PERHITUNGAN VOLUME TANAH

NO. PATLUAS GALIAN (M2) LUAS TIMBUNAN (M2) JARAK (M') VOLUME GALIAN (M3)

GC.14 90.72 2.75


15 2,456
GC.15 236.78 4.15
15 4,197
GC.16 322.8 3.19
15 4,478
GC.17 274.24 24.83
15 3,613.43
GC.18 207.550 55.610
15 3,092.10
GC.19 204.730 47.73
15 2,538.08
GC.20 133.68 63.41
15 1,579.65
GC.21 76.94 46.91
15 1,190.40
GC.22 81.78 61.35
15 990.23
GC.23 50.25 58.36
15 701.63
GC.24 43.30 83.25
15 446.93
GC.25 16.29 26.05
JUMLAH 25,283.33
VOLUME TIMBUNAN (M3)

51.75

55.05

210.15

603.30

775.05

833.55

827.40

811.95

897.83

1,062.08

819.75

6,947.85
18,335.48
DAFTAR ANALISA HARGA SATUAN
A.2.2.1. HARGA SATUAN PEKERJAAN PERSIAPAN

A.2.2.1.9. 1 M2 Pembersihan Lapangan dan Perataan


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.1000 82,000.00 8,200.00
Mandor L04 OH 0.0500 110,000.00 5,500.00
-
-
JUMLAH TENAGA KERJA 13,700.00
B. BAHAN
-
-
-
JUMLAH HARGA BAHAN -
C. PERALATAN
-
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 13,700.00


E. Overhead & Provit 10% XD 1,370.00
F. Harga Satuan Pekerjaan 15,070.00

A.Pagar Str Pembuatan 1 M Pagar Sementara


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.200 82,000.00 16,400.00
Tukang L02 OH 0.400 100,000.00 40,000.00
Kepala Tukang L03 OH 0.020 129,000.00 2,580.00
Mandor L04 OH 0.020 110,000.00 2,200.00
JUMLAH TENAGA KERJA 61,180.00
B. BAHAN
Kayu Dolken diameter 8 - 10 / 400 cm Btg 1.200 50,000.00 60,000.00
Semen / PC (40 Kg) kg 0.250 1,347.50 336.88
Seng Gelombang 0.25 mm 8 "(kaki) Lbr 1.200 72,000.00 86,400.00
Kayu Kelas IV M3 0.025 3,300,000.00 82,500.00
Pasir Beton M3 0.050 185,000.00 9,250.00
Paku Kayu kg 0.060 23,000.00 1,380.00

JUMLAH HARGA BAHAN 239,866.88


C. PERALATAN
-
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 301,046.88


E. Overhead & Provit 10% XD 30,104.69
F. Harga Satuan Pekerjaan 331,151.56
A.2.3.1. HARGA SATUAN PEKERJAAN TANAH

A.2.3.1.1. 1 M3 Galian Tanah Biasa Sedalam 1 M'


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.7500 82,000.00 61,500.00
Mandor L04 OH 0.0250 110,000.00 2,750.00

JUMLAH TENAGA KERJA 64,250.00


B. BAHAN
-
-
-
JUMLAH HARGA BAHAN -
C. PERALATAN
-
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 64,250.00


E. Overhead & Provit 10% XD 6,425.00
F. Harga Satuan Pekerjaan 70,675.00

A.2.3.1.9. 1 M3 Urugan Kembali Bekas Galian


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.2500 82,000.00 20,500.00
Mandor L04 OH 0.0500 110,000.00 5,500.00
-
-
JUMLAH TENAGA KERJA 26,000.00
B. BAHAN
-
-
-
JUMLAH HARGA BAHAN -
C. PERALATAN
-
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 26,000.00


E. Overhead & Provit 10% XD 2,600.00
F. Harga Satuan Pekerjaan 28,600.00
A.2.3.1.11 1 M3 Timbunan Tanah Didatangkan
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.3000 82,000.00 24,600.00
Mandor L04 OH 0.0100 110,000.00 1,100.00
-
-
JUMLAH TENAGA KERJA 25,700.00
B. BAHAN
Tanah Timbun M3 1.2000 69,000.00 82,800.00
-
-
JUMLAH HARGA BAHAN 82,800.00
C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 108,500.00


E. Overhead & Provit 10% XD 10,850.00
F. Harga Satuan Pekerjaan 119,350.00

Analisa ijuk 1 M2 memasang Ijuk Peresapan


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.1500 82,000.00 12,300.00
Mandor L04 OH 0.0150 110,000.00 1,650.00
-
-
JUMLAH TENAGA KERJA 13,950.00
B. BAHAN
Ijuk kg 6.0000 18,000.00 108,000.00
-
-
JUMLAH HARGA BAHAN 108,000.00
C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 121,950.00


E. Overhead & Provit 10% XD 12,195.00
F. Harga Satuan Pekerjaan 134,145.00

A.2.3.1.11. a 1 M3 Mengurug dengan Pasir Urug


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.3000 82,000.00 24,600.00
Mandor L04 OH 0.0100 110,000.00 1,100.00
-
-
JUMLAH TENAGA KERJA 25,700.00
B. BAHAN
Pasir Urug M3 1.2000 103,000.00 123,600.00
-
-
JUMLAH HARGA BAHAN 123,600.00
C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 149,300.00


E. Overhead & Provit 10% XD 14,930.00
F. Harga Satuan Pekerjaan 164,230.00
A.2.3.1.11.b 1 M3 Mengurug dengan Pasir Kerikil
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.3000 82,000.00 24,600.00
Mandor L04 OH 0.0100 110,000.00 1,100.00
-
-
JUMLAH TENAGA KERJA 25,700.00
B. BAHAN
Kerikil M3 1.2000 250,000.00 300,000.00
-
-
JUMLAH HARGA BAHAN 300,000.00
C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 325,700.00


E. Overhead & Provit 10% XD 32,570.00
F. Harga Satuan Pekerjaan 358,270.00

A.2.3.1.11.c 1 M3 Mengurug dengan Pasir Pasang


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.3000 82,000.00 24,600.00
Mandor L04 OH 0.0100 110,000.00 1,100.00
-
-
JUMLAH TENAGA KERJA 25,700.00
B. BAHAN
Pasir Pasang M3 1.2000 185,000.00 222,000.00
-
-
JUMLAH HARGA BAHAN 222,000.00
C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 247,700.00


E. Overhead & Provit 10% XD 24,770.00
F. Harga Satuan Pekerjaan 272,470.00

A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI


A.3.2.1.2. 1 M3 Pasangan Batu Gunung/Belah Campuran 1SP : 4 PP
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 1.5000 82,000.00 123,000.00
Tukang L02 OH 0.7500 100,000.00 75,000.00
Kepala Tukang L03 OH 0.0750 129,000.00 9,675.00
Mandor L04 OH 0.0750 110,000.00 8,250.00
JUMLAH TENAGA KERJA 215,925.00
B. BAHAN
Batu Belah M3 1.2000 196,000.00 235,200.00
Semen Portland Kg 163.00 1,347.50 219,642.50
Pasir Pasang M3 0.5200 185,000.00 96,200.00
JUMLAH HARGA BAHAN 551,042.50
C. PERALATAN
-
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 766,967.50


E. Overhead & Provit 10% XD 76,696.75
F. Harga Satuan Pekerjaan 843,664.25
A.3.2.1.9 1 M3 Pasangan Batu Kosong ( Anstamping )
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.7800 82,000.00 63,960.00
Tukang L02 OH 0.3900 100,000.00 39,000.00
Kepala Tukang L03 OH 0.0390 129,000.00 5,031.00
Mandor L04 OH 0.0390 110,000.00 4,290.00
JUMLAH TENAGA KERJA 112,281.00
B. BAHAN
Batu Belah M3 1.2000 196,000.00 235,200.00
Pasir Urug M3 0.4320 103,000.00 44,496.00
JUMLAH HARGA BAHAN 279,696.00
C. PERALATAN
-
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 391,977.00


E. Overhead & Provit 10% XD 39,197.70
F. Harga Satuan Pekerjaan 431,174.70

Analisa EI-422 1 M3 Lps. Pond. Ag. Kls. B (LPB)


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.250 82,000.00 20,490.85
Tukang L02 OH - 100,000.00 -
Kepala Tukang L03 OH - 129,000.00 -
Mandor L04 OH 0.036 110,000.00 3,926.82
JUMLAH TENAGA KERJA 24,417.67
B. BAHAN
Agregat Kasar B M3 0.420 290,000.00 121,800.00
Agregat Halus C M3 0.240 261,000.00 62,640.00
Sirtu M4 0.540 120,000.00 64,800.00
JUMLAH HARGA BAHAN 184,440.00
C. PERALATAN
Wheel Loader Jam 0.0350 250,000.00 8,750.00
Dump Truck Jam 0.2300 150,000.00 34,500.00
Motor Grader Jam 0.0040 250,000.00 1,000.00
Tandem Roller Jam 0.0060 220,000.00 1,320.00
Water Tanker Jam 0.0210 150,000.00 3,150.00
Alat Bantu Ls 1.0000 2,000.00 2,000.00
JUMLAH HARGA ALAT 50,720.00

D. Jumlah (A+B+C) 259,577.67


E. Overhead & Provit 10% XD 25,957.77
F. Harga Satuan Pekerjaan 285,535.44
A.4.1.1. HARGA SATUAN PEKERJAAN BETON
A.4.1.1.8. MEMBUAT 1 M3 BETON MUTU f’c = 21.7 MPa (K-250). SLUMP (12 ± 2) CM. W/C = 0.56 READY MIX
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 1.6500 82,000.00 135,300.00
Tukang L02 OH 0.2750 100,000.00 27,500.00
Kepala Tukang L03 OH 0.0280 129,000.00 3,612.00
Mandor L04 OH 0.0830 110,000.00 9,130.00
JUMLAH TENAGA KERJA 175,542.00
B. BAHAN
Semen Portland Kg 384.0000 1,347.50 517,440.00
Pasir Beton Kg 692.0000 132.14 91,442.86
Kerikil (Maks 30 mm) Kg 1,039.0000 214.81 223,192.59
Air Liter 215.0000 150.00 32,250.00

JUMLAH HARGA BAHAN 864,325.45


C. PERALATAN
Vibrator Jam 0.0520 65,000.00 3,380.00
Pompa beton Jam 0.0520 275,000.00 14,300.00
Peralatan Lainnya Ls 1.0000 50,000.00 50,000.00
JUMLAH HARGA ALAT 67,680.00

D. Jumlah (A+B+C) 1,107,547.45


E. Overhead & Provit 10% XD 110,754.74
F. Harga Satuan Pekerjaan 1,218,302.19

A.4.1.1.7. MEMBUAT 1 M3 BETON MUTU f’c = 19.3 MPa (K-225). SLUMP (12 ± 2) CM. W/C = 0.58
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 1.6500 82,000.00 135,300.00
Tukang L02 OH 0.2750 100,000.00 27,500.00
Kepala Tukang L03 OH 0.0280 129,000.00 3,612.00
Mandor L04 OH 0.0830 110,000.00 9,130.00
JUMLAH TENAGA KERJA 175,542.00
B. BAHAN
Semen Portland Kg 371.00 1,347.50 499,922.50
Pasir Beton Kg 698.00 132.14 92,235.71
Kerikil (Maks 30 mm) Kg 1,047.00 214.81 224,911.11
Air Liter 215.00 150.00 32,250.00

JUMLAH HARGA BAHAN 849,319.33


C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 1,024,861.33


E. Overhead & Provit 10% XD 102,486.13
F. Harga Satuan Pekerjaan 1,127,347.46
A.4.1.1.5 MEMBUAT 1 M3 Beton Mutu F'c = 14,5 Mpa (K 175), Slump (12 ± 2) cm, W/c = 0,66
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 1.6500 82,000.00 135,300.00
Tukang L02 OH 0.2750 100,000.00 27,500.00
Kepala Tukang L03 OH 0.0280 129,000.00 3,612.00
Mandor L04 OH 0.0830 110,000.00 9,130.00
JUMLAH TENAGA KERJA 175,542.00
B. BAHAN
Semen Portland Kg 326.0000 1,347.50 439,285.00
Pasir Beton Kg 760.0000 132.14 100,428.57
Kerikil (Maks 30 mm) Kg 1,029.0000 214.81 221,044.44
Air Liter 215.0000 150.00 32,250.00

JUMLAH HARGA BAHAN 793,008.02


C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 968,550.02


E. Overhead & Provit 10% XD 96,855.00
F. Harga Satuan Pekerjaan 1,065,405.02

A.4.1.1.17.a 10 Kg Pembesian dengan Besi Polos


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.0700 82,000.00 5,740.00
Tukang L02 OH 0.0700 100,000.00 7,000.00
Kepala Tukang L03 OH 0.0070 129,000.00 903.00
Mandor L04 OH 0.0040 110,000.00 440.00
JUMLAH TENAGA KERJA 14,083.00
B. BAHAN
Besi Beton Polos Kg 10.50 13,400.00 140,700.00
Kawat Beton Kg 0.15 22,000.00 3,300.00

JUMLAH HARGA BAHAN 144,000.00


C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 158,083.00


E. Overhead & Provit 10% XD 15,808.30
F. Harga Satuan Pekerjaan 173,891.30
Harga Satuan Pekerjaan untuk 1 Kg Besi = 17,389.13
A.4.1.1.17.b 10 Kg Pembesian dengan Besi ulir
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.0700 82,000.00 5,740.00
Tukang L02 OH 0.0700 100,000.00 7,000.00
Kepala Tukang L03 OH 0.0070 129,000.00 903.00
Mandor L04 OH 0.0040 110,000.00 440.00
JUMLAH TENAGA KERJA 14,083.00
B. BAHAN
Besi Beton Polos Kg 10.50 15,000.00 157,500.00
Kawat Beton Kg 0.15 22,000.00 3,300.00

