Anda di halaman 1dari 2

PEMERINTAH KABUPATEN BULELENG

KECAMATAN KUBUTAMBAHAN
PERBEKEL BULIAN
RENCANA PENGGUNAAN DANA (RPD)
PROGRAM PENYEDIAAN AIR MINUM DAN SANITASI BERBASIS MASYARAKAT
(PAMSIMAS) III TAHUN 2018
DESA BULIAN KECAMATAN KUBUTAMBNAHAN

HARGA
JUMLAH
NO URAIAN VOLUME SATUAN SATUAN
( Rp. )
( Rp. )
1 2 3 4 5 6 = ( 3X5 )
I Pengadaan dan Pemasangan PIPA Transmisi HDPE SNI PN 10 Dia 90 mm (3”)
A. BAHAN
1. Pipa HDPEPN 10 Dia 216,91 M 81.630,00 17.706.310,00
3” ( 90 mm )
JUMLAH I 17.706.310,00
II Pengadaan dan Pemasangan PIPA Distribusi PVC SNI S 12,5 (RRJ) Dia
63 mm (2”)
A. UPAH TENAGA KERJA
1. Tukang Pipa 20,00 OH 109.600,00 2.192.000,00
2. Pekerja 294,00 OH 86.600,00 25.460.400,00
B. BAHAN
1. Pipa Distribusi 1.321,55 M 29.430,00 38.893.328,56
PVC SNI S 12,5
(RRJ) Dia 63 mm
(2”)
2. Accessories 1,00 LS 7.447.967,82 7.447.967,82
JUMLAH II 73.993.696,38
III Reservoar (4 x 5 x 3) m

A. UPAH TENAGA KERJA


1. Pekerja 100,00 OH 86.600,00 8.660.000,00
B. BAHAN
1. Kayu Begesting 1,00 M3 7.837.400,00 7.837.400,00
2. Papan Begesting 2,00 M3 13.500,00 27.000,00
3. Paku 20,00 Kg 20.800,00 416.000,00
4. Pasir Urug 1,00 M3 182.900,00 182.900,00
5. Pasir Pasang 2,00 M3 313.000,00 627.200,00
6. Pasir Beton 4,00 M3 288.000,00 1.152.000,00
7. Batu Kosong 1,00 M3 227.700,00 227.700,00
8. Batu Kali 2,00 M3 224.600,00 449.200,00
9. Bata Merah 315,00 Buah 3.150,00 992.250,00
10. Kawat 13,98 Kg 20.800,00 290.800,00
11. Semen 67,00 Zak 67.100,00 4.495.700,00
12. Koral 5,00 M3 339.600,00 1.698.000,00
13. Minyak 8,00 Ltr 30.500,00 244.000,00
Begesting
14. Besi 1.013,00 Kg 8.721,66 8.835.043,62
15. Playwood 9 mm 15,00 Lbr 120.000,00 1.800.000,00
16. Bambu pj. 4 m 101,00 Btg 26.000,00 2.626.000,00
17. Cat 58,00 Kg 68.700,00 3.984.600,00
Waterproofing
18. Pipa GI 3” 6,00 M 191.650,00 1.149.900,00
19. Gate Valve AF 1,00 Buah 1.800.000,00 1.800.000,00
3”
20. Flang Las 3” 4,00 Buah 141.075,00 564.300,00
21. Baut 40,00 Buah 6.000,00 240.000,00
JUMLAH III 48.299.993,62
TOTAL 140.000.000,00