Item pekerjaan dan volume yang diperoleh dari lapangan dapat dilihat pada
tabel 4.1. sebagai berikut:
TABEL 4.1.
TABEL DAFTAR ITEM PEKERJAAN DAN VOLUME
NO URAIAN PEKERJAAN VOLUME SATUAN
PEKERJAAN STRUKTUR
I PEKERJAAN PONDASI
1 Strous ø 40 cm K-300 74.62 m3
2 Urugan pasir bawah pilecap t = 10 cm 16.51 m3
3 Rabat beton bawah pilecap t = 5 cm 8.26 m3
4 Pilecap (Beton K-300)
- PC1 6.05 m3
- PC2 31.45 m3
- PC3 56.24 m3
5 Plat lantai pit lift t = 20 cm K-300 2.03 m3
6 Plat dinding pit lift t = 20 cm K-300 3.18 m3
II STRUKTUR LANTAI LOWER GROUND 1 ELV - 7,50
1 Sloof Tie Beam (Beton K-300)
-TB1 35 x 70 23.46 m3
-TB2 30 x 60 16.63 m3
-TB3 25 x 50 12.50 m3
-TB4 20 x 40 5.20 m3
2 Rabat beton bawah lantai t = 5 cm 27.90 m3
3 Plat lantai t = 20 cm K-300 111.60 m3
4 Kolom (Beton K-300)
- K1 65 x 65 35.71 m3
- K2 40 x 60 6.17 m3
- K3 L 20 x 40 1.76 m3
- K4 40 x 40 0.59 m3
5 Dinding retaining wall t = 20 cm K-350 39.31 m3
6 Plat dan balok tangga K-300 3.61 m3
7 Balok separator lift 20 x 30 K-300 0.63 m3
8 Balok Latei di atas kusen 15 x 20 K-175 1.32 m3
9 Kolom praktis 15 x 15 K-175 5.39 m3
10 Plat Meja Wastafel t = 15 cm K-175 0.52 m3
III STRUKTUR LANTAI LOWER GROUND 2 ELV - 4,00
1 Balok (Beton K-300)
- B1 40 x 80 25.27 m3
- B2 35 x 70 12.35 m3
- B3 30 x 60 27.75 m3
- B4 25 x 50 12.63 m3
- B5 20 x 40 6.28 m3
NO URAIAN PEKERJAAN VOLUME SATUAN
2 Plat Lantai (Beton K-300)
-Plat lantai S1 t = 12 cm 55.60 m3
-Plat lantai S2 t = 14 cm 9.26 m3
-Plat lantai S3 t = 16 cm 15.05 m3
-Plat lantai t = 10 cm entrance 7.81 m3
3 Kolom (Beton K-300)
- K1 65 x 65 40.81 m3
- K2 40 x 60 7.06 m3
- K3 L 20 x 40 2.02 m3
- K4 40 x 40 0.67 m3
4 Plat dan balok tangga K-300 3.61 m3
5 Balok separator lift 20 x 30 K-300 0.63 m3
6 Balok Latei di atas kusen 15 x 20 K-175 3.82 m3
7 Kolom praktis 15 x 15 K-175 3.59 m3
IV STRUKTUR LANTAI 1/LOBBY ELV ± 0,00
1 Balok (Beton K-300)
- B1 40 x 80 25.27 m3
- B2 35 x 70 14.48 m3
- B3 30 x 60 29.19 m3
- B4 25 x 50 13.72 m3
- B5 20 x 40 6.28 m3
2 Plat Lantai (Beton K-300)
-Plat lantai S1 t = 12 cm 64.15 m3
-Plat lantai S2 t = 14 cm 9.26 m3
-Plat lantai S3 t = 16 cm 15.05 m3
-Plat lantai t = 10 cm entrance 7.81 m3
3 Kolom (Beton K-300)
- K2 40 x 60 7.06 m3
- K3 L 20 x 40 2.02 m3
- K4 40 x 40 0.67 m3
- K5 65 x 65 30.17 m3
3 Plat dan balok tangga K-300 3.61 m3
4 Balok separator lift 20 x 30 K-300 0.63 m3
