Uas Estikon
Uas Estikon
HARGA SATUAN
NO URAIAN VOLUME SATUAN PPN 10%
(Rp)
1 2 3 4 5 6
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
#REF!
#REF!
#REF!
#REF!
1 2 3 4 5 6 7 = (3X5)+6
II PEKERJAAN KANTOR UPTD, IWAPA DAN PENGELOLAAN PASAR
A. PEKERJAAN PERSIAPAN (KONTRAK LUMPSUM)
1 Pek. Pengukuran Kembali (Staking Out) 1.00 ls 923,000.00 92,300.00 1,015,300.00
JUMLAH TOTAL A (Masuk Dalam Rekapitulasi) 1,015,300.00
1 2 3 4 5 6 7 = (3X5)+6
III PEKERJAAN KANTOR PELAYANAN PASAR
A. PEKERJAAN PERSIAPAN (KONTRAK LUMPSUM)
1 Pek. Pengukuran Kembali (Staking Out) 1.00 ls 923,000.00 92,300.00 1,015,300.00
JUMLAH TOTAL A (Masuk Dalam Rekapitulasi) 1,015,300.00
PEKERJAAN KIOS
PEKERJAAN KIOS LANTAI SATU (KONTRAK LUMPSUM)
A. PEKERJAAN KIOS TYPE 1 UK. 2 x 3M JUMLAH KIOS 192 UNIT (KONTRAK LUMPSUM)
A.1 PEKERJAAN BETON (KONTRAK LUMPSUM)
Ref. Produk, PCC: Sekualitas Tiga Roda
Ref. Produk, Baja Tulangan: sekualitas KS SNI Cilegon
1 Pek. Kolom Praktis KP 15 x 15 cm
• Baja Tulangan, BJTP U24, Ø10 2,813.28 kg 15,000.00 4,219,919.06 46,419,109.61
• Baja Tulangan, BJTP U24, Ø8 - 150 1,880.64 kg 15,000.00 2,820,959.54 31,030,554.93
• Begisting 299.97 m² 138,600.00 4,157,584.20 45,733,426.20
• • Cor Beton,Site Mix fc' 14,5 Mpa, K-175 22.50 m³ 1,151,300.00 2,590,165.96 28,491,825.53
2 Pek. Ring Balok RB 15 x 20 cm
• Baja Tulangan, BJTP U24, Ø12 3,683.71 kg 15,000.00 5,525,569.07 60,781,259.75
• Baja Tulangan, BJTP U24, Ø10 - 150 2,984.93 kg 15,000.00 4,477,398.25 49,251,380.70
• Begisting 381.60 m² 175,400.00 6,693,264.00 73,625,904.00
• • Cor Beton,Site Mix fc' 14,5 Mpa, K-175 28.62 m³ 1,151,300.00 3,295,020.60 36,245,226.60
3 Pek. Balok Lintel BL 20 x 30 cm
• Baja Tulangan, BJTP U24, Ø10 2,775.94 kg 15,000.00 4,163,905.81 45,802,963.86
• Baja Tulangan, BJTP U24, Ø8 - 150 1,776.96 kg 15,000.00 2,665,446.13 29,319,907.44
• Begisting 517.61 m² 175,400.00 9,078,923.25 99,868,155.75
• • Cor Beton,Site Mix fc' 14,5 Mpa, K-175 31.06 m³ 1,151,300.00 3,575,563.63 39,331,199.90
JUMLAH TOTAL PEKERJAAN A.1 (Masuk Dalam Rekapitulasi) 585,900,914.26
D. PEKERJAAN KIOS TYPE 4 UK. 2,5 x 2,5M JUMLAH KIOS 72 UNIT (KONTRAK LUMPSUM)
A.1 PEKERJAAN BETON (KONTRAK LUMPSUM)
Ref. Produk, PCC: Sekualitas Tiga Roda
Ref. Produk, Baja Tulangan: sekualitas KS SNI Cilegon
1 Pek. Kolom Praktis KP 15 x 15 cm
• Baja Tulangan, BJTP U24, Ø10 1,295.81 kg 15,000.00 1,943,720.29 21,380,923.21
• Baja Tulangan, BJTP U24, Ø8 - 150 866.23 kg 15,000.00 1,299,351.06 14,292,861.67
• Begisting 192.71 m² 138,600.00 2,670,932.88 29,380,261.68
• • Cor Beton,Site Mix fc' 14,5 Mpa, K-175 10.36 m³ 1,151,300.00 1,193,046.14 13,123,507.52
2 Pek. Ring Balok RB 15 x 20 cm
• Baja Tulangan, BJTP U24, Ø12 3,049.44 kg 15,000.00 4,574,163.38 50,315,797.19
• Baja Tulangan, BJTP U24, Ø10 - 150 2,471.06 kg 15,000.00 3,706,583.45 40,772,417.97
• Begisting 315.90 m² 263,900.00 8,336,474.33 91,701,217.61
• • Cor Beton,Site Mix fc' 14,5 Mpa, K-175 23.69 m³ 1,151,300.00 2,727,676.08 30,004,436.86
3 Pek. Balok Lintel BL 20 x 30 cm
• Baja Tulangan, BJTP U24, Ø10 1,595.21 kg 15,000.00 2,392,820.46 26,321,025.09
• Baja Tulangan, BJTP U24, Ø8 - 150 1,021.30 kg 15,000.00 1,531,951.51 16,851,466.62
• Begisting 297.45 m² 175,400.00 5,217,273.00 57,390,003.00
• • Cor Beton,Site Mix fc' 14,5 Mpa, K-175 17.85 m³ 1,151,300.00 2,054,725.11 22,601,976.21
JUMLAH TOTAL PEKERJAAN A.1 (Masuk Dalam Rekapitulasi) 414,135,894.62
1 2 3 4 5 6 7 = (3x5)+6
1 2 3 4 5 6 7 = (3X5)+6
PENAMPANG
NO ITEM PEKERJAAN & SKETSA BENTUK UNIT SATUAN JUMLAH
P L T
PEKERJAAN MASJID
4 #NAME?
5 #NAME?
1 #NAME?
- Cor Beton 1.00 1.00 0.30 20.00 m3 6.00
#NAME? 1,111.34 kg 1,111.34
5 #NAME?
#NAME? 116.50 0.20 0.30 m3 6.99
#NAME? 563.09 kg 563.09
#NAME? 206.85 kg 206.85
#NAME? 260.48 kg 260.48
#NAME? 116.50 0.30 2.00 m2 34.95
6 #NAME?
#NAME? 14.00 0.15 0.20 m3 0.42
#NAME? 49.71 kg 49.71
#NAME? 24.67 kg 24.67
#NAME? 14.00 0.20 2.00 m2 2.80
7 #NAME?
#NAME? 0.30 0.30 4.12 20.00 m3 7.42
#NAME? 530.29 530.29
- Besi tulangan 4D12 406.00 406.00
#NAME? 341.37 341.37
#NAME? 0.30 2.00 4.20 20.00 m2 25.20
50.40
8 #NAME?
#NAME? 0.15 0.15 4.20 10.00 m3 0.95
#NAME? 14.91 14.91
#NAME? 62.97 62.97
#NAME? 0.15 4.00 4.20 10.00 m2 12.60
9 #NAME?
#NAME? 0.15 0.40 3.00 9.00 m3 1.62
#NAME? 340.90 340.90
#NAME? 75.99 75.99
#NAME? 0.15 2.00 3.00 9.00 m2 4.05
14.85
10 #NAME?
#NAME? 0.15 0.15 3.00 6.00 m3 0.41
#NAME? 63.92 63.92
#NAME? 26.99 26.99
#NAME? 0.15 4.00 3.00 9.00 m2 8.10
11 #NAME?
#NAME? 0.20 0.40 116.50 1.00 m3 9.32
#NAME? 919.32 919.32
- Besi tulangan 4 D 14 563.09 563.09
#NAME? 327.89 327.89
#NAME? 0.40 2.00 30.00 1.00 m2 12.00
#NAME? 0.15 1.00 30.00 1.00 m2 2.25
12 #NAME? 14.25
#NAME? 0.15 0.30 94.00 1.00 m3 4.23
#NAME? 454.34 454.34
#NAME? 83.45 83.45
#NAME? 200.28 200.28
#NAME? 0.30 2.00 94.00 1.00 m2 28.20
35.25
13 #NAME?
#NAME? 0.15 0.30 108.50 1.00 m3 4.88
#NAME? 524.42 524.42
#NAME? 288.97 288.97
#NAME? 248.30 248.30
#NAME? 0.30 2.00 108.50 1.00 m2 32.55
#NAME? 0.15 1.00 108.50 1.00 m2 8.14
40.69
14 #NAME?
#NAME? 0.15 0.20 73.50 1.00 m3 2.21
#NAME? 261.00 261.00
#NAME? 200.28 200.28
#NAME? 0.20 2.00 73.50 1.00 m2 14.70
20.21
15 #NAME?
#NAME? 37.11 0.12 1.00 1.00 m3 4.45
#NAME? 37.11 11.34 4.00
16 #NAME?
#NAME? 23.80 0.12 1.00 1.00 m3 2.86
#NAME? 23.80 11.34 3.00
18 beton tangga Pj lb tg bh
3.45
TOTAL
1 #NAME?
M2 -
TOTAL 136.66
2 #NAME?
M1 -
M1 -
M1 -
TOTAL 273.31
10 #NAME?
### ###
### ###
3 #NAME?
38.10 1.00 m1 38.10
59.70 1.00 m1 59.70
TOTAL 97.80
### ###
1 #NAME? 3.00 4.50 m2 13.50
6.00 3.30 m2 19.80
3.00 2.00 m2 6.00
22.30 1.00 m2 22.30
3.00 3.00 m2 9.00
3.00 3.00 9.00
-
-
-
TOTAL 79.60
3 #NAME?
3.00 1.50 m2 4.50
2.30 1.50 m2 3.45
m2 -
m2 -
-
TOTAL 7.95
### ###
1 #NAME?
17.00 2.00 m1 34.00
Kaca 0.15 9.00 m2 1.35
1.26 1.00 m2 1.26
2.61
-
TOTAL
3 #NAME?
Pek. Pas. Tangga Vertikal
- Beton 0.15 1.00 23.20 1.00 m3 3.48
- Besi D13 - 150 549.23 1.00 kg 549.23
- Besi D10 - 200 65.76 1.00 kg 65.76
- Bekisting 1.30 5.25 2.00 2.00 m2 13.65
- Pengecatan Anti Karat 5.25 0.90 4.00 m2 18.90
- Accessories
- Huruf Acrilyc Spoon
- Kubah Mesjid Galvanium
TOTAL
RENCANA ANGGARAN BIAYA
PEMBANGUNAN PAVING BLOCK & RABAT PANJANG 627 METER
HARGA SATUAN
NO URAIAN
PEKERJAAN (RP)
I. PEKERJAAN PERSIAPAN
1 PAPAN NAMA PROYEK 500,000.00
2 SHOP DRAWING DAN ASBULL DRAWING 2,500,000.00
3 DUKUMENTASI DAN ADMINISTRASI PROYEK 1,500,000.00
4 PEMBUATAN 1 M2 PAGAR SEMENTARA DARI SENG GELOMBANG TINGGI 2 M (A. 2.2.1.2 HSP BIDANG KARYA CIPTA BALITBANG PU) 357,700.00
5 1 M1 PENGUKURAN dan PEMASANGAN BOUWPLANK (Analisa PU2016 A.2.2.1.4) 62,800.00
6 1 LS PENGUKURAN KEMBALI (STAKING OUT) 923,000.00
7 1 M2 (k3) MEMBERSIHKAN LAPANGAN dan PERATAAN (Analisa PU2016 A.2.2.1.9) 17,200.00
8 SEWA OFFICE CONTAINER 40 FEET 10,000,000.00
9 PEMBUATAN 1 M2 KANTOR SEMENTARA LANTAI PLESTERAN (A. 2.2.1.5 HSP BIDANG KARYA CIPTA BALITBANG PU) 1,120,200.00
10 PEMBERSIHKAN M² LAPANGAN dan PERATAAN dengan ALAT BERAT(Analisa PU2016 A.2.2.1.9) 104,100.00
11 1 M2 PEMBUATAN GUDANG SEMEN DAN PERALATANYA (Analisa PU2016 A.2.2.1.7) 1,019,300.00
12 1 M2 PEMBUATAN BEDENG PEKERJA (Analisa PU2016 A.2.2.1.8) 1,165,700.00
13 1 PEKERJAAN PEMBUATAN AIR KERJA 1,227,800.00
14 1 PEKERJAAN PEMASANGAN METERAN LISTRIK DAN INSTALASI ACCESORIESNYA 2,346,500.00
15 PEK. MOBILASI DAN DEMOBILISASI CRANE CRAWLER KAPASITAS 100 TON 120,000.00
16 PEK. MOBILISASI DAN DEMOBILISASI ALAT PANCANG HSPD 95,000.00
17 PEMBONGKARAN 1 M³ BETON BERTULANG (A. 2.21.13 HSP BIDANG KARYA CIPTA BALITBANG PU) 1,568,600.00
18 PEMBONGKARAN 1 M² DINDING TEMBOK BATA MERAH (SNI REV. 2005) 8,600.00
19 PEMBONGKARAN 1 M² LANTAI KERAMIK (SNI REV. 2005) 6,900.00
20 PEMBONGKARAN 1 M² RANGKA PLAFOND - (BONGKARAN TIDAK DIPAKAI LAGI) (SNI REV. 2005) 14,500.00
21 PEMBONGKARAN 1 M² PENUTUP PLAFOND - (BONGKARAN TIDAK DIPAKAI LAGI) (SNI REV. 2005) 3,700.00
V. PEKERJAAN ATAP
1 1 M2 PASAGAN BAJA RINGAN 218,800.00
2 1 M2 PASANGAN PENUTUP ATAP Atap Bitumen Bergelombang Monolayer 3 mm 253,800.00
2 1 M2 PENUTUP POLYCARBONAT 244,400.00
3 1 M1 PASANGAN NOK GENTENG ASPAL (Analisa PU A.4.5.2.34) 296,800.00
4 1 M1 PASANGAN LISTPLANK GRC LEBAR 30 CM (Analisa PU A.4.6.1.22) 101,500.00
5 1 M2 PASANGAN PENUTUP ATAP METAL ZICALUME, t= 0,45 mm, incl. Roofmesh, Glasswool dan Allumunium Foil 185,100.00
6 1 M1 PASANGAN NOK GENTENG METAL ZINCALUME, t= 0,45 mm, incl. Roofmesh, Glasswool dan Allumunium Foil 60,300.00
7 1 M2 PASANGAN ALLUMUNIUM FOIL DAN ROOFMESH 61,700.00
8 1 M2 PASANGAN PENUTUP ATAP KACA TEMPERED 15 MM 1,015,300.00
9 1 M1 TALANG METAL ZINCALUME 281,100.00
10 1 M2 PASANGAN PENUTUP ATAP ASBES CAP GAJAH 249,600.00
11 1 M2 PASANGAN PENUTUP TALANG AIR 153,800.00
12 1 m Memasang Talang Datar / Jurai alumunium Lebar 90 cm 121,500.00
X. PEKERJAAN PLAFOUND
1 1 M2 RANGKA PLAFOND, BESI HOLLOW 1X40X40X0,4 mm, MODUL 60X60, (Analisa PU A.4.2.1.21) 84,200.00
2 1 M2 PENUTUP PLAFOND, GRC, 120X240X6 mm, (Analisa PU A.4.5.1.7) 43,500.00
3 1 M2 PENUTUP PLAFOND, GGYPSUM BOARD, 120X240X6 mm, (Analisa PU A.4.5.1.7) 53,000.00
4 1 M1 LIST GYPSUM 39,900.00
5 1 M2 RANGKA PLAFOND, BESI HOLLOW 40 x 40mm dan 20 x 20mm, (Analisa PU A.4.2.1.21) 72,300.00
JUMLAH C.1 -
JUMLAH C.2 -
C. Pekerjaan Pompa
1 Pemasangan Pompa Transfer head 80 mAq 29,280,500.00
1 Pemasangan Pompa Submersible Pump Cap. 50 LPM 13,035,000.00
1 Pemasangan Pompa Submersible Pump Cap. 250 LPM 20,763,400.00
2 Pemasangan Pompa Submersible 6,443,600.00
3 Pemasangan Pompa Booster 11,719,300.00
4 Pemasangan Pompa Submersible Sumur dalam 6,443,600.00
5 Pembuatan Sumur Bor kedalaman 70 meter 20,450,700.00
6 Pekerjaan Deep Well Pump 35,200,000.00
7 Pemasangan Pompa Transfer cap 150 lpm, head : 20 m 18,150,000.00
L. Pekerjaan Telepon
1 Pemasangan Unit PABX (8 Co line,24 Line Ext. ) 29,822,100.00
2 Pemasangan Single Line Telepon 242,000.00
3 Pemasangan Terminal Box Telepon 465,800.00
O. Pekerjaan CCTV
1 Pemasangan Network Digital Video (NVR) 32 Channel, HDD 1 Terra Byte 47,698,700.00
2 Pemasangan Network Digital Video (NVR) 16 Channel, HDD 1 Terra Byte 33,000,000.00
3 Pemasangan Display LED 32" 4,933,500.00
4 Pemasangan IP Camera 3,814,800.00
5 Pemasangan Dome Fix Camera 1,254,000.00
6 Keyboard Controller 21,516,000.00
7 Instalasi Kamera CCTV
P. Pekerjaan MATV
1 Pemasangan MATV 8,451,800.00
2 Pemasangan Spliter 16 Way 206,200.00
U. Pekerjaan Panel
1 PANEL - LVMDP 34,235,200.00
2 PANEL - SDP 28,522,000.00
3 PANEL PP/LP - LD 6,110,800.00
4 PANEL PP/LP - L1 6,732,700.00
5 PANEL PP/LP - L2 7,106,900.00
6 PANEL PP/LP - L3 7,777,300.00
7 PANEL PP/LP - L4 6,997,400.00
8 PANEL PP/LP - 0L 7,962,100.00
9 PANEL SDP-PUMP 12,046,500.00
10 PANEL SDP-PUMP HYDRANT 9,397,900.00
11 PANEL SDP-PUMP TRANSFER 9,252,100.00
12 PANEL SDP-PUMP BOOSTER 6,022,800.00
13 PANEL SDP-AC-LIFT 5,115,300.00
14 PANEL SDP-AC.D 5,219,100.00
15 PANEL SDP-AC.1 6,596,200.00
16 PANEL SDP-AC.2 6,720,900.00
17 PANEL SDP-AC.3 6,845,600.00
HARGA SATUAN
NO URAIAN VOLUME SATUAN PPN 10%
(Rp)
1 2 3 4 5 6
I. KIOS RELOKASI TYPE A1
A. PEKERJAAN PERSIAPAN (KONTRAK LUMPSUM)
1 Shop Drawing dan Asbuilt Drawing ls 2,500,000.00 -
