Anda di halaman 1dari 30

JADWAL PEKERJAAN

LANJUTAN PEMBANGUNAN STADION BAROMBONG


UNIT PEKERJAAN : PEKERJAAN STRUKTUR, MEP, ARSITEK PADA TRIBUN BARAT
SUMBER DANA : APBD
ANGGARAN : TAHUN 2018

JANGKA WAKTU PELAKSANAAN = 89 HK


NO. JENIS PEKERJAAN TOTAL HARGA (Rp.) BOBOT MARET APRIL MEI KETERANGAN
4 - 10 11 17 18 - 24 25 - 31 1-7 8 - 14 15 - 21 22 - 28 29 - 5 6 - 12 13 - 19 20 - 26 27 - 31
1 PEKERJAAN STRUKTUR Rp. 31,884,082,922.16 100 %
I Pekerjaan Persiapan Rp. 208,877,312.50 0.522 0.174 0.174 0.174
II Pekerjaan Tanah Dan Lain-Lain Rp. 292,318,026.00 0.731 0.244 0.244 0.244
III Pekerjaan Tiang Pancang Dan Pondasi Garis Rp. 204,036,583.99 0.510 0.170 0.170 0.170
IV Pekerjaan Konstruksi Stadion
B. PEKERJAAN STRUKTUR TRIBUN SISI UTARA (01 S/D 08) dan SISI SELATAN (54 S/D 72)
A1 Pek. Pile Cab Pondasi Tiang Pancang Rp. 817,213,859.73 2.044 1.022 1.022
A2 Pek. Kolom Pedestal/Stek Pile Cab Rp. 236,505,612.76 0.592 0.296 0.296
A3 Pek. Tie Beam/Sloef Rp. 1,618,807,432.28 4.049 1.350 1.350 1.350
A4 Pek. Kolom Struktur Rp. 2,370,313,556.01 5.929 1.186 1.186 1.186 1.186 1.186
A5 Pek. Balok Dan Plat Tribun Lantai II Rp. 6,022,686,567.77 15.064 2.152 2.152 2.152 2.152 2.152 2.152 2.152
A6 Pekerjaan Plat, Tribun Dan Tangga Rp. 6,570,614,055.37 16.434 2.348 2.348 2.348 2.348 2.348 2.348 2.348
C. PEKERJAAN STRUKTUR TRIBUN SISI UTARA (15 S/D 10) dan SISI SELATAN (54 S/D 71)
A1 Pek. Pile Cab Pondasi Tiang Pancang Rp. 393,682,573.93 0.985 0.492 0.492
A2 Pek. Kolom Pedestal/Stek Pile Cab Rp. 168,430,406.30 0.421 0.211 0.211
A3 Pek. Tie Beam/Sloef Rp. 1,319,469,219.88 3.300 1.100 1.100 1.100
A4 Pek. Kolom Struktur Rp. 2,249,151,075.36 5.626 1.125 1.125 1.125 1.125 1.125
A5 Pek. Balok Dan Plat Tribun Lantai II Rp. 4,632,673,798.04 11.587 1.655 1.655 1.655 1.655 1.655 1.655 1.655 50 %
A6 Pekerjaan Plat, Tribun Dan Tangga Rp. 4,779,302,842.23 11.954 1.708 1.708 1.708 1.708 1.708 1.708 1.708
-
2 PEKERJAAN MEP Rp. 2,726,755,000.00
I Pekerjaan Mekanikal Dan Plumbing Rp. 2,341,835,500.00 5.857 0.732 0.732 0.732 0.732 0.732 0.732 0.732 0.732
II Pekerjaan Elektrikal Rp. 384,919,500.00 0.963 0.138 0.138 0.138 0.138 0.138 0.138 0.138

3 PEKERJAAN ARSITEK Rp. 5,369,802,300.00


I PEK. DINDING, PINTU, JENDELA & VENTILASI Rp. 747,000,000.00 1.868 0.374 0.374 0.374 0.374 0.374
II PEK. PLAFOND & LAMPU Rp. 277,620,000.00 0.694 0.139 0.139 0.139 0.139 0.139
III PEK. LANTAI RUANGAN & TRIBUN Rp. 1,573,360,000.00 3.935 0.787 0.787 0.787 0.787 0.787
IV PEK. SANITAIR TOILET VVIP, VIP, PEMAIN & PENONTON Rp. 448,680,000.00 1.122 0.224 0.224 0.224 0.224 0.224
V PEK. PAGAR LANTAI DASAR, LANTAI 1 & LANTAI 2 Rp. 1,329,600,000.00 3.326 0.831 0.831 0.831 0.831
VI PEK. RAILING TANGGA Rp. 264,800,000.00 0.662 0.166 0.166 0.166 0.166
VII PEK. FINISHING DINDING, PLAFOND & LANTAI Rp. 456,742,300.00 1.142 0.228 0.228 0.228 0.228 0.228
VIII PEK. PENGADAAN & PEMASANGAN KURSI Rp. - 0.000
IX PEK. LAIN - LAIN Rp. 272,000,000.00 0.680 0.136 0.136 0.136 0.136 0.136 0%
BOBOT RENCANA Rp. 39,980,640,222.16 100.000 0.344 1.859 4.815 3.200 3.426 11.150 11.043 11.780 12.932 13.929 11.618 11.618 2.286
KOMULATIF BOBOT RENCANA 0.000 0.344 2.203 7.018 10.218 13.643 24.793 35.836 47.617 60.549 74.478 86.096 97.714 100.000
BOBOT REALISASI 1.130
BOBOT REALISASI 1.130
DEVIASI ( + / - ) 0.785
LAPORAN MINGGUAN
KEMAJUAN PEKERJAAN
LANJUTAN PEMBANGUNAN STADION BAROMBONG
PROVINSI SULAWESI SELATAN
TAHUN ANGGARAN 2017
PEKERJAAN : LANJUTAN PEMBANGUNAN STADION BAROMBONG
INSTANSI : DINAS PEMUDA DAN OLAHRAGA
NO. KONTRAK : 416/3518/DISPORA/X/2017
NILAI KONTRAK : Rp. 43.978.704.000
KONT. PELAKSANA : PT. USAHA SUBUR SEJAHTERA MINGGU KE : Ke 1 (SATU)

KONS. PENGAWAS : PT. KANTA KARYA UATAMA MULAI TGL ; 04 Oktober 2017

PELAKSANAAN : 90 HARI KALENDER S/D TGL : 10 Oktober 2017

SUMBER DANA : APBD TAHUN 2017

TRIBUN BARAT

KONTRAK AWAL S/D MINGGU LALU MINGGU INI S/D MINGGU INI

NO. JENIS PEKERJAAN KET


VOL. SAT. HARGA SAT. JUMLAH HARGA BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) Progress

I PEKERJAAN PERSIAPAN
1 Pek. Pengukuran 1.00 Ls 2,500,000.00 2,500,000.00 0.006 - - 0.077 0.000 0.077 0.000 7.692
2 Pek. Pembersihan Lokasi Luar Pagar Existing 1.00 Ls 2,500,000.00 2,500,000.00 0.006 - - - - - - -
3 Pembuatan Direksi Keet, Uk. 9 x 4 1.00 Ls 7,500,000.00 7,500,000.00 0.019 - - - - - - -
4 Papan Nama Proyek 1.00 Ls 500,000.00 500,000.00 0.001 - - - - - - -
5 Listrik Kerja dan Air Kerja 1.00 Ls 7,500,000.00
6 P3K Dan Keselamatan Kerja 1.00 Ls 6,000,000.00 6,000,000.00 0.015 - - - - - - -
7 Dokumentasi Dan Pelaporan 1.00 Ls 7,500,000.00 7,500,000.00 0.019 - - - - - - -
8 Mobilisasi Dan Demobilisasi 1.00 Ls 7,500,000.00 7,500,000.00 0.019 - - 0.250 0.005 0.250 0.005 25.000
9 Pek. Penimbunan Sirtu Jalan Masuk Lokasi 675.00 M3 259,077.50 174,877,312.50 0.437 - - - - - - -

Jumlah I 208,877,312.50 0.52 - 0.01 0.01

II PEKERJAAN TANAH DAN LAIN - LAIN

A Pekerjaan Penimbunan Area Tribun (Luar Pagar Existing) SU (01 S/D 08) dan SS (72 S/D 79)
1 Pek. Penimbunan Tanah Sisi Luar Pagar existing 599.76 m3 248,783.33 149,210,292.00 0.373 - - - - - - -
(Daerah Rawa, Menggunakan Alat)
2 Pek. Pemadatan Lapis perlapis Per 20 Cm 599.76 m3 51,150.00 30,677,724.00 0.077 - - - - - - -

Jumlah II (B) 179,888,016.00 0.45 - - -

B Pekerjaan Penimbunan Area Tribun (Luar Pagar Existing) (79 S/D 88)
1 Pek. Penimbunan Tanah Sisi Luar Pagar existing 374.85 m3 248,783.33 93,256,432.50 0.233 - - - - - - -
(Daerah Rawa, Menggunakan Alat)
2 Pek. Pemadatan Lapis perlapis Per 20 Cm 374.85 m3 51,150.00 19,173,577.50 0.048 - - - - - - -

Jumlah II (C) 112,430,010.00 0.28 - - -


Jumlah II (A+B+C) 292,318,026.00 0.73 - - -
III PEKERJAAN TIANG PANCANG DAN PONDASI GARIS
A Pekerjaan Tiang Pancang
1 Pekerjaan Pemotongan Dan Pengupasan Tiang Pancang SU (01 S/D 8) dan SS (54 S/D 72) 125.00 ttk 223,630.00 27,953,750.00 0.070 - - 75.000 0.042 75.000 0.042 60.000
2 Pengadaan tiang Pancang Mini Pile 25x25
3 Pek. Pemancangan
TRIBUN BARAT

KONTRAK AWAL S/D MINGGU LALU MINGGU INI S/D MINGGU INI

NO. JENIS PEKERJAAN KET


VOL. SAT. HARGA SAT. JUMLAH HARGA BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) Progress

Jumlah A 27,953,750.00 0.07 - 0.04 0.04

B Pekerjaan Pondasi Garis Sisi Utara (01 S/D 8) dan Sisi Selatan (54 S/D 72)
B.1 Pekerjaan Pondasi Garis Luar Gedung (Selasar Keliling)
1 Pek. Galian Tanah Pondasi Garis 208.25 m3 66,825.00 13,916,306.25 0.035 - - - - - - -
2 Pek. Urugan Kembali 44.77 m3 22,209.00 994,380.21 0.002 - - - - - - -
3 Pek. Pasir Urug Alas Pondasi 10.41 m3 253,770.00 2,642,380.13 0.007 - - - - - - -
4 Pek. Batu Kosong 31.24 m3 682,194.15 21,310,039.76 0.053 - - - - - - -
5 Pek. Pondasi Batu Gunung, Camp. 1pc : 4ps 121.83 m3 1,126,356.00 137,219,727.65 0.343 - - - - - - -

Jumlah B (B1+B2) 176,082,833.99 0.44 - - -


Jumlah III (A+B+C+D) 204,036,583.99 0.51 - 0.04 0.04

IV PEKERJAAN KONSTRUKSI STADION


B. PEKERJAAN STRUKTUR TRIBUN SISI UTARA (01 S/D 08) dan SISI SELATAN (72 S/D 79)
B.1 Pek. Pile Cab Pondasi Tiang Pancang
1 Pek. Pile Cab Pondasi Tiang Pancang P1, Uk. 160 x 200 14.00 Bh
- Galian Tanah 86.94 m3 83,160.00 7,229,930.40 0.018 - - 86.940 0.018 86.940 0.018 100.000
- Urugan Kembali 55.58 m3 22,209.00 1,234,376.22 0.003 - - - - - - -
- Pek. Urugan Pasir Alas Pile Cap, Tbl = 10 cm 2.24 m3 253,770.00 568,444.80 0.001 - - 2.240 0.001 2.240 0.001 100.000
- Lantai Kerja Pile Cab, Beton K. 100, T = 10 Cm 2.24 m3 1,044,336.65 2,339,314.10 0.006 - - 2.240 0.006 2.240 0.006 100.000
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 26.88 m3 1,323,787.50 35,583,408.00 0.089 - - - - - - -
- Besi Beton Ulir 3,097.08 Kg 19,194.45 59,446,727.86 0.149 - - 3,097.079 0.149 3,097.079 0.149 100.000
- Bekisting 2 x Pemakaian 80.64 m2 151,195.00 12,192,364.80 0.030 - - 80.640 0.030 80.640 0.030 100.000

2 Pek. Pile Cab Pondasi Tiang Pancang P2, Uk. 160 x 160 25.00 Bh
- Galian Tanah 121.50 m3 83,160.00 10,103,940.00 0.025 - - 121.500 0.025 121.500 0.025 100.000
- Urugan Kembali 76.70 m3 22,209.00 1,703,430.30 0.004 - - - - - - -
- Pek. Urugan Pasir Alas Pile Cap, Tbl = 10 cm 3.20 m3 253,770.00 812,064.00 0.002 - - 3.200 0.002 3.200 0.002 100.000
- Lantai Kerja Pile Cab, Beton K. 100, T = 10 Cm 3.20 m3 1,044,336.65 3,341,877.29 0.008 - - 3.200 0.008 3.200 0.008 100.000
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 38.40 m3 1,323,787.50 50,833,440.00 0.127 - - - - - - -
- Besi Beton Ulir 7,518.34 Kg 19,194.45 144,310,416.57 0.361 - - 7,518.341 0.361 7,518.341 0.361 100.000
- Bekisting 2 x Pemakaian 112.00 m2 151,195.00 16,933,840.00 0.042 - - 112.000 0.042 112.000 0.042 100.000

3 Pek. Pile Cab Pondasi Tiang Pancang P3, Uk. 160 x 160 25.00 Bh
- Galian Tanah 121.50 m3 83,160.00 10,103,940.00 0.025 - - 121.500 0.025 121.500 0.025 100.000
- Urugan Kembali 76.70 m3 22,209.00 1,703,430.30 0.004 - - - - - - -
- Pek. Urugan Pasir Alas Pile Cap, Tbl = 10 cm 3.20 m3 253,770.00 812,064.00 0.002 - - 3.200 0.002 3.200 0.002 100.000
- Lantai Kerja Pile Cab, Beton K. 100, T = 10 Cm 3.20 m3 1,044,336.65 3,341,877.29 0.008 - - 3.200 0.008 3.200 0.008 100.000
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 38.40 m3 1,323,787.50 50,833,440.00 0.127 - - - - - - -
- Besi Beton Ulir 7,518.34 Kg 19,194.45 144,310,416.57 0.361 - - 7,518.341 0.361 7,518.341 0.361 100.000
- Bekisting 2 x Pemakaian 112.00 m2 151,195.00 16,933,840.00 0.042 - - 112.000 0.042 112.000 0.042 100.000

