Anda di halaman 1dari 246

HARGA SAT JUMLAH

NO PEKERJAAN VOL SAT


Rp. Rp.
1 2 3 4 5 6
I PEKERJAAN PENDAHULUAN
1 Perencanaan dan pengawasan 1,860.00 m2 250,000.00 465,000,000.00
2 Urus IMB 1,860.00 m2 35,000.00 65,100,000.00
3 Pek. Zondir 4.00 ttk 7,500,000.00 30,000,000.00
4 Pek. Pembersihan lahan + pengukuran lahan dng theodolite 2,400.00 m2 25,550.00 61,320,000.00
5 Pek. Direksi keet 40.00 m2 2,044,000.00 81,760,000.00
6 Pas. Gudang kerja 20.00 m2 1,184,700.00 23,694,000.00
7 Pas. Mess pekerja 196.00 m2 1,184,700.00 232,201,200.00
8 Pas. Listrik kerja 12.00 ls 10,161,250.00 121,935,000.00
1,081,010,200.00
II PEK. BANGUNAN LT. I
A PEKERJAAN TANAH
1. Pasang bouwplank 206.00 m1 95,450.00 19,662,700.00
2. Galian tanah pondasi 2,827.22 m3 120,550.00 340,821,371.00
3. Galian pondasi rolag 50.06 m3 120,550.00 6,034,467.79
4. Galian tanah file cap PC.I 9.68 m3 147,750.00 1,430,220.00
5. Galian tanah file cap PC.II 5.88 m3 147,750.00 868,770.00
6. Urugan tanah kembali 954.64 m3 40,150.00 38,328,654.43
7. Urugan pasir urug bawah lantai 10 cm 133.40 m3 206,600.00 27,560,026.80
8. Urugan tanah ke dalam bangunan 30 cm 611.82 m3 173,600.00 106,211,952.00
9. Pemadatan tanah bawah lantai 2,039.40 m3 3,600.00 7,341,840.00
548,260,002.02
B PEKERJAAN PASANGAN PONDASI
1. Pas. Pondasi Batu kali/belah Camp. 1pc : 4ps 173.49 m3 1,236,300.00 214,483,832.55
2. Pas. Pondasi rolag 4 lapis 118.48 m1 156,100.00 18,494,728.00
232,978,560.55
C PEKERJAAN BETON STRUKTUR
1. Pek. Lantai kerja dibawah lantai 101.97 m3 1,187,550.00 121,094,473.50
2. Pek. Lantai Kerja di bawah pile cap 10.76 m3 1,187,550.00 12,773,287.80
3. Pek. Pondasi tiang pancang Uk.∆ 30x30X30 cm kedalaman 12 m' 1,128.00 m1 485,750.00 547,926,000.00
4. Pek. Pondasi pile cap PC.I 142.56 m3 7,489,550.00 1,067,710,248.00
5. Pek. Pondasi pile cap PC.II 1.30 m 3
7,489,550.00 9,706,456.80
6. Membuat kolom pedestal beton bertulang (50x50) 11.00 m3 8,942,700.00 98,369,700.00
7. Membuat kolom pedestal beton bertulang (50x30) 0.90 m3 8,942,700.00 8,048,430.00
8. Membuat kolom komposit beton bertulang (50x50) 77.40 m3 7,500,600.00 580,546,440.00
9. Membuat sloof beton 20x40 cm 44.64 m3 6,172,227.89 275,528,253.01
10. Membuat sloof beton 15x20 cm 32.52 m3 6,172,227.89 200,720,850.98
11. Membuat kolom beton bertulang (12 x 12) 0.78 m3 7,500,600.00 5,832,466.56
12. Membuat kolom beton bertulang (12 x 30) 5.88 m 3
8,942,700.00 52,549,809.16
13. Pas. Besi wermest Ø 8 mm untuk lantai beton 2 lapis 2,039.40 m2 204,560.36 417,180,398.18
14. Membuat lantai beton tebal 20 cm K - 250 203.94 m3 1,587,600.00 323,775,144.00
15. Membuat dak beton bertulang tebal 12 cm 3.36 m3 6,117,500.00 20,554,800.00
16. Membuat ring balok beton bertulang (12 x15) 0.34 m3 5,179,550.00 1,771,406.10
2.
1 2 3 4 5 6
17. Membuat balok latai 0.19 m 3
5,179,550.00 964,639.39
18. Membuat pelat meja wastafel beton bertulang tebal 8 0.07 m3 3,644,350.00 244,900.32
3,692,747,894.65
D PEKERJAAN PASANGAN
1. Pas. Dinding 1/2 bata 1,344.14 m2 142,300.00 191,271,691.20
2. Pek. Plesteran 2,688.29 m2 92,200.00 247,860,153.60
3. Pek. Acian 2,688.29 m2 57,050.00 153,366,830.40
592,498,675.20
E PEKERJAAN KONSTRUKSI BAJA + EREKSEN
1. Pek. Kolom baja
a HB 400 60,621.74 kg 37,500.00 2,273,315,400.00
g WF 400 1,845.36 kg 37,500.00 69,201,000.00
2,342,516,400.00
2. Rafter
a WF400 23,697.83 kg 37,500.00 888,668,550.00
888,668,550.00
3. Ring & Floor Beam
a WF400 24,948.00 kg 37,500.00 935,550,000.00
935,550,000.00
4. Bracing
a Rod Dia.19 1,370.15 kg 37,500.00 51,380,568.00
b Sagrod Dia.12 845.23 kg 37,500.00 31,696,272.00
83,076,840.00
5. Gording dan Clading
a Gording CNP150.65.20.2,3 9,350.00 kg 34,155.00 319,349,250.00
b Clading besi plat 12 mm 446.76 kg 34,155.00 15,259,087.80
334,608,337.80
6. Sambungan Baja
a Base Plate 1,681.47 Kg 37,200.00 62,550,684.00
b Cap Plate 2,289.06 Kg 37,200.00 85,153,032.00
c End Plate 10,830.65 Kg 37,200.00 402,899,994.00
d Pelat Stiffener 1,368.35 Kg 37,200.00 50,902,590.24
e Mur & Baut M19 4,400.00 bh 12,075.00 53,130,000.00
f Mur & Baut M22 440.00 bh 20,700.00 9,108,000.00
g Angkur M22 Type A325 440.00 bh 80,500.00 35,420,000.00
699,164,300.24
F PEKERJAAN KUSEN DAN DAUN PINTU/JENDELA KAYU
1. Pas. kusen besi canal C 125.50.20.3,2 189.42 Kg 34,155.00 6,469,640.10
2. Pas. Pintu panel oven 7.20 M² 870,800.00 6,269,760.00
3. Pas. Pintu kaca tb 10 mm , rangka allumunium 10.40 M² 1,247,700.00 12,976,080.00
4. Pas. BV KM/WC, rangka allumunium 1.12 M² 836,150.00 936,488.00
5. Pasang kusen pintu jendela allumunium 426.50 M' 174,650.00 74,488,225.00
6. Pasang jendela kaca, rangka allumunium 979.05 M² 836,150.00 818,628,476.75
7. Pas. Pintu rolng door 65.19 M² 769,350.00 50,153,926.50
8. Pasang pintu aluminium KM/WC 4.20 M² 836,150.00 3,511,830.00
973,434,426.35
G PEKERJAAN KONSTRUKSI LANGIT-LANGIT/PLAFON
1. Pasang list cornice gypsum lebar sampai 5-10 cm 48.00 M' 45,300.00 2,174,400.00
2. Penutup plafon Gypsumboard 9 mm dgn rangka hollow tebal 0.6 mm 72.00 M² 189,450.00 13,640,400.00
15,814,800.00
H PEKERJAAN PENUTUP ATAP
1. Pasang teras + kolom ACP rangka besi hollow 1031.05 M² 838,600.00 864,638,530.00
2. Pasang listplank ACP rangka besi hollow 684.00 M² 838,600.00 573,602,400.00
3. Pasang atap Spandek 1990.00 M² 233,900.00 465,461,000.00
4. Pasang nok Spandek 50.00 M' 118,050.00 5,902,500.00
3.
1 2 3 4 5 6
5. Pasang talang datar 200.00 M' 229,350.00 45,870,000.00
6. Pasang ornamen besi hollow di atas dak 189.14 M² 603,700.00 114,180,799.50
7. Pasang pipa galvanis penguat atap ACP Ø 4' 25.30 M' 561,200.00 14,198,360.00
8. Pasang talang PVC Ø 4" 180.00 M' 180,800.00 32,544,000.00
2,116,397,589.50
I PEKERJAAN SANITASI
1. Memasang kloset duduk 6.00 Bh 3,540,055.00 21,240,330.00
2. Memasang pipa PVC tipe AW dia 1/2" 40.00 M' 28,150.00 1,126,000.00
3. Memasang pipa PVC tipe AW dia 3/4" 120.00 M' 37,600.00 4,512,000.00
4. Memasang pipa PVC tipe AW dia 3" 36.00 M' 149,600.00 5,385,600.00
5. Memasang pipa PVC tipe AW dia 4" 36.00 M' 180,800.00 6,508,800.00
6. Memasang jet washer 6.00 Bh 81,350.00 488,100.00
7. Memasang floor drain stainless 6.00 Bh 71,600.00 429,600.00
8. Membuat tanki septik kapasitas (vol. 4,5 m³) 2.00 Bh 10,748,700.00 21,497,400.00
9. Membuat resapan Ø 0,8 m (digali 1 m) 2.00 Bh 1,601,200.00 3,202,400.00
10. Membuat saluran air buis beton ½ Ø 20 cm 202.00 M' 176,100.00 35,572,200.00
11. Pas bak kontrol 45x45 + tutup 6.00 Bh 625,300.00 3,751,800.00
103,714,230.00
J PEKERJAAN KUNCI DAN KACA
1. Pasang kunci silinder allumunium 13.00 Bh 213,250.00 2,772,250.00
2. Pasang engsel pintu kuningan/stainless 39.00 Bh 66,950.00 2,611,050.00
3. Pasang pegangan pintu/door holder 15.00 Bh 159,500.00 2,392,500.00
4. Pasang grendel pintu 15.00 Bh 84,600.00 1,269,000.00
9,044,800.00
K PEKERJAAN PENUTUP LANTAI DAN DINDING
1. Pasang Granit lantai + tangga ukuran 60 x 60 cm 590.00 M² 295,451.68 174,316,490.02
2. Pasang lantai Km/Wc Granit lantai + tangga ukuran 60 x 60 cm 36.00 M² 295,451.68 10,636,260.41
3. Pasang dinding Km/Wc 30 x 60 cm 196.75 M² 295,451.68 58,130,117.65
4. Pasang Granit warna hitam pintu masuk 10.80 M² 418,350.00 4,518,180.00
247,601,048.07
L PEKERJAAN PENGECATAN
1. Pengecatan tembok baru 2688.29 M² 53,150.00 142,882,507.20
2. Pengecatan Plafond 77.76 M² 53,150.00 4,132,944.00
3. Pengecatan waterproofing membran 36.00 M² 191,100.00 6,879,600.00
4. Pengecatan lantai dng epoxy 1404.00 M² 51,450.00 72,235,800.00
5. Pengecatan cycroma baja 4918.40 M² 50,700.00 249,362,626.50
475,493,477.70
M PEKERJAAN INSTALASI LISTRIK
1. Pasang Meterisasi listrik 65.000 KVA 1.00 Unit 75,000,000.00 75,000,000.00
2. Pasang instalasi lampu untuk lampu 15.00 Titik 780,050.00 11,700,750.00
3. Pasang instalasi lampu kabel NYM 2x 2,5 mm 44.00 Titik 354,500.00 15,598,000.00
4. Pasang instalasi stop kontak 20.00 Bh 354,100.00 7,082,000.00
5. Pasang Panel Genset ATS AMF 33 KVA 3phase 1.00 Unit 27,517,100.00 27,517,100.00
4.
1 2 3 4 5 6
6. Pasang lampu LED untuk 15.00 Bh 418,000.00 6,270,000.00
7. Pasang lampu SL 44.00 Titik 73,800.00 3,247,200.00
8. Pasang saklar tunggal 7.00 Bh 129,550.00 906,850.00
9. Pasang saklar ganda 15.00 Bh 147,200.00 2,208,000.00
10. Pasang stop kontak 20.00 Bh 146,200.00 2,924,000.00
152,453,900.00

Jumlah ###
Ppn 10 % 1,444,402,383.21
Total jumlah ###
Dibulatkan ###

Perencana,

Anword studio arsitektur


team work
5

RINGKASAN HARGA SATUAN PEKERJAAN (UNIT PRICE)


BANGUNAN GEDUNG, PERUMAHAN DAN PRASARANA
WILAYAH PALEMBANG TA. 2020

NO. URAIAN HSP (Rp)

A PEKERJAAN PENDAHULUAN
1. Pagar sementara dari seng gelombang tinggi 2 meter tiap 1 m' 757,450
2. Pagar sementara dari kawat duri tinggi 1,8 meter tiap 1 m' 135,250
3. Pembuatan kantor sementara, dengan lantai plesteran tiap 1 m² 2,044,000
4. Pembuatan kantor sementara dengan lantai plesteran + meja & bangku kayu tiap 1 m² 1,184,700
5. Pembuatan gudang semen dan peralatan tiap 1 m² 1,998,750
6. Pembuatan jalan sementara tebal 20 cm tiap 1 m² 276,650
7. Pembuatan jalan sementara tebal 25 cm tiap 1 m² 316,250
8. Pasang bouwplank tiap 1 m' 95,450
9. Membersihkan puing-puing tiap 1 m2 30,800
10. Pengukuran dengan alat ukur ( theodolite) tiap 1 m2 5,500

B PEKERJAAN TANAH
1. Pembersihan lapangan dan perataan tiap 1 m² 25,550
2. Pekerjaan stripping setinggi 1 meter (pembersihan lahan skala besar) tiap 1 m² ( SNI ) 8,700
3. Galian tanah biasa sedalam 1 meter tiap 1 m³ ( SNI ) 120,550
4. Galian tanah biasa sedalam 2 meter tiap 1 m³ ( SNI ) 147,750
5. Galian tanah biasa sedalam 3 meter tiap 1 m³ ( SNI ) 175,300
6. Galian tanah keras sedalam 1 meter tiap 1 m³ ( SNI ) 160,500
7. Galian tanah cadas sedalam 1 meter tiap 1 m³ ( SNI ) 243,200
8. Galian tanah lumpur sedalam 1 meter tiap 1 m³ ( SNI ) 193,950
9. Pekerjaan Bor Pile D 30 cm tiap 1 m' 370,650
10. Pembuangan tanah sejauh 150 m tiap 1 m³ 89,600
11. Urugan tanah kembali tiap 1 m³ 40,150
12. Urugan tanah mendatangkan tiap 1 m³ 173,600
13. Mengangkut tanah sejauh 30 m tiap 1 m³ 52,850
14. Menghampar tanah dengan menghampar tiap 1 m³ 40,500
15. Pemadatan tanah (tenaga manusia) tiap 1 m³ 87,150
16. Pemadatan tanah (tenaga manusia) tebal 20 cm tiap 1 m² 17,400
17. Pemadatan tanah dengan tamper/hand compactor 6 lintasan / tebal 20cm tiap 1 m³ 18,100
18. Pemadatan tanah tebal 20 cm dengan tamper/hand compactor 6 lintasan / tebal 20cm tiap 1 m² 3,600
6

NO. URAIAN HSP (Rp)

19. Pemadatan tanah dengan tamper/hand compactor 10 lintasan / tebal 20cm tiap 1 m³ 30,200
20. Pemadatan tanah tebal 20 cm dengan tamper/hand compactor 10 lintasan / tebal 20cm tiap 1 m² 6,000
21. Pemadatan tanah dengan Vibrating Roller tiap 1 m³ 2,250
22. Pemadatan tanah tebal 20 cm dengan Vibrating Roller tiap 1 m² 450
23. Urugan sirtu tiap 1 m³ ( SNI ) 593,400
24. Urugan pasir urug tiap 1 m³ ( SNI ) 206,600
25. Urugan tanah merah tiap 1 m³ 173,600
26. Urugan pasir pasang tiap 1 m³ 283,400
27. Pemancangan tiang/cerucuk dolken kecil dalam 2 m' tiap 1 titik 22,300
28. Pemancangan tiang/cerucuk dolken besar dalam 2 m' tiap 1 titik 24,600
29. Pemasangan lapisan ijuk tiap 1 m2 200,050
30. Pemasangan lapisan geotekstil non woven tiap 1 m2 115,100

C PEKERJAAN PASANGAN BATU KALI/BELAH


1. Pasang pondasi/pasangan batu kali/belah 1 Pc : 2 Ps tiap 1 m³ 1,337,400
2. Pasang pondasi/pasangan batu kali/belah 1 Pc : 3 Ps tiap 1 m³ ( SNI ) 1,285,200
3. Pasang pondasi/pasangan batu kali/belah 1 Pc : 4 Ps tiap 1 m³ ( SNI ) 1,236,300
4. Pasang pondasi/pasangan batu kali/belah 1 Pc : 5 Ps tiap 1 m³ ( SNI ) 1,202,400
5. Pasang pondasi batu kosong (aanstamping) tiap 1 m³ ( SNI ) 769,600
6. Pasang pondasi siklop 40% batu kali tiap 1 m³ 2,830,050
7. Pasang pondasi sumuran diameter 100 cm tiap 1 m³ ( SNI ) 1,303,500

D PEKERJAAN DINDING
1. Pasangan bata merah tebal 1 bata, 1 Pc : 2 Ps tiap 1m² ( SNI ) 317,150
2. Pasangan bata merah tebal 1 bata, 1 Pc : 4 Ps tiap 1m² ( SNI ) 295,450
3. Pasangan bata merah tebal 1/2 bata, 1 Pc : 2 Ps tiap 1m² ( SNI ) 154,150
4. Pasangan bata merah tebal 1/2 bata, 1 Pc : 4 Ps tiap 1m² ( SNI ) 144,500
5. Pasangan bata merah tebal 1/2 bata, 1 Pc : 5 Ps tiap 1m² ( SNI ) 142,300
6. Pasangan bata merah 1 Pc : 2 Ps tiap 1m³ (dibagi tebal bata 11 cm) 1,426,900
7. Pasangan bata merah 1 Pc : 4 Ps tiap 1m³ (dibagi tebal bata 11 cm) 1,339,050
8. Pasangan dinding batako tiap 1m² 162,150
9. Pasangan dinding hebel dengan perekat mortar tiap 1m² 230,100
10. Pasangan rollag bata merah 1 Pc : 5 Ps , tiap 1 m' (1 lapis bata) 33,250
11. Pasangan rollag bata merah 1 Pc : 4 Ps , tiap 1 m' (2 lapis bata) 78,050
12. Pasangan dinding hollowblock HB 20 tiap 1m², spesi 1:4 ( SNI ) 204,750
13. Pasangan dinding hollowblock HB 15 tiap 1m², spesi 1:4 ( SNI ) 178,000
14. Pasangan dinding hollowblock HB 10 tiap 1m², spesi 1:4 ( SNI ) 133,200
15. Pasangan dinding Roster bata merah 12 x 24 x 10 tiap 1m², spesi 1:3 584,100
16. Roster keramik 30 x 30 x 7 64,150
17. Pasangan dinding Glass block 20 x 20 x 10 tiap 1m² 600,600
7

NO. URAIAN HSP (Rp)

E PEKERJAAN PLESTERAN
1. Plesteran 1 Pc : 2 Ps tebal 15 mm tiap 1m² ( SNI ) 97,150
2. Plesteran 1 Pc : 3 Ps tebal 15 mm tiap 1m² ( SNI ) 94,200
3. Plesteran 1 Pc : 4 Ps tebal 15 mm tiap 1m² ( SNI ) 92,200
4. Plesteran 1 Pc : 2 Ps tebal 20 mm tiap 1m² ( SNI ) 130,000
5. Plesteran 1 Pc : 3 Ps tebal 20 mm tiap 1m² ( SNI ) 102,700
6. Plesteran 1 Pc : 4 Ps tebal 20 mm tiap 1m² ( SNI ) 123,400
7. Plesteran 1 Pc : 2 Ps tebal 25 mm tiap 1m² 112,700
8. Plesteran 1 Pc : 3 Ps tebal 25 mm tiap 1m² 111,650
9. Plesteran 1 Pc : 4 Ps tebal 25 mm tiap 1m² 109,000
10. Plesteran dinding dengan mortar tiap 1m² 167,000
11. Plesteran Berapen 1 Pc : 3 Ps tebal 15 mm tiap 1m² 52,650
12. Plesteran Berapen 1 Pc : 5 Ps tebal 15 mm tiap 1m² ( SNI ) 51,100
13. Plesteran Skoning (benangan/ tali air) 1 Pc : 2 Ps lebar 10 cm / tiap 1m' ( SNI ) 94,700
14. Plesteran Ciprat 1 Pc : 2 Ps tiap 1m² ( SNI ) 76,150
15. Plesteran Siar 1 Pc : 2 Ps untuk pasangan batu kali tiap 1m²( SNI ) 90,000
16. Acian 1 m2 ( SNI ) 57,050
17. Acian dengan mortar tiap 1m² 57,300

F PEKERJAAN KUSEN DAN DAUN PINTU/JENDELA KAYU


1. Pasang kusen pintu dan jendela Kayu Jati tiap 1m³ ( SNI ) 31,385,950
2. Pasang kusen pintu dan jendela Kayu Kamper Samarinda Oven tiap 1m³ ( SNI ) 13,239,550
3. Pasang kusen pintu dan jendela Kayu Kamper Medan/Kruing tiap 1m³( SNI ) 10,553,800
4. Pasang kusen pintu dan jendela Kayu Meranti Palembang tiap 1m³ ( SNI ) 10,553,800
5. Pasang kusen pintu dan jendela Kayu Borneo tiap 1m³ 10,553,800
6. Pasang pintu panel Kayu Jati tiap 1m² ( SNI ) 1,885,550
7. Pasang pintu panel Kayu Kamper Samarinda Oven tiap 1m² ( SNI ) 527,100
8. Pasang pintu panel Kayu Kamper Medan/Kruing tiap 1m² ( SNI ) 421,750
9. Pasang pintu panel Kayu Borneo tiap 1m² 797,150
10. Pasang pintu panel Kayu Meranti Sampit tiap 1m² 870,800
11. Pasang pintu dan jendela kaca Kayu Jati tiap 1m² ( SNI ) 1,281,650
12. Pasang pintu dan jendela kaca Kayu Kamper Samarinda Oven tiap 1m² ( SNI ) 759,650
13. Pasang pintu dan jendela kaca Kayu Kamper Medan/Kruing tiap 1m² 653,200
14. Pasang pintu dan jendela kaca Kayu Meranti Sampit tiap 1m² 653,200
15. Pasang pintu dan jendela kaca Kayu Borneo tiap 1m² 609,000
16. Pasang pintu dan jendela jalusi Kayu Jati tiap 1m² ( SNI ) 2,554,500
17. Pasang pintu dan jendela jalusi Kayu Kamper Samarinda Oven tiap 1m² 1,162,450
18. Pasang pintu dan jendela jalusi Kayu Kamper Singkil tiap 1m² 1,162,450
19. Pasang pintu dan jendela jalusi Kayu Kamper Medan/Kruing tiap 1m² 1,087,500
20. Pasang pintu dan jendela jalusi Kayu Meranti Sampit tiap 1m² 1,087,500
21. Pasang pintu dan jendela jalusi Kayu Borneo tiap 1m² 969,700
8

NO. URAIAN HSP (Rp)

22. Pasang jalusi mati Kayu Jati tiap 1m² ( SNI ) 2,238,400
23. Pasang jalusi mati Kayu Kamper Samarinda oven tiap 1m² ( SNI ) 933,400
24. Pasang jalusi mati Kayu Kamper Medan/Kruing tiap 1m² ( SNI ) 863,100
25. Pasang pintu teakwood rangkap, rangka Kayu Kamper Samarinda oven tiap 1m² ( SNI ) 899,450
26. Pasang pintu teakwood rangkap, rangka Kayu Kamper Medan/Kruing tiap 1m² 766,700
27. Pasang pintu teakwood rangkap, rangka Kayu Meranti Palembang tiap 1m² 766,700
28. Pasang pintu triplek rangkap, rangka Kayu Kamper Medan/Kruing tiap 1m² 705,100
29. Pasang pintu triplek rangkap, rangka Kayu Meranti Palembang tiap 1m² 705,100
30. Pasang pintu teakwood dan formika, rangka Kayu Kamper Samarinda oven tiap 1m² ( SNI ) 1,023,200
31. Pasang pintu teakwood dan formika, rangka Kayu Kamper Medan/Kruing tiap 1m² 981,550
32. Pasang pintu teakwood dan formika, rangka Kayu Meranti Palembang tiap 1m² 981,550
33. Pasang pintu triplek dan formika, rangka Kayu Kamper Medan/Kruing tiap 1m² 919,950
34. Pasang pintu triplek dan formika, rangka Kayu Meranti Palembang tiap 1m² 919,950
35. Pasang pintu triplek dan double formika, rangka Kayu Meranti Palembang tiap 1m² 1,054,600
36. Pasang kawat harmonika tiap 1 m² 62,250
37. Pasang kawat nyamuk tiap 1 m² 66,050
38. Pasang kawat kasa tiap 1 m² 66,700

G PEKERJAAN KONSTRUKSI ATAP KAYU


1. Pasang konstruksi kuda-kuda Kayu Borneo tiap 1m³ 8,835,900
2. Pasang konstruksi kuda-kuda Kayu Kamper Medan/Kruing tiap 1m³ ( SNI ) 10,865,150
3. Pasang konstruksi kuda-kuda expose Kayu Samarinda tiap 1m³ ( SNI ) 14,085,500
4. Pasang Konstruksi Gording Kayu Kamper Medan/Kruing tiap 1m³ ( SNI ) 7,578,250
5. Pasang kaso + reng genteng kodok Kayu Kamper Medan/Kruing tiap 1m²( SNI ) 149,000
6. Pasang kaso + reng genteng kodok Kayu Meranti Jambi tiap 1m² 128,400
7. Pasang kaso + reng genteng keramik Kayu Kamper Medan/Kruing tiap 1m²( SNI ) 347,350
8. Pasang kaso + reng genteng keramik Kayu Meranti Jambi tiap 1m² ( SNI ) 288,800
9. Pasang kaso + reng genteng beton Kayu Kamper Medan/Kruing tiap 1m² ( SNI ) 475,900
10. Pasang kaso + reng genteng beton Kayu Meranti Jambi tiap 1m² 138,800
11. Pasang kaso + reng atap sirap kayu kamper tiap 1m² ( SNI ) 1,057,400
12. Pasang lisplank (3 x 20) cm Kayu Kamper Samarinda tiap 1m' 92,250
13. Pasang lisplank (3 x 20) cm Kayu Kamper Medan/Kruing tiap 1m' 92,250
14. Pasang lisplank (3 x 20) cm Kayu Meranti Palembang tiap 1m' 92,250
15. Pasang lisplank (3 x 30) cm Kayu Kamper Samarinda tiap 1m' 116,500
16. Pasang lisplank (3 x 30) cm Kayu Kamper Medan/Kruing tiap 1m' 116,500
17. Pasang lisplank (3 x 30) cm Kayu Meranti Palembang tiap 1m' 116,500
18. Pasang lisplank 2 x (2 x 20) cm Kayu Kamper Samarinda tiap 1m' 80,800
19. Pasang lisplank 2 x (2 x 20) cm Kayu Kamper Medan/Kruing tiap 1m' 80,800
20. Pasang lisplank 2 x (2 x 20) cm Kayu Meranti Palembang tiap 1m' 80,800
21. Pasang listplank Kalsiplank 8-jati 8.0x300x30000 tiap 1m' 165,950
22. Membuat listplank asbes plat ram kayu tiap 1 m2 635,700
9

NO. URAIAN HSP (Rp)

H PEKERJAAN KONSTRUKSI LANGIT-LANGIT/PLAFON DAN PENUTUP


1. Pasang rangka plafon (1,00 x 1,00) m Kayu Kamper Samarinda tiap 1m² 149,150
2. Pasang rangka plafon (1,00 x 1,00) m Kayu Kamper Medan/Kruing tiap 1m² 135,050
3. Pasang rangka plafon (1,00 x 1,00) m Kayu Meranti Palembang tiap 1m² 135,050
4. Pasang rangka plafon (50 x 100) cm Kayu Kamper Samarinda tiap 1m² ( SNI ) 195,600
5. Pasang rangka plafon (50 x 100) cm Kayu Kamper Medan/Kruing tiap 1m² ( SNI ) 163,800
6. Pasang rangka plafon (50 x 100) cm Kayu Meranti Palembang tiap 1m² ( SNI ) 163,800
7. Pasang rangka plafon (60 x 120) cm Kayu Kamper Samarinda tiap 1m² 158,850
8. Pasang rangka plafon (60 x 120) cm Kayu Kamper Medan/Kruing tiap 1m² 143,600
9. Pasang rangka plafon (60 x 120) cm Kayu Meranti Palembang tiap 1m² 143,600
10. Pasang rangka plafon (60 x 60) cm Kayu Kamper Samarinda tiap 1m² 196,650
11. Pasang rangka plafon (60 x 60) cm Kayu Kamper Medan/Kruing tiap 1m² 177,550
12. Pasang rangka plafon (60 x 60) cm Kayu Meranti Palembang tiap 1m² 177,550
13. Pasang rangka plafon (30 x 60) cm Kayu Kamper Samarinda tiap 1m² 235,500
14. Pasang rangka plafon (30 x 60) cm Kayu Kamper Medan/Kruing tiap 1m² 208,600
15. Pasang rangka plafon (30 x 60) cm Kayu Meranti Palembang tiap 1m² 208,600
16. List Plafon kayu profil tiap 1m' 43,950
17. List plafon bahan Kayu Kamper Samarinda papan 1x5 cm tiap 1 m' 33,800
18. List plafon bahan triplek 0,3x5 cm tiap 1 m' 33,050
19. Pasang list profil cornice gypsum lebar sampai 5 cm tiap 1 m' 41,150
20. Pasang list profil cornice gypsum lebar sampai 5-10 cm tiap 1 m' 45,300
21. Pasang list profil cornice gypsum lebar lebih dari 10 cm tiap 1 m' 50,900
22. Penutup plafon asbes (1,00 x 1,00) m tebal 2,7 mm tiap 1m² 46,850
23. Penutup plafon akustik (60 x 120) cm tiap 1m² 130,700
24. Penutup plafon teakwood (60 x 120) cm tebal 3 mm tiap 1m² 81,600
25. Penutup plafon gypsum board 9 mm tiap 1m² 66,459
26. Penutup plafon GRC-board 4 mm tiap 1m² 63,066
27. Penutup plafon Calsiboard 4 mm tiap 1m² 59,850
28. Penutup plafon triplek 4 mm tiap 1m² 58,600
29. Penutup plafon triplek 6 mm tiap 1m² 64,800
30. Penutup plafon asbes (1,00 x 1,00) m tebal 2,7 mm lengkap rangka Kamper Medan/Kruing tiap 1m² 181,850
31. Penutup plafon triplek 4 mm (60 x 120) cm lengkap rangka Kamper Medan/Kruing tiap 1m² 197,150
32. Penutup plafon Gypsumboard 9 mm lengkap dgn rangka hollow tiap (6mx6m) = 36 m² 6,273,300
33. Penutup plafon Gypsumboard 9 mm lengkap dgn rangka hollow tebal 0.3 mm / tiap 1 m² 174,250
34. Penutup plafon Gypsumboard 9 mm lengkap dgn rangka hollow tebal 0.6 mm / tiap 1 m² 189,450
35. Penutup plafon GRC-board 4 mm lengkap dgn rangka hollow tebal 0.6 mm / tiap 1 m² 186,050
37. Penutup plafon Calsiboard 4,5 mm lengkap dgn rangka hollow tebal 0.6 mm / tiap 1 m² 182,850
38. Penutup plafon Calsiboard 6 mm lengkap dgn rangka hollow tebal 0.6 mm / tiap 1 m² 186,450
39. Penutup plafon Akustik ukuran 60x120 cm + rangka alumunium / tiap 1 m² 279,200
40. Plafond Papan (Lambriziring) 10 cm, tebal 1 cm + Rangka Kayu Borneo Super tiap 1 m2 297,150
10

NO. URAIAN HSP (Rp)

I. PEKERJAAN DINDING
1. Pasang rangka dinding pemisah Kayu Kamper Medan/Kruing tiap 1m² ( SNI ) 254,600
2. Pasang rangka dinding pemisah Kayu Meranti Palembang tiap 1m² ( SNI ) 254,600
3. Pasang dinding pemisah teakwood rangkap rangka Kayu Kamper Medan/Kruing tiap 1m² ( SNI ) 390,500
4. Pasang dinding pemisah teakwood rangkap rangka Kayu Meranti Palembang tiap 1m² 427,950
5. Pasang teakwood tebal 3 mm untuk dinding tiap 1m² 73,050
6. Pasang triplek tebal 4 mm untuk dinding tiap 1m² 48,450
7. Pasang triplek tebal 6 mm untuk dinding tiap 1m² 55,050
8. Pasang gypsum tebal 12 mm untuk dinding tiap 1m² 54,300
9. Dinding partisi gypsum 12 mm lkp rk metal Studs 2 muka tiap 1 m² 268,500
10. Dinding partisi gypsum 12 mm lkp rk hollow tiap 1 m² 317,100
11. Dinding partisi double GRC-board 6 mm rk Kamper Medan/Kruing tiap 1 m² 347,050
12. Dinding partisi double GRC-board 6 mm rk hollow tiap 1 m² 300,150
13. Dinding Convering ACP lkp rk hollow tiap 1 m² 838,600

J PEKERJAAN BETON
1. Beton Non Struktur 1Pc : 3Ps : 5Kr - untuk rabatan/ beton tumbuk tiap 1m³ 1,187,550
2. Lantai Kerja Beton 1Pc : 3Ps : 5Kr - untuk beton tumbuk tebal 5 cm 224,600
3. Beton K-125 (1Pc : 3Ps : 4Kr) tiap 1m³ 1,187,550
4. Beton K-175 (1Pc : 2,5Ps : 3,5Kr) tiap 1m³ 1,236,450
5. Beton Struktur K-225 (1Pc : 2Ps : 3Kr) tiap 1m³ 1,372,250
6. Beton Struktur K-275 (1Pc : 1,5Ps : 3Kr) tiap 1m³ 1,573,800
7. Beton Struktur K-350 (1Pc : 1,5Ps : 2,75Kr) tiap 1m³ 1,515,000
8. Beton Struktur K-400 (1Pc : 1,5Ps : 2,5Kr) tiap 1m³ 1,543,300
9. Beton Cyclope 1pc:3ps:5kr tiap 1m³ 1,982,900
10. Pasang pondasi sumuran diameter 100 cm tiap 1 m³ ( SNI ) 1,303,500
11. 1 M' Pembuatan Tiang Pancang Ø 30 cm, Beton Tulang 1,194,800
12. Pasang pondasi tiang pancang Tiap 1 m' 485,750
13. Pembesian dengan besi polos tiap 1 kg 16,700
14. Pembesian dengan besi ulir tiap 1 kg 24,800
15. Pasang bekisting untuk pondasi 1 m² 267,950
16. Pasang bekisting untuk sloof 1 m² 283,500
17. Pasang bekisting untuk sloof 1 m² dengan bahan tripleks 9 mm 279,200
18. Pasang bekisting untuk kolom 1 m² 422,850
19. Pasang bekisting untuk balok 1 m² 465,300
20. Pasang bekisting untuk pelat lantai 1 m² 502,750
21. Pasang bekisting untuk dinding 1 m² 496,400
22. Pasang bekisting untuk tangga 1 m² 418,900
23. Membokar cetakan bekesting tiap 1m³ 616,000
24. Stutwerk untuk 1 m³, tinggi 3 - 4 m (memakai dolken) 3,087,800
11

NO. URAIAN HSP (Rp)

25. Stutwerk untuk 1 m³, tinggi 3 - 4 m (memakai scafolding) 2,210,100


26. Membuat pondasi beton bertulang (150 kg besi + bekisting) tiap 1m³ 5,179,550
27. Membuat pondasi beton bertulang (200 kg besi + bekisting) tiap 1m³ 7,489,550
28. Membuat sloof beton bertulang (160 kg besi + bekisting) tiap 1m³ Gudang/Rumah 6,172,228
29. Membuat sloof beton bertulang (200 kg besi + bekisting) tiap 1m³ Gudang 8,449,228
30. Membuat kolom beton bertulang (150 kg besi + bekisting) tiap 1m³ 7,500,600
31. Membuat kolom beton bertulang (200 kg besi + bekisting) tiap 1m³ 8,942,700
32. Membuat balok beton bertulang (200 kg besi + bekisting) tiap 1m³ 9,477,450
33. Membuat balok beton bertulang (150 kg besi + bekisting) tiap 1m³ 6,038,200
34. Membuat dinding beton bertulang (150 kg besi + bekisting) tiap 1m³ 6,796,000
35. Membuat tangga beton bertulang (200 kg besi + bekisting) tiap 1m³ 7,360,250
36. Membuat beton ring balok dinding (150 kg besi + bekisting) tiap 1m³ 5,179,550
37. Membuat 1 unit pelat pondasi beton bertulang (100 x 100 x 20) cm 1,067,100
38. Membuat sloof beton bertulang (15 x 20) cm tiap 1 m' 172,850
39. Membuat sloof beton bertulang (15 x 30) cm tiap 1 m' 257,100
40. Membuat kolom penguat/praktis beton bertulang tiap 1m' 5,179,550
41. Membuat kolom beton bertulang (11 x 20) cm tiap 1 m' 127,800
42. Membuat kolom beton bertulang (11 x 30) cm tiap 1 m' 222,050
43. Membuat kolom beton bertulang (30 x 30) cm tiap 1 m' 940,800
44. Membuat ring balok beton bertulang (10 x 15) cm tiap 1m' 144,000
45. Membuat pelat lantai beton bertulang tebal 15cm tiap 1 m² 726,200
46. Pekerjaan Plat Lantai Beton tebal 12 cm, tiap 1 m3 6,117,500
47. Pekerjaan Plat Lantai Beton Tebal 15 cm tiap 1 m3 6,051,650
48. Pekerjaan Plat Lantai Beton tebal 12 cm, tiap 1 m3 + bekisting bondek 7,812,500
49. Pekerjaan Plat Meja Beton tebal 8 cm, tiap 1 m3 3,644,350
50. Plat Duiker Pintu Masuk, lebar saluran 0,5 m tiap 1 m' (Tebal plat 10 cm) 1,555,550
51. Plat Duiker Pintu Masuk, lebar saluran 0,75 m tiap 1 m' (Tebal plat 12,5 cm) 841,750
52. Plat Duiker Pintu Masuk, lebar saluran 1 m tiap 1 m' (Tebal plat 15 cm) 1,219,700
53. Pasang Plastik Cor tiap 1m² 6,700

K PEKERJAAN PENUTUP ATAP


1. Pasang atap genteng plentong natural tiap 1m² 89,000
2. Pasang atap genteng plentong besar/super tiap 1m² 83,950
3. Pasang atap genteng kodok tiap 1m² 122,000
4. Pasang atap genteng keramik Kanmuri natural tiap 1m² 130,600
5. Pasang atap genteng keramik Ikad natural tiap 1m² 273,200
6. Pasang atap genteng beton Monier standar tiap 1m² 149,800
7. Pasang atap genteng metal tiap 1m² 122,400
8. Pasang atap asbes gelombang 2,5 x 0,92 m x 5 mm tiap 1m² 74,800
9. Pasang atap asbes gelombang 2,25 x 0,92 m x 5 mm tiap 1m² 84,950
10. Pasang atap asbes gelombang 2,00 x 0,92 m x 5 mm tiap 1m² 71,000
12

NO. URAIAN HSP (Rp)

11. Pasang atap asbes gelombang 1,80 x 0,92 m x 5 mm tiap 1m² 78,400
12. Pasang atap seng gelombang BJLS 25 (0,25 mm) tiap 1m² 162,400
13. Pasang atap spandek tiap 1m² 233,900
14. Pasang atap Fibreglass ukuran 180 X 90 cm tiap 1 m2 56,850
15. Pasang alumunium foil tiap 1m² 48,950
16. Pasang glasswool tiap 1m² 58,550
17. Pasang Nok genteng plentong tiap 1m' 141,500
18. Pasang Nok genteng plentong besar tiap 1m' 142,200
19. Pasang Nok genteng keramik Kanmuri tiap 1m' 161,800
20. Pasang Nok genteng keramik M Class tiap 1m' 367,150
21. Pasang Nok genteng beton tiap 1m' 165,450
22. Pasang nok genteng metal tiap 1m' 113,900
23. Pasang nok/bubung stel gelombang 0,92 m tiap 1m' 136,950
24. Pasang nok paten 0,92 m tiap 1m' 116,500
25. Pasang nok stel rata 0,92 m tiap 1m' 121,650
26. Pasang atap nok seng tiap 1m' 53,750
27. Pasang nok asbes tiap 1m' 70,700
28. Pasang nok spandek standar tiap 1m' 118,050
29. Pasang Flashing tiap 1m' 177,200
30. Pasang atap policarbonat tiap 1 m2 535,600
31. Pasang rangka atap baja ringan zincalum untuk atap metal roof tiap 1 m² 160,700
32. Pas. Rangka hollow tbl. 0.6 mm tiap 1 m² 232,600
33. Pas. Ralling tangga besi hollow tbl. 0.6 mm tiap 1 m² 286,400

L PEKERJAAN SANITASI
1. Memasang 1 buah kloset duduk/monoblok (lux) 4,406,650
2. Memasang 1 buah kloset duduk/monoblok setara INA (sedang) 3,672,900
3. Memasang 1 buah kloset duduk/monoblok 3,540,055
4. Memasang 1 buah kloset jongkok sederhana 785,450
5. Memasang 1 buah kloset jongkok sedang 1,397,600
6. Memasang 1 buah kloset jongkok tdk sederhana 1,267,950
7. Memasang 1 buah urinoir 4,801,450
8. Memasang 1 buah penyekat urinoir 860,950
9. Memasang 1 buah wastafel 1,829,300
10. Memasang 1 buah bak mandi fibreglass volume 0,3 m³ 2,399,250
12. Memasang 1 buah bak mandi batu bata volume 0,3 m³ 2,526,600
13. Memasang 1 buah bak mandi batu bata volume 0,3 m³ (60x60x80 cm) 1,048,950
14. Memasang pipa galvanis dia 1/2" tiap m' 76,100
15. Memasang pipa galvanis dia 3/4" tiap m' 81,450
16. Memasang pipa galvanis dia 1" tiap m' 96,650
17. Memasang pipa galvanis dia 1 ¼" tiap m' 112,850
13

NO. URAIAN HSP (Rp)

18. Memasang pipa galvanis dia 1 ½" tiap m' 155,000


19. Memasang pipa galvanis dia 2" tiap m' 191,250
20. Memasang pipa galvanis dia 2 ½" tiap m' 232,150
21. Memasang pipa galvanis dia 3" tiap m' 520,650
22. Memasang pipa galvanis dia 4" tiap m' 561,200
23. Memasang pipa PVC tipe AW dia 1/2" tiap m' 28,150
24. Memasang pipa PVC tipe AW dia 3/4" tiap m' 37,600
25. Memasang pipa PVC tipe AW dia 1" tiap m' 57,100
26. Memasang pipa PVC tipe AW dia 1 ¼" tiap m' 69,250
27. Memasang pipa PVC tipe D dia 1 ¼" tiap m' 67,950
28. Memasang pipa PVC tipe AW dia 1 ½" tiap m' 76,350
29. Memasang pipa PVC tipe D dia 1 ½" tiap m' 76,000
30. Memasang pipa PVC tipe AW dia 2" tiap m' 98,000
31. Memasang pipa PVC tipe D dia 2" tiap m' 96,150
32. Memasang pipa PVC tipe AW dia 2 ½" tiap m' 113,150
33. Memasang pipa PVC tipe D dia 2 ½" tiap m' 111,300
34. Memasang pipa PVC tipe AW dia 3" cm tiap m' 150,800
35. Memasang pipa PVC tipe D dia 3" cm tiap m' 149,600
36. Memasang pipa PVC tipe AW dia 4" tiap m' 184,750
37. Memasang pipa PVC tipe D dia 4" tiap m' 180,800
38. Memasang pipa PVC tipe AW dia 6" tiap m' 198,600
39. Memasang pipa PVC tipe D dia 6" tiap m' 194,150
40. Memasang 1 buah bak cuci piring stainless steel 1,665,000
41. Memasang 1 buah kran dia 3/4" atau 1/2" sederhana 52,500
42. Memasang 1 buah kran dia 3/4" atau 1/2" stainless 81,350
43. Memasang 1 buah kran leher angsa stainless 327,200
44. Memasang 1 buah kran bebek stainless 341,750
45. Memasang 1 buah tempat sabun 220,400
52. Memasang 1 floor drain sederhana 71,600
53. Memasang 1 floor drain stainless 384,650
54. Membuat 1 unit sumur air tanah bor manual dalam 12 m' + pompa air listrik 4,146,650
55. Membuat 1 unit tanki septik sederhana kapasitas Ø 1,2 m dalam 1,2 m 2,608,600
56. Membuat 1 unit tanki septik kapasitas 1,7x0,85 m dalam 1,3 m (vol. 1,88 m³ u/ 5 pemakai) 4,481,200
57. Membuat tanki septik kapasitas tiap 1 m³ 2,388,600
58. Membuat 1 unit resapan Ø 0,8 m (digali 1 m) dalam 1 m (digali 1,9 m) kap. 0,5 m³ 800,600
59. Memasang 1 Doop 1" 1 bh 1,100

M PEKERJAAN BESI DAN ALUMINIUM


1. Pasang Besi Profil tiap kg 37,200
2. Pasang Rangka Atap Baja tiap kg 39,650
3. Kuda-kuda baja dengan WF / kg 37,500
14

NO. URAIAN HSP (Rp)

4. Kuda-kuda baja dengan siku / kg 29,400


5. Gording baja CNP / Kg 34,155
6. Pengelasan Las Listrik setiap 1 cm 3,950
7. Pasang pintu besi plat baja tebal 2 mm rangkap, rangka baja siku / tiap m² 870,350
8. Pasang rangka jendela besi Scuare Tube (25x5) cm / tiap m² 240,550
9. Pasang pintu lipat tiap m² (Folding Door) 1,065,200
10. Pasang rolling door tiap m² 769,350
11. Pasang kusen pintu aluminium tiap m' 164,750
12. Pasang kusen pintu aluminium powder coating tiap m' 174,650
13. Memasang 1 m² pintu/jendela/BV kaca, rangka allumunium kaca 8 mm 843,000
14. Memasang 1 m² pintu/jendela/BV kaca, rangka allumunium kaca 5 mm 836,150
15. Memasang 1 m² pintu/jendela/BV kaca, rangka allumunium kaca 10 mm 1,247,700
16. Pasang terali besi tiap m² 809,900
17. Pasang jendela nako dan teralis tiap m² 287,000
18. Pasang talang datar, seng BJLS 28 (0,28 mm) tiap 1 m' 229,350
19. Pasang talang miring, seng BJLS 28 (0,28 mm) tiap 1 m' 260,550
20. Pasang talang 1/2 lingkaran D-15 cm, seng BJLS 30 / tiap 1 m' 115,200
21. Pasang pipa jemuran, rangka besi galvanis / tiap m1 99,450
22. Pasang kawat jemuran, galvanis / tiap m1 18,900
23. Pasang besi weirmes / tiap m2 Ø 8 mm single mest 102,280
24. Pas. Grill besi lebar 20 cm tiap 1 m¹ 87,300
25. Pasang pipa besi penahan ban / set 1,205,800
26. Pasang besi expended tiap 1m² 296,800

N PEKERJAAN KUNCI DAN KACA


1. Pasang 1 buah kunci tanam antik 424,600
2. Pasang 1 buah kunci tanam sederhana 210,200
3. Pasang 1 buah kunci tanam biasa 269,850
4. Pasang 1 buah kunci tanam KM 183,300
5. Pasang 1 buah kunci silinder Pintu Aluminium 213,250
6. Pasang 1 buah kunci lemari 140,800
7. Pasang kunci gembok tiap 1 buah 111,400
8. Pasang 1 buah engsel pintu biasa/sederhana 46,450
9. Pasang 1 buah engsel pintu kuningan/stainless 66,950
10. Pasang 1 buah engsel jendela kuningan/stainless 57,950
11. Pasang 1 buah engsel angin 65,650
12. Pasang 1 buah spring knip 59,300
13. Pasang 1 buah kait angin 55,750
14. Pasang 1 buah door closer 394,950
15. Pasang 1 buah kunci selot 143,450
16. Pasang 1 buah grendel 84,600
15

NO. URAIAN HSP (Rp)

17. Pasang 1 buah window casement 159,650


18. Pasang 1 buah rambuncis 79,100
19. Pasang 1 buah pegangan pintu/door holder 159,500
20. Pasang 1 buah door stop 64,700
21. Pasang 1 buah rel pintu dorong 282,150
22. Pasang kaca es tebal 3 mm tiap 1 m² 111,000
23. Pasang kaca tebal 5 mm tiap 1 m² 357,400
24. Pasang kaca es tebal 5 mm tiap 1 m² 200,050
25. Pasang kaca rayben tebal 5 mm tiap 1 m² 391,800
26. Pasang kaca tebal 8 mm tiap 1 m² 367,750
27. Pasang kaca rayben tebal 8 mm tiap 1 m² 381,750
28. Pasang kaca rayben tebal 10 mm tiap 1 m² 736,900
29. Pasang kaca rayben tebal 12 mm tiap 1 m² 1,401,350
30. Pasang kaca cermin tebal 5 mm tiap 1m² 230,000
31. Pasang kaca patri tebal 5 mm tiap 1 m² 1,181,500

O PEKERJAAN PENUTUP LANTAI DAN DINDING


1. Pasang lantai Granito ukuran 60 x 60 cm tiap 1m² 295,452
2. Pasang lantai keramik ukuran 40 x 40 cm Roman tiap 1m² 220,600
3. Pasang lantai keramik ukuran 40 x 40 cm setara mulia tiap 1m² 173,400
4. Pasang lantai Granito ukuran 30 x 30 cm tiap 1m² 578,850
5. Pasang lantai keramik ukuran 30 x 30 cm Roman tiap 1m² 215,050
6. Pasang lantai keramik ukuran 30 x 30 cm setara mulia tiap 1m² 164,250
7. Pasang lantai keramik ukuran 20 x 20 cm Roman tiap 1m² 219,850
8. Pasang lantai keramik ukuran 20 x 20 cm setara mulia tiap 1m² 198,250
9. Pasang lantai keramik ukuran 10 x 20 cm Roman tiap 1 m² 241,550
10. Pasang lantai keramik ukuran 10 x 20 cm setara mulia tiap 1 m² 133,650
11. Pasang lantai marmer tiap 1m² (100x100) cm 345,850
12. Pasang lantai parquet jati tiap 1m² 458,700
13. Pasang lantai vinyl karet kl 1 tiap 1m² 133,650
14. Pasang Floor Hardener tiap 1m² 70,650
15. Pasang dinding marmer tiap 1m² 418,350
16. Pasang dinding keramik 20 x 20 cm Roman tiap 1m² 254,950
17. Pasang dinding keramik 20 x 20 cm setara mulia tiap 1m² 226,100
18. Pasang dinding keramik 20 x 25 cm Roman tiap 1m² 263,800
19. Pasang dinding keramik 20 x 25 cm setara mulia tiap 1m² 228,150
20. Pasang dinding batu tempel tiap m2 372,450
21. Pasang dinding batu tempel palimanan tiap 1m² 372,450
22. Pasang plint ubin marmer ukuran 10 x 60 cm tiap 1m' 74,600
23. Pasang plint ubin marmer ukuran 10 x 40 cm tiap 1m' 53,100
24. Pasang plint ubin marmer ukuran 10 x 30 cm tiap 1m' 48,200
16

NO. URAIAN HSP (Rp)

25. Pasang plint granito tile ukuran 10 x 40 cm / tiap 1m' 99,750


26. Pasang plint granito tile ukuran 10 x 30 cm / tiap 1m' 51,850
27. Pasang plint keramik ukuran 10 x 40 cm Roman tiap 1m' 52,100
28. Pasang plint keramik ukuran 10 x 30 cm Roman tiap 1m' 48,200
29. Pasang plint keramik ukuran 10 x 20 cm Roman tiap 1m' 49,850
30. Pasang plint keramik (list) ukuran 5 x 20 cm Roman tiap 1m' 42,350
31. Pasang plint keramik (list) ukuran 5 x 20 cm setara mulia tiap 1m' 38,650
32. Pasang keramik stepnosing 5/30 tiap 1 m' 70,200
33. Pasang plint vinyil 1m² 51,500
34. Pasang plint kayu 2 x 10 cm tiap 1m' 129,450

P PEKERJAAN PENGECATAN

1. Mendempul dan menggosok 1 m² 11,750


2. Pengecatan dengan cat KW 2 bidang kayu lama 1 m² 58,700
3. Pengecatan dengan cat Mowilex bidang kayu lama 1 m² 66,850
4. Pengecatan bidang kayu baru dg plamir 1 m² + 1 lps dsr + 2 lps penutup KW 2 70,850
5. Pengecatan bidang kayu baru dg plamir 1 m² + 1 lps dsr + 2 lps penutup Mowilex 80,500
6. Pengecatan bidang kayu baru dg plamir 1 m² + 1 lps dsr + 3 lps penutup KW 2 80,900
7. Pengecatan bidang kayu baru dg plamir 1 m² + 1 lps dsr + 3 lps penutup Mowilex 92,050
8. Pelaburan bidang kayu dgn politur 1 m² 75,200
9. Pengecatan bidang kayu dengan politur Ultran tiap 1 m² 132,200
10. Pengecatan bidang kayu dengan melamik Impra tiap 1 m² 236,300
11. Pengecatan kusen kayu dengan melamik Impra tiap 1 m' 121,000
12. Pelaburan bidang kayu dgn residu dan ter 1 m² 24,550
13. Pelaburan bidang kayu dgn vernis 1 m² 71,650
14. Pengecatan tembok baru dg plamir 1 m² + 1 lps dsr + 2 lps penutup KW 2 44,200
15. Pengecatan tembok baru dg plamir 1 m² + 1 lps dsr + 2 lps 31,050
16. Pengecatan tembok baru dg wall sealer 1 m² + 1 lps dsr + 2 lps 35,100
17. Pengecatan tembok baru dg wall sealer 1 m² + 1 lps dsr + 2 lps jotun 53,150
18. Pengecatan bidang tembok lama 1 m² dg 1 lps dsr + 2 lps penutup KW 2 26,100
19. Pengecatan bidang tembok lama 1 m² dg 1 lps dsr + 2 lps 24,600
20. Pengecatan bidang tembok lama 1 m² dg 1 lps dsr + 2 lps 31,200
21. Memasang wallpaper 1 m² 127,600
22. Mengecat genteng 1 m² ( renovasi ) 30,000
23. Pengecatan permukaan baja 1 m² dgn meni besi 46,750
24. Pengecatan permukaan baja 1 m² dgn meni besi & perancah 94,600
25. Pengecatan permukaan baja tiap 1 m² dengan zinchromate 50,700
26. Pengecatan permukaan baja tiap 1 m² dengan Cat KW 2 58,800
27. Pengecatan permukaan baja tiap 1 m² dengan Cat Mowilex 68,450
28. Pekerjaan cat duko 3x tiap 1 m² 114,200
17

NO. URAIAN HSP (Rp)

29. Pengecatan waterproofing (coating) tiap 1 m² 30,500


30. Pengecatan permukaan kayu 1 m² dgn meni 51,450
31. Waterproofing membrane 1 m2 191,100

Q PEKERJAAN BONGKARAN
1. Bongkar beton bertulang tiap 1m³ 1,094,450
2. Bongkar dinding tembok bata merah tiap 1m³ 109,400
3. Bongkar dinding ½ bata tiap 1m² 11,950
4. Bongkar pelat beton bertulang tiap 1m² 131,300
5. Bongkar batu kali tebal < 50 cm tiap 1 m³ 246,250
6. Bongkar batu kali tebal > 50 cm tiap 1 m³ 492,500
7. Bongkar lantai tiap 1 m² 8,700
8. Bongkar paving block tiap 1 m² 8,700
9. Bongkar plesteran tiap 1 m² 8,200
10. Bongkar atap genteng tiap 1 m² 5,100
11. Bongkar karpusan atap genteng tiap 1 m' 7,650
12. Bongkar atap seng/asbes tiap 1 m² 12,100
13. Bongkar kaso dan reng kayu (kayu akan dipakai lagi) tiap 1 m² 21,300
14. Bongkar kaso dan reng kayu (kayu tidak akan dipakai lagi) tiap 1 m² 16,400
15. Bongkar balok kuda-kuda & loteng (kayu akan dipakai lagi) tiap 1 m³ 1,220,800
16. Bongkar balok kuda-kuda & loteng (kayu tidak akan dipakai lagi) tiap 1 m³ 783,200
17. Bongkar rangka plafon tiap 1 m² 16,400
18. Bongkar penutup plafon tiap 1 m² 5,850

R PEKERJAAN INSTALASI LISTRIK


1. Pasang instalasi lampu dg NYM 3x2,5 mm² tiap 1 titik (tidak termasuk fitting, sakelar & lampu) 355,750
2. Pasang instalasi lampu dg NYM 2x2,5 mm² tiap 1 titik (tidak termasuk fitting, sakelar & lampu) 354,500
3. Pasang instalasi lampu dg NYM 2x1,5 mm² tiap 1 titik (tidak termasuk fitting, sakelar & lampu) 354,600
4. Pasang instalasi lampu untuk gedung pertemuan & gudang tiap 1 titik (tidak termasuk fitting, sakelar & l 780,050
5. Pasang instalasi stop kontak tiap 1 titik (tidak termasuk stop kontak) 354,100
6. Pasang instalasi stop kontak lebih dari 500 watt tiap 1 titik (tidak termasuk stop kontak) 900,350
7. Pasang instalasi listrik + outlet AC tiap 1 titik (tidak termasuk AC) 491,600
8. Pasang instalasi + tiang antena TV tiap 1 titik (tidak termasuk socket & antena) 521,850
9. Pasang instalasi telepon tiap 1 titik (tidak termasuk outlet, pesawat telepon & sambungan Telkom) 399,050
10. Pasang instalasi telepon paralel/extension line tiap 1 titik (tidak termasuk outlet, pesawat telepon) 259,600
11. Pasang Panel Pembagi Daya 1300 VA / 6 A (3 grup @ 6 A) tiap 1 unit 1,815,850
12. Pasang Panel Pembagi Daya 2200 VA / 10 A (3 grup @ 10 A) tiap 1 unit 1,852,150
13. Pasang pentanahan (grounding) tiap 1 titik 165,200
14. Pasang 1 buah lampu SL 73,800
15. Pasang 1 buah lampu TL 1x18 RM 270,100
16. Pasang 1 buah lampu TL 2x18 RM 507,250
18

NO. URAIAN HSP (Rp)

17. Pasang 1 buah lampu TL 2x36 RM 588,500


18. Pasang 1 buah lampu TL 1x18 Balk 94,100
19. Pasang 1 buah lampu TL 2x18 Balk 155,200
20. Pasang 1 buah lampu TL 2x36 Balk 261,650
21. Pasang 1 buah lampu baret 116,850
22. Pasang 1 buah lampu pijar 43,300
23. Pasang 1 buah lampu LED 418,000
24. Pasang 1 buah saklar tunggal 129,550
25. Pasang 1 buah saklar ganda 147,200
26. Pasang 1 buah stop kontak 146,200
27. Pasang 1 buah Exhaust Fan 477,400
28. Pekerjaan Pasangan Panel 3 Phase 19,267,100
29. Pas. Penangkal petir + instalasi + acesories 1 titik 25,619,250
30. Pas. Panel ATS/Genset 27,517,100
31. Pekerjaan Intalasi Panel + Cable Try 512,100
32. Pekerjaan Vetilator cyclone 1,615,050

S PEKERJAAN PRASARANA LINGKUNGAN - DRAINASE


1. Memasang pipa beton, dia 15-20 cm tiap m' 185,000
2. Memasang pipa beton, dia 30 cm tiap m' 520,900
3. Memasang pipa beton, dia 40 cm tiap m' 585,850
4. Memasang pipa beton, dia 50 cm tiap m' 661,450
5. Memasang pipa beton, dia 60 cm tiap m' 763,950
6. Memasang pipa beton, dia 80 cm tiap m' 1,132,100
7. Memasang pipa beton, dia 100 cm tiap m' 1,303,800
8. Memasang 1 buah bak kontrol pas.batu bata 30 x 30 cm tinggi 35 cm 704,600
9. Memasang 1 buah bak kontrol pas.batu bata 45 x 45 cm tinggi 50 cm 625,300
10. Memasang 1 buah bak kontrol pas.batu bata 60 x 60 cm tinggi 65 cm 968,050
11. Membuat saluran dinding bata dalam 15-20 cm tiap 1 m' 176,100
12. Membuat saluran air buis beton ½ Ø 30 cm dinding bata dalam 30-45 cm tiap 1 m' 346,750
13. Membuat saluran air dari batu kali lebar bawah 30 cm tinggi 60 cm tiap 1 m' 668,500
14. Membuat saluran air dari batu kali lebar bawah 60 cm tinggi 80 cm tiap 1 m' 998,750
15. Membuat saluran air dari batu kali lebar bawah 80 cm tinggi 100 cm tiap 1 m' 1,441,350
16. Membuat saluran air dari batu kali lebar bawah 100 cm tinggi 120 cm tiap 1 m' 1,881,050
17. Membuat saluran air dari U-dit 200.200.120 tiap 1 m' 8,786,650

T PEKERJAAN PRASARANA LINGKUNGAN - PAGAR


1. Pasang pagar beton pracetak tinggi 1,6 m tiap 1 m' 441,600
2. Pasang pagar beton pracetak tinggi 2 m tiap 1 m' 502,800
3. Membuat pagar dinding tinggi 2 m bata merah + plesteran + cat tembok tiap 1 m' 1,544,400
4. Membuat pagar dinding tinggi 3 m bata merah + plesteran + cat tembok tiap 1 m' 1,957,450
19

NO. URAIAN HSP (Rp)

5. Membuat pagar dinding tinggi 2 m bata hollow ekspos + kolom/ringbalk diplester & dicat tiap 1 m' 1,275,350
6. Membuat pagar dinding tinggi 1,5 m bata hollow ekspos + kolom/ringbalk diplester & dicat tiap 1 m' 955,700
7. Membuat pagar BRC 1,2 m tinggi jadi 1,5 m (pondasi batu kali + sloof 15/20 + ½ bata 30 cm + plester + ca 1,133,000
8. Membuat pagar BRC 0,9 m tinggi jadi 1,2 m (pondasi batu kali + sloof 15/20 + ½ bata 30 cm + plester + ca 819,250

U PEKERJAAN PRASARANA LINGKUNGAN - JALAN, LAPANGAN PARKIR, LAPANGAN UPACARA/APEL


1. Galian dengan excavator (skala besar) tiap 1m³ 157,100
2. Galian dengan tenaga manusia tiap 1m³ 200,050
3. Urugan tanah merah dipadatkan alat berat tiap 1m³ 173,400
4. Penyiapan badan jalan / tanah dasar (Subgrade) tiap 1m² 7,050
5. Urugan sirtu (agregat kelas C) dipadatkan tiap 1m³ 602,000
6. Lapis Pondasi Bawah (LPB / Subbase Course) Kelas C Sirtu tebal 10 cm tiap 1m² 60,950
7. Lapis Pondasi Jalan Tanpa Penutup Aspal jenis Waterbound Macadam tiap 1m³ 683,550
8. Lapis Pondasi Atas (LPA / Base Course) Agregat Kelas A tiap 1m³ 631,550
9. Lapis Resap Ikat (Prime Coat) tiap 1 Liter 29,050
10. Lapis Perekat (Tack Coat) tiap 1 Liter 31,600
( untuk per M2 dibutuhkan 2 Liter lapis perekat ) 63,200
11. Aspal untuk Pelaburan tiap 1 Liter 31,250
12. Lapisan Penetrasi (LAPEN) / Lapisan Permukaan (Surface Course) Macadam tebal 5 cm tiap 1m² 199,450
13. Lapisan Tipis Aspal Beton (LATASTON / HRS-Hot Rolled Sheet) tebal 3 cm tiap 1m² 189,750
14. Lapisan Permukaan Aspal Beton (LASTON / AC-Asphalt Concrete) tebal 5 cm tiap 1m² 293,700
15. Pembuatan jalan aspal biasa (Sirtu t=10 cm, Agregat Kelas A t=20 cm, Permukaan Macadam t=5 cm) tia 393,800
16. Pembuatan jalan aspal biasa lebar 3 m' tiap 1 m' 1,181,400
17. Pembuatan jalan aspal biasa lebar 4 m' tiap 1 m' 1,575,200
18. Pembuatan jalan aspal biasa lebar 5 m' tiap 1 m' 1,969,000
19. Pembuatan jalan aspal biasa lebar 6 m' tiap 1 m' 2,362,800
20. Pembuatan jalan aspal biasa lebar 8 m' tiap 1 m' 3,150,400
21. Pembuatan jalan aspal beton t=3 cm (Sirtu = 10 cm, Agregat Kelas A t=20 cm, LATASTON HRS-WC = 3 407,400
22. Pembuatan jalan aspal beton t=3 cm lebar 3 m' tiap 1 m' 1,222,200
23. Pembuatan jalan aspal beton t=3 cm lebar 4 m' tiap 1 m' 1,629,600
24. Pembuatan jalan aspal beton t=3 cm lebar 5 m' tiap 1 m' 2,037,000
25. Pembuatan jalan aspal beton t=3 cm lebar 6 m' tiap 1 m' 2,444,400
26. Pembuatan jalan aspal beton t=3 cm lebar 8 m' tiap 1 m' 3,259,200
27. Pembuatan jalan aspal beton t=5 cm (Sirtu = 10 cm, Agregat Kelas A t=20 cm, LASTON AC-WC = 5 cm) 511,350
28. Pembuatan jalan aspal beton t=5 cm lebar 3 m' tiap 1 m' 1,534,050
29. Pembuatan jalan aspal beton t=5 cm lebar 4 m' tiap 1 m' 2,045,400
30. Pembuatan jalan aspal beton t=5 cm lebar 5 m' tiap 1 m' 2,556,750
31. Pembuatan jalan aspal beton t=5 cm lebar 6 m' tiap 1 m' 3,068,100
32. Pembuatan jalan aspal beton t=5 cm lebar 8 m' tiap 1 m' 4,090,800
33. Pekerjaan paving parkir kendaraan (warna abu T-16 uk. 8x10,5x21) + urugan sirtu 20 cm + urugan pasir 248,600
35. Pekerjaan paving jalan setapak (warna abu T-16 uk. 8x10,5x21) + urugan sirtu 10 cm + urugan pasir 5 c 170,050
20

