Revisi Cashflow K 1
Revisi Cashflow K 1
Total Biaya
Rp 2,295,000
Rp 91,800,000
Rp 160,650,000
Rp 840,000
Rp 7,700,000
Rp 263,285,000
Total Biaya
Rp 500,000
Rp 20,000,000
Rp 35,000,000
Rp 720,000
Rp 6,600,000
Rp 62,820,000
Total Biaya
Rp 525,000
Rp 21,000,000
Rp 36,750,000
Rp 600,000
Rp 5,500,000
Rp 64,375,000
Rp 487,980,000
Jumlah
Nominal (Rp)
15,000,000
30,000,000
250,000,000
750,000,000
800,000,000
1,845,000,000
Biaya Perijinan
No Jenis Retribusi Jumlah
1 Surat Izin Pendirian Badan Rp 5,000,000
2 Surat Izin Keterangan Domisili Perusahan Rp 5,000,000
3 Surat Izin Gangguan (HO) Rp 5,000,000
4 Surat Tanda Daftar Perusahaan Rp 5,000,000
5 Surat Usaha Perdagangan (SIUP) Rp 5,000,000
6 Surat Izin Tempat Usaha / SITU Rp 5,000,000
7 Surat Setoran Bukan Pajak (SSBP) Rp 5,000,000
8 Surat Izin Terdaftar Nomor Pajak Wajib Pajak Rp 5,000,000
Total Rp 40,000,000
INFRASTRUKTUR
Deskripsi Jumlah Biaya/M2 (Rp) Biaya Total (Rp)
A. Sarana Pendukung Tambang
Pos Keamanan 1 Unit 4 Rp 1,500,000 Rp 6,000,000
Workshop 1 Unit 150 Rp 1,500,000 Rp 225,000,000
Kantor 1 Unit 150 Rp 1,500,000 Rp 225,000,000
Mess 1 Unit 150 Rp 1,500,000 Rp 225,000,000
Kantin & Dapur 1 Unit 50 Rp 1,500,000 Rp 75,000,000
Musholla 1 Unit 50 Rp 1,500,000 Rp 75,000,000
Power Station 1 Unit 100 Rp 1,500,000 Rp 150,000,000
Menara Radio 1 Unit 4 Rp 1,500,000 Rp 6,000,000
Instalasi WP 1 Unit 1 Rp 2,500,000,000 Rp 2,500,000,000
Stockpile 1 Unit 1 Rp 300,000,000 Rp 300,000,000
Stockyard 1 Unit 1 Rp 300,000,000 Rp 300,000,000
Pompa Air 1 Unit 310 Rp 1,500,000 Rp 465,000,000
Sub Total 12 Rp 4,552,000,000
B. Sarana Layanan Tambang
Settling Pond 4 Unit 3000 Rp 1,000,000 Rp 3,000,000,000
Timbunan TPS 1 16 Rp 200,000 Rp 3,200,000
Timbunan B3 1 16 Rp 200,000 Rp 3,200,000
Sub Total 6 Rp 3,006,400,000
C. Infrastruktur
Jalan Tambang 1 7,525.71 Rp 2,000,000 Rp 15,051,420,000
Sub Total 1 Rp 15,051,420,000
TOTAL Rp 22,609,820,000
22,609,820,000
Biaya Pembebasan Lahan
No Area Total
1 Lokasi Penambangan 22,050,000,000
TOTAL 22,050,000,000
22,050,000,000
Biaya Land Clearing
Keterangan Satuan Unit Harga Satuan Total Jam Jumlah Biaya
Sewa Bulldozer Hari 31 Rp 200,000 248 Rp 49,600,000
BBM Bulldozer Liter/Jam 34 Rp 11,150 8432 Rp 94,016,800
BBM Excavator Liter/Jam 30 Rp 11,150 7440 Rp 82,956,000
Total Rp 226,572,800
OB
TOTAL
Tahun Jam Kerja Pelumas Konsumsi/Unit Satuan Harga Satuan Total Biaya /Bulan
Oli Mesin 0.12 Liter/Jam 14,365 1654848
1 960 Oli Transmisi 0.05 Liter/Jam 14,365 689520
Oli Hidrolik 0.14 Liter/Jam 10,000 1344000