4 Pek. Pile Cab Pondasi Tiang Pancang P4, Uk. 120 x 120 25.00 Bh
- Galian Tanah 84.38 m3 83,160.00 7,016,625.00 0.018 - - - - - - -
- Urugan Kembali 59.18 m3 22,209.00 1,314,217.58 0.003 - - - - - - -
- Pek. Urugan Pasir Alas Pile Cap, Tbl = 10 cm 1.80 m3 253,770.00 456,786.00 0.001 - - - - - - -
- Lantai Kerja Pile Cab, Beton K. 100, T = 10 Cm 1.80 m3 1,044,336.65 1,879,805.98 0.005 - - - - - - -
TRIBUN BARAT

KONTRAK AWAL S/D MINGGU LALU MINGGU INI S/D MINGGU INI

NO. JENIS PEKERJAAN KET


VOL. SAT. HARGA SAT. JUMLAH HARGA BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) Progress

- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 21.60 m3 1,323,787.50 28,593,810.00 0.072 - - - - - - -
- Besi Beton Ulir 4,928.55 Kg 19,194.45 94,600,760.48 0.237 - - - - - - -
- Bekisting 2 x Pemakaian 84.00 m2 151,195.00 12,700,380.00 0.032 - - - - - - -

5 Pek. Pile Cab Pondasi Tiang Pancang P5, Uk. 90 x 90 25.00 Bh -


- Galian Tanah 54.00 m3 83,160.00 4,490,640.00 0.011 - - - - - - -
- Urugan Kembali 39.83 m3 22,209.00 884,473.43 0.002 - - - - - - -
- Pek. Urugan Pasir Alas Pile Cap, Tbl = 10 cm 1.01 m3 253,770.00 256,942.13 0.001 - - - - - - -
- Lantai Kerja Pile Cab, Beton K. 100, T = 10 Cm 1.01 m3 1,044,336.65 1,057,390.86 0.003 - - - - - - -
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 12.15 m3 1,323,787.50 16,084,018.13 0.040 - - - - - - -
- Besi Beton Ulir 3,317.63 Kg 19,194.45 63,680,142.66 0.159 - - - - - - -
- Bekisting 2 x Pemakaian 63.00 m2 151,195.00 9,525,285.00 0.024 - - - - - - -

Jumlah B.1 817,213,859.73 2.04 - 1.08 1.08

B.2 Pek. Kolom Pedestal/Stek Pile Cab


1 Pek. Kolom Pedestal/Stek Pile Cab Pond. Tiang Pancang P1, Uk. 80 x 100 14.00 Bh
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 8.96 m3 1,323,787.50 11,861,136.00 0.030 - - - - - - -
- Besi Beton Ulir 2,455.90 Kg 19,194.45 47,139,635.63 0.118 - - - - - - -
- Bekisting 2 x Pemakaian 40.32 m2 258,242.88 10,412,352.72 0.026 - - - - - - -

2 Pek. Kolom Pedestal/Stek Pile Cab Pond. Tiang Pancang P2, Uk. 80 x 80 14.00 Bh
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 7.17 m3 1,323,787.50 9,488,908.80 0.024 - - - - - - -
- Besi Beton Ulir 2,020.34 Kg 19,194.45 38,779,401.10 0.097 - - - - - - -
- Bekisting 2 x Pemakaian 35.84 m2 258,242.88 9,255,424.64 0.023 - - - - - - -
3 Pek. Kolom Pedestal/Stek Pile Cab Pond. Tiang Pancang P3, Uk. 60 x 80 14.00 Bh
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 5.38 m3 1,323,787.50 7,116,681.60 0.018 - - - - - - -
- Besi Beton Ulir 1,638.09 Kg 19,194.45 31,442,327.81 0.079 - - - - - - -
- Bekisting 2 x Pemakaian 31.36 m2 258,242.88 8,098,496.56 0.020 - - - - - - -
4 Pek. Kolom Pedestal/Stek Pile Cab Pond. Tiang Pancang P4, Uk. 40 x 40 14.00 Bh
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 1.79 m3 1,323,787.50 2,372,227.20 0.006 - - - - - - -
- Besi Beton Ulir 658.99 Kg 19,194.45 12,649,029.53 0.032 - - - - - - -
- Bekisting 2 x Pemakaian 17.92 m2 258,242.88 4,627,712.32 0.012 - - - - - - -
5 Pek. Kolom Pedestal/Stek Pile Cab Pond. Tiang Pancang P5, Uk. 30 x 30 14.00 Bh
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 3.53 m3 1,323,787.50 4,670,322.30 0.012 - - - - - - -
- Besi Beton Ulir 1,377.70 Kg 19,194.45 26,444,211.70 0.066 - - - - - - -
- Bekisting 2 x Pemakaian 47.04 m2 258,242.88 12,147,744.84 0.030 - - - - - - -
Jumlah B.2 236,505,612.76 0.59 - - -

B.3 Pek. Tie Beam/Sloef


1 Pek. Tie Beam TB1, Uk. 40/80 749.56 M'
- Pasir Urug Alas Tie Beam, T = 5 cm 14.99 m3 253,770.00 3,804,316.82 0.010 - - - - - - -
- Lantai Kerja Tie Beam, Beton K. 100, T = 5 Cm 14.99 m3 1,044,336.65 15,655,859.64 0.039 - - - - - - -
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 239.86 m3 1,323,787.50 317,522,610.72 0.794 - - - - - - -
- Besi Beton Ulir 40,239.99 Kg 19,194.45 772,384,546.68 1.932 - - - - - - -
- Bekisting 2 x Pemakaian 1,349.21 m2 159,241.50 214,849,905.73 0.537 - - - - - - -

2 Pek. Tie Beam TB1, Uk. 40/80 (Selasar Luar Keliling Stadion) 42.00 M'
TRIBUN BARAT

KONTRAK AWAL S/D MINGGU LALU MINGGU INI S/D MINGGU INI

NO. JENIS PEKERJAAN KET


VOL. SAT. HARGA SAT. JUMLAH HARGA BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) Progress

- Pasir Urug Alas Tie Beam, T = 5 cm 0.84 m3 253,770.00 213,166.80 0.001 - - - - - - -


- Lantai Kerja Tie Beam, Beton K. 100, T = 5 Cm 0.84 m3 1,044,336.65 877,242.79 0.002 - - - - - - -
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 13.44 m3 1,323,787.50 17,791,704.00 0.045 - - - - - - -
- Besi Beton Ulir 2,254.76 Kg 19,194.45 43,278,924.92 0.108 - - - - - - -
- Bekisting 2 x Pemakaian 75.60 m2 159,241.50 12,038,657.40 0.030 - - - - - - -

3 Pek. Tie Beam TB2, Uk. 30/80 102.48


- Pasir Urug Alas Tie Beam, T = 5 cm 1.54 m3 253,770.00 390,095.24 0.001 - - - - - - -
- Lantai Kerja Tie Beam, Beton K. 100, T = 5 Cm 1.54 m3 1,044,336.65 1,605,354.30 0.004 - - - - - - -
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 24.60 m3 1,323,787.50 32,558,818.32 0.081 - - - - - - -
- Besi Beton Ulir 4,450.32 Kg 19,194.45 85,421,504.70 0.214 - - - - - - -
- Bekisting 2 x Pemakaian 184.46 m2 159,241.50 29,374,324.06 0.073 - - - - - - -
4 Pek. Sloef/Tie Beam Type TB3, Uk. 25 x 50 Cm 76.00 M'
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 9.50 m3 1,323,787.50 12,575,981.25 0.031 - - - - - - -
- Besi Beton Ulir 2,289.29 Kg 19,194.45 43,941,594.11 0.110 - - - - - - -
- Bekisting 2 x Pemakaian 91.20 m2 159,241.50 14,522,824.80 0.036 - - - - - - -
4 Pek. Sloef/Tie Beam Type TB4, Uk. 30 x 60 Cm 76.00 M'
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52
- Besi Beton Ulir
- Bekisting 2 x Pemakaian
Jumlah B.3 1,618,807,432.28 4.05 - - -

B.4 Pek. Kolom Struktur


I Pekerjaan Kolom Lt. I
1 Pek. Kolom Type K1, Uk. 80 x 100 Cm 14.00 Bh
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 56.00 m3 1,323,787.50 74,132,100.00 0.185 - - - - - - -
- Besi Beton Ulir 9,021.12 Kg 22,312.95 201,287,826.28 0.503 - - - - - - -
- Bekisting 2 x Pemakaian 252.00 m2 258,242.88 65,077,204.50 0.163 - - - - - - -

2 Pek. Kolom Type K2, Uk. 80 x 80 Cm 14.00 Bh


- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 44.80 m3 1,323,787.50 59,305,680.00 0.148 - - - - - - -
- Besi Beton Ulir 7,595.28 Kg 22,312.95 169,473,102.88 0.424 - - - - - - -
- Bekisting 2 x Pemakaian 224.00 m2 258,242.88 57,846,404.00 0.145 - - - - - - -

3 Pek. Kolom Type K3, Uk. 60 x 80 Cm 14.00 Bh


- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 33.60 m3 1,323,787.50 44,479,260.00 0.111 - - - - - - -
- Besi Beton Ulir 5,934.68 Kg 22,312.95 132,420,119.93 0.331 - - - - - - -
- Bekisting 2 x Pemakaian 196.00 m2 258,242.88 50,615,603.50 0.127 - - - - - - -

4 Pek. Kolom Type K4, Uk. 40 x 40 Cm 14.00 Bh


- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 6.72 m3 1,323,787.50 8,895,852.00 0.022 - - - - - - -
- Besi Beton Ulir 1,375.44 Kg 22,312.95 30,690,038.27 0.077 - - - - - - -
- Bekisting 2 x Pemakaian 67.20 m2 258,242.88 17,353,921.20 0.043 - - - - - - -

5 Pek. Kolom Type K5, Uk. 30 x 30 Cm


- Beton mutu f'c=14,5 Mpa (K 175), slump (12 ± 2) cm, w/c=0,66 6.66 m3 1,025,184.81 6,827,730.83 0.017 - - - - - - -
- Besi Beton Polos 1,810.24 Kg 22,312.95 40,391,823.17 0.101 - - - - - - -
TRIBUN BARAT

KONTRAK AWAL S/D MINGGU LALU MINGGU INI S/D MINGGU INI

NO. JENIS PEKERJAAN KET


VOL. SAT. HARGA SAT. JUMLAH HARGA BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) Progress

- Bekisting 2 x Pemakaian 128.40 m2 258,242.88 33,158,385.15 0.083 - - - - - - -

II Pekerjaan Kolom Lt. II


1 Pek. Kolom Type K1, Uk. 80 x 100 Cm 14.00 Bh
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 59.02 m3 1,323,787.50 78,135,233.40 0.195 - - - - - - -
- Besi Beton Ulir 10,374.29 Kg 22,312.95 231,481,000.22 0.579 - - - - - - -
- Bekisting 2 x Pemakaian 289.80 m2 258,242.88 74,838,785.18 0.187 - - - - - - -

2 Pek. Kolom Type K2, Uk. 80 x 80 Cm 14.00 Bh


- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 51.52 m3 1,323,787.50 68,201,532.00 0.171 - - - - - - -
- Besi Beton Ulir 8,734.57 Kg 22,312.95 194,894,068.31 0.487 - - - - - - -
- Bekisting 2 x Pemakaian 257.60 m2 258,242.88 66,523,364.60 0.166 - - - - - - -

3 Pek. Kolom Type K3, Uk. 60 x 80 Cm 14.00 Bh


- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 20.16 m3 1,323,787.50 26,687,556.00 0.067 - - - - - - -
- Besi Beton Ulir 3,560.81 Kg 22,312.95 79,452,071.96 0.199 - - - - - - -
- Bekisting 2 x Pemakaian 117.60 m2 258,242.88 30,369,362.10 0.076 - - - - - - -

4 Pek. Kolom Type KP, Uk. 15 x 15 Cm


- Beton mutu f'c=14,5 Mpa (K 175), slump (12 ± 2) cm, w/c=0,66 8.28 m3 1,025,184.81 8,488,530.22 0.021 - - - - - - -
- Besi Beton Polos 1,916.61 Kg 22,312.95 42,765,326.99 0.107 - - - - - - -
- Bekisting 2 x Pemakaian 110.40 m2 258,242.88 28,510,013.40 0.071 - - - - - - -

5 Pek. Kolom Railing, Uk. 15 x 15 Cm, T = 100 Cm


- Beton mutu f'c=14,5 Mpa (K 175), slump (12 ± 2) cm, w/c=0,66 0.63 m3 1,025,184.81 645,866.43 0.002 - - - - - - -
- Besi Beton Polos 145.83 Kg 22,312.95 3,253,883.58 0.008 - - - - - - -
- Bekisting 2 x Pemakaian 8.40 m2 258,242.88 2,169,240.15 0.005 - - - - - - -

III Pekerjaan Kolom Lt. III


1 Pek. Kolom K1, Uk. 80 x 100 14.00 Bh
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 39.65 m3 1,323,787.50 52,485,526.80 0.131 - - - - - - -
- Besi Beton Ulir 6,386.95 Kg 22,312.95 142,511,781.01 0.356 - - - - - - -
- Bekisting 2 x Pemakaian 178.42 m2 258,242.88 46,074,660.79 0.115 - - - - - - -

2 Pek. Kolom Dudukan Kuda-Kuda, Uk. 80 x 100 14.00 Bh


- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 30.69 m3 1,323,787.50 40,624,390.80 0.102 - - - - - - -
- Besi Beton Ulir 4,943.57 Kg 22,312.95 110,305,728.80 0.276 - - - - - - -
- Bekisting 2 x Pemakaian 138.10 m2 258,242.88 35,662,308.07 0.089 - - - - - - -

3 Pek. Kolom Type KP, Uk. 15 x 15 Cm


- Beton mutu f'c=14,5 Mpa (K 175), slump (12 ± 2) cm, w/c=0,66 1.50 m3 1,025,184.81 1,533,932.77 0.004 - - - - - - -
- Besi Beton Polos 342.70 Kg 22,312.95 7,646,626.40 0.019 - - - - - - -
- Bekisting 2 x Pemakaian 19.74 m2 258,242.88 5,097,714.35 0.013 - - - - - - -

Jumlah B.4 2,370,313,556.01 5.93 - - -

B.5 Pek. Balok Dan Plat Tribun Lantai II


I Pekerjaan Balok Lt. II
TRIBUN BARAT

KONTRAK AWAL S/D MINGGU LALU MINGGU INI S/D MINGGU INI

NO. JENIS PEKERJAAN KET


VOL. SAT. HARGA SAT. JUMLAH HARGA BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) Progress

1 Pek. Balok Plat B1, Uk. 40/80


- Beton K.300 211.88 m3 1,025,184.81 217,213,204.91 0.543 - - - - - - -
- Besi Beton Ulir 44,305.91 Kg 22,312.95 988,595,616.53 2.473 - - - - - - -
- Bekisting 2 x Pemakaian 1,370.97 m2 264,277.75 362,316,761.21 0.906 - - - - - - -