NO. URAIAN HSP (Rp)

36. Pekerjaan kanstin tiap 1 m' 201,300


37. Pasang grassblock tebal 10 cm tiap 1 1m² 243,650
38. Gebalan rumput tiap 1m² 89,750
39. Pas. Pagar besi hollow tbl. 0.6 mm tiap 1 m² 603,700

V PEKERJAAN ANALISA TAMBAHAN


1. Foto Dokumentasi 258,500
2. Listrik Kerja (Sewa Genset) 3,074,150
3. Listrik Kerja dengan penyambungan daya sementara utk ± 5 bln 10,161,250
4. Memasang 1 buah pompa sumur listrik 2,152,550
5. Air Kerja dalam unit 4,350,650
6. Pemasangan AC Split 548,200
7 Beton Ready Mix K.350 / m3 1,676,150
8 Beton Ready Mix K.300 / m3 1,638,200
9 Beton Ready Mix K.275 / m3 1,625,550
10 Beton Ready Mix K.250 / m3 1,587,600
11 Beton Ready Mix K.225 / m3 1,509,500
21

URAIAN ANALISIS HARGA SATUAN PEKERJAAN (UNIT PRICE)


BANGUNAN GEDUNG, PERUMAHAN DAN PRASARANA
WILAYAH PALEMBANG TA. 2020

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

A PEKERJAAN PENDAHULUAN
1. Pagar sementara dari seng gelombang tinggi 2 meter tiap 1 m'
Harga bahan:
- Kayu dolken Ø 8-10/400 cm btg 1.25 11,878 14,847.50
- Semen portland kg 2.5 1,300 3,250.00
- Pasir beton m³ 0.005 178,164 890.82
- Batu pecah/split 2/3 m³ 0.009 475,000 4,275.00
- Kayu Meranti Palembang kaso m³ 0.072 4,500,000 324,000.00
- Paku biasa 2"-5" kg 0.06 19,286 1,157.16
- Seng gelombang 3x6 ft BJLS 20 (0,2 mm) Lbr 1.2 198,744 238,492.80
- Cat meni besi kg 0.45 14,200 6,390.00
Jumlah Harga Bahan 593,303.28
Upah tenaga:
- Tukang kayu Oh 0.2 160,000 32,000.00
- Pekerja Oh 0.4 140,000 56,000.00
- Kepala tukang Oh 0.02 180,000 3,600.00
- Mandor Oh 0.02 185,000 3,700.00
Jumlah Upah Tenaga 95,300.00
Jumlah Total 688,603.28
Jumlah Total + jasa 10% 757,450
2. Pagar sementara dari kawat duri tinggi 1,8 meter tiap 1 m'
Harga bahan:
- Kayu dolken Ø 8-10/400 cm btg 1 11,878 11,878.00
- Semen portland kg 2 1,300 2,600.00
- Pasir beton m³ 0.005 178,164 890.82
- Batu pecah/split 2/3 m³ 0.009 475,000 4,275.00
- Paku biasa 2"-5" kg 0.06 19,286 1,157.16
- Kawat duri (10kg/60m/rol) kg 2.5 8,350 20,875.00
Jumlah Harga Bahan 41,675.98
Upah tenaga:
- Tukang kayu Oh 0.2 160,000 32,000.00
- Pekerja Oh 0.3 140,000 42,000.00
- Kepala tukang Oh 0.02 180,000 3,600.00
- Mandor Oh 0.02 185,000 3,700.00
22

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Upah Tenaga 81,300.00


Jumlah Total 122,975.98
Jumlah Total + jasa 10% 135,250
3. Pembuatan kantor sementara, dengan lantai plesteran tiap 1 m²
Harga bahan:
- Kayu dolken Ø 8-10/400 cm btg 1.25 11,878 14,847.50
- Kayu Meranti Palembang kaso m³ 0.18 4,500,000 810,000.00
- Paku biasa 2"-5" kg 0.85 19,286 16,393.10
- Besi pelat strip kg 1.1 16,111 17,722.10
- Semen portland kg 35 1,300 45,500.00
- Pasir pasang m³ 0.15 178,164 26,724.60
- Pasir beton m³ 0.1 178,164 17,816.40
- Batu pecah/split 2/3 m³ 0.15 475,000 71,250.00
- Bata merah bh 30 660 19,800.00
- Seng gelombang 3x6 ft BJLS 20 (0,2 mm) Lbr 0.25 198,744 49,686.00
- Jendela nako (rangka) daun 2 23,580 47,160.00
- Kaca 3 mm m² 0.08 182,515 14,601.20
- Kunci tanam sederhana bh 0.15 107,839 16,175.85
- Teakwood 4x8 ft 3 mm lbr 0.06 120,983 7,258.98
Jumlah Harga Bahan 1,174,935.73
Upah tenaga:
- Tukang kayu Oh 2 160,000 320,000.00
- Tukang batu Oh 1 160,000 160,000.00
- Pekerja Oh 1 140,000 140,000.00
- Kepala tukang Oh 0.3 180,000 54,000.00
- Mandor Oh 0.05 185,000 9,250.00
Jumlah Upah Tenaga 683,250.00
Jumlah Total 1,858,185.73
Jumlah Total + jasa 10% 2,044,000
4. Pembuatan kantor sementara dengan lantai plesteran + meja & bangku kayu tiap 1 m²
Harga bahan:
- Semen portland kg 20 1,300 26,000.00
- Pasir beton m³ 0.04 178,164 7,126.56
- Batu pecah/split 2/3 m³ 0.0666 475,000 31,635.00
- Kayu Meranti Palembang kaso m³ 0.0479 4,500,000 215,550.00
- Paku biasa 2"-5" kg 0.27 19,286 5,207.22
- Paku biasa 1/2"- 1" kg 0.079 19,286 1,523.59
- Triplek 4x8 ft 4 mm lbr 1.189 65,000 77,285.00
- Seng gelombang 3x6 ft BJLS 20 (0,2 mm) Lbr 1.158 198,744 230,145.55
- Jendela nako (rangka) daun 0.541 23,580 12,756.78
- Besi segi empat 3/8"x3/8" (0,83kg/m') kg 0.269 7,100 1,909.90
- Kaca 5 mm m² 0.049 269,069 13,184.38
- Engsel pintu biasa/sederhana set 0.078 13,289 1,036.54
- Kunci tanam sederhana bh 0.078 107,839 8,411.44
Harga bahan untuk meja & kursi sederhana:
- Triplek 4x8 ft 6 mm lbr 0.051 80,000 4,080.00
- Kayu Meranti Palembang kaso m³ 0.01 4,500,000 45,000.00
23

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Kayu Meranti Palembang papan m³ 0.004 4,500,000 18,000.00


- Paku biasa 2"-5" kg 0.074 19,286 1,427.16
- Paku biasa 1/2"- 1" kg 0.007 19,286 135.00
Jumlah Harga Bahan 700,414.14
Upah tenaga:
- Pekerja Oh 0.931 140,000 130,340.00
- Tukang kayu Oh 1.319 160,000 211,040.00
- Tukang batu Oh 0.022 160,000 3,520.00
- Kepala tukang Oh 0.135 180,000 24,300.00
- Mandor Oh 0.04 185,000 7,400.00
Jumlah Upah Tenaga 376,600.00
Jumlah Total 1,077,014.14
Jumlah Total + jasa 10% 1,184,700
5. Pembuatan gudang semen dan peralatan tiap 1 m²
Harga bahan:
- Kayu dolken Ø 8-10/400 cm btg 1.7 11,878 20,192.60
- Kayu Meranti Palembang kaso m³ 0.21 4,500,000 945,000.00
- Paku biasa 2"-5" kg 0.3 19,286 5,785.80
- Semen portland kg 10.5 1,300 13,650.00
- Pasir beton m³ 0.03 178,164 5,344.92
- Batu pecah/split 2/3 m³ 0.05 475,000 23,750.00
- Seng gelombang 3x6 ft BJLS 20 (0,2 mm) Lbr 1.5 198,744 298,116.00
Jumlah Harga Bahan 1,311,839.32
Upah tenaga:
- Tukang kayu Oh 2 160,000 320,000.00
- Pekerja Oh 1 140,000 140,000.00
- Kepala tukang Oh 0.2 180,000 36,000.00
- Mandor Oh 0.05 185,000 9,250.00
Jumlah Upah Tenaga 505,250.00
Jumlah Total 1,817,089.32
Jumlah Total + jasa 10% 1,998,750
6. Pembuatan jalan sementara tebal 20 cm tiap 1 m²
Harga bahan:
- Batu belah 15/20 m³ 0.15 385,000 57,750.00
- Batu pecah 5/7 m³ 0.09 475,000 42,750.00
- Pasir pasang m³ 0.01 178,164 1,781.64
Jumlah Harga Bahan 102,281.64
Upah tenaga:
- Pekerja Oh 1 140,000 140,000.00
- Mandor Oh 0.05 185,000 9,250.00
Jumlah Upah Tenaga 149,250.00
Jumlah Total 251,531.64
Jumlah Total + jasa 10% 276,650
7. Pembuatan jalan sementara tebal 25 cm tiap 1 m²
Harga bahan:
- Batu belah 15/20 m³ 0.275 385,000 105,875.00
- Batu pecah/split 3/5 m³ 0.03 475,000 14,250.00
24

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Pasir pasang m³ 0.05 178,164 8,908.20


Jumlah Harga Bahan 129,033.20
Upah tenaga:
- Pekerja Oh 1 140,000 140,000.00
- Mandor Oh 0.1 185,000 18,500.00
Jumlah Upah Tenaga 158,500.00
Jumlah Total 287,533.20
Jumlah Total + jasa 10% 316,250
8. Pasang bouwplank tiap 1 m'
Harga bahan:
- Kayu Terentang balok m³ 0.007 2,826,516 19,785.61
- Kayu Terentang kaso m³ 0.012 2,826,516 33,918.19
- Paku biasa 2"-5" kg 0.02 19,286 385.72
Jumlah Harga Bahan 54,089.52
Upah tenaga:
- Tukang kayu Oh 0.1 160,000 16,000.00
- Pekerja Oh 0.1 140,000 14,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 32,725.00
Jumlah Total 86,814.52
Jumlah Total + jasa 10% 95,450
9 Membersihkan puing-puing tiap 1 m2
- Pekerja Oh 0.2 140,000 28,000.00
Jumlah Upah Tenaga 28,000.00
Jumlah Total + jasa 10% 30,800

10 Pengukuran dengan alat ukur ( theodolite) tiap 1 m2


- Alat ukur ( theodolite ) m2 1 5,000 5,000.00
Jumlah Upah Tenaga 5,000.00
Jumlah Total + jasa 10% 5,500

B PEKERJAAN TANAH

1. Pembersihan lapangan dan perataan tiap 1 m²


Upah tenaga:
- Pekerja Oh 0.1 140,000 14,000.00
- Mandor Oh 0.05 185,000 9,250.00 0.005
Jumlah Upah Tenaga 23,250.00
Jumlah Total 23,250.00
Jumlah Total + jasa 10% 25,550
2. Pekerjaan stripping setinggi 1 meter (pembersihan lahan skala besar) tiap 1 m² ( SNI )
Upah tenaga:
- Pekerja Oh 0.05 140,000 7,000.00
25

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Mandor Oh 0.005 185,000 925.00


Jumlah Upah Tenaga 7,925.00
Jumlah Total 7,925.00
Jumlah Total + jasa 10% 8,700
3. Galian tanah biasa sedalam 0,9 meter tiap 1 m³
Upah tenaga:
- Pekerja Oh 0.675 140,000 94,500.00
- Mandor Oh 0.0225 185,000 4,162.50
Jumlah Upah Tenaga 98,662.50
Jumlah Total 98,662.50
Jumlah Total + jasa 10% 108,500
4. Galian tanah biasa sedalam 1 meter tiap 1 m³ ( SNI )
Upah tenaga:
- Pekerja Oh 0.75 140,000 105,000.00
- Mandor Oh 0.025 185,000 4,625.00
Jumlah Upah Tenaga 109,625.00
Jumlah Total 109,625.00
Jumlah Total + jasa 10% 120,550
4. Galian tanah biasa sedalam 1 meter tiap 1 m³ ( SNI )
Upah tenaga:
- Pekerja Oh 0.75 140,000 105,000.00
- Mandor Oh 0.025 185,000 4,625.00
Jumlah Upah Tenaga 109,625.00
Jumlah Total 109,625.00
Jumlah Total + jasa 10% 120,550
5. Galian tanah biasa sedalam 2 meter tiap 1 m³ ( SNI )
Upah tenaga:
- Pekerja Oh 0.9 140,000 126,000.00
- Mandor Oh 0.045 185,000 8,325.00
Jumlah Upah Tenaga 134,325.00
Jumlah Total 134,325.00
Jumlah Total + jasa 10% 147,750
6. Galian tanah biasa sedalam 3 meter tiap 1 m³ ( SNI )
Upah tenaga:
- Pekerja Oh 1.05 140,000 147,000.00
- Mandor Oh 0.067 185,000 12,395.00
Jumlah Upah Tenaga 159,395.00
Jumlah Total 159,395.00
Jumlah Total + jasa 10% 175,300
7. Galian tanah keras sedalam 1 meter tiap 1 m³ ( SNI )
Upah tenaga:
- Pekerja Oh 1 140,000 140,000.00
- Mandor Oh 0.032 185,000 5,920.00
Jumlah Upah Tenaga 145,920.00
Jumlah Total 145,920.00
Jumlah Total + jasa 10% 160,500
8. Galian tanah cadas sedalam 1 meter tiap 1 m³ ( SNI )
26

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Upah tenaga:
- Pekerja Oh 1.5 140,000 210,000.00
- Mandor Oh 0.06 185,000 11,100.00
Jumlah Upah Tenaga 221,100.00
Jumlah Total 221,100.00
Jumlah Total + jasa 10% 243,200
9. Galian tanah lumpur sedalam 1 meter tiap 1 m³ ( SNI )
Upah tenaga:
- Pekerja Oh 1.2 140,000 168,000.00
- Mandor Oh 0.045 185,000 8,325.00
Jumlah Upah Tenaga 176,325.00
Jumlah Total 176,325.00
Jumlah Total + jasa 10% 193,950
10. Pekerjaan Bor Pile D 30 cm tiap 1 m' m'
- Sewa Crawler crane Jam 0.25 350,000 87,500.00
- Sewa Mesin Bor Jam 0.25 300,000 75,000.00
- Operator alat berat Oh 0.60 165,000 99,000.00
- Pembantu operator alat berat Oh 0.35 120,000 42,000.00
- Tukang Gali Oh 0.20 160,000 32,000.00
- Mandor Oh 0.01 185,000 1,480.00
Jumlah Upah Tenaga 336,980.00
Jumlah Total + jasa 10% 370,650
11. Pembuangan tanah sejauh 150 m tiap 1 m³
Upah tenaga:
- Pekerja Oh 0.516 140,000 72,240.00
- Mandor Oh 0.05 185,000 9,250.00
Jumlah Upah Tenaga 81,490.00
Jumlah Total 81,490.00
Jumlah Total + jasa 10% 89,600
12. Urugan tanah kembali tiap 1 m³
Upah tenaga:
- Pekerja Oh 0.25 140,000 35,000.00
- Mandor Oh 0.0083 185,000 1,535.50
Jumlah Upah Tenaga 36,535.50
Jumlah Total 36,535.50
Jumlah Total + jasa 10% 40,150
13. Urugan tanah mendatangkan tiap 1 m³
Harga bahan:
- Tanah merah m³ 1.200 95,000 114,000.00
Jumlah Harga Bahan 114,000.00
Upah tenaga:
- Pekerja Oh 0.300 140,000 42,000.00
- Mandor Oh 0.010 185,000 1,850.00
Jumlah Upah Tenaga 43,850.00
Jumlah Total 157,850.00
Jumlah Total + jasa 10% 173,600
14. Mengangkut tanah sejauh 30 m tiap 1 m³
27

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Upah tenaga:
- Pekerja Oh 0.3300 140,000 46,200.00
- Mandor Oh 0.0100 185,000 1,850.00
Jumlah Upah Tenaga 48,050.00
Jumlah Total + jasa 10% 52,850
15. Menghampar tanah dengan menghampar tiap 1 m³
Upah tenaga:
- Pekerja Oh 0.2500 140,000 35,000.00
- Mandor Oh 0.0100 185,000 1,850.00
Jumlah Upah Tenaga 36,850.00
Jumlah Total + jasa 10% 40,500
16. Pemadatan tanah (tenaga manusia) tiap 1 m³
Upah tenaga:
- Pekerja Oh 0.5 140,000 70,000.00
- Mandor Oh 0.05 185,000 9,250.00
Jumlah Upah Tenaga 79,250.00
Jumlah Total 79,250.00
Jumlah Total + jasa 10% 87,150
17. Pemadatan tanah (tenaga manusia) tebal 20 cm tiap 1 m²
Upah tenaga:
- Pekerja Oh 0.1 140,000 14,000.00
- Mandor Oh 0.01 185,000 1,850.00
Jumlah Upah Tenaga 15,850.00
Jumlah Total 15,850.00
Jumlah Total + jasa 10% 17,400
18. Pemadatan tanah dengan tamper/hand compactor 6 lintasan / tebal 20cm tiap 1 m³

Kecepatan alat v 0.5 km/jam


Efisiensi alat Fa 0.83
Lebar pemadatan b 0.25 m'
Banyak lintasan (pass) n 6 lintasan 3 kali bolak-balik
Tebal lapis hamparan t 0.2 m'

Kap. prod / jam = (v x 1000) x b x t x Fa Qj 3.4583333 m³/jam


n

Koefisien Alat / m³ = 1 : Qj Qt 0.2892 jam

Harga pemakaian alat:


- TAMPER / HAND COMPACTOR jam 0.2892 56,997 16,483.45
Jumlah Bahan & Tenaga & Alat 16,483.45
Jumlah Total 16,483.45
Jumlah Total + jasa 10% 18,100
19. Pemadatan tanah tebal 20 cm dengan tamper/hand compactor 6 lintasan / tebal 20cm tiap 1 m²
Harga pemakaian alat:
- TAMPER / HAND COMPACTOR jam 0.0579 56,997 3,300.11
Jumlah Bahan & Tenaga & Alat 3,300.11
28

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Total 3,300.11


Jumlah Total + jasa 10% 3,600
20. Pemadatan tanah dengan tamper/hand compactor 10 lintasan / tebal 20cm tiap 1 m³

Kecepatan alat v 0.5 km/jam


Efisiensi alat Fa 0.83
Lebar pemadatan b 0.25 m'
Banyak lintasan (pass) n 10 lintasan 5 kali bolak-balik
Tebal lapis hamparan t 0.2 m'

Kap. prod / jam = (v x 1000) x b x t x Fa Qj 2.075 m³/jam


n

Koefisien Alat / m³ = 1 : Qj Qt 0.482 jam

Harga pemakaian alat:


- TAMPER / HAND COMPACTOR jam 0.482 56,997 27,472.42
Jumlah Bahan & Tenaga & Alat 27,472.42
Jumlah Total 27,472.42
Jumlah Total + jasa 10% 30,200
21. Pemadatan tanah tebal 20 cm dengan tamper/hand compactor 10 lintasan / tebal 20cm tiap 1 m²
Harga pemakaian alat:
- TAMPER / HAND COMPACTOR jam 0.0964 56,997 5,494.48
Jumlah Bahan & Tenaga & Alat 5,494.48
Jumlah Total 5,494.48
Jumlah Total + jasa 10% 6,000
22. Pemadatan tanah dengan Vibrating Roller tiap 1 m³

Kecepatan alat v 4 km/jam


Efisiensi alat Fa 0.83
Lebar pemadatan b 1.2 m'
Banyak lintasan (pass) n 6 lintasan 3 kali bolak-balik
Tebal lapis hamparan t 0.2 m'

Kap. prod / jam = (v x 1000) x b x t x Fa Qj 132.8 m³/jam


n

Koefisien Alat / m³ = 1 : Qj Qt 0.0076 jam

Harga pemakaian alat:


- VIBRATING ROLLER 6-8 TON jam 0.0076 273,161 2,076.02
Jumlah Bahan & Tenaga & Alat 2,076.02
Jumlah Total 2,076.02
Jumlah Total + jasa 10% 2,250
23. Pemadatan tanah tebal 20 cm dengan Vibrating Roller tiap 1 m²
Harga pemakaian alat:
- VIBRATING ROLLER 6-8 TON jam 0.0016 273,161 437.06
29

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Bahan & Tenaga & Alat 437.06


Jumlah Total 437.06
Jumlah Total + jasa 10% 450
24. Urugan sirtu tiap 1 m³ ( SNI )
Harga bahan:
- Sirtu m³ 1.2 416,539 499,846.80
Jumlah Harga Bahan 499,846.80
Upah tenaga:
- Pekerja Oh 0.25 140,000 35,000.00
- Mandor Oh 0.025 185,000 4,625.00
Jumlah Upah Tenaga 39,625.00
Jumlah Total 539,471.80
Jumlah Total + jasa 10% 593,400
25. Urugan pasir urug tiap 1 m³ ( SNI )
Harga bahan:
- Pasir urug m³ 1.2 120,000 144,000.00
Jumlah Harga Bahan 144,000.00
Upah tenaga:
- Pekerja Oh 0.3 140,000 42,000.00
- Mandor Oh 0.01 185,000 1,850.00
Jumlah Upah Tenaga 43,850.00
Jumlah Total 187,850.00
Jumlah Total + jasa 10% 206,600
26. Urugan tanah merah tiap 1 m³
Harga bahan:
- Tanah merah m³ 1.2 95,000 114,000.00
Jumlah Harga Bahan 114,000.00
Upah tenaga:
- Pekerja Oh 0.3 140,000 42,000.00
- Mandor Oh 0.01 185,000 1,850.00
Jumlah Upah Tenaga 43,850.00
Jumlah Total 157,850.00
Jumlah Total + jasa 10% 173,600
27. Urugan pasir pasang tiap 1 m³
Harga bahan:
- Pasir pasang m³ 1.2 178,164 213,796.80
Jumlah Harga Bahan 213,796.80
Upah tenaga:
- Pekerja Oh 0.3 140,000 42,000.00
- Mandor Oh 0.01 185,000 1,850.00
Jumlah Upah Tenaga 43,850.00
Jumlah Total 257,646.80
Jumlah Total + jasa 10% 283,400
28. Pemancangan tiang/cerucuk dolken kecil dalam 2 m' tiap 1 titik
Harga bahan:
- Kayu dolken Ø 5-7/400 cm btg 0.55 8,114 4,462.70
Jumlah Harga Bahan 4,462.70
30

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Upah tenaga:
- Pekerja Oh 0.1 140,000 14,000.00
- Mandor Oh 0.01 185,000 1,850.00
Jumlah Upah Tenaga 15,850.00
Jumlah Total 20,312.70
Jumlah Total + jasa 10% 22,300
29. Pemancangan tiang/cerucuk dolken besar dalam 2 m' tiap 1 titik
Harga bahan:
- Kayu dolken Ø 8-10/400 cm btg 0.55 11,878 6,532.90
Jumlah Harga Bahan 6,532.90
Upah tenaga:
- Pekerja Oh 0.1 140,000 14,000.00
- Mandor Oh 0.01 185,000 1,850.00
Jumlah Upah Tenaga 15,850.00
Jumlah Total 22,382.90
Jumlah Total + jasa 10% 24,600
30. Pemasangan lapisan ijuk tiap 1 m2
Harga bahan:
- Ijuk ikatan kg 6 26,350 158,100.00
Jumlah Harga Bahan 158,100.00
Upah tenaga:
- Pekerja Oh 0.15 140,000 21,000.00
- Mandor Oh 0.015 185,000 2,775.00
Jumlah Upah Tenaga 23,775.00
Jumlah Total 181,875.00
Jumlah Total + jasa 10% 200,050
31. Pemasangan lapisan geotekstil non woven tiap 1 m2
Harga bahan:
- Geotekstil non woven m2 1.1 13,750 15,125.00
Jumlah Harga Bahan 15,125.00
Upah tenaga:
- Pekerja Oh 0.6 140,000 84,000.00
- Mandor Oh 0.03 185,000 5,550.00
Jumlah Upah Tenaga 89,550.00
Jumlah Total 104,675.00
Jumlah Total + jasa 10% 115,100
C PEKERJAAN PASANGAN BATU KALI/BELAH

1. Pasang pondasi/pasangan batu kali/belah 1 Pc : 2 Ps tiap 1 m³


Harga bahan:
- Batu belah 15/20 m³ 1.2 385,000 462,000.00
- Semen portland kg 267 1,300 347,100.00
- Pasir pasang m³ 0.427 178,164 76,076.03
Jumlah Harga Bahan 885,176.03
Upah tenaga:
- Pekerja Oh 1.5 140,000 210,000.00
- Tukang batu Oh 0.6 160,000 96,000.00
31

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Kepala tukang Oh 0.06 180,000 10,800.00


- Mandor Oh 0.075 185,000 13,875.00
Jumlah Upah Tenaga 330,675.00
Jumlah Total 1,215,851.03
Jumlah Total + jasa 10% 1,337,400
2. Pasang pondasi/pasangan batu kali/belah 1 Pc : 3 Ps tiap 1 m³ ( SNI )
Harga bahan:
- Batu belah 15/20 m³ 1.2 385,000 462,000.00
- Semen portland kg 202 1,300 262,600.00
- Pasir pasang m³ 0.485 178,164 86,409.54
Jumlah Harga Bahan 811,009.54
Upah tenaga:
- Pekerja Oh 1.5 140,000 210,000.00
- Tukang batu Oh 0.75 160,000 120,000.00
- Kepala tukang Oh 0.075 180,000 13,500.00
- Mandor Oh 0.075 185,000 13,875.00
Jumlah Upah Tenaga 357,375.00
Jumlah Total 1,168,384.54
Jumlah Total + jasa 10% 1,285,200
3. Pasang pondasi/pasangan batu kali/belah 1 Pc : 4 Ps tiap 1 m³ ( SNI )
Harga bahan:
- Batu belah 15/20 m³ 1.2 385,000 462,000.00
- Semen portland kg 163 1,300 211,900.00
- Pasir pasang m³ 0.52 178,164 92,645.28
Jumlah Harga Bahan 766,545.28
Upah tenaga:
- Pekerja Oh 1.5 140,000 210,000.00
- Tukang batu Oh 0.75 160,000 120,000.00
- Kepala tukang Oh 0.075 180,000 13,500.00
- Mandor Oh 0.075 185,000 13,875.00
Jumlah Upah Tenaga 357,375.00
Jumlah Total 1,123,920.28
Jumlah Total + jasa 10% 1,236,300
4. Pasang pondasi/pasangan batu kali/belah 1 Pc : 5 Ps tiap 1 m³ ( SNI )
Harga bahan:
- Batu belah 15/20 m³ 1.2 385,000 462,000.00
- Semen portland kg 136 1,300 176,800.00
- Pasir pasang m³ 0.544 178,164 96,921.22
Jumlah Harga Bahan 735,721.22
Upah tenaga:
- Pekerja Oh 1.5 140,000 210,000.00
- Tukang batu Oh 0.75 160,000 120,000.00
- Kepala tukang Oh 0.075 180,000 13,500.00
- Mandor Oh 0.075 185,000 13,875.00
Jumlah Upah Tenaga 357,375.00
Jumlah Total 1,093,096.22
Jumlah Total + jasa 10% 1,202,400
32

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

5. Pasang pondasi batu kosong (aanstamping) tiap 1 m³ ( SNI )


Harga bahan:
- Batu belah 15/20 m³ 1.2 385,000 462,000.00
- Pasir urug m³ 0.432 120,000 51,840.00
Jumlah Harga Bahan 513,840.00
Upah tenaga:
- Pekerja Oh 0.780 140,000 109,200.00
- Tukang batu Oh 0.390 160,000 62,400.00
- Kepala tukang Oh 0.039 180,000 7,020.00
- Mandor Oh 0.039 185,000 7,215.00
Jumlah Upah Tenaga 185,835.00
Jumlah Total 699,675.00
Jumlah Total + jasa 10% 769,600
6. Pasang pondasi siklop 40% batu kali tiap 1 m³
Harga bahan:
- Besi beton ulir kg 75 19,000 1,425,000.00
- Semen portland kg 202 1,300 262,600.00
- Pasir beton kg 0.32 178,164 57,012.48
- Koral beton m³ 0.49 435,000 213,150.00
- Kawat beton kg 0.8 20,000 16,000.00
Jumlah Harga Bahan 1,973,762.48
Upah tenaga:
- Pekerja Oh 3 140,000 420,000.00
- Tukang batu Oh 0.85 160,000 136,000.00
- Kepala tukang Oh 0.085 180,000 15,300.00
- Mandor Oh 0.15 185,000 27,750.00
Jumlah Upah Tenaga 599,050.00
Jumlah Total 2,572,812.48
Jumlah Total + jasa 10% 2,830,050
7. Pasang pondasi sumuran diameter 100 cm tiap 1 m³ ( SNI )
Harga bahan:
- Batu belah 15/20 m³ 0.45 385,000 173,250.00
- Semen portland kg 194 1,300 252,200.00
- Pasir beton m³ 0.312 178,164 55,587.17
- Koral beton m³ 0.468 435,000 203,580.00
Jumlah Harga Bahan 684,617.17
Upah tenaga:
- Pekerja Oh 2.4 140,000 336,000.00
- Tukang batu Oh 0.8 160,000 128,000.00
- Kepala tukang Oh 0.08 180,000 14,400.00
- Mandor Oh 0.119 185,000 22,015.00
Jumlah Upah Tenaga 500,415.00
Jumlah Total 1,185,032.17
Jumlah Total + jasa 10% 1,303,500
8. 1 M' Pembuatan Tiang Pancang Ø 30 cm, Beton Tulang
Harga bahan:

- Pasir Urug M3 0.0190 120,000 2,280.00


33

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Pasir pasang M3 0.0940 178,164 16,747.42

- Koral Beton M3 0.1500 435,000 65,250.00

- Semen Portland Kg 60.5000 1,300 78,650.00

- Besi Beton polos Kg 45.0000 12,000 540,000.00

- Kawat Beton Kg 0.9000 20,000 18,000.00

- Kayu Terentang balok M3 0.0320 2,826,516 90,448.51

- Paku biasa 2"-5" Kg 0.1200 19,286 2,314.32

- Minyak Bekisting Ltr 0.0900 8,820 793.80

- Plamir Tembok Kg 0.2400 13,289 3,189.36


Jumlah Harga Bahan 817,673.41
Upah tenaga:
- Pekerja Oh 1.0000 140,000 140,000.00
- Tukang batu Oh 0.6700 160,000 107,200.00
- Kepala tukang Oh 0.0670 180,000 12,060.00
- Mandor Oh 0.0500 185,000 9,250.00
Jumlah Upah Tenaga 268,510.00
Jumlah Total 1,086,183.41
Jumlah Total + jasa 10% 1,194,800
9. 1 M' Memancang Tiang Pancang Beton Tulang
- mini pile jam 0.1170 1,500,000 175,500.00

- Pekerja Oh 1.0000 140,000 140,000.00

- Mandor Oh 0.0500 185,000 9,250.00


Jumlah Upah Tenaga 324,750.00
Jumlah Total 324,750.00
Jumlah Total + jasa 10% 357,200
JUMLAH 1 M' BAHAN + PANCANG 1,552,000

10. Pasang pondasi tiang pancang Tiap 1 m'


Harga bahan:

- Ukuran 30x30 cm² panjang s/d 12 m' M1 1.0000 242,900 242,900.00


Jumlah Harga Bahan 242,900.00
Jumlah Total + jasa 10% 267,150

1 M' Memancang Tiang Pancang Beton Tulang


- mini pile jam 0.1170 1,500,000 175,500.00

- Pekerja Oh 0.1000 140,000 14,000.00

- Mandor Oh 0.0500 185,000 9,250.00


Jumlah Upah Tenaga 198,750.00
Jumlah Total 198,750.00
Jumlah Total + jasa 10% 218,600
JUMLAH 1 M' BAHAN + PANCANG 485,750

D PEKERJAAN DINDING

1. Pasangan bata merah tebal 1 bata, 1 Pc : 2 Ps tiap 1m² ( SNI )


Catatan: Ukuran bata 22 x 11 x 5 cm.
Harga bahan:
- Bata merah bh 140 660 92,400.00
- Semen portland kg 43.5 1,300 56,550.00
34

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Pasir pasang m³ 0.08 178,164 14,253.12


Jumlah Harga Bahan 163,203.12
Upah tenaga:
- Pekerja Oh 0.6 140,000 84,000.00
- Tukang batu Oh 0.2 160,000 32,000.00
- Kepala tukang Oh 0.02 180,000 3,600.00
- Mandor Oh 0.03 185,000 5,550.00
Jumlah Upah Tenaga 125,150.00
Jumlah Total 288,353.12
Jumlah Total + jasa 10% 317,150
2. Pasangan bata merah tebal 1 bata, 1 Pc : 4 Ps tiap 1m² ( SNI )
Harga bahan:
- Bata merah bh 140 660 92,400.00
- Semen portland kg 26.55 1,300 34,515.00
- Pasir pasang m³ 0.093 178,164 16,569.25
Jumlah Harga Bahan 143,484.25
Upah tenaga:
- Pekerja Oh 0.6 140,000 84,000.00
- Tukang batu Oh 0.2 160,000 32,000.00
- Kepala tukang Oh 0.02 180,000 3,600.00
- Mandor Oh 0.03 185,000 5,550.00
Jumlah Upah Tenaga 125,150.00
Jumlah Total 268,634.25
Jumlah Total + jasa 10% 295,450
3. Pasangan bata merah tebal 1/2 bata, 1 Pc : 2 Ps tiap 1m² ( SNI )
Harga bahan:
- Bata merah bh 70 660 46,200.00
- Semen portland kg 18.95 1,300 24,635.00
- Pasir pasang m³ 0.038 178,164 6,770.23
Jumlah Harga Bahan 77,605.23
Upah tenaga:
- Pekerja Oh 0.3 140,000 42,000.00
- Tukang batu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.015 185,000 2,775.00
Jumlah Upah Tenaga 62,575.00
Jumlah Total 140,180.23
Jumlah Total + jasa 10% 154,150
4. Pasangan bata merah tebal 1/2 bata, 1 Pc : 4 Ps tiap 1m² ( SNI )
Harga bahan:
- Bata merah bh 70 660 46,200.00
- Semen portland kg 11.5 1,300 14,950.00
- Pasir pasang m³ 0.043 178,164 7,661.05
Jumlah Harga Bahan 68,811.05

Upah tenaga:
35

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Pekerja Oh 0.3 140,000 42,000.00


- Tukang batu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.015 185,000 2,775.00
Jumlah Upah Tenaga 62,575.00
Jumlah Total 131,386.05
Jumlah Total + jasa 10% 144,500
5. Pasangan bata merah tebal 1/2 bata, 1 Pc : 5 Ps tiap 1m² ( SNI )
Harga bahan:
- Bata merah bh 70 660 46,200.00
- Semen portland kg 9.68 1,300 12,584.00
- Pasir pasang m³ 0.045 178,164 8,017.38
Jumlah Harga Bahan 66,801.38
Upah tenaga:
- Pekerja Oh 0.3 140,000 42,000.00
- Tukang batu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.015 185,000 2,775.00
Jumlah Upah Tenaga 62,575.00
Jumlah Total 129,376.38
Jumlah Total + jasa 10% 142,300
6. Pasangan bata merah 1 Pc : 2 Ps tiap 1m³ (dibagi tebal bata 11 cm)
Catatan: Analisis ini digunakan untuk menghitung pasangan bata dengan ketebalan dinding selain 1/2 bata & 1 bata.
Harga bahan:
- Bata merah bh 637 660 420,420.00
- Semen portland kg 172.27 1,300 223,951.00
- Pasir pasang m³ 0.345 178,164 61,466.58
Jumlah Harga Bahan 705,837.58
Upah tenaga:
- Pekerja Oh 2.9 140,000 406,000.00
- Tukang batu Oh 0.9 160,000 144,000.00
- Kepala tukang Oh 0.09 180,000 16,200.00
- Mandor Oh 0.136 185,000 25,160.00
Jumlah Upah Tenaga 591,360.00
Jumlah Total 1,297,197.58
Jumlah Total + jasa 10% 1,426,900
7. Pasangan bata merah 1 Pc : 4 Ps tiap 1m³ (dibagi tebal bata 11 cm)
Catatan: Analisis ini digunakan untuk menghitung pasangan bata dengan ketebalan dinding selain 1/2 bata & 1 bata.
Harga bahan:
- Bata merah bh 637 660 420,420.00
- Semen portland kg 104.55 1,300 135,915.00
- Pasir pasang m³ 0.391 178,164 69,662.12
Jumlah Harga Bahan 625,997.12
Upah tenaga:
- Pekerja Oh 2.9 140,000 406,000.00
- Tukang batu Oh 0.9 160,000 144,000.00
- Kepala tukang Oh 0.09 180,000 16,200.00
36

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Mandor Oh 0.136 185,000 25,160.00


Jumlah Upah Tenaga 591,360.00
Jumlah Total 1,217,357.12
Jumlah Total + jasa 10% 1,339,050
8. Pasangan dinding batako tiap 1m²
Harga bahan:
- Batako bh 13.000 4,600 59,800.00
- Semen portland kg 12.500 1,250 15,625.00
- Pasir pasang m³ 0.040 123,600 4,944.00
Jumlah Harga Bahan 80,369.00
Upah tenaga:
- Pekerja Oh 0.500 100,000 50,000.00
- Tukang batu Oh 0.100 120,000 12,000.00
- Kepala tukang Oh 0.010 130,000 1,300.00
- Mandor Oh 0.025 150,000 3,750.00
Jumlah Upah Tenaga 67,050.00
Jumlah Total 147,419.00
Jumlah Total + jasa 10% 162,150
9. Pasangan dinding hebel dengan perekat mortar tiap 1m²
Harga bahan:
- Hebel uk.60x20x10 bh 8.333 12,500 104,162.50
- Perekat PM-100 (perekat) kg 2.600 3,750 9,750.00
Jumlah Harga Bahan 113,912.50
Upah tenaga:
- Pekerja Oh 0.400 140,000 56,000.00
- Tukang batu Oh 0.200 160,000 32,000.00
- Kepala tukang Oh 0.020 180,000 3,600.00
- Mandor Oh 0.020 185,000 3,700.00
Jumlah Upah Tenaga 95,300.00
Jumlah Total 209,212.50
Jumlah Total + jasa 10% 230,100
10. Pasangan rollag bata merah 1 Pc : 5 Ps , tiap 1 m' (1 lapis bata)
Harga bahan:
- Bata merah bh 16 660 10,560.00
- Semen portland kg 2.442 1,300 3,174.60
- Pasir pasang m³ 0.01122 178,164 1,999.00
Jumlah Harga Bahan 15,733.60
Upah tenaga:
- Pekerja Oh 0.0715 140,000 10,010.00
- Tukang batu Oh 0.022 160,000 3,520.00
- Kepala tukang Oh 0.0022 180,000 396.00
- Mandor Oh 0.0033 185,000 610.50
Jumlah Upah Tenaga 14,536.50
Jumlah Total 30,270.10
Jumlah Total + jasa 10% 33,250
11. Pasangan rollag bata merah 1 Pc : 4 Ps , tiap 1 m' (2 lapis bata)
Harga bahan:
37

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Bata merah bh 32 660 21,120.00


- Semen portland kg 7.318 1,300 9,513.40
- Pasir pasang m³ 0.0274 178,164 4,881.69
Jumlah Harga Bahan 35,515.09
Upah tenaga:
- Pekerja Oh 0.174 140,000 24,360.00
- Tukang batu Oh 0.0540 160,000 8,640.00
- Kepala tukang Oh 0.0054 180,000 972.00
- Mandor Oh 0.008 185,000 1,480.00
Jumlah Upah Tenaga 35,452.00
Jumlah Total 70,967.09
Jumlah Total + jasa 10% 78,050
12. Pasangan dinding hollowblock HB 20 tiap 1m², spesi 1:4 ( SNI )
Harga bahan:
- Hollow block HB. 20 bh 12.5 5,250 65,625.00
- Semen portland kg 24.56 1,300 31,928.00
- Pasir pasang m³ 0.0772 178,164 13,754.26
- Besi beton polos kg 0.28 12,000 3,360.00
Jumlah Harga Bahan 114,667.26

Upah tenaga:
- Pekerja Oh 0.3 140,000 42,000.00
- Tukang batu Oh 0.15 160,000 24,000.00
- Kepala tukang Oh 0.015 180,000 2,700.00
- Mandor Oh 0.015 185,000 2,775.00
Jumlah Upah Tenaga 71,475.00
Jumlah Total 186,142.26
Jumlah Total + jasa 10% 204,750
13. Pasangan dinding hollowblock HB 15 tiap 1m², spesi 1:4 ( SNI )
Harga bahan:
- Hollow block HB. 15 bh 12.5 3,950 49,375.00
- Semen portland kg 18.2 1,300 23,660.00
- Pasir pasang m³ 0.0582 178,164 10,369.14
- Besi beton polos kg 0.28 12,000 3,360.00
Jumlah Harga Bahan 86,764.14
Upah tenaga:
- Pekerja Oh 0.36 140,000 50,400.00
- Tukang batu Oh 0.12 160,000 19,200.00

- Kepala tukang Oh 0.012 180,000 2,160.00


- Mandor Oh 0.018 185,000 3,330.00
Jumlah Upah Tenaga 75,090.00
Jumlah Total 161,854.14
38

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Total + jasa 10% 178,000


14. Pasangan dinding hollowblock HB 10 tiap 1m², spesi 1:4 ( SNI )
Harga bahan:
- Hollow block HB. 10 bh 12.5 2,600 32,500.00
- Semen portland kg 12.13 1,300 15,769.00
- Pasir pasang m³ 0.0388 178,164 6,912.76
- Besi beton polos kg 0.28 12,000 3,360.00
Jumlah Harga Bahan 58,541.76
Upah tenaga:
- Pekerja Oh 0.3 140,000 42,000.00
- Tukang batu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.015 185,000 2,775.00
Jumlah Upah Tenaga 62,575.00
Jumlah Total 121,116.76
Jumlah Total + jasa 10% 133,200
15. Pasangan dinding Roster bata merah 12 x 24 x 10 tiap 1m², spesi 1:3
Harga bahan:
- Roster bata merah 12 x 24 x 10 bh 30 14,818 444,540.00
- Semen portland kg 14 1,300 18,200.00
- Pasir pasang m³ 0.032 178,164 5,701.25
Jumlah Harga Bahan 468,441.25
Upah tenaga:
- Pekerja Oh 0.3 140,000 42,000.00
- Tukang batu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.015 185,000 2,775.00
Jumlah Upah Tenaga 62,575.00
Jumlah Total 531,016.25
Jumlah Total + jasa 10% 584,100
16. Roster keramik 30 x 30 x 7
Harga bahan:
- Roster beton 20 x 20 x 7 bh 1 57,500 57,500.00
- Semen portland kg 0.1045 1,300 135.85
- Pasir pasang m³ 0.00038 178,164 67.70
Jumlah Harga Bahan 57,703.55
Upah tenaga:
- Pekerja Oh 0.003 140,000 420.00
- Tukang batu Oh 0.001 160,000 160.00
- Kepala tukang Oh 0.0001 180,000 18.00
- Mandor Oh 0.00015 185,000 27.75
Jumlah Upah Tenaga 625.75
Jumlah Total 58,329.30
Jumlah Total + jasa 10% 64,150
17. Pasangan dinding Glass block 20 x 20 x 10 tiap 1m²
Harga bahan:
- Glass block 20 x 20 x 10 bh 23 19,500 448,500.00
39

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Semen portland kg 11.5 1,300 14,950.00


- Pasir pasang m³ 0.042 178,164 7,482.89
Jumlah Harga Bahan 470,932.89
Upah tenaga:
- Pekerja Oh 0.36 140,000 50,400.00
- Tukang batu Oh 0.12 160,000 19,200.00
- Kepala tukang Oh 0.012 180,000 2,160.00
- Mandor Oh 0.018 185,000 3,330.00
Jumlah Upah Tenaga 75,090.00
Jumlah Total 546,022.89
Jumlah Total + jasa 10% 600,600

E PEKERJAAN PLESTERAN

1. Plesteran 1 Pc : 2 Ps tebal 15 mm tiap 1m² ( SNI )


Catatan: Analisis E1 s/d E14 pekerjaan plesteran sudah termasuk acian & benangan/ tali air untuk sudut & siku bangunan, kecuali benangan/ tali air u
ornamen/ variasi/ skoning dihitung tersendiri. Plesteran tebal 15 mm untuk bangunan gedung & rumah; plesteran 20-30 mm untuk bangunan air, salur
Harga bahan:
- Semen portland kg 10.224 1,300 13,291.20
- Pasir pasang m³ 0.02 178,164 3,563.28
Jumlah Harga Bahan 16,854.48
Upah tenaga:
- Pekerja Oh 0.3 140,000 42,000.00
- Tukang batu Oh 0.15 160,000 24,000.00
- Kepala tukang Oh 0.015 180,000 2,700.00
- Mandor Oh 0.015 185,000 2,775.00
Jumlah Upah Tenaga 71,475.00
Jumlah Total 88,329.48
Jumlah Total + jasa 10% 97,150
2. Plesteran 1 Pc : 3 Ps tebal 15 mm tiap 1m² ( SNI )
Harga bahan:
- Semen portland kg 7.776 1,300 10,108.80
- Pasir pasang m³ 0.023 178,164 4,097.77
Jumlah Harga Bahan 14,206.57
Upah tenaga:
- Pekerja Oh 0.3 140,000 42,000.00
40

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Tukang batu Oh 0.15 160,000 24,000.00


- Kepala tukang Oh 0.015 180,000 2,700.00
- Mandor Oh 0.015 185,000 2,775.00
Jumlah Upah Tenaga 71,475.00
Jumlah Total 85,681.57
Jumlah Total + jasa 10% 94,200
3. Plesteran 1 Pc : 4 Ps tebal 15 mm tiap 1m² ( SNI )
Harga bahan:
- Semen portland kg 6.24 1,300 8,112.00
- Pasir pasang m³ 0.024 178,164 4,275.94
Jumlah Harga Bahan 12,387.94
Upah tenaga:
- Pekerja Oh 0.3 140,000 42,000.00
- Tukang batu Oh 0.15 160,000 24,000.00
- Kepala tukang Oh 0.015 180,000 2,700.00
- Mandor Oh 0.015 185,000 2,775.00
Jumlah Upah Tenaga 71,475.00
Jumlah Total 83,862.94
Jumlah Total + jasa 10% 92,200
4. Plesteran 1 Pc : 2 Ps tebal 20 mm tiap 1m² ( SNI )
Harga bahan:
- Semen portland kg 13.632 1,300 17,721.60
- Pasir pasang m³ 0.027 178,164 4,810.43
Jumlah Harga Bahan 22,532.03
Upah tenaga:
- Pekerja Oh 0.4 140,000 56,000.00
- Tukang batu Oh 0.2 160,000 32,000.00
- Kepala tukang Oh 0.02 180,000 3,600.00
- Mandor Oh 0.022 185,000 4,070.00
Jumlah Upah Tenaga 95,670.00
Jumlah Total 118,202.03
Jumlah Total + jasa 10% 130,000
5. Plesteran 1 Pc : 3 Ps tebal 20 mm tiap 1m² ( SNI )
Harga bahan:
- Semen portland kg 10.368 1,300 13,478.40
- Pasir pasang m³ 0.031 178,164 5,523.08
Jumlah Harga Bahan 19,001.48
Upah tenaga:
- Pekerja Oh 0.26 140,000 36,400.00
- Tukang batu Oh 0.2 160,000 32,000.00
- Kepala tukang Oh 0.02 180,000 3,600.00
- Mandor Oh 0.013 185,000 2,405.00
Jumlah Upah Tenaga 74,405.00
Jumlah Total 93,406.48
Jumlah Total + jasa 10% 102,700
6. Plesteran 1 Pc : 4 Ps tebal 20 mm tiap 1m² ( SNI )
Harga bahan:
41

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Semen portland kg 8.32 1,300 10,816.00


- Pasir pasang m³ 0.032 178,164 5,701.25
Jumlah Harga Bahan 16,517.25
Upah tenaga:
- Pekerja Oh 0.4 140,000 56,000.00
- Tukang batu Oh 0.2 160,000 32,000.00
- Kepala tukang Oh 0.02 180,000 3,600.00
- Mandor Oh 0.022 185,000 4,070.00
Jumlah Upah Tenaga 95,670.00
Jumlah Total 112,187.25
Jumlah Total + jasa 10% 123,400
7. Plesteran 1 Pc : 2 Ps tebal 25 mm tiap 1m²
Harga bahan:
- Semen portland kg 15.5 1,300 20,150.00
- Pasir pasang m³ 0.013 178,164 2,316.13
Jumlah Harga Bahan 22,466.13
Upah tenaga:
- Pekerja Oh 0.3 140,000 42,000.00
- Tukang batu Oh 0.2 160,000 32,000.00
- Kepala tukang Oh 0.02 180,000 3,600.00
- Mandor Oh 0.013 185,000 2,405.00
Jumlah Upah Tenaga 80,005.00
Jumlah Total 102,471.13
Jumlah Total + jasa 10% 112,700
8. Plesteran 1 Pc : 3 Ps tebal 25 mm tiap 1m²
Harga bahan:
- Semen portland kg 11.75 1,300 15,275.00
- Pasir pasang m³ 0.035 178,164 6,235.74
Jumlah Harga Bahan 21,510.74
Upah tenaga:
- Pekerja Oh 0.3 140,000 42,000.00
- Tukang batu Oh 0.2 160,000 32,000.00
- Kepala tukang Oh 0.02 180,000 3,600.00
- Mandor Oh 0.013 185,000 2,405.00
Jumlah Upah Tenaga 80,005.00
Jumlah Total 101,515.74
Jumlah Total + jasa 10% 111,650
9. Plesteran 1 Pc : 4 Ps tebal 25 mm tiap 1m²
Harga bahan:
- Semen portland kg 9.48 1,300 12,324.00
- Pasir pasang m³ 0.038 178,164 6,770.23
Jumlah Harga Bahan 19,094.23
Upah tenaga:
- Pekerja Oh 0.3 140,000 42,000.00
- Tukang batu Oh 0.2 160,000 32,000.00
- Kepala tukang Oh 0.02 180,000 3,600.00
- Mandor Oh 0.013 185,000 2,405.00
42

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Upah Tenaga 80,005.00


Jumlah Total 99,099.23
Jumlah Total + jasa 10% 109,000
10. Plesteran dinding dengan mortar tiap 1m²
Harga bahan:
- Perekat PM-200 (plesteran) kg 22.000 3,950 86,900.00
Jumlah Harga Bahan 86,900.00
Upah tenaga:
- Pekerja Oh 0.260 140,000 36,400.00
- Tukang batu Oh 0.150 160,000 24,000.00
- Kepala tukang Oh 0.015 180,000 2,700.00
- Mandor Oh 0.010 185,000 1,850.00
Jumlah Upah Tenaga 64,950.00
Jumlah Total 151,850.00
Jumlah Total + jasa 10% 167,000
11. Plesteran Berapen 1 Pc : 3 Ps tebal 15 mm tiap 1m²
Harga bahan:
- Semen portland kg 7.07 1,300 9,191.00
- Pasir pasang m³ 0.021 178,164 3,741.44
Jumlah Harga Bahan 12,932.44
Upah tenaga:
- Pekerja Oh 0.15 140,000 21,000.00
- Tukang batu Oh 0.07 160,000 11,200.00
- Kepala tukang Oh 0.007 180,000 1,260.00
- Mandor Oh 0.008 185,000 1,480.00
Jumlah Upah Tenaga 34,940.00
Jumlah Total 47,872.44
Jumlah Total + jasa 10% 52,650
12. Plesteran Berapen 1 Pc : 5 Ps tebal 15 mm tiap 1m² ( SNI )
Harga bahan:
- Semen portland kg 5.184 1,300 6,739.20
- Pasir pasang m³ 0.026 178,164 4,632.26
Jumlah Harga Bahan 11,371.46
Upah tenaga:
- Pekerja Oh 0.15 140,000 21,000.00
- Tukang batu Oh 0.07 160,000 11,200.00
- Kepala tukang Oh 0.008 180,000 1,440.00
- Mandor Oh 0.008 185,000 1,480.00
Jumlah Upah Tenaga 35,120.00
Jumlah Total 46,491.46
Jumlah Total + jasa 10% 51,100
13. Plesteran Skoning (benangan/ tali air) 1 Pc : 2 Ps lebar 10 cm / tiap 1m' ( SNI )
Harga bahan:
- Semen portland kg 0.5 1,300 650.00
- Pasir pasang m³ 0.013 178,164 2,316.13
Jumlah Harga Bahan 2,966.13
Upah tenaga:
43

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Pekerja Oh 0.08 140,000 11,200.00


- Tukang batu Oh 0.4 160,000 64,000.00
- Kepala tukang Oh 0.04 180,000 7,200.00
- Mandor Oh 0.004 185,000 740.00
Jumlah Upah Tenaga 83,140.00
Jumlah Total 86,106.13
Jumlah Total + jasa 10% 94,700
14. Plesteran Ciprat 1 Pc : 2 Ps tiap 1m² ( SNI )
Harga bahan:
- Semen portland kg 4.32 1,300 5,616.00
- Pasir pasang m³ 0.006 178,164 1,068.98
Jumlah Harga Bahan 6,684.98
Upah tenaga:
- Pekerja Oh 0.3 140,000 42,000.00
- Tukang batu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.015 185,000 2,775.00
Jumlah Upah Tenaga 62,575.00
Jumlah Total 69,259.98
Jumlah Total + jasa 10% 76,150
15. Plesteran Siar 1 Pc : 2 Ps untuk pasangan batu kali tiap 1m²( SNI )
Harga bahan:
- Semen portland kg 6.34 1,300 8,242.00
- Pasir pasang m³ 0.012 178,164 2,137.97
Jumlah Harga Bahan 10,379.97
Upah tenaga:
- Pekerja Oh 0.3 140,000 42,000.00
- Tukang batu Oh 0.15 160,000 24,000.00
- Kepala tukang Oh 0.015 180,000 2,700.00
- Mandor Oh 0.015 185,000 2,775.00
Jumlah Upah Tenaga 71,475.00
Jumlah Total 81,854.97
Jumlah Total + jasa 10% 90,000
16. Acian 1 m2 ( SNI )
Harga bahan:
- Semen portland kg 3.25 1,300 4,225.00
Jumlah Harga Bahan 4,225.00
Upah tenaga:
- Pekerja Oh 0.2 140,000 28,000.00
- Tukang batu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.01 185,000 1,850.00
Jumlah Upah Tenaga 47,650.00
Jumlah Total 51,875.00
Jumlah Total + jasa 10% 57,050
17 Acian dengan mortar tiap 1m²
Harga bahan:
44

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Perekat PM-300 (acian) kg 3.000 3,950 11,850.00


Jumlah Harga Bahan 11,850.00
Upah tenaga:
- Pekerja Oh 0.150 140,000 21,000.00
- Tukang batu Oh 0.100 160,000 16,000.00
- Kepala tukang Oh 0.010 180,000 1,800.00
- Mandor Oh 0.008 185,000 1,480.00
Jumlah Upah Tenaga 40,280.00
Jumlah Total 52,130.00
Jumlah Total + jasa 10% 57,300

F PEKERJAAN KUSEN DAN DAUN PINTU/JENDELA KAYU

1. Pasang kusen pintu dan jendela Kayu Jati tiap 1m³ ( SNI )
Harga bahan:
- Kayu Jati balok m³ 1.1 21,537,300 23,691,030.00
- Paku biasa 2"-5" kg 1.25 19,286 24,107.50
- Lem kayu kg 1 34,800 34,800.00
Jumlah Harga Bahan 23,749,937.50
Upah tenaga:
- Pekerja Oh 7 140,000 980,000.00
- Tukang kayu Oh 21 160,000 3,360,000.00
- Kepala tukang Oh 2.1 180,000 378,000.00
- Mandor Oh 0.35 185,000 64,750.00
Jumlah Upah Tenaga 4,782,750.00
Jumlah Total 28,532,687.50
Jumlah Total + jasa 10% 31,385,950
2. Pasang kusen pintu dan jendela Kayu Kamper Samarinda Oven tiap 1m³ ( SNI )
Harga bahan:
- Kayu Kamper Samarinda Oven balok m³ 1.2 6,564,650 7,877,580.00
- Paku biasa 2"-5" kg 1.25 19,286 24,107.50
- Lem kayu kg 1 34,800 34,800.00
Jumlah Harga Bahan 7,936,487.50
Upah tenaga:
- Pekerja Oh 6 140,000 840,000.00
- Tukang kayu Oh 18 160,000 2,880,000.00
- Kepala tukang Oh 1.8 180,000 324,000.00
- Mandor Oh 0.3 185,000 55,500.00
Jumlah Upah Tenaga 4,099,500.00
Jumlah Total 12,035,987.50
Jumlah Total + jasa 10% 13,239,550
3. Pasang kusen pintu dan jendela Kayu Kamper Medan/Kruing tiap 1m³( SNI )
Harga bahan:
- Kayu Kamper Medan/Kruing balok m³ 1.2 4,500,000 5,400,000.00
- Paku biasa 2"-5" kg 1.25 19,286 24,107.50
- Lem kayu kg 1 34,800 34,800.00
Jumlah Harga Bahan 5,458,907.50
45

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Upah tenaga:
- Pekerja Oh 6 140,000 840,000.00
- Tukang kayu Oh 18 160,000 2,880,000.00
- Kepala tukang Oh 2 180,000 360,000.00
- Mandor Oh 0.3 185,000 55,500.00
Jumlah Upah Tenaga 4,135,500.00
Jumlah Total 9,594,407.50
Jumlah Total + jasa 10% 10,553,800
4. Pasang kusen pintu dan jendela Kayu Meranti Palembang tiap 1m³ ( SNI )
Harga bahan:
- Kayu Meranti Palembang balok m³ 1.2 4,500,000 5,400,000.00
- Paku biasa 2"-5" kg 1.25 19,286 24,107.50
- Lem kayu kg 1 34,800 34,800.00
Jumlah Harga Bahan 5,458,907.50
Upah tenaga:
- Pekerja Oh 6 140,000 840,000.00
- Tukang kayu Oh 18 160,000 2,880,000.00
- Kepala tukang Oh 2 180,000 360,000.00
- Mandor Oh 0.3 185,000 55,500.00
Jumlah Upah Tenaga 4,135,500.00
Jumlah Total 9,594,407.50
Jumlah Total + jasa 10% 10,553,800
5. Pasang kusen pintu dan jendela Kayu Borneo tiap 1m³
Harga bahan:
- Kayu Borneo balok m³ 1.2 4,500,000 5,400,000.00
- Paku biasa 2"-5" kg 1.25 19,286 24,107.50
- Lem kayu kg 1 34,800 34,800.00
Jumlah Harga Bahan 5,458,907.50
Upah tenaga:
- Pekerja Oh 6 140,000 840,000.00
- Tukang kayu Oh 18 160,000 2,880,000.00
- Kepala tukang Oh 2 180,000 360,000.00
- Mandor Oh 0.3 185,000 55,500.00
Jumlah Upah Tenaga 4,135,500.00
Jumlah Total 9,594,407.50
Jumlah Total + jasa 10% 10,553,800
6. Pasang pintu panel Kayu Jati tiap 1m² ( SNI )
Harga bahan:
- Kayu Jati papan m³ 0.04 25,338,000 1,013,520.00
- Lem kayu kg 0.5 34,800 17,400.00
Jumlah Harga Bahan 1,030,920.00
Upah tenaga:
- Pekerja Oh 1 140,000 140,000.00
- Tukang kayu Oh 3 160,000 480,000.00
- Kepala tukang Oh 0.3 180,000 54,000.00
- Mandor Oh 0.05 185,000 9,250.00
Jumlah Upah Tenaga 683,250.00
46

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Total 1,714,170.00


Jumlah Total + jasa 10% 1,885,550
7. Pasang pintu panel Kayu Kamper Samarinda Oven tiap 1m² ( SNI )
Harga bahan:
- Kayu Kamper Samarinda Oven papan m³ 0.04 5,564,714 222,588.56
- Lem kayu kg 0.5 34,800 17,400.00
Jumlah Harga Bahan 239,988.56
Upah tenaga:
- Pekerja Oh 0.35 140,000 49,000.00
- Tukang kayu Oh 1.05 160,000 168,000.00
- Kepala tukang Oh 0.105 180,000 18,900.00
- Mandor Oh 0.018 185,000 3,330.00
Jumlah Upah Tenaga 239,230.00
Jumlah Total 479,218.56
Jumlah Total + jasa 10% 527,100
8. Pasang pintu panel Kayu Kamper Medan/Kruing tiap 1m² ( SNI )
Harga bahan:
- Kayu Kamper Medan/Kruing papan m³ 0.04 4,500,000 180,000.00
- Lem kayu kg 0.5 34,800 17,400.00
Jumlah Harga Bahan 197,400.00
Upah tenaga:
- Pekerja Oh 1.05 140,000 147,000.00
- Tukang kayu Oh 0.105 160,000 16,800.00
- Kepala tukang Oh 0.105 180,000 18,900.00
- Mandor Oh 0.018 185,000 3,330.00
Jumlah Upah Tenaga 186,030.00
Jumlah Total 383,430.00
Jumlah Total + jasa 10% 421,750
9. Pasang pintu panel Kayu Borneo tiap 1m²
Harga bahan:
- Kayu Borneo papan 3 cm m³ 0.04 2,826,516 113,060.64
- Lem kayu kg 0.5 34,800 17,400.00
Jumlah Harga Bahan 130,460.64
Upah tenaga:
- Pekerja Oh 1 140,000 140,000.00
- Tukang kayu Oh 2.5 160,000 400,000.00
- Kepala tukang Oh 0.25 180,000 45,000.00
- Mandor Oh 0.05 185,000 9,250.00
Jumlah Upah Tenaga 594,250.00
Jumlah Total 724,710.64
Jumlah Total + jasa 10% 797,150
10. Pasang pintu panel Kayu Meranti Sampit tiap 1m²
Harga bahan:
- Kayu Meranti Sampit papan m³ 0.04 4,500,000 180,000.00
- Lem kayu kg 0.5 34,800 17,400.00
Jumlah Harga Bahan 197,400.00
Upah tenaga:
47

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Pekerja Oh 1 140,000 140,000.00