JUMLAH HARGA BAHAN 160,800.00


C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 174,883.00


E. Overhead & Provit 10% XD 17,488.30
F. Harga Satuan Pekerjaan 192,371.30
Harga Satuan Pekerjaan untuk 1 Kg Besi = 19,237.13

A.4.1.1.19 1 Kg Memasang Jaring Kawat Baja / Wire Mesh


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.0250 82,000.00 2,050.00
Tukang L02 OH 0.0250 100,000.00 2,500.00
Kepala Tukang L03 OH 0.0020 129,000.00 258.00
Mandor L04 OH 0.0010 110,000.00 110.00
JUMLAH TENAGA KERJA 4,918.00
B. BAHAN
Kawat Wiremesh Kg 1.0200 18,566.78 18,938.11
Kawat Beton Kg 0.0500 22,000.00 1,100.00

JUMLAH HARGA BAHAN 20,038.11


C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 24,956.11


E. Overhead & Provit 10% XD 2,495.61
F. Harga Satuan Pekerjaan 27,451.72
A.4.1.1.20 1 M2 Memasang Bekisting Untuk Pondasi
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.5200 82,000.00 42,640.00
Tukang L02 OH 0.2600 100,000.00 26,000.00
Kepala Tukang L03 OH 0.0260 129,000.00 3,354.00
Mandor L04 OH 0.0260 110,000.00 2,860.00
JUMLAH TENAGA KERJA 74,854.00
B. BAHAN
Kayu Kelas III M3 0.0400 4,300,000.00 172,000.00
Paku 5-12 cm Kg 0.3000 23,000.00 6,900.00
Minyak Bekisting Liter 0.1000 19,000.00 1,900.00

JUMLAH HARGA BAHAN 180,800.00


C. PERALATAN
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 255,654.00


E. Overhead & Provit 10% XD 25,565.40
F. Harga Satuan Pekerjaan 281,219.40

A.4.1.1.21 1 M2 Memasang Bekisting Untuk Sloof


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.5200 82,000.00 42,640.00
Tukang L02 OH 0.2600 100,000.00 26,000.00
Kepala Tukang L03 OH 0.0260 129,000.00 3,354.00
Mandor L04 OH 0.0260 110,000.00 2,860.00
JUMLAH TENAGA KERJA 74,854.00
B. BAHAN
Kayu Kelas III M3 0.0450 4,300,000.00 193,500.00
Paku 5-12 cm Kg 0.3000 23,000.00 6,900.00
Minyak Bekisting Liter 0.1000 19,000.00 1,900.00

JUMLAH HARGA BAHAN 202,300.00


C. PERALATAN
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 277,154.00


E. Overhead & Provit 10% XD 27,715.40
F. Harga Satuan Pekerjaan 304,869.40
A.4.1.1.22. 1 M2 Pemasangan Bekisting Untuk Kolom
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.6600 82,000.00 54,120.00
Tukang L02 OH 0.3300 100,000.00 33,000.00
Kepala Tukang L03 OH 0.0330 129,000.00 4,257.00
Mandor L04 OH 0.0330 110,000.00 3,630.00
JUMLAH TENAGA KERJA 95,007.00
B. BAHAN
Kayu Kelas III M3 0.040 4,300,000.00 172,000.00
Paku 5-12 cm Kg 0.400 23,000.00 9,200.00
Minyak Bekisting Liter 0.200 19,000.00 3,800.00
Balok Kayu Kelas II M3 0.015 5,800,000.00 87,000.00
Plywood 9 mm Lbr 0.350 218,000.00 76,300.00
Dolken Kayu 8-10 cm x 4 m Batang 2.000 50,000.00 100,000.00

JUMLAH HARGA BAHAN 448,300.00


C. PERALATAN
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 543,307.00


E. Overhead & Provit 10% XD 54,330.70
F. Harga Satuan Pekerjaan 597,637.70

A.4.1.1.23 1 M2 Pemasangan Bekisting Untuk Balok


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.6600 82,000.00 54,120.00
Tukang L02 OH 0.3300 100,000.00 33,000.00
Kepala Tukang L03 OH 0.0330 129,000.00 4,257.00
Mandor L04 OH 0.0330 110,000.00 3,630.00
JUMLAH TENAGA KERJA 95,007.00
B. BAHAN
Kayu Kelas III M3 0.0400 4,300,000.00 172,000.00
Paku 5-12 cm Kg 0.4000 23,000.00 9,200.00
Minyak Bekisting Liter 0.2000 19,000.00 3,800.00
Balok Kayu Kelas II M3 0.0180 5,800,000.00 104,400.00
Plywood 9 mm Lbr 0.3500 218,000.00 76,300.00
Dolken Kayu 8-10 cm x 4 m Batang 2.0000 50,000.00 100,000.00

JUMLAH HARGA BAHAN 465,700.00


C. PERALATAN
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 560,707.00


E. Overhead & Provit 10% XD 56,070.70
F. Harga Satuan Pekerjaan 616,777.70
A.4.1.1.24 1 M2 Memasang Bekisting Untuk Plat Lantai
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.6600 82,000.00 54,120.00
Tukang L02 OH 0.3300 100,000.00 33,000.00
Kepala Tukang L03 OH 0.0330 129,000.00 4,257.00
Mandor L04 OH 0.0330 110,000.00 3,630.00
JUMLAH TENAGA KERJA 95,007.00
B. BAHAN
Kayu Kelas III M3 0.0400 4,300,000.00 172,000.00
Paku 5-12 cm Kg 0.4000 23,000.00 9,200.00
Minyak Bekisting Liter 0.2000 19,000.00 3,800.00
Balok Kayu Kelas II M3 0.0150 5,800,000.00 87,000.00
Plywood 9 mm Lbr 0.3500 218,000.00 76,300.00
Dolken Kayu 8-10 cm x 4 m Batang 6.0000 50,000.00 300,000.00

JUMLAH HARGA BAHAN 648,300.00


C. PERALATAN
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 743,307.00


E. Overhead & Provit 10% XD 74,330.70
F. Harga Satuan Pekerjaan 817,637.70

A.4.1.1.25 1 M2 Memasang Bekisting Untuk Dinding


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.6600 82,000.00 54,120.00
Tukang L02 OH 0.3300 100,000.00 33,000.00
Kepala Tukang L03 OH 0.0330 129,000.00 4,257.00
Mandor L04 OH 0.0330 110,000.00 3,630.00
JUMLAH TENAGA KERJA 95,007.00
B. BAHAN
Kayu Kelas III M3 0.0300 4,300,000.00 129,000.00
Paku 5-12 cm Kg 0.4000 23,000.00 9,200.00
Minyak Bekisting Liter 0.2000 19,000.00 3,800.00
Balok Kayu Kelas II M3 0.0200 5,800,000.00 116,000.00
Plywood 9 mm Lbr 0.3500 218,000.00 76,300.00
Dolken Kayu 8-10 cm x 4 m Batang 3.0000 50,000.00 150,000.00
Penjaga jarak / Spacer bh 4.0000 1,000.00 4,000.00
JUMLAH HARGA BAHAN 488,300.00
C. PERALATAN
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 583,307.00


E. Overhead & Provit 10% XD 58,330.70
F. Harga Satuan Pekerjaan 641,637.70
Pekerjaan Lain-lain (Membongkar Bekisting & Menyiram Beton)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 1.0000 82,000.00 82,000.00

JUMLAH TENAGA KERJA 82,000.00


B. BAHAN

JUMLAH HARGA BAHAN -


C. PERALATAN
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 82,000.00


E. Overhead & Provit 10% XD 8,200.00
F. Harga Satuan Pekerjaan 90,200.00

Analisa 1 1 M3 Pondasi Tapak 180x180x30


Harga Satuan Jumlah Harga
Analisa Uraian Pekerjaan Volume Satuan
Rp. Rp.

A.4.1.1.8. Beton K 250 1 M3 1,218,302.19 1,218,302.19


A.4.1.1.17.b Pembesian /Besi Ulir 153.691 Kg 19,237.13 2,956,571.38
A.4.1.1.20 Bekisting 2.19 M2 1 x pakai 281,219.40 616,182.95
Pekerjaan Lain-Lain 1 Ls 90,200.00 90,200.00

Jumlah 4,881,256.53
Harga Satuan 4,881,256.53

Analisa 2 1 M3 Pondasi Tapak 250x150x30


Harga Satuan Jumlah Harga
Analisa Uraian Pekerjaan Volume Satuan
Rp. Rp.

A.4.1.1.8. Beton K 250 1 M3 1,218,302.19 1,218,302.19


A.4.1.1.17.b Pembesian /Besi Ulir 156.498 Kg 19,237.13 3,010,565.04
A.4.1.1.20 Bekisting 2.23 M2 1 x pakai 281,219.40 628,056.66
Pekerjaan Lain-Lain 1 Ls 90,200.00 90,200.00

Jumlah 4,947,123.90
Harga Satuan 4,947,123.90

Analisa 3 1 M3 Pondasi Tapak 60x60x20


Harga Satuan Jumlah Harga
Analisa Uraian Pekerjaan Volume Satuan
Rp. Rp.

A.4.1.1.8. Beton K 250 1 M3 1,218,302.19 1,218,302.19


A.4.1.1.17.a Pembesian /Besi Polos 180.210 Kg 17,389.13 3,133,689.67
A.4.1.1.20 Bekisting 3.57 M2 1 x pakai 281,219.40 1,004,890.66
Pekerjaan Lain-Lain 1 Ls 90,200.00 90,200.00

Jumlah 5,447,082.52
Harga Satuan 5,447,082.52

Analisa 4 1 M3 Sloof Beton Bertulang 30x40cm


Harga Satuan Jumlah Harga
Analisa Uraian Pekerjaan Volume Satuan
Rp. Rp.

A.4.1.1.8. Beton K 250 1 M3 1,218,302.19 1,218,302.19


A.4.1.1.17.a Pembesian /Besi Polos 49.512 Kg 17,389.13 860,971.93
A.4.1.1.17.b Pembesian /Besi Ulir 67.665 Kg 19,237.13 1,301,680.34
A.4.1.1.21 Bekisting 6.67 M2 2 x pakai 152,434.70 1,016,231.33
Pekerjaan Lain-Lain 1 Ls 90,200.00 90,200.00

Jumlah 4,487,385.80
Harga Satuan 4,487,385.80
Analisa 5 1 M3 Sloof Beton Bertulang 20x25cm
Harga Satuan Jumlah Harga
Analisa Uraian Pekerjaan Volume Satuan
Rp. Rp.

A.4.1.1.8. Beton K 250 1 M3 1,218,302.19 1,218,302.19


A.4.1.1.17.a Pembesian /Besi Polos 147.658 Kg 17,389.13 2,567,639.48
A.4.1.1.17.b Pembesian /Besi Ulir - Kg 19,237.13 -
A.4.1.1.21 Bekisting 11.11 M2 2 x pakai 152,434.70 1,693,718.89
Pekerjaan Lain-Lain 1 Ls 90,200.00 90,200.00

Jumlah 5,569,860.56
Harga Satuan 5,569,860.56

Analisa 6 1 M3 Kolom Bertulang 40x50


Harga Satuan Jumlah Harga
Analisa Uraian Pekerjaan Volume Satuan
Rp. Rp.

A.4.1.1.8. Beton K 250 1 M3 1,218,302.19 1,218,302.19


A.4.1.1.17.a Pembesian /Besi Polos 48.423 Kg 17,389.13 842,031.40
A.4.1.1.17.b Pembesian /Besi Ulir 99.435 Kg 19,237.13 1,912,847.43
A.4.1.1.21 Bekisting 9.00 M2 2 x pakai 298,818.85 2,689,369.65
Pekerjaan Lain-Lain 1 Ls 90,200.00 90,200.00

Jumlah 6,752,750.68
Harga Satuan 6,752,750.68

Analisa 7 1 M3 Kolom Bertulang 40x40


Harga Satuan Jumlah Harga
Analisa Uraian Pekerjaan Volume Satuan
Rp. Rp.

A.4.1.1.8. Beton K 250 1 M3 1,218,302.19 1,218,302.19


A.4.1.1.17.a Pembesian /Besi Polos 52.461 Kg 17,389.13 912,254.29
A.4.1.1.17.b Pembesian /Besi Ulir 103.578 Kg 19,237.13 1,992,549.41
A.4.1.1.21 Bekisting 10.00 M2 2 x pakai 298,818.85 2,988,188.50
Pekerjaan Lain-Lain 1 Ls 90,200.00 90,200.00

Jumlah 7,201,494.40
Harga Satuan 7,201,494.40

Analisa 8 1 M3 Kolom Bertulang 25x25


Harga Satuan Jumlah Harga
Analisa Uraian Pekerjaan Volume Satuan
Rp. Rp.

A.4.1.1.8. Beton K 250 1 M3 1,218,302.19 1,218,302.19


A.4.1.1.17.a Pembesian /Besi Polos 128.716 Kg 17,389.13 2,238,258.28
A.4.1.1.17.b Pembesian /Besi Ulir - Kg 19,237.13 -
A.4.1.1.21 Bekisting 16.00 M2 2 x pakai 298,818.85 4,781,101.60
Pekerjaan Lain-Lain 1 Ls 90,200.00 90,200.00

Jumlah 8,327,862.07
Harga Satuan 8,327,862.07

Analisa 9 1 M3 Kolom Bertulang 13x13


Harga Satuan Jumlah Harga
Analisa Uraian Pekerjaan Volume Satuan
Rp. Rp.