2 Pek. Balok Plat BA, Uk. 30/60


- Beton K.300 154.95 m3 1,025,184.81 158,849,187.66 0.397 - - - - - - -
- Besi Beton Ulir 34,826.73 Kg 22,312.95 777,087,137.03 1.944 - - - - - - -
- Bekisting 2 x Pemakaian 1,299.84 m2 264,277.75 343,519,107.69 0.859 - - - - - - -

3 Pek. Balok Plat B1, Uk. 40/80 (Konsol)


- Beton K.300 7.62 m3 1,025,184.81 7,807,807.51 0.020 - - - - - - -
- Besi Beton Ulir 1,592.59 Kg 22,312.95 35,535,428.34 0.089 - - - - - - -
- Bekisting 2 x Pemakaian 49.28 m2 264,277.75 13,023,607.52 0.033 - - - - - - -

4 Pek. Balok Plat BA, Uk. 30/60 (Konsol)


- Beton K.300 m3 1,205,977.50
- Besi Beton Ulir Kg 17,463.60
- Bekisting 2 x Pemakaian m2 280,791.50

5 Pek. Balok Type B2, Uk. 25 x 50 Cm


- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 12.13 m3 1,025,184.81 12,435,081.67 0.031 - - - - - - -
- Besi Beton Ulir 2,024.28 Kg 22,312.95 45,167,663.25 0.113 - - - - - - -
- Bekisting 2 x Pemakaian 112.78 m2 264,277.75 29,806,301.76 0.075 - - - - - - -

II Pekerjaan Balok Lt. III Dan Tribun Bagian Atas


a. Area Tribun LT. III
1 Pek. Balok Plat B1, Area Tribun , Uk. 40/80
- Beton K.300 171.49 m3 1,025,184.81 175,813,453.80 0.440 - - - - - - -
- Besi Beton Ulir 30,482.21 Kg 22,312.95 680,148,098.50 1.701 - - - - - - -
- Bekisting 2 x Pemakaian 1,071.84 m2 264,277.75 283,263,463.56 0.709 - - - - - - -
2 Pek. Balok Plat BA, Area Tribun, Uk. 30/60
- Beton K.300 88.72 m3 1,025,184.81 90,953,494.14 0.227 - - - - - - -
- Besi Beton Ulir 19,941.01 Kg 22,312.95 444,942,724.63 1.113 - - - - - - -
- Bekisting 2 x Pemakaian 759.88 m2 264,277.75 200,819,588.09 0.502 - - - - - - -
3 Pek. Balok Plat B1, Area Tribun VIP Dan VVIP, Uk. 40/80 (Konsol)
- Beton K.300 11.20 m3 1,025,184.81 11,482,069.87 0.029 - - - - - - -
- Besi Beton Ulir 2,146.10 Kg 22,312.95 47,885,780.72 0.120 - - - - - - -
- Bekisting 2 x Pemakaian 70.00 m2 264,277.75 18,499,442.50 0.046 - - - - - - -
5 Pek. Balok Type B2, Uk. 25 x 50 Cm
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 11.44 m3 1,025,184.81 11,726,063.85 0.029 - - - - - - -
- Besi Beton Ulir 1,908.86 Kg 22,312.95 42,592,314.03 0.107 - - - - - - -
- Bekisting 2 x Pemakaian 121.60 m2 264,277.75 32,137,231.51 0.080 - - - - - - -

b. Area Tribun Bagian Atas


1 Pek. Balok Plat B1, Uk. 40/80 (Bagian Atas)
- Beton K.300 63.17 m3 1,025,184.81 64,765,763.29 0.162 - - - - - - -
- Besi Beton Ulir 11,228.97 Kg 22,312.95 250,551,421.40 0.627 - - - - - - -
- Bekisting 2 x Pemakaian 408.78 m2 264,277.75 108,030,824.38 0.270 - - - - - - -
TRIBUN BARAT

KONTRAK AWAL S/D MINGGU LALU MINGGU INI S/D MINGGU INI

NO. JENIS PEKERJAAN KET


VOL. SAT. HARGA SAT. JUMLAH HARGA BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) Progress

2 Pek. Balok Plat BA, Uk. 30/60


- Beton K.300 32.64 m3 1,025,184.81 33,461,048.01 0.084 - - - - - - -
- Besi Beton Ulir 7,336.13 Kg 22,312.95 163,690,796.16 0.409 - - - - - - -
- Bekisting 2 x Pemakaian 285.59 m2 264,277.75 75,475,505.47 0.189 - - - - - - -

c. Pek. Ringbalk Penghubung Kolom Kuda-Kuda


1 Pek. Ringbalk RB, Uk. 60 x 80
- Beton K.300 53.96 m3 1,025,184.81 55,320,612.62 0.138 - - - - - - -
- Besi Beton Ulir 7,816.44 Kg 22,312.95 174,407,735.95 0.436 - - - - - - -
- Bekisting 2 x Pemakaian 247.32 m2 264,277.75 65,362,230.24 0.163 - - - - - - -

Jumlah B5 6,022,686,567.77 15.06 - - -

B.6 Pekerjaan Plat, Tribun Dan Tangga


1 Pek. Plat lantai Lantai II
- Pek. Plat Lt. II, Tbl = 12 cm
- Beton K.300 189.81 m3 1,025,184.81 194,590,328.70 0.487 - - - - - - -
- Besi Beton Ulir 23,403.57 Kg 22,312.95 522,202,754.17 1.306 - - - - - - -
- Bekisting 2 x Pemakaian 1,581.75 m2 313,242.88 495,471,917.53 1.239 - - - - - - -

2 Pek. Plat Tribun


- Pek. Plat Tribun Lt. II, Tbl = 12 cm
- Beton K.300 180.74 m3 1,025,184.81 185,295,511.12 0.463 - - - - - - -
- Besi Beton Ulir 22,285.68 Kg 22,312.95 497,259,174.66 1.244 - - - - - - -
- Bekisting 2 x Pemakaian 2,671.35 m2 313,242.88 836,781,354.13 2.093 - - - - - - -

3 - Pek. Plat Tribun Lt. III, Tbl = 12 cm,


- Beton K.300 190.04 m3 1,025,184.81 194,828,155.17 0.487 - - - - - - -
- Besi Beton Ulir 23,432.18 Kg 22,312.95 522,840,985.47 1.308 - - - - - - -
- Bekisting 2 x Pemakaian 1,583.68 m2 313,242.88 496,077,478.66 1.241 - - - - - - -

4 - Pek. Plat Tribun Lt. III, Tbl = 12 cm, Area Tribun Bagian Atas
- Beton K.300 215.65 m3 1,025,184.81 221,079,439.27 0.553 - - - - - - -
- Besi Beton Ulir 26,589.44 Kg 22,312.95 593,288,951.48 1.484 - - - - - - -
- Bekisting 2 x Pemakaian 2,117.94 m2 313,242.88 663,428,173.76 1.659 - - - - - - -

5 Pek. Plat Dinding Depan Tribun Lt. II, Tbl = 15 cm (Dekat Lapangan)
- Beton K.300 14.11 m3 1,025,184.81 14,467,408.03 0.036 - - - - - - -
- Besi Beton Ulir 1,856.01 Kg 22,312.95 41,413,063.68 0.104 - - - - - - -
- Bekisting 2 x Pemakaian 188.16 m2 453,744.50 85,376,565.12 0.214 - - - - - - -

6 Pek. Plat Dinding Depan Tribun Lt. III, Tbl = 15 cm


- Beton K.300 14.11 m3 1,025,184.81 14,467,408.03 0.036 - - - - - - -
- Besi Beton Ulir 1,856.01 Kg 22,312.95 41,413,063.68 0.104 - - - - - - -
- Bekisting 2 x Pemakaian 188.16 m2 453,744.50 85,376,565.12 0.214 - - - - - - -

7 Pek. Tangga Beton


I Pek. Tangga Beton Lantai I - II
TRIBUN BARAT

KONTRAK AWAL S/D MINGGU LALU MINGGU INI S/D MINGGU INI

NO. JENIS PEKERJAAN KET


VOL. SAT. HARGA SAT. JUMLAH HARGA BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) Progress

a. Pek. Tangga Beton I (Area Tribun) 7.00 Bh


- Pek. Sloef/Tie Beam Tangga, Uk. 30/60
- Pasir Urug Alas Tie Beam, T = 5 cm 0.84 m3 253,770.00 213,166.80 0.001 - - - - - - -
- Lantai Kerja Tie Beam, Beton K. 100, T = 5 Cm 0.84 m3 1,044,336.65 877,242.79 0.002 - - - - - - -
- Beton K.300 2.52 m3 1,205,977.50 3,039,063.30 0.008 - - - - - - -
- Besi Beton Ulir 453.13 Kg 22,312.95 10,110,611.25 0.025 - - - - - - -
- Bekisting 2 x Pemakaian 84.00 m2 159,241.50 13,376,286.00 0.033 - - - - - - -

- Pek. Tangga Beton


- Beton K.300 18.50 m3 1,205,977.50 22,311,789.73 0.056 - - - - - - -
- Besi Beton Ulir 5,129.77 Kg 22,312.95 114,460,242.09 0.286 - - - - - - -
- Bekisting 2 x Pemakaian 163.59 m2 241,737.38 39,545,817.18 0.099 - - - - - - -

b. Pek. Tangga Beton II (Area Plat Lt. II/Plat datar) 7.00 Bh


- Pek. Sloef/Tie Beam Tangga, Uk. 30/60
- Pasir Urug Alas Tie Beam, T = 5 cm 0.84 m3 253,770.00 213,166.80 0.001 - - - - - - -
- Lantai Kerja Tie Beam, Beton K. 100, T = 5 Cm 0.84 m3 1,044,336.65 877,242.79 0.002 - - - - - - -
- Beton K.300 2.52 m3 1,205,977.50 3,039,063.30 0.008 - - - - - - -
- Besi Beton Ulir 453.13 Kg 22,312.95 10,110,611.25 0.025 - - - - - - -
- Bekisting 2 x Pemakaian 84.00 m2 159,241.50 13,376,286.00 0.033 - - - - - - -

- Pek. Kolom Tangga Beton, Uk. 30 x 30


- Beton K.300 1.89 m3 1,205,977.50 2,279,297.48 0.006 - - - - - - -
- Besi Beton Ulir 513.72 Kg 22,312.95 11,462,544.41 0.029 - - - - - - -
- Bekisting 2 x Pemakaian 25.20 m2 258,242.88 6,507,720.45 0.016 - - - - - - -

- Pek. Balok Tangga Beton, Uk. 25 x 40


- Beton K.300 1.40 m3 1,205,977.50 1,688,368.50 0.004 - - - - - - -
- Besi Beton Ulir 233.55 Kg 22,312.95 5,211,297.91 0.013 - - - - - - -
- Bekisting 2 x Pemakaian 14.70 m2 264,277.75 3,884,882.93 0.010 - - - - - - -

- Pek. Tangga Beton


- Beton K.300 30.30 m3 1,205,977.50 36,544,736.18 0.091 - - - - - - -
- Besi Beton Ulir 8,402.10 Kg 22,312.95 187,475,742.72 0.469 - - - - - - -
- Bekisting 2 x Pemakaian 270.27 m2 241,737.38 65,334,360.34 0.163 - - - - - - -

II Pek. Tangga Beton Lantai II - III


a. Pek. Tangga Beton III (Area Tribun Biasa) 7.00 Bh
- Pek. Kolom Tangga Beton, Uk. 30 x 30
- Beton K.300 2.77 m3 1,205,977.50 3,342,969.63 0.008 - - - - - - -
- Besi Beton Ulir 753.45 Kg 22,312.95 16,811,731.81 0.042 - - - - - - -
- Bekisting 2 x Pemakaian 36.96 m2 258,242.88 9,544,656.66 0.024 - - - - - - -
- Pek. Balok Tangga Beton, Uk. 25 x 40
- Beton K.300 2.80 m3 1,205,977.50 3,376,737.00 0.008 - - - - - - -
- Besi Beton Ulir 467.11 Kg 22,312.95 10,422,595.83 0.026 - - - - - - -
- Bekisting 2 x Pemakaian 29.40 m2 264,277.75 7,769,765.85 0.019 - - - - - - -
- Pek. Tangga Beton
- Beton K.300 27.24 m3 1,205,977.50 32,847,209.17 0.082 - - - - - - -
- Besi Beton Ulir 7,552.00 Kg 22,312.95 168,507,303.05 0.421 - - - - - - -
TRIBUN BARAT

KONTRAK AWAL S/D MINGGU LALU MINGGU INI S/D MINGGU INI

NO. JENIS PEKERJAAN KET


VOL. SAT. HARGA SAT. JUMLAH HARGA BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) Progress

- Bekisting 2 x Pemakaian 249.83 m2 241,737.38 60,393,248.40 0.151 - - - - - - -

Jumlah B6 6,570,614,055.37 16.43 - - -

Jumlah IV B (B1+B2+B3+B4+B5+B6) 17,636,141,083.92 44.11 - 1.08 1.08

C. PEKERJAAN STRUKTUR VVIP BARAT (79 S/D 01)


C.1 Pek. Pile Cab Pondasi Tiang Pancang
1 Pek. Pile Cab Pondasi Tiang Pancang P1, Uk. 160 x 200 11.00 Bh
- Galian Tanah 68.31 m3 83,160.00 5,680,659.60 0.014 - - - - - - -
- Urugan Kembali 43.67 m3 22,209.00 969,867.03 0.002 - - - - - - -
- Pek. Urugan Pasir Alas Pile Cap, Tbl = 10 cm 1.76 m3 253,770.00 446,635.20 0.001 - - - - - - -
- Lantai Kerja Pile Cab, Beton K. 100, T = 10 Cm 1.76 m3 1,110,589.46 1,954,637.46 0.005 - - - - - - -
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 21.12 m3 1,323,787.50 27,958,392.00 0.070 - - - - - - -
- Besi Beton Ulir 2,433.42 Kg 22,312.95 54,296,761.12 0.136 - - - - - - -
- Bekisting 2 x Pemakaian 63.36 m2 151,195.00 9,579,715.20 0.024 - - - - - - -

2 Pek. Pile Cab Pondasi Tiang Pancang P2, Uk. 160 x 160 11.00 Bh
- Galian Tanah 53.46 m3 83,160.00 4,445,733.60 0.011 - - - - - - -
- Urugan Kembali 33.75 m3 22,209.00 749,509.33 0.002 - - - - - - -
- Pek. Urugan Pasir Alas Pile Cap, Tbl = 10 cm 1.41 m3 253,770.00 357,308.16 0.001 - - - - - - -
- Lantai Kerja Pile Cab, Beton K. 100, T = 10 Cm 1.41 m3 1,110,589.46 1,563,709.97 0.004 - - - - - - -
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 16.90 m3 1,323,787.50 22,366,713.60 0.056 - - - - - - -
- Besi Beton Ulir 3,308.07 Kg 22,312.95 73,812,799.44 0.185 - - - - - - -
- Bekisting 2 x Pemakaian 49.28 m2 151,195.00 7,450,889.60 0.019 - - - - - - -