5 Balok Latei di atas kusen 15 x 20 K-175 3.82 m3
6 Kolom praktis 15 x 15 K-175 3.59 m3
V STRUKTUR LANTAI 2 ELV + 4,00
1 Balok (Beton K-300)
- B1 40 x 80 28.43 m3
- B2 35 x 70 12.35 m3
- B3 30 x 60 30.58 m3
- B4 25 x 50 12.08 m3
- B5 20 x 40 6.26 m3
2 Plat Lantai (Beton K-300)
-Plat lantai S1 t = 12 cm 63.54 m3
-Plat lantai S3 t = 16 cm 15.05 m3
5 Kolom (Beton K-300)
- K4 40 x 40 0.67 m3
- K5 65 x 65 30.17 m3
- K6 40 x 60 7.06 m3
- K7 L 20 x 40 2.02 m3
NO URAIAN PEKERJAAN VOLUME SATUAN
6 Plat dan balok tangga K-300 3.61 m3
7 Balok separator lift 20 x 30 K-300 0.63 m3
8 Balok Latei di atas kusen 15 x 20 K-175 0.82 m3
9 Kolom praktis 15 x 15 K-175 6.80 m3
VI STRUKTUR LANTAI 3 ELV + 8,00
1 Balok (Beton K-300)
- B1 40 x 80 25.27 m3
- B2 35 x 70 12.35 m3
- B3 30 x 60 29.82 m3
- B4 25 x 50 12.60 m3
- B5 20 x 40 6.24 m3
2 Plat Lantai (Beton K-300)
-Plat lantai S1 t = 12 cm 63.54 m3
-Plat lantai S3 t = 16 cm 15.05 m3
3 Kolom (Beton K-300)
- K6 40 x 60 7.06 m3
- K7 L 20 x 40 2.02 m3
- K8 65 x 65 30.17 m3
- K9 40 x 40 0.67 m3
4 Plat dan balok tangga K-300 3.61 m3
5 Balok separator lift 20 x 30 K-300 0.63 m3
6 Balok Latei di atas kusen 15 x 20 K-175 0.80 m3
7 Kolom praktis 15 x 15 K-175 8.32 m3
VII STRUKTUR LANTAI 4 ELV +12,00
1 Balok (Beton K-300)
- B1 40 x 80 25.27 m3
- B2 35 x 70 12.35 m3
- B3 30 x 60 29.82 m3
- B4 25 x 50 12.60 m3
- B5 20 x 40 6.24 m3
2 Plat Lantai (Beton K-300)
-Plat lantai S1 t = 12 cm 63.54 m3
-Plat lantai S3 t = 16 cm 15.05 m3
3 Kolom (Beton K-300)
- K6 40 x 60 7.06 m3
- K7 L 20 x 40 2.02 m3
- K8 65 x 65 30.17 m3
- K9 40 x 40 0.67 m3
4 Plat dan balok tangga K-300 3.61 m3
5 Balok separator lift 20 x 30 K-300 0.63 m3
6 Balok Latei di atas kusen 15 x 20 K-175 0.98 m3
7 Kolom praktis 15 x 15 K-175 7.37 m3
VIII STRUKTUR LANTAI ATAP ELV + 16,00
Balok (Beton K-300)
- B1 40 x 80 25.27 m3
- B2 35 x 70 12.35 m3
- B3 30 x 60 29.82 m3
- B4 25 x 50 12.60 m3
- B5 20 x 40 6.24 m3
Plat Lantai (Beton K-300)
NO URAIAN PEKERJAAN VOLUME SATUAN
-Plat lantai S1 t = 12 cm 74.83 m3
Kolom (Beton K-300)
- K7 L 20 x 40 1.51 m3
- K9 40 x 40 2.02 m3
Balok separator lift 20 x 30 K-300 0.63 m3
Kolom praktis 15 x 15 K-175 0.76 m3
IX STRUKTUR LANTAI RUMAH LIFT ELV + 19,50
Balok (Beton K-300)
- B4 25 x 50 2.05 m3
- B5 20 x 40 2.82 m3
Plat Lantai (Beton K-300)
-Plat lantai S1 t = 12 cm 5.29 m3
Balok separator lift 20 x 30 K-300 0.63 m3
TABEL 4.1.
