REKAPAN PEKERJAAN RENOVASI KANDANG DAN

PT. MULTI SARANA PAKANINDO


FARM CIKAWAO - BANDUNG

REVIEW HARGA
NO ITEM PEKERJAAN SATUAN HARGA JUMLAH HARGA
1 RENOVASI KANDANG 1 DAN 2 1 UNIT 330,848,400 330,848,400
2 GROUNDTANK 100 M3 1 UNIT 133,282,063 133,282,063
3 MENARA AIR 12 M 1 UNIT 157,584,176 157,584,176
4 RUMAH PANEL SUMUR 1.2 X 1.2M 1 UNIT 9,700,391 9,700,391
5 RUANG LIMBAH B3 2X2M 1 UNIT 21,029,064 21,029,064
6 RUANG GENSET 1 TAPAK PANEL KIRI (8x8M) 1 UNIT 144,329,038 144,329,038
7 DUDUKAN & R. TANGKI SOLAR 8.1 X 4 M 1 UNIT 53,287,575 53,287,575
8 GUDANG SEKAM (7x8 M) 1 UNIT 112,714,970 112,714,970
TOTAL 962,775,677
PPN 10 % 96,277,568
GRAND TOTAL 1,059,053,244
Pph 2 % 19,255,514
DIBAYARKAN 1,039,797,731
BILL OF QUANTITY : PT. MULTI SARANA PAKANINDO
JENIS PEKERJAAN : RENOVASI KANDANG
SPESIFIKASI : UNP. 50.38.5
LOKASI : FARM CIKAWAO
VALIDASI :

REVIEW HARGA RAP


Harga Satuan Jumlah Harga Satuan Jumlah
Material +
NO JENIS PEKERJAAN VOL SAT Harga Material + Jasa Harga
Jasa
(Rp.) (Rp.) (Rp.) (Rp.)

I PEKERJAAN PERSIAPAN
1 Pek. Pengukuran
Pembersihan & Pemasangan
dan Perapihan Bouvlank
Area setelah 1.00 ls 1,000,000 1,000,000 1,000,000 1,000,000
2 pekerjaan 1.00 ls 1,000,000 1,000,000 1,000,000 1,000,000
3 Biaya Air Kerja 1.00 ls 1,500,000 1,500,000 1,500,000 1,500,000

II PEKERJAAN RENOVASI KANDANG


A KANDANG 1
1 480 m Pek. Pemasang Balok UNP 50.38.5 2,400.00 Kg 18,000 43,200,000 15,700 37,680,000
2 Pek. Zinkromat 12.09 Kg 95,000 1,148,550 84,000 1,015,560
3 960 m Pemasangan Bambu 160.00 Btng 25,000 4,000,000 25,000 4,000,000
4 Perapihan Pasangan bambu lama 100.00 Btng 3,500 350,000 15,000 1,500,000
5 Pek. Slate Bambu 480.00 m2 20,000 9,600,000 24,000 11,520,000
Perapihan Slate Bambu Lama 960.00 m2 3,500 3,360,000 5,000 4,800,000
6 Pek. Cor Lantai K-175 T = 5 cm 72.00 m3 950,000 68,400,000 768,657 55,343,280
7 Pek. Pasangan 1 bata merah 19.20 m2 220,000 4,224,000 124,920 2,398,464
8 Plesteran 77.88 m2 40,000 3,115,200 40,705 3,170,105
9 Acian 77.88 m2 20,000 1,557,600 29,185 2,272,928
10 Seng Galvalume (bagian luar) 64.80 m2 52,000 3,369,600 65,000 4,212,000
11 Lantai PVC Collingpad 24.00 m2 180,000 4,320,000 180,000 4,320,000
12 Pintu Collingpad (Rangka Bajaringan 0.75, 2.00 unit 350,000
Penutup Wiremesh M6 + Kawat Loket) 700,000 400,000 800,000