A.4.1.1.8. Beton K 250 1 M3 1,218,302.19 1,218,302.19


A.4.1.1.17.a Pembesian /Besi Polos 271.330 Kg 17,389.13 4,718,200.91
A.4.1.1.17.b Pembesian /Besi Ulir - Kg 19,237.13 -
A.4.1.1.21 Bekisting 30.77 M2 2 x pakai 298,818.85 9,194,426.15
Pekerjaan Lain-Lain 1 Ls 90,200.00 90,200.00

Jumlah 15,221,129.26
Harga Satuan 15,221,129.26
Analisa 10 1 M3 Balok Bertulang 35x50
Harga Satuan Jumlah Harga
Analisa Uraian Pekerjaan Volume Satuan
Rp. Rp.

A.4.1.1.8. Beton K 250 1 M3 1,218,302.19 1,218,302.19


A.4.1.1.17.a Pembesian /Besi Polos 43.165 Kg 17,389.13 750,596.15
A.4.1.1.17.b Pembesian /Besi Ulir 76.44 Kg 19,237.13 1,470,420.14
A.4.1.1.21 Bekisting 7.71 M2 2 x pakai 308,388.85 2,378,999.70
Pekerjaan Lain-Lain 1 Ls 90,200.00 90,200.00

Jumlah 5,908,518.18
Harga Satuan 5,908,518.18

Analisa 11 1 M3 Balok Bertulang 30x40


Harga Satuan Jumlah Harga
Analisa Uraian Pekerjaan Volume Satuan
Rp. Rp.

A.4.1.1.8. Beton K 250 1 M3 1,218,302.19 1,218,302.19


A.4.1.1.17.a Pembesian /Besi Polos 49.512 Kg 17,389.13 860,971.93
A.4.1.1.17.b Pembesian /Besi Ulir 111.47 Kg 19,237.13 2,144,362.70
A.4.1.1.21 Bekisting 9.17 M2 2 x pakai 308,388.85 2,826,897.79
Pekerjaan Lain-Lain 1 Ls 90,200.00 90,200.00

Jumlah 7,140,734.61
Harga Satuan 7,140,734.61

Analisa 12 1 M3 Balok Bertulang 25x30


Harga Satuan Jumlah Harga
Analisa Uraian Pekerjaan Volume Satuan
Rp. Rp.

A.4.1.1.8. Beton K 250 1 M3 1,218,302.19 1,218,302.19


A.4.1.1.17.a Pembesian /Besi Polos 58.061 Kg 17,389.13 1,009,637.18
A.4.1.1.17.b Pembesian /Besi Ulir 112.06 Kg 19,237.13 2,155,748.70
A.4.1.1.21 Bekisting 11.33 M2 2 x pakai 308,388.85 3,495,073.63
Pekerjaan Lain-Lain 1 Ls 90,200.00 90,200.00

Jumlah 7,968,961.70
Harga Satuan 7,968,961.70

Analisa 13 1 M3 Balok Bertulang 30x50


Harga Satuan Jumlah Harga
Analisa Uraian Pekerjaan Volume Satuan
Rp. Rp.

A.4.1.1.8. Beton K 250 1 M3 1,218,302.19 1,218,302.19


A.4.1.1.17.a Pembesian /Besi Polos 46.724 Kg 17,389.13 812,488.95
A.4.1.1.17.b Pembesian /Besi Ulir 89.18 Kg 19,237.13 1,715,490.16
A.4.1.1.21 Bekisting 8.67 M2 2 x pakai 308,388.85 2,672,703.37
Pekerjaan Lain-Lain 1 Ls 90,200.00 90,200.00

Jumlah 6,509,184.67
Harga Satuan 6,509,184.67

Analisa 14 1 M3 Plat Lantai


Harga Satuan Jumlah Harga
Analisa Uraian Pekerjaan Volume Satuan
Rp. Rp.

A.4.1.1.8. Beton K 250 1 M3 1,218,302.19 1,218,302.19


A.4.1.1.17.a Pembesian /Besi Polos 93.193 Kg 17,389.13 1,620,542.72
A.4.1.1.17.b Pembesian /Besi Ulir - Kg 19,237.13 -
A.4.1.1.21 Bekisting 3.33 M2 1x pakai 817,637.70 2,725,459.00
Pekerjaan Lain-Lain 1 Ls 90,200.00 90,200.00

Jumlah 5,654,503.92
Harga Satuan 5,654,503.92
A.4.4.1. HARGA SATUAN PEKERJAAN PASANGAN DINDING

A.4.4.1.7. 1 M2 Pasangan Bata Merah tebal 1/2 Bata Campuran 1SP : 2PP
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.3000 82,000.00 24,600.00
Tukang L02 OH 0.1000 100,000.00 10,000.00
Kepala Tukang L03 OH 0.0200 129,000.00 2,580.00
Mandor L04 OH 0.0150 110,000.00 1,650.00
JUMLAH TENAGA KERJA 38,830.00
B. BAHAN
Batu Bata Bh 70.00 880.00 61,600.00
Semen Portland Kg 18.95 1,347.50 25,535.13
Pasir Pasang M3 0.038 185,000.00 7,030.00

JUMLAH HARGA BAHAN 94,165.13


C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 132,995.13


E. Overhead & Provit 10% XD 13,299.51
F. Harga Satuan Pekerjaan 146,294.64
A.4.4.1.9. 1 M2 Pasangan Bata Merah tebal 1/2 Bata Campuran 1SP : 4PP
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.3000 82,000.00 24,600.00
Tukang L02 OH 0.1000 100,000.00 10,000.00
Kepala Tukang L03 OH 0.0200 129,000.00 2,580.00
Mandor L04 OH 0.0150 110,000.00 1,650.00
JUMLAH TENAGA KERJA 38,830.00
B. BAHAN
Batu Bata Bh 70.00 880.00 61,600.00
Semen Portland Kg 11.50 1,347.50 15,496.25
Pasir Pasang M3 0.043 185,000.00 7,955.00

JUMLAH HARGA BAHAN 85,051.25


C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 123,881.25


E. Overhead & Provit 10% XD 12,388.13
F. Harga Satuan Pekerjaan 136,269.38

A.4.4.2. HARGA SATUAN PEKERJAAN PLESTERAN


A.4.4.2.2. 1 M2 Plesteran 1SP : 2PP, Tebal 15 mm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.3000 82,000.00 24,600.00
Tukang L02 OH 0.1500 100,000.00 15,000.00
Kepala Tukang L03 OH 0.0150 129,000.00 1,935.00
Mandor L04 OH 0.0150 110,000.00 1,650.00
JUMLAH TENAGA KERJA 43,185.00
B. BAHAN
Semen Portland Kg 10.2240 1,347.50 13,776.84
Pasir Pasang M3 0.0200 185,000.00 3,700.00

JUMLAH HARGA BAHAN 17,476.84


C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 60,661.84


E. Overhead & Provit 10% XD 6,066.18
F. Harga Satuan Pekerjaan 66,728.02
A.4.4.2.4. 1 M2 Plesteran 1SP : 4PP, Tebal 15 mm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.3000 82,000.00 24,600.00
Tukang L02 OH 0.1500 100,000.00 15,000.00
Kepala Tukang L03 OH 0.0150 129,000.00 1,935.00
Mandor L04 OH 0.0150 110,000.00 1,650.00
JUMLAH TENAGA KERJA 43,185.00
B. BAHAN
Semen Portland Kg 6.24 1,347.50 8,408.40
Pasir Pasang M3 0.024 185,000.00 4,440.00

JUMLAH HARGA BAHAN 12,848.40


C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 56,033.40


E. Overhead & Provit 10% XD 5,603.34
F. Harga Satuan Pekerjaan 61,636.74

A.4.4.2.27. 1 M2 Pemasangan Acian


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.2000 82,000.00 16,400.00
Tukang L02 OH 0.1000 100,000.00 10,000.00
Kepala Tukang L03 OH 0.0100 129,000.00 1,290.00
Mandor L04 OH 0.0100 110,000.00 1,100.00
JUMLAH TENAGA KERJA 28,790.00
B. BAHAN
Semen Portland Kg 3.25 1,347.50 4,379.38

JUMLAH HARGA BAHAN 4,379.38


C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 33,169.38


E. Overhead & Provit 10% XD 3,316.94
F. Harga Satuan Pekerjaan 36,486.31
A.4.4.3. HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING

A.4.4.3.35.a 1 M2 Pasangan Lantai Granit Ukuran 60 cm x 60 cm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.7000 82,000.00 57,400.00
Tukang L02 OH 0.3500 100,000.00 35,000.00
Kepala Tukang L03 OH 0.0350 129,000.00 4,515.00
Mandor L04 OH 0.0350 110,000.00 3,850.00
JUMLAH TENAGA KERJA 100,765.00
B. BAHAN
Granit Uk 60 x60 M2 1.0000 290,000.00 290,000.00
Semen Portland Kg 10.0000 1,347.50 13,475.00
Pasir Pasang M3 0.0450 185,000.00 8,325.00
Semen Warna Kg 1.5000 4,660.00 6,990.00
JUMLAH HARGA BAHAN 318,790.00
C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 419,555.00


E. Overhead & Provit 10% XD 41,955.50
F. Harga Satuan Pekerjaan 461,510.50

A.4.4.3.35.b 1 M2 Pasangan Lantai Keramik Anti Slip Ukuran 40 cm x 40 cm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.7000 82,000.00 57,400.00
Tukang L02 OH 0.3500 100,000.00 35,000.00
Kepala Tukang L03 OH 0.0350 129,000.00 4,515.00
Mandor L04 OH 0.0350 110,000.00 3,850.00
JUMLAH TENAGA KERJA 100,765.00
B. BAHAN
Keramik 40cm x 40 cm Bh 6.6800 13,666.67 91,293.33
Semen Portland Kg 10.4000 1,347.50 14,014.00
Pasir Pasang M3 0.0450 185,000.00 8,325.00
Semen Warna Kg 1.6200 4,660.00 7,549.20
JUMLAH HARGA BAHAN 121,181.53
C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 221,946.53


E. Overhead & Provit 10% XD 22,194.65
F. Harga Satuan Pekerjaan 244,141.19
A.4.4.3.35.c 1 M2 Pasangan Lantai Keramik Anti Slip Ukuran 20 cm x 20 cm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.7000 82,000.00 57,400.00
Tukang L02 OH 0.3500 100,000.00 35,000.00
Kepala Tukang L03 OH 0.0350 129,000.00 4,515.00
Mandor L04 OH 0.0350 110,000.00 3,850.00
JUMLAH TENAGA KERJA 100,765.00
B. BAHAN
Keramik 40cm x 40 cm Bh 26.7500 2,720.00 72,760.00
Semen Portland Kg 10.4000 1,347.50 14,014.00
Pasir Pasang M3 0.0450 185,000.00 8,325.00
Semen Warna Kg 1.6200 4,660.00 7,549.20
JUMLAH HARGA BAHAN 102,648.20
C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 203,413.20


E. Overhead & Provit 10% XD 20,341.32
F. Harga Satuan Pekerjaan 223,754.52

A.4.4.3.54.a 1 M2 Pasangan Dinding Keramik Ukuran 20 cm x 40 cm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.9000 82,000.00 73,800.00
Tukang L02 OH 0.4500 100,000.00 45,000.00
Kepala Tukang L03 OH 0.0450 129,000.00 5,805.00
Mandor L04 OH 0.0450 110,000.00 4,950.00
JUMLAH TENAGA KERJA 129,555.00
B. BAHAN
Keramik 20cm x 40 cm Bh 13.7500 6,800.00 93,500.00
Semen Portland Kg 9.3000 1,347.50 12,531.75
Pasir Pasang M3 0.0180 185,000.00 3,330.00
Semen Warna Kg 1.9400 4,660.00 9,040.40
JUMLAH HARGA BAHAN 118,402.15
C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 247,957.15


E. Overhead & Provit 10% XD 24,795.72
F. Harga Satuan Pekerjaan 272,752.87
A.4.4.3.54.b 1 M2 Pasangan Dinding Batu Alam Ukuran 20 cm x 40 cm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.9000 82,000.00 73,800.00
Tukang L02 OH 0.4500 100,000.00 45,000.00
Kepala Tukang L03 OH 0.0450 129,000.00 5,805.00
Mandor L04 OH 0.0450 110,000.00 4,950.00
JUMLAH TENAGA KERJA 129,555.00
B. BAHAN
Batu Alam 20 cm x 40 cm Bh 13.7500 31,666.67 435,416.67
Semen Portland Kg 9.3000 1,347.50 12,531.75
Pasir Pasang M3 0.0180 185,000.00 3,330.00
Semen Warna Kg 1.9400 4,660.00 9,040.40
JUMLAH HARGA BAHAN 460,318.82
C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 589,873.82


E. Overhead & Provit 10% XD 58,987.38
F. Harga Satuan Pekerjaan 648,861.20

A.4.4.3.53. 1 M2 Pasangan Dinding Keramik Ukuran 10 cm x 20 cm


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.9000 82,000.00 73,800.00
Tukang L02 OH 0.4500 100,000.00 45,000.00
Kepala Tukang L03 OH 0.0450 129,000.00 5,805.00
Mandor L04 OH 0.0450 110,000.00 4,950.00
JUMLAH TENAGA KERJA 129,555.00
B. BAHAN
Keramik 10cm x 20 cm Bh 53.0000 2,000.00 106,000.00
Semen Portland Kg 9.3000 1,347.50 12,531.75
Pasir Pasang M3 0.0180 185,000.00 3,330.00
Semen Warna Kg 2.7500 4,660.00 12,815.00
JUMLAH HARGA BAHAN 134,676.75
C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 264,231.75