3 Pek. Pile Cab Pondasi Tiang Pancang P3, Uk. 160 x 160 11.00 Bh
- Galian Tanah 53.46 m3 83,160.00 4,445,733.60 0.011 - - - - - - -
- Urugan Kembali 33.75 m3 22,209.00 749,509.33 0.002 - - - - - - -
- Pek. Urugan Pasir Alas Pile Cap, Tbl = 10 cm 1.41 m3 253,770.00 357,308.16 0.001 - - - - - - -
- Lantai Kerja Pile Cab, Beton K. 100, T = 10 Cm 1.41 m3 1,110,589.46 1,563,709.97 0.004 - - - - - - -
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 16.90 m3 1,323,787.50 22,366,713.60 0.056 - - - - - - -
- Besi Beton Ulir 3,308.07 Kg 22,312.95 73,812,799.44 0.185 - - - - - - -
- Bekisting 2 x Pemakaian 49.28 m2 151,195.00 7,450,889.60 0.019 - - - - - - -

4 Pek. Pile Cab Pondasi Tiang Pancang P4, Uk. 120 x 120 11.00 Bh
- Galian Tanah 37.13 m3 83,160.00 3,087,315.00 0.008 - - - - - - -
- Urugan Kembali 26.04 m3 22,209.00 578,255.73 0.001 - - - - - - -
- Pek. Urugan Pasir Alas Pile Cap, Tbl = 10 cm 0.79 m3 253,770.00 200,985.84 0.001 - - - - - - -
- Lantai Kerja Pile Cab, Beton K. 100, T = 10 Cm 0.79 m3 1,110,589.46 879,586.86 0.002 - - - - - - -
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 9.50 m3 1,323,787.50 12,581,276.40 0.031 - - - - - - -
- Besi Beton Ulir 2,168.56 Kg 22,312.95 48,386,991.92 0.121 - - - - - - -
- Bekisting 2 x Pemakaian 36.96 m2 151,195.00 5,588,167.20 0.014 - - - - - - -

Jumlah C.1 393,682,573.93 0.98 - - -


C.2 Pek. Kolom Pedestal/Stek Pile Cab
1 Pek. Kolom Pedestal/Stek Pile Cab Pond. Tiang Pancang P1, Uk. 80 x 100 11.00 Bh
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 7.04 m3 1,323,787.50 9,319,464.00 0.023 - - - - - - -
- Besi Beton Ulir 1,929.64 Kg 22,312.95 43,055,852.31 0.108 - - - - - - -
- Bekisting 2 x Pemakaian 31.68 m2 258,242.88 8,181,134.28 0.020 - - - - - - -
TRIBUN BARAT

KONTRAK AWAL S/D MINGGU LALU MINGGU INI S/D MINGGU INI

NO. JENIS PEKERJAAN KET


VOL. SAT. HARGA SAT. JUMLAH HARGA BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) Progress

2 Pek. Kolom Pedestal/Stek Pile Cab Pond. Tiang Pancang P2, Uk. 80 x 80 11.00 Bh
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 5.63 m3 1,323,787.50 7,455,571.20 0.019 - - - - - - -
- Besi Beton Ulir 1,587.41 Kg 22,312.95 35,419,878.50 0.089 - - - - - - -
- Bekisting 2 x Pemakaian 28.16 m2 258,242.88 7,272,119.36 0.018 - - - - - - -
3 Pek. Kolom Pedestal/Stek Pile Cab Pond. Tiang Pancang P3, Uk. 60 x 80 11.00 Bh
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 4.22 m3 1,323,787.50 5,591,678.40 0.014 - - - - - - -
- Besi Beton Ulir 1,287.07 Kg 22,312.95 28,718,427.80 0.072 - - - - - - -
- Bekisting 2 x Pemakaian 24.64 m2 258,242.88 6,363,104.44 0.016 - - - - - - -
4 Pek. Kolom Pedestal/Stek Pile Cab Pond. Tiang Pancang P4, Uk. 40 x 40 11.00 Bh
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 1.41 m3 1,323,787.50 1,863,892.80 0.005 - - - - - - -
- Besi Beton Ulir 517.78 Kg 22,312.95 11,553,223.53 0.029 - - - - - - -
- Bekisting 2 x Pemakaian 14.08 m2 258,242.88 3,636,059.68 0.009 - - - - - - -

Jumlah C.2 168,430,406.30 0.42 - - -

C.3 Pek. Tie Beam/Sloef


1 Pek. Tie Beam TB1, Uk. 40/80 608.80 M'
- Pasir Urug Alas Tie Beam, T = 5 cm 12.18 m3 253,770.00 3,089,903.52 0.008 - - - - - - -
- Lantai Kerja Tie Beam, Beton K. 100, T = 5 Cm 12.18 m3 1,044,336.65 12,715,843.09 0.032 - - - - - - -
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 194.82 m3 1,323,787.50 257,894,985.60 0.645 - - - - - - -
- Besi Beton Ulir 32,683.32 Kg 22,312.95 729,261,249.65 1.824 - - - - - - -
- Bekisting 2 x Pemakaian 1,095.84 m2 159,241.50 174,503,205.36 0.436 - - - - - - -

2 Pek. Tie Beam TB1, Uk. 40/80 (Selasar Luar Keliling Stadion) 33.00 M'
- Pasir Urug Alas Tie Beam, T = 5 cm 0.66 m3 253,770.00 167,488.20 0.000 - - - - - - -
- Lantai Kerja Tie Beam, Beton K. 100, T = 5 Cm 0.66 m3 1,044,336.65 689,262.19 0.002 - - - - - - -
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 10.56 m3 1,323,787.50 13,979,196.00 0.035 - - - - - - -
- Besi Beton Ulir 1,771.60 Kg 22,312.95 39,529,601.25 0.099 - - - - - - -
- Bekisting 2 x Pemakaian 59.40 m2 159,241.50 9,458,945.10 0.024 - - - - - - -

4 Pek. Sloef/Tie Beam Type TB3, Uk. 25 x 50 Cm 76.00 M'


- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 9.50 m3 1,323,787.50 12,575,981.25 0.031 - - - - - - -
- Besi Beton Ulir 2,289.29 Kg 22,312.95 51,080,733.87 0.128 - - - - - - -
- Bekisting 2 x Pemakaian 91.20 m2 159,241.50 14,522,824.80 0.036 - - - - - - -

Jumlah C.3 1,319,469,219.88 3.30 - - -

C.4 Pek. Kolom Struktur


I Pekerjaan Kolom Lt. I
1 Pek. Kolom Type K1, Uk. 80 x 100 Cm 11.00 Bh
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 44.00 m3 1,323,787.50 58,246,650.00 0.146 - - - - - - -
- Besi Beton Ulir 7,088.02 Kg 22,312.95 158,154,720.65 0.396 - - - - - - -
- Bekisting 2 x Pemakaian 198.00 m2 258,242.88 51,132,089.25 0.128 - - - - - - -

2 Pek. Kolom Type K2, Uk. 80 x 80 Cm 11.00 Bh


- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 35.20 m3 1,323,787.50 46,597,320.00 0.117 - - - - - - -
- Besi Beton Ulir 5,967.72 Kg 22,312.95 133,157,437.97 0.333 - - - - - - -
TRIBUN BARAT

KONTRAK AWAL S/D MINGGU LALU MINGGU INI S/D MINGGU INI

NO. JENIS PEKERJAAN KET


VOL. SAT. HARGA SAT. JUMLAH HARGA BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) Progress

- Bekisting 2 x Pemakaian 176.00 m2 258,242.88 45,450,746.00 0.114 - - - - - - -

3 Pek. Kolom Type K3, Uk. 60 x 80 Cm 11.00 Bh


- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 26.40 m3 1,323,787.50 34,947,990.00 0.087 - - - - - - -
- Besi Beton Ulir 4,662.96 Kg 22,312.95 104,044,379.94 0.260 - - - - - - -
- Bekisting 2 x Pemakaian 154.00 m2 258,242.88 39,769,402.75 0.099 - - - - - - -

4 Pek. Kolom Type K4, Uk. 40 x 40 Cm 11.00 Bh


- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 5.28 m3 1,323,787.50 6,989,598.00 0.017 - - - - - - -
- Besi Beton Ulir 1,080.70 Kg 22,312.95 24,113,601.49 0.060 - - - - - - -
- Bekisting 2 x Pemakaian 52.80 m2 258,242.88 13,635,223.80 0.034 - - - - - - -

5 Pek. Kolom Type K5, Uk. 30 x 30 Cm (Pintu Masuk Utama) 11.00 Bh


- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 11.61 m3 1,323,787.50 15,369,172.88 0.038 - - - - - - -
- Besi Beton Ulir 3,155.69 Kg 22,312.95 70,412,772.82 0.176 - - - - - - -
- Bekisting 2 x Pemakaian 154.80 m2 258,242.88 39,975,997.05 0.100 - - - - - - -

6 Pek. Kolom Type K4, Uk. 15 x 15 Cm


- Beton mutu f'c=14,5 Mpa (K 175), slump (12 ± 2) cm, w/c=0,66 1.49 m3 1,025,184.81 1,522,399.44 0.004 - - - - - - -
- Besi Beton Polos 882.08 Kg 22,312.95 19,681,769.81 0.049 - - - - - - -
- Bekisting 2 x Pemakaian 48.60 m2 258,242.88 12,550,603.73 0.031 - - - - - - -

II Pekerjaan Kolom Lt. II


1 Pek. Kolom Type K1, Uk. 80 x 100 Cm 11.00 Bh
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 46.38 m3 1,323,787.50 61,391,969.10 0.154 - - - - - - -
- Besi Beton Ulir 8,151.23 Kg 22,312.95 181,877,928.75 0.455 - - - - - - -
- Bekisting 2 x Pemakaian 227.70 m2 258,242.88 58,801,902.64 0.147 - - - - - - -

2 Pek. Kolom Type K2, Uk. 80 x 80 Cm 11.00 Bh


- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 40.48 m3 1,323,787.50 53,586,918.00 0.134 - - - - - - -
- Besi Beton Ulir 6,862.88 Kg 22,312.95 153,131,053.67 0.383 - - - - - - -
- Bekisting 2 x Pemakaian 202.40 m2 258,242.88 52,268,357.90 0.131 - - - - - - -

3 Pek. Kolom Type K3, Uk. 60 x 80 Cm 11.00 Bh


- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 15.84 m3 1,323,787.50 20,968,794.00 0.052 - - - - - - -
- Besi Beton Ulir 2,797.78 Kg 22,312.95 62,426,627.97 0.156 - - - - - - -
- Bekisting 2 x Pemakaian 92.40 m2 258,242.88 23,861,641.65 0.060 - - - - - - -

4 Pek. Kolom Type KP, Uk. 15 x 15 Cm


- Beton mutu f'c=14,5 Mpa (K 175), slump (12 ± 2) cm, w/c=0,66 3.96 m3 1,025,184.81 4,059,731.85 0.010 - - - - - - -
- Besi Beton Polos 9,499.74 Kg 22,312.95 211,967,272.90 0.530 - - - - - - -
- Bekisting 2 x Pemakaian 52.80 m2 258,242.88 13,635,223.80 0.034 - - - - - - -
5 Pek. Kolom Railing, Uk. 15 x 15 Cm, T = 100 Cm
- Beton mutu f'c=14,5 Mpa (K 175), slump (12 ± 2) cm, w/c=0,66 0.50 m3 1,025,184.81 507,466.48 0.001 - - - - - - -
- Besi Beton Polos 114.58 Kg 22,312.95 2,556,622.81 0.006 - - - - - - -
- Bekisting 2 x Pemakaian 6.60 m2 258,242.88 1,704,402.98 0.004 - - - - - - -
TRIBUN BARAT

KONTRAK AWAL S/D MINGGU LALU MINGGU INI S/D MINGGU INI

NO. JENIS PEKERJAAN KET


VOL. SAT. HARGA SAT. JUMLAH HARGA BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) Progress

III Pekerjaan Kolom Lt. III


1 Pek. Kolom K1, Uk. 80 x 100 11.00 Bh
- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 31.15 m3 1,323,787.50 41,238,628.20 0.103 - - - - - - -
- Besi Beton Ulir 5,018.32 Kg 22,312.95 111,973,542.22 0.280 - - - - - - -
- Bekisting 2 x Pemakaian 140.18 m2 258,242.88 36,201,519.19 0.091 - - - - - - -

2 Pek. Kolom Dudukan Kuda-Kuda, Uk. 80 x 100 (Bercabang Dua) 11.00 Bh


- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 24.11 m3 1,323,787.50 31,919,164.20 0.080 - - - - - - -
- Besi Beton Ulir 3,884.24 Kg 22,312.95 86,668,786.92 0.217 - - - - - - -
- Bekisting 2 x Pemakaian 108.50 m2 258,242.88 28,020,384.91 0.070 - - - - - - -

2 Pek. Kolom K2, Uk. 80 x 80 (Area VIP Dan VVIP) 11.00 Bh


- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 19.29 m3 1,323,787.50 25,535,331.36 0.064 - - - - - - -
- Besi Beton Ulir 3,270.31 Kg 22,312.95 72,970,276.01 0.183 - - - - - - -
- Bekisting 2 x Pemakaian 96.45 m2 258,242.88 24,907,008.81 0.062 - - - - - - -

3 Pek. Kolom Type KP, Uk. 15 x 15 Cm


- Beton mutu f'c=14,5 Mpa (K 175), slump (12 ± 2) cm, w/c=0,66 1.18 m3 1,025,184.81 1,205,232.89 0.003 - - - - - - -
- Besi Beton Polos 269.26 Kg 22,312.95 6,008,063.60 0.015 - - - - - - -
- Bekisting 2 x Pemakaian 15.51 m2 258,242.88 4,005,346.99 0.010 - - - - - - -

Jumlah C.4 2,249,151,075.36 5.63 - - -

C.5 Pek. Balok Dan Plat Tribun Lantai II


I Pekerjaan Balok Lt. II
1 Pek. Balok Plat B1, Uk. 40/80
- Beton K.300 102.69 m3 1,025,184.81 105,274,341.75 0.263 - - - - - - -
- Besi Beton Ulir 21,473.26 Kg 22,312.95 479,131,795.10 1.198 - - - - - - -
- Bekisting 2 x Pemakaian 664.45 m2 264,277.75 175,600,090.97 0.439 - - - - - - -

2 Pek. Balok Plat BA, Uk. 30/60


- Beton K.300 138.23 m3 1,025,184.81 141,711,214.21 0.354 - - - - - - -
- Besi Beton Ulir 31,069.33 Kg 22,312.95 693,248,504.16 1.734 - - - - - - -
- Bekisting 2 x Pemakaian 1,209.51 m2 264,277.75 319,647,057.10 0.800 - - - - - - -