B KANDANG 2
1 480 m Pek. Pemasang Balok UNP 50.38.5 2,400.00 Kg 18,000 43,200,000 15,700 37,680,000
2 Pek. Zinkromate 12.09 Kg 95,000 1,148,550 84,000 1,015,560
3 960 m Pemasangan Bambu 160.00 Btng 25,000 4,000,000 25,000 4,000,000
4 Perapihan Pasangan bambu lama 100.00 Btng 3,500 350,000 15,000 1,500,000
5 Pek. Slate Bambu 480.00 m2 20,000 9,600,000 24,000 11,520,000
Perapihan Slate Bambu Lama 960.00 m2 3,500 3,360,000 5,000 4,800,000
6 Pek. Cor Lantai K-175 T = 5 cm 70.75 m3 950,000 67,212,500 768,657 54,382,459
Pek. Cor Lantai K-175 T = 10 cm 2.50 m3 950,000 2,375,000 124,920 312,300
7 Pek. Pasangan 1 bata merah 19.20 m2 220,000 4,224,000 124,920 2,398,464
8 Plesteran 77.88 m2 40,000 3,115,200 40,705 3,170,105
9 Acian 77.88 m2 20,000 1,557,600 29,185 2,272,928
10 Seng Galvalume (bagian luar) 64.80 m2 52,000 3,369,600 65,000 4,212,000
11 Lantai PVC Collingpad 24.00 m2 180,000 4,320,000 180,000 4,320,000
12 Pintu Collingpad (Rangka Bajaringan 0.75, 2.00 unit 350,000
Penutup Wiremesh M6 + Kawat Loket) 700,000 400,000 800,000
13 Pek. Bongkaran Dinding bata 10.80 m2 20,000 216,000 15,000 162,000
14 47 m Pek. Pasangan Betu belah 33.84 m3 725,000 24,534,000 659,340 22,312,066
15 47 m Pek. Toping Plesteran + acian 14.10 m2 60,000 846,000 69,890 985,449
16 25 m Pek. Sloof Beton 20/25 1.25 m3 3,200,000 4,000,000 3,298,773 4,123,466
17 25 m Cor Rabat beton T = 10 cm K 100 (Selasar) 2.50 m3 750,000 1,875,000 530,536 1,326,340
TOTAL 330,848,400 297,825,474
BILL OF QUANTITY : PT. MULTI SARANA PAKANINDO
JENIS PEKERJAAN : GROUND TANK 100 M3
SPESIFIKASI : RANGKA ATAP BAJA RINGAN
LOKASI : FARM CIKAWAO
VALIDASI :
REVIEW HARGA RAP
Harga
Harga Satuan Jumlah Jumlah
Satuan
NO JENIS PEKERJAAN VOL SAT
Pekerjaan Harga Pekerjaan Harga
(Rp.) (Rp.) (Rp.) (Rp.)

I PEKERJAAN PERSIAPAN
1 Pek. Pengukuran & Pemasangan Bowplank 36.00 m' 10,000 360,000 38,150 1,373,400
2 Pembersihan dan Perapihan Area setelah pekerjaan 1.00 ls 500,000 500,000 500,000 500,000
3 Biaya Air Kerja 1.00 ls 1,000,000 1,000,000 1,000,000 1,000,000

II PEKERJAAN TANAH
1 Galian tanah untuk Pedestal 25x30 cm 0.75 m3 55,000 41,250 52,600 39,450
2 Galian tanah untuk Dinding Beton 20 cm 115.50 m3 55,000 6,352,500 52,600 6,075,300
3 Urugan Tanah Bekas Galian Pondasi 29.06 m3 25,000 726,563 13,050 379,266

III PEKERJAAN PONDASI DAN BETON


1 Urugan Pasir bawah sloof, t = 5 cm 1.75 m2 35,000 61,250 12,863 22,509
2 Sloof gantung 20/25cm , tul Ø 10, cincinØ 6 mm - 150 1.75 m3 3,200,000 5,600,000 3,298,773 5,772,853
3 Pedestal 25/25cm dan kolom terusan keatas uk 20/20cm , tul Ø 10, cincinØ 6 mm - 150 1.56 m3 3,200,000 5,000,000 3,293,799 5,146,560
4 Pekerjaan dinding Beton Cor K225 Wiremesh M6-150 double layer t=20cm 14.00 m3 3,200,000 44,800,000 2,050,472 28,706,603
5 Ringbalk 10/12 diatas dinding Beton, tul Ø 10, cincinØ 6 mm - 150 35.00 m' 48,000 1,680,000 42,199 1,476,973

IV PEKERJAAN LANTAI
1 Perataan dan Pemadatan Tanah untuk Lantai dan Rabat 50.00 m2 5,000 250,000 2,610 130,500
2 Pekerjaan lantai Cor K225 Wiremesh M6-150 double layer t=20cm 10.00 m3 3,200,000 32,000,000 2,050,472 20,504,717
3 Rabat K-100 tebal 7 cm finish acian 17.00 m2 59,500 1,011,500 53,054 901,911

VI PEKERJAAN ATAP DAN PLAFOND


1 Plafond Seng Galvalum Spandex 0.35,Rangka Atap baja ringan t = 0,75 mm 84.50 m2 295,000 24,927,500 205,190 17,338,555
2 Rangka hollow untuk ManHole 70x70cm 0.49 m2 350,000 171,500 350,000 171,500

XI PEKERJAAN PENGECATAN
1 Pengecatan Waterproof ex. Sika 80.00 m2 110,000 8,800,000 100,000 8,000,000

TOTAL 133,282,063 97,540,097


BILL OF QUANTITY : PT. MULTI SARANA PAKANINDO
JENIS BANGUNAN : PONDASI MENARA AIR TINGGI 12 M
SPESIFIKASI : RANGKA SIKU, PONDASI TAPAK
LOKASI : FARM CIKAWAO
VALIDASI :
REVIEW HARGA RAP
Harga Satuan Jumlah Harga Satuan Jumlah
NO JENIS PEKERJAAN VOL SAT Pekerjaan Harga Pekerjaan Harga
(Rp.) (Rp.) (Rp.) (Rp.)