- Tukang kayu Oh 2.5 160,000 400,000.00
- Kepala tukang Oh 0.25 180,000 45,000.00
- Mandor Oh 0.05 185,000 9,250.00
Jumlah Upah Tenaga 594,250.00
Jumlah Total 791,650.00
Jumlah Total + jasa 10% 870,800
11. Pasang pintu dan jendela kaca Kayu Jati tiap 1m² ( SNI )
Harga bahan:
- Kayu Jati papan m³ 0.024 25,338,000 608,112.00
- Lem kayu kg 0.3 34,800 10,440.00
Jumlah Harga Bahan 618,552.00
Upah tenaga:
- Pekerja Oh 0.8 140,000 112,000.00
- Tukang kayu Oh 2.4 160,000 384,000.00
- Kepala tukang Oh 0.24 180,000 43,200.00
- Mandor Oh 0.04 185,000 7,400.00
Jumlah Upah Tenaga 546,600.00
Jumlah Total 1,165,152.00
Jumlah Total + jasa 10% 1,281,650
12. Pasang pintu dan jendela kaca Kayu Kamper Samarinda Oven tiap 1m² ( SNI )
Harga bahan:
- Kayu Kamper Samarinda Oven papan m³ 0.024 5,564,714 133,553.14
- Lem kayu kg 0.3 34,800 10,440.00
Jumlah Harga Bahan 143,993.14
Upah tenaga:
- Pekerja Oh 0.8 140,000 112,000.00
- Tukang kayu Oh 2.4 160,000 384,000.00
- Kepala tukang Oh 0.24 180,000 43,200.00
- Mandor Oh 0.04 185,000 7,400.00
Jumlah Upah Tenaga 546,600.00
Jumlah Total 690,593.14
Jumlah Total + jasa 10% 759,650
13. Pasang pintu dan jendela kaca Kayu Kamper Medan/Kruing tiap 1m²
Harga bahan:
- Kayu Kamper Medan/Kruing papan m³ 0.024 4,500,000 108,000.00
- Lem kayu kg 0.3 34,800 10,440.00
Jumlah Harga Bahan 118,440.00
Upah tenaga:
- Pekerja Oh 0.8 140,000 112,000.00
- Tukang kayu Oh 2 160,000 320,000.00
- Kepala tukang Oh 0.2 180,000 36,000.00
- Mandor Oh 0.04 185,000 7,400.00
Jumlah Upah Tenaga 475,400.00
Jumlah Total 593,840.00
Jumlah Total + jasa 10% 653,200
14. Pasang pintu dan jendela kaca Kayu Meranti Sampit tiap 1m²
48

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Harga bahan:
- Kayu Meranti Sampit papan m³ 0.024 4,500,000 108,000.00
- Lem kayu kg 0.3 34,800 10,440.00
Jumlah Harga Bahan 118,440.00
Upah tenaga:
- Pekerja Oh 0.8 140,000 112,000.00
- Tukang kayu Oh 2 160,000 320,000.00
- Kepala tukang Oh 0.2 180,000 36,000.00
- Mandor Oh 0.04 185,000 7,400.00
Jumlah Upah Tenaga 475,400.00
Jumlah Total 593,840.00
Jumlah Total + jasa 10% 653,200
15. Pasang pintu dan jendela kaca Kayu Borneo tiap 1m²
Harga bahan:
- Kayu Borneo papan 3 cm m³ 0.024 2,826,516 67,836.38
- Lem kayu kg 0.3 34,800 10,440.00
Jumlah Harga Bahan 78,276.38
Upah tenaga:
- Pekerja Oh 0.8 140,000 112,000.00
- Tukang kayu Oh 2 160,000 320,000.00
- Kepala tukang Oh 0.2 180,000 36,000.00
- Mandor Oh 0.04 185,000 7,400.00
Jumlah Upah Tenaga 475,400.00
Jumlah Total 553,676.38
Jumlah Total + jasa 10% 609,000
16. Pasang pintu dan jendela jalusi Kayu Jati tiap 1m² ( SNI )
Harga bahan:
- Kayu Jati papan m³ 0.064 25,338,000 1,621,632.00
- Lem kayu kg 0.5 34,800 17,400.00
Jumlah Harga Bahan 1,639,032.00
Upah tenaga:
- Pekerja Oh 1 140,000 140,000.00
- Tukang kayu Oh 3 160,000 480,000.00
- Kepala tukang Oh 0.3 180,000 54,000.00
- Mandor Oh 0.05 185,000 9,250.00
Jumlah Upah Tenaga 683,250.00
Jumlah Total 2,322,282.00
Jumlah Total + jasa 10% 2,554,500
17. Pasang pintu dan jendela jalusi Kayu Kamper Samarinda Oven tiap 1m²
Harga bahan:
- Kayu Kamper Samarinda Oven papan m³ 0.064 5,564,714 356,141.70
- Lem kayu kg 0.5 34,800 17,400.00
Jumlah Harga Bahan 373,541.70

Upah tenaga:
- Pekerja Oh 1 140,000 140,000.00
- Tukang kayu Oh 3 160,000 480,000.00
49

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Kepala tukang Oh 0.3 180,000 54,000.00


- Mandor Oh 0.05 185,000 9,250.00
Jumlah Upah Tenaga 683,250.00
Jumlah Total 1,056,791.70
Jumlah Total + jasa 10% 1,162,450
18. Pasang pintu dan jendela jalusi Kayu Kamper Singkil tiap 1m²
Harga bahan:
- Kayu Kamper Singkil papan m³ 0.064 5,564,714 356,141.70
- Lem kayu kg 0.5 34,800 17,400.00
Jumlah Harga Bahan 373,541.70
Upah tenaga:
- Pekerja Oh 1 140,000 140,000.00
- Tukang kayu Oh 3 160,000 480,000.00
- Kepala tukang Oh 0.3 180,000 54,000.00
- Mandor Oh 0.05 185,000 9,250.00
Jumlah Upah Tenaga 683,250.00
Jumlah Total 1,056,791.70
Jumlah Total + jasa 10% 1,162,450
19. Pasang pintu dan jendela jalusi Kayu Kamper Medan/Kruing tiap 1m²
Harga bahan:
- Kayu Kamper Medan/Kruing papan m³ 0.064 4,500,000 288,000.00
- Lem kayu kg 0.5 34,800 17,400.00
Jumlah Harga Bahan 305,400.00
Upah tenaga:
- Pekerja Oh 1 140,000 140,000.00
- Tukang kayu Oh 3 160,000 480,000.00
- Kepala tukang Oh 0.3 180,000 54,000.00
- Mandor Oh 0.05 185,000 9,250.00
Jumlah Upah Tenaga 683,250.00
Jumlah Total 988,650.00
Jumlah Total + jasa 10% 1,087,500
20. Pasang pintu dan jendela jalusi Kayu Meranti Sampit tiap 1m²
Harga bahan:
- Kayu Meranti Sampit papan m³ 0.064 4,500,000 288,000.00
- Lem kayu kg 0.5 34,800 17,400.00
Jumlah Harga Bahan 305,400.00
Upah tenaga:
- Pekerja Oh 1 140,000 140,000.00
- Tukang kayu Oh 3 160,000 480,000.00
- Kepala tukang Oh 0.3 180,000 54,000.00
- Mandor Oh 0.05 185,000 9,250.00
Jumlah Upah Tenaga 683,250.00
Jumlah Total 988,650.00
Jumlah Total + jasa 10% 1,087,500
21. Pasang pintu dan jendela jalusi Kayu Borneo tiap 1m²
Harga bahan:
- Kayu Borneo papan 3 cm m³ 0.064 2,826,516 180,897.02
50

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Lem kayu kg 0.5 34,800 17,400.00


Jumlah Harga Bahan 198,297.02
Upah tenaga:
- Pekerja Oh 1 140,000 140,000.00
- Tukang kayu Oh 3 160,000 480,000.00
- Kepala tukang Oh 0.3 180,000 54,000.00
- Mandor Oh 0.05 185,000 9,250.00
Jumlah Upah Tenaga 683,250.00
Jumlah Total 881,547.02
Jumlah Total + jasa 10% 969,700
22. Pasang jalusi mati Kayu Jati tiap 1m² ( SNI )
Harga bahan:
- Kayu Jati papan m³ 0.06 25,338,000 1,520,280.00
- Paku biasa 1/2"- 1" kg 0.15 19,286 2,892.90
Jumlah Harga Bahan 1,523,172.90
- Pekerja Oh 0.67 140,000 93,800.00
- Tukang kayu Oh 2 160,000 320,000.00
- Kepala tukang Oh 0.2 180,000 36,000.00
- Mandor Oh 0.335 185,000 61,975.00
Jumlah Upah Tenaga 511,775.00
Jumlah Total 2,034,947.90
Jumlah Total + jasa 10% 2,238,400
23. Pasang jalusi mati Kayu Kamper Samarinda oven tiap 1m² ( SNI )
Harga bahan:
- Kayu Kamper Samarinda oven papan m³ 0.06 5,564,714 333,882.84
- Paku biasa 1/2"- 1" kg 0.15 19,286 2,892.90
Jumlah Harga Bahan 336,775.74
Upah tenaga:
- Pekerja Oh 0.67 140,000 93,800.00
- Tukang kayu Oh 2 160,000 320,000.00
- Kepala tukang Oh 0.2 180,000 36,000.00
- Mandor Oh 0.335 185,000 61,975.00
Jumlah Upah Tenaga 511,775.00
Jumlah Total 848,550.74
Jumlah Total + jasa 10% 933,400
24. Pasang jalusi mati Kayu Kamper Medan/Kruing tiap 1m² ( SNI )
Harga bahan:
- Kayu Kamper Medan/Kruing papan m³ 0.06 4,500,000 270,000.00
- Paku biasa 1/2"- 1" kg 0.15 19,286 2,892.90
Jumlah Harga Bahan 272,892.90
Upah tenaga:
- Pekerja Oh 0.67 140,000 93,800.00
- Tukang kayu Oh 2 160,000 320,000.00
- Kepala tukang Oh 0.2 180,000 36,000.00
- Mandor Oh 0.335 185,000 61,975.00
Jumlah Upah Tenaga 511,775.00
Jumlah Total 784,667.90
51

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Total + jasa 10% 863,100


25. Pasang pintu teakwood rangkap, rangka Kayu Kamper Samarinda oven tiap 1m² ( SNI )
Harga bahan:
- Kayu Kamper Samarinda oven papan m³ 0.025 5,564,714 139,117.85
- Paku biasa 1/2"- 1" kg 0.03 19,286 578.58
- Lem kayu lt 0.3 34,800 10,440.00
- Teakwood 4x8 ft 3 mm lbr 1 120,983 120,983.00
Jumlah Harga Bahan 271,119.43
Upah tenaga:
- Pekerja Oh 0.8 140,000 112,000.00
- Tukang kayu Oh 2.4 160,000 384,000.00
- Kepala tukang Oh 0.24 180,000 43,200.00
- Mandor Oh 0.04 185,000 7,400.00
Jumlah Upah Tenaga 546,600.00
Jumlah Total 817,719.43
Jumlah Total + jasa 10% 899,450
26. Pasang pintu teakwood rangkap, rangka Kayu Kamper Medan/Kruing tiap 1m²
Harga bahan:
- Kayu Kamper Medan/Kruing papan m³ 0.025 4,500,000 112,500.00
- Paku biasa 1/2"- 1" kg 0.03 19,286 578.58
- Lem kayu lt 0.5 34,800 17,400.00
- Teakwood 4x8 ft 3 mm lbr 1 120,983 120,983.00
Jumlah Harga Bahan 251,461.58
Upah tenaga:
- Pekerja Oh 0.6 140,000 84,000.00
- Tukang kayu Oh 2 160,000 320,000.00
- Kepala tukang Oh 0.2 180,000 36,000.00
- Mandor Oh 0.03 185,000 5,550.00
Jumlah Upah Tenaga 445,550.00
Jumlah Total 697,011.58
Jumlah Total + jasa 10% 766,700
27. Pasang pintu teakwood rangkap, rangka Kayu Meranti Palembang tiap 1m²
Harga bahan:
- Kayu Meranti Palembang papan m³ 0.025 4,500,000 112,500.00
- Paku biasa 1/2"- 1" kg 0.03 19,286 578.58
- Lem kayu lt 0.5 34,800 17,400.00
- Teakwood 4x8 ft 3 mm lbr 1 120,983 120,983.00
Jumlah Harga Bahan 251,461.58
Upah tenaga:
- Pekerja Oh 0.6 140,000 84,000.00
- Tukang kayu Oh 2 160,000 320,000.00
- Kepala tukang Oh 0.2 180,000 36,000.00
- Mandor Oh 0.03 185,000 5,550.00
Jumlah Upah Tenaga 445,550.00
Jumlah Total 697,011.58
Jumlah Total + jasa 10% 766,700
28. Pasang pintu triplek rangkap, rangka Kayu Kamper Medan/Kruing tiap 1m²
52

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Harga bahan:
- Kayu Kamper Medan/Kruing papan m³ 0.025 4,500,000 112,500.00
- Paku biasa 1/2"- 1" kg 0.03 19,286 578.58
- Lem kayu lt 0.5 34,800 17,400.00
- Triplek 4x8 ft 4 mm lbr 1 65,000 65,000.00
Jumlah Harga Bahan 195,478.58
Upah tenaga:
- Pekerja Oh 0.6 140,000 84,000.00
- Tukang kayu Oh 2 160,000 320,000.00
- Kepala tukang Oh 0.2 180,000 36,000.00
- Mandor Oh 0.03 185,000 5,550.00
Jumlah Upah Tenaga 445,550.00
Jumlah Total 641,028.58
Jumlah Total + jasa 10% 705,100
29. Pasang pintu triplek rangkap, rangka Kayu Meranti Palembang tiap 1m²
Harga bahan:
- Kayu Meranti Palembang papan m³ 0.025 4,500,000 112,500.00
- Paku biasa 1/2"- 1" kg 0.03 19,286 578.58
- Lem kayu lt 0.5 34,800 17,400.00
- Triplek 4x8 ft 4 mm lbr 1 65,000 65,000.00
Jumlah Harga Bahan 195,478.58
Upah tenaga:
- Pekerja Oh 0.6 140,000 84,000.00
- Tukang kayu Oh 2 160,000 320,000.00
- Kepala tukang Oh 0.2 180,000 36,000.00
- Mandor Oh 0.03 185,000 5,550.00
Jumlah Upah Tenaga 445,550.00
Jumlah Total 641,028.58
Jumlah Total + jasa 10% 705,100
30. Pasang pintu teakwood dan formika, rangka Kayu Kamper Samarinda oven tiap 1m² ( SNI )
Harga bahan:
- Kayu Kamper Samarinda oven papan m³ 0.025 5,564,714 139,117.85
- Paku biasa 1/2"- 1" kg 0.03 19,286 578.58
- Lem kayu lt 0.8 34,800 27,840.00
- Teakwood 4x8 ft 3 mm lbr 1 120,983 120,983.00
- Formika 3x7 ft lbr 0.5 121,650 60,825.00
Jumlah Harga Bahan 349,344.43
Upah tenaga:
- Pekerja Oh 0.85 140,000 119,000.00
- Tukang kayu Oh 2.55 160,000 408,000.00
- Kepala tukang Oh 0.255 180,000 45,900.00
- Mandor Oh 0.043 185,000 7,955.00
Jumlah Upah Tenaga 580,855.00
Jumlah Total 930,199.43
Jumlah Total + jasa 10% 1,023,200
31. Pasang pintu teakwood dan formika, rangka Kayu Kamper Medan/Kruing tiap 1m²
Harga bahan:
53

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Kayu Kamper Medan/Kruing papan m³ 0.025 4,500,000 112,500.00


- Paku biasa 1/2"- 1" kg 0.3 19,286 5,785.80
- Lem kayu lt 0.8 34,800 27,840.00
- Teakwood 4x8 ft 3 mm lbr 1 120,983 120,983.00
- Formika 3x7 ft lbr 0.5 121,650 60,825.00
Jumlah Harga Bahan 327,933.80
Upah tenaga:
- Pekerja Oh 0.8 140,000 112,000.00
- Tukang kayu Oh 2.5 160,000 400,000.00
- Kepala tukang Oh 0.25 180,000 45,000.00
- Mandor Oh 0.04 185,000 7,400.00
Jumlah Upah Tenaga 564,400.00
Jumlah Total 892,333.80
Jumlah Total + jasa 10% 981,550
32. Pasang pintu teakwood dan formika, rangka Kayu Meranti Palembang tiap 1m²
Harga bahan:
- Kayu Meranti Palembang papan m³ 0.025 4,500,000 112,500.00
- Paku biasa 1/2"- 1" kg 0.3 19,286 5,785.80
- Lem kayu lt 0.8 34,800 27,840.00
- Teakwood 4x8 ft 3 mm lbr 1 120,983 120,983.00
- Formika 3x7 ft lbr 0.5 121,650 60,825.00
Jumlah Harga Bahan 327,933.80
Upah tenaga:
- Pekerja Oh 0.8 140,000 112,000.00
- Tukang kayu Oh 2.5 160,000 400,000.00
- Kepala tukang Oh 0.25 180,000 45,000.00
- Mandor Oh 0.04 185,000 7,400.00
Jumlah Upah Tenaga 564,400.00
Jumlah Total 892,333.80
Jumlah Total + jasa 10% 981,550
33. Pasang pintu triplek dan formika, rangka Kayu Kamper Medan/Kruing tiap 1m²
Harga bahan:
- Kayu Kamper Medan/Kruing papan m³ 0.025 4,500,000 112,500.00
- Paku biasa 1/2"- 1" kg 0.3 19,286 5,785.80
- Lem kayu lt 0.8 34,800 27,840.00
- Triplek 4x8 ft 4 mm lbr 1 65,000 65,000.00
- Formika 3x7 ft lbr 0.5 121,650 60,825.00
Jumlah Harga Bahan 271,950.80
Upah tenaga:
- Pekerja Oh 0.8 140,000 112,000.00
- Tukang kayu Oh 2.5 160,000 400,000.00
- Kepala tukang Oh 0.25 180,000 45,000.00
- Mandor Oh 0.04 185,000 7,400.00
Jumlah Upah Tenaga 564,400.00
Jumlah Total 836,350.80
Jumlah Total + jasa 10% 919,950
34. Pasang pintu triplek dan formika, rangka Kayu Meranti Palembang tiap 1m²
54

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Harga bahan:
- Kayu Meranti Palembang papan m³ 0.025 4,500,000 112,500.00
- Paku biasa 1/2"- 1" kg 0.3 19,286 5,785.80
- Lem kayu lt 0.8 34,800 27,840.00
- Triplek 4x8 ft 4 mm lbr 1 65,000 65,000.00
- Formika 3x7 ft lbr 0.5 121,650 60,825.00
Jumlah Harga Bahan 271,950.80
- Pekerja Oh 0.8 140,000 112,000.00
- Tukang kayu Oh 2.5 160,000 400,000.00
- Kepala tukang Oh 0.25 180,000 45,000.00
- Mandor Oh 0.04 185,000 7,400.00
Jumlah Upah Tenaga 564,400.00
Jumlah Total 836,350.80
Jumlah Total + jasa 10% 919,950
35. Pasang pintu triplek dan double formika, rangka Kayu Meranti Palembang tiap 1m²
Harga bahan:
- Kayu Meranti Palembang papan m³ 0.025 4,500,000 112,500.00
- Paku biasa 1/2"- 1" kg 0.3 19,286 5,785.80
- Lem kayu lt 1.2 34,800 41,760.00
- Triplek 4x8 ft 4 mm lbr 1 65,000 65,000.00
- Formika 3x7 ft lbr 1 121,650 121,650.00
Jumlah Harga Bahan 346,695.80
Upah tenaga:
- Pekerja Oh 1 140,000 140,000.00
- Tukang kayu Oh 2.6 160,000 416,000.00
- Kepala tukang Oh 0.26 180,000 46,800.00
- Mandor Oh 0.05 185,000 9,250.00
Jumlah Upah Tenaga 612,050.00
Jumlah Total 958,745.80
Jumlah Total + jasa 10% 1,054,600
36. Pasang kawat harmonika tiap 1 m²
Harga bahan:
- Kawat harmonika Ø 2 mm spasi 40x40 mm m² 1.1000 14,750 16,225.00
- Paku biasa 1/2"- 1" kg 0.0200 19,286 385.72
- Kayu Kamper Medan/Kruing papan m3 0.0018 4,500,000 8,100.00
Jumlah Harga Bahan 24,710.72
Upah tenaga:
- Pekerja Oh 0.1000 140,000 14,000.00
- Tukang kayu Oh 0.1000 160,000 16,000.00
- Kepala tukang Oh 0.0100 180,000 1,800.00
- Mandor Oh 0.0005 185,000 92.50
Jumlah Upah Tenaga 31,892.50
Jumlah Total 56,603.22
Jumlah Total + jasa 10% 62,250
37. Pasang kawat nyamuk tiap 1 m²
Harga bahan:
- Kawat nyamuk m² 1.1000 17,900 19,690.00
55

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Paku biasa 1/2"- 1" kg 0.0200 19,286 385.72


- Kayu Kamper Medan/Kruing papan m3 0.0018 4,500,000 8,100.00
Jumlah Harga Bahan 28,175.72
Upah tenaga:
- Pekerja Oh 0.1000 140,000 14,000.00
- Tukang kayu Oh 0.1000 160,000 16,000.00
- Kepala tukang Oh 0.0100 180,000 1,800.00
- Mandor Oh 0.0005 185,000 92.50
Jumlah Upah Tenaga 31,892.50
Jumlah Total 60,068.22
Jumlah Total + jasa 10% 66,050
38. Pasang kawat kasa tiap 1 m²
Harga bahan:
- Kawat kasa (parabola) m² 1.1000 18,450 20,295.00
- Paku biasa 1/2"- 1" kg 0.0200 19,286 385.72
- Kayu Kamper Medan/Kruing papan m3 0.0018 4,500,000 8,100.00
Jumlah Harga Bahan 28,780.72
Upah tenaga:
- Pekerja Oh 0.1000 140,000 14,000.00
- Tukang kayu Oh 0.1000 160,000 16,000.00
- Kepala tukang Oh 0.0100 180,000 1,800.00
- Mandor Oh 0.0005 185,000 92.50
Jumlah Upah Tenaga 31,892.50
Jumlah Total 60,673.22
Jumlah Total + jasa 10% 66,700

G PEKERJAAN KONSTRUKSI ATAP KAYU

1. Pasang konstruksi kuda-kuda Kayu Borneo tiap 1m³


Harga bahan:
- Kayu Borneo balok m³ 1.1 4,500,000 4,950,000.00
- Besi pelat strip kg 15 16,111 241,665.00
- Paku biasa 2"-5" kg 5.6 19,286 108,001.60
Jumlah Harga Bahan 5,299,666.60
Upah tenaga:
- Pekerja Oh 4 140,000 560,000.00
- Tukang kayu Oh 12 160,000 1,920,000.00
- Kepala tukang Oh 1.2 180,000 216,000.00
- Mandor Oh 0.2 185,000 37,000.00
Jumlah Upah Tenaga 2,733,000.00
Jumlah Total 8,032,666.60
Jumlah Total + jasa 10% 8,835,900
2. Pasang konstruksi kuda-kuda Kayu Kamper Medan/Kruing tiap 1m³ ( SNI )
Harga bahan:
- Kayu Kamper Medan/Kruing balok m³ 1.1 4,500,000 4,950,000.00
- Besi pelat strip kg 15 16,111 241,665.00
- Paku biasa 2"-5" kg 5.6 19,286 108,001.60
56

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Harga Bahan 5,299,666.60


Upah tenaga:
- Pekerja Oh 6.7 140,000 938,000.00
- Tukang kayu Oh 20.1 160,000 3,216,000.00
- Kepala tukang Oh 2.01 180,000 361,800.00
- Mandor Oh 0.335 185,000 61,975.00
Jumlah Upah Tenaga 4,577,775.00
Jumlah Total 9,877,441.60
Jumlah Total + jasa 10% 10,865,150
3. Pasang konstruksi kuda-kuda expose Kayu Samarinda tiap 1m³ ( SNI )
Harga bahan:
- Kayu Kamper Samarinda Oven balok m³ 1.2 6,564,650 7,877,580.00
- Besi pelat strip kg 15 16,111 241,665.00
- Paku biasa 2"-5" kg 5.6 19,286 108,001.60
Jumlah Harga Bahan 8,227,246.60
- Pekerja Oh 6.7 140,000 938,000.00
- Tukang kayu Oh 20.1 160,000 3,216,000.00
- Kepala tukang Oh 2.01 180,000 361,800.00
- Mandor Oh 0.335 185,000 61,975.00
Jumlah Upah Tenaga 4,577,775.00
Jumlah Total 12,805,021.60
Jumlah Total + jasa 10% 14,085,500
4. Pasang Konstruksi Gording Kayu Kamper Medan/Kruing tiap 1m³ ( SNI )
Harga bahan:
- Kayu Kamper Medan/Kruing balok m³ 1.1 4,500,000 4,950,000.00
- Besi pelat strip kg 15 16,111 241,665.00
- Paku biasa 2"-5" kg 3 19,286 57,858.00
Jumlah Harga Bahan 5,249,523.00
Upah tenaga:
- Pekerja Oh 2.4 140,000 336,000.00
- Tukang kayu Oh 7.2 160,000 1,152,000.00
- Kepala tukang Oh 0.72 180,000 129,600.00
- Mandor Oh 0.12 185,000 22,200.00
Jumlah Upah Tenaga 1,639,800.00
Jumlah Total 6,889,323.00
Jumlah Total + jasa 10% 7,578,250
5. Pasang kaso + reng genteng kodok Kayu Kamper Medan/Kruing tiap 1m²( SNI )
Harga bahan:
- Kayu Kamper Medan/Kruing kaso m³ 0.014 5,564,714 77,906.00
- Kayu Kamper Medan/Kruing reng m³ 0.0036 5,564,714 20,032.97
- Paku biasa 2"-5" kg 0.25 19,286 4,821.50
Jumlah Harga Bahan 102,760.47
Upah tenaga:
- Pekerja Oh 0.1 140,000 14,000.00
- Tukang kayu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.005 185,000 925.00
57

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Upah Tenaga 32,725.00


Jumlah Total 135,485.47
Jumlah Total + jasa 10% 149,000
6. Pasang kaso + reng genteng kodok Kayu Meranti Jambi tiap 1m²
Harga bahan:
- Kayu Meranti Jambi kaso m³ 0.014 4,500,000 63,000.00
- Kayu Meranti Jambi reng m³ 0.0036 4,500,000 16,200.00
- Paku biasa 2"-5" kg 0.25 19,286 4,821.50
Jumlah Harga Bahan 84,021.50
Upah tenaga:
- Pekerja Oh 0.1 140,000 14,000.00
- Tukang kayu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 32,725.00
Jumlah Total 116,746.50
Jumlah Total + jasa 10% 128,400
7. Pasang kaso + reng genteng keramik Kayu Kamper Medan/Kruing tiap 1m²( SNI )
Harga bahan:
- Kayu Kamper Medan/Kruing kaso m³ 0.014 5,564,714 77,906.00
- Kayu Kamper Medan/Kruing reng m³ 0.036 5,564,714 200,329.70
- Paku biasa 2"-5" kg 0.25 19,286 4,821.50
Jumlah Harga Bahan 283,057.20
Upah tenaga:
- Pekerja Oh 0.1 140,000 14,000.00
- Tukang kayu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 32,725.00
Jumlah Total 315,782.20
Jumlah Total + jasa 10% 347,350
8. Pasang kaso + reng genteng keramik Kayu Meranti Jambi tiap 1m² ( SNI )
Harga bahan:
- Kayu Meranti Jambi kaso m³ 0.014 4,500,000 63,000.00
- Kayu Meranti Jambi reng m³ 0.036 4,500,000 162,000.00
- Paku biasa 2"-5" kg 0.25 19,286 4,821.50
Jumlah Harga Bahan 229,821.50
Upah tenaga:
- Pekerja Oh 0.1 140,000 14,000.00
- Tukang kayu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 32,725.00
Jumlah Total 262,546.50
Jumlah Total + jasa 10% 288,800
9. Pasang kaso + reng genteng beton Kayu Kamper Medan/Kruing tiap 1m² ( SNI )
Harga bahan:
58

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Kayu Kamper Medan/Kruing kaso m³ 0.014 5,564,714 77,906.00


- Kayu Kamper Medan/Kruing reng m³ 0.057 5,564,714 317,188.70
- Paku biasa 2"-5" kg 0.25 19,286 4,821.50
Jumlah Harga Bahan 399,916.19
Upah tenaga:
- Pekerja Oh 0.1 140,000 14,000.00
- Tukang kayu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 32,725.00
Jumlah Total 432,641.19
Jumlah Total + jasa 10% 475,900
10. Pasang kaso + reng genteng beton Kayu Meranti Jambi tiap 1m²
Harga bahan:
- Kayu Meranti Jambi kaso m³ 0.014 4,500,000 63,000.00
- Kayu Meranti Jambi reng m³ 0.0057 4,500,000 25,650.00
- Paku biasa 2"-5" kg 0.25 19,286 4,821.50
Jumlah Harga Bahan 93,471.50
Upah tenaga:
- Pekerja Oh 0.1 140,000 14,000.00
- Tukang kayu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 32,725.00
Jumlah Total 126,196.50
Jumlah Total + jasa 10% 138,800
11. Pasang kaso + reng atap sirap kayu kamper tiap 1m² ( SNI )
Harga bahan:
- Kayu Kamper Samarinda kaso m³ 0.165 5,564,714 918,177.81
- Paku biasa 2"-5" kg 0.2 19,286 3,857.20
Jumlah Harga Bahan 922,035.01
Upah tenaga:
- Pekerja Oh 0.12 140,000 16,800.00
- Tukang kayu Oh 0.12 160,000 19,200.00
- Kepala tukang Oh 0.012 180,000 2,160.00
- Mandor Oh 0.006 185,000 1,110.00
Jumlah Upah Tenaga 39,270.00
Jumlah Total 961,305.01
Jumlah Total + jasa 10% 1,057,400
12. Pasang lisplank (3 x 20) cm Kayu Kamper Samarinda tiap 1m'
Harga bahan:
- Kayu Kamper Samarinda papan m³ 0.0072 4,500,000 32,400.00
- Paku biasa 2"-5" kg 0.05 19,286 964.30
Jumlah Harga Bahan 33,364.30
Upah tenaga:
- Pekerja Oh 0.1 140,000 14,000.00
- Tukang kayu Oh 0.2 160,000 32,000.00
59

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Kepala tukang Oh 0.02 180,000 3,600.00


- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 50,525.00
Jumlah Total 83,889.30
Jumlah Total + jasa 10% 92,250
13. Pasang lisplank (3 x 20) cm Kayu Kamper Medan/Kruing tiap 1m'
Harga bahan:
- Kayu Kamper Medan/Kruing papan m³ 0.0072 4,500,000 32,400.00
- Paku biasa 2"-5" kg 0.05 19,286 964.30
Jumlah Harga Bahan 33,364.30
Upah tenaga:
- Pekerja Oh 0.1 140,000 14,000.00
- Tukang kayu Oh 0.2 160,000 32,000.00
- Kepala tukang Oh 0.02 180,000 3,600.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 50,525.00
Jumlah Total 83,889.30
Jumlah Total + jasa 10% 92,250
14. Pasang lisplank (3 x 20) cm Kayu Meranti Palembang tiap 1m'
Harga bahan:
- Kayu Meranti Palembang papan m³ 0.0072 4,500,000 32,400.00
- Paku biasa 2"-5" kg 0.05 19,286 964.30
Jumlah Harga Bahan 33,364.30
Upah tenaga:
- Pekerja Oh 0.1 140,000 14,000.00
- Tukang kayu Oh 0.2 160,000 32,000.00
- Kepala tukang Oh 0.02 180,000 3,600.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 50,525.00
Jumlah Total 83,889.30
Jumlah Total + jasa 10% 92,250
15. Pasang lisplank (3 x 30) cm Kayu Kamper Samarinda tiap 1m'
Harga bahan:
- Kayu Kamper Samarinda papan m³ 0.011 4,500,000 49,500.00
- Paku biasa 2"-5" kg 0.05 19,286 964.30
Jumlah Harga Bahan 50,464.30
Upah tenaga:
- Pekerja Oh 0.11 140,000 15,400.00
- Tukang kayu Oh 0.22 160,000 35,200.00
- Kepala tukang Oh 0.022 180,000 3,960.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 55,485.00
Jumlah Total 105,949.30
Jumlah Total + jasa 10% 116,500
16. Pasang lisplank (3 x 30) cm Kayu Kamper Medan/Kruing tiap 1m'
Harga bahan:
- Kayu Kamper Medan/Kruing papan m³ 0.011 4,500,000 49,500.00
60

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Paku biasa 2"-5" kg 0.05 19,286 964.30


Jumlah Harga Bahan 50,464.30
Upah tenaga:
- Pekerja Oh 0.11 140,000 15,400.00
- Tukang kayu Oh 0.22 160,000 35,200.00
- Kepala tukang Oh 0.022 180,000 3,960.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 55,485.00
Jumlah Total 105,949.30
Jumlah Total + jasa 10% 116,500
17. Pasang lisplank (3 x 30) cm Kayu Meranti Palembang tiap 1m'
Harga bahan:
- Kayu Meranti Palembang papan m³ 0.011 4,500,000 49,500.00
- Paku biasa 2"-5" kg 0.05 19,286 964.30
Jumlah Harga Bahan 50,464.30
Upah tenaga:
- Pekerja Oh 0.11 140,000 15,400.00
- Tukang kayu Oh 0.22 160,000 35,200.00
- Kepala tukang Oh 0.022 180,000 3,960.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 55,485.00
Jumlah Total 105,949.30
Jumlah Total + jasa 10% 116,500
18. Pasang lisplank 2 x (2 x 20) cm Kayu Kamper Samarinda tiap 1m'
Harga bahan:
- Kayu Kamper Samarinda papan m³ 0.0088 4,500,000 39,600.00
- Paku biasa 2"-5" kg 0.06 19,286 1,157.16
Jumlah Harga Bahan 40,757.16
Upah tenaga:
- Pekerja Oh 0.1 140,000 14,000.00
- Tukang kayu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 32,725.00
Jumlah Total 73,482.16
Jumlah Total + jasa 10% 80,800
19. Pasang lisplank 2 x (2 x 20) cm Kayu Kamper Medan/Kruing tiap 1m'
Harga bahan:
- Kayu Kamper Medan/Kruing papan m³ 0.0088 4,500,000 39,600.00
- Paku biasa 2"-5" kg 0.06 19,286 1,157.16
Jumlah Harga Bahan 40,757.16
Upah tenaga:
- Pekerja Oh 0.1 140,000 14,000.00
- Tukang kayu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 32,725.00
61

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Total 73,482.16


Jumlah Total + jasa 10% 80,800
20. Pasang lisplank 2 x (2 x 20) cm Kayu Meranti Palembang tiap 1m'
Harga bahan:
- Kayu Meranti Palembang papan m³ 0.0088 4,500,000 39,600.00
- Paku biasa 2"-5" kg 0.06 19,286 1,157.16
Jumlah Harga Bahan 40,757.16
Upah tenaga:
- Pekerja Oh 0.1 140,000 14,000.00
- Tukang kayu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 32,725.00
Jumlah Total 73,482.16
Jumlah Total + jasa 10% 80,800
21. Pasang listplank Kalsiplank 8-jati 8.0x300x30000 tiap 1m'
Harga bahan:
- Kalsiplank 8-jati 8.0x300x30000 Lbr 0.38 53,150 20,197.00
- Kalsifuring CR 50x25x4000 Btg 0.32 38,070 12,182.40
- Kalsifuring MR 38x13x4 Btg 0.3 33,950 11,543.00
- Sekrup 6x1-1,5 bh 16 100 1,600.00
- Compound GRC zak 0.0200 81,250 1,625.00
- Paku peluru ramset bh 0.39 1,700 663.00
- Sekrup gypsum bh 21 130 2,730.00
- Kalsi tape rol 0.011 27,550 306.11
- Amplas lbr 0.1 5,880 823.20
Jumlah Harga Bahan 51,669.71
Upah tenaga:
- Pekerja Oh 0.2 140,000 28,000.00
- Tukang alumunium Oh 0.1 180,000 26,100.00
- Tukang gypsum Oh 0.1 180,000 26,100.00
- Kepala tukang Oh 0.1 180,000 18,000.00
- Mandor Oh 0.0054 185,000 999.00
Jumlah Upah Tenaga 99,199.00
Jumlah Total 150,868.71
Jumlah Total + jasa 10% 165,950
22. Membuat listplank asbes plat ram kayu tiap 1 m2
Harga bahan:
- Kayu Kamper Medan/Kruing reng m³ 0.0250 5,564,714 139,117.85
- Plat asbes 100x100 cm 2,7 mm lbr 1.0000 23,100 23,100.00
- Paku biasa 1/2"- 1" kg 0.3000 19,286 5,785.80
Jumlah Harga Bahan 168,003.65
Upah tenaga:
- Pekerja Oh 0.6000 140,000 84,000.00
- Tukang kayu Oh 1.8000 160,000 288,000.00
- Kepala tukang Oh 0.1800 180,000 32,400.00
- Mandor Oh 0.0300 185,000 5,550.00
62

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Upah Tenaga 409,950.00


Jumlah Total 577,953.65
Jumlah Total + jasa 10% 635,700

H PEKERJAAN KONSTRUKSI LANGIT-LANGIT/PLAFON DAN PENUTUP

1. Pasang rangka plafon (1,00 x 1,00) m Kayu Kamper Samarinda tiap 1m²
Harga bahan:
- Kayu Kamper Samarinda balok m³ 0.012 5,564,714 66,776.57
- Paku biasa 2"-5" kg 0.1 19,286 1,928.60
Jumlah Harga Bahan 68,705.17
Upah tenaga:
- Pekerja Oh 0.15 140,000 21,000.00
- Tukang kayu Oh 0.25 160,000 40,000.00
- Kepala tukang Oh 0.025 180,000 4,500.00
- Mandor Oh 0.0075 185,000 1,387.50
Jumlah Upah Tenaga 66,887.50
Jumlah Total 135,592.67
Jumlah Total + jasa 10% 149,150
2. Pasang rangka plafon (1,00 x 1,00) m Kayu Kamper Medan/Kruing tiap 1m²
Harga bahan:
- Kayu Kamper Medan/Kruing balok m³ 0.012 4,500,000 54,000.00
- Paku biasa 2"-5" kg 0.1 19,286 1,928.60
Jumlah Harga Bahan 55,928.60
Upah tenaga:
- Pekerja Oh 0.15 140,000 21,000.00
- Tukang kayu Oh 0.25 160,000 40,000.00
- Kepala tukang Oh 0.025 180,000 4,500.00
- Mandor Oh 0.0075 185,000 1,387.50
Jumlah Upah Tenaga 66,887.50
Jumlah Total 122,816.10
Jumlah Total + jasa 10% 135,050
3. Pasang rangka plafon (1,00 x 1,00) m Kayu Meranti Palembang tiap 1m²
Harga bahan:
- Kayu Meranti Palembang balok m³ 0.012 4,500,000 54,000.00
- Paku biasa 2"-5" kg 0.1 19,286 1,928.60
Jumlah Harga Bahan 55,928.60
Upah tenaga:
- Pekerja Oh 0.15 140,000 21,000.00
- Tukang kayu Oh 0.25 160,000 40,000.00
- Kepala tukang Oh 0.025 180,000 4,500.00
- Mandor Oh 0.0075 185,000 1,387.50
Jumlah Upah Tenaga 66,887.50
Jumlah Total 122,816.10
Jumlah Total + jasa 10% 135,050
4. Pasang rangka plafon (50 x 100) cm Kayu Kamper Samarinda tiap 1m² ( SNI )
Harga bahan:
63

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Kayu Kamper Samarinda balok m³ 0.0154 5,564,714 85,696.60


- Paku biasa 2"-5" kg 0.2 19,286 3,857.20
Jumlah Harga Bahan 89,553.80
Upah tenaga:
- Pekerja Oh 0.15 140,000 21,000.00
- Tukang kayu Oh 0.3 160,000 48,000.00
- Kepala tukang Oh 0.03 180,000 5,400.00
- Mandor Oh 0.075 185,000 13,875.00
Jumlah Upah Tenaga 88,275.00
Jumlah Total 177,828.80
Jumlah Total + jasa 10% 195,600
5. Pasang rangka plafon (50 x 100) cm Kayu Kamper Medan/Kruing tiap 1m² ( SNI )
Harga bahan:
- Kayu Kamper Medan/Kruing balok m³ 0.0154 4,500,000 69,300.00
- Paku biasa 2"-5" kg 0.2 19,286 3,857.20
Jumlah Harga Bahan 73,157.20
Upah tenaga:
- Pekerja Oh 0.15 140,000 21,000.00
- Tukang kayu Oh 0.3 160,000 48,000.00
- Kepala tukang Oh 0.03 180,000 5,400.00
- Mandor Oh 0.0075 185,000 1,387.50
Jumlah Upah Tenaga 75,787.50
Jumlah Total 148,944.70
Jumlah Total + jasa 10% 163,800
6. Pasang rangka plafon (50 x 100) cm Kayu Meranti Palembang tiap 1m² ( SNI )
Harga bahan:
- Kayu Meranti Palembang balok m³ 0.0154 4,500,000 69,300.00
- Paku biasa 2"-5" kg 0.2 19,286 3,857.20
Jumlah Harga Bahan 73,157.20
Upah tenaga:
- Pekerja Oh 0.15 140,000 21,000.00
- Tukang kayu Oh 0.3 160,000 48,000.00
- Kepala tukang Oh 0.03 180,000 5,400.00
- Mandor Oh 0.0075 185,000 1,387.50
Jumlah Upah Tenaga 75,787.50
Jumlah Total 148,944.70
Jumlah Total + jasa 10% 163,800
7. Pasang rangka plafon (60 x 120) cm Kayu Kamper Samarinda tiap 1m²
Harga bahan:
- Kayu Kamper Samarinda balok m³ 0.013 5,564,714 72,341.28
- Paku biasa 2"-5" kg 0.1 19,286 1,928.60
Jumlah Harga Bahan 74,269.88
Upah tenaga:
- Pekerja Oh 0.16 140,000 22,400.00
- Tukang kayu Oh 0.26 160,000 41,600.00
- Kepala tukang Oh 0.026 180,000 4,680.00
- Mandor Oh 0.008 185,000 1,480.00
64

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Upah Tenaga 70,160.00


Jumlah Total 144,429.88
Jumlah Total + jasa 10% 158,850
8. Pasang rangka plafon (60 x 120) cm Kayu Kamper Medan/Kruing tiap 1m²
Harga bahan:
- Kayu Kamper Medan/Kruing balok m³ 0.013 4,500,000 58,500.00
- Paku biasa 2"-5" kg 0.1 19,286 1,928.60
Jumlah Harga Bahan 60,428.60
Upah tenaga:
- Pekerja Oh 0.16 140,000 22,400.00
- Tukang kayu Oh 0.26 160,000 41,600.00
- Kepala tukang Oh 0.026 180,000 4,680.00
- Mandor Oh 0.008 185,000 1,480.00
Jumlah Upah Tenaga 70,160.00
Jumlah Total 130,588.60
Jumlah Total + jasa 10% 143,600
9. Pasang rangka plafon (60 x 120) cm Kayu Meranti Palembang tiap 1m²
Harga bahan:
- Kayu Meranti Palembang balok m³ 0.013 4,500,000 58,500.00
- Paku biasa 2"-5" kg 0.1 19,286 1,928.60
Jumlah Harga Bahan 60,428.60
Upah tenaga:
- Pekerja Oh 0.16 140,000 22,400.00
- Tukang kayu Oh 0.26 160,000 41,600.00
- Kepala tukang Oh 0.026 180,000 4,680.00
- Mandor Oh 0.008 185,000 1,480.00
Jumlah Upah Tenaga 70,160.00
Jumlah Total 130,588.60
Jumlah Total + jasa 10% 143,600
10. Pasang rangka plafon (60 x 60) cm Kayu Kamper Samarinda tiap 1m²
Harga bahan:
- Kayu Kamper Samarinda balok m³ 0.0163 5,564,714 90,704.84
- Paku biasa 2"-5" kg 0.25 19,286 4,821.50
Jumlah Harga Bahan 95,526.34
Upah tenaga:
- Pekerja Oh 0.2 140,000 28,000.00
- Tukang kayu Oh 0.3 160,000 48,000.00
- Kepala tukang Oh 0.03 180,000 5,400.00
- Mandor Oh 0.01 185,000 1,850.00
Jumlah Upah Tenaga 83,250.00
Jumlah Total 178,776.34
Jumlah Total + jasa 10% 196,650
11. Pasang rangka plafon (60 x 60) cm Kayu Kamper Medan/Kruing tiap 1m²
Harga bahan:
- Kayu Kamper Medan/Kruing balok m³ 0.0163 4,500,000 73,350.00
- Paku biasa 2"-5" kg 0.25 19,286 4,821.50
Jumlah Harga Bahan 78,171.50
65

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Upah tenaga:
- Pekerja Oh 0.2 140,000 28,000.00
- Tukang kayu Oh 0.3 160,000 48,000.00
- Kepala tukang Oh 0.03 180,000 5,400.00
- Mandor Oh 0.01 185,000 1,850.00
Jumlah Upah Tenaga 83,250.00
Jumlah Total 161,421.50
Jumlah Total + jasa 10% 177,550
12. Pasang rangka plafon (60 x 60) cm Kayu Meranti Palembang tiap 1m²
Harga bahan:
- Kayu Meranti Palembang balok m³ 0.0163 4,500,000 73,350.00
- Paku biasa 2"-5" kg 0.25 19,286 4,821.50
Jumlah Harga Bahan 78,171.50
Upah tenaga:
- Pekerja Oh 0.2 140,000 28,000.00
- Tukang kayu Oh 0.3 160,000 48,000.00
- Kepala tukang Oh 0.03 180,000 5,400.00
- Mandor Oh 0.01 185,000 1,850.00
Jumlah Upah Tenaga 83,250.00
Jumlah Total 161,421.50
Jumlah Total + jasa 10% 177,550
13. Pasang rangka plafon (30 x 60) cm Kayu Kamper Samarinda tiap 1m²
Harga bahan:
- Kayu Kamper Samarinda balok m³ 0.023 5,564,714 127,988.42
- Paku biasa 2"-5" kg 0.15 19,286 2,892.90
Jumlah Harga Bahan 130,881.32
Upah tenaga:
- Pekerja Oh 0.2 140,000 28,000.00
- Tukang kayu Oh 0.3 160,000 48,000.00
- Kepala tukang Oh 0.03 180,000 5,400.00
- Mandor Oh 0.01 185,000 1,850.00
Jumlah Upah Tenaga 83,250.00
Jumlah Total 214,131.32
Jumlah Total + jasa 10% 235,500
14. Pasang rangka plafon (30 x 60) cm Kayu Kamper Medan/Kruing tiap 1m²
Harga bahan:
- Kayu Kamper Medan/Kruing balok m³ 0.023 4,500,000 103,500.00
- Paku biasa 2"-5" kg 0.15 19,286 2,892.90
Jumlah Harga Bahan 106,392.90
Upah tenaga:
- Pekerja Oh 0.2 140,000 28,000.00
- Tukang kayu Oh 0.3 160,000 48,000.00
- Kepala tukang Oh 0.03 180,000 5,400.00
- Mandor Oh 0.01 185,000 1,850.00
Jumlah Upah Tenaga 83,250.00
Jumlah Total 189,642.90
Jumlah Total + jasa 10% 208,600
66

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

15. Pasang rangka plafon (30 x 60) cm Kayu Meranti Palembang tiap 1m²
Harga bahan:
- Kayu Meranti Palembang balok m³ 0.023 4,500,000 103,500.00
- Paku biasa 2"-5" kg 0.15 19,286 2,892.90
Jumlah Harga Bahan 106,392.90
Upah tenaga:
- Pekerja Oh 0.2 140,000 28,000.00
- Tukang kayu Oh 0.3 160,000 48,000.00
- Kepala tukang Oh 0.03 180,000 5,400.00
- Mandor Oh 0.01 185,000 1,850.00
Jumlah Upah Tenaga 83,250.00
Jumlah Total 189,642.90
Jumlah Total + jasa 10% 208,600
16. List Plafon kayu profil tiap 1m'
Harga bahan:
- Kayu list profil m' 1.05 22,226 23,337.30
- Paku biasa 1/2"- 1" kg 0.01 19,286 192.86
Jumlah Harga Bahan 23,530.16
Upah tenaga:
- Pekerja Oh 0.05 140,000 7,000.00
- Tukang kayu Oh 0.05 160,000 8,000.00
- Kepala tukang Oh 0.005 180,000 900.00
- Mandor Oh 0.003 185,000 555.00
Jumlah Upah Tenaga 16,455.00
Jumlah Total 39,985.16
Jumlah Total + jasa 10% 43,950
17. List plafon bahan Kayu Kamper Samarinda papan 1x5 cm tiap 1 m'
Harga bahan:
- Kayu Kamper Samarinda papan m³ 0.00055 4,500,000 2,475.00
- Paku biasa 1/2"- 1" kg 0.05 19,286 964.30
Jumlah Harga Bahan 3,439.30
Upah tenaga:
- Pekerja Oh 0.04 140,000 5,600.00
- Tukang kayu Oh 0.12 160,000 19,200.00
- Kepala tukang Oh 0.012 180,000 2,160.00
- Mandor Oh 0.002 185,000 370.00
Jumlah Upah Tenaga 27,330.00
Jumlah Total 30,769.30
Jumlah Total + jasa 10% 33,800
18. List plafon bahan triplek 0,3x5 cm tiap 1 m'
Harga bahan:
- Triplek 4x8 ft 6 mm lbr 0.022 80,000 1,760.00
- Paku biasa 1/2"- 1" kg 0.05 19,286 964.30
Jumlah Harga Bahan 2,724.30
Upah tenaga:
- Pekerja Oh 0.04 140,000 5,600.00
- Tukang kayu Oh 0.12 160,000 19,200.00
67

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Kepala tukang Oh 0.012 180,000 2,160.00


- Mandor Oh 0.002 185,000 370.00
Jumlah Upah Tenaga 27,330.00
Jumlah Total 30,054.30
Jumlah Total + jasa 10% 33,050
19. Pasang list profil cornice gypsum lebar sampai 5 cm tiap 1 m'
Harga bahan:
- List profil cornice gypsum lebar sampai 5 m' 1.1000 8,400 9,240.00
- Compound gypsum zak 0.0350 108,000 3,780.00
- Alkasit kg 0.0035 15,800 55.30
Jumlah Harga Bahan 13,075.30
Upah tenaga:
- Pekerja Oh 0.1125 140,000 15,750.00
- Tukang gypsum Oh 0.0375 180,000 6,750.00
- Kepala tukang Oh 0.0037 180,000 666.00
- Mandor Oh 0.0065 185,000 1,202.50
Jumlah Upah Tenaga 24,368.50
Jumlah Total 37,443.80
Jumlah Total + jasa 10% 41,150
20. Pasang list profil cornice gypsum lebar sampai 5-10 cm tiap 1 m'
Harga bahan:
- List profil cornice gypsum lebar 5-10 cm m' 1.1000 10,950 12,045.00
- Compound gypsum zak 0.04375 108,000 4,725.00
- Alkasit kg 0.0044 15,800 69.52
Jumlah Harga Bahan 16,839.52
Upah tenaga:
- Pekerja Oh 0.1125 140,000 15,750.00
- Tukang gypsum Oh 0.0375 180,000 6,750.00
- Kepala tukang Oh 0.0037 180,000 666.00
- Mandor Oh 0.0065 185,000 1,202.50
Jumlah Upah Tenaga 24,368.50
Jumlah Total 41,208.02
Jumlah Total + jasa 10% 45,300
21. Pasang list profil cornice gypsum lebar lebih dari 10 cm tiap 1 m'
Harga bahan:
- List profil cornice gypsum lebih dari 10 cm m' 1.1000 14,250 15,675.00
- Compound gypsum zak 0.0525 108,000 5,670.00
- Alkasit kg 0.0053 15,800 83.74
Jumlah Harga Bahan 21,428.74
Upah tenaga:
- Pekerja Oh 0.1125 140,000 15,750.00
- Tukang gypsum Oh 0.0400 180,000 7,200.00
- Kepala tukang Oh 0.0040 180,000 720.00
- Mandor Oh 0.0065 185,000 1,202.50
Jumlah Upah Tenaga 24,872.50
Jumlah Total 46,301.24
Jumlah Total + jasa 10% 50,900
68

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

22. Penutup plafon asbes (1,00 x 1,00) m tebal 2,7 mm tiap 1m²
Harga bahan:
- Plat asbes 100x100 cm 2,7 mm lbr 1.1 23,100 25,410.00
- Paku biasa 1/2"- 1" kg 0.01 19,286 192.86
Jumlah Harga Bahan 25,602.86
Upah tenaga:
- Pekerja Oh 0.03 140,000 4,200.00
- Tukang kayu Oh 0.07 160,000 11,200.00
- Kepala tukang Oh 0.007 180,000 1,260.00
- Mandor Oh 0.002 185,000 370.00
Jumlah Upah Tenaga 17,030.00
Jumlah Total 42,632.86
Jumlah Total + jasa 10% 46,850
23. Penutup plafon akustik (60 x 120) cm tiap 1m²
Harga bahan:
- Akustik 60 x 120 cm lbr 1.5 60,750 91,125.00
- Paku biasa 1/2"- 1" kg 0.05 19,286 964.30
Jumlah Harga Bahan 92,089.30
Upah tenaga:
- Pekerja Oh 0.06 140,000 8,400.00
- Tukang kayu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.003 185,000 555.00
Jumlah Upah Tenaga 26,755.00
Jumlah Total 118,844.30
Jumlah Total + jasa 10% 130,700
24. Penutup plafon teakwood (60 x 120) cm tebal 3 mm tiap 1m²
Harga bahan:
- Teakwood 4x8 ft 3 mm lbr 0.375 120,983 45,368.63
- Paku biasa 1/2"- 1" kg 0.03 19,286 578.58
Jumlah Harga Bahan 45,947.21
Upah tenaga:
- Pekerja Oh 0.07 140,000 9,800.00
- Tukang kayu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.0035 185,000 647.50
Jumlah Upah Tenaga 28,247.50
Jumlah Total 74,194.71
Jumlah Total + jasa 10% 81,600
25. Penutup plafon gypsum board 9 mm tiap 1m²
Harga bahan:
- Gypsumboard 120x240 cm 9 mm lbr 0.364 75,000 27,300.00
- Paku Sekrup kg 0.11 48,569 5,342.59
- Textile tape rol 0.024 8,400 201.60
- Compound gypsum zak 0.02 108,000 2,160.00
- Amplas lbr 0.1 5,880 588.00
Jumlah Harga Bahan 35,592.19
69

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Upah tenaga:
- Pekerja Oh 0.1 140,000 14,000.00
- Tukang gypsum Oh 0.05 180,000 9,000.00
- Kepala tukang Oh 0.005 180,000 900.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 24,825.00
Jumlah Total 60,417.19
Jumlah Total + jasa 10% 66,458.90
26. Penutup plafon GRC-board 4 mm tiap 1m²
Harga bahan:
- GRC-board 120x240 cm 4 mm lbr 0.364 68,000 24,752.00
- Paku Sekrup kg 0.11 48,569 5,342.59
- Textile tape rol 0.024 8,400 201.60
- Compound GRC zak 0.02 81,250 1,625.00
- Amplas lbr 0.1 5,880 588.00
Jumlah Harga Bahan 32,509.19
Upah tenaga:
- Pekerja Oh 0.1 140,000 14,000.00
- Tukang gypsum Oh 0.05 180,000 9,000.00
- Kepala tukang Oh 0.005 180,000 900.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 24,825.00
Jumlah Total 57,334.19
Jumlah Total + jasa 10% 63,066.50
27. Penutup plafon Calsiboard 4 mm tiap 1m²
Harga bahan:
- Calsiboard 120x240 cm 4 mm lbr 0.364 60,000 21,840.00
- Paku Sekrup kg 0.11 48,569 5,342.59
- Textile tape rol 0.024 8,400 201.60
- Compound GRC zak 0.02 81,250 1,625.00
- Amplas lbr 0.1 5,880 588.00
Jumlah Harga Bahan 29,597.19
Upah tenaga:
- Pekerja Oh 0.1 140,000 14,000.00
- Tukang gypsum Oh 0.05 180,000 9,000.00
- Kepala tukang Oh 0.005 180,000 900.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 24,825.00
Jumlah Total 54,422.19
Jumlah Total + jasa 10% 59,850
28. Penutup plafon triplek 4 mm tiap 1m²
Harga bahan:
- Paku biasa 1/2"- 1" kg 0.03 19,286 578.58
- Triplek 4x8 ft 4 mm lbr 0.375 65,000 24,375.00
Jumlah Harga Bahan 24,953.58
Upah tenaga:
- Pekerja Oh 0.07 140,000 9,800.00
70

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Tukang kayu Oh 0.1 160,000 16,000.00


- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.004 185,000 740.00
Jumlah Upah Tenaga 28,340.00
Jumlah Total 53,293.58
Jumlah Total + jasa 10% 58,600
29. Penutup plafon triplek 6 mm tiap 1m²
Harga bahan:
- Paku biasa 1/2"- 1" kg 0.03 19,286 578.58
- Triplek 4x8 ft 6 mm lbr 0.375 80,000 30,000.00
Jumlah Harga Bahan 30,578.58
Upah tenaga:
- Pekerja Oh 0.07 140,000 9,800.00
- Tukang kayu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.004 185,000 740.00
Jumlah Upah Tenaga 28,340.00
Jumlah Total 58,918.58
Jumlah Total + jasa 10% 64,800
30. Penutup plafon asbes (1,00 x 1,00) m tebal 2,7 mm lengkap rangka Kamper Medan/Kruing tiap 1m²
Harga bahan:
- Kayu Kamper Medan/Kruing balok m³ 0.012 4,500,000 54,000.00
- Paku biasa 1/2"- 1" kg 0.11 19,286 2,121.46
- Plat asbes 100x100 cm 2,7 mm lbr 1.1 23,100 25,410.00
Jumlah Harga Bahan 81,531.46
Upah tenaga:
- Pekerja Oh 0.18 140,000 25,200.00
- Tukang kayu Oh 0.32 160,000 51,200.00
- Kepala tukang Oh 0.032 180,000 5,760.00
- Mandor Oh 0.009 185,000 1,665.00
Jumlah Upah Tenaga 83,825.00
Jumlah Total 165,356.46
Jumlah Total + jasa 10% 181,850
31. Penutup plafon triplek 4 mm (60 x 120) cm lengkap rangka Kamper Medan/Kruing tiap 1m²
Harga bahan:
- Kayu Kamper Medan/Kruing balok m³ 0.013 4,500,000 58,500.00
- Paku biasa 1/2"- 1" kg 0.16 19,286 3,085.76
- Triplek 4x8 ft 4 mm lbr 0.364 65,000 23,660.00
Jumlah Harga Bahan 85,245.76
Upah tenaga:
- Pekerja Oh 0.26 140,000 36,400.00
- Tukang kayu Oh 0.31 160,000 49,600.00
- Kepala tukang Oh 0.031 180,000 5,580.00
- Mandor Oh 0.013 185,000 2,405.00
Jumlah Upah Tenaga 93,985.00
Jumlah Total 179,230.76
Jumlah Total + jasa 10% 197,150
71

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

32. Penutup plafon Gypsumboard 9 mm lengkap dgn rangka hollow tiap (6mx6m) = 36 m²
Harga bahan:
- Paku peluru ramset bh 14 1,700 23,800.00
- Hollow 4x4 cm tbl 0.35 mm btg 16.5 29,000 478,500.00
- Hollow 2x4 cm tbl 0.35 mm btg 15.51 22,500 348,975.00
- Paku beton kg 0.357 21,000 7,497.00
- Sekrup 6x1-1,5 bh 502 100 50,200.00
- Gypsumboard 120x240 cm 9 mm lbr 13.125 75,000 984,375.00
- Sekrup gypsum bh 745 130 96,850.00
- Textile tape rol 0.864 8,400 7,257.60
- Compound gypsum zak 0.72 108,000 77,760.00
- Amplas lbr 3.6 5,880 21,168.00
Jumlah Harga Bahan 2,096,382.60
Upah tenaga:
- Pekerja Oh 9.36 140,000 1,310,400.00
- Tukang alumunium Oh 9.36 180,000 1,684,800.00
- Tukang gypsum Oh 1.8 180,000 324,000.00
- Kepala tukang Oh 1.116 180,000 200,880.00
- Mandor Oh 0.468 185,000 86,580.00
Jumlah Upah Tenaga 3,606,660.00
Jumlah Total 5,703,042.60
Jumlah Total + jasa 10% 6,273,300
33. Penutup plafon Gypsumboard 9 mm lengkap dgn rangka hollow tebal 0.3 mm / tiap 1 m²
Harga bahan:
- Paku peluru ramset bh 0.39 1,700 663.00
- Hollow 4x4 cm tbl 0.35 mm btg 0.459 29,000 13,311.00
- Hollow 2x4 cm tbl 0.35 mm btg 0.431 22,500 9,697.50
- Paku beton kg 0.01 21,000 210.00
- Sekrup 6x1-1,5 bh 14 100 1,400.00
- Gypsumboard 120x240 cm 9 mm lbr 0.364 75,000 27,300.00
- Sekrup gypsum bh 21 130 2,730.00
- Textile tape rol 0.024 8,400 201.60
- Compound gypsum zak 0.02 108,000 2,160.00
- Amplas lbr 0.1 5,880 588.00
Jumlah Harga Bahan 58,261.10
Upah tenaga:
- Pekerja Oh 0.26 140,000 36,400.00
- Tukang alumunium Oh 0.26 180,000 46,800.00
- Tukang gypsum Oh 0.05 180,000 9,000.00
- Kepala tukang Oh 0.031 180,000 5,580.00
- Mandor Oh 0.013 185,000 2,405.00
Jumlah Upah Tenaga 100,185.00
Jumlah Total 158,446.10
Jumlah Total + jasa 10% 174,250
34. Penutup plafon Gypsumboard 9 mm lengkap dgn rangka hollow tebal 0.6 mm / tiap 1 m²
Harga bahan:
- Paku peluru ramset bh 0.39 1,700 663.00
72

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Hollow 4x4 cm tbl 0.6 mm btg 0.459 46,350 21,274.65


- Hollow 2x4 cm tbl 0.6 mm btg 0.431 36,050 15,537.55
- Paku beton kg 0.01 21,000 210.00
- Sekrup 6x1-1,5 bh 14 100 1,400.00
- Gypsumboard 120x240 cm 9 mm lbr 0.364 75,000 27,300.00
- Sekrup gypsum bh 21 130 2,730.00
- Textile tape rol 0.024 8,400 201.60
- Compound gypsum zak 0.02 108,000 2,160.00
- Amplas lbr 0.1 5,880 588.00
Jumlah Harga Bahan 72,064.80
Upah tenaga:
- Pekerja Oh 0.26 140,000 36,400.00
- Tukang alumunium Oh 0.26 180,000 46,800.00
- Tukang gypsum Oh 0.05 180,000 9,000.00
- Kepala tukang Oh 0.031 180,000 5,580.00
- Mandor Oh 0.013 185,000 2,405.00
Jumlah Upah Tenaga 100,185.00
Jumlah Total 172,249.80
Jumlah Total + jasa 10% 189,450
35. Penutup plafon GRC-board 4 mm lengkap dgn rangka hollow tebal 0.6 mm / tiap 1 m²
Harga bahan:
- Paku peluru ramset bh 0.39 1,700 663.00
- Hollow 4x4 cm tbl 0.6 mm btg 0.459 46,350 21,274.65
- Hollow 2x4 cm tbl 0.6 mm btg 0.431 36,050 15,537.55
- Paku beton kg 0.01 21,000 210.00
- Sekrup 6x1-1,5 bh 14 100 1,400.00
- GRC-board 120x240 cm 4 mm lbr 0.364 68,000 24,752.00
- Sekrup gypsum bh 21 130 2,730.00
- Textile tape rol 0.024 8,400 201.60
- Compound GRC zak 0.02 81,250 1,625.00
- Amplas lbr 0.1 5,880 588.00
Jumlah Harga Bahan 68,981.80
Upah tenaga:
- Pekerja Oh 0.26 140,000 36,400.00
- Tukang alumunium Oh 0.26 180,000 46,800.00
- Tukang gypsum Oh 0.05 180,000 9,000.00
- Kepala tukang Oh 0.031 180,000 5,580.00
- Mandor Oh 0.013 185,000 2,405.00
Jumlah Upah Tenaga 100,185.00
Jumlah Total 169,166.80
Jumlah Total + jasa 10% 186,050
36. Rangka hollow tebal 0.6 mm / tiap 1 m²
Harga bahan:
- Hollow 4x4 cm tbl 0.6 mm btg 0.459 46,350 21,274.65
- Hollow 2x4 cm tbl 0.6 mm btg 0.431 36,050 15,537.55
- Paku beton kg 0.01 21,000 210.00
- Sekrup 6x1-1,5 bh 14 100 1,400.00
73