2 Dokumentasi dan Administrasi Proyek ls 1,500,000.00 -
3 Pek. Pengukuran Kembali dan Bouwplank m¹ 62,800.00 -
4 Membersihkan Lapangan dan Perataan ls 17,200.00 -
JUMLAH TOTAL PEKERJAAN A (Masuk Dalam Rekapitulasi)
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Err:509
Err:509
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Err:509
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Err:509
Err:509
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Err:509
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Err:509
Err:509
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Err:509
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Err:509
Err:509
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Err:509
ANALISA HARGA SATUAN MEKANIKAL
C. PEKERJAAN POMPA
1 Pemasangan Pompa Transfer Head 80 mAg
Pompa Head 80 meter 'Groundfos' kap. 60ltr/m unit 2.00 7,800,000.00 15,600,000.00
Pipa Header 100mm ls 1.00 500,000.00 500,000.00
Gate Valve dia.32 mm unit 6.00 271,920.00 1,631,520.00
Gate Valve dia.50 mm unit 2.00 496,980.00 993,960.00
Check Valve dia.50 mm unit 1.00 1,771,000.00 1,771,000.00
BAHAN Floating Valve dia. 50 mm unit 1.00 315,000.00 315,000.00
Flexible Joint Dia. 50mm unit 1.00 327,800.00 327,800.00
Strainer dia. 50 mm unit 1.00 825,000.00 825,000.00
Preasure Swithc unit 1.00 935,000.00 935,000.00
Preasure Gauge unit 1.00 247,500.00 247,500.00
Alat Bantu ls 1.00 1,157,300.00 1,157,300.00
Tenaga Ongkos Pemasangan ls 1.00 2,314,600.00 2,314,600.00
JUMLAH 24,304,080.00 2,314,600.00 26,618,680.00
KEUNTUNGAN MAX 10% 2,430,408.00 231,460.00 2,661,868.00
10%
JUMLAH + KEUNTUNGAN 26,734,488.00 2,546,060.00 29,280,548.00
DIBULATKAN 26,734,400.00 2,546,000.00 29,280,500.00
7 Pemasangan TB - FA 10 Pairs
TB - FA 10 Pairs bh 1.00 660,000.00 660,000.00
BAHAN
Peralatan Bantu ls 1.00 33,000.00 33,000.00
Tenaga Ongkos Pemasangan ls 1.00 69,300.00 69,300.00
JUMLAH 693,000.00 69,300.00 762,300.00
KEUNTUNGAN MAX 10% 69,300.00 6,930.00 76,230.00
10%
JUMLAH + KEUNTUNGAN 762,300.00 76,230.00 838,530.00
DIBULATKAN 762,300.00 76,200.00 838,500.00
ANALISA HARGA SATUAN ELEKTRIKAL
1. PEKERJAAN PANEL
A. PANEL - LVMDP
Box Panel ( 180 x 80 x 60 ) cm unit 1.00 5,680,180.00 5,680,180.00
MCCB, 300 - 400 A / 50 KA unit 1.00 4,560,600.00 4,560,600.00
MCCB, 175 - 250 A / 36 KA unit 1.00 2,279,200.00 2,279,200.00
MCCB, 80 - 100 A / 36 KA unit 2.00 1,088,450.00 2,176,900.00
MCB, 6 - 10 - 16 - 20 A / 3 PH/10-15KA unit 4.00 334,075.00 1,336,300.00
KW Meter 3P/4W3CT WTC96 AN unit 1.00 2,637,500.00 2,637,500.00
Double Volt Meter unit 1.00 694,400.00 694,400.00
Cos Phi Meter FECT96 unit 3.00 2,206,600.00 6,619,800.00
BAHAN
Ampere Meter 800/5A EC 96 unit 1.00 276,500.00 276,500.00
Fuse Control 2 A unit 2.00 15,000.00 30,000.00
Pilot Lamp 220 VAC c/w : LED unit 1.00 25,000.00 25,000.00
Emergency Stop unit 1.00 314,100.00 314,100.00
Busbar & accessories ls 3.00 450,000.00 1,350,000.00
Alat Bantu ls 1.00 1,047,500.00 1,047,500.00
Wirring & Instalasi pemasangan ls 1.00 2,095,000.00 2,095,000.00
BAHAN
Parabola Satelite Antena unit 1.00 1,750,000.00 1,750,000.00
UHF Antena 17 Element unit 1.00 450,000.00 450,000.00
BAHAN
Terminal Box & P.supply unit 1.00 2,750,000.00 2,750,000.00
Booster unit 1.00 150,000.00 150,000.00
Aksessories & Setting Alat ls 1.00 635,000.00 635,000.00
TENAGA ONGKOS PEMASANGAN ls 1.00 698,500.00 698,500.00
Jumlah 6,985,000.00 698,500.00 7,683,500.00
Keuntungan Max 10% 10% 698,500.00 69,850.00 768,350.00
Jumlah + Keuntungan 7,683,500.00 768,350.00 8,451,850.00
Dibulatkan 7,683,500.00 768,300.00 8,451,800.00
2 Pemasangan Spliter 16 Way
Spliter 16 Way unit 1.00 155,000.00 155,000.00
BAHAN
Aksessories & Setting Alat ls 1.00 15,500.00 15,500.00
TENAGA ONGKOS PEMASANGAN ls 1.00 17,000.00 17,000.00
Jumlah 170,500.00 17,000.00 187,500.00
Keuntungan Max 10% 10% 17,050.00 1,700.00 18,750.00
Jumlah + Keuntungan 187,550.00 18,700.00 206,250.00
Dibulatkan 187,500.00 18,700.00 206,200.00
11. PEKERJAAN PENANGKAL PETIR
1 Pemasangan Penangkal Petir Air Termination Electrostatic Type EF R= 50 m
Current Air Terminal Electro Statis Radius 50 M unit 1.00 6,500,000.00 6,500,000.00
Pipa GIP medium class ø 50 mm (H = 2 m¹) m' 3.00 265,000.00 795,000.00
Down conductor XLPE 70 mm² m' 20.00 480,000.00 9,600,000.00
HV Lighting Crrier ( Coaxial Cable ) m' 25.00 155,000.00 3,875,000.00
BAHAN
Control box (50 x 50 x 50) cm bh 1.00 275,000.00 275,000.00
Connectiong Sleave bh 4.00 275,000.00 1,100,000.00
Clamp, bolt & material support bh 1.00 1,550,000.00 1,550,000.00
Wirring & Setting ls 1.00 1,184,700.00 1,184,700.00
TENAGA ONGKOS PEMASANGAN ls 1.00 621,900.00 621,900.00
Jumlah 24,879,700.00 621,900.00 25,501,600.00
Keuntungan Max 10% 10% 2,487,970.00 62,190.00 2,550,160.00
Jumlah + Keuntungan 27,367,670.00 684,090.00 28,051,760.00
Dibulatkan 27,367,600.00 684,000.00 28,051,600.00
2 Arde Grounding Box
Grounding split 1" m' 10.00 75,000.00 750,000.00
BAHAN bak kontrol 60x60x60 cm unit 1.00 939,100.00 939,100.00
Wirring & Setting ls 1.00 337,800.00 337,800.00
TENAGA ONGKOS PEMASANGAN ls 1.00 168,900.00 168,900.00
Jumlah 2,026,900.00 168,900.00 2,195,800.00
Keuntungan Max 10% 10% 202,690.00 16,890.00 219,580.00
Jumlah + Keuntungan 2,229,590.00 185,790.00 2,415,380.00
Dibulatkan 2,229,500.00 185,700.00 2,415,200.00
3 Instalasi Kabel BC 50 mm² /m1
MCCB, 140 - 200 A / 36 KA m' 1.00 2,213,200.00 2,213,200.00
BAHAN
Pipa Hi-PVC, klem, dan alat bantu ls 1.00 442,600.00 442,600.00
TENAGA ONGKOS PEMASANGAN ls 1.00 221,300.00 221,300.00
Jumlah 2,655,800.00 221,300.00 2,877,100.00
Keuntungan Max 10% 10% 265,580.00 22,130.00 287,710.00
Jumlah + Keuntungan 2,921,380.00 243,430.00 3,164,810.00
Dibulatkan 2,921,300.00 243,400.00 3,164,700.00
12. PEKERJAAN PENINGDRA KEBAKARAN
1 Pemasangan Unit MCFA (MASTER CONTROL FIRE ALARM) Full Adressable
MCFA (Master Control Fire Alarm) full Adressable unit 1.00 26,000,000.00 26,000,000.00
BAHAN
Wirring & Setting ls 1.00 5,200,000.00 5,200,000.00
TENAGA ONGKOS PEMASANGAN ls 1.00 2,600,000.00 2,600,000.00
Jumlah 31,200,000.00 2,600,000.00 33,800,000.00
Keuntungan Max 10% 10% 3,120,000.00 260,000.00 3,380,000.00
Jumlah + Keuntungan 34,320,000.00 2,860,000.00 37,180,000.00
Dibulatkan 34,320,000.00 2,860,000.00 37,180,000.00
2 Pemasangan Terminal Box Fire Alarm
Terminal Box Fire Alarm ( TBF) unit 1.00 500,000.00 500,000.00
BAHAN
Wirring & Setting ls 1.00 100,000.00 100,000.00
TENAGA ONGKOS PEMASANGAN ls 1.00 50,000.00 50,000.00
Jumlah 600,000.00 50,000.00 650,000.00
Keuntungan Max 10% 10% 60,000.00 5,000.00 65,000.00
Jumlah + Keuntungan 660,000.00 55,000.00 715,000.00
Dibulatkan 660,000.00 55,000.00 715,000.00
3 Pemasangan Unit Rate Of Rise Heat Detector
Rate Of Rise Heat Detector unit 1.00 162,500.00 162,500.00
BAHAN
TENAGA ONGKOS PEMASANGAN ls 1.00 16,200.00 16,200.00
Jumlah 162,500.00 16,200.00 178,700.00
Keuntungan Max 10% 10% 16,250.00 1,620.00 17,870.00
Jumlah + Keuntungan 178,750.00 17,820.00 196,570.00
Dibulatkan 178,700.00 17,800.00 196,500.00
4 Pemasangan Unit Smoke Detector
Smoke Detector 4 Wire unit 1.00 165,000.00 165,000.00
BAHAN
TENAGA ONGKOS PEMASANGAN ls 1.00 16,500.00 16,500.00
Jumlah 165,000.00 16,500.00 181,500.00
Keuntungan Max 10% 10% 16,500.00 1,650.00 18,150.00
Jumlah + Keuntungan 181,500.00 18,150.00 199,650.00
Dibulatkan 181,500.00 18,100.00 199,600.00
5 Pemasangan Unit Fix Themperature Detector
Fix Themperature Detector unit 1.00 195,500.00 195,500.00
BAHAN
TENAGA ONGKOS PEMASANGAN ls 1.00 19,500.00 19,500.00
Jumlah 195,500.00 19,500.00 215,000.00
Keuntungan Max 10% 10% 19,550.00 1,950.00 21,500.00
Jumlah + Keuntungan 215,050.00 21,450.00 236,500.00
Dibulatkan 215,000.00 21,400.00 236,400.00
6 Pemasangan Unit Photoelectric Smoke Detector
Photo elektric smoke detector c/w base unit 1.00 537,500.00 537,500.00
BAHAN
TENAGA ONGKOS PEMASANGAN ls 1.00 53,700.00 53,700.00
Jumlah 537,500.00 53,700.00 591,200.00
Keuntungan Max 10% 10% 53,750.00 5,370.00 59,120.00
Jumlah + Keuntungan 591,250.00 59,070.00 650,320.00
Dibulatkan 591,200.00 59,000.00 650,200.00
7 Pemasangan Manual Call Point Unit
Manual break glass unit 1.00 237,500.00 237,500.00
BAHAN
TENAGA ONGKOS PEMASANGAN ls 1.00 23,700.00 23,700.00
Jumlah 237,500.00 23,700.00 261,200.00
Keuntungan Max 10% 10% 23,750.00 2,370.00 26,120.00
Jumlah + Keuntungan 261,250.00 26,070.00 287,320.00
Dibulatkan 261,200.00 26,000.00 287,200.00
8 Pemasangan Alarm Bell Unit
Alarm bell unit 1.00 425,000.00 425,000.00
BAHAN
TENAGA ONGKOS PEMASANGAN ls 1.00 42,500.00 42,500.00
Jumlah 425,000.00 42,500.00 467,500.00
Keuntungan Max 10% 10% 42,500.00 4,250.00 46,750.00
Jumlah + Keuntungan 467,500.00 46,750.00 514,250.00
Dibulatkan 467,500.00 46,700.00 514,200.00
9 Pemasangan lampu indikator Unit
Indicator lamp Red Flasher unit 1.00 162,500.00 162,500.00
BAHAN
TENAGA ONGKOS PEMASANGAN ls 1.00 16,200.00 16,200.00
Jumlah 162,500.00 16,200.00 178,700.00
Keuntungan Max 10% 10% 16,250.00 1,620.00 17,870.00
Jumlah + Keuntungan 178,750.00 17,820.00 196,570.00
Dibulatkan 178,700.00 17,800.00 196,500.00
10 Pemasangan Indoor Hydrant Box
Indoor Hydrant Box unit 1.00 4,120,000.00 4,120,000.00
BAHAN
Support dan Accesories ls 1.00 824,000.00 824,000.00
TENAGA ONGKOS PEMASANGAN ls 1.00 412,000.00 412,000.00
Jumlah 4,944,000.00 412,000.00 5,356,000.00
Keuntungan Max 10% 10% 494,400.00 41,200.00 535,600.00
Jumlah + Keuntungan 5,438,400.00 453,200.00 5,891,600.00
Dibulatkan 5,438,400.00 453,200.00 5,891,600.00
11 Pemasangan Outdoor Hydrant Box
Outdoor Hydrant Box unit 1.00 4,739,000.00 4,739,000.00
BAHAN
Support dan Accesories ls 1.00 947,800.00 947,800.00
TENAGA ONGKOS PEMASANGAN ls 1.00 473,900.00 473,900.00
Jumlah 5,686,800.00 473,900.00 6,160,700.00
Keuntungan Max 10% 10% 568,680.00 47,390.00 616,070.00
Jumlah + Keuntungan 6,255,480.00 521,290.00 6,776,770.00
Dibulatkan 6,255,400.00 521,200.00 6,776,600.00
13. PEKERJAAN GENERATOR SET
1 Pemasangan Genset 200 Kva
Genset 200 Kva unit 1.00 370,000,000.00 370,000,000.00
BAHAN
Wirring & Setting ls 1.00 5,550,000.00 5,550,000.00
TENAGA ONGKOS PEMASANGAN ls 1.00 3,700,000.00 3,700,000.00
Jumlah 375,550,000.00 3,700,000.00 379,250,000.00
Keuntungan Max 10% 10% 37,555,000.00 370,000.00 37,925,000.00
Jumlah + Keuntungan 413,105,000.00 4,070,000.00 417,175,000.00
Dibulatkan 413,105,000.00 4,070,000.00 417,175,000.00
2 Pemasangan Genset 100 Kva Type Silent
Genset 100 Kva Type Silent unit 1.00 165,000,000.00 165,000,000.00
BAHAN
Wirring & Setting ls 1.00 4,125,000.00 4,125,000.00
TENAGA ONGKOS PEMASANGAN ls 1.00 2,475,000.00 2,475,000.00
Jumlah 169,125,000.00 2,475,000.00 171,600,000.00
Keuntungan Max 10% 10% 16,912,500.00 247,500.00 17,160,000.00
Jumlah + Keuntungan 186,037,500.00 2,722,500.00 188,760,000.00
Dibulatkan 186,037,500.00 2,722,500.00 188,760,000.00
3 Pemasangan Panel Kontrol Genset (Sinkronize, AMF & ATS)
Motorized COS 3P 200 A unit 1.00 4,827,600.00 4,827,600.00
MCCB 3P 200 A unit 3.00 1,039,000.00 3,117,000.00