Grease 0.016 Pain 990,000 15206400
TOTAL 18894768
Tahun Jam Kerja Pelumas Konsumsi/Unit Satuan Harga Satuan Total Biaya /Bulan
Oli Mesin 0.12 Liter/Jam 14,365 1965132
2 1140 Oli Transmisi 0.05 Liter/Jam 14,365 818805
Oli Hidrolik 0.14 Liter/Jam 10,000 1596000
2 1140
Tahun Jam Kerja Pelumas Konsumsi/Unit Satuan Harga Satuan Total Biaya /Bulan
Oli Mesin 0.12 Liter/Jam 14,365 1654848
Oli Transmisi 0.05 Liter/Jam 14,365 689520
3 960
Oli Hidrolik 0.14 Liter/Jam 10,000 1344000
Grease 0.016 Pain 990,000 15206400
TOTAL 18894768
Tahun Jam Kerja Pelumas Konsumsi/Unit Satuan Harga Satuan Total Biaya /Bulan
Oli Mesin 0.12 Liter/Jam 14,365 1654848
Oli Transmisi 0.05 Liter/Jam 14,365 689520
4 960
Oli Hidrolik 0.14 Liter/Jam 10,000 1344000
Grease 0.016 Pain 990,000 15206400
TOTAL 18894768
OB
Total
Total Biaya
Konsumsi Harga Satuan Total Biaya BBM Per Tahun
BBM per bulan
BBM/Bulan
Rp 66,900,000 Rp 802,800,000
BIAYA OB/TAHUN
Tahun Biaya BBM Biya Pelumas & Grease Total Keseluruhan
1 10,704,000 18894768 Rp 29,598,768
2 16,056,000 22437537 Rp 38,493,537
3 10,704,000 18894768 Rp 29,598,768
4 10,704,000 18894768 Rp 29,598,768
5 18,732,000 33065644 Rp 51,797,644
6 8,028,000 14171076 Rp 22,199,076
Total Rp 201,286,561
Tahun
Aktivitas
2024 2025 2026
Pemuatan & Pengangkutan Bauksit
Excavator Komatsu PC200 Rp 1,700,073,840 Rp 1,802,758,300 Rp 1,911,644,901
DT Hino FM 260 JD Rp 1,252,075,320 Rp 1,327,700,669 Rp 1,407,893,790
TOTAL BIAYA Rp 2,952,149,160 Rp 3,130,458,969 Rp 3,319,538,691
Jam Kerja Efektif/Bulan Total Konsumsi BBM/Bulan Harga Satuan Total Biaya BBM per bulan
200 1000 11,150 Rp 11,150,000
200 12000 11,150 Rp 133,800,000
200 9000 11,150 Rp 100,350,000
AL Rp 245,300,000
Tahun
2027 2028 2029
No Aktivitas
2024
1 Pengupasan OB
Excavator Komatsu PC200 Rp 29,598,768
2 Pemuatan & Pengangkutan Bauksit
Excavator Komatsu PC200 Rp 1,700,073,840
DT Hino FM 260 JD Rp 1,252,075,320
3 Penggerukan Settling Pond
Excavator Komatsu PC200 Rp 272,011,814
TOTAL BIAYA Rp 3,253,759,742
3,253,759,742
Biaya Land Clearing
Keterangan Satuan Unit
Sewa Bulldozer Hari 31
BBM Bulldozer Liter/Jam 34
BBM Excavator Liter/Jam 30
Total
Total
Sub Total
Satuan Jam Kerja Efektif/Bulan Total Konsumsi BBM/Bulan Harga Satuan
Liter/Jam 200 1000 11,150
Liter/Jam 200 12000 11,150
Liter/Jam 200 9000 11,150
TOTAL
Total Rp 272,011,814
272,011,814
Rp 3,480,332,542
3,480,332,542
Total Biaya BBM per bulan Total Biaya BBM Per Tahun
Rp 11,150,000 Rp 133,800,000
Rp 133,800,000 Rp 1,605,600,000
Rp 100,350,000 Rp 1,204,200,000
