Proyek :
Pekerjaan : PEMBUATAN dak
Lokasi : KEDIRI
A PEKERJAAN PERSIAPAN
1 Safety aparatus 1,0 Ls
2 Shop drawing 1,0 Ls
3 Peralatan kerja 1,0 Ls
4 Listrik & air kerja 1,0 Ls
5 Pembersihan lahan selama proyek 1,0 Ls 10.000.000 10.000.000
10.000.000
B PEMBUATAN BANGUNAN KOS KOSAN
I PEKERJAAN TANAH
1 Galian Tanah 4,4 m3 134.000 586.116
2 Urug tanah kembali 2,0 m3 100.000 200.000
4 Pasir urug 10cm 1,0 m3 180.000 180.000
5 Lantai kerja 5cm 5,0 m2 35.000 175.000
1.141.116
II PEKERJAAN STRUKTUR
1 Pasir urug bawah pondasi 10cm 8,3 m3 180.000 1.494.000
3 Lantai kerja bawah pile cap 5cm 2,2 m2 35.000 75.600
4 Strouss Ø30cm
- Bor strouss 2,5m 6,0 ttk 150.000 900.000
- Besi beton Ø12 250,0 kg 11.200 2.800.000
- Besi beton Ø8-100 75,0 kg 11.200 840.000
- Cor beton Site Mix 1,1 m3 927.400 1.061.437
5 Pile cap 0,6m x 0,6m -
- Bekisting 3,6 m2 96.601 347.764
- Besi beton Ø12-150 138,7 kg 11.200 1.553.126
- Cor beton Site Mix 0,4 m3 927.400 400.637
7 Kolom K1 20x20
- Bekisting 16,8 m2 96.601 1.622.897
- Besi beton Ø12 300,0 kg 11.200 3.360.000
- Besi beton Ø8-100 Besi polos 110,0 kg 11.200 1.232.000
- Cor beton 1,2 m3 927.400 1.112.880
- Acian halus 50,0 m2 15.000 750.000
- Benangan 65,0 m1 15.000 975.000
8 Kolom K2 15x15
- Bekisting 25,0 m2 96.601 2.415.026
- Besi beton Ø12 175,0 kg 11.200 1.960.000
- Besi beton Ø8-100 Besi polos 50,0 kg 11.200 560.000
- Cor beton 1,0 m3 927.400 927.400
- Acian halus 100,0 m2 15.000 1.500.000
- Benangan 50,0 m1 15.000 750.000
9 Kolom KP
- Bekisting 1,8 m2 96.601 173.882
- Besi beton Ø12 Besi polos 35,0 kg 11.200 392.000
- Besi beton Ø6-150 Besi polos 24,0 kg 11.200 268.800
- Cor beton Site Mix 0,8 m3 927.400 741.920
10 Balok B1 15x3
- Bekisting 15,0 m2 96.601 1.449.016
- Besi beton Ø12 Besi ulir 176,0 kg 11.200 1.971.200
- Besi beton Ø8-150 Besi polos 125,0 kg 11.200 1.400.000
- Cor beton 1,9 m3 927.400 1.803.793
11 Balok B2 15x15
- Bekisting 12,0 m2 96.601 1.159.212
- Besi beton Ø12 Besi polos 75,0 kg 11.200 840.000
- Besi beton Ø8-150 Besi polos 158,0 kg 11.200 1.769.600
- Cor beton 2,0 m3 927.400 1.854.800
12 Balok B3 15x25
- Bekisting 11,7 m2 96.601 1.130.232
- Besi beton Ø12 Besi polos 75,0 kg 11.200 840.000
- Besi beton Ø8-150 Besi polos 94,8 kg 11.200 1.061.760
- Cor beton 1,4 m3 927.400 1.251.990
13 Listplank beton
- Bekisting 4,5 m2 96.601 434.705
- Besi beton Ø8-150 Besi polos 55,0 kg 11.200 616.000
- Cor beton 1,0 m3 927.400 927.400
No. Pekerjaan Spesifikasi Volume Harga satuan Total Ket.
94.141.012