JADWAL PELAKSANAAN PEKERJAAN (TIME SCHEDULE)

PENGADAAN PERALATAN GEDUNG KANTOR BADAN PENGELOLAAN KEUANGAN DAN ASET DAERAH KAB. MIMIKA
TAHUN ANGGARAN 2021

BOBOT
NO URAIAN SAT Kuantitas HARGA SATUAN APRIL MEI JUNI JULI AGUSTUS SEPTEMER OKTOBER NOVEMBER KET.
PERSEN (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

100

1. PENGADAAN ALAT TULIS KANTOR (ATK) LS 1.00 1,144,005,940.00 100.00 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 50

0
TOTAL BOBOT 100.0

PRESTASI FISIK 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94 2.94
RENCANA
KOMULATIF 2.94 5.88 8.82 11.76 14.71 17.65 20.59 23.53 26.47 29.41 32.35 35.29 38.24 41.18 44.12 47.06 50.00 52.94 55.88 58.82 61.76 64.71 67.65 70.59 73.53 76.47 79.41 82.35 85.29 88.24 91.18 94.12 97.06 100.00
PRESTASI FISIK
PELAKSANAAN
KOMULATIF

DEVIASI +/-

PENYEDIA JASA
CV. U L P I M A

CARL GUSTAF NIAAMAN GIAY.


DIREKTUR