3 Pek. Balok Plat B1, Uk. 40/80 (Konsol)


- Beton K.300 5.98 m3 1,025,184.81 6,134,705.90 0.015 - - - - - - -
- Besi Beton Ulir 1,251.32 Kg 22,312.95 27,920,693.70 0.070 - - - - - - -
- Bekisting 2 x Pemakaian 38.72 m2 264,277.75 10,232,834.48 0.026 - - - - - - -

5 Pek. Balok Type B2, Uk. 25 x 50 Cm


- Beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52 9.53 m3 1,025,184.81 9,770,421.31 0.024 - - - - - - -
- Besi Beton Ulir 1,590.51 Kg 22,312.95 35,488,878.26 0.089 - - - - - - -
- Bekisting 2 x Pemakaian 88.62 m2 264,277.75 23,419,237.09 0.059 - - - - - - -

II Pekerjaan Balok Lt. III Dan Plat Dak


a. Area Tribun LT. III
1 Pek. Balok Plat B1, Area Tribun VIP Dan VVIP, Uk. 40/80
- Beton K.300 120.81 m3 1,025,184.81 123,852,166.76 0.310 - - - - - - -
- Besi Beton Ulir 21,473.26 Kg 22,312.95 479,131,795.10 1.198 - - - - - - -
TRIBUN BARAT

KONTRAK AWAL S/D MINGGU LALU MINGGU INI S/D MINGGU INI

NO. JENIS PEKERJAAN KET


VOL. SAT. HARGA SAT. JUMLAH HARGA BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) Progress

- Bekisting 2 x Pemakaian 755.06 m2 264,277.75 199,545,557.92 0.499 - - - - - - -


2 Pek. Balok Plat BA, Area Tribun VIP Dan VVIP, Uk. 30/60
- Beton K.300 80.95 m3 1,025,184.81 82,990,145.59 0.208 - - - - - - -
- Besi Beton Ulir 18,195.09 Kg 22,312.95 405,986,178.39 1.015 - - - - - - -
- Bekisting 2 x Pemakaian 687.81 m2 264,277.75 181,772,086.39 0.455 - - - - - - -
3 Pek. Balok Plat B1, Area Tribun VIP Dan VVIP, Uk. 40/80 (Konsol)
- Beton K.300 8.80 m3 1,025,184.81 9,021,626.32 0.023 - - - - - - -
- Besi Beton Ulir 1,686.22 Kg 22,312.95 37,624,541.99 0.094 - - - - - - -
- Bekisting 2 x Pemakaian 55.00 m2 264,277.75 14,535,276.25 0.036 - - - - - - -
5 Pek. Balok Plat Dak B1, Area Tribun VIP Dan VVIP, Uk. 40/80
- Beton K.300 2.58 m3 1,025,184.81 2,647,129.70 0.007 - - - - - - -
- Besi Beton Ulir 525.29 Kg 22,312.95 11,720,662.63 0.029 - - - - - - -
- Bekisting 2 x Pemakaian 24.56 m2 264,277.75 6,491,718.65 0.016 - - - - - - -

b. Area Tribun Bagian Atas


1 Pek. Balok Plat B1, Uk. 40/80 (Bagian Atas)
- Beton K.300 85.82 m3 1,025,184.81 87,985,461.09 0.220 - - - - - - -
- Besi Beton Ulir 16,177.60 Kg 22,312.95 360,969,890.67 0.903 - - - - - - -
- Bekisting 2 x Pemakaian 472.03 m2 264,277.75 124,747,554.89 0.312 - - - - - - -
2 Pek. Balok Plat BA, Uk. 30/60
- Beton K.300 32.23 m3 1,025,184.81 33,038,835.89 0.083 - - - - - - -
- Besi Beton Ulir 7,237.70 Kg 22,312.95 161,494,409.65 0.404 - - - - - - -
- Bekisting 2 x Pemakaian 187.99 m2 264,277.75 49,682,102.78 0.124 - - - - - - -

c. Pek. Ringbalk Penghubung Kolom Kuda-Kuda


1 Pek. Ringbalk RB, Uk. 60 x 80
- Beton K.300 42.40 m3 1,025,184.81 43,466,195.63 0.109 - - - - - - -
- Besi Beton Ulir 6,141.49 Kg 22,312.95 137,034,649.67 0.343 - - - - - - -
- Bekisting 2 x Pemakaian 194.33 m2 264,277.75 51,356,038.05 0.128 - - - - - - -

Jumlah C.5 4,632,673,798.04 11.59 - - -

C.6 Pekerjaan Plat, Tribun Dan Tangga


1 Pek. Plat lantai Lantai II
- Pek. Plat Lt. II, Tbl = 12 cm
- Beton K.300 178.55 m3 1,025,184.81 183,043,467.15 0.458 - - - - - - -
- Besi Beton Ulir 22,014.82 Kg 19,194.45 422,562,370.19 1.057 - - - - - - -
- Bekisting 2 x Pemakaian 1,487.89 m2 227,775.00 338,904,144.75 0.848 - - - - - - -

2 Pek. Plat lantai III (Area VVIP Dan VIP)


- Pek. Plat Lt. III, Tbl = 12 cm, Area Tribun VIP Dan VVIP (Sisi Barat)
- Beton K.300 188.85 m3 1,025,184.81 193,611,072.17 0.484 - - - - - - -
- Besi Beton Ulir 23,285.80 Kg 19,194.45 446,958,063.16 1.118 - - - - - - -
- Bekisting 2 x Pemakaian 1,573.79 m2 227,775.00 358,470,017.25 0.897 - - - - - - -

3 Pek. Plat Dak Lantai III (Area VVIP Dan VIP)


- Pek. Plat Dak Lt. III, Tbl = 12 cm (Sisi Barat)
- Beton K.300 174.81 m3 1,025,184.81 179,215,632.11 0.448 - - - - - - -
- Besi Beton Ulir 21,554.44 Kg 19,194.45 413,725,676.52 1.035 - - - - - - -
- Bekisting 2 x Pemakaian 1,456.78 m2 227,775.00 331,816,925.63 0.830 - - - - - - -
TRIBUN BARAT

KONTRAK AWAL S/D MINGGU LALU MINGGU INI S/D MINGGU INI

NO. JENIS PEKERJAAN KET


VOL. SAT. HARGA SAT. JUMLAH HARGA BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) Progress

4 Pek. Plat Tribun


- Pek. Plat Tribun Lt. III, Tbl = 12 cm, Area Tribun VIP Dan VVIP (Sisi Barat)
- Beton K.300 151.46 m3 1,025,184.81 155,272,194.84 0.388 - - - - - - -
- Besi Beton Ulir 18,674.74 Kg 19,194.45 358,451,397.90 0.897 - - - - - - -
- Bekisting 2 x Pemakaian 1,262.15 m2 227,775.00 287,485,760.70 0.719 - - - - - - -

5 Pek. Plat Dinding Depan Tribun Lt. II, Tbl = 15 cm (Dekat Lapangan)
- Beton K.300 11.09 m3 1,025,184.81 11,367,249.17 0.028 - - - - - - -
- Besi Beton Ulir 1,458.29 Kg 19,194.45 27,991,146.66 0.070 - - - - - - -
- Bekisting 2 x Pemakaian 147.84 m2 227,775.00 33,674,256.00 0.084 - - - - - - -
6 Pek. Plat Dinding Depan Tribun Lt. III, Tbl = 15 cm
- Beton K.300 11.09 m3 1,025,184.81 11,367,249.17 0.028 - - - - - - -
- Besi Beton Ulir 1,458.29 Kg 19,194.45 27,991,146.66 0.070 - - - - - - -
- Bekisting 2 x Pemakaian 147.84 m2 227,775.00 33,674,256.00 0.084 - - - - - - -
7 Pek. Tangga Beton
I Pek. Tangga Beton Lantai I - II
a. Pek. Tangga Beton I (Area Tribun) 8.00 Bh
- Pek. Sloef/Tie Beam Tangga, Uk. 30/60
- Pasir Urug Alas Tie Beam, T = 5 cm 0.24 m3 253,770.00 60,904.80 0.000 - - - - - - -
- Lantai Kerja Tie Beam, Beton K. 100, T = 5 Cm 0.24 m3 1,044,336.65 250,640.80 0.001 - - - - - - -
- Beton K.300 2.88 m3 1,205,977.50 3,473,215.20 0.009 - - - - - - -
- Besi Beton Ulir 517.86 Kg 22,312.95 11,554,984.29 0.029 - - - - - - -
- Bekisting 2 x Pemakaian 24.00 m2 159,241.50 3,821,796.00 0.010 - - - - - - -

- Pek. Tangga Beton


- Beton K.300 21.14 m3 1,205,977.50 25,499,188.26 0.064 - - - - - - -
- Besi Beton Ulir 5,862.59 Kg 22,312.95 130,811,705.24 0.327 - - - - - - -
- Bekisting 2 x Pemakaian 186.96 m2 241,737.38 45,195,219.63 0.113 - - - - - - -

b. Pek. Tangga Beton II (Area Plat Lt. II/Plat datar) 8.00 Bh


- Pek. Sloef/Tie Beam Tangga, Uk. 30/60
- Pasir Urug Alas Tie Beam, T = 5 cm 0.24 m3 253,770.00 60,904.80 0.000 - - - - - - -
- Lantai Kerja Tie Beam, Beton K. 100, T = 5 Cm 0.24 m3 1,044,336.65 250,640.80 0.001 - - - - - - -
- Beton K.300 2.88 m3 1,205,977.50 3,473,215.20 0.009 - - - - - - -
- Besi Beton Ulir 517.86 Kg 22,312.95 11,554,984.29 0.029 - - - - - - -
- Bekisting 2 x Pemakaian 24.00 m2 159,241.50 3,821,796.00 0.010 - - - - - - -

- Pek. Kolom Tangga Beton, Uk. 30 x 30


- Beton K.300 2.16 m3 1,205,977.50 2,604,911.40 0.007 - - - - - - -
- Besi Beton Ulir 587.11 Kg 22,312.95 13,100,050.76 0.033 - - - - - - -
- Bekisting 2 x Pemakaian 28.80 m2 258,242.88 7,437,394.80 0.019 - - - - - - -

- Pek. Balok Tangga Beton, Uk. 25 x 40


- Beton K.300 1.60 m3 1,205,977.50 1,929,564.00 0.005 - - - - - - -
- Besi Beton Ulir 266.92 Kg 22,312.95 5,955,769.04 0.015 - - - - - - -
- Bekisting 2 x Pemakaian 16.80 m2 264,277.75 4,439,866.20 0.011 - - - - - - -

- Pek. Tangga Beton


TRIBUN BARAT

KONTRAK AWAL S/D MINGGU LALU MINGGU INI S/D MINGGU INI

NO. JENIS PEKERJAAN KET


VOL. SAT. HARGA SAT. JUMLAH HARGA BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) Progress

- Beton K.300 34.63 m3 1,205,977.50 41,765,412.78 0.104 - - - - - - -


- Besi Beton Ulir 9,602.41 Kg 22,312.95 214,257,991.68 0.536 - - - - - - -
- Bekisting 2 x Pemakaian 308.88 m2 241,737.38 74,667,840.39 0.187 - - - - - - -

II Pek. Tangga Beton Lantai II - III


a. Pek. Tangga Beton III (Area Tribun Biasa) 8.00 Bh
- Pek. Kolom Tangga Beton, Uk. 30 x 30
- Beton K.300 3.17 m3 1,205,977.50 3,820,536.72 0.010 - - - - - - -
- Besi Beton Ulir 861.09 Kg 22,312.95 19,213,407.78 0.048 - - - - - - -
- Bekisting 2 x Pemakaian 42.24 m2 258,242.88 10,908,179.04 0.027 - - - - - - -

- Pek. Balok Tangga Beton, Uk. 25 x 40


- Beton K.300 3.20 m3 1,205,977.50 3,859,128.00 0.010 - - - - - - -
- Besi Beton Ulir 533.84 Kg 22,312.95 11,911,538.09 0.030 - - - - - - -
- Bekisting 2 x Pemakaian 33.60 m2 264,277.75 8,879,732.40 0.022 - - - - - - -

- Pek. Tangga Beton


- Beton K.300 31.13 m3 1,205,977.50 37,539,667.62 0.094 - - - - - - -
- Besi Beton Ulir 8,630.85 Kg 22,312.95 192,579,774.92 0.482 - - - - - - -
- Bekisting 2 x Pemakaian 285.52 m2 241,737.38 69,020,855.31 0.173 - - - - - - -

Jumlah C.6 4,779,302,842.23 11.95 - - -

Jumlah IV C (C1+C2+C3+C4+C5+C6) 13,542,709,915.75 33.87 - - -

Jumlah IV (IVA+IVB+IVC) 31,178,850,999.67 77.98 - 1.08 1.08


JUMLAH PEKERJAAN STRUKTUR Jumlah I + II + III + IV 31,884,082,922.16 79.75 - 1.13 1.13

GEDUNG TRIBUN BARAT, SUB PEKERJAAN MEKANIKAL DAN ELEKTRIKAL


PEKERJAAN STANDAR
I PEKERJAAN MEKANIKAL DAN PLUMBING

I.1 PEKERJAAN AIR BERSIH

A. INSTALASI SHAFT
1 Pemipaan Polypropelyne PN.10 :
a. Diameter 65 mm 30.00 m¹ 215,000.00 6,450,000.00 0.016 - - - - - - -
b Peralatan Bantu ( Fitting-Fitting ) 1.00 Ls 157,000.00 157,000.00 0.000 - - - - - - -
c Diameter 40 mm 30.00 m 144,500.00 4,335,000.00 0.011 - - - - - - -
Gate Valve
a. Diameter 40 mm 1.00 Bh 466,000.00 466,000.00 0.001 - - - - - - -
b Diameter 65 mm 1.00 Bh 735,000.00 735,000.00 0.002 - - - - - - -

B. LANTAI DASAR
1 Gate Valve :
a. Diameter 40 mm 5.00 Bh 466,500.00 2,332,500.00 0.006 - - - - - - -
b. Diameter 32 mm Bh -
TRIBUN BARAT

KONTRAK AWAL S/D MINGGU LALU MINGGU INI S/D MINGGU INI

NO. JENIS PEKERJAAN KET


VOL. SAT. HARGA SAT. JUMLAH HARGA BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) Progress

2 Pemipaan Polypropelyne PN.10 :


a. Diameter 40 mm 80.00 m¹ 144,000.00 11,520,000.00 0.029 - - - - - - -
b. Diameter 32 mm 100.00 m¹ 97,500.00 9,750,000.00 0.024 - - - - - - -
c. Diameter 25 mm 150.00 m¹ 71,500.00 10,725,000.00 0.027 - - - - - - -
d. Diameter 20 mm 720.00 m¹ 56,500.00 40,680,000.00 0.102 - - - - - - -
3 Peralatan Bantu ( Fitting-Fitting ) 1.00 Ls 723,500.00 723,500.00 0.002 - - - - - - -