E. Overhead & Provit 10% XD 26,423.18
F. Harga Satuan Pekerjaan 290,654.93
A.4.6.1.1 1 M3 Membuat dan Memasang Kusen pintu dan Kusen Jendela, Kayu Kelas I
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 7.0000 82,000.00 574,000.00
Tukang L02 OH 21.0000 100,000.00 2,100,000.00
Kepala Tukang L03 OH 2.1000 129,000.00 270,900.00
Mandor L04 OH 0.3500 110,000.00 38,500.00
JUMLAH TENAGA KERJA 2,983,400.00
B. BAHAN
Balok Kayu Kelas I M3 1.1000 6,500,000.00 7,150,000.00
Paku Kayu Kg 1.2500 23,000.00 28,750.00
Lem Kayu Kg 1.0000 35,000.00 35,000.00
JUMLAH HARGA BAHAN 7,213,750.00
C. PERALATAN
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 10,197,150.00


E. Overhead & Provit 10% XD 1,019,715.00
F. Harga Satuan Pekerjaan 11,216,865.00

A.4.6.1.10 1 M2 Memasang Jalusi Kusen, Kayu Kelas I


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.6700 82,000.00 54,940.00
Tukang L02 OH 2.0000 100,000.00 200,000.00
Kepala Tukang L03 OH 0.2000 129,000.00 25,800.00
Mandor L04 OH 0.3350 110,000.00 36,850.00
JUMLAH TENAGA KERJA 317,590.00
B. BAHAN
Balok Kayu Kelas I M3 0.0600 6,500,000.00 390,000.00
Paku Kayu Kg 0.1500 23,000.00 3,450.00
-
JUMLAH HARGA BAHAN 393,450.00
C. PERALATAN
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 711,040.00


E. Overhead & Provit 10% XD 71,104.00
F. Harga Satuan Pekerjaan 782,144.00
A.4.6.1.5 Pembuatan dan Pemasangan 1 M2 daun pintu panel, Kayu Kelas I
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 1.0000 82,000.00 82,000.00
Tukang L02 OH 3.0000 100,000.00 300,000.00
Kepala Tukang L03 OH 0.3000 129,000.00 38,700.00
Mandor L04 OH 0.0500 110,000.00 5,500.00
JUMLAH TENAGA KERJA 426,200.00
B. BAHAN
Papan kayu M3 0.0400 6,500,000.00 260,000.00
Lem kayu Kg 0.5000 35,000.00 17,500.00
-
JUMLAH HARGA BAHAN 277,500.00
C. PERALATAN
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 703,700.00


E. Overhead & Provit 10% XD 70,370.00
F. Harga Satuan Pekerjaan 774,070.00
A.4.6.1.6 Pembuatan dan Pemasangan 1 M2 pintu dan jendela kaca, Kayu Kelas I
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.8000 82,000.00 65,600.00
Tukang L02 OH 2.4000 100,000.00 240,000.00
Kepala Tukang L03 OH 0.2400 129,000.00 30,960.00
Mandor L04 OH 0.0400 110,000.00 4,400.00
JUMLAH TENAGA KERJA 340,960.00
B. BAHAN
Papan kayu M3 0.0240 25,000.00 600.00
Lem kayu Kg 0.3000 298,750.00 89,625.00
-
JUMLAH HARGA BAHAN 90,225.00
C. PERALATAN
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 431,185.00


E. Overhead & Provit 10% XD 43,118.50
F. Harga Satuan Pekerjaan 474,303.50
A.4.7.1. HARGA SATUAN PEKERJAAN CAT

A.4.7.1.10. 1 M2 Mengecat Bidang Tembok Baru


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.0200 82,000.00 1,640.00
Tukang L02 OH 0.0630 100,000.00 6,300.00
Kepala Tukang L03 OH 0.0063 129,000.00 812.70
Mandor L04 OH 0.0030 110,000.00 330.00
JUMLAH TENAGA KERJA 9,082.70
B. BAHAN
Plamir Kg 0.10 25,000.00 2,500.00
Cat Dasar Tembok Kg 0.10 28,000.00 2,800.00
Cat Penutup Tembok Kg 0.26 28,000.00 7,280.00

JUMLAH HARGA BAHAN 12,580.00


C. PERALATAN
Roller/Kuas bh 0.0100 27,000.00 270.00
-
JUMLAH HARGA ALAT 270.00

D. Jumlah (A+B+C) 21,932.70


E. Overhead & Provit 10% XD 2,193.27
F. Harga Satuan Pekerjaan 24,125.97

A.4.7.1.4 1 M2 Pengecatan Bidang Kayu Baru (1 x plamir, 1 x cat dasar,2 x cat penutup)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.0700 82,000.00 5,740.00
Tukang L02 OH 0.0090 100,000.00 900.00
Kepala Tukang L03 OH 0.0060 129,000.00 774.00
Mandor L04 OH 0.0030 110,000.00 330.00
JUMLAH TENAGA KERJA 7,744.00
B. BAHAN
Cat Menie Kg 0.2000 32,000.00 6,400.00
Plamir Kayu Kg 0.1500 21,000.00 3,150.00
Cat dasar kayu Kg 0.1700 67,000.00 11,390.00
Cat kayu penutup Kg 0.2600 67,000.00 17,420.00
Kuas Bh 0.0100 27,000.00 270.00
Pengencer Liter 0.0300 27,000.00 810.00
Ampelas' Lembar 0.2000 4,200.00 840.00
JUMLAH HARGA BAHAN 40,280.00
C. PERALATAN
Roller/Kuas bh 0.0100 20,000.00 200.00
-
JUMLAH HARGA ALAT 200.00

D. Jumlah (A+B+C) 48,224.00


E. Overhead & Provit 10% XD 4,822.40
F. Harga Satuan Pekerjaan 53,046.40
A.5.1.2. HARGA SATUAN PEKERJAAN ATAP

A.4.5.2.32. Pemasangan 1 M2 Atap Spandek


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.2000 82,000.00 16,400.00
Tukang L02 OH 0.1000 100,000.00 10,000.00
Kepala Tukang L03 OH 0.0100 129,000.00 1,290.00
Mandor L04 OH 0.0010 110,000.00 110.00
JUMLAH TENAGA KERJA 27,800.00
B. BAHAN
Atap genteng metal m2 1.02 95,000.00 96,900.00
Paku biasa Kg 0.20 23,000.00 4,600.00
-
-
JUMLAH HARGA BAHAN 101,500.00
C. PERALATAN
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 129,300.00


E. Overhead & Provit 10% XD 12,930.00
F. Harga Satuan Pekerjaan 142,230.00

A.4.5.2.36.a Pemasangan 1 M' Nok Seng Spandek


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.2500 82,000.00 20,500.00
Tukang L02 OH 0.1500 100,000.00 15,000.00
Kepala Tukang L03 OH 0.0150 129,000.00 1,935.00
Mandor L04 OH 0.0130 110,000.00 1,430.00
JUMLAH TENAGA KERJA 38,865.00
B. BAHAN
Nok Genteng metal M' 1.10 45,000.00 49,500.00
Paku Kg 0.05 23,000.00 1,150.00
-
-
JUMLAH HARGA BAHAN 50,650.00
C. PERALATAN
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 89,515.00


E. Overhead & Provit 10% XD 8,951.50
F. Harga Satuan Pekerjaan 98,466.50

A.4.6.1.14 1 M3 Memasang Konstruksi Kuda-Kuda, Kayu Kelas I


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 6.7000 82,000.00 549,400.00
Tukang L02 OH 20.1000 100,000.00 2,010,000.00
Kepala Tukang L03 OH 2.0100 129,000.00 259,290.00
Mandor L04 OH 0.3350 110,000.00 36,850.00
JUMLAH TENAGA KERJA 2,855,540.00
B. BAHAN
Balok Kayu Kelas I M3 1.2000 6,500,000.00 7,800,000.00
Besi Strip Tebal 5 mm Kg 15.0000 18,000.00 270,000.00
Paku Kayu Kg 5.6000 23,000.00 128,800.00
-
JUMLAH HARGA BAHAN 8,198,800.00
C. PERALATAN
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 11,054,340.00


E. Overhead & Provit 10% XD 1,105,434.00
F. Harga Satuan Pekerjaan 12,159,774.00
A.4.6.1.15 1 M3 Memasang Konstruksi Gordeng, Kayu Kelas II
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 2.4000 82,000.00 196,800.00
Tukang L02 OH 7.2000 100,000.00 720,000.00
Kepala Tukang L03 OH 0.7200 129,000.00 92,880.00
Mandor L04 OH 0.1200 110,000.00 13,200.00
JUMLAH TENAGA KERJA 1,022,880.00
B. BAHAN
Balok Kayu Kelas II M3 1.2000 5,800,000.00 6,960,000.00
Besi Strip Tebal 5 mm Kg 15.0000 18,000.00 270,000.00
Paku Kayu Kg 5.6000 23,000.00 128,800.00
-
JUMLAH HARGA BAHAN 7,358,800.00
C. PERALATAN
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 8,381,680.00


E. Overhead & Provit 10% XD 838,168.00
F. Harga Satuan Pekerjaan 9,219,848.00

A.4.6.1.21 1 M Memasang Listplank Uk. 3 x 20 Cm Kayu Kelas II


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.1000 82,000.00 8,200.00
Tukang L02 OH 0.1000 100,000.00 10,000.00
Kepala Tukang L03 OH 0.0100 129,000.00 1,290.00
Mandor L04 OH 0.0500 110,000.00 5,500.00
JUMLAH TENAGA KERJA 24,990.00
B. BAHAN
Kayu Kelas II M3 0.0088 4,300,000.00 37,840.00
Paku Kayu Kg 0.0600 23,000.00 1,380.00
-
JUMLAH HARGA BAHAN 39,220.00
C. PERALATAN
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 64,210.00


E. Overhead & Provit 10% XD 6,421.00
F. Harga Satuan Pekerjaan 70,631.00

A.4.6.1.20 1 M2 Memasang Rangka Langit-Langit (60 x 60) Cm, Kelas II


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.2000 82,000.00 16,400.00
Tukang L02 OH 0.3000 100,000.00 30,000.00
Kepala Tukang L03 OH 0.0300 129,000.00 3,870.00
Mandor L04 OH 0.0100 110,000.00 1,100.00
JUMLAH TENAGA KERJA 51,370.00
B. BAHAN
Kayu Kelas II M3 0.0163 5,800,000.00 94,540.00
Paku Kayu Kg 0.2500 23,000.00 5,750.00
-
JUMLAH HARGA BAHAN 100,290.00
C. PERALATAN
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 151,660.00


E. Overhead & Provit 10% XD 15,166.00
F. Harga Satuan Pekerjaan 166,826.00
A.4.5.1.5 1 M2 Memasang Langit-Langit Tripleks Ukuran (120 x 240) cm, tebal 6 mm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.1000 82,000.00 8,200.00
Tukang L02 OH 0.1000 100,000.00 10,000.00
Kepala Tukang L03 OH 0.0100 129,000.00 1,290.00
Mandor L04 OH 0.0050 110,000.00 550.00
JUMLAH TENAGA KERJA 20,040.00
B. BAHAN
Multiplek 6 mm lbr 0.3750 138,000.00 51,750.00
Paku Kayu Kg 0.0300 23,000.00 690.00
-
JUMLAH HARGA BAHAN 52,440.00
C. PERALATAN
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 72,480.00


E. Overhead & Provit 10% XD 7,248.00
F. Harga Satuan Pekerjaan 79,728.00

A.5.1.1. HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG


A.5.1.1.1. Pemasangan 1 Bh Kloset Duduk/Monoblock
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 3.3000 82,000.00 270,600.00
Tukang L02 OH 1.1000 100,000.00 110,000.00
Kepala Tukang L03 OH 0.0100 129,000.00 1,290.00
Mandor L04 OH 0.1600 110,000.00 17,600.00
JUMLAH TENAGA KERJA 399,490.00
B. BAHAN
Kloset duduk Bh 1.00 2,500,000.00 2,500,000.00
Perlengkapan % 6% 2,500,000.00 150,000.00

JUMLAH HARGA BAHAN 2,650,000.00


C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 3,049,490.00


E. Overhead & Provit 10% XD 304,949.00
F. Harga Satuan Pekerjaan 3,354,439.00

A.5.1.1.2. Pemasangan 1 Bh Kloset Jongkok


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 1.0000 82,000.00 82,000.00
Tukang L02 OH 1.5000 100,000.00 150,000.00
Kepala Tukang L03 OH 0.1500 129,000.00 19,350.00
Mandor L04 OH 0.1600 110,000.00 17,600.00
JUMLAH TENAGA KERJA 268,950.00
B. BAHAN
Kloset Jongkok Bh 1.00 435,000.00 435,000.00
Semen Portland Kg 6.00 1,347.50 8,085.00
Pasir Pasang M3 0.0100 185,000.00 1,850.00
JUMLAH HARGA BAHAN 444,935.00
C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 713,885.00


E. Overhead & Provit 10% XD 71,388.50
F. Harga Satuan Pekerjaan 785,273.50
A.5.1.1.4. Pemasangan 1 Bh Urinoir
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 1.0000 82,000.00 82,000.00
Tukang L02 OH 1.0000 100,000.00 100,000.00
Kepala Tukang L03 OH 0.1000 129,000.00 12,900.00
Mandor L04 OH 0.0500 110,000.00 5,500.00
JUMLAH TENAGA KERJA 200,400.00
B. BAHAN
Urinoir Bh 1.00 1,300,000.00 1,300,000.00
Semen Portland Kg 6.00 1,347.50 8,085.00
Pasir Pasang M3 0.01 185,000.00 1,850.00
Perlengkapan % 30% 1,300,000.00 390,000.00
JUMLAH HARGA BAHAN 1,699,935.00
C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 1,900,335.00


E. Overhead & Provit 10% XD 190,033.50
F. Harga Satuan Pekerjaan 2,090,368.50

A.5.1.1.5. Pemasangan 1 Bh Wastafel


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 1.2000 82,000.00 98,400.00
Tukang L02 OH 1.4500 100,000.00 145,000.00
Kepala Tukang L03 OH 0.1500 129,000.00 19,350.00
Mandor L04 OH 0.0600 110,000.00 6,600.00
JUMLAH TENAGA KERJA 269,350.00
B. BAHAN
Wastafel Bh 1.00 415,000.00 415,000.00
Semen Portland Kg 6.00 1,347.50 8,085.00
Pasir Pasang M3 0.01 185,000.00 1,850.00
Perlengkapan % 12% 415,000.00 49,800.00
JUMLAH HARGA BAHAN 474,735.00
C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 744,085.00


