TOTAL VOLUME PEKERJAAN STRUKTUR BETON

PENANGANAN LONGSORAN (SEGMEN 4 & 5) SEKSI 2 MENTEWE


VOLUME PEKERJAAN STRUKTUR BETON
Volume Bktg Rasio Bktg
Mutu Beton Beton (M2) (M2/M3)
No Item Pekerjaan
(Mpa)
(M3)
4 Segmen 4 Km. 234+900 – Km. 234+950
4.1 Dinding Penahan Tanah L = 35.87 M' f'c 20 191,89 354,65 1,848
4.2 Bore Pile D = 11 M' f'c 20 93,22 - -
4.3 U-Ditch L = 87 M' f'c 20 51,33 781,26 15,220
4.4 Lantai Kerja Pile Cap DPT (10 cm) L = 35.87 M' f'c 10 17,94 - -
4.5 Lantai Kerja U-Ditch (10 cm) L = 87 M' f'c 10 11,31 - -
5 Segmen 5 Km. 235+500 – Km. 235+550
5.1 Dinding Penahan Tanah L = 51.20 M' f'c 25 252,52 401,94 1,592
5.2 Bore Pile D = 10 M' f'c 25 102,90 - -
5.3 Cor Tambahan L = 0.86 M' f'c 25 0,24 3,05 12,708
5.4 Wing Wall Box Culvert L = 2 M' f'c 25 1,32 9,98 7,561
5.5 U-Ditch L = 111 M' f'c 25 74,34 1.131,48 15,220
5.6 Rigid Pavement L = 53.11 M' f'c 30 111,55 69,75 0,625
5.7 Lantai Kerja Pile Cap DPT (10 cm) L = 51.20 M' f'c 10 17,92 - -
5.8 Lantai Kerja U-Ditch (10 cm) L = 111 M' f'c 10 14,43 - -
5.9 Lantai Kerja Rigid (10 cm) L = 53.11 M' f'c 10 37,18 - -
5.10 Bak Kontrol (jika dikerjakan) L = 2.60 M' f'c 25 10,86 62,00 5,709
5.11 Balok Saluran DS (jika dikerjakan) L = 15 M' f'c 25 5,07 21,08 4,158
5.12 Saluran Penghantar (jika dikerjakan) L = 1.80 M' f'c 25 2,28 13,60 5,965
5.13 Box Culvert (jika dikerjakan) L = 8 M' f'c 25 23,20 23,59 1,017
5.14 Lantai Kerja lainnya (10 cm) f'c 10 4,60 - -

1.024,09 2.872,38
M3 M2

Vol Vol
Mutu Beton TOTAL KEPERLUAN BETON
No Area Pekerjaan Beton Bktg
(Mpa) SEGMEN 4 & SEGMEN 5
(M3) (M2)
4 Segmen 4 Km. 234+900 – Km. 234+950 f'c 10 98,77 M3
f'c 10 29,25 - f'c 20 336,44 M3
f'c 20 336,44 1.135,91 f'c 25 431,32 M3
5 Segmen 5 Km. 235+500 – Km. 235+550 f'c 30 111,55 M3
f'c 10 69,53 -
f'c 25 431,32 1.546,45
f'c 30 111,55 69,75 Tambahan Jika 5.10 s.d 5.14 dikerjakan
Jika 5.10 s.d 5.13 dikerjakan f'c 25 41,41 120,27 f'c 10 4,60 M3
Jika 5.14 dikerjakan f'c 10 4,60 - f'c 25 41,41 M3

Tabel JMF'
Material Sat f'c 30 f'c 25 f'c 20 f'c 10
Split 2-3 Kg 422,5 434,7 444,7 458,6
Split 1-2 Kg 591,5 608,6 622,6 642,0
Pasir Kg 676,0 695,5 711,6 733,7
Semen Kg 500,0 451,2 411,1 355,8

TOTAL KEBUTUHAN PENGADAAN MATERIAL UNTUK SEGMEN 4 & 5


KEBUTUHAN PENGADAAN
Area Sat f'c 30 f'c 25 f'c 20 f'c 10
MATERIAL SEGMEN 4 & 5
Split 2-3 M3 40,00 159,00 127,00 39,00 365,00 M3
Split 1-2 M3 56,00 223,00 178,00 54,00 511,00 M3
Pasir M3 70,00 275,00 220,00 67,00 632,00 M3
Semen sak/50kg 1.228,00 4.282,00 3.043,00 774,00 9.327,00 sak/50kg atau 466,40 ton

KEBUTUHAN TAMBAHAN MATERIAL JIKA POINT 5.10 s/d 5.14 DIKERJAKAN


Area Sat f'c 30 f'c 25 f'c 20 f'c 10 KEBUTUHAN PENGADAAN
Split 2-3 M3 - 16,00 - 2,00 18,00 M3
Split 1-2 M3 - 22,00 - 3,00 25,00 M3
Pasir M3 - 27,00 - 4,00 31,00 M3
Semen sak/50kg - 412,00 - 37,00 449,00 sak/50kg atau 22,50 ton