No Item 

Pekrjaan Volume Sat Kelas Beton Start


1 Pengecoran Struktur BUP 1
‐ Pekerjaan Lantai Kerja          59 m3 Kelas E 11/10/2021
‐ Bottom (Tahap 1)        246 m3 Kelas C 30/11/2021
‐ Dinding  (Tahap 1)        151 m3 Kelas C 30/11/2021
‐ Bottom (Tahap 2)        246 m3 Kelas C 15/12/2021
‐ Dinding  (Tahap 2)        151 m3 Kelas C 16/12/2021
‐ Slab Atas  (Full)        505 m3 Kelas C 20/01/2022
2 Pengecoran Struktur BUP 3
‐ Bottom (Tahap 1)        229 m3 Kelas C 06/11/2021
‐ Dinding  (Tahap 1)        156 m3 Kelas C 12/11/2021
‐ Bottom (Tahap 2)        229 m3 Kelas C 16/11/2021
‐ Dinding  (Tahap 2)        156 m3 Kelas C 20/11/2021
‐ Bottom (Tahap 3)        229 m3 Kelas C 24/11/2021
‐ Dinding  (Tahap3)        156 m3 Kelas C 28/11/2021
‐ Slab Atas (Full)        670 m3 Kelas C 03/12/2021
3 LC Fronatage          50 m3 Kelas E 11/11/2021
LC Fronatage        120 m3 Kelas E 13/11/2021
4 Rigid 3+400        160 m3 Kelas P 15/11/2021
       160 m3 Kelas P 16/11/2021
5 Rigid 3+000        150 m3 Kelas P 18/11/2021
       150 m3 Kelas P 19/11/2021
6 LC Frontage 0+800          90 m3 Kelas E 17/11/2021
         90 m3 Kelas E 18/11/2021
7 Pengecoran Struktur BUP 2
‐ Pekerjaan Lantai Kerja tahap4          72 m3 Kelas E 12/11/2021
‐ Bottom (Tahap 1)        543 m3 Kelas C 30/10/2021
‐ Dinding  (Tahap 1) A1        153 m3 Kelas C 09/11/2021
‐ Dinding  (Tahap 1) A2        153 m3 Kelas C 13/11/2021
‐ Bottom (Tahap 2)        543 m3 Kelas C 03/11/2021
‐ Dinding  (Tahap 2) A1        153 m3 Kelas C 17/11/2021
‐ Dinding  (Tahap 2) A2        153 m3 Kelas C 18/11/2021
‐ Bottom (Tahap 3)        543 m3 Kelas C 10/11/2021
‐ Dinding  (Tahap3) A1        153 m3 Kelas C 23/11/2021
‐ Dinding  (Tahap3) A2        153 m3 Kelas C 24/11/2021
‐ Bottom (Tahap 4)        543 m3 Kelas C 24/11/2021
‐ Dinding  (Tahap4) A1        153 m3 Kelas C 30/11/2021
‐ Dinding  (Tahap4) A2        153 m3 Kelas C 01/12/2021
‐ Slab Atas  (Tahap 1)        543 m3 Kelas C 14/12/2021
‐ Slab Atas  (Tahap 2)        543 m3 Kelas C 15/12/2021
‐ Slab Atas   (Tahap 3)        543 m3 Kelas C 16/12/2021
‐ Slab Atas   (Tahap 4)        543 m3 Kelas C 17/12/2021