E. Overhead & Provit 10% XD 74,408.50
F. Harga Satuan Pekerjaan 818,493.50
A.5.1.1.14. Pemasangan 1 Bh Floor Drain
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.0100 82,000.00 820.00
Tukang L02 OH 0.1000 100,000.00 10,000.00
Kepala Tukang L03 OH 0.0100 129,000.00 1,290.00
Mandor L04 OH 0.0050 110,000.00 550.00
JUMLAH TENAGA KERJA 12,660.00
B. BAHAN
Floor Drain Bh 1.00 25,000.00 25,000.00

JUMLAH HARGA BAHAN 25,000.00


C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 37,660.00


E. Overhead & Provit 10% XD 3,766.00
F. Harga Satuan Pekerjaan 41,426.00

A.5.1.1.19. Pemasangan 1 Bh Kran diameter 1/2" atau 3/4"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.0100 82,000.00 820.00
Tukang L02 OH 0.4000 100,000.00 40,000.00
Kepala Tukang L03 OH 0.0400 129,000.00 5,160.00
Mandor L04 OH 0.0050 110,000.00 550.00
JUMLAH TENAGA KERJA 46,530.00
B. BAHAN
Kran air Bh 1.00 75,000.00 75,000.00
Sealtape Bh 0.0250 5,000.00 125.00
JUMLAH HARGA BAHAN 75,125.00
C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 121,655.00


E. Overhead & Provit 10% XD 12,165.50
F. Harga Satuan Pekerjaan 133,820.50
A.5.1.1.19.a Pemasangan 1 Bh Shower Spray/Jet Shower
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.0100 82,000.00 820.00
Tukang L02 OH 0.4000 100,000.00 40,000.00
Kepala Tukang L03 OH 0.0400 129,000.00 5,160.00
Mandor L04 OH 0.0050 110,000.00 550.00
JUMLAH TENAGA KERJA 46,530.00
B. BAHAN
Shower Spray Bh 1.00 250,000.00 250,000.00
Sealtape Bh 0.0250 5,000.00 125.00
JUMLAH HARGA BAHAN 250,125.00
C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 296,655.00


E. Overhead & Provit 10% XD 29,665.50
F. Harga Satuan Pekerjaan 326,320.50

A.5.1.1.25. Pemasangan 1 M' Pipa PVC tipe AW diameter 1/2"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.0360 82,000.00 2,952.00
Tukang L02 OH 0.0600 100,000.00 6,000.00
Kepala Tukang L03 OH 0.0060 129,000.00 774.00
Mandor L04 OH 0.0020 110,000.00 220.00
JUMLAH TENAGA KERJA 9,946.00
B. BAHAN
Pipa PVC 1/2" M' 1.20 6,000.00 7,200.00
Perlengkapan % 35% 6,000.00 2,100.00
JUMLAH HARGA BAHAN 9,300.00
C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 19,246.00


E. Overhead & Provit 10% XD 1,924.60
F. Harga Satuan Pekerjaan 21,170.60

A.5.1.1.26. Pemasangan 1 M' Pipa PVC tipe AW diameter 3/4"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.0360 82,000.00 2,952.00
Tukang L02 OH 0.0600 100,000.00 6,000.00
Kepala Tukang L03 OH 0.0060 129,000.00 774.00
Mandor L04 OH 0.0020 110,000.00 220.00
JUMLAH TENAGA KERJA 9,946.00
B. BAHAN
Pipa PVC 3/4" M' 1.20 6,833.33 8,200.00
Perlengkapan % 35% 6,833.33 2,391.67
JUMLAH HARGA BAHAN 10,591.67
C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 20,537.67


E. Overhead & Provit 10% XD 2,053.77
F. Harga Satuan Pekerjaan 22,591.43
A.5.1.1.27. Pemasangan 1 M' Pipa PVC tipe AW diameter 1"
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.0360 82,000.00 2,952.00
Tukang L02 OH 0.0600 100,000.00 6,000.00
Kepala Tukang L03 OH 0.0060 129,000.00 774.00
Mandor L04 OH 0.0020 110,000.00 220.00
JUMLAH TENAGA KERJA 9,946.00
B. BAHAN
Pipa PVC 1" M' 1.20 10,166.67 12,200.00
Perlengkapan % 35% 10,166.67 3,558.33
JUMLAH HARGA BAHAN 15,758.33
C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 25,704.33


E. Overhead & Provit 10% XD 2,570.43
F. Harga Satuan Pekerjaan 28,274.77

A.5.1.1.29. Pemasangan 1 M' Pipa PVC tipe AW diameter 2"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.0540 82,000.00 4,428.00
Tukang L02 OH 0.0900 100,000.00 9,000.00
Kepala Tukang L03 OH 0.0090 129,000.00 1,161.00
Mandor L04 OH 0.0030 110,000.00 330.00
JUMLAH TENAGA KERJA 14,919.00
B. BAHAN
Pipa PVC 2" M' 1.20 21,500.00 25,800.00
Perlengkapan % 35% 21,500.00 7,525.00
JUMLAH HARGA BAHAN 33,325.00
C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 48,244.00


E. Overhead & Provit 10% XD 4,824.40
F. Harga Satuan Pekerjaan 53,068.40

A.5.1.1.31. Pemasangan 1 M' Pipa PVC tipe AW diameter 3"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.0810 82,000.00 6,642.00
Tukang L02 OH 0.1350 100,000.00 13,500.00
Kepala Tukang L03 OH 0.0135 129,000.00 1,741.50
Mandor L04 OH 0.0040 110,000.00 440.00
JUMLAH TENAGA KERJA 22,323.50
B. BAHAN
Pipa PVC 3" M' 1.200 28,333.33 34,000.00
Perlengkapan % 35% 28,333.33 9,916.67
JUMLAH HARGA BAHAN 43,916.67
C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 66,240.17


E. Overhead & Provit 10% XD 6,624.02
F. Harga Satuan Pekerjaan 72,864.18
A.5.1.1.32. Pemasangan 1 M' Pipa PVC tipe AW diameter 4"
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.0810 82,000.00 6,642.00
Tukang L02 OH 0.1350 100,000.00 13,500.00
Kepala Tukang L03 OH 0.0135 129,000.00 1,741.50
Mandor L04 OH 0.0040 110,000.00 440.00
JUMLAH TENAGA KERJA 22,323.50
B. BAHAN
Pipa PVC 4" M' 1.200 45,833.33 55,000.00
Perlengkapan % 35% 45,833.33 16,041.67
JUMLAH HARGA BAHAN 71,041.67
C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 93,365.17


E. Overhead & Provit 10% XD 9,336.52
F. Harga Satuan Pekerjaan 102,701.68

A.4.2.1. HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM

Analisa 15 15 M2 Pagar Kawat Harmonika


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 4.0000 82,000.00 328,000.00
Tukang L02 OH 5.0000 100,000.00 500,000.00
Kepala Tukang L03 OH 1.0000 129,000.00 129,000.00
Mandor L04 OH 0.0520 110,000.00 5,720.00
JUMLAH TENAGA KERJA 962,720.00
B. BAHAN
Besi Siku L40.40.3 Btg 2.75 110,000.00 302,500.00
Kawat Harmonika Galvanis lubang 43x43 dia kawat 3.4mm M2 15.000 105,000.00 1,575,000.00
Pipa Galvanis 3" Btg 2.200 850,000.00 1,870,000.00
Kawat las Ls 1.000 20,000.00 20,000.00

JUMLAH HARGA BAHAN 3,767,500.00


C. PERALATAN
Peralatan Pengelasan Ls 1.0000 150,000.00 150,000.00

JUMLAH HARGA ALAT 150,000.00

D. Jumlah (A+B+C) 4,880,220.00


E. Overhead & Provit 10% XD 488,022.00
F. Harga Satuan Pekerjaan 5,368,242.00
1 M2 = 357,882.80
AHSP PU P.12.a Pemasangan Gebalan Rumput
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefesien
Rp. Rp.
A. TENAGA
Pekerja L01 OH 0.075 82,000.00 6,150.00
Tukang L02 OH - 100,000.00 -
Kepala Tukang L03 OH - 129,000.00 -
Mandor L04 OH 0.010 110,000.00 1,100.00
JUMLAH TENAGA KERJA 7,250.00
B. BAHAN
Lempengan /Gebalan Rumput M2 1.000 37,000.00 37,000.00
JUMLAH HARGA BAHAN 37,000.00
C. PERALATAN
-
-
JUMLAH HARGA ALAT -

D. Jumlah (A+B+C) 44,250.00


E. Overhead & Provit 10% XD 4,425.00
F. Harga Satuan Pekerjaan 48,675.00
REKAPITULASI
BILL OF QUANTITY (BOQ)

PEKERJAAN : PEMBANGUNAN STADION MINI (LAP.SEPAK BOLA DAN FASILITAS ATLETIK)


SUMBER DANA : APBD
LOKASI : KAB.ACEH BESAR

No Uraian Pekerjaan Jumlah Harga (Rp)

I PEKERJAAN PERSIAPAN DAN PEMATANGAN LAHAN 1,239,523,207.74

II PEKERJAAN TRIBUN PENONTON 4,735,931,293.88


A. PEKERJAAN TANAH 166,989,793.63
B. PEKERJAAN PONDASI 965,768,878.45
C. PEKERJAAN BETON 2,160,214,003.57
D. PEKERJAAN PASANGAN & PLESTERAN 162,427,025.15
E. PEKERJAAN ATAP 656,032,085.39
F. PEKERJAAN ALUMINIUM, BESI DAN PVC 159,080,000.00
G. PEKERJAAN PENUTUP LANTAI DAN DINDING 304,881,514.07
H. PEKERJAAN LANGIT-LANGIT 54,000,000.00
I. PEKERJAAN ELECTRICAL DAN MEKANIKAL 25,865,000.00
J. PEKERJAAN PENGECATAN 37,812,150.26
K. PEKERJAAN SANITASI 42,860,843.37

III PEKERJAAN PAGAR 1,545,416,667.98


A. PEKERJAAN TANAH 11,710,416.67
B. PEKERJAAN PONDASI DAN SLOOF 497,749,176.21
C. PEKERJAAN PAGAR 1,035,957,075.10

IV PEMBUATAN LAPANGAN BOLA KAKI 1,955,263,145.59


A. PEKERJAAN TANAH 184,714,315.50
B. PEKERJAAN DRAINASE 1,291,114,555.09
C. PEKERJAAN LAPANGAN 479,434,275.00

V PEMBUATAN LINTASAN ATLETIK 9,121,799,431.21


A. PEKERJAAN TANAH 538,666,953.63
B. PEKERJAAN BETON 1,099,223,308.39
C. PEKERJAAN LINTASAN ATLETIK 7,136,716,326.89
D. PEKERJAAN PENDUKUNG PERALATAN DAN PERLENGKAPAN ATLETIK 347,192,842.31

JUMLAH HARGA 18,597,933,746.41


PPN 10% 1,859,793,374.64
JUMLAH 20,457,727,121.05
PEMBULATAN 20,457,700,000.00
Terbilang: Dua puluh milyar empat ratus lima puluh tujuh juta tujuh ratus ribu rupiah
BIL OF QUANTITY (BOQ)
PEKERJAAN : PEMBANGUNAN STADION MINI (LAP.SEPAK BOLA DAN FASILITAS ATLETIK)
LOKASI : KAB.ACEH BESAR

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN VOLUME SAT ANALISA
(Rp) (Rp)
1 2 3 4 5 6 7