Rp 245,300,000 Rp 2,943,600,000
2029
Rp 22,199,076
Rp 2,279,378,146
Rp 1,678,723,038
Rp 364,700,503
Rp 4,345,000,762
4,345,000,762
Harga Satuan Total Biaya BBM per bulan Total Biaya BBM Per Tahun
11,150 Rp 21,408,000 Rp 256,896,000
Rp 21,408,000 Rp 256,896,000
Total Konsumsi/Bulan Harga Satuan Total Biaya /Bulan Total Biaya /Tahun
7.68 Rp 14,365 Rp 110,323 Rp 1,323,878
3.2 Rp 14,365 Rp 45,968 Rp 551,616
8.96 Rp 10,000 Rp 89,600 Rp 1,075,200
1.024 Rp 990,000 Rp 1,013,760 Rp 12,165,120
Rp 1,259,651 Rp 15,115,814
Biaya Pembelian Alat
Jenis Alat Jumlah Unit Harga Satuan/Unit Harga Total Umur Alat
A. Alat Operasi
Excavator 3 Rp 1,075,000,000 Rp 3,225,000,000 10
Dumptruck 3 Rp 925,000,000 Rp 2,775,000,000 10
Sub Total Rp 6,000,000,000
B. Pengolahan
Instalasi Washing Plant 1 Rp 2,500,000,000 Rp 2,500,000,000 16
Sub Total Rp 2,500,000,000
C. Peralatan Workshop
Dongkrak 1 Rp 2,500,000 Rp 2,500,000 16
Alat Las & Patri 2 Rp 20,000,000 Rp 40,000,000 16
Alat Bengkel 1 Rp 10,000,000 Rp 10,000,000 16
Kompresor 1 Rp 10,000,000 Rp 10,000,000 16
Sub Total Rp 62,500,000
D. Peralatan Pendukung Operasional
Genset 1 Rp 20,000,000 Rp 20,000,000 16
Mobil Operasional 1 Rp 200,000,000 Rp 200,000,000 16
HT 1 Rp 2,000,000 Rp 2,000,000 6
Sub Total Rp 220,000,000
E. Peralatan K3
Helm Pengaman 58 Rp 100,000 Rp 5,800,000 5
Sepatu Pengaman 58 Rp 500,000 Rp 29,000,000 5
Kacamata Pelindung 58 Rp 250,000 Rp 14,500,000 5
Ear Protector 58 Rp 225,000 Rp 13,050,000 5
Masker Debu 58 Rp 25,000 Rp 1,450,000 5
Perlengkapan P3K 3 Rp 5,000,000 Rp 15,000,000 5
Sub Total Rp 78,800,000
F. Inventarisasi
1. Inventaris Mess & Kantor
Meja 10 Rp 1,500,000 Rp 15,000,000 16
Kursi 10 Rp 300,000 Rp 3,000,000 16
Lemari Arsip 2 Rp 5,000,000 Rp 10,000,000 16
Komputer 2 Rp 7,000,000 Rp 14,000,000 16
Printer 1 Rp 5,000,000 Rp 5,000,000 16
Telephone 1 Rp 500,000 Rp 500,000 16
Dispenser 2 Rp 1,500,000 Rp 3,000,000 16
Lampu 7 Rp 2,500,000 Rp 17,500,000 5
Tempat Tidur Karyawan 35 Rp 2,000,000 Rp 70,000,000 16
ATK 1 Rp 10,000,000 Rp 10,000,000 1
Sub Total Rp 148,000,000
Total Investasi Peralatan Rp 9,009,300,000
9,009,300,000
Pekerjaan Gaji/Bulan Total Karyawan Total Gaji Karyawan TH 1
Rp 42,542,719 Rp 44,669,855
Rp 9,116,297 Rp 9,572,112
Rp 30,387,656 Rp 31,907,039
Rp 21,879,113 Rp 22,973,068
Rp 5,469,778 Rp 5,743,267
Rp 5,469,778 Rp 5,743,267
Rp 5,469,778 Rp 5,743,267
Rp 21,879,113 Rp 22,973,068
Rp 9,116,297 Rp 9,572,112
Rp 17,017,088 Rp 17,867,942
Rp 4,254,272 Rp 4,466,985
Rp 30,387,656 Rp 31,907,039
Rp 9,724,050 Rp 10,210,253
