Multiple Choice
Instructions
a) Project Closure
b) Implementation
c) Testing
d) Initiation
e) Specification
a) Project Mandate
b) Project Initiation Document
c) Project Brief
d) Issue Log
e) Lessons Learned blank report
a) Project plans
b) Stage control
c) Quality
d) Specialist
a) Controlling a Stage
b) Managing Stage Boundaries
c) Managing Product Delivery
d) Closing a Project
9. Project controls are set up based on the Project Brief, the Project Quality
Plan and which other product?
10. Two products are re-assessed and refined to reflect the current
understanding of the project, and to form a basis for updating the Project
Plan. Which are they?
team structure
c) The project quality plan and project approach
d) The business case and the risk log
a) Issue Log
b) Product Descriptions
c) Quality Plan
d) Risk Log
a) Configuration items
b) Requests for Change
c) Project Issues
d) Exception Reports
e) Action items
14. Apart from the Issue Log, which other product is updated in the process
“Examining Project Issues”?
a) Planning
b) Managing Product Delivery
c) Authorising Work Packages
d) Assessing Progress
e) Taking Corrective Action
a) Project Manager
b) Project Board
c) Senior User
d) Team Manager
18. Where a management stage ends part way through one or more elements
of specialist work, what technique is useful in helping to identify the
detailed products to be processed in a given management stage?
a) Configuration Management
b) Work Package Authorisation
c) The Management of Risk
d) Product-Based Planning
a) Planning A Project
b) Setting Up Project Controls
c) Refining the Business Case and Risks
d) Preparing a Project Brief
a) Planning a Stage
b) Reporting Stage End
c) Updating a Project Plan
d) Producing an Exception Plan
24. Which of these products is not part of the Project Initiation Document?
25. Which product evaluates the actual project outcome versus that envisaged
in the project initiation document?
a) Product Checklist
b) Project Closure Meeting
c) Lessons Learned Report
d) End Project Report
28. If there is a need to know what the precise components of a product were
three months ago, what part of PRINCE would most help us?
30. In the PRINCE 2 approach, stages (and their duration’s) are defined by
reference to:
a) Senior Supplier
b) Project Assurance
c) Team Manager
d) Configuration Librarian
34. The Project Plan is based on the Project Brief, the Project Quality
Plan and which other product?
35. Which sub process checks for any changes to the project management
team?
a) Planning a Stage
b) Updating the Project Plan
c) Reporting Stage End
d) Reviewing Stage Status
a) Project Mandate
b) Project Board appointment
c) Authorising Initiation
d) Project Initiation Document approval
e) Project manager appointment
38. When does the Project Board decide where the authority for making
change lies?
40. Apart from the Issue Log, which product is an input to the sub process
“Identifying Follow-On Actions?
44. When does a Team Manager report on the status of a Work Package to the
Project Manager?
45. Which sub process may trigger a premature close to the project?
a) Planning Quality
b) Authorising Work Package
c) Assessing Progress
d) Planning a Stage
f) B and D
49. If the Project Board decides to accept an Off Specification without any
corrective action, what is this called?
a) An exception
b) A concession
c) An action item
d) A deviation
52. The key to successful use of the process model is where each process is
approached with a key question. Which of the following is the key
question?
b) “Is how I use this process clear? If not, is it any clearer at the
next level down?”
c) “How extensively should this process be applied on this project?”
d) “How can I prove that I have done this process adequately?”
53. By what are technical stages (as opposed to management stages) typified?
a) Check that the need for the project has not changed
b) Review the Next Stage Plan against the Project Plans
c) Disseminate useful lessons learned
d) Review the tolerances set for the next stage
a) Project Exception
b) Request For Change
c) A Specialist Query
d) Statement of Concern
57. Which one of these products is NOT an output from Closing a Project?
a) To identify products
b) To create products
c) To track products
d) To protect products
59. Which one of these statements describes the true purpose of Acceptance
Criteria?
a) Prevention
b) Denial
c) Reduction
d) Transference
e) Contingency
62. Why would a copy of the Project Issue be returned to the author?
a) a Management Product
b) a Quality Product
c) a Specialist Product
67. Which one of these is the true principle behind Evaluating a Project?
70. In Decommissioning a Project the project files are archived. What is the
explanation given for this?
74. Which of these Starting Up a Project processes creates a blank Risk Log?
a) Planning a Project
b) Refining the Business Case
c) Planning Quality
d) Setting up Project Files