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Harga Bahan 38,422.20


Upah tenaga:
- Pekerja Oh 0.26 140,000 36,400.00
- Tukang alumunium Oh 0.26 180,000 46,800.00
- Tukang gypsum Oh 0.05 180,000 9,000.00
- Kepala tukang Oh 0.031 180,000 5,580.00
- Mandor Oh 0.013 185,000 2,405.00
Jumlah Upah Tenaga 100,185.00
Jumlah Total 138,607.20
Jumlah Total + jasa 10% 152,450
37. Penutup plafon Calsiboard 4,5 mm lengkap dgn rangka hollow tebal 0.6 mm / tiap 1 m²
Harga bahan:
- Paku peluru ramset bh 0.39 1,700 663.00
- Hollow 4x4 cm tbl 0.6 mm btg 0.459 46,350 21,274.65
- Hollow 2x4 cm tbl 0.6 mm btg 0.431 36,050 15,537.55
- Paku beton kg 0.01 21,000 210.00
- Sekrup 6x1-1,5 bh 14 100 1,400.00
- Calsiboard 120x240 cm 4 mm lbr 0.364 60,000 21,840.00
- Sekrup gypsum bh 21 130 2,730.00
- Textile tape rol 0.024 8,400 201.60
- Compound GRC zak 0.02 81,250 1,625.00
- Amplas lbr 0.1 5,880 588.00
Jumlah Harga Bahan 66,069.80
Upah tenaga:
- Pekerja Oh 0.26 140,000 36,400.00
- Tukang alumunium Oh 0.26 180,000 46,800.00
- Tukang gypsum Oh 0.05 180,000 9,000.00
- Kepala tukang Oh 0.031 180,000 5,580.00
- Mandor Oh 0.013 185,000 2,405.00
Jumlah Upah Tenaga 100,185.00
Jumlah Total 166,254.80
Jumlah Total + jasa 10% 182,850
38. Penutup plafon Calsiboard 6 mm lengkap dgn rangka hollow tebal 0.6 mm / tiap 1 m²
Harga bahan:
- Paku peluru ramset bh 0.39 1,700 663.00
- Hollow 4x4 cm tbl 0.6 mm btg 0.459 46,350 21,274.65
- Hollow 2x4 cm tbl 0.6 mm btg 0.431 36,050 15,537.55
- Paku beton kg 0.01 21,000 210.00
- Sekrup 6x1-1,5 bh 14 100 1,400.00
- Calsiboard 6.0x1220x2440 cm 6 mm lbr 0.364 69,000 25,116.00
- Sekrup gypsum bh 21 130 2,730.00
- Textile tape rol 0.024 8,400 201.60
- Compound GRC zak 0.02 81,250 1,625.00
- Amplas lbr 0.1 5,880 588.00
Jumlah Harga Bahan 69,345.80
Upah tenaga:
- Pekerja Oh 0.26 140,000 36,400.00
74

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Tukang alumunium Oh 0.26 180,000 46,800.00


- Tukang gypsum Oh 0.05 180,000 9,000.00
- Kepala tukang Oh 0.031 180,000 5,580.00
- Mandor Oh 0.013 185,000 2,405.00
Jumlah Upah Tenaga 100,185.00
Jumlah Total 169,530.80
Jumlah Total + jasa 10% 186,450
39. Penutup plafon Akustik ukuran 60x120 cm + rangka alumunium / tiap 1 m²
Harga bahan:
- Profil alumunium "T" (akustik) m' 3.6000 10,600 38,160.00
- Kawat diameter 4 mm kg 0.1500 9,100 1,365.00
- Paku peluru ramset bh 1.0500 1,700 1,785.00
- Akustik 60 x 120 cm lbr 1.5000 60,750 91,125.00
Jumlah Harga Bahan 132,435.00
Upah tenaga:
- Pekerja Oh 0.1500 140,000 21,000.00
- Tukang gypsum Oh 0.5000 180,000 90,000.00
- Kepala tukang Oh 0.0500 180,000 9,000.00
- Mandor Oh 0.0075 185,000 1,387.50
Jumlah Upah Tenaga 121,387.50
Jumlah Total 253,822.50
Jumlah Total + jasa 10% 279,200
40. Plafond Papan (Lambriziring) 10 cm, tebal 1 cm + Rangka Kayu Borneo Super tiap 1 m2
Harga bahan:
- Kayu Borneo balok bh 0.02 4,500,000 90,000.00
- Paku biasa 2"-5" btg 0.20 19,286 3,857.20
- Kayu Kamper Samarinda oven papan btg 0.02 5,564,714 111,294.28
Jumlah Harga Bahan 205,151.48
Upah tenaga:
- Pekerja Oh 0.35 140,000 49,000.00
- Tukang kayu Oh 0.05 160,000 8,000.00
- Kepala tukang Oh 0.031 180,000 5,580.00
- Mandor Oh 0.013 185,000 2,405.00
Jumlah Upah Tenaga 64,985.00
Jumlah Total 270,136.48
Jumlah Total + jasa 10% 297,150
41. Penutup plafon sundha plafond bermotif lengkap dgn rangka hollow tebal 0.6 mm / tiap 1 m²
Harga bahan:
- Paku peluru ramset bh 0.40 1,700 680.00
- Hollow 4x4 cm tbl 0.6 mm btg 0.75 46,350 34,762.50
- Hollow 2x4 cm tbl 0.6 mm btg 0.75 36,050 27,037.50
- Paku beton kg 0.01 21,000 210.00
- Sekrup 6x1-1,5 bh 14 100 1,400.00
- Calsiboard 6.0x1220x2440 cm 6 mm lbr 0.364 69,000 25,116.00
- Sekrup gypsum bh 21 130 2,730.00
- Textile tape rol 0.024 8,400 201.60
- Compound GRC zak 0.02 81,250 1,625.00
75

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Amplas lbr 0.1 5,880 588.00


Jumlah Harga Bahan 94,350.60
Upah tenaga:
- Pekerja Oh 0.26 140,000 36,400.00
- Tukang alumunium Oh 0.26 180,000 46,800.00
- Tukang gypsum Oh 0.05 180,000 9,000.00
- Kepala tukang Oh 0.031 180,000 5,580.00
- Mandor Oh 0.013 185,000 2,405.00
Jumlah Upah Tenaga 100,185.00
Jumlah Total 194,535.60
Jumlah Total + jasa 10% 213,950

1. Pasang rangka dinding pemisah Kayu Kamper Medan/Kruing tiap 1m² ( SNI )
Harga bahan:
- Kayu Kamper Medan/Kruing balok m³ 0.028 4,500,000 126,000.00
- Paku biasa 2"-5" kg 0.15 19,286 2,892.90
Jumlah Harga Bahan 128,892.90

Upah tenaga:
- Pekerja Oh 0.15 140,000 21,000.00
- Tukang kayu Oh 0.45 160,000 72,000.00
- Kepala tukang Oh 0.045 180,000 8,100.00
- Mandor Oh 0.008 185,000 1,480.00
Jumlah Upah Tenaga 102,580.00
Jumlah Total 231,472.90
Jumlah Total + jasa 10% 254,600
2. Pasang rangka dinding pemisah Kayu Meranti Palembang tiap 1m² ( SNI )
Harga bahan:
- Kayu Meranti Palembang balok m³ 0.028 4,500,000 126,000.00
- Paku biasa 2"-5" kg 0.15 19,286 2,892.90
Jumlah Harga Bahan 128,892.90
Upah tenaga:
- Pekerja Oh 0.15 140,000 21,000.00
- Tukang kayu Oh 0.45 160,000 72,000.00
- Kepala tukang Oh 0.045 180,000 8,100.00
- Mandor Oh 0.008 185,000 1,480.00
Jumlah Upah Tenaga 102,580.00
Jumlah Total 231,472.90
Jumlah Total + jasa 10% 254,600
3. Pasang dinding pemisah teakwood rangkap rangka Kayu Kamper Medan/Kruing tiap 1m² ( SNI )
Harga bahan:
- Kayu Kamper Medan/Kruing balok m³ 0.028 4,500,000 126,000.00
- Paku biasa 2"-5" kg 0.15 19,286 2,892.90
- Lem kayu lt 0.56 34,800 19,488.00
- Teakwood 4x8 ft 3 mm lbr 0.86 120,983 104,045.38
Jumlah Harga Bahan 252,426.28
Upah tenaga:
76

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Pekerja Oh 0.15 140,000 21,000.00


- Tukang kayu Oh 0.45 160,000 72,000.00
- Kepala tukang Oh 0.045 180,000 8,100.00
- Mandor Oh 0.008 185,000 1,480.00
Jumlah Upah Tenaga 102,580.00
Jumlah Total 355,006.28
Jumlah Total + jasa 10% 390,500
4. Pasang dinding pemisah teakwood rangkap rangka Kayu Meranti Palembang tiap 1m²
Harga bahan:
- Kayu Meranti Palembang balok m³ 0.028 4,500,000 126,000.00
- Paku biasa 2"-5" kg 0.15 19,286 2,892.90
- Lem kayu lt 0.56 34,800 19,488.00
- Teakwood 4x8 ft 3 mm lbr 0.86 120,983 104,045.38
Jumlah Harga Bahan 252,426.28
Upah tenaga:
- Pekerja Oh 0.2 140,000 28,000.00
- Tukang kayu Oh 0.6 160,000 96,000.00
- Kepala tukang Oh 0.06 180,000 10,800.00
- Mandor Oh 0.01 185,000 1,850.00
Jumlah Upah Tenaga 136,650.00
Jumlah Total 389,076.28
Jumlah Total + jasa 10% 427,950
5. Pasang teakwood tebal 3 mm untuk dinding tiap 1m²
Harga bahan:
- Paku biasa 1/2"- 1" kg 0.05 19,286 964.30
- Teakwood 4x8 ft 3 mm lbr 0.4 120,983 48,393.20
Jumlah Harga Bahan 49,357.50
Upah tenaga:
- Pekerja Oh 0.025 140,000 3,500.00
- Tukang kayu Oh 0.075 160,000 12,000.00
- Kepala tukang Oh 0.0075 180,000 1,350.00
- Mandor Oh 0.0013 185,000 240.50
Jumlah Upah Tenaga 17,090.50
Jumlah Total 66,448.00
Jumlah Total + jasa 10% 73,050
6. Pasang triplek tebal 4 mm untuk dinding tiap 1m²
Harga bahan:
- Paku biasa 1/2"- 1" kg 0.05 19,286 964.30
- Triplek 4x8 ft 4 mm lbr 0.4 65,000 26,000.00
Jumlah Harga Bahan 26,964.30
Upah tenaga:
- Pekerja Oh 0.025 140,000 3,500.00
- Tukang kayu Oh 0.075 160,000 12,000.00
- Kepala tukang Oh 0.0075 180,000 1,350.00
- Mandor Oh 0.0013 185,000 240.50
Jumlah Upah Tenaga 17,090.50
Jumlah Total 44,054.80
77

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Total + jasa 10% 48,450


7. Pasang triplek tebal 6 mm untuk dinding tiap 1m²
Harga bahan:
- Paku biasa 1/2"- 1" kg 0.05 19,286 964.30
- Triplek 4x8 ft 6 mm lbr 0.4 80,000 32,000.00
Jumlah Harga Bahan 32,964.30
Upah tenaga:
- Pekerja Oh 0.025 140,000 3,500.00
- Tukang kayu Oh 0.075 160,000 12,000.00
- Kepala tukang Oh 0.0075 180,000 1,350.00
- Mandor Oh 0.0013 185,000 240.50
Jumlah Upah Tenaga 17,090.50
Jumlah Total 50,054.80
Jumlah Total + jasa 10% 55,050
8. Pasang gypsum tebal 12 mm untuk dinding tiap 1m²
Harga bahan:
- Paku biasa 1/2"- 1" kg 0.05 19,286 964.30
- Gypsumboard 120x240 cm 12 mm lbr 0.4 78,300 31,320.00
Jumlah Harga Bahan 32,284.30
Upah tenaga:
- Pekerja Oh 0.025 140,000 3,500.00
- Tukang kayu Oh 0.075 160,000 12,000.00
- Kepala tukang Oh 0.0075 180,000 1,350.00
- Mandor Oh 0.0013 185,000 240.50
Jumlah Upah Tenaga 17,090.50
Jumlah Total 49,374.80
Jumlah Total + jasa 10% 54,300
9. Dinding partisi gypsum 12 mm lkp rk metal Studs 2 muka tiap 1 m²
Harga bahan:
- Metal wall stud 35mm x 40mm m' 2 15,900 31,800.00
- Metal wall track 30mm x 40mm m' 0.75 14,350 10,762.50
- Paku rivet bh 4 50 200.00
- Sekrup 6x1-1,5 bh 8 100 800.00
- Gypsumboard 120x240 cm 12 mm lbr 0.75 78,300 58,725.00
- Textile tape roll 0.24 8,400 2,016.00
- Compound gypsum zak 0.12 108,000 12,960.00
- Sekrup gypsum bh 24 130 3,120.00
- Amplas lbr 0.5 5,880 2,940.00
Jumlah Harga Bahan 123,323.50
Upah tenaga:
- Pekerja Oh 0.2 140,000 28,000.00
- Tukang gypsum Oh 0.3 180,000 54,000.00
- Tukang alumunium Oh 0.2 180,000 36,000.00
- Mandor Oh 0.015 185,000 2,775.00
Jumlah Upah Tenaga 120,775.00
Jumlah Total 244,098.50
Jumlah Total + jasa 10% 268,500
78

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

10. Dinding partisi gypsum 12 mm lkp rk hollow tiap 1 m²


Harga bahan:
- Hollow 4x4 cm tbl 0.6 mm btg 1.25 46,350 57,937.50
- Hollow 2x4 cm tbl 0.6 mm btg 0.8 36,050 28,840.00
- Paku rivet bh 4 50 200.00
- Sekrup 6x1-1,5 bh 8 100 800.00
- Gypsumboard 120x240 cm 12 mm lbr 0.75 78,300 58,725.00
- Textile tape roll 0.24 8,400 2,016.00
- Compound gypsum zak 0.12 108,000 12,960.00
- Sekrup gypsum bh 24 130 3,120.00
- Amplas lbr 0.5 5,880 2,940.00
Jumlah Harga Bahan 167,538.50
Upah tenaga:
- Pekerja Oh 0.2 140,000 28,000.00
- Tukang gypsum Oh 0.3 180,000 54,000.00
- Tukang alumunium Oh 0.2 180,000 36,000.00
- Mandor Oh 0.015 185,000 2,775.00
Jumlah Upah Tenaga 120,775.00
Jumlah Total 288,313.50
Jumlah Total + jasa 10% 317,100
11. Dinding partisi double GRC-board 6 mm rk Kamper Medan/Kruing tiap 1 m²
Harga bahan:
- Kayu Kamper Medan/Kruing balok m³ 0.025 4,500,000 112,500.00
- Paku biasa 2"-5" kg 0.3 19,286 5,785.80
- GRC-board 120x240 cm 6 mm lbr 0.75 70,000 52,500.00
- Textile tape roll 0.24 8,400 2,016.00
- Compound GRC zak 0.12 81,250 9,750.00
- Sekrup gypsum bh 32 130 4,160.00
- Amplas lbr 0.5 5,880 2,940.00
Jumlah Harga Bahan 189,651.80
Upah tenaga:
- Pekerja Oh 0.2 140,000 28,000.00
- Tukang kayu Oh 0.6 160,000 96,000.00
- Mandor Oh 0.01 185,000 1,850.00
Jumlah Upah Tenaga 125,850.00
Jumlah Total 315,501.80
Jumlah Total + jasa 10% 347,050
12. Dinding partisi double GRC-board 6 mm rk hollow tiap 1 m²
Harga bahan:
- Hollow 4x4 cm tbl 0.6 mm btg 1.25 46,350 57,937.50
- Hollow 2x4 cm tbl 0.6 mm btg 0.8 36,050 28,840.00
- Paku rivet bh 4 50 200.00
- Sekrup 6x1-1,5 bh 8 100 800.00
- GRC-board 120x240 cm 6 mm lbr 0.75 70,000 52,500.00
- Textile tape roll 0.24 8,400 2,016.00
- Compound GRC zak 0.12 81,250 9,750.00
- Sekrup gypsum bh 24 130 3,120.00
79

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Amplas lbr 0.5 5,880 2,940.00


Jumlah Harga Bahan 158,103.50
- Pekerja Oh 0.2 140,000 28,000.00
- Tukang kayu Oh 0.3 160,000 48,000.00
- Tukang alumunium Oh 0.2 180,000 36,000.00
- Mandor Oh 0.015 185,000 2,775.00
Jumlah Upah Tenaga 114,775.00
Jumlah Total 272,878.50
Jumlah Total + jasa 10% 300,150

13. Dinding Convering ACP lkp rk hollow tiap 1 m²


Harga bahan:
- Hollow 4x4 cm tbl 0.6 mm btg 0.8 46,350 37,080.00
- Breaket Siku/spigot/stifner btg 0.267 60,000 16,020.00
- Paku skrup beton kg 0.08 21,600 1,728.00
- Paku Sekrup kg 0.11 21,600 2,376.00
- Allumunium Composite panel m2 1.1 420,500 462,550.00
- Sealant tube 0.25 36,950 9,237.50
- Alat bantu 10 % zak 0.1 528,992 52,899.15
Jumlah Harga Bahan 581,890.65
Upah tenaga:
- Pekerja Oh 0.39 140,000 54,600.00
- Tukang besi Oh 0.7 160,000 112,000.00
- Kepala tukang Oh 0.07 180,000 12,600.00
- Mandor Oh 0.007 185,000 1,295.00
Jumlah Upah Tenaga 180,495.00
Jumlah Total 762,385.65
Jumlah Total + jasa 10% 838,600

J PEKERJAAN BETON

1. Beton Non Struktur 1Pc : 3Ps : 5Kr - untuk rabatan/ beton tumbuk tiap 1m³
Harga bahan:
- Semen portland kg 218 1,300 283,400.00
- Pasir beton m³ 0.52 178,164 92,645.28
- Batu pecah/split 2/3 m³ 0.87 475,000 413,250.00
Jumlah Harga Bahan 789,295.28
Upah tenaga:
- Pekerja Oh 1.65 140,000 231,000.00
- Tukang batu Oh 0.25 160,000 40,000.00
- Kepala tukang Oh 0.025 180,000 4,500.00
- Mandor Oh 0.08 185,000 14,800.00
Jumlah Upah Tenaga 290,300.00
Jumlah Total 1,079,595.28
Jumlah Total + jasa 10% 1,187,550
2. Lantai Kerja Beton 1Pc : 3Ps : 5Kr - untuk beton tumbuk tebal 5 cm
Harga bahan:
80

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Semen portland kg 10 1,300 13,000.00


- Pasir beton m³ 0.026 178,164 4,632.26
- Batu pecah/split 2/3 m³ 0.044 475,000 20,900.00
Jumlah Harga Bahan 38,532.26
Upah tenaga:
- Pekerja Oh 1.15 140,000 161,000.00
- Tukang batu Oh 0.02 160,000 3,200.00
- Kepala tukang Oh 0.002 180,000 360.00
- Mandor Oh 0.006 185,000 1,110.00
Jumlah Upah Tenaga 165,670.00
Jumlah Total 204,202.26
Jumlah Total + jasa 10% 224,600
3. Beton K-125 (1Pc : 3Ps : 4Kr) tiap 1m³
Harga bahan:
- Semen portland kg 218 1,300 283,400.00
- Pasir beton m³ 0.52 178,164 92,645.28
- Batu pecah/split 2/3 m³ 0.87 475,000 413,250.00
Jumlah Harga Bahan 789,295.28
Upah tenaga:
- Pekerja Oh 1.65 140,000 231,000.00
- Tukang batu Oh 0.25 160,000 40,000.00
- Kepala tukang Oh 0.025 180,000 4,500.00
- Mandor Oh 0.08 185,000 14,800.00
Jumlah Upah Tenaga 290,300.00
Jumlah Total 1,079,595.28
Jumlah Total + jasa 10% 1,187,550
4. Beton K-175 (1Pc : 2,5Ps : 3,5Kr) tiap 1m³
Harga bahan:
- Semen portland kg 300 1,300 390,000.00
- Pasir beton m³ 0.526 178,164 93,714.26
- Batu pecah/split 2/3 m³ 0.737 475,000 350,075.00
Jumlah Harga Bahan 833,789.26
Upah tenaga:
- Pekerja Oh 1.65 140,000 231,000.00
- Tukang batu Oh 0.25 160,000 40,000.00
- Kepala tukang Oh 0.025 180,000 4,500.00
- Mandor Oh 0.08 185,000 14,800.00
Jumlah Upah Tenaga 290,300.00
Jumlah Total 1,124,089.26
Jumlah Total + jasa 10% 1,236,450
5. Beton Struktur K-225 (1Pc : 2Ps : 3Kr) tiap 1m³
Harga bahan:
- Semen portland kg 350 1,300 455,000.00
- Pasir beton m³ 0.485 178,164 86,409.54
- Batu pecah/split 2/3 m³ 0.727 475,000 345,325.00
Jumlah Harga Bahan 886,734.54
Upah tenaga:
81

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Pekerja Oh 2 140,000 280,000.00


- Tukang batu Oh 0.35 160,000 56,000.00
- Kepala tukang Oh 0.035 180,000 6,300.00
- Mandor Oh 0.1 185,000 18,500.00
Jumlah Upah Tenaga 360,800.00
Jumlah Total 1,247,534.54
Jumlah Total + jasa 10% 1,372,250
6. Beton Struktur K-275 (1Pc : 1,5Ps : 3Kr) tiap 1m³
Harga bahan:
- Semen portland kg 400 1,300 520,000.00
- Pasir beton m³ 0.417 178,164 74,294.39
- Batu pecah/split 2/3 m³ 0.833 475,000 395,675.00
Jumlah Harga Bahan 989,969.39
Upah tenaga:
- Kepala tukang Oh 2 180,000 360,000.00
- Tukang batu Oh 0.35 160,000 56,000.00
- Kepala tukang Oh 0.035 180,000 6,300.00
- Mandor Oh 0.1 185,000 18,500.00
Jumlah Upah Tenaga 440,800.00
Jumlah Total 1,430,769.39
Jumlah Total + jasa 10% 1,573,800
7. Beton Struktur K-350 (1Pc : 1,5Ps : 2,75Kr) tiap 1m³
Harga bahan:
- Semen portland kg 425 1,300 552,500.00
- Pasir beton m³ 0.442 178,164 78,748.49
- Batu pecah/split 2/3 m³ 0.811 475,000 385,225.00
Jumlah Harga Bahan 1,016,473.49
Upah tenaga:
- Pekerja Oh 2 140,000 280,000.00
- Tukang batu Oh 0.35 160,000 56,000.00
- Kepala tukang Oh 0.035 180,000 6,300.00
- Mandor Oh 0.1 185,000 18,500.00
Jumlah Upah Tenaga 360,800.00
Jumlah Total 1,377,273.49
Jumlah Total + jasa 10% 1,515,000
8. Beton Struktur K-400 (1Pc : 1,5Ps : 2,5Kr) tiap 1m³
Harga bahan:
- Semen portland kg 450 1,300 585,000.00
- Pasir beton m³ 0.46 178,164 81,955.44
- Batu pecah/split 2/3 m³ 0.79 475,000 375,250.00
Jumlah Harga Bahan 1,042,205.44
Upah tenaga:
- Pekerja Oh 2 140,000 280,000.00
- Tukang batu Oh 0.35 160,000 56,000.00
- Kepala tukang Oh 0.035 180,000 6,300.00
- Mandor Oh 0.1 185,000 18,500.00
Jumlah Upah Tenaga 360,800.00
82

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Total 1,403,005.44


Jumlah Total + jasa 10% 1,543,300
9. Beton Cyclope 1pc:3ps:5kr tiap 1m³
Harga bahan:
- Batu kali m³ 0.7000 385,000 269,500.00
- Semen portland kg 61.2500 1,300 79,625.00
- Pasir pasang m³ 0.4000 178,164 71,265.60
- Batu pecah/split 2/3 m³ 0.6500 475,000 308,750.00
Jumlah Harga Bahan 729,140.60
Upah tenaga:
- Pekerja Oh 6.0000 140,000 840,000.00
- Tukang batu Oh 1.0000 160,000 160,000.00
- Kepala tukang Oh 0.1000 180,000 18,000.00
- Mandor Oh 0.3000 185,000 55,500.00
Jumlah Upah Tenaga 1,073,500.00
Jumlah Total 1,802,640.60
Jumlah Total + jasa 10% 1,982,900
10. Pembesian dengan besi polos tiap 1 kg
Harga bahan:
- Besi beton polos kg 1.05 12,000 12,600.00
- Kawat beton kg 0.015 20,000 300.00
Jumlah Harga Bahan 12,900.00
Upah tenaga:
- Pekerja Oh 0.007 140,000 980.00
- Tukang besi Oh 0.007 160,000 1,120.00
- Kepala tukang Oh 0.0007 180,000 126.00
- Mandor Oh 0.0004 185,000 74.00
Jumlah Upah Tenaga 2,300.00
Jumlah Total 15,200.00
Jumlah Total + jasa 10% 16,700
11. Pembesian dengan besi ulir tiap 1 kg
Harga bahan:
- Besi beton ulir kg 1.05 19,000 19,950.00
- Kawat beton kg 0.015 20,000 300.00
Jumlah Harga Bahan 20,250.00
Upah tenaga:
- Pekerja Oh 0.007 140,000 980.00
- Tukang besi Oh 0.007 160,000 1,120.00
- Kepala tukang Oh 0.0007 180,000 126.00
- Mandor Oh 0.0004 185,000 74.00
Jumlah Upah Tenaga 2,300.00
Jumlah Total 22,550.00
Jumlah Total + jasa 10% 24,800
12. Pasang bekisting untuk pondasi 1 m²
Harga bahan:
- Kayu Terentang papan 3 cm m³ 0.04 2,826,516 113,060.64
- Paku biasa 2"-5" kg 0.3 19,286 5,785.80
83

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Minyak Bekisting lt 0.1 8,820 882.00


Jumlah Harga Bahan 119,728.44
Upah tenaga:
- Pekerja Oh 0.52 140,000 72,800.00
- Tukang kayu Oh 0.26 160,000 41,600.00
- Kepala tukang Oh 0.026 180,000 4,680.00
- Mandor Oh 0.026 185,000 4,810.00
Jumlah Upah Tenaga 123,890.00
Jumlah Total 243,618.44
Jumlah Total + jasa 10% 267,950
13. Pasang bekisting untuk sloof 1 m²
Harga bahan:
- Kayu Terentang papan 3 cm m³ 0.045 2,826,516 127,193.22
- Paku biasa 2"-5" kg 0.3 19,286 5,785.80
- Minyak Bekisting lt 0.1 8,820 882.00
Jumlah Harga Bahan 133,861.02
Upah tenaga:
- Pekerja Oh 0.52 140,000 72,800.00
- Tukang kayu Oh 0.26 160,000 41,600.00
- Kepala tukang Oh 0.026 180,000 4,680.00
- Mandor Oh 0.026 185,000 4,810.00
Jumlah Upah Tenaga 123,890.00
Jumlah Total 257,751.02
Jumlah Total + jasa 10% 283,500
14. Pasang bekisting untuk sloof 1 m² dengan bahan tripleks 9 mm
Harga bahan:
- Triplek 4x8 ft 9 mm lbr 0.35 110,000 38,500.00
- Kayu Terentang kaso m³ 0.03 2,826,516 84,795.48
- Paku biasa 2"-5" kg 0.3 19,286 5,785.80
- Minyak Bekisting lt 0.1 8,820 882.00
Jumlah Harga Bahan 129,963.28
Upah tenaga:
- Pekerja Oh 0.52 140,000 72,800.00
- Tukang kayu Oh 0.26 160,000 41,600.00
- Kepala tukang Oh 0.026 180,000 4,680.00
- Mandor Oh 0.026 185,000 4,810.00
Jumlah Upah Tenaga 123,890.00
Jumlah Total 253,853.28
Jumlah Total + jasa 10% 279,200
15. Pasang bekisting untuk kolom 1 m²
Harga bahan:
- Kayu Terentang kaso m³ 0.04 2,826,516 113,060.64
- Paku biasa 2"-5" kg 0.4 19,286 7,714.40
- Minyak bekisting lt 0.2 8,820 1,764.00
- Kayu Terentang balok m³ 0.015 2,826,516 42,397.74
- Triplek 4x8 ft 9 mm lbr 0.35 110,000 38,500.00
- Kayu dolken Ø 8-10/400 cm btg 2 11,878 23,756.00
84

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Harga Bahan 227,192.78


Upah tenaga:
- Pekerja Oh 0.66 140,000 92,400.00
- Tukang kayu Oh 0.33 160,000 52,800.00
- Kepala tukang Oh 0.033 180,000 5,940.00
- Mandor Oh 0.033 185,000 6,105.00
Jumlah Upah Tenaga 157,245.00
Jumlah Total 384,437.78
Jumlah Total + jasa 10% 422,850
16. Pasang bekisting untuk balok 1 m²
Harga bahan:
- Kayu Terentang kaso m³ 0.04 2,826,516 113,060.64
- Paku biasa 2"-5" kg 0.4 19,286 7,714.40
- Minyak bekisting lt 0.2 8,820 1,764.00
- Kayu Meranti Palembang balok m³ 0.018 4,500,000 81,000.00
- Triplek 4x8 ft 9 mm lbr 0.35 110,000 38,500.00
- Kayu dolken Ø 8-10/400 cm btg 2 11,878 23,756.00
Jumlah Harga Bahan 265,795.04
Upah tenaga:
- Pekerja Oh 0.66 140,000 92,400.00
- Tukang kayu Oh 0.33 160,000 52,800.00
- Kepala tukang Oh 0.033 180,000 5,940.00
- Mandor Oh 0.033 185,000 6,105.00
Jumlah Upah Tenaga 157,245.00
Jumlah Total 423,040.04
Jumlah Total + jasa 10% 465,300
17. Pasang bekisting untuk pelat lantai 1 m²
Harga bahan:
- Kayu Terentang kaso m³ 0.04 2,826,516 113,060.64
- Paku biasa 2"-5" kg 0.4 19,286 7,714.40
- Minyak bekisting lt 0.2 8,820 1,764.00
- Kayu Meranti Palembang balok m³ 0.015 4,500,000 67,500.00
- Triplek 4x8 ft 9 mm lbr 0.35 110,000 38,500.00
- Kayu dolken Ø 8-10/400 cm btg 6 11,878 71,268.00
Jumlah Harga Bahan 299,807.04
Upah tenaga:
- Pekerja Oh 0.66 140,000 92,400.00
- Tukang kayu Oh 0.33 160,000 52,800.00
- Kepala tukang Oh 0.033 180,000 5,940.00
- Mandor Oh 0.033 185,000 6,105.00
Jumlah Upah Tenaga 157,245.00
Jumlah Total 457,052.04
Jumlah Total + jasa 10% 502,750
18. Pasang bekisting untuk dinding 1 m²
Harga bahan:
- Kayu Terentang kaso m³ 0.03 2,826,516 84,795.48
- Paku biasa 2"-5" kg 0.4 19,286 7,714.40
85

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Minyak bekisting lt 0.2 8,820 1,764.00


- Kayu Meranti Palembang balok m³ 0.02 4,500,000 90,000.00
- Triplek 4x8 ft 9 mm lbr 0.35 110,000 38,500.00
- Kayu dolken Ø 8-10/400 cm btg 6 11,878 71,268.00
Jumlah Harga Bahan 294,041.88
Upah tenaga:
- Pekerja Oh 0.66 140,000 92,400.00
- Tukang kayu Oh 0.33 160,000 52,800.00
- Kepala tukang Oh 0.033 180,000 5,940.00
- Mandor Oh 0.033 185,000 6,105.00
Jumlah Upah Tenaga 157,245.00
Jumlah Total 451,286.88
Jumlah Total + jasa 10% 496,400
19. Pasang bekisting untuk tangga 1 m²
Harga bahan:
- Kayu Terentang kaso m³ 0.03 2,826,516 84,795.48
- Paku biasa 2"-5" kg 0.4 19,286 7,714.40
- Minyak Bekisting lt 0.15 8,820 1,323.00
- Kayu Meranti Palembang balok m³ 0.015 4,500,000 67,500.00
- Triplek 4x8 ft 9 mm lbr 0.35 110,000 38,500.00
- Kayu dolken Ø 8-10/400 cm btg 2 11,878 23,756.00
Jumlah Harga Bahan 223,588.88

Upah tenaga:
- Pekerja Oh 0.66 140,000 92,400.00
- Tukang kayu Oh 0.33 160,000 52,800.00
- Kepala tukang Oh 0.033 180,000 5,940.00
- Mandor Oh 0.033 185,000 6,105.00
Jumlah Upah Tenaga 157,245.00
Jumlah Total 380,833.88
Jumlah Total + jasa 10% 418,900
20. Membokar cetakan bekesting tiap 1m³
Upah tenaga:
- Pekerja Oh 4.0000 140,000 560,000.00
Jumlah Upah Tenaga 560,000.00
Jumlah Total + jasa 10% 616,000
21. Stutwerk untuk 1 m³, tinggi 3 - 4 m (memakai dolken)
Harga bahan:
- Kayu dolken Ø 8-10/400 cm btg 35.0000 11,878 415,730.00
Jumlah Harga Bahan 415,730.00
Upah tenaga:
- Pekerja Oh 3.5000 140,000 490,000.00
- Tukang kayu Oh 10.5000 160,000 1,680,000.00
- Kepala tukang Oh 1.0500 180,000 189,000.00
- Mandor Oh 0.1750 185,000 32,375.00
Jumlah Upah Tenaga 2,391,375.00
Jumlah Total 2,807,105.00
86

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Total + jasa 10% 3,087,800


22. Stutwerk untuk 1 m³, tinggi 3 - 4 m (memakai scafolding)
Harga bahan:
- Sewa Scafolding unit 32.0000 33,000 1,056,000.00
Jumlah Harga Bahan 1,056,000.00
Upah tenaga:
- Pekerja Oh 2.2000 140,000 308,000.00
- Tukang kayu Oh 3.5000 160,000 560,000.00
- Kepala tukang Oh 0.3500 180,000 63,000.00
- Mandor Oh 0.1200 185,000 22,200.00
Jumlah Upah Tenaga 953,200.00
Jumlah Total 2,009,200.00
Jumlah Total + jasa 10% 2,210,100
23. Membuat pondasi beton bertulang (150 kg besi + bekisting) tiap 1m³
Harga bahan:
- Kayu Terentang balok m³ 0.2 2,826,516 565,303.20
- Paku biasa 2"-5" kg 1.5 19,286 28,929.00
- Minyak Bekisting lt 0.4 8,820 3,528.00
- Besi beton polos kg 157.5 12,000 1,890,000.00
- Kawat beton kg 2.25 20,000 45,000.00
- Semen portland kg 336 1,300 436,800.00
- Pasir beton m³ 0.54 178,164 96,208.56
- Batu pecah/split 2/3 m³ 0.81 475,000 384,750.00
Jumlah Harga Bahan 3,450,518.76
Upah tenaga:
- Pekerja Oh 5.3 140,000 742,000.00
- Tukang batu Oh 0.275 160,000 44,000.00
- Tukang kayu Oh 1.3 160,000 208,000.00
- Tukang besi Oh 1.05 160,000 168,000.00
- Kepala tukang Oh 0.262 180,000 47,160.00
- Mandor Oh 0.265 185,000 49,025.00
Jumlah Upah Tenaga 1,258,185.00
Jumlah Total 4,708,703.76
Jumlah Total + jasa 10% 5,179,550
24. Membuat pondasi beton bertulang (200 kg besi + bekisting) tiap 1m³
Harga bahan:
- Kayu Terentang balok m³ 0.2 2,826,516 565,303.20
- Paku biasa 2"-5" kg 1.5 19,286 28,929.00
- Minyak Bekisting lt 0.4 8,820 3,528.00
- Besi beton ulir kg 210 19,000 3,990,000.00
- Kawat beton kg 2.25 20,000 45,000.00
- Semen portland kg 336 1,300 436,800.00
- Pasir beton m³ 0.54 178,164 96,208.56
- Batu pecah/split 2/3 m³ 0.81 475,000 384,750.00
Jumlah Harga Bahan 5,550,518.76
Upah tenaga:
- Pekerja Oh 5.3 140,000 742,000.00
87

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Tukang batu Oh 0.275 160,000 44,000.00


- Tukang kayu Oh 1.3 160,000 208,000.00
- Tukang besi Oh 1.05 160,000 168,000.00
- Kepala tukang Oh 0.262 180,000 47,160.00
- Mandor Oh 0.265 185,000 49,025.00
Jumlah Upah Tenaga 1,258,185.00
Jumlah Total 6,808,703.76
Jumlah Total + jasa 10% 7,489,550

24. Membuat sloof beton bertulang (160 kg besi + bekisting) tiap 1m³ Gudang/Rumah
Harga bahan:
- Kayu Terentang balok m³ 0.4 2,826,516 1,130,606.40
- Paku biasa 2"-5" kg 4 19,286 77,144.00
- Minyak Bekisting lt 1 8,820 8,820.00
- Besi beton polos kg 160 12,000 1,920,000.00
- Kawat beton kg 4 20,000 80,000.00
- Semen portland kg 377 1,300 490,100.00
- Pasir beton m³ 0.55 178,164 97,990.20
- Batu pecah/split 2/3 m³ 0.8156 475,000 387,410.00
Jumlah Harga Bahan 4,192,070.60
Upah tenaga:
- Pekerja Oh 5.65 140,000 791,000.00
- Tukang batu Oh 0.275 160,000 44,000.00
- Tukang kayu Oh 1.56 160,000 249,600.00
- Tukang besi Oh 1.4 160,000 224,000.00
- Kepala tukang Oh 0.323 180,000 58,140.00
- Mandor Oh 0.283 185,000 52,355.00
Jumlah Upah Tenaga 1,419,095.00
Jumlah Total 5,611,165.60
Jumlah Total + jasa 10% 6,172,227.89
25. Membuat sloof beton bertulang (200 kg besi + bekisting) tiap 1m³ Gudang
Harga bahan:
- Kayu Terentang balok m³ 0.4 2,826,516 1,130,606.40
- Paku biasa 2"-5" kg 4 19,286 77,144.00
- Minyak Bekisting lt 1 8,820 8,820.00
- Besi beton ulir kg 210 19,000 3,990,000.00
- Kawat beton kg 4 20,000 80,000.00
- Semen portland kg 377 1,300 490,100.00
- Pasir beton m³ 0.55 178,164 97,990.20
- Batu pecah/split 2/3 m³ 0.8156 475,000 387,410.00
Jumlah Harga Bahan 6,262,070.60
Upah tenaga:
- Pekerja Oh 5.65 140,000 791,000.00
- Tukang batu Oh 0.275 160,000 44,000.00
- Tukang kayu Oh 1.56 160,000 249,600.00
- Tukang besi Oh 1.4 160,000 224,000.00
- Kepala tukang Oh 0.323 180,000 58,140.00
88

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Mandor Oh 0.283 185,000 52,355.00


Jumlah Upah Tenaga 1,419,095.00
Jumlah Total 7,681,165.60
Jumlah Total + jasa 10% 8,449,227.89
26. Membuat kolom beton bertulang (150 kg besi + bekisting) tiap 1m³
Harga bahan:
- Kayu Terentang balok m³ 0.2 2,826,516 565,303.20
- Paku biasa 2"-5" kg 3.2 19,286 61,715.20
- Minyak Bekisting lt 1.668 8,820 14,711.76
- Besi beton ulir kg 141 19,000 2,679,000.00
- Kawat beton kg 2.256 20,000 45,120.00
- Semen portland kg 300 1,300 390,000.00
- Pasir beton m³ 0.525 178,164 93,536.10
- Batu pecah/split 2/3 m³ 0.78 475,000 370,500.00
- Kayu Meranti Palembang balok m³ 0.15 4,500,000 675,000.00
- Triplek 4x8 ft 9 mm lbr 2.8 110,000 308,000.00
- Kayu dolken Ø 8-10/400 cm btg 16 11,878 190,048.00
Jumlah Harga Bahan 5,392,934.26
Upah tenaga:
- Pekerja Oh 5 140,000 700,000.00
- Tukang batu Oh 0.3 160,000 48,000.00
- Tukang kayu Oh 2.5 160,000 400,000.00
- Tukang besi Oh 1.05 160,000 168,000.00
- Kepala tukang Oh 0.42 180,000 75,600.00
- Mandor Oh 0.185 185,000 34,225.00
Jumlah Upah Tenaga 1,425,825.00
Jumlah Total 6,818,759.26
Jumlah Total + jasa 10% 7,500,600
27. Membuat kolom beton bertulang (200 kg besi + bekisting) tiap 1m³
Harga bahan:
- Kayu Terentang balok m³ 0.2 2,826,516 565,303.20
- Paku biasa 2"-5" kg 3.2 19,286 61,715.20
- Minyak Bekisting lt 1.668 8,820 14,711.76
- Besi beton ulir kg 210 19,000 3,990,000.00
- Kawat beton kg 2.256 20,000 45,120.00
- Semen portland kg 300 1,300 390,000.00
- Pasir beton m³ 0.525 178,164 93,536.10
- Batu pecah/split 2/3 m³ 0.78 475,000 370,500.00
- Kayu Meranti Palembang balok m³ 0.15 4,500,000 675,000.00
- Triplek 4x8 ft 9 mm lbr 2.8 110,000 308,000.00
- Kayu dolken Ø 8-10/400 cm btg 16 11,878 190,048.00
Jumlah Harga Bahan 6,703,934.26
Upah tenaga:
- Pekerja Oh 5 140,000 700,000.00
- Tukang batu Oh 0.3 160,000 48,000.00
- Tukang kayu Oh 2.5 160,000 400,000.00
- Tukang besi Oh 1.05 160,000 168,000.00
89

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Kepala tukang Oh 0.42 180,000 75,600.00


- Mandor Oh 0.185 185,000 34,225.00
Jumlah Upah Tenaga 1,425,825.00
Jumlah Total 8,129,759.26
Jumlah Total + jasa 10% 8,942,700
28. Membuat balok beton bertulang (200 kg besi + bekisting) tiap 1m³
Harga bahan:
- Kayu Terentang balok m³ 0.32 2,826,516 904,485.12
- Paku biasa 2"-5" kg 3.2 19,286 61,715.20
- Minyak Bekisting lt 1.6 8,820 14,112.00
- Besi beton ulir kg 210 19,000 3,990,000.00
- Kawat beton kg 3 20,000 60,000.00
- Semen portland kg 336 1,300 436,800.00
- Pasir beton m³ 0.54 178,164 96,208.56
- Batu pecah/split 2/3 m³ 0.81 475,000 384,750.00
- Kayu Meranti Palembang balok m³ 0.14 4,500,000 630,000.00
- Triplek 4x8 ft 9 mm lbr 2.8 110,000 308,000.00
- Kayu dolken Ø 8-10/400 cm btg 16 11,878 190,048.00
Jumlah Harga Bahan 7,076,118.88
Upah tenaga:
- Pekerja Oh 6.35 140,000 889,000.00
- Tukang batu Oh 0.275 160,000 44,000.00
- Tukang kayu Oh 1.65 160,000 264,000.00
- Tukang besi Oh 1.4 160,000 224,000.00
- Kepala tukang Oh 0.333 180,000 59,940.00
- Mandor Oh 0.318 185,000 58,830.00
Jumlah Upah Tenaga 1,539,770.00
Jumlah Total 8,615,888.88
Jumlah Total + jasa 10% 9,477,450
29. Membuat balok beton bertulang (150 kg besi + bekisting) tiap 1m³
Harga bahan:
- Kayu Terentang balok m³ 0.21 2,826,516 593,568.36
- Paku biasa 2"-5" kg 3.2 19,286 61,715.20
- Minyak Bekisting lt 1.6 8,820 14,112.00
- Besi beton polos kg 150 12,000 1,800,000.00
- Kawat beton kg 2.25 20,000 45,000.00
- Semen portland kg 323 1,300 419,900.00
- Pasir beton m³ 0.52 178,164 92,645.28
- Batu pecah/split 2/3 m³ 0.78 475,000 370,500.00
- Triplek 4x8 ft 9 mm lbr 2.8 110,000 308,000.00
- Kayu dolken Ø 8-10/400 cm btg 16 11,878 190,048.00
Jumlah Harga Bahan 3,895,488.84
Upah tenaga:
- Pekerja Oh 5.8 140,000 812,000.00
- Tukang batu Oh 0.35 160,000 56,000.00
- Tukang kayu Oh 2.8 160,000 448,000.00
- Tukang besi Oh 1.05 160,000 168,000.00
90

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Kepala tukang Oh 0.42 180,000 75,600.00


- Mandor Oh 0.185 185,000 34,225.00
Jumlah Upah Tenaga 1,593,825.00

Jumlah Total 5,489,313.84


Jumlah Total + jasa 10% 6,038,200
30. Membuat dinding beton bertulang (150 kg besi + bekisting) tiap 1m³
Harga bahan:
- Kayu Terentang balok m³ 0.24 2,826,516 678,363.84
- Paku biasa 2"-5" kg 3.2 19,286 61,715.20
- Minyak Bekisting lt 1.6 8,820 14,112.00
- Besi beton polos kg 157.5 12,000 1,890,000.00
- Kawat beton kg 2.25 20,000 45,000.00
- Semen portland kg 336 1,300 436,800.00
- Pasir beton m³ 0.54 178,164 96,208.56
- Batu pecah/split 2/3 m³ 0.81 475,000 384,750.00
- Kayu Meranti Palembang balok m³ 0.16 4,500,000 720,000.00
- Triplek 4x8 ft 9 mm lbr 2.8 110,000 308,000.00
- Kayu dolken Ø 8-10/400 cm btg 24 11,878 285,072.00
Jumlah Harga Bahan 4,920,021.60
Upah tenaga:
- Pekerja Oh 5.3 140,000 742,000.00
- Tukang batu Oh 0.275 160,000 44,000.00
- Tukang kayu Oh 1.3 160,000 208,000.00
- Tukang besi Oh 1.05 160,000 168,000.00
- Kepala tukang Oh 0.262 180,000 47,160.00
- Mandor Oh 0.265 185,000 49,025.00
Jumlah Upah Tenaga 1,258,185.00
Jumlah Total 6,178,206.60
Jumlah Total + jasa 10% 6,796,000
31. Membuat tangga beton bertulang (200 kg besi + bekisting) tiap 1m³
Harga bahan:
- Kayu Terentang balok m³ 0.4 2,826,516 1,130,606.40
- Paku biasa 2"-5" kg 4 19,286 77,144.00
- Minyak Bekisting lt 1 8,820 8,820.00
- Besi beton polos kg 250 12,000 3,000,000.00
- Kawat beton kg 4 20,000 80,000.00
- Semen portland kg 377 1,300 490,100.00
- Pasir beton m³ 0.55 178,164 97,990.20
- Batu pecah/split 2/3 m³ 0.8156 475,000 387,410.00
Jumlah Harga Bahan 5,272,070.60

Pekerja Oh 5.65 140,000 791,000.00


- Tukang batu Oh 0.275 160,000 44,000.00
- Tukang kayu Oh 1.56 160,000 249,600.00
- Tukang besi Oh 1.4 160,000 224,000.00
- Kepala tukang Oh 0.323 180,000 58,140.00
91

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Mandor Oh 0.283 185,000 52,355.00


Jumlah Upah Tenaga 1,419,095.00
Jumlah Total 6,691,165.60
Jumlah Total + jasa 10% 7,360,250
30. Membuat beton ring balok dinding (150 kg besi + bekisting) tiap 1m³
Harga bahan:
- Kayu Terentang balok m³ 0.2 2,826,516 565,303.20
- Paku biasa 2"-5" kg 1.5 19,286 28,929.00
- Minyak Bekisting lt 0.4 8,820 3,528.00
- Besi beton polos kg 157.5 12,000 1,890,000.00
- Kawat beton kg 2.25 20,000 45,000.00
- Semen portland kg 336 1,300 436,800.00
- Pasir beton m³ 0.54 178,164 96,208.56
- Batu pecah/split 2/3 m³ 0.81 475,000 384,750.00
Jumlah Harga Bahan 3,450,518.76
Upah tenaga:
- Pekerja Oh 5.3 140,000 742,000.00
- Tukang batu Oh 0.275 160,000 44,000.00
- Tukang kayu Oh 1.3 160,000 208,000.00
- Tukang besi Oh 1.05 160,000 168,000.00
- Kepala tukang Oh 0.262 180,000 47,160.00
- Mandor Oh 0.265 185,000 49,025.00
Jumlah Upah Tenaga 1,258,185.00
Jumlah Total 4,708,703.76
Jumlah Total + jasa 10% 5,179,550
31. Membuat 1 unit pelat pondasi beton bertulang (100 x 100 x 20) cm
Harga bahan:
- Kayu Terentang balok m³ 0.048 2,826,516 135,672.77
- Paku biasa 2"-5" kg 0.36 19,286 6,942.96
- Minyak Bekisting lt 0.12 8,820 1,058.40
- Besi beton polos kg 30 12,000 360,000.00
- Kawat beton kg 0.43 20,000 8,600.00
- Semen portland kg 70 1,300 91,000.00
- Pasir beton m³ 0.097 178,164 17,281.91
- Batu pecah/split 2/3 m³ 0.1454 475,000 69,065.00
Jumlah Harga Bahan 689,621.04
Upah tenaga:
- Pekerja Oh 1.16 140,000 162,400.00
- Tukang batu Oh 0.105 160,000 16,800.00
- Tukang kayu Oh 0.312 160,000 49,920.00
- Tukang besi Oh 0.2 160,000 32,000.00
- Kepala tukang Oh 0.0617 180,000 11,106.00
- Mandor Oh 0.0446 185,000 8,251.00
Jumlah Upah Tenaga 280,477.00
Jumlah Total 970,098.04
Jumlah Total + jasa 10% 1,067,100
32. Membuat sloof beton bertulang (15 x 20) cm tiap 1 m'
92

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Harga bahan:
- Kayu Terentang papan 3 cm m³ 0.006 2,826,516 16,959.10
- Paku biasa 2"-5" kg 0.12 19,286 2,314.32
- Minyak Bekisting lt 0.04 8,820 352.80
- Besi beton polos kg 4.44 12,000 53,280.00
- Kawat beton kg 0.064 20,000 1,280.00
- Semen portland kg 10.5 1,300 13,650.00
- Pasir beton m³ 0.0146 178,164 2,601.19
- Batu pecah/split 2/3 m³ 0.022 475,000 10,450.00
Jumlah Harga Bahan 100,887.41
Upah tenaga:
- Pekerja Oh 0.21 140,000 29,400.00
- Tukang kayu Oh 0.104 160,000 16,640.00
- Tukang besi Oh 0.03 160,000 4,800.00
- Tukang batu Oh 0.0105 160,000 1,680.00
- Kepala tukang Oh 0.01445 180,000 2,601.00
- Mandor Oh 0.00627 185,000 1,159.95
Jumlah Upah Tenaga 56,280.95
Jumlah Total 157,168.36
Jumlah Total + jasa 10% 172,850
---> Pekerjaan Sloof Beton Bertulang 15x20 cm tiap 1 m3
- Pek. Sloof Beton Bertulang 15x20 m' 33.33 172,850 5,761,666.67 5,761,666.67
Dibulatkan 5,761,650
33. Membuat sloof beton bertulang (15 x 30) cm tiap 1 m'
Harga bahan:
- Kayu Terentang papan 3 cm m³ 0.009 2,826,516 25,438.64
- Paku biasa 2"-5" kg 0.18 19,286 3,471.48
- Minyak Bekisting lt 0.06 8,820 529.20
- Besi beton polos kg 6.53 12,000 78,360.00
- Kawat beton kg 0.094 20,000 1,880.00
- Semen portland kg 15.75 1,300 20,475.00
- Pasir beton m³ 0.022 178,164 3,919.61
- Batu pecah/split 2/3 m³ 0.033 475,000 15,675.00
Jumlah Harga Bahan 149,748.93
Upah tenaga:
- Pekerja Oh 0.3136 140,000 43,904.00
- Tukang kayu Oh 0.156 160,000 24,960.00
- Tukang besi Oh 0.0436 160,000 6,976.00
- Tukang batu Oh 0.0158 160,000 2,528.00
- Kepala tukang Oh 0.02154 180,000 3,877.20
- Mandor Oh 0.0094 185,000 1,739.00
Jumlah Upah Tenaga 83,984.20
Jumlah Total 233,733.13
Jumlah Total + jasa 10% 257,100
---> Pekerjaan Sloof Beton Bertulang 15x30 cm tiap 1 m3
- Pek. Sloof Beton Bertulang 15x30 m' 22.22 257,100 5,713,333.33 5,713,333.33
Dibulatkan 5,713,300
93

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

34. Membuat kolom penguat/praktis beton bertulang tiap 1m'


Harga bahan:
Harga bahan:
- Kayu Terentang balok m³ 0.2 2,826,516 565,303.20
- Paku biasa 2"-5" kg 1.5 19,286 28,929.00
- Minyak Bekisting lt 0.4 8,820 3,528.00
- Besi beton polos kg 157.5 12,000 1,890,000.00
- Kawat beton kg 2.25 20,000 45,000.00
- Semen portland kg 336 1,300 436,800.00
- Pasir beton m³ 0.54 178,164 96,208.56
- Batu pecah/split 2/3 m³ 0.81 475,000 384,750.00
Jumlah Harga Bahan 3,450,518.76
Upah tenaga:
- Pekerja Oh 5.3 140,000 742,000.00
- Tukang batu Oh 0.275 160,000 44,000.00
- Tukang kayu Oh 1.3 160,000 208,000.00
- Tukang besi Oh 1.05 160,000 168,000.00
- Kepala tukang Oh 0.262 180,000 47,160.00
- Mandor Oh 0.265 185,000 49,025.00
Jumlah Upah Tenaga 1,258,185.00
Jumlah Total 4,708,703.76
Jumlah Total + jasa 10% 5,179,550

35. Membuat kolom beton bertulang (11 x 20) cm tiap 1 m'


Harga bahan:
- Kayu Terentang balok m³ 0.003 2,826,516 8,479.55
- Paku biasa 2"-5" kg 0.02 19,286 385.72
- Besi beton polos kg 4.4 12,000 52,800.00
- Kawat beton kg 0.063 20,000 1,260.00
- Semen portland kg 7.7 1,300 10,010.00
- Pasir beton m³ 0.011 178,164 1,959.80
- Batu pecah/split 2/3 m³ 0.016 475,000 7,600.00
Jumlah Harga Bahan 82,495.07
Upah tenaga:
- Pekerja Oh 0.1273 140,000 17,822.00
- Tukang kayu Oh 0.047 160,000 7,520.00
- Tukang besi Oh 0.03 160,000 4,800.00
- Tukang batu Oh 0.0077 160,000 1,232.00
- Kepala tukang Oh 0.0085 180,000 1,530.00
- Mandor Oh 0.0044 185,000 814.00
Jumlah Upah Tenaga 33,718.00
Jumlah Total 116,213.07
Jumlah Total + jasa 10% 127,800
36. Membuat kolom beton bertulang (11 x 30) cm tiap 1 m'
Harga bahan:
- Kayu Terentang balok m³ 0.008 2,826,516 22,612.13
94

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Paku biasa 2"-5" kg 0.05 19,286 964.30


- Besi beton polos kg 6.49 12,000 77,880.00
- Kawat beton kg 0.1 20,000 2,000.00
- Semen portland kg 11.55 1,300 15,015.00
- Pasir beton m³ 0.016 178,164 2,850.62
- Batu pecah/split 2/3 m³ 0.024 475,000 11,400.00
Jumlah Harga Bahan 132,722.05
Upah tenaga:
- Pekerja Oh 0.254 140,000 35,560.00
- Tukang kayu Oh 0.125 160,000 20,000.00
- Tukang besi Oh 0.044 160,000 7,040.00
- Tukang batu Oh 0.0116 160,000 1,856.00
- Kepala tukang Oh 0.018 180,000 3,240.00
- Mandor Oh 0.008 185,000 1,480.00
Jumlah Upah Tenaga 69,176.00
Jumlah Total 201,898.05
Jumlah Total + jasa 10% 222,050
37. Membuat kolom beton bertulang (30 x 30) cm tiap 1 m'
Harga bahan:
- Kayu Terentang papan 3 cm m³ 0.048 2,826,516 135,672.77
- Paku biasa 2"-5" kg 0.48 19,286 9,257.28
- Minyak Bekisting lt 0.24 8,820 2,116.80
- Kayu Terentang balok m³ 0.018 2,826,516 50,877.29
- Triplek 4x8 ft 9 mm lbr 0.42 110,000 46,200.00
- Kayu dolken Ø 8-10/400 cm btg 2.4 11,878 28,507.20
- Besi beton ulir kg 16.2 19,000 307,800.00
- Kawat beton kg 0.24 20,000 4,800.00
- Semen portland kg 31.5 1,300 40,950.00
- Pasir beton m³ 0.044 178,164 7,839.22
- Batu pecah/split 2/3 m³ 0.066 475,000 31,350.00
Jumlah Harga Bahan 665,370.55
Upah tenaga:
- Pekerja Oh 0.648 140,000 90,720.00
- Tukang kayu Oh 0.396 160,000 63,360.00
- Tukang besi Oh 0.108 160,000 17,280.00
- Tukang batu Oh 0.0315 160,000 5,040.00
- Kepala tukang Oh 0.05355 180,000 9,639.00
- Mandor Oh 0.0209 185,000 3,866.50
Jumlah Upah Tenaga 189,905.50
Jumlah Total 855,276.05
---> Jumlah Total + jasa 10% 940,800
Pekerjaan Kolom Beton Struktur 30x30 cm tiap 1 m3
- Kolom Beton Bertulang 30x30 m' 11.11 940,800 10,453,333.33 10,453,333.33
Jumlah Total + jasa 10% 11,498,650
38. Membuat ring balok beton bertulang (10 x 15) cm tiap 1m'
Harga bahan:
- Kayu Terentang papan 3 cm m³ 0.003 2,826,516 8,479.55
95

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Paku biasa 2"-5" kg 0.02 19,286 385.72


- Besi beton polos kg 3.6 12,000 43,200.00
- Kawat beton kg 0.05 20,000 1,000.00
- Semen portland kg 5.5 1,300 7,150.00
- Pasir beton m³ 0.009 178,164 1,603.48
- Batu pecah/split 2/3 m³ 0.015 475,000 7,125.00
Jumlah Harga Bahan 68,943.74
Upah tenaga:
- Pekerja Oh 0.297 140,000 41,580.00
- Tukang batu Oh 0.033 160,000 5,280.00
- Tukang kayu Oh 0.033 160,000 5,280.00
- Tukang besi Oh 0.033 160,000 5,280.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.015 185,000 2,775.00
Jumlah Upah Tenaga 61,995.00
Jumlah Total 130,938.74
---> Jumlah Total + jasa 10% 144,000
Pekerjaan Ring Balok 10x15 cm tiap 1 m3
- Kolom Penguat/praktis beton bertulang 10 m' 66.67 144,000 9,600,000.00 9,600,000.00
Dibulatkan 9,600,000
39. Membuat pelat lantai beton bertulang tebal 15cm tiap 1 m²
Harga bahan:
- Kayu Terentang papan 3 cm m³ 0.04 2,826,516 113,060.64
- Kayu Terentang balok m³ 0.015 2,826,516 42,397.74
- Paku biasa 2"-5" kg 0.4 19,286 7,714.40
- Minyak Bekisting lt 0.2 8,820 1,764.00
- Kayu dolken Ø 8-10/400 cm btg 4.5 11,878 53,451.00
- Besi beton polos kg 12.95 12,000 155,400.00
- Kawat beton kg 0.185 20,000 3,700.00
- Semen portland kg 42 1,300 54,600.00
- Pasir beton m³ 0.0582 178,164 10,369.14
- Batu pecah/split 2/3 m³ 0.0873 475,000 41,467.50
Jumlah Harga Bahan 483,924.42
Upah tenaga:
- Pekerja Oh 0.647 140,000 90,580.00
- Tukang kayu Oh 0.33 160,000 52,800.00
- Tukang besi Oh 0.087 160,000 13,920.00
- Tukang batu Oh 0.042 160,000 6,720.00
- Kepala tukang Oh 0.0459 180,000 8,262.00
- Mandor Oh 0.0217 185,000 4,014.50
Jumlah Upah Tenaga 176,296.50
Jumlah Total 660,220.92
---> Jumlah Total + jasa 10% 726,200
Pekerjaan Plat Lantai Beton Tebal 15 cm tiap 1 m3
- Pek. Plat Lantai Beton m2 8.33 726,200 6,051,666.67 6,051,666.67
Dibulatkan 6,051,650
40. Membuat pelat atap beton bertulang tebal 12 cm tiap 1 m²
96

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Harga bahan:
- Kayu Terentang balok m³ 0.04 2,826,516 113,060.64
- Kayu Meranti Palembang balok m³ 0.015 4,500,000 67,500.00
- Paku biasa 2"-5" kg 0.4 19,286 7,714.40
- Residu lt 0.2 18,581 3,716.20
- Kayu dolken Ø 8-10/400 cm btg 3.5 11,878 41,573.00
- Besi beton polos kg 8 12,000 96,000.00
- Kawat beton kg 0.1 20,000 2,000.00
- Semen portland kg 35 1,300 45,500.00
- Pasir beton m³ 0.04 178,164 7,126.56
- Batu pecah/split 2/3 m³ 0.07 475,000 33,250.00
Jumlah Harga Bahan 417,440.80
Upah tenaga:
- Pekerja Oh 0.5 140,000 70,000.00
- Tukang kayu Oh 0.33 160,000 52,800.00
- Tukang besi Oh 0.0587 160,000 9,392.00
- Tukang batu Oh 0.035 160,000 5,600.00
- Kepala tukang Oh 0.004 180,000 720.00
- Mandor Oh 0.001 185,000 185.00
Jumlah Upah Tenaga 138,697.00
Jumlah Total 556,137.80
---> Jumlah Total + jasa 10% 611,750
Pekerjaan Plat Lantai Beton tebal 12 cm, tiap 1 m3
- Pek. Plat Lantai Beton tebal 12 cm m2 10.00 611,750 6,117,500.00 6,117,500.00
41. Membuat pelat atap beton bertulang tebal 12 cm tiap 1 m² dengan bekisting bondek
Harga bahan:
- Kayu Terentang balok m³ 0.003 2,826,516 8,479.55
- Superdek BMT 0.70 mm m2 1 159,500 159,500.00
- Paku biasa 2"-5" kg 0.1 19,286 1,928.60
- Sewa Scafolding m2 1.1 33,000 36,300.00
- Besi wermest dia. 8 mm m2 2.2 60,000 132,000.00
- Kawat beton kg 2.232 20,000 44,640.00
- Ready Mix K225 m³ 0.125 1,509,500 188,687.50
Jumlah Harga Bahan 571,535.65
Upah tenaga:
- Pekerja Oh 0.5 140,000 70,000.00
- Tukang kayu Oh 0.33 160,000 52,800.00
- Tukang besi Oh 0.0587 160,000 9,392.00
- Tukang batu Oh 0.035 160,000 5,600.00
- Kepala tukang Oh 0.004 180,000 720.00
- Mandor Oh 0.001 185,000 185.00
Jumlah Upah Tenaga 138,697.00
Jumlah Total 710,232.65
---> Jumlah Total + jasa 10% 781,250
Pekerjaan Plat Lantai Beton tebal 12 cm, tiap 1 m3 + bekisting bondek
- Pek. Plat Lantai Beton tebal 12 cm m2 10.00 781,250 7,812,500.00 7,812,500.00
97

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

42. Membuat pelat meja beton bertulang tebal 8 cm tiap 1 m²


Harga bahan:
- Kayu Terentang balok m³ 0.004 2,826,516 11,306.06
- Paku biasa 2"-5" kg 0.18 19,286 3,471.48
- Triplek 4x8 ft 9 mm lbr 0.35 110,000 38,500.00
- Besi beton polos kg 4.15 12,000 49,800.00
- Kawat beton kg 0.06 20,000 1,200.00
- Semen portland kg 28 1,300 36,400.00
- Pasir beton m³ 0.039 178,164 6,948.40
- Batu pecah/split 2/3 m³ 0.058 475,000 27,550.00
Jumlah Harga Bahan 175,175.94
- Pekerja Oh 0.347 140,000 48,580.00
- Tukang kayu Oh 0.165 160,000 26,400.00
- Tukang besi Oh 0.027 160,000 4,320.00
- Tukang batu Oh 0.028 160,000 4,480.00
- Kepala tukang Oh 0.0215 180,000 3,870.00
- Mandor Oh 0.0122 185,000 2,257.00
Jumlah Upah Tenaga 89,907.00
Jumlah Total 265,082.94
Jumlah Total + jasa 10% 291,550
--->
Pekerjaan Plat Meja Beton tebal 8 cm, tiap 1 m3
- Pek. Plat Meja Beton tebal 8 cm m2 12.50 291,550 3,644,375.00 3,644,375.00
Dibulatkan 3,644,350
43. Plat Duiker Pintu Masuk, lebar saluran 0,5 m tiap 1 m' (Tebal plat 10 cm)
- Pekerjaan beton 1:2:3 m3 0.7000 1,372,250 960,575.00
- Bekesting papan m2 0.5000 502,750 251,375.00
- Besi beton dia 10 mm, 2 lapis jarak 15 cm kg 9.5020 16,700 158,683.40
- Besi beton dia 8 mm, 2 lapis jarak 20 cm kg 2.6070 16,700 43,536.90
Jumlah Total 1,414,170.30
Jumlah Total + jasa 10% 1,555,550
44. Plat Duiker Pintu Masuk, lebar saluran 0,75 m tiap 1 m' (Tebal plat 12,5 cm)
- Pekerjaan beton 1:2:3 m3 0.1190 1,372,250 163,297.75
- Bekesting papan m2 0.7500 502,750 377,062.50
- Besi beton dia 10 mm, 2 lapis jarak 15 cm kg 10.8590 16,700 181,345.30
- Besi beton dia 8 mm, 2 lapis jarak 20 cm kg 2.6070 16,700 43,536.90
Jumlah Total 765,242.45
Jumlah Total + jasa 10% 841,750
45. Plat Duiker Pintu Masuk, lebar saluran 1 m tiap 1 m' (Tebal plat 15 cm)
- Pekerjaan beton 1:2:3 m3 0.1800 1,372,250 247,005.00
- Bekesting papan m2 1.0000 502,750 502,750.00
- Besi beton dia 10 mm, 2 lapis jarak 15 cm kg 16.2890 16,700 272,026.30
- Besi beton dia 8 mm, 2 lapis jarak 20 cm kg 5.2140 16,700 87,073.80
Jumlah Total 1,108,855.10
Jumlah Total + jasa 10% 1,219,700

