Anda di halaman 1dari 18

LAPORAN KEMAJUAN PEKERJAAN

KEGIATAN : PROGRAM BEDAH RUMAH RAKYAT TIDAK LAYAK HUNI ( BERARTI )


NAMA PENERIMA BANTUAN : VINCENTIUS L. SENA
ALAMAT : RT.006/RW.003
DESA : MAURISU UTARA
KECAMATAN : BIKOMI SELATAN
KABUPATEN : TIMOR TENGAH UTARA
NILAI PEKERJAAN : Rp. 25.000.000,-
PROGRESS
JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT. BOBOT %
HARGA ( Rp ) VOLUME
SAT. BOBOT %
REALISASI
1 PEKERJAAN PONDASI 5.16 M² 1,235,000 119.09 1,235,000 M² 5.16
2 PEKERJAAN SLOOF ( 15/20 ) 46.70 M² 3,066,167 12.26 3,065,000 M² 12.26
3 PEKERJAAN KOLOM ( 10 X 10 ) 24.86 M² 1,583,167 6.33 1,583,167 M² 6.33
4 PEKERJAAN PASANGAN TEMBOK 1.420.35 M² 8,355,831 33.42 8,190,000 M² 32.76
5 PEKERJAAN PLESTERAN 44.00 M² 2,586,668 10.35 - M² 0.00
6 PEKERJAAN ACIAN 7.00 M² 371,000 1.48 - M² 0.00
7 PEKERJAAN RINGBALK DAN GEWEL 50.38 M² 3,129,667 12.52 - M² 0.00
8 PEKERJAAN ATAP DAN KUDA-KUDA 85.00 M² 3,530,000 14.12 - M² 0.00
9 PEKERJAAN LANTAI 22.73 M² 1,340,501 5.36 - M² 0.00
10 PEKERJAAN LAIN-LAIN 91.00 Ls 1,037,000 4.15 - Ls 0.00
TOTAL 25,000,000 100.00 12,838,167 51.35

Progres sampai dengan Bulan November = 51.35 %


LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PROGRAM BEDAH RUMAH RAKYAT TIDAK LAYAK HUNI ( BERARTI )
NAMA PENERIMA BANTUAN : ALBERTUS SASI
ALAMAT : RT.006/RW.003
DESA : MAURISU UTARA
KECAMATAN : BIKOMI SELATAN
KABUPATEN : TIMOR TENGAH UTARA
NILAI PEKERJAAN : Rp. 25.000.000,-
PROGRESS
JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT. BOBOT % VOLUME
HARGA ( Rp ) SAT. BOBOT %
REALISASI
1 PEKERJAAN PONDASI 5.16 M² 1,235,000 119.09 1,235,000 M² 5.16
2 PEKERJAAN SLOOF ( 15/20 ) 46.70 M² 3,066,167 12.26 3,065,000 M² 12.26
3 PEKERJAAN KOLOM ( 10 X 10 ) 24.86 M² 1,583,167 6.33 1,583,167 M² 6.33
4 PEKERJAAN PASANGAN TEMBOK 1.420.35 M² 8,355,831 33.42 8,190,000 M² 32.76
5 PEKERJAAN PLESTERAN 44.00 M² 2,586,668 10.35 - M² 0.00
6 PEKERJAAN ACIAN 7.00 M² 371,000 1.48 - M² 0.00
7 PEKERJAAN RINGBALK DAN GEWEL 50.38 M² 3,129,667 12.52 1,622,500.00 M² 6.49
8 PEKERJAAN ATAP DAN KUDA-KUDA 85.00 M² 3,530,000 14.12 3,530,000 M² 14.12
9 PEKERJAAN LANTAI 22.73 M² 1,340,501 5.36 - M² 0.00
10 PEKERJAAN LAIN-LAIN 91.00 Ls 1,037,000 4.15 - Ls 0.00
TOTAL 25,000,000 100.00 17,990,667 71.96

Progres sampai dengan Bulan November = 71.96 %


LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PROGRAM BEDAH RUMAH RAKYAT TIDAK LAYAK HUNI ( BERARTI )
NAMA PENERIMA BANTUAN : YOHANES KOLO
ALAMAT : RT.006/RW.003
DESA : MAURISU UTARA
KECAMATAN : BIKOMI SELATAN
KABUPATEN : TIMOR TENGAH UTARA
NILAI PEKERJAAN : Rp. 25.000.000,-
PROGRESS
JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT. BOBOT % VOLUME
HARGA ( Rp ) SAT. BOBOT %
REALISASI
1 PEKERJAAN PONDASI 5.16 M² 1,235,000 119.09 1,235,000 M² 5.16

