PEKERJAAN : PEMBANGUNAN GEDUNG GEREJA PANTEKOSTA di INDONESIA (GPdI) JEMAAT PANCARAN KASIH
LOKASI : DESA LEKSULA, KECAMATAN LEKSULA, KABUPATEN BURU SELATAN, MALUKU
TAHUN : 2022
A JUMLAH ( A + B ) Rp 1,839,066,876.14
B DIBULATKAN Rp 1,839,000,000.00
Terbilang : Satu Milyar Delapan Ratus Tiga Puluh Sembilan Juta Rupiah
…………………….. ……………………….
A. PEKERJAAN PERSIAPAN
1 Pembersihan dan Perataan M2 137.50 Rp. 23,100.00 Rp. 3,176,250.00
2 Pemasangan Bouwplank M' 47.00 Rp. 94,050.00 Rp. 4,420,350.00
Jumlah sub I. Rp. 7,596,600.00
Total Jumlah A Rp. 7,596,600.00
B. PEKERJAAN PEMBANGUNAN GEDUNG GEREJA
I. PEKERJAAN TANAH
1 Galian Pondasi M3 73.21 Rp. 88,550.00 Rp. 6,482,302.75
2 Urugan Tanah Kembali M3 18.30 Rp. 67,100.00 Rp. 1,228,013.88
3 Timbunan Tanah Bawah Lantai, Pengurugan Sirtu Padat Disiram & Dipadatkan M3 228.85 Rp. 231,550.00 Rp. 52,989,638.63
4 Urug Pasir Bawah Lantai M3 11.82 Rp. 299,420.00 Rp. 3,539,256.68
Jumlah Rp. 64,239,211.93
II PEKERJAAN PASANGAN DAN BETON 25/20
1 Pas. Batu Kosong M3 26.62 Rp. 724,350.00 Rp. 19,282,197.00
2 Pas. Pondasi Bt. Kali, ad. 1 : 4 M3 88.25 Rp. 1,256,750.00 Rp. 110,902,280.78
3 Rabat beton Bawah Lantai mutu f’c = 7,4 MPa slump (3-6) cm, w/c = 0,87 M3 14.28 Rp. 1,593,738.20 Rp. 22,763,362.71
4 Pas. Dinding Batako Bangunan M2 450.00 Rp. 224,532.00 Rp. 101,039,400.00
5 Beton mutu f’c = 14,5 Mpa (K 175 M3) ad. 1 : 2 : 3
a Pondasi Telapak
- Beton 22.42 Rp. 1,969,412.94 Rp. 44,160,392.53
- Bekisting 172.65 Rp. 269,940.00 Rp. 46,605,141.00
- Besi 4,428.76 Rp. 16,185.40 Rp. 71,681,206.78
a. SLOOF 20/25 ###
- Beton M3 74.55 Rp. 1,969,412.94 Rp. 146,819,734.68
- Bekisting M2 74.55 Rp. 269,940.00 Rp. 20,124,027.00
- Besi Kg 911 Rp. 16,185.40 Rp. 14,746,275.16
b. Kolom Beton 30/30 cm (Elv. 0,00 - 40,00 m)
- Beton M3 7.20 Rp. 1,969,412.94 Rp. 14,179,773.17
- Bekisting M2 96.00 Rp. 454,520.00 Rp. 43,633,920.00
- Besi Kg 419.92 Rp. 16,185.40 Rp. 6,796,521.37
c. Kolom Beton 25/20 cm (Elv. 0,00 - 6,5 m) ###
- Beton M3 1.95 Rp. 1,969,412.94 Rp. 3,840,355.23
- Bekisting M2 35.10 Rp. 454,520.00 Rp. 15,953,652.00
- Besi Kg 240.51 Rp. 16,185.40 Rp. 3,892,672.86
d. Kolom Beton 25/40 cm (Elv. 0,00 - 4,70 m)
- Beton M3 1.88 Rp. 1,969,412.94 Rp. 3,702,496.33
- Bekisting M2 24.44 Rp. 454,520.00 Rp. 11,108,468.80
- Besi Kg 136.54 Rp. 16,185.40 Rp. 2,209,876.83
f. Kolom Beton 25/20 cm (Elv. 0,00 - 5,00 m)
- Beton M3 7.25 Rp. 1,969,412.94 Rp. 14,278,243.82
- Bekisting M2 130.50 Rp. 454,520.00 Rp. 59,314,860.00
- Besi Kg 896.74 Rp. 16,185.40 Rp. 14,514,157.10
g. Kolom Beton 25/20 cm (Elv. 0,00 - 7,00 m)
- Beton M3 0.70 Rp. 1,969,412.94 Rp. 1,378,589.06
- Bekisting M2 12.60 Rp. 454,520.00 Rp. 5,726,952.00
- Besi Kg 37.82 Rp. 16,185.40 Rp. 612,164.20
h. Kolom Beton 30/20 cm (Elv. 0,00 - 5,00 m)
- Beton M3 2.25 Rp. 1,969,412.94 Rp. 4,431,179.12
- Bekisting M2 30.00 Rp. 454,520.00 Rp. 13,635,600.00
- Besi Kg 193.57 Rp. 16,185.40 Rp. 3,132,962.56
i. Kolom Beton 20/18 cm (Elv. 4,70 - 10 m)
- Beton M3 0.58 Rp. 1,969,412.94 Rp. 1,134,381.85
- Bekisting M2 12.16 Rp. 454,520.00 Rp. 5,526,963.20
- Besi Kg 93.21 Rp. 16,185.40 Rp. 1,508,712.35
j. Kolom Beton 10/10 cm (Elv. 0,00 - 5,00 m)
- Beton M3 1.30 Rp. 1,969,412.94 Rp. 2,560,236.82
- Bekisting M2 31.20 Rp. 454,520.00 Rp. 14,181,024.00
- Besi Kg 37.82 Rp. 16,185.40 Rp. 612,164.20
k. BALOK 25/20
- Beton M3 8.36 Rp. 1,969,412.94 Rp. 16,454,445.11
- Bekisting M2 56.50 Rp. 464,420.00 Rp. 26,239,730.00
- Besi Kg 1,021.03 Rp. 16,185.40 Rp. 16,525,762.78
Lembar 3 dari 3