I PEKERJAAN PERSIAPAN
1 Pek. Pengukuran & Pemasangan Bowplank 20.00 m' 10,000 200,000 38,150 763,000
2 Pembersihan dan Perapihan Area setelah pekerjaan 1.00 ls 500,000 500,000 500,000 500,000
3 Biaya Air Kerja 1.00 ls 1,500,000 1,500,000 1,500,000 1,500,000

II PEKERJAAN GALIAN / URUGAN


1 4 m Galian tanah untuk pondasi tapak dan sloof, 130 cm x 220 cm, 220 cm 25.17 m3 55,000 1,384,240 52,600 1,323,837
2 Urugan Tanah bekas galian tanah pondasi 6.29 m3 25,000 157,300 13,050 82,111

III PEKERJAAN PASANGAN PONDASI DAN SLOOF


1 Urugan Pasir Bawah Pondasi dan Sloof, t = 5 cm 38.36 m2 35,000 1,342,600 12,863 493,406
2 Pondasi Tapak Plat, 220x220x30cm Ø12-150 mm 5.81 m3 3,200,000 18,585,600 3,804,639 22,097,341
3 Kolom Pedestal 45cmx45cmx100cm, 4bh, Tul. 6 - Ø12, cincin Ø8 - 150 mm 0.81 m3 3,200,000 2,592,000 3,293,799 2,667,977
4 Sloof 20/25, Tul. 4 - Ø12, cincin Ø8 - 150 mm 0.91 m3 3,200,000 2,912,000 3,298,773 3,001,883

IV PEKERJAAN LANTAI
1 Perataan dan Pemadatan Tanah Area Pondasi 11.84 m2 5,000 59,186 2,610 30,895
2 Pas. Bata merah keliling dasar, t = 20 cm, finish plester-aci sisi luar 20.00 m' 50,000 1,000,000 54,169 1,083,380
3 Lantai dasar Beton K-175, t = 10 cm, finish aci 24.75 m2 95,000 2,351,250 80,827 2,000,472

V PEKERJAAN LAIN - LAIN


1 Pekerjaan Struktur Menara (Erection) Komplit+ Jasa Pemasangan , t = 12 m 1.00 unit 125,000,000 125,000,000 155,000,000 155,000,000

TOTAL 157,584,176 190,544,302


BILL OF QUANTITY : PT MULTI SARANA PAKANINDO
JENIS BANGUNAN : RUMAH PANEL SUMUR 1,2 X 1,2M
SPESIFIKASI : ATAP COR BETON
LOKASI : FARM CIKAWAO
VALIDASI :
REVIEW HARGA RAP
Harga Satuan Jumlah Harga Satuan Jumlah
NO JENIS PEKERJAAN VOL SAT Pekerjaan Harga Pekerjaan Harga
(Rp.) (Rp.) (Rp.) (Rp.)

I PEKERJAAN PERSIAPAN
1 Pek. Pengukuran & Pemasangan Bowplank 8.80 m' 10,000 88,000 38,150 335,720
2 Pembersihan dan Perapihan area setelah pekerjaan 1.00 ls 500,000 500,000 500,000 500,000
3 Biaya Air Kerja 1.00 ls 100,000 100,000 100,000 100,000

II PEKERJAAN GALIAN / URUGAN


1 Galian tanah untuk pondasi batu kali keliling, 60 cm x 100 cm 2.88 m3 55,000 158,400 52,600 151,488
2 Urugan Tanah Bekas Galian Pondasi 0.72 m3 25,000 18,000 13,050 9,396

III PEKERJAAN PASANGAN PONDASI DAN SLOOF


1 Urugan Pasir Bawah Pondasi, t = 5 cm 1.68 m2 35,000 58,800 12,863 21,609
2 Pondasi pasangan batu kali menerus 30/60 x 100 cm 2.16 m3 725,000 1,566,000 659,340 1,424,174
3 4.8 m Sloof 12/15 diatas pondasi batu kali, tul Ø 10, cincinØ 6 mm 0.09 m3 3,200,000 276,480 3,298,773 285,014
4 4 bh Kolom Praktis 11/11 Tinggi = 1,50 m, Tul. Ø 10 mm, Cincin Ø 6 mm 6.00 m' 48,400 290,400 42,551 255,305
5 Ringbalk 10/12 diatas Pasangan Bata Ø 8, cincinØ 6 mm 4.80 m' 48,000 230,400 42,199 202,556

IV PEKERJAAN DINDING
1 Dinding tinggi 1,5 m pasangan 1/2 bata merah 6.10 m2 110,000 671,000 124,920 762,012
2 Plester 12.20 m2 40,000 488,000 40,705 496,601
3 Acian 12.20 m2 20,000 244,000 29,185 356,057

V PEKERJAAN LANTAI
1 Perataan dan Pemadatan Tanah Bagian Dalam 0.41 m3 5,000 2,041 8,700 3,552
2 Lantai Cor Beton t = 5 cm, finish plester - aci 1.17 m2 55,000 64,152 80,827 94,277
3 Rabat tebal 5 cm finish acian 0.79 m2 55,000 43,560 53,054 42,018