2 PEKERJAAN SLOOF ( 15/20 ) 46.70 M² 3,066,167 12.26 3,065,000 M² 12.26

3 PEKERJAAN KOLOM ( 10 X 10 ) 24.86 M² 1,583,167 6.33 1,583,167 M² 6.33

4 PEKERJAAN PASANGAN TEMBOK 1.420.35 M² 8,355,831 33.42 5,472,500 M² 21.89

5 PEKERJAAN PLESTERAN 44.00 M² 2,586,668 10.35 - M² 0.00

6 PEKERJAAN ACIAN 7.00 M² 371,000 1.48 - M² 0.00

7 PEKERJAAN RINGBALK DAN GEWEL 50.38 M² 3,129,667 12.52 - M² 0.00

8 PEKERJAAN ATAP DAN KUDA-KUDA 85.00 M² 3,530,000 14.12 - M² 0.00

9 PEKERJAAN LANTAI 22.73 M² 1,340,501 5.36 - M² 0.00

10 PEKERJAAN LAIN-LAIN 91.00 Ls 1,037,000 4.15 - Ls 0.00

TOTAL 25,000,000 100.00 10,120,667 40.48

Progres sampai dengan Bulan November = 40.48 %


LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PROGRAM BEDAH RUMAH RAKYAT TIDAK LAYAK HUNI ( BERARTI )
NAMA PENERIMA BANTUAN : TIBERTIUS BANI
ALAMAT : RT.006/RW.003
DESA : MAURISU UTARA
KECAMATAN : BIKOMI SELATAN
KABUPATEN : TIMOR TENGAH UTARA
NILAI PEKERJAAN : Rp. 25.000.000,-
PROGRESS
JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT. BOBOT % VOLUME
HARGA ( Rp ) SAT. BOBOT %
REALISASI
1 PEKERJAAN PONDASI 5.16 M² 1,235,000 119.09 1,235,000 M² 5.16
2 PEKERJAAN SLOOF ( 15/20 ) 46.70 M² 3,066,167 12.26 3,065,000 M² 12.26
3 PEKERJAAN KOLOM ( 10 X 10 ) 24.86 M² 1,583,167 6.33 1,583,167 M² 6.33
4 PEKERJAAN PASANGAN TEMBOK 1.420.35 M² 8,355,831 33.42 5,472,500 M² 21.89
5 PEKERJAAN PLESTERAN 44.00 M² 2,586,668 10.35 - M² 0.00
6 PEKERJAAN ACIAN 7.00 M² 371,000 1.48 - M² 0.00
7 PEKERJAAN RINGBALK DAN GEWEL 50.38 M² 3,129,667 12.52 3,130,000.00 M² 12.52
8 PEKERJAAN ATAP DAN KUDA-KUDA 85.00 M² 3,530,000 14.12 - M² 0.00
9 PEKERJAAN LANTAI 22.73 M² 1,340,501 5.36 - M² 0.00
10 PEKERJAAN LAIN-LAIN 91.00 Ls 1,037,000 4.15 - Ls 0.00
TOTAL 25,000,000 100.00 13,250,667 53.00

Progres sampai dengan Bulan November = 53.00 %


LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PROGRAM BEDAH RUMAH RAKYAT TIDAK LAYAK HUNI ( BERARTI )
NAMA PENERIMA BANTUAN : GREGORIUS MOLO
ALAMAT : RT.006/RW.003
DESA : MAURISU UTARA
KECAMATAN : BIKOMI SELATAN
KABUPATEN : TIMOR TENGAH UTARA
NILAI PEKERJAAN : Rp. 25.000.000,-
PROGRESS
JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT. BOBOT % VOLUME
HARGA ( Rp ) SAT. BOBOT %
REALISASI
1 PEKERJAAN PONDASI 5.16 M² 1,235,000 119.09 1,235,000 M² 5.16