Battrey Charger 24V/5A unit 1.00 1,500,000.00 1,500,000.00
AMF Module 6120 unit 1.00 2,500,000.00 2,500,000.00
relay unit 1.00 35,000.00 35,000.00
MCB 1P 6A unit 2.00 45,000.00 90,000.00
BAHAN Digital Power Meter unit 6.00 2,085,000.00 12,510,000.00
Pilot Lamp unit 6.00 25,000.00 150,000.00
Fuse Pilot Lamp unit 6.00 15,000.00 90,000.00
Arrester 3 phase 25 kA unit 2.00 250,000.00 500,000.00
Wiring & Busbar unit 1.00 5,500,000.00 5,500,000.00
Panel Kosong uk. 180 x 70 x 70 cm unit 1.00 5,500,000.00 5,500,000.00
Ongkos Pasang & Steel ls 1.00 907,900.00 907,900.00
TENAGA ONGKOS PEMASANGAN ls 1.00 907,900.00 907,900.00
Jumlah 37,227,500.00 907,900.00 38,135,400.00
Keuntungan Max 10% 10% 3,722,750.00 90,790.00 3,813,540.00
Jumlah + Keuntungan 40,950,250.00 998,690.00 41,948,940.00
Dibulatkan 40,950,200.00 998,600.00 41,948,800.00
4 Pemasangan Transformator 100 kva
Transformator 100 kva bh 1.00 45,000,000.00 45,000,000.00
BAHAN
Peralatan Bantu ls 1.00 9,000,000.00 9,000,000.00
TENAGA ONGKOS PEMASANGAN ls 1.00 4,500,000.00 4,500,000.00
Jumlah 54,000,000.00 4,500,000.00 58,500,000.00
Keuntungan Max 10% 10% 5,400,000.00 450,000.00 5,850,000.00
Jumlah + Keuntungan 59,400,000.00 4,950,000.00 64,350,000.00
Dibulatkan 59,400,000.00 4,950,000.00 64,350,000.00
14. PEKERJAAN PEMASANGAN SCORING BOARD SEPAK BOLA
1 Pemasangan Scoring Board Sepak Bola Uk. (18 x 2,5 meter) Menyesuaikan di Lapangan
Pemasangan Scoring Board Sepak Bola Uk. (18 x 2,5 meter) Menyesuaik unit 1.00 185,000,000.00 185,000,000.00
BAHAN
Wirring & Setting ls 1.00 37,000,000.00 37,000,000.00
TENAGA ONGKOS PEMASANGAN ls 1.00 18,500,000.00 18,500,000.00
Jumlah 222,000,000.00 18,500,000.00 240,500,000.00
Keuntungan Max 10% 10% 22,200,000.00 1,850,000.00 24,050,000.00
Jumlah + Keuntungan 244,200,000.00 20,350,000.00 264,550,000.00
Dibulatkan 244,200,000.00 20,350,000.00 264,550,000.00
15. PEKERJAAN PEMASANGAN DAYA LISTRIK 75,3kVa
1 Pemasangan Daya Listrik 182,4 kVa
Pemasangan Daya Listrik Baru 75,3 kVa kVa 75.30 750,000.00 56,475,000.00
BAHAN
SLO dan UJL kVa 75.30 25.00 1,882.50
TENAGA ONGKOS PEMASANGAN ls 1.00 1,411,900.00 1,411,900.00
Jumlah 56,476,882.50 1,411,900.00 57,888,782.50
Keuntungan Max 10% 10% 5,647,688.25 141,190.00 5,788,878.25
Jumlah + Keuntungan 62,124,570.75 1,553,090.00 63,677,660.75
Dibulatkan 62,124,500.00 1,553,000.00 63,677,500.00
1 Lampu Downlight Spotlight
Downlight Spotlight unit 1.00 90,000.00 90,000.00
BAHAN
TENAGA ONGKOS PEMASANGAN ls 1.00 9,000.00 9,000.00
Jumlah 90,000.00 9,000.00 99,000.00
Keuntungan Max 10% 10% 9,000.00 900.00 9,900.00
Jumlah + Keuntungan 99,000.00 9,900.00 108,900.00
Dibulatkan 99,000.00 9,900.00 108,900.00
1 Lampu Downlight Kotak
Downlight Kotak unit 1.00 65,000.00 65,000.00
BAHAN
TENAGA ONGKOS PEMASANGAN ls 1.00 6,500.00 6,500.00
Jumlah 65,000.00 6,500.00 71,500.00
Keuntungan Max 10% 10% 6,500.00 650.00 7,150.00
Jumlah + Keuntungan 71,500.00 7,150.00 78,650.00
Dibulatkan 71,500.00 7,100.00 78,600.00
1 Lampu Dinding Tangga
Lampu Dinding tangga unit 1.00 280,000.00 280,000.00
BAHAN
TENAGA ONGKOS PEMASANGAN ls 1.00 28,000.00 28,000.00
Jumlah 280,000.00 28,000.00 308,000.00
Keuntungan Max 10% 10% 28,000.00 2,800.00 30,800.00
Jumlah + Keuntungan 308,000.00 30,800.00 338,800.00
Dibulatkan 308,000.00 30,800.00 338,800.00
1 Lampu Meja Makan
Lampu Maja Makan unit 1.00 125,000.00 125,000.00
BAHAN
TENAGA ONGKOS PEMASANGAN ls 1.00 12,500.00 12,500.00
Jumlah 125,000.00 12,500.00 137,500.00
Keuntungan Max 10% 10% 12,500.00 1,250.00 13,750.00
Jumlah + Keuntungan 137,500.00 13,750.00 151,250.00
Dibulatkan 137,500.00 13,700.00 151,200.00
ANALISA HARGA SATUAN PEKERJAAN
AN 47 1m¹ Memasang Electric Pump 750 USGPM, Head : 100 m (vertical Turbin)
Harga Bahan 1.000 m¹ 125,000,000.00 125,000,000.00
Material Bantu 1.000 m¹ 6,250,000.00 6,250,000.00
Upah Pasang
Pekerja 0.250 org 85,000.00
Tukang Pipa 0.250 org 95,000.00
JUMLAH 131,250,000.00
KEUNTUNGAN 10% 13,125,000.00
JUMLAH 144,375,000.00
DIBULATKAN 144,375,000.00
AN 48 1m¹ Memasang Diesel Pump 750 USGPM, Head : 100 m (vertical Turbin)
Harga Bahan 1.000 m¹ 245,000,000.00 245,000,000.00
Material Bantu 1.000 m¹ 12,250,000.00 12,250,000.00
Upah Pasang
Pekerja 0.250 org 85,000.00
Tukang Pipa 0.250 org 95,000.00
JUMLAH 257,250,000.00
KEUNTUNGAN 10% 25,725,000.00
JUMLAH 282,975,000.00
DIBULATKAN 282,975,000.00
58,000.00
9,775.00
11,400.00
3,135.00
1,320.00
25,630.00
2,563.00
28,193.00
29,000.00
83,000.00
14,025.00
16,150.00
5,985.00
3,520.00
39,680.00
3,968.00
43,648.00
44,000.00
106,000.00
18,275.00
20,900.00
7,885.00
5,720.00
52,780.00
5,278.00
58,058.00
59,000.00
135,000.00
22,525.00
25,650.00
9,310.00
7,700.00
65,185.00
6,518.50
71,703.50
72,000.00
186,000.00
26,775.00
30,400.00
10,735.00
9,680.00
77,590.00
7,759.00
85,349.00
86,000.00
227,000.00
30,175.00
34,200.00
11,875.00
11,330.00
87,580.00
8,758.00
96,338.00
97,000.00
292,000.00
33,575.00
38,000.00
13,015.00
12,980.00
97,570.00
9,757.00
107,327.00
108,000.00
445,000.00
36,975.00
41,800.00
14,155.00
14,630.00
107,560.00
10,756.00
118,316.00
119,000.00
524,000.00
40,375.00
45,600.00
15,295.00
16,280.00
117,550.00
11,755.00
129,305.00
130,000.00
661,200.00
43,775.00
49,400.00
16,435.00
17,930.00
127,540.00
12,754.00
140,294.00
140,200.00
458,500.00
43,775.00
49,400.00
93,175.00
9,317.50
102,492.50
102,500.00
533,500.00
43,775.00
49,400.00
93,175.00
9,317.50
102,492.50
102,500.00
677,300.00
52,275.00
58,900.00
111,175.00
11,117.50
122,292.50
122,300.00
893,700.00
60,350.00
69,350.00
129,700.00
12,970.00
142,670.00
142,700.00
1,246,600.00
66,300.00
76,950.00
143,250.00
14,325.00
157,575.00
157,600.00
3,954,500.00
43,775.00
49,400.00
93,175.00
9,317.50
102,492.50
102,500.00
8,166,500.00
43,775.00
49,400.00
93,175.00
9,317.50
102,492.50
102,500.00
10,219,500.00
43,775.00
49,400.00
93,175.00
9,317.50
102,492.50
102,500.00
12,699,300.00
52,275.00
58,900.00
111,175.00
11,117.50
122,292.50
122,300.00
17,098,700.00
60,350.00
69,350.00
129,700.00
12,970.00
142,670.00
142,700.00
36,097,600.00
66,300.00
76,950.00
143,250.00
14,325.00
157,575.00
157,600.00
55,772,600.00
66,300.00
76,950.00
143,250.00
14,325.00
157,575.00
157,600.00
4,096,600.00
66,300.00
76,950.00
143,250.00
14,325.00
157,575.00
157,600.00
2,490,500.00
43,775.00
49,400.00
93,175.00
9,317.50
102,492.50
102,500.00
3,001,300.00
52,275.00
58,900.00
111,175.00
11,117.50
122,292.50
122,300.00
4,344,700.00
60,350.00
69,350.00
129,700.00
12,970.00
142,670.00
142,700.00
8,700,600.00
66,300.00
76,950.00
143,250.00
14,325.00
157,575.00
157,600.00
11,128,600.00
66,300.00
76,950.00
143,250.00
14,325.00
157,575.00
157,600.00
5,701,600.00
66,300.00
76,950.00
143,250.00
14,325.00
157,575.00
157,600.00
1,532,600.00
66,300.00
76,950.00
143,250.00
14,325.00
157,575.00
157,600.00
2,339,500.00
43,775.00
49,400.00
93,175.00
9,317.50
102,492.50
102,500.00
2,461,300.00
52,275.00
58,900.00
111,175.00
11,117.50
122,292.50
122,300.00
3,411,700.00
60,350.00
69,350.00
129,700.00
12,970.00
142,670.00
142,700.00
8,700,600.00
66,300.00
76,950.00
143,250.00
14,325.00
157,575.00
157,600.00
3,045,500.00
43,775.00
49,400.00
93,175.00
9,317.50
102,492.50
102,500.00
4,685,300.00
52,275.00
58,900.00
111,175.00
11,117.50
122,292.50
122,300.00
592,900.00
26,350.00
39,900.00
66,250.00
6,625.00
72,875.00
72,900.00
814,800.00
29,750.00
43,700.00
73,450.00
7,345.00
80,795.00
80,800.00
920,800.00
33,150.00
47,500.00
80,650.00
8,065.00
88,715.00
88,800.00
1,598,700.00
36,550.00
51,300.00
87,850.00
8,785.00
96,635.00
96,700.00
791,700.00
36,550.00
51,300.00
87,850.00
8,785.00
96,635.00
96,700.00
878,700.00
36,550.00
51,300.00
87,850.00
8,785.00
96,635.00
96,700.00
3,181,700.00
36,550.00
51,300.00
87,850.00
8,785.00
96,635.00
96,700.00
2,175,700.00
36,550.00
51,300.00
87,850.00
8,785.00
96,635.00
96,700.00
14,534,700.00
36,550.00
51,300.00
87,850.00
8,785.00
96,635.00
96,700.00
1,771,700.00
36,550.00
51,300.00
87,850.00
8,785.00
96,635.00
96,700.00
4,083,900.00
127,500.00
161,500.00
289,000.00
28,900.00
317,900.00
317,900.00
3,494,900.00
127,500.00
161,500.00
289,000.00
28,900.00
317,900.00
317,900.00
113,500.00
21,250.00
23,750.00
45,000.00
4,500.00
49,500.00
49,500.00
20,608,500.00
21,250.00
23,750.00
45,000.00
4,500.00
49,500.00
49,500.00
144,424,500.00
21,250.00
23,750.00
45,000.00
4,500.00
49,500.00
49,500.00
283,024,500.00
21,250.00
23,750.00
45,000.00
4,500.00
49,500.00
49,500.00
64,729,500.00
21,250.00
23,750.00
45,000.00
4,500.00
49,500.00
49,500.00
4,649,000.00
-
-
-
-
DAFTAR HARGA SATUAN DASAR MATERIAL DAN UPAH
I. JENIS MATERIAL DAN BAHAN
NO MATERIAL KODE SATUAN HARGA SATUAN (RP)
A BAHAN AGREGAT, BAHAN PEREKAT, dan BAHAN JADINYA
Ref. Produk, PC: sekualitas Tiga Roda
Tanah Urug A01 m³ 50,000.00
Sirtu A02 m³ 165,000.00
Pasir Urug A03 m³ 150,000.00
Pasir Pasang A04 m³ 165,000.00
Pasir Beton A05 m³ 185,000.00
Batu Kali A06 m³ 150,000.00
Split 2-3 A07 m³ 185,000.00
Agregat Kela A A08 m³ 325,000.00
Agregat Kelas B A09 m³ 355,000.00
Portland Cement (1 zak = 50 kg) A10 kg 1,100.00
Portland Cement (1 zak = 50 kg) A11 zak 55,000.00
Bata Merah Bakar Kelas 1 A12 bh 550.00
Bata Ringan 600x200x7.5 A13 m³ 525,000.00
Ready Mix K-250 A14 m³ 955,000.00
Ready Mix K-300 A15 m³ 995,000.00
Ready Mix K-350 A16 m³ 1,150,000.00
Sewa Pompa Beton/m3 A17 m³ 50,000.00
Vibrator A18 sewa/hari 250,000.00
Air A19 liter 500.00
Spacer A20 bh 2,500.00
Water Stop PVC Lebar 230-320 mm A21 m' 235,000.00
Integral Waterproofing A22 liter 35,000.00
Waterproofing A23 m² 35,000.00
Waterproofing Membrane (Duo HT 4 AGR/ F C 180 Mecano) A24 m² 150,000.00
Dry Mix/Semen Instan Perekat Pasangan Bata, @40kg A25 zak 85,000.00
Dry Mix/Semen Instan Pelester, @40kg A26 zak 85,000.00
Dry Mix/Semen Instan Acian, @40kg A27 zak 85,000.00
Semen Instan Floor hardener @ 25 kg A28 kg 16,200.00
Semen Warna A29 kg 10,000.00
Semen Grouting Untuk Sambungan Struktur A30 zak 6,000.00
Graffel Ø30 cm A31 m' 50,000.00
Buis Beton 1/2 Lingkaran Dia. 40 cm A32 unit 90,000.00
Glass Block A33 bh 20,000.00
Rooster A34 bh 85,000.00
Rooster Beton 15 x 30 A35 bh 15,000.00
Rooster Batako 20 x 20 A36 bh 10,000.00
Karet Dilatasi A37 m' 265,000.00
Kansteen Jalan type DKI uk. 60 x 25 x 22 x 18 A38 bh 50,000.00
Kansteen Taman type Taman uk. 40 x 25 x 15 x 13 A39 bh 45,000.00
Kansteen Jalan 600x150x300 sek. Conblock A40 bh 70,000.00
Kansteen Paving Blok uk. 400x60x150 sek. Cisangkan, masterblock, Alphan A41 bh 18,000.00
Kansteen Jepit A42 bh 52,500.00
Paving Blok t = 8 cm Natural Sek. Cisangkan A43 m² 108,000.00
Paving Blok t = 8 cm WarnaSek. Cisangkan A44 m² 134,000.00
U-DITCH 30x50x120 A45 unit 450,000.00
U-DITCH 60x80x120 A46 unit 950,000.00
U-DITCH 120x120x120 A47 unit 2,150,000.00
COVER U-DITCH LD 30 A48 bh 150,000.00
COVER U-DITCH LD 60 A49 bh 229,900.00
COVER U-DITCH LD 120 A50 bh 650,000.00
Box Culvur 150 x 150 x 100 A51 unit 7,000,000.00
Residu A52 liter 8,500.00
Lem Kayu A53 kg 20,000.00
Gheotextile 25 cm A54 m' 12,500.00
Gheotextile 150 cm A55 m² 15,000.00
Rumput Sepak Bola Ttpe Zoysia Matrella Limmer A56 m² 75,000.00