PERHITUNGAN DURASI NORMAL DAN KEBUTUHAN TENAGA KERJA
Durasi
No. Uraian pekerjaan Volume Satuan
(hari)
(1) (2) (3) (4) (5)
PEKERJAAN STRUKTUR
I PEKERJAAN PONDASI
1 Strous ø 40 cm K-300
- Besi beton 10,715.29 kg 4
- Beton 74.62 m3 6
2 Urugan pasir bawah pilecap t = 10 cm 16.51 m3 1
3 Rabat beton bawah pilecap t = 5 cm 8.26 m3 1
4 Pilecap (Beton K-300)
PC 1
- Besi beton 721.24 kg 1
- Bekisting 20.16 m2 1
- Beton 6.05 m3 1
- PC2
- Besi beton 4,454.08 kg 2
- Bekisting 78.62 m2 2
- Beton 31.45 m3 2
- PC3
- Besi beton 7,392.01 kg 3
- Bekisting 116.31 m2 3
- Beton 56.24 m3 2
5 Plat lantai pit lift t = 20 cm K-300
- Besi beton 505.02 kg 1
- Bekisting 2.65 m2 1
- Beton 2.03 m3 1
6 Plat dinding pit lift t = 20 cm K-300
- Besi beton 822.13 kg 1
- Bekisting 31.75 m2 1
- Beton 3.18 m3 1
II STRUKTUR LANTAI LOWER GROUND 1 ELV - 7,50
1 Sloof Tie Beam (Beton K-300)
-TB1 35 x 70
- Besi beton 5,148.02 kg 2
- Bekisting 134.06 m2 4
- Beton 23.46 m3 1
-TB2 30 x 60
- Besi beton 3,158.58 kg 2
- Bekisting 110.88 m2 3
- Beton 16.63 m3 1
-TB3 25 x 50
- Besi beton 2,458.59 kg 1
- Bekisting 99.96 m2 3
- Beton 12.50 m3 1
-TB4 20 x 40 5.20 m3
- Besi beton 724.93 kg 1
- Bekisting 52.00 m2 2
- Beton 5.20 m3 1
2 Rabat beton bawah lantai t = 5 cm 27.90 m3 3
3 Plat lantai t = 20 cm K-300
- Wiremesh M7-150 2,360.08 kg 3
- Bekisting 446.41 m2 12
- Beton 111.60 m3 3
4 Kolom (Beton K-300)
- K1 65 x 65
- Besi beton 12,112.77 kg 5
- Bekisting 219.77 m2 6
- Beton 35.71 m3 1
- K2 40 x 60
- Besi beton 1,951.16 kg 1
- Bekisting 51.45 m2 2
- Beton 6.17 m3 1
- K3 L 20 x 40
- Besi beton 1,060.14 kg 1
- Bekisting 23.52 m2 1
- Beton 1.76 m3 1
- K4 40 x 40
- Besi beton 174.37 kg 1
- Bekisting 5.88 m2 1
- Beton 0.59 m3 1
5 Dinding retaining wall t = 20 cm K-350
- Besi beton 3,978.80 kg 2
- Bekisting 393.12 m2 11
- Beton 39.31 m3 3
6 Plat dan balok tangga K-300
- Besi beton 1,253.16 kg 1
- Bekisting 27.26 m2 1
- Beton 3.61 m3 1
7 Balok separator lift 20 x 30 K-300
- Besi beton 170.52 kg 1
- Bekisting 6.28 m2 1
- Beton 0.63 m3 1
8 Balok Latei di atas kusen 15 x 20 K-175
- Besi beton 263.66 kg 1
- Bekisting 24.17 m2 2
- Beton 1.32 m3 1
9 Kolom praktis 15 x 15 K-175
- Besi beton 1,335.50 kg 1
- Bekisting 71.82 m2 4
- Beton 5.39 m3 1
10 Plat Meja Wastafel t = 15 cm K-175
- Besi beton 51.82 kg 1
- Bekisting 4.32 m2 1
- Beton 0.52 m3 1