2 PEKERJAAN SLOOF ( 15/20 ) 46.70 M² 3,066,167 12.26 3,065,000 M² 12.26

3 PEKERJAAN KOLOM ( 10 X 10 ) 24.86 M² 1,583,167 6.33 1,583,167 M² 6.33

4 PEKERJAAN PASANGAN TEMBOK 1.420.35 M² 8,355,831 33.42 8,190,000 M² 32.76

5 PEKERJAAN PLESTERAN 44.00 M² 2,586,668 10.35 - M² 0.00

6 PEKERJAAN ACIAN 7.00 M² 371,000 1.48 - M² 0.00

7 PEKERJAAN RINGBALK DAN GEWEL 50.38 M² 3,129,667 12.52 1,622,500.00 M² 6.49

8 PEKERJAAN ATAP DAN KUDA-KUDA 85.00 M² 3,530,000 14.12 3,530,000 M² 14.12

9 PEKERJAAN LANTAI 22.73 M² 1,340,501 5.36 - M² 0.00

10 PEKERJAAN LAIN-LAIN 91.00 Ls 1,037,000 4.15 - Ls 0.00

TOTAL 25,000,000 100.00 17,990,667 71.96

Progres sampai dengan Bulan November = 71.96 %


LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PROGRAM BEDAH RUMAH RAKYAT TIDAK LAYAK HUNI ( BERARTI )
NAMA PENERIMA BANTUAN : PETRUS NAITILI
ALAMAT : RT.005/RW.003
DESA : MAURISU UTARA
KECAMATAN : BIKOMI SELATAN
KABUPATEN : TIMOR TENGAH UTARA
NILAI PEKERJAAN : Rp. 25.000.000,-
PROGRESS
JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT. BOBOT % VOLUME
HARGA ( Rp ) SAT. BOBOT %
REALISASI
1 PEKERJAAN PONDASI 5.16 M² 1,235,000 119.09 1,235,000 M² 5.16
2 PEKERJAAN SLOOF ( 15/20 ) 46.70 M² 3,066,167 12.26 3,065,000 M² 12.26
3 PEKERJAAN KOLOM ( 10 X 10 ) 24.86 M² 1,583,167 6.33 1,583,167 M² 6.33
4 PEKERJAAN PASANGAN TEMBOK 1.420.35 M² 8,355,831 33.42 6,975,000 M² 27.90
5 PEKERJAAN PLESTERAN 44.00 M² 2,586,668 10.35 - M² 0.00
6 PEKERJAAN ACIAN 7.00 M² 371,000 1.48 - M² 0.00
7 PEKERJAAN RINGBALK DAN GEWEL 50.38 M² 3,129,667 12.52 3,130,000.00 M² 12.52
8 PEKERJAAN ATAP DAN KUDA-KUDA 85.00 M² 3,530,000 14.12 2,222,500 M² 8.89
9 PEKERJAAN LANTAI 22.73 M² 1,340,501 5.36 - M² 0.00
10 PEKERJAAN LAIN-LAIN 91.00 Ls 1,037,000 4.15 - Ls 0.00
TOTAL 25,000,000 100.00 16,975,667 67.90

Progres sampai dengan Bulan November = 67.90 %


LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PROGRAM BEDAH RUMAH RAKYAT TIDAK LAYAK HUNI ( BERARTI )
NAMA PENERIMA BANTUAN : YOSEP TPOY
ALAMAT : RT.001/RW.001
DESA : MAURISU UTARA
KECAMATAN : BIKOMI SELATAN
KABUPATEN : TIMOR TENGAH UTARA
NILAI PEKERJAAN : Rp. 25.000.000,-
PROGRESS
JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT. BOBOT % VOLUME
HARGA ( Rp ) SAT. BOBOT %
REALISASI
1 PEKERJAAN PONDASI 5.16 M² 1,235,000 119.09 1,235,000 M² 5.16