46. Pasang Plastik Cor tiap 1m²


98

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Harga bahan:
- Plastik Cor m² 1.05 4,500 4,725.00
Jumlah Harga Bahan 4,725.00
Upah tenaga:
- Pekerja Oh 0.01 140,000 1,400.00
Jumlah Upah Tenaga 1,400.00
Jumlah Total 6,125.00
Jumlah Total + jasa 10% 6,700

K PEKERJAAN PENUTUP ATAP

1. Pasang atap genteng plentong natural tiap 1m²


Harga bahan:
- Genteng plentong kecil natural bh 25 1,800 45,000.00
Jumlah Harga Bahan 45,000.00
Upah tenaga:
- Pekerja Oh 0.15 140,000 21,000.00
- Tukang kayu Oh 0.075 160,000 12,000.00
- Kepala tukang Oh 0.008 180,000 1,440.00
- Mandor Oh 0.008 185,000 1,480.00
Jumlah Upah Tenaga 35,920.00
Jumlah Total 80,920.00
Jumlah Total + jasa 10% 89,000
2. Pasang atap genteng plentong besar/super tiap 1m²
Harga bahan:
- Genteng plentong super/besar bh 12 3,600 43,200.00
Jumlah Harga Bahan 43,200.00
Upah tenaga:
- Pekerja Oh 0.15 140,000 21,000.00
- Tukang kayu Oh 0.06 160,000 9,600.00
- Kepala tukang Oh 0.006 180,000 1,080.00
- Mandor Oh 0.008 185,000 1,480.00
Jumlah Upah Tenaga 33,160.00
Jumlah Total 76,360.00
Jumlah Total + jasa 10% 83,950
3. Pasang atap genteng kodok tiap 1m²
Harga bahan:
- Genteng kodok natural bh 25 3,000 75,000.00
Jumlah Harga Bahan 75,000.00
Upah tenaga:
- Pekerja Oh 0.15 140,000 21,000.00
- Tukang kayu Oh 0.075 160,000 12,000.00
- Kepala tukang Oh 0.008 180,000 1,440.00
- Mandor Oh 0.008 185,000 1,480.00
Jumlah Upah Tenaga 35,920.00
Jumlah Total 110,920.00
Jumlah Total + jasa 10% 122,000
99

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

4. Pasang atap genteng keramik Kanmuri natural tiap 1m²


Harga bahan:
- Genteng keramik Kanmuri natural bh 14 6,115 85,610.00
Jumlah Harga Bahan 85,610.00
Upah tenaga:
- Pekerja Oh 0.15 140,000 21,000.00
- Tukang kayu Oh 0.06 160,000 9,600.00
- Kepala tukang Oh 0.006 180,000 1,080.00
- Mandor Oh 0.008 185,000 1,480.00
Jumlah Upah Tenaga 33,160.00
Jumlah Total 118,770.00
Jumlah Total + jasa 10% 130,600
5. Pasang atap genteng keramik Ikad natural tiap 1m²
Harga bahan:
- Genteng keramik M Class bh 15 14,347 215,205.00
Jumlah Harga Bahan 215,205.00
Upah tenaga:
- Pekerja Oh 0.15 140,000 21,000.00
- Tukang kayu Oh 0.06 160,000 9,600.00
- Kepala tukang Oh 0.006 180,000 1,080.00
- Mandor Oh 0.008 185,000 1,480.00
Jumlah Upah Tenaga 33,160.00
Jumlah Total 248,365.00
Jumlah Total + jasa 10% 273,200
6. Pasang atap genteng beton Monier standar tiap 1m²
Harga bahan:
- Genteng beton Monier standar bh 11 7,997 87,967.00
- Paku biasa 2"-5" kg 0.03 19,286 578.58
Jumlah Harga Bahan 88,545.58
Upah tenaga:
- Pekerja Oh 0.2 140,000 28,000.00
- Tukang kayu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.01 185,000 1,850.00
Jumlah Upah Tenaga 47,650.00
Jumlah Total 136,195.58
Jumlah Total + jasa 10% 149,800
7. Pasang atap genteng metal tiap 1m²
Harga bahan:
- Genteng metal m² 1.04 74,980 77,979.20
- Paku biasa 2"-5" kg 0.2 19,286 3,857.20
Jumlah Harga Bahan 81,836.40
Upah tenaga:
- Pekerja Oh 0.2 85,000 17,000.00
- Tukang kayu Oh 0.1 110,000 11,000.00
- Kepala tukang Oh 0.01 130,000 1,300.00
- Mandor Oh 0.001 140,000 140.00
100

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Upah Tenaga 29,440.00


Jumlah Total 111,276.40
Jumlah Total + jasa 10% 122,400
8. Pasang atap asbes gelombang 2,5 x 0,92 m x 5 mm tiap 1m²
Harga bahan:
- Asbes gelombang 2,5x,92 m 5 mm lbr 0.5 63,450 31,725.00
- Paku sekrup 3,5" bh 4 450 1,800.00
Jumlah Harga Bahan 33,525.00
Upah tenaga:
- Pekerja Oh 0.14 140,000 19,600.00
- Tukang kayu Oh 0.075 160,000 12,000.00
- Kepala tukang Oh 0.008 180,000 1,440.00
- Mandor Oh 0.008 185,000 1,480.00
Jumlah Upah Tenaga 34,520.00
Jumlah Total 68,045.00
Jumlah Total + jasa 10% 74,800
9. Pasang atap asbes gelombang 2,25 x 0,92 m x 5 mm tiap 1m²
Harga bahan:
- Asbes gelombang 2,25x,92 m 5 mm lbr 0.6 68,250 40,950.00
- Paku sekrup 3,5" bh 4 450 1,800.00
Jumlah Harga Bahan 42,750.00
Upah tenaga:
- Pekerja Oh 0.14 140,000 19,600.00
- Tukang kayu Oh 0.075 160,000 12,000.00
- Kepala tukang Oh 0.008 180,000 1,440.00
- Mandor Oh 0.008 185,000 1,480.00
Jumlah Upah Tenaga 34,520.00
Jumlah Total 77,270.00
Jumlah Total + jasa 10% 84,950
10. Pasang atap asbes gelombang 2,00 x 0,92 m x 5 mm tiap 1m²
Harga bahan:
- Asbes gelombang 2,00x,92 m 5 mm lbr 0.6 49,000 29,400.00
- Paku sekrup 3,5" bh 4 450 1,800.00
Jumlah Harga Bahan 31,200.00
Upah tenaga:
- Pekerja Oh 0.14 140,000 19,600.00
- Tukang kayu Oh 0.07 160,000 11,200.00
- Kepala tukang Oh 0.007 180,000 1,260.00
- Mandor Oh 0.007 185,000 1,295.00
Jumlah Upah Tenaga 33,355.00
Jumlah Bahan & Tenaga 64,555.00
Jumlah Total + jasa 10% 71,000
11. Pasang atap asbes gelombang 1,80 x 0,92 m x 5 mm tiap 1m²
Harga bahan:
- Asbes gelombang 1,80x,92 m 5 mm lbr 0.75 48,200 36,150.00
- Paku sekrup 3,5" bh 4 450 1,800.00
Jumlah Harga Bahan 37,950.00
101

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Pekerja Oh 0.14 140,000 19,600.00


- Tukang kayu Oh 0.07 160,000 11,200.00
- Kepala tukang Oh 0.007 180,000 1,260.00
- Mandor Oh 0.007 185,000 1,295.00
Jumlah Upah Tenaga 33,355.00
Jumlah Total 71,305.00
Jumlah Total + jasa 10% 78,400
12. Pasang atap seng gelombang BJLS 25 (0,25 mm) tiap 1m²
Harga bahan:
- Seng gelombang 3x6 ft BJLS 25 (0,25 mm Lbr 0.7 169,579 118,705.30
- Paku biasa 1/2"- 1" kg 0.02 19,286 385.72
Jumlah Harga Bahan 119,091.02
Upah tenaga:
- Pekerja Oh 0.12 140,000 16,800.00
- Tukang kayu Oh 0.06 160,000 9,600.00
- Kepala tukang Oh 0.006 180,000 1,080.00
- Mandor Oh 0.006 185,000 1,110.00
Jumlah Upah Tenaga 28,590.00
Jumlah Total 147,681.02
Jumlah Total + jasa 10% 162,400
13. Pasang atap spandek tiap 1m²
Harga bahan:
- Spandek m² 1.00 77,000 77,000.00
- angkur pengikat atap kg 4.00 27,000 108,000.00
Jumlah Harga Bahan 185,000.00
Upah tenaga:
- Pekerja Oh 0.08 140,000 11,200.00
- Tukang besi Oh 0.08 160,000 12,800.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.01 185,000 1,850.00
Jumlah Upah Tenaga 27,650.00
Jumlah Total 212,650.00
Jumlah Total + jasa 10% 233,900
14. Pasang atap Fibreglass ukuran 180 X 90 cm tiap 1 m2
Harga bahan:
- Atap Fibreglass m² 1.00 17,400 17,400.00
- Paku biasa 2"-5" kg 0.05 19,286 964.30
Jumlah Harga Bahan 18,364.30
Upah tenaga:
- Pekerja Oh 0.14 140,000 19,600.00
- Tukang besi Oh 0.07 160,000 11,200.00
- Kepala tukang Oh 0.007 180,000 1,260.00
- Mandor Oh 0.007 185,000 1,295.00
Jumlah Upah Tenaga 33,355.00
Jumlah Total 51,719.30
Jumlah Total + jasa 10% 56,850
15. Pasang alumunium foil tiap 1m²
102

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Harga bahan:
- Allumunium foil m² 1.05 12,500 13,125.00
Jumlah Harga Bahan 13,125.00
Upah tenaga:
- Pekerja Oh 0.15 140,000 21,000.00
- Tukang besi Oh 0.05 160,000 8,000.00
- Kepala tukang Oh 0.005 180,000 900.00
- Mandor Oh 0.008 185,000 1,480.00
Jumlah Upah Tenaga 31,380.00
Jumlah Total 44,505.00
Jumlah Total + jasa 10% 48,950
16. Pasang glasswool tiap 1m²
Harga bahan:
- Glasswool BG 50 m² 1.05 20,850 21,892.50
Jumlah Harga Bahan 21,892.50
Upah tenaga:
- Pekerja Oh 0.15 140,000 21,000.00
- Tukang besi Oh 0.05 160,000 8,000.00
- Kepala tukang Oh 0.005 180,000 900.00
- Mandor Oh 0.008 185,000 1,480.00
Jumlah Upah Tenaga 31,380.00
Jumlah Total 53,272.50
Jumlah Total + jasa 10% 58,550
17. Pasang Nok genteng plentong tiap 1m'
Harga bahan:
- Nok genteng plentong kecil natural bh 5 4,116 20,580.00
- Semen portland kg 8 1,300 10,400.00
- Pasir pasang m³ 0.032 178,164 5,701.25
Jumlah Harga Bahan 36,681.25
Upah tenaga:
- Pekerja Oh 0.4 140,000 56,000.00
- Tukang kayu Oh 0.2 160,000 32,000.00
- Kepala tukang Oh 0.02 180,000 3,600.00
- Mandor Oh 0.002 185,000 370.00
Jumlah Upah Tenaga 91,970.00
Jumlah Total 128,651.25
Jumlah Total + jasa 10% 141,500
18. Pasang Nok genteng plentong besar tiap 1m'
Harga bahan:
- Nok genteng plentong super/besar bh 4 4,500 18,000.00
- Semen portland kg 9.6 1,300 12,480.00
- Pasir pasang m³ 0.0384 178,164 6,841.50
Jumlah Harga Bahan 37,321.50
Upah tenaga:
- Pekerja Oh 0.4 140,000 56,000.00
- Tukang kayu Oh 0.2 160,000 32,000.00
- Kepala tukang Oh 0.02 180,000 3,600.00
103

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Mandor Oh 0.002 185,000 370.00


Jumlah Upah Tenaga 91,970.00
Jumlah Total 129,291.50
Jumlah Total + jasa 10% 142,200
19. Pasang Nok genteng keramik Kanmuri tiap 1m'
Harga bahan:
- Nok genteng keramik Kanmuri natural bh 3.5 10,231 35,808.50
- Semen portland kg 9.6 1,300 12,480.00
- Pasir pasang m³ 0.0384 178,164 6,841.50
Jumlah Harga Bahan 55,130.00
Upah tenaga:
- Pekerja Oh 0.4 140,000 56,000.00
- Tukang kayu Oh 0.2 160,000 32,000.00
- Kepala tukang Oh 0.02 180,000 3,600.00
- Mandor Oh 0.002 185,000 370.00
Jumlah Upah Tenaga 91,970.00
Jumlah Total 147,100.00
Jumlah Total + jasa 10% 161,800
20. Pasang Nok genteng keramik M Class tiap 1m'
Harga bahan:
- Nok genteng keramik M Class bh 4 55,625 222,500.00
- Semen portland kg 9.6 1,300 12,480.00
- Pasir pasang m³ 0.0384 178,164 6,841.50
Jumlah Harga Bahan 241,821.50
Upah tenaga:
- Pekerja Oh 0.4 140,000 56,000.00
- Tukang kayu Oh 0.2 160,000 32,000.00
- Kepala tukang Oh 0.02 180,000 3,600.00
- Mandor Oh 0.002 185,000 370.00
Jumlah Upah Tenaga 91,970.00
Jumlah Total 333,791.50
Jumlah Total + jasa 10% 367,150
21. Pasang Nok genteng beton tiap 1m'
Harga bahan:
- Nok genteng beton Monier standar bh 3.5 10,114 35,399.00
- Paku biasa 2"-5" kg 0.05 19,286 964.30
- Semen portland kg 10.8 1,300 14,040.00
- Pasir pasang m³ 0.032 178,164 5,701.25
- Semen warna kg 1 2,375 2,375.00
Jumlah Harga Bahan 58,479.55
Upah tenaga:
- Pekerja Oh 0.4 140,000 56,000.00
- Tukang kayu Oh 0.2 160,000 32,000.00
- Kepala tukang Oh 0.02 180,000 3,600.00
- Mandor Oh 0.002 185,000 370.00
Jumlah Upah Tenaga 91,970.00
Jumlah Total 150,449.55
104

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Total + jasa 10% 165,450


22. Pasang nok genteng metal tiap 1m'
Harga bahan:
- Nok genteng metal bh 1.1 35,000 38,500.00
- Paku biasa 1/2"- 1" kg 0.05 19,286 964.30
Jumlah Harga Bahan 39,464.30
Upah tenaga:
- Pekerja Oh 0.25 140,000 35,000.00
- Tukang kayu Oh 0.15 160,000 24,000.00
- Kepala tukang Oh 0.015 180,000 2,700.00
- Mandor Oh 0.013 185,000 2,405.00
Jumlah Upah Tenaga 64,105.00
Jumlah Total 103,569.30
Jumlah Total + jasa 10% 113,900
23. Pasang nok/bubung stel gelombang 0,92 m tiap 1m'
Harga bahan:
- Nok stel gelombang lbr 2.4 36,250 87,000.00
- Paku sekrup 3,5" bh 6 450 2,700.00
Jumlah Harga Bahan 89,700.00
Upah tenaga:
- Pekerja Oh 0.084 140,000 11,760.00
- Tukang kayu Oh 0.125 160,000 20,000.00
- Kepala tukang Oh 0.013 180,000 2,340.00
- Mandor Oh 0.004 185,000 740.00
Jumlah Upah Tenaga 34,840.00
Jumlah Total 124,540.00
Jumlah Total + jasa 10% 136,950
24. Pasang nok paten 0,92 m tiap 1m'
Harga bahan:
- Nok paten lbr 1.2 57,000 68,400.00
- Paku sekrup 3,5" bh 6 450 2,700.00
Jumlah Harga Bahan 71,100.00
Upah tenaga:
- Pekerja Oh 0.084 140,000 11,760.00
- Tukang kayu Oh 0.125 160,000 20,000.00
- Kepala tukang Oh 0.013 180,000 2,340.00
- Mandor Oh 0.004 185,000 740.00
Jumlah Upah Tenaga 34,840.00
Jumlah Total 105,940.00
Jumlah Total + jasa 10% 116,500
25. Pasang nok stel rata 0,92 m tiap 1m'
Harga bahan:
- Nok stel rata lbr 1.1 60,750 66,825.00
- Paku sekrup 3,5" bh 6 450 2,700.00
Jumlah Harga Bahan 69,525.00
Upah tenaga:
- Pekerja Oh 0.1 140,000 14,000.00
105

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Tukang kayu Oh 0.15 160,000 24,000.00


- Kepala tukang Oh 0.013 180,000 2,340.00
- Mandor Oh 0.004 185,000 740.00
Jumlah Upah Tenaga 41,080.00
Jumlah Total 110,605.00
Jumlah Total + jasa 10% 121,650
26. Pasang atap nok seng tiap 1m'
Harga bahan:
- Seng plat 3x6 ft BJLS 25 (0,25 mm) Lbr 0.3 44,570 13,371.00
- Paku biasa 1/2"- 1" kg 0.04 19,286 771.44
Jumlah Harga Bahan 14,142.44
Upah tenaga:
- Pekerja Oh 0.15 140,000 21,000.00
- Tukang kayu Oh 0.07 160,000 11,200.00
- Kepala tukang Oh 0.008 180,000 1,440.00
- Mandor Oh 0.006 185,000 1,110.00
Jumlah Upah Tenaga 34,750.00
Jumlah Total 48,892.44
Jumlah Total + jasa 10% 53,750
27. Pasang nok asbes tiap 1m'
Harga bahan:
- Nok asbes bh 1.100 26,350 28,985.00
- Paku asbes bh 6.000 75 450.00
Jumlah Harga Bahan 29,435.00
Upah tenaga:
- Pekerja Oh 0.084 140,000 11,760.00
- Tukang kayu Oh 0.125 160,000 20,000.00
- Kepala tukang Oh 0.013 180,000 2,340.00
- Mandor Oh 0.004 185,000 740.00
Jumlah Upah Tenaga 34,840.00
Jumlah Total 64,275.00
Jumlah Total + jasa 10% 70,700
28. Pasang nok spandek standar tiap 1m'
Harga bahan:
- Nok spandek standar m' 1.1 65,000 71,500.00
- angkur pengikat atap kg 0.04 27,000 1,080.00
Jumlah Harga Bahan 72,580.00
Upah tenaga:
- Pekerja Oh 0.15 140,000 21,000.00
- Tukang besi Oh 0.07 160,000 11,200.00
- Kepala tukang Oh 0.008 180,000 1,440.00
- Mandor Oh 0.006 185,000 1,110.00
Jumlah Upah Tenaga 34,750.00
Jumlah Total 107,330.00
Jumlah Total + jasa 10% 118,050
29. Pasang Flashing tiap 1m'
Harga bahan:
106

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Flashing m' 1.1 25,284 27,812.40


- angkur pengikat atap kg 0.56 27,000 15,120.00
Jumlah Harga Bahan 42,932.40
Upah tenaga:
- Pekerja Oh 0.53 140,000 74,200.00
- Tukang kayu Oh 0.25 160,000 40,000.00
- Kepala tukang Oh 0.02 180,000 3,600.00
- Mandor Oh 0.002 185,000 370.00
Jumlah Upah Tenaga 118,170.00
Jumlah Total 161,102.40
Jumlah Total + jasa 10% 177,200
30. Pasang atap policarbonat tiap 1 m2
Harga bahan:
- Policarbonat m2 1.0500 253,350 266,017.50
- Besi rangka kg 7.0000 8,200 57,400.00
- Paku sekrup 3,5" bh 9.0000 450 4,050.00
Jumlah Harga Bahan 327,467.50
Upah tenaga:
- Pekerja Oh 0.5000 140,000 70,000.00
- Tukang besi Oh 0.5000 160,000 80,000.00
- Kepala tukang Oh 0.0500 180,000 9,000.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 159,462.50
Jumlah Total 486,930.00
Jumlah Total + jasa 10% 535,600
31. Pas. Rangka hollow tbl. 0.6 mm tiap 1 m²
Harga bahan:
- Hollow 4x4 cm tbl 0.6 mm btg 1.25 46,350 57,937.50
- Hollow 2x4 cm tbl 0.6 mm btg 0.8 36,050 28,840.00
- Paku rivet bh 4 50 200.00
- Sekrup 6x1-1,5 bh 8 100 800.00
- Amplas lbr 0.5 5,880 2,940.00
Jumlah Harga Bahan 90,717.50
Upah tenaga:
- Pekerja Oh 0.2 140,000 28,000.00
- Tukang gypsum Oh 0.30 180,000 54,000.00
- Tukang alumunium Oh 0.20 180,000 36,000.00
- Mandor Oh 0.02 185,000 2,775.00
Jumlah Upah Tenaga 120,775
Jumlah Total 211,492.50
Jumlah Total + jasa 10% 232,600

32. Pasang rangka atap baja ringan zincalum untuk atap metal roof tiap 1 m²
Harga bahan:
- Baja truss C 75.75.5 m¹ 4.07 15,333 62,406.67
- Reng U 50 m¹ 3.1 7,833 24,283.33
- Screw/dynabolt Pcs 35 500 17,500.00
107

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Harga Bahan 104,190.00


Upah tenaga:
- Pekerja Oh 0.1 140,000 14,000.00
- Tukang besi Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.056 180,000 10,080.00
- Mandor Oh 0.01 185,000 1,850.00
Jumlah Upah Tenaga 41,930.00
Jumlah Total 146,120.00
Jumlah Total + jasa 10% 160,700

33. Pas. Ralling tangga besi hollow tbl. 0.6 mm tiap 1 m²


Harga bahan:
- Hollow 4x4 cm tbl 0.6 mm btg 1.5 46,350 69,525.00
- Hollow 2x4 cm tbl 0.6 mm btg 1.3 36,050 46,865.00
- las 15 % dari bahan ls 0.15 116,390 17,458.50
- Amplas lbr 2 5,880 11,760.00
Jumlah Harga Bahan 145,608.50
Upah tenaga:
- Pekerja Oh 0.2 140,000 28,000.00
- Tukang las Oh 0.30 160,000 48,000.00
- Tukang alumunium Oh 0.20 180,000 36,000.00
- Mandor Oh 0.02 185,000 2,775.00
Jumlah Upah Tenaga 114,775
Jumlah Total 260,383.50
Jumlah Total + jasa 10% 286,400

L PEKERJAAN SANITASI

1. Memasang 1 buah kloset duduk/monoblok (lux)


Harga bahan:
- Kloset duduk ex KIA (LUX) bh 1 3,149,328 3,149,328.00
- Perlengkapan (6% harga kloset) % 6 3,149,328 188,959.68
Jumlah Harga Bahan 3,338,287.68
Upah tenaga:
- Pekerja Oh 3.3 140,000 462,000.00
- Tukang batu Oh 1.1 160,000 176,000.00
- Kepala tukang Oh 0.001 180,000 180.00
- Mandor Oh 0.16 185,000 29,600.00
Jumlah Upah Tenaga 667,780.00
Jumlah Total 4,006,067.68
Jumlah Total + jasa 10% 4,406,650
2. Memasang 1 buah kloset duduk/monoblok setara INA (sedang)
Harga bahan:
- Kloset duduk setara TOTO (LUX) bh 1 2,520,050 2,520,050.00
- Perlengkapan (6% harga kloset) % 6 2,520,050 151,203.00
Jumlah Harga Bahan 2,671,253.00
Upah tenaga:
108

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Pekerja Oh 3.3 140,000 462,000.00


- Tukang batu Oh 1.1 160,000 176,000.00
- Kepala tukang Oh 0.001 180,000 180.00
- Mandor Oh 0.16 185,000 29,600.00
Jumlah Upah Tenaga 667,780.00
Jumlah Total 3,339,033.00
Jumlah Total + jasa 10% 3,672,900
3. Memasang 1 buah kloset duduk/monoblok
Harga bahan:
- Kloset duduk Toto lengkap bh 1 2,406,000 2,406,000.00
- Perlengkapan (6% harga kloset) % 6 2,406,000 144,360.00
Jumlah Harga Bahan 2,550,360.00
Upah tenaga:
- Pekerja Oh 3.3 140,000 462,000.00
- Tukang batu Oh 1.1 160,000 176,000.00
- Kepala tukang Oh 0.001 180,000 180.00
- Mandor Oh 0.16 185,000 29,600.00
Jumlah Upah Tenaga 667,780.00
Jumlah Total 3,218,140.00
Jumlah Total + jasa 10% 3,540,055

4. Memasang 1 buah kloset jongkok sederhana


Harga bahan:
- Kloset jongkok sederhana bh 1 267,893 267,893.00
- Semen portland kg 6 1,300 7,800.00
- Pasir pasang m³ 0.01 178,164 1,781.64
Jumlah Harga Bahan 277,474.64
Upah tenaga:
- Pekerja Oh 1 140,000 140,000.00
- Tukang batu Oh 1.5 160,000 240,000.00
- Kepala tukang Oh 0.15 180,000 27,000.00
- Mandor Oh 0.16 185,000 29,600.00
Jumlah Upah Tenaga 436,600.00
Jumlah Total 714,074.64
Jumlah Total + jasa 10% 785,450
5. Memasang 1 buah kloset jongkok sedang
Harga bahan:
- Kloset jongkok sedang bh 1 824,376 824,376.00
- Semen portland kg 6 1,300 7,800.00
- Pasir pasang m³ 0.01 178,164 1,781.64
Jumlah Harga Bahan 833,957.64
Upah tenaga:
- Pekerja Oh 1 140,000 140,000.00
- Tukang batu Oh 1.5 160,000 240,000.00
- Kepala tukang Oh 0.15 180,000 27,000.00
- Mandor Oh 0.16 185,000 29,600.00
Jumlah Upah Tenaga 436,600.00
109

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Total 1,270,557.64


Jumlah Total + jasa 10% 1,397,600
6. Memasang 1 buah kloset jongkok tdk sederhana
Harga bahan:
- Kloset jongkok Toto bh 1 706,541 706,541.00
- Semen portland kg 6 1,300 7,800.00
- Pasir pasang m³ 0.01 178,164 1,781.64
Jumlah Harga Bahan 716,122.64
Upah tenaga:
- Pekerja Oh 1 140,000 140,000.00
- Tukang batu Oh 1.5 160,000 240,000.00
- Kepala tukang Oh 0.15 180,000 27,000.00
- Mandor Oh 0.16 185,000 29,600.00
Jumlah Upah Tenaga 436,600.00
Jumlah Total 1,152,722.64
Jumlah Total + jasa 10% 1,267,950
7. Memasang 1 buah urinoir
Harga bahan:
- Urinoir muslim Toto lengkap bh 1 3,091,469 3,091,469.00
- Perlengkapan (30% harga urinoir) % 30 3,091,469 927,440.70
- Semen portland kg 6 1,300 7,800.00
- Pasir pasang m³ 0.01 178,164 1,781.64
Jumlah Harga Bahan 4,028,491.34
Upah tenaga:
- Pekerja Oh 1 140,000 140,000.00
- Tukang batu Oh 1 160,000 160,000.00
- Kepala tukang Oh 0.1 180,000 18,000.00
- Mandor Oh 0.1 185,000 18,500.00
Jumlah Upah Tenaga 336,500.00
Jumlah Total 4,364,991.34
Jumlah Total + jasa 10% 4,801,450
8. Memasang 1 buah penyekat urinoir
Harga bahan:
- Penyekat Urinoir Toto lengkap bh 1 335,866 335,866.00
- Perlengkapan (30% harga penyekat urinoir % 30 335,866 100,759.80
- Semen portland kg 6 1,300 7,800.00
- Pasir pasang m³ 0.01 178,164 1,781.64
Jumlah Harga Bahan 446,207.44
Upah tenaga:
- Pekerja Oh 1 140,000 140,000.00
- Tukang batu Oh 1 160,000 160,000.00
- Kepala tukang Oh 0.1 180,000 18,000.00
- Mandor Oh 0.1 185,000 18,500.00
Jumlah Upah Tenaga 336,500.00
Jumlah Total 782,707.44
Jumlah Total + jasa 10% 860,950
9. Memasang 1 buah wastafel
110

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Harga bahan:
- Wastafel Toto lengkap bh 1 1,078,510 1,078,510.00
- Perlengkapan (12% harga wastafel) % 12 1,078,510 129,421.20
- Semen portland kg 6 1,300 7,800.00
- Pasir pasang m³ 0.01 178,164 1,781.64
Jumlah Harga Bahan 1,217,512.84
Upah tenaga:
- Pekerja Oh 1.2 140,000 168,000.00
- Tukang batu Oh 1.45 160,000 232,000.00
- Kepala tukang Oh 0.15 180,000 27,000.00
- Mandor Oh 0.1 185,000 18,500.00
Jumlah Upah Tenaga 445,500.00
Jumlah Total 1,663,012.84
Jumlah Total + jasa 10% 1,829,300
10. Memasang 1 buah bak mandi fibreglass volume 0,3 m³
Harga bahan:
- Bak fibreglass 0.3 m³ bh 1 1,169,179 1,169,179.00
- Perlengkapan (18% harga bak) % 18 1,169,179 210,452.22
Jumlah Harga Bahan 1,379,631.22
Upah tenaga:
- Pekerja Oh 1.8 140,000 252,000.00
- Tukang batu Oh 2.7 160,000 432,000.00
- Kepala tukang Oh 0.54 180,000 97,200.00
- Mandor Oh 0.11 185,000 20,350.00
Jumlah Upah Tenaga 801,550.00
Jumlah Total 2,181,181.22
Jumlah Total + jasa 10% 2,399,250
11. Memasang 1 buah bak mandi fibreglass volume 0,3 m³ lapis keramik
Harga bahan:
- Bak fibreglass 0.3 m³ bh 1 1,169,179 1,169,179.00
- Perlengkapan (18% harga bak) % 18 1,169,179 210,452.22
- Bata merah bh 16 660 10,560.00
- Semen portland kg 2.442 1,300 3,174.60
- Pasir pasang m³ 0.01122 178,164 1,999.00
- Ubin keramik 20 x 20 cm setara mulia bh 18 3,410 61,380.00
- Semen portland kg 10.4 1,300 13,520.00
- Pasir pasang m³ 0.045 178,164 8,017.38
- Semen warna kg 1.62 2,375 3,847.50
Jumlah Harga Bahan 1,482,129.70

Upah tenaga:
- Pekerja Oh 1.96 140,000 274,400.00
- Tukang batu Oh 1.33 160,000 212,800.00
- Kepala tukang Oh 0.133 180,000 23,940.00
- Mandor Oh 0.097 185,000 17,945.00
Jumlah Upah Tenaga 529,085.00
Jumlah Total 2,011,214.70
111

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Total + jasa 10% 2,212,300


12. Memasang 1 buah bak mandi batu bata volume 0,3 m³
Harga bahan:
- Bata merah bh 242 660 159,720.00
- Semen portland kg 120 1,300 156,000.00
- Pasir pasang m³ 0.3 178,164 53,449.20
- Ubin keramik 20 x 20 cm Roman bh 110 4,400 484,000.00
- Semen warna kg 6 2,375 14,250.00
Jumlah Harga Bahan 867,419.20
Upah tenaga:
- Pekerja Oh 6 140,000 840,000.00
- Tukang batu Oh 3 160,000 480,000.00
- Kepala tukang Oh 0.3 180,000 54,000.00
- Mandor Oh 0.3 185,000 55,500.00
Jumlah Upah Tenaga 1,429,500.00
Jumlah Total 2,296,919.20
Jumlah Total + jasa 10% 2,526,600
13. Memasang 1 buah bak mandi batu bata volume 0,3 m³ (60x60x80 cm)
Harga bahan:
- Bata merah bh 72 660 47,520.00
- Semen portland kg 40.06 1,300 52,078.00
- Pasir pasang m³ 0.09 178,164 16,034.76
- Ubin keramik 20 x 20 cm Roman bh 68 4,400 299,200.00
- Semen warna kg 4.08 2,375 9,690.00
Jumlah Harga Bahan 424,522.76
Upah tenaga:
- Pekerja Oh 1.96 140,000 274,400.00
- Tukang batu Oh 1.33 160,000 212,800.00
- Kepala tukang Oh 0.133 180,000 23,940.00
- Mandor Oh 0.097 185,000 17,945.00
Jumlah Upah Tenaga 529,085.00
Jumlah Total 953,607.76
Jumlah Total + jasa 10% 1,048,950
14. Memasang pipa galvanis dia 1/2" tiap m'
Harga bahan:
- Pipa galvanis dia 1/2" m' 1.2 26,754 32,104.80
- Perlengkapan (35% harga pipa) % 35 32,105 11,236.68
Jumlah Harga Bahan 43,341.48
Upah tenaga:
- Pekerja Oh 0.054 140,000 7,560.00
- Tukang pasang pipa Oh 0.09 180,000 16,200.00
- Kepala tukang Oh 0.009 180,000 1,620.00
- Mandor Oh 0.0027 185,000 499.50
Jumlah Upah Tenaga 25,879.50
Jumlah Total 69,220.98
Jumlah Total + jasa 10% 76,100
15. Memasang pipa galvanis dia 3/4" tiap m'
112

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Harga bahan:
- Pipa galvanis dia 3/4" m' 1.2 29,753 35,703.30
- Perlengkapan (35% harga pipa) % 35 35,703 12,496.16
Jumlah Harga Bahan 48,199.46
Upah tenaga:
- Pekerja Oh 0.054 140,000 7,560.00
- Tukang pasang pipa Oh 0.09 180,000 16,200.00
- Kepala tukang Oh 0.009 180,000 1,620.00
- Mandor Oh 0.0027 185,000 499.50
Jumlah Upah Tenaga 25,879.50
Jumlah Total 74,078.96
Jumlah Total + jasa 10% 81,450
16. Memasang pipa galvanis dia 1" tiap m'
Harga bahan:
- Pipa galvanis dia 1" m' 1.2 38,279 45,934.50
- Perlengkapan (35% harga pipa) % 35 45,935 16,077.08
Jumlah Harga Bahan 62,011.58
Upah tenaga:
- Pekerja Oh 0.054 140,000 7,560.00
- Tukang pasang pipa Oh 0.09 180,000 16,200.00
- Kepala tukang Oh 0.009 180,000 1,620.00
- Mandor Oh 0.0027 185,000 499.50
Jumlah Upah Tenaga 25,879.50
Jumlah Total 87,891.08
Jumlah Total + jasa 10% 96,650
17. Memasang pipa galvanis dia 1 ¼" tiap m'
Harga bahan:
- Pipa galvanis dia 1 ¼" m' 1.2 47,375 56,850.00
- Perlengkapan (35% harga pipa) % 35 56,850 19,897.50
Jumlah Harga Bahan 76,747.50
Upah tenaga:
- Pekerja Oh 0.054 140,000 7,560.00
- Tukang pasang pipa Oh 0.09 180,000 16,200.00
- Kepala tukang Oh 0.009 180,000 1,620.00
- Mandor Oh 0.0027 185,000 499.50
Jumlah Upah Tenaga 25,879.50
Jumlah Total 102,627.00
Jumlah Total + jasa 10% 112,850
18. Memasang pipa galvanis dia 1 ½" tiap m'
Harga bahan:
- Pipa galvanis dia 1 ½" m' 1.2 55,037 66,044.10
- Perlengkapan (35% harga pipa) % 35 66,044 23,115.44
Jumlah Harga Bahan 89,159.54
Upah tenaga:
- Pekerja Oh 0.108 140,000 15,120.00
- Tukang pasang pipa Oh 0.18 180,000 32,400.00
- Kepala tukang Oh 0.018 180,000 3,240.00
113

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Mandor Oh 0.0054 185,000 999.00


Jumlah Upah Tenaga 51,759.00
Jumlah Total 140,918.54
Jumlah Total + jasa 10% 155,000
19. Memasang pipa galvanis dia 2" tiap m'
Harga bahan:
- Pipa galvanis dia 2" m' 1.2 75,382 90,457.80
- Perlengkapan (35% harga pipa) % 35 90,458 31,660.23
Jumlah Harga Bahan 122,118.03
Upah tenaga:
- Pekerja Oh 0.108 140,000 15,120.00
- Tukang pasang pipa Oh 0.18 180,000 32,400.00
- Kepala tukang Oh 0.018 180,000 3,240.00
- Mandor Oh 0.0054 185,000 999.00
Jumlah Upah Tenaga 51,759.00
Jumlah Total 173,877.03
Jumlah Total + jasa 10% 191,250
20. Memasang pipa galvanis dia 2 ½" tiap m'
Harga bahan:
- Pipa galvanis dia 2 ½" m' 1.2 98,343 118,011.60
- Perlengkapan (35% harga pipa) % 35 118,012 41,304.06
Jumlah Harga Bahan 159,315.66
Upah tenaga:
- Pekerja Oh 0.108 140,000 15,120.00
- Tukang pasang pipa Oh 0.18 180,000 32,400.00
- Kepala tukang Oh 0.018 180,000 3,240.00
- Mandor Oh 0.0054 185,000 999.00
Jumlah Upah Tenaga 51,759.00
Jumlah Total 211,074.66
Jumlah Total + jasa 10% 232,150
21. Memasang pipa galvanis dia 3" tiap m'
Harga bahan:
- Pipa galvanis dia 3" m' 1.2 260,249 312,298.80
- Perlengkapan (35% harga pipa) % 35 312,299 109,304.58
Jumlah Harga Bahan 421,603.38
Upah tenaga:
- Pekerja Oh 0.108 140,000 15,120.00
- Tukang pasang pipa Oh 0.18 180,000 32,400.00
- Kepala tukang Oh 0.018 180,000 3,240.00
- Mandor Oh 0.0054 185,000 999.00
Jumlah Upah Tenaga 51,759.00
Jumlah Total 473,362.38
Jumlah Total + jasa 10% 520,650
22. Memasang pipa galvanis dia 4" tiap m'
Harga bahan:
- Pipa galvanis dia 4" m' 1.2 275,000 330,000.00
- Perlengkapan (35% harga pipa) % 35 330,000 115,500.00
114

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Harga Bahan 445,500.00


Upah tenaga:
- Pekerja Oh 0.135 140,000 18,900.00
- Tukang pasang pipa Oh 0.225 180,000 40,500.00
- Kepala tukang Oh 0.0225 180,000 4,050.00
- Mandor Oh 0.0068 185,000 1,258.00
Jumlah Upah Tenaga 64,708.00
Jumlah Total 510,208.00
Jumlah Total + jasa 10% 561,200
23. Memasang pipa PVC tipe AW dia 1/2" tiap m'
Harga bahan:
- Pipa PVC dia 1/2" AW m' 1.2 5,174 6,208.80
- Perlengkapan (35% harga pipa) % 35 6,209 2,173.08
Jumlah Harga Bahan 8,381.88
Upah tenaga:
- Pekerja Oh 0.036 140,000 5,040.00
- Tukang pasang pipa Oh 0.06 180,000 10,800.00
- Kepala tukang Oh 0.006 180,000 1,080.00
- Mandor Oh 0.0018 185,000 333.00
Jumlah Upah Tenaga 17,253.00
Jumlah Total 25,634.88
Jumlah Total + jasa 10% 28,150
24. Memasang pipa PVC tipe AW dia 3/4" tiap m'
Harga bahan:
- Pipa PVC dia 3/4" AW m' 1.2 10,466 12,559.20
- Perlengkapan (35% harga pipa) % 35 12,559 4,395.72
Jumlah Harga Bahan 16,954.92
Upah tenaga:
- Pekerja Oh 0.036 140,000 5,040.00
- Tukang pasang pipa Oh 0.06 180,000 10,800.00
- Kepala tukang Oh 0.006 180,000 1,080.00
- Mandor Oh 0.0018 185,000 333.00
Jumlah Upah Tenaga 17,253.00
Jumlah Total 34,207.92
Jumlah Total + jasa 10% 37,600
25. Memasang pipa PVC tipe AW dia 1" tiap m'
Harga bahan:
- Pipa PVC dia 1" AW m' 1.2 21,403 25,683.60
- Perlengkapan (35% harga pipa) % 35 25,684 8,989.26
Jumlah Harga Bahan 34,672.86

Upah tenaga:
- Pekerja Oh 0.036 140,000 5,040.00
- Tukang pasang pipa Oh 0.06 180,000 10,800.00
- Kepala tukang Oh 0.006 180,000 1,080.00
- Mandor Oh 0.0018 185,000 333.00
Jumlah Upah Tenaga 17,253.00
115

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Total 51,925.86


Jumlah Total + jasa 10% 57,100
26. Memasang pipa PVC tipe AW dia 1 ¼" tiap m'
Harga bahan:
- Pipa PVC dia 1 ¼" AW m' 1.2 28,224 33,868.80
- Perlengkapan (35% harga pipa) % 35 33,869 11,854.08
Jumlah Harga Bahan 45,722.88
Upah tenaga:
- Pekerja Oh 0.036 140,000 5,040.00
- Tukang pasang pipa Oh 0.06 180,000 10,800.00
- Kepala tukang Oh 0.006 180,000 1,080.00
- Mandor Oh 0.0018 185,000 333.00
Jumlah Upah Tenaga 17,253.00
Jumlah Total 62,975.88
Jumlah Total + jasa 10% 69,250
27. Memasang pipa PVC tipe D dia 1 ¼" tiap m'
Harga bahan:
- Pipa PVC dia 1 ¼" D m' 1.2 27,500 33,000.00
- Perlengkapan (35% harga pipa) % 35 33,000 11,550.00
Jumlah Harga Bahan 44,550.00
Upah tenaga:
- Pekerja Oh 0.036 140,000 5,040.00
- Tukang pasang pipa Oh 0.06 180,000 10,800.00
- Kepala tukang Oh 0.006 180,000 1,080.00
- Mandor Oh 0.0018 185,000 333.00
Jumlah Upah Tenaga 17,253.00
Jumlah Total 61,803.00
Jumlah Total + jasa 10% 67,950
28. Memasang pipa PVC tipe AW dia 1 ½" tiap m'
Harga bahan:
- Pipa PVC dia 1 ½" AW m' 1.2 32,222 38,666.40
- Perlengkapan (35% harga pipa) % 35 38,666 13,533.24
Jumlah Harga Bahan 52,199.64
Upah tenaga:
- Pekerja Oh 0.036 140,000 5,040.00
- Tukang pasang pipa Oh 0.06 180,000 10,800.00
- Kepala tukang Oh 0.006 180,000 1,080.00
- Mandor Oh 0.0018 185,000 333.00
Jumlah Upah Tenaga 17,253.00
Jumlah Total 69,452.64
Jumlah Total + jasa 10% 76,350
29. Memasang pipa PVC tipe D dia 1 ½" tiap m'
Harga bahan:
- Pipa PVC dia 1 ½" D m' 1.2 32,000 38,400.00
- Perlengkapan (35% harga pipa) % 35 38,400 13,440.00
Jumlah Harga Bahan 51,840.00
Upah tenaga:
116

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Pekerja Oh 0.036 140,000 5,040.00


- Tukang pasang pipa Oh 0.06 180,000 10,800.00
- Kepala tukang Oh 0.006 180,000 1,080.00
- Mandor Oh 0.0018 185,000 333.00
Jumlah Upah Tenaga 17,253.00
Jumlah Total 69,093.00
Jumlah Total + jasa 10% 76,000
30. Memasang pipa PVC tipe AW dia 2" tiap m'
Harga bahan:
- Pipa PVC dia 2" AW m' 1.2 39,043 46,851.60
- Perlengkapan (35% harga pipa) % 35 46,852 16,398.06
Jumlah Harga Bahan 63,249.66
Upah tenaga:
- Pekerja Oh 0.054 140,000 7,560.00
- Tukang pasang pipa Oh 0.09 180,000 16,200.00
- Kepala tukang Oh 0.009 180,000 1,620.00
- Mandor Oh 0.0027 185,000 499.50
Jumlah Upah Tenaga 25,879.50
Jumlah Total 89,129.16
Jumlah Total + jasa 10% 98,000
31. Memasang pipa PVC tipe D dia 2" tiap m'
Harga bahan:
- Pipa PVC dia 2" D m' 1.2 38,000 45,600.00
- Perlengkapan (35% harga pipa) % 35 45,600 15,960.00
Jumlah Harga Bahan 61,560.00
Upah tenaga:
- Pekerja Oh 0.054 140,000 7,560.00
- Tukang pasang pipa Oh 0.09 180,000 16,200.00
- Kepala tukang Oh 0.009 180,000 1,620.00
- Mandor Oh 0.0027 185,000 499.50
Jumlah Upah Tenaga 25,879.50
Jumlah Total 87,439.50
Jumlah Total + jasa 10% 96,150
32. Memasang pipa PVC tipe AW dia 2 ½" tiap m'
Harga bahan:
- Pipa PVC dia 2 ½" AW m' 1.2 53,038 63,645.60
- Perlengkapan (35% harga pipa) % 35 63,646 22,275.96
Jumlah Harga Bahan 85,921.56
Upah tenaga:
- Pekerja Oh 0.036 140,000 5,040.00
- Tukang pasang pipa Oh 0.06 180,000 10,800.00
- Kepala tukang Oh 0.006 180,000 1,080.00
- Mandor Oh 0.00018 185,000 33.30
Jumlah Upah Tenaga 16,953.30
0.054 Jumlah Total 102,874.86
0.0027 Jumlah Total + jasa 10% 113,150
33. Memasang pipa PVC tipe D dia 2 ½" tiap m'
117

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Harga bahan:
- Pipa PVC dia 2 ½" D m' 1.2 52,000 62,400.00
- Perlengkapan (35% harga pipa) % 35 62,400 21,840.00
Jumlah Harga Bahan 84,240.00
Upah tenaga:
- Pekerja Oh 0.036 140,000 5,040.00
- Tukang pasang pipa Oh 0.06 180,000 10,800.00
- Kepala tukang Oh 0.006 180,000 1,080.00
- Mandor Oh 0.00018 185,000 33.30
Jumlah Upah Tenaga 16,953.30
0.054 Jumlah Total 101,193.30
0.0027 Jumlah Total + jasa 10% 111,300
34. Memasang pipa PVC tipe AW dia 3" cm tiap m'
Harga bahan:
- Pipa PVC dia 3" AW m' 1.2 60,682 72,818.40
- Perlengkapan (35% harga pipa) % 35 72,818 25,486.44
Jumlah Harga Bahan 98,304.84
Upah tenaga:
- Pekerja Oh 0.081 140,000 11,340.00
- Tukang pasang pipa Oh 0.135 180,000 24,300.00
- Kepala tukang Oh 0.0135 180,000 2,430.00
- Mandor Oh 0.0041 185,000 758.50
Jumlah Upah Tenaga 38,828.50
Jumlah Total 137,133.34
Jumlah Total + jasa 10% 150,800
35. Memasang pipa PVC tipe D dia 3" cm tiap m'
Harga bahan:
- Pipa PVC dia 3" D m' 1.2 60,000 72,000.00
- Perlengkapan (35% harga pipa) % 35 72,000 25,200.00
Jumlah Harga Bahan 97,200.00
Upah tenaga:
- Pekerja Oh 0.081 140,000 11,340.00
- Tukang pasang pipa Oh 0.135 180,000 24,300.00
- Kepala tukang Oh 0.0135 180,000 2,430.00
- Mandor Oh 0.0041 185,000 758.50
Jumlah Upah Tenaga 38,828.50
Jumlah Total 136,028.50
Jumlah Total + jasa 10% 149,600
36. Memasang pipa PVC tipe AW dia 4" tiap m'
Harga bahan:
- Pipa PVC dia 4" AW m' 1.2 79,733 95,679.60
- Perlengkapan (35% harga pipa) % 35 95,680 33,487.86
Jumlah Harga Bahan 129,167.46
Upah tenaga:
- Pekerja Oh 0.081 140,000 11,340.00
- Tukang pasang pipa Oh 0.135 180,000 24,300.00
- Kepala tukang Oh 0.0135 180,000 2,430.00
118

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Mandor Oh 0.0041 185,000 758.50


Jumlah Upah Tenaga 38,828.50
Jumlah Total 167,995.96
Jumlah Total + jasa 10% 184,750
37. Memasang pipa PVC tipe D dia 4" tiap m'
Harga bahan:
- Pipa PVC dia 4" D m' 1.2 77,500 93,000.00
- Perlengkapan (35% harga pipa) % 35 93,000 32,550.00
Jumlah Harga Bahan 125,550.00
Upah tenaga:
- Pekerja Oh 0.081 140,000 11,340.00
- Tukang pasang pipa Oh 0.135 180,000 24,300.00
- Kepala tukang Oh 0.0135 180,000 2,430.00
- Mandor Oh 0.0041 185,000 758.50
Jumlah Upah Tenaga 38,828.50
Jumlah Total 164,378.50
Jumlah Total + jasa 10% 180,800
38. Memasang pipa PVC tipe AW dia 6" tiap m'
Harga bahan:
- Pipa PVC dia 6" AW m' 1.2 87,500 105,000.00
- Perlengkapan (35% harga pipa) % 35 105,000 36,750.00
Jumlah Harga Bahan 141,750.00
Upah tenaga:
- Pekerja Oh 0.081 140,000 11,340.00
- Tukang pasang pipa Oh 0.135 180,000 24,300.00
- Kepala tukang Oh 0.0135 180,000 2,430.00
- Mandor Oh 0.0041 185,000 758.50
Jumlah Upah Tenaga 38,828.50
Jumlah Total 180,578.50
Jumlah Total + jasa 10% 198,600
39. Memasang pipa PVC tipe D dia 6" tiap m'
Harga bahan:
- Pipa PVC dia 6" D m' 1.2 85,000 102,000.00
- Perlengkapan (35% harga pipa) % 35 102,000 35,700.00
Jumlah Harga Bahan 137,700.00
Upah tenaga:
- Pekerja Oh 0.081 140,000 11,340.00
- Tukang pasang pipa Oh 0.135 180,000 24,300.00
- Kepala tukang Oh 0.0135 180,000 2,430.00
- Mandor Oh 0.0041 185,000 758.50
Jumlah Upah Tenaga 38,828.50
Jumlah Total 176,528.50
Jumlah Total + jasa 10% 194,150
40. Memasang 1 buah bak cuci piring stainless steel
Harga bahan:
- Bak cuci stainless steel bh 1 824,376 824,376.00
- Water drain + asesoris set 1 631,394 631,394.00
119

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Harga Bahan 1,455,770.00


Upah tenaga:
- Pekerja Oh 0.03 140,000 4,200.00
- Tukang batu Oh 0.3 160,000 48,000.00
- Kepala tukang Oh 0.03 180,000 5,400.00
- Mandor Oh 0.0015 185,000 277.50
Jumlah Upah Tenaga 57,877.50
Jumlah Total 1,513,647.50
Jumlah Total + jasa 10% 1,665,000
41. Memasang 1 buah kran dia 3/4" atau 1/2" sederhana
Harga bahan:
- Kran air lokal (sederhana) bh 1 25,284 25,284.00
- Seal tape bh 0.025 14,300 357.50
Jumlah Harga Bahan 25,641.50
Upah tenaga:
- Pekerja Oh 0.01 140,000 1,400.00
- Tukang pasang pipa Oh 0.1 180,000 18,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 22,125.00
Jumlah Total 47,766.50
Jumlah Total + jasa 10% 52,500
42. Memasang 1 buah kran dia 3/4" atau 1/2" stainless
Harga bahan:
- Kran air stainless Toto bh 1 51,509 51,509.00
- Seal tape bh 0.025 14,300 357.50
Jumlah Harga Bahan 51,866.50
Upah tenaga:
- Pekerja Oh 0.01 140,000 1,400.00
- Tukang pasang pipa Oh 0.1 180,000 18,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 22,125.00
Jumlah Total 73,991.50
Jumlah Total + jasa 10% 81,350
43. Memasang 1 buah kran leher angsa stainless
Harga bahan:
- Kran air leher angsa stainless bh 1 275,000 275,000.00
- Seal tape bh 0.025 14,300 357.50
Jumlah Harga Bahan 275,357.50
Upah tenaga:
- Pekerja Oh 0.01 140,000 1,400.00
- Tukang pasang pipa Oh 0.1 180,000 18,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 22,125.00
Jumlah Total 297,482.50
120

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Total + jasa 10% 327,200


44. Memasang 1 buah kran bebek stainless
Harga bahan:
- Kran bebek Toto bh 1 288,200 288,200.00
- Seal tape bh 0.025 14,300 357.50
Jumlah Harga Bahan 288,557.50
Upah tenaga:
- Pekerja Oh 0.01 140,000 1,400.00
- Tukang pasang pipa Oh 0.1 180,000 18,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 22,125.00
Jumlah Total 310,682.50
Jumlah Total + jasa 10% 341,750
45. Memasang 1 buah tempat sabun
Harga bahan:
- Tempat sabun Toto bh 1 180,250 180,250.00
Jumlah Harga Bahan 180,250.00
Upah tenaga:
- Pekerja Oh 0.01 140,000 1,400.00
- Tukang batu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 20,125.00
Jumlah Total 200,375.00
Jumlah Total + jasa 10% 220,400

46. Memasang 1 buah shower tiang


Harga bahan:
- Shower tiang (km/wc utama) JB bh 1 5,407,500 5,407,500.00
Jumlah Harga Bahan 5,407,500.00
Upah tenaga:
- Pekerja Oh 0.01 140,000 1,400.00
- Tukang batu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 20,125.00
Jumlah Total 5,427,625.00
Jumlah Total + jasa 10% 5,970,350
47. Memasang 1 buah shower tiang
Harga bahan:
- Shower tiang (km/wc anak + tamu) bh 1 3,399,000 3,399,000.00
Jumlah Harga Bahan 3,399,000.00
Upah tenaga:
- Pekerja Oh 0.01 140,000 1,400.00
- Tukang batu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
121

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Mandor Oh 0.005 185,000 925.00


Jumlah Upah Tenaga 20,125.00
Jumlah Total 3,419,125.00
Jumlah Total + jasa 10% 3,761,000
48. Memasang 1 buah box shower kaca (km/wc utama)
Harga bahan:
- Box shower kaca (km/wc utama) Icepool bh 1 3,939,500 3,939,500.00
Jumlah Harga Bahan 3,939,500.00
Upah tenaga:
- Pekerja Oh 0.01 140,000 1,400.00
- Tukang batu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 20,125.00
Jumlah Total 3,959,625.00
Jumlah Total + jasa 10% 4,355,550
49. Memasang 1 buah Wastafel kaca + cermin + kran lengkap (km/wc utama)
Harga bahan:
- Wastafel kaca + cermin + kran lengkap (k bh 1 15,398,500 15,398,500.00
Jumlah Harga Bahan 15,398,500.00
Upah tenaga:
- Pekerja Oh 0.01 140,000 1,400.00
- Tukang batu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 20,125.00
Jumlah Total 15,418,625.00
Jumlah Total + jasa 10% 16,960,450
50. Memasang 1 buah Wastafel kaca + cermin + kran lengkap (km/wc anak + tamu)
Harga bahan:
- Wastafel kaca + cermin + kran lengkap (km bh 1 2,549,250 2,549,250.00
Jumlah Harga Bahan 2,549,250.00
Upah tenaga:
- Pekerja Oh 0.01 140,000 1,400.00
- Tukang batu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 20,125.00
Jumlah Total 2,569,375.00
Jumlah Total + jasa 10% 2,826,300
51. Memasang 1 buah shower tiang
Harga bahan:
- Shower tiang (km/wc utama) GBV bh 1 4,635,000 4,635,000.00
Jumlah Harga Bahan 4,635,000.00
Upah tenaga:
- Pekerja Oh 0.01 140,000 1,400.00
- Tukang batu Oh 0.1 160,000 16,000.00
122

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Kepala tukang Oh 0.01 180,000 1,800.00


- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 20,125.00
Jumlah Total 4,655,125.00
Jumlah Total + jasa 10% 5,120,600
52. Memasang 1 floor drain sederhana
Harga bahan:
- Floor drain sederhana bh 1 45,000 45,000.00
Jumlah Harga Bahan 45,000.00
Upah tenaga:
- Pekerja Oh 0.01 140,000 1,400.00
- Tukang batu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 20,125.00
Jumlah Total 65,125.00
Jumlah Total + jasa 10% 71,600
53. Memasang 1 floor drain stainless
Harga bahan:
- Floor drain stainless Toto bh 1 329,600 329,600.00
Jumlah Harga Bahan 329,600.00
Upah tenaga:
- Pekerja Oh 0.01 140,000 1,400.00
- Tukang batu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 20,125.00
Jumlah Total 349,725.00
Jumlah Total + jasa 10% 384,650
54. Membuat 1 unit sumur air tanah bor manual dalam 12 m' + pompa air listrik
Harga bahan:
- Pipa PVC dia 3/4" AW m' 14 10,466 146,524.00
- Pipa PVC dia 2" D m' 12 38,000 456,000.00
- Pompa air listrik 250 W unit 1 1,500,000 1,500,000.00
- Perlengkapan (35% harga pipa+pompa) % 35 2,102,524 735,883.40
Jumlah Harga Bahan 2,838,407.40
Upah tenaga:
- Pekerja Oh 3.162 140,000 442,680.00
- Tukang pasang pipa Oh 2.32 180,000 417,600.00
- Kepala tukang Oh 0.232 180,000 41,760.00
- Mandor Oh 0.1581 185,000 29,248.50
Jumlah Upah Tenaga 931,288.50
Jumlah Total 3,769,695.90
Jumlah Total + jasa 10% 4,146,650
55. Membuat 1 unit tanki septik sederhana kapasitas Ø 1,2 m dalam 1,2 m
Harga bahan:
- Bata merah bh 441 660 291,060.00
123

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Semen portland kg 126.17 1,300 164,021.00


- Pasir pasang m³ 0.439 178,164 78,214.00
- Batu pecah/split 2/3 m³ 0.13 475,000 61,750.00
- Besi beton polos kg 11.44 12,000 137,280.00
- Kawat beton kg 0.164 20,000 3,280.00
- Pasir beton m³ 0.093 178,164 16,569.25
- Pasir urug m³ 0.106 120,000 12,720.00
- Kayu Terentang balok m³ 0.007 2,826,516 19,785.61
- Triplek 4x8 ft 9 mm lbr 0.675 110,000 74,250.00
- Paku biasa 2"-5" kg 0.71 19,286 13,693.06
- Pipa PVC dia 2" D m' 1 38,000 38,000.00
- Pipa PVC dia 4" D m' 1.7 77,500 131,750.00
- Perlengkapan (35% harga pipa) % 35 169,750 59,412.50
Jumlah Harga Bahan 1,101,785.42
Upah tenaga:
- Pekerja Oh 5.44 140,000 761,600.00
- Tukang batu Oh 2.181 160,000 348,960.00
- Tukang pasang pipa Oh 0.32 180,000 57,600.00
- Kepala tukang Oh 0.25 180,000 45,000.00
- Mandor Oh 0.3055 185,000 56,517.50
Jumlah Upah Tenaga 1,269,677.50
Jumlah Total 2,371,462.92
Jumlah Total + jasa 10% 2,608,600
56. Membuat 1 unit tanki septik kapasitas 1,7x0,85 m dalam 1,3 m (vol. 1,88 m³ u/ 5 pemakai)
Harga bahan:
- Bata merah bh 722 660 476,520.00
- Semen portland kg 304.86 1,300 396,318.00
- Pasir pasang m³ 0.589 178,164 104,938.60
- Batu pecah/split 2/3 m³ 0.2 475,000 95,000.00
- Besi beton polos m³ 31.17 12,000 374,040.00
- Kawat beton kg 0.445 20,000 8,900.00
- Pasir beton m³ 0.134 178,164 23,873.98
- Pasir urug m³ 0.138 120,000 16,560.00
- Kayu Terentang balok m³ 0.0427 2,826,516 120,692.23
- Triplek 4x8 ft 9 mm lbr 0.8 110,000 88,000.00
- Paku biasa 2"-5" kg 0.92 19,286 17,743.12
- Pipa PVC dia 2" D m' 3 38,000 114,000.00
- Pipa PVC dia 4" D m' 1.7 77,500 131,750.00
- Perlengkapan (35% harga pipa) % 35 245,750 86,012.50
Jumlah Harga Bahan 2,054,348.43
Upah tenaga:
- Pekerja Oh 8.648 140,000 1,210,720.00
- Tukang batu Oh 3.486 160,000 557,760.00
- Tukang pasang pipa Oh 0.5 180,000 90,000.00
- Kepala tukang Oh 0.399 180,000 71,820.00
- Mandor Oh 0.482 185,000 89,170.00
Jumlah Upah Tenaga 2,019,470.00
124

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Total 4,073,818.43


Jumlah Total + jasa 10% 4,481,200
57. Membuat tanki septik kapasitas tiap 1 m³
Harga bahan:
- Bata merah bh 385 660 254,100.00
- Semen portland kg 162.29 1,300 210,977.00
- Pasir pasang m³ 0.314 178,164 55,943.50
- Batu pecah/split 2/3 m³ 0.107 475,000 50,825.00
- Besi beton polos m³ 16.594 12,000 199,128.00
- Kawat beton kg 0.237 20,000 4,740.00
- Pasir beton m³ 0.072 178,164 12,827.81
- Pasir urug m³ 0.074 120,000 8,880.00
- Kayu Terentang balok m³ 0.023 2,826,516 65,009.87
- Triplek 4x8 ft 9 mm lbr 0.426 110,000 46,860.00
- Paku biasa 2"-5" kg 0.49 19,286 9,450.14
- Pipa PVC dia 2" D m' 1.6 38,000 60,800.00
- Pipa PVC dia 4" D m' 0.91 77,500 70,525.00
- Perlengkapan (35% harga pipa) % 35 131,325 45,963.75
Jumlah Harga Bahan 1,096,030.06
Upah tenaga:
- Pekerja Oh 4.604 140,000 644,560.00
- Tukang batu Oh 1.856 160,000 296,960.00
- Tukang pasang pipa Oh 0.267 180,000 48,060.00
- Kepala tukang Oh 0.213 180,000 38,340.00
- Mandor Oh 0.257 185,000 47,545.00
Jumlah Upah Tenaga 1,075,465.00
Jumlah Total 2,171,495.06
Jumlah Total + jasa 10% 2,388,600
58. Membuat 1 unit resapan Ø 0,8 m (digali 1 m) dalam 1 m (digali 1,9 m) kap. 0,5 m³
Harga bahan:
- Batu pecah/split 3/5 m³ 0.603 475,000 286,425.00
- Ijuk kg 0.716 95,000 68,020.00
- Pipa PVC dia 4" D m' 2 77,500 155,000.00
Jumlah Harga Bahan 509,445.00
Upah tenaga:
- Pekerja Oh 1.05 140,000 147,000.00
- Tukang pasang pipa Oh 0.27 180,000 48,600.00
- Kepala tukang Oh 0.027 180,000 4,860.00
- Mandor Oh 0.0969 185,000 17,926.50
Jumlah Upah Tenaga 218,386.50
Jumlah Total 727,831.50
Jumlah Total + jasa 10% 800,600

59. Memasang 1 Doop 1" 1 bh


Harga bahan:
- Doop PVC 1 " bh 1 950 950.00
Jumlah Harga Bahan 950.00
125

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Upah tenaga:
- Perlengkapan 10 % Oh 0.1 950 95.00
Jumlah Upah Tenaga 95.00
Jumlah Total 1,045.00
Jumlah Total + jasa 10% 1,100

M PEKERJAAN BESI DAN ALUMINIUM

1. Pasang Besi Profil tiap kg


Harga bahan:
- Besi profil kg 1.15 12,350 14,202.50
Jumlah Harga Bahan 14,202.50
Upah tenaga:
- Pekerja Oh 0.06 140,000 8,400.00
- Tukang las Oh 0.06 160,000 9,600.00
- Kepala tukang Oh 0.006 180,000 1,080.00
- Mandor Oh 0.003 185,000 555.00
Jumlah Upah Tenaga 19,635.00
Jumlah Total 33,837.50
Jumlah Total + jasa 10% 37,200
2. Pasang Rangka Atap Baja tiap kg
Harga bahan:
- Besi baja WF kg 1.15 14,300 16,445.00
Jumlah Harga Bahan 16,445.00
Upah tenaga:
- Pekerja Oh 0.06 140,000 8,400.00
- Tukang las Oh 0.06 160,000 9,600.00
- Kepala tukang Oh 0.006 180,000 1,080.00
- Mandor Oh 0.003 185,000 555.00
Jumlah Upah Tenaga 19,635.00
Jumlah Total 36,080.00
Jumlah Total + jasa 10% 39,650
3. Kuda-kuda baja dengan WF / kg
Harga bahan:
- Besi baja WF kg 1.1000 14,300 15,730.00
- Sewa Genset unit 0.0020 261,375 522.75
- Travo las unit 0.0020 1,795,000 3,590.00
- Mesin gurinda unit 0.0010 690,000 690.00
- Mesin bor unit 0.0010 1,045,500 1,045.50
- Mata gerinda bh 0.0030 35,500 106.50
- Mata bor bh 0.0030 25,000 75.00
- Kawat Las listrik kg 0.0030 19,600 58.80
Jumlah Harga Bahan 21,818.55
Upah buat:
- Pekerja Oh 0.0400 140,000 5,600.00
- Tukang besi konstruksi Oh 0.0400 160,000 6,400.00
- Mandor Oh 0.0070 185,000 1,295.00
126