Pupuk Kandang A57 kmg 85,000.00
2 Mst NPK 3 gr N A58 kg 165,000.00
3 Mst Urea 2,5 gr N A59 kg 800.00
4 Mst Kapur A60 kg 8,000.00
5 Mst NPK 3 gr N A61 kg 16,000.00
Ansar (Hibersida Selektif) A62 liter 4,750,000.00
1 Set Tiang Gawang Pipa Alumunium A63 set 80,000,000.00
Tiang bendera tendangan sudut pipa fiber padat Dia.1 1/2" + kain bendera A64 set 875,000.00
Catch Basin Uk. 30 x 30 x 30 cm A65 bh 375,000.00
Beton Precast Half Slab 80 x 05 x 5 A64 m² 158,100.00
B BAHAN KAYU DAN BAHAN JADINYA
Kayu Papan Terentang B01 m³ 1,500,000.00
Kayu Balok Terentang B02 m³ 1,500,000.00
Dolken Dia. 8 s/d 10 cm B03 btg 21,000.00
Kayu Kelas Kuat III B04 m³ 1,500,000.00
Balok Kelas Kuat II B05 m³ 2,200,000.00
Multipleks 9mm, uk. 1,20 x 2,40 B06 lbr 120,000.00
Multipleks 12mm, uk. 1,20 x 2,40 B07 lbr 155,000.00
Taekwood 4mm B08 lbr 120,000.00
Plywood Tebal 9mm B09 lbr 210,000.00
Plywood Tebal 4mm B10 lbr 120,000.00
HPL B11 lbr 105,000.00
Papan Nama Proyek B12 ls 500,000.00
Kayu 5/10 Meranti B13 m 15,000.00
E BAHAN PANCANG
Ref. Produk, Tiang Pancang : Sekualitas Wijaya Karya Beton, PP Precast
Tiang Pancang Beton Bertulang Tipe Spun Pile Ø 40cm, t = 7,5 cm E01 m' 600,000.00
Bobokan Kepala Pondasi Tiang E02 ttk 175,000.00
Tiang Pancang Prategang Tipe Kotak Uk. 30 x 30 cm E03 m' 225,000.00
H BAHAN ATAP
Ref. Produk, Penutup atap Aspal Bitumen = Ondumline
Pasang Rangka Atap Baja Ringan
• Mobilisasi H01 ls 10,500.00
• Main Trus C-75-75 H02 m¹ 13,500.00
• Roof Botton/ Reng 33-0.45 H03 m¹ 7,500.00
• Self Driling Screw Dia. 6x20 mm (Truss Screw) H04 bh 500.00
• Self Driling Screw Dia. 4x16 mm (Truss Screw) H05 bh 550.00
• Dynabol Dia. 12x120 mm H06 bh 1,200.00
Genteng Beton Cisangka Type Victoria Pine H07 bh 12,500.00
Nok / Ridge Onduline H08 lbr 95,000.00
Listplank GRC, Lebar 30 cm H09 m¹ 45,000.00
Talang Datar/Juray, Zincalume Lebar 90 cm H10 m¹ 35,900.00
Penutup Atap Bintumen (Onduline/Onduvilla) H11 lbr 195,000.00
Wood Plastic Composite ( 10 x 1 cm H12 btg 120,000.00
SolarPlate 1,2 mm L = 122 cm Transparan H13 m² 600,000.00
Penutup Atap Metal Zincalume, t= 0,45 mm H14 m² 80,000.00
Nok / Bubungan Metal Zincalume, t= 0,45 mm H15 m¹ 35,000.00
Allumunium Foil H16 m² 20,000.00
RoofMesh H17 m² 7,500.00
Glasswool H18 m² 15,000.00
Penutup Atap Polycarbonat H19 m² 100,000.00
I BAHAN FLAFOUND
Ref. Produk, Gyptile : Knauf, Jaya Board, dan Elephant
Ref. Produk, GRC : Kalsiboard, Jaya Board, Elephant
Ref. Produk, Compound: Aplus, Knauf, dan Jaya Board
GRC 1200 x 2400, t = 4 mm I01 lbr 45,000.00
Plafound Zincalume, t = 0,8 mm I02 m² 120,000.00
Semen Coumpound Adhesive, @20 kg I03 kg 8,000.00
Joint Tape @75 m (kasa gypsum) I04 roll 10,000.00
Gypsum 120 x 240 t = 9 mm I05 lbr 65,000.00
Gypsum 120 x 240 t = 12 mm I06 lbr 95,000.00
List Gypsum C-7 I07 m¹ 14,200.00
Tepung Gypsum I08 kg 4,200.00
Alkasit Pembantu Coumpound I09 kg 20,000.00
L RAIN GUN
Tanah Humus L01 m² 50,000.00
Tanaman Jawer Kotok L02 bh 5,000.00
Pohon Glodogan Tiang L03 bh 15,000.00
Rumput Gajah Mini L04 m² 25,000.00
Pohon Pucuk Merah L05 bh 200,000.00
Rain Gun Type SR 3003 Merki Rain Bird L06 bh 28,500,000.00
Tiang Rain Gun L07 bh 3,750,000.00
Quick Coupling 2" L08 bh 3,500,000.00
Gate Valve 2" Kitz Kuningan L09 bh 550,000.00
Pipa Gip dia. 2" L10 bh 2,500,000.00
Pipa Gip dia. 4" L11 bh 3,250,000.00
Pompa Sentrifugal End Section L12 bh 70,500,000.00
Panel Control L13 bh 18,000,000.00
Pressure Tank Kap 1000lt @ 10 Bar-ACC L14 bh 21,500,000.00
Alat Pelindung Kerja terdiri atas: Jaring Pengaman (Safety Net); N15 Ls 3,500,000.00
Tali Keselamatan (Life Line); N16 Ls 750,000.00
Penahan Jatuh (Safety Deck); N17 Ls 3,500,000.00
Pagar Pengaman (Guard Railling); N18 Ls 2,000,000.00
Pembatas Area (Restricted Area ). N19 Ls 2,000,000.00
AKSESORRIS PEMIPAAN
1 Check valve dia. 50 mm 1,771,000.00
2 Flexible Joint dia. 50 mm 327,800.00
3 Strainer dia. 50 mm 825,000.00
4 Floating valve dia 50 mm 315,000.00
5 Clean Out dia. Ø 50 mm 123,000.00
6 Clean Out dia. Ø 100 mm 220,000.00
7 Clean Out dia. Ø 75 mm 169,000.00
8 Water Level Control (WLC) 350,000.00
9 Water Meter 170,000.00
10 Pressure Switch 935,000.00
11 Pressure Gauge 247,500.00
12 Reducer Tee Sch 40 4" x 2" 195,000.00
Pipa BSP
1 Pipa BSP 1" Schedule 40 23,750.00
2 Pipa BSP 1 1/4" Schedule 40 32,038.33
3 Pipa BSP 11/2" Schedule 40 38,641.67
4 Pipa BSP 2" Schedule 40 51,846.67
5 Pipa BSP 2 1/2" Schedule 40 81,985.00
6 Pipa BSP 3" Schedule 40 107,088.33
7 Pipa BSP 4" Schedule 40 151,998.33
8 Pipa BSP 6" Schedule 40 268,636.67
9 Pipa BSP 8" Schedule 40 325,000.00
10 Pipa Header BSP 8" Schedule 40 410,000.00
Air Conditioner
Ref Produk : Sekualitas Samsung, Daikin
1 Type Wall Mounting Kapasitas 5.000 btu/h 4,340,000.00
2 Type Wall Mounting Kapasitas 7.000 btu/h 5,810,000.00
3 Type Wall Mounting Kapasitas 9.000 btu/h 6,380,000.00
4 Type Wall Mounting Kapasitas 12.000 btu/h 7,560,000.00
5 Type Wall Mounting Kapasitas 18.000 btu/h 5,450,000.00
6 Type Wall Mounting Kapasitas 22.000 btu/h 15,530,000.00
7 Type Ceiling Kapasitas 24.000 btu/h 19,800,000.00
8 Type Ceiling Kapasitas 28.000 btu/h 20,860,000.00
9 Type Ceiling Kapasitas 36.000 btu/h 30,550,000.00
10 Type Ceiling Kapasitas 42.000 btu/h 35,750,000.00
11 Type Ceiling Kapasitas 48.000 btu/h 39,750,000.00
12 Out door Unit AC Kapasitas 230.000 Btu/h 263,479,000.00
13 Out door Unit AC Kapasitas 268.000 Btu/h 307,375,000.00
14 Out door Unit AC Kapasitas 285.000 Btu/h 333,484,000.00
15 Out door Unit AC Kapasitas 382.000 Btu/h 438,869,000.00
16 Type Standing Ac Portable Kapasitas 24.900 Btu/h 12,000,000.00
17 Refnet Joint & Header 4,770,000.00
18 Pipa AC < 19.100 Btu/h dia.6,35 mm (1/4) x 12,7 mm (1/2) 44,500.00
19 Pipa AC < 54.600 Btu/h dia.9,52 mm (3/8) x 15,88 mm (5/8) 65,500.00
20 Pipa AC < 242.300 Btu/h dia.15,88 mm (5/8) x 28,58 mm (9/8) 382,000.00
21 Pipa AC < 354.900 Btu/h dia.19,05 mm (3/4) x 41,3 mm (1.5/8) 432,700.00
PERALATAN PANEL TR
B Bahan:
C Peralatan:
PEMBUATAN 1 M2 KANTOR SEMENTARA LANTAI PLESTERAN (A. 2.2.1.5 HSP BIDANG KARYA CIPTA BALITBANG PU)
A TENAGA:
Pekerja Terampil L.01 oh 2.00 85,000.00 170,000.00
Tukang Terampil L.02 oh 2.00 95,000.00 190,000.00
Kepala Tukang L.03 oh 0.30 95,000.00 28,500.00
Mandor L.04 oh 0.05 110,000.00 5,500.00
B Bahan:
Dolken kayu diameter 8-10/400 cm Batang 1.25 21,000.00 26,250.00
Kayu m3 0.18 1,500,000.00 270,000.00
Paku biasa kg 0.08 18,000.00 1,440.00
Besi strip kg 1.10 11,500.00 12,650.00
Semen portland kg 35.00 1,100.00 38,500.00
Pasir pasang m3 0.15 165,000.00 24,750.00
Pasir beton m3 0.10 185,000.00 18,500.00
Koral beton m3 0.15 185,000.00 27,750.00
Bata merah Bh 30.00 550.00 16,500.00
Seng plat Lbr 0.25 60,000.00 15,000.00
Kaca polos m2 0.08 115,000.00 9,200.00
Plywood 4mm Lbr 0.06 120,000.00 7,200.00
C Peralatan:
C Peralatan:
C Peralatan:
Buldozert jam 0.05 150,000.00 7,650.00
Alat Bantu set 1.00 12,000.00 12,000.00
D Jumlah (A+B+C) 19,650.00 60,440.00 80,090.00
E Over Head & Profit, 10% x D 24,027.00
0.30 x D
F Jumlah (D+E) 104,117.00
G Dibulatkan 104,100.00
C Peralatan:
Mesin Pompa Air Diesel 5kw Unit 7.00 55,000.00 385,000.00
Mata Bor Tanah Unit 0.66 125,000.00 82,875.00
Solar Ltr 3.50 6,800.00 23,800.00
Pipa Besi 1,5" M' 1.00 30,853.00 30,853.00
Mesin Pompa Air Semi ZetPump Unit 1.00 85,000.00 85,000.00
C Peralatan:
C Peralatan:
C Peralatan:
C Peralatan:
C Peralatan:
Sewa Theodolite F28 \hari 0.007 500,000.00 3,350.00
C Peralatan:
Dump Truck F14 jam 0.002 200,000.00 400.00
Alat Bantu ls 1.000 1,000.00 1,000.00
D Jumlah (A+B+C) 1,400.00 7,490.00 8,890.00
E Over Head & Profit, 10% x D 2,667.00
0.30 x D
F Jumlah (D+E) 11,557.00
G Dibulatkan 11,500.00
M³ GALIAN TANAH DENGAN ALAT BERAT (Analisa PU2016 A.2.3.1.11)
A TENAGA:
Pekerja Terampil L.01 oh 0.076 85,000.00 6,460.00
Mandor L04 oh 0.039 110,000.00 4,265.80
B Bahan:
C Peralatan:
Excavator F06 jam 0.038 248,536.00 9,394.66
Dump Truck F14 jam 0.172 200,000.00 34,440.00
Alat Bantu ls 1.000 1,000.00 1,000.00
D Jumlah (A+B+C) 44,834.66 10,725.80 55,560.46
E Over Head & Profit, 10% x D 16,668.14
0.30 x D
F Jumlah (D+E) 72,228.60
G Dibulatkan 72,200.00
M² PEMBENTUKAN BADAN JALAN DAN PEMADATAN TANAH CBR 4 (Analisa PU2016 A.2.3.1.11)
A TENAGA:
Pekerja Terampil L.01 oh 0.082 85,000.00 6,970.00
Mandor L04 oh 0.010 110,000.00 1,133.00
B Bahan:
C Peralatan:
Pedestrian Roller F12 jam 0.010 52,727.00 543.09
Alat Bantu ls 1.000 5,000.00 5,000.00
D Jumlah (A+B+C) 5,543.09 8,103.00 13,646.09
E Over Head & Profit, 10% x D 4,093.83
0.30 x D
F Jumlah (D+E) 17,739.91
G Dibulatkan 17,700.00
C Peralatan:
Excavator F06 jam 0.0342 248,536.00 8,499.93
Dump Truck 3.5 - 4 T F14 jam 0.1702 200,000.00 34,040.00
Motor Grader F08 jam 0.0037 289,993.00 1,072.97
Vibrator Roler F19 jam 0.0042 435,000.00 1,827.00
Truck Tangki Air F13 jam 0.0070 143,187.00 1,002.31
Alat Bantu ls 1.000 5,000.00 5,000.00
D Jumlah (A+B+C) 111,442.21 15,390.00 126,832.21
E Over Head & Profit, 10% x D 38,049.66
0.30 x D
F Jumlah (D+E) 164,881.88
G Dibulatkan 164,800.00
C Peralatan:
Excavator F06 jam 0.0342 248,536.00 8,499.93
Dump Truck 3.5 - 4 T F14 jam 0.1702 200,000.00 34,040.00
Motor Grader F08 jam 0.0037 289,993.00 1,072.97
Vibrator Roler F19 jam 0.0042 435,000.00 1,827.00
Truck Tangki Air F13 jam 0.0070 143,187.00 1,002.31
Alat Bantu ls 1.000 5,000.00 5,000.00
D Jumlah (A+B+C) 111,442.21 15,385.00 126,827.21
E Over Head & Profit, 10% x D 38,048.16
0.30 x D
F Jumlah (D+E) 164,875.38
G Dibulatkan 164,800.00
C Peralatan:
Sewa Baby Woles F17 jam 0.0750 87,500.00 6,562.50
C Peralatan:
C Peralatan:
C Peralatan:
C Peralatan:
PEMBONGKARAN 1 M² RANGKA PLAFOND - (BONGKARAN TIDAK DIPAKAI LAGI) (SNI REV. 2005)
A TENAGA:
Pekerja Terampil L.01 oh 0.1250 85,000.00 10,625.00
Mandor L.04 oh 0.0050 110,000.00 550.00
B Bahan:
C Peralatan:
PEMBONGKARAN 1 M² PENUTUP PLAFOND - (BONGKARAN TIDAK DIPAKAI LAGI) (SNI REV. 2005)
A TENAGA:
Pekerja Terampil L.01 oh 0.0300 85,000.00 2,550.00
Mandor L.04 oh 0.0030 110,000.00 330.00
B Bahan:
C Peralatan:
1 M1 PEMBUANGAN TANAH
A TENAGA:
Pekerja Terampil L.01 oh 0.3300 85,000.00 28,050.00
Mandor L04 oh 0.0100 110,000.00 1,100.00
B Bahan:
C Peralatan:
C Peralatan:
Pipa Geopipe (Perforated Corrugated Pipe) dia. DN 100 mm D43 m¹ 1.20 330,000.00 396,000.00
C Peralatan:
C Peralatan:
C Peralatan:
C Peralatan:
C Peralatan:
II PEKERJAAN STRUKTUR
Ref. Produk, PCC: Sekualitas Tiga Roda
Ref. Produk, Baja Tulangan: sekualitas KS SNI Cilegon
Ref. Produk Pasir, batu kali, Batu Split: Quary terbaik dan teruji mutu di lokasi pekerjaan
Ref. Produk, Baja Tulangan: sekualitas KS SNI Cilegon
Ref. Produk, Tiang Pancang: Sekualitas Wijaya Karya Beton, PP Precast
PEMBUATAN 1 M3 BETON MUTU f'c = 7,4 Mpa (K 100), slump (3-6) cm, w/c = 0,87 (A. 4.1.1.1 HSP BIDANG KARYA CIPTA BALITBANG PU)
A TENAGA:
Pekerja L.01 OH 1.2000 85,000.00 102,000.00
Tukang Batu L.02 OH 0.2000 95,000.00 19,000.00
Kepala Tukang L.03 OH 0.0200 95,000.00 1,900.00
Mandor L.04 OH 0.0600 110,000.00 6,600.00
B Bahan:
Semen portlan A10 kg 230.000 1,100.00 253,000.00