2 PEKERJAAN SLOOF ( 15/20 ) 46.70 M² 3,066,167 12.26 3,065,000 M² 12.26

3 PEKERJAAN KOLOM ( 10 X 10 ) 24.86 M² 1,583,167 6.33 1,583,167 M² 6.33

4 PEKERJAAN PASANGAN TEMBOK 1.420.35 M² 8,355,831 33.42 8,355,000 M² 33.42

5 PEKERJAAN PLESTERAN 44.00 M² 2,586,668 10.35 - M² 0.00

6 PEKERJAAN ACIAN 7.00 M² 371,000 1.48 - M² 0.00

7 PEKERJAAN RINGBALK DAN GEWEL 50.38 M² 3,129,667 12.52 3,130,000.00 M² 12.52

8 PEKERJAAN ATAP DAN KUDA-KUDA 85.00 M² 3,530,000 14.12 3,530,000 M² 14.12

9 PEKERJAAN LANTAI 22.73 M² 1,340,501 5.36 - M² 0.00

10 PEKERJAAN LAIN-LAIN 91.00 Ls 1,037,000 4.15 - Ls 0.00

TOTAL 25,000,000 100.00 19,663,167 78.65

Progres sampai dengan Bulan November =78.65 %


LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PROGRAM BEDAH RUMAH RAKYAT TIDAK LAYAK HUNI ( BERARTI )
NAMA PENERIMA BANTUAN : YASIXTUS NULLE
ALAMAT : RT.004/RW.002
DESA : MAURISU UTARA
KECAMATAN : BIKOMI SELATAN
KABUPATEN : TIMOR TENGAH UTARA
NILAI PEKERJAAN : Rp. 25.000.000,-
PROGRESS
JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT. BOBOT % VOLUME
HARGA ( Rp ) SAT. BOBOT %
REALISASI
1 PEKERJAAN PONDASI 5.16 M² 1,235,000 119.09 1,235,000 M² 5.16

2 PEKERJAAN SLOOF ( 15/20 ) 46.70 M² 3,066,167 12.26 3,065,000 M² 12.26

3 PEKERJAAN KOLOM ( 10 X 10 ) 24.86 M² 1,583,167 6.33 1,583,167 M² 6.33

4 PEKERJAAN PASANGAN TEMBOK 1.420.35 M² 8,355,831 33.42 8,355,000 M² 33.42

5 PEKERJAAN PLESTERAN 44.00 M² 2,586,668 10.35 1,280,000 M² 5.12

6 PEKERJAAN ACIAN 7.00 M² 371,000 1.48 280,000 M² 1.12

7 PEKERJAAN RINGBALK DAN GEWEL 50.38 M² 3,129,667 12.52 3,130,000.00 M² 12.52

8 PEKERJAAN ATAP DAN KUDA-KUDA 85.00 M² 3,530,000 14.12 3,530,000 M² 14.12

9 PEKERJAAN LANTAI 22.73 M² 1,340,501 5.36 1,340,000 M² 5.36

10 PEKERJAAN LAIN-LAIN 91.00 Ls 1,037,000 4.15 - Ls 0.00

TOTAL 25,000,000 100.00 22,563,167 90.25

Progres sampai dengan Bulan November = 90.25 %


LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PROGRAM BEDAH RUMAH RAKYAT TIDAK LAYAK HUNI ( BERARTI )
NAMA PENERIMA BANTUAN : DORATEA KOLO
ALAMAT : RT.004/RW.002
DESA : MAURISU UTARA
KECAMATAN : BIKOMI SELATAN
KABUPATEN : TIMOR TENGAH UTARA
NILAI PEKERJAAN : Rp. 25.000.000,-
PROGRESS
JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT. BOBOT % VOLUME
HARGA ( Rp ) SAT. BOBOT %
REALISASI
1 PEKERJAAN PONDASI 5.16 M² 1,235,000 119.09 1,235,000 M² 5.16