VI PEKERJAAN ATAP
1 Atap Dak Beton Bertulang M6-150, t = 8 cm finish acian 2.96 m2 320,000 946,688 196,643 581,750
2 Pekerjaan Alas Dak Beton dengan Bondek 2.96 m2 175,000 517,720 138,840 410,744
3 Langit - Langit finish Cat Aquaproof 2.96 m2 125,000 369,800 125,000 369,800

VII PEKERJAAN KUSEN PINTU DAN VENTILASI


1 Pekerjaan Kusen dan Daun Pintu Besi Plat, 1,1 m x 1 m (Double Swing) plat 1,8 mm 1.00 bh 1,500,000 1,500,000 1,500,000 1,500,000
2 Pasangan Ventilasi Loster 15 x 10 1.00 bh 50,000 50,000 45,000 45,000
3 pasangan Pipa PVC 2 '' 2.00 bh 75,000 150,000 75,000 150,000

VIII PEKERJAAN PARIT RABAT KELILING


1 Galian Tanah 30 cm x 25 cm 1.29 m3 55,000 70,950 52,600 67,854
2 Rabat Pasangan Bata Merah 20x15 cm, finish plester - aci 8.60 m' 50,000 430,000 53,054 456,261

IX PEKERJAAN PENGECATAN DINDING DAN PINTU


1 Pengecatan Dinding Outdoor Cat Vinilex 5000 12.20 m2 30,000 366,000 25,000 305,000
2 Pengecatan Pintu dan Ventilasi, (Cat Bee Brand Junior 66 NP 656 Chestnut Brown) 1.00 ls 500,000 500,000 500,000 500,000

TOTAL 9,700,391 9,426,189


RENCANA ANGGARAN BIAYA : PT MULTI SARANA PAKANINDO
JENIS BANGUNAN : RUANG LIMBAH B3 (2x2M)
SPESIFIKASI : RANGKA ATAP BAJA RINGAN
LOKASI : FARM CIKAWAO
VALIDASI :
REVIEW HARGA RAP
Harga Satuan Jumlah Harga Satuan Jumlah
NO JENIS PEKERJAAN VOL SAT Material Harga Material Harga
(Rp.) (Rp.) (Rp.) (Rp.)

I PEKERJAAN PERSIAPAN
1 Pek. Pengukuran & Pemasangan Bowplank 12.50 m' 10,000 125,000 38,150 476,875
2 Pembersihan dan Perapihan area setelah pekerjaan 1.00 ls 500,000 500,000 500,000 500,000
3 Biaya Air Kerja 1.00 ls 1,000,000 1,000,000 1,000,000 1,000,000

II PEKERJAAN GALIAN / URUGAN


1 8.0 m Galian tanah untuk pondasi batu kali menerus, 60 cm x 100 cm, 0.48 m3 55,000 26,400 52,600 25,248
2 Urugan Tanah Bekas Galian Pondasi 0.12 m3 25,000 3,000 13,050 1,566

III PEKERJAAN PASANGAN PONDASI DAN SLOOF


1 Urugan Pasir Bawah Pondasi, t = 5 cm 4.80 m2 35,000 168,000 12,863 61,740
2 8.0 m Pondasi pasangan batu kali menerus 30/60 x 100 cm, 3.60 m3 725,000 2,610,000 659,340 2,373,624
3 8.0 m Sloof 15/20 diatas pondasi batu kali, tul Ø 10, cincinØ 6 mm - 150 0.24 m3 3,200,000 768,000 3,298,773 791,705
4 4.0 bh Kolom Praktis 15/15 Tinggi = 3,0 m, Tul. Ø 10 mm, Cincin Ø 6 mm - 150 12.00 m' 90,000 1,080,000 42,551 510,611
5 8.0 m Ringbalk 12/15 diatas Pasangan Bata, tul Ø 10, cincinØ 6 mm - 150 8.00 m' 72,000 576,000 42,199 337,594

IV PEKERJAAN DINDING
1 8.0 Dinding tinggi 1.5 m pasangan 1/2 bata merah 12.00 m2 110,000 1,320,000 124,920 1,499,040
2 Dinding sofi-sofi pasangan 1/2 bata merah 1.20 m2 110,000 132,000 124,920 149,904
3 Pek. Frame Hollow 40.40 Penutup Kawat Harmonika (lihat Gambar Design) 12.40 m2 50,000 620,000 102,594 1,272,171
4 Plester 26.40 m2 40,000 1,056,000 40,705 1,074,612
5 Acian 26.40 m2 20,000 528,000 29,185 770,484

V PEKERJAAN LANTAI
1 Perataan dan Pemadatan Tanah Bagian Dalam 9.77 m2 5,000 48,828 2,610 25,488
2 Lantai Cor Beton K-175 Tak Bertulang t = 10 cm, finish acian (bagian Dalam) 4.00 m2 100,000 400,000 80,827 323,309
3 Rabat K100 Finish Acian 5.77 m2 70,000 403,594 53,054 305,887
4 Pekerjaan Tali Air 2.00 m' 10,000 20,000 10,000 20,000
5 Pekerjaan Bak Kontrol (lihat gambar design) 1.00 unit 1,500,000 1,500,000 1,500,000 1,500,000