Pasir beton A05 m³ 0.638 185,000.00 118,003.57
Kerikil (Maks 30mm) A07 m³ 0.761 185,000.00 140,737.04
Air A19 ltr 200.000 500.00 100,000.00
C Peralatan:
PEMBUATAN 1 M3 BETON MUTU f'c =14,5 Mpa (K 175), slump (12**2) cm, w/c = 0,66 (A.A. 4.1.1.5 HSP BIDANG KARYA CIPTA BALITBANG PU)
A TENAGA:
Pekerja L.01 OH 1.6500 85,000.00 140,250.00
Tukang Batu L.02 OH 0.2750 95,000.00 26,125.00
Kepala Tukang L.03 OH 0.0280 95,000.00 2,660.00
Mandor L.04 OH 0.0830 110,000.00 9,130.00
B Bahan:
Semen portlan A10 kg 326.000 1,100.00 358,600.00
Pasir beton A05 m³ 0.543 185,000.00 100,455.00
Kerikil (Maks 30mm) A07 m³ 0.762 185,000.00 140,970.00
Air A19 ltr 215.000 500.00 107,500.00
C Peralatan:
C Peralatan:
PEMASANGAN 1 M3 BETON MUTU f'c =21.7 Mpa (K 250), slump (12**2) cm, w/c = 0,56 (A. 4.1.1.8 HSP BIDANG KARYA CIPTA BALITBANG PU)
A TENAGA:
Pekerja L.01 OH 1.6500 85,000.00 140,250.00
Tukang Batu L.02 OH 0.2750 95,000.00 26,125.00
Kepala Tukang L.03 OH 0.0280 95,000.00 2,660.00
Mandor L.04 OH 0.0830 110,000.00 9,130.00
B Bahan:
Semen portlan A10 kg 384.000 1,100.00 422,400.00
Pasir beton A05 m³ 0.494 185,000.00 91,442.86
Kerikil (Maks 30mm) A07 m³ 0.577 185,000.00 106,786.11
Air A19 ltr 215.000 500.00 107,500.00
C Peralatan:
PEMASANGAN 1 M3 BETON MUTU f'c =24 Mpa (K 275), slump (12**2) cm, w/c = 0,53 (A. 4.1.1.9 HSP BIDANG KARYA CIPTA BALITBANG PU)
A TENAGA:
Pekerja L.01 OH 1.6500 85,000.00 140,250.00
Tukang Batu L.02 OH 0.2750 95,000.00 26,125.00
Kepala Tukang L.03 OH 0.0280 95,000.00 2,660.00
Mandor L.04 OH 0.0830 110,000.00 9,130.00
B Bahan:
Semen portlan A10 kg 406.000 1,100.00 446,600.00
Pasir beton A05 m³ 0.489 185,000.00 90,385.71
Kerikil (Maks 30mm) A07 m³ 0.570 185,000.00 105,450.00
Air A19 ltr 215.000 500.00 107,500.00
C Peralatan:
PEMASANGAN 1 M3 BETON MUTU f'c =26,4 Mpa (K 300), slump (12**2) cm, w/c = 0,52 (A. 4.1.1.10 HSP BIDANG KARYA CIPTA BALITBANG PU)
A TENAGA:
Pekerja L.01 OH 1.6500 85,000.00 140,250.00
Tukang Batu L.02 OH 0.2750 95,000.00 26,125.00
Kepala Tukang L.03 OH 0.0280 95,000.00 2,660.00
Mandor L.04 OH 0.0830 110,000.00 9,130.00
B Bahan:
Semen portlan A10 kg 413.000 1,100.00 454,300.00
Pasir beton A05 m³ 0.486 185,000.00 89,989.29
Kerikil (Maks 30mm) A07 m³ 0.567 185,000.00 104,936.11
Air A19 ltr 215.000 500.00 107,500.00
C Peralatan:
C Peralatan:
Sewa Pompa Beton/m³ F27 m³ 1.0000 3,306.00 3,306.00 3,306.00
C Peralatan:
Vibrator A18 sewa/hari 0.1000 250,000.00 25,000.00 25,000.00
1 M3 BETON READY MIX K-250, f'c = 20.75Mpa, SLUMP (12±2) CM, w/c = 0.52 (Analisa PU2013 A.4.1.1.10)
A TENAGA:
Pekerja L.01 OH 1.6500 85,000.00 140,250.00
Tukang Batu L.02 OH 0.2750 95,000.00 26,125.00
Kepala Tukang L.03 OH 0.0280 95,000.00 2,660.00
Mandor L.04 OH 0.0830 110,000.00 9,130.00
B Bahan:
Readymix K-250 A14 m³ 1.050 955,000.00 1,002,750.00
C Peralatan:
Sewa Pompa Beton/m3 F27 m³ 1.0000 3,306.00 3,306.00 3,306.00
Alat Bantu (Vibrator, dll) ls 1.0000 15,000.00 15,000.00 15,000.00
1 M3 BETON READY MIX K-300, f'c = 24.9 Mpa, SLUMP (12±2) CM, w/c = 0.52 (Analisa PU2013 A.4.1.1.10)
A TENAGA:
Pekerja L.01 OH 1.6500 85,000.00 140,250.00
Tukang Batu L.02 OH 0.2750 95,000.00 26,125.00
Kepala Tukang L.03 OH 0.0280 95,000.00 2,660.00
Mandor L.04 OH 0.0830 110,000.00 9,130.00
B Bahan:
Readymix K-300 A15 m³ 1.050 995,000.00 1,044,750.00
C Peralatan:
Sewa Pompa Beton/m3 F27 m³ 1.0000 3,306.00 3,306.00 3,306.00
Alat Bantu (Vibrator, dll) ls 1.0000 15,000.00 15,000.00 15,000.00
1 M3 BETON READY MIX K-350, f'c = 24.9 Mpa, SLUMP (12±2) CM, w/c = 0.52 (Analisa PU2013 A.4.1.1.10)
A TENAGA:
Pekerja L.01 OH 1.0000 85,000.00 85,000.00
Tukang Batu L.02 OH 0.2500 95,000.00 23,750.00
Kepala Tukang L.03 OH 0.0250 95,000.00 2,375.00
Mandor L.04 OH 0.1000 110,000.00 11,000.00
B Bahan:
Readymix K-350 A16 m³ 1.020 1,150,000.00 1,173,000.00
C Peralatan:
Sewa Pompa Beton/m3 F27 m³ 1.0000 29,200.00 29,200.00 29,200.00
Alat Bantu (Vibrator, dll) ls 1.0000 95,800.00 95,800.00 95,800.00
C Peralatan:
Alat Bantu ls 1.0000 25,000.00 25,000.00 25,000.00
1 TITIK JASA MELAKUKAN GOUTING SAMBUNGAN STRUKTUR (AAnalisa PU A.4.1.2.21 dan Analisa PU A.4.1.2.22)
A TENAGA:
Tukang Batu L.02 OH 0.3670 95,000.00 34,865.00
Kepala Tukang L.03 OH 0.0740 95,000.00 7,030.00
Mandor L.04 OH 0.0370 110,000.00 4,070.00
B Bahan:
C Peralatan:
C Peralatan:
C Peralatan:
C Peralatan:
C Peralatan:
1 M2 BEKISTING PONDASI/SLOOP PAS. BATA MERAH, T. 1/2 BATA, 1 PC : 5 PP (Analisa PU2016 A.4.4.1.10)
A TENAGA:
Pekerja L.01 OH 0.3000 85,000.00 25,500.00
Tukang Batu L.02 OH 0.1000 95,000.00 9,500.00
Kepala Tukang L.03 OH 0.0100 95,000.00 950.00
Mandor L.04 OH 0.0150 110,000.00 1,650.00
B Bahan:
Bata Merah Bakar Kelas 1 A12 bh 70.000 550.00 38,500.00
Portland Cement (1 zak = 50 kg) A04 kg 9.680 1,100.00 10,648.00
Pasir Pasang A10 m³ 0.045 165,000.00 7,425.00
C Peralatan:
C Peralatan:
C Peralatan:
C Peralatan:
C Peralatan:
1 M2 (K3) PASANG BEKISTING dengan PAPAN 3X20, 3X PAKAI (Analisa PU2016 SDA B.22)
A TENAGA:
Pekerja L.01 OH 0.2200 85,000.00 18,700.00
Tukang Batu L.02 OH 0.6600 95,000.00 62,700.00
Kepala Tukang L.03 OH 0.0660 95,000.00 6,270.00
Mandor L.04 OH 0.0220 110,000.00 2,420.00
B Bahan:
Kayu Kelas Kuat III B04 m³ 0.016 1,500,000.00 24,000.00
Paku ukuran 4cm-12cm D13 kg 0.400 18,000.00 7,200.00
Balok Kayu Kelas Kuat II B05 m³ 0.006 2,200,000.00 13,640.00
C Peralatan:
C Peralatan:
1 M2 (K3) PASANG BEKISTING UNTUK PLAT DINDING 3X PAKAI (Analisa PU2016 A.4.1.1.25)
A TENAGA:
Pekerja L.01 OH 0.6600 85,000.00 56,100.00
Tukang Batu L.02 OH 0.3300 95,000.00 31,350.00
Kepala Tukang L.03 OH 0.0330 95,000.00 3,135.00
Mandor L.04 OH 0.0330 110,000.00 3,630.00
B Bahan:
Kayu Kelas Kuat III B04 m³ 0.010 1,500,000.00 14,625.00
Paku ukuran 4cm-12cm D13 kg 0.400 18,000.00 7,200.00
Balok Kayu Kelas Kuat II B05 m³ 0.006 2,200,000.00 13,640.00
Multipleks 12 mm, uk. 1,20 x 2,40 B07 lbr 0.127 155,000.00 19,692.75
Dolken dia 8 s/d 10 cm B03 btg 0.975 21,000.00 20,475.00
Spacer D17 bh 4.000 3,500.00 14,000.00
C Peralatan:
C Peralatan:
1 M2 PASANG BEGISTING METAL DECK UNTUK PLAT LANTAI 1X PAKAI (Analisa PU A.4.1.1.24)
A TENAGA:
Pekerja L.01 OH 0.6600 85,000.00 56,100.00
Tukang Batu L.02 OH 0.3300 95,000.00 31,350.00
Kepala Tukang L.03 OH 0.0330 95,000.00 3,135.00
Mandor L.04 OH 0.0330 110,000.00 3,630.00
B Bahan:
Kayu Kelas Kuat III B04 m³ 0.040 1,500,000.00 60,000.00
Paku ukuran 4cm-12cm D13 kg 0.400 18,000.00 7,200.00
Balok Kayu Kelas Kuat II B05 m³ 0.015 2,200,000.00 33,000.00
Metal Deck D06 lbr 1.050 125,000.00 131,250.00
Dolken dia 8 s/d 10 cm B03 btg 6.000 21,000.00 126,000.00
C Peralatan:
B Bahan:
Tiang Pancang Square 30 x 30 E03 m' 1.030 225,000.00 231,750.00
C Peralatan:
Alat Pancang, Jacked in Pile, Hydraulic Jacked F32 hari/sewa 0.035 600,000.00 21,000.00
Piling Sytem
Alat Penyambung Tiang Pancang F05 bh 0.250 95,000.00 23,750.00
B Bahan:
Tiang Pancang Beton Tipe Spun Pile Ø 40 cm, t= 7,5 cm E01 m' 1.030 600,000.00 618,000.00
C Peralatan:
Crane 5-10 ton F01 hari/sewa 0.073 200,000.00 14,560.00
Alat Pancang, HYDRAULIC SYSTEM PILE DRIVER (HSPD) F04 hari/sewa 0.073 600,000.00 43,680.00
Alat Penyambung Tiang Pancang F05 bh 0.250 95,000.00 23,750.00
B Bahan:
Water Stop PVC Lebar 230-320 mm A21 m' 1.050 235,000.00 246,750.00
C Peralatan:
B Bahan:
Integral Waterproofing A22 m' 2.000 35,000.00 70,000.00
C Peralatan:
B Bahan:
Semen Instan Floor hardener @ 25 kg A28 kg 5.000 16,200.00 81,000.00
C Peralatan:
B Bahan:
Batu Kali A06 m³ 1.200 150,000.00 180,000.00
Pasir Urug A03 m³ 0.432 150,000.00 64,800.00
C Peralatan:
B Bahan:
Batu Kali A06 m³ 1.200 150,000.00 180,000.00
Portland Cement (1 zak = 50 kg) A10 kg 136.000 1,100.00 149,600.00
Pasir Pasang A04 m³ 0.544 165,000.00 89,760.00
C Peralatan:
B Bahan:
Bata Merah A06 m³ 20.000 550.00 11,000.00
Portland Cement (1 zak = 50 kg) A10 kg 9.680 10,000.00 96,800.00
Pasir Pasang A04 m³ 0.045 35,000.00 1,575.00
C Peralatan:
B Bahan:
Baja Profil, IWF/INP/DIR/DIN/CHANEL D08 m 1.150 11,500.00 13,225.00
Material Pendukung Lainnya, 5% dari Jumlah Bahan ls 1.000 661.25 661.25
C Peralatan:
PEMASANGAN 1 M Pipa Baja dia. 1" (A. 8.4.1.64. HSP BIDANG KARYA CIPTA BALITBANG PU)
A TENAGA:
Upah Pemasangan dan Pabrikasi ls 1.0000 3,210.30 3,210.30
B Bahan:
Pipa Baja dia. 1" D20 m 1.000 30,853.00 30,853.00
Finsih Cat K01 m² 0.050 25,000.00 1,250.00
C Peralatan:
PEMASANGAN 1 M Pipa Baja dia. 1-1 1/4" (A. 8.4.1.65. HSP BIDANG KARYA CIPTA BALITBANG PU)
A TENAGA:
Upah Pemasangan dan Pabrikasi ls 1.0000 5,588.30 5,588.30
B Bahan:
Pipa Baja SCH dia. 1-1 1/4" D21 m 1.000 54,633.00 54,633.00
Finsih Cat K01 m² 0.050 25,000.00 1,250.00
C Peralatan:
PEMASANGAN 1 M Pipa Baja dia. 1-1 1/2" (A. 8.4.1.66. HSP BIDANG KARYA CIPTA BALITBANG PU)
A TENAGA:
Upah Pemasangan dan Pabrikasi ls 1.0000 3,980.00 3,980.00
B Bahan:
Pipa Baja dia. 1-1 1/2". D22 m 1.000 38,550.00 38,550.00
Finsih Cat K01 m² 0.050 25,000.00 1,250.00
C Peralatan:
D Jumlah (A+B+C) 39,800.00 3,980.00 43,780.00
E Over Head & Profit, 10% x D 13,134.00
0.30 x D
F Jumlah (D+E) 56,914.00
G Dibulatkan 56,900.00
PEMASANGAN 1 M Pipa Baja dia. 2" (A. 8.4.1.67. HSP BIDANG KARYA CIPTA BALITBANG PU)
A TENAGA:
Upah Pemasangan dan Pabrikasi ls 1.0000 6,575.00 6,575.00
B Bahan:
Pipa Baja dia. 2" D23 m 1.000 64,500.00 64,500.00
Finsih Cat K01 m² 0.050 25,000.00 1,250.00
C Peralatan:
PEMASANGAN 1 M Pipa Baja dia. 2 -2 1/2" (A. 8.4.1.68. HSP BIDANG KARYA CIPTA BALITBANG PU)
A TENAGA:
Upah Pemasangan dan Pabrikasi ls 1.0000 8,183.30 8,183.30
B Bahan:
Pipa Baja dia. 2 -2 1/2" D24 m 1.000 80,583.00 80,583.00
Finsih Cat K01 m² 0.050 25,000.00 1,250.00
C Peralatan:
PEMASANGAN 1 M Pipa Baja dia. 3" (A. 8.4.1.69. HSP BIDANG KARYA CIPTA BALITBANG PU)
A TENAGA:
Upah Pemasangan dan Pabrikasi ls 1.0000 11,033.30 11,033.30
B Bahan:
Pipa Baja dia. 3" D25 m 1.000 109,083.00 109,083.00
Finsih Cat K01 m² 0.050 25,000.00 1,250.00
C Peralatan:
PEMASANGAN 1 M Pipa Baja dia. 3 -3 1/2" (A. 8.4.1.70. HSP BIDANG KARYA CIPTA BALITBANG PU)
A TENAGA:
Upah Pemasangan dan Pabrikasi ls 1.0000 12,998.30 12,998.30
B Bahan:
Pipa Baja dia. 3 -3 1/2" D26 m 1.000 128,733.00 128,733.00
Finsih Cat K01 m² 0.050 25,000.00 1,250.00
C Peralatan:
PEMASANGAN 1 M Pipa Baja dia. 4" (A. 8.4.1.70. HSP BIDANG KARYA CIPTA BALITBANG PU)
A TENAGA:
Upah Pemasangan dan Pabrikasi ls 1.0000 16,068.30 16,068.30
B Bahan:
Pipa Baja dia. 4" D27 m 1.000 159,433.00 159,433.00
Finsih Cat K01 m² 0.050 25,000.00 1,250.00
C Peralatan:
B Bahan:
Pipa Seamless SCH 40 dia. 1/2" D28 m 1.000 19,166.67 19,166.67
C Peralatan:
B Bahan:
Pipa Seamless SCH 40 dia. 3/4" D29 m 1.000 22,500.00 22,500.00
C Peralatan:
B Bahan:
Pipa Seamless SCH 40 dia. 1" D30 m 1.000 29,166.67 29,166.67
C Peralatan:
B Bahan:
Pipa Seamless SCH 40 dia. 1-1/4" D31 m 1.000 39,166.67 39,166.67
C Peralatan:
B Bahan:
Pipa Seamless SCH 40 dia. 1-1/2" D32 m 1.000 44,166.67 44,166.67
C Peralatan:
B Bahan:
Pipa Seamless SCH 40 dia. 2" D33 m 1.000 56,666.67 56,666.67
C Peralatan:
B Bahan:
Pipa Seamless SCH 40 dia. 2-1/2" A34 m 1.000 77,500.00 77,500.00