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Upah Buat 13,295.00


Upah erection:
- Transport kg 1.0000 1,840.50 1,840.50
- Pekerja Oh - 140,000 0.00
- Tukang besi konstruksi / Alat Berat Oh 0.0034 160,000 544.00
- Mandor Oh - 185,000 0.00
Jumlah Upah Erection 2,384.50
Jumlah Total 37,498.05
Dibulatkan 37,500
4. Kuda-kuda baja dengan siku / kg
Harga bahan:
- Besi siku kg 1.1000 10,650 11,715.00
- Sewa Genset unit 0.0020 261,375 522.75
- Travo las unit 0.0020 1,795,000 3,590.00
- Mesin gurinda unit 0.0010 690,000 690.00
- Mesin bor unit 0.0010 1,045,500 1,045.50
- Mata gerinda bh 0.0030 35,500 106.50
- Mata bor bh 0.0030 25,000 75.00
- Kawat Las listrik kg 0.0030 19,600 58.80
Jumlah Harga Bahan 17,803.55
Upah buat:
- Pekerja Oh 0.0200 140,000 2,800.00
- Tukang besi konstruksi Oh 0.0200 160,000 3,200.00
- Mandor Oh 0.0070 185,000 1,295.00
Jumlah Upah Buat 7,295.00
Upah erection:
- Transport kg 1.0000 1,780 1,780.36
- Pekerja Oh 0.0100 140,000 1,400.00
- Tukang besi konstruksi Oh 0.0050 160,000 800.00
- Mandor Oh 0.0020 185,000 370.00
Jumlah Upah Erection 4,350.36
Jumlah Total 29,448.91
Dibulatkan 29,400
5. Gording baja CNP / Kg
Harga bahan:
- Baja CNP kg 1.1000 12,073 13,279.75
- Sewa Genset unit 0.0020 261,375 522.75
- Travo las unit 0.0020 1,795,000 3,590.00
- Mesin gurinda unit 0.0010 690,000 690.00
- Mesin bor unit 0.0010 1,045,500 1,045.50
- Mata gerinda bh 0.0030 35,500 106.50
- Mata bor bh 0.0030 25,000 75.00
- Baut dia 12 mm - 1" kg 0.1500 10,500 1,575.00
Jumlah Harga Bahan 20,884.50
Upah buat:
- Pekerja Oh 0.0200 140,000 2,800.00
- Tukang besi konstruksi Oh 0.0300 160,000 4,800.00
127

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Mandor Oh 0.0070 185,000 1,295.00


Jumlah Upah Buat 8,895.00
Upah erection:
- Transport kg 1.0000 1,805 1,805.00
- Pekerja Oh 0.0100 140,000 1,400.00
- Tukang besi konstruksi Oh 0.0050 160,000 800.00
- Mandor Oh 0.0020 185,000 370.00
Jumlah Upah Erection 4,375.00
Jumlah Total 34,154.50
Dibulatkan 34,155
3. Pengelasan Las Listrik setiap 1 cm
Harga bahan:
- Kawat las listrik kg 0.04 19,600 784.00
- Solar ltr 0.03 10,200 306.00
- Pelumas ltr 0.004 74,323 297.29
Jumlah Harga Bahan 1,387.29
Upah tenaga:
- Pekerja Oh 0.004 140,000 560.00
- Tukang las Oh 0.002 160,000 320.00
- Kepala tukang Oh 0.0002 180,000 36.00
- Mandor Oh 0.0002 185,000 37.00
Jumlah Upah Tenaga 953.00

Sewa Alat: jam 0.017 75,000 1,275.00 1,275.00


Jumlah Total 3,615.29
Jumlah Total + jasa 10% 3,950
4. Pasang pintu besi plat baja tebal 2 mm rangkap, rangka baja siku / tiap m²
Harga bahan:
- Besi siku kg 15 10,650 159,750.00
- Besi plat baja kg 32.8 8,750 287,000.00
- Kawat Las Listrik kg 0.05 19,600 980.00
Jumlah Harga Bahan 447,730.00
Upah tenaga:
- Pekerja Oh 1.05 140,000 147,000.00
- Tukang besi Oh 1.05 160,000 168,000.00
- Kepala tukang Oh 0.105 180,000 18,900.00
- Mandor Oh 0.052 185,000 9,620.00
Jumlah Upah Tenaga 343,520.00
Jumlah Total 791,250.00
Jumlah Total + jasa 10% 870,350
5. Pasang rangka jendela besi Scuare Tube (25x5) cm / tiap m²
Harga bahan:
- Besi Scuare Tube m' 4.76 1,275 6,069.00
- Besi lis kaca (1x1) cm m' 4.522 3,615 16,348.35
- Pengelasan cm 20 3,950 79,000.00
Jumlah Harga Bahan 6,069.00
Upah tenaga:
128

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Pekerja Oh 0.65 140,000 91,000.00


- Tukang besi Oh 0.65 160,000 104,000.00
- Kepala tukang Oh 0.065 180,000 11,700.00
- Mandor Oh 0.032 185,000 5,920.00
Jumlah Upah Tenaga 212,620.00
Jumlah Total 218,689.00
Jumlah Total + jasa 10% 240,550
6. Pasang pintu lipat tiap m² (Folding Door)
Harga bahan:
- Pintu lipat m² 1 824,376 824,376.00
Jumlah Harga Bahan 824,376.00
Upah tenaga:
- Pekerja Oh 0.44 140,000 61,600.00
- Tukang besi Oh 0.44 160,000 70,400.00
- Kepala tukang Oh 0.044 180,000 7,920.00
- Mandor Oh 0.022 185,000 4,070.00
Jumlah Upah Tenaga 143,990.00
Jumlah Total 968,366.00
Jumlah Total + jasa 10% 1,065,200
7. Pasang rolling door tiap m²
Harga bahan:
- Roll door m² 1 316,700 316,700.00
Jumlah Harga Bahan 316,700.00
Upah tenaga:
- Pekerja Oh 1.2 140,000 168,000.00
- Tukang besi Oh 1.2 160,000 192,000.00
- Kepala tukang Oh 0.12 180,000 21,600.00
- Mandor Oh 0.006 185,000 1,110.00
Jumlah Upah Tenaga 382,710.00
Jumlah Total 699,410.00
Jumlah Total + jasa 10% 769,350
8. Pasang kusen pintu aluminium tiap m'
Harga bahan:
- Profil Allumunium Kusen m' 1.1 120,000 132,000.00
- Skrup fixer bh 2 750 1,500.00
- Sealant tube 0.06 36,950 2,217.00
Jumlah Harga Bahan 135,717.00
Upah tenaga:
- Pekerja Oh 0.043 140,000 6,020.00
- Tukang besi konstruksi Oh 0.043 160,000 6,880.00
- Kepala tukang Oh 0.0043 180,000 774.00
- Mandor Oh 0.0021 185,000 388.50
Jumlah Upah Tenaga 14,062.50
Jumlah Total 149,779.50
Jumlah Total + jasa 10% 164,750

9. Pasang kusen pintu aluminium powder coating tiap m'


129

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Harga bahan:
- Profil Allumunium Kusen m' 1.1 127,500 140,250.00
- Skrup fixer bh 2 900 1,800.00
- Sealant tube 0.06 44,340 2,660.40
Jumlah Harga Bahan 144,710.40
Upah tenaga:
- Pekerja Oh 0.043 140,000 6,020.00
- Tukang besi konstruksi Oh 0.043 160,000 6,880.00
- Kepala tukang Oh 0.0043 180,000 774.00
- Mandor Oh 0.0021 185,000 388.50
Jumlah Upah Tenaga 14,062.50
Jumlah Total 158,772.90
Jumlah Total + jasa 10% 174,650
10. Memasang 1 m² pintu/jendela/BV kaca, rangka allumunium kaca 8 mm
Harga bahan:
- Profil Allumunium Rangka Natural m' 4.400 100,000 440,000.00
- Kaca polos 8 mm m2 1.050 275,000 288,750.00
- Sealant tube 0.270 36,950 9,976.50
Jumlah Harga Bahan 738,726.50
Upah tenaga:
- Pekerja Oh 0.085 140,000 11,900.00
- Tukang kayu Oh 0.085 160,000 13,600.00
- Kepala tukang Oh 0.008 180,000 1,440.00
- Mandor Oh 0.004 185,000 740.00
Jumlah Upah Tenaga 27,680.00
Jumlah Total 766,406.50
Jumlah Total + jasa 10% 843,000
11. Memasang 1 m² pintu/jendela/BV kaca, rangka allumunium kaca 5 mm
Harga bahan:
- Profil Allumunium Rangka Natural m' 4.400 100,000 440,000.00
- Kaca polos 5 mm m2 1.050 269,069 282,522.45
- Sealant tube 0.270 36,950 9,976.50
Jumlah Harga Bahan 732,498.95
Upah tenaga:
- Pekerja Oh 0.085 140,000 11,900.00
- Tukang kayu Oh 0.085 160,000 13,600.00
- Kepala tukang Oh 0.008 180,000 1,440.00
- Mandor Oh 0.004 185,000 740.00
Jumlah Upah Tenaga 27,680.00
Jumlah Total 760,178.95
Jumlah Total + jasa 10% 836,150
12. Memasang 1 m² pintu/jendela/BV kaca, rangka allumunium kaca 10 mm
Harga bahan:
- Profil Allumunium Rangka Natural m' 4.400 100,000 440,000.00
- Kaca Tempered polos 10 mm m2 1.050 625,350 656,617.50
- Sealant tube 0.270 36,950 9,976.50
Jumlah Harga Bahan 1,106,594.00
130

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Upah tenaga:
- Pekerja Oh 0.085 140,000 11,900.00
- Tukang kayu Oh 0.085 160,000 13,600.00
- Kepala tukang Oh 0.008 180,000 1,440.00
- Mandor Oh 0.004 185,000 740.00
Jumlah Upah Tenaga 27,680.00
Jumlah Total 1,134,274.00
Jumlah Total + jasa 10% 1,247,700

13. Pasang terali besi tiap m²


Pelat strip (3 x 19) mm x 6 m = 2,68 kg = 0,44745 kg/m'; 11,5 m besi plat strip = 5,146 kg.
Harga bahan:
- Besi pelat strip kg 5.146 16,111 82,907.21
- Pengelasan cm 27 3,950 106,966.00
Jumlah Harga Bahan 189,873.21
Upah tenaga:
- Pekerja Oh 1.67 140,000 233,800.00
- Tukang las Oh 1.67 160,000 267,200.00
- Kepala tukang Oh 0.167 180,000 30,060.00
- Mandor Oh 0.083 185,000 15,355.00
Jumlah Upah Tenaga 546,415.00
Jumlah Total 736,288.21
Jumlah Total + jasa 10% 809,900
14. Pasang jendela nako dan teralis tiap m²
Harga bahan:
- Jendela nako (rangka) daun 6.67 23,580 157,278.60
- Paku biasa 1/2"- 1" kg 0.02 19,286 385.72
- Besi segi empat 3/8"x3/8" (0,83kg/m') kg 5.56 7,100 39,476.00
Jumlah Harga Bahan 197,140.32
Upah tenaga:
- Pekerja Oh 0.2 140,000 28,000.00
- Tukang kayu Oh 0.2 160,000 32,000.00
- Kepala tukang Oh 0.02 180,000 3,600.00
- Mandor Oh 0.001 185,000 185.00
Jumlah Upah Tenaga 63,785.00
Jumlah Total 260,925.32
Jumlah Total + jasa 10% 287,000
15. Pasang talang datar, seng BJLS 28 (0,28 mm) tiap 1 m'
Harga bahan:
- Seng plat 3x6 ft BJLS 28 (0,28 mm) Lbr 0.5 41,630 20,815.00
- Paku biasa 1/2"- 1" kg 0.015 19,286 289.29
- Kayu Kamper Medan/Kruing papan m³ 0.019 4,500,000 85,500.00
- Cat meni besi kg 0.25 14,200 3,550.00
Jumlah Harga Bahan 110,154.29
Upah tenaga:
- Pekerja Oh 0.2 140,000 28,000.00
- Tukang kayu Oh 0.4 160,000 64,000.00
131

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Kepala tukang Oh 0.025 180,000 4,500.00


- Mandor Oh 0.01 185,000 1,850.00
Jumlah Upah Tenaga 98,350.00
Jumlah Total 208,504.29
Jumlah Total + jasa 10% 229,350
16. Pasang talang miring, seng BJLS 28 (0,28 mm) tiap 1 m'
Harga bahan:
- Seng gelomb.Zincalume 3x6 ft (0,30 mm) Lbr 0.5 145,000 72,500.00
- Paku biasa 1/2"- 1" kg 0.015 19,286 289.29
- Kayu Kamper Medan/Kruing papan m³ 0.019 4,500,000 85,500.00
- Cat meni besi kg 0.3 14,200 4,260.00
Jumlah Harga Bahan 162,549.29
Upah tenaga:
- Pekerja Oh 0.04 140,000 5,600.00
- Tukang kayu Oh 0.4 160,000 64,000.00
- Kepala tukang Oh 0.025 180,000 4,500.00
- Mandor Oh 0.00125 185,000 231.25
Jumlah Upah Tenaga 74,331.25
Jumlah Total 236,880.54
Jumlah Total + jasa 10% 260,550
17. Pasang talang 1/2 lingkaran D-15 cm, seng BJLS 30 / tiap 1 m'
Harga bahan:
- Seng plat 3x6 ft BJLS 28 (0,28 mm) Lbr 0.5 41,630 20,815.00
- Paku biasa 1/2"- 1" kg 0.01 19,286 192.86
- Besi pelat strip kg 0.5 16,111 8,055.50
Jumlah Harga Bahan 29,063.36
Upah tenaga:
- Pekerja Oh 0.15 140,000 21,000.00
- Tukang kayu Oh 0.3 160,000 48,000.00
- Kepala tukang Oh 0.03 180,000 5,400.00
- Mandor Oh 0.007 185,000 1,295.00
Jumlah Upah Tenaga 75,695.00
Jumlah Total 104,758.36
Jumlah Total + jasa 10% 115,200
18. Pasang pipa jemuran, rangka besi galvanis / tiap m 1

Harga bahan:

- Pipa galvanis dia 2" m1 1 75,382 75,381.50


- Kawat Las Listrik kg 0.05 19,600 980.00
Jumlah Harga Bahan 76,361.50
Upah tenaga:
- Pekerja Oh 0.043 140,000 6,020.00
- Tukang besi Oh 0.043 160,000 6,880.00
- Kepala tukang Oh 0.0043 180,000 774.00
- Mandor Oh 0.0021 185,000 388.50
Jumlah Upah Tenaga 14,062.50
Jumlah Total 90,424.00
132

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Total + jasa 10% 99,450


19. Pasang kawat jemuran, galvanis / tiap m 1

Harga bahan:

- Kawat diameter 4 mm m1 1 9,100 9,100.00


- perlengkapan 10 % ls 0.1 9,100 910.00
Jumlah Harga Bahan 10,010.00
Upah tenaga:
- Pekerja Oh 0.043 140,000 6,020.00
- Kepala tukang Oh 0.0043 180,000 774.00
- Mandor Oh 0.0021 185,000 388.50
Jumlah Upah Tenaga 7,182.50
Jumlah Total 17,192.50
Jumlah Total + jasa 10% 18,900
20. Pasang besi weirmes / tiap m2 Ø 8 mm single mest
Harga bahan:

- besi wermest dia. 8 mm m2 1.10 60,000 66,000.00


- perlengkapan 10 % ls 0.10 66,000.00 6,600.00
- Besi beton polos Kg 1.10 12,000 13,200.00
Jumlah Harga Bahan 85,800.00
Upah tenaga:
- Pekerja Oh 0.04 140,000.00 6,020.00
- Kepala tukang Oh 0.00 180,000.00 774.00
- Mandor Oh 0.00 185,000.00 388.50
Jumlah Upah Tenaga 7,182.50
Jumlah Total 92,982.50
Jumlah Total + jasa 10% 102,280.18
Dibulatkan 102,200
21. Pas. Grill besi lebar 20 cm tiap 1 m¹
Harga bahan:
- Besi siku L 30.30.3 kg 1.36 10,650 14,484.00
- Besi beton polos kg 0.89 12,000 10,700.00
Jumlah Harga Bahan 25,184.00
Upah tenaga:
- Pekerja Oh 0.03 140,000 4,200.00
- Tukang besi Oh 0.3 160,000 48,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.001 185,000 185.00
Jumlah Upah Tenaga 54,185.00
Jumlah Total 79,369.00
Jumlah Total + jasa 10% 87,300

22. Pasang pipa besi penahan ban / set


Harga bahan:
- Pipa galvanis dia 4" m2 3.6 275,000 990,000.00
- perlengkapan 10 % ls 0.1 990,000 99,000.00
133

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Harga Bahan 1,089,000.00


Upah tenaga:
- Pekerja Oh 0.043 140,000 6,020.00
- Kepala tukang Oh 0.0043 180,000 774.00
- Mandor Oh 0.0021 185,000 388.50
Jumlah Upah Tenaga 7,182.50
Jumlah Total 1,096,182.50
Jumlah Total + jasa 10% 1,205,800
23. Pasang besi expended tiap 1m²
Harga bahan:
- Kawat besi expeded m² 1.1 118,403 130,243.06
- Besi pelat strip kg 1.256 13,700 17,207.20
- Pengelasan cm 27.08 4,000 108,320.00
Jumlah Harga Bahan 255,770.26
Upah tenaga:
- Pekerja Oh 0.043 140,000 6,020.00
- Tukang las Oh 0.043 160,000 6,880.00
- Kepala tukang Oh 0.0043 180,000 774.00
- Mandor Oh 0.00215 185,000 397.75
Jumlah Upah Tenaga 14,071.75
Jumlah Total 269,842.01
Jumlah Total + jasa 10% 296,800

N PEKERJAAN KUNCI DAN KACA

1. Pasang 1 buah kunci tanam antik


Harga bahan:
- Kunci tanam antik bh 1 270,245 270,245.00
Jumlah Harga Bahan 270,245.00
Upah tenaga:
- Pekerja Oh 0.06 140,000 8,400.00
- Tukang kayu Oh 0.6 160,000 96,000.00
- Kepala tukang Oh 0.06 180,000 10,800.00
- Mandor Oh 0.003 185,000 555.00
Jumlah Upah Tenaga 115,755.00
Jumlah Total 386,000.00
Jumlah Total + jasa 10% 424,600
2. Pasang 1 buah kunci tanam sederhana
Harga bahan:
- Kunci tanam sederhana bh 1 107,839 107,839.00
Jumlah Harga Bahan 107,839.00
Upah tenaga:
- Pekerja Oh 0.01 140,000 1,400.00
- Tukang kayu Oh 0.5 160,000 80,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.0005 185,000 92.50
Jumlah Upah Tenaga 83,292.50
134

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Total 191,131.50


Jumlah Total + jasa 10% 210,200
3. Pasang 1 buah kunci tanam biasa
Harga bahan:
- Kunci tanam biasa bh 1 162,053 162,053.00
Jumlah Harga Bahan 162,053.00

Upah tenaga:
- Pekerja Oh 0.01 140,000 1,400.00
- Tukang kayu Oh 0.5 160,000 80,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.0005 185,000 92.50
Jumlah Upah Tenaga 83,292.50
Jumlah Total 245,345.50
Jumlah Total + jasa 10% 269,850
4. Pasang 1 buah kunci tanam KM
- Kunci tanam KM bh 1 85,000 85,000.00
Jumlah Harga Bahan 85,000.00
Upah tenaga:
- Pekerja Oh 0.005 140,000 700.00
- Tukang kayu Oh 0.5 160,000 80,000.00
- Kepala tukang Oh 0.005 180,000 900.00
- Mandor Oh 0.00025 185,000 46.25
Jumlah Upah Tenaga 81,646.25
Jumlah Total 166,646.25
Jumlah Total + jasa 10% 183,300
5. Pasang 1 buah kunci silinder Pintu Aluminium
Harga bahan:
- Kunci silinder pintu aluminium bh 1 112,245 112,245.00
Jumlah Harga Bahan 112,245.00
Upah tenaga:
- Pekerja Oh 0.005 140,000 700.00
- Tukang kayu Oh 0.5 160,000 80,000.00
- Kepala tukang Oh 0.005 180,000 900.00
- Mandor Oh 0.00025 185,000 46.25
Jumlah Upah Tenaga 81,646.25
Jumlah Total 193,891.25
Jumlah Total + jasa 10% 213,250
6. Pasang 1 buah kunci lemari
Harga bahan:
- Kunci lemari bh 1.0000 79,800 79,800.00
Jumlah Harga Bahan 79,800.00
Upah tenaga:
- Pekerja Oh 0.0250 140,000 3,500.00
- Tukang kayu Oh 0.2500 160,000 40,000.00
- Kepala tukang Oh 0.0250 180,000 4,500.00
135

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Mandor Oh 0.0013 185,000 240.50


Jumlah Upah Tenaga 48,240.50
Jumlah Total 128,040.50
Jumlah Total + jasa 10% 140,800
7. Pasang kunci gembok tiap 1 buah
Harga bahan:
- Kunci gembok bh 1.0000 53,050 53,050.00
Jumlah Harga Bahan 53,050.00
Upah tenaga:
- Pekerja Oh 0.0250 140,000 3,500.00
- Tukang kayu Oh 0.2500 160,000 40,000.00
- Kepala tukang Oh 0.0250 180,000 4,500.00
- Mandor Oh 0.0013 185,000 240.50
Jumlah Upah Tenaga 48,240.50
Jumlah Total 101,290.50
Jumlah Total + jasa 10% 111,400
8. Pasang 1 buah engsel pintu biasa/sederhana
Harga bahan:
- Engsel pintu biasa/sederhana bh 1 13,289 13,289.00
Jumlah Harga Bahan 13,289.00
Upah tenaga:
- Pekerja Oh 0.015 140,000 2,100.00
- Tukang kayu Oh 0.15 160,000 24,000.00
- Kepala tukang Oh 0.015 180,000 2,700.00
- Mandor Oh 0.00075 185,000 138.75
Jumlah Upah Tenaga 28,938.75
Jumlah Total 42,227.75
Jumlah Total + jasa 10% 46,450
9. Pasang 1 buah engsel pintu kuningan/stainless
Harga bahan:
- Engsel pintu kuningan/stainless 4" bh 1 31,950 31,950.00
Jumlah Harga Bahan 31,950.00
Upah tenaga:
- Pekerja Oh 0.015 140,000 2,100.00
- Tukang kayu Oh 0.15 160,000 24,000.00
- Kepala tukang Oh 0.015 180,000 2,700.00
- Mandor Oh 0.00075 185,000 138.75
Jumlah Upah Tenaga 28,938.75
Jumlah Total 60,888.75
Jumlah Total + jasa 10% 66,950
10. Pasang 1 buah engsel jendela kuningan/stainless
Harga bahan:
- Engsel jendela kuningan/stainless 3" bh 1 23,750 23,750.00
Jumlah Harga Bahan 23,750.00
Upah tenaga:
- Pekerja Oh 0.015 140,000 2,100.00
- Tukang kayu Oh 0.15 160,000 24,000.00
136

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Kepala tukang Oh 0.015 180,000 2,700.00


- Mandor Oh 0.00075 185,000 138.75
Jumlah Upah Tenaga 28,938.75
Jumlah Total 52,688.75
Jumlah Total + jasa 10% 57,950
11. Pasang 1 buah engsel angin
Harga bahan:
- Engsel angin bh 1 21,100 21,100.00
Jumlah Harga Bahan 21,100.00
Upah tenaga:
- Pekerja Oh 0.02 140,000 2,800.00
- Tukang kayu Oh 0.2 160,000 32,000.00
- Kepala tukang Oh 0.02 180,000 3,600.00
- Mandor Oh 0.001 185,000 185.00
Jumlah Upah Tenaga 38,585.00
Jumlah Total 59,685.00
Jumlah Total + jasa 10% 65,650
12. Pasang 1 buah spring knip
Harga bahan:
- Spring knip DB018BR-SN bh 1 25,000 25,000.00
Jumlah Harga Bahan 25,000.00
Upah tenaga:
- Pekerja Oh 0.015 140,000 2,100.00
- Tukang kayu Oh 0.15 160,000 24,000.00
- Kepala tukang Oh 0.015 180,000 2,700.00
- Mandor Oh 0.00075 185,000 138.75
Jumlah Upah Tenaga 28,938.75
Jumlah Total 53,938.75
Jumlah Total + jasa 10% 59,300
13. Pasang 1 buah kait angin
Harga bahan:
- Kait angin kuningan bh 1 21,756 21,756.00
Jumlah Harga Bahan 21,756.00
Upah tenaga:
- Pekerja Oh 0.015 140,000 2,100.00
- Tukang kayu Oh 0.15 160,000 24,000.00
- Kepala tukang Oh 0.015 180,000 2,700.00
- Mandor Oh 0.00075 185,000 138.75
Jumlah Upah Tenaga 28,938.75
Jumlah Total 50,694.75
Jumlah Total + jasa 10% 55,750
14. Pasang 1 buah door closer
Harga bahan:
- Door closer DKS HO-NA/BA bh 1 262,600 262,600.00
Jumlah Harga Bahan 262,600.00
Upah tenaga:
- Pekerja Oh 0.05 140,000 7,000.00
137

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Tukang kayu Oh 0.5 160,000 80,000.00


- Kepala tukang Oh 0.05 180,000 9,000.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 96,462.50
Jumlah Total 359,062.50
Jumlah Total + jasa 10% 394,950
15. Pasang 1 buah kunci selot
Harga bahan:
- Kunci selot bh 1 91,846 91,846.00
Jumlah Harga Bahan 91,846.00
Upah tenaga:
- Pekerja Oh 0.02 140,000 2,800.00
- Tukang kayu Oh 0.2 160,000 32,000.00
- Kepala tukang Oh 0.02 180,000 3,600.00
- Mandor Oh 0.001 185,000 185.00
Jumlah Upah Tenaga 38,585.00
Jumlah Total 130,431.00
Jumlah Total + jasa 10% 143,450
16. Pasang 1 buah grendel
Harga bahan:
- Grendel bh 1 28,106 28,106.00
Jumlah Harga Bahan 28,106.00
Upah tenaga:
- Pekerja Oh 0.025 140,000 3,500.00
- Tukang kayu Oh 0.25 160,000 40,000.00
- Kepala tukang Oh 0.028 180,000 5,040.00
- Mandor Oh 0.0015 185,000 277.50
Jumlah Upah Tenaga 48,817.50
Jumlah Total 76,923.50
Jumlah Total + jasa 10% 84,600
17. Pasang 1 buah window casement
Harga bahan:
- Window Casement bh 1 123,600 123,600.00
Jumlah Harga Bahan 123,600.00
Upah tenaga:
- Pekerja Oh 0.015 100,000 1,500.00
- Tukang kayu Oh 0.15 120,000 18,000.00
- Kepala tukang Oh 0.015 130,000 1,950.00
- Mandor Oh 0.00075 150,000 112.50
Jumlah Upah Tenaga 21,562.50
Jumlah Total 145,162.50
Jumlah Total + jasa 10% 159,650
Pasang 1 buah rambuncis
18. Harga bahan:
- Rambuncis bh 1 43,000 43,000.00
Jumlah Harga Bahan 43,000.00
Upah tenaga:
138

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Pekerja Oh 0.015 140,000 2,100.00


- Tukang kayu Oh 0.15 160,000 24,000.00
- Kepala tukang Oh 0.015 180,000 2,700.00
- Mandor Oh 0.00075 185,000 138.75
Jumlah Upah Tenaga 28,938.75
Jumlah Total 71,938.75
Jumlah Total + jasa 10% 79,100
19. Pasang 1 buah pegangan pintu/door holder
Harga bahan:
- Door holder bh 1 48,550 48,550.00
Jumlah Harga Bahan 48,550.00
Upah tenaga:
- Pekerja Oh 0.05 140,000 7,000.00
- Tukang kayu Oh 0.5 160,000 80,000.00
- Kepala tukang Oh 0.05 180,000 9,000.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 96,462.50
Jumlah Total 145,012.50
Jumlah Total + jasa 10% 159,500
20. Pasang 1 buah door stop
Harga bahan:
- Door stop DKS 887 bh 1 39,550 39,550.00
Jumlah Harga Bahan 39,550.00
Upah tenaga:
- Pekerja Oh 0.01 140,000 1,400.00
- Tukang kayu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.01 180,000 1,800.00
- Mandor Oh 0.0005 185,000 92.50
Jumlah Upah Tenaga 19,292.50
Jumlah Total 58,842.50
Jumlah Total + jasa 10% 64,700
21. Pasang 1 buah rel pintu dorong
Harga bahan:
- Rel pintu dorong bh 1 140,750 140,750.00
Jumlah Harga Bahan 140,750.00
Upah tenaga:
- Pekerja Oh 0.06 140,000 8,400.00
- Tukang kayu Oh 0.6 160,000 96,000.00
- Kepala tukang Oh 0.06 180,000 10,800.00
- Mandor Oh 0.003 185,000 555.00
Jumlah Upah Tenaga 115,755.00
Jumlah Total 256,505.00
Jumlah Total + jasa 10% 282,150
22. Pasang kaca es tebal 3 mm tiap 1 m²
Harga bahan:
- Kaca es 3 mm m² 1.1 65,450 71,995.00
Jumlah Harga Bahan 71,995.00
139

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Upah tenaga:
- Pekerja Oh 0.015 140,000 2,100.00
- Tukang kayu Oh 0.15 160,000 24,000.00
- Kepala tukang Oh 0.015 180,000 2,700.00
- Mandor Oh 0.00075 185,000 138.75
Jumlah Upah Tenaga 28,938.75
Jumlah Total 100,933.75
Jumlah Total + jasa 10% 111,000
23. Pasang kaca tebal 5 mm tiap 1 m²
Harga bahan:
- Kaca 5 mm m² 1.1 269,069 295,975.90
Jumlah Harga Bahan 295,975.90
Upah tenaga:
- Pekerja Oh 0.015 140,000 2,100.00
- Tukang kayu Oh 0.15 160,000 24,000.00
- Kepala tukang Oh 0.015 180,000 2,700.00
- Mandor Oh 0.00075 185,000 138.75
Jumlah Upah Tenaga 28,938.75
Jumlah Total 324,914.65
Jumlah Total + jasa 10% 357,400
24. Pasang kaca es tebal 5 mm tiap 1 m²
Harga bahan:
- Kaca es 5 mm m² 1.1 139,050 152,955.00
Jumlah Harga Bahan 152,955.00
Upah tenaga:
- Pekerja Oh 0.015 140,000 2,100.00
- Tukang kayu Oh 0.15 160,000 24,000.00
- Kepala tukang Oh 0.015 180,000 2,700.00
- Mandor Oh 0.00075 185,000 138.75
Jumlah Upah Tenaga 28,938.75
Jumlah Total 181,893.75
Jumlah Total + jasa 10% 200,050
25. Pasang kaca rayben tebal 5 mm tiap 1 m²
Harga bahan:
- Kaca rayben 5 mm m² 1.1 297,528 327,280.80
Jumlah Harga Bahan 327,280.80
Upah tenaga:
- Pekerja Oh 0.015 140,000 2,100.00
- Tukang kayu Oh 0.15 160,000 24,000.00
- Kepala tukang Oh 0.015 180,000 2,700.00
- Mandor Oh 0.00075 185,000 138.75
Jumlah Upah Tenaga 28,938.75
Jumlah Total 356,219.55
Jumlah Total + jasa 10% 391,800
26. Pasang kaca tebal 8 mm tiap 1 m²
Harga bahan:
- Kaca 8 mm m² 1.1 275,000 302,500.00
140

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Harga Bahan 302,500.00


Upah tenaga:
- Pekerja Oh 0.0165 140,000 2,310.00
- Tukang kayu Oh 0.165 160,000 26,400.00
- Kepala tukang Oh 0.0165 180,000 2,970.00
- Mandor Oh 0.0008 185,000 148.00
Jumlah Upah Tenaga 31,828.00
Jumlah Total 334,328.00
Jumlah Total + jasa 10% 367,750
27. Pasang kaca rayben tebal 8 mm tiap 1 m²
Harga bahan:
- Kaca rayben 8 mm m² 1.1 286,591 315,250.10
Jumlah Harga Bahan 315,250.10
- Pekerja Oh 0.0165 140,000 2,310.00
- Tukang kayu Oh 0.165 160,000 26,400.00
- Kepala tukang Oh 0.0165 180,000 2,970.00
- Mandor Oh 0.0008 185,000 148.00
Jumlah Upah Tenaga 31,828.00
Jumlah Total 347,078.10
Jumlah Total + jasa 10% 381,750
28. Pasang kaca rayben tebal 10 mm tiap 1 m²
Harga bahan:
- Kaca rayben 10 mm m² 1.1 580,100 638,110.00
Jumlah Harga Bahan 638,110.00
- Pekerja Oh 0.0165 140,000 2,310.00
- Tukang kayu Oh 0.165 160,000 26,400.00
- Kepala tukang Oh 0.0165 180,000 2,970.00
- Mandor Oh 0.0008 185,000 148.00
Jumlah Upah Tenaga 31,828.00
Jumlah Total 669,938.00
Jumlah Total + jasa 10% 736,900
29. Pasang kaca rayben tebal 12 mm tiap 1 m²
Harga bahan:
- Kaca rayben 12 mm m² 1.1 1,114,300 1,225,730.00
Jumlah Harga Bahan 1,225,730.00
- Pekerja Oh 0.025 140,000 3,500.00
- Tukang kayu Oh 0.25 160,000 40,000.00
- Kepala tukang Oh 0.025 180,000 4,500.00
- Mandor Oh 0.00125 185,000 231.25
Jumlah Upah Tenaga 48,231.25
Jumlah Total 1,273,961.25
Jumlah Total + jasa 10% 1,401,350
30. Pasang kaca cermin tebal 5 mm tiap 1m²
Harga bahan:
- Kaca cermin tebal 5 mm m2 1.1000 163,800 180,180.00
Jumlah Harga Bahan 180,180.00
Upah tenaga:
141

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Pekerja Oh 0.0150 140,000 2,100.00


- Tukang kayu Oh 0.1500 160,000 24,000.00
- Kepala tukang Oh 0.0150 180,000 2,700.00
- Mandor Oh 0.0008 185,000 148.00
Jumlah Upah Tenaga 28,948.00
Jumlah Total 209,128.00
Jumlah Total + jasa 10% 230,000
31. Pasang kaca patri tebal 5 mm tiap 1 m²
Harga bahan:
- Kaca patri tebal 5 mm m2 1.1000 950,150 1,045,165.00
Jumlah Harga Bahan 1,045,165.00
Upah tenaga:
- Pekerja Oh 0.0150 140,000 2,100.00
- Tukang kayu Oh 0.1500 160,000 24,000.00
- Kepala tukang Oh 0.0150 180,000 2,700.00
- Mandor Oh 0.0008 185,000 148.00
Jumlah Upah Tenaga 28,948.00
Jumlah Total 1,074,113.00
Jumlah Total + jasa 10% 1,181,500

O PEKERJAAN PENUTUP LANTAI DAN DINDING

1. Pasang lantai Granito ukuran 60 x 60 cm tiap 1m²


Harga bahan:
- Granito tile 60x60 cm bh 2.78 64,750 180,005.00
- Semen portland kg 9.8 1,300 12,740.00
- Pasir pasang m³ 0.045 178,164 8,017.38
- Semen warna kg 1.3 2,375 3,087.50
Jumlah Harga Bahan 203,849.88
Upah tenaga:
- Pekerja Oh 0.25 140,000 35,000.00
- Tukang batu Oh 0.2 125,000 25,000.00
- Kepala tukang Oh 0.013 180,000 2,340.00
- Mandor Oh 0.013 185,000 2,405.00
Jumlah Upah Tenaga 64,745.00
Jumlah Total 268,594.88
Jumlah Total + jasa 10% 295,451.68
2. Pasang lantai keramik ukuran 40 x 40 cm Roman tiap 1m²
Harga bahan:
- Ubin keramik 40 x 40 cm Roman bh 6 19,500 117,000.00
- Semen portland kg 9.8 1,300 12,740.00
- Pasir pasang m³ 0.045 178,164 8,017.38
- Semen warna kg 1.3 2,375 3,087.50
Jumlah Harga Bahan 140,844.88
Upah tenaga:
- Pekerja Oh 0.25 140,000 35,000.00
- Tukang batu Oh 0.125 160,000 20,000.00
142

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Kepala tukang Oh 0.013 180,000 2,340.00


- Mandor Oh 0.013 185,000 2,405.00
Jumlah Upah Tenaga 59,745.00
Jumlah Total 200,589.88
Jumlah Total + jasa 10% 220,600
3. Pasang lantai keramik ukuran 40 x 40 cm setara mulia tiap 1m²
Harga bahan:
- Ubin keramik 40 x 40 cm setara mulia bh 6 12,348 74,088.00
- Semen portland kg 9.8 1,300 12,740.00
- Pasir pasang m³ 0.045 178,164 8,017.38
- Semen warna kg 1.3 2,375 3,087.50
Jumlah Harga Bahan 97,932.88
Upah tenaga:
- Pekerja Oh 0.25 140,000 35,000.00
- Tukang batu Oh 0.125 160,000 20,000.00
- Kepala tukang Oh 0.013 180,000 2,340.00
- Mandor Oh 0.013 185,000 2,405.00
Jumlah Upah Tenaga 59,745.00
Jumlah Total 157,677.88
Jumlah Total + jasa 10% 173,400
4. Pasang lantai Granito ukuran 30 x 30 cm tiap 1m²
Harga bahan:
- Granito tile 30x30 cm bh 11.87 37,044 439,712.28
- Semen portland kg 10 1,300 13,000.00
- Pasir pasang m³ 0.045 178,164 8,017.38
- Semen warna kg 1.5 2,375 3,562.50
Jumlah Harga Bahan 464,292.16
Upah tenaga:
- Pekerja Oh 0.26 140,000 36,400.00
- Tukang batu Oh 0.13 160,000 20,800.00
- Kepala tukang Oh 0.013 180,000 2,340.00
- Mandor Oh 0.013 185,000 2,405.00
Jumlah Upah Tenaga 61,945.00
Jumlah Total 526,237.16
Jumlah Total + jasa 10% 578,850
5. Pasang lantai keramik ukuran 30 x 30 cm Roman tiap 1m²
Harga bahan:
- Ubin keramik 30 x 30 cm Roman bh 11.87 9,182 108,988.18
- Semen portland kg 10 1,300 13,000.00
- Pasir pasang m³ 0.045 178,164 8,017.38
- Semen warna kg 1.5 2,375 3,562.50
Jumlah Harga Bahan 133,568.06
Upah tenaga:
- Pekerja Oh 0.26 140,000 36,400.00
- Tukang batu Oh 0.13 160,000 20,800.00
- Kepala tukang Oh 0.013 180,000 2,340.00
- Mandor Oh 0.013 185,000 2,405.00
143

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Upah Tenaga 61,945.00


Jumlah Total 195,513.06
Jumlah Total + jasa 10% 215,050
6. Pasang lantai keramik ukuran 30 x 30 cm setara mulia tiap 1m²
Harga bahan:
- Ubin keramik 30 x 30 cm setara mulia bh 11.87 5,292 62,816.04
- Semen portland kg 10 1,300 13,000.00
- Pasir pasang m³ 0.045 178,164 8,017.38
- Semen warna kg 1.5 2,375 3,562.50
Jumlah Harga Bahan 87,395.92
Upah tenaga:
- Pekerja Oh 0.26 140,000 36,400.00
- Tukang batu Oh 0.13 160,000 20,800.00
- Kepala tukang Oh 0.013 180,000 2,340.00
- Mandor Oh 0.013 185,000 2,405.00
Jumlah Upah Tenaga 61,945.00
Jumlah Total 149,340.92
Jumlah Total + jasa 10% 164,250
7. Pasang lantai keramik ukuran 20 x 20 cm Roman tiap 1m²
Harga bahan:
- Ubin keramik 20 x 20 cm Roman bh 25 4,400 110,000.00
- Semen portland kg 10.4 1,300 13,520.00
- Pasir pasang m³ 0.045 178,164 8,017.38
- Semen warna kg 1.62 2,375 3,847.50
Jumlah Harga Bahan 135,384.88
Upah tenaga:
- Pekerja Oh 0.27 140,000 37,800.00
- Tukang batu Oh 0.135 160,000 21,600.00
- Kepala tukang Oh 0.014 180,000 2,520.00
- Mandor Oh 0.014 185,000 2,590.00
Jumlah Upah Tenaga 64,510.00
Jumlah Total 199,894.88
Jumlah Total + jasa 10% 219,850
8. Pasang lantai keramik ukuran 20 x 20 cm setara mulia tiap 1m²
Harga bahan:
- Ubin keramik 20 x 20 cm setara mulia bh 26.5 3,410 90,365.00
- Semen portland kg 10.4 1,300 13,520.00
- Pasir pasang m³ 0.045 178,164 8,017.38
- Semen warna kg 1.62 2,375 3,847.50
Jumlah Harga Bahan 115,749.88
Upah tenaga:
- Pekerja Oh 0.27 140,000 37,800.00
- Tukang batu Oh 0.135 160,000 21,600.00
- Kepala tukang Oh 0.014 180,000 2,520.00
- Mandor Oh 0.014 185,000 2,590.00
Jumlah Upah Tenaga 64,510.00
Jumlah Total 180,259.88
144

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Total + jasa 10% 198,250

9. Pasang lantai keramik ukuran 10 x 20 cm Roman tiap 1 m²


Harga bahan:
- Ubin keramik 10 x 20 cm Roman bh 53 750 39,750.00
- Semen portland kg 8.19 1,300 10,647.00
- Pasir pasang m³ 0.045 178,164 8,017.38
- Semen warna kg 2.75 2,375 6,531.25
Jumlah Harga Bahan 64,945.63
Upah tenaga:
- Pekerja Oh 0.62 140,000 86,800.00
- Tukang batu Oh 0.35 160,000 56,000.00
- Kepala tukang Oh 0.035 180,000 6,300.00
- Mandor Oh 0.03 185,000 5,550.00
Jumlah Upah Tenaga 154,650.00
Jumlah Total 219,595.63
Jumlah Total + jasa 10% 241,550
10. Pasang lantai keramik ukuran 10 x 20 cm setara mulia tiap 1 m²
Harga bahan:
- Ubin keramik 10 x 20 cm setara mulia bh 53 600 31,800.00
- Semen portland kg 8.19 1,300 10,647.00
- Pasir pasang m³ 0.045 178,164 8,017.38
- Semen warna kg 2.75 2,375 6,531.25
Jumlah Harga Bahan 56,995.63
Upah tenaga:
- Pekerja Oh 0.27 140,000 37,800.00
- Tukang batu Oh 0.135 160,000 21,600.00
- Kepala tukang Oh 0.014 180,000 2,520.00
- Mandor Oh 0.014 185,000 2,590.00
Jumlah Upah Tenaga 64,510.00
Jumlah Total 121,505.63
Jumlah Total + jasa 10% 133,650
11. Pasang lantai marmer tiap 1m² (100x100) cm
Harga bahan:
- Marmer m² 1.06 131,667 139,566.67
- Semen portland kg 8.19 1,300 10,647.00
- Pasir pasang m³ 0.045 178,164 8,017.38
- Semen warna kg 0.65 2,375 1,543.75
Jumlah Harga Bahan 159,774.80
Upah tenaga:
- Pekerja Oh 0.62 140,000 86,800.00
- Tukang batu Oh 0.35 160,000 56,000.00
- Kepala tukang Oh 0.035 180,000 6,300.00
- Mandor Oh 0.03 185,000 5,550.00
Jumlah Upah Tenaga 154,650.00
Jumlah Total 314,424.80
Jumlah Total + jasa 10% 345,850
145

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

12. Pasang lantai parquet jati tiap 1m²


Harga bahan:
- Parquet m² 1.05 229,050 240,502.50
- Lem vinyl kg 0.6 28,700 17,220.00
Jumlah Harga Bahan 257,722.50
Upah tenaga:
- Pekerja Oh 0.65 140,000 91,000.00
- Tukang batu Oh 0.35 160,000 56,000.00
- Kepala tukang Oh 0.035 180,000 6,300.00
- Mandor Oh 0.0325 185,000 6,012.50
Jumlah Upah Tenaga 159,312.50
Jumlah Total 417,035.00
Jumlah Total + jasa 10% 458,700
13. Pasang lantai vinyl karet kl 1 tiap 1m²
Harga bahan:
- Vinyl karet 30 x 30 cm kl 1 bh 11.87 5,250 62,317.50
- Lem Vinyl kg 0.35 28,700 10,045.00
Jumlah Harga Bahan 72,362.50
Upah tenaga:
- Pekerja Oh 0.15 140,000 21,000.00
- Tukang batu Oh 0.15 160,000 24,000.00
- Kepala tukang Oh 0.015 180,000 2,700.00
- Mandor Oh 0.008 185,000 1,480.00
Jumlah Upah Tenaga 49,180.00
Jumlah Total 121,542.50
Jumlah Total + jasa 10% 133,650
14. Pasang Floor Hardener tiap 1m²
Harga bahan:
- Floor Hardener PM-700 kg 5 5,000 25,000.00
Jumlah Harga Bahan 25,000.00
Upah tenaga:
- Pekerja Oh 0.12 140,000 16,800.00
- Tukang batu Oh 0.12 160,000 19,200.00
- Kepala tukang Oh 0.012 180,000 2,160.00
- Mandor Oh 0.006 185,000 1,110.00
Jumlah Upah Tenaga 39,270.00
Jumlah Total 64,270.00
Jumlah Total + jasa 10% 70,650
15. Pasang dinding marmer tiap 1m²
Harga bahan:
- Marmer m² 1.02 131,667 134,300.00
- Paku sekrup 3,5" bh 2 450 900.00
- Semen portland kg 12.44 1,300 16,172.00
- Pasir pasang m³ 0.025 178,164 4,454.10
- Semen warna kg 0.65 2,375 1,543.75
Jumlah Harga Bahan 157,369.85
Upah tenaga:
146

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Pekerja Oh 0.72 140,000 100,800.00


- Tukang batu Oh 0.65 160,000 104,000.00
- Kepala tukang Oh 0.065 180,000 11,700.00
- Mandor Oh 0.035 185,000 6,475.00
Jumlah Upah Tenaga 222,975.00
Jumlah Total 380,344.85
Jumlah Total + jasa 10% 418,350
16. Pasang dinding keramik 20 x 20 cm Roman tiap 1m²
Harga bahan:
- Ubin keramik 20 x 20 cm Roman bh 26.5 4,400 116,600.00
- Semen portland kg 9.3 1,300 12,090.00
- Pasir pasang m³ 0.018 178,164 3,206.95
- Semen warna kg 1.94 2,375 4,607.50
Jumlah Harga Bahan 136,504.45
Upah tenaga:
- Pekerja Oh 0.4 140,000 56,000.00
- Tukang batu Oh 0.2 160,000 32,000.00
- Kepala tukang Oh 0.02 180,000 3,600.00
- Mandor Oh 0.02 185,000 3,700.00
Jumlah Upah Tenaga 95,300.00
Jumlah Total 231,804.45
Jumlah Total + jasa 10% 254,950
17. Pasang dinding keramik 20 x 20 cm setara mulia tiap 1m²
Harga bahan:
- Ubin keramik 20 x 20 cm setara mulia bh 26.5 3,410 90,365.00
- Semen portland kg 9.3 1,300 12,090.00
- Pasir pasang m³ 0.018 178,164 3,206.95
- Semen warna kg 1.94 2,375 4,607.50
Jumlah Harga Bahan 110,269.45
Upah tenaga:
- Pekerja Oh 0.4 140,000 56,000.00
- Tukang batu Oh 0.2 160,000 32,000.00
- Kepala tukang Oh 0.02 180,000 3,600.00
- Mandor Oh 0.02 185,000 3,700.00
Jumlah Upah Tenaga 95,300.00
Jumlah Total 205,569.45
Jumlah Total + jasa 10% 226,100
18. Pasang dinding keramik 20 x 25 cm Roman tiap 1m²
Harga bahan:
- Ubin keramik 20 x 25 cm Roman bh 21.2 5,880 124,656.00
- Semen portland kg 9.3 1,300 12,090.00
- Pasir pasang m³ 0.018 178,164 3,206.95
- Semen warna kg 1.94 2,375 4,607.50
Jumlah Harga Bahan 144,560.45
Upah tenaga:
- Pekerja Oh 0.4 140,000 56,000.00
- Tukang batu Oh 0.2 160,000 32,000.00
147

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Kepala tukang Oh 0.02 180,000 3,600.00


- Mandor Oh 0.02 185,000 3,700.00
Jumlah Upah Tenaga 95,300.00
Jumlah Total 239,860.45
Jumlah Total + jasa 10% 263,800

19. Pasang dinding keramik 20 x 25 cm setara mulia tiap 1m²


Harga bahan:
- Ubin keramik 20 x 25 cm setara mulia bh 21.2 4,351 92,241.20
- Semen portland kg 9.3 1,300 12,090.00
- Pasir pasang m³ 0.018 178,164 3,206.95
- Semen warna kg 1.94 2,375 4,607.50
Jumlah Harga Bahan 112,145.65
Upah tenaga:
- Pekerja Oh 0.4 140,000 56,000.00
- Tukang batu Oh 0.2 160,000 32,000.00
- Kepala tukang Oh 0.02 180,000 3,600.00
- Mandor Oh 0.02 185,000 3,700.00
Jumlah Upah Tenaga 95,300.00
Jumlah Total 207,445.65
Jumlah Total + jasa 10% 228,150
20. Pasang dinding batu tempel tiap m2
Harga bahan:
- Batu tempel m² 1.1 165,000 181,500.00
- Semen portland kg 11.75 1,300 15,275.00
- Pasir pasang m³ 0.035 178,164 6,235.74
Jumlah Harga Bahan 203,010.74

Upah tenaga:
- Pekerja Oh 0.45 140,000 63,000.00
- Tukang batu Oh 0.2 160,000 32,000.00
- Kepala tukang Oh 0.02 180,000 3,600.00
- Mandor Oh 0.2 185,000 37,000.00
Jumlah Upah Tenaga 135,600.00
Jumlah Total 338,610.74
Jumlah Total + jasa 10% 372,450
21. Pasang dinding batu tempel palimanan tiap 1m²
Harga bahan:
- Batu palimanan/andesit m² 1.1 165,000 181,500.00
- Pasir pasang m³ 0.035 178,164 6,235.74
- Semen portland kg 11.75 1,300 15,275.00
Jumlah Harga Bahan 203,010.74
Upah tenaga:
- Pekerja Oh 0.45 140,000 63,000.00
- Tukang batu Oh 0.2 160,000 32,000.00
- Kepala tukang Oh 0.02 180,000 3,600.00
- Mandor Oh 0.2 185,000 37,000.00
148

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Upah Tenaga 135,600.00


Jumlah Total 338,610.74
Jumlah Total + jasa 10% 372,450
22. Pasang plint ubin marmer ukuran 10 x 60 cm tiap 1m'
Harga bahan:
- Plint ubin marmer 10 x 60 bh 1.7 17,150 29,155.00
- Semen portland kg 1.14 1,300 1,482.00
- Pasir pasang m³ 0.003 178,164 534.49
- Semen warna kg 0.1 2,375 237.50
Jumlah Harga Bahan 31,408.99
Upah tenaga:
- Pekerja Oh 0.1 140,000 14,000.00
- Tukang batu Oh 0.1 160,000 16,000.00
- Kepala tukang Oh 0.03 180,000 5,400.00
- Mandor Oh 0.0055 185,000 1,017.50
Jumlah Upah Tenaga 36,417.50
Jumlah Total 67,826.49
Jumlah Total + jasa 10% 74,600
23. Pasang plint ubin marmer ukuran 10 x 40 cm tiap 1m'
Harga bahan:
- Plint ubin marmer 10 x 40 bh 2.65 6,233 16,517.45
- Semen portland kg 1.14 1,300 1,482.00
- Pasir pasang m³ 0.003 178,164 534.49
- Semen warna kg 0.1 2,375 237.50
Jumlah Harga Bahan 18,771.44
Upah tenaga:
- Pekerja Oh 0.09 140,000 12,600.00
- Tukang batu Oh 0.09 160,000 14,400.00
- Kepala tukang Oh 0.009 180,000 1,620.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 29,545.00
Jumlah Total 48,316.44
Jumlah Total + jasa 10% 53,100
24. Pasang plint ubin marmer ukuran 10 x 30 cm tiap 1m'
Harga bahan:
- Plint ubin marmer 10 x 30 bh 3.53 3,410 12,037.30
- Semen portland kg 1.14 1,300 1,482.00
- Pasir pasang m³ 0.003 178,164 534.49
- Semen warna kg 0.1 2,375 237.50
Jumlah Harga Bahan 14,291.29
Upah tenaga:
- Pekerja Oh 0.09 140,000 12,600.00
- Tukang batu Oh 0.09 160,000 14,400.00
- Kepala tukang Oh 0.009 180,000 1,620.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 29,545.00
Jumlah Total 43,836.29
149

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Total + jasa 10% 48,200


25. Pasang plint granito tile ukuran 10 x 40 cm / tiap 1m'
Harga bahan:
- Plint granito tile 10x40 cm bh 2.65 22,226 58,898.90
- Semen portland kg 1.14 1,300 1,482.00
- Pasir pasang m³ 0.003 178,164 534.49
- Semen warna kg 0.1 2,375 237.50
Jumlah Harga Bahan 61,152.89
Upah tenaga:
- Pekerja Oh 0.09 140,000 12,600.00
- Tukang batu Oh 0.09 160,000 14,400.00
- Kepala tukang Oh 0.009 180,000 1,620.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 29,545.00
Jumlah Total 90,697.89
Jumlah Total + jasa 10% 99,750
26. Pasang plint granito tile ukuran 10 x 30 cm / tiap 1m'
Harga bahan:
- Plint granito tile 10x30 cm bh 3.53 4,351 15,359.03
- Semen portland kg 1.14 1,300 1,482.00
- Pasir pasang m³ 0.003 178,164 534.49
- Semen warna kg 0.1 2,375 237.50
Jumlah Harga Bahan 17,613.02
- Pekerja Oh 0.09 140,000 12,600.00
- Tukang batu Oh 0.09 160,000 14,400.00
- Kepala tukang Oh 0.009 180,000 1,620.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 29,545.00
Jumlah Total 47,158.02
Jumlah Total + jasa 10% 51,850
27. Pasang plint keramik ukuran 10 x 40 cm Roman tiap 1m'
Harga bahan:
- Plint keramik 10x40 cm bh 2.5 6,233 15,582.50
- Semen portland kg 1.14 1,300 1,482.00
- Pasir pasang m³ 0.003 178,164 534.49
- Semen warna kg 0.1 2,375 237.50
Jumlah Harga Bahan 17,836.49
Upah tenaga:
- Pekerja Oh 0.09 140,000 12,600.00
- Tukang batu Oh 0.09 160,000 14,400.00
- Kepala tukang Oh 0.009 180,000 1,620.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 29,545.00
Jumlah Total 47,381.49
Jumlah Total + jasa 10% 52,100
28. Pasang plint keramik ukuran 10 x 30 cm Roman tiap 1m'
Harga bahan:
150

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Plint keramik 10x30 cm bh 3.53 3,410 12,037.30


- Semen portland kg 1.14 1,300 1,482.00
- Pasir pasang m³ 0.003 178,164 534.49
- Semen warna kg 0.1 2,375 237.50
Jumlah Harga Bahan 14,291.29
Upah tenaga:
- Pekerja Oh 0.09 140,000 12,600.00
- Tukang batu Oh 0.09 160,000 14,400.00
- Kepala tukang Oh 0.009 180,000 1,620.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 29,545.00
Jumlah Total 43,836.29
Jumlah Total + jasa 10% 48,200
29. Pasang plint keramik ukuran 10 x 20 cm Roman tiap 1m'
Harga bahan:
- Plint keramik 10x20 cm bh 5.3 2,587 13,711.10
- Semen portland kg 1.14 1,300 1,482.00
- Pasir pasang m³ 0.003 178,164 534.49
- Semen warna kg 0.025 2,375 59.38
Jumlah Harga Bahan 15,786.97
- Pekerja Oh 0.09 140,000 12,600.00
- Tukang batu Oh 0.09 160,000 14,400.00
- Kepala tukang Oh 0.009 180,000 1,620.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 29,545.00
Jumlah Total 45,331.97
Jumlah Total + jasa 10% 49,850
30. Pasang plint keramik (list) ukuran 5 x 20 cm Roman tiap 1m'
Harga bahan:
- Ubin keramik 5 x 20 cm Roman bh 5.3 1,500 7,950.00
- Semen portland kg 0.57 1,300 741.00
- Pasir pasang m³ 0.0015 178,164 267.25
- Semen warna kg 0.013 2,375 30.88
Jumlah Harga Bahan 8,989.12
Upah tenaga:
- Pekerja Oh 0.09 140,000 12,600.00
- Tukang batu Oh 0.09 160,000 14,400.00
- Kepala tukang Oh 0.009 180,000 1,620.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 29,545.00
Jumlah Total 38,534.12
Jumlah Total + jasa 10% 42,350
31. Pasang plint keramik (list) ukuran 5 x 20 cm setara mulia tiap 1m'
Harga bahan:
- Ubin keramik 5 x 20 cm setara mulia bh 5.3 862 4,568.65
- Semen portland kg 0.57 1,300 741.00
- Pasir pasang m³ 0.0015 178,164 267.25
151

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Semen warna kg 0.013 2,375 30.88


Jumlah Harga Bahan 5,607.77
Upah tenaga:
- Pekerja Oh 0.09 140,000 12,600.00
- Tukang batu Oh 0.09 160,000 14,400.00
- Kepala tukang Oh 0.009 180,000 1,620.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 29,545.00
Jumlah Total 35,152.77
Jumlah Total + jasa 10% 38,650
32. Pasang keramik stepnosing 5/30 tiap 1 m'
Harga bahan:
- Stepnosing bh 3.6000 10,500 37,800.00
- Semen portland kg 0.4080 1,300 530.40
- Pasir pasang m³ 0.0009 178,164 160.35
- Semen putih Tiga Roda m³ 0.0600 1,300 78.00
Jumlah Harga Bahan 38,568.75
Upah tenaga:
- Pekerja Oh 0.0500 140,000 7,000.00
- Tukang batu Oh 0.1000 160,000 16,000.00
- Kepala tukang Oh 0.0100 180,000 1,800.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 25,262.50
Jumlah Total 63,831.25
Jumlah Total + jasa 10% 70,200
33. Pasang plint vinyil 1m²
Harga bahan:
- Vinyl karet 30 x 30 cm kl 1 bh 3.5 5,250 18,375.00
- Lem vinyl kg 0.08 28,700 2,296.00
Jumlah Harga Bahan 20,671.00
Upah tenaga:
- Pekerja Oh 0.08 140,000 11,200.00
- Tukang batu Oh 0.08 160,000 12,800.00
- Kepala tukang Oh 0.008 180,000 1,440.00
- Mandor Oh 0.004 185,000 740.00
Jumlah Upah Tenaga 26,180.00
Jumlah Total 46,851.00
Jumlah Total + jasa 10% 51,500
34. Pasang plint kayu 2 x 10 cm tiap 1m'
Harga bahan:
- Kayu Jati papan m³ 0.003 25,338,000 76,014.00
- Paku sekrup kg 0.05 48,569 2,428.45
Jumlah Harga Bahan 78,442.45
Upah tenaga:
- Pekerja Oh 0.12 140,000 16,800.00
- Tukang kayu Oh 0.12 160,000 19,200.00
- Kepala tukang Oh 0.012 180,000 2,160.00
152

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Mandor Oh 0.006 185,000 1,110.00


Jumlah Upah Tenaga 39,270.00
Jumlah Total 117,712.45
Jumlah Total + jasa 10% 129,450

P PEKERJAAN PENGECATAN

1. Pengecatan dengan cat KW 2 bidang kayu lama 1 m²


Harga bahan:
- Plamir kayu kg 0.15 40,870 6,130.50
- Cat kayu/besi KW 2 (cat dasar) kg 0.17 37,162 6,317.54
- Cat kayu/besi KW 2 (cat penutup) kg 0.17 50,450 8,576.50
- Amplas lbr 0.5 5,880 2,940.00
- Minyak cat/ thinner ltr 0.2 25,284 5,056.80
- kuas bh 0.05 14,818 740.90
Jumlah Harga Bahan 29,762.24
Upah tenaga:
- Pekerja Oh 0.07 140,000 9,800.00
- Tukang cat Oh 0.075 160,000 12,000.00
- Kepala tukang Oh 0.0075 180,000 1,350.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 23,612.50
Jumlah Total 53,374.74
Jumlah Total + jasa 10% 58,700
2. Pengecatan dengan cat Mowilex bidang kayu lama 1 m²
Harga bahan:
- Plamir kayu kg 0.15 40,870 6,130.50
- Cat kayu/besi Mowilex (cat dasar) kg 0.17 65,600 11,152.00
- Cat kayu/besi Mowilex (cat penutup) kg 0.17 65,600 11,152.00
- Amplas lbr 0.5 5,880 2,940.00
- Minyak cat/ thinner ltr 0.2 25,284 5,056.80
- kuas bh 0.05 14,818 740.90
Jumlah Harga Bahan 37,172.20
Upah tenaga:
- Pekerja Oh 0.07 140,000 9,800.00
- Tukang cat Oh 0.075 160,000 12,000.00
- Kepala tukang Oh 0.0075 180,000 1,350.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 23,612.50
Jumlah Total 60,784.70
Jumlah Total + jasa 10% 66,850
3. Pengecatan bidang kayu baru dg plamir 1 m² + 1 lps dsr + 2 lps penutup KW 2
Harga bahan:
- Cat meni kayu kg 0.2 21,991 4,398.20
- Plamir kayu kg 0.15 40,870 6,130.50
- Cat kayu/besi KW 2 (cat dasar) kg 0.17 37,162 6,317.54
- Cat kayu/besi KW 2 (cat penutup) kg 0.26 50,450 13,117.00
153

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Amplas lbr 0.5 5,880 2,940.00


- Minyak cat/ thinner ltr 0.2 25,284 5,056.80
- kuas bh 0.05 14,818 740.90
Jumlah Harga Bahan 38,700.94
Upah tenaga:
- Pekerja Oh 0.07 140,000 9,800.00
- Tukang cat Oh 0.09 160,000 14,400.00
- Kepala tukang Oh 0.006 180,000 1,080.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 25,742.50
Jumlah Total 64,443.44
Jumlah Total + jasa 10% 70,850
4. Pengecatan bidang kayu baru dg plamir 1 m² + 1 lps dsr + 2 lps penutup Mowilex
Harga bahan:
- Cat meni kayu kg 0.2 21,991 4,398.20
- Plamir kayu kg 0.15 40,870 6,130.50
- Cat kayu/besi Mowilex (cat dasar) kg 0.17 65,600 11,152.00
- Cat kayu/besi Mowilex (cat penutup) kg 0.26 65,600 17,056.00
- Amplas lbr 0.5 5,880 2,940.00
- Minyak cat/ thinner ltr 0.2 25,284 5,056.80
- kuas bh 0.05 14,818 740.90
Jumlah Harga Bahan 47,474.40
Upah tenaga:
- Pekerja Oh 0.07 140,000 9,800.00
- Tukang cat Oh 0.09 160,000 14,400.00
- Kepala tukang Oh 0.006 180,000 1,080.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 25,742.50
Jumlah Total 73,216.90
Jumlah Total + jasa 10% 80,500
5. Pengecatan bidang kayu baru dg plamir 1 m² + 1 lps dsr + 3 lps penutup KW 2
Harga bahan:
- Cat meni kayu kg 0.2 21,991 4,398.20
- Plamir kayu kg 0.15 40,870 6,130.50
- Cat kayu/besi KW 2 (cat dasar) kg 0.17 37,162 6,317.54
- Cat kayu/besi KW 2 (cat penutup) kg 0.35 50,450 17,657.50
- Amplas lbr 0.5 5,880 2,940.00
- Minyak cat/ thinner ltr 0.3 25,284 7,585.20
- kuas bh 0.05 14,818 740.90
Jumlah Harga Bahan 45,769.84
Upah tenaga:
- Pekerja Oh 0.07 140,000 9,800.00
- Tukang cat Oh 0.105 160,000 16,800.00
- Kepala tukang Oh 0.004 180,000 720.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 27,782.50
Jumlah Total 73,552.34
154

