HARGA

NO MATERIAL DAN UPAH SATUAN SATUAN


(Rp.) Kode
1

I UPAH TENAGA / PEKERJA G.51.I

1 Mandor hari 134,400 SK SNI


T-03-1991-
2 Kepala tukang hari
144,400 03
3 Tukang besi hari 134,400
4 Tukang batu hari 134,400
5 Tukang kayu hari 134,400
6 Pekerja hari 114,400

II BAHAN
1 Semen zak 54,400
2 Pasir beton M3 194,400
3 Kerikil M3
244,400
4 Besi beton diameter 4 mm btg 16,400
5 Besi beton diameter 6 mm btg 31,400
6 Besi beton diameter 8 mm btg 47,400
7 Besi beton diameter 10 mm btg 69,400
8 bendrat kg 19,400

9 Kayu bekesting M3
3,404,400
10 Paku kg 20,400

No

1
2
Uraian Kuantitas Harga Satuan Jumlah
2 3 4 5

1 M2 - BETON
DEKING CAMP 1 PC : 3
PS TEBAL 1,5 CM

zak PC 0.162 54,400 8,812.80


m3 Pasir pasang 0.019 194,400 3,693.60
Tukang batu 0.02 134,400 2,688.00
Kepala tukang batu 0.002 144,400 288.80
Pekerja 0.04 114,400 4,576.00
Mandor 0.004 134,400 537.60
A 20,596.80
UNTUK KETEBALAN
LAIN
2 cm 1.333 21,400 28,526.20
2,5 cm -
3 cm 2 21,400 42,800.00
3,5 cm -
71,326.20

Untuk ketebalan > 1,5 cm, konversikan dengan ketebalan 1,5


cm

Harga Satuan Jumlah Harga


Uraian Pekerjaan Luas Analisa
(Rp) (Rp)

PEKERJAAN BETON

Beton deking T 2 cm 12 28,526.20 342,314.40


Beton deking T 3 cm 10 42,800.00 428,000.00
JUMLAH 770,314.40
HARGA SATUAN
NO MATERIAL DAN UPAH SATUAN
(Rp.)

I UPAH TENAGA / PEKERJA

1 Mandor hari 132,400


2 Kepala tukang hari 142,400
3 Tukang besi hari 132,400
4 Tukang batu hari 132,400
5 Tukang kayu hari 132,400
6 Pekerja hari 112,400

II BAHAN
1 Semen zak 52,400
2 Pasir beton M3 192,400

3 Kerikil M3
242,400
4 Besi beton diameter 4 mm btg 14,400
5 Besi beton diameter 6 mm btg 29,400
6 Besi beton diameter 8 mm btg 45,400
7 Besi beton diameter 10 mm btg 67,400
8 bendrat kg 17,400
9 Kayu bekesting M3 3,402,400
10 Paku kg 18,400
Kode Uraian Kuantitas Harga Satuan Jumlah
1 2 3 4 5

I.2 PEKERJAAN PEMBESIAN BETON

kg Besi Beton 125 29,400 3,675,000.00


kg Kawat Bendrat 2 17,400 34,800.00
Tukang besi 9 132,400 1,191,600.00
Kepala tukang besi 3 142,400 427,200.00
Pekerja 9 112,400 1,011,600.00
A 6,340,200.00
Tulangan 100 kg = 4/5 x A 5,072,160.00
Tulangan 139 kg = 1.39 x (4/5 x A) 7,050,302.40

SUP.Va BESI TULANGAN 139 kg

Pembesian 1 7,050,302.40 7,050,302.40


 Harga satuan per kg 50,721.60

Harga Satuan
No Uraian Pekerjaan Berat Analisa
(Rp)

I PEKERJAAN PEMBESIAN

1 Sengkang 10 x 20 cm 96.22 50,721.60


2 Sengkang 9 x 9 cm 43.16 50,721.60
JUMLAH
Jumlah Harga
(Rp)

4,880,432.35
2,189,144.26
7,069,576.61
HARGA SATUAN
NO MATERIAL DAN UPAH SATUAN
(Rp.)
Kode
I UPAH TENAGA / PEKERJA 1

1 Mandor hari
132,400 G.41.a
2 Kepala tukang hari 142,400
3 Tukang besi hari 132,400
4 Tukang batu hari 132,400
5 Tukang kayu hari 132,400
6 Pekerja hari 112,400

II BAHAN
1 Semen zak 52,400
2 Pasir beton M3 192,400
3 Kerikil M3 F.8
242,400
4 Besi beton diameter 4 mm btg 14,400
5 Besi beton diameter 6 mm btg 29,400
6 Besi beton diameter 8 mm btg 45,400
7 Besi beton diameter 10 mm btg 67,400
8 bendrat kg 17,400
9 Kayu bekesting M3 3,402,400
10 Paku kg 18,400

G.45

I.2
1

F.40

SUP.Va

No

1
Uraian Kuantitas Harga Satuan Jumlah
2 3 4 5

1 M3 BETON COR 1 PC : 2 PS : 3 KR

m3 Koral/split 0.8200 242,400.00 198,768.00


m3 Pasir beton 0.5400 192,400.00 103,896.00
zak PC 6.8000 52,400.00 356,320.00
Tukang batu 1.0000 132,400.00 132,400.00
Kepala tukang batu 0.1000 142,400.00 14,240.00
Pekerja 6.0000 112,400.00 674,400.00
Mandor 0.3000 132,400.00 39,720.00
1,519,744.00
1 M3 BETON PERLU 10 M2 KAYU
CETAKAN
m3 Papan Bekisting 0.4000 3,402,400.00 1,360,960.00
kg Paku 4.0000 18,400.00 73,600.00
Tukang kayu 5.0000 132,400.00 662,000.00
Kepala tukang kayu 0.5000 142,400.00 71,200.00
Pekerja 2.0000 112,400.00 224,800.00
Mandor 0.1000 132,400.00 13,240.00
Pekerja membongkar 2.0000 112,400.00 224,800.00
2,630,600.00

1 M3 BETON COR 1 PC : 3 PS : 5 KR

m3 Koral/split 1.0000 242,400.00 242,400.00


m3 Pasir beton 0.5000 192,400.00 96,200.00
zak PC 4.2400 52,400.00 222,176.00
Tukang batu 0.5000 132,400.00 66,200.00
Kepala tukang batu 0.0500 142,400.00 7,120.00
Pekerja 6.0000 112,400.00 674,400.00
Mandor 0.3000 132,400.00 39,720.00
1,348,216.00

PEKERJAAN PEMBESIAN BETON

kg Besi Beton 125.0000 45,400.00 5,675,000.00


kg Kawat Bendrat 2.0000 17,400.00 34,800.00
Tukang besi 9.0000 132,400.00 1,191,600.00
Kepala tukang besi 3.0000 142,400.00 427,200.00
Pekerja 9.0000 112,400.00 1,011,600.00
A 8,340,200.00
Tulangan 100 kg = 4/5 x A 6,672,160.00
Tulangan 256 kg = 2,56 x (4/5 x A) 17,080,729.60

2 3 4 5

BETON DENGAN TIANG PERANCAH

m3 Ky Kalimantan / Perancah 0.7000 3,402,400.00 2,381,680.00


kg Paku 7.0000 18,400.00 128,800.00
Tukang kayu 5.0000 132,400.00 662,000.00
Kepala tukang kayu 0.1050 142,400.00 14,952.00
Pekerja 3.5000 112,400.00 393,400.00
Mandor 0.1750 132,400.00 23,170.00
3,604,002.00
1 M3 BETON BERTULANG 1 :2 : 3
BESI TULANGAN 100 kg
Cor beton 1.0000 1,519,744.00 1,519,744.00
Pembesian 1.0000 6,672,160.00 6,672,160.00
Cetakan beton 0.2000 2,630,600.00 526,120.00
 Tiang perancah 0.5000 3,604,002.00 1,802,001.00
Harga 1 m3 beton camp !:2:3 10,520,025.00

Harga Satuan
Uraian Pekerjaan Volume Analisa
(Rp)

PEKERJAAN BETON

Pelat 256 SUP V a 105,200.25


JUMLAH
Jumlah Harga
(Rp)

26,931,264.00
26,931,264.00