Rp 4,862,025 Rp 5,105,126
Rp 12,155,063 Rp 12,762,816
Rp 6,077,531 Rp 6,381,408
Rp 4,254,272 Rp 4,466,985
Rp 9,724,050 Rp 10,210,253
Rp 6,685,284 Rp 7,019,549
Rp 5,469,778 Rp 5,743,267
Rp 12,155,063 Rp 12,762,816
Rp 6,077,531 Rp 6,381,408
Rp 4,862,025 Rp 5,105,126
Rp 4,862,025 Rp 5,105,126
Rp 4,862,025 Rp 5,105,126
Rp 4,862,025 Rp 5,105,126
Rp 4,862,025 Rp 5,105,126
Rp 4,862,025 Rp 5,105,126
Rp 3,646,519 Rp 3,828,845
Rp 9,724,050 Rp 10,210,253
Rp 4,862,025 Rp 5,105,126
Rp 4,862,025 Rp 5,105,126
Rp 4,862,025 Rp 5,105,126
Rp 4,862,025 Rp 5,105,126
Rp 4,862,025 Rp 5,105,126
Rp 3,646,519 Rp 3,828,845
Rp 9,724,050 Rp 10,210,253
Rp 6,320,633 Rp 6,636,664
Rp 3,646,519 Rp 3,828,845
Rp 3,646,519 Rp 3,828,845
Rp 6,077,531 Rp 6,381,408
Rp 5,469,778 Rp 5,743,267
Rp 4,254,272 Rp 4,466,985
Rp 4,254,272 Rp 4,466,985
Rp 3,646,519 Rp 3,828,845
Rp 397,713,645 Rp 417,599,327
Rp 397,713,645 Rp 417,599,327
200,000,000
CSR
Tahun
No Rincian Comdev
2024 2025 2026 2027
1 Pendidikan 25%
Perbaikan Saran Pendidikan Rp 50,000,000 Rp 50,000,000 Rp 50,000,000 Rp 50,000,000
2 Kesehatan 25%
Perbaikan & Bantuan Sarana Kesehatan Rp 50,000,000 Rp 50,000,000 Rp 50,000,000 Rp 50,000,000
3 Bangunan 30%
Pembangunan Sarana Keagamaan Rp 30,000,000 Rp 30,000,000 Rp 30,000,000 Rp 30,000,000
Pembangunan Sarana Air Bersih Rp 30,000,000 Rp 30,000,000 Rp 30,000,000 Rp 30,000,000
4 DLL 20%
Perbaikan Fasilitas Umum Rp 40,000,000 Rp 40,000,000 Rp 40,000,000 Rp 40,000,000
Total Rp 200,000,000 Rp 200,000,000 Rp 200,000,000 Rp 200,000,000
2028 2029
Rp 50,000,000 Rp 50,000,000
Rp 50,000,000 Rp 50,000,000
Rp 30,000,000 Rp 30,000,000
Rp 30,000,000 Rp 30,000,000
Rp 40,000,000 Rp 40,000,000
Rp 200,000,000 Rp 200,000,000
Biaya K3
Tahap/Tahun 2024 2025 2026 2027 2028
Diklat/Kursus K3 Rp 20,000,000 Rp 20,000,000 Rp 20,000,000 Rp 20,000,000 Rp 20,000,000
Pemasangan Rambu Rp 4,000,000 Rp 4,000,000 Rp 4,000,000 Rp 4,000,000 Rp 4,000,000
Asuransi Pekerja Rp 500,000,000 Rp 500,000,000 Rp 500,000,000 Rp 500,000,000 Rp 500,000,000
Pemerikasaan Kesehatan Rp 40,000,000 Rp 40,000,000 Rp 40,000,000 Rp 40,000,000 Rp 40,000,000
Total Rp 564,000,000 Rp 564,000,000 Rp 564,000,000 Rp 564,000,000 Rp 564,000,000
2029
Rp 20,000,000
Rp 4,000,000
Rp 500,000,000
Rp 40,000,000
Rp 564,000,000
A. Operational Cost Peralatan Penunjang Jumlah Unit Konsumsi BBM PerUnit
1 Excavator Komatsu PC-200 1 30
TOTAL
Total
Rp 272,011,814
Biaya
Rp 272,011,814
Rp 272,011,814
Rp 272,011,814
Rp 272,011,814
Rp 272,011,814
Rp 272,011,814
Rp 1,632,070,884