VI PEKERJAAN ATAP DAN PLAFOND


1 Rangka Atap Baja Ringan, t = 0,75 mm 15.37 m2 150,000 2,305,920 140,190 2,155,113
2 Atap Seng Galvalum Spandek 0.35 15.37 m2 100,000 1,537,280 65,000 999,232
3 Pasangan Listplank GRC 2/200mm 15.86 m' 20,000 317,160 54,450 863,468

VIII PEKERJAAN KUSEN PINTU, JENDELA DAN VENTILASI


Pekerjaan Kusen Besi UNP dan Daun Pintu Besi Plat Profil Pabrikasi, 1 m x 2 m single (Swing)
1 Penutup Wiremesh sisi atas (lihat gambar design) 1.00 unit 2,500,000 2,500,000 2,500,000 2,500,000

IX PEKERJAAN PENGECATAN DINDING DAN PLAFOND


1 Pengecatan Dinding Outdoor dan Indoor, Cat Vinilex 5000 (926 : Light cream) 26.40 m2 30,000 792,000 25,000 660,000
2 Pengecatan Listplank GRC Board 9 mm, (Cat Bee Brand Junior 66 NP 656 Chestnut Brown) 3.49 m2 55,000 191,882 25,000 87,219
3 Pengecatan Pintu Besi 1.00 Ls 500,000 500,000 500,000 500,000

TOTAL 21,029,064 20,784,890


BILL OF QUANTITY : PT. MULTI SARANA PAKANINDO
JENIS BANGUNAN : RUANG GENSET
1 TAPAK PANEL
SPESIFIKASI : KIRI (8x8M)
RANGKA ATAP BAJA RINGAN
LOKASI : DENGAN TEMPAT
FARM CIKAWAO
VALIDASI : TANGKI SOLAR
(2.5x2.5)m REVIEW HARGA RAP
Harga Satuan Jumlah Harga Satuan Jumlah
NO JENIS PEKERJAAN VOL SAT Pekerjaan Harga Pekerjaan Harga
(Rp.) (Rp.) (Rp.) (Rp.)

I PEKERJAAN PERSIAPAN
1 Pek. Pengukuran & Pemasangan Bowplank 53.00 m' 10,000 530,000 38,150 2,021,950
2 Pembersihan dan Perapihan area setelah pekerjaan 1.00 ls 500,000 500,000 500,000 500,000
3 Biaya Air Kerja 1.00 ls 1,000,000 1,000,000 1,000,000 1,000,000

II PEKERJAAN GALIAN / URUGAN


1 39.5 m Galian tanah untuk pondasi batu kali menerus, 50 cm x 100 cm, 19.75 m3 55,000 1,086,250 52,600 1,038,850
2 1.0 bh Galian tanah untuk pondasi dudukan genset 210 cm x 410 cm x 20 cm, 1.72 m3 55,000 94,710 52,600 90,577
3 14.0 m Galian tanah untuk parit kabel, 65 cm x 65 cm, 5.92 m3 55,000 325,325 52,600 311,129
4 Urugan Tanah Bekas Galian Pondasi 5.37 m3 25,000 134,200 13,050 70,052

III PEKERJAAN PASANGAN PONDASI DAN SLOOF


1 39.5 m Urugan Pasir Bawah Pondasi, t = 5 cm 23.70 m2 35,000 829,500 12,863 304,841
2 39.5 m Pondasi pasangan batu kali menerus 30/60 x 100 cm 17.78 m3 725,000 12,886,875 659,340 11,719,769
3 1.0 unit Pondasi Pasangan Batu Kali Dudukan Genset 2 x 4 m, t = 20 cm, 1.60 m3 725,000 1,160,000 659,340 1,054,944
4 Sloof 15/20 diatas pondasi batu kali, tul Ø 10, cincinØ 6 mm 1.19 m3 3,200,000 3,792,000 3,298,773 3,909,046
5 10.0 Bh Kolom Praktis 11/11 Tinggi = 4 m, Tul. Ø 10 mm, Cincin Ø 6 mm 40.00 m' 38,720 1,548,800 42,551 1,702,036
6 6.0 Bh Kolom Praktis 20/20 Tinggi = 4 m, Tul. Ø 10 mm, Cincin Ø 6 mm 24.00 m' 128,000 3,072,000 140,664 3,375,939
7 2.0 Bh Kolom Praktis 11/11 Tinggi = 1 m, Tul. Ø 10 mm, Cincin Ø 6 mm 2.00 m' 38,720 77,440 42,551 85,102
8 Ringbalk 10/12 diatas Pasangan Bata, tul Ø 10, cincinØ 6 mm 39.50 m' 38,720 1,529,440 42,199 1,666,870
9 Ringbalk 10/12 tengah dinding Pasangan Bata, tul Ø 10, cincinØ 6 mm, 33.50 m' 38,720 1,297,120 42,199 1,413,675
10 Balok dan Kolom Sofi2 10/12 ,Tul. Ø 10 mm, Cincin Ø 6 mm 20.40 m' 38,720 789,888 42,199 860,865
Dudukan Genset Pas. Cor Beton Bertulang 2m x 4m, t = 20 cm, 1 unit, tul Ø 10 mm double layer 1.60 m3 3,200,000
5,120,000
11 3,057,722 4,892,355

