ANALISA BIAYA OPERASI ALAT BERAT

Kode Analisa Alat :


Jenis Alat : Excavator Long Arm , Excavator+Ponton, Ponton dan Bulldozer
Satuan Pembayaran : Rupiah / Jam

No. URAIAN KODE SATUAN PERHITUNGAN BIAYA OPERASI PERALATAN KET

A. URAIAN PERALATAN Excavator 2 Excavator 1


Ponton - 2 Bulldozer
1. Jenis Peralatan (Long Arm) + Ponton -1
2. Merk / Type 80-140 HP 80-140 HP 100-150 HP
3. Tenaga Pw HP 133,0 133,0 120,0 150,0
4. Kapasitas Cp - 0,6 0,6 - -
5. Umur Ekonomis A Tahun 5,0 5,0 5,0 5,0
6. Jam Operasi Dalam 1 Tahun W Jam 2.000 2.000 2.000 2.000
7. Harga Alat B Rp. 1.080.000.000,00 1.265.000.000,00 185.000.000,00 825.000.000,00

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = (10% X B) C Rp. 108.000.000,00 126.500.000,00 18.500.000,00 82.500.000,00
Suku Bunga
2. Faktor Angsuran Modal = i(1+i)^A / (1+i)^A-1 D - 0,26380 0,26380 0,26380 0,26380 i = 10%

3. Biaya Pasti Per Jam :


a. Biaya Pengembalian Modal = (B - C) x D / W E Rp/Jam 128.205,58 150.166,72 21.961,14 97.934,81

b. Asuransi, dll = 0.002 x B / W F Rp/Jam 1.080,00 1.265,00 185,00 825,00 Asuransi 0,2%

Biaya Pasti per Jam = (E + F) G Rp/Jam 129.285,58 151.431,72 22.146,14 98.759,81

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = {12%-15%} x Pw x Ms H 143.640,00 143.640,00 129.600,00 162.000,00 12,0%

2. Pelumas = {2,5%-3%} x Pw x Mp I 91.437,50 91.437,50 82.500,00 103.125,00 2,50%

Biaya Bengkel = {6,25%-8,75%} x B / W J 33.750,00 39.531,25 5.781,25 25.781,25 6,25%

3. Perawatan dan Perbaikan = {12,5%-17,5%} x B / W K 67.500,00 79.062,50 11.562,50 51.562,50 12,50%

4. Operator = {m orang/jam} x U1 M 12.857,14 12.857,14 12.857,14 12.857,14


5. Pembantu Operator = {n orang/jam} x U2 L 6.428,57 6.428,57 6.428,57 6.428,57

Biaya Operasi (Per jam) = (H+I+J+K+M+N) P Rp/Jam 355.613,21 372.956,96 248.729,46 361.754,46

D. BIAYA OPERASI ALAT PER JAM KERJA = (G+P) S Rp/Jam 484.898,79 524.388,68 270.875,60 460.514,28

E. LAIN - LAIN
1. Bahan Bakar Premium (non Subsidi) Mb Liter 8.500,00 8.500,00 8.500,00 8.500,00
2. Bahan Bakar Solar (non Subsidi) Ms Liter 9.000,00 9.000,00 9.000,00 9.000,00
3. Minyak Pelumas Mp Liter 27.500,00 27.500,00 27.500,00 27.500,00
ANALISA BIAYA OPERASI ALAT BERAT

Kode Analisa Alat :


Jenis Alat : Excavator, Dump Truck, Vibro Roller dan Water Tanker
Satuan Pembayaran : Rupiah / Jam

No. URAIAN KODE SATUAN PERHITUNGAN BIAYA OPERASI PERALATAN KET

A. URAIAN PERALATAN Excavator Dump Truck


Vibro Roller Water Tanker
1. Jenis Peralatan (Standart) 4 M3
2. Merk / Type 80-140 HP 3 - 4 M3 5 - 8 Ton 3000-4500 ltr
3. Tenaga Pw HP 133,0 100,0 82,0 100,0
4. Kapasitas Cp - 0,9 4,0 7,1 4.000,0
5. Umur Ekonomis A Tahun 5,0 5,0 5,0 5,0
6. Jam Operasi Dalam 1 Tahun W Jam 2.000 2.000 2.000 2.000
7. Harga Alat B Rp. 800.000.000,00 310.000.000,00 815.000.000,00 325.000.000,00