Total Biaya BBM per bulan Total Biaya BBM Per Tahun
Rp 21,408,000 Rp 256,896,000
Rp 21,408,000 Rp 256,896,000
Umur Tahun
Depresiasi/Unit
Alat 2024 2025 2026 2027
Rp 193,500,000 Rp 193,500,000
Rp 232,200,000 Rp 232,200,000
Rp 425,700,000 Rp 425,700,000
Rp 140,625,000 Rp 140,625,000
Rp 140,625,000 Rp 140,625,000
Rp 140,625 Rp 140,625
Rp 2,250,000 Rp 2,250,000
Rp 562,500 Rp 562,500
Rp 562,500 Rp 562,500
Rp 3,515,625 Rp 3,515,625
Rp 1,125,000 Rp 1,125,000
Rp 11,250,000 Rp 11,250,000
Rp 300,000 Rp 300,000
Rp 12,675,000 Rp 12,675,000
Rp 1,044,000 Rp 1,044,000
Rp 5,220,000 Rp 5,220,000
Rp 2,610,000 Rp 2,610,000
Rp 2,349,000 Rp 2,349,000
Rp 261,000 Rp 261,000
Rp 2,700,000 Rp 2,700,000
Rp 14,184,000 Rp 14,184,000
Rp 84,375 Rp 84,375
Rp 168,750 Rp 168,750
Rp 562,500 Rp 562,500
Rp 787,500 Rp 787,500
Rp 281,250 Rp 281,250
Rp 28,125 Rp 28,125
Rp 168,750 Rp 168,750
Rp 3,150,000 Rp 3,150,000
Rp 3,937,500 Rp 3,937,500
Rp 9,000,000 Rp 9,000,000
Rp 18,168,750 Rp 18,168,750
Rp 615,627,750 Rp 615,627,750
Biaya Perijinan
No Jenis Retribusi Jumlah Amortisasi 12,5% 2024
1 Surat Izin Pendirian Badan Rp 5,000,000 Rp 625,000 Rp 625,000
2 Surat Izin Keterangan Domisili Perusahan Rp 5,000,000 Rp 625,000 Rp 625,000
3 Surat Izin Gangguan (HO) Rp 5,000,000 Rp 625,000 Rp 625,000
4 Surat Tanda Daftar Perusahaan Rp 5,000,000 Rp 625,000 Rp 625,000
5 Surat Usaha Perdagangan (SIUP) Rp 5,000,000 Rp 625,000 Rp 625,000
6 Surat Izin Tempat Usaha / SITU Rp 5,000,000 Rp 625,000 Rp 625,000
7 Surat Setoran Bukan Pajak (SSBP) Rp 5,000,000 Rp 625,000 Rp 625,000
8 Surat Izin Terdaftar Nomor Pajak Wajib Pajak Rp 5,000,000 Rp 625,000 Rp 625,000
Total Rp 5,000,000
n
2025 2026 2027 2028 2029
Rp 625,000 Rp 625,000 Rp 625,000 Rp 625,000 Rp 625,000
Rp 625,000 Rp 625,000 Rp 625,000 Rp 625,000 Rp 625,000
Rp 625,000 Rp 625,000 Rp 625,000 Rp 625,000 Rp 625,000
Rp 625,000 Rp 625,000 Rp 625,000 Rp 625,000 Rp 625,000
Rp 625,000 Rp 625,000 Rp 625,000 Rp 625,000 Rp 625,000
Rp 625,000 Rp 625,000 Rp 625,000 Rp 625,000 Rp 625,000
Rp 625,000 Rp 625,000 Rp 625,000 Rp 625,000 Rp 625,000
Rp 625,000 Rp 625,000 Rp 625,000 Rp 625,000 Rp 625,000
Rp 5,000,000 Rp 5,000,000 Rp 5,000,000 Rp 5,000,000 Rp 5,000,000
Pendapatan
Washed Bauxite
Produksi/Hari 330 MT
Produksi/Bulan 8300 MT
Produksi/Tahun 100,000 MT
Produksi 6 Tahun 590,000
Tahun
Sasaran Produksi 2024 2025 2026 2027 2028 2029
Washed Bauxite 100,000 100,000 100,000 100,000 100,000 90,000
Pendapatan
Produk Harga/Ton (Rp)
1 2 3 4 5 6
