Anda di halaman 1dari 10

RENCANA ANGGARAN BIAYA

Propinsi : Kalimantan Tengah No. RAB :


Kabupaten : Katingan Program : PNPM-MPd
Kecamatan : Bukit Raya Jenis Kegiatan : MCK
Desa : Tbg. Kaburai Ukuran / Dimensi : 3x4 6 Unit

Volume Kategori Harga Satuan Jumlah Jumlah PNPM -


No Uraian Material Satuan
Total Swadaya PNPM Biaya (Rp ) Swadaya (Rp) MPD (Rp)
a b c=a-b d c f g=bxf h=cxf

BAHAN

1 Semen Gresik. 40 Kg 26 26 Zak I-b 150,000 3,900,000


2 Pasir Beton 7 7 M3 I-a 200,000 1,360,000
3 Kerikil Beton 0 0 M3 I-a 200,000 72,000
4 Kawat Harmonika 5 5 M2 I-b 40,000 180,000
5 Batako 224 224 Bh I-b 5,000 1,120,000
6 Besi Ø 10 mm 6 6 Btng I-b 60,000 384,000
7 Besi Ø 6 mm 13 13 Btng I-b 45,000 576,000
8 Batu Belah 3 3 M3 I-b 350,000 1,146,600
9 Balok Kuda -Kuda 5/7 10 10 Bh I-a 25,000 250,000
10 Balok Kasau 5/5 10 10 Bh I-a 15,000 150,000
11 Papan Lap 2/10 6 6 Bh I-a 15,000 90,000
12 Papan Listplank Ulin 4 4 Kpng I-a 60,000 240,000
13 Atap Seng 8 8 Lbr I-b 60,000 480,000
14 Nok Atap Seng/ Bubungan 4 4 M1 I-b 20,000 80,000
15 Cat Kilap 4 4 Kg I-b 60,000 240,000
16 Klosed Jongkok 1 1 Bh I-b 150,000 150,000
17 Pipa PVC Dia. 4 " 2 2 Btng I-b 180,000 360,000
18 Pipa PVC Dia. 2 " 1 1 Btng I-b 70,000 70,000
19 Lem dan Seal Tape 3 3 Bh I-b 20,000 60,000
20 Engsel dan Kunci 3 3 Bh I-b 200,000 600,000
21 Pintu Panel ( 90 x 180 cm ) 1 1 Bh I-b 700,000 700,000
22 Bak Air Biasa 1 1 Bh I-b 200,000 200,000
23 Sepitank 1 1 Bh I-b 3,000,000 3,000,000
24 Papan Nama Kegiatan 1 1 Bh I-a 200,000 200,000 -
25 Prasasti / Plakat PNPM - MP 1 1 Bh I-b 250,000 250,000

TOTAL BAHAN 200,000 15,408,600


ALAT - ALAT
1 Satu Set alat tukang kayu 1 1 Set 1,000,000 1,000,000
2 Satu Set alat tukang beton 1 1 Set 500,000 500,000
TOTAL ALAT 1,500,000 -
UPAH KERJA

1 Mandor / Kepala Kerja 5 5 Hok 65,000 325,000


2 Tukang 20 20 Hok 60,000 1,200,000
3 Pekerja 20 20 Hok 55,000 1,100,000

TOTAL UPAH 2,625,000.00

Swadaya Rp 1,700,000
Sumber Lain Rp -
SUMBER DANA
PNPM - MP Rp 18,033,600
TOTAL BIAYA Rp 19,733,600

Rp 18,033,600 x 6 Unit = PNPM Rp 108,201,600

Rp 1,700,000 x 6 Unit = Swadaya Rp 10,200,000

Tbg. Kajamei, Januari 2011

Diketahui Oleh : Diperiksa Oleh : Dibuat Oleh :


Fasilitator Kecamatan Ketua TPK
EBIT THEOPILUS, SH. YUPARNADI DODONG

Lembar 3

,
477
,
RENCANA ANGGARAN BIAYA

Propinsi : Kalimantan Tengah No. RAB :


Kabupaten : Katingan Program : PNPM-MPd
Kecamatan : Bukit Raya Jenis Kegiatan : MCK
Desa : Tbg. Kaburai Ukuran / Dimensi : 3x4 1 Unit

Volume Kategori Harga Satuan Jumlah Jumlah PNPM -


No Uraian Material Satuan
Total Swadaya PNPM Biaya (Rp ) Swadaya (Rp) MPD (Rp)
a b c=a-b d c f g=bxf h=cxf