C. LANTAI SATU
1 Gate Valve :
a. Diameter 40 mm 5.00 Bh 466,500.00 2,332,500.00 0.006 - - - - - - -

2 Pemipaan Polypropelyne PN.10 :


a. Diameter 50 mm 20.00 m¹ 166,500.00 3,330,000.00 0.008 - - - - - - -
b. Diameter 40 mm 80.00 m¹ 145,500.00 11,640,000.00 0.029 - - - - - - -
c. Diameter 32 mm 100.00 m¹ 97,000.00 9,700,000.00 0.024 - - - - - - -
d. Diameter 25 mm 150.00 m¹ 71,500.00 10,725,000.00 0.027 - - - - - - -
e. Diameter 20 mm 730.00 m¹ 56,500.00 41,245,000.00 0.103 - - - - - - -
3 Peralatan Bantu ( Fitting-Fitting ) 1.00 Ls 692,500.00 692,500.00 0.002 - - - - - - -

D. LANTAI DUA
1 Gate Valve :
a. Diameter 40 mm Bh -
2 Pemipaan Polypropelyne PN.10 :
a. Diameter 50 mm m¹ -
b. Diameter 40 mm m¹ -
c. Diameter 32 mm m¹ -
d. Diameter 25 mm m¹ -
e. Diameter 20 mm m¹ -
3 Peralatan Bantu ( Fitting-Fitting ) Ls -

E. Tanki Air Domestik / roof tank


a. Roof Tank/ Water Tank, kapasitas : 4 M3 Fiber Glass Panel Unit DITUNDA
b. Floating valve diameter 50 mm Buah DITUNDA
c. Water level cintrol ( WLC ) Unit DITUNDA
d. Gate Valve, 10 K :
- Diameter 100 mm Buah DITUNDA
- Diameter 80 mm Buah DITUNDA
- Diameter 65 mm Buah DITUNDA
e. Cek Valve 65 mm Buah

TOTAL PEKERJAAN AIR BERSIH 167,539,000.00 0.42 - - -

I.2 PEKERJAAN AIR PANAS

1 Mesin Pemanas Air ( wika Heat Electrik Kapasitas 30 Liter ) 


Type : …. Unit -
Ascesoriec dan alat bantu ls -
Stop kontak Kabel Power pemanas Air ls -

A. INSTALASI SHAFT
TRIBUN BARAT

KONTRAK AWAL S/D MINGGU LALU MINGGU INI S/D MINGGU INI

NO. JENIS PEKERJAAN KET


VOL. SAT. HARGA SAT. JUMLAH HARGA BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) Progress

1 Pemipaan Polypropelyne PN.20 :


a. Diameter 50 mm 24.00 m¹ 255,000.00 6,120,000.00 0.015 - - - - - - -
Diameter 40 mm 24.00 m¹ 197,500.00 4,740,000.00 0.012 - - - - - - -
2 Peralatan Bantu ( Fitting-Fitting ) 1.00 Ls 457,500.00 457,500.00 0.001 - - - - - - -

B. LANTAI DARAS TOILET PEMAIN


1 Gate Valve :
a. Diameter 32 mm 5.00 Bh 351,500.00 1,757,500.00 0.004 - - - - - - -
b. Diameter 40 mm 5.00 Bh 466,500.00 2,332,500.00 0.006 - - - - - - -
2 Pemipaan Polypropelyne PN.20 :
a. Diameter 40 mm 60.00 m¹ 198,000.00 11,880,000.00 0.030 - - - - - - -
b. Diameter 32 mm 100.00 m¹ 148,000.00 14,800,000.00 0.037 - - - - - - -
c. Diameter 25 mm 90.00 m¹ 103,000.00 9,270,000.00 0.023 - - - - - - -
d. Diameter 20 mm 100.00 m¹ 84,000.00 8,400,000.00 0.021 - - - - - - -
3 Peralatan Bantu ( Fitting-Fitting ) 1.00 Ls 457,500.00 457,500.00 0.001 - - - - - - -

C. LANTAI SATU UNTUK TOILET VIP


1 Gate Valve :
a. Diameter 32 mm 2.00 Bh 351,500.00 703,000.00 0.002 - - - - - - -
b. Diameter 40 mm 2.00 Bh 466,500.00 933,000.00 0.002 - - - - - - -
2 Pemipaan Polypropelyne PN.20 :
a. Diameter 40 mm 24.00 m¹ 198,000.00 4,752,000.00 0.012 - - - - - - -
b. Diameter 32 mm 40.00 m¹ 148,000.00 5,920,000.00 0.015 - - - - - - -
c. Diameter 25 mm 36.00 m¹ 103,000.00 3,708,000.00 0.009 - - - - - - -
d. Diameter 20 mm 40.00 m¹ 84,000.00 3,360,000.00 0.008 - - - - - - -
3 Peralatan Bantu ( Fitting-Fitting ) 1.00 Ls 457,500.00 457,500.00 0.001 - - - - - - -

D. LANTAI DUA
1 Gate Valve :
a. Diameter 32 mm 2.00 Bh 352,000.00 704,000.00 0.002 - - - - - - -
b. Diameter 40 mm 2.00 Bh 467,000.00 934,000.00 0.002 - - - - - - -

2 Pemipaan Polypropelyne PN.20 :


a. Diameter 40 mm 24.00 m¹ 198,000.00 4,752,000.00 0.012 - - - - - - -
b. Diameter 32 mm 40.00 m¹ 148,000.00 5,920,000.00 0.015 - - - - - - -
c. Diameter 25 mm 36.00 m¹ 103,000.00 3,708,000.00 0.009 - - - - - - -
d. Diameter 20 mm 40.00 m¹ 84,000.00 3,360,000.00 0.008 - - - - - - -
3 Peralatan Bantu ( Fitting-Fitting ) 1.00 Ls 457,500.00 457,500.00 0.001 - - - - - - -

TOTAL PEKERJAAN AIR PANAS 99,884,000.00 0.25 - - -

I.3. PEKERJAAN AIR KOTOR BERAT DAN CAIR

A. INSTALASI SHAFT
1 Pemipaan Air kotor padat PVC Kelas 10 kg/cm2 :
Diameter 100 mm 30.00 m¹ 136,500.00 4,095,000.00 0.010 - - - - - - -

2 Pemipaan Air kotor Cair PVC Kelas 10 kg/cm2 :


Diameter 100 mm 30.00 m¹ 136,500.00 4,095,000.00 0.010 - - - - - - -
3 Pemipaan Vent PVC Kelas 10 kg/cm2 :
TRIBUN BARAT

KONTRAK AWAL S/D MINGGU LALU MINGGU INI S/D MINGGU INI

NO. JENIS PEKERJAAN KET


VOL. SAT. HARGA SAT. JUMLAH HARGA BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) Progress

Diameter 50 mm 30.00 m¹ 49,000.00 1,470,000.00 0.004 - - - - - - -


4 Peralatan Bantu ( Fitting-Fitting ) 1.00 Ls 1,125,000.00 1,125,000.00 0.003 - - - - - - -
B. LANTAI DASAR
1 Pemipaan Air kotor padat PVC Kelas 10 kg/cm2 :
a. Diameter 150 mm m¹ -
b. Diameter 100 mm 300.00 m¹ 137,000.00 41,100,000.00 0.103 - - - - - - -
c. CO diameter 150 mm Bh -
d. CO diameter 100 mm 12.00 Bh 415,000.00 4,980,000.00 0.012 - - - - - - -
2 Pemipaan Air kotor cair PVC Kelas 10 kg/cm2 :
a. Diameter 100mm 220.00 m¹ 137,000.00 30,140,000.00 0.075 - - - - - - -
b. Diameter 80 mm 150.00 m¹ 86,000.00 12,900,000.00 0.032 - - - - - - -
c. Diameter 50 mm 46.00 m¹ 49,000.00 2,254,000.00 0.006 - - - - - - -
d. Diameter 32mm 320.00 m¹ 32,000.00 10,240,000.00 0.026 - - - - - - -
e CO diameter 80 mm 4.00 Bh 277,500.00 1,110,000.00 0.003 - - - - - - -
3 Pemipaan Air kotor vent PVC Kelas 10 kg/cm2 :
a. Diameter 40 mm 50.00 m¹ 38,000.00 1,900,000.00 0.005 - - - - - - -
b. Diameter 32 mm 42.00 m¹ 32,000.00 1,344,000.00 0.003 - - - - - - -
4 Peralatan Bantu ( Fitting-Fitting ) 1.00 Ls 1,088,000.00 1,088,000.00 0.003 - - - - - - -
5 STP/Biotek sistem, kap. 6 m3 6.00 set 47,500,000.00 285,000,000.00 0.713 - - - - - - -

C. LANTAI SATU
1 Pemipaan Air kotor padat PVC Kelas 10 kg/cm2 :
a. Diameter 100 mm 120.00 m¹ 137,000.00 16,440,000.00 0.041 - - - - - - -
b. CO diameter 100 mm 2.00 Bh 415,000.00 830,000.00 0.002 - - - - - - -
2 Pemipaan Air kotor cair PVC Kelas 10 kg/cm2 :
a. Diameter 80 mm 140.00 m¹ 85,000.00 11,900,000.00 0.030 - - - - - - -
b. Diameter 50 mm 100.00 m¹ 48,500.00 4,850,000.00 0.012 - - - - - - -
c. Diameter 32 mm 24.00 m¹ 32,000.00 768,000.00 0.002 - - - - - - -
d. CO diameter 80 mm 2.00 Bh 280,000.00 560,000.00 0.001 - - - - - - -
3 Pemipaan Air kotor vent PVC Kelas 10 kg/cm2 :
a. Diameter 40 mm 40.00 m¹ 38,000.00 1,520,000.00 0.004 - - - - - - -
b. Diameter 32 mm 40.00 m¹ 32,000.00 1,280,000.00 0.003 - - - - - - -
4 Peralatan Bantu ( Fitting-Fitting ) 1.00 Ls 328,500.00 328,500.00 0.001 - - - - - - -

D. LANTAI DUA
1 Pemipaan Air kotor padat PVC Kelas 10 kg/cm2 :
a. Diameter 100 mm m¹
b. CO diameter 100 mm Bh
2 Pemipaan Air kotor cair PVC Kelas 10 kg/cm2 :
a. Diameter 80 mm m¹
b. Diameter 50 mm m¹
c. Diameter 65 mm m¹
d. Diameter 32mm m¹
e CO diameter 80 mm Bh
3 Pemipaan Air kotor vent PVC Kelas 10 kg/cm2 :
a. Diameter 40 mm m¹
b. Diameter 32 mm m¹
4 Peralatan Bantu ( Fitting-Fitting ) Ls
TRIBUN BARAT

KONTRAK AWAL S/D MINGGU LALU MINGGU INI S/D MINGGU INI

NO. JENIS PEKERJAAN KET


VOL. SAT. HARGA SAT. JUMLAH HARGA BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) Progress

TOTAL PEKERJAAN AIR KOTOR DAN CAIR 441,317,500.00 1.10 - - -

I.4. PEKERJAAN AIR HUJAN / DRAIN LAPANGAN


1 Pekerjaan gutter saluran dalam Air hujan / drain menerus mengikuti existing uk. 128.00 m' 645,000.00 82,560,000.00 0.206 - - - - - - -
2 100x80cm
Pemipaan Air hujan / drain PVC Kelas AW dia. 30cm2 : 168.00 Bh 1,835,000.00 308,280,000.00 0.771 - - - - - - -
3 Peralatan Bantu ( Fitting-Fitting SOK ) 42.00 Bh 415,000.00 17,430,000.00 0.044 - - - - - - -
4 Pemipaan Air hujan / drain PVC Kelas AW dia. 100mm2, di area overstek Tribun lt.1 100.00 m' 137,000.00 13,700,000.00 0.034 - - - - - - -
5 Pengadaan dan pemasangan roof drain , besi tempa dia. 100mm2 - home idustry. Di 25.00 bh 324,500.00 8,112,500.00 0.020 - - - - - - -
6 area overstek
Pekerjaan bakTribun
kontrolBarat Lt.1 uk.50x50x60cm. Termasuk tutup bak kontrol (beton
Air hujan, 25.00 ttk 324,500.00 8,112,500.00 0.020 - - - - - - -
7 bertulang)
Pekerjaan pemipaan air hujan dari bak kontrol Air hujan, ke saluran luar diia. 150 mm) 200.00 m' 324,500.00 64,900,000.00 0.162 - - - - - - -
8 Pekerjaan gutter saluran Air hujan / drain luar, area depan selasar, menerus. Sudah
a termasuk pekerjaan
Box Culvert (K 350),galian, urugan pemadatan dan perapihan
uk. 120x120x100cm 201.00 m' 5,000,000.00 1,005,000,000.00 2.514 - - - - - - -
b U Ditch (K 350), uk. 120x120x120cm + cover penutup U Ditch (K 350) 25.00 bh 5,000,000.00 125,000,000.00 0.313 - - - - - - -
9 Pekerjaan finishing tutup saluran air hujan / saluran luar (beton bertulang) bh

TOTAL PEKERJAAN AIR HUJAN 1,633,095,000.00 4.08 - - -

II PEKERJAAN ELEKTRIKAL

II.1. PEKERJAAN PANEL


A. LANTAI.1
1 Panel Listrik
- PP.1 DAN PP.2 2.00 Unit 9,500,000.00 19,000,000.00 0.048 - - - - - - -
Pekerjaan Sparing bawah tanah.