III STRUKTUR LANTAI LOWER GROUND 2 ELV - 4,00
1 Balok (Beton K-300)
- B1 40 x 80
- Besi beton 4,780.58 kg 2
- Bekisting 126.34 m2 4
- Beton 25.27 m3 1
- B2 35 x 70
- Besi beton 2,726.45 kg 1
- Bekisting 70.56 m2 3
- Beton 12.35 m3 1
- B3 30 x 60
- Besi beton 5,117.48 kg 2
- Bekisting 184.97 m2 6
- Beton 27.75 m3 1
- B4 25 x 50
- Besi beton 2,180.22 kg 1
- Bekisting 84.21 m2 3
- Beton 12.63 m3 1
- B5 20 x 40
- Besi beton 1,003.97 kg 1
- Bekisting 62.85 m2 2
- Beton 6.28 m3 1
2 Plat Lantai (Beton K-300)
-Plat lantai S1 t = 12 cm
- Besi beton 5,781.95 kg 2
- Bekisting 463.32 m2 12
- Beton 55.60 m3 2
-Plat lantai S2 t = 14 cm
- Besi beton 857.94 kg 1
- Bekisting 66.15 m2 2
- Beton 9.26 m3 1
-Plat lantai S3 t = 16 cm
- Besi beton 2,698.18 kg 1
- Bekisting 94.08 m2 3
- Beton 15.05 m3 1
-Plat lantai t = 10 cm entrance
- Besi beton 330.40 kg 1
- Bekisting 31.25 m2 2
- Beton 7.81 m3 1
3 Kolom (Beton K-300)
- K1 65 x 65
- Besi beton 13,843.17 kg 5
- Bekisting 251.16 m2 6
- Beton 40.81 m3 1
- K2 40 x 60
- Besi beton 2,229.90 kg 1
- Bekisting 58.80 m2 2
- Beton 7.06 m3 1
- K3 L 20 x 40
- Besi beton 1,211.58 kg 1
- Bekisting 26.88 m2 1
- Beton 2.02 m3 1
- K4 40 x 40
- Besi beton 199.28 kg 1
- Bekisting 6.72 m2 1
- Beton 0.67 m3 1
4 Plat dan balok tangga K-300
- Besi beton 1,253.16 kg 1
- Bekisting 27.26 m2 2
- Beton 3.61 m3 1
5 Balok separator lift 20 x 30 K-300
- Besi beton 170.52 kg 1
- Bekisting 6.28 m2 1
- Beton 0.63 m3 1
6 Balok Latei di atas kusen 15 x 20 K-175
- Besi beton 764.82 kg 1
- Bekisting 70.11 m2 3
- Beton 3.82 m3 1
7 Kolom praktis 15 x 15 K-175
- Besi beton 890.33 kg 1
- Bekisting 47.88 m2 2
- Beton 3.59 m3 1
IV STRUKTUR LANTAI 1/LOBBY ELV ± 0,00
1 Balok (Beton K-300)
- B1 40 x 80
- Besi beton 4,780.58 kg 2
- Bekisting 126.34 m2 4
- Beton 25.27 m3 1
- B2 35 x 70
- Besi beton 3,197.89 kg 2
- Bekisting 82.76 m2 3
- Beton 14.48 m3 1
- B3 30 x 60
- Besi beton 5,384.17 kg 2
- Bekisting 194.61 m2 6
- Beton 29.19 m3 1
- B4 25 x 50
- Besi beton 2,368.25 kg 1
- Bekisting 91.47 m2 3
- Beton 13.72 m3 1
- B5 20 x 40
- Besi beton 1,003.97 kg 1
- Bekisting 62.85 m2 2
- Beton 6.28 m3 1
2 Plat Lantai (Beton K-300)
-Plat lantai S1 t = 12 cm
- Besi beton 6,671.04 kg 3
- Bekisting 534.57 m2 18
- Beton 64.15 m3 2
-Plat lantai S2 t = 14 cm
- Besi beton 857.94 kg 1
- Bekisting 66.15 m2 3
- Beton 9.26 m3 1
-Plat lantai S3 t = 16 cm