2 PEKERJAAN SLOOF ( 15/20 ) 46.70 M² 3,066,167 12.26 3,065,000 M² 12.26

3 PEKERJAAN KOLOM ( 10 X 10 ) 24.86 M² 1,583,167 6.33 1,583,167 M² 6.33

4 PEKERJAAN PASANGAN TEMBOK 1.420.35 M² 8,355,831 33.42 7,225,000 M² 28.90

5 PEKERJAAN PLESTERAN 44.00 M² 2,586,668 10.35 2,197,500 M² 8.79

6 PEKERJAAN ACIAN 7.00 M² 371,000 1.48 250,000 M² 1.00

7 PEKERJAAN RINGBALK DAN GEWEL 50.38 M² 3,129,667 12.52 3,130,000.00 M² 12.52

8 PEKERJAAN ATAP DAN KUDA-KUDA 85.00 M² 3,530,000 14.12 3,530,000 M² 14.12

9 PEKERJAAN LANTAI 22.73 M² 1,340,501 5.36 - M² 0.00

10 PEKERJAAN LAIN-LAIN 91.00 Ls 1,037,000 4.15 - Ls 0.00

TOTAL 25,000,000 100.00 20,980,667 83.92

Progres sampai dengan Bulan November = 83.92 %


LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PROGRAM BEDAH RUMAH RAKYAT TIDAK LAYAK HUNI ( BERARTI )
NAMA PENERIMA BANTUAN : YEREMIAS SUNI
ALAMAT : RT.004/RW.002
DESA : MAURISU UTARA
KECAMATAN : BIKOMI SELATAN
KABUPATEN : TIMOR TENGAH UTARA
NILAI PEKERJAAN : Rp. 25.000.000,-
PROGRESS
JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT. BOBOT % VOLUME
HARGA ( Rp ) SAT. BOBOT %
REALISASI
1 PEKERJAAN PONDASI 5.16 M² 1,235,000 119.09 1,235,000 M² 5.16

2 PEKERJAAN SLOOF ( 15/20 ) 46.70 M² 3,066,167 12.26 3,065,000 M² 12.26

3 PEKERJAAN KOLOM ( 10 X 10 ) 24.86 M² 1,583,167 6.33 1,583,167 M² 6.33

4 PEKERJAAN PASANGAN TEMBOK 1.420.35 M² 8,355,831 33.42 8,190,000 M² 32.76

5 PEKERJAAN PLESTERAN 44.00 M² 2,586,668 10.35 822,500 M² 3.29

6 PEKERJAAN ACIAN 7.00 M² 371,000 1.48 222,500 M² 0.89

7 PEKERJAAN RINGBALK DAN GEWEL 50.38 M² 3,129,667 12.52 3,130,000.00 M² 12.52

8 PEKERJAAN ATAP DAN KUDA-KUDA 85.00 M² 3,530,000 14.12 3,530,000 M² 14.12

9 PEKERJAAN LANTAI 22.73 M² 1,340,501 5.36 597,500 M² 2.39

10 PEKERJAAN LAIN-LAIN 91.00 Ls 1,037,000 4.15 - Ls 0.00

TOTAL 25,000,000 100.00 21,140,667 84.56

Progres sampai dengan Bulan November = 84.56 %


LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PROGRAM BEDAH RUMAH RAKYAT TIDAK LAYAK HUNI ( BERARTI )
NAMA PENERIMA BANTUAN : YOHANES LAKE
ALAMAT : RT.004/RW.002
DESA : MAURISU UTARA
KECAMATAN : BIKOMI SELATAN
KABUPATEN : TIMOR TENGAH UTARA
NILAI PEKERJAAN : Rp. 25.000.000,-
PROGRESS
JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT. BOBOT % VOLUME
HARGA ( Rp ) SAT. BOBOT %
REALISASI
1 PEKERJAAN PONDASI 5.16 M² 1,235,000 119.09 1,235,000 M² 5.16
2 PEKERJAAN SLOOF ( 15/20 ) 46.70 M² 3,066,167 12.26 3,065,000 M² 12.26
3 PEKERJAAN KOLOM ( 10 X 10 ) 24.86 M² 1,583,167 6.33 1,583,167 M² 6.33
4 PEKERJAAN PASANGAN TEMBOK 1.420.35 M² 8,355,831 33.42 8,355,000 M² 33.42
5 PEKERJAAN PLESTERAN 44.00 M² 2,586,668 10.35 - M² 0.00
6 PEKERJAAN ACIAN 7.00 M² 371,000 1.48 - M² 0.00
7 PEKERJAAN RINGBALK DAN GEWEL 50.38 M² 3,129,667 12.52 1,622,500.00 M² 6.49
8 PEKERJAAN ATAP DAN KUDA-KUDA 85.00 M² 3,530,000 14.12 3,530,000 M² 14.12
9 PEKERJAAN LANTAI 22.73 M² 1,340,501 5.36 - M² 0.00
10 PEKERJAAN LAIN-LAIN 91.00 Ls 1,037,000 4.15 - Ls 0.00
TOTAL 25,000,000 100.00 18,155,667 72.62

Progres sampai dengan Bulan November = 72.62 %


LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PROGRAM BEDAH RUMAH RAKYAT TIDAK LAYAK HUNI ( BERARTI )
NAMA PENERIMA BANTUAN : BRIYANTO TIMO
ALAMAT : RT.003/RW.002
DESA : MAURISU UTARA
KECAMATAN : BIKOMI SELATAN
KABUPATEN : TIMOR TENGAH UTARA
NILAI PEKERJAAN : Rp. 25.000.000,-
PROGRESS
JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT. BOBOT % VOLUME
HARGA ( Rp ) SAT. BOBOT %
REALISASI
1 PEKERJAAN PONDASI 5.16 M² 1,235,000 119.09 1,235,000 M² 5.16