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Total + jasa 10% 80,900


6. Pengecatan bidang kayu baru dg plamir 1 m² + 1 lps dsr + 3 lps penutup Mowilex
Harga bahan:
- Cat meni kayu kg 0.2 21,991 4,398.20
- Plamir kayu kg 0.15 40,870 6,130.50
- Cat kayu/besi Mowilex (cat dasar) kg 0.17 65,600 11,152.00
- Cat kayu/besi Mowilex (cat penutup) kg 0.35 65,600 22,960.00
- Amplas lbr 0.5 5,880 2,940.00
- Minyak cat/ thinner ltr 0.3 25,284 7,585.20
- kuas bh 0.05 14,818 740.90
Jumlah Harga Bahan 55,906.80
Upah tenaga:
- Pekerja Oh 0.07 140,000 9,800.00
- Tukang cat Oh 0.105 160,000 16,800.00
- Kepala tukang Oh 0.004 180,000 720.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 27,782.50
Jumlah Total 83,689.30
Jumlah Total + jasa 10% 92,050
7. Pelaburan bidang kayu dgn politur 1 m²
Harga bahan:
- Politur Ltr 0.15 81,732 12,259.80
- Politur jadi Ltr 0.372 82,500 30,690.00
- Amplas Lbr 2 5,880 11,760.00
- kuas bh 0.05 14,818 740.90
Jumlah Harga Bahan 55,450.70
Upah tenaga:
- Tukang cat Oh 0.06 160,000 9,600.00
- Kepala tukang Oh 0.016 180,000 2,880.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 12,942.50
Jumlah Total 68,393.20
Jumlah Total + jasa 10% 75,200
8. Pengecatan bidang kayu dengan politur Ultran tiap 1 m²
Harga bahan:
- Wood filler Ultran kg 0.2 51,979 10,395.80
- Politur Ultran kg 0.3 43,000 12,900.00
- Minyak cat/ thinner Ltr 0.1 25,284 2,528.40
- Amplas Lbr 0.5 5,880 2,940.00
- Kuas bh 0.05 14,818 740.90
Jumlah Harga Bahan 29,505.10
Upah tenaga:
- Pekerja Oh 0.25 140,000 35,000.00
- Tukang cat Oh 0.28 160,000 44,800.00
- Kepala tukang Oh 0.04 180,000 7,200.00
- Mandor Oh 0.02 185,000 3,700.00
Jumlah Upah Tenaga 90,700.00
155

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Total 120,205.10


Jumlah Total + jasa 10% 132,200
9. Pengecatan bidang kayu dengan melamik Impra tiap 1 m²
Harga bahan:
- Wood filler Ultran kg 0.25 51,979 12,994.75
- Sanding sealer Impra kg 0.35 160,450 56,157.50
- Cat warna Ultran kg 0.25 41,700 10,425.00
- Melamic Impra kg 0.3 29,000 8,700.00
- Thinner (High Class) Ltr 0.5 32,500 16,250.00
- Amplas Lbr 0.6 5,880 3,528.00
- Sprayer m2 1 0.00
Jumlah Harga Bahan 108,055.25
Upah tenaga:
- Tukang cat Melamic Oh 0.6 160,000 96,000.00
- Kepala tukang cat Melamic Oh 0.06 180,000 10,800.00
Jumlah Upah Tenaga 106,800.00
Jumlah Total 214,855.25
Jumlah Total + jasa 10% 236,300
10. Pengecatan kusen kayu dengan melamik Impra tiap 1 m'
Harga bahan:
- Wood filler Ultran kg 0.12 51,979 6,237.48
- Sanding sealer Impra kg 0.18 160,450 28,881.00
- Cat warna Ultran kg 0.125 41,700 5,212.50
- Melamic Impra kg 0.2 29,000 5,800.00
- Thinner (High Class) Ltr 0.25 32,500 8,125.00
- Amplas Lbr 0.4 5,880 2,352.00
- Sprayer m' 1 0.00
Jumlah Harga Bahan 56,607.98
Upah tenaga:
- Tukang cat Melamic Oh 0.3 160,000 48,000.00
- Kepala tukang cat Melamic Oh 0.03 180,000 5,400.00
Jumlah Upah Tenaga 53,400.00
Jumlah Bahan & Tenaga 110,007.98
Jumlah Total + jasa 10% 121,000
11. Pelaburan bidang kayu dgn residu dan ter 1 m²
Harga bahan:
- Residu Ltr 0.35 18,581 6,503.35
- kuas bh 0.05 14,818 740.90
Jumlah Harga Bahan 7,244.25
Upah tenaga:
- Pekerja Oh 0.1 140,000 14,000.00
- Mandor Oh 0.006 185,000 1,110.00
Jumlah Upah Tenaga 15,110.00
Jumlah Total 22,354.25
Jumlah Total + jasa 10% 24,550
12. Pelaburan bidang kayu dgn vernis 1 m²
Harga bahan:
156

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Vernis Ltr 0.15 81,732 12,259.80


- Dempul kayu Kg 0.05 16,699 834.95
- Amplas Lbr 0.1 5,880 588.00
- Kuas Bh 0.01 14,818 148.18
Jumlah Harga Bahan 13,830.93
Upah tenaga:
- Pekerja Oh 0.16 140,000 22,400.00
- Tukang cat Oh 0.16 160,000 25,600.00
- Kepala tukang Oh 0.016 180,000 2,880.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 51,342.50
Jumlah Total 65,173.43
Jumlah Total + jasa 10% 71,650
13. Pengecatan tembok baru dg plamir 1 m² + 1 lps dsr + 2 lps penutup KW 2
Harga bahan:
- Plamir tembok kg 0.1 13,289 1,328.90
- Cat tembok KW 2 (cat dasar) kg 0.1 37,162 3,716.20
- Cat tembok KW 2 (cat penutup) kg 0.26 29,350 7,631.00
- Amplas lbr 0.3 5,880 1,764.00
- kuas roll bh 0.015 25,000 375.00
- bak cat bh 0.015 15,500 232.50
Jumlah Harga Bahan 15,047.60
Upah tenaga:
- Pekerja Oh 0.02 140,000 2,800.00
- Tukang cat Oh 0.063 160,000 10,080.00
- Kepala tukang Oh 0.0063 180,000 1,134.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 14,476.50
Jumlah Total 29,524.10
Jumlah Total + jasa 10% 32,450
Mendempul dan menggosok 1 m²
Harga bahan:
- Dempul duco kg 0.08 34,750 2,780.00
- Minyak cat/ thinner Ltr 0.02 25,284 505.68
- Amplas Lbr 0.1 5,880 588.00
Jumlah Harga Bahan 3,873.68
Upah tenaga:
- Pekerja Oh 0.02 140,000 2,800.00
- Tukang cat Oh 0.02 160,000 3,200.00
- Kepala tukang Oh 0.002 180,000 360.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 6,822.50
Jumlah Total 10,696.18
Jumlah Total + jasa 10% 11,750
Mendempul dan menggosok + Pengecatan plafond 1 m² 44,200
14. Pengecatan tembok baru dg plamir 1 m² + 1 lps dsr + 2 lps
Harga bahan:
157

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Plamir tembok kg 0.1 13,289 1,328.90


- Cat tembok Catylac (cat dasar) kg 0.1 28,000 2,800.00
- Cat tembok Catylac (cat penutup) kg 0.26 28,000 7,280.00
- Amplas lbr 0.3 5,880 1,764.00
- kuas roll bh 0.015 25,000 375.00
- bak cat bh 0.015 15,500 232.50
Jumlah Harga Bahan 13,780.40
Upah tenaga:
- Pekerja Oh 0.02 140,000 2,800.00
- Tukang cat Oh 0.063 160,000 10,080.00
- Kepala tukang Oh 0.0063 180,000 1,134.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 14,476.50
Jumlah Total 28,256.90
Jumlah Total + jasa 10% 31,050
Mengikis/mengerok permukaan tiap 1 m²
Upah tenaga:
- Pekerja Oh 0.11 140,000 15,400.00
- Mandor Oh 0.0012 185,000 222.00
Jumlah Upah Tenaga 15,622.00
Jumlah Total 15,622.00
Jumlah Total + jasa 10% 17,150
Mengikis/mengerok permukaan + Pengecatan tembok baru tiap 1 m² 48,200
15. Pengecatan tembok baru dg wall sealer 1 m² + 1 lps dsr + 2 lps
Harga bahan:
- Wall sealer jotashiel kg 0.1 61,800 6,180.00
- Cat tembok jotun jotaplast (cat dasar) kg 0.1 89,100 8,910.00
- Amplas lbr 0.3 5,880 1,764.00
- kuas roll bh 0.015 25,000 375.00
- bak cat bh 0.015 15,500 232.50
Jumlah Harga Bahan 17,461.50
Upah tenaga:
- Pekerja Oh 0.02 140,000 2,800.00
- Tukang cat Oh 0.063 160,000 10,080.00
- Kepala tukang Oh 0.0063 180,000 1,134.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 14,476.50
Jumlah Total 31,938.00
Jumlah Total + jasa 10% 35,100
Mengikis/mengerok permukaan tembok tiap 1 m²
Upah tenaga:
- Pekerja Oh 0.11 140,000 15,400.00
- Mandor Oh 0.0012 185,000 222.00
Jumlah Upah Tenaga 15,622.00
Jumlah Total 15,622.00
Jumlah Total + jasa 10% 17,150
Mengikis/mengerok permukaan tembok + Pengecatan tembok baru tiap 1 m² 52,250
158

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

16. Pengecatan tembok baru dg wall sealer 1 m² + 1 lps dsr + 2 lps jotun
Harga bahan:
- Cat tembok jotun jotaplast (cat dasar) kg 0.1 89,100 8,910.00
- Cat tembok jotun jotaplast (cat penurtup) kg 0.24 95,000 22,800.00
- Amplas lbr 0.3 5,880 1,764.00
- kuas roll bh 0.015 25,000 375.00
Jumlah Harga Bahan 33,849.00
Upah tenaga:
- Pekerja Oh 0.02 140,000 2,800.00
- Tukang cat Oh 0.063 160,000 10,080.00
- Kepala tukang Oh 0.0063 180,000 1,134.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 14,476.50
Jumlah Total 48,325.50
Jumlah Total + jasa 10% 53,150
Mengikis/mengerok permukaan tembok tiap 1 m²
Upah tenaga:
- Pekerja Oh 0.11 140,000 15,400.00
- Mandor Oh 0.0012 185,000 222.00
Jumlah Upah Tenaga 15,622.00
Jumlah Total 15,622.00
Jumlah Total + jasa 10% 17,150
Mengikis/mengerok permukaan tembok + Pengecatan tembok baru tiap 1 m² 70,300
17. Pengecatan bidang tembok lama 1 m² dg 1 lps dsr + 2 lps penutup KW 2
Harga bahan:
- Cat tembok KW 2 (cat dasar) kg 0.12 37,162 4,459.44
- Cat tembok KW 2 (cat penutup) kg 0.18 29,350 5,283.00
- Amplas lbr 0.3 5,880 1,764.00
- kuas roll bh 0.015 25,000 375.00
Jumlah Harga Bahan 11,881.44
Upah tenaga:
- Pekerja Oh 0.028 140,000 3,920.00
- Tukang cat Oh 0.042 160,000 6,720.00
- Kepala tukang Oh 0.0042 180,000 756.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 11,858.50
Jumlah Total 23,739.94
Jumlah Total + jasa 10% 26,100
18. Pengecatan bidang tembok lama 1 m² dg 1 lps dsr + 2 lps
Harga bahan:
- Cat tembok Catylac (cat dasar) kg 0.12 28,000 3,360.00
- Cat tembok Catylac (cat penutup) kg 0.18 28,000 5,040.00
- Amplas lbr 0.3 5,880 1,764.00
- kuas roll bh 0.015 25,000 375.00
Jumlah Harga Bahan 10,539.00
Upah tenaga:
- Pekerja Oh 0.028 140,000 3,920.00
159

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Tukang cat Oh 0.042 160,000 6,720.00


- Kepala tukang Oh 0.0042 180,000 756.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 11,858.50
Jumlah Total 22,397.50
Jumlah Total + jasa 10% 24,600
19. Pengecatan bidang tembok lama 1 m² dg 1 lps dsr + 2 lps
Harga bahan:
- Cat tembok Dulux/ICI (cat dasar) kg 0.12 48,000 5,760.00
- Cat tembok Dulux/ICI (cat penutup) kg 0.18 48,000 8,640.00
- Amplas lbr 0.3 5,880 1,764.00
- kuas roll bh 0.015 25,000 375.00
Jumlah Harga Bahan 16,539.00
Upah tenaga:
- Pekerja Oh 0.028 140,000 3,920.00
- Tukang cat Oh 0.042 160,000 6,720.00
- Kepala tukang Oh 0.0042 180,000 756.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 11,858.50
Jumlah Total 28,397.50
Jumlah Total + jasa 10% 31,200
20. Memasang wallpaper 1 m²
Harga bahan:
- Wallpaper m2 1.1 90,000 99,000.00
- Lem perekat kg 0.18 28,700 5,166.00
Jumlah Harga Bahan 104,166.00
Upah tenaga:
- Pekerja Oh 0.028 140,000 3,920.00
- Tukang cat Oh 0.042 160,000 6,720.00
- Kepala tukang Oh 0.0042 180,000 756.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 11,858.50
Jumlah Total 116,024.50
Jumlah Total + jasa 10% 127,600
21. Mengecat genteng 1 m² ( renovasi )
Harga bahan:
- Cat genteng KW 2 kg 0.3600 35,633 12,827.88

Jumlah Harga Bahan 12,827.88


Upah tenaga:
- Pekerja Oh 0.02 140,000 2,800.00
- Tukang cat Oh 0.063 160,000 10,080.00
- Kepala tukang Oh 0.0063 180,000 1,134.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 14,476.50
Jumlah Total 27,304.38
Jumlah Total + jasa 10% 30,000
160

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

22. Mengecat genteng 1 m² ( baru )


Harga bahan:
Mengikis dan mengerok permukaan m2 1.0000 17,150 17,150
- Cat genteng KW 2 kg 0.3600 35,633 12,828
- Kuas bh 0.0300 14,818 445

Jumlah Harga Bahan 30,422.42


Upah tenaga:
- Pekerja Oh 0.02 140,000 2,800.00
- Tukang cat Oh 0.063 160,000 10,080.00
- Kepala tukang Oh 0.0063 180,000 1,134.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 14,476.50
Jumlah Total 44,898.92
Jumlah Total + jasa 10% 49,350
23. Pengecatan permukaan baja 1 m² dgn meni besi
Harga bahan:
- Cat meni besi kg 0.1 14,200 1,420.00
- Kuas bh 0.01 14,818 148.18
- Amplas lbr 0.4 5,880 2,352.00
Jumlah Harga Bahan 3,920.18
Upah tenaga:
- Pekerja Oh 0.02 140,000 2,800.00
- Tukang cat Oh 0.20 160,000 32,000.00
- Kepala tukang Oh 0.02 180,000 3,600.00
- Mandor Oh 0.001 185,000 185.00
Jumlah Upah Tenaga 38,585.00
Jumlah Total 42,505.18
Jumlah Total + jasa 10% 46,750
24. Pengecatan permukaan baja 1 m² dgn meni besi & perancah
Harga bahan:
- Cat meni besi kg 0.1 14,200 1,420.00
- Kuas bh 0.01 14,818 148.18
- Kayu Terentang balok m³ 0.002 2,826,516 5,653.03
- Amplas lbr 0.4 5,880 2,352.00
Jumlah Harga Bahan 9,573.21
Upah tenaga:
- Pekerja Oh 0.25 140,000 35,000.00
- Tukang cat Oh 0.225 160,000 36,000.00
- Kepala tukang Oh 0.0225 180,000 4,050.00
- Mandor Oh 0.0075 185,000 1,387.50
Jumlah Upah Tenaga 76,437.50
Jumlah Total 86,010.71
Jumlah Total + jasa 10% 94,600
25. Pengecatan permukaan baja tiap 1 m² dengan zinchromate
Harga bahan:
- Cat zinchromate kg 0.3 50,100 15,030.00
161

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Minyak cat/ thinner ltr 0.1 25,284 2,528.40


- Amplas lbr 0.4 5,880 2,352.00
- kuas bh 0.03 14,818 444.54
Jumlah Harga Bahan 20,354.94
Upah tenaga:
- Pekerja Oh 0.07 140,000 9,800.00
- Tukang cat Oh 0.09 160,000 14,400.00
- Kepala tukang Oh 0.006 180,000 1,080.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 25,742.50
Jumlah Total 46,097.44
Jumlah Total + jasa 10% 50,700
26. Pengecatan permukaan baja tiap 1 m² dengan Cat KW 2
Harga bahan:
- Cat meni besi kg 0.1 14,200 1,420.00
- Cat kayu/besi KW 2 (cat dasar) kg 0.17 37,162 6,317.54
- Cat kayu/besi KW 2 (cat penutup) kg 0.26 50,450 13,117.00
- Minyak cat/ thinner ltr 0.15 25,284 3,792.60
- Amplas lbr 0.4 5,880 2,352.00
- kuas bh 0.05 14,818 740.90
Jumlah Harga Bahan 27,740.04
Upah tenaga:
- Pekerja Oh 0.07 140,000 9,800.00
- Tukang cat Oh 0.09 160,000 14,400.00
- Kepala tukang Oh 0.006 180,000 1,080.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 25,742.50
Jumlah Total 53,482.54
Jumlah Total + jasa 10% 58,800
27. Pengecatan permukaan baja tiap 1 m² dengan Cat Mowilex
Harga bahan:
- Cat meni besi kg 0.1 14,200 1,420.00
- Cat kayu/besi Mowilex (cat dasar) kg 0.17 65,600 11,152.00
- Cat kayu/besi Mowilex (cat penutup) kg 0.26 65,600 17,056.00
- Minyak cat/ thinner ltr 0.15 25,284 3,792.60
- Amplas lbr 0.4 5,880 2,352.00
- kuas bh 0.05 14,818 740.90
Jumlah Harga Bahan 36,513.50
Upah tenaga:
- Pekerja Oh 0.07 140,000 9,800.00
- Tukang cat Oh 0.09 160,000 14,400.00
- Kepala tukang Oh 0.006 180,000 1,080.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 25,742.50
Jumlah Total 62,256.00
Jumlah Total + jasa 10% 68,450
28. Pekerjaan cat duko 3x tiap 1 m²
162

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Harga bahan:
- Cat Duco Nippe 2000 kg 0.4250 42,750 18,168.75
- Thinner (High Class) ltr 0.0570 32,500 1,852.50
- Amplas lbr 0.1000 5,880 588.00
Jumlah Harga Bahan 20,609.25
Upah tenaga:
- Pekerja Oh 0.2000 140,000 28,000.00
- Tukang cat Oh 0.3000 160,000 48,000.00
- Kepala tukang Oh 0.0300 180,000 5,400.00
- Mandor Oh 0.0100 185,000 1,850.00
Jumlah Upah Tenaga 83,250.00
Jumlah Total 103,859.25
Jumlah Total + jasa 10% 114,200
29. Pengecatan waterproofing (coating) tiap 1 m²
Harga bahan:
- Cumoir Waterproofing Coating kg 0.3 34,300 10,290.00
- kuas bh 0.2 14,818 2,963.60
Jumlah Harga Bahan 13,253.60
Upah tenaga:
- Pekerja Oh 0.02 140,000 2,800.00
- Tukang cat Oh 0.063 160,000 10,080.00
- Kepala tukang Oh 0.0063 180,000 1,134.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 14,476.50
Jumlah Total 27,730.10
Jumlah Total + jasa 10% 30,500
30. Pengecatan waterproofing sika tiap 1 m²
Harga bahan:
- Waterproofing Sika m2 1.05 140,000 147,000.00
- Material primer kg 0.3 21,100 6,330.00
- kuas bh 0.2 14,818 2,963.60
- Pengetesan m2 1 3,000 3,000.00
Jumlah Harga Bahan 159,293.60
Upah tenaga:
- Pekerja Oh 0.02 140,000 2,800.00
- Tukang cat Oh 0.063 160,000 10,080.00
- Kepala tukang Oh 0.0063 180,000 1,134.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 14,476.50
Jumlah Total 173,770.10
Jumlah Total + jasa 10% 191,100
31. Pengecatan permukaan kayu 1 m² dgn meni
Harga bahan:
- Cat meni kayu kg 0.25 21,991 5,497.75
- Kuas bh 0.025 14,818 370.45
- Amplas lbr 0.4 5,880 2,352.00
Jumlah Harga Bahan 8,220.20
163

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Upah tenaga:
- Pekerja Oh 0.02 140,000 2,800.00
- Tukang cat Oh 0.20 160,000 32,000.00
- Kepala tukang Oh 0.02 180,000 3,600.00
- Mandor Oh 0.001 185,000 185.00
Jumlah Upah Tenaga 38,585.00
Jumlah Total 46,805.20
Jumlah Total + jasa 10% 51,450

Q PEKERJAAN BONGKARAN

1. Bongkar beton bertulang tiap 1m³


Upah tenaga:
- Pekerja Oh 6.667 140,000 933,380.00
- Mandor Oh 0.333 185,000 61,605.00
Jumlah Upah Tenaga 994,985.00
Jumlah Total 994,985.00
Jumlah Total + jasa 10% 1,094,450
2. Bongkar dinding tembok bata merah tiap 1m³
Upah tenaga:
- Pekerja Oh 0.667 140,000 93,380.00
- Mandor Oh 0.033 185,000 6,105.00
Jumlah Upah Tenaga 99,485.00
Jumlah Total 99,485.00
Jumlah Total + jasa 10% 109,400
3. Bongkar dinding ½ bata tiap 1m²
Upah tenaga:
- Pekerja Oh 0.073 140,000 10,220.00
- Mandor Oh 0.0036 185,000 666.00
Jumlah Upah Tenaga 10,886.00
Jumlah Total 10,886.00
Jumlah Total + jasa 10% 11,950
4. Bongkar pelat beton bertulang tiap 1m²
Upah tenaga:
- Pekerja Oh 0.8 140,000 112,000.00
- Mandor Oh 0.04 185,000 7,400.00
Jumlah Upah Tenaga 119,400.00
Jumlah Total 119,400.00
Jumlah Total + jasa 10% 131,300
5. Bongkar batu kali tebal < 50 cm tiap 1 m³
Upah tenaga:
- Pekerja Oh 1.5 140,000 210,000.00
- Mandor Oh 0.075 185,000 13,875.00
Jumlah Upah Tenaga 223,875.00
Jumlah Total 223,875.00
Jumlah Total + jasa 10% 246,250
6. Bongkar batu kali tebal > 50 cm tiap 1 m³
164

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Upah tenaga:
- Pekerja Oh 3 140,000 420,000.00
- Mandor Oh 0.15 185,000 27,750.00
Jumlah Upah Tenaga 447,750.00
Jumlah Total 447,750.00
Jumlah Total + jasa 10% 492,500
7. Bongkar lantai tiap 1 m²
Upah tenaga:
- Pekerja Oh 0.05 140,000 7,000.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 7,925.00
Jumlah Total 7,925.00
Jumlah Total + jasa 10% 8,700
8. Bongkar paving block tiap 1 m²
Upah tenaga:
- Pekerja Oh 0.05 140,000 7,000.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 7,925.00
Jumlah Total 7,925.00
Jumlah Total + jasa 10% 8,700
9. Bongkar plesteran tiap 1 m²
Upah tenaga:
- Pekerja Oh 0.05 140,000 7,000.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 7,462.50
Jumlah Total 7,462.50
Jumlah Total + jasa 10% 8,200
10. Bongkar atap genteng tiap 1 m²
Upah tenaga:
- Pekerja Oh 0.02 140,000 2,800.00
- Mandor Oh 0.01 185,000 1,850.00
Jumlah Upah Tenaga 4,650.00
Jumlah Total 4,650.00
Jumlah Total + jasa 10% 5,100
11. Bongkar karpusan atap genteng tiap 1 m'
Upah tenaga:
- Pekerja Oh 0.03 140,000 4,200.00
- Mandor Oh 0.015 185,000 2,775.00
Jumlah Upah Tenaga 6,975.00
Jumlah Total 6,975.00
Jumlah Total + jasa 10% 7,650
12. Bongkar atap seng/asbes tiap 1 m²
Upah tenaga:
- Pekerja Oh 0.05 140,000 7,000.00
- Tukang besi Oh 0.025 160,000 4,000.00
Jumlah Upah Tenaga 11,000.00
Jumlah Total 11,000.00
165

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Total + jasa 10% 12,100


13. Bongkar kaso dan reng kayu (kayu akan dipakai lagi) tiap 1 m²
Upah tenaga:
- Pekerja Oh 0.1 140,000 14,000.00
- Tukang kayu Oh 0.025 160,000 4,000.00
- Kepala tukang Oh 0.0025 180,000 450.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 19,375.00
Jumlah Total 19,375.00
Jumlah Total + jasa 10% 21,300
14. Bongkar kaso dan reng kayu (kayu tidak akan dipakai lagi) tiap 1 m²
Upah tenaga:
- Pekerja Oh 0.1 140,000 14,000.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 14,925.00
Jumlah Total 14,925.00
Jumlah Total + jasa 10% 16,400
15. Bongkar balok kuda-kuda & loteng (kayu akan dipakai lagi) tiap 1 m³
Upah tenaga:
- Pekerja Oh 2.666 140,000 373,240.00
- Tukang kayu Oh 4 160,000 640,000.00
- Kepala tukang Oh 0.4 180,000 72,000.00
- Mandor Oh 0.133 185,000 24,605.00
Jumlah Upah Tenaga 1,109,845.00
Jumlah Total 1,109,845.00
Jumlah Total + jasa 10% 1,220,800
16. Bongkar balok kuda-kuda & loteng (kayu tidak akan dipakai lagi) tiap 1 m³
Upah tenaga:
- Tukang kayu Oh 4 160,000 640,000.00
- Kepala tukang Oh 0.4 180,000 72,000.00
Jumlah Upah Tenaga 712,000.00
Jumlah Total 712,000.00
Jumlah Total + jasa 10% 783,200
17. Bongkar rangka plafon tiap 1 m²
Upah tenaga:
- Pekerja Oh 0.1 140,000 14,000.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 14,925.00
Jumlah Total 14,925.00
Jumlah Total + jasa 10% 16,400
18. Bongkar penutup plafon tiap 1 m²
Upah tenaga:
- Tukang kayu Oh 0.03 160,000 4,800.00
- Kepala tukang Oh 0.003 180,000 540.00
Jumlah Upah Tenaga 5,340.00
Jumlah Total 5,340.00
Jumlah Total + jasa 10% 5,850
166

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

R PEKERJAAN INSTALASI LISTRIK

1. Pasang instalasi lampu dg NYM 3x2,5 mm² tiap 1 titik (tidak termasuk fitting, sakelar & lampu)
Catatan: Asumsi tinggi plafond 4 m', bentang ruang 8 m', uk. Kabel standar PUIL 2000
Harga bahan:
- Kabel NYM 3x2,5 mm² m' 12.000 9,800 117,600.00
- Conduit pipa PVC dia ⅝" C m' 12.000 9,500 114,000.00
- Tee dos bh 1.000 3,100 3,100.00
- Inbow doos bh 1.000 2,000 2,000.00
- Sock bh 3.000 2,000 6,000.00
- Klem conduit bh 9.000 2,000 18,000.00
- Lastdop bh 3.000 3,000 9,000.00
- Flexible pipe m' 1.000 1,500 1,500.00
- Elbow bh 2.000 2,000 4,000.00
- Paku, sekrup, fisher (10% harga conduit) % 10.000 114,000 11,400.00
Jumlah Harga Bahan 286,600.00
Upah tenaga:
- Instalator Oh 0.14 180,000 25,560.00
- Pekerja Oh 0.07 140,000 9,940.00
- Mandor Oh 0.01 185,000 1,313.50
Jumlah Upah Tenaga 36,813.50
Jumlah Total 323,413.50
Jumlah Total + jasa 10% 355,750
2. Pasang instalasi lampu dg NYM 2x2,5 mm² tiap 1 titik (tidak termasuk fitting, sakelar & lampu)
Catatan: Tdk termasuk fitting lampu, sakelar & lampu. Asumsi tinggi plafond 4 m', bentang ruang 8 m', uk. Kabel standar PUIL 2000
Harga bahan:
- Kabel NYM 2x2,5 mm² m' 12 9,707 116,480.40
- Conduit pipa PVC dia ⅝" C m' 12 9,500 114,000.00
- Tee dos bh 1 3,100 3,100.00
- Inbow doos bh 1 2,000 2,000.00
- Sock bh 3 2,000 6,000.00
- Klem conduit bh 9 2,000 18,000.00
- Lastdop bh 3 3,000 9,000.00
- Flexible pipe m' 1 1,500 1,500.00
- Elbow bh 2 2,000 4,000.00
- Paku, sekrup, fisher (10% harga conduit) % 10 114,000 11,400.00
Jumlah Harga Bahan 285,480.40
Upah tenaga:
- Instalator Oh 0.14 180,000 25,560.00
- Pekerja Oh 0.071 140,000 9,940.00
- Mandor Oh 0.0071 185,000 1,313.50
Jumlah Upah Tenaga 36,813.50
Jumlah Total 322,293.90
Jumlah Total + jasa 10% 354,500
3. Pasang instalasi lampu dg NYM 2x1,5 mm² tiap 1 titik (tidak termasuk fitting, sakelar & lampu)
Catatan: Fitting lampu, sakelar & lampu tidak dimasukkan dalam analisis, tergantung spesifikasi teknis dan merek yang diinginkan.
167

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Analisis dibuat untuk rumah & gedung sederhana, kabel yang dipakai NYM 2x1,5 mm².
Harga bahan:
- Kabel NYM 2x1,5 mm² m' 12 6,301 75,612.00
- Conduit pipa PVC dia ⅝" C m' 12 9,500 114,000.00
- Tee dos bh 1 3,100 3,100.00
- Inbow doos bh 1 2,000 2,000.00
- Sock bh 3 2,000 6,000.00
- Klem conduit bh 9 2,000 18,000.00
- Lastdop bh 3 3,000 9,000.00
- Flexible pipe m' 1 1,500 1,500.00
- Elbow bh 2 2,000 4,000.00
- Paku, sekrup, fisher (10% harga conduit) % 10 114,000 11,400.00
Jumlah Harga Bahan 244,612.00
Upah tenaga:
- Instalator Oh 0.3 180,000 54,000.00
- Pekerja Oh 0.15 140,000 21,000.00
- Mandor Oh 0.015 185,000 2,775.00
Jumlah Upah Tenaga 77,775.00
Jumlah Total 322,387.00
Jumlah Total + jasa 10% 354,600
4. Pasang instalasi lampu untuk gedung pertemuan & gudang tiap 1 titik (tidak termasuk fitting, sakelar & lampu)
Catatan: Fitting lampu, sakelar & lampu tidak dimasukkan dalam analisis, tergantung spesifikasi teknis dan merek yang diinginkan.
Asumsi tinggi plafon 4-10 m', analisis tersebut dipakai untuk ruangan seperti gudang, gedung pertemuan, aula, rumah ibadat, bengkel.
Harga bahan:
- Kabel NYM 3x2,5 mm² m' 24 9,800 235,200.00
- Conduit pipa PVC dia ⅝" C m' 24 9,500 228,000.00
- Tee dos bh 1 3,100 3,100.00
- Inbow doos bh 1 2,000 2,000.00
- Sock bh 6 2,000 12,000.00
- Klem conduit bh 18 2,000 36,000.00
- Lastdop bh 3 3,000 9,000.00
- Flexible pipe m' 1 1,500 1,500.00
- Elbow bh 2 2,000 4,000.00
- Paku, sekrup, fisher (10% harga conduit) % 10 228,000 22,800.00
Jumlah Harga Bahan 553,600.00
Upah tenaga:
- Instalator Oh 0.6 180,000 108,000.00
- Pekerja Oh 0.3 140,000 42,000.00
- Mandor Oh 0.03 185,000 5,550.00
Jumlah Upah Tenaga 155,550.00
Jumlah Total 709,150.00
Jumlah Total + jasa 10% 780,050
5. Pasang instalasi stop kontak tiap 1 titik (tidak termasuk stop kontak)
Catatan: Stop kontak tidak dimasukkan dalam analisis, tergantung spesifikasi teknis dan merek yang diinginkan.
Harga bahan:
- Kabel NYM 3x2,5 mm² m' 12 9,800 117,600.00
- Conduit pipa PVC dia ⅝" C m' 12 9,500 114,000.00
168

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Tee dos bh 1 3,100 3,100.00


- Inbow doos bh 1 2,000 2,000.00
- Sock bh 3 2,000 6,000.00
- Klem conduit bh 9 2,000 18,000.00
- Lastdop bh 3 3,000 9,000.00
- Elbow bh 2 2,000 4,000.00
- Paku, sekrup, fisher (10% harga conduit) % 10 114,000 11,400.00
Jumlah Harga Bahan 285,100.00
Upah tenaga:
- Instalator Oh 0.14 180,000 25,560.00
- Pekerja Oh 0.071 140,000 9,940.00
- Mandor Oh 0.0071 185,000 1,313.50
Jumlah Upah Tenaga 36,813.50
Jumlah Total 321,913.50
Jumlah Total + jasa 10% 354,100
6. Pasang instalasi stop kontak lebih dari 500 watt tiap 1 titik (tidak termasuk stop kontak)
Catatan: Stop kontak tidak dimasukkan dalam analisis, tergantung spesifikasi teknis dan merek yang diinginkan.
Harga bahan:
- Kabel NYM 3x4 mm² m' 24.000 14,500 348,000.00
- Conduit pipa PVC dia ⅝" C m' 24.000 9,500 228,000.00
- Outlet Box Metal bh 1.000 10,000 10,000.00
- Tee dos bh 1.000 3,100 3,100.00
- Inbow doos bh 1.000 2,000 2,000.00
- Sock bh 9.000 2,000 18,000.00
- Klem conduit bh 20.000 2,000 40,000.00
- Lastdop bh 3.000 3,000 9,000.00
- Elbow bh 4.000 2,000 8,000.00
- Paku, sekrup, fisher (10% harga conduit) % 10.000 228,000 22,800.00
Jumlah Harga Bahan 688,900.00
Upah tenaga:
- Instalator Oh 0.500 180,000 90,000.00
- Pekerja Oh 0.250 140,000 35,000.00
- Mandor Oh 0.025 185,000 4,625.00
Jumlah Upah Tenaga 129,625.00
Jumlah Total 818,525.00
Jumlah Total + jasa 10% 900,350
7. Pasang instalasi listrik + outlet AC tiap 1 titik (tidak termasuk AC)
Catatan: Unit AC tidak dimasukkan dalam analisis, tergantung spesifikasi teknis dan merek yang diinginkan.
Harga bahan:
- Kabel NYM 3x2,5 mm² m' 12 9,800 117,600.00
- Conduit pipa PVC dia ⅝" C m' 12 9,500 114,000.00
- Kotak kontak khusus (KKK) bh 1 125,000 125,000.00
- Tee dos bh 1 3,100 3,100.00
- Inbow doos bh 1 2,000 2,000.00
- Sock bh 3 2,000 6,000.00
- Klem conduit bh 9 2,000 18,000.00
- Lastdop bh 3 3,000 9,000.00
169

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Elbow bh 2 2,000 4,000.00


- Paku, sekrup, fisher (10% harga conduit) % 10 114,000 11,400.00
Jumlah Harga Bahan 410,100.00
Upah tenaga:
- Instalator Oh 0.14 180,000 25,560.00
- Pekerja Oh 0.071 140,000 9,940.00
- Mandor Oh 0.0071 185,000 1,313.50
Jumlah Upah Tenaga 36,813.50
Jumlah Total 446,913.50
Jumlah Total + jasa 10% 491,600

Catatan :
Analisis Pasang Instalasi Lampu dgn NYM 3x2,5 mm2 dan Pasang Instalasi Stop Kontak diatas 500 W , tertulis di
V Pekerjaan Analisa Tambahan Halaman 80.

8. Pasang instalasi + tiang antena TV tiap 1 titik (tidak termasuk socket & antena)
Catatan: Socket & antena tidak dimasukkan dalam analisis, tergantung spesifikasi teknis dan merek yang diinginkan.
Harga bahan:
- Kabel antena TV m' 20 6,300 126,000.00
- Conduit pipa PVC dia ⅝" C m' 20 9,500 190,000.00
- Inbow doos bh 1 2,000 2,000.00
- Sock bh 5 2,000 10,000.00
- Klem conduit bh 14 2,000 28,000.00
- Klem pipa besi 3/4" bh 2 1,550 3,100.00
- Pipa galvanis dia 3/4" m' 2 29,753 59,505.50
- Paku, sekrup, fisher (10% harga conduit) % 10 190,000 19,000.00
Jumlah Harga Bahan 437,605.50
Upah tenaga:
- Instalator Oh 0.14 180,000 25,560.00
- Pekerja Oh 0.071 140,000 9,940.00
- Mandor Oh 0.0071 185,000 1,313.50
Jumlah Upah Tenaga 36,813.50
Jumlah Total 474,419.00
Jumlah Total + jasa 10% 521,850
9. Pasang instalasi telepon tiap 1 titik (tidak termasuk outlet, pesawat telepon & sambungan Telkom)
Catatan: Outlet & pesawat telepon tidak dimasukkan dalam analisis, tergantung spesifikasi teknis dan merek yang diinginkan.
Harga bahan:
- Kabel telepon m' 20 3,650 73,000.00
- Conduit pipa PVC dia ⅝" C m' 20 9,500 190,000.00
- Inbow doos bh 1 2,000 2,000.00
- Sock bh 5 2,000 10,000.00
- Klem conduit bh 14 2,000 28,000.00
- Elbow bh 2 2,000 4,000.00
- Paku, sekrup, fisher (10% harga conduit) % 10 190,000 19,000.00
Jumlah Harga Bahan 326,000.00
Upah tenaga:
170

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Instalator Oh 0.14 180,000 25,560.00


- Pekerja Oh 0.071 140,000 9,940.00
- Mandor Oh 0.0071 185,000 1,313.50
Jumlah Upah Tenaga 36,813.50
Jumlah Total 362,813.50
Jumlah Total + jasa 10% 399,050
10. Pasang instalasi telepon paralel/extension line tiap 1 titik (tidak termasuk outlet, pesawat telepon)
Catatan: Outlet & pesawat telepon tidak dimasukkan dalam analisis, tergantung spesifikasi teknis dan merek yang diinginkan.
Harga bahan:
- Kabel telepon m' 12 3,650 43,800.00
- Conduit pipa PVC dia ⅝" C m' 12 9,500 114,000.00
- Inbow doos bh 1 2,000 2,000.00
- Sock bh 3 2,000 6,000.00
- Klem conduit bh 9 2,000 18,000.00
- Elbow bh 2 2,000 4,000.00
- Paku, sekrup, fisher (10% harga conduit) % 10 114,000 11,400.00
Jumlah Harga Bahan 199,200.00
- Instalator Oh 0.14 180,000 25,560.00
- Pekerja Oh 0.071 140,000 9,940.00
- Mandor Oh 0.0071 185,000 1,313.50
Jumlah Upah Tenaga 36,813.50
Jumlah Total 236,013.50
Jumlah Total + jasa 10% 259,600
11. Pasang Panel Pembagi Daya 1300 VA / 6 A (3 grup @ 6 A) tiap 1 unit
Catatan: Belum termasuk penyambungan daya listrik PLN
Harga bahan:
- Kabel NYM 3x4 mm² m' 10 14,500 145,000.00
- Kabel NYM 3x2,5 mm² m' 30 9,800 294,000.00
- Conduit pipa PVC dia ⅝" C m' 40 9,500 380,000.00
- MCB box isi 4 bh 1 40,000 40,000.00
- MCB 6 A bh 4 105,000 420,000.00
- Tee dos bh 4 3,100 12,400.00
- Sock bh 10 2,000 20,000.00
- Klem conduit bh 27 2,000 54,000.00
- Lastdop bh 12 3,000 36,000.00
- Elbow bh 2 2,000 4,000.00
- Paku, sekrup, fisher (10% harga conduit) % 10 380,000 38,000.00
Jumlah Harga Bahan 1,443,400.00
Upah tenaga:
- Instalator Oh 0.8 180,000 144,000.00
- Pekerja Oh 0.4 140,000 56,000.00
- Mandor Oh 0.04 185,000 7,400.00
Jumlah Upah Tenaga 207,400.00
Jumlah Total 1,650,800.00
Jumlah Total + jasa 10% 1,815,850
12. Pasang Panel Pembagi Daya 2200 VA / 10 A (3 grup @ 10 A) tiap 1 unit
Catatan: Belum termasuk penyambungan daya listrik PLN
171

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Harga bahan:
- Kabel NYM 3x4 mm² m' 10 14,500 145,000.00
- Kabel NYM 3x2,5 mm² m' 30 9,800 294,000.00
- Conduit pipa PVC dia ⅝" C m' 40 9,500 380,000.00
- MCB box isi 4 bh 1 40,000 40,000.00
- MCB 10 A bh 4 113,249 452,996.00
- Tee dos bh 4 3,100 12,400.00
- Sock bh 10 2,000 20,000.00
- Klem conduit bh 27 2,000 54,000.00
- Lastdop bh 12 3,000 36,000.00
- Elbow bh 2 2,000 4,000.00
- Paku, sekrup, fisher (10% harga conduit) % 10 380,000 38,000.00
Jumlah Harga Bahan 1,476,396.00
Upah tenaga:
- Instalator Oh 0.8 180,000 144,000.00
- Pekerja Oh 0.4 140,000 56,000.00
- Mandor Oh 0.04 185,000 7,400.00
Jumlah Upah Tenaga 207,400.00
Jumlah Total 1,683,796.00
Jumlah Total + jasa 10% 1,852,150
13. Pasang pentanahan (grounding) tiap 1 titik
Harga bahan:
- Kabel BC 10 mm m' 5 11,600 58,000.00
- Conduit pipa PVC dia ⅝" C m' 3 9,500 28,500.00
- Klem conduit bh 3 2,000 6,000.00
- Lastdop bh 1 3,000 3,000.00
- Paku, sekrup, fisher (10% harga conduit) % 10 28,500 2,850.00
Jumlah Harga Bahan 98,350.00
Upah tenaga:
- Instalator Oh 0.2 180,000 36,000.00
- Pekerja Oh 0.1 140,000 14,000.00
- Mandor Oh 0.01 185,000 1,850.00
Jumlah Upah Tenaga 51,850.00
Jumlah Total 150,200.00
Jumlah Total + jasa 10% 165,200
14. Pasang 1 buah lampu SL
Harga bahan:
- Lampu SL 20 watt bh 1 41,700 41,700.00
- Accecories ( 1 % alat ) % 1 41,700 417.00
Jumlah Harga Bahan 42,117.00
Upah tenaga:
- Instalator Oh 0.1 180,000 18,000.00
- Pekerja Oh 0.05 140,000 7,000.00
Jumlah Upah Tenaga 25,000.00
Jumlah Total 67,117.00
Jumlah Total + jasa 10% 73,800
15. Pasang 1 buah lampu TL 1x18 RM
172

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Harga bahan:
- Lampu TL 1x18 watt RM bh 1 213,444 213,444.00
- Accecories ( 1 % alat ) % 1 213,444 2,134.44
Jumlah Harga Bahan 215,578.44
Upah tenaga:
- Instalator Oh 0.12 180,000 21,600.00
- Pekerja Oh 0.06 140,000 8,400.00
Jumlah Upah Tenaga 30,000.00
Jumlah Total 245,578.44
Jumlah Total + jasa 10% 270,100
16. Pasang 1 buah lampu TL 2x18 RM
Harga bahan:
- Lampu TL 2x18 watt RM bh 1 426,888 426,888.00
- Accecories ( 1 % alat ) % 1 426,888 4,268.88
Jumlah Harga Bahan 431,156.88
Upah tenaga:
- Instalator Oh 0.12 180,000 21,600.00
- Pekerja Oh 0.06 140,000 8,400.00
Jumlah Upah Tenaga 30,000.00
Jumlah Total 461,156.88
Jumlah Total + jasa 10% 507,250
17. Pasang 1 buah lampu TL 2x36 RM
Harga bahan:
- Lampu TL 2x36 watt RM bh 1 500,000 500,000.00
- Accecories ( 1 % alat ) % 1 500,000 5,000.00
Jumlah Harga Bahan 505,000.00
Upah tenaga:
- Instalator Oh 0.12 180,000 21,600.00
- Pekerja Oh 0.06 140,000 8,400.00
Jumlah Upah Tenaga 30,000.00
Jumlah Total 535,000.00
Jumlah Total + jasa 10% 588,500
18. Pasang 1 buah lampu TL 1x18 Balk
Harga bahan:
- Lampu TL 1x18 watt Balk bh 1 55,000 55,000.00
- Accecories ( 1 % alat ) % 1 55,000 550.00
Jumlah Harga Bahan 55,550.00
Upah tenaga:
- Instalator Oh 0.12 180,000 21,600.00
- Pekerja Oh 0.06 140,000 8,400.00
Jumlah Upah Tenaga 30,000.00
Jumlah Total 85,550.00
Jumlah Total + jasa 10% 94,100
19. Pasang 1 buah lampu TL 2x18 Balk
Harga bahan:
- Lampu TL 2x18 watt Balk bh 1 110,000 110,000.00
- Accecories ( 1 % alat ) % 1 110,000 1,100.00
173

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Harga Bahan 111,100.00


Upah tenaga:
- Instalator Oh 0.12 180,000 21,600.00
- Pekerja Oh 0.06 140,000 8,400.00
Jumlah Upah Tenaga 30,000.00
Jumlah Total 141,100.00
Jumlah Total + jasa 10% 155,200
20. Pasang 1 buah lampu TL 2x36 Balk
Harga bahan:
- Lampu TL 2x36 watt Balk bh 1 205,850 205,850.00
- Accecories ( 1 % alat ) % 1 205,850 2,058.50
Jumlah Harga Bahan 207,908.50
Upah tenaga:
- Instalator Oh 0.12 180,000 21,600.00
- Pekerja Oh 0.06 140,000 8,400.00
Jumlah Upah Tenaga 30,000.00
Jumlah Total 237,908.50
Jumlah Total + jasa 10% 261,650
21. Pasang 1 buah lampu baret
Harga bahan:
- Lampu Baret 11 watt bh 1 75,500 75,500.00
- Accecories ( 1 % alat ) % 1 75,500 755.00
Jumlah Harga Bahan 76,255.00
Upah tenaga:
- Instalator Oh 0.12 180,000 21,600.00
- Pekerja Oh 0.06 140,000 8,400.00
Jumlah Upah Tenaga 30,000.00
Jumlah Total 106,255.00
Jumlah Total + jasa 10% 116,850
22. Pasang 1 buah lampu pijar
Harga bahan:
- Lampu pijar 25 watt bh 1 9,290 9,290.00
- Accecories ( 1 % alat ) % 1 9,290 92.90
Jumlah Harga Bahan 9,382.90
Upah tenaga:
- Instalator Oh 0.12 180,000 21,600.00
- Pekerja Oh 0.06 140,000 8,400.00
Jumlah Upah Tenaga 30,000.00
Jumlah Total 39,382.90
Jumlah Total + jasa 10% 43,300
23. Pasang 1 buah lampu LED
Harga bahan:
- Lampu LED bh 1 346,567 346,567.00
- Accecories ( 1 % alat ) % 1 346,567 3,465.67
Jumlah Harga Bahan 350,032.67
Upah tenaga:
- Instalator Oh 0.12 180,000 21,600.00
174

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Pekerja Oh 0.06 140,000 8,400.00


Jumlah Upah Tenaga 30,000.00
Jumlah Total 380,032.67
Jumlah Total + jasa 10% 418,000
24. Pasang 1 buah saklar tunggal
Harga bahan:
- Saklar tunggal Broco bh 1 30,000 30,000.00
- Accecories ( 1 % alat ) % 1 30,000 300.00
Jumlah Harga Bahan 30,300.00
Upah tenaga:
- Instalator Oh 0.35 180,000 63,000.00
- Pekerja Oh 0.175 140,000 24,500.00
Jumlah Upah Tenaga 87,500.00
Jumlah Total 117,800.00
Jumlah Total + jasa 10% 129,550
25. Pasang 1 buah saklar ganda
Harga bahan:
- Saklar seri Broco bh 1 45,900 45,900.00
- Accecories ( 1 % alat ) % 1 45,900 459.00
Jumlah Harga Bahan 46,359.00
Upah tenaga:
- Instalator Oh 0.35 180,000 63,000.00
- Pekerja Oh 0.175 140,000 24,500.00
Jumlah Upah Tenaga 87,500.00
Jumlah Total 133,859.00
Jumlah Total + jasa 10% 147,200
26. Pasang 1 buah stop kontak
Harga bahan:
- Stop kontak Broco bh 1 45,000 45,000.00
- Accecories ( 1 % alat ) % 1 45,000 450.00
Jumlah Harga Bahan 45,450.00
Upah tenaga:
- Instalator Oh 0.35 180,000 63,000.00
- Pekerja Oh 0.175 140,000 24,500.00
Jumlah Upah Tenaga 87,500.00
Jumlah Total 132,950.00
Jumlah Total + jasa 10% 146,200
27. Pasang 1 buah Exhaust Fan
Harga bahan:
- Exhaust Fan bh 1 343,100 343,100.00
- Accecories ( 1 % alat ) % 1 343,100 3,431.00
Jumlah Harga Bahan 346,531.00
Upah tenaga:
- Instalator Oh 0.35 180,000 63,000.00
- Pekerja Oh 0.175 140,000 24,500.00
Jumlah Upah Tenaga 87,500.00
Jumlah Total 434,031.00
175

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Total + jasa 10% 477,400

28. Pekerjaan Pasangan Panel 3 Phase


- Panel listrik 3Phase 31.200 watt - 41.800 wat unit 1.00 17,500,000 17,500,000.00
- Perlengkapan Ls 0.02 250,000 6,000.00
- Pekerja Oh 0.04 140,000 5,600.00
- Instalator Oh 0.02 180,000 3,600.00
- Mandor Oh 0.00 185,000 370.00
Jumlah Upah Tenaga 17,515,570.00
Jumlah Total 17,515,570.00
Jumlah Total + jasa 10% 19,267,100

29. Pas. Penangkal petir + instalasi + acesories 1 titik


- Kabel BC 35 mm m' 195.00 100,000 19,500,000.00
- Jarum penangkap (tembaga) unit 5.00 500,000 2,500,000.00
- Klem Penyangga Kabel BC Bh 20.00 15,000 300,000.00
- Perlengkapan Ls 1.00 250,000 250,000.00
- Pekerja Oh 1.20 140,000 168,000.00
- Instalator Oh 2.10 180,000 378,000.00
- Mandor Oh 1.05 185,000 194,250.00
Jumlah Upah Tenaga 23,290,250.00
Jumlah Total 23,290,250.00
Jumlah Total + jasa 10% 25,619,250
30. Pas. Panel ATS/Genset
- Panel Genset ATS AMF 33 KVA 3phase DSE unit 1.000 25,000,000 25,000,000.00
- Perlengkapan Ls 0.024 250,000 6,000.00
- Pekerja Oh 0.040 140,000 5,600.00
- Instalator Oh 0.020 180,000 3,600.00
- Mandor Oh 0.002 185,000 370.00
Jumlah Upah Tenaga 25,015,570.00
Jumlah Total 25,015,570.00
Jumlah Total + jasa 10% 27,517,100
31. Pekerjaan Intalasi Panel + Cable Try
- Cable Try Type U 200 x 50 x 3000 nn HotDi unit 1.00 450,000 450,000.00
- Perlengkapan Ls 0.02 250,000 6,000.00
- Pekerja Oh 0.04 140,000 5,600.00
- Instalator Oh 0.02 180,000 3,600.00
- Mandor Oh 0.00 185,000 370.00
Jumlah Upah Tenaga 465,570.00
Jumlah Total 465,570.00
Jumlah Total + jasa 10% 512,100
32. Pekerjaan Vetilator cyclone
- Ventilator Cyclone 45 cm unit 1.00 1,100,000 1,100,000.00
- Perlengkapan Ls 0.02 250,000 6,000.00
- Pekerja Oh 1.20 140,000 168,000.00
- Mandor Oh 1.05 185,000 194,250.00
Jumlah Upah Tenaga 1,468,250.00
176

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Total 1,468,250.00


Jumlah Total + jasa 10% 1,615,050

S PEKERJAAN PRASARANA LINGKUNGAN - DRAINASE

1. Memasang pipa beton, dia 15-20 cm tiap m'


Harga bahan:
- Buis beton dia 20 panj. 100 cm bh 1.1 96,667 106,333.70
- Bata merah bh 16 660 10,560.00
- Semen portland kg 3.92 1,300 5,096.00
- Pasir pasang m³ 0.056 178,164 9,977.18
- Pasir urug m³ 0.024 120,000 2,880.00
Jumlah Harga Bahan 134,846.88
Upah tenaga:
- Pekerja Oh 0.14 140,000 19,600.00
- Tukang batu Oh 0.07 160,000 11,200.00
- Kepala tukang Oh 0.007 180,000 1,260.00
- Mandor Oh 0.007 185,000 1,295.00
Jumlah Upah Tenaga 33,355.00
Jumlah Total 168,201.88
Jumlah Total + jasa 10% 185,000
2. Memasang pipa beton, dia 30 cm tiap m'
Harga bahan:
- Buis beton dia 30 panj. 100 cm bh 1.1 133,829 147,211.90
- Bata merah bh 308 660 203,280.00
- Semen portland kg 10.3 1,300 13,390.00
- Pasir pasang m³ 0.061 178,164 10,868.00
- Pasir urug m³ 0.069 120,000 8,280.00
Jumlah Harga Bahan 383,029.90
- Pekerja Oh 0.38 140,000 53,200.00
- Tukang batu Oh 0.19 160,000 30,400.00
- Kepala tukang Oh 0.019 180,000 3,420.00
- Mandor Oh 0.019 185,000 3,515.00
Jumlah Upah Tenaga 90,535.00
Jumlah Total 473,564.90
Jumlah Total + jasa 10% 520,900
3. Memasang pipa beton, dia 40 cm tiap m'
Harga bahan:
- Buis beton dia 40 panj. 100 cm bh 1.1 187,500 206,250.00
- Bata merah bh 308 660 203,280.00
- Semen portland kg 10.3 1,300 13,390.00
- Pasir pasang m³ 0.061 178,164 10,868.00
- Pasir urug m³ 0.069 120,000 8,280.00
Jumlah Harga Bahan 442,068.00
Upah tenaga:
- Pekerja Oh 0.38 140,000 53,200.00
- Tukang batu Oh 0.19 160,000 30,400.00
177

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Kepala tukang Oh 0.019 180,000 3,420.00


- Mandor Oh 0.019 185,000 3,515.00
Jumlah Upah Tenaga 90,535.00
Jumlah Total 532,603.00
Jumlah Total + jasa 10% 585,850
4. Memasang pipa beton, dia 50 cm tiap m'
Harga bahan:
- Buis beton dia 50 panj. 100 cm bh 1.1 250,000 275,000.00
- Bata merah bh 308 660 203,280.00
- Semen portland kg 10.3 1,300 13,390.00
- Pasir pasang m³ 0.061 178,164 10,868.00
- Pasir urug m³ 0.069 120,000 8,280.00
Jumlah Harga Bahan 510,818.00
Upah tenaga:
- Pekerja Oh 0.38 140,000 53,200.00
- Tukang batu Oh 0.19 160,000 30,400.00
- Kepala tukang Oh 0.019 180,000 3,420.00
- Mandor Oh 0.019 185,000 3,515.00
Jumlah Upah Tenaga 90,535.00
Jumlah Total 601,353.00
Jumlah Total + jasa 10% 661,450
5. Memasang pipa beton, dia 60 cm tiap m'
Harga bahan:
- Buis beton dia 60 panj. 100 cm bh 1.1 334,690 368,159.00
- Bata merah bh 308 660 203,280.00
- Semen portland kg 10.3 1,300 13,390.00
- Pasir pasang m³ 0.061 178,164 10,868.00
- Pasir urug m³ 0.069 120,000 8,280.00
Jumlah Harga Bahan 603,977.00
Upah tenaga:
- Pekerja Oh 0.38 140,000 53,200.00
- Tukang batu Oh 0.19 160,000 30,400.00
- Kepala tukang Oh 0.019 180,000 3,420.00
- Mandor Oh 0.019 185,000 3,515.00
Jumlah Upah Tenaga 90,535.00
Jumlah Total 694,512.00
Jumlah Total + jasa 10% 763,950
6. Memasang pipa beton, dia 80 cm tiap m'
Harga bahan:
- Buis beton dia 80 panj. 50 cm bh 2.1 334,690 702,849.00
- Bata merah bh 308 660 203,280.00
- Semen portland kg 10.3 1,300 13,390.00
- Pasir pasang m³ 0.061 178,164 10,868.00
- Pasir urug m³ 0.069 120,000 8,280.00
Jumlah Harga Bahan 938,667.00
Upah tenaga:
- Pekerja Oh 0.38 140,000 53,200.00
178

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Tukang batu Oh 0.19 160,000 30,400.00


- Kepala tukang Oh 0.019 180,000 3,420.00
- Mandor Oh 0.019 185,000 3,515.00
Jumlah Upah Tenaga 90,535.00
Jumlah Total 1,029,202.00
Jumlah Total + jasa 10% 1,132,100
7. Memasang pipa beton, dia 100 cm tiap m'
Harga bahan:
- Buis beton dia 100 panj. 50 cm bh 2.1 409,013 858,927.30
- Bata merah bh 308 660 203,280.00
- Semen portland kg 10.3 1,300 13,390.00
- Pasir pasang m³ 0.061 178,164 10,868.00
- Pasir urug m³ 0.069 120,000 8,280.00
Jumlah Harga Bahan 1,094,745.30
Upah tenaga:
- Pekerja Oh 0.38 140,000 53,200.00
- Tukang batu Oh 0.19 160,000 30,400.00
- Kepala tukang Oh 0.019 180,000 3,420.00
- Mandor Oh 0.019 185,000 3,515.00
Jumlah Upah Tenaga 90,535.00
Jumlah Total 1,185,280.30
Jumlah Total + jasa 10% 1,303,800
8. Memasang 1 buah bak kontrol pas.batu bata 30 x 30 cm tinggi 35 cm
Harga bahan:
- Bata merah bh 82 660 54,120.00
- Semen portland kg 44 1,300 57,200.00
- Pasir pasang m³ 0.07 178,164 12,471.48
- Batu pecah/split 2/3 m³ 0.07 475,000 33,250.00
- Besi beton polos m³ 1.6 12,000 19,200.00
- Pasir beton m³ 0.06 178,164 10,689.84
Jumlah Harga Bahan 186,931.32
Upah tenaga:
- Pekerja Oh 3.2 140,000 448,000.00
- Tukang batu Oh 0.015 160,000 2,400.00
- Kepala tukang Oh 0.0015 180,000 270.00
- Mandor Oh 0.016 185,000 2,960.00
Jumlah Upah Tenaga 453,630.00
Jumlah Total 640,561.32
Jumlah Total + jasa 10% 704,600
9. Memasang 1 buah bak kontrol pas.batu bata 45 x 45 cm tinggi 50 cm
Harga bahan:
- Bata merah bh 140 660 92,400.00
- Semen portland kg 77 1,300 100,100.00
- Pasir pasang m³ 0.13 178,164 23,161.32
- Batu pecah/split 2/3 m³ 0.02 475,000 9,500.00
- Besi beton polos m³ 2.6 12,000 31,200.00
- Pasir beton m³ 0.09 178,164 16,034.76
179

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Harga Bahan 272,396.08


Upah tenaga:
- Pekerja Oh 1.42 140,000 198,800.00
- Tukang batu Oh 0.473 160,000 75,680.00
- Kepala tukang Oh 0.047 180,000 8,460.00
- Mandor Oh 0.071 185,000 13,135.00
Jumlah Upah Tenaga 296,075.00
Jumlah Total 568,471.08
Jumlah Total + jasa 10% 625,300
10. Memasang 1 buah bak kontrol pas.batu bata 60 x 60 cm tinggi 65 cm
Harga bahan:
- Bata merah bh 208 660 137,280.00
- Semen portland kg 114 1,300 148,200.00
- Pasir pasang m³ 0.184 178,164 32,782.18
- Batu pecah/split 2/3 m³ 0.033 475,000 15,675.00
- Besi beton polos m³ 4.85 12,000 58,200.00
- Pasir beton m³ 0.12 178,164 21,379.68
Jumlah Harga Bahan 413,516.86

Upah tenaga:
- Pekerja Oh 2.16 140,000 302,400.00
- Tukang batu Oh 0.72 160,000 115,200.00
- Kepala tukang Oh 0.072 180,000 12,960.00
- Mandor Oh 0.108 185,000 19,980.00
- Tukang gali Oh 0.1 160,000 16,000.00
Jumlah Upah Tenaga 466,540.00
Jumlah Total 880,056.86
Jumlah Total + jasa 10% 968,050
11. Membuat saluran dinding bata dalam 15-20 cm tiap 1 m'
Harga bahan:
- Bata merah bh 42 660 27,720.00
- Semen portland kg 14.79 1,300 19,220.50
- Pasir pasang m³ 0.042 178,164 7,482.89
- Pasir urug m³ 0.00828 120,000 993.60
Jumlah Harga Bahan 55,416.99
Upah tenaga:
- Pekerja Oh 0.46 140,000 64,400.00
- Tukang batu Oh 0.198 160,000 31,680.00
- Kepala tukang Oh 0.02 180,000 3,600.00
- Mandor Oh 0.027 185,000 4,995.00
Jumlah Upah Tenaga 104,675.00
Jumlah Total 160,091.99
Jumlah Total + jasa 10% 176,100
12. Membuat saluran air buis beton ½ Ø 30 cm dinding bata dalam 30-45 cm tiap 1 m'
Harga bahan:
- Bata merah bh 77 660 50,820.00
- Semen portland kg 23.11 1,300 30,046.90
180

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Pasir pasang m³ 0.066 178,164 11,758.82


- Pasir urug m³ 0.03384 120,000 4,060.80
- Buis beton 1/2 dia 20 panj. 100 cm bh 1.1 48,334 53,166.85
Jumlah Harga Bahan 149,853.37
- Pekerja Oh 0.771 140,000 107,940.00
- Tukang batu Oh 0.272 160,000 43,520.00
- Kepala tukang Oh 0.028 180,000 5,040.00
- Mandor Oh 0.048 185,000 8,880.00
Jumlah Upah Tenaga 165,380.00
Jumlah Total 315,233.37
Jumlah Total + jasa 10% 346,750
13. Membuat saluran air dari batu kali lebar bawah 30 cm tinggi 60 cm tiap 1 m'
Harga bahan:
- Batu belah 15/20 m³ 0.473 385,000 182,105.00
- Semen portland kg 94.42 1,300 122,746.00
- Pasir pasang m³ 0.22675 178,164 40,398.69
Jumlah Harga Bahan 345,249.69
Harga pemakaian alat:
- TAMPER / HAND COMPACTOR jam 0.04632 56,997 2,640.09
Jumlah Harga Alat 2,640.09
Upah tenaga:
- Pekerja Oh 1.24112 140,000 173,756.80
- Tukang batu Oh 0.398 160,000 63,680.00
- Kepala tukang Oh 0.0398 180,000 7,164.00
- Mandor Oh 0.0826 185,000 15,281.00
Jumlah Upah Tenaga 259,881.80
Jumlah Total 607,771.58
Jumlah Total + jasa 10% 668,500
14. Membuat saluran air dari batu kali lebar bawah 60 cm tinggi 80 cm tiap 1 m'
Harga bahan:
- Batu belah 15/20 m³ 0.704 385,000 271,040.00
- Semen portland kg 136.84 1,300 177,892.00
- Pasir pasang m³ 0.3286 178,164 58,544.69
- Galian tanah m³ 1.12 7,925 8,876.00
Jumlah Harga Bahan 516,352.69
Harga pemakaian alat:
- TAMPER / HAND COMPACTOR jam 0.06948 56,997 3,960.13
Jumlah Harga Alat 3,960.13
Upah tenaga:
- Pekerja Oh 1.9246 140,000 269,444.00
- Tukang batu Oh 0.524 160,000 83,840.00
- Kepala tukang Oh 0.0524 180,000 9,432.00
- Mandor Oh 0.13475 185,000 24,928.75
Jumlah Upah Tenaga 387,644.75
Jumlah Total 907,957.57
Jumlah Total + jasa 10% 998,750
15. Membuat saluran air dari batu kali lebar bawah 80 cm tinggi 100 cm tiap 1 m'
181

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Harga bahan:
- Batu belah 15/20 m³ 1.012 385,000 389,620.00
- Semen portland kg 193.4 1,300 251,420.00
- Pasir pasang m³ 0.4644 178,164 82,739.36
Jumlah Harga Bahan 723,779.36
Harga pemakaian alat:
- TAMPER / HAND COMPACTOR jam 0.09264 56,997 5,280.18
Jumlah Harga Alat 5,280.18
Upah tenaga:
- Pekerja Oh 2.98348 140,000 417,687.20
- Tukang batu Oh 0.692 160,000 110,720.00
- Kepala tukang Oh 0.0692 180,000 12,456.00
- Mandor Oh 0.21855 185,000 40,431.75
Jumlah Upah Tenaga 581,294.95
Jumlah Total 1,310,354.49
Jumlah Total + jasa 10% 1,441,350
16. Membuat saluran air dari batu kali lebar bawah 100 cm tinggi 120 cm tiap 1 m'
Harga bahan:
- Batu belah 15/20 m³ 1.287 385,000 495,495.00
- Semen portland kg 244.98 1,300 318,474.00
- Pasir pasang m³ 0.58825 178,164 104,804.97
Jumlah Harga Bahan 918,773.97
Harga pemakaian alat:
- TAMPER / HAND COMPACTOR jam 0.10422 56,997 5,940.20
Jumlah Harga Alat 5,940.20
Upah tenaga:
- Pekerja Oh 4.1048 140,000 574,672.00
- Tukang batu Oh 0.862 160,000 137,920.00
- Kepala tukang Oh 0.0862 180,000 15,516.00
- Mandor Oh 0.30945 185,000 57,248.25
Jumlah Upah Tenaga 785,356.25
Jumlah Total 1,710,070.42
Jumlah Total + jasa 10% 1,881,050
17. Membuat saluran air dari U-dit 200.200.120 tiap 1 m'
Harga bahan:
- U- dit 200x200x120 m³ 1.1 6,258,000 6,883,800.00
- Beton alas kerja ls 0.041 6,883,800 282,235.80
Jumlah Harga Bahan 7,166,035.80
Harga pemakaian alat:
- Sewa Crawler crane jam 0.10422 350,000 36,477.00
Jumlah Harga Alat 36,477.00
Upah tenaga:
- Pekerja Oh 4.1048 140,000 574,672.00
- Tukang batu Oh 0.862 160,000 137,920.00
- Kepala tukang Oh 0.0862 180,000 15,516.00
- Mandor Oh 0.30945 185,000 57,248.25
Jumlah Upah Tenaga 785,356.25
182

