REKAPITULASI RENCANA ANGGARAN BIAYA

Kegiatan : PEMBANGUNAN MASJID AGUNG


Pekerjaan : PEMBANGUNAN MENARA MASJID
Lokasi : MANDANGIN SAMPANG

NO URAIAN JUMLAH HARGA (Rp.)

I
A PEKERJAAN PERSIAPAN DAN BONGKARAN 450,000.00

B PEKERJAAN PONDASI DAN BETON 150,425,634.52

C PEKERJAAN PASANGAN 36,638,144.00

E PEKERJAAN INSTALASI LISTRIK 6,209,000.00

F PEKERJAAN PENGECATAN 1,634,262.00

TOTAL 195,357,040.52
DIBULATKAN 195,357,000.00
RENCANA ANGGARAN BIAYA

Kegiatan : PEMBANGUNAN MASJID AGUNG


Pekerjaan : PEMBANGUNAN MENARA MASJID
Lokasi : MANDANGIN SAMPANG

SATUA
NO URAIAN VOLUME HARGA SATUAN (Rp) JUMLAH HARGA (Rp.)
N

A PEKERJAAN PERSIAPAN DAN BONGKARAN


1 Uitzet dan pasang bowplank 1.00 ls 350,000.00 350,000.00
2 Pembersihan Lokasi 1.00 ls 100,000.00 100,000.00
JUMLAH 450,000.00
B PEKERJAAN PONDASI DAN BETON
1 Galian pondasi 25.60 m3 99,800.00 2,554,880.00
2 Urugan tanah kembali 17.92 m3 21,090.00 377,932.80
3
3 Pasir bawah pondasi 34.80 m 138,000.00 4,802,400.00
4 Urug sirtu peninggian peil lantai 39.00 m3 105,500.00 4,114,500.00
5 Pondasi rollag 0.80 m3 847,840.00 678,272.00
6 Rabatan lantai tebal 5 cm 16.00 m2 33,186.00 530,976.00
7 Bor strouse 70.00 m' 22,000.00 1,540,000.00
8 Pondasi strouse pile 70.00 m3 168,275.89 11,779,312.43
9 Pondasi Pile cap 3.50 m3 2,969,397.02 10,392,889.55
3
10 Cor sloof 20/30 cm 1.89 m 2,969,397.02 5,612,160.36
11 Cor kolom K1 30x30 cm 9.38 m3 4,715,835.96 44,210,962.10
12 Cor Kolom K2 20x20 cm 0.14 m3 5,862,960.00 820,814.40
13 Cor balok B1 15/35 cm 3.39 m3 5,273,730.74 17,871,355.04
14 Cor Balok B2 20/35 cm 8.56 m3 5,273,730.74 45,139,179.83
JUMLAH 150,425,634.52
C PEKERJAAN PASANGAN
1 Pasang keramik lantai 216.40 m2 136,960.00 29,638,144.00
2 Ornament kaki kolom 14.00 unit 225,000.00 3,150,000.00
3 Ornament Kolom atas 14.00 unit 275,000.00 3,850,000.00
JUMLAH 36,638,144.00
F PEKERJAAN INSTALASI LISTRIK
1 Pasang instalasi listrik 29.00 ttk 165,000.00 4,785,000.00
2 Pasang lampu SL 18 watt down light 24.00 bh 50,000.00 1,200,000.00
2 Pasang saklar ganda 12.00 bh 14,000.00 168,000.00
3 Pasang stop kontak 4.00 bh 14,000.00 56,000.00
JUMLAH 6,209,000.00
G PEKERJAAN PENGECATAN
1 Cat tembok 84.00 m2 19,455.50 1,634,262.00
JUMLAH 1,634,262.00

TOTAL 195,357,040.52
DIBULATKAN 195,357,000.00