Anda di halaman 1dari 2

Status is resubmit AS noted.

comments of Electrical power shopdrawings:


--------------------------------------------
power layouts:
1-disconntion time schedule not submitted as mension in drawing notes.
2-short circuit calculations to be submitted for review with SLD.
3-setting out plan to be sumbitted,SU2 power cabling layouts to be submitted,Ele
ctrical rooms no's to be the same for nearest LV room.
4-consider the irrigation electrical load in SLD,and second sump pump for bigger
swell tank to be added with aproper KW load estimation.
5-same reting for spare CB's to be provided as per 7.8.17 -electricity wiring re
gulation.
6-very important missing affected current carring factor to be consider for cabl
e size and voltage drop calculations as per appendixes A7(a)-A7(h) -electricity
wiring regulation & as per c.1.4.18 -volume 1-MEP RPS spec's and resubmit it by
details in tables.
7-DB spare to be added ,u have 14ways.
8-location of LV panels to be mentioned in SLD's.
9-power factor to be corrected to 0.93 not 0.85 as mention in notes.
10-follow the ADDC & project spec's.
11-lux calculation to be submitted then the no's of ex.light to be decided.
12-follow C.1.4.13-volume 1-RPS.
13-space of electrical room is subject to ADDC approval.
14-SU2,3 power layouts not submitted.
15-seperate the telephone submittal than power layouts submittals.
16-PDF files for load schedual not clear enough to review,submitted properly.
17-units feeded from SMDB12 to be fed from LV panels in LV room 1 to reduce the
no of ducts in conjusted areas like section B-B it will be 3 layers instead of
4 layers & 3 main cables will cancelled from section C-C.
18-merging proposa
19-another duty water pump to be consider.
20-all mechnical equipments to be protected as per the ......
21-TN-s to provided as per RPS ....
22-load scheduals to be as per the approved mechanical materials.
23-variation is rejected for DUCTS as per RSB regulation clause no:7.5.8.
24-manholes details to be submitted for all differant cases .
25-cables routing under ground in ducts to be at least 600mm not 300mm as shown
in section B-B beside the footing and coordinate .
26-submit the coordination drawings after involoved the previous comments.
27-cables to be submitted as LSF material.
28-provide the approved supported document from authorities for the selected div
ersity factors.
29-consider the heavy truck as per page 15-item 4.1 in outline RPS spec's to con
firm the duct class by supported calculations.
30-all outgoing SMDB cables to be LSF type as per RPS spec's no C.1.4.15/16/18 -
vol 1.
31-variation is rejected for bus coupler as per RSB regulation clause no:7.9.5
32-DB comments:
b-spare ways to be added for power section.
c-power section to be protected as per table no A5(m).
d-all final circuits cables to be LSF type.
33-voltage surge protection to be provided as per RPS regulation no C.1.4.25/14.
34-requested sections to be submitted as per located in drawing no..
35-coordinate with other services.
36-irrigation system not included in electrical shop drawing,to be considered.
37-coordinate with infrastructre contractor/drawings .
38-all materials to be submitted.
39-diversity factor to be clarify C.1.4.16/13.
40-submit repeation for typical factory unit DB to be removed.
41-load schedual for each LV panel's to be submitted sepertaly.
42-table no A5(m) to be applied for landlord SMDB's and factory unit typical DB.
43-LV panels dimenstion is subject to the shopdrawings & panels approval.
44-submit capbank.
45-20% spare to be added for factory unit DB as per RPS spec's C.1.4.16
46-unify the symbol of duct for all whole length.
47-Pf to be improved to 0.93 but not 0.85 as stated in SLD notes.
48-disconntion time data not submitted.
49-supply of emergency light to be indicated in drawing and load scheduals.
50-follow the metering
51-routing of type B is rejected,follow the same concept for other types.
52-cap banks to be beside it's LV Panel,and rearrange.
53-cables entris details to be submitted for the electrical rooms in trenches.
54-coordinate with etisalat authority for approval.
55-previous drawings comments are valid where applicable .
56-complaince statments for bms
57-complaince statments for telephone
a-pull boxes to be installled,its apart from the containment system.
b-provide concrete duct for crossing road as per etislate where appliaca
ble.
c-earthing for MDF is a part from earthing system as per C30.4 Rps spec'
s
d-coordinate with infrastructure contractor/drawings.
58-spacing between cables not mentioned in drawing.
59-SLD for SU2 not typical of SU1 to be modified according to diffrenct location
of pumps rooms.
60-all whole length for cables to be ducted by class 10.
61-incoming supply intake from infrastructure drawing is differant than used in
distribution voltage used in calculation,previously commented ,contractor has ap
ply it.
62-at least 300mm spacing to be in section B-B between main cables and distribut
ed cables to allow handling the cables by decreasing the spacing between cables.
63-section (c-c) & (b-b)are wrong to be corrected .
64-manholes to be installed to allow 8D bending radius for all cables.
65-manholes to be installed next to Electrical room 1,2 to entering the main cab
les easily,cable ladder by layers to be installed at electrical rooms trenshs.
66-maholes location to be avoid the entrance of industrial units.
67-additional manhole required to be installed at (B-01).
68-based on letter no:.....Diversity factor approved subject to ADDC.
69-details to be provided for entries of cables for both electrical rooms provid
ing cable ladders by layers.

Anda mungkin juga menyukai