition for
pedestrian and Bicycle traffic onto the BRT
• Bicycle racks are needed at core stations and the Silver Line ends
• ITP is currently looking at different buses, and will likely have 60’ articulated units
• Low-flow hybrid electric buses are desirable

8164 Executive Court, Suite A – Lansing, Michigan 48917 517.622.2500 Fax: 517.622.2525
Wilbur Smith Associates Inc., Michigan
• ITP has future plans to build park’n’ride facilities at 54th and 60th, however this is not part
of this contract
• The fiber optic currently does not go south of 28th St, but an economical data system can
be installed in the interim to avoid the initial cost

Stations
• Stations can be shared between BRT and regular fixed route service however there is
concern over the logistics i.e. will both buses use the exact location which will cause
delay to the Silver Line, will the regular stations be offset to reserve the spot BRT etc.
• If regular fixed route stations are offset the consultant team recommends downstream to
all easy entry for Silver Line buses to line up correctly with the curb
• Verification is needed on whether BRT buses will be allowed to leave the designated
lane to avoid regular fixed route buses or right turning traffic blocking the bus line while
waiting for pedestrians
• ITP will evaluate the operation at each location to recommend a function
• Technology should differentiate between which bus types are arriving
• The MOU needs to allow changes in the operation to be made over time
• 5 stations are currently located on grades steeper than 2% which is the maximum
allowable ADA grade
• The team will explore options and make a recommendation on a treatment at each of
these locations
• Precision docking is an option that would allow a ADA accessible landing area
• Precision docking will impact the ability of the station to be used for regular fixed route
operations.

Signal Priority
• The team recommends keeping the Opticom system which is currently used to save
additional cost of upgrading the entire system
• The system is currently set up to hold green and not switch to green
o This is signal priority which is how the proposed will work vs. signal preemption
which allows emergency vehicles to always get a green light
• The optimal station location is past the signal not prior to

Action Items
• ITP to assess each station for combined Fixed Route and BRT services impacts.
• Schedule a site visit to recommend regular fixed route bus interaction with BRT stations
for WSA team
• ITP to assess potential of tying cameras into City Traffic Management Center
• Consultant team to recommend fare collection system
• Consultant team to review parking and other signage along BRT route at proposed
station locations.
• Wayfinding and other signage needs to be a consideration

The meeting was adjourned at 12:00 p.m.

8164 Executive Court, Suite A – Lansing, Michigan 48917 517.622.2500 Fax: 517.622.2525
 

 
 
Appendix B 
 
Existing Bus Routes  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
  
Bus Operations, Traffic Signals, and Communications Concept Report 
 
 
196
US - 13 1

ALP

IT
THREE MILE MI CH I G AN

CO
RK
VE TER A N S THREE MILE

PA
FAC I L I TY

E
ID

FULLER
RS
MEIJ ER 616.776.1100 www.ridetherapid.org

VE
T H E DELTAPL EX
RIVERSIDE

RI
MIDDLE SCHOOL

CELEBRATIO
VILLAGE

D
EL

EAST BELTLINE
KNAPP KNAPP

FI
KNAPP

N
AI

DIAMOND
PL
MEIJER
ORD BLANDFORD RICHMOND ANN

US - 131
OOL NATURE PARK CRESTON
W

LEFFINGWELL
CENTER HIGH SCHOOL CITY MIDDLE/HIGH
AL SCHOOL KENT CAREER
KE

BRISTOL
R TECH CENTER
KEC BELTLINE
GRCC OCCUPATIONAL
TRAINING CENTER GRAND R
LEONARD LEONARD BAPTIST
LEONARD

ALPINE
CORNERSTONE
KENT

MARYLAND
UNIVERSITY

LAFAYETTE

BALL
1 - Division JUVENILE

ER
FREDERIK

TU RN ER

COLLEGE
BELKNAP CENTER
MEJIER

SC RI BN

FULLER
PARK S PEC TR U M GARDENS
KE N T CO MM. E
VIC
C EN TER
SER

PLYMOUTH
COVELL

U NIO N W ES T WO O D

ST
HIG H SC H O O L MIDDL E SC H O OL HIGHLAND KEN T
PARK

OC
COU N TY
J AI L

GARFIELD

KI
BRIDGE BRIDGE US - 196

N
LAKE MICHIGAN DRIVE MICHIGAN MICH IGAN

G
SEE DOWNTOWN MAP

LAKESIDE
LANE
VALLEY FOR MORE ROUTING DETAIL

OTTAWA
LAKE MICHIGAN DRIVE FULTON
FULTON US
- 1 B ROUTE 14 FULTON FULTON
31
WILCOX AQUI N AS

DIVISION
JOHN BALL PARK
AND ZOO PARK CO LLEGE CA
CHERRY SC
LAK AD
E
A E D
R IVE F IS
K L
WEALTHY WEALTHY AK
ROUTE 5 E
S PE CTR UM H EALTH WE RE

FULLE R
AL ED
W E A LTH Y B L OD GE TT CAM PU S TH S L
G R CC FAMILY THEATE R Y A KE
6

M -TE C H INDEPENDENCE
9
-1

ER AGENCY GASLIGHT EA ST G R A N D R A P ID S
R IV
ND VILLAGE
GRA C ROUTE 2 CIT Y H AL L AN D P O LIC E
S

FRANKLIN
R
U

GIDDIN GS
STE

OXFO RD EAST GR AND R AP ID S E A ST GR AN D R AP ID S


E
ILL

H IGH SC HO O L M I DDL E SCH O O L


CHE

31
DV

BRETO N
IR OQ UOI S
- 1

MI DDLE SCH OOL


AN
DOR

HALL HALL
GR

US

PLYM OUT H
R EY
DF
IV ER CHIC AGO DR. G O
D R
BUCHANAN

BOSTON
DIVIS ION
N

KA
EASTE RN
RA

MADISON
G GO DFREY L EE

BRE TON
LA
MIDDL E A ND B RET O N

M
HIG H S C HO O L VILL A G E CALV

AZ
CO LL EG

OO
BURTON
ROUTE 24 D BURTON BURTON BURTON
B UR T O N
W Y OM ING
MIDDLE
SE NI OR C IT IZE NS OTTAWA H ILLS
SC H OO L
BURLINGAM E

C E NTE R HI GH SCH OO L
DE

PORTER W Y OM ING W
P O LIC E &
HO

PORTER LAKE GR AN D R API DS C HR IS T IA N


C OURT H O US E H IGH SCH OOL WO O DL A N D
OP
CENTER
BYRON

WY O MING PA RK M AL L
YRO

HIGH SC H O OL W YO M ING

RADCLI FF
C ITY HA LL
B
C

28TH ROUTE 28 28TH 28TH


28TH
CLYD E PARK

M EI J ER
MICHAEL

29T

KALAMAZOO
W Y OM I N G D AV E N POR T COL L E GE
G OO D W I LL Y C OM M U N I TY C A R EER CE N TER
IN D U S T R I ES PKW EDUCATI O N
PRAIRIE PR A IR IE 32ND
US - 13 1

R O G ERS 32ND 32ND 32ND


IVANREST

JEFFERSON

HI G H S CHOO L W YO M ING HO PE
R
.B

L IBRA RY N ETW O RK
.
C
H

GOD W I N H EI G HTS
A
FF

36TH HI GH S C HO O L E 36TH
EE

1 WEEKDAY ONLY
SERVICE ON
DIVISION
ROUT E 10

36TH STREET
DIVISIO N

EASTE RN

44TH 44TH ROUTE 44 F 44TH 44TH


BYRO N CENT ER

44TH
CLYD E PARK

WALMA
BURLINGAME

ME IJE R KEL L OG S V IL L E
M I DD L E S C H OOL
K EL L O GS VI L LE BR
ET
H I G H S C H OOL ON K E NT
P O L IC
D IS C OV ER Y
US - 13 1

K EN T WO
H I GH S C HO OL C IT Y H A
WY O M IN G
SEN I O R C IT I ZEN S
52ND CEN TER 52ND

54TH
MEIJ ER H 1
KALAM AZOO

WEEKDAY EVE &


GEZON PARKWAY SUNDAY
1 WEEKDAY EVE &
DIVISION

NO SERVICE
SUNDAY
DIVISION
CLYDE PARK

SOUTH OF 54TH
ME T R O PO L ITAN TWO WAY
HE ALT H VIL LA G E
SERVICE ON
54TH STREET 60TH
DIVISIO N

W OOD F IE LD
CLOC KTOWER
APA R TM EN TS
CENT ER
EAST KEN TW O O D
M - 6 H IGH SCH OO L

K-M A R T
68TH G
S PE CT R U M HEA LTH
S OU TH PAVI L I ON
PINE REST
C HR I S TI AN
M E N TAL H EA LTH
E
KNAPP KNAPP

FI
N
AI

DIAMOND
PL
ANN 616.776.1100 www.ridetherapid.org
RICHMOND
PARK CRESTON
HIGH SCHOOL CITY MIDDLE/HIGH
SCHOOL
BRISTOL

GRCC OCCUPATIONAL
TRAINING CENTER
LEONARD
LEONARD

ALPI NE
KENT

LAFAYETTE

BALL
JUVENILE

ER
TU RN ER

COLLEGE
BELKNAP CENTER
3 - Madison

S C R IB N

FULLE R
PARK SP ECT RU M
KE N T CO MM. E
VIC
CE N TER
SER

PLYMOUTH
WESTWOOD
ST

OL M ID D L E S CH O OL HIGHLAND K ENT
PARK
OC

CO UNTY
J AI L
GARFIELD

KI

DGE BRIDGE US - 196


N

MICHIGAN MIC HIG AN


G

SEE DOWNTOWN MAP

LAKESID E
LANE

FOR MORE ROUTING DETAIL


VALL EY

LAKE MICHIGAN DRIVE OTTAWA FULTON


FULTON US
- 1 B ROUTE 14 FULTON FULTON
31
DIVISIO N
WILCOX A QU INA S
JOHN BALL PARK RO

JEFF ERSO N
AND ZOO UT PARK CO LLE GE
E 4 CHERRY N
A
LAK
E D R O B IN S O
R IVE FIS
K L
WEALTHY ROUTE 5 WEALTHY AK E
S PE CTR U M HE ALTH WE

FUL LER
W E A LTH Y B L OD G ETT C AM PUS AL
G RCC FAMILY
TH
PLEASANT T H EATE R Y
96

M- TE CH INDEPENDENCE
-1

IVER AGENCY GA SLI G HT


R
ND VI LL AGE
GRA ROUTE 2 C FRANKLIN
S

GIDD ING S
STE

OX FOR D E A ST GR AN D RA
E
ILL

HI GH SC
CHE

31
DV

I R OQ UO IS
- 1

MI DDLE SC HO OL
AN
DOR

HA LL HALL
GR

US

PLYM OU TH
Y
F RE
CH ICA GO DR . G OD
BUCHANAN

BOST O
KA
EAS TER N
DIV ISIO N

MADISON

GO DFREY LEE
M I DDLE A ND LA
HI GH SCH OO L M
AZ
OO
BURTON
ROUTE 24 D BURTON BURTON
B U RT O N
ROUTE 4

WY OM IN G
MI DD L E
SENI OR C IT I ZE N S OTTAWA HI LLS
S C HO OL
BURLIN GAME

C EN TER HI G H SC H OOL
DE

WYO MI NG
POLI C E &
HO

GRA N D RA PIDS CH R
C OU RT HO US E HI G H SC H OO L
OP

ARK
L W Y OM I N G
C I TY HA L L
28TH 28T H E ROUTE 28 28TH
CLY DE PAR K

ME I JE R
MICHAEL

KALAMA ZOO

W YO MI N G D AVE N PO R T CO L L E GE
CO MM UN I T Y CA R EER C EN TER
32ND E DU CATI O N
US - 131

32N D F
JEFFERSON

WYO MI N G HOPE
R
.B

LI BRA RY N ET WO RK
.
C

G
H

G ODW I N H E IG HTS
A
FF

TH H I GH S CH OO L 36TH
EE
DIVIS ION

44TH 44TH ROUTE 44 44TH


BURLIN

CLY DE
616.776.1100 www.ridetherapid.org

LAMOREAUX

N
OR

11 - Plainfield
NH
PE
AL

HENZE

FOUR MILE
FOUR MILE

R IV E R
O LD OR C HA RD APA RTM E N T S

GRAND
NORTH CENTER ELMD
ALE
GR E EN R I DG E M A LL E
CENTE R

ELD
I NFI
ALPI NE

US - 1
96 PLA
US - 96
IT

REE MILE M I C HI GA N
CO
RK

VE T ER ANS THREE MILE


PA

FAC I LITY
E
ID

FULLE R
RS

ME I JE R
VE

T H E D ELTA PL EX
RIVERSIDE
RI

MIDDLE SCHOOL
US - 13 1

KNAPP KNAPP
D
ROUTE 13
DIAMOND

RICHMOND ANN
PARK CRESTON

US - 96
CITY MIDDLE/HIGH
D

HIGH SCHOOL
EL

SCHOOL
FI
N
AI

GRCC OCCUPATIONAL
PL

TRAINING CENTER
LEONARD LEONARD
C ROUTE 15 EAST LEONARD
ALPI NE

KENT

MARYLAND
LAFAYETTE

BALL

JUVENILE
ER
TU RN ER

COLLEGE

BELKNAP CENTER
S C R IB N

FULLE R

PARK S P E CT R UM
K E N T CO M M . E
VIC
CE N T ER
SER
PLYMOUTH

D
ST

HIGHLAND KENT
H O OL
PARK
OC

COUNTY
JAIL
GARFIELD

KI

BRIDGE US - 196
N

MICHIGAN MI CH IGA N
G

B MICHI GAN
LAKESID E
LANE
VALL EY

OTTAW A
IONIA
MONROE

LAKE MICHIGAN DRIVE PEARL


DIVISIO N

FULTON FULTON
FULTON
L PARK WILCOX A Q U I N AS
PARK C O L L E GE
CHERRY
N
A LAK
E D R O B IN S O
SEE DOWNTOWN MAP FOR R IVE FIS
K L
WEALTHY AK E
MORE ROUTING DETAIL
S P E C T R U M H E A LT H WE RE
FUL LER

AL ED
W E A LT H Y BL O DG E T T C A M P US TH
GRCC FAMILY TH E ATE R Y
M - TEC H INDEPENDENCE
ER AGENCY G AS L IG HT
RIV EA
VI L L AG E CIT
FRANKLIN
R

GIDD ING S
STE

OX FOR D E A ST G RA ND RA P ID S E
E
ILL

HIG H SC HO O L M
CHE

31
DV

BRE TON

IROQUOIS
- 1

M I D D L E S CH O O L
AN
DOR

HA LL HALL
GR

US

H
 

 
 
Appendix C 
 
Dedicated Lane Base Maps 
And 
Station Locations 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
  
Bus Operations, Traffic Signals, and Communications Concept Report 
 
 
31
US-1
Legend

WILLIAMS
Final Proposed BRT Stations
MA New Crosswalk Proposed
R KE
T

WEALTHY
Parcel Lines (from REGIS)
FINNEY Lane Assignments During Peak Hours
7am - 9am & 4pm - 6pm
Dedicated Lane

131
WEALTHY
Shared Lane

US-
GOODRICH

BARTLETT

OAKES
ALLEY OAKES

WESTON
GRANDVILLE
WEALTHY

FULTON
CHERRY
MO
N RO
E

AU
ALLEY OTTAWA

MP
ELLSWORTH

CA
ALLEY GRANDVILLE

OTTAWA

PRIVATE

US-131

BUSINESS US-131
US-131
BUSINESS US-131

ALLEY IONIA

WESTON

S
UI
LO
IONIA
GOODRICH

BARTLETT

WILLIAMS

ALLEY IONIA
WEALTHY

Silver Line BRT Base Mapping Sheet


0 100 200
COMMERCE
Station Locations and Dedicated and Feet
Shared Lane Assignments 1 1 of 17
During Peak Periods 1 inch = 200 feet
Legend

BRIDGE
Final Proposed BRT Stations

New Crosswalk Proposed

Parcel Lines (from REGIS)

FULTON
Lane Assignments During Peak Hours
MA 7am - 9am & 4pm - 6pm
R

LOUIS
KE
T Dedicated Lane
Shared Lane

CAMPAU

ALLEY OTTAWA

LYON
MONROE

Louis St (SB)
Van Andel (SB)
S
UI

Louis St (NB)
LO

Van Andel (NB)

MICHIGAN
ALLEY IONIA

69
I-1
PEARL
OTTAWA

ALLEY IONIA
FOUNTAIN

COMMERCE

69
I-1
IONIA
ER
NT
CE

CRESCENT
E
O
NR
O
M

I ON
DIVIS

Silver Line BRT Base Mapping Sheet


0 100 200
LIBRARY

Station Locations and Dedicated and Feet


Shared Lane Assignments 2 2 of 17
WINCHESTER
During Peak Periods 1 inch = 200 feet
Legend

S
UI
LO

PEARL

LYON
Final Proposed BRT Stations
COMMERCE

69
New Crosswalk Proposed

I-1
Parcel Lines (from REGIS)
IONIA
Lane Assignments During Peak Hours

ER
NT
7am - 9am & 4pm - 6pm

CE

CRESCENT
Dedicated Lane

E
O
NR
Shared Lane

O
M
I ON
DIVIS

LIBRARY
WINCHESTER

SHELDON

SHELDON

BOSTWICK
ALLEY FULTON

PARK Michigan St (EB) Michigan St

CRESCENT
LA GRAVE

RANSOM

Fulton St (SB)
G.R.C.C. (SB) COIT
JEFFERSON Fulton St (NB)
G.R.C.C. (NB)