BAHAN

1 Semen @. 50 Kg 26.00 26.00 Zak I-b 150,000 3,900,000


2 Pasir Beton 6.80 6.80 M3 I-a 200,000 1,360,000
3 Kerikil Beton 0.36 0.36 M3 I-a 200,000 72,000
4 Kawat Harmonika 4.50 4.50 M2 I-b 40,000 180,000
5 Batako 224.00 224.00 Bh I-b 5,000 1,120,000
6 Besi Ø 10 mm 6.40 6.40 Btng I-b 60,000 384,000
7 Besi Ø 6 mm 12.80 12.80 Btng I-b 45,000 576,000
8 Batu Belah 3.28 3.28 M3 I-b 350,000 1,146,600
9 Balok Kuda -Kuda 5/7 10.00 10.00 Bh I-a 25,000 250,000
10 Balok Kasau 5/5 10.00 10.00 Bh I-a 15,000 150,000
11 Papan Lap 2/10 6.00 6.00 Bh I-a 15,000 90,000
12 Papan Listplank Ulin 4.00 4.00 Kpng I-a 60,000 240,000
13 Atap Seng 8.00 8.00 Lbr I-b 60,000 480,000
14 Nok Atap Seng/ Bubungan 4.00 4.00 M1 I-b 20,000 80,000
15 Cat Kilap 4.00 4.00 Kg I-b 60,000 240,000
16 Klosed Jongkok 1.00 1.00 Bh I-b 150,000 150,000
17 Pipa PVC Dia. 4 " 2.00 2.00 Btng I-b 180,000 360,000
18 Pipa PVC Dia. 2 " 1.00 1.00 Btng I-b 70,000 70,000
19 Lem dan Seal Tape 3.00 3.00 Bh I-b 20,000 60,000
20 Engsel dan Kunci 3.00 3.00 Bh I-b 200,000 600,000
21 Pintu Panel ( 90 x 180 cm ) 1.00 1.00 Bh I-b 700,000 700,000
22 Bak Air Biasa 1.00 1.00 Bh I-b 200,000 200,000
23 Sepitank 1.00 1.00 Bh I-b 3,000,000 3,000,000
24 Papan Nama Kegiatan 1.00 1.00 Bh I-a 200,000 200,000 -
25 Prasasti / Plakat PNPM - MP 1.00 1.00 Bh I-b 250,000 250,000

TOTAL BAHAN 200,000 15,408,600


ALAT - ALAT

TOTAL ALAT -
UPAH KERJA

1 Mandor / Kepala Kerja 5.0 5.0 Hok 65,000 325,000


2 Tukang 20.0 20.0 Hok 60,000 1,200,000
3 Pekerja 20.0 20.0 Hok 55,000 1,100,000

TOTAL UPAH 2,625,000.00

Swadaya Rp 200,000
Sumber Lain Rp -
SUMBER DANA
PNPM - MP Rp 18,033,600
TOTAL BIAYA Rp 18,233,600
18,233,600 x 6 Unit = 109,401,600

Tbg. Kaburai, Januari 2011

Diketahui Oleh : Diperiksa Oleh : Dibuat Oleh :


Fasilitator Kecamatan Ketua TPK
EBIT THEOPILUS, SH. YUPARNADI DODONG

Lembar 3

,
,
KECAMATAN BUKIT RAYA
DAFTAR HARGA SATUAN BAHAN DAN UPAH KERJA

NO MATERIAL / BARANG SATUAN HARGA (Rp) KET.

