WIND PARK
PROJECT PRESENTATION
1
MULTIMEDIA ART&TEHNIC
One can remark that there is and will continue to be a clear deficit of
installed capacity of wind parks, today and in the next 10 years. The 2015
installed capacity is the sum of the announcements made by some
investors like Iberdrola, CEZ, Verbund, OMV, EDP-ER. As long in the next
years we will face a deficit of installed wind parks capacity, the
opportunity of investing in this field is obvious.
2
MULTIMEDIA ART&TEHNIC
pct. 1
Using the measurements it has been determined the yearly average wind
speed, the total wind hours and the main direction of the wind, the results
being presented in Appendix 3. The average speed, at 50m height, long
term is 6,20 m/s and the main direction is very narrow. Using the
WindFarmer software from Garrad Hassan (WasP software as engine), it
has been determined an average wind speed, at 119m, of >=6,55 m/s,
proper for an efficient wind park.
Projects description:
- Position:
o WPH is located North of Husi town, at a distance of 15 km;
the position in Romania is presented in Appendix 4, and
the position in the Vaslui county is presented in Appendix
6.
- Technical specification:
o WPH has an installed capacity of 69 MW, that will be
generated by 23 turbines
For the design of the wind parks it has been considered
the Vestas V112, 3MW, turbine. Alternatively one can use
3
MULTIMEDIA ART&TEHNIC
the Vestas V112, 3MW, 94 m tower. The V112 presentation
is attached as Appendix 7.
Estimated incomes:
Using the wind measurements and the software application WindFarmer
from Wasp it has been generated a wind assement, in fact the equivalent
working hours at installed power: 2.566 for WPH. The capacity factor is
over 29,3%, making the project very attractive energetically and
economically.
The estimated ERS outputs are presented in the bellow table.
Equiv hours output
Project installed power
H MWh
WPH 2.566 177.037
The annual and global incomes from ERS production are presented in
tabel 3, presented in atachment.
Estimated expenses:
Estimated expenses are presented in tabel 2, presented in atachment.
4
MULTIMEDIA ART&TEHNIC
Investment estimation:
Investment estimation is presented in table 1, in attachment.
Estimated investment costs for WPH: 97.330 K Euro
Financial rentability:
Data is presented in table 4, in attachment. One can notice that the
payback period is 5 years, the annual IRR is 0,2 and VAN (on top of the
investment) is 96.960 K Euro.
Risk analisys:
Potential risks:
- Change of economical hypotesis; still fragile economical
environment; average risk
- Legal modifications; can only be in the favour of ERS; no risk
- Technical risks; the equipments are from a famous manufacturer,
with many other equipments in service at customers; low risk
- Climate changes; will lead to stronger winds, good for the
business
The above risks have been considerd in independent scenarios and
cumulative scenario, in a sensitivity analisys. The result is that the influence
of the potential risks is small.
Validity of offer :
The offer is valid 4 months.
5
MULTIMEDIA ART&TEHNIC
Wind Park Project 69 MW, Husi
MULTIMEDIA ART&TEHNIC
Aleea Barajul Sadului, nr.3-5, bl. N12-N13, sc. A, apt 11, Sector 3, Bucuresti
Tel : +40 744 505 507; fax: +4 031 804 44 12; email: marius.bohan@gmail.com
1
MULTIMEDIA ART&TEHNIC
Establishment License A.N.R.E. : we applied for it, analisys of docs in
progress, expected to be released in April 2011
Electrical power generation premises :
- wind measurements ; wind parameters are measured begining with
01.12.2008, with own met mast, 50m height ; data have been processed
with the application WindFarmer, from Garrad-Hassan ; average wind
speed at 119m, is >= 6,55 m/s ; one have been determined the equivalent
run time at nominal power of 3 MW=2.566 hours, meaning a capacity
factor of 29,3%
- selected machine ; the machine Vestas V112, with rotor height of 119m,
112m rotor diameter, delivers the best energy output
- estimated electrical output : annually energy output >= 177 GWh, P50
net
Layout information : there are 23 turbines, disposed at a distance of
1.000 m turbine to turbine, in main wind direction, and 450 m turbine to
turbine, transverse main wind direction ; foundations are of 15m
diameter ; access will be done by road means, asphalt road till 3 km from
the park, 3 km of concrete road and a net of 13 km of gravel roads ;
operational platforms will be covered with gravel ; the 20KV internal
cables will be underground, under the graveled roads
MULTIMEDIA ART&TEHNIC
Aleea Barajul Sadului, nr.3-5, bl. N12-N13, sc. A, apt 11, Sector 3, Bucuresti
Tel : +40 744 505 507; fax: +4 031 804 44 12; email: marius.bohan@gmail.com
2
Anexa 1 / Appendix 1
1.2 Husi
V 6.0 m/s
k 1.98
A 6.7 m/s
Gust 32.8 m/s
Availability 96.9%
Mean TI 12 %
Mean Temp 11.5 °C
Mean RH 44%
Table 3: wind data characteristics at 50m
14%
Data Distribution
12%
Weibull Distribution (1.98, 6.7)
10%
8%
6%
4%
2%
0%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
N N
NNW NNE NNW NNE
NW NE NW NE
W E W E
SW SE SW SE
SSW SSE SSW SSE
S S
5
Anexa 6 / Appendix 6