Washed Bauxite 452,000 Rp 45,200,000,000 Rp 45,200,000,000 Rp 45,200,000,000 Rp 45,200,000,000 Rp 45,200,000,000 Rp 40,680,000,000
Pajak Daerah (10% Pendapatan) Perda No 8 Th 2010 Pasal 36 -4,520,000,000 -4,520,000,000 -4,520,000,000 -4,520,000,000 -4,520,000,000 -4,068,000,000
Pendapatan Setelah Royalti Dan Pajak Daerah 38,872,000,000 38,872,000,000 38,872,000,000 38,872,000,000 38,872,000,000 34,984,800,000
Nilai Sisa
Biaya Operasi Tetap
Gaji Karyawan -321,200,000 -342,560,000 -360,738,000 -378,774,900 -397,713,645 -417,599,327
Biaya K3 -564,000,000 -564,000,000 -564,000,000 -564,000,000 -564,000,000 -564,000,000
Biaya Operasi Tidak Tetap
Biaya Operasi Alat Tambang -3,253,759,742 -3,457,393,834 -3,655,000,643 -3,873,974,916 -4,128,374,111 -4,345,000,762
Biaya Operasi Pengolahan -1,430,000,000 -1,430,000,000 -1,430,000,000 -1,430,000,000 -1,430,000,000 -1,430,000,000
Biaya Perawatan -1,213,095,218 -1,286,366,169 -1,364,062,686 -1,446,452,027 -1,533,817,777 -1,626,460,371
Biaya Administrasi -16,920,000 -17,942,968 -19,025,663 -20,174,813 -21,393,372 -22,685,531
Biaya Pengembangan Masyarakat -200,000,000 -200,000,000 -200,000,000 -200,000,000 -200,000,000 -200,000,000
Depresiasi -615,627,750 -615,627,750 -615,627,750 -615,627,750 -615,627,750 -615,627,750
Amortisasi -5,000,000 -5,000,000 -5,000,000 -5,000,000 -5,000,000 -5,000,000
Total Pengeluaran -7,619,602,710 -7,918,890,721 -8,213,454,742 -8,534,004,406 -8,895,926,655 -9,226,373,741
Pendapatan Terpajak 31,252,397,290 30,953,109,279 30,658,545,258 30,337,995,594 29,976,073,345 25,758,426,259
Pajak Pendapatan (25% Pendapatan Terpajak) -7,813,099,323 -7,738,277,320 -7,664,636,315 -7,584,498,899 -7,494,018,336 -6,439,606,565
Pendapatan Bersih 23,439,297,968 23,214,831,959 22,993,908,944 22,753,496,696 22,482,055,009 19,318,819,694
Depresiasi 615,627,750 615,627,750 615,627,750 615,627,750 615,627,750 615,627,750
Amortisasi 5,000,000 5,000,000 5,000,000 5,000,000 5,000,000 5,000,000
Investasi Alat Tahunan -26,450,000 -26,450,000 -26,450,000 -26,450,000 -26,450,000 -26,450,000
Investasi Total -57,891,236,940
Modal Kerja Kembali
Net Cash Flow -57,891,236,940 24,033,475,718 23,809,009,709 23,588,086,694 23,347,674,446 23,076,232,759 19,912,997,444
Cumulative Cash Flow -57,891,236,940 -33,857,761,223 -10,048,751,513 13,539,335,180 36,887,009,626 59,963,242,385 79,876,239,829
NPV
NET CASH FLOW Tahun Discount factor 10% Discount factor 20%
-57,891,236,940 0 1 1
24,003,475,718 1 0.909090909090909 0.833333333333333
23,809,009,709 2 0.826446280991735 0.694444444444444
