KEGIATAN :
PEKERJAAN :
LOKASI :
TAHUN ANGGARAN :
…………………..
Direktur
DAFTAR ANALISA UPAH DAN BAHAN
KEGIATAN : 0
PEKERJAAN : 0
LOKASI : 0
TAHUN ANGGARAN : 0
A. PEKERJAAN PERSIAPAN
B. PEKERJAAN TANAH
B. 1 Galian Tanah Keras Sedalam 1 M 1 M3
0.6250 OH Pembantu Tukang 55,000.00 34,375.00
0.0620 OH Mandor 80,000.00 4,960.00
39,335.00 39,335.00
B. 3 Urugan Kembali 1 M2
0.1920 OH Pembantu Tukang 55,000.00 10,560.00
0.0190 OH Mandor 80,000.00 1,520.00
12,080.00 12,080.00
B. 4 Urugan Tanah M3
1.2000 M3 Tanah urug 68,000.00 81,600.00
0.3000 OH Pekerja Biasa 55,000.00 16,500.00
0.0100 OH Mandor 80,000.00 800.00
17,300.00 81,600.00 98,900.00
B. 5 Urugan Tanah 1 M3
1.2000 M3 Tanah pilihan 68,000.00 81,600.00
0.2500 OH Pekerja Biasa 55,000.00 13,750.00
0.0250 OH Mandor 80,000.00 2,000.00
15,750.00 81,600.00 97,350.00
B. 6 Urugan Pasir 1 M3
1.2000 M3 Pasir Urug (Mahakam) 80,000.00 96,000.00
0.3000 OH Pembantu Tukang 55,000.00 16,500.00
0.0100 OH Mandor 80,000.00 800.00
17,300.00 96,000.00 113,300.00
C. PEKERJAAN BETON
C. 1 Membuat Beton Tumbuk Camp. 1 Pc : 3 Ps : 5 Kr 1 M3
0.8700 M3 Koral Beton/kerikil Palu 280,000.00 243,600.00
218.0000 Kg Semen Portland 50 Kg 1,200.00 261,600.00
0.5200 M3 Pasir Beton 190,000.00 98,800.00
1.6500 OH Pekerja Biasa 50,000.00 82,500.00
0.2500 OH Tukang Batu 65,000.00 16,250.00
0.0250 OH Kepala Tukang 70,000.00 1,750.00
0.0800 OH Mandor 80,000.00 6,400.00
106,900.00 604,000.00 710,900.00
J. PEKERJAAN PAVING
J. 1 Pasang Paving Block M2
35.0000 Bh Paving Stone 5,000.00 175,000.00
0.1200 M3 Pasir Urug 80,000.00 9,600.00
0.1560 Oh Tukang 65,000.00 10,140.00
0.0156 Oh Kepala Tukang 70,000.00 1,092.00
0.3000 Oh Pekerja 50,000.00 15,000.00
0.0150 Oh Mandor 80,000.00 1,200.00
27,432.00 184,600.00 212,032.00
……………………..
Direktur
RENCANA ANGGARAN BIAYA ( RAB )
KEGIATAN :
PEKERJAAN :
LOKASI :
TAHUN ANGGARA:
A PEKERJAAN PENDAHULUAN
1 Pembersihan 294.480 M2 A. 1 9,500.00 2,797,560.00
JUMLAH 2,797,560.00
C PEKERJAAN BETON
1 Cor Rabat 29.448 M3 C. 1 710,900.00 20,934,583.20
2 Pasang Wire Mash M6 294.480 M2 40,000.00 11,779,200.00
JUMLAH 32,713,783.20
TERBILANG : LIMA PULUH DUA JUTA TIGA RATUS EMPAT PULUH TIGA RIBU RUPIAH
…………………………………. ……………………….
NIP. Direktur