- Besi beton 2,698.18 kg 2
- Bekisting 94.08 m2 4
- Beton 15.05 m3 1
-Plat lantai t = 10 cm entrance
- Besi beton 330.40 kg 1
- Bekisting 31.25 m2 2
- Beton 7.81 m3 1
3 Kolom (Beton K-300)
- K2 40 x 60
- Besi beton 1,894.06 kg 1
- Bekisting 58.80 m2 2
- Beton 7.06 m3 1
- K3 L 20 x 40
- Besi beton 1,028.62 kg 1
- Bekisting 26.88 m2 1
- Beton 2.02 m3 1
- K4 40 x 40
- Besi beton 169.59 kg 1
- Bekisting 6.72 m2 1
- Beton 0.67 m3 1
- K5 65 x 65
- Besi beton 6,510.71 kg 3
- Bekisting 185.64 m2 5
- Beton 30.17 m3 1
3 Plat dan balok tangga K-300
- Besi beton 1,253.16 kg 2
- Bekisting 27.26 m2 1
- Beton 3.61 m3 1
4 Balok separator lift 20 x 30 K-300
- Besi beton 170.52 kg 1
- Bekisting 6.28 m2 1
- Beton 0.63 m3 1
5 Balok Latei di atas kusen 15 x 20 K-175
- Besi beton 764.82 kg 1
- Bekisting 70.11 m2 3
- Beton 3.82 m3 1
6 Kolom praktis 15 x 15 K-175
- Besi beton 890.33 kg 1
- Bekisting 47.88 m2 2
- Beton 3.59 m3 1
V STRUKTUR LANTAI 2 ELV + 4,00
1 Balok (Beton K-300)
- B1 40 x 80
- Besi beton 5,378.15 kg 2
- Bekisting 142.13 m2 5
- Beton 28.43 m3 1
- B2 35 x 70
- Besi beton 2,726.45 kg 2
- Bekisting 70.56 m2 3
- Beton 12.35 m3 1
- B3 30 x 60
- Besi beton 5,640.39 kg 3
- Bekisting 203.87 m2 7
- Beton 30.58 m3 1
- B4 25 x 50
- Besi beton 2,084.17 kg 1
- Bekisting 80.50 m2 3
- Beton 12.08 m3 1
- B5 20 x 40
- Besi beton 999.68 kg 1
- Bekisting 62.58 m2 3
- Beton 6.26 m3 1
2 Plat Lantai (Beton K-300)
-Plat lantai S1 t = 12 cm
- Besi beton 6,607.46 kg 3
- Bekisting 529.47 m2 15
- Beton 63.54 m3 2
-Plat lantai S3 t = 16 cm
- Besi beton 2,698.18 kg 2
- Bekisting 94.08 m2 4
- Beton 15.05 m3 1
5 Kolom (Beton K-300)
- K4 40 x 40
- Besi beton 169.59 kg 1
- Bekisting 6.72 m2 1
- Beton 0.67 m3 1
- K5 65 x 65
- Besi beton 6,510.71 kg 3
- Bekisting 185.64 m2 5
- Beton 30.17 m3 1
- K6 40 x 60
- Besi beton 1,288.67 kg 1
- Bekisting 58.80 m2 2
- Beton 7.06 m3 1
- K7 L 20 x 40
- Besi beton 711.52 kg 1
- Bekisting 26.88 m2 1
- Beton 2.02 m3 1
6 Plat dan balok tangga K-300
- Besi beton 1,253.16 kg 1
- Bekisting 27.26 m2 1
- Beton 3.61 m3 1
7 Balok separator lift 20 x 30 K-300
- Besi beton 170.52 kg 1
- Bekisting 6.28 m2 1
- Beton 0.63 m3 1
8 Balok Latei di atas kusen 15 x 20 K-175
- Besi beton 163.17 kg 1
- Bekisting 14.96 m2 1
- Beton 0.82 m3 1
9 Kolom praktis 15 x 15 K-175
- Besi beton 1,686.94 kg 1
- Bekisting 90.72 m2 3
