RENCANA ANGGARAN BIAYA IPAL KAPASITAS 6 Mᶟ

NO URAIAN MATRIAL DAN TENAGA KERJA VOLUME SATUAN HARGA SATUAN JUMLAH
1 ATAP BAJA RINGAN 2 M2 250,000 500,000
2 PLAT BETON BERTULANG U 100X150X0.6 16 BUAH 420,000 6,720,000
3 PLAT BETON BERTULANG TUTUP ATAS U 100X100X0.6 5 BUAH 380,000 1,900,000
4 PIPA PVC WAVIN AW 3" 4 BATANG 280,000 1,120,000
5 SHOCK T 3" 6 BUAH 30,000 180,000
6 PIPA PVC WAVIN AW 1" 5 BATANG 85,000 425,000
7 SHOCK T 1" 18 BUAH 10,000 180,000
8 SHOCK SAMBUNG 1" 6 BUAH 10,000 60,000
9 LEM PARALON 1 KALENG 24,000 24,000
10 BLOWER OKSIGEN 0,5HP 1 BUAH 1,500,000 1,500,000
11 BLOWER SIRKULASI 1 BUAH 1,500,000 1,500,000
12 BUIS BETON Ø100 1 BUAH 650,000 650,000
13 BATU SPLIT PENYARINGAN 2 M2 400,000 800,000
14 IJUK PENYARINGAN 1 LS 500,000 500,000
15 PASIR CUCI 1.5 M3 250,000 375,000
16 ONGKOS TENAGA KERJA 1 PAKET 2,600,000 2,600,000
-
-
19,034,000