1 Pengecoran Struktur BUP 1 ‐ Pekerjaan Lantai Kerja 59 m3 Kelas E 11/10/2021 ‐ Bottom (Tahap 1) 246 m3 Kelas C 30/11/2021 ‐ Dinding (Tahap 1) 151 m3 Kelas C 30/11/2021 ‐ Bottom (Tahap 2) 246 m3 Kelas C 15/12/2021 ‐ Dinding (Tahap 2) 151 m3 Kelas C 16/12/2021 ‐ Slab Atas (Full) 505 m3 Kelas C 20/01/2022 2 Pengecoran Struktur BUP 3 ‐ Bottom (Tahap 1) 229 m3 Kelas C 06/11/2021 ‐ Dinding (Tahap 1) 156 m3 Kelas C 12/11/2021 ‐ Bottom (Tahap 2) 229 m3 Kelas C 16/11/2021 ‐ Dinding (Tahap 2) 156 m3 Kelas C 20/11/2021 ‐ Bottom (Tahap 3) 229 m3 Kelas C 24/11/2021 ‐ Dinding (Tahap3) 156 m3 Kelas C 28/11/2021 ‐ Slab Atas (Full) 670 m3 Kelas C 03/12/2021 3 LC Fronatage 50 m3 Kelas E 11/11/2021 LC Fronatage 120 m3 Kelas E 13/11/2021 4 Rigid 3+400 160 m3 Kelas P 15/11/2021 160 m3 Kelas P 16/11/2021 5 Rigid 3+000 150 m3 Kelas P 18/11/2021 150 m3 Kelas P 19/11/2021 6 LC Frontage 0+800 90 m3 Kelas E 17/11/2021 90 m3 Kelas E 18/11/2021 7 Pengecoran Struktur BUP 2 ‐ Pekerjaan Lantai Kerja tahap4 72 m3 Kelas E 12/11/2021 ‐ Bottom (Tahap 1) 543 m3 Kelas C 30/10/2021 ‐ Dinding (Tahap 1) A1 153 m3 Kelas C 09/11/2021 ‐ Dinding (Tahap 1) A2 153 m3 Kelas C 13/11/2021 ‐ Bottom (Tahap 2) 543 m3 Kelas C 03/11/2021 ‐ Dinding (Tahap 2) A1 153 m3 Kelas C 17/11/2021 ‐ Dinding (Tahap 2) A2 153 m3 Kelas C 18/11/2021 ‐ Bottom (Tahap 3) 543 m3 Kelas C 10/11/2021 ‐ Dinding (Tahap3) A1 153 m3 Kelas C 23/11/2021 ‐ Dinding (Tahap3) A2 153 m3 Kelas C 24/11/2021 ‐ Bottom (Tahap 4) 543 m3 Kelas C 24/11/2021 ‐ Dinding (Tahap4) A1 153 m3 Kelas C 30/11/2021 ‐ Dinding (Tahap4) A2 153 m3 Kelas C 01/12/2021 ‐ Slab Atas (Tahap 1) 543 m3 Kelas C 14/12/2021 ‐ Slab Atas (Tahap 2) 543 m3 Kelas C 15/12/2021 ‐ Slab Atas (Tahap 3) 543 m3 Kelas C 16/12/2021 ‐ Slab Atas (Tahap 4) 543 m3 Kelas C 17/12/2021