23,588,086,694 3 0.751314800901578 0.578703703703704
23,347,674,446.00 4 0.683013455365071 0.482253086419753
23,076,232,759.00 5 0.620921323059155 0.401877572016461
19,912,997,444 6 0.564473930053777 0.334897976680384
SUKU BUNGA
NET CASH FLOW Tahun 10% 20%
-57,891,236,940 0 -57,891,236,940 -57,891,236,940
24,003,475,718 1 21,821,341,562 20,002,896,432
23,809,009,709 2 19,676,867,528 16,534,034,520
23,588,086,694 3 17,722,078,658 13,650,513,133
23,347,674,446 4 15,946,775,798 11,259,488,062
23,076,232,759 5 14,328,524,976 9,273,820,392
19,912,997,444 6 11,240,367,926 6,668,822,554
42,844,719,508 19,498,338,153
IRR = 0.2296688701
= 22.97%
SUKU BUNGA
30% 40% 50%
-57,891,236,940 -57,891,236,940 -57,891,236,940
18,464,212,091 17,145,339,799 16,002,317,145
14,088,171,425 12,147,453,933 10,581,782,093
10,736,498,268 8,596,241,507 6,989,062,724
8,174,669,811 6,077,591,224 4,611,886,310
6,215,100,408 4,290,666,233 3,038,845,466
4,125,499,361 2,644,651,336 1,748,191,820
3,912,914,423 -6,989,292,909 -14,919,151,382
CASH FLOW
Tahun
URAIAN
0 1
Pendapatan 47,460,000,000
2 3 4 5 6
50,326,584,000 53,366,309,674 56,589,634,778 60,007,648,718 45,293,925,600
SUKU BUNGA
NET CASH FLOW Tahun 10% 20%
-57,891,236,940 0 -57,891,236,940 -57,891,236,940
25,695,184,578 1 23,359,258,707 21,412,653,815
27,331,987,385 2 22,588,419,326 18,980,546,795
29,084,753,821 3 21,851,806,026 16,831,454,758
30,937,241,867 4 21,130,552,467 14,919,580,376
32,885,111,652 5 20,419,067,036 13,215,788,826
23,162,504,834 6 13,074,630,134 7,757,076,004
64,532,496,757 35,225,863,633
IRR = 0.2358248791
= 23.58%
SUKU BUNGA
30% 40% 50%
-57,891,236,940 -57,891,236,940 -57,891,236,940
19,765,526,598 18,353,703,270 17,130,123,052
16,172,773,601 13,944,891,523 12,147,549,949
13,238,395,003 10,599,400,081 8,617,704,836
10,831,988,329 8,053,217,895 6,111,060,122
8,856,916,681 6,114,474,559 4,330,549,683
4,798,719,990 3,076,219,416 2,033,470,932
15,773,083,261 2,250,669,804 -7,520,778,367
CASH FLOW
Tahun
URAIAN
0 1
Pendapatan 49,720,000,000
2 3 4 5 6
52,723,088,000 55,907,562,515 59,284,379,291 62,865,155,800 47,450,779,200
SUKU BUNGA
NET CASH FLOW Tahun 10% 20%
-57,891,236,940 0 -57,891,236,940 -57,891,236,940
27,152,884,578 1 24,684,440,525 22,627,403,815
28,877,732,465 2 23,865,894,599 20,053,980,878
30,723,861,904 3 23,083,292,189 17,780,012,676
32,675,352,078 4 22,317,705,128 15,757,789,389
34,728,203,720 5 21,563,482,201 13,956,486,191
24,553,675,406 6 13,859,909,654 8,222,976,214
71,483,487,357 40,507,412,224