BARCLAY BARCLAY BARCLAY

CRESCENT
FULTON

MIC HIGAN
FOUNTAIN

CLAREMONT
JOHN

Silver Line BRT Base Mapping Sheet


0 100 200
WILLOW

Station Locations and Dedicated and Feet


Shared Lane Assignments 3 3 of 17
During Peak Periods 1 inch = 200 feet
WESTON
MCCONNELL Legend

GOODRICH

BARTLETT
Final Proposed BRT Stations

WILLIAMS
ALLEY COMMERCE

CHERRY

OAKES
New Crosswalk Proposed

Parcel Lines (from REGIS)


Lane Assignments During Peak Hours
DIVISION 7am - 9am & 4pm - 6pm
Dedicated Lane
Shared Lane

GOODRICH

CHERRY
ALLEY DIVISION

SHELDON

SHELDON SHELDON

ALLEY FULTON
WESTON
OAKES
ALLEY SHELDON ALLEY SHELDON

MAPLE
PARK

LA GRAVE

RANSOM

ALLEY LAGRAVE
GOODRICH

Fulton
JEFFERSON Fulton
CESS
SAINT MARY’S AC

Wealthy St (SB) BARCLAY

Wealthy St (NB)

CASS

FULTON
WASHINGTON
E
AT
ST
WEALTHY

LAFAYETTE
Silver Line BRT Base Mapping Sheet
0 100 200
Station Locations and Dedicated and Feet
Shared Lane Assignments 4 4 of 17
During Peak Periods 1 inch = 200 feet
PLEASA NT
GRANT
Legend
COMMONS IONIA Final Proposed BRT Stations

New Crosswalk Proposed

Parcel Lines (from REGIS)


Lane Assignments During Peak Hours
7am - 9am & 4pm - 6pm

WEALTHY
Dedicated Lane
Shared Lane

MCCONNELL
ANTOINE

LOGAN
GRAHAM

GRANT
DIVISION

SYCAMORE
Franklin St (SB) Logan StALLEY
(SB)DIVISION

PLEASA NT
RINQUETTE Franklin
CORNWALLSt (NB) CODY

Logan St (EB) SHELDON


FRANKLIN

BUCKLEY
SHELDON ALLEY SHELDON

ALLEY HAIFLEY
HAIFLEY

MAJOR LA GRAVE

THOMPSON

ALLEY BUCKLEY
ALLEY LAGRAVE

JEFFERSON

ALLEY JEFFERSON O NS
ALLEY JEFFERSON
O MM

LOGAN
Silver Line BRT Base Mapping EC
AG Sheet
0 100 200 RIT
HE
Station Locations and Dedicated and Feet
Shared Lane Assignments
CASS
CASS
CASS 5 5 of 17
During Peak Periods 1 inch = 200 feet
Legend
Final Proposed BRT Stations

New Crosswalk
COMMON S Proposed

SHELBY
Parcel Lines (from REGIS)

RYERSON
CANTON
Lane Assignments During Peak Hours

ANTOINE
7am - 9am & 4pm - 6pm
Dedicated Lane
IONIA
Shared Lane
COMMONS

DELAWARE
ALBANY
PUTNAM
HOME

ZENO
RENA

SHELBY
DIVISION

ALLEY DIVISION Green St (SB)


ARLINGTON

DELAWARE
Green St (NB)

GREEN
EUCLID

VILAS
SHELDON

SALEM

HIGHLAND
PRIVATE
HALL

Silver Line BRT Base Mapping Sheet


JEFFERSON
0 100 200
JEFFERSON
HIGHLAND

DELAWARE
Station Locations and Dedicated and

POWELL
Feet
Shared Lane Assignments 6 6 of 17
During Peak Periods ALLEY JEFFERSON1 inch = 200 feet
Legend
Final Proposed BRT Stations

PRIVATE
New Crosswalk Proposed

Parcel Lines (from REGIS)


Lane Assignments During Peak Hours
7am - 9am & 4pm - 6pm
Dedicated Lane
IONIA
Shared Lane

COTTAGE GROVE
DICKINSON

STEVENS
CORINNE
GRIGGS

BROWN
ELM

LA BELLE
FOX
DIVISION
BROWN

DICKINSON

ALLEY DIVISION ALLEY DIVISION Cottage Grove St (SB)


Cottage Grove St (NB)

HOME
LA BELLE
HORTON
HORTON

COTTAGE GROVE
VILAS

GARD EN
ALLEY HORTON

FAIR
FRANCIS DOREMUS
FRANCIS
CROFTON

ALLEY FRANCIS

Silver Line BRT Base Mapping Sheet


0 100 200
JEFFERSON
Station Locations and Dedicated and Feet
Shared Lane Assignments 7 7 of 17
During Peak Periods 1 inch = 200 feet
ALLEY IONIA Legend
Final Proposed BRT Stations

New Crosswalk Proposed


IONIA Parcel Lines (from REGIS)
Lane Assignments During Peak Hours
7am - 9am & 4pm - 6pm
Dedicated Lane

ALLEY KIRTLAND

ALLEY QUIGLEY
SUTTON
Shared Lane

KIRTLA ND

QUIGLEY

ALLEY STEWART

ALLEY ROSE
ALLEY BURTON

STEWART
BANNER

CUTLER
BAYLIS

ANDRE

ROSE
BURTON

ELM
DIVISION
MELVILLE

ALLEY DIVISION ALLEY DIVISION Burton St (SB) ALLEY DIVISION

ALLEY ANDRE
Burton St (NB)

HORTON
ANDRE

ALLEY HORTON

FRANCIS

GRIGGS
Silver Line BRT Base Mapping Sheet
0 100 200
Station Locations and Dedicated and Feet JEFFERSON
Shared Lane Assignments 8 8 of 17
During Peak Periods 1 inch = 200 feet
SOUTHFIELD
Legend

NORTHVIEW
Final Proposed BRT Stations

New Crosswalk Proposed

Parcel Lines (from REGIS)


Lane Assignments During Peak Hours
VANGIE 7am - 9am & 4pm - 6pm
Dedicated Lane
Shared Lane

WITHEY
ANSONIA

BAYLIS
BATT

PLASTER

DETROIT
BLACKBURN
BATT

REEKC

SOUTHVIEW
CLAIRE

KEN-O-SHA
DIVISION

SOUTHVIEW
Southview
ALLEY DIVISION St (SB)
ALLEY DIVISION ALLEY DIVISION

Southview St (NB)

44TH
KEN-O-SHA
EOLA

HORTON
HORTON
ROSEMARY

ALLEY HORTON
MEERSE

FRANCIS

ALGER
Silver Line BRT Base Mapping Sheet
0 100 200
Station Locations and Dedicated and Feet
Shared Lane Assignments 9 9 of 17
EVEREST
During Peak Periods 1 inch = 200 feet
Legend
Final Proposed BRT Stations
SER
REI New Crosswalk Proposed

Parcel Lines (from REGIS)


Lane Assignments During Peak Hours
7am - 9am & 4pm - 6pm
Dedicated Lane

BUCKINGHAM

CANTERBURY

HONEOYE
Shared Lane

COLRAIN
CELIA
MANCHESTER
32ND

ONEIDA

BUCKINGHAM

COLRAIN
CELIA
DIVISION

28th St (SB)

28th St (NB)

EOLA
COLRAIN
WESLEY
LEMYRA

CELIA

YE
O
ONE
H

28TH
Silver Line BRT Base Mapping Sheet
0 100 200
Station Locations and Dedicated and Feet
Shared Lane Assignments 10 10 of 17
During Peak Periods JEFFERSON 1 inch = 200 feet
OPAL
Legend
Final Proposed BRT Stations

New Crosswalk Proposed

Parcel Lines (from REGIS)


SER Lane Assignments During Peak Hours
REI
7am - 9am & 4pm - 6pm

34TH
COOLIDGE

Dedicated Lane
Shared Lane

32ND
33RD

AVONLEA
35TH
REISER
COOLIDGE

AVONLEA
DIVISION

36th St (SB)

36th St (NB)

HORTON

FRONTENAC
CLEMENTS
WEXFORD

FREEDOM

EXCHANGE
35TH

34TH
36TH

FRANCIS

Silver Line BRT Base Mapping Sheet


0 100 200
Station Locations and Dedicated and Feet
Shared Lane Assignments 11 11 of 17
During Peak Periods 1 inch = 200 feet
JEFFERSON
OPAL Legend
Final Proposed BRT Stations

New Crosswalk Proposed

Parcel Lines (from REGIS)


URBAN Lane Assignments During Peak Hours
7am - 9am & 4pm - 6pm

COOLIDGE
Dedicated Lane
Shared Lane

40TH
LORAINE
FLOYD
41ST

39TH
WADSWORTH

CALHOUN
JORDAN

COOLIDGE
40TH

DIVISION

SPANISH
3

HORTON
WILBUR

WALTER
JANET

HIMES
ABBIE
BURT

FRANCIS

Silver Line BRT Base Mapping Sheet


0 100 200
Station Locations and Dedicated and Feet
Shared Lane Assignments 12 12 of 17
During Peak Periods 1 inch = 200 feet
Legend
Final Proposed BRT Stations

New Crosswalk Proposed

Parcel Lines (from REGIS)


Lane Assignments During Peak Hours
7am - 9am & 4pm - 6pm
Dedicated Lane
Shared Lane
PINEHURST

MAPLELAWN
MURRAY

THURSTON

BELLEVUE
43RD

41ST
WILKSHIRE

DIVISION

44th St (SB)

44th St (NB)
RIDGEWOOD

FARNHAM

BELLEVUE
44TH

MAPLELAWN
Silver Line BRT Base Mapping 43RD
0 100 200 Sheet
Station Locations and Dedicated and Feet
Shared Lane Assignments 13 13 of 17
During Peak Periods 1 inch = 200 feet
Legend
Final Proposed BRT Stations

New Crosswalk Proposed

DON
URBAN Parcel Lines (from REGIS)
Lane Assignments During Peak Hours
7am - 9am & 4pm - 6pm
Dedicated Lane
Shared Lane
PINEHURST

JEAN
FLORIDA

WILKSHIRE

LEROY
ELWELL
HOLLY
50TH

DIVISION
DANIEL

47TH
GARLAND
SLUYTER

MONTEBELLO
48TH
HORTON

Silver Line BRT Base Mapping Sheet


0 100 200
Station Locations and Dedicated and Feet
Shared Lane Assignments 14 14 of 17
During Peak Periods 1 inch = 200 feet
Legend
Final Proposed BRT Stations

New Crosswalk Proposed

Parcel Lines (from REGIS)


Lane Assignments During Peak Hours
7am - 9am & 4pm - 6pm
Dedicated Lane
Shared Lane

54TH

50TH
DIVISION

54th St (SB)

54th St (NB)

52ND
KELLOGG WOODS
PARK
OODS

Silver Line BRT Base Mapping Sheet


GG W

0 100 200
Station Locations and Dedicated and
KELLO

Feet
Shared Lane Assignments 15 15 of 17
During Peak Periods 1 inch = 200 feet
Legend
Final Proposed BRT Stations

New Crosswalk Proposed

Parcel Lines (from REGIS)


Lane Assignments During Peak Hours
7am - 9am & 4pm - 6pm
Dedicated Lane
Shared Lane

56TH
DIVISION

60th St (NB)
MAJESTIC

58TH

ELDEE

NANCY
NORA
DEBAAR

REGENT
FESCUE

Silver Line BRT BaseFREETON


Mapping Sheet
0 100 200
KLEYLA

Station Locations and Dedicated and Feet


Shared Lane Assignments 16 16 of 17
During Peak Periods 1 inch = 200 feet
Legend
Final Proposed BRT Stations
INTERURBAN
New Crosswalk Proposed

Parcel Lines (from REGIS)


Lane Assignments During Peak Hours
7am - 9am & 4pm - 6pm
Dedicated Lane
Shared Lane

60TH
HYACINTH

JONQUIL

DIVISION

60th St (NB)

MAJESTIC

58TH
ELDEE

NANCY
NORA
DEBAAR
BARKWAY

REGENT
FESCUE

Silver Line BRT Base Mapping FREETON


Sheet
0 100 200
Station Locations and Dedicated and
KLEYLA

Feet
Shared Lane Assignments 17 17 of 17
During Peak Periods 1 inch = 200 feet
 

 
 
Appendix D 
 
VISSIM Simulation CD 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
   
  
Bus Operations, Traffic Signals, and Communications Concept Report 
 
 
 

 
Appendix E 
 
Traffic Signal Priority, Transit Operations, 
and 
Communications Cost Estimate 
 
 
 Project Construction Cost Estimate 
Detail cost estimate for cost categories 
50.02, 50.06 and 50.05 
 
 

  
Bus Operations, Traffic Signals, and Communications Concept Report 
 
 
Project Construction Cost Estimate
Silver Line BRT Transit Signal Priority Implementation

WSA Project No. 104601


Date of Estimate: 11-Oct-10
Specification Number
(DOT or CSI)
Description Estimated Unit Unit Price Price
Quantity 2010 Dollars Dollars

Opticom Priority System at Signals 5 Each $ 4,000 $ 20,000


Opticom Priority System for Vehicles 10 Each $ 2,200 $ 22,000
Opticom Priority System Communications and Adjustments 28 Each $ 1,000 $ 28,000
Transit Signal Heads 0 Each $ 1,000 $ -
New Masts and Mast Arms 0 Each $ 15,000 $ -
New Pedestrian Signal Heads and Call Buttons 0 Each $ 800 $ -
System Integration and Calibration 1 LS $ 50,000 $ 50,000

50.02 Total Traffic Signal Construction Cost Estimate $ 120,000

Project Construction Cost Estimate


Silver Line BRT Transit Operations

WSA Project No. 104601


Date of Estimate: 11-Oct-10
Specification Number
(DOT or CSI)
Description Estimated Unit Unit Price Price
Quantity 2010 Dollars Dollars

Emergency Telephone with CCTV Camera 33 Each $ 5,509 $ 181,790


One Additional CCTV Camera 33 Each $ 2,200 $ 72,600
Fare Validation Device 33 Each $ 3,000 $ 99,000
Ticket Vending Machine 33 Each $ 45,000 $ 1,485,000
Smart Card Reader 33 Each $ 3,000 $ 99,000
Next Bus Sign With Audio 33 Each $ 10,000 $ 330,000
Passenger Information Sign and Kiosk 33 Each $ 10,200 $ 336,600
Audio Station Announcement on the Bus 10 Each $ 1,000 $ 10,000
Station Software for Fare Collection 1 LS $ 10,000 $ 10,000
Central Software for Fare Collection 1 LS $ 200,000 $ 200,000

50.06 Total Transit Operations Construction Cost Estimate $ 2,823,990


Project Construction Cost Estimate
Silver Line BRT Office Communications

WSA Project No. 104601


Date of Estimate: 11-Oct-10
Specification Number
(DOT or CSI)
Description Estimated Unit Unit Price Price
Quantity 2010 Dollars Dollars

16147 Fiber Optic Cable, Aerial, 64 Fibers 0 Mile $ 38,000 $ -


16147 Fiber Optic Aerial Splice Closure 1 Each $ 1,100 $ 1,100
16147 Fiber Distribution Unit 1 Each $ 2,500 $ 2,500
16147 Fiber Optic Drop Installation 1 Each $ 2,000 $ 2,000
16160 Enclosure, Free Standing, NEMA 3R 0 Each $ 11,000 $ -
16160 Enclosure, Free Standing, NEMA 3R, Cooled 0 Each $ 15,000 $ -
16702 Switch / Router 3 Each $ 10,000 $ 30,000
16702 Uninterruptible Power Supply 1 Each $ 1,500 $ 1,500
16702 Miscellaneous Power Material 1 Lot $ 1,000 $ 1,000
16702 Wire and Cable 1 Lot $ 5,000 $ 5,000
16702 Network Video Recorder, 4 Channel 0 Each $ 8,000 $ -
16702 Network Video Recorder, 32 Channel 3 Each $ 12,000 $ 36,000
16702 Installation of MPLS Service 0 Each $ 5,000 $ -
16702 VoIP PBX Configuration 1 Each $ 25,000 $ 25,000
16702 CCTV Display Configuration 1 Each $ 50,000 $ 50,000
16702 Network Management System 1 Lot $ 50,000 $ 50,000

Office Communication Construction Cost Estimate $ 204,100

Project Construction Cost Estimate


Silver Line BRT Station Communications - Fiber Optic Cable Option

WSA Project No. 104601


Date of Estimate: 11-Oct-10
Specification Number
(DOT or CSI)
Description Estimated Unit Unit Price Price
Quantity 2010 Dollars Dollars

16147 Fiber Optic Cable, Aerial, 64 Fibers 4 Mile $ 38,000 $ 152,000


16147 Fiber Optic Aerial Splice Closure 17 Each $ 1,100 $ 18,700
16147 Fiber Distribution Unit 17 Each $ 2,500 $ 42,500
16147 Fiber Optic Drop Installation 17 Each $ 2,000 $ 26,000
16160 Enclosure, Free Standing, NEMA 3R 17 Each $ 11,000 $ 187,000
16160 Enclosure, Free Standing, NEMA 3R, Cooled 0 Each $ 15,000 $ -
16702 Switch / Router 17 Each $ 10,000 $ 170,000
16702 Uninterruptible Power Supply 17 Each $ 1,500 $ 25,500
16702 Miscellaneous Power Material 17 Lot $ 500 $ 8,500
16702 Wire and Cable 17 Lot $ 3,000 $ 51,000
16702 Network Video Recorder, 4 Channel 0 Each $ 6,000 $ -
16702 Network Video Recorder, 32 Channel 0 Each $ 12,000 $ -
16702 Installation of MPLS Service 0 Each $ 5,000 $ -
16702 VoIP PBX Configuration 0 Each $ 25,000 $ -
16702 CCTV Display Configuration 0 Each $ 50,000 $ -
16702 Network Management System 0 Lot $ 50,000 $ -

Station Communication Construction Cost Estimate $ 681,200

50.05 Total Communication Construction Cost Estimate $ 885,300


 

 
Appendix I 
 
Cost Estimate Report 
 
 

  
Final Task I Vision Report 
 
 
SILVER LINE BRT

Cost Estimate Report

Tasks 4.4, 6.10 and 7.8

December 30, 2010

Prepared by:
Wilbur Smith Associates
Table of Contents
Cost Estimate Report

CONTENTS

1.0 Introduction and Purpose ........................................................................................................... 1

2.0 FTA Estimate Template ............................................................................................................... 1

3.0 EA Estimate and Budget Control................................................................................................. 1

4.0 Detailed Estimate ....................................................................................................................... 2

4.1 Stations ............................................................................................................................. 2


4.2 Roadway ........................................................................................................................... 2
4.3 Signal Prioritization, Operations, and Communications .................................................... 3

5.0 Final FTA Main Worksheet Estimate ........................................................................................... 4

6.0 Items Not Included in Worksheet ............................................................................................... 6

FIGURES

Figure 1 - Final FTA Main Worksheet Estimate

APPENDICES

Appendix A Cost Estimate Meeting Minutes

Appendix B SCC category list and SCC definitions

Appendix C EA estimate Summary

Appendix D Detailed Estimates

Appendix E Inflation Worksheet

Traffic Concepts Report


Page i
 
Cost Estimate Report 
 
 

1.0 Introduction and Purpose 
 
The  Silver  Line  Bus  Rapid  Transit  (BRT)  route,  as  defined  in  the  Environmental  Assessment  (EA) 
report  prepared  in  2010,  runs  through  three  cities;  Grand  Rapids,  Wyoming,  and  Kentwood  and 
includes 33 proposed Silver Line BRT stations along a 9.6 mile route.   
 
