DAFTAR RINCIAN DAN HARGA PENAWARAN

TAHUN 2021
PEMBANGUNAN RUKO EKSKLUSIF DAMAI PRESTIGIA LOKASI GENTAN, SINDUHARJO,
BOBOT
NO ITEM PEKERJAAN JUMLAH KETERANGAN
(%)
AGUSTUS SEPTEMBER OKTOBER NOVEMBER DESEMBER JANUARI FEBRUARI

A PEKERJAAN PERSIAPAN 46.431.431,50 0,99% 0,99% 0,99%

B PEKERJAAN GALIAN DAN URUGAN 111.549.817,77 2,38% 0,25% 2,12% 2,38%

C PEKERJAAN PASANGAN 1.272.998.973,68 27,13% 0,65% 0,89% 8,53% 8,53% 8,53% 18,60%

D PEKERJAAN BETON 1.388.731.252,61 29,59% 1,89% 2,30% 8,54% 11,55% 5,31% 29,59%
D2 PEKERJAAN BETON STRUKTUR LT.1 585.527.990,22 12,48% 6,24% 6,24%
D3 PEKERJAAN BETON LT-03 (Elev. +6,85) DAN ROOF TOP 498.290.717,30 10,62% 5,31%

E PEKERJAAN KUSEN DAN DAUN PINTU JENDELA 309.084.100,00 6,59% 2,54% 4,04% 6,59%
E1 PEKERJAAN KUSEN dan DAUN PJ LT-01 119.357.125,00 2,54% 2,54%
E2 PEKERJAAN KUSEN dan DAUN PJ LT-LT-02+ROOF TOOP 189.726.975,000 4,04%

F PEKERJAAN ACCESORIS PINTU DAN JENDELA 19.651.500,00 0,42% 0,42% 0,42%


F1 PEKERJAAN SLOT DAN HANDLE PINTU RUANG 15.592.500,00 0,33% 0,33%
F2 PEMASANGAN ENGSEL PINTU 4.059.000,00 0,09% 0,09%

G PEKERJAAN RANGKA ATAP 26.880.950,25 0,57% 0,57% 0,57%


G1 PEMASANGAN RANGKA ATAP BAJA RINGAN GIGA STEEL/SETARA 26.880.950,25 0,57% 0,57%

H PEKERJAAN PENUTUP ATAP 18.230.947,50 0,39% 0,39% 0,39%


H1 PENUTUP ATAP GALVALUM TEBAL 0,45 mm 18.230.947,50 0,39% 0,39%

I PEKERJAAN PLAFOND 123.756.350,00 2,64% 2,64% 2,64%


I1 PEKERJAAN PLAFOND LT-01ekerjaan Plafond LT-01 63.230.050,00 1,35%
I2 PEKERJAAN PLAFOND LT-02 60.526.300,00 1,29%

J PEKERJAAN KERAMIK 521.682.303,93 11,12% 5,56% 5,56% 11,12%

K PEKERJAAN CAT 181.842.922,06 3,88% 3,88% 3,88%

L PEKERJAAN INSTALASI AIR 335.074.016,64 7,14% 1,90% 0,56% 2,70% 1,98% 7,14%

M PEKERJAAN SANITAIR 97.233.400,00 2,07% 2,07% 2,07%


M1 Pek. Closed Duduk KM/WC + Jet Shower TOTO 65.615.000,00 1,40% 1,40%
M2 Pek. Kran TX 131L+Shower THX19NB TOTO 31.618.400,00 0,67% 0,67%
97.233.400,00

N PEKERJAAN INSTALASI LISTRIK 75.207.000,00 1,60% 0,39% 1,22% 1,60%


N1 PEKERJAAN LISTRIK LT-01 36.278.000,00 0,77% 0,39% 0,39% 0,77%
N2 PEKERJAAN LISTRIK LT-02 38.929.000,00 0,83% 0,83% 0,83%

O PEKERJAAN LAIN-LAIN 164.206.075,00 3,50% 1,44% 2,06% 3,50%


3,785% 7,218% 17,63% 28,83% 24,82% 14,69% 3,02% 100,00%

TOTAL SUB JUMLAH = 4.692.561.040,94 100%

RENCANA PROGRES 3,55% 7,10% 21,32% 34,27% 19,68% 10,57% 3,55% 100%
RENCANA KUMULATIF PROGRES 3,55% 10,65% 31,97% 66,24% 85,92% 96,49% 100,0% 100%
REALISASI 3,78% 7,22% 17,63% 28,83% 24,82% 14,69% 3,02% 100,00%
REALISASI KUMULATIF PROGRES 0,23% 7,45% 25,09% 53,91% 78,73% 93,43% 96%