TABEL MONITORING UJI KUAT TEKAN SAMPEL BETON

TANGGAL UJI TEKAN SAMPEL


N.O. ITEM PENGECORAN TANGGAL PENGOCORAN
7 HARI 28 HARI PENANGGUNG JAWAB
1 PONDASI SUMURAN
05-Nov-21 12-Nov-21 03-Dec-21 LKMP sudah kuat uji beton

2 PILECAPE P1 (3-A Dan 4-A)


08-Nov-21 15-Nov-21 06-Dec-21 TIGA LASKAR Persiapan uji kuat tekan beton

3 PILECAPE P1 (1-A Dan 2-A)


10-Nov-21 17-Nov-21 08-Dec-21 STATIKA
4 PILECAP SUMURAN
10-Nov-21 17-Nov-21 08-Dec-21 STATIKA
5 PILECAPE P1 (1-D Dan 2-D)
20-Nov-21 27-Nov-21 18-Dec-21 STATIKA
6 PILECAPE P2 (1-BC Dan 2-BC)
25-Nov-21 02-Dec-21 23-Dec-21 STATIKA
7 SLOFF (1-2 / A-D)
27-Nov-21 04-Dec-21 25-Dec-21 STATIKA
8 PILECAPE P3 (7-A dan 7-D)
27-Nov-21 04-Dec-21 25-Dec-21 STATIKA
9 PILECAP P4 (7-BC)
27-Nov-21 04-Dec-21 25-Dec-21 STATIKA
10 KOLOM K1 Lantai 1 (1-A dan 2-A )
27-Nov-21 04-Dec-21 25-Dec-21 STATIKA
11 KOLOM K2 LANTAI 1 (2-EF)
27-Nov-21 04-Dec-21 25-Dec-21 STATIKA
11 P2 & P5
29-Nov-21 06-Dec-21 27-Dec-21 STATIKA
12 PILE CAP P5 5-6
01-Dec-21 08-Dec-21 29-Dec-21 STATIKA
13 PILE CAP P6,P1,P2
02-Dec-21 09-Dec-21 30-Dec-21 STATIKA
14 SLOOF S1, S2,&S3
02-Dec-21 09-Dec-21 30-Dec-21 STATIKA
15 SLOOF S1, S2, S3, & S4
07-Dec-21 14-Dec-21 04-Jan-22 STATIKA
16 KOLOM K1 Lantai 1 ( 4A )
07-Dec-21 14-Dec-21 04-Jan-22 STATIKA
Catatan : uji kuat tekan beton independen dalam PT.FAZA JAYA PRATAMA MAKASSAR