The purpose of this technical paper is to summarize the cost estimating process used to develop the 
final visioning phase estimate for the Silver Line BRT and to explain the details of each component 
of the estimate.    This estimate was developed from the design analysis done during the final 
visioning process.   The intent of this estimate is to provide a preliminary cost to provide 
information to Interurban Transit Partnership (ITP) – The Rapid and the Federal Transit Authority 
(FTA) to confirm that the project is within budget as an aid in moving the project forward to the 
final design and construction phases. 
 
To verify the cost estimate method and assumptions the study team met with representatives from 
the  ITP.    The  final  estimate  includes  the  changes  as  discussed  at  the  meeting  and  the  notes  are 
attached in Appendix A. 
 

2.0 FTA Estimate Template 
 
The FTA cost estimating spreadsheet template was used to summarize the cost estimate 
components calculated for the Silver Line BRT.   The spreadsheet utilizes Standard Cost Categories 
(SCC) established by the FTA to allow for a consistent cost format and convenient comparison to 
the EA estimate for this project.   The SCC list is separated into 10 categories; the full SCC category 
list and SCC definitions are included in Appendix B. 
 

3.0 EA Estimate and Budget Control 
 
The EA estimate developed by AECOM on 3/16/2010 as shown in Appendix C, was provided to the 
design team as a starting point for the cost estimating efforts.   The EA estimate was initially 
updated to provide a base estimate to fit with the available $30 million budget for the very small 
starts project application to the FTA.  The following is a list of modifications initially made to the EA 
estimate at the beginning of phase I, by the design team in order to confirm that the Total Project 
Cost at the Year of Expenditure was controlled to meet the budget; 
 
 
 
BRT Vehicles 
Traffic Concepts Report 
Page 1 
 
 

The cost of vehicles (SCC 70.04 = $8 million) and spare parts (SCC 70.07 = $0.26 million) were 
removed from the EA estimate.  These items were added back in for the final phase I estimate. 
 
Contingency Change 
The EA estimate had a variable contingency rate which the design team adjusted to bring it in‐line 
with contingency percentages experienced on previous projects to suit the early stage of this 
project.  The adjusted contingency was calculated as 33 percent of the total 2010 cost for each SCC 
item, kept consistent to the EA estimate.   A consistent 33 percent contingency was applied to all 
SCC items.  Note that 33 percent contingency calculated for each revised SCC item in the final phase 
I estimate.  
 
Unallocated Contingency 
The unallocated contingency was adjusted to round the total project cost up to the $30 million 
project budget. Note that the final phase I estimate includes a flat $1 million. 
 

4.0 Detailed Estimate 
 
The design team developed detailed cost estimates to feed into each of the SCC categories.  Each 
detailed estimate was developed based on the design done for the final visioning phase, and then 
given a 33 percent contingency in the main SCC worksheet to account for unknowns in design, 
adjustments to unit costs, and final quantities.   All costs are based on 2010 dollars. 
 
4.1 Stations 
The station estimate includes all cost items associated with the station canopy and the concrete pad 
foundation and is shown is Appendix D.  It also includes the following items integral to the station; 
 trees 
 benches and bike racks 
 station lighting 
 electrical  
 
The unit costs for the station estimate were based on the Euclid Corridor bid tabs and escalated by 
3% annually to 2010 dollars. 
 
4.2 Roadway 
The roadway estimate includes all costs associated with SCC items 10.02 (Guideway – concrete bus 
pad), 10.03 (At‐grade in Mixed Traffic), 20.01 (At‐grade Station), 40.02 (Site Utilities/Utility 
Relocations) and is detailed in Appendix D.  The unit costs under roadway tasks are based on the 
2010 MDOT Average Unit Prices.  The unit costs were selected based on similar small projects 
within the same geographical area to ensure conservative costs were used. 
  
10.02 Guideway – concrete bus pad 
SCC 10.02 includes cost items associated with the in‐road concrete bus pad such as pavement 
removal, concrete, earthwork and manhole adjustments 
 
 
10.03 At­grade in Mixed Traffic 

  
Cost Estimate Report 
Page 2 
 
SCC 10.03 includes cost items associated with Maintenance of Traffic for the construction of all
construction components.

20.01 At-grade Station


SCC 20.01 At-grade Station includes cost items associated with civil works behind the edge of
roadway, including curb and gutter, sidewalk, removal items, drainage, and earthwork. This item
also includes the station costs discussed in Section 4.1.

40.02 Site Utilities/Utility Relocations


SCC 40.02 Site Utilities/Utility Relocations includes all public utilities including water, sewer, and
electrical items owned and operated by municipalities. Private utilities are not included in this
estimate. For a full list of items not included in the estimate please refer to Section 6.0.

4.3 Signal Prioritization, Operations, and Communications


The detailed cost estimates associated with 50.02 Traffic signals and crossing protection, 50.05
Communications, and 50.06 Fare collection system and equipment, are prioritized in detail in
technical paper Bus Operations, Traffic Signals, and Communications Concept Report. The
detailed spreadsheet estimate for these items is included in Appendix D.

The following cost items are detailed in Appendix D;

50.01 Traffic signals and crossing protection


SCC 50.01 Traffic signals and crossing protection includes the cost to provide traffic signal
preemption for the Silver Line BRT. The components include Transit Priority System at Signals
where not currently located, Transit Priority System for all BRT vehicles, and Transit Priority
System Communications and Adjustments.

50.05 Communications
SCC 50.05 Communications includes all items relating to communication infrastructure at the
stations and at the main office.

50.06 Fare collection system and other station equipment


SCC 50.06 Fare collection system and other station equipment includes all items relating to station
fare collection and station communication.

Cost Estimate Report


Page 3
5.0 Final FTA Main Worksheet Estimate
The final FTA Main Worksheet estimate based on the concept design is shown in Figure 1. This
estimate is compiled from the detailed cost estimates. The worksheet calculates the year of
expenditure costs based on a construction schedule of 2012-2013, and a year of revenue operations
of 2014. The inflation worksheet is included in Appendix E.

Cost Items Not Revised


The following cost items that were carried over from the EA estimate unchanged;

• 30.02 Light Maintenance Facility


• 60.01 Purchase or lease of real estate
• 70.04 Bus

80 Professional Services
SCC items under SCC 80 - Professional Services were updated as percentage costs based on the total
base year construction sub-total (SCC 10 through 50) cost estimate. Table 1.0 shows a summary of
each professional service task and the percentage of the construction sub-total;

Table 5-1 Professional Service Percentages


80.01 Preliminary Engineering 5%
80.02 Final Design 10%
80.03 Project Management for Design and Construction 2%
80.04 Construction Administration & Management 10%
80.08 Start up 10%

Cost Estimate Report


Page 4
Figure 1 – Final FTA Main Worksheet Estimate

MAIN WORKSHEET-BUILD ALTERNATIVE (Rev.13, June 1, 2010)


Today's
Interurban Transit Partnership - THE RAPID (construction with 33% contingency) 12/30/10
Date
Yr of Base
Division Avenue BRT - Cities of Grand Rapids, Kentwood, and Wyoming, Michigan 2010
Year $
Project Development Phase (Very Small Starts) Yr of Revenue Ops 2014

Quantity Base Year Base Year Base Year Base Year Base Year Base Year YOE Dollars
Dollars Dollars
Dollars w/o Dollars Dollars Dollars Unit Total
Percentage Percentage
Contingency Allocated TOTAL Cost of of (X000)
(X000) Contingency (X000) (X000) Construction Total
(X000) Cost Project Cost

10 GUIDEWAY & TRACK ELEMENTS (route miles) 9.60 1,241 410 1,651 $ 172 10% 5% 1,799
10.01 Guideway: At-grade exclusive right-of-way 0 0
10.02 Guideway: At-grade semi-exclusive (allows cross-traffic) 9.60 188 62 250 $ 26 273
10.03 Guideway: At-grade in mixed traffic 1,053 347 1,400 1,526
10.04 Guideway: Aerial structure 0 0
10.05 Guideway: Built-up fill 0 0
10.06 Guideway: Underground cut & cover 0 0
10.07 Guideway: Underground tunnel 0 0
10.08 Guideway: Retained cut or fill 0 0
10.09 Track: Direct fixation 0 0
10.10 Track: Embedded 0 0
10.11 Track: Ballasted 0 0
10.12 Track: Special (switches, turnouts) 0 0
10.13 Track: Vibration and noise dampening 0 0
20 STATIONS, STOPS, TERMINALS, INTERMODAL (number) 33 5,878 1,940 7,818 $ 237 47% 24% 8,521
20.01 At-grade station, stop, shelter, mall, terminal, platform 33 5,878 1,940 7,818 $ 237 8,521
20.02 Aerial station, stop, shelter, mall, terminal, platform 0 0
20.03 Underground station, stop, shelter, mall, terminal, platform 0 0
20.04 Other stations, landings, terminals: Intermodal, ferry, trolley, etc. 0 0
20.05 Joint development 0 0
20.06 Automobile parking multi-story structure 0 0
20.07 Elevators, escalators 0 0
30 SUPPORT FACILITIES: YARDS, SHOPS, ADMIN. BLDGS 9.60 218 72 290 $ 30 2% 1% 316
30.01 Administration Building: Office, sales, storage, revenue counting 0 0
30.02 Light Maintenance Facility 218 72 290 316
30.03 Heavy Maintenance Facility 0 0
30.04 Storage or Maintenance of Way Building 0 0
30.05 Yard and Yard Track 0 0
40 SITEWORK & SPECIAL CONDITIONS 9.60 745 246 991 $ 103 6% 3% 1,080
40.01 Demolition, Clearing, Earthwork 0 0
40.02 Site Utilities, Utility Relocation 245 81 326 355
40.03 Haz. mat'l, contam'd soil removal/mitigation, ground water treatments 0 0
40.04 Environmental mitigation, e.g. wetlands, historic/archeologic, parks 0 0
40.05 Site structures including retaining walls, sound walls 0 0
40.06 Pedestrian / bike access and accommodation, landscaping 0 0
40.07 Automobile, bus, van accessways including roads, parking lots 0 0
40.08 Temporary Facilities and other indirect costs during construction 500 165 665 725
50 SYSTEMS 9.60 4,460 1,472 5,932 $ 618 36% 18% 6,465
50.01 Train control and signals 0 0
50.02 Traffic signals and crossing protection 370 122 492 536
50.03 Traction power supply: substations 0 0
50.04 Traction power distribution: catenary and third rail 0 0
50.05 Communications 885 292 1,177 1,283
50.06 Fare collection system and equipment 3,205 1,058 4,263 4,646
50.07 Central Control 0 0
Construction Subtotal (10 - 50) 9.60 12,542 4,139 16,681 $ 1,738 100% 51% 18,182
60 ROW, LAND, EXISTING IMPROVEMENTS 9.60 489 161 650 $ 68 2% 673
60.01 Purchase or lease of real estate 489 161 650 673
60.02 Relocation of existing households and businesses 0 0
70 VEHICLES (number) 10 5,741 1,894 7,635 $ 763 23% 8,402
70.01 Light Rail 0 0
70.02 Heavy Rail 0 0
70.03 Commuter Rail 0 0
70.04 Bus 10 5,562 1,835 7,397 $ 740 8,140
70.05 Other 179 59 238 262
70.06 Non-revenue vehicles 0 0
70.07 Spare parts 0 0
80 PROFESSIONAL SERVICES (applies to Cats. 10-50) 9.60 4,641 1,531 6,172 $ 643 37% 19% 6,558
80.01 Preliminary Engineering 627 207 834 886
80.02 Final Design 1,254 414 1,668 1,772
80.03 Project Management for Design and Construction 251 83 334 354
80.04 Construction Administration & Management 1,254 414 1,668 1,772
80.05 Professional Liability and other Non-Construction Insurance 0 0
80.06 Legal; Permits; Review Fees by other agencies, cities, etc. 0 0
80.07 Surveys, Testing, Investigation, Inspection 0 0
80.08 Start up 1,254 414 1,668 1,772
Subtotal (10 - 80) 9.60 23,412 7,726 31,138 $ 3,244 95% 33,814
90 UNALLOCATED CONTINGENCY 1,000 3% 1,090
Subtotal (10 - 90) 9.60 32,138 $ 3,348 98% 34,904
100 FINANCE CHARGES 760 2% 822
Total Project Cost (10 - 100) 9.60 32,898 $ 3,427 100% 35,726
Allocated Contingency as % of Base Yr Dollars w/o Contingency 33.00%
Unallocated Contingency as % of Base Yr Dollars w/o Contingency 4.27%
Total Contingency as % of Base Yr Dollars w/o Contingency 37.27%
Unallocated Contingency as % of Subtotal (10 - 80) 3.21%
YOE Construction Cost per Mile (X000) $1,894
YOE Total Project Cost per Mile Not Including Vehicles (X000) $2,846
YOE Total Project Cost per Mile (X000) $3,721

Cost Estimate Report
Page 5
 

6.0 Items Not Included in Worksheet 
 
Several cost items were not included in this estimate that could present additional cost to the 
project if they occur.   
 
New traffic signals or Signal controllers 
Possible upgrades to traffic signals may be possible in the future that could have cost impact to the 
Silver Line BRT.  An allowance of $250,000 to upgrade signals and one intersection are included in 
SCC line item 50.02  
 
ADA ramps 
Most intersections already have ADA ramps but not locations impacted by the Silver Line BRT have 
been verified 
 
Park’n’Ride 
An area at the southern end of the project could potentially attract commuters to used the Silver 
Line BRT system.  This item is to be determined as part of future studies 
 
Private utility relocations 
It is common for private utilities to pay for utility relocations within city ROW however there are 
some cases where some or all of the cost would be borne by the land owner. 
 
Facility for CCTV monitoring 
Not currently scoped for the project, but a feature that could be added in during the design phase. 
 
Programming etc. for Internet Kiosk 
The cost to program the internet kiosk that will be located at each station depends greatly on the 
intended function of the kiosk, much of which will be established during the design phase. 
 
Significant plantings and irrigation system 
Dependent on decisions made during the design phase 
 
Snow Melt System 
Dependent on decisions made during the design phase 

Other costs are anticipated as part of the project classified as system amenities that were not 
designed during the visioning phase but were developed as draft plug costs that are included under 
SCC 70.05 – Other, in the Final FTA Main Worksheet Estimate as plug costs. 
 
 GPS Signal Prioritization = $76,000 
 Pedestrian signals (upgrades needed at 14 of the total 18 stations) = $28,000 
 AVL System Changes = $75,000 
 33 percent contingency = $59,000 
 Total = $238,000 

  
Cost Estimate Report 
Page 6 
 
APPENDICES

Cost Estimate Report


Appendix A

Cost Estimate Meeting

Cost Estimate Report


ITP - The Rapid Silver Line BRT

Memorandum
TO: Attendees
File

FROM: Wilbur Smith Associates

DATE: November 17, 2010

SUBJECT: Cost Estimate Meeting Minutes

PROJECT: Silver Line BRT Project

Date/Time: November 16, 2010 at 1:00 p.m.

Location: Interurban Transit Partnership – The Rapid Office


300 Ellsworth Avenue SW
Grand Rapids, MI 49503

Attendees: See attached sign-in sheet

The following represents our understanding of the key points of discussion at the meeting with The Rapid
and other members of the Project Team. If anything appears misrepresented, please let us know.

Cost Estimate Items Not Included

New crosswalk locations


• Because the crossings aren’t warranted pedestrian signals will not be permitted by
MDOT and would not be funded by FTA.
• Tai asked what increase in cost it would be for new crossings. Approximately $100K
typical, $150K for more complicated crossings.

LEED @ Stations?
• May not be required based on square footage
• Avoid rain barrels, consider using runoff water for tree plantings
• Utilizing local vendors/contractors

Snow Melt System


• Currently BRT doesn’t remove snow at stops
• Rapid requested WSA provide capital costs, operational costs and any experience with
the system.
• If infrastructure is there (steam lines/hot water), it might be beneficial
• Ralph suggested waiting until Design Phase to do research into what it will take to
provide snow melt at stations

8164 Executive Court, Suite A – Lansing, Michigan 48917 517.622.2500 Fax: 517.622.2525
ITP - The Rapid Silver Line BRT
The Rapid requested WSA look at adding cost breakdown/estimate for additional cost items. Tai would
rather have an item for system amenities with a cost that can be presented to the Board if need be.
Additional items included in the “system amenities” will be:
• GPS/Radio detectors at each signal for transit priority and emergency vehicle preemption.
• Countdown pedestrian signals and new pedestrian call buttons.
• AVL upgrades to support “Next Bus” information (cost from Rapid’s AVL vendor)

Cost Estimate Review

o Add vehicles to estimate with a year of expenditure 2013 ($8.2M) including contingency

Stations

o Last station at 54th St. (SB) can be scaled back as most alight at this point and don’t wait for a bus
o A ticket vending machine might not be required at the last station

Ticketing vending machines

o average of one per station


o Multiple vending machines may be considered at high traveled stations and reserve vending
machines should be on hand for replacement/maintenance. WSA will add 7 additional to round
quantity up to 40

Ticketing and Media Kiosk

o Add additional cost for larger kiosk (as shown on station illustration)

Bike Rack
o Bike rack quantity will be doubled to provide more capacity at high traveled stations
• Bike groups may want to include their own design

40.8 Temporary Facilities during Construction


o Due to the length of project, Tai suggested facilities for the inspector be provided and suggested
adding it to Section 30 of the estimate

The Rapid suggested that the FTA’s definition be included for each line item for presentation to the
board.

It was agreed that all the miscellaneous items be listed individually with the 33% contingency rather than
assume they are part of the contingency amount.

Action Items

Gary will send estimate comments to WSA on Friday, 11/19.


WSA will send hard copies of station plans to BRT for their review by Monday, 11/22.
WSA will send word version of Communication, Traffic, and Bus Operations Report to Gary on
Wednesday, 11/17 for his use in providing comments.

8164 Executive Court, Suite A – Lansing, Michigan 48917 517.622.2500 Fax: 517.622.2525
ITP - The Rapid Silver Line BRT

8164 Executive Court, Suite A – Lansing, Michigan 48917 517.622.2500 Fax: 517.622.2525
Appendix B

SCC category list and SCC definitions

Cost Estimate Report


Standard Cost Categories for Capital Projects
(Rev.13, June 1, 2010)
10 GUIDEWAY & TRACK ELEMENTS (route miles)
10.01 Guideway: At-grade exclusive right-of-way
10.02 Guideway: At-grade semi-exclusive (allows cross-traffic)
10.03 Guideway: At-grade in mixed traffic
10.04 Guideway: Aerial structure
10.05 Guideway: Built-up fill
10.06 Guideway: Underground cut & cover
10.07 Guideway: Underground tunnel
10.08 Guideway: Retained cut or fill
10.09 Track: Direct fixation
10.10 Track: Embedded
10.11 Track: Ballasted
10.12 Track: Special (switches, turnouts)
10.13 Track: Vibration and noise dampening
20 STATIONS, STOPS, TERMINALS, INTERMODAL (number)
20.01 At-grade station, stop, shelter, mall, terminal, platform
20.02 Aerial station, stop, shelter, mall, terminal, platform
20.03 Underground station, stop, shelter, mall, terminal, platform
20.04 Other stations, landings, terminals: Intermodal, ferry, trolley, etc.
20.05 Joint development
20.06 Automobile parking multi-story structure
20.07 Elevators, escalators
30 SUPPORT FACILITIES: YARDS, SHOPS, ADMIN. BLDGS
30.01 Administration Building: Office, sales, storage, revenue counting
30.02 Light Maintenance Facility
30.03 Heavy Maintenance Facility
30.04 Storage or Maintenance of Way Building
30.05 Yard and Yard Track
40 SITEWORK & SPECIAL CONDITIONS
40.01 Demolition, Clearing, Earthwork
40.02 Site Utilities, Utility Relocation
40.03 Haz. mat'l, contam'd soil removal/mitigation, ground water treatments
40.04 Environmental mitigation, e.g. wetlands, historic/archeologic, parks
40.05 Site structures including retaining walls, sound walls
40.06 Pedestrian / bike access and accommodation, landscaping
40.07 Automobile, bus, van accessways including roads, parking lots
40.08 Temporary Facilities and other indirect costs during construction
50 SYSTEMS
50.01 Train control and signals
50.02 Traffic signals and crossing protection
50.03 Traction power supply: substations
50.04 Traction power distribution: catenary and third rail
50.05 Communications
50.06 Fare collection system and equipment
50.07 Central Control
60 ROW, LAND, EXISTING IMPROVEMENTS
60.01 Purchase or lease of real estate
60.02 Relocation of existing households and businesses
70 VEHICLES (number)
70.01 Light Rail
70.02 Heavy Rail
70.03 Commuter Rail
70.04 Bus
70.05 Other
70.06 Non-revenue vehicles
70.07 Spare parts
80 PROFESSIONAL SERVICES (applies to Cats. 10-50)
80.01 Preliminary Engineering
80.02 Final Design
80.03 Project Management for Design and Construction
80.04 Construction Administration & Management
80.05 Professional Liability and other Non-Construction Insurance
80.06 Legal; Permits; Review Fees by other agencies, cities, etc.
80.07 Surveys, Testing, Investigation, Inspection
80.08 Start up
90 UNALLOCATED CONTINGENCY
100 FINANCE CHARGES
NOTE: The SCC cost breakdown is based on a traditional Design Bid Build model. If
Standard Cost Categories for Capital Projects your project is Design Build, to the best of your ability, separate construction costs from
DEFINITIONS design, administration, testing, etc. Put all construction costs in 10 through 50. Put
design, administration, testing, etc. in 80 Professional Services .
(Rev.13, June 1, 2010)
Include guideway and track costs for all transit modes (Heavy rail, light rail, commuter
rail, BRT, rapid bus, bus, monorail, cable car, etc.) The unit of measure is route miles of
guideway, regardless of width. As associated with the guideway, include costs for rough
grading, excavation, and concrete base for guideway where applicable. Include all
construction materials and labor regardless of whom is performing the work.
10 GUIDEWAY & TRACK ELEMENTS (route miles)
In your written description of the scope and in supporting graphic diagrams, indicate
whether busway or rail track is single, double, triple, relocated, etc. Put guideway and
track elements associated with yards in 30 Support Facilities below.

10.01 Guideway: At-grade exclusive right-of-way


10.02 Guideway: At-grade semi-exclusive (allows cross-traffic)
10.03 Guideway: At-grade in mixed traffic
Include foundation excavation; guideway structures including caissons, columns,
10.04 Guideway: Aerial structure
bridges, viaducts, cross-overs, fly-overs.
10.05 Guideway: Built-up fill Include construction of earthen berms.
Include excavation, retaining walls, backfill, underground guideway structure and
10.06 Guideway: Underground cut & cover
finishes.
Include tunneling by means of a tunnel boring machine, drill blasting, mining, and
10.07 Guideway: Underground tunnel
immersed tube tunneling; tunnel structure and finishes.
Include excavation, retaining walls, backfill, underground guideway structure and
10.08 Guideway: Retained cut or fill
finishes.
10.09 Track: Direct fixation Include rails, connectors.
10.10 Track: Embedded Include rails, ties; ballast where applicable
10.11 Track: Ballasted Include rails, ties and ballast.
10.12 Track: Special (switches, turnouts) Include transitional curves.
10.13 Track: Vibration and noise dampening Include upcharge for vib/noise dampening to any track condition above.
As associated with stations, include costs for rough grading, excavation, station
structures, enclosures, finishes, equipment; mechanical and electrical components
including HVAC, ventilation shafts and equipment, station power, lighting, public
address/customer information system, safety systems such as fire detection and
20 STATIONS, STOPS, TERMINALS, INTERMODAL (number) prevention, security surveillance, access control, life safety systems, etc. Include all
construction materials and labor regardless of whom is performing the work.

Put guideway and track associated with stations in 10 Guideway & Track Elements
above.
20.01 At-grade station, stop, shelter, mall, terminal, platform
20.02 Aerial station, stop, shelter, mall, terminal, platform Include station structures including caissons, columns, platforms, superstructures, etc.
20.03 Underground station, stop, shelter, mall, terminal, platform Include retaining walls, backfill, structure.
20.04 Other stations, landings, terminals: Intermodal, ferry, trolley, etc.
Per FTA's Joint Development Guidance, "Joint development is any income-producing
activity with a transit nexus related to a real estate asset in which FTA has an interest. .
20.05 Joint development .Joint development projects are commercial, residential, industrial, or mixed-use
developments that are induced by or enhance the effectiveness of transit projects. . ."

20.06 Automobile parking multi-story structure Include retaining walls, backfill, structure.
20.07 Elevators, escalators
As associated with support facilities, include costs for rough grading, excavation, support
structures, enclosures, finishes, equipment; mechanical and electrical components
including HVAC, ventilation shafts and equipment, facility power, lighting, public address
system, safety systems such as fire detection and prevention, security surveillance,
access control, life safety systems, etc. Include fueling stations. Include all construction
materials and labor regardless of whom is performing the work.
30 SUPPORT FACILITIES: YARDS, SHOPS, ADMIN. BLDGS

Where a support facility shares the structure with a station, its cost may be included with
station cost. Identify this with a note.
Except for guideway and track associated with a yard, include all guideway and track
costs associated with support facilities in 10 Guideway & Track Elements above.

30.01 Administration Building: Office, sales, storage, revenue counting


30.02 Light Maintenance Facility Include service, inspection, and storage facilities and equipment.
30.03 Heavy Maintenance Facility Include heavy maintenance and overhaul facilities and equipment.
30.04 Storage or Maintenance of Way Building
30.05 Yard and Yard Track Include yard construction, guideway and track associated with yard.
40 SITEWORK & SPECIAL CONDITIONS Include all construction materials and labor regardless of whom is performing the work.
40.01 Demolition, Clearing, Earthwork Include project-wide clearing, demolition and fine grading.
40.02 Site Utilities, Utility Relocation Include all site utilities - storm, sewer, water, gas, electric.
Include underground storage tanks, fuel tanks, other hazardous materials and
40.03 Haz. mat'l, contam'd soil removal/mitigation, ground water treatments
treatments, etc.
40.04 Environmental mitigation, e.g. wetlands, historic/archeologic, parks Include other environmental mitigation not listed.
40.05 Site structures including retaining walls, sound walls
Include sidewalks, paths, plazas, landscape, site and station furniture, site lighting,
40.06 Pedestrian / bike access and accommodation, landscaping
signage, public artwork, bike facilities, permanent fencing.
40.07 Automobile, bus, van accessways including roads, parking lots Include all on-grade paving.
As a general rule and to the extent possible, appropriately allocate indirect costs among
the construction costs in Categories 10 through 50. Where that is not possible, include
in 40.08 Temporary Facilities costs for mobilization, demobilization, phasing; time and
temporary construction associated with weather (heat, rain, freezing, etc.); temporary
power and facilities; temporary construction, easements, and barriers for storm water
40.08 Temporary Facilities and other indirect costs during construction pollution prevention, temporary access and to mitigate construction impacts; project and
construction supervision; general conditions, overhead, profit.
NOTE: Include contractor's general liability and other insurance related to
construction such as builder's risk in Cats. 10 - 50, not in 80 Professional
Services below.

50 SYSTEMS Include all construction materials and labor regardless of whom is performing the work.

50.01 Train control and signals


50.02 Traffic signals and crossing protection Include signal prioritization at intersections.
50.03 Traction power supply: substations
50.04 Traction power distribution: catenary and third rail
Include passenger information systems at stations and on vehicles (real time travel
50.05 Communications information; static maps and schedules).
Include equipment to allow communications among vehicles and with central control.
50.06 Fare collection system and equipment Include fare sales and swipe machines, fare counting equipment.
50.07 Central Control
Construction Subtotal (10 - 50)
Include professional services associated with the real estate component of the
60 ROW, LAND, EXISTING IMPROVEMENTS project. These costs may include agency staff oversight and administration, real
estate and relocation consultants, legal counsel, court expenses, insurance, etc.
If the value of right-of-way, land, and existing improvements is to be used as local match
to the Federal funding of the project, include the total cost on this line item. In backup
documentation, separate cost for land from cost for improvements. Identify whether items
60.01 Purchase or lease of real estate are leased, purchased or acquired through payment or for free. Include the costs for
permanent surface and subsurface easements, trackage rights, etc.

60.02 Relocation of existing households and businesses In compliance with Uniform Relocation Act.
Include professional services associated with the vehicle component of the
project. These costs may include agency staff oversight and administration,
70 VEHICLES (number)
vehicle consultants, design and manufacturing contractors, legal counsel,
warranty and insurance costs, etc.
70.01 Light Rail Include light rail and streetcar rail using electric, diesel or other power supply.
70.02 Heavy Rail
Include locomotives (diesel, electric, or other), trailer cars, self-propelled multiple units
70.03 Commuter Rail
(EMU electric or DMU diesel, or other power supply)
Includes "rubber-tired" buses and trolleys including new, used, historic replica,
70.04 Bus
articulated, using electric, diesel, dual-power, or other power supply.
Include Vans, Sedan/Station Wagon, Cable Car, People Mover, Monorail, Car/Inclined
70.05 Other
Railway, Ferry Boat, Transferred Vehicle
70.06 Non-revenue vehicles
70.07 Spare parts
80 PROFESSIONAL SERVICES (applies to Cats. 10-50) Cat. 80 applies to Cats. 10-50. Cat. 80 includes all professional, technical and
management services related to the design and construction of fixed infrastructure (Cats.
10 - 50) during the preliminary engineering, final design, and construction phases of the
80.01 Preliminary Engineering
project. This includes environmental work, design, engineering and architectural
services; specialty services such as safety or security analyses; value engineering, risk
assessment, cost estimating, scheduling, Before and After studies, ridership modeling
80.02 Final Design
and analyses, auditing, legal services, administration and management, etc. by agency
staff or outside consultants.
80.03 Project Management for Design and Construction
Include professional liability insurance and other non-construction insurance on 80.05
unless insurance for the agency and its consultants is already included in other lines.
80.04 Construction Administration & Management
Include costs associated with professional services related to real estate and vehicles in
Cats. 60 and 70.
80.05 Professional Liability and other Non-Construction Insurance
(Note that costs for alternatives analysis and NEPA work done before FTA approval to
enter preliminary engineering (PE), regardless of funding source,
are not included in an FFGA and therefore, should not be included in the
80.06 Legal; Permits; Review Fees by other agencies, cities, etc.
Standard Cost Category worksheets. For example, on one and the same grant, costs
incurred prior to FTA approval to enter PE should be omitted from these worksheets
whereas costs incurred after FTA approval to enter PE should be included.)
80.07 Surveys, Testing, Investigation, Inspection

Include start up and training. Include in Cats. 10 - 50 above access and protection work
80.08 Start up by agency staff or outside contractors.
Subtotal (10 - 80)
Includes unallocated contingency, project reserves. Document allocated contingencies
90 UNALLOCATED CONTINGENCY
for individual line items on the Main worksheets.
Subtotal (10 - 90)
Include finance charges expected to be paid by the project sponsor/grantee prior to
either the completion of the project or the fulfillment of the New Starts funding
commitment, whichever occurs later in time. Finance charges incurred after this date
should not be included in Total Project Cost. (See FFGA Circular FTA C5200.1A
Chapter III for additional information.)
100 FINANCE CHARGES
Derive finance charges from the New Starts project's financial plan, based on an
analysis of the sources and uses of funds. The amount and type of debt financing
required and revenues available determine the finance charges. By year, compute
finance charges in year-of-expenditure (YOE) dollars. On the Inflation Calculation to
YOE worksheet enter the finance charges for the appropriate years.
Total Project Cost (10 - 100)
Appendix C

EA estimate

Cost Estimate Report


MAIN WORKSHEET-BUILD ALTERNATIVE (Rev.12, July 31, 2009)

Interurban Transit Partnership - THE RAPID (Revised 3/16/2010 to FY2010 Base Year) Today's Date 3/16/10

Division Avenue BRT - Cities of Grand Rapids, Kentwood, and Wyoming, Michigan Yr of Base Year $ 2010

Project Development Phase (Very Small Starts) Yr of Revenue Ops 2013

Quantity Base Year Base Year Base Year Base Year Base Year Base Year YOE Dollars
Dollars w/o Dollars Dollars Dollars Unit Dollars Dollars Total
Percentage Percentage
Contingency Allocated TOTAL Cost of of
(X000)
(X000) Contingency (X000) (X000) Construction Total
(X000) Cost Project Cost

10 GUIDEWAY & TRACK ELEMENTS (route miles) 9.60 2,880 432 3,312 $ 345 20% 10% 3,723
10.01 Guideway: At-grade exclusive right-of-way 0 0
10.02 Guideway: At-grade semi-exclusive (allows cross-traffic) 0 0
10.03 Guideway: At-grade in mixed traffic 9.60 2,880 432 3,312 $ 345 3,723
10.04 Guideway: Aerial structure 0 0
10.05 Guideway: Built-up fill 0 0
10.06 Guideway: Underground cut & cover 0 0
10.07 Guideway: Underground tunnel 0 0
10.08 Guideway: Retained cut or fill 0 0
10.09 Track: Direct fixation 0 0
10.10 Track: Embedded 0 0
10.11 Track: Ballasted 0 0
10.12 Track: Special (switches, turnouts) 0 0
10.13 Track: Vibration and noise dampening 0 0
20 STATIONS, STOPS, TERMINALS, INTERMODAL (number) 18 6,873 1,030 7,903 $ 439 47% 24% 8,898
20.01 At-grade station, stop, shelter, mall, terminal, platform 18 6,873 1,030 7,903 $ 439 8,898
20.02 Aerial station, stop, shelter, mall, terminal, platform 0 0
20.03 Underground station, stop, shelter, mall, terminal, platform 0 0
20.04 Other stations, landings, terminals: Intermodal, ferry, trolley, etc. 0 0
20.05 Joint development 0 0
20.06 Automobile parking multi-story structure 0 0
20.07 Elevators, escalators 0 0
30 SUPPORT FACILITIES: YARDS, SHOPS, ADMIN. BLDGS 9.60 250 40 290 $ 30 2% 1% 333
30.01 Administration Building: Office, sales, storage, revenue counting 0 0
30.02 Light Maintenance Facility 250 40 290 333
30.03 Heavy Maintenance Facility 0 0
30.04 Storage or Maintenance of Way Building 0 0
30.05 Yard and Yard Track 0 0
40 SITEWORK & SPECIAL CONDITIONS 9.60 760 118 878 $ 91 5% 3% 973
40.01 Demolition, Clearing, Earthwork 0 0
40.02 Site Utilities, Utility Relocation 720 108 828 918
40.03 Haz. mat'l, contam'd soil removal/mitigation, ground water treatments 0 0
40.04 Environmental mitigation, e.g. wetlands, historic/archeologic, parks 0 0
40.05 Site structures including retaining walls, sound walls 0 0
40.06 Pedestrian / bike access and accommodation, landscaping 40 10 50 55
40.07 Automobile, bus, van accessways including roads, parking lots 0 0
40.08 Temporary Facilities and other indirect costs during construction 0 0
50 SYSTEMS 9.60 3,875 581 4,456 $ 464 26% 13% 5,028
50.01 Train control and signals 0 0
50.02 Traffic signals and crossing protection 1,702 255 1,957 2,208
50.03 Traction power supply: substations 0 0
50.04 Traction power distribution: catenary and third rail 0 0
50.05 Communications 1,014 152 1,166 1,316
50.06 Fare collection system and equipment 1,159 174 1,333 1,504
50.07 Central Control 0 0
Construction Subtotal (10 - 50) 9.60 14,638 2,201 16,839 $ 1,754 100% 51% 18,955
60 ROW, LAND, EXISTING IMPROVEMENTS 9.60 500 150 650 $ 68 2% 708
60.01 Purchase or lease of real estate 500 150 650 708
60.02 Relocation of existing households and businesses 0 0
70 VEHICLES (number) 10 6,612 653 7,265 $ 727 22% 8,201
70.01 Light Rail 0 0
70.02 Heavy Rail 0 0
70.03 Commuter Rail 0 0
70.04 Bus 10 6,400 632 7,032 $ 703 7,938
70.05 Other 0 0
70.06 Non-revenue vehicles 0 0
70.07 Spare parts 212 21 233 263
80 PROFESSIONAL SERVICES (applies to Cats. 10-50) 9.60 4,103 332 4,435 $ 462 26% 13% 4,804
80.01 Preliminary Engineering 970 50 1,020 1,105
80.02 Final Design 560 60 620 672
80.03 Project Management for Design and Construction 170 27 197 213
80.04 Construction Administration & Management 1,550 80 1,630 1,766
80.05 Professional Liability and other Non-Construction Insurance 0 0 0 0
80.06 Legal; Permits; Review Fees by other agencies, cities, etc. 0 0 0 0
80.07 Surveys, Testing, Investigation, Inspection 550 70 620 672
80.08 Start up 303 45 348 377
Subtotal (10 - 80) 9.60 25,853 3,336 29,189 $ 3,041 88% 32,667
90 UNALLOCATED CONTINGENCY 2,970 9% 3,309
Subtotal (10 - 90) 9.60 32,159 $ 3,350 97% 35,976
100 FINANCE CHARGES 917 3% 1,024
Total Project Cost (10 - 100) 9.60 33,076 $ 3,445 100% 37,000
Allocated Contingency as % of Base Yr Dollars w/o Contingency 12.90%
Unallocated Contingency as % of Base Yr Dollars w/o Contingency 11.49%
Total Contingency as % of Base Yr Dollars w/o Contingency 24.39%
Unallocated Contingency as % of Subtotal (10 - 80) 10.18%
YOE Construction Cost per Mile (X000) $1,974
YOE Total Project Cost per Mile Not Including Vehicles (X000) $3,000
YOE Total Project Cost per Mile (X000) $3,854
Appendix D

Detailed Estimates

Cost Estimate Report


Project Construction Cost Estimate
Silver Line BRT Transit Signal Priority Implementation

WSA Project No. 104601


Date of Estimate: 8-Dec-10
Specification Number
(DOT or CSI)
Description Estimated Unit Unit Price Price
Quantity 2010 Dollars Dollars

Opticom Priority System at Signals 5 Each $ 4,000 $ 20,000


Opticom Priority System for Vehicles 10 Each $ 2,200 $ 22,000
Opticom Priority System Communications and Adjustments 28 Each $ 1,000 $ 28,000
Transit Signal Heads 0 Each $ 1,000 $ -
New Masts and Mast Arms 0 Each $ 15,000 $ -
New Pedestrian Signal Heads and Call Buttons 0 Each $ 800 $ -
System Integration and Calibration 1 LS $ 50,000 $ 50,000
Potential new signal (per AECOM estimate) 1 LS $ 250,000 $ 250,000

50.02 Total Traffic Signal Construction Cost Estimate $ 370,000

Project Construction Cost Estimate


Silver Line BRT Transit Operations

WSA Project No. 104601


Date of Estimate: 11-Oct-10
Specification Number
(DOT or CSI)
Description Estimated Unit Unit Price Price
Quantity 2010 Dollars Dollars

Emergency Telephone with CCTV Camera 33 Each $ 5,509 $ 181,790


One Additional CCTV Camera 33 Each $ 2,200 $ 72,600
Fare Validation Device 33 Each $ 3,000 $ 99,000
Ticket Vending Machine 40 Each $ 45,000 $ 1,800,000
Smart Card Reader 33 Each $ 3,000 $ 99,000
Next Bus Sign With Audio 33 Each $ 10,000 $ 330,000
Ticket + Media Kiosk 33 Each $ 2,000 $ 66,000
Passenger Information Sign and Kiosk 33 Each $ 10,200 $ 336,600
Audio Station Announcement on the Bus 10 Each $ 1,000 $ 10,000
Station Software for Fare Collection 1 LS $ 10,000 $ 10,000
Central Software for Fare Collection 1 LS $ 200,000 $ 200,000

50.06 Total Transit Operations Construction Cost Estimate $ 3,204,990


Project Construction Cost Estimate
Silver Line BRT Office Communications

WSA Project No. 104601


Date of Estimate: 11-Oct-10
Specification Number
(DOT or CSI)
Description Estimated Unit Unit Price Price
Quantity 2010 Dollars Dollars

16147 Fiber Optic Cable, Aerial, 64 Fibers 0 Mile $ 38,000 $ -


16147 Fiber Optic Aerial Splice Closure 1 Each $ 1,100 $ 1,100
16147 Fiber Distribution Unit 1 Each $ 2,500 $ 2,500
16147 Fiber Optic Drop Installation 1 Each $ 2,000 $ 2,000
16160 Enclosure, Free Standing, NEMA 3R 0 Each $ 11,000 $ -
16160 Enclosure, Free Standing, NEMA 3R, Cooled 0 Each $ 15,000 $ -
16702 Switch / Router 3 Each $ 10,000 $ 30,000
16702 Uninterruptible Power Supply 1 Each $ 1,500 $ 1,500
16702 Miscellaneous Power Material 1 Lot $ 1,000 $ 1,000
16702 Wire and Cable 1 Lot $ 5,000 $ 5,000
16702 Network Video Recorder, 4 Channel 0 Each $ 8,000 $ -
16702 Network Video Recorder, 32 Channel 3 Each $ 12,000 $ 36,000
16702 Installation of MPLS Service 0 Each $ 5,000 $ -
16702 VoIP PBX Configuration 1 Each $ 25,000 $ 25,000
16702 CCTV Display Configuration 1 Each $ 50,000 $ 50,000
16702 Network Management System 1 Lot $ 50,000 $ 50,000

Office Communication Construction Cost Estimate $ 204,100

Project Construction Cost Estimate


Silver Line BRT Station Communications - Fiber Optic Cable Option

WSA Project No. 104601


Date of Estimate: 11-Oct-10
Specification Number
(DOT or CSI)
Description Estimated Unit Unit Price Price
Quantity 2010 Dollars Dollars

16147 Fiber Optic Cable, Aerial, 64 Fibers 4 Mile $ 38,000 $ 152,000


16147 Fiber Optic Aerial Splice Closure 17 Each $ 1,100 $ 18,700
16147 Fiber Distribution Unit 17 Each $ 2,500 $ 42,500
16147 Fiber Optic Drop Installation 17 Each $ 2,000 $ 26,000
16160 Enclosure, Free Standing, NEMA 3R 17 Each $ 11,000 $ 187,000
16160 Enclosure, Free Standing, NEMA 3R, Cooled 0 Each $ 15,000 $ -
16702 Switch / Router 17 Each $ 10,000 $ 170,000
16702 Uninterruptible Power Supply 17 Each $ 1,500 $ 25,500
16702 Miscellaneous Power Material 17 Lot $ 500 $ 8,500
16702 Wire and Cable 17 Lot $ 3,000 $ 51,000
16702 Network Video Recorder, 4 Channel 0 Each $ 6,000 $ -
16702 Network Video Recorder, 32 Channel 0 Each $ 12,000 $ -
16702 Installation of MPLS Service 0 Each $ 5,000 $ -
16702 VoIP PBX Configuration 0 Each $ 25,000 $ -
16702 CCTV Display Configuration 0 Each $ 50,000 $ -
16702 Network Management System 0 Lot $ 50,000 $ -

Station Communication Construction Cost Estimate $ 681,200

50.05 Total Communication Construction Cost Estimate $ 885,300


Project Construction Cost Estimate
Silver Line BRT Bus Stations

WSA Project No. 104601


Date of Estimate:

Bid Item Unit Price Source


Description Estimated Unit Unit Price Price bid tab year Unit price Escalated @
Quantity 2010 Dollars Dollars 3%
Per Pair
50' Station Alternate
Excavation 52 CY 13.44 $ 699 38-C04/7 2006 $ 12 $ 13.44
Select Backfill 12 CY 31.36 $ 376 38-C04/8 2006 $ 28 $ 31.36
Structural Concrete 40 CY 802.20 $ 32,088 38-C04/154 2006 $ 716 $ 802.20
Stainless Steel Columns (hot rolled) 4,400 LBS 5.00 $ 22,000 Plug $ -
Stainless Steel Roof Framing (cold formed) 8,400 LBS 5.00 $ 42,000 Plug $ -
Stainless Steel edge strut 4,080 LBS 5.00 $ 20,400 Plug $ -
Curtian Wall (sides) 528 SF 20.00 $ 10,560 Plug $ -
Curtian Wall (wind break) 288 SF 20.00 $ 5,760 Plug $ -
Additional Cost for Custom Station Design 1 LSUM 10,072.00 $ 10,072 Plug $ -
Ceiling 600 SF 20.00 $ 12,000 Plug $ -
3 inch caliper Tree 4 EA 812.00 $ 3,248 38-C04/275+274 2006 $ 725 $ 812.00
Benches 8 EA 2,800.00 $ 22,400 38-C04/277 2006 $ 2,500 $ 2,800.00
Bike Rack 4 EA 1,680.00 $ 6,720 38-C04/279 2006 $ 1,500 $ 1,680.00
Detectable Warning Paver 120 SF 19.04 $ 2,285 38-C04/239 2006 $ 17 $ 19.04
Underdrain 120 LF 11.20 $ 1,344 38-C04/52 2006 $ 10 $ 11.20
Signage Tower 6 EA 10,000.00 $ 60,000 Plug $ -
Station Electrical 2 EA 12,320.00 $ 24,640 38-C05B/104 2006 $ 11,000 $12,320.00
Station Lighting 40 EA 300.00 $ 12,000 Plug $ -
Duct Bank to Far Side Station (3x2) 170 LF 56.00 $ 9,520 38-C04/130 2006 $ 50 $ 56.00
Excavation and Pavement Repair for Duct Bank 170 LF 41.25 $ 7,013 38-C04/139+65 2006 $ 37 $ 41.25
Electrical Pole Foundation 1 EA 3,584.00 $ 3,584 38-C04/149 2006 $ 3,200 $ 3,584.00
Electrical Strain Pole 1 EA 3,696.00 $ 3,696 38-C05B/47 2006 $ 3,300 $ 3,696.00
25 Power Source 1 EA 1,120.00 $ 1,120 38-C05B/83 2006 $ 1,000 $ 1,120.00
Hand Holes 6 EA 448.00 $ 2,688 38-C04/142 2006 $ 400 $ 448.00
Underground Conduit 1,000 LF 1.12 $ 1,120 38-C04/133 2006 $ 1 $ 1.12
Station Ameneties (trash cans, recycling) 1 EA 2,000.00 $ 2,000 Plug $ -

Price per 50' Station Pair $ 319,333

Station Pairs 16.5 EA $ 319,333 $ 5,268,996


Project Construction Cost Estimate
Silver Line BRT System Ammenities

WSA Project No. 104601


Date of Estimate:

Bid Item Unit Price Source


Description Estimated Unit Unit Price Price bid tab year
Quantity 2010 Dollars Dollars
Per Pair
GPS Signal Prioritization (at signal) 28 EA 2,000.00 $ 56,000 PLUG
GPS Signal Prioritization (on bus) 10 EA 2,000.00 $ 20,000 PLUG
Pedestrian Signal System, Accessible 14 EA 2,000.00 $ 28,000 MDOT AUP 2010
AVL Upgrades 1 LSUM 75000 $ 75,000 PLUG

Total System $ 179,000


Project Construction Cost Estimate
Silver Line BRT

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/15/2010

Description Price (Dollars)


Cost Code Cost Code Cost Code Cost Code
10.02 10.03 20.01 40.02 Total
1 Louis Street Station NB $ 6,472.00 $ 5,500.00 $ 9,024.00 $ 8,575.00 $ 29,571.00
2 Louis Street Station SB $ 6,151.00 $ 5,500.00 $ 17,286.00 $ 8,575.00 $ 37,512.00
3 DeVos Place Station NB $ 5,239.00 $ 5,500.00 $ 9,096.00 $ 9,075.00 $ 28,910.00
4 DeVos Place Station SB $ 5,728.00 $ 5,500.00 $ 7,411.50 $ 11,575.00 $ 30,214.50
5 Michigan Street Station NB $ 6,268.00 $ 5,500.00 $ 12,627.50 $ 6,075.00 $ 30,470.50
6 Michigan Street Station SB $ 6,268.00 $ 5,500.00 $ 16,825.50 $ 12,075.00 $ 40,668.50
7 GRCC Station NB $ 8,876.00 $ 5,500.00 $ 6,855.50 $ 8,575.00 $ 29,806.50
8 GRCC Station SB $ 8,876.00 $ 5,500.00 $ 17,604.00 $ 6,075.00 $ 38,055.00
9 Fulton Street Station NB $ 5,178.00 $ 5,500.00 $ 7,287.50 $ 8,575.00 $ 26,540.50
10 Fulton Street Station SB $ 5,178.00 $ 5,500.00 $ 7,538.50 $ 6,075.00 $ 24,291.50
11 Wealthy Street Station NB $ - $ 5,500.00 $ 5,863.00 $ 6,575.00 $ 17,938.00
12 Wealthy Street Station SB $ - $ 5,500.00 $ 7,713.00 $ 6,075.00 $ 19,288.00
13 Logan Street Station NB $ 8,441.00 $ 5,500.00 $ 7,449.50 $ 6,075.00 $ 27,465.50
14 Logan Street Station SB $ 5,728.00 $ 5,500.00 $ 6,828.00 $ 12,075.00 $ 30,131.00
15 Franklin Street Station NB $ 4,801.00 $ 5,500.00 $ 8,565.00 $ 6,075.00 $ 24,941.00
16 Franklin Street Station SB $ 5,728.00 $ 5,500.00 $ 7,355.50 $ 6,075.00 $ 24,658.50
17 Green Street Station NB $ 1,918.00 $ 5,500.00 $ 16,924.00 $ 6,075.00 $ 30,417.00
18 Green Street Station SB $ - $ 5,500.00 $ 12,774.00 $ 6,075.00 $ 24,349.00
19 Cottage Grove Street Station NB $ 5,993.00 $ 5,500.00 $ 15,806.00 $ 6,075.00 $ 33,374.00
20 Cottage Grove Street Station SB $ 5,993.00 $ 5,500.00 $ 19,075.00 $ 8,575.00 $ 39,143.00
21 Burton Street Station NB $ 5,178.00 $ 5,500.00 $ 16,901.00 $ 8,575.00 $ 36,154.00
22 Burton Street Station SB $ 6,454.00 $ 5,500.00 $ 17,121.00 $ 6,075.00 $ 35,150.00
23 Southview Street Station NB $ 6,268.00 $ 5,500.00 $ 18,785.50 $ 6,075.00 $ 36,628.50
24 Southview Street Station SB $ 6,268.00 $ 5,500.00 $ 5,656.00 $ 6,075.00 $ 23,499.00
25 28th Street Station NB $ 7,075.00 $ 5,500.00 $ 7,879.00 $ 11,575.00 $ 32,029.00
26 28th Street Station SB $ 6,757.00 $ 5,500.00 $ 6,473.50 $ 6,075.00 $ 24,805.50
27 36th Street Station NB $ 7,351.00 $ 5,500.00 $ 20,349.00 $ 6,075.00 $ 39,275.00
28 36th Street Station SB $ 7,393.00 $ 5,500.00 $ 11,236.50 $ 6,075.00 $ 30,204.50
29 44th Street Station NB $ 6,757.00 $ 5,500.00 $ 17,339.00 $ 6,075.00 $ 35,671.00
30 44th Street Station SB $ 6,757.00 $ 5,500.00 $ 18,011.50 $ 6,075.00 $ 36,343.50
31 54th Street Station NB $ 6,268.00 $ 5,500.00 $ 16,977.00 $ 6,075.00 $ 34,820.00
32 54th Street Station SB $ 6,310.00 $ 5,500.00 $ 15,549.00 $ 6,075.00 $ 33,434.00
33 60th Street Station (southern alternate) $ 5,728.00 $ 5,500.00 $ 18,783.00 $ 8,575.00 $ 38,586.00
Grandville Ave. Reconstruction from Oakes St to
34 Weston St $ - $ 244,780.00 $ - $ - $ 244,780.00
Logan St Resurfacing from Division to Sheldon
35 and from LaGrave to Jefferson $ - $ 54,750.00 $ - $ - $ 54,750.00
Jefferson Ave Resurfacing from Logan St to south
36 of Wealthy St $ - $ 43,925.00 $ - $ - $ 43,925.00
Ransom Ave Resurfacing from Lyon St to
Crescent St and Crescent St Resurfacing from
37 Ransom Ave to Bostwick Ave $ - $ 66,475.00 $ - $ - $ 66,475.00
37 Pavement Markings $ - $ 177,000.00 $ - $ - $ 177,000.00
38 Traffic Signage $ - $ 285,000.00 $ - $ - $ 285,000.00

10.02 10.03 20.01 40.02


Cost Code Totals $ 187,400.00 $ 1,053,430.00 $ 410,970.00 $ 244,475.00
Total Project Cost Estimate $ 1,896,275.00

URS Corporation 1
Project Construction Cost Estimate
Silver Line BRT - Louis Street Station NB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/02/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 142 Syd $ 6.00 $ 852.00
3010002 Subbase, CIP (12 inch) 36 Cyd $ 10.00 $ 360.00
3020016 Aggregate Base, 6 inch 108 Syd $ 5.00 $ 540.00
6020108 Conc Pavt, Nonreinf, 10 inch 108 Syd $ 40.00 $ 4,320.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 6,472.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 0 Ea $ 500.00 $ -
2040006 Curb and Gutter, Rem 207 Ft $ 5.00 $ 1,035.00
2040013 Sidewalk, Rem 92 Syd $ 5.50 $ 506.00
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 16 Cyd $ 10.00 $ 160.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 93 Ft $ 15.00 $ 1,395.00
8027001 Curb and Gutter, Conc, Det F4, Mod 38 Ft $ 15.00 $ 570.00
8030002 Sidewalk, Conc, 4 inch 1,006 Sft $ 3.00 $ 3,018.00
8030003 Sidewalk, Conc, 6 inch 140 Sft $ 3.50 $ 490.00
8160050 Slope Restoration 0 Syd $ 3.00 $ -
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 0 Sft $ 10.00 $ -
Total for FTA Code 20.01 $ 9,024.00

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 1 Ea $ 2,500.00 $ 2,500.00
8250095 Hydrant, Relocate, Case 1 0 Ea $ 3,000.00 $ -
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 8,575.00

Station Construction Cost Estimate $ 29,571.00

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - Louis Street Station SB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/02/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 96 Syd $ 6.00 $ 576.00
3010002 Subbase, CIP (12 inch) 36 Cyd $ 10.00 $ 360.00
3020016 Aggregate Base, 6 inch 107 Syd $ 5.00 $ 535.00
6020108 Conc Pavt, Nonreinf, 10 inch 107 Syd $ 40.00 $ 4,280.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 6,151.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 0 Ea $ 500.00 $ -
2040006 Curb and Gutter, Rem 99 Ft $ 5.00 $ 495.00
2040013 Sidewalk, Rem 211 Syd $ 5.50 $ 1,160.50
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 27 Cyd $ 10.00 $ 270.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 0 Ft $ 15.00 $ -
8027001 Curb and Gutter, Conc, Det F4, Mod 40 Ft $ 15.00 $ 600.00
8030002 Sidewalk, Conc, 4 inch 711 Sft $ 3.00 $ 2,133.00
8030003 Sidewalk, Conc, 6 inch 643 Sft $ 3.50 $ 2,250.50
8160050 Slope Restoration 59 Syd $ 3.00 $ 177.00
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 835 Sft $ 10.00 $ 8,350.00
Total for FTA Code 20.01 $ 17,286.00

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 1 Ea $ 2,500.00 $ 2,500.00
8250095 Hydrant, Relocate, Case 1 0 Ea $ 3,000.00 $ -
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 8,575.00

Station Construction Cost Estimate $ 37,512.00

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - DeVos Place Station NB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/02/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 89 Syd $ 6.00 $ 534.00
3010002 Subbase, CIP (12 inch) 30 Cyd $ 10.00 $ 300.00
3020016 Aggregate Base, 6 inch 89 Syd $ 5.00 $ 445.00
6020108 Conc Pavt, Nonreinf, 10 inch 89 Syd $ 40.00 $ 3,560.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 5,239.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 2 Ea $ 500.00 $ 1,000.00
2040006 Curb and Gutter, Rem 80 Ft $ 5.00 $ 400.00
2040013 Sidewalk, Rem 182 Syd $ 5.50 $ 1,001.00
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 17 Cyd $ 10.00 $ 170.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 80 Ft $ 15.00 $ 1,200.00
8027001 Curb and Gutter, Conc, Det F4, Mod 30 Ft $ 15.00 $ 450.00
8030002 Sidewalk, Conc, 4 inch 635 Sft $ 3.00 $ 1,905.00
8030003 Sidewalk, Conc, 6 inch 320 Sft $ 3.50 $ 1,120.00
8160050 Slope Restoration 0 Syd $ 3.00 $ -
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 0 Sft $ 10.00 $ -
Total for FTA Code 20.01 $ 9,096.00

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 0 Ea $ 2,500.00 $ -
8250095 Hydrant, Relocate, Case 1 1 Ea $ 3,000.00 $ 3,000.00
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 9,075.00

Station Construction Cost Estimate $ 28,910.00

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - DeVos Place Station SB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/02/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 98 Syd $ 6.00 $ 588.00
3010002 Subbase, CIP (12 inch) 33 Cyd $ 10.00 $ 330.00
3020016 Aggregate Base, 6 inch 98 Syd $ 5.00 $ 490.00
6020108 Conc Pavt, Nonreinf, 10 inch 98 Syd $ 40.00 $ 3,920.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 5,728.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 0 Ea $ 500.00 $ -
2040006 Curb and Gutter, Rem 88 Ft $ 5.00 $ 440.00
2040013 Sidewalk, Rem 153 Syd $ 5.50 $ 841.50
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 19 Cyd $ 10.00 $ 190.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 0 Ft $ 15.00 $ -
8027001 Curb and Gutter, Conc, Det F4, Mod 38 Ft $ 15.00 $ 570.00
8030002 Sidewalk, Conc, 4 inch 530 Sft $ 3.00 $ 1,590.00
8030003 Sidewalk, Conc, 6 inch 446 Sft $ 3.50 $ 1,561.00
8160050 Slope Restoration 123 Syd $ 3.00 $ 369.00
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 0 Sft $ 10.00 $ -
Total for FTA Code 20.01 $ 7,411.50

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 1 Ea $ 2,500.00 $ 2,500.00
8250095 Hydrant, Relocate, Case 1 1 Ea $ 3,000.00 $ 3,000.00
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 11,575.00

Station Construction Cost Estimate $ 30,214.50

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - Michigan Street Station NB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/02/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 108 Syd $ 6.00 $ 648.00
3010002 Subbase, CIP (12 inch) 36 Cyd $ 10.00 $ 360.00
3020016 Aggregate Base, 6 inch 108 Syd $ 5.00 $ 540.00
6020108 Conc Pavt, Nonreinf, 10 inch 108 Syd $ 40.00 $ 4,320.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 6,268.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 0 Ea $ 500.00 $ -
2040006 Curb and Gutter, Rem 246 Ft $ 5.00 $ 1,230.00
2040013 Sidewalk, Rem 119 Syd $ 5.50 $ 654.50
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 23 Cyd $ 10.00 $ 230.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 0 Ft $ 15.00 $ -
8027001 Curb and Gutter, Conc, Det F4, Mod 38 Ft $ 15.00 $ 570.00
8030002 Sidewalk, Conc, 4 inch 594 Sft $ 3.00 $ 1,782.00
8030003 Sidewalk, Conc, 6 inch 546 Sft $ 3.50 $ 1,911.00
8160050 Slope Restoration 0 Syd $ 3.00 $ -
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 440 Sft $ 10.00 $ 4,400.00
Total for FTA Code 20.01 $ 12,627.50

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 0 Ea $ 2,500.00 $ -
8250095 Hydrant, Relocate, Case 1 0 Ea $ 3,000.00 $ -
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 6,075.00

Station Construction Cost Estimate $ 30,470.50

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - Michigan Street Station SB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/02/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 108 Syd $ 6.00 $ 648.00
3010002 Subbase, CIP (12 inch) 36 Cyd $ 10.00 $ 360.00
3020016 Aggregate Base, 6 inch 108 Syd $ 5.00 $ 540.00
6020108 Conc Pavt, Nonreinf, 10 inch 108 Syd $ 40.00 $ 4,320.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 6,268.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 1 Ea $ 500.00 $ 500.00
2040006 Curb and Gutter, Rem 138 Ft $ 5.00 $ 690.00
2040013 Sidewalk, Rem 105 Syd $ 5.50 $ 577.50
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 28 Cyd $ 10.00 $ 280.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 0 Ft $ 15.00 $ -
8027001 Curb and Gutter, Conc, Det F4, Mod 38 Ft $ 15.00 $ 570.00
8030002 Sidewalk, Conc, 4 inch 711 Sft $ 3.00 $ 2,133.00
8030003 Sidewalk, Conc, 6 inch 708 Sft $ 3.50 $ 2,478.00
8160050 Slope Restoration 109 Syd $ 3.00 $ 327.00
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 742 Sft $ 10.00 $ 7,420.00
Total for FTA Code 20.01 $ 16,825.50

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 1 Ea $ 2,500.00 $ 2,500.00
8250095 Hydrant, Relocate, Case 1 1 Ea $ 3,000.00 $ 3,000.00
xxxxxxx Relocate Street Sign 1 Ea $ 500.00 $ 500.00
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 12,075.00

Station Construction Cost Estimate $ 40,668.50

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - GRCC Station NB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/04/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 156 Syd $ 6.00 $ 936.00
3010002 Subbase, CIP (12 inch) 52 Cyd $ 10.00 $ 520.00
3020016 Aggregate Base, 6 inch 156 Syd $ 5.00 $ 780.00
6020108 Conc Pavt, Nonreinf, 10 inch 156 Syd $ 40.00 $ 6,240.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 8,876.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 2 Ea $ 500.00 $ 1,000.00
2040006 Curb and Gutter, Rem 88 Ft $ 5.00 $ 440.00
2040013 Sidewalk, Rem 65 Syd $ 5.50 $ 357.50
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 15 Cyd $ 10.00 $ 150.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 0 Ft $ 15.00 $ -
8027001 Curb and Gutter, Conc, Det F4, Mod 38 Ft $ 15.00 $ 570.00
8030002 Sidewalk, Conc, 4 inch 456 Sft $ 3.00 $ 1,368.00
8030003 Sidewalk, Conc, 6 inch 320 Sft $ 3.50 $ 1,120.00
8160050 Slope Restoration 0 Syd $ 3.00 $ -
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 0 Sft $ 10.00 $ -
Total for FTA Code 20.01 $ 6,855.50

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 1 Ea $ 2,500.00 $ 2,500.00
8250095 Hydrant, Relocate, Case 1 0 Ea $ 3,000.00 $ -
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 8,575.00

Station Construction Cost Estimate $ 29,806.50

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - GRCC Station SB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/04/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 156 Syd $ 6.00 $ 936.00
3010002 Subbase, CIP (12 inch) 52 Cyd $ 10.00 $ 520.00
3020016 Aggregate Base, 6 inch 156 Syd $ 5.00 $ 780.00
6020108 Conc Pavt, Nonreinf, 10 inch 156 Syd $ 40.00 $ 6,240.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 8,876.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 2 Ea $ 500.00 $ 1,000.00
2040006 Curb and Gutter, Rem 88 Ft $ 5.00 $ 440.00
2040013 Sidewalk, Rem 65 Syd $ 5.50 $ 357.50
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 18 Cyd $ 10.00 $ 180.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 0 Ft $ 15.00 $ -
8027001 Curb and Gutter, Conc, Det F4, Mod 38 Ft $ 15.00 $ 570.00
8030002 Sidewalk, Conc, 4 inch 526 Sft $ 3.00 $ 1,578.00
8030003 Sidewalk, Conc, 6 inch 429 Sft $ 3.50 $ 1,501.50
8160050 Slope Restoration 109 Syd $ 3.00 $ 327.00
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 980 Sft $ 10.00 $ 9,800.00
Total for FTA Code 20.01 $ 17,604.00

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 0 Ea $ 2,500.00 $ -
8250095 Hydrant, Relocate, Case 1 0 Ea $ 3,000.00 $ -
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 6,075.00

Station Construction Cost Estimate $ 38,055.00

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - Fulton Street Station NB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/04/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 88 Syd $ 6.00 $ 528.00
3010002 Subbase, CIP (12 inch) 29 Cyd $ 10.00 $ 290.00
3020016 Aggregate Base, 6 inch 88 Syd $ 5.00 $ 440.00
6020108 Conc Pavt, Nonreinf, 10 inch 88 Syd $ 40.00 $ 3,520.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 5,178.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 1 Ea $ 500.00 $ 500.00
2040006 Curb and Gutter, Rem 88 Ft $ 5.00 $ 440.00
2040013 Sidewalk, Rem 54 Syd $ 5.50 $ 297.00
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 12 Cyd $ 10.00 $ 120.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 88 Ft $ 15.00 $ 1,320.00
8027001 Curb and Gutter, Conc, Det F4, Mod 38 Ft $ 15.00 $ 570.00
8030002 Sidewalk, Conc, 4 inch 418 Sft $ 3.00 $ 1,254.00
8030003 Sidewalk, Conc, 6 inch 259 Sft $ 3.50 $ 906.50
8160050 Slope Restoration 10 Syd $ 3.00 $ 30.00
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 0 Sft $ 10.00 $ -
Total for FTA Code 20.01 $ 7,287.50

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 1 Ea $ 2,500.00 $ 2,500.00
8250095 Hydrant, Relocate, Case 1 0 Ea $ 3,000.00 $ -
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 8,575.00

Station Construction Cost Estimate $ 26,540.50

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - Fulton Street Station SB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/04/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 88 Syd $ 6.00 $ 528.00
3010002 Subbase, CIP (12 inch) 29 Cyd $ 10.00 $ 290.00
3020016 Aggregate Base, 6 inch 88 Syd $ 5.00 $ 440.00
6020108 Conc Pavt, Nonreinf, 10 inch 88 Syd $ 40.00 $ 3,520.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 5,178.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 0 Ea $ 500.00 $ -
2040006 Curb and Gutter, Rem 88 Ft $ 5.00 $ 440.00
2040013 Sidewalk, Rem 131 Syd $ 5.50 $ 720.50
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 15 Cyd $ 10.00 $ 150.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 88 Ft $ 15.00 $ 1,320.00
8027001 Curb and Gutter, Conc, Det F4, Mod 38 Ft $ 15.00 $ 570.00
8030002 Sidewalk, Conc, 4 inch 456 Sft $ 3.00 $ 1,368.00
8030003 Sidewalk, Conc, 6 inch 320 Sft $ 3.50 $ 1,120.00
8160050 Slope Restoration 0 Syd $ 3.00 $ -
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 0 Sft $ 10.00 $ -
Total for FTA Code 20.01 $ 7,538.50

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 0 Ea $ 2,500.00 $ -
8250095 Hydrant, Relocate, Case 1 0 Ea $ 3,000.00 $ -
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 6,075.00

Station Construction Cost Estimate $ 24,291.50

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - Wealthy Street Station NB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/04/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 0 Syd $ 6.00 $ -
3010002 Subbase, CIP (12 inch) 0 Cyd $ 10.00 $ -
3020016 Aggregate Base, 6 inch 0 Syd $ 5.00 $ -
6020108 Conc Pavt, Nonreinf, 10 inch 0 Syd $ 40.00 $ -
205xxxx Excavation and Embankment 0 LS $ 200.00 $ -
402xxxx Manhole and catch basin adjustments 0 LS $ 200.00 $ -
Total for FTA Code 10.02 $ -