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Total 7,987,869.05


Jumlah Total + jasa 10% 8,786,650

T PEKERJAAN PRASARANA LINGKUNGAN - PAGAR

1. Pasang pagar beton pracetak tinggi 1,6 m tiap 1 m'


Harga bahan:
- Panel beton pracetak 50x400x2130 Lbr 1.778 125,000 222,250.00
- Kolom beton pracetak 160x200x2750 btg 0.445 190,450 84,750.25
- Pasir beton m³ 0.0103 178,164 1,835.09
- Batu pecah/split 2/3 m³ 0.0171 475,000 8,122.50
- Semen portland kg 4.89 1,300 6,357.00
Jumlah Harga Bahan 323,314.84
Upah tenaga:
- Tukang batu Oh 0.125 160,000 20,000.00
- Pekerja Oh 0.375 140,000 52,500.00
- Kepala tukang Oh 0.012 180,000 2,160.00
- Mandor Oh 0.019 185,000 3,515.00
Jumlah Upah Tenaga 78,175.00
Jumlah Total 401,489.84
Jumlah Total + jasa 10% 441,600
2. Pasang pagar beton pracetak tinggi 2 m tiap 1 m'
Harga bahan:
- Panel beton pracetak 50x400x2130 Lbr 2.223 125,000 277,875.00
- Kolom beton pracetak 160x200x2750 btg 0.445 190,450 84,750.25
- Pasir beton m³ 0.0103 178,164 1,835.09
- Batu pecah/split 2/3 m³ 0.0171 475,000 8,122.50
- Semen portland kg 4.89 1,300 6,357.00
Jumlah Harga Bahan 378,939.84
- Tukang batu Oh 0.125 160,000 20,000.00
- Pekerja Oh 0.375 140,000 52,500.00
- Kepala tukang Oh 0.012 180,000 2,160.00
- Mandor Oh 0.019 185,000 3,515.00
Jumlah Upah Tenaga 78,175.00
Jumlah Total 457,114.84
Jumlah Total + jasa 10% 502,800
3. Membuat pagar dinding tinggi 2 m bata merah + plesteran + cat tembok tiap 1 m'
Harga bahan:
- Batu belah 15/20 m³ 0.36 385,000 138,600.00
- Batu pecah/split 2/3 m³ 0.06 475,000 28,500.00
- Bata merah bh 115.5 660 76,230.00
- Semen portland kg 105.47 1,300 137,111.00
- Pasir urug m³ 0.028 120,000 3,360.00
- Pasir pasang m³ 0.265 178,164 47,213.46
- Pasir beton m³ 0.038 178,164 6,770.23
- Kayu Terentang balok m³ 0.014 2,826,516 39,571.22
- Paku biasa 2"-5" kg 0.167 19,286 3,220.76
183

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Minyak Bekisting lt 0.04 8,820 352.80


- Besi beton polos kg 14.7 12,000 176,400.00
- Kawat beton kg 0.868 20,000 17,360.00
- Plamir tembok kg 0.4 13,289 5,315.60
- Cat tembok Catylac (cat dasar) kg 0.4 28,000 11,200.00
- Cat tembok Catylac (cat penutup) kg 1.04 28,000 29,120.00
Jumlah Harga Bahan 720,325.08
Harga pemakaian alat:
- TAMPER / HAND COMPACTOR jam 0.03474 56,997 1,980.07
Jumlah Harga Alat 1,980.07
Upah tenaga:
- Pekerja Oh 2.661 140,000 372,540.00
- Tukang kayu Oh 0.186 160,000 29,760.00
- Tukang besi Oh 0.112 160,000 17,920.00
- Tukang batu Oh 1.029 160,000 164,640.00
- Tukang cat Oh 0.252 160,000 40,320.00
- Kepala tukang Oh 0.158 180,000 28,440.00
- Mandor Oh 0.152 185,000 28,120.00
Jumlah Upah Tenaga 681,740.00
Jumlah Total 1,404,045.14
Jumlah Total + jasa 10% 1,544,400
4. Membuat pagar dinding tinggi 3 m bata merah + plesteran + cat tembok tiap 1 m'
Harga bahan:
- Batu belah 15/20 m³ 0.36 385,000 138,600.00
- Batu pecah/split 2/3 m³ 0.065 475,000 30,875.00
- Bata merah bh 185.5 660 122,430.00
- Semen portland kg 135.28 1,300 175,864.00
- Pasir urug m³ 0.028 120,000 3,360.00
- Pasir pasang m³ 0.343 178,164 61,110.25
- Pasir beton m³ 0.042 178,164 7,482.89
- Kayu Terentang balok m³ 0.015 2,826,516 42,397.74
- Paku biasa 2"-5" kg 0.173 19,286 3,336.48
- Minyak Bekisting lt 0.04 8,820 352.80
- Besi beton polos kg 16.56 12,000 198,720.00
- Kawat beton kg 1.147 20,000 22,940.00
- Plamir tembok kg 0.6 13,289 7,973.40
- Cat tembok Catylac (cat dasar) kg 0.6 28,000 16,800.00
- Cat tembok Catylac (cat penutup) kg 1.56 28,000 43,680.00
Jumlah Harga Bahan 875,922.56
Harga pemakaian alat:
- TAMPER / HAND COMPACTOR jam 0.03474 56,997 1,980.07
Jumlah Harga Alat 1,980.07
Upah tenaga:
- Pekerja Oh 3.458 140,000 484,120.00
- Tukang kayu Oh 0.199 160,000 31,840.00
- Tukang besi Oh 0.1243 160,000 19,888.00
- Tukang batu Oh 1.442 160,000 230,720.00
184

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Tukang cat Oh 0.378 160,000 60,480.00


- Kepala tukang Oh 0.215 180,000 38,700.00
- Mandor Oh 0.194 185,000 35,890.00
Jumlah Upah Tenaga 901,638.00
Jumlah Total 1,779,540.62
Jumlah Total + jasa 10% 1,957,450
5. Membuat pagar dinding tinggi 2 m bata hollow ekspos + kolom/ringbalk diplester & dicat tiap 1 m'
Harga bahan:
- Batu belah 15/20 m³ 0.36 385,000 138,600.00
- Batu pecah/split 2/3 m³ 0.06 475,000 28,500.00
- Hollow block HB. 10 bh 20.625 2,600 53,625.00
- Semen portland kg 77.46 1,300 100,698.00
- Pasir urug m³ 0.028 120,000 3,360.00
- Pasir pasang m³ 0.195 178,164 34,741.98
- Pasir beton m³ 0.038 178,164 6,770.23
- Kayu Terentang balok m³ 0.014 2,826,516 39,571.22
- Paku biasa 2"-5" kg 0.167 19,286 3,220.76
- Minyak Bekisting lt 0.04 8,820 352.80
- Besi beton polos kg 17.92 12,000 215,040.00
- Kawat beton kg 0.868 20,000 17,360.00
- Plamir tembok kg 0.143 13,289 1,900.33
- Cat tembok Catylac (cat dasar) kg 0.143 28,000 4,004.00
- Cat tembok Catylac (cat penutup) kg 0.371 28,000 10,388.00
Jumlah Harga Bahan 658,132.33
Harga pemakaian alat:
- TAMPER / HAND COMPACTOR jam 0.03474 56,997 1,980.07
Jumlah Harga Alat 1,980.07
Upah tenaga:
- Pekerja Oh 2.096 140,000 293,440.00
- Tukang kayu Oh 0.186 160,000 29,760.00
- Tukang besi Oh 0.1119 160,000 17,904.00
- Tukang batu Oh 0.643 160,000 102,880.00
- Tukang cat Oh 0.09 160,000 14,400.00
- Kepala tukang Oh 0.104 180,000 18,720.00
- Mandor Oh 0.12 185,000 22,200.00
Jumlah Upah Tenaga 499,304.00
Jumlah Total 1,159,416.39
Jumlah Total + jasa 10% 1,275,350
6. Membuat pagar dinding tinggi 1,5 m bata hollow ekspos + kolom/ringbalk diplester & dicat tiap 1 m'
Harga bahan:
- Batu belah 15/20 m³ 0.174 385,000 66,990.00
- Batu pecah/split 2/3 m³ 0.053 475,000 25,175.00
- Hollow block HB. 10 bh 14.375 2,600 37,375.00
- Semen portland kg 61.27 1,300 79,651.00
- Pasir pasang m³ 0.143 178,164 25,477.45
- Pasir beton m³ 0.034 178,164 6,057.58
- Kayu Terentang balok m³ 0.013 2,826,516 36,744.71
185

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Paku biasa 2"-5" kg 0.16 19,286 3,085.76


- Minyak Bekisting lt 0.04 8,820 352.80
- Besi beton polos kg 14.8725 12,000 178,470.00
- Kawat beton kg 0.5575 20,000 11,150.00
- Plamir tembok kg 0.134 13,289 1,780.73
- Cat tembok Catylac (cat dasar) kg 0.134 28,000 3,752.00
- Cat tembok Catylac (cat penutup) kg 0.3484 28,000 9,755.20
Jumlah Harga Bahan 485,817.22

Harga pemakaian alat:


- TAMPER / HAND COMPACTOR jam 0.031845 56,997 1,815.06
Jumlah Harga Alat 1,815.06
Upah tenaga:
- Pekerja Oh 1.535 140,000 214,900.00
- Tukang kayu Oh 0.173 160,000 27,680.00
- Tukang besi Oh 0.0981 160,000 15,696.00
- Tukang batu Oh 0.49 160,000 78,400.00
- Tukang cat Oh 0.08442 160,000 13,507.20
- Kepala tukang Oh 0.085 180,000 15,300.00
- Mandor Oh 0.085 185,000 15,725.00
Jumlah Upah Tenaga 381,208.20
Jumlah Total 868,840.48
Jumlah Total + jasa 10% 955,700
7. Membuat pagar BRC 1,2 m tinggi jadi 1,5 m (pondasi batu kali + sloof 15/20 + ½ bata 30 cm + plester + cat) tiap 1 m'
Harga bahan:
- Batu belah 15/20 m³ 0.274 385,000 105,490.00
- Batu pecah/split 2/3 m³ 0.022 475,000 10,450.00
- Bata merah bh 21 660 13,860.00
- Semen portland kg 43.76 1,300 56,888.00
- Pasir urug m³ 0.025 120,000 3,000.00
- Pasir pasang m³ 0.12 178,164 21,379.68
- Pasir beton m³ 0.0146 178,164 2,601.19
- Kayu Terentang balok m³ 0.006 2,826,516 16,959.10
- Paku biasa 2"-5" kg 0.12 19,286 2,314.32
- Minyak Bekisting lt 0.04 8,820 352.80
- Besi beton polos kg 4.44 12,000 53,280.00
- Kawat beton kg 0.064 20,000 1,280.00
- Pagar BRC tinggi 1,2 m' m' 1 381,100 381,100.00
- Tiang pagar BRC tinggi 1,2 m' bh 0.555 114,550 63,575.25
- Plamir tembok kg 0.115 13,289 1,528.24
- Cat tembok Catylac (cat dasar) kg 0.115 28,000 3,220.00
- Cat tembok Catylac (cat penutup) kg 0.299 28,000 8,372.00
Jumlah Harga Bahan 745,650.58
Upah tenaga:
- Pekerja Oh 1.188 140,000 166,320.00
- Tukang kayu Oh 0.104 160,000 16,640.00
- Tukang besi Oh 0.072 160,000 11,520.00
186

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Tukang batu Oh 0.341 160,000 54,560.00


- Tukang cat Oh 0.07245 160,000 11,592.00
- Kepala tukang Oh 0.059 180,000 10,620.00
- Mandor Oh 0.071 185,000 13,135.00
Jumlah Upah Tenaga 284,387.00
Jumlah Total 1,030,037.58
Jumlah Total + jasa 10% 1,133,000
8. Membuat pagar BRC 0,9 m tinggi jadi 1,2 m (pondasi batu kali + sloof 15/20 + ½ bata 30 cm + plester + cat) tiap 1 m'
Harga bahan:
- Batu belah 15/20 m³ 0.274 385,000 105,490.00
- Batu pecah/split 2/3 m³ 0.022 475,000 10,450.00
- Bata merah bh 21 660 13,860.00
- Semen portland kg 43.76 1,300 56,888.00
- Pasir urug m³ 0.025 120,000 3,000.00
- Pasir pasang m³ 0.12 178,164 21,379.68
- Pasir beton m³ 0.0146 178,164 2,601.19
- Kayu Terentang balok m³ 0.006 2,826,516 16,959.10
- Paku biasa 2"-5" kg 0.12 19,286 2,314.32
- Minyak Bekisting lt 0.04 8,820 352.80
- Besi beton polos kg 4.44 12,000 53,280.00
- Kawat beton kg 0.064 20,000 1,280.00
- Pagar BRC tinggi 0,9 m' m' 1 109,500 109,500.00
- Tiang pagar BRC tinggi 0,9 m' bh 0.555 89,950 49,922.25
- Plamir tembok kg 0.115 13,289 1,528.24
- Cat tembok Catylac (cat dasar) kg 0.115 28,000 3,220.00
- Cat tembok Catylac (cat penutup) kg 0.299 28,000 8,372.00
Jumlah Harga Bahan 460,397.58
Upah tenaga:
- Pekerja Oh 1.188 140,000 166,320.00
- Tukang kayu Oh 0.104 160,000 16,640.00
- Tukang besi Oh 0.072 160,000 11,520.00
- Tukang batu Oh 0.341 160,000 54,560.00
- Tukang cat Oh 0.07245 160,000 11,592.00
- Kepala tukang Oh 0.059 180,000 10,620.00
- Mandor Oh 0.071 185,000 13,135.00
Jumlah Upah Tenaga 284,387.00
Jumlah Total 744,784.58
Jumlah Total + jasa 10% 819,250

U PEKERJAAN PRASARANA LINGKUNGAN - JALAN, LAPANGAN PARKIR, LAPANGAN UPACARA/APEL

1. Galian dengan excavator (skala besar) tiap 1m³

Asumsi:
Faktor pengembangan bahan Fk 1.2
Jarak lokasi ke pembuangan L 40 Km
187

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jam kerja efektif Tk 7 jam

EXCAVATOR 150 HP Kobelco SK200


Kapasitas bucket v 0.9 m³
Faktor bucket Fb 0.9
Efisiensi alat Fa 0.83
Waktu siklus Ts1
- Menggali / memuat T1 0.5 menit
- Lain-lain T2 0.5 menit
Ts1 1 menit

Kap. prod / jam = v x Fb x Fa x 60 Q1 33.615 m³/jam


Ts1 x Fk

Koefisien Alat / m³ = 1 : Q1 Qt1 0.0298 jam

DUMP TRUCK 3-4 M³ / 6 TON


Kapasitas bak V 6 m³
Efisiensi alat Fa 0.83
Kecepatan rata-rata bermuatan v1 45 Km/jam
Kecepatan rata-rata kosong v2 60 Km/jam
Waktu siklus Ts2
- Waktu tempuh isi = (L : v1) x 60 T1 53.333333 menit
- Waktu tempuh kosong = (L : v2) x 60 T2 40 menit
- Memuat = (V : Q1) x 60 T3 10.709505 menit
- Lain-lain T2 1 menit
Ts2 105.04284 menit

Kap. prod / jam = v x Fa x 60 Q2 2.3704615 m³/jam


Ts2 x Fk

Koefisien Alat / m³ = 1 : Q2 Qt2 0.4219 jam

TENAGA
Produksi menentukan: EXCAVATOR Q1 33.615 m³/jam
Produksi galian / hari = Tk x Q1 Qt 235.305 m³/hari
Kebutuhan tenaga:
- Pekerja P 2 orang
- Mandor M 1 orang
Koefisien tenaga / m³
- Pekerja = P : Qt 0.0085 Oh
- Mandor = M : Qt 0.0043 Oh

Harga pemakaian alat:


- EXCAVATOR 150 HP Kobelco SK200 jam 0.0298 508,480 15,152.72
- DUMP TRUCK 3-4 M³ / 6 TON jam 0.4219 297,961 125,709.78
188

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Harga Peralatan 140,862.50


Upah tenaga:
- Pekerja Oh 0.0085 140,000 1,190.00
- Mandor Oh 0.0043 185,000 795.50
Jumlah Upah Tenaga 1,985.50
Jumlah Total 142,848.00
Jumlah Total + jasa 10% 157,100
2. Galian dengan tenaga manusia tiap 1m³
Harga pemakaian alat:
- DUMP TRUCK 3-4 M³ / 6 TON jam 0.0625 297,961 18,622.57
Jumlah Harga Peralatan 18,622.57
Upah tenaga:
- Pekerja Oh 1.125 140,000 157,500.00
- Mandor Oh 0.03125 185,000 5,781.25
Jumlah Upah Tenaga 163,281.25
Jumlah Total 181,903.82
Jumlah Total + jasa 10% 200,050

3. Urugan tanah merah dipadatkan alat berat tiap 1m³

VIBRATING ROLLER 6-8 TON


Kecepatan alat v 4 km/jam
Efisiensi alat Fa 0.83
Lebar pemadatan b 1.2 m'
Banyak lintasan (pass) n 6 lintasan 3 kali bolak-balik
Tebal lapis hamparan t 0.2 m'

Kap. prod / jam = (v x 1000) x b x t x Fa Qj 132.8 m³/jam


n

Koefisien Alat / m³ = 1 : Qj Qt 0.0076 jam

WATER TANK TRUCK 3000-4500 L


Volume tangki air V 4 m³
Efisiensi alat Fa 0.83
Kebutuhan air / m³ material padat Wc 0.07 m³
Pengisian tangki / jam n 3 kali

Kap. prod / jam = V x n x Fa Qj 142.28571 m³/jam


Wc

Koefisien Alat / m³ = 1 : Qj Qt 0.0071 jam

Harga bahan:
- Tanah merah m³ 1.2 95,000 114,000.00
Jumlah Harga Bahan 114,000.00
189

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Harga pemakaian alat:


- VIBRATING ROLLER 6-8 TON jam 0.0076 273,161 2,076.02
- WATER TANK TRUCK 3000-4500 L jam 0.0071 273,553 1,942.23
Jumlah Harga Peralatan 4,018.25
Upah tenaga:
- Pekerja Oh 0.25 140,000 35,000.00
- Mandor Oh 0.025 185,000 4,625.00
Jumlah Upah Tenaga 39,625.00
Jumlah Total 157,643.25
Jumlah Total + jasa 10% 173,400

4. Penyiapan badan jalan / tanah dasar (Subgrade) tiap 1m²

VIBRATING ROLLER 6-8 TON


Kecepatan alat v 2.5 km/jam
Efisiensi alat Fa 0.83
Lebar pemadatan b 1.2 m'
Banyak lintasan (pass) n 8 lintasan 4 kali bolak-balik

Kap. prod / jam = (v x 1000) x b x Fa Qj 311.25 m²/jam


n

Koefisien Alat / m² = 1 : Qj Qt 0.0033 jam

WATER TANK TRUCK 3000-4500 L


Volume tangki air V 4 m³
Efisiensi alat Fa 0.83
Kebutuhan air / m² tanah Wc 0.07 m³
Pengisian tangki / jam n 3 kali

Kap. prod / jam = V x n x Fa Qj 142.28571 m²/jam


Wc

Koefisien Alat / m² = 1 : Qj Qt 0.0071 jam

Harga pemakaian alat:


- VIBRATING ROLLER 6-8 TON jam 0.0033 273,161 901.43
- WATER TANK TRUCK 3000-4500 L jam 0.0071 273,553 1,942.23
Jumlah Harga Peralatan 2,843.65
Upah tenaga:
- Pekerja Oh 0.025 140,000 3,500.00
- Mandor Oh 0.0004 185,000 74.00
Jumlah Upah Tenaga 3,574.00
Jumlah Total 6,417.65
Jumlah Total + jasa 10% 7,050

5. Urugan sirtu (agregat kelas C) dipadatkan tiap 1m³


190

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

VIBRATING ROLLER 6-8 TON


Kecepatan alat v 2.5 km/jam
Efisiensi alat Fa 0.83
Lebar pemadatan b 1.2 m'
Banyak lintasan (pass) n 8 lintasan 4 kali bolak-balik
Tebal lapis hamparan t 0.15 m'

Kap. prod / jam = (v x 1000) x b x t x Fa Qj 46.6875 m³/jam


n

Koefisien Alat / m³ = 1 : Qj Qt 0.0215 jam

WATER TANK TRUCK 3000-4500 L


Volume tangki air V 4 m³
Efisiensi alat Fa 0.83
Kebutuhan air / m³ material padat Wc 0.07 m³
Pengisian tangki / jam n 3 kali

Kap. prod / jam = V x n x Fa Qj 142.28571 m³/jam


Wc

Koefisien Alat / m³ = 1 : Qj Qt 0.0071 jam

Harga bahan:
- Sirtu m³ 1.2 416,539 499,846.80
Jumlah Harga Bahan 499,846.80

Harga pemakaian alat:


- VIBRATING ROLLER 6-8 TON jam 0.0215 273,161 5,872.95
- WATER TANK TRUCK 3000-4500 L jam 0.0071 273,553 1,942.23
Jumlah Harga Peralatan 7,815.18
Upah tenaga:
- Pekerja Oh 0.25 140,000 35,000.00
- Mandor Oh 0.025 185,000 4,625.00
Jumlah Upah Tenaga 39,625.00
Jumlah Total 547,286.98
Jumlah Total + jasa 10% 602,000

6. Lapis Pondasi Bawah (LPB / Subbase Course) Kelas C Sirtu tebal 10 cm tiap 1m²

VIBRATING ROLLER 6-8 TON


Kecepatan alat v 2.5 km/jam
Efisiensi alat Fa 0.83
Lebar pemadatan b 1.2 m'
Banyak lintasan (pass) n 8 lintasan 4 kali bolak-balik
191

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Kap. prod / jam = (v x 1000) x b x Fa Qj 311.25 m²/jam


n

Koefisien Alat / m² = 1 : Qj Qt 0.0033 jam

WATER TANK TRUCK 3000-4500 L


Volume tangki air V 4 m³
Efisiensi alat Fa 0.83
Kebutuhan air / m² material padat Wc 0.007 m³
Pengisian tangki / jam n 1 kali

Kap. prod / jam = V x n x Fa Qj 474.28571 m³/jam


Wc

Koefisien Alat / m³ = 1 : Qj Qt 0.0022 jam

Harga bahan:
- Sirtu m³ 0.12 416,539 49,984.68
Jumlah Harga Bahan 49,984.68
Harga pemakaian alat:
- VIBRATING ROLLER 6-8 TON jam 0.0033 273,161 901.43
- WATER TANK TRUCK 3000-4500 L jam 0.0022 273,553 601.82
Jumlah Harga Peralatan 1,503.25
Upah tenaga:
- Pekerja Oh 0.025 140,000 3,500.00
- Mandor Oh 0.0025 185,000 462.50
Jumlah Upah Tenaga 3,962.50
Jumlah Total 55,450.43
Jumlah Total + jasa 10% 60,950

7. Lapis Pondasi Jalan Tanpa Penutup Aspal jenis Waterbound Macadam tiap 1m³

THREE WHEEL ROLLER 8-10 TON


Kecepatan alat v 3 km/jam
Efisiensi alat Fa 0.83
Lebar pemadatan b 1.2 m'
Banyak lintasan (pass) n 8 lintasan 4 kali bolak-balik
Tebal lapis hamparan t 0.1 m' 6 lintasan u/ agregat kasar;
2 lintasan u/ agregat halus.
Kap. prod / jam = (v x 1000) x b x t x Fa Qj 37.35 m³/jam
n

Koefisien Alat / m³ = 1 : Qj Qt 0.0268 jam

WATER TANK TRUCK 3000-4500 L


192

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Volume tangki air V 4 m³


Efisiensi alat Fa 0.83
Kebutuhan air / m² material padat Wc 0.07 m³
Pengisian tangki / jam n 1 kali

Kap. prod / jam = V x n x Fa Qj 47.428571 m³/jam


Wc

Koefisien Alat / m³ = 1 : Qj Qt 0.0211 jam

Harga bahan:
- Batu pecah 5/7 m³ 0.935 475,000 444,125.00
- Pasir urug m³ 0.165 120,000 19,800.00
Jumlah Harga Bahan 463,925.00
Harga pemakaian alat:
- THREE WHEEL ROLLER 8-10 TON jam 0.0268 203,528 5,454.55
- WATER TANK TRUCK 3000-4500 L jam 0.0211 273,553 5,771.96
Jumlah Harga Peralatan 11,226.52
Upah tenaga:
- Pekerja Oh 1 140,000 140,000.00
- Mandor Oh 0.034 185,000 6,290.00
Jumlah Upah Tenaga 146,290.00
Jumlah Total 621,441.52
Jumlah Total + jasa 10% 683,550

8. Lapis Pondasi Atas (LPA / Base Course) Agregat Kelas A tiap 1m³

THREE WHEEL ROLLER 8-10 TON


Kecepatan alat v 3 km/jam
Efisiensi alat Fa 0.83
Lebar pemadatan b 1.2 m'
Banyak lintasan (pass) n 12 lintasan 6 kali bolak-balik
Tebal lapis hamparan t 0.15 m'

Kap. prod / jam = (v x 1000) x b x t x Fa Qj 37.35 m³/jam


n

Koefisien Alat / m³ = 1 : Qj Qt 0.0268 jam

WATER TANK TRUCK 3000-4500 L


Volume tangki air V 4 m³
Efisiensi alat Fa 0.83
Kebutuhan air / m² material padat Wc 0.07 m³
Pengisian tangki / jam n 1 kali

Kap. prod / jam = V x n x Fa Qj 47.428571 m³/jam


193

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Wc

Koefisien Alat / m³ = 1 : Qj Qt 0.0211 jam

Harga bahan:
- Batu pecah/split 2/3 m³ 0.768 475,000 364,800.00
- Pasir urug m³ 0.432 120,000 51,840.00
Jumlah Harga Bahan 416,640.00
Harga pemakaian alat:
- THREE WHEEL ROLLER 8-10 TON jam 0.0268 203,528 5,454.55
- WATER TANK TRUCK 3000-4500 L jam 0.0211 273,553 5,771.96
Jumlah Harga Peralatan 11,226.52
Upah tenaga:
- Pekerja Oh 1 140,000 140,000.00
- Mandor Oh 0.034 185,000 6,290.00
Jumlah Upah Tenaga 146,290.00
Jumlah Total 574,156.52
Jumlah Total + jasa 10% 631,550
9. Lapis Resap Ikat (Prime Coat) tiap 1 Liter
Harga bahan:
- Aspal Polimer Lokal kg 0.6417 23,500 15,079.95
- Minyak Tanah Ltr 0.4889 17,758 8,681.89
Jumlah Harga Bahan 23,761.84
Harga pemakaian alat:
- ASPHALT SPRAYER jam 0.003 101,938 305.81
- AIR COMPRESSOR jam 0.0031 224,250 695.17
- DUMP TRUCK 3-4 M³ / 6 TON jam 0.003 297,961 893.88
Jumlah Harga Peralatan 1,894.87
Upah tenaga:
- Pekerja Oh 0.0043 140,000 602.00
- Mandor Oh 0.0009 185,000 166.50
Jumlah Upah Tenaga 768.50
Jumlah Total 26,425.21
Jumlah Total + jasa 10% 29,050
10. Lapis Perekat (Tack Coat) tiap 1 Liter
Harga bahan:
- Aspal Polimer Lokal kg 0.888 23,500 20,868.00
- Minyak Tanah Ltr 0.253 17,758 4,492.77
Jumlah Harga Bahan 25,360.77
Harga pemakaian alat:
- ASPHALT SPRAYER jam 0.003 101,938 305.81
- AIR COMPRESSOR jam 0.0063 224,250 1,412.77
- DUMP TRUCK 3-4 M³ / 6 TON jam 0.003 297,961 893.88
Jumlah Harga Peralatan 2,612.47

Upah tenaga:
- Pekerja Oh 0.0043 140,000 602.00
194

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Mandor Oh 0.0009 185,000 166.50


Jumlah Upah Tenaga 768.50
Jumlah Total 28,741.74
Jumlah Total + jasa 10% 31,600
( untuk per M2 dibutuhkan 2 Liter lapis perekat ) 63,200
11. Aspal untuk Pelaburan tiap 1 Liter
Harga bahan:
- Aspal Polimer Lokal kg 1.1 23,500 25,850.00
- Minyak Tanah Ltr 0.052 17,758 923.42
Jumlah Harga Bahan 26,773.42
Harga pemakaian alat:
- ASPHALT SPRAYER jam 0.0015 101,938 152.91
- AIR COMPRESSOR jam 0.0031 224,250 695.17
- DUMP TRUCK 3-4 M³ / 6 TON jam 0.0015 297,961 446.94
Jumlah Harga Peralatan 1,295.02
Upah tenaga:
- Pekerja Oh 0.0022 140,000 308.00
- Mandor Oh 0.00022 185,000 40.70
Jumlah Upah Tenaga 348.70
Jumlah Total 28,417.14
Jumlah Total + jasa 10% 31,250

12. Lapisan Penetrasi (LAPEN) / Lapisan Permukaan (Surface Course) Macadam tebal 5 cm tiap 1m²

THREE WHEEL ROLLER 8-10 TON


Kecepatan alat v 3 km/jam 6 lintasan u/ batu 3/5 & 2/3
Efisiensi alat Fa 0.83 2 lintasan u/ batu 1/2; 2 lintasan u/ pasir
Lebar pemadatan b 1.2 m'
Banyak lintasan (pass) n 8 lintasan 4 kali bolak-balik

Kap. prod / jam = (v x 1000) x b x Fa Qj 373.5 m²/jam


n

Koefisien Alat / m² = 1 : Qj Qt 0.0027 jam

ASPHALT SPRAYER
Berat jenis bahan aspal Da 1.01 ton/m³
Pemakaian aspal / m² As 4.8 kg/m²
Kapasitas alat V 800 Liter
Efisiensi alat Fa 0.83
Waktu siklus (termasuk proses pemanasan Ts 2 Jam

Kap. prod / jam = V x Fa x Da Qj 69.858333 m²/jam


Ts x As

Koefisien Alat / m² = 1 : Qj Qt 0.0144 jam


195

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Harga bahan:
- Batu pecah/split 3/5 m³ 0.04 475,000 19,000.00
- Batu pecah/split 2/3 m³ 0.022 475,000 10,450.00
- Batu pecah/split 1/2 m³ 0.011 475,000 5,225.00
- Abu batu m³ 0.0025 607,639 1,519.10
- Aspal Polimer Lokal kg 4.8 23,500 112,800.00
- Minyak tanah Ltr 0.322 17,758 5,718.08
Jumlah Harga Bahan 154,712.17
Harga pemakaian alat:
- THREE WHEEL ROLLER 8-10 TON jam 0.0027 203,528 549.53
- ASPHALT SPRAYER jam 0.0144 101,938 1,467.90
- DUMP TRUCK 3-4 M³ / 6 TON jam 0.0108 297,961 3,217.98
Jumlah Harga Peralatan 5,235.41
Upah tenaga:
- Pekerja Oh 0.1415 140,000 19,810.00
- Tukang aspal Oh 0.0043 180,000 774.00
- Mandor Oh 0.0043 185,000 795.50
Jumlah Upah Tenaga 21,379.50
Jumlah Total 181,327.08
Jumlah Total + jasa 10% 199,450
13. Lapisan Tipis Aspal Beton (LATASTON / HRS-Hot Rolled Sheet) tebal 3 cm tiap 1m²

Jam kerja efektif rata-rata Tk 7 jam


Jarak lokasi pengolahan AMP ke proyek L 20 km
Tebal Lapis jalan padat t 0.03 m
Faktor kehilangan material : - Agregat Fh1 1.1
- Aspal Fh2 1.05
Komposisi campuran AC : - Coarse Agrega CA 29.5 % 20-40%
- Fine Agregat FA 56.5 % 46-67%
- Fraksi Filler FF 6.49 % 5-9%
- Asphalt AS 7.51 % minimum 7,3%
Berat jenis bahan: - HRS D1 2.24 ton/m³
- Coarse agregat & Fi D2 1.8 ton/m³
- Fraksi Filler D3 2 ton/m³
- Asphalt D4 1.03 ton/m³

BAHAN
- Agregat kasar = (CA x (D1 x t m3) x Fh1) (M03) 0.0121 m³
- Agregat halus = (FA x (D1 x t m3) x Fh1) (M04) 0.0232 m³
- Filler = (FF x (D1 x t m3) x Fh1) (M05) 4.7974 kg
- Asphalt = (AS x (D1 x t m3) x Fh2) (M06) 5.2991 kg

WHEEL LOADER 1,0-1,6 M3


Kapasitas bucket V 1.8 m³
Faktor bucket Fb 0.9
Efisiensi alat Fa 0.83
Waktu siklus Ts1
196

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Memuat T1 1.5 menit


- Lain-lain T2 0.5 menit
Ts1 2 menit

Kap. prod / jam = D2 x V x Fb x Fa x 60 Q1 1080.4821 m³/jam


D1 x Ts1 x t

Koefisien Alat / m³ = 1 : Q1 Qt1 0.001 jam

ASPHALT MIXING PLANT (AMP)


Kapasitas produksi alat V 50 Ton/jam
Efisiensi alat Fa 0.83

Kap. prod / jam = V x Fa Q2 617.56 m²/jam


D1 x t

Koefisien Alat / m² = 1 : Q2 Qt2 0.0017 jam

GENERATOR SET 125 KVA


Kap. prod / jam = SAMA DENGAN AMP Q3 617.56 m²/jam
Koefisien Alat / m² = 1 : Q3 Qt3 0.0017 jam

DUMP TRUCK 3-4 M³ / 6 TON


Kapasitas bak V 6 ton
Efisiensi alat Fa 0.83
Kecepatan rata-rata bermuatan v1 40 Km/jam
Kecepatan rata-rata kosong v2 50 Km/jam
Kapasitas AMP / batch Q2b 0.5 ton
Waktu menyiapkan 1 batch HRS Tb 1 menit
Waktu siklus Ts2
- Mengisi bak = (V : Q2b) x Tb T1 12 menit
- Waktu tempuh isi = (L : v1) x 60 T2 30 menit
- Waktu tempuh kosong = (L : v2) x 60 T3 24 menit
- Lain-lain (tunggu + dump + putar) T4 15 menit
Ts2 81 menit

Kap. prod / jam = v x Fa x 60 Q4 54.89418 m³/jam


D1 x Ts2 x t

Koefisien Alat / m³ = 1 : Q4 Qt4 0.0183 jam

ASPHALT FINISHER
Kapasitas produksi alat V 40 Ton/jam
Efisiensi alat Fa 0.83

Kap. prod / jam = V x Fa Q5 494.05 m²/jam


197

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

D1 x t

Koefisien Alat / m² = 1 : Q5 Qt5 0.0021 jam

TANDEM ROLLER 6-8 TON


Kecepatan alat v 3.5 km/jam
Efisiensi alat Fa 0.83
Lebar pemadatan b 1.2 m'
Banyak lintasan (pass) n 6 lintasan 3 kali bolak-balik

Kap. prod / jam = (v x 1000) x b x Fa Q6 581 m²/jam


n

Koefisien Alat / m² = 1 : Q6 Qt6 0.0018 jam

PNEUMATIC TYRE ROLLER 8-12 TON


Kecepatan alat v 5 km/jam
Efisiensi alat Fa 0.83
Lebar pemadatan b 1.5 m'
Banyak lintasan (pass) n 8 lintasan 4 kali bolak-balik

Kap. prod / jam = (v x 1000) x b x Fa Qj 778.125 m²/jam


n

Koefisien Alat / m² = 1 : Qj Qt 0.0013 jam

TENAGA
Produksi menentukan: AMP Q2 617.56 m²/jam
Produksi HRS / hari = Tk x Q2 Qt 4,322.92 m²/hari
Kebutuhan tenaga:
- Pekerja P 10 orang
- Mandor M 1 orang
Koefisien tenaga / m³
- Pekerja = P : Qt 0.0024 Oh
- Mandor = M : Qt 0.0003 Oh

Harga bahan:
- Batu pecah/split 1/2 m³ 0.0122 475,000 5,795.00
- Abu batu m³ 0.0233 607,639 14,157.99
- Filler untuk hotmix (semen) kg 4.7975 2,380 11,418.05
- Aspal Polimer Lokal kg 5.2991 23,500 124,528.85
Jumlah Harga Bahan 155,899.89
Harga pemakaian alat:
- WHEEL LOADER 1,0-1,6 M3 jam 0.001 383,386 383.39
- ASPHALT MIXING PLANT (AMP) jam 0.0017 5,024,901 8,542.33
- GENERATOR SET 125 KVA jam 0.0017 429,044 729.37
198

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- DUMP TRUCK 3-4 M³ / 6 TON jam 0.0183 297,961 5,452.69


- ASPHALT FINISHER jam 0.0021 211,644 444.45
- TANDEM ROLLER 6-8 TON jam 0.0018 217,574 391.63
- PNEUMATIC TYRE ROLLER 8-12 TON jam 0.0013 234,992 305.49
Jumlah Harga Peralatan 16,249.36
Upah tenaga:
- Pekerja Oh 0.0024 140,000 336.00
- Mandor Oh 0.0003 185,000 55.50
Jumlah Upah Tenaga 391.50
Jumlah Total 172,540.74
Jumlah Total + jasa 10% 189,750
( untuk per M2 dibutuhkan 2 Liter lapis perekat ) + Lapisan Tipis Aspal Beton (LATASTON / HRS-Hot Rolled Sheet) tebal 3 cm ti 252,950

14. Lapisan Permukaan Aspal Beton (LASTON / AC-Asphalt Concrete) tebal 5 cm tiap 1m²

Jam kerja efektif rata-rata Tk 7 jam


Jarak lokasi pengolahan AMP ke proyek L 20 km
Tebal Lapis jalan padat t 0.05 m
Faktor kehilangan material : - Agregat Fh1 1.1
- Aspal Fh2 1.05
Komposisi campuran AC : - Coarse Agrega CA 61.15 % 30-50%
- Fine Agregat FA 27 % 39-59%
- Fraksi Filler FF 4.85 % 4,5-7,5%
- Asphalt AS 7 % minimum 5,7%
Berat jenis bahan: - Asphalt Concrete (AC) D1 2.25 ton/m³
- Coarse agregat & Fi D2 1.8 ton/m³
- Fraksi Filler D3 2 ton/m³
- Asphalt D4 1.03 ton/m³

BAHAN
- Agregat kasar = (CA x (D1 x t m3) x Fh1) (M03) 0.0420 m³
- Agregat halus = (FA x (D1 x t m3) x Fh1) (M04) 0.0186 m³
- Filler = (FF x (D1 x t m3) x Fh1) (M05) 6.0019 kg
- Asphalt = (AS x (D1 x t m3) x Fh2) (M06) 8.2688 kg

WHEEL LOADER 1,0-1,6 M3


Kapasitas bucket V 1.8 m³
Faktor bucket Fb 0.9
Efisiensi alat Fa 0.83
Waktu siklus Ts1
- Memuat T1 1.5 menit
- Lain-lain T2 0.5 menit
Ts1 2 menit

Kap. prod / jam = D2 x V x Fb x Fa x 60 Q1 645.408 m³/jam


D1 x Ts1 x t
199

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Koefisien Alat / m³ = 1 : Q1 Qt1 0.0016 jam

ASPHALT MIXING PLANT (AMP)


Kapasitas produksi alat V 50 Ton/jam
Efisiensi alat Fa 0.83

Kap. prod / jam = V x Fa Q2 368.89 m²/jam


D1 x t

Koefisien Alat / m² = 1 : Q2 Qt2 0.0028 jam

GENERATOR SET 125 KVA


Kap. prod / jam = SAMA DENGAN AMP Q3 368.89 m²/jam
Koefisien Alat / m² = 1 : Q3 Qt3 0.0028 jam

DUMP TRUCK 3-4 M³ / 6 TON


Kapasitas bak V 6 ton
Efisiensi alat Fa 0.83
Kecepatan rata-rata bermuatan v1 40 Km/jam
Kecepatan rata-rata kosong v2 50 Km/jam
Kapasitas AMP / batch Q2b 0.5 ton
Waktu menyiapkan 1 batch HRS Tb 1 menit
Waktu siklus Ts2
- Mengisi bak = (V : Q2b) x Tb T1 12 menit
- Waktu tempuh isi = (L : v1) x 60 T2 30 menit
- Waktu tempuh kosong = (L : v2) x 60 T3 24 menit
- Lain-lain (tunggu + dump + putar) T4 15 menit
Ts2 81 menit

Kap. prod / jam = v x Fa x 60 Q4 32.790123 m³/jam


D1 x Ts2 x t

Koefisien Alat / m³ = 1 : Q4 Qt4 0.0305 jam

ASPHALT FINISHER
Kapasitas produksi alat V 40 Ton/jam
Efisiensi alat Fa 0.83

Kap. prod / jam = V x Fa Q5 295.11 m²/jam


D1 x t

Koefisien Alat / m² = 1 : Q5 Qt5 0.0034 jam

TANDEM ROLLER 6-8 TON


Kecepatan alat v 2.5 km/jam
Efisiensi alat Fa 0.83
200

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Lebar pemadatan b 1.2 m'


Banyak lintasan (pass) n 4 lintasan 2 kali bolak-balik

Kap. prod / jam = (v x 1000) x b x Fa Q6 622.5 m²/jam


n

Koefisien Alat / m² = 1 : Q6 Qt6 0.0017 jam

PNEUMATIC TYRE ROLLER 8-12 TON


Kecepatan alat v 3.5 km/jam
Efisiensi alat Fa 0.83
Lebar pemadatan b 1.5 m'
Banyak lintasan (pass) n 8 lintasan 4 kali bolak-balik

Kap. prod / jam = (v x 1000) x b x Fa Qj 544.6875 m²/jam


n

Koefisien Alat / m² = 1 : Qj Qt 0.0019 jam

TENAGA
Produksi menentukan: AMP Q2 368.89 m²/jam
Produksi HRS / hari = Tk x Q2 Qt 2,582.22 m²/hari
Kebutuhan tenaga:
- Pekerja P 10 orang
- Mandor M 1 orang
Koefisien tenaga / m³
- Pekerja = P : Qt 0.0039 Oh
- Mandor = M : Qt 0.0004 Oh

Harga bahan:
- Batu pecah/split 1/2 m³ 0.0421 475,000 19,997.50
- Abu batu m³ 0.0186 607,639 11,302.09
- Filler untuk hotmix (semen) kg 6.0019 2,380 14,284.52
- Aspal Polimer Lokal kg 8.2688 23,500 194,316.80
Jumlah Harga Bahan 239,900.91
Harga pemakaian alat:
- WHEEL LOADER 1,0-1,6 M3 jam 0.0016 383,386 613.42
- ASPHALT MIXING PLANT (AMP) jam 0.0028 5,024,901 14,069.72
- GENERATOR SET 125 KVA jam 0.0028 429,044 1,201.32
- DUMP TRUCK 3-4 M³ / 6 TON jam 0.0305 297,961 9,087.81
- ASPHALT FINISHER jam 0.0034 211,644 719.59
- TANDEM ROLLER 6-8 TON jam 0.0017 217,574 369.88
- PNEUMATIC TYRE ROLLER 8-12 TON jam 0.0019 234,992 446.49
Jumlah Harga Peralatan 26,508.23
Upah tenaga:
201

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Pekerja Oh 0.0039 140,000 546.00


- Mandor Oh 0.0004 185,000 74.00
Jumlah Upah Tenaga 620.00
Jumlah Total 267,029.13
Jumlah Total + jasa 10% 293,700
15. Pembuatan jalan aspal biasa (Sirtu t=10 cm, Agregat Kelas A t=20 cm, Permukaan Macadam t=5 cm) tiap m²
Harga bahan:
- Sirtu m³ 0.12 416,539 49,984.68
- Batu pecah/split 3/5 m³ 0.04 475,000 19,000.00
- Batu pecah/split 2/3 m³ 0.1756 475,000 83,410.00
- Batu pecah/split 1/2 m³ 0.011 475,000 5,225.00
- Abu batu m³ 0.0025 607,639 1,519.10
- Aspal Polimer Lokal kg 4.8 23,500 112,800.00
- Minyak tanah Ltr 0.322 17,758 5,718.08
- Pasir urug m³ 0.0864 120,000 10,368.00
Jumlah Harga Bahan 288,024.85
Harga pemakaian alat:
- VIBRATING ROLLER 6-8 TON jam 0.0066 273,161 1,802.86
- WATER TANK TRUCK 3000-4500 L jam 0.01352 273,553 3,698.43
- THREE WHEEL ROLLER 8-10 TON jam 0.00806 203,528 1,640.44
- ASPHALT SPRAYER jam 0.0144 101,938 1,467.90
- DUMP TRUCK 3-4 M³ / 6 TON jam 0.0108 297,961 3,217.98
Jumlah Harga Peralatan 11,827.61
Upah tenaga:
- Pekerja Oh 0.3915 140,000 54,810.00
- Tukang aspal Oh 0.0043 180,000 774.00
- Mandor Oh 0.014 185,000 2,590.00
Jumlah Upah Tenaga 58,174.00
Jumlah Total 358,026.47
Jumlah Total + jasa 10% 393,800

16. Pembuatan jalan aspal biasa lebar 3 m' tiap 1 m' 1,181,400
17. Pembuatan jalan aspal biasa lebar 4 m' tiap 1 m' 1,575,200
18. Pembuatan jalan aspal biasa lebar 5 m' tiap 1 m' 1,969,000
19. Pembuatan jalan aspal biasa lebar 6 m' tiap 1 m' 2,362,800
20. Pembuatan jalan aspal biasa lebar 8 m' tiap 1 m' 3,150,400

21. Pembuatan jalan aspal beton t=3 cm (Sirtu = 10 cm, Agregat Kelas A t=20 cm, LATASTON HRS-WC = 3 cm) tiap m²
Harga bahan:
- Sirtu m³ 0.12 416,539 49,984.68
- Batu pecah/split 2/3 m³ 0.1536 475,000 72,960.00
- Pasir urug m³ 0.0864 120,000 10,368.00
- Aspal Polimer Lokal kg 5.81246 23,500 136,592.81
- Minyak Tanah Ltr 0.39112 17,758 6,945.51
- Batu pecah/split 1/2 m³ 0.0122 475,000 5,795.00
- Abu batu m³ 0.0233 607,639 14,157.99
- Filler untuk hotmix (semen) kg 4.7975 2,380 11,418.05
202

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Harga Bahan 308,222.04

Harga pemakaian alat:


- VIBRATING ROLLER 6-8 TON jam 0.0066 273,161 1,802.86
- WATER TANK TRUCK 3000-4500 L jam 0.01352 273,553 3,698.43
- THREE WHEEL ROLLER 8-10 TON jam 0.00536 203,528 1,090.91
- ASPHALT SPRAYER jam 0.0024 101,938 244.65
- AIR COMPRESSOR jam 0.00248 224,250 556.14
- DUMP TRUCK 3-4 M³ / 6 TON jam 0.0207 297,961 6,167.79
- WHEEL LOADER 1,0-1,6 M3 jam 0.001 383,386 383.39
- ASPHALT MIXING PLANT (AMP) jam 0.0017 5,024,901 8,542.33
- GENERATOR SET 125 KVA jam 0.0017 429,044 729.37
- ASPHALT FINISHER jam 0.0021 211,644 444.45
- TANDEM ROLLER 6-8 TON jam 0.0018 217,574 391.63
- PNEUMATIC TYRE ROLLER 8-12 TON jam 0.0013 234,992 305.49
Jumlah Harga Peralatan 24,357.46
Upah tenaga:
- Pekerja Oh 0.25584 140,000 35,817.60
- Mandor Oh 0.0108 185,000 1,998.00
Jumlah Upah Tenaga 37,815.60
Jumlah Total 370,395.09
Jumlah Total + jasa 10% 407,400

22. Pembuatan jalan aspal beton t=3 cm lebar 3 m' tiap 1 m' 1,222,200
23. Pembuatan jalan aspal beton t=3 cm lebar 4 m' tiap 1 m' 1,629,600
24. Pembuatan jalan aspal beton t=3 cm lebar 5 m' tiap 1 m' 2,037,000
25. Pembuatan jalan aspal beton t=3 cm lebar 6 m' tiap 1 m' 2,444,400
26. Pembuatan jalan aspal beton t=3 cm lebar 8 m' tiap 1 m' 3,259,200

27. Pembuatan jalan aspal beton t=5 cm (Sirtu = 10 cm, Agregat Kelas A t=20 cm, LASTON AC-WC = 5 cm) tiap m²
Harga bahan:
- Sirtu m³ 0.12 416,539 49,984.68
- Batu pecah/split 2/3 m³ 0.1536 475,000 72,960.00
- Pasir urug m³ 0.0864 120,000 10,368.00
- Aspal Polimer Lokal kg 8.78216 23,500 206,380.76
- Minyak Tanah Ltr 0.39112 17,758 6,945.51
- Batu pecah/split 1/2 m³ 0.0421 475,000 19,997.50
- Abu batu m³ 0.0186 607,639 11,302.09
- Filler untuk hotmix (semen) kg 6.0019 2,380 14,284.52
Jumlah Harga Bahan 392,223.06
Harga pemakaian alat:
- VIBRATING ROLLER 6-8 TON jam 0.0066 273,161 1,802.86
- WATER TANK TRUCK 3000-4500 L jam 0.01352 273,553 3,698.43
- THREE WHEEL ROLLER 8-10 TON jam 0.00536 203,528 1,090.91
- ASPHALT SPRAYER jam 0.0024 101,938 244.65
- AIR COMPRESSOR jam 0.00248 224,250 556.14
- DUMP TRUCK 3-4 M³ / 6 TON jam 0.0329 297,961 9,802.92
203

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- WHEEL LOADER 1,0-1,6 M3 jam 0.0016 383,386 613.42


- ASPHALT MIXING PLANT (AMP) jam 0.0028 5,024,901 14,069.72
- GENERATOR SET 125 KVA jam 0.0028 429,044 1,201.32
- ASPHALT FINISHER jam 0.0034 211,644 719.59
- TANDEM ROLLER 6-8 TON jam 0.0017 217,574 369.88
- PNEUMATIC TYRE ROLLER 8-12 TON jam 0.0019 234,992 446.49
Jumlah Harga Peralatan 34,616.33
Upah tenaga:
- Pekerja Oh 0.25734 140,000 36,027.60
- Mandor Oh 0.0109 185,000 2,016.50
Jumlah Upah Tenaga 38,044.10
Jumlah Total 464,883.48
Jumlah Total + jasa 10% 511,350

28. Pembuatan jalan aspal beton t=5 cm lebar 3 m' tiap 1 m' 1,534,050
29. Pembuatan jalan aspal beton t=5 cm lebar 4 m' tiap 1 m' 2,045,400
30. Pembuatan jalan aspal beton t=5 cm lebar 5 m' tiap 1 m' 2,556,750
31. Pembuatan jalan aspal beton t=5 cm lebar 6 m' tiap 1 m' 3,068,100
32. Pembuatan jalan aspal beton t=5 cm lebar 8 m' tiap 1 m' 4,090,800

33. Pekerjaan paving parkir kendaraan (warna abu T-16 uk. 8x10,5x21) + urugan sirtu 20 cm + urugan pasir 5 cm tiap m²

TAMPER / HAND COMPACTOR


Kecepatan alat v 0.5 km/jam
Efisiensi alat Fa 0.83
Lebar pemadatan b 0.25 m'
Banyak lintasan (pass) n 14 lintasan 7 kali bolak-balik

Kap. prod / jam = (v x 1000) x b x Fa Qj 7.4107143 m²/jam


n

Koefisien Alat / m² = 1 : Qj Qt 0.135 jam

PLATE COMPACTOR
Kecepatan alat v 0.5 km/jam
Efisiensi alat Fa 0.83
Lebar pemadatan b 0.43 m'
Banyak lintasan (pass) n 6 lintasan 3 kali bolak-balik

Kap. prod / jam = (v x 1000) x b x Fa Qj 29.741667 m²/jam


n

Koefisien Alat / m² = 1 : Qj Qt 0.0337 jam

Harga bahan:
- Sirtu m³ 0.24 416,539 99,969.36
- Pasir urug m³ 0.06 120,000 7,200.00
204

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Paving abu-abu segi enam, tebal 8 cm m² 1.1 40,100 44,110.00


- Abu batu m³ 0.018 607,639 10,937.50
Jumlah Harga Bahan 162,216.86
Harga pemakaian alat:
- TAMPER / HAND COMPACTOR jam 0.135 56,997 7,694.56
- PLATE COMPACTOR jam 0.0337 59,856 2,017.14
Jumlah Harga Peralatan 9,711.70
Upah tenaga:
- Pekerja Oh 0.2125 140,000 29,750.00
- Tukang batu Oh 0.12 160,000 19,200.00
- Kepala tukang Oh 0.012 180,000 2,160.00
- Mandor Oh 0.01625 185,000 3,006.25
Jumlah Upah Tenaga 54,116.25
Jumlah Total 226,044.81
Jumlah Total + jasa 10% 248,600

34. Pekerjaan paving parkir kendaraan (warna abu T-16 uk. 6x10,5x21) + urugan sirtu 20 cm + urugan pasir 5 cm tiap m²

TAMPER / HAND COMPACTOR


Kecepatan alat v 0.5 km/jam
Efisiensi alat Fa 0.83
Lebar pemadatan b 0.25 m'
Banyak lintasan (pass) n 14 lintasan 7 kali bolak-balik

Kap. prod / jam = (v x 1000) x b x Fa Qj 7.4107143 m²/jam


n

Koefisien Alat / m² = 1 : Qj Qt 0.135 jam

PLATE COMPACTOR
Kecepatan alat v 0.5 km/jam
Efisiensi alat Fa 0.83
Lebar pemadatan b 0.43 m'
Banyak lintasan (pass) n 6 lintasan 3 kali bolak-balik

Kap. prod / jam = (v x 1000) x b x Fa Qj 29.741667 m²/jam


n

Koefisien Alat / m² = 1 : Qj Qt 0.0337 jam

Harga bahan:
- Sirtu m³ 0.24 416,539 99,969.36
- Pasir urug m³ 0.06 120,000 7,200.00
- Paving abu-abu segi enam, tebal 6 cm m² 1.1 33,750 37,125.00
- Abu batu m³ 0.018 607,639 10,937.50
Jumlah Harga Bahan 155,231.86
Harga pemakaian alat:
205

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- TAMPER / HAND COMPACTOR jam 0.135 56,997 7,694.56


- PLATE COMPACTOR jam 0.0337 59,856 2,017.14
Jumlah Harga Peralatan 9,711.70
Upah tenaga:
- Pekerja Oh 0.2125 140,000 29,750.00
- Tukang batu Oh 0.12 160,000 19,200.00
- Kepala tukang Oh 0.012 180,000 2,160.00
- Mandor Oh 0.01625 185,000 3,006.25
Jumlah Upah Tenaga 54,116.25
Jumlah Total 219,059.81
Jumlah Total + jasa 10% 240,950

35. Pekerjaan paving jalan setapak (warna abu T-16 uk. 8x10,5x21) + urugan sirtu 10 cm + urugan pasir 5 cm tiap m²

TAMPER / HAND COMPACTOR


Kecepatan alat v 0.5 km/jam
Efisiensi alat Fa 0.83
Lebar pemadatan b 0.25 m'
Banyak lintasan (pass) n 14 lintasan 7 kali bolak-balik

Kap. prod / jam = (v x 1000) x b x Fa Qj 7.4107143 m²/jam


n

Koefisien Alat / m² = 1 : Qj Qt 0.135 jam

PLATE COMPACTOR
Kecepatan alat v 0.5 km/jam
Efisiensi alat Fa 0.83
Lebar pemadatan b 0.43 m'
Banyak lintasan (pass) n 6 lintasan 3 kali bolak-balik

Kap. prod / jam = (v x 1000) x b x Fa Qj 29.741667 m²/jam


n

Koefisien Alat / m² = 1 : Qj Qt 0.0337 jam

Harga bahan:
- Sirtu m³ 0.12 416,539 49,984.68
- Pasir urug m³ 0.06 120,000 7,200.00
- Paving abu-abu segi enam, tebal 8 cm m² 1.05 40,100 42,105.00
- Abu batu m³ 0.018 607,639 10,937.50
Jumlah Harga Bahan 110,227.18
Harga pemakaian alat:
- TAMPER / HAND COMPACTOR jam 0.135 56,997 7,694.56
- PLATE COMPACTOR jam 0.0337 59,856 2,017.14
Jumlah Harga Peralatan 9,711.70
Upah tenaga:
206

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Pekerja Oh 0.1875 140,000 26,250.00


- Tukang batu Oh 0.12 160,000 19,200.00
- Kepala tukang Oh 0.012 180,000 2,160.00
- Mandor Oh 0.01375 185,000 2,543.75
Jumlah Upah Tenaga 50,153.75
Jumlah Total 170,092.63
Dibulatkan 170,050
36. Pekerjaan kanstin tiap 1 m'
Harga bahan:
- Kayu Meranti Palembang papan m³ 0.0007 4,500,000 3,150.00
- Kayu Meranti Palembang kaso m³ 0.0012 4,500,000 5,400.00
- Paku biasa 2"-5" kg 0.002 19,286 38.57
- Pasir urug m³ 0.015 120,000 1,800.00
- Kanstin abu-abu 15 x 25 x 40 bh 2.625 55,000 144,375.00
- Semen portland kg 7.075 1,300 9,197.50
- Pasir pasang m³ 0.0195 178,164 3,474.20
Jumlah Harga Bahan 167,435.27
Upah tenaga:
- Pekerja Oh 0.076 140,000 10,640.00
- Tukang batu Oh 0.0225 160,000 3,600.00
- Kepala tukang Oh 0.00225 180,000 405.00
- Mandor Oh 0.005 185,000 925.00
Jumlah Upah Tenaga 15,570.00
Jumlah Total 183,005.27
Jumlah Total + jasa 10% 201,300
37. Pasang grassblock tebal 10 cm tiap 1 1m²
Harga bahan:
- Grassblock m² 1.0000 96,400 96,400.00
- Pasir urug 0.0500 120,000 6,000.00
Jumlah Harga Bahan 102,400.00
Upah tenaga:
- Pekerja Oh 0.5000 140,000 70,000.00
- Tukang batu Oh 0.2500 160,000 40,000.00
- Kepala tukang Oh 0.0250 180,000 4,500.00
- Mandor Oh 0.0250 185,000 4,625.00
Jumlah Upah Tenaga 119,125.00
Jumlah Total 221,525.00
Jumlah Total + jasa 10% 243,650
38. Gebalan rumput tiap 1m²
Harga bahan:
- Gebalan rumput m² 1.0000 70,000 70,000.00
Jumlah Harga Bahan 70,000.00
Upah tenaga:
- Pekerja Oh 0.0500 140,000 7,000.00
- Mandor Oh 0.0250 185,000 4,625.00
Jumlah Upah Tenaga 11,625.00
Jumlah Total 81,625.00
207

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Total + jasa 10% 89,750


39. Pas. Pagar besi hollow tbl. 0.6 mm tiap 1 m²
Harga bahan:
- Hollow 4 X 6 cm tbl 0.3 mm btg 0.333 29,000 9,657.00
- Hollow 2 x 4 cm tbl 0.3 mm btg 3.167 22,500 71,250.00
- Pengelasan cm 27.08 4,500 121,860.00
- Aksesoris 10 % (engsel besi + kawat las % 0.1 9,657 965.70
Jumlah Harga Bahan 203,732.70
Upah tenaga:
- Pekerja Oh 1.2 140,000 168,000.00
- Tukang las Oh 1.2 160,000 192,000.00
- Kepala tukang Oh 0.012 180,000 2,160.00
- Mandor Oh 0.008 185,000 1,480.00
Jumlah Upah Tenaga 363,640.00
Jasa 10% 36,364.00
Jumlah Total 603,736.70
Dibulatkan 603,700

V PEKERJAAN ANALISA TAMBAHAN

1. Foto Dokumentasi
- Cetak foto pada kertas lbr 20.00 5,500 110,000.00
- CD / Flesdics bh 1.00 75,000 75,000.00
- Jilid bh 2.00 25,000 50,000.00
Jumlah Total 235,000.00
Jumlah Total + jasa 10% 258,500
2. Listrik Kerja (Sewa Genset)
- sewa generator 1 KVA unit/bln 1.00 429,044 429,043.99
- solar ltr/bln 40.00 10,200 408,000.00
- pelumas ltr/bln 2.00 74,323 148,646.00
- Operator Genset org/hr 10.00 110,000 1,100,000.00
- instalasi penerangan ttk 2.00 354,500 709,000.00
Jumlah Total 2,794,689.99
Jumlah Total + jasa 10% 3,074,150
3. Listrik Kerja dengan penyambungan daya sementara utk ± 5 bln
- Penyambungan daya unit 1.00 1,350,000 1,350,000.00
- pengabelan titik lampu unit 3.00 354,500 1,063,500.00
- pengabelan stop kontak tenaga 500 watt unit 2.00 750,000 1,500,000.00
- pengabelan stop Kontak tenaga 1000 watt unit 1.00 1,250,000 1,250,000.00
- MCB 3 phase 6 A bh 1.00 1,250,000 1,250,000.00
- MCB 1 phase 6 A bh 1.00 74,000 74,000.00
- Box MCB 3 group set 1.00 250,000 250,000.00
- Pemakaian selama 5 bulan bln 5.00 500,000 2,500,000.00
Jumlah Total 9,237,500.00
Jumlah Total + jasa 10% 10,161,250
4 Memasang 1 buah pompa sumur listrik
Harga bahan:
208

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Pompa air listrik 250 W bh 1 1,500,000 1,500,000.00


- Perlengkapan (25% harga pompa) % 25 1,500,000 375,000.00
Jumlah Harga Bahan 1,875,000.00
Upah tenaga:
- Pekerja Oh 0.08 140,000 11,200.00
- Tukang pasang pipa Oh 0.14 180,000 25,200.00
- Kepala tukang Oh 0.15 180,000 27,000.00
- Mandor Oh 0.1 185,000 18,500.00
Jumlah Upah Tenaga 81,900.00
Jumlah Total 1,956,900.00
Jumlah Total + jasa 10% 2,152,550
5 Air Kerja dalam unit
- Pantek sumur unit 1.000 2,152,550.00 2,152,550.00
- Pompa air tangan unit 1.000 400,000.00 400,000.00
- Pipa PVC dia.1 1/4" m' 10.000 69,250.00 692,500.00
- Pipa GIP dia.1 1/4" m' 2.000 112,850.00 225,700.00
- Sock draad dalam besi 1 1/4" bh 1.000 6,000.00 6,000.00
- Sock draad luar PVC 1 1/4" bh 1.000 6,000.00 6,000.00
- Bak penampung drum 200 ltr bh 2.000 236,200.00 472,400.00
Jumlah 3,955,150.00
Jumlah Total + jasa 10% 4,350,650
6. Pemasangan AC Split
Harga bahan:
- Material Bantu unit 1.000 384,375 384,375.00
Jumlah Harga Bahan 384,375.00
Upah tenaga:
- Pekerja Oh 0.300 140,000 42,000.00
- Instalator Oh 0.400 180,000 72,000.00
Jumlah Upah Tenaga 114,000.00
Jumlah Total 498,375.00
Jumlah Total + jasa 10% 548,200
7. Beton Ready Mix K.350 / m3
Harga bahan:
- Ready Mix K350 slump 12 m³ 1.1500 830,000 954,500.00
Jumlah Harga Bahan 954,500.00
Upah :
- Pekerja Oh 2.5000 140,000 350,000.00
- Tukang batu Oh 0.4170 160,000 66,720.00
- Kepala Tukang Oh 0.0420 180,000 7,560.00
- Mandor Oh 0.0080 185,000 1,480.00
Jumlah Upah Tenaga 425,760.00
Alat bantu Utama:
- Sewa Pompa Beton s/d lt 4 m³ 1.0000 79,349 79,349.00
- Sewa Vibrator jam 1.0000 58,596 58,596.15
- Ember aduk bh 0.0500 5,500 275.00
- Pacul aduk bh 0.0500 52,500 2,625.00
- Sekop bh 0.0500 53,500 2,675.00
209

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

Jumlah Upah Tenaga 143,520.15


Jumlah Total 1,523,780.15
Jumlah Total + jasa 10% 1,676,150
8. Beton Ready Mix K.300 / m3
Harga bahan:
- Ready Mix K300 slump 12 m³ 1.1500 800,000 920,000.00
Jumlah Harga Bahan 920,000.00
Upah :
- Pekerja Oh 2.5000 140,000 350,000.00
- Tukang batu Oh 0.4170 160,000 66,720.00
- Kepala Tukang Oh 0.0420 180,000 7,560.00
- Mandor Oh 0.0080 185,000 1,480.00
Jