The Power of Smart Metering


Capgemini and Trilliant Networks Team with Hydro One
to Meet Aggressive Energy Conservation Goals

Hydro One Networks Inc., wholly will need to refurbish, rebuild, replace
owned by the province of Ontario, or conserve 25,000 megawatts of
delivers electricity safely, reliably generating capacity—more than 80
and responsibly to homes and percent of Ontario's current electricity
businesses across the province. generating capacity—at an estimated
The company owns and operates cost of $70 billion CAD.
Ontario's 29,000 kilometer (km)
high-voltage transmission network Building new generation sources for
that delivers electricity to large electricity is only part of the answer.
industrial customers and municipal There are tremendous opportunities
utilities, as well as a 122,000 km low- to reduce the supply-demand gap
voltage distribution system that serves through a shift in when electricity
1.3 million end-use customers and is used by consumers.
smaller municipal utilities.

The Situation
To meet the growing needs of the
province, Ontario must build an
almost entirely new electricity system
by 2025. Estimates show that over
the next 20 years, Ontario

“ We are implementing the


most capable AMR solution
ever deployed to more than
one million meters.

Rick Stevens
Director, Development Strategies
Hydro One Networks Inc.
‘‘ This team leverages hundreds of
utility field personnel who actively
seek assignment to our
By introducing advanced metering
infrastructure (AMI) and time-of-use
(TOU) rates—charging higher rates
The Solution
Taking the utility leadership role
in advancing this technology and
during peak demand hours and lower supporting the provincial government’s
challenging and exciting Smart
rates at night and other off-peak times goal to have a smart meter in every
Meter Project. Having worked with
when there is a surplus of electric Ontario home and small business,
many teams during my time with generation capacity—consumers will Hydro One compiled a dedicated team,
Hydro One, as well as my role on be incented to shift their consumption beginning in 2005, by developing and
the AMRA Board and other patterns in terms of when and how testing the processes, tools and network
capacities, I have never seen such they use electricity. For Ontario, this infrastructure to support the mass
a diverse, professional and new infrastructure will provide a deployment of unified, AMI-enabled
capable team come together. foundation for achieving more than a smart meters in 2007 through 2010.

Rick Stevens
’’ five percent reduction in provincial
demand through load shifting, energy
The objectives were to:
■ Deploy smart meters across the

Director, Development Strategies savings and price awareness. residential and small commercial
Hydro One Networks Inc. customer base
Following the East Coast power outage ■ Build enabling communications
of 2003—and the concurrent wholesale
network and infrastructure
price volatility—Ontario acted quickly.
■ Develop and test regulated price plan
On July 16, 2004, the Energy Minister
directed that 800,000 smart meters be (RPP) and TOU billing, including
installed by December 31, 2007, Ontario Energy Board (OEB)
and for all of Ontario’s 4.5 million mandated billing data links with the
customers by December 31, 2010. Independent Electricity System
Operator (IESO) by 2008
Capgemini’s project management
scope includes: For Hydro One, the scope of this In addition to meeting the requirements
challenge was made even more laid out by the OEB, Hydro One also
■ Meter installation and field service difficult because of the complexity of set an objective for its AMI project to
logistics—from strategy and guidelines providing service to both the urban deploy a platform that could enable
to tracking and extremely rugged rural areas of a broad range of new initiatives that
■ Commission head-end systems Canada’s most populous province. will extend beyond basic automated
■ Prepare and integrate TOU billing and The province of Ontario has a meter reading for billing purposes.
customer care operations landmass twice the size of Texas The following initiatives are included
■ Offer strategic direction on retail and
and is larger than France and Spain in Hydro One’s strategy for meeting
wholesale activities combined. The utility’s most remote future energy needs, while also
customers are accessible only by rail, delivering better service to customers:
helicopter, snowmobile or boat. ■ TOU pricing
Trilliant Networks’ implementation of In some cases, utility employees ■ Theft detection and other
AMI provides Hydro One with: must travel an entire day to reach
automated billing functions
just a few customers.
■ High availability with automatic ■ Direct and/or premises-based

failover through self-healing RF load control


mesh network architecture ■ In-premise displays

■ Fast data acquisition and end-point


■ Real time outage information
control with maximum data reliability
■ Distribution automation
■ Commercial and residential electric
and gas commodities measurement ■ Distribution grid monitoring

■ Urban and rural coverage options


■ Choice of meters from multiple suppliers
■ Connectivity with premised and
mobile devices

2
AutovationSM 2007: The AMRA International Symposium September 30 - October 3

How Hydro One, Capgemini and


Smart Meters: How They Work
Trilliant Work Together The diagram below illustrates how the Smart Meter infrastructure and wireless network
Given the vast territory of Ontario, will be implemented.
Hydro One quickly realized that to be
successful this project needed to be
more than a basic AMR implementation.
At the core of the solution is the need
for a ubiquitous communications
network and integration approach. Both
elements are required to enable the
exploitation of data from many types of
devices—AMR, load control, in-home
displays, distribution monitoring and
control—by posting and making the
information available to numerous
enterprise applications, such as
customer information systems,
outage management, asset management,
geographic information systems and
work execution systems.