B. LANTAI 2
1 Panel Listrik
- PP.1B DAN PP.2B 2.00 Unit 9,500,000.00 19,000,000.00 0.048 - - - - - - -

TOTAL PEKERJAAN PANEL DAN KABEL FEEDER 38,000,000.00 0.10 - - -

II.2. PEKERJAAN TITIK INSTALASI DAYA DAN PENERANGAN


A. LANTAI.DASAR
1 Saklar dan Stop kontak
a. Saklar tunggal Bh
b. Saklar ganda Bh
c. Saklar hotel Bh
d. Saklar group ( 6 modul ) Bh DI PENDING (HANYA
e. Stop Kontak 200 W / 16 A Bh INSTALASI SAJA
f. Stop Kontak 350 W / 16 A Bh
g. Stop Kontak 500 W / 16 A Bh
h. Stop Kontak / 16 A / 3 Phase Bh
2 Titik instalasi
a. Instalasi saklar, NYM 3 x 2,5 mm2 dalam conduit PVC 26.00 Titik 355,000.00 9,230,000.00 0.023 - - - - - - -
b. Instalasi stop kontak, NYM 3 x 2,5 mm2 dalam conduit PVC 40.00 Titik 367,500.00 14,700,000.00 0.037 - - - - - - -
TRIBUN BARAT

KONTRAK AWAL S/D MINGGU LALU MINGGU INI S/D MINGGU INI

NO. JENIS PEKERJAAN KET


VOL. SAT. HARGA SAT. JUMLAH HARGA BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) Progress

c. Instalasi stop kontak 3 Phase , NYM 4 x 2,5 mm2 dalam conduit PVC Titik -

B. LANTAI.1
1 Saklar & Stop kontak
a. Saklar tunggal Bh
b. Saklar ganda Bh
c. Saklar hotel Bh
d. Saklar group ( 6 modul ) Bh DI PENDING (HANYA
e. Saklar Handle Bh INSTALASI SAJA
e. Stop Kontak 200 W / 16 A Bh
f. Stop Kontak 500 W / 16 A Bh
g. Stop Kontak / 16 A / 3 Phase Bh
2 Titik instalasi
a. Instalasi saklar, NYM 3 x 2,5 mm2 dalam conduit PVC 50.00 Titik 355,000.00 17,750,000.00 0.044 - - - - - - -
b. Instalasi stop kontak, NYM 3 x 2,5 mm2 dalam conduit PVC 31.00 Titik 367,500.00 11,392,500.00 0.028 - - - - - - -
c. Instalasi stop kontak 3 Phase , NYM 4 x 2,5 mm2 dalam conduit PVC Titik -

C. LANTAI.2 VIP
1 Saklar & Stop kontak
a. Saklar tunggal Bh
b. Saklar ganda Bh
c. Saklar hotel Bh
DI PENDING (HANYA
d. Stop Kontak 200 W / 16 A Bh
INSTALASI SAJA
e. Stop Kontak 200 W / 16 A / UPS Bh
f. Stop Kontak 500 W / 16 A Bh
g. Stop Kontak / 16 A / 3 Phase Bh
2 Titik instalasi
a. Instalasi saklar, NYM 3 x 2,5 mm2 dalam conduit PVC Titik -
b. Instalasi stop kontak, NYM 3 x 2,5 mm2 dalam conduit PVC Titik -
c. Instalasi stop kontak 3 Phase , NYM 4 x 2,5 mm2 dalam conduit PVC Titik -

TOTAL PEKERJAAN INSTALASI DAYA DAN PENERANGAN 53,072,500.00 0.13 - - -

PEKERJAAN NON STANDAR


PEKERJAAN ELEKTRIKAL ARUS KUAT
II.3. PEKERJAAN RAK KABEL DAN FIXTURE ARMATUR PENERANGAN
A. LANTAI.DASAR
1 Rak Kabel
- Ukuran 40 cm, termasuk sambungan & penunjangya u/ arus kuat 180.00 m¹ 215,000.00 38,700,000.00 0.097 - - - - - - -
- Ukuran 20 cm, termasuk sambungan & penunjangya u/ arus lemah 180.00 m¹ 141,000.00 25,380,000.00 0.063 - - - - - - -
2 Fixtures lampu lengkap dengan armature
- Lampu TL 2 x 36 W / Louvre M6 Bh
- Lampu TL 2 x 36 W / Louvre M6 + battere Bh
- Lampu TL 1 x 36 W / Louvre M6 Bh

DI PENDING (HANYA
INSTALASI SAJA
TRIBUN BARAT

KONTRAK AWAL S/D MINGGU LALU MINGGU INI S/D MINGGU INI

NO. JENIS PEKERJAAN KET


VOL. SAT. HARGA SAT. JUMLAH HARGA BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) Progress

- Lampu TL 1 x 36 W / Louvre M6 + Battere Bh


- Lampu Down Light SL LED 2 x 13 W Bh
DI PENDING (HANYA
- Lampu Down Light SL LED 2 x 13 W + Batter Bh
INSTALASI SAJA
- Lampu Down Light SL LED 8 W / Cover glass Bh
- Lampu Down Light SL LED 8 W / Cover glass + Batter Bh
- Lampu Dinding PLC 18 W Bh
- Lampu Exit Bh
- Lampu TL 1 x 36 W / TKO / BALK Bh
3 Instalasi penerangan, NYM 3 x 2,5 mm2 dalam conduit PVC 285.00 Titik 355,000.00 101,175,000.00 0.253 - - - - - - -

B. LANTAI.1
1 Rak Kabel
- Ukuran 40 cm, termasuk sambungan & penunjangya 145.00 m¹ 215,000.00 31,175,000.00 0.078 - - - - - - -
- Ukuran 20 cm, termasuk sambungan & penunjangya 137.00 m¹ 141,000.00 19,317,000.00 0.048 - - - - - - -

2 Fixtures lampu lengkap dengan armature


- Lampu TL 2 x 36 W / Louvre M6 Bh
- Lampu TL 2 x 36 W / Louvre M6 + battere Bh
- Lampu TL 1 x 36 W / Louvre M6 Bh
- Lampu TL 1 x 36 W / Louvre M6 + Battere Bh
- Lampu Down Light SL LED 2 x 13 W Bh
- Lampu Down Light SL LED 2 x 13 W + Batter Bh
- Lampu Down Light SL LED 8 W / Cover glass Bh DI PENDING (HANYA
- Lampu Down Light SL LED 8 W / Cover glass + Batter Bh INSTALASI SAJA
- Lampu Dinding PLC 18 W Bh
- Lampu Down Light PLC 11 W / Cover glass Bh
- Lampu TL 1 x 36 W / TKO / BALK Bh
- Lampu Exit Bh
- Lampu Metal Halide 1x125w Bh
- Lampu Metal Halide 1x125w +batery Bh
3 Instalasi penerangan, NYM 3 x 2,5 mm2 dalam conduit PVC 220.00 Titik 355,000.00 78,100,000.00 0.195 - - - - - - -

C. LANTAI.2 VIP
1 Rak Kabel
- Ukuran 40 cm, termasuk sambungan & penunjangya m¹ -
- Ukuran 20 cm, termasuk sambungan & penunjangya m¹ -
2 Fixtures lampu lengkap dengan armature
- Lampu TL 2 x 36 W / Louvre M6 Bh
- Lampu TL 2 x 36 W / Louvre M6 + battere Bh
- Lampu TL 1 x 36 W / Louvre M6 Bh
- Lampu TL 1 x 36 W / Louvre M6 + Battere Bh
DI PENDING (HANYA
- Lampu Down Light SL LED 2 x 13 W Bh
INSTALASI SAJA
- Lampu Down Light SL LED 2 x 13 W + Batter Bh
- Lampu Down Light PLC 11 W / Cover glass Bh
- Lampu TL 1 x 36 W / TKO / BALK Bh
- Lampu Exit Bh

TOTAL PEKERJAAN ELEKTRIKAL ARUS KUAT 293,847,000.00 0.73 - - -


TOTAL PEKERJAAN MEP 2,726,755,000.00 6.82 - - -
TRIBUN BARAT

KONTRAK AWAL S/D MINGGU LALU MINGGU INI S/D MINGGU INI

NO. JENIS PEKERJAAN KET


VOL. SAT. HARGA SAT. JUMLAH HARGA BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) Progress

1 PEK. DINDING, PINTU, JENDELA & VENTILASI


1.1. LANTAI DASAR
1 Dinding bata ringan
1 Dinding bata ringan aduk mortar 420.00 m² 80,000.00 33,600,000.00 0.084 - - - - - - -
2 Plesteran dinding bata tebal 2,5 cm aduk mortar 840.00 m² 70,000.00 58,800,000.00 0.147 - - - - - - -

2 Pintu
1 Pintu utama pipa stainless dia 3 inc & plat stainless t 4 mm 2.00 unit 60,500,000.00 121,000,000.00 0.303 - - - - - - -
2 Pintu emergency pipa giv dia 3 inc & plat 4.00 unit 20,000,000.00 80,000,000.00 0.200 - - - - - - -
2 Pintu ruangan alumunium dilapis kaca film 12.00 unit 1,350,000.00 16,200,000.00 0.041 - - - - - - -
3 Pintu toilet kusen & daun jendela alumunium 36.00 unit 450,000.00 16,200,000.00 0.041 - - - - - - -
3 Partisi alumunium isi kalsiboard & kaca tebal 5 mm
1 Ruang Tamu VVIP 512.00 m² 600,000.00 307,200,000.00 0.768 - - - - - - -
2 m² -
3 m² -
4 Ventilasi 1 Glass box 8.00 m² 600,000.00 4,800,000.00 0.012 - - - - - - -
2 Roster keramik 8.00 m² 450,000.00 3,600,000.00 0.009 - - - - - - -
1.2. LANTAI 1
1 Dinding bata ringan
1 Dinding bata ringan aduk mortar 480.00 m² 80,000.00 38,400,000.00 0.096 - - - - - - -
2 Plesteran tebal 2,5 cm aduk mortar 960.00 m² 70,000.00 67,200,000.00 0.168 - - - - - - -
2 Pintu alumunium 1 Pintu ruangan unit -
2 Pintu toilet unit -
3 Partisi alumunium isi kalsiboard & kaca tebal 5 mm m2 -
1 Ruang Tamu VVIP m² -
2 m² -
4 Ventilasi 1 Glass box -
2 Roster keramik m2
Jumlah 747,000,000.00 1.87 - - -
2 PEK. PLAFOND & LAMPU
2.1. LANTAI DASAR
1 PEK. PLAFOND 1 Rangka Plafond Metal Furing 480.00 m² 140,000.00 67,200,000.00 0.168 - - - - - - -
2 Plafond GRC 4 mm m² 90,000.00 -
3 Plafond GRC 4 mm (toilet) m² 90,000.00 -
4 List plafond gypsum profil m¹ 90,000.00 -
2 PEK. LAMPU 1 Lampu tanam drop celing hall 8.00 unit 350,000.00 2,800,000.00 0.007 - - - - - - -
2 Lampu ruangan 32.00 unit 250,000.00 8,000,000.00 0.020 - - - - - - -
3 Lampu toilet 48.00 unit 180,000.00 8,640,000.00 0.022 - - - - - - -
4 Lampu selasar 42.00 unit 220,000.00 9,240,000.00 0.023 - - - - - - -

2.2. LANTAI 1
1 PEK. PLAFOND 1 Rangka Plafond Metal Furing 480.00 m² 140,000.00 67,200,000.00 0.168 - - - - - - -
2 Plafond GRC 4 mm m² 90,000.00 -
3 Plafond GRC 4 mm (toilet) m² 90,000.00 -
4 List plafond gypsum profil 120.00 m¹ 90,000.00 10,800,000.00 0.027 - - - - - - -
2 PEK. LAMPU 1 Lampu gantung di Hall 1.00 unit 6,000,000.00 6,000,000.00 0.015 - - - - - - -
2 Lampu ruangan 24.00 unit 250,000.00 6,000,000.00 0.015 - - - - - - -
3 Lampu toilet 24.00 unit 180,000.00 4,320,000.00 0.011 - - - - - - -
TRIBUN BARAT

KONTRAK AWAL S/D MINGGU LALU MINGGU INI S/D MINGGU INI

NO. JENIS PEKERJAAN KET


VOL. SAT. HARGA SAT. JUMLAH HARGA BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) Progress

4 Lampu selasar 36.00 unit 220,000.00 7,920,000.00 0.020 - - - - - - -

2.3. LANTAI 2
PEK. LAMPU TRIBUN 1 Atas VVIP 9.00 unit 1,500,000.00 13,500,000.00 0.034 - - - - - - -
2 Atas VIP 36.00 unit 900,000.00 32,400,000.00 0.081 - - - - - - -
3 Atas Tribun 48.00 unit 700,000.00 33,600,000.00 0.084 - - - - - - -
Jumlah 277,620,000.00 0.69 - - -
3 PEK. LANTAI RUANGAN & TRIBUN
3.1. LANTAI DASAR
1 Lantai keramik 40 x 40 cm un polish 1,200.00 m² 330,000.00 396,000,000.00 0.990 - - - - - - -
2 Plint keramik 10 x 40 cm 320.00 m1 120,000.00 38,400,000.00 0.096 - - - - - - -
3 Lantai keramik unpolish 20 x 20 cm (Toilet) 256.00 m² 160,000.00 40,960,000.00 0.102 - - - - - - -
4 Dinding keramik 20 x 25 cm (Toilet ) m² 160,000.00 -
3.2. LANTAI 1
1 Lantai keramik 40 x 40 cm un polish 600.00 m² 1,500,000.00 900,000,000.00 2.251 - - - - - - -
2 Plint keramik 10 x 40 cm m² 17,456.00 -
3 Lantai Keramik Polos 20 x 20 cm (Toilet) m² 20,100.00 -
4 Keramik dinding 20 x 25 cm (Toilet ) m² 187,191.68 -
3.3. LANTAI 2
1 Lantai keramik 40 x 40 cm un polish 600.00 m² 330,000.00 198,000,000.00 0.495 - - - - - - -
2 Plint keramik 10 x 40 cm m² 41,670.00 -
3 Lantai Keramik Polos 20 x 20 cm (Toilet) m² 68,667.00 -
4 Keramik dinding 20 x 25 cm (Toilet ) m² 187,191.68 -
Jumlah 1,573,360,000.00 3.94 - - -
4 PEK. SANITAIR TOILET VVIP, VIP, PEMAIN & PENONTON
4.1 LANTAI DASAR
A. Toilet Pemain 2 tim
1 Closet duduk 2 x 10 20.00 unit 2,400,000.00 48,000,000.00 0.120 - - - - - - -
2 Closet jongkok 2x2 4.00 unit 800,000.00 3,200,000.00 0.008 - - - - - - -
3 Urinoir 2x6 12.00 unit 2,800,000.00 33,600,000.00 0.084 - - - - - - -
4 Wastafel & cermin 2x3 8.00 unit 1,200,000.00 9,600,000.00 0.024 - - - - - - -
5 Kran air dia. 1/2" 2x3 6.00 unit 90,000.00 540,000.00 0.001 - - - - - - -
6 Shower mandi 2 x 12 24.00 unit 300,000.00 7,200,000.00 0.018 - - - - - - -
7 Shower cebok 2 x 12 24.00 unit 160,000.00 3,840,000.00 0.010 - - - - - - -
8 Floor drain 2 x 12 24.00 unit 140,000.00 3,360,000.00 0.008 - - - - - - -
B. Toilet VVIP & Oficial
1 Closet duduk 2 x 10 20.00 unit 90,000.00 1,800,000.00 0.005 - - - - - - -
2 Closet jongkok 2x2 4.00 unit 800,000.00 3,200,000.00 0.008 - - - - - - -
3 Urinoir 2x6 12.00 unit 2,800,000.00 33,600,000.00 0.084 - - - - - - -
4 Wastafel & cermin 2x3 8.00 unit 1,200,000.00 9,600,000.00 0.024 - - - - - - -
5 Kran air dia. 1/2" 2x3 6.00 unit 90,000.00 540,000.00 0.001 - - - - - - -
6 Shower mandi 2 x 12 24.00 unit 300,000.00 7,200,000.00 0.018 - - - - - - -
7 Shower cebok 2 x 12 24.00 unit 160,000.00 3,840,000.00 0.010 - - - - - - -
8 Floor drain 2 x 12 24.00 unit 140,000.00 3,360,000.00 0.008 - - - - - - -
C. Toilet Penonton VIP & Tribun Sudut
1 Closet duduk 2 x 10 20.00 unit 4,000,000.00 80,000,000.00 0.200 - - - - - - -
2 Closet jongkok 2x2 4.00 unit 800,000.00 3,200,000.00 0.008 - - - - - - -
3 Urinoir 2x6 12.00 unit 2,800,000.00 33,600,000.00 0.084 - - - - - - -
4 Wastafel & cermin 2x3 8.00 unit 1,200,000.00 9,600,000.00 0.024 - - - - - - -
5 Kran air dia. 1/2" 2x3 6.00 unit 90,000.00 540,000.00 0.001 - - - - - - -
TRIBUN BARAT