C Peralatan:
B Bahan:
Pipa Seamless SCH 40 dia. 3" A35 m 1.000 101,666.67 101,666.67
C Peralatan:
B Bahan:
Pipa Seamless SCH 40 dia. 3-1/2" D36 m 1.000 120,833.33 120,833.33
C Peralatan:
B Bahan:
Pipa Seamless SCH 40 dia. 4" D37 m 1.000 142,500.00 142,500.00
C Peralatan:
B Bahan:
Pipa Seamless SCH 40 dia. 5" D38 m 1.000 192,500.00 192,500.00
C Peralatan:
B Bahan:
Pipa Seamless SCH 40 dia. 6" D39 m 1.000 258,333.33 258,333.33
C Peralatan:
B Bahan:
Pipa Seamless SCH 40 dia. 8" D40 m 1.000 375,833.33 375,833.33
C Peralatan:
B Bahan:
Pipa Seamless SCH 40 dia. 8" D40 m 1.000 750,000.00 750,000.00
C Peralatan:
B Bahan:
Karet Dilatasi A35 m³ 1.020 265,000.00 270,300.00
Alat bantu m³ 0.050 15,000.00 750.00
C Peralatan:
B Bahan:
Mobilisasi H01 ls 1.000 10,500.00 10,500.00
Main Truss C-75-75 H02 m' 2.800 13,500.00 37,800.00
Roof Bottom/Reng 33-0.45 H03 m' 5.100 7,500.00 38,250.00
Self Drilling Screw dia. 6 x 20 mm (Truss Screw) H04 bh 25.000 500.00 12,500.00
Self Drilling Screw dia. 4 x 16 mm (Roof Bottom Screw) H05 bh 35.000 550.00 19,250.00
Dynabol dia 12 x 120 mm H06 bh 1.000 1,200.00 1,200.00
C Peralatan:
B Bahan:
Atap Bitumen Bergelombang Monolayer 3 mm H11 lbr 0.650 195,000.00 126,750.00
Paku atau Sekrup D14 bh 16.000 500.00 8,000.00
Sealent G30 m' 4.000 8,000.00 32,000.00
C Peralatan:
1 M2 PENUTUP POLYCARBONAT
A TENAGA:
Pekerja L.01 OH 0.5000 85,000.00 42,500.00
Tukang L.02 OH 0.2000 95,000.00 19,000.00
Kepala Tukang L.03 OH 0.1000 95,000.00 9,500.00
Mandor L.04 OH 0.1000 110,000.00 11,000.00
B Bahan:
POLYCARBONAT M2 1.010 100,000.00 101,000.00
C Peralatan:
ALAT BANTU LS 1.000 5,000.00 5,000.00
D Jumlah (A+B+C) 106,000.00 82,000.00 188,000.00
E Over Head & Profit, 10% x D 56,400.00
0.30 x D
F Jumlah (D+E) 244,400.00
G Dibulatkan 244,400.00
B Bahan:
Genteng Aspal H08 lbr 2.000 95,000.00 190,000.00
Paku Biasa ½" - 1" D13 kg 0.050 18,000.00 900.00
C Peralatan:
C Peralatan:
B Bahan:
Atap Zincalume m² 1.000 80,000.00 80,000.00
Glasswool m² 1.000 15,000.00 15,000.00
Allumunium Foil m² 1.050 20,000.00 21,000.00
Roofmesh m² 1.000 7,500.00 7,500.00
Paku Pengikat / Skrup kg 0.175 500.00 87.50
Sealant kg 0.065 8,000.00 520.00
C Peralatan:
B Bahan:
Atap Zincalume m² 0.350 80,000.00 28,000.00
Paku Pengikat / Skrup kg 0.155 500.00 77.50
Sealant kg 0.025 8,000.00 200.00
C Peralatan:
B Bahan:
Atap Zincalume m² 0.350 110,000.00 38,500.00
Paku Pengikat / Skrup kg 0.155 500.00 77.50
Sealant kg 0.025 8,000.00 200.00
C Peralatan:
B Bahan:
Allumunium Foil m² 1.000 20,000.00 20,000.00
Roofmesh m² 1.000 7,500.00 7,500.00
C Peralatan:
B Bahan:
kaca m2 1.100 690,000.00 759,000.00
Skrup bh 4.000 500.00 2,000.00
C Peralatan:
B Bahan:
ASBES m² 1.100 100,000.00 110,000.00
C Peralatan:
Alat Bantu ls 1.000 5,000.00
B Bahan:
Talang Metal Zincallum t= 0,8 mm m² 1.050 35,900.00 37,695.00
kg 3.750 32,400.00 121,500.00
C Peralatan:
B Bahan:
Pelat Baja (0.8 mm) kg 6.280 11,500.00 72,220.00
Paku Pengikat / Skrup kg 0.175 195,000.00 34,125.00
Sealant kg 0.065 15,000.00 975.00
C Peralatan:
B Bahan:
Bata merah A12 bh 70.000 550.00 38,500.00
Semen portlan A10 kg 9.680 1,100.00 10,648.00
Pasir pasang A04 m³ 0.045 165,000.00 7,425.00
C Peralatan:
B Bahan:
Bata Ringan 600x200x7.5 A13 m³ 0.079 525,000.00 41,354.09
Dry Mix/Semen Instan Perekat Pasangan Bata, @40kg A25 zak 0.066 85,000.00 5,578.13
C Peralatan:
B Bahan:
Roster Beton 20 x 20 bh 36.000 10,000.00 360,000.00
Semen Portland Kg 11.000 1,100.00 12,100.00
Pasir Pasang m3 0.300 165,000.00 49,500.00
C Peralatan:
B Bahan:
Besi profil D08 kg 1.150 11,500.00 13,225.00
C Peralatan:
PEMASANGAN 1 M2 ROLLING DOOR ALLUMUNIUM (A. 4.2.1.10 HSP BIDANG KARYA CIPTA BALITBANG PU)
A TENAGA:
Pekerja L.01 OH 1.0000 85,000.00 85,000.00
Tukang Khusus Allumunium L.02 OH 1.0000 95,000.00 95,000.00
Kepala Tukang L.03 OH 0.1000 95,000.00 9,500.00
Mandor L.04 OH 0.0500 110,000.00 5,500.00
B Bahan:
Rolling door allumunium G19 m² 1.000 249,000.00 249,000.00
C Peralatan:
PEMASANGAN 1 M2 KUSEN PINTU ALLUMUNIUM (A. 4.2.1.11 HSP BIDANG KARYA CIPTA BALITBANG PU)
A TENAGA:
Pekerja L.01 OH 1.0000 85,000.00 85,000.00
Tukang Khusus Allumunium L.02 OH 1.0000 95,000.00 95,000.00
Kepala Tukang L.03 OH 0.1000 95,000.00 9,500.00
Mandor L.04 OH 0.0500 110,000.00 5,500.00
B Bahan:
Profil Allumunium D10 m 1.100 85,000.00 93,500.00
Skrup fixer D14 bh 2.000 500.00 1,000.00
Rolling door allumunium G19 tube 0.060 249,000.00 14,940.00
C Peralatan:
B Bahan:
Rangka Hollow Galvalum 30.30.2 mm D09 m' 3.500 10,000.00 35,000.00
Assesoris (perkuatan, las dll) ls 10%x rangka 3,500.00 3,500.00
C Peralatan:
B Bahan:
Rangka metal hollow 40.40.2 mm D09 m' 4.000 11,667.00 46,668.00
Assesoris (perkuatan, las dll) ls 10%x rangka 4,666.80 4,666.80
C Peralatan:
B Bahan:
Rangka metal hollow 50x100x1,6 D09 m' 4.000 61,000.00 244,000.00
Assesoris (perkuatan, las dll) ls 10%x rangka 24,400.00 24,400.00
C Peralatan:
B Bahan:
Rangka metal hollow 40x40x1,6 D09 m' 1.000 11,667.00 11,667.00
Rangka metal hollow 50x100x1,6 D09 m' 1.000 61,000.00 61,000.00
Assesoris (perkuatan, las dll) ls 10%x rangka 1,166.70 1,166.70
C Peralatan:
B Bahan:
Kayu Papan 3/20 cm klas ll / klas lll m³ 0.020 2,200,000.00 44,000.00
paku bh 10.000 18,000.00 18,000.00
C Peralatan:
PEMASANGAN 1 M2 RANGKA BESI HOLLOW 1X40.40.2 MM, MODUL 60X120 CM, DINDING PARTISI (A. 4.2.1.20 HSP BIDANG KARYA CIPTA BALITBANG PU)
A TENAGA:
Pekerja L.01 OH 0.2500 85,000.00 21,250.00
Tukang Besi L.02 OH 0.2500 95,000.00 23,750.00
Kepala Tukang L.03 OH 0.0250 95,000.00 2,375.00
Mandor L.04 OH 0.0130 110,000.00 1,430.00
B Bahan:
Rangka metal hollow 40.40.2 mm D09 m' 3.500 11,667.00 40,834.50
Assesoris (perkuatan, las dll) ls 10%x rangka 4,083.45 4,083.45
C Peralatan:
C Peralatan:
VI PEKERJAAN PLESTERAN
PEMASANGAN 1 M2 PLESTERAN 1SP:5PP TEBAL 15 MM (A. 4.4.2.5 HSP BIDANG KARYA CIPTA BALITBANG PU)
A TENAGA:
Pekerja L.01 OH 0.3000 67,200.00 20,160.00
Tukang Batu L.02 OH 0.1500 95,000.00 14,250.00
Kepala Tukang L.03 OH 0.0150 95,000.00 1,425.00
Mandor L.04 OH 0.0150 110,000.00 1,650.00
B Bahan:
Portland Cement A10 kg 5.184 1,100.00 5,702.40
Pasir Pasang A04 m³ 0.026 165,000.00 4,290.00
C Peralatan:
B Bahan:
Portland Cement A10 kg 18.650 1,100.00 20,515.00
Pasir Pasang A04 m³ 0.035 165,000.00 5,775.00
C Peralatan:
PEMASANGAN 1 M2 PLESTERAN SKONING 1SP:3PP TEBAL 10 MM (A. 4.4.2.20 HSP BIDANG KARYA CIPTA BALITBANG PU)
A TENAGA:
Pekerja L.01 OH 0.0800 67,200.00 5,376.00
Tukang Batu L.02 OH 0.4000 95,000.00 38,000.00
Kepala Tukang L.03 OH 0.0400 95,000.00 3,800.00
Mandor L.04 OH 0.0040 110,000.00 440.00
B Bahan:
Portland Cement A10 kg 0.500 1,100.00 550.00
Pasir Pasang A04 m³ 0.013 165,000.00 2,145.00
C Peralatan:
PEMASANGAN 1 M2 ACIAN (A. 4.4.2.26 HSP BIDANG KARYA CIPTA BALITBANG PU)
A TENAGA:
Pekerja L.01 OH 0.2000 67,200.00 13,440.00
Tukang Batu L.02 OH 0.1000 95,000.00 9,500.00
Kepala Tukang L.03 OH 0.0100 95,000.00 950.00
Mandor L.04 OH 0.0100 110,000.00 1,100.00
B Bahan:
Portland Cement A10 kg 3.250 1,100.00 3,575.00
C Peralatan:
B Bahan:
Besi Hollow Galvanis 40x40mm, t = 0,4 mm D09 m' 0.028 11,667.00 326.68
Assesoris (Perkuatan, las, dll) ls 0.150 15,000.00 2,250.00
Multiplek 9 mm, uk. 1,20 x 2,40 B06 lbr 0.364 120,000.00 43,680.00
HPL B11 lbr 0.364 105,000.00 38,220.00
C Peralatan:
1 M2 PASANG PARTISI GYPSUM BOARD TEBAL 9 MM, RANGKA HOLLOW 4 X 4, TEBAL 0,5 MM
A TENAGA:
Pekerja L.01 OH 0.2400 67,200.00 16,128.00
Tukang Kayu L.02 OH 0.3700 95,000.00 35,150.00
Kepala Tukang L.03 OH 0.0370 95,000.00 3,515.00
Mandor L.04 OH 0.0120 110,000.00 1,320.00
B Bahan:
Rangka Hollow 4 x 4 m' 4.500 4,166.00 18,747.00
Gypsum Board 9mm lbr 0.720 65,000.00 46,800.00
Kasa Gypsum roll 0.050 10,000.00 500.00
Tepung Gypsum (Coumpound) kg 0.450 8,000.00 3,600.00
Alkasit ( Pembantu Semen ) kg 0.003 20,000.00 60.00
Paku Skrup Gypsum kg 0.150 20,000.00 3,000.00
C Peralatan:
B Bahan:
Rangka Baja ringan C75 m' 2.000 13,500.00 27,000.00
Besi Hollow 20x20x0,3mm Rangka Plafon Galvalum m' 2.000 3,333.00 6,666.00
Gypsum Board 9mm m² 1.100 65,000.00 71,500.00
Paku Gypsum kg 0.300 20,000.00 6,000.00
C Peralatan:
B Bahan:
Dry Mix/Semen Instan Pelester, @40kg A26 zak 0.479 85,000.00 40,715.00
C Peralatan:
B Bahan:
Dry Mix/Semen Instan Acian, @40kg A27 zak 0.058 85,000.00 4,887.50
C Peralatan:
B Bahan:
Granit Tile 60 x 60 Polished J08 m² 1.050 250,000.00 262,500.00
PCC A10 kg 9.800 1,100.00 10,780.00
Pasir Pasang A04 m³ 0.045 165,000.00 7,425.00
Semen Warna A29 kg 1.300 10,000.00 13,000.00
C Peralatan:
B Bahan:
Granit Tile 60 x 60 Unpolished J08 m² 1.050 275,000.00 288,750.00
PCC A10 kg 9.800 1,100.00 10,780.00
Pasir Pasang A04 m³ 0.045 165,000.00 7,425.00
Semen Warna A29 kg 1.300 10,000.00 13,000.00
C Peralatan:
B Bahan:
Granit Tile 30x30 Unpolished J08 m² 1.050 190,000.00 199,500.00
PCC A10 kg 9.800 1,100.00 10,780.00
Pasir Pasang A04 m³ 0.045 165,000.00 7,425.00
Semen Warna A29 kg 1.300 10,000.00 13,000.00
C Peralatan:
B Bahan:
Granite Tile 25 X 75 Polished J10 m² 1.100 125,000.00 137,500.00
PCC A10 kg 9.300 1,100.00 10,230.00
Pasir Pasang A04 m³ 0.018 165,000.00 2,970.00
Semen Warna A29 kg 1.940 10,000.00 19,400.00
C Peralatan:
B Bahan:
Keramik Anti Slip uk. 20 x 20 J02 m² 1.050 30,000.00 31,500.00
PCC A10 kg 9.800 1,100.00 10,780.00
Pasir Pasang A04 m³ 0.045 165,000.00 7,425.00
Semen Warna A29 kg 1.300 10,000.00 13,000.00
C Peralatan:
D Jumlah (A+B+C) 62,705.00 31,237.50 93,942.50
E Over Head & Profit, 10% x D 28,182.75
0.30 x D
F Jumlah (D+E) 122,125.25
G Dibulatkan 122,100.00
B Bahan:
Keramik Anti Slip uk. 25 x 25 J02 m² 1.050 50,000.00 52,500.00
PCC A10 kg 9.800 1,100.00 10,780.00
Pasir Pasang A04 m³ 0.045 165,000.00 7,425.00
Semen Warna A29 kg 1.300 10,000.00 13,000.00
C Peralatan:
B Bahan:
Keramik uk. 20 x 20 J06 m² 1.050 35,000.00 36,750.00
PCC A10 kg 9.800 1,100.00 10,780.00
Pasir Pasang A04 m³ 0.045 165,000.00 7,425.00
Semen Warna A29 kg 1.300 10,000.00 13,000.00
C Peralatan:
B Bahan:
Keramik uk. 30 x 30 J03 m² 1.050 34,000.00 35,700.00
PCC A10 kg 9.800 1,100.00 10,780.00
Pasir Pasang A04 m³ 0.045 165,000.00 7,425.00
Semen Warna A29 kg 1.300 10,000.00 13,000.00
C Peralatan:
B Bahan:
Keramik uk. 30 x 30 J03 m² 1.050 38,950.00 40,897.50
PCC A10 kg 9.800 1,100.00 10,780.00
Pasir Pasang A04 m³ 0.045 165,000.00 7,425.00
Semen Warna A29 kg 1.300 10,000.00 13,000.00
C Peralatan:
B Bahan:
Keramik uk. 30 x 30 J03 m² 1.050 45,000.00 47,250.00
PCC A10 kg 9.800 1,100.00 10,780.00
Pasir Pasang A04 m³ 0.045 165,000.00 7,425.00
Semen Warna A29 kg 1.300 10,000.00 13,000.00
C Peralatan:
B Bahan:
Keramik uk. 40 x 40 J04 m² 1.050 41,500.00 43,575.00
PCC A10 kg 9.800 1,100.00 10,780.00
Pasir Pasang A04 m³ 0.045 165,000.00 7,425.00
Semen Warna A29 kg 1.300 10,000.00 13,000.00
C Peralatan:
B Bahan:
Keramik uk. 20 x 40 J05 m² 1.050 35,500.00 37,275.00
PCC A10 kg 9.800 1,100.00 10,780.00
Pasir Pasang A04 m³ 0.045 165,000.00 7,425.00
Semen Warna A29 kg 1.300 10,000.00 13,000.00
C Peralatan:
B Bahan:
Keramik uk. 25 x 45 J05 m² 1.050 80,000.00 84,000.00
