Company
LOGO
Agenda
1. Definitions
3. Estimate Cost
4. Determine Budget
5. Control Cost
0 1 2 3 4
10%
1. Scope Baselines
Scope Statement
WBS
WBS Dictionary
2. Project Schedule
3. Human Resource Plan
1. Expert Judgment
3. Parametric Estimating
4. Bottom-up estimating
5. Three-point Estimating
6. Reserve Analysis
7. Cost of Quality
Analogous estimating:
A. uses bottom-up estimating techniques.
B. is used most frequently during the executing
processes of the project
C. uses top-down estimating techniques.
D. uses actual detailed historical costs.
2. Basis of Estimates
3. Scope Baseline
4. Project Schedule
5. Resource Calendars
6. Contracts
1. Cost Aggregation
2. Reserve Analysis
3. Expert Judgment
4. Historical Relationships
2. Forecasting
4. Performance Reviews
5. Variance Analysis
2. Budget Forecasts
4. Change Requests
use EVM.
PV = $42,000
EV = $38,000
AC = $48,000
CV = EV – AC
= $38,000 - $48,000 = -$10,000
CV% = CV / EV
= -$10,000 / $38,000 = -26%
5/16/2009 Compiled by: Waleed El-Naggar 33
EVM Example – contd.
PV = $42,000
EV = $38,000
AC = $48,000
SV = EV – PV
= $38,000 - $42,000 = -$4,000
SV% = SV / EV
= -$4,000 / $42,000 = -9.5%
5/16/2009 Compiled by: Waleed El-Naggar 34
EVM Example – contd.
PV = $42,000
EV = $38,000
AC = $48,000
CPI= EV / AC
= $38,000 / $48,000 = 0.79
For each $1 spent, a work worth $0.79 was
actually performed.
5/16/2009 Compiled by: Waleed El-Naggar 35
EVM Example – contd.
PV = $42,000
EV = $38,000
AC = $48,000
SPI= EV / PV
= $38,000 / $42,000 = 0.90
• AC = $ 1,700
Spending Variance = EV – AC
= - $ 200
SV = EV – PV = - $ 400
SV % = SV / PV x 100 = - 21 %
CV = EV – AC = - $ 200
CV % = CV / EV x 100 = -13 %
SPI = EV / PV = $ 0.79
CPI = EV / AC = $ 0.88
EV = $ 2,400
AC = $ 2,200
SPI = 0.92
SV = - $ 200; SV % = - 8 %
CV = $ 200; CV % = 8 %
CPI = 1.09
SV = - $ 200; SV % = - 12 %
SPI = 0.88
5/16/2009 Compiled by: Waleed El-Naggar 49
Case 4
PV = $ 1,700
...but the cost of EV = $ 1,500
the work
accomplished is AC = $ 1,500
just as we
budgeted.
CV = $ 0.00
CPI = 1.00
PV = $ 1,400
EV = $ 1,600
A positive scenario; AC = $ 1,400
right? But is it because
we are out-performing
our learning-curve
standards or because
we planned too
pessimistically?
SPI = 1.14
CPI = 1.14
SV = $ 200; SV % = 14 %
CV = $ 200; CV % = 12.5 %
Text
Text