KONTRAK AWAL S/D MINGGU LALU MINGGU INI S/D MINGGU INI

NO. JENIS PEKERJAAN KET


VOL. SAT. HARGA SAT. JUMLAH HARGA BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) Progress

6 Shower mandi 2 x 12 24.00 unit 300,000.00 7,200,000.00 0.018 - - - - - - -


7 Shower cebok 2 x 12 24.00 unit 160,000.00 3,840,000.00 0.010 - - - - - - -
8 Floor drain 2 x 12 24.00 unit 140,000.00 3,360,000.00 0.008 - - - - - - -
4.2. LANTAI 1
A Toilet VVIP & VIP
1 Closet duduk 2 x 10 20.00 unit 700,000.00 14,000,000.00 0.035 - - - - - - -
2 Closet jongkok 2x2 4.00 unit 800,000.00 3,200,000.00 0.008 - - - - - - -
3 Urinoir 2x6 12.00 unit 2,800,000.00 33,600,000.00 0.084 - - - - - - -
4 Wastafel & cermin 2x3 8.00 unit 1,200,000.00 9,600,000.00 0.024 - - - - - - -
5 Kran air dia. 1/2" 2x3 6.00 unit 300,000.00 1,800,000.00 0.005 - - - - - - -
6 Shower mandi 2 x 12 24.00 unit 300,000.00 7,200,000.00 0.018 - - - - - - -
7 Shower cebok 2 x 12 24.00 unit 160,000.00 3,840,000.00 0.010 - - - - - - -
8 Floor drain 2 x 12 24.00 unit 140,000.00 3,360,000.00 0.008 - - - - - - -
B Toilet Penonton
1 Closet duduk 2 x 10 2.00 unit 2,400,000.00 4,800,000.00 0.012 - - - - - - -
2 Closet jongkok 2x2 8.00 unit 800,000.00 6,400,000.00 0.016 - - - - - - -
3 Urinoir 2x6 12.00 unit 2,800,000.00 33,600,000.00 0.084 - - - - - - -
4 Wastafel & cermin 2x3 6.00 unit 1,200,000.00 7,200,000.00 0.018 - - - - - - -
5 Kran air dia. 1/2" 2x3 18.00 unit 90,000.00 1,620,000.00 0.004 - - - - - - -
6 Shower cebok 2 x 12 8.00 unit 160,000.00 1,280,000.00 0.003 - - - - - - -
7 Floor drain 2 x 12 24.00 unit 140,000.00 3,360,000.00 0.008 - - - - - - -
Jumlah 448,680,000.00 1.12 - - -
5 PEK. PAGAR LANTAI DASAR, LANTAI 1 & LANTAI 2
5.1. LANTAI DASAR
1 Pagar selasar tinggi 300.00 m1 4,000,000.00 1,200,000,000.00 3.001 - - - - - - -
2 Pagar selasar tinggi depan m² -
5.2. LANTAI 1
1 Pagar void hall 36.00 m² 1,800,000.00 64,800,000.00 0.162 - - - - - - -
2 Pagar void koridor m² - -
5.3. LANTAI 2 / Tribun
1 Pagar pembatas tribun 36.00 m² 1,800,000.00 64,800,000.00 0.162 - - - - - - -
2 Pagar tribun VVIP m² - -
Jumlah 1,329,600,000.00 3.33 - - -
6 PEK. RAILING TANGGA
6.1. Railing tangga lantai dasar ke lantai 1
1 Tangga VIP stainless steel dia 3 inc 32.00 m1 4,000,000.00 128,000,000.00 0.320 - - - - - - -
2 Tangga Penonton pipa giv dia 3 inc 64.00 m1 650,000.00 41,600,000.00 0.104 - - - - - - -
3 -
6.2. Railing tangga lantai 1 ke lantai 2
1 Tangga VIP stainless steel dia 3 inc 16.00 m1 4,000,000.00 64,000,000.00 0.160 - - - - - - -
2 Tangga Penonton pipa giv dia 3 inc 48.00 m1 650,000.00 31,200,000.00 0.078 - - - - - - -
-
Jumlah 264,800,000.00 0.66 - - -
7 PEK. FINISHING DINDING, PLAFOND & LANTAI -
7.1. Finishing Lantai Dasar
1 Cat minyak untuk dinding 1,175.00 m² 110,000.00 129,250,000.00 0.323 - - - - - - -
2 Cat air untuk dinding 800.00 m² 70,000.00 56,000,000.00 0.140 - - - - - - -
3 Cat plafond m² 90,000.00 -
7.2. Finishing Lantai 1
1 Cat minyak untuk dinding 874.93 m² 110,000.00 96,242,300.00 0.241 - - - - - - -
TRIBUN BARAT

KONTRAK AWAL S/D MINGGU LALU MINGGU INI S/D MINGGU INI

NO. JENIS PEKERJAAN KET


VOL. SAT. HARGA SAT. JUMLAH HARGA BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) VOLUME BOBOT(%) Progress

2 Cat air untuk dinding 800.00 m² 70,000.00 56,000,000.00 0.140 - - - - - - -


3 Cat plafond m² 90,000.00 -
7.3. Finishing Lantai 2
1 Cat minyak untuk dinding 575.00 m² 110,000.00 63,250,000.00 0.158 - - - - - - -
2 Cat air untuk dinding 800.00 m² 70,000.00 56,000,000.00 0.140 - - - - - - -
Jumlah 456,742,300.00 1.14 - - -
8 PEK. PENGADAAN & PEMASANGAN KURSI -
-
9 PEK. LAIN - LAIN
1 Papan nama stadion stainless steel & lampu 4.00 unit 20,000,000.00 80,000,000.00 0.200 - - - - - - -
2 Pagar pintu masuk stainless steel 32.00 m1 6,000,000.00 192,000,000.00 0.480 - - - - - - -
unit -
Jumlah 272,000,000.00 0.68 - - -
TOTAL PEKERJAAN ARSITEKTUR 5,369,802,300.00 13.43 - - -
SUB JUMLAH 39,980,640,222.16 100.00 - 1.13 1.13
TINGKAT KEMAJUAN PELAKSANAAN PROYEK S/D MINGGU INI = 1.13 %
Terbilang : Satu Koma Satu Tiga Persen

Makassar, 10 Oktober 2017

: Dibuat Oleh
: Diperiksa Oleh Kontraktor Pelaksana
: Diketahui Oleh : Disetujui Oleh
Konsultan Pengawas PT. USAHA SUBUR SEJAHTERA
PPTK PAKET LANJUTAN PEMBANGUNAN STADION TIM TEKNIS KEGIATAN
PT. KANTA KARYA UTAMA
BAROMBONG MAKASSAR TA. 2017

NURYEDY ABBAS
.Ir. ANZAR CHALID, MT Direktur Utama
DR. H. MUHLIS, M.M Dr. Ir. H. JUMRAS, M.Si
Team Leader
NIP. 1968123 199203 1 055 NIP. 19620707 199203 1 012
REKAPITULASI LAPORAN MINGGUAN
KEMAJUAN PEKERJAAN
LANJUTAN PEMBANGUNAN STADION BAROMBONG
PROVINSI SULAWESI SELATAN
TAHUN ANGGARAN 2017
PEKERJAAN : LANJUTAN PEMBANGUNAN STADION BAROMBONG
INSTANSI : DINAS PEMUDA DAN OLAHRAGA
NO. KONTRAK : 416/3518/DISPORA/X/2017
NILAI KONTRAK : Rp. 43.978.704.000
KONT. PELAKSANA : PT. USAHA SUBUR SEJAHTERA
KONS. PENGAWAS : PT. KANTA KARYA UTAMA MINGGU KE : Ke 1 (SATU)

PELAKSANAAN : 90 HARI KALENDER MULAI TGL ; 04 Oktober 2017

SUMBER DANA : APBD TAHUN 2017 S/D TGL : 10 Oktober 2017

PROGRESS PEKERJAAN

NO. JENIS PEKERJAAN TOTAL HARGA (Rp.) BOBOT (%) S/D MINGGU LALU MINGGU INI S/D MINGGU INI KET
Progress Progress Progress
BOBOT (%) BOBOT (%) BOBOT (%)
(%) (%) (%)

I PEKERJAAN PERSIAPAN 208,877,312.50 0.52 - - 0.005 0.990 0.005 0.990

II PEKERJAAN TANAH DAN LAIN - LAIN


A. Pekerjaan Penimbunan Area Tribun (Luar Pagar Existing) SU (01 S/D 08) dan SS (72 S/D 79) 179,888,016.00 0.45 - - - - - -
B. Pekerjaan Penimbunan Area Tribun (Luar Pagar Existing) (79 S/D 88) 112,430,010.00 0.28 - - - - - -

III PEKERJAAN TIANG PANCANG DAN PONDASI GARIS


A Pekerjaan Tiang Pancang 27,953,750.00 0.07 - - 0.042 60.000 0.042 60.000
B Pekerjaan Pondasi Garis Sisi Utara (01 S/D 8) dan Sisi Selatan (54 S/D 72) 176,082,833.99 0.44 - - - - - -

IV PEKERJAAN KONSTRUKSI STADION


B. PEKERJAAN STRUKTUR TRIBUN SISI UTARA (01 S/D 08) dan SISI SELATAN (54 S/D 72)
. Pek. Pile Cab Pondasi Tiang Pancang 817,213,859.73 2.04 - - 1.082 52.958 1.082 52.958
. Pek. Kolom Pedestal/Stek Pile Cab 236,505,612.76 0.59 - - - - - -
. Pek. Tie Beam/Sloef 1,618,807,432.28 4.05 - - - - - -
. Pek. Kolom Struktur 2,370,313,556.01 5.93 - - - - - -
. Pek. Balok Dan Plat Tribun Lantai II 6,022,686,567.77 15.06 - - - - - -
. Pekerjaan Plat, Tribun Dan Tangga 6,570,614,055.37 16.43 - - - - - -

C. PEKERJAAN STRUKTUR TRIBUN SISI UTARA (15 S/D 10) dan SISI SELATAN (54 S/D 71)
. Pek. Pile Cab Pondasi Tiang Pancang 393,682,573.93 0.98 - - - - - -
. Pek. Kolom Pedestal/Stek Pile Cab 168,430,406.30 0.42 - - - - - -
. Pek. Tie Beam/Sloef 1,319,469,219.88 3.30 - - - - - -
. Pek. Kolom Struktur 2,249,151,075.36 5.63 - - - - - -
. Pek. Balok Dan Plat Tribun Lantai II 4,632,673,798.04 11.59 - - - - - -
. Pekerjaan Plat, Tribun Dan Tangga 4,779,302,842.23 11.95 - - - - - -

2 PEKERJAAN MEP
I Pekerjaan Mekanikal Dan Plumbing
1.1. Pekerjaan Air Bersih 167,539,000.00 0.42 - - - - - -
1.2. Pekerjaan Air Panas 99,884,000.00 0.25 - - - - - -
1.3. Pekerjaan air kotor berat dan cair 441,317,500.00 1.10 - - - - - -
1.4. Pekerjaan air hujan/drain lapangan 1,633,095,000.00 4.08 - - - - - -

II Pekerjaan Elektrikal
II.1. Pekerjaan Panel 38,000,000.00 0.10 - - - - - -
II.2. Pekerjaan titik instalasi daya dan penerangan 53,072,500.00 0.13 - - - - - -
II.3 Pekerjaan rak kabel dan fixture armartur penerangan 293,847,000.00 0.73 - - - - - -

3 PEKERJAAN ARSITEK
I PEK. DINDING, PINTU, JENDELA & VENTILASI 747,000,000.00 1.87 - - - - - -
II PEK. PLAFOND & LAMPU 277,620,000.00 0.69 - - - - - -
III PEK. LANTAI RUANGAN & TRIBUN 1,573,360,000.00 3.94 - - - - - -
IV PEK. SANITAIR TOILET VVIP, VIP, PEMAIN & PENONTON 448,680,000.00 1.12 - - - - - -
V PEK. PAGAR LANTAI DASAR, LANTAI 1 & LANTAI 2 1,329,600,000.00 3.33 - - - - - -
VI PEK. RAILING TANGGA 264,800,000.00 0.66 - - - - - -
VII PEK. FINISHING DINDING, PLAFOND & LANTAI 456,742,300.00 1.14 - - - - - -
VIII PEK. PENGADAAN & PEMASANGAN KURSI -
IX PEK. LAIN - LAIN 272,000,000.00 0.68 - - - - - -

JUMLAH 39,980,640,222.160 100.00


TOTAL REALISASI 0.00 1.13 1.13
TOTAL RENCANA 0.00 0.34 0.34
OVER/ UNDER 0.00 0.79 0.79

Makassar, 10 Oktober 2017


: Dibuat Oleh
: Diketahui Oleh : Disetujui Oleh : Diperiksa Oleh
Kontraktor Pelaksana
PPTK PAKET LANJUTAN PEMBANGUNAN TIM TEKNIS KEGIATAN Konsultan Pengawas
PT. USAHA SUBUR SEJAHTERA
STADION BAROMBONG MAKASSAR TA. 2017 PT. KANTA KARYA UTAMA

NURYEDY ABBAS
DR. H. MUHLIS, M.M Dr. Ir. H. JUMRAS, M.Si .Ir. ANZAR CHALID, MT
Direktur Utama
NIP. 1968123 199203 1 055 NIP. 19620707 199203 1 012 Team Leader
NURYEDY ABBAS
DR. H. MUHLIS, M.M Dr. Ir. H. JUMRAS, M.Si .Ir. ANZAR CHALID, MT
Direktur Utama
NIP. 1968123 199203 1 055 NIP. 19620707 199203 1 012 Team Leader
1 04 Oktober 2017 7 10 Oktober 2017
2 11 Oktober 2017 7 17 Oktober 2017
3 18 Oktober 2017 7 24 Oktober 2017
4 25 Oktober 2017 7 31 Oktober 2017
5 01 November 2017 7 07 November 2017
6 08 November 2017 7 14 November 2017
7 15 November 2017 7 21 November 2017
8 22 November 2017 7 28 November 2017
9 29 November 2017 7 05 Desember 2017
10 06 Desember 2017 7 12 Desember 2017
11 13 Desember 2017 7 19 Desember 2017
12 20 Desember 2017 7 26 Desember 2017
13 27 Desember 2017 5 31 Desember 2017
89