I PEKERJAAN PERSIAPAN DAN PEMATANGAN LAHAN


1 Pasang bowplank/pengukuran 1.000 Ls Taksir 12,000,000.00 12,000,000.00
2 Direksi Keet/barak kerja 1.000 Sewa Taksir 15,000,000.00 15,000,000.00
3 Mobilisasi dan Demobilisasi 1.000 Ls Taksir 30,000,000.00 30,000,000.00
4 Papan nama proyek 1.000 Ls Taksir 450,000.00 450,000.00
5 Keselamatan pekerja dan P3K 1.000 Ls Taksir 3,000,000.00 3,000,000.00
6 Pagar pengaman sementara Proyek/ Seng Gelombang BJLS 0.25 190.000 m A.Pagar Str 331,151.56 62,918,796.88
mm 8" Rangka Kayu Bagian Depan dan Samping Rencana Stadion
7 Air Kerja 1.000 Ls Taksir 5,000,000.00 5,000,000.00
8 Listrik Kerja 1.000 Ls Taksir 7,000,000.00 7,000,000.00
9 Penyiapan Lahan 0.000
- Tebang Tebas Pohon,semak dan lain-lain 19,368.000 m2 Taksir 3,000.00 58,104,000.00
- Cut and Fill lahan 25,283.325 m3 Taksir 19,000.00 480,383,175.00
- Timbunan Tanah Didatangkan 1,936.800 m3 A.2.3.1.11 119,350.00 231,157,080.00
- Dinding Penahan Tanah
Tapak 50 x 50 cm tiang pagar dan Tiang Sokong 3.33 m3 Analisa 3 5,447,082.52 18,156,941.72
Pedestal 25x25cm tiang pagar dan Tiang Sokong 10.42 m3 Analisa 8 8,327,862.07 86,748,563.23
Lantai Kerja K175 16.00 m3 A.4.1.1.5 1,065,405.02 17,046,480.28
Pasangan pondasi batu gunung 180.00 m3 A.3.2.1.2. 843,664.25 151,859,565.00
Sloof beton S1 (20 x 25) cm 10.00 m3 Analisa 5 5,569,860.56 55,698,605.64
10 Quality control 1.00 Ls Taksir 2,000,000.00 2,000,000.00
11 Pembersihan Terakhir 1.00 Ls Taksir 3,000,000.00 3,000,000.00
Jumlah 1,239,523,207.74
II PEKERJAAN TRIBUN PENONTON
A. PEKERJAAN TANAH
1 Galian tanah Pondasi 1,010.726 m3 A.2.3.1.1. 70,675.00 71,433,024.71
2 Urugan kembali galian pondasi 336.909 m3 A.2.3.1.9. 28,600.00 9,635,583.10
3 Urugan tanah timbun dalam bangunan 406.500 m3 A.2.3.1.11 119,350.00 48,515,775.00
4 Urugan pasir di bawah pondasi 35.367 m3 A.2.3.1.11. a 164,230.00 5,808,322.41
5 Lapisan pasir bawah lantai 101.625 m3 A.2.3.1.11. a 164,230.00 16,689,873.75
6 Pasangan Batu Bata 1 PC : 2 PS/Trasram tangga teras 53.288 m2 A.4.4.1.7. 146,294.64 7,795,675.50
7 Plesteran 1 PC : 2 PS 106.575 m2 A.4.4.2.2. 66,728.02 7,111,539.16
Jumlah 166,989,793.63
B. PEKERJAAN PONDASI
1 Tapak / Poor Pile 180 x 180 cm 104.98 m3 Analisa 1 4,881,256.53 512,414,785.44
2 Tapak / Poor Pile 250 x 150 (Pondasi Tangga) 1.13 m3 Analisa 2 4,947,123.90 5,565,514.39
3 Pedestal K1 (40/50) cm 48.88 m3 Analisa 6 6,752,750.68 330,074,453.40
4 Pedestal K2(40/40) cm 1.50 m3 Analisa 7 7,201,494.40 10,831,047.58
5 Pasangan Batu Kosong ( Anstamping ) Dibawah Pondasi Tapak 67.75 m3 A.3.2.1.9 431,174.70 29,212,301.51
6 Lantai Kerja Dibawah Pondasi batu Gunung 14.70 m3 A.4.1.1.5 1,065,405.02 15,661,453.76
7 Pasangan pondasi batu gunung 73.500 m3 A.3.2.1.2. 843,664.25 62,009,322.38
Jumlah 965,768,878.45
C. PEKERJAAN BETON
1 Cor Rabat Beton K.175 (Dibawah Lantai Keramik) 67.750 m3 A.4.1.1.5 1,065,405.02 72,181,189.93
2 Sloof beton S1 (30 x 40) cm 51.360 m3 Analisa 4 4,487,385.80 230,472,134.76
3 Kolom K1 (40/50) cm 69.152 m3 Analisa 6 6,752,750.68 466,966,215.26
4 Kolom K2(40/40) cm 2.912 m3 Analisa 7 7,201,494.40 20,970,751.69
5 Balok B1 ( 35 x 50 ) cm 31.360 m3 Analisa 10 5,908,518.18 185,291,130.13
6 Balok B2 (30 x 50 ) cm 29.400 m3 Analisa 13 6,509,184.67 191,370,029.34
7 Balok B3 ( 25 x 30 ) cm 2.400 m3 Analisa 12 7,968,961.70 19,125,508.09
8 Balok B4 (30x40)cm 5.280 m3 Analisa 11 7,140,734.61 37,703,078.77
8 Plat Lantai T. 30 cm 152.400 m3 Analisa 14 5,654,503.92 861,746,396.84
9 Tangga tempat duduk Tribun 7.280 m3 Analisa 14 5,654,503.92 41,164,788.51
10 Tangga Akses 2.600 m3 Analisa 14 5,654,503.92 14,701,710.18
10 Kolom Praktis 1.217 m3 Analisa 9 15,221,129.26 18,521,070.08
Jumlah 2,160,214,003.57
D. PEKERJAAN PASANGAN & PLESTERAN
1 Pasangan batu bata trasram 1 PC : 2 PS /dinding toilet 145.90 m2 A.4.4.1.7. 146,294.64 21,344,387.61
2 Pasangan batu bata 1 PC : 4 PS 468.560 m2 A.4.4.1.9. 136,269.38 63,850,378.35
3 Plasteran 1 PC : 2 PS 291.80 m2 A.4.4.2.2. 66,728.02 19,471,237.40
4 Plasteran 1 PC : 4 PS 937.12 m2 A.4.4.2.4. 61,636.74 57,761,021.79
Jumlah 162,427,025.15
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SAT ANALISA
(Rp) (Rp)
1 2 3 4 5 6 7
E. PEKERJAAN ATAP
1 Rangka dan sokongan kuda-kuda
- Rangka Atap Kuda -kuda Tribun besi Siku L 40.40.3 676.48 m2 Taksir 350,000.00 236,768,000.00
- Rangka Atap Teras Rangka Baja ringan 45.90 m2 Taksir 200,000.00 9,180,000.00
- Sopi-sopi/kerawang /tolak Angin diteras 9.20 m2 Taksir 750,000.00 6,900,000.00
2 Gording
- Besi Holow 40x60x2 mm fin cat 966.40 m Taksir 35,000.00 33,824,000.00
- Pemasangan dan Pengelasan + Pengait 966.40 m Taksir 15,000.00 14,496,000.00
3 Tiang kuda-kuda
Tiang pipa gip 4'' Tingg 600 cm terpasang 16.00 Buah Taksir 1,800,000.00 28,800,000.00
Tiang pipa gip 4'' Tingg 370 cm terpasang 16.00 Buah Taksir 1,200,000.00 19,200,000.00
Tiang pipa gip 4'' Tingg 310 cm terpasang 16.00 Buah Taksir 850,000.00 13,600,000.00
Plat tumpuan tiang + angkur 48.00 Buah Taksir 600,000.00 28,800,000.00
4 Ikatan angin besi polos dia 10 mm + pasang 570 cm per ikatan 60.00 btg Taksir 95,000.00 5,700,000.00
5 Penutup Atap
Seng Spandek 0.40 mm 722.38 m2 A.4.5.2.32. 142,230.00 102,744,107.40
Lisplang Alumunium Composite Panel 71.60 m2 Taksir 1,300,000.00 93,080,000.00
Talang Plat Alumunium 60.40 m Taksir 850,000.00 51,340,000.00
6 Pipa Pembuang 159.20 m2 A.5.1.1.31. 72,864.18 11,599,977.99
Jumlah 656,032,085.39
F. PEKERJAAN ALUMINIUM, BESI DAN PVC
1 Pintu Type P1 (Lengkap Acessories/Handle,Engsel,Kunci) 2.00 Unit Taksir 4,000,000.00 8,000,000.00
2 Pintu Type P2 (Lengkap Acessories/Engsel ,Pacok,Kunci) 2.00 Unit Taksir 1,500,000.00 3,000,000.00
3 Pintu Type P3 fiber 10.00 Unit Taksir 300,000.00 3,000,000.00
4 Jendela Type J1 (Lengkap Acessories) 4.00 Unit Taksir 2,000,000.00 8,000,000.00
5 Ventilasi Type V1 (Lengkap Acessories) 8.00 Unit Taksir 300,000.00 2,400,000.00
6 Reiling Tribun dan Tangga T 1m pakai Pipa gip 1,5'' fin cat 207.20 m Taksir 650,000.00 134,680,000.00
Jumlah 159,080,000.00
G. PEKERJAAN PENUTUP LANTAI DAN DINDING
Penutup lantai
1 Lantai Keramik Ukuran 40 x 40 cm termasuk Tribun 1,073.60 m² A.4.4.3.35.b 244,141.19 262,109,978.01
2 Lantai Keramik Ukuran 20 x 20 cm (anti slip) 40.00 m² A.4.4.3.35.c 223,754.52 8,950,180.80
Penutup Dinding
3 Dinding Keramik Ukuran 20 x 40 cm 124.00 m² A.4.4.3.54.a 272,752.87 33,821,355.26
Jumlah 304,881,514.07
H. PEKERJAAN LANGIT-LANGIT
1 Rangka Furring Holow 360.00 m2 Taksir 80,000.00 28,800,000.00
2 Pemasangan Plafond Gibsum 9 mm 360.00 m2 Taksir 70,000.00 25,200,000.00
Jumlah 54,000,000.00
I. PEKERJAAN ELECTRICAL DAN MEKANIKAL
1 MCB 2.00 Unit Taksir 750,000.00 1,500,000.00
2 Box Panel 1.00 Unit Taksir 500,000.00 500,000.00
3 Lampu Downlight 14.00 Buah Taksir 40,000.00 560,000.00
4 Lampu Hemat Energi 14.00 Buah Taksir 30,000.00 420,000.00
5 Saklar Tunggal 5.00 Buah Taksir 35,000.00 175,000.00
6 Saklar Ganda 2.00 Buah Taksir 35,000.00 70,000.00
7 Stop Kontak 4.00 Buah Taksir 35,000.00 140,000.00
8 Kabel NYM 2,5 1.00 Ls Taksir 7,500,000.00 7,500,000.00
9 Penangkal Petir 1.00 Ls Taksir 15,000,000.00 15,000,000.00
Jumlah 25,865,000.00
J. PEKERJAAN PENGECATAN
1 Cat tembok 1,207.28 m2 A.4.7.1.10. 24,125.97 29,126,801.06
2 Cat plafond 360.00 m2 A.4.7.1.10. 24,125.97 8,685,349.20
Jumlah 37,812,150.26
K. PEKERJAAN SANITASI
1 Memasang Closet Jongkok 8 buah A.5.1.1.2. 785,273.50 6,282,188.00
2 Urinoir 8 buah A.5.1.1.4. 2,090,368.50 16,722,948.00
3 Pipa Air kotor PVC 3"/acesoris/instalasi 54 m1 A.5.1.1.31. 72,864.18 3,934,665.90
4 Pipa Air bersih 3/4"/acesoris/instalasi 68 m1 A.5.1.1.26. 22,591.43 1,536,217.47
5 Fooldrain 10 buah A.5.1.1.14. 41,426.00 414,260.00
6 Kran 8 buah A.5.1.1.19. 133,820.50 1,070,564.00
7 bak fiber 6 buah Taksir 150,000.00 900,000.00
8 Pembuatan Septiktank 3 buah Taksir 3,000,000.00 9,000,000.00
9 Pembuatan Peresapan 3 buah Taksir 1,000,000.00 3,000,000.00
Jumlah 42,860,843.37
III PEKERJAAN PAGAR
A. PEKERJAAN TANAH
1 Galian tanah Pondasi 146.000 m3 A.2.3.1.1. 70,675.00 10,318,550.00
2 Urugan kembali galian pondasi 48.667 m3 A.2.3.1.9. 28,600.00 1,391,866.67
Jumlah 11,710,416.67
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SAT ANALISA
(Rp) (Rp)
1 2 3 4 5 6 7
B. PEKERJAAN PONDASI DAN SLOOF
1 Tapak 50 x 50 cm tiang pagar dan Tiang Sokong 15.21 m3 Analisa 3 5,447,082.52 82,841,046.61
2 Pedestal 25x25cm tiang pagar dan Tiang Sokong 11.41 m3 Analisa 8 8,327,862.07 94,989,676.73
3 Lantai Kerja K175 36.50 m3 A.4.1.1.5 1,065,405.02 38,887,283.14
4 Pasangan pondasi batu gunung 182.50 m3 A.3.2.1.2. 843,664.25 153,968,725.63
5 Sloof beton S1 (20 x 25) cm 22.81 m3 Analisa 5 5,569,860.56 127,062,444.11
Jumlah 497,749,176.21
C. PEKERJAAN PAGAR
1 Pintu Penonton Rangka GIP 3", Kawat Harmonika + Assesoris 8.000 Buah Taksir 3,500,000.00 28,000,000.00
lubang 43x43 dia kawat 3.4mm Ukuran 150 cm x220 cm x 2 daun
2 Pintu Mobilisasi Rangka GIP 3", Kawat Harmonika + Assesoris 1.000 Buah Taksir 4,400,000.00 4,400,000.00
lubang 43x43 dia kawat 3.4mm Ukuran 150 cm x300cm x 2 daun
3 Pagar Rangka GIP 3"dan Besi siku L 40.40.3,8 Kawat Harmonika + 2,273.250 m2 Analisa 15 357,882.80 813,557,075.10
Assesoris lubang 43x43 dia kawat 3.4mm
4 Tiang Sokong GIP 3" 152.000 btg Taksir 1,250,000.00 190,000,000.00
Jumlah 1,035,957,075.10
IV PEMBUATAN LAPANGAN BOLA KAKI
A. PEKERJAAN TANAH
1 Pemerataan dan Pemadatan Lapangan 7,150.000 m2 Taksir 21,000.00 150,150,000.00
2 Galian tanah Untuk Peresapan 489.060 m3 A.2.3.1.1. 70,675.00 34,564,315.50
Jumlah 184,714,315.50
B. PEKERJAAN DRAINASE
1 Drainase Dalam Area Lapangan
- Pipa utama PVC 6 '' ( sudah di lobang 10 mm) terpasang 626.40 m Taksir 368,333.33 230,724,000.00
- Pipa sirip PVC 4 '' ( sudah di lobang 10 mm) terpasang 1,152.00 m Taksir 59,583.33 68,640,000.00
- Kerikil Lapisan Setelah Ijuk 240.08 m3 A.2.3.1.11.b 358,270.00 86,014,894.68
- Ijuk Lapisan Pipa Utama dan Sirip 2,703.17 m2 Analisa ijuk 134,145.00 362,616,471.36
2 Drainase /Saluran( Luar Lapangan /Samping dalam Lintasan )
- Galian tanah 179.10 m3 A.2.3.1.1. 28,600.00 5,122,260.00
- Pasir Urug Dibawah Saluran 11.94 m3 A.2.3.1.11. a 164,230.00 1,960,906.20
- Cor Dinding Saluran K175 95.52 m3 A.4.1.1.5 1,065,405.02 101,767,487.27
- Mal /Cetakan Dinding Saluran 2X pakai 477.60 m2 A.4.1.1.25 320,818.85 153,223,082.76
- Penutup Saluran /Grill Besi 380.00 m Taksir 350,000.00 133,000,000.00
- Pipa Pembuang 4 " Kelua Area Stadion 159.20 m A.5.1.1.32. 102,701.68 16,350,107.99
3 Drainase /Saluran( Luar Lintasan /Samping Pagar Dalam )
- Galian tanah 90.00 m3 A.2.3.1.1. 28,600.00 2,574,000.00
- Pasir Urug Dibawah Saluran 6.00 m3 A.2.3.1.11. a 164,230.00 985,380.00
- Cor Dinding Saluran K175 48.00 m3 A.4.1.1.5 1,065,405.02 51,139,440.84
- Mal /Cetakan Dinding Saluran 2X pakai 240.00 m2 A.4.1.1.25 320,818.85 76,996,524.00
Jumlah 1,291,114,555.09
C. PEKERJAAN LAPANGAN
1 Urugan Pasir di atas Lapangan 5 cm 357.500 m3 A.2.3.1.11.c 272,470.00 97,408,025.00
2 Penanaman Lempeng Rumput 7,150.000 m2 AHSP PU P.12.a 48,675.00 348,026,250.00
3 Pengecatan Garis Garis Lapangan 1.000 Ls Taksir 10,000,000.00 10,000,000.00
4 Pengadaan Gawang Goal Standar 2.000 buah Taksir 12,000,000.00 24,000,000.00
Jumlah 479,434,275.00
V PEMBUATAN LINTASAN ATLETIK
A. PEKERJAAN TANAH
1 Penyiapan Badan Jalan/Lintasan 4,267.88 m2 12,000.00 51,214,560.00
2 Pondasi Lintasan/ lapisan Agregat Base B 1,707.15 m3 Analisa EI-422 285,535.44 487,452,393.63
Jumlah 538,666,953.63
B. PEKERJAAN BETON
1 Mal /Cetakan Pengecoran 2x Pakai 168.80 m2 A.4.1.1.25 320,818.85 54,154,221.88
2 Pemasangan Wiremesh M6 Pemasangan Besi WireMesh Ø 6mm 13,102.39 kg A.4.1.1.19 27,451.72 359,683,209.43
(Standar Pabrikasi)
3 Pemasangan Plastik Cor dibawah beton 4,267.88 m2 Taksir 10,000.00 42,678,800.00

