Uraian Pekerjaan Satuan Vol Harga Satuan Jumlah Harga

PEKERJAAN PENGECATAN

A. RUANGAN PERPUSTAKAAN EX. JOTASHIELD ANTIFADE


Dinding depan m2 16.43 48,662 799,638
Dinding belakang m2 23.46 48,662 1,141,610
Dinding samping m2 43.50 48,662 2,116,797

B. PENGECATAN RUANG RUANGAN KELAS VIII D dan VIII E EX.


JOTASHIELD ANTIFADE
Dinding depan m2 29.34 48,662 1,427,743
Dinding belakang m2 21.06 48,662 1,024,822
Dinding samping m2 41.04 48,662 1,997,088

C. PENGECATAN RUANG KELAS VII D EX. JOTASHIELD ANTIFADE


Dinding depan m2 19.04 48,662 926,524
Dinding belakang m2 15.69 48,662 763,507
Dinding samping m2 28 48,662 1,362,536

D. PENGECATAN RUANG KELAS DUA PINTU EX. JOTASHIELD


ANTIFADE
Dinding depan m2 21.16 48,662 1,029,688
Dinding belakang m2 21.285 48,662 1,035,771
Dinding samping m2 21 48,662 1,021,902

E. PENGECATAN RUANG KELAS BARU 1 PINTU EX. JOTASHIELD


ANTIFADE
Dinding depan m2 33.105 48,662 1,610,955
Dinding belakang m2 38.935 48,662 1,894,655
Dinding samping m2 56 48,662 2,725,072
Kolom m2 11.412 48,662 555,331

F. RUANG KELAS BELUM DI CAT TAHUN 2020


Dinding samping m2 22.4 Rp 48,662 1,090,029

G. RUANG GURU DEPAN


Sisi Belakang Depan m2 121.43 Rp 48,662 5,909,027
Sisi Belakang Samping m2 72.3675 Rp 48,662 3,521,547

H. SAMPING KANTOR
Sisi Belakang m2 21 Rp 48,662 1,021,902

I. LAIN-LAIN
1. Sewa Alat Bantu (scafollding) ls 1 5,000,000 5,000,000
2. Pekerjaan Persiapan dan pembersihan ls 1 3,500,000 3,500,000
3. Perbaikan keretakan dan aci ulang ls 1 4,685,674 4,685,674

TOTAL 46,161,818
PPN 10% 4,616,182
GRAN TOTAL Rp 50,778,000