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = (10% X B) C Rp. 80.000.000,00 31.000.000,00 81.500.000,00 32.500.000,00
Suku Bunga
2. Faktor Angsuran Modal = i(1+i)^A / (1+i)^A-1 D - 0,26380 0,26380 0,26380 0,26380 i = 10%

3. Biaya Pasti Per Jam :


a. Biaya Pengembalian Modal = (B - C) x D / W E Rp/Jam 94.967,09 36.799,75 96.747,73 38.580,38

b. Asuransi, dll = 0.002 x B / W F Rp/Jam 800,00 310,00 815,00 325,00 Asuransi 0,2%

Biaya Pasti per Jam = (E + F) G Rp/Jam 95.767,09 37.109,75 97.562,73 38.905,38

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = {12%-15%} x Pw x Ms H 143.640,00 108.000,00 88.560,00 108.000,00 12,0%

2. Pelumas = {2,5%-3%} x Pw x Mp I 91.437,50 68.750,00 56.375,00 68.750,00 2,50%

Biaya Bengkel = {6,25%-8,75%} x B / W J 25.000,00 9.687,50 25.468,75 10.156,25 6,25%

3. Perawatan dan Perbaikan = {12,5%-17,5%} x B / W K 50.000,00 19.375,00 50.937,50 20.312,50 12,50%

4. Operator = {m orang/jam} x U1 M 12.857,14 12.857,14 12.857,14 12.857,14


5. Pembantu Operator = {n orang/jam} x U2 L 6.428,57 6.428,57 6.428,57 6.428,57

Biaya Operasi (Per jam) = (H+I+J+K+M+N) P Rp/Jam 329.363,21 225.098,21 240.626,96 226.504,46

D. BIAYA OPERASI ALAT PER JAM KERJA = (G+P) S Rp/Jam 425.130,31 262.207,96 338.189,69 265.409,85

E. LAIN - LAIN
1. Bahan Bakar Premium (non Subsidi) Mb Liter 8.500,00 8.500,00 8.500,00 8.500,00
2. Bahan Bakar Solar (non Subsidi) Ms Liter 9.000,00 9.000,00 9.000,00 9.000,00
3. Minyak Pelumas Mp Liter 27.500,00 27.500,00 27.500,00 27.500,00
ANALISA BIAYA OPERASI ALAT BERAT

Kode Analisa Alat :


Jenis Alat : Concrette Mixer, Concrette Vibrator, Tamper dan Jack Hammer
Satuan Pembayaran : Rupiah / Jam

No. URAIAN KODE SATUAN PERHITUNGAN BIAYA OPERASI PERALATAN KET

A. URAIAN PERALATAN Concrette Concrette


Tamper Jack Hammer
1. Jenis Peralatan Mixer Vibrator
2. Merk / Type 0,3 - 0,6 M3
3. Tenaga Pw HP 20,0 5,5 4,7 2,7
4. Kapasitas Cp - 500,0 25,0 121,0 1.330,0
5. Umur Ekonomis A Tahun 5,0 5,0 5,0 5,0
6. Jam Operasi Dalam 1 Tahun W Jam 2.000 2.000 2.000 2.000
7. Harga Alat B Rp. 18.500.000,00 7.500.000,00 9.500.000,00 12.000.000,00

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = (10% X B) C Rp. 1.850.000,00 750.000,00 950.000,00 1.200.000,00
Suku Bunga
2. Faktor Angsuran Modal = i(1+i)^A / (1+i)^A-1 D - 0,57619 0,31547 0,31547 0,26380 i = 10%

3. Biaya Pasti Per Jam :


a. Biaya Pengembalian Modal = (B - C) x D / W E Rp/Jam 4.796,79 1.064,71 1.348,64 1.424,51

b. Asuransi, dll = 0.002 x B / W F Rp/Jam 18,50 7,50 9,50 12,00 Asuransi 0,2%

Biaya Pasti per Jam = (E + F) G Rp/Jam 4.815,29 1.072,21 1.358,14 1.436,51

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = {12%-15%} x Pw x Ms H 21.600,00 5.610,00 4.794,00 2.754,00 12,0%