PCC A10 kg 9.800 1,100.00 10,780.00
Pasir Pasang A04 m³ 0.045 165,000.00 7,425.00
Semen Warna A29 kg 1.300 10,000.00 13,000.00
C Peralatan:
B Bahan:
PLIN KRAMIK 10 X 40 CM J07 m² 1.950 38,500.00 75,075.00
PCC A10 kg 1.140 1,100.00 1,254.00
Pasir Pasang A04 m³ 0.100 165,000.00 16,500.00
Semen Warna A29 kg 0.003 10,000.00 30.00
C Peralatan:
B Bahan:
Stepnoshing J11 m² 3.500 55,000.00 192,500.00
PCC A10 kg 1.650 1,100.00 1,815.00
Pasir Pasang A04 m³ 0.032 165,000.00 5,280.00
Semen Warna A29 kg 0.100 10,000.00 1,000.00
C Peralatan:
D Jumlah (A+B+C) 200,595.00 19,955.00 220,550.00
E Over Head & Profit, 10% x D 66,165.00
0.30 x D
F Jumlah (D+E) 286,715.00
G Dibulatkan 286,700.00
1 M2 PASANGAN BATU TEMPEL HITAM
A TENAGA:
Pekerja L.01 OH 0.7000 67,200.00 47,040.00
Tukang Batu L.02 OH 0.3500 95,000.00 33,250.00
Kepala Tukang L.03 OH 0.0350 95,000.00 3,325.00
Mandor L.04 OH 0.0350 110,000.00 3,850.00
B Bahan:
Batu Tempel Hitam J01 m² 1.100 87,400.00 96,140.00
PCC A10 kg 11.750 1,100.00 12,925.00
Pasir Pasang A04 m³ 0.035 165,000.00 5,775.00
C Peralatan:
B Bahan:
besi hollow 40x40 mm D09 m; 2.200 11,667.00 25,667.40
Paku Skrup D14 bh 6.000 500.00 3,000.00
C Peralatan:
B Bahan:
GRC 1200x2400, t= 4 mm I01 lbr 0.364 45,000.00 16,380.00
Paku Skrup D14 kg 0.110 500.00 55.00
Semen Compound I03 kg 0.500 8,000.00 4,000.00
Joint Tape @75 m I04 roll 0.056 10,000.00 560.00
C Peralatan:
B Bahan:
Gypsum Board, t=9 mm I05 lbr 0.364 65,000.00 23,660.00
Paku Skrup D14 kg 0.110 500.00 55.00
Semen Compound I03 kg 0.500 8,000.00 4,000.00
Joint Tape @75 m I04 roll 0.056 10,000.00 560.00
C Peralatan:
1 M1 LIST GYPSUM
A TENAGA:
Pekerja L.01 OH 0.0210 67,200.00 1,411.20
Tukang Batu L.02 OH 0.1250 95,000.00 11,875.00
Kepala Tukang L.03 OH 0.0125 95,000.00 1,187.50
Mandor L.04 OH 0.0125 110,000.00 1,375.00
B Bahan:
List Gypsum I07 m² 1.050 14,200.00 14,910.00
C Peralatan:
B Bahan:
besi hollow 40x40 mm galvalum D09 m' 2.200 4,166.00 9,165.20
besi hollow 20x20 mm galvalum D09 m' 2.200 3,333.00 7,332.60
Paku Skrup D14 bh 6.000 500.00 3,000.00
C Peralatan:
IX PEKERJAAN PENGECATAN
1 M2 PENGECATAN DINDING INTERIOR (Analisa PU A.4.7.1.10)
A TENAGA:
Pekerja L.01 OH 0.0200 67,200.00 1,344.00
Tukang Batu L.02 OH 0.0630 95,000.00 5,985.00
Kepala Tukang L.03 OH 0.0063 95,000.00 598.50
Mandor L.04 OH 0.0025 110,000.00 275.00
B Bahan:
Plamir K09 kg 0.100 12,000.00 1,200.00
Ampelas K13 lbr 0.150 3,200.00 480.00
Cat Dasar K01 kg 0.100 25,000.00 2,500.00
Cat Penutup, 2x K02 kg 0.130 45,000.00 5,850.00
C Peralatan:
Roll Cat K12 bh 0.010 20,000.00 200.00
B Bahan:
Plamir K09 kg 0.100 12,000.00 1,200.00
Ampelas K13 lbr 0.150 3,200.00 480.00
Cat Dasar K01 kg 0.100 25,000.00 2,500.00
Cat Penutup, 2x K03 kg 0.260 50,000.00 13,000.00
C Peralatan:
Roll Cat K12 bh 0.010 20,000.00 200.00
B Bahan:
Plamir K09 kg 0.120 12,000.00 1,440.00
Ampelas K13 lbr 0.150 3,200.00 480.00
Cat Dasar K01 kg 0.100 25,000.00 2,500.00
Cat Penutup, 2x K02 kg 0.280 45,000.00 12,600.00
C Peralatan:
Roll Cat K12 bh 0.010 20,000.00 200.00
B Bahan:
Cat Besi K04 kg 0.100 40,000.00 4,000.00
Terpentin K10 lbr 0.010 10,000.00 100.00
Ampelas K13 lbr 0.100 3,200.00 320.00
Cat Menie K16 kg 0.200 50,000.00 10,000.00
Plamir K09 kg 0.150 12,000.00 1,800.00
Ampelas K13 lbr 0.200 3,200.00 640.00
C Peralatan:
Roll Cat K12 bh 0.010 20,000.00 200.00
1 M2 WATER PROOFING
A TENAGA:
Upah Pasang (B) ls 1.0000 3,500.00 3,500.00
B Bahan:
Water Proofing A23 m² 1.000 35,000.00 35,000.00
C Peralatan:
Alat Bantu (B) ls 1.000 15,000.00 15,000.00
B Bahan:
Vernis k07 ltr 0.150 22,500.00 3,375.00
C Peralatan:
1 M2 PENGECATANGARIS LAPANG
A TENAGA:
Pekerja L.01 OH 0.0200 67,200.00 1,344.00
Tukang Batu L.02 OH 0.0630 95,000.00 5,985.00
Kepala Tukang L.03 OH 0.0063 95,000.00 598.50
Mandor L.04 OH 0.0025 110,000.00 275.00
B Bahan:
Cat Khusus Lapang K05 ltr 0.100 38,500.00 3,850.00
C Peralatan:
Alat Bantu ls 1.000 15,000.00 15,000.00
B Bahan:
Kaca Tempered 12 mm m² 3.982 520,000.00 2,070,432.00
Floor Hinges bh 4.000 1,500,000.00 6,000,000.00
Patch Fitting bh 2.000 1,000,000.00 2,000,000.00
Pull Handle Pintu Kaca set 2.000 950,000.00 1,900,000.00
Lockset Pintu Tempered bh 1.000 600,000.00 600,000.00
C Peralatan:
Alat Bantu ls 1.000 628,521.60 628,521.60 628,521.60
B Bahan:
Hollow 150 x 50 m' 4.900 88,000.00 431,200.00
Daun Pintu Plat Baja 5mm kg 56.324 11,500.00 647,723.13
Sealant m' 1.300 8,000.00 10,400.00
Assesories Penunjanga dan Lain - Lain ls 1.00 272,330.78
C Peralatan:
Alat Bantu ls 1.000 54,466.16 54,466.16 54,466.16
B Bahan:
Kusen Aluminium 4" Sek. Alexindo m' 10.520 110,000.00 1,157,200.00
Daun Pintu Lapis Taekwood Lapis HPL, tebal 4 mm m² 2.513 740,700.00 1,861,527.24
Sealant m' 21.040 8,000.00 168,320.00
List Nat U- Allumunium m' 3.660 10,200.00 37,332.00
Kunci Sek. Dekson set 1.000 195,000.00 195,000.00
Handel Sek. Dekson set 2.000 325,000.00 650,000.00
Engsel Pintu,Stainless Steel 4"x3"x2", bh 6.000 28,000.00 168,000.00
Daun Jendela m2 0.38 600,000.00 225,600.00
Kaca Tempered 12 mm m2 0.41 520,000.00 215,332.00
Patch Fitting unit 1.00 1,000,000.00 1,000,000.00
Pull Handle Pintu Kaca unit 1.00 700,000.00 700,000.00
Lockset Pintu Tempered unit 1.00 600,000.00 600,000.00
C Peralatan:
Alat Bantu ls 1.000 70,845.00 70,845.00 70,845.00
B Bahan:
Kusen Aluminium 4" Sek. Alexindo m' 5.450 110,000.00 599,500.00
Daun Pintu Lapis Spandrel Unit 1.000 750,000.00 750,000.00
Kaca Polos 5 mm m² 0.308 115,000.00 35,362.50
Sealant m' 10.900 8,000.00 87,200.00
Kunci Sek. Dekson set 1.000 195,000.00 195,000.00
Handel Sek. Dekson pcs 2.000 325,000.00 650,000.00
Engsel Pintu,Stainless Steel 4"x3"x2", bh 3.000 28,000.00 84,000.00
C Peralatan:
Alat Bantu ls 1.000 76,550.00 76,550.00 76,550.00
B Bahan:
Kusen Aluminium 4" Sek. Alexindo m' 4.820 110,000.00 530,200.00
Daun Pintu Taekwood Lapis HPL, t= 4mm m² 1.607 740,700.00 1,190,453.04
List Nat U- Allumunium m' 3.260 10,200.00 33,252.00
Sealant m' 9.640 8,000.00 77,120.00
Kunci Sek. Dekson set 1.000 195,000.00 195,000.00
Handel Sek. Dekson set 1.000 325,000.00 325,000.00
Engsel Pintu,Stainless Steel 4"x3"x2", bh 3.000 28,000.00 84,000.00
C Peralatan:
Alat Bantu ls 1.000 70,845.00 70,845.00 70,845.00
B Bahan:
Kusen Aluminium 4" Sek. Alexindo m' 23.860 110,000.00 2,624,600.00
Kaca Polos 10mm m² 11.881 335,000.00 3,980,001.00
Sealant m' 47.720 8,000.00 381,760.00
Lapis Kaca Film m² 11.881 125,000.00 1,485,075.00
C Peralatan:
Alat Bantu ls 1.000 22,650.00 22,650.00 22,650.00
B Bahan:
Kusen Aluminium 4" Sek. Alexindo G02 m' 13.390 110,000.00 1,472,900.00
Kaca Polos 10mm G37 m² 4.264 335,000.00 1,428,574.00
Sealant G30 m' 26.780 8,000.00 214,240.00
Lapis Kaca Film, m² 4.264 125,000.00 533,050.00
C Peralatan:
Alat Bantu ls 1.000 22,650.00 22,650.00 22,650.00
B Bahan:
Kusen Aluminium 4" Sek. Alexindo G02 m' 14.700 110,000.00 1,617,000.00
Kaca Polos 10mm G37 m² 4.489 335,000.00 1,503,748.00
Sealant G30 m' 29.400 8,000.00 235,200.00
Lapis Kaca Film, m² 4.489 125,000.00 561,100.00
C Peralatan:
Alat Bantu ls 1.000 22,650.00 22,650.00 22,650.00
B Bahan:
Kusen Aluminium 4" Sek. Alexindo G02 m' 11.440 110,000.00 1,258,400.00
Kaca Polos 10mm G37 m² 3.862 335,000.00 1,293,904.00
Sealant G30 m' 22.880 8,000.00 183,040.00
Lapis Kaca Film, m² 3.862 125,000.00 482,800.00
C Peralatan:
Alat Bantu ls 1.000 22,650.00 22,650.00 22,650.00
B Bahan:
Kusen Aluminium 4" Sek. Alexindo G02 m' 2.240 110,000.00 246,400.00
Kaca Polos 5mm G37 m² 0.260 115,000.00 29,946.00
Sealant G30 m' 4.480 8,000.00 35,840.00
C Peralatan:
Alat Bantu ls 1.000 11,650.00 11,650.00 11,650.00
B Bahan:
Kusen Aluminium 4" Sek. Alexindo G02 m' 2.840 110,000.00 312,400.00
Plat Strip G37 m' 5.600 17,100.00 95,760.00
Sealant G30 m' 5.680 8,000.00 45,440.00
C Peralatan:
Alat Bantu ls 1.000 6,755.00 6,755.00 6,755.00
B Bahan:
Rangka Kusen Curtain Wall + Kaca Polos 8mm m² 1.100 720,000.00 792,000.00
Pelapis Kaca Film m² 1.000 125,000.00 125,000.00
Assesories dan Alat Bantu ls 1.000 137,550.00 137,550.00
C Peralatan:
B Bahan:
Kusen Aluminium 4" Sek. Alexindo m' 0.028 110,000.00 3,080.00
Kaca Polos 10 mm m² 0.364 335,000.00 121,940.00
Sealent m' 4.000 8,000.00 32,000.00
Assesories dan Alat Bantu ls 1.000 31,255.00 31,255.00
C Peralatan:
B Bahan:
Besi Hollow Galvanis 40x40mm, t = 0,4 mm m' 0.028 11,667.00 326.68
Assesoris (Perkuatan, las, dll) ls 0.150 8,222.67 1,233.40
Multiplek 9 mm, uk. 1,20 x 2,40 lbr 0.364 120,000.00 43,680.00
HPL lbr 0.364 105,000.00 38,220.00
C Peralatan:
B Bahan:
Rangka Metal Cutting Pelat Besi 3mm Finish Powder Cutting m² 1.000 850,000.00 850,000.00
Mobilisasi, Pengadaan dan Accesoris Ls 1.00 85,000.00 85,000.00
C Peralatan:
Alat Bantu ls 1.000 42,500.00 42,500.00 42,500.00
PEMASANGAN 1 M2 PINTU ALLUMUNIUM STRIP LEBAR 8 CM (A. 4.2.1.12 HSP BIDANG KARYA CIPTA BALITBANG PU)
A TENAGA:
Pekerja L01 OH 0.0850 85,000.00 7,225.00
Tukang Khusus Allumunium L02 OH 0.0850 95,000.00 8,075.00
Kepala Tukang L03 OH 0.0085 95,000.00 807.50
Mandor L04 OH 0.0042 110,000.00 462.00
B Bahan:
Profil Allumunium G05 m' 1.000 10,200.00 10,200.00
Allumunium strip G09 m' 1.000 17,100.00 17,100.00
C Peralatan:
B Bahan:
Kaca tebal 3 mm G39 m² 1.100 60,000.00 66,000.00
Sealant G30 kg 0.050 8,000.00 400.00
C Peralatan:
PEMASANGAN 1 M² KACA TEBAL 5 MM (A.4.6.2.16. HSP BIDANG KARYA CITPA BALITBANG PU)
A TENAGA:
Pekerja L01 OH 0.0150 85,000.00 1,275.00
Tukang Kayu L02 OH 0.1500 95,000.00 14,250.00
Kepala Tukang L03 OH 0.0150 95,000.00 1,425.00
Mandor L04 OH 0.0008 110,000.00 88.00
B Bahan:
Kaca tebal 5 mm G37 m² 1.100 17,100.00 18,810.00
Sealant G30 kg 0.050 8,000.00 400.00
C Peralatan:
PEMASANGAN 1 M² KACA CERMIN TEBAL 5 MM (A.4.6.2.20. HSP BIDANG KARYA CITPA BALITBANG PU)
A TENAGA:
Pekerja L01 OH 0.0150 85,000.00 1,275.00
Tukang Kayu L02 OH 0.1500 95,000.00 14,250.00
Kepala Tukang L03 OH 0.0150 95,000.00 1,425.00
Mandor L04 OH 0.0080 110,000.00 880.00
B Bahan:
Kaca Cermin 5 mm G47 m² 1.100 145,000.00 159,500.00
C Peralatan:
PEMASANGAN 1 M² TEAKWOOD RANGKAP LAPIS HPL, RANGKA EXPOSE KAYU KELAS II (A. 4.6.1.12 HSP BIDANG KARYA CIPTA BALITBANG PU)
A TENAGA:
Pekerja L01 OH 0.8500 85,000.00 72,250.00
Tukang Kayu L02 OH 2.5500 95,000.00 242,250.00
Kepala Tukang L03 OH 0.2550 95,000.00 24,225.00
Mandor L04 OH 0.0430 110,000.00 4,730.00
B Bahan:
Papan kayu B02 m³ 0.025 1,500,000.00 37,500.00
Paku 1 - 2,4 cm D12 kg 0.030 13,000.00 390.00
Lem kayu A48 kg 0.800 20,000.00 16,000.00
Teakwood 4 mm 90x 220 cm B08 lbr 1.000 120,000.00 120,000.00
HPL B11 lbr 0.500 105,000.00 52,500.00
C Peralatan:
PEMBUATAN DAN PEMASANGAN 1 M² PINTU PLYWOOD RANGKAP, RANGKA EXPOSE KAYU KELAS I ATAU II (A. 4.6.1.9 HSP BIDANG KARYA CIPTA BALITBANG PU)
A TENAGA:
Pekerja L01 OH 1.0000 85,000.00 85,000.00
Tukang Kayu L02 OH 3.0000 95,000.00 285,000.00
Kepala Tukang L03 OH 0.3000 95,000.00 28,500.00
Mandor L04 OH 0.0500 110,000.00 5,500.00
B Bahan:
Papan kayu B02 m³ 0.026 1,500,000.00 38,400.00
Paku 1 - 2,4 cm D12 kg 0.030 13,000.00 390.00
Lem kayu A48 kg 0.500 20,000.00 10,000.00