2 PEKERJAAN SLOOF ( 15/20 ) 46.70 M² 3,066,167 12.26 3,065,000 M² 12.26

3 PEKERJAAN KOLOM ( 10 X 10 ) 24.86 M² 1,583,167 6.33 1,583,167 M² 6.33

4 PEKERJAAN PASANGAN TEMBOK 1.420.35 M² 8,355,831 33.42 8,190,000 M² 32.76

5 PEKERJAAN PLESTERAN 44.00 M² 2,586,668 10.35 195,000 M² 0.78

6 PEKERJAAN ACIAN 7.00 M² 371,000 1.48 250,000 M² 1.00

7 PEKERJAAN RINGBALK DAN GEWEL 50.38 M² 3,129,667 12.52 1,622,500.00 M² 6.49

8 PEKERJAAN ATAP DAN KUDA-KUDA 85.00 M² 3,530,000 14.12 3,530,000 M² 14.12

9 PEKERJAAN LANTAI 22.73 M² 1,340,501 5.36 - M² 3.67

10 PEKERJAAN LAIN-LAIN 91.00 Ls 1,037,000 4.15 - Ls 0.00

TOTAL 25,000,000 100.00 18,435,667 77.41

Progres sampai dengan Bulan November = 77.41 %


LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PROGRAM BEDAH RUMAH RAKYAT TIDAK LAYAK HUNI ( BERARTI )
NAMA PENERIMA BANTUAN : YOHANES Y.K. LAKE
ALAMAT : RT.003/RW.002
DESA : MAURISU UTARA
KECAMATAN : BIKOMI SELATAN
KABUPATEN : TIMOR TENGAH UTARA
NILAI PEKERJAAN : Rp. 25.000.000,-
PROGRESS
JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT. BOBOT % VOLUME
HARGA ( Rp ) SAT. BOBOT %
REALISASI
1 PEKERJAAN PONDASI 5.16 M² 1,235,000 119.09 1,235,000 M² 5.16

2 PEKERJAAN SLOOF ( 15/20 ) 46.70 M² 3,066,167 12.26 3,065,000 M² 12.26

3 PEKERJAAN KOLOM ( 10 X 10 ) 24.86 M² 1,583,167 6.33 1,583,167 M² 6.33

4 PEKERJAAN PASANGAN TEMBOK 1.420.35 M² 8,355,831 33.42 8,355,000 M² 33.42

5 PEKERJAAN PLESTERAN 44.00 M² 2,586,668 10.35 - M² 0.00

6 PEKERJAAN ACIAN 7.00 M² 371,000 1.48 - M² 0.00

7 PEKERJAAN RINGBALK DAN GEWEL 50.38 M² 3,129,667 12.52 3,130,000.00 M² 12.52

8 PEKERJAAN ATAP DAN KUDA-KUDA 85.00 M² 3,530,000 14.12 3,530,000 M² 14.12

9 PEKERJAAN LANTAI 22.73 M² 1,340,501 5.36 337,500 M² 1.35

10 PEKERJAAN LAIN-LAIN 91.00 Ls 1,037,000 4.15 - Ls 0.00

TOTAL 25,000,000 100.00 20,000,667 80.00

Progres sampai dengan Bulan November = 80.00 %


LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PROGRAM BEDAH RUMAH RAKYAT TIDAK LAYAK HUNI ( BERARTI )
NAMA PENERIMA BANTUAN : VINSENSIUS SANI
ALAMAT : RT.004/RW.002
DESA : MAURISU UTARA
KECAMATAN : BIKOMI SELATAN
KABUPATEN : TIMOR TENGAH UTARA
NILAI PEKERJAAN : Rp. 25.000.000,-
PROGRESS
JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT. BOBOT % VOLUME
HARGA ( Rp ) SAT. BOBOT %
REALISASI
1 PEKERJAAN PONDASI 5.16 M² 1,235,000 119.09 1,235,000 M² 5.16