IV PEKERJAAN DINDING
1 Dinding tinggi 3,9 m pasangan 1/2 bata merah 138.14 m2 110,000 15,195,125 124,920 17,256,137
2 Dinding sofi-sofi tinggi pasangan 1/2 bata merah 9.60 m2 110,000 1,056,000 124,920 1,199,232
3 Dinding tinggi 1 m pasangan 1/2 bata merah 6.00 m2 110,000 660,000 124,920 749,520
4 Pasangan Rangka Hollow penutup Dinding Kawat untuk tangki solar 18.75 m2 135,000 2,531,250 126,447 2,370,880
5 Plester 297.88 m2 40,000 11,915,000 40,705 12,125,002
6 Acian 297.88 m2 20,000 5,957,500 29,185 8,693,482

V PEKERJAAN LANTAI
1 Perataan dan Pemadatan Tanah Bagian Dalam (Siap Cor) 70.25 m2 5,000 351,250 2,610 183,353
2 Lantai Cor Beton K-175 Tak Bertulang t = 10 cm, finish acian 62.25 m2 100,000 6,225,000 80,827 5,031,491
3 Parit Kabel, Cor Beton K175 M 10-150 t = 10cm uk. 60x70 finish acian waterproofing 14.00 m' 320,000 4,480,000 382,763 5,358,675
4 Plester - aci permukaan dudukan genset 10.56 m2 60,000 633,600 69,890 738,038
5 Rabat K-100 tebal 7 cm finish acian 45.00 m2 59,500 2,677,500 53,054 2,387,411

VI PEKERJAAN PARIT RABAT KELILING


1 Galian Tanah 30 cm x 60 cm 8.10 m3 55,000 445,500 52,600 426,060
2 Parit Rabat penampang 20 x 40 Pasangan Bata Merah, finish plester - aci 45.00 m' 25,000 1,125,000 53,054 2,387,411
3 Pekerjaan Duicker Beton t=7cm M6-10 1.44 m2 210,000 302,400 210,000 302,400

VII PEKERJAAN ATAP DAN PLAFOND


1 Rangka Atap Besi Double CNP 100, Gording CNP 75 124.65 m2 190,000 23,683,500 185,000 23,060,250
2 Atap Seng Galvalum Spandek 0.35 +Trackstang +Erection 124.65 m2 100,000 12,465,000 65,000 8,102,250
3 Pasangan Listplank GRC 2/200mm 45.90 m' 45,000 2,065,500 54,450 2,499,255
4 Pas. Canopy Rangka Baja ringan, penutup galvalum (di atas panel) didalam bangunan 16.00 m2 250,000 4,000,000 Rp 215,000 3,440,000

VIII PEKERJAAN KUSEN PINTU DAN VENTILASI


Pekerjaan Kusen Besi Siku dan Daun Pintu Besi Plat Profil Pabrikasi, 2.75 m x 2.15 m (Sliding) Plate
1.00 set 5,000,000 5,000,000 3,467,053 3,467,053
1 2 mm (Lihat Gambar Design)
2 Pekerjaan Ventilasi 170 cm x 170 cm, Besi beton Ø 10 mm, frame besi siku 50.50.5 1.00 bh 750,000 750,000 683,400 683,400
3 Pekerjaan Penutup Ventilasi dan Pintu menggunakan Wiremesh (kawat loket uk 1 cm) 7.89 m2 65,000 512,850 101,695 802,374

IX PEKERJAAN PENGECATAN DINDING DAN PLAFOND


1 Pengecatan Dinding Indoor dan Outdoor, Cat Vinilex 5000 (926 : Light cream) 148.94 m2 30,000 4,468,125 25,000 3,723,438
2 Pengecatan Listplank 10.10 m2 55,000 555,390 25,000 252,450
3 Pengecatan pintu Besi dan ventilasi 1.00 Ls 1,500,000 1,500,000 100,000 100,000

TOTAL BUDGET 144,329,038 141,357,559


BILL OF QUANTITY : PT MULTI SARANA PAKANINDO
JENIS BANGUNAN : DUDUKAN & R. TANGKI SOLAR 8.1 X 4 M
SPESIFIKASI : RANGKA ATAP BAJA
LOKASI : FARM CIKAWAO
VALIDASI :
REVIEW HARGA RAP
Harga Satuan Jumlah Harga Satuan Jumlah
NO JENIS PEKERJAAN VOL SAT Satuan Harga Satuan Harga
(Rp.) (Rp.) (Rp.) (Rp.)