IRR = 0.2375479743
= 23.75%
SUKU BUNGA
30% 40% 50%
-57,891,236,940 -57,891,236,940 -57,891,236,940
20,886,834,291 19,394,917,556 18,101,923,052
17,087,415,660 14,733,536,972 12,834,547,762
13,984,461,495 11,196,742,676 9,103,366,490
11,440,549,028 8,505,662,244 6,454,390,534
9,353,314,961 6,457,168,836 4,573,261,395
5,086,937,438 3,260,981,209 2,155,603,877
19,948,275,932 5,657,772,553 -4,668,143,830
CASH FLOW
Tahun
URAIAN
0 1
Pendapatan 42,940,000,000
2 3 4 5 6
40,346,424,000 37,909,499,990 35,619,776,191 33,468,332,313 36,311,781,600
SUKU BUNGA
NET CASH FLOW Tahun 10% 20%
-57,891,236,940 0 -57,891,236,940 -57,891,236,940
22,779,784,578 1 20,708,895,071 18,983,153,815
20,894,784,185 2 17,268,416,682 14,510,266,795
19,115,111,575 3 14,361,466,247 11,061,985,865
17,411,683,079 4 11,892,413,824 8,396,837,905
15,767,252,571 5 9,790,223,327 6,336,505,181
17,369,021,954 6 9,804,360,084 5,816,850,309
25,934,538,294 7,214,362,930
IRR = 0.2222383083
= 22.22%
SUKU BUNGA
30% 40% 50%
-57,891,236,940 -57,891,236,940 -57,891,236,940
17,522,911,214 16,271,274,699 15,186,523,052
12,363,777,624 10,660,604,176 9,286,570,749
8,700,551,468 6,966,148,533 5,663,736,763
6,096,314,232 4,532,403,967 3,439,344,806
4,246,579,540 2,931,675,152 2,076,346,018
3,598,448,158 2,306,785,166 1,524,852,407
-5,362,654,704 -14,222,345,247 -20,713,863,145
CASH FLOW
Tahun
URAIAN
0 1
Pendapatan 40,680,000,000
2 3 4 5 6
38,222,928,000 35,914,263,149 33,745,041,655 31,706,841,139 34,400,635,200
SUKU BUNGA
NET CASH FLOW Tahun 10% 20%
-57,891,236,940 0 -57,891,236,940 -57,891,236,940
21,322,084,578 1 19,383,713,253 17,768,403,815
19,525,129,265 2 16,136,470,467 13,559,117,545
17,828,183,813 3 13,394,578,372 10,317,236,003
16,202,479,303 4 11,066,511,374 7,813,695,652
14,631,090,764 5 9,084,756,235 5,879,907,232
16,136,332,526 6 9,108,539,038 5,404,025,114
20,283,331,798 2,851,148,421
IRR = 0.2186703382
= 21.87%
SUKU BUNGA
30% 40% 50%
-57,891,236,940 -57,891,236,940 -57,891,236,940
16,401,603,522 15,230,060,413 14,214,723,052
11,553,330,926 9,961,800,645 8,677,835,229
8,114,785,532 6,497,151,535 5,282,424,833
5,672,938,379 4,217,638,303 3,200,489,739
3,940,578,132 2,720,423,552 1,926,728,002
3,343,064,233 2,143,071,303 1,416,632,759
-8,864,936,217 -17,121,091,189 -23,172,403,325
ANALISIS KEPEKAAN - SKENARIO HARGA JUAL +5%, +10%, -5% DAN -
10%
harga jual + 5%
23.58% Rp. 64.532.496.757
Bauksit 474,600
harga jual - 5%
22.22% Rp. 25.934.538.294
Bauksit 429,400
PBP (tahun)
2.5
2.2
2.1
2.7
2.9