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 0 Ea $ 500.00 $ -
2040006 Curb and Gutter, Rem 74 Ft $ 5.00 $ 370.00
2040013 Sidewalk, Rem 104 Syd $ 5.50 $ 572.00
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 16 Cyd $ 10.00 $ 160.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 0 Ft $ 15.00 $ -
8027001 Curb and Gutter, Conc, Det F4, Mod 24 Ft $ 15.00 $ 360.00
8030002 Sidewalk, Conc, 4 inch 327 Sft $ 3.00 $ 981.00
8030003 Sidewalk, Conc, 6 inch 440 Sft $ 3.50 $ 1,540.00
8160050 Slope Restoration 10 Syd $ 3.00 $ 30.00
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 0 Sft $ 10.00 $ -
Total for FTA Code 20.01 $ 5,863.00

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 0 Ea $ 2,500.00 $ -
8250095 Hydrant, Relocate, Case 1 0 Ea $ 3,000.00 $ -
xxxxxxx Relocate Street Sign 1 Ea $ 500.00 $ 500.00
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 6,575.00

Station Construction Cost Estimate $ 17,938.00

Note: Assume replacement of existing curb and sidewalk, but not pavement

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - Wealthy Street Station SB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/04/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 0 Syd $ 6.00 $ -
3010002 Subbase, CIP (12 inch) 0 Cyd $ 10.00 $ -
3020016 Aggregate Base, 6 inch 0 Syd $ 5.00 $ -
6020108 Conc Pavt, Nonreinf, 10 inch 0 Syd $ 40.00 $ -
205xxxx Excavation and Embankment 0 LS $ 200.00 $ -
402xxxx Manhole and catch basin adjustments 0 LS $ 200.00 $ -
Total for FTA Code 10.02 $ -

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 0 Ea $ 500.00 $ -
2040006 Curb and Gutter, Rem 74 Ft $ 5.00 $ 370.00
2040013 Sidewalk, Rem 155 Syd $ 5.50 $ 852.50
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 16 Cyd $ 10.00 $ 160.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 74 Ft $ 15.00 $ 1,110.00
8027001 Curb and Gutter, Conc, Det F4, Mod 24 Ft $ 15.00 $ 360.00
8030002 Sidewalk, Conc, 4 inch 692 Sft $ 3.00 $ 2,076.00
8030003 Sidewalk, Conc, 6 inch 267 Sft $ 3.50 $ 934.50
8160050 Slope Restoration 0 Syd $ 3.00 $ -
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 0 Sft $ 10.00 $ -
Total for FTA Code 20.01 $ 7,713.00

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 0 Ea $ 2,500.00 $ -
8250095 Hydrant, Relocate, Case 1 0 Ea $ 3,000.00 $ -
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 6,075.00

Station Construction Cost Estimate $ 19,288.00

Note: Assume replacement of existing curb and sidewalk, but not pavement

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - Logan Street Station NB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/04/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 156 Syd $ 6.00 $ 936.00
3010002 Subbase, CIP (12 inch) 49 Cyd $ 10.00 $ 490.00
3020016 Aggregate Base, 6 inch 147 Syd $ 5.00 $ 735.00
6020108 Conc Pavt, Nonreinf, 10 inch 147 Syd $ 40.00 $ 5,880.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 8,441.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 0 Ea $ 500.00 $ -
2040006 Curb and Gutter, Rem 88 Ft $ 5.00 $ 440.00
2040013 Sidewalk, Rem 59 Syd $ 5.50 $ 324.50
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 6 Cyd $ 10.00 $ 60.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 38 Ft $ 15.00 $ 570.00
8027001 Curb and Gutter, Conc, Det F4, Mod 0 Ft $ 15.00 $ -
8030002 Sidewalk, Conc, 4 inch 303 Sft $ 3.00 $ 909.00
8030003 Sidewalk, Conc, 6 inch 80 Sft $ 3.50 $ 280.00
8160050 Slope Restoration 32 Syd $ 3.00 $ 96.00
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 292 Sft $ 10.00 $ 2,920.00
Total for FTA Code 20.01 $ 7,449.50

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 0 Ea $ 2,500.00 $ -
8250095 Hydrant, Relocate, Case 1 0 Ea $ 3,000.00 $ -
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 6,075.00

Station Construction Cost Estimate $ 27,465.50

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - Logan Street Station SB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/04/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 98 Syd $ 6.00 $ 588.00
3010002 Subbase, CIP (12 inch) 33 Cyd $ 10.00 $ 330.00
3020016 Aggregate Base, 6 inch 98 Syd $ 5.00 $ 490.00
6020108 Conc Pavt, Nonreinf, 10 inch 98 Syd $ 40.00 $ 3,920.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 5,728.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 0 Ea $ 500.00 $ -
2040006 Curb and Gutter, Rem 88 Ft $ 5.00 $ 440.00
2040013 Sidewalk, Rem 120 Syd $ 5.50 $ 660.00
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 8 Cyd $ 10.00 $ 80.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 126 Ft $ 15.00 $ 1,890.00
8027001 Curb and Gutter, Conc, Det F4, Mod 0 Ft $ 15.00 $ -
8030002 Sidewalk, Conc, 4 inch 636 Sft $ 3.00 $ 1,908.00
8030003 Sidewalk, Conc, 6 inch 0 Sft $ 3.50 $ -
8160050 Slope Restoration 0 Syd $ 3.00 $ -
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 0 Sft $ 10.00 $ -
Total for FTA Code 20.01 $ 6,828.00

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 1 Ea $ 2,500.00 $ 2,500.00
8250095 Hydrant, Relocate, Case 1 1 Ea $ 3,000.00 $ 3,000.00
xxxxxxx Relocate Street Sign 1 Ea $ 500.00 $ 500.00
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 12,075.00

Station Construction Cost Estimate $ 30,131.00

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - Franklin Street Station NB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/04/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 81 Syd $ 6.00 $ 486.00
3010002 Subbase, CIP (12 inch) 27 Cyd $ 10.00 $ 270.00
3020016 Aggregate Base, 6 inch 81 Syd $ 5.00 $ 405.00
6020108 Conc Pavt, Nonreinf, 10 inch 81 Syd $ 40.00 $ 3,240.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 4,801.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 0 Ea $ 500.00 $ -
2040006 Curb and Gutter, Rem 61 Ft $ 5.00 $ 305.00
2040013 Sidewalk, Rem 82 Syd $ 5.50 $ 451.00
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 9 Cyd $ 10.00 $ 90.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 0 Ft $ 15.00 $ -
8027001 Curb and Gutter, Conc, Det F4, Mod 31 Ft $ 15.00 $ 465.00
8030002 Sidewalk, Conc, 4 inch 391 Sft $ 3.00 $ 1,173.00
8030003 Sidewalk, Conc, 6 inch 164 Sft $ 3.50 $ 574.00
8160050 Slope Restoration 39 Syd $ 3.00 $ 117.00
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 354 Sft $ 10.00 $ 3,540.00
Total for FTA Code 20.01 $ 8,565.00

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 0 Ea $ 2,500.00 $ -
8250095 Hydrant, Relocate, Case 1 0 Ea $ 3,000.00 $ -
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 6,075.00

Station Construction Cost Estimate $ 24,941.00

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - Franklin Street Station SB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/04/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 98 Syd $ 6.00 $ 588.00
3010002 Subbase, CIP (12 inch) 33 Cyd $ 10.00 $ 330.00
3020016 Aggregate Base, 6 inch 98 Syd $ 5.00 $ 490.00
6020108 Conc Pavt, Nonreinf, 10 inch 98 Syd $ 40.00 $ 3,920.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 5,728.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 0 Ea $ 500.00 $ -
2040006 Curb and Gutter, Rem 88 Ft $ 5.00 $ 440.00
2040013 Sidewalk, Rem 125 Syd $ 5.50 $ 687.50
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 10 Cyd $ 10.00 $ 100.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 88 Ft $ 15.00 $ 1,320.00
8027001 Curb and Gutter, Conc, Det F4, Mod 38 Ft $ 15.00 $ 570.00
8030002 Sidewalk, Conc, 4 inch 796 Sft $ 3.00 $ 2,388.00
8030003 Sidewalk, Conc, 6 inch 0 Sft $ 3.50 $ -
8160050 Slope Restoration 0 Syd $ 3.00 $ -
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 0 Sft $ 10.00 $ -
Total for FTA Code 20.01 $ 7,355.50

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 0 Ea $ 2,500.00 $ -
8250095 Hydrant, Relocate, Case 1 0 Ea $ 3,000.00 $ -
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 6,075.00

Station Construction Cost Estimate $ 24,658.50

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - Green Street Station NB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/04/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 28 Syd $ 6.00 $ 168.00
3010002 Subbase, CIP (12 inch) 9 Cyd $ 10.00 $ 90.00
3020016 Aggregate Base, 6 inch 28 Syd $ 5.00 $ 140.00
6020108 Conc Pavt, Nonreinf, 10 inch 28 Syd $ 40.00 $ 1,120.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 1,918.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 1 Ea $ 500.00 $ 500.00
2040006 Curb and Gutter, Rem 101 Ft $ 5.00 $ 505.00
2040013 Sidewalk, Rem 156 Syd $ 5.50 $ 858.00
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 22 Cyd $ 10.00 $ 220.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 8 Ft $ 15.00 $ 120.00
8027001 Curb and Gutter, Conc, Det F4, Mod 51 Ft $ 15.00 $ 765.00
8030002 Sidewalk, Conc, 4 inch 648 Sft $ 3.00 $ 1,944.00
8030003 Sidewalk, Conc, 6 inch 512 Sft $ 3.50 $ 1,792.00
8160050 Slope Restoration 90 Syd $ 3.00 $ 270.00
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 810 Sft $ 10.00 $ 8,100.00
Total for FTA Code 20.01 $ 16,924.00

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 0 Ea $ 2,500.00 $ -
8250095 Hydrant, Relocate, Case 1 0 Ea $ 3,000.00 $ -
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 6,075.00

Station Construction Cost Estimate $ 30,417.00

Note: Assume replacement of existing HMA pavement only

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - Green Street Station SB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/04/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 0 Syd $ 6.00 $ -
3010002 Subbase, CIP (12 inch) 0 Cyd $ 10.00 $ -
3020016 Aggregate Base, 6 inch 0 Syd $ 5.00 $ -
6020108 Conc Pavt, Nonreinf, 10 inch 0 Syd $ 40.00 $ -
205xxxx Excavation and Embankment 0 LS $ 200.00 $ -
402xxxx Manhole and catch basin adjustments 0 LS $ 200.00 $ -
Total for FTA Code 10.02 $ -

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 0 Ea $ 500.00 $ -
2040006 Curb and Gutter, Rem 151 Ft $ 5.00 $ 755.00
2040013 Sidewalk, Rem 86 Syd $ 5.50 $ 473.00
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 7 Cyd $ 10.00 $ 70.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 0 Ft $ 15.00 $ -
8027001 Curb and Gutter, Conc, Det F4, Mod 101 Ft $ 15.00 $ 1,515.00
8030002 Sidewalk, Conc, 4 inch 217 Sft $ 3.00 $ 651.00
8030003 Sidewalk, Conc, 6 inch 156 Sft $ 3.50 $ 546.00
8160050 Slope Restoration 78 Syd $ 3.00 $ 234.00
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 668 Sft $ 10.00 $ 6,680.00
Total for FTA Code 20.01 $ 12,774.00

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 0 Ea $ 2,500.00 $ -
8250095 Hydrant, Relocate, Case 1 0 Ea $ 3,000.00 $ -
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 6,075.00

Station Construction Cost Estimate $ 24,349.00

Note: Assume no replacement of existing pavement

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - Cottage Grove Station NB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/14/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 103 Syd $ 6.00 $ 618.00
3010002 Subbase, CIP (12 inch) 34 Cyd $ 10.00 $ 340.00
3020016 Aggregate Base, 6 inch 103 Syd $ 5.00 $ 515.00
6020108 Conc Pavt, Nonreinf, 10 inch 103 Syd $ 40.00 $ 4,120.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 5,993.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 0 Ea $ 500.00 $ -
2040006 Curb and Gutter, Rem 88 Ft $ 5.00 $ 440.00
2040013 Sidewalk, Rem 60 Syd $ 5.50 $ 330.00
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 14 Cyd $ 10.00 $ 140.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 0 Ft $ 15.00 $ -
8027001 Curb and Gutter, Conc, Det F4, Mod 38 Ft $ 15.00 $ 570.00
8030002 Sidewalk, Conc, 4 inch 398 Sft $ 3.00 $ 1,194.00
8030003 Sidewalk, Conc, 6 inch 330 Sft $ 3.50 $ 1,155.00
8160050 Slope Restoration 109 Syd $ 3.00 $ 327.00
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 980 Sft $ 10.00 $ 9,800.00
Total for FTA Code 20.01 $ 15,806.00

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 0 Ea $ 2,500.00 $ -
8250095 Hydrant, Relocate, Case 1 0 Ea $ 3,000.00 $ -
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 6,075.00

Station Construction Cost Estimate $ 33,374.00

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - Cottage Grove Station SB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/14/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 103 Syd $ 6.00 $ 618.00
3010002 Subbase, CIP (12 inch) 34 Cyd $ 10.00 $ 340.00
3020016 Aggregate Base, 6 inch 103 Syd $ 5.00 $ 515.00
6020108 Conc Pavt, Nonreinf, 10 inch 103 Syd $ 40.00 $ 4,120.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 5,993.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 0 Ea $ 500.00 $ -
2040006 Curb and Gutter, Rem 88 Ft $ 5.00 $ 440.00
2040013 Sidewalk, Rem 54 Syd $ 5.50 $ 297.00
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 18 Cyd $ 10.00 $ 180.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 0 Ft $ 15.00 $ -
8027001 Curb and Gutter, Conc, Det F4, Mod 38 Ft $ 15.00 $ 570.00
8030002 Sidewalk, Conc, 4 inch 512 Sft $ 3.00 $ 1,536.00
8030003 Sidewalk, Conc, 6 inch 410 Sft $ 3.50 $ 1,435.00
8160050 Slope Restoration 109 Syd $ 3.00 $ 327.00
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 1,244 Sft $ 10.00 $ 12,440.00
Total for FTA Code 20.01 $ 19,075.00

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 1 Ea $ 2,500.00 $ 2,500.00
8250095 Hydrant, Relocate, Case 1 0 Ea $ 3,000.00 $ -
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 8,575.00

Station Construction Cost Estimate $ 39,143.00

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - Burton Street Station NB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/14/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 88 Syd $ 6.00 $ 528.00
3010002 Subbase, CIP (12 inch) 29 Cyd $ 10.00 $ 290.00
3020016 Aggregate Base, 6 inch 88 Syd $ 5.00 $ 440.00
6020108 Conc Pavt, Nonreinf, 10 inch 88 Syd $ 40.00 $ 3,520.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 5,178.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 0 Ea $ 500.00 $ -
2040006 Curb and Gutter, Rem 88 Ft $ 5.00 $ 440.00
2040013 Sidewalk, Rem 122 Syd $ 5.50 $ 671.00
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 16 Cyd $ 10.00 $ 160.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 0 Ft $ 15.00 $ -
8027001 Curb and Gutter, Conc, Det F4, Mod 38 Ft $ 15.00 $ 570.00
8030002 Sidewalk, Conc, 4 inch 426 Sft $ 3.00 $ 1,278.00
8030003 Sidewalk, Conc, 6 inch 372 Sft $ 3.50 $ 1,302.00
8160050 Slope Restoration 0 Syd $ 3.00 $ -
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 1,063 Sft $ 10.00 $ 10,630.00
Total for FTA Code 20.01 $ 16,901.00

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 1 Ea $ 2,500.00 $ 2,500.00
8250095 Hydrant, Relocate, Case 1 0 Ea $ 3,000.00 $ -
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 8,575.00

Station Construction Cost Estimate $ 36,154.00

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - Burton Street Station SB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/14/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 219 Syd $ 6.00 $ 1,314.00
3010002 Subbase, CIP (12 inch) 33 Cyd $ 10.00 $ 330.00
3020016 Aggregate Base, 6 inch 98 Syd $ 5.00 $ 490.00
6020108 Conc Pavt, Nonreinf, 10 inch 98 Syd $ 40.00 $ 3,920.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 6,454.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 0 Ea $ 500.00 $ -
2040006 Curb and Gutter, Rem 163 Ft $ 5.00 $ 815.00
2040013 Sidewalk, Rem 87 Syd $ 5.50 $ 478.50
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 21 Cyd $ 10.00 $ 210.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 88 Ft $ 15.00 $ 1,320.00
8027001 Curb and Gutter, Conc, Det F4, Mod 113 Ft $ 15.00 $ 1,695.00
8030002 Sidewalk, Conc, 4 inch 1,207 Sft $ 3.00 $ 3,621.00
8030003 Sidewalk, Conc, 6 inch 209 Sft $ 3.50 $ 731.50
8160050 Slope Restoration 0 Syd $ 3.00 $ -
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 640 Sft $ 10.00 $ 6,400.00
Total for FTA Code 20.01 $ 17,121.00

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 0 Ea $ 2,500.00 $ -
8250095 Hydrant, Relocate, Case 1 0 Ea $ 3,000.00 $ -
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 6,075.00