I PEKERJAAN PERSIAPAN
1 Pek. Pengukuran & Pemasangan Bowplank 24.20 m' 10,000 242,000 38,150 923,230
2 Pembersihan dan Perapihan area setelah pekerjaan 1.00 ls 250,000 250,000 250,000 250,000
3 Biaya Air Kerja 1.00 ls 1,000,000 1,000,000 1,000,000 1,000,000

II PEKERJAAN GALIAN
1 3 bh Galian tanah untuk pondasi Fuel Tank, 65 cm x 200 cm x 45 cm 1.76 m3 55,000 96,525 52,600 92,313
2 6 bh Galian tanah untuk pondasi pedestal 50 x 60 x 60cm 1.08 m3 25,000 27,000 52,600 56,808

III PEKERJAAN PASANGAN DINDING BETON, SLOOF & DUDUKAN TANGKI


1 2 jalur Sloof 40/40 Tul. Utama 4 Ø 10mm, Cincin Ø 6mm -150 mm, panjang 355cm 1.14 m3 3,200,000 3,635,200 3,298,773 3,747,406
Dinding beton Tul. 3 Ø 10mm, Cincin Ø 10mm - 150 mm, (200 cm x 40 cm x 210 cm) 3 layer 3.36 m3 3,200,000
2 2 bh 10,752,000 3,298,773 11,083,877
3 Acian Permukaan Dudukan Tangki 22.63 m2 20,000 452,600 29,185 660,457
0
IV PEKERJAAN DINDING BAK PENAMPUNGAN 0
1 20.2 m Sloof 15/20 Tul. Utama 4 Ø 10mm, Cincin Ø 6mm -150 mm 0.61 m3 3,200,000 1,939,200 3,298,773 1,999,056
2 6 bh Pedestal 20cm x 60cm x 60cm Cincin Ø 10mm - 150 mm 0.43 m3 3,200,000 1,382,400 3,293,799 1,422,921
3 24 bh Angkur sambungan dari pipa ke sloof pedestal 24.00 bh 35,000 840,000 26,000 624,000
4 24 bh Plat L siku pengaku pipa ke pedestal L 50x5x5 24.00 bh 50,000 1,200,000 50,000 1,200,000
5 Ringbalk 10/12 diatas Pasangan Bata Tul. Utama 4 Ø 10mm, Cincin Ø 6mm -150 mm 20.20 m' 36,000 727,200 42,199 852,425
6 Dinding tinggi 1 m pasangan 1/2 bata merah 20.20 m2 110,000 2,222,000 124,920 2,523,384
7 Plester 40.40 m2 40,000 1,616,000 40,705 1,644,482
8 Acian 40.40 m2 20,000 808,000 29,185 1,179,074
9 Pengecatan Dinding Outdoor Cat Vinilex 5000 40.40 m2 30,000 1,212,000 25,000 1,010,000
10 Pengerjaan Tangga dari pasangan bata di luar dan di bagian dalam 2.00 unit 2,500,000 5,000,000 2,500,000 5,000,000

V PEKERJAAN LANTAI
1 Perataan dan Pemadatan Tanah 32.4 m2 5,000 162,000 2,610 84,564
2 Lantai Cor Beton K-175 Tak Bertulang t = 10 cm, finish acian 21.30 m2 100,000 2,130,000 80,827 1,721,619
3 Rabat beton K-100 tebal 5 cm finish acian 11.10 m2 59,500 660,450 53,054 588,895

VI PEKERJAAN ATAP, PONDASI & TIANG


1 Rangka Atap Baja Pipa 4" , Pipa 2" dan Purlin CNP 50 37.26 m2 200,000 7,452,000 182,495 6,799,750
2 Atap Genteng Galvalum t = 0,4 mm 37.26 m2 100,000 3,726,000 65,000 2,421,900
3 Pasangan Nok(Sesuai Genteng) 8.10 m' 50,000 405,000 70,000 567,000
4 Tiang Struktur Besi Pipa 4", t = 4,5 m ; Baseplat 25x25 cm, t = 2 mm 6.00 ls 500,000 3,000,000 483,000 2,898,000
5 Pondasi Setempatl Beton Bertulang, Pedestal 30x30x40 cm (Pondasi Tiang) 6.00 bh 350,000 2,100,000 350,000 2,100,000

VII PEKERJAAN LAIN


1 Pengecetan besi (Cat Bee Brand Junior 66 NP 656 Chestnut Brown) 1.00 ls 250,000 250,000 250,000 250,000

TOTAL BUDGET 53,287,575 52,701,160


BILL OF QUANTITY :
JENIS BANGUNAN : GUDANG SEKAM (7x8 M)
SPESIFIKASI : RANGKA ATAP BAJA RINGAN
LOKASI : FARM CIKAWAO
VALIDASI :
REVIEW HARGA RAP
Harga Satuan Jumlah Harga Satuan
NO JENIS PEKERJAAN VOL SAT Material &
Material & Jasa Harga
Jasa
(Rp.) (Rp.) (Rp.)