2 PEKERJAAN SLOOF ( 15/20 ) 46.70 M² 3,066,167 12.26 3,065,000 M² 12.26

3 PEKERJAAN KOLOM ( 10 X 10 ) 24.86 M² 1,583,167 6.33 1,583,167 M² 6.33

4 PEKERJAAN PASANGAN TEMBOK 1.420.35 M² 8,355,831 33.42 8,355,000 M² 33.42

5 PEKERJAAN PLESTERAN 44.00 M² 2,586,668 10.35 - M² 0.00

6 PEKERJAAN ACIAN 7.00 M² 371,000 1.48 - M² 0.00

7 PEKERJAAN RINGBALK DAN GEWEL 50.38 M² 3,129,667 12.52 1,622,500.00 M² 6.49

8 PEKERJAAN ATAP DAN KUDA-KUDA 85.00 M² 3,530,000 14.12 3,530,000 M² 14.12

9 PEKERJAAN LANTAI 22.73 M² 1,340,501 5.36 - M² 0.00

10 PEKERJAAN LAIN-LAIN 91.00 Ls 1,037,000 4.15 - Ls 0.00

TOTAL 25,000,000 100.00 18,155,667 72.62

Progres sampai dengan Bulan November = 72.62 %


LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PROGRAM BEDAH RUMAH RAKYAT TIDAK LAYAK HUNI ( BERARTI )
NAMA PENERIMA BANTUAN : HIRONIMUS TIMO
ALAMAT : RT.004/RW.002
DESA : MAURISU UTARA
KECAMATAN : BIKOMI SELATAN
KABUPATEN : TIMOR TENGAH UTARA
NILAI PEKERJAAN : Rp. 25.000.000,-
PROGRESS
JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT. BOBOT % VOLUME
HARGA ( Rp ) SAT. BOBOT %
REALISASI
1 PEKERJAAN PONDASI 5.16 M² 1,235,000 119.09 1,235,000 M² 5.16

2 PEKERJAAN SLOOF ( 15/20 ) 46.70 M² 3,066,167 12.26 3,065,000 M² 12.26

3 PEKERJAAN KOLOM ( 10 X 10 ) 24.86 M² 1,583,167 6.33 1,583,167 M² 6.33

4 PEKERJAAN PASANGAN TEMBOK 1.420.35 M² 8,355,831 33.42 8,355,000 M² 33.42

5 PEKERJAAN PLESTERAN 44.00 M² 2,586,668 10.35 - M² 0.00

6 PEKERJAAN ACIAN 7.00 M² 371,000 1.48 - M² 0.00

7 PEKERJAAN RINGBALK DAN GEWEL 50.38 M² 3,129,667 12.52 3,130,000.00 M² 12.52

8 PEKERJAAN ATAP DAN KUDA-KUDA 85.00 M² 3,530,000 14.12 3,530,000 M² 14.12

9 PEKERJAAN LANTAI 22.73 M² 1,340,501 5.36 - M² 0.00

10 PEKERJAAN LAIN-LAIN 91.00 Ls 1,037,000 4.15 - Ls 0.00

TOTAL 25,000,000 100.00 19,663,167 78.65

Progres sampai dengan Bulan November = 78.62 %


LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PROGRAM BEDAH RUMAH RAKYAT TIDAK LAYAK HUNI ( BERARTI )
NAMA PENERIMA BANTUAN : FELIX K. UN TAOLIN
ALAMAT : RT.001/RW.001
DESA : MAURISU UTARA
KECAMATAN : BIKOMI SELATAN
KABUPATEN : TIMOR TENGAH UTARA
NILAI PEKERJAAN : Rp. 25.000.000,-
PROGRESS
JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT. BOBOT % VOLUME
HARGA ( Rp ) SAT. BOBOT %
REALISASI
1 PEKERJAAN PONDASI 5.16 M² 1,235,000 119.09 1,235,000 M² 5.16