1 2 3 4 5

BAHAN BANGUNAN
1 Pasir pasang M³ Rp. 200,000-
2 ###Kerikil M³ Rp. 200,000-
Batu utk pondasi ø 20 s/d 40 cm M³ Rp. 350,000-
3 Semen PC ( isi 40 Kg ) Gresik Zak Rp. 150,000-
4 Kayu Ulin
10/10 cm - 4 M Btg Rp. 90,000-
5/10 cm - 4 M Btg Rp. 60,000-
8/8 cm - 4 M Btg Rp. 75,000-
5/7 cm - 4 M Btg Rp. 40,000-
5/5 cm - 4 M Btg Rp. 30,000-
3/20 cm - 4 M Kpg Rp. 125,000-
2/20 cm - 4 M Kpg Rp. 60,000-
5 Kayu Meranti
10/10 cm - 4 M Btg Rp. 60,000-
5/10 cm - 4 M Btg Rp. 30,000-
8/8 cm - 4 M Btg Rp. 40,000-
5/7 cm - 4 M Btg Rp. 25,000-
5/5 cm - 4 M Btg Rp. 15,000-
3/5 cm - 4 M Kpg Rp. 10,000-
2/20 cm - 4 M Kpg Rp. 25,000-
6 Paku Kayu Kg Rp. 30,000-
7 Paku Ulin Kg Rp. 50,000-
8 Batako Bh Rp. 5,000-
9 Besi diameter 10 cm Btg Rp. 60,000-
10 Besi diameter 6 cm Btg Rp. 45,000-
11 Genteng metal Prima colour tebal 0,35 mm M² Rp. 95,000-
12 Bubungan Genteng metal M' Rp. 30,000-
13 Seng plat 3" x 6" BJLS 28 Lbr Rp. 60,000-
14 Kawat Harmonika M2 Rp. 40,000-
15 Bak Mandi Fibreglass ukuran sedang Bh Rp. 200,000-
16 Closed jongkok porselen Bh Rp. 150,000-
17 Pipa PVC diameter 2" AW (Maspion) Btg Rp. 70,000-
18 Pipa PVC diameter 4" AW (Maspion) Btg Rp. 180,000-
19 Cat Kayu Mengkilat merk Platon Kg Rp. 60,000-
20 Cat Menie Kg Rp. 30,000-
21 Cat Dasar Kg Rp. 25,000-
22 Kran Air Kg Rp. 25,000-
23 Baut 10 cm s/d 24 cm Kg Rp. 20,000-
24 Minyak Cat ( Thiner A ) Ltr Rp. 25,000-
25 Hitachi Bh Rp. 600,000-
26 Sambungan, L, T, PVC Lbr Rp. 10,000-
27 Engsel jendela ( kualitas standart ) Bh Rp. 15,000-
28 Engsel pintu ( kualitas standart ) Bh Rp. 20,000-
29 Kunci tanam 2 slag Bh Rp. 150,000-
30 Kaca bening ukuran 3 mm M² Rp. 150,000-
31 Septicktank Unit Rp. 3,000,000-

UPAH
NO. URAIAN TENAGA SATUAN KET
HARIAN

1 2 3 4 5

1 Tukang Batu HOK Rp. 90,000- 6 jam/hari


2 Tukang Kayu HOK Rp. 90,000- 6 jam/hari
3 Tukang Pancang HOK Rp. 90,000- 6 jam/hari
4 Tukang Cat HOK Rp. 90,000- 6 jam/hari
5 Pekerja HOK Rp. 70,000- 6 jam/hari

NO. HARGA BAHAN JADI SATUAN HARGA (Rp) KET

1 2 3 4 5

1 Pintu Panel Kayu Meranti Unit 700,000


2 Bingkai Jendela Unit 180,000
3 Papan sudah dimoulding Kpg 50,000
4 Almari Buku Unit 1,200,000
5 Meja 1/2 biro Unit 500,000
6 Meja belajar Unit 250,000
7 Satu Kursi TK + Meja Set 350,000
Kabupaten : Katingan Jenis Prasarana : Sarana dan Prasarana
Kecamatan : Bukit Raya TAKE OF SHEET Lokasi : Tbg. Kaburai
Desa : Tbg. Kaburai Volume :

I. PERHITUNGAN WC

Panjang = 2.5 M1
Lebar = 1.8 M1

1. Batu Belah 1.8 x 3 + 2.5 x 2 = 10.4 m1

Volume Batu ( 0,5 + 0,25 ) / 2 x 0.7 = 0.263 M2

10.4 x 0.263 x 1.2 = 3.276 M3

2. Timbunan Banah Biasa 0.35 x 2.5 x 1.8 = 1.575 M3

3. Tulangan Kolom 12/12 Besi Ø 10 mm 2.5 x 6 x 4 = 60 m1


Tulangan Sloof / Ringbalk 12/12 Besi Ø 10 mm = 10.4 M1

Jumlah Besi Ø 10 mm 70.4 / 11 = 6.4 Btng


Jumlah Besi Ø 6 mm 352 x 0.4 / 11 = 12.8 Btng

4. Semen untuk Pondasi ( SNI 02.1.1 )


Semen 4.04 Zak x 3.276 = 13.24 Zak
Pasir 0.52 x 3.276 = 1.704 M3
Kerikil

Lantai Semen 4.04 Zak x 0.1 x 1.8 x 2.5 = 1.818 Zak


( SNI 14,1,4 ) Pasir 0.5 M3 x 0.1 x 1.8 x 2.5 = 0.225 M3
Kerikil 0.8 M3 x 0.1 x 1.8 x 2.5 = 0.36 M3

Dinding Batako 2.5 x 2 x 2.4 = 12


( SNI 3,2,6 ) 1.8 x 2 x 2.4 = 8.64

20.64 - 2 = 18.64 M2 x 12 = 223.68 Bh

Semen 0.2 Zak x 18.64 = 3.728 Zak


Pasir 0.2 M3 x 18.64 = 3.728 M3

Plesteran
( SNI 3,3,1 ) Semen 0.2 Zak x 37.28 = 7.456 Zak
Pasir 0.013 M3 x 37.28 = 0.485 M3