4 Cor Beton K250 pakai ready Mix 426.79 m3 A.4.1.1.8. 1,218,302.19 519,956,757.08
5 Kerb beton Pembatas Lintasan 840.00 m Taksir 75,000.00 63,000,000.00
6 Finishing Level Lintasan Yang Sudah Dicor 4,267.88 m2 Taksir 14,000.00 59,750,320.00
Jumlah 1,099,223,308.39
C. PEKERJAAN LINTASAN ATLETIK
1 Pengadaan dan pemasangan lapisan sintetik t=13 mm (standar 4,267.88 m2 Analisa Khusus 1 1,633,397.00 6,971,142,388.36
IAAF)

2 Pengecatan Garis Lintasan Bahan Polyuerthane 2,107.00 m Analisa Khusus 2 78,582.79 165,573,938.53
Jumlah 7,136,716,326.89
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SAT ANALISA
(Rp) (Rp)
1 2 3 4 5 6 7
D. PEKERJAAN PENDUKUNG PERALATAN DAN PERLENGKAPAN ATLETIK
1 Pondasi papan lompat Jauh dan Lompat jangkit 12.00 set Analisa Khusus 3 7,062,915.15 84,754,981.81
2 Papan Tumpuan Lompat jauh 6.00 Bh Analisa Khusus 4 10,291,900.00 61,751,400.00
3 Bak Tumpuan Loncat Galah 2.00 Bh Analisa Khusus 5 4,661,897.00 9,323,794.00
4 Ring Besi Untuk Cakram dan Martil 1.00 Bh Analisa Khusus 7 20,605,982.50 20,605,982.50
5 Ring Besi Untuk Tolak Peluru 2.00 Bh Analisa Khusus 8 9,805,692.00 19,611,384.00
6 Almunium curb 400.00 M' Analisa Khusus 10 312,100.00 124,840,000.00
7 Pondasi dan gawang Pada Bak Air untuk Lari Halang rintang 1.00 Bh Analisa Khusus 9 26,305,300.00 26,305,300.00
Jumlah 347,192,842.31
DAFTAR HARGA UPAH DAN BAHAN KAB. ACEH BESAR
Pekerjaan : PEMBANGUNAN STADION MINI (LAP.SEPAK BOLA DAN FASILITAS ATLETIK)

Lokasi : KAB.ACEH BESAR

Harga
No. Uraian Upah/Bahan Satuan
Rp.

A. UPAH
1 L01 Pekerja OH 82,000.00
2 L02 Tukang OH 100,000.00
3 L03 Kepala Tukang OH 129,000.00
4 L04 Mandor OH 110,000.00
5 Instalator Lintasan Atletik OH 250,000.00
6 Pembatu Instalator OH 85,000.00
7 Tenaga Ahli Equiment Atletik OH 200,000.00

B. ALAT
1 Vibrator Jam 65,000.00
2 Pompa beton Jam 275,000.00

C. BAHAN
1 Kayu Balok 5/7 M3 4,300,000.00
2 Paku 2" - 3" Kg 23,000.00
3 Kayu Papan M3 4,300,000.00
4 Pasir Urug M3 103,000.00
5 Semen Portland 40kg Kg 53,900.00
6 Semen Portland 40kg Kg 1,347.50
7 Pasir Pasang M3 185,000.00
8 Pasir Pasang Kg 13,214.29
9 Pasir Beton M3 185,000.00
10 Pasir Beton Kg 132.14
11 Batu gunung/belah M3 196,000.00
10 Kerikil Biasa Untuk Peresapan M3 250,000.00
12 Kerikil /batu pecah (Maks 30 mm) M3 290,000.00
13 Kerikil/batu pecah (Maks 30 mm) Kg 214.81
14 Agregat Kelas B M3 290,000.00
15 Agregat Kelas C M3 261,000.00
15 Sirtu M3 120,000.00
16 Tanah Timbun M3 69,000.00
17 Air Liter 150.00
18 Besi Beton Polos Kg 13,400.00
19 Besi Beton Ulir Kg 15,000.00
20 Besi Siku L40.40.3,8 Kg 110,000.00
21 Kawat Beton Kg 22,000.00
22 Kawat Harmonika Galvanis lubang 43x43 dia kawat 3.4mm M2 105,000.00
23 WireMesh Ø 6mm (Standar Pabrikasi) M2 57,000.00
24 WireMesh Ø 6mm (Standar Pabrikasi) Kg 18,566.78
25 Paku 5-10 cm Kg 23,000.00
26 Minyak Bekisting Liter 19,000.00
27 Kayu Kelas I M3 6,500,000.00
28 Kayu Kelas II M3 5,800,000.00
Harga
No. Uraian Upah/Bahan Satuan
Rp.
29 Kayu Kelas III M3 4,300,000.00
Harga
No. Uraian Upah/Bahan Satuan
Rp.
30 Kayu Kelas IV M3 3,300,000.00
31 Besi Strip Tebal 5 mm Kg 18,000.00
32 Multiplek 9 mm Lembar 218,000.00
33 Multiplek 6 mm Lembar 138,000.00
34 Dolken Kayu (sembarang keras) 8-10 cm x 4 m Batang 50,000.00
35 Kloset duduk lengkap asesoris TOTO Bh 2,500,000.00
36 Kloset Jongkok Bh 435,000.00
37 Urinoir Keramik Bh 1,300,000.00
38 Wastafel lengkap asesoris Bh 415,000.00
39 Floor Drain Bh 25,000.00
40 Stop Kran Bh 75,000.00
41 Bak Mandi fibre glass, uk. Besar Bh 250,000.00
42 Sealtape Bh 5,000.00
43 Seng gelombang Lbr 72,000.00
44 Seng plat Lbr 65,000.00
45 Jet Shower Buah 250,000.00
46 Plamur Kg 25,000.00
47 Cat dasar Kg 28,000.00
48 Cat Penutup Kg 28,000.00
49 Cat Menie Kg 32,000.00
50 Plamir kayu Kg 21,000.00
51 Cat Dasar kayu Kg 67,000.00
52 Cat Penutup kayu Kg 67,000.00
53 Pengecer /tiner Liter 27,000.00
54 Amplase Lembar 4,200.00
55 Kuas bh 27,000.00
56 Seng Spandek 0.4 mm M2 95,000.00
57 Nok genteng metal M' 45,000.00
58 Pipa PVC 1/2" M' 6,000.00
59 Pipa PVC 3/4" M' 6,833.33
60 Pipa PVC 1" M' 10,166.67
61 Pipa PVC 2" M' 21,500.00
62 Pipa PVC 3" M' 28,333.33
63 Pipa PVC 4" M' 45,833.33
64 Pipa PVC 6" M' 283,333.33
64 Pipa Galvanis 3" Btng 850,000.00
65 Pipa Galvanis 4" Btng 1,200,000.00
66 Skrup fixer bh 3,000.00
67 Sealant Kg 180,000.00
68 Batu bata bh 880.00
69 Keramik Lantai 40cm x 40 cm bh 13,666.67
70 Granit Lantai 60 cm x 60 cm anti gores M2 290,000.00
71 Keramik Lantai 20 cm x20 cm bh 2,720.00
72 Keramik Dinding 20cm x 40 cm bh 6,800.00
73 Keramik 10cm x 20 cm bh 2,000.00
74 Batu Alam bh 31,666.67
75 Semen warna Kg 4,660.00
76 Shower Spray toto THX 20 NBW Bh 300,000.00
77 Lem pipa Liter 160,000.00
78 Lem kayu kg 35,000.00
79 Lempengan Rumput m2 37,000.00
80 Kunci Pintu Bh 154,000.00
81 Engsel Pintu Pasang 20,000.00
82 Engsel Jendela Pasang 20,000.00
Harga
No. Uraian Upah/Bahan Satuan
Rp.
83 Pacok Jendela Bh 18,200.00
84 Tarikan Jendela Bh 8,000.00
85 Hak Angin Steenless Bh 19,000.00
86 Lampu TL 2 X 36 Watt termasuk cover Bh 420,000.00
87 Lampu HE 45 Watt Bh 53,000.00
88 Lampu HE 14 Watt Bh 35,000.00
89 Kabel NYA 2.5 Rol 442,750.00
90 Saklar Tunggal stara Panasonic Bh 29,000.00
91 Saklar Ganda stara Panasonic Bh 43,000.00
92 Stop Kontak stara Panasonic Bh 27,000.00
93 Eksosfans Bh 800,000.00
94 Ijuk Kg 18,000.00
95 Kaca Polos 5 mm M2 155,000.00
Bahan Khusus Atletik
1 Cat Polyurethane Kg 144,375.00
2 PU Adhesive Kg 130,360.00
3 Shockpad 10 mm m2 275,100.00
4 Seal coat Kg 217,140.00
5 PU wear coat Kg 298,750.00
6 Granule / EPDM Kg 97,020.00
SEWA ALAT BERAT
1 Wheel Loader Jam 250,000.00
2 Dump Truck Jam 150,000.00
3 Motor Grader Jam 250,000.00
4 Tandem Roller Jam 220,000.00
5 Water Tanker Jam 150,000.00
pengurangan K1 1 0.33 2
2 0.99 2
3 1.65 2
4 2.31 2
5 2.97 2
6 3.63 2
7 4.29 2
8 4.95 2
9 5.61 2
10 6.27 2
11 6.93 2
0.66
1.98
3.3
4.62
5.94
7.26
8.58
9.9
11.22
12.54
13.86
79.86
Berat Besi (kg/m)
6 0.222
7 0.302
8 0.395
10 0.617
12 0.888
14 1.208
16 1.578
18 1.998
19 2.226
20 2.466
21 2.719
22 2.984

PERHITUNGAN BERAT TULANGAN / M3 BETON

Besi Bangunan Gudang

1 Tapak 180x180
D14
b= 1.800 m h= 0.300 m Lb = 1.85 m
Spasi = 0.125 m
D14 = 1.208 kg/m n= 15.81 btg
D14 = 1.208 kg/m n= 15.40 btg
Teromol 2Ø14 = 1.208 kg/m n= 2.00 btg
berat tul. Ulir b = 81.412 kg » 2.19 M2 Bekistg
berat tul. Ulir Lb = 70.041 kg » 1.10
berat tul. Ulir tromol = 2.238 kg »
153.691

2 Tapak 250x150
D14
b= 1.500 m h= 0.300 m Lb = 2.22 m
Spasi = 0.125 m
D14 = 1.208 kg/m n= 18.78 btg
D14 = 1.208 kg/m n= 13.00 btg
Teromol 2D14 = 1.208 kg/m n= 2.00 btg
berat tul. Ulir 14 b = 83.050 kg » 2.23 M2 Bekistg
berat tul. Ulir14 Lb = 70.762 kg » 1.12
berat tul. Ulir tromol = 2.685 kg »
156.498