I PEKERJAAN PERSIAPAN
1 Pek. Pengukuran & Pemasangan Bowplank 38.00 m' 10,000 380,000 38,150
2 Biaya Air Kerja dan Perapihan Kerja 1.00 ls 500,000 500,000 500,000
3 Biaya Air Kerja 1.00 ls 1,000,000 1,000,000 1,000,000

II PEKERJAAN GALIAN / URUGAN


1 Galian tanah untuk pondasi batu kali menerus, 50 cm x 100 cm 15.00 m3 55,000 825,000 52,600
2 Urugan Tanah Bekas Galian Pondasi 3.75 m3 25,000 93,750 13,050

III PEKERJAAN PASANGAN PONDASI DAN SLOOF


1 Urugan Pasir Bawah Pondasi, t = 5 cm 15.00 m2 35,000 525,000 12,863
2 Pondasi pasangan batu kali menerus 30/60 x 100 cm 13.50 m3 725,000 9,787,500 659,340
3 Sloof 15/20 diatas pondasi batu kali, tul Ø 10, cincinØ 6 mm 0.90 m3 3,200,000 2,880,000 3,298,773
4 8 Kolom Praktis 11/11 Tinggi = 3.5 m, Tul. Ø 10 mm, Cincin Ø 6 mm 28.00 m' 48,400 1,355,200 42,551
5 6 Kolom Praktis 20/20 Tinggi = 3.5 m, Tul. Ø 10 mm, Cincin Ø 6 mm 21.00 m' 160,000 3,360,000 140,664
6 Ringbalk 10/12 diatas Pasangan Bata, tul Ø 10, cincinØ 6 mm 30.00 m' 48,000 1,440,000 42,199
7 Balok dan Kolom Sofi2 10/12 Tinggi = 1,2 m, 4 Bh, Tul. Ø 10 mm, Cincin Ø 6 mm 19.60 m' 48,000 940,800 42,199

IV PEKERJAAN DINDING
1 Dinding tinggi 3,3 m pasangan 1/2 bata merah 89.08 m2 110,000 9,798,800 124,920
2 Dinding sofi-sofi tinggi pasangan 1/2 bata merah 3.60 m2 110,000 396,000 124,920
3 Plester 185.36 m2 40,000 7,414,400 40,705
4 Acian 185.36 m2 20,000 3,707,200 29,185

V PEKERJAAN LANTAI
1 Perataan dan Pemadatan Tanah Bagian Luar dan Dalam 90.00 m2 5,000 450,000 2,610
2 Lantai Cor Beton K-175 Tak Bertulang t = 10 cm, finish acian 56.00 m2 100,000 5,600,000 80,827
3 Rabat K-100 tebal 7 cm finish acian 34.00 m2 59,500 2,023,000 53,054

VI PEKERJAAN ATAP DAN PLAFON


1 Rangka Atap Baja Ringan, t = 0,75 mm 93.60 m2 150,000 14,040,000 140,190
2 Atap Transparan t= 0.35 93.60 m2 100,000 9,360,000 105,663
3 Rangka Hollow 40.40.4, Plafond GRC Bagian Luar Bangunan 39.20 m2 150,000 5,880,000 121,690
4 Pasangan Listplank GRC 2/200mm 39.20 m' 45,000 1,764,000 54,450

VII PEKERJAAN KUSEN PINTU DAN VENTILASI


1 Pekerjaan Kusen Besi UNP dan Daun Pintu Besi Plat Profil, 2 m x 2 m (Swing) Plate 2 mm 2.00 unit 6,000,000 12,000,000 4,500,000
2 Bouven Light 60 x 40 cm (Alumunium), Kaca 5 mm 8.00 unit 750,000 6,000,000 500,000

VIII PEKERJAAN PARIT RABAT KELILING


1 Galian Tanah 30 cm x 40 cm 4.56 m3 55,000 250,800 52,600
2 Parit Rabat Pasangan Bata Merah, finish plester - aci 38.00 m' 25,000 950,000 53,054
3 Pekerjaan Duicker Beton t=7cm M6-10 1.44 m2 210,000 302,400 210,000

IX PEKERJAAN PENGECATAN DINDING DAN PLAFOND


1 Pengecatan Dinding , Cat Vinilex 5000 (926 : Light cream) 185.36 m2 30,000 5,560,800 25,000
2 Pengecatan Plafond, Cat Vinilex 5000 (300 : White) 39.20 m2 55,000 2,156,000 49,500
3 Pengecatan Listplank 8.62 m2 55,000 474,320 49,500
4 Pengecatan pintu Besi 2.00 set 750,000 1,500,000 300,000

TOTAL 112,714,970
RAP
Jumlah

Harga
(Rp.)

1,449,700
500,000
1,000,000

789,000
48,938

192,938
8,901,090
2,968,896
1,191,425
2,953,947
1,265,977
827,105

11,127,874
449,712
7,545,079
5,409,732

234,900
4,526,321
1,803,822

13,121,784
9,890,088
4,770,248
2,134,440

9,000,000
4,000,000

239,856
2,016,036
302,400

4,634,000
1,940,400
426,888
600,000

106,262,594