2. Pelumas = {2,5%-3%} x Pw x Mp I 13.750,00 3.781,25 3.231,25 1.856,25 2,50%

Biaya Bengkel = {6,25%-8,75%} x B / W J 578,13 234,38 296,88 375,00 6,25%

3. Perawatan dan Perbaikan = {12,5%-17,5%} x B / W K 1.156,25 468,75 593,75 750,00 12,50%

4. Operator = {m orang/jam} x U1 M 12.857,14 12.857,14 12.857,14 12.857,14


5. Pembantu Operator = {n orang/jam} x U2 L 6.428,57 6.428,57 6.428,57 6.428,57

Biaya Operasi (Per jam) = (H+I+J+K+M+N) P Rp/Jam 56.370,09 29.380,09 28.201,59 25.020,96

D. BIAYA OPERASI ALAT PER JAM KERJA = (G+P) S Rp/Jam 61.185,38 30.452,30 29.559,73 26.457,47

E. LAIN - LAIN
1. Bahan Bakar Premium (non Subsidi) Mb Liter 8.500,00 8.500,00 8.500,00 8.500,00
2. Bahan Bakar Solar (non Subsidi) Ms Liter 9.000,00 9.000,00 9.000,00 9.000,00
3. Minyak Pelumas Mp Liter 27.500,00 27.500,00 27.500,00 27.500,00
ANALISA BIAYA OPERASI ALAT BERAT

Kode Analisa Alat :


Jenis Alat : HAMMER 2 TON, TRIPOD TINGGI 5 METER DAN DUMP TRUCK 20 TON
Satuan Pembayaran : Rupiah / Jam

No. URAIAN KODE SATUAN PERHITUNGAN BIAYA OPERASI PERALATAN KET

A. URAIAN PERALATAN HAMMER TRIPOD DUMP TRUCK


1. Jenis Peralatan 10 - 20 T
2. Merk / Type 2 Ton 5 MTER
3. Tenaga Pw HP 5,0 20,0 190,0
4. Kapasitas Cp - 2,0 1,0 8,0
5. Umur Ekonomis A Tahun 5,0 5,0 5,0
6. Jam Operasi Dalam 1 Tahun W Jam 2.000 2.000 2.000
7. Harga Alat B Rp. 7.000.000,00 8.500.000,00 425.000.000,00

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = (10% X B) C Rp. 700.000,00 850.000,00 42.500.000,00
Suku Bunga
2. Faktor Angsuran Modal = i(1+i)^A / (1+i)^A-1 D - 0,57619 0,31547 0,26380 i = 10%

3. Biaya Pasti Per Jam :


a. Biaya Pengembalian Modal = (B - C) x D / W E Rp/Jam 1.815,00 1.206,68 50.451,27

b. Asuransi, dll = 0.002 x B / W F Rp/Jam 7,00 8,50 425,00 Asuransi 0,2%

Biaya Pasti per Jam = (E + F) G Rp/Jam 1.822,00 1.215,18 50.876,27

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = {12%-15%} x Pw x Ms H 5.400,00 21.600,00 205.200,00 12,0%

2. Pelumas = {2,5%-3%} x Pw x Mp I 3.437,50 13.750,00 130.625,00 2,50%

Biaya Bengkel = {6,25%-8,75%} x B / W J 218,75 265,63 13.281,25 6,25%

3. Perawatan dan Perbaikan = {12,5%-17,5%} x B / W K 437,50 531,25 26.562,50 12,50%

4. Operator = {m orang/jam} x U1 M 12.857,14 12.857,14 12.857,14


5. Pembantu Operator = {n orang/jam} x U2 L 6.428,57 6.428,57 6.428,57

Biaya Operasi (Per jam) = (H+I+J+K+M+N) P Rp/Jam 28.779,46 55.432,59 394.954,46

D. BIAYA OPERASI ALAT PER JAM KERJA = (G+P) S Rp/Jam 30.601,46 56.647,77 445.830,73

E. LAIN - LAIN
1. Bahan Bakar Premium (non Subsidi) Mb Liter 8.500,00 8.500,00 8.500,00 8.500,00
2. Bahan Bakar Solar (non Subsidi) Ms Liter 9.000,00 9.000,00 9.000,00 9.000,00
3. Minyak Pelumas Mp Liter 27.500,00 27.500,00 27.500,00 27.500,00