- Beton 6.80 m3 1
VI STRUKTUR LANTAI 3 ELV + 8,00
1 Balok (Beton K-300)
- B1 40 x 80
- Besi beton 4,780.58 kg 2
- Bekisting 126.34 m2 5
- Beton 25.27 m3 1
- B2 35 x 70
- Besi beton 2,726.45 kg 2
- Bekisting 70.56 m2 3
- Beton 1
- B3 30 x 60
- Besi beton 5,500.95 kg 3
- Bekisting 198.83 m2 7
- Beton 29.82 m3 1
- B4 25 x 50
- Besi beton 2,174.78 kg 1
- Bekisting 84.00 m2 3
- Beton 12.60 m3 1
- B5 20 x 40
- Besi beton 996.33 kg 1
- Bekisting 62.37 m2 3
- Beton 6.24 m3 1
2 Plat Lantai (Beton K-300)
-Plat lantai S1 t = 12 cm
- Besi beton 6,607.46 kg 2
- Bekisting 529.47 m2 15
- Beton 63.54 m3 2
-Plat lantai S3 t = 16 cm
- Besi beton 2,698.18 kg 2
- Bekisting 94.08 m2 4
- Beton 15.05 m3 1
3 Kolom (Beton K-300)
- K6 40 x 60
- Besi beton 1,288.67 kg 1
- Bekisting 58.80 m2 2
- Beton 7.06 m3 1
- K7 L 20 x 40
- Besi beton 711.52 kg 1
- Bekisting 26.88 m2 1
- Beton 2.02 m3 1
- K8 65 x 65
- Besi beton 4,972.35 kg 2
- Bekisting 185.64 m2 5
- Beton 30.17 m3 1
- K9 40 x 40
- Besi beton 121.38 kg 1
- Bekisting 6.72 m2 1
- Beton 0.67 m3 1
4 Plat dan balok tangga K-300
- Besi beton 1,253.16 kg 1
- Bekisting 27.26 m2 1
- Beton 3.61 m3 1
5 Balok separator lift 20 x 30 K-300
- Besi beton 170.52 kg 1
- Bekisting 6.28 m2 1
- Beton 0.63 m3 1
6 Balok Latei di atas kusen 15 x 20 K-175
- Besi beton 160.02 kg 1
- Bekisting 14.67 m2 1
- Beton 0.80 m3 1
7 Kolom praktis 15 x 15 K-175
- Besi beton 2,061.82 kg 1
- Bekisting 110.88 m2 3
- Beton 8.32 m3 1
VII STRUKTUR LANTAI 4 ELV +12,00
1 Balok (Beton K-300)
- B1 40 x 80
- Besi beton 4,780.58 kg 2
- Bekisting 126.34 m2 5
- Beton 25.27 m3 1
- B2 35 x 70
- Besi beton 2,726.45 kg 2
- Bekisting 70.56 m2 3
- Beton 12.35 m3 1
- B3 30 x 60
- Besi beton 5,500.95 kg 3
- Bekisting 198.83 m2 7
- Beton 29.82 m3 1
- B4 25 x 50
- Besi beton 2,174.78 kg 1
- Bekisting 84.00 m2 3
- Beton 12.60 m3 1
- B5 20 x 40
- Besi beton 996.33 kg 1
- Bekisting 62.37 m2 3
- Beton 6.24 m3 1
2 Plat Lantai (Beton K-300)
-Plat lantai S1 t = 12 cm
- Besi beton 6,607.46 kg 2
- Bekisting 529.47 m2 15
- Beton 63.54 m3 2
-Plat lantai S3 t = 16 cm
- Besi beton 2,698.18 kg 2
- Bekisting 94.08 m2 4
- Beton 15.05 m3 1
3 Kolom (Beton K-300)
- K6 40 x 60
- Besi beton 1,288.67 kg 1
- Bekisting 58.80 m2 2
- Beton 7.06 m3 1
- K7 L 20 x 40
- Besi beton 711.52 kg 1
- Bekisting 26.88 m2 1
- Beton 2.02 m3 1
- K8 65 x 65