Plywoodtebal 4 mm Ukuran (90 x 220) cm B10 lbr 1.000 120,000.00 120,000.00
C Peralatan:
B Bahan:
Papan kayu B02 m³ 0.026 1,500,000.00 38,400.00
Paku 1 - 2,4 cm D13 kg 0.030 18,000.00 540.00
Lem kayu A48 kg 0.500 20,000.00 10,000.00
Multiplek tebal 12 mm B07 lbr 1.000 155,000.00 155,000.00
C Peralatan:
B Bahan:
Bahan Kayu m³ 0.003 1,500,000.00 3,750.00
C Peralatan:
Alat Bantu ls 1.000 10,000.00 10,000.00 10,000.00
B Bahan:
Pengadaan ACP m2 1.050 275,000.00 288,750.00
Rangka Hollow 40/40 Galvanis btg 0.800 115,000.00 92,000.00
Breket Siku /Spigot/stiffener btg 0.267 60,000.00 16,020.00
Paku Sekrup Beton kg 0.080 18,000.00 1,440.00
Sealent tube 0.250 12,800.00 3,200.00
Paku/Skrup kg 0.110 20,000.00 2,200.00
C Peralatan:
Peralatan dan Alat Bantu ls 1.000 25,000.00 25,000.00
B Bahan:
Pengadaan Bahan Acrylic + List Stainless cm 0.800 15,000.00 12,000.00
Lampu LED modul/bh 1.000 18,000.00 18,000.00
C Peralatan:
Peralatan dan Alat Bantu ls 1.000 25,000.00 25,000.00
1 MODUL PEK. PEMASANGAN LED LATTER BOX (HURUF TIMBUL ACRYLIC), TINGGI= 50CM
A TENAGA:
Upah Jasa Pemasangan Dan Instalasi ls 1.0000 300.00 300.00
B Bahan:
Pengadaan Bahan Acrylic + List Stainless cm 0.200 15,000.00 3,000.00
Lampu LED modul/bh 1.000 18,000.00 18,000.00
C Peralatan:
Peralatan dan Alat Bantu ls 1.000 25,000.00 25,000.00
B Bahan:
Pengadaan Bahan Acrylic + List Stainless cm 0.650 15,000.00 9,750.00
Lampu LED modul/bh 1.000 18,000.00 18,000.00
C Peralatan:
Peralatan dan Alat Bantu ls 1.000 25,000.00 25,000.00
B Bahan:
Agregat B A09 jam 1.259 355,000.00 446,803.00
C Peralatan:
Wheel Loader F11 jam 0.007 279,287.00 1,982.94
Dump Truck F14 jam 0.336 200,000.00 67,100.00
Motor Grader F08 jam 0.028 289,993.00 8,148.80
Tandem Roler F09 jam 0.011 123,074.00 1,316.89
Truck Tangki Air F13 jam 0.014 143,187.00 2,018.94
Peralatan dan Alat Bantu ls 1.000 5,000.00 5,000.00
B Bahan:
Agregat A A08 jam 1.259 325,000.00 409,045.00
C Peralatan:
Wheel Loader F11 jam 0.007 279,287.00 1,982.94
Dump Truck F14 jam 0.336 200,000.00 67,100.00
Motor Grader F08 jam 0.028 289,993.00 8,148.80
Tandem Roler F09 jam 0.011 123,074.00 1,316.89
Truck Tangki Air F13 jam 0.014 143,187.00 2,018.94
Peralatan dan Alat Bantu ls 1.000 5,000.00 5,000.00
B Bahan:
Aspal C06 kg 0.690 9,500.00 6,555.00
Karosene C05 ltr 0.371 15,700.00 5,821.56
C Peralatan:
Asp Distributor F24 jam 0.000 395,000.00 79.00
Compressor F26 jam 0.000 65,963.00 13.19
B Bahan:
Hotmix C07 kg 0.069 1,300,000.00 89,700.00
Alat Bantu ltr 0.050 5,000.00 250.00
C Peralatan:
Asphalt Finisher F23 jam 0.003 119,389.00 322.35
Tandem Roller F09 jam 0.003 123,074.00 393.84
P. Tyre Roller F09 jam 0.001 123,074.00 61.54
B Bahan:
Duo HT 4 AGR/ F C 180 Mecano A24 m² 1.000 150,000.00 150,000.00
Fastener + Mecano Plate D15 pcs 3.000 12,000.00 36,000.00
Termination Profile D16 pcs 0.167 55,000.00 9,185.00
C Peralatan:
B Bahan:
Kansteen Jalan 600x150x300 A36 bh 1.660 70,000.00 116,200.00
Semen Portland A10 kg 0.500 1,500.00 750.00
Pasir Pasang A04 m³ 0.012 220,000.00 2,640.00
Alat Bantu ls 0.050 5,000.00 250.00
C Peralatan:
B Bahan:
Kansteen Paving Blok uk. 400x60x150 A37 bh 1.660 18,000.00 29,880.00
Semen Portland A10 kg 0.500 1,500.00 750.00
Pasir Pasang A04 m³ 0.012 220,000.00 2,640.00
Alat Bantu ls 0.050 5,000.00 250.00
C Peralatan:
B Bahan:
Kansteen Jepit A38 bh 2.500 52,500.00 131,250.00
Semen Portland A10 kg 0.500 1,500.00 750.00
Pasir Pasang A04 m³ 0.012 220,000.00 2,640.00
Alat Bantu ls 0.050 70,000.00 3,500.00
C Peralatan:
B Bahan:
Kansteen Type DKI bh 1.660 50,000.00 83,000.00
Semen 50 kg zak 0.120 1,100.00 132.00
Pasir Pasang m³ 0.008 220,000.00 1,760.00
B Bahan:
Kansteen Type Taman bh 1.660 45,000.00 74,700.00
Semen 50 kg zak 0.120 1,100.00 132.00
Pasir Pasang m³ 0.008 220,000.00 1,760.00
B Bahan:
Paving Blok Natural 8 cm A10 m² 1.010 108,000.00 109,080.00
Pasir Pasang A04 m³ 0.100 220,000.00 22,000.00
B Bahan:
Paving Blok Warna 8 cm A10 m² 1.010 134,000.00 135,340.00
Pasir Pasang A04 m³ 0.100 220,000.00 22,000.00
B Bahan:
U-DITCH 30X50X120 A40 bh 0.833 450,000.00 374,850.00
Urugan Pasir A03 m³ 0.020 150,000.00 3,000.00
Alat Bantu ls 1.000 5,000.00 5,000.00
C Peralatan:
B Bahan:
U-DITCH 60X80X120 A41 bh 0.833 950,000.00 791,350.00
Urugan Pasir A03 m³ 0.020 150,000.00 3,000.00
Alat Bantu ls 1.000 5,000.00 5,000.00
C Peralatan:
B Bahan:
U-DITCH 120X120X120 A42 bh 0.833 2,150,000.00 1,790,950.00
Urugan Pasir A03 m³ 0.030 150,000.00 4,500.00
Alat Bantu ls 1.000 5,000.00 5,000.00
C Peralatan:
B Bahan:
COVER U-DITCH LD 30 A43 bh 1.667 150,000.00 250,005.00
Alat Bantu ls 1.000 5,000.00 5,000.00
C Peralatan:
B Bahan:
COVER U-DITCH LD 60 A44 bh 1.667 229,900.00 383,243.30
Alat Bantu ls 1.000 5,000.00 5,000.00
C Peralatan:
B Bahan:
COVER U-DITCH LD 120 A45 bh 1.667 650,000.00 1,083,550.00
Alat Bantu ls 1.000 5,000.00 5,000.00
C Peralatan:
B Bahan:
Box Culvert 200 x 200 x 100 A46 bh 1.667 7,000,000.00 11,666,900.00
Lantai Kerja K- 225 m³ 0.016 1,161,600.00 18,585.60
Urugan Pasir A03 m132 0.016 150,000.00 2,400.00
Alat Bantu ls 1.000 5,000.00 5,000.00
C Peralatan:
B Bahan:
Galian Tanah m³ 0.220 85,900.00 18,898.00
Graffel U 30 cm A31 m' 1.100 50,000.00 55,000.00
Bata Merah A12 bh 92.000 550.00 50,600.00
PCC A10 kg 10.300 1,100.00 11,330.00
PP A04 m³ 0.061 165,000.00 10,065.00
PU A03 m² 0.069 150,000.00 10,350.00
C Peralatan:
B Bahan:
Buis Beton 1/2 Lingkaran Dia. 40 cm A32 bh 1.000 90,000.00 90,000.00
C Peralatan:
Peralatan ls 1.000 25,000.00 25,000.00
B Bahan:
Baja Profil UNP 100X50X5 kg 4.494 11,500.00 51,681.00
Besi Beton BJTP U24 Dia. 12" kg 0.162 9,500.00 1,539.00
C Peralatan:
Peralatan ls 1.000 2,100.00 2,100.00
B Bahan:
Karet Dilatasi A38 m 1.020 265,000.00 270,300.00
Alat bantu ls 0.050 27,030.00 1,351.50
C Peralatan:
B Bahan:
Pipa Stainless steel 4 " D33 m 1.150 142,500.00 163,875.00
Material Pendukung Lainnya ls 1.000 16,387.50 16,387.50
C Peralatan:
B Bahan:
Huruf Acyrilc (PASAR INPRES) bh 11.000 56,870.00 625,570.00
Huruf Acyrilc (KABUPATEN SUMEDANG) bh 17.000 88,479.05 1,504,143.85
Logo Akrilik Termasuk Finsihing unit 2.000 500,000.00 1,000,000.00
C Peralatan:
Upah Tenaga dan Alat Bantu ls 1.000 15,648.57 15,648.57
B Bahan:
Ketapang Kencana L02 phn 1.000 5,000.00 5,000.00
C Peralatan:
B Bahan:
Ketapang Kencana L04 phn 1.000 25,000.00 25,000.00
C Peralatan:
B Bahan:
dolken /bambu btg 1.500 125,000.00 187,500.00
Tali m 0.240 55,575.00 13,338.00
C Peralatan:
B Bahan:
Rumput Gajah Mini L04 m² 1.050 25,000.00 26,250.00
Tanah Humus L01 m³ 0.069 50,000.00 3,450.00
Lot 0.05 15,000.00 750.00
C Peralatan:
B Bahan:
Rain Gun Type SR 3003 Merk Rain Bird L06 pcs 1.000 28,500,000.00 28,500,000.00
Tiang Rain Gun L07 bh 0.069 3,750,000.00 258,750.00
Aksesoris Lot 0.035 28,500,000.00 997,500.00
C Peralatan:
D Jumlah (A+B+C) 29,756,250.00 51,100.00 29,807,350.00
E Over Head & Profit, 10% x D 0.30 x D 8,942,205.00
F Jumlah (D+E) 38,749,555.00
G Dibulatkan 38,749,500.00
B Bahan:
Quick Coupling 2" L08 pcs 1.000 3,500,000.00 3,500,000.00
Gate Valve 2" Kitz Kuningan L09 bh 0.069 550,000.00 37,950.00
Aksesoris Lot 0.035 3,500,000.00 122,500.00
C Peralatan:
B Bahan:
Pipa Gip dia. 2" L10 bh 1.000 2,500,000.00 2,500,000.00
Aksesoris Lot 0.035 2,500,000.00 87,500.00
C Peralatan:
B Bahan:
Pipa Gip dia. 4" L11 bh 1.000 3,250,000.00 3,250,000.00
Aksesoris Lot 0.035 3,250,000.00 113,750.00
C Peralatan:
B Bahan:
Pompa Sentrifugal End Section L12 bh 1.000 70,500,000.00 70,500,000.00
Aksesoris ls 1.000 3,525,000.00 3,525,000.00
C Peralatan:
B Bahan:
Panel Control L13 bh 1.000 18,000,000.00 18,000,000.00
Aksesoris ls 1.000 900,000.00 900,000.00
C Peralatan:
B Bahan:
Metal Dek L14 bh 1.000 125,000.00 125,000.00
Kaso btg 1.000 21,000.00 21,000.00
Paku kg 0.02 13,000.00 260.00
Kawat kg 0.48 15,000.00 7,200.00
. .
C Peralatan:
1 KG BAJA CANAL C
A TENAGA:
Pekerja L01 OH 0.1100 85,000.00 9,350.00
Tukang L02 OH 0.1100 95,000.00 10,450.00
Kepala Tukang L03 OH 0.0110 95,000.00 1,045.00
Mandor L04 OH 0.0010 110,000.00 110.00
B Bahan:
Baja Canal L14 bh 1.050 20,000.00 21,000.00
kawat las % 0.050 15,000.00 750.00
Oksigen 1.000 300.00 300.00
C Peralatan:
Alat Bantu Ls 1.000 400.00 400.00
D Jumlah (A+B+C) 22,450.00 20,955.00 43,405.00
E Over Head & Profit, 10% x D 0.30 x D 13,021.50
F Jumlah (D+E) 56,426.50
G Dibulatkan 56,400.00
B Bahan:
Pressure Tank Kap 1000 lt @ 10 Bar -ACC L14 bh 1.000 5,000.00 5,000.00
Perlengkapan/Aksesories % 0.035 175.00 6.13
C Peralatan:
B Bahan:
Baja Canal L14 bh 1.050 16,000.00 16,800.00
kawat las % 0.050 15,000.00 750.00
Oksigen 1.000 300.00 300.00
C Peralatan:
Alat Bantu Ls 1.000 400.00 400.00
D Jumlah (A+B+C) 18,250.00 20,955.00 39,205.00
E Over Head & Profit, 10% x D 0.30 x D 11,761.50
F Jumlah (D+E) 50,966.50
G Dibulatkan 50,900.00
1 M Tali Air
A TENAGA:
Pekerja L01 OH 0.1100 85,000.00 9,350.00
Tukang L02 OH 0.1100 95,000.00 10,450.00
Kepala Tukang L03 OH 0.0110 95,000.00 1,045.00
Mandor L04 OH 0.0010 110,000.00 110.00
B Bahan:
Tali Air L14 m 1.050 23,000.00 24,150.00
C Peralatan:
Alat Bantu Ls 1.000 400.00 400.00
D Jumlah (A+B+C) 24,550.00 20,955.00 45,505.00
E Over Head & Profit, 10% x D 0.30 x D 13,651.50
F Jumlah (D+E) 59,156.50
G Dibulatkan 59,100.00
1 Unit Bak Kontrol
A TENAGA:
Pekerja L01 OH 2.6100 85,000.00 221,850.00
Tukang L02 OH 0.7200 95,000.00 68,400.00
Kepala Tukang L03 OH 0.0720 95,000.00 6,840.00
Mandor L04 OH 0.1080 110,000.00 11,880.00
B Bahan:
Bata L14 bh 186.000 550.00 102,300.00
Semen PC kg 114.000 1,500.00 171,000.00
Pasir Pasang m3 0.184 165,000.00 30,360.00
Batu Becah 2/3 m3 0.033 185,000.00 6,105.00
Besi kg 15.000 11,500.00 172,500.00
Pasir Beton m3 0.120 185,000.00
C Peralatan:
Alat Bantu Ls 1.000 400.00 400.00
D Jumlah (A+B+C) 482,665.00 308,970.00 791,635.00
E Over Head & Profit, 10% x D 0.30 x D 237,490.50
F Jumlah (D+E) 1,029,125.50
G Dibulatkan 1,029,100.00
Jasa
1 2 4
IV PEKERJAAN ARSITEKTUR
IV.1 PEK. PAS. DINDING DAN PELAPISAN DINDING
1 Pek. Pas. Dinding Bata 136.655
Bata merah 70.000 9,565.850 bh
Semen portlan 9.680 1,322.820 kg
Pasir pasang 0.045 6.149 m³
2 Pek. Pas. Plesteran Dinding 273.310
Portland Cement 5.184 1,416.839 kg
Pasir Pasang 0.026 7.106 m³
3 Pek. Pas. Acian Dinding 273.310
Portland Cement 3.250 888.258 kg
V PEKERJAAN ATAP
V.1 ATAP RUMAH
1 Pekerjaan Konstruksi Atap Baja Ringan (Design By Vendor) 58.100
Main Truss C-75-75 2.800 162.680 m'
Roof Bottom/Reng 33-0.45 5.100 296.310 m'
Self Drilling Screw dia. 6 x 20 mm (Truss Screw) 25.000 1,452.500 bh
Self Drilling Screw dia. 4 x 16 mm (Roof Bottom Screw) 35.000 2,033.500 bh
Dynabol dia 12 x 120 mm 1.000 58.100 bh
2 Pekerjaan Penutup Asbes Cap Gajah 27.900
3 Pekerjaan Penutup Kaca Tempered 15mm 25.650
4 Pekerjaan Talang 20.600
Alumunium Plat 1.050 21.630 m'
Paku Skrup 1 cm - 2.5 cm 0.015 0.309 kg
Main Truss 0.019 0.391 m³
V CANOPY
1 Rangka Hollow 30.600
Rangka metal hollow 50x100x1,6 4.000 122.400 m'
2 Pipa Besi 28.000
3 Pekerjaan Penutup Kaca Tempered 15mm 10.710
4 Pekerjaan Penutup Asbes Cap Gajah Polycarbonat 19.890
VI PEKERJAAN PLUMBING
g Panel listrik