Station Construction Cost Estimate $ 35,150.00

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - Southview Street Station NB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/14/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 108 Syd $ 6.00 $ 648.00
3010002 Subbase, CIP (12 inch) 36 Cyd $ 10.00 $ 360.00
3020016 Aggregate Base, 6 inch 108 Syd $ 5.00 $ 540.00
6020108 Conc Pavt, Nonreinf, 10 inch 108 Syd $ 40.00 $ 4,320.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 6,268.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 0 Ea $ 500.00 $ -
2040006 Curb and Gutter, Rem 88 Ft $ 5.00 $ 440.00
2040013 Sidewalk, Rem 76 Syd $ 5.50 $ 418.00
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 32 Cyd $ 10.00 $ 320.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 0 Ft $ 15.00 $ -
8027001 Curb and Gutter, Conc, Det F4, Mod 38 Ft $ 15.00 $ 570.00
8030002 Sidewalk, Conc, 4 inch 768 Sft $ 3.00 $ 2,304.00
8030003 Sidewalk, Conc, 6 inch 815 Sft $ 3.50 $ 2,852.50
8160050 Slope Restoration 77 Syd $ 3.00 $ 231.00
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 980 Sft $ 10.00 $ 9,800.00
Total for FTA Code 20.01 $ 18,785.50

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 0 Ea $ 2,500.00 $ -
8250095 Hydrant, Relocate, Case 1 0 Ea $ 3,000.00 $ -
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 6,075.00

Station Construction Cost Estimate $ 36,628.50

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - Southview Street Station SB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/14/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 108 Syd $ 6.00 $ 648.00
3010002 Subbase, CIP (12 inch) 36 Cyd $ 10.00 $ 360.00
3020016 Aggregate Base, 6 inch 108 Syd $ 5.00 $ 540.00
6020108 Conc Pavt, Nonreinf, 10 inch 108 Syd $ 40.00 $ 4,320.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 6,268.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 0 Ea $ 500.00 $ -
2040006 Curb and Gutter, Rem 88 Ft $ 5.00 $ 440.00
2040013 Sidewalk, Rem 63 Syd $ 5.50 $ 346.50
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 13 Cyd $ 10.00 $ 130.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 0 Ft $ 15.00 $ -
8027001 Curb and Gutter, Conc, Det F4, Mod 38 Ft $ 15.00 $ 570.00
8030002 Sidewalk, Conc, 4 inch 433 Sft $ 3.00 $ 1,299.00
8030003 Sidewalk, Conc, 6 inch 283 Sft $ 3.50 $ 990.50
8160050 Slope Restoration 10 Syd $ 3.00 $ 30.00
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 0 Sft $ 10.00 $ -
Total for FTA Code 20.01 $ 5,656.00

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 0 Ea $ 2,500.00 $ -
8250095 Hydrant, Relocate, Case 1 0 Ea $ 3,000.00 $ -
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 6,075.00

Station Construction Cost Estimate $ 23,499.00

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - 28th Street Station NB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/14/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 170 Syd $ 6.00 $ 1,020.00
3010002 Subbase, CIP (12 inch) 39 Cyd $ 10.00 $ 390.00
3020016 Aggregate Base, 6 inch 117 Syd $ 5.00 $ 585.00
6020108 Conc Pavt, Nonreinf, 10 inch 117 Syd $ 40.00 $ 4,680.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 7,075.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 0 Ea $ 500.00 $ -
2040006 Curb and Gutter, Rem 88 Ft $ 5.00 $ 440.00
2040013 Sidewalk, Rem 66 Syd $ 5.50 $ 363.00
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 18 Cyd $ 10.00 $ 180.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 98 Ft $ 15.00 $ 1,470.00
8027001 Curb and Gutter, Conc, Det F4, Mod 38 Ft $ 15.00 $ 570.00
8030002 Sidewalk, Conc, 4 inch 477 Sft $ 3.00 $ 1,431.00
8030003 Sidewalk, Conc, 6 inch 450 Sft $ 3.50 $ 1,575.00
8160050 Slope Restoration 0 Syd $ 3.00 $ -
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 0 Sft $ 10.00 $ -
Total for FTA Code 20.01 $ 7,879.00

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 1 Ea $ 2,500.00 $ 2,500.00
8250095 Hydrant, Relocate, Case 1 1 Ea $ 3,000.00 $ 3,000.00
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 11,575.00

Station Construction Cost Estimate $ 32,029.00

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - 28th Street Station SB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/14/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 117 Syd $ 6.00 $ 702.00
3010002 Subbase, CIP (12 inch) 39 Cyd $ 10.00 $ 390.00
3020016 Aggregate Base, 6 inch 117 Syd $ 5.00 $ 585.00
6020108 Conc Pavt, Nonreinf, 10 inch 117 Syd $ 40.00 $ 4,680.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 6,757.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 0 Ea $ 500.00 $ -
2040006 Curb and Gutter, Rem 88 Ft $ 5.00 $ 440.00
2040013 Sidewalk, Rem 65 Syd $ 5.50 $ 357.50
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 18 Cyd $ 10.00 $ 180.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 0 Ft $ 15.00 $ -
8027001 Curb and Gutter, Conc, Det F4, Mod 38 Ft $ 15.00 $ 570.00
8030002 Sidewalk, Conc, 4 inch 468 Sft $ 3.00 $ 1,404.00
8030003 Sidewalk, Conc, 6 inch 440 Sft $ 3.50 $ 1,540.00
8160050 Slope Restoration 44 Syd $ 3.00 $ 132.00
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 0 Sft $ 10.00 $ -
Total for FTA Code 20.01 $ 6,473.50

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 0 Ea $ 2,500.00 $ -
8250095 Hydrant, Relocate, Case 1 0 Ea $ 3,000.00 $ -
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 6,075.00

Station Construction Cost Estimate $ 24,805.50

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - 36th Street Station NB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/14/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 216 Syd $ 6.00 $ 1,296.00
3010002 Subbase, CIP (12 inch) 39 Cyd $ 10.00 $ 390.00
3020016 Aggregate Base, 6 inch 117 Syd $ 5.00 $ 585.00
6020108 Conc Pavt, Nonreinf, 10 inch 117 Syd $ 40.00 $ 4,680.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 7,351.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 0 Ea $ 500.00 $ -
2040006 Curb and Gutter, Rem 327 Ft $ 5.00 $ 1,635.00
2040013 Sidewalk, Rem 72 Syd $ 5.50 $ 396.00
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 31 Cyd $ 10.00 $ 310.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 0 Ft $ 15.00 $ -
8027001 Curb and Gutter, Conc, Det F4, Mod 114 Ft $ 15.00 $ 1,710.00
8030002 Sidewalk, Conc, 4 inch 1,045 Sft $ 3.00 $ 3,135.00
8030003 Sidewalk, Conc, 6 inch 656 Sft $ 3.50 $ 2,296.00
8160050 Slope Restoration 109 Syd $ 3.00 $ 327.00
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 869 Sft $ 10.00 $ 8,690.00
Total for FTA Code 20.01 $ 20,349.00

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 0 Ea $ 2,500.00 $ -
8250095 Hydrant, Relocate, Case 1 0 Ea $ 3,000.00 $ -
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 6,075.00

Station Construction Cost Estimate $ 39,275.00

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - 36th Street Station SB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/14/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 223 Syd $ 6.00 $ 1,338.00
3010002 Subbase, CIP (12 inch) 39 Cyd $ 10.00 $ 390.00
3020016 Aggregate Base, 6 inch 117 Syd $ 5.00 $ 585.00
6020108 Conc Pavt, Nonreinf, 10 inch 117 Syd $ 40.00 $ 4,680.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 7,393.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 0 Ea $ 500.00 $ -
2040006 Curb and Gutter, Rem 331 Ft $ 5.00 $ 1,655.00
2040013 Sidewalk, Rem 30 Syd $ 5.50 $ 165.00
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 21 Cyd $ 10.00 $ 210.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 88 Ft $ 15.00 $ 1,320.00
8027001 Curb and Gutter, Conc, Det F4, Mod 116 Ft $ 15.00 $ 1,740.00
8030002 Sidewalk, Conc, 4 inch 1,130 Sft $ 3.00 $ 3,390.00
8030003 Sidewalk, Conc, 6 inch 259 Sft $ 3.50 $ 906.50
8160050 Slope Restoration 0 Syd $ 3.00 $ -
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 0 Sft $ 10.00 $ -
Total for FTA Code 20.01 $ 11,236.50

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 0 Ea $ 2,500.00 $ -
8250095 Hydrant, Relocate, Case 1 0 Ea $ 3,000.00 $ -
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 6,075.00

Station Construction Cost Estimate $ 30,204.50

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - 44th Street Station NB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/14/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 117 Syd $ 6.00 $ 702.00
3010002 Subbase, CIP (12 inch) 39 Cyd $ 10.00 $ 390.00
3020016 Aggregate Base, 6 inch 117 Syd $ 5.00 $ 585.00
6020108 Conc Pavt, Nonreinf, 10 inch 117 Syd $ 40.00 $ 4,680.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 6,757.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 0 Ea $ 500.00 $ -
2040006 Curb and Gutter, Rem 88 Ft $ 5.00 $ 440.00
2040013 Sidewalk, Rem 50 Syd $ 5.50 $ 275.00
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 23 Cyd $ 10.00 $ 230.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 0 Ft $ 15.00 $ -
8027001 Curb and Gutter, Conc, Det F4, Mod 38 Ft $ 15.00 $ 570.00
8030002 Sidewalk, Conc, 4 inch 615 Sft $ 3.00 $ 1,845.00
8030003 Sidewalk, Conc, 6 inch 572 Sft $ 3.50 $ 2,002.00
8160050 Slope Restoration 109 Syd $ 3.00 $ 327.00
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 980 Sft $ 10.00 $ 9,800.00
Total for FTA Code 20.01 $ 17,339.00

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 0 Ea $ 2,500.00 $ -
8250095 Hydrant, Relocate, Case 1 0 Ea $ 3,000.00 $ -
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 6,075.00

Station Construction Cost Estimate $ 35,671.00

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - 44th Street Station SB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/14/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 117 Syd $ 6.00 $ 702.00
3010002 Subbase, CIP (12 inch) 39 Cyd $ 10.00 $ 390.00
3020016 Aggregate Base, 6 inch 117 Syd $ 5.00 $ 585.00
6020108 Conc Pavt, Nonreinf, 10 inch 117 Syd $ 40.00 $ 4,680.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 6,757.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 1 Ea $ 500.00 $ 500.00
2040006 Curb and Gutter, Rem 88 Ft $ 5.00 $ 440.00
2040013 Sidewalk, Rem 55 Syd $ 5.50 $ 302.50
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 24 Cyd $ 10.00 $ 240.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 0 Ft $ 15.00 $ -
8027001 Curb and Gutter, Conc, Det F4, Mod 38 Ft $ 15.00 $ 570.00
8030002 Sidewalk, Conc, 4 inch 632 Sft $ 3.00 $ 1,896.00
8030003 Sidewalk, Conc, 6 inch 596 Sft $ 3.50 $ 2,086.00
8160050 Slope Restoration 109 Syd $ 3.00 $ 327.00
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 980 Sft $ 10.00 $ 9,800.00
Total for FTA Code 20.01 $ 18,011.50

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 0 Ea $ 2,500.00 $ -
8250095 Hydrant, Relocate, Case 1 0 Ea $ 3,000.00 $ -
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 6,075.00

Station Construction Cost Estimate $ 36,343.50

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - 54th Street Station NB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/14/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 108 Syd $ 6.00 $ 648.00
3010002 Subbase, CIP (12 inch) 36 Cyd $ 10.00 $ 360.00
3020016 Aggregate Base, 6 inch 108 Syd $ 5.00 $ 540.00
6020108 Conc Pavt, Nonreinf, 10 inch 108 Syd $ 40.00 $ 4,320.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 6,268.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 0 Ea $ 500.00 $ -
2040006 Curb and Gutter, Rem 88 Ft $ 5.00 $ 440.00
2040013 Sidewalk, Rem 54 Syd $ 5.50 $ 297.00
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 21 Cyd $ 10.00 $ 210.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 0 Ft $ 15.00 $ -
8027001 Curb and Gutter, Conc, Det F4, Mod 38 Ft $ 15.00 $ 570.00
8030002 Sidewalk, Conc, 4 inch 573 Sft $ 3.00 $ 1,719.00
8030003 Sidewalk, Conc, 6 inch 504 Sft $ 3.50 $ 1,764.00
8160050 Slope Restoration 109 Syd $ 3.00 $ 327.00
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 980 Sft $ 10.00 $ 9,800.00
Total for FTA Code 20.01 $ 16,977.00

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 0 Ea $ 2,500.00 $ -
8250095 Hydrant, Relocate, Case 1 0 Ea $ 3,000.00 $ -
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 6,075.00

Station Construction Cost Estimate $ 34,820.00

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - 54th Street Station SB

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/14/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 115 Syd $ 6.00 $ 690.00
3010002 Subbase, CIP (12 inch) 36 Cyd $ 10.00 $ 360.00
3020016 Aggregate Base, 6 inch 108 Syd $ 5.00 $ 540.00
6020108 Conc Pavt, Nonreinf, 10 inch 108 Syd $ 40.00 $ 4,320.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 6,310.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 0 Ea $ 500.00 $ -
2040006 Curb and Gutter, Rem 88 Ft $ 5.00 $ 440.00
2040013 Sidewalk, Rem 53 Syd $ 5.50 $ 291.50
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 12 Cyd $ 10.00 $ 120.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 0 Ft $ 15.00 $ -
8027001 Curb and Gutter, Conc, Det F4, Mod 38 Ft $ 15.00 $ 570.00
8030002 Sidewalk, Conc, 4 inch 417 Sft $ 3.00 $ 1,251.00
8030003 Sidewalk, Conc, 6 inch 257 Sft $ 3.50 $ 899.50
8160050 Slope Restoration 109 Syd $ 3.00 $ 327.00
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 980 Sft $ 10.00 $ 9,800.00
Total for FTA Code 20.01 $ 15,549.00

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 0 Ea $ 2,500.00 $ -
8250095 Hydrant, Relocate, Case 1 0 Ea $ 3,000.00 $ -
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 6,075.00

Station Construction Cost Estimate $ 33,434.00

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - 60th Street Station, Northern Alternate

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/14/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 98 Syd $ 6.00 $ 588.00
3010002 Subbase, CIP (12 inch) 33 Cyd $ 10.00 $ 330.00
3020016 Aggregate Base, 6 inch 98 Syd $ 5.00 $ 490.00
6020108 Conc Pavt, Nonreinf, 10 inch 98 Syd $ 40.00 $ 3,920.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 5,728.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 0 Ea $ 500.00 $ -
2040006 Curb and Gutter, Rem 88 Ft $ 5.00 $ 440.00
2040013 Sidewalk, Rem 55 Syd $ 5.50 $ 302.50
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inches) 16 Cyd $ 10.00 $ 160.00
402xxxx Drainage 1 LS $ 1,300.00 $ 1,300.00
8027001 Curb, Conc, Det E4, Mod 0 Ft $ 15.00 $ -
8027001 Curb and Gutter, Conc, Det F4, Mod 38 Ft $ 15.00 $ 570.00
8030002 Sidewalk, Conc, 4 inch 570 Sft $ 3.00 $ 1,710.00
8030003 Sidewalk, Conc, 6 inch 324 Sft $ 3.50 $ 1,134.00
8160050 Slope Restoration 28 Syd $ 3.00 $ 84.00
xxxxxxx Station Shelter 1 Ea $ - $ -
xxxxxxx Right-of-Way - Sidewalk/Grading Easement 250 Sft $ 10.00 $ 2,500.00
Total for FTA Code 20.01 $ 8,750.50

40.02 Site Utilities/Utility Relocation


819xxxx Relocate Street Light 1 Ea $ 2,500.00 $ 2,500.00
8250095 Hydrant, Relocate, Case 1 0 Ea $ 3,000.00 $ -
xxxxxxx Relocate Street Sign 0 Ea $ 500.00 $ -
825xxxx Relocated water line (6 inch) 45 Ft $ 120.00 $ 5,400.00
8190157 Direct burial pvc conduit (2-2 inch dia) 45 Ft $ 15.00 $ 675.00
Total for FTA Code 40.02 $ 8,575.00

Station Construction Cost Estimate $ 28,553.50

URS Corporation
Project Construction Cost Estimate
Silver Line BRT - 60th Street Station, Southern Alternate

WSA Project No. 104601


URS Project No. 12942679
Date of Estimate: 11/14/2010

FTA MDOT Pay Estimated


Code Item Code Description Quantity Unit Unit Price Price
2010 Dollars Dollars
10.02 Guideway - concrete bus pad
2040011 Pavt, Rem 98 Syd $ 6.00 $ 588.00
3010002 Subbase, CIP (12 inch) 33 Cyd $ 10.00 $ 330.00
3020016 Aggregate Base, 6 inch 98 Syd $ 5.00 $ 490.00
6020108 Conc Pavt, Nonreinf, 10 inch 98 Syd $ 40.00 $ 3,920.00
205xxxx Excavation and Embankment 1 LS $ 200.00 $ 200.00
402xxxx Manhole and catch basin adjustments 1 LS $ 200.00 $ 200.00
Total for FTA Code 10.02 $ 5,728.00

10.03 At-grade in Mixed Traffic


xxxxxxx Maintaining Traffic for Station Construction 1 LS $ 5,500.00 $ 5,500.00
Total for FTA Code 10.03 $ 5,500.00

20.01 At-grade Station


2020004 Tree, Rem, 6 inch to 18 inch 0 Ea $ 500.00 $ -
2040006 Curb and Gutter, Rem 88 Ft $ 5.00 $ 440.00
2040013 Sidewalk, Rem 54 Syd $ 5.50 $ 297.00
205xxxx Excavation and Embankment 1 LS $ 300.00 $ 300.00
208xxxx Erosion Control 1 LS $ 250.00 $ 250.00
3010002 Subbase, CIP (varies 4 to 9 inch

Anda mungkin juga menyukai