Harga Satuan Jumlah Harga No Uraian Kode Satuan Koefisien (Rp) (Rp) A TENAGA Pekerja L.01 OH 0.9000 80,000.00 72,000.00 Tukang Batu L.02 OH 0.4500 120,000.00 54,000.00 Kepala tukang L.03 OH 0.0450 120,000.00 5,400.00 Mandor L.04 OH 0.0450 120,000.00 5,400.00 JUMLAH TENAGA KERJA 136,800.00 B BAHAN Keramik artistik Bh 26.5000 3,300.00 87,450.00 Semen Portlan Kg 9.3000 1,890.00 17,577.00 Pasir Pasang M3 0.0180 87,120.00 1,568.16 Semen warna Kg 1.9400 4,875.00 9,457.50 JUMLAH HARGA BAHAN 116,052.66 C PERALATAN
JUMLAH HARGA ALAT
D Jumlah A+B+C 252,852.66
E Overhead & Profit 15% x D 37,927.90 F Harga Satuan Pekerjaan D+E 290,780.56