- Besi beton 4,972.35 kg 2
- Bekisting 185.64 m2 5
- Beton 30.17 m3 1
- K9 40 x 40
- Besi beton 121.38 kg 1
- Bekisting 6.72 m2 1
- Beton 0.67 m3 1
4 Plat dan balok tangga K-300
- Besi beton 1,253.16 kg 1
- Bekisting 27.26 m2 1
- Beton 3.61 m3 1
5 Balok separator lift 20 x 30 K-300
- Besi beton 170.52 kg 1
- Bekisting 6.28 m2 1
- Beton 0.63 m3 1
6 Balok Latei di atas kusen 15 x 20 K-175
- Besi beton 195.93 kg 1
- Bekisting 17.96 m2 1
- Beton 0.98 m3 1
7 Kolom praktis 15 x 15 K-175
- Besi beton 1,827.52 kg 1
- Bekisting 98.28 m2 3
- Beton 7.37 m3 1
VIII STRUKTUR LANTAI ATAP ELV + 16,00
1 Balok (Beton K-300)
- B1 40 x 80
- Besi beton 4,780.58 kg 2
- Bekisting 126.34 m2 5
- Beton 25.27 m3 1
- B2 35 x 70
- Besi beton 2,726.45 kg 2
- Bekisting 70.56 m2 3
- Beton 12.35 m3 1
- B3 30 x 60
- Besi beton 5,500.95 kg 3
- Bekisting 198.83 m2 7
- Beton 29.82 m3 3
- B4 25 x 50
- Besi beton 2,174.78 kg 1
- Bekisting 84.00 m2 3
- Beton 12.60 m3 1
- B5 20 x 40
- Besi beton 996.33 kg 1
- Bekisting 62.37 m2 3
- Beton 6.24 m3 1
2 Plat Lantai (Beton K-300)
-Plat lantai S1 t = 12 cm
- Besi beton 7,781.52 kg 3
- Bekisting 623.55 m2 17
- Beton 74.83 m3 2
3 Kolom (Beton K-300)
- K7 L 20 x 40
- Besi beton 533.64 kg 1
- Bekisting 20.16 m2 1
- Beton 1.51 m3 1
- K9 40 x 40
- Besi beton 364.13 kg 1
- Bekisting 20.16 m2 1
- Beton 2.02 m3 1
4 Balok separator lift 20 x 30 K-300
- Besi beton 155.68 kg 1
- Bekisting 8.37 m2 1
- Beton 0.63 m3 1
5 Kolom praktis 15 x 15 K-175
- Besi beton 187.44 kg 1
- Bekisting 10.08 m2 1
- Beton 0.76 m3 1
IX STRUKTUR LANTAI RUMAH LIFT ELV + 19,50
1 Balok (Beton K-300)
- B4 25 x 50
- Besi beton 353.40 kg 1
- Bekisting 13.65 m2 1
- Beton 2.05 m3 1
- B5 20 x 40
- Besi beton 449.79 kg 1
- Bekisting 28.16 m2 1
- Beton 2.82 m3 1
2 Plat Lantai (Beton K-300)
-Plat lantai S1 t = 12 cm
- Besi beton 550.34 kg 1
- Bekisting 44.10 m2 2
- Beton 5.29 m3 1
3 Balok separator lift 20 x 30 K-300
- Besi beton 155.68 kg 1
- Bekisting 8.37 m2 1
- Beton 0.63 m3 1
Tahun Tanggal Keterangan
01/01/2018 Tahun Baru Masehi
16/02/2018 Tahun Baru Imlek
17/03/2018 Hari Raya Nyepi
30/03/2018 Jumat Agung
14/04/2018 Isra' Mi'raj
01/05/2018 Hari Buruh
10/05/2018 Kenaikan Isa Almasih
29/05/2018 Hari Waisak
01/06/2018 Hari Kesaktian Pancasila
11/06/2018 Cuti Bersama Lebaran
12/06/2018 Cuti Bersama Lebaran
13/06/2018 Cuti Bersama Lebaran
2018