To accomplish this task, Hydro One


assembled a team of industry leaders
to develop the vision for an end-to-end using a robust proven governance
solution that embraced open standards model which smoothly manages the 12 The Results to Date
and the use of Internet Protocol (IP) at discrete work streams. Hydro One and its partners continue
all communications levels. This would to execute steadily to meet project
ensure that the network and integration Trilliant Networks, a leader in the objectives as planned. Initial meter
would be available and compatible delivery of wireless networking deployments started in late 2006,
with multiple field applications. solutions for utility applications, and in June 2007, the Hydro One
bases its technology on the global 2.4 teams surpassed a notable milestone
Capgemini, an integral part of the GHz IEEE 802.15.4 standards. The of 100,000 installed smart meters.
project team, is responsible for overall company is the first AMI supplier to This puts the project on target for
project management support, new deliver an integrated standards-based meeting its goal to have 240,000
systems integration, legacy systems platform for AMI and demand response meters installed by the end of 2007.
management, integrated process design (i.e., load control) incorporating As a result, Hydro One will be the
and operational services. Trilliant thermostats and other loads such as only utility in the province in this
Networks designs and supplies the pool pumps and water heaters. The position. This exceptional achievement
AMI including a standards-based 2.4 solution also supports in-home played a role in leading the Utility
gigahertz (GHz), RF mesh network, consumer displays that control loads Planning Network to select
head-end software and 1.3 million and posts meter readings and messages Hydro One as their 2007 award
smart meters to be installed by from utility providers. recipient for AMR deployment.
Hydro One operations.
The joint team set even more aggressive
With deep experience managing goals by aiming to deploy 240,000
large-scale projects like smart meter smart meters by 2007 and the full 1.3
deployments, Capgemini brings a clear, million by 2010.
well-developed, practical approach to
implementing this new generation AMI.
They work closely with Hydro One,

The Power of Smart Metering 3


Hydro One Project Mission About Trilliant Networks
Statement and Description Trilliant Networks, Inc. is an industry
To deploy a smart metering/ leader in open solutions for advanced
network solution that meets the metering infrastructure (AMI), demand
Ministry of Energy’s requirements at response, and grid management. The
the lowest possible cost and to be an company offers end-to-end solutions for
enabler for other business processes wireless cellular and RF mesh AMI
and transformations. networks. With technology based on
open standards and over 20 years
experience, Trilliant Networks has
enabled more than 100 utility
companies to provide their customers
better understanding of energy usage,
energy conservation tools, and
reductions in billing. Customers include
Duke Energy, E.ON U.S., Hydro One,
Northeast Utilities, Public Service Gas &
Electric and San Diego Gas & Electric.
Headquartered in Redwood City, Calif.,
with operations in Granby, Quebec and
Concord, Ontario, Trilliant Networks is
privately owned.

For more information about Trilliant


Networks, Inc., please visit our web site
at http://www.trilliantnetworks.com.

About Capgemini and the


Collaborative Business Experience

Capgemini, one of the focused methods and tools. Through


world’s foremost providers of commitment to mutual success and the
Consulting, Technology and Outsourcing achievement of tangible value, we help
services, has a unique way of working businesses implement growth strategies,
with its clients, called the Collaborative leverage technology and thrive through
Business Experience. the power of collaboration.
Backed by over three decades of industry Capgemini employs approximately 80,000
and service experience, the Collaborative people worldwide and reported 2006
Business Experience is designed to help global revenues of approximately
our clients achieve better, faster, more $9.625 billion or EUR 7.7 billion.
sustainable results through seamless
More information about our
access to our network of world-leading
services and research is available at
technology partners and collaboration-
www.us.capgemini.com/smartmeter

Approved by
EUC_HYDR1SS_092808_020

Rick Stevens Paul Karr Gary Wasslen


Hydro One Trilliant Capgemini