RENCANA ANGGARAN BIAYA

BAHAN MATERIAL DAN UPAH


PEKERJAAN : RABAT BETON JUT KEDONDONG
LOKASI : DUSUN KEDONDONG DESA NGAMPEL
KEC.BALONGPANGGANG KAB.GRESIK

NO BAHAN / MATERIAL VOL SAT HARSAT JUMLAH

I PEKERJAAN PERSIAPAN

1 Sirtu 46.000 m3 Rp 300,000.00 Rp 13,800,000.00

2 Kayu Bagesting 3.000 m2 Rp 3,000,000.00 Rp 9,000,000.00

3 Minyak Bagesting 8.000 Lt Rp 15,000.00 Rp 120,000.00

4 Paku 78.000 kg Rp 23,000.00 Rp 1,794,000.00

SUB JUMLAH Rp 24,714,000.00

II PEKERJAAN RABAT

5 Plastik Polythene 204.000 m2 Rp 3,500.00 Rp 714,000.00

6 Beton K-300 60.000 m3 Rp 825,000.00 Rp 49,500,000.00

7 Wermes M8 89.000 m2 Rp 60,000.00 Rp 5,340,000.00

8 Besi Polos 100.000 kg Rp 8,000.00 Rp 800,000.00

9 Kawat Bendrat 54.000 kg Rp 20,000.00 Rp 1,080,000.00

SUB JUMLAH Rp 57,434,000.00

III UPAH

10 Pekerja 800.000 oh Rp 110,000 Rp 88,000,000.00

11 Tukang 222.000 oh Rp 130,000 Rp 28,860,000.00

SUB JUMLAH Rp 116,860,000.00

Total Jumlah Rp 199,008,000.00

Belanja Jasa Konsultasi Perencanaan Rp 1,000,000.00

Jumlah Rp 200,008,000.00

Dibulatkan Rp 200,000,000.00

Terbilang : DUA RATUS JUTA RUPIAH