3 Tapak 60x60
Ø12
b= 0.600 m h= 0.200 m Lb = 8.33 m
Spasi = 0.125 m
Ø12 = 0.888 kg/m n= 67.67 btg
Ø12 = 0.888 kg/m n= 5.80 btg
Teromol 2Ø12 = 0.888 kg/m n= 2.00 btg
berat tul. Ulir 14 b = 87.710 kg » 3.57 M2 Bekistg
berat tul. Ulir14 Lb = 85.101 kg » 1.79
berat tul. Ulir tromol = 7.398 kg »
180.210
4 Sloof 30/40
tulang 5D14,2D12, behel Ø10 - 10 cm
b= 0.300 m h= 0.400 m Lb = 8.33 m
Spasi = 0.10-0.15 m Panjang behel = 1.14 m
D14 = 1.208 kg/m n= 5.00 btg
D12 = 0.888 kg/m n= 2.00 btg
Ø10 = 0.617 kg/m n= 70.44 btg
berat tul. Ulir 14 = 52.868 kg » 6.67 M2 Bekistg
berat tul. Ulir 12 = 14.797 kg
total ulir 67.665
berat tul. Polos = 49.512 kg » 3.33
117.177
5 Sloof 20/25
5Ø12,Ø8 - 10 cm
b= 0.180 m h= 0.250 m Lb = 22.22 m
Spasi = 0.10-0.15 m Ls = 0.60 m
Ø12 = 0.888 kg/m n= 5.00 btg
Ø8 = 0.395 kg/m n= 186.19 btg
berat tul. Polos = 103.578 kg » 11.11 M2 Bekistg
berat tul. Polos = 44.079 kg » 5.56
147.658
6 Kolom 40/50
tulang 12D16,behel Ø10 - 10 cm
b= 0.400 m h= 0.500 m Lb = 5.00 m
Spasi = 0.100 m Ls = 1.54 m
D16 = 1.578 kg/m n= 12.00 btg
Ø10 = 0.617 kg/m n= 51.00 btg
berat tul. Ulir = 99.435 kg » 9.00 M2 Bekistg
berat tul. Polos = 48.423 kg » 4.50
total besi 147.858

7 Kolom 40/40
tulang 10D16,behel Ø10 - 10 cm
b= 0.400 m h= 0.400 m Lb = 6.25 m
Spasi = 0.100 m Ls = 1.34 m
D16 = 1.578 kg/m n= 10.00 btg
Ø10 = 0.617 kg/m n= 63.50 btg
berat tul. Ulir = 103.578 kg » 10.00 M2 Bekistg
berat tul. Polos = 52.461 kg » 5.00
total besi 156.039

8 Kolom 25/25
6Ø12, Ø8 - 10 cm
b= 0.250 m h= 0.250 m Lb = 16.00 m
Spasi = 0.10-0.15 m Ls = 0.74 m
Ø12 = 0.888 kg/m n= 6.00 btg
Ø8 = 0.395 kg/m n= 134.33 btg
berat tul. Polos = 89.492 kg » 16.00 M2 Bekistg
berat tul. Polos = 39.224 kg » 8.00
128.716
9 Kolom 13/13
4Ø12, Ø8 - 10 cm
b= 0.130 m h= 0.130 m Lb = 59.17 m
Spasi = 0.10-0.15 m Ls = 0.26 m
Ø12 = 0.888 kg/m n= 4.00 btg
Ø8 = 0.395 kg/m n= 494.10 btg
berat tul. Polos = 220.640 kg » 30.77 M2 Bekistg
berat tul. Polos = 50.690 kg » 15.38
271.330

10 Balok 35/50
tulang 7D14,2D12, behel Ø10 - 10 cm
b= 0.350 m h= 0.500 m Lb = 5.71 m
Spasi = 0.10-0.15 m Panjang behel = 1.44 m
D16 = 1.578 kg/m n= 7.00 btg
D12 = 0.888 kg/m n= 2.00 btg
Ø10 = 0.617 kg/m n= 48.62 btg
berat tul. Ulir 14 = 66.290 kg » 7.71 M2 Bekistg
berat tul. Ulir 12 = 10.146 kg
total ulir 76.437
berat tul. Polos = 43.165 kg » 3.86
119.601

11 Balok 30/40
tulang 7D14,2D12, behel Ø10 - 10 cm
b= 0.300 m h= 0.400 m Lb = 8.33 m
Spasi = 0.10-0.15 m Panjang behel = 1.14 m
D16 = 1.578 kg/m n= 7.00 btg
D12 = 0.888 kg/m n= 2.00 btg
Ø10 = 0.617 kg/m n= 70.44 btg
berat tul. Ulir 14 = 96.673 kg » 9.17 M2 Bekistg
berat tul. Ulir 12 = 14.797 kg
total ulir 111.470
berat tul. Polos = 49.512 kg » 4.58
160.982

12 Balok 25/30
tulang 4D14,2D12, behel Ø10 - 10 cm
b= 0.250 m h= 0.300 m Lb = 13.33 m
Spasi = 0.10-0.15 m Panjang behel = 0.84 m
D16 = 1.578 kg/m n= 4.00 btg
D12 = 0.888 kg/m n= 2.00 btg
Ø10 = 0.617 kg/m n= 112.11 btg
berat tul. Ulir 14 = 88.387 kg » 11.33 M2 Bekistg
berat tul. Ulir 12 = 23.675 kg
total ulir 112.062
berat tul. Polos = 58.061 kg » 5.67
170.123

13 Balok 30/50
tulang 7D14,2D12, behel Ø10 - 10 cm
b= 0.300 m h= 0.500 m Lb = 6.67 m
Spasi = 0.10-0.15 m Panjang behel = 1.34 m
D16 = 1.578 kg/m n= 7.00 btg
D12 = 0.888 kg/m n= 2.00 btg
Ø10 = 0.617 kg/m n= 56.56 btg
berat tul. Ulir 14 = 77.338 kg » 8.67 M2 Bekistg
berat tul. Ulir 12 = 11.838 kg
total ulir 89.176
berat tul. Polos = 46.724 kg » 4.33
135.900

14 Plat Beton/Lantai
Ø12
b= 1.000 m h= 0.300 m Lb = 3.33 m 3.33
Spasi = 0.150 m
Ø12 = 0.888 kg/m n= 23.22 btg
Ø12 = 0.888 kg/m n= 7.67 btg
berat tul. Polos = 46.182 kg » 3.33 M2 Bekistg
berat tul. Polos = 47.011 kg » 1.67
93.193
PEKERJAAN Analisa Khusus 1
KHUSUS M2 Pekerjaan Lapisan Sintetik prefebricated mat t=13mm 1,633,397
BAHAN
PU Adhesive Kg 1.1000 130,360 143,396
Shockpad 10 mm m2 1.0000 275,100 275,100
Seal coat Kg 0.5000 217,140 108,570
PU wear coat Kg 2.1000 298,750 627,375
Granule / EPDM Kg 2.8000 97,020 271,656
Alat bantu kerja Jam 0.2000 200,000 40,000
JUMLAH HARGA BAHAN 1,466,097
TENAGA
Tenaga ahli pasang Sintetik Oh 0.4000 250,000 100,000
Pekerja Oh 0.1500 82,000 12,300
Mandor Oh 0.5000 110,000 55,000
JUMLAH HARGA TENAGA 167,300
JUMLAH HARGA TENAGA DAN BAHAN 1,633,397
HARGA SATUAN PEKERJAAN 1,633,397
Analisa Khusus 2
M1 Pekerjaan Pengecatan Garis Lintasan 78,583
BAHAN
Cat Polyurethane Kg 0.0600 Rp 144,375 8,663

JUMLAH HARGA BAHAN 8,663


TENAGA
Pekerja Oh 0.4667 Rp 82,000 38,269
Tukang cat Oh 0.1167 Rp 100,000 11,670
Mandor Oh 0.1167 Rp 110,000 12,837
JUMLAH HARGA TENAGA 62,776
JUMLAH HARGA TENAGA DAN BAHAN 71,439
OVER HEAD DAN PROFIT 7,144
HARGA SATUAN PEKERJAAN 78,583
Analisa Khusus 3
1 Set Foundation tray for take off board & Blanking Board /Pondasi papan lompat Jauh dan Lompat jangkit 7,062,915
BAHAN
Foundation tray for take off board & Blanking Board set 1.0000 6,000,000 6,000,000
Lapisan sintetik m2 0.4148 1,633,397 677,533
Semen Portland zak 0.8150 53,900 43,929
Pasir beton m3 0.0594 185,000 10,984
Koral beton m3 0.0955 290,000 27,689
JUMLAH HARGA BAHAN 6,760,135
TENAGA
Tenaga ahli built in equipment Oh 0.8000 200,000 160,000
Pekerja Oh 1.6500 82,000 135,300
Mandor Oh 0.0680 110,000 7,480
JUMLAH HARGA TENAGA 302,780
JUMLAH HARGA TENAGA DAN BAHAN 7,062,915
HARGA SATUAN PEKERJAAN 7,062,915
Analisa Khusus 4
1 bh Take off board/Papan Tumpuan Lompat jauh 10,291,900
BAHAN
Take off board bh 1.0000 10,000,000 10,000,000
JUMLAH HARGA BAHAN 10,000,000
TENAGA
Tenaga ahli built in equipment Oh 0.7500 200,000 150,000
Pekerja Oh 1.6500 82,000 135,300
Mandor Oh 0.0600 110,000 6,600
JUMLAH HARGA TENAGA 291,900
JUMLAH HARGA TENAGA DAN BAHAN 10,291,900
HARGA SATUAN PEKERJAAN 10,291,900
Analisa Khusus 5
1 Set Pole vault galvanis steel/Bak Tumpuan Loncat Galah 4,661,897
BAHAN
Pole vault + cover galvanis steel set 1.0000 4,000,000 4,000,000
Lapisan sintetik m2 0.2500 1,160,000 290,000
Semen Portland zak 0.7300 53,900 39,347
Pasir beton m3 0.0500 185,000 9,250
Koral beton m3 0.0700 290,000 20,300
JUMLAH HARGA BAHAN 4,358,897
TENAGA
Tenaga ahli built in equipment Oh 0.8000 200,000 160,000
Pekerja Oh 1.6500 82,000 135,300
Mandor Oh 0.0700 110,000 7,700
JUMLAH HARGA TENAGA 303,000
JUMLAH HARGA TENAGA DAN BAHAN 4,661,897
HARGA SATUAN PEKERJAAN 4,661,897
Analisa Khusus 6
1 Set Soft curb for landing pit/Ring Besi Untuk Tolak Peluru 2,751,850
BAHAN
Soft curb for landing pit set 1.0000 1,500,000 1,500,000
Semen Portland zak 6.5000 53,900 350,350
Pasir beton m3 0.7000 185,000 129,500
JUMLAH HARGA BAHAN 1,979,850
TENAGA
Tenaga ahli built in equipment Oh 2.0000 200,000 400,000
Pekerja Oh 4.0000 82,000 328,000
Mandor Oh 0.4000 110,000 44,000
JUMLAH HARGA TENAGA 772,000
JUMLAH HARGA TENAGA DAN BAHAN 2,751,850
HARGA SATUAN PEKERJAAN 2,751,850

Analisa Khusus 7
1 bh Discus ring & hammer ring and adjust ring dia 3.15 m/Ring Besi Untuk Cakram dan Martil 20,605,983
BAHAN
Discus ring & hammer ring and adjust ring dia 3.15 m bh 1.0000 18,000,000 18,000,000
Semen Portland zak 16.3000 53,900 878,570
Pasir beton m3 1.0925 185,000 202,113
Koral beton m3 1.8700 290,000 542,300
JUMLAH HARGA BAHAN 19,622,983
TENAGA
Tenaga ahli built in equipment Oh 3.0000 200,000 600,000
Pekerja Oh 4.0000 82,000 328,000
Mandor Oh 0.5000 110,000 55,000
JUMLAH HARGA TENAGA 983,000
JUMLAH HARGA TENAGA DAN BAHAN 20,605,983
HARGA SATUAN PEKERJAAN 20,605,983

Analisa Khusus 8
1 bh Shot put ring with concrete floor dia 2.50 m/Ring Besi Untuk Tolak Peluru 9,805,692
BAHAN
Shot put ring dia 2.50 m bh 1.0000 8,000,000 8,000,000
Semen Portland zak 9.7800 53,900 527,142
Pasir beton m3 0.7900 185,000 146,150
Koral beton m3 0.8600 290,000 249,400
JUMLAH HARGA BAHAN 8,922,692
TENAGA
Tenaga ahli built in equipment Oh 2.5000 200,000 500,000
Pekerja Oh 4.0000 82,000 328,000
Mandor Oh 0.5000 110,000 55,000
JUMLAH HARGA TENAGA 883,000
JUMLAH HARGA TENAGA DAN BAHAN 9,805,692
HARGA SATUAN PEKERJAAN 9,805,692
Analisa Khusus 9
1 Set Water jump high hurdle /Pondasi dan gawang Pada Bak Air untuk Lari Halang rintang 26,305,300
BAHAN
Water jump high hurdle set 1.0000 25,000,000 25,000,000
JUMLAH HARGA BAHAN 25,000,000
TENAGA
Tenaga ahli built in equipment Oh 4.5000 200,000 900,000
Pekerja Oh 4.5000 82,000 369,000
Mandor Oh 0.3300 110,000 36,300
JUMLAH HARGA TENAGA 1,305,300
JUMLAH HARGA TENAGA DAN BAHAN 26,305,300
HARGA SATUAN PEKERJAAN 26,305,300

Analisa Khusus 10
1 M' Alumunium Curb 312,100
BAHAN
Alumunium Curb M' 1.0000 150,000 150,000
JUMLAH HARGA BAHAN 150,000
TENAGA
Tenaga ahli built in equipment Oh 0.4500 200,000 90,000
Pekerja Oh 0.4500 82,000 36,900
Mandor Oh 0.3200 110,000 35,200
JUMLAH HARGA TENAGA 162,100
JUMLAH HARGA TENAGA DAN BAHAN 312,100
HARGA SATUAN PEKERJAAN 312,100
1.6
352000
563,200.00