2 PEKERJAAN SLOOF ( 15/20 ) 46.70 M² 3,066,167 12.26 3,065,000 M² 12.26

3 PEKERJAAN KOLOM ( 10 X 10 ) 24.86 M² 1,583,167 6.33 1,583,167 M² 6.33

4 PEKERJAAN PASANGAN TEMBOK 1.420.35 M² 8,355,831 33.42 7,522,500 M² 30.09

5 PEKERJAAN PLESTERAN 44.00 M² 2,586,668 10.35 - M² 0.00

6 PEKERJAAN ACIAN 7.00 M² 371,000 1.48 - M² 0.00

7 PEKERJAAN RINGBALK DAN GEWEL 50.38 M² 3,129,667 12.52 1,622,500.00 M² 6.49

8 PEKERJAAN ATAP DAN KUDA-KUDA 85.00 M² 3,530,000 14.12 3,530,000 M² 14.12

9 PEKERJAAN LANTAI 22.73 M² 1,340,501 5.36 - M² 5.36

10 PEKERJAAN LAIN-LAIN 91.00 Ls 1,037,000 4.15 - Ls 0.00

TOTAL 25,000,000 100.00 17,323,167 74.65

Progres sampai dengan Bulan November = 74.65 %


LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PROGRAM BEDAH RUMAH RAKYAT TIDAK LAYAK HUNI ( BERARTI )
NAMA PENERIMA BANTUAN :THERESIA TPOY
ALAMAT : RT.001/RW.001
DESA : MAURISU UTARA
KECAMATAN : BIKOMI SELATAN
KABUPATEN : TIMOR TENGAH UTARA
NILAI PEKERJAAN : Rp. 25.000.000,-
PROGRESS
JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT. BOBOT % VOLUME
HARGA ( Rp ) SAT. BOBOT %
REALISASI
1 PEKERJAAN PONDASI 5.16 M² 1,235,000 119.09 1,235,000 M² 5.16

2 PEKERJAAN SLOOF ( 15/20 ) 46.70 M² 3,066,167 12.26 3,065,000 M² 12.26

3 PEKERJAAN KOLOM ( 10 X 10 ) 24.86 M² 1,583,167 6.33 1,583,167 M² 6.33

4 PEKERJAAN PASANGAN TEMBOK 1.420.35 M² 8,355,831 33.42 8,355,000 M² 33.42

5 PEKERJAAN PLESTERAN 44.00 M² 2,586,668 10.35 - M² 0.00

6 PEKERJAAN ACIAN 7.00 M² 371,000 1.48 - M² 0.00

7 PEKERJAAN RINGBALK DAN GEWEL 50.38 M² 3,129,667 12.52 3,130,000.00 M² 12.52

8 PEKERJAAN ATAP DAN KUDA-KUDA 85.00 M² 3,530,000 14.12 3,530,000 M² 14.12

9 PEKERJAAN LANTAI 22.73 M² 1,340,501 5.36 - M² 0.00

10 PEKERJAAN LAIN-LAIN 91.00 Ls 1,037,000 4.15 - Ls 0.00

TOTAL 25,000,000 100.00 19,663,167 78.65

Progres sampai dengan Bulan November = 78.65 %


LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PROGRAM BEDAH RUMAH RAKYAT TIDAK LAYAK HUNI ( BERARTI )
NAMA PENERIMA BANTUAN :PATRISIA NULLE
ALAMAT : RT.001/RW.001
DESA : MAURISU UTARA
KECAMATAN : BIKOMI SELATAN
KABUPATEN : TIMOR TENGAH UTARA
NILAI PEKERJAAN : Rp. 25.000.000,-
PROGRESS
JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT. BOBOT % VOLUME
HARGA ( Rp ) SAT. BOBOT %
REALISASI
1 PEKERJAAN PONDASI 5.16 M² 1,235,000 119.09 1,235,000 M² 5.16

2 PEKERJAAN SLOOF ( 15/20 ) 46.70 M² 3,066,167 12.26 3,065,000 M² 12.26

3 PEKERJAAN KOLOM ( 10 X 10 ) 24.86 M² 1,583,167 6.33 1,583,167 M² 6.33

4 PEKERJAAN PASANGAN TEMBOK 1.420.35 M² 8,355,831 33.42 8,355,000 M² 33.42

5 PEKERJAAN PLESTERAN 44.00 M² 2,586,668 10.35 - M² 0.00

6 PEKERJAAN ACIAN 7.00 M² 371,000 1.48 - M² 0.00

7 PEKERJAAN RINGBALK DAN GEWEL 50.38 M² 3,129,667 12.52 3,130,000.00 M² 12.52

8 PEKERJAAN ATAP DAN KUDA-KUDA 85.00 M² 3,530,000 14.12 3,530,000 M² 14.12

9 PEKERJAAN LANTAI 22.73 M² 1,340,501 5.36 - M² 3.11

10 PEKERJAAN PINTU DAN JENDELA 91.00 Ls 1,037,000 4.15 - Ls 0.00

TOTAL 25,000,000 100.00 19,663,167 81.76

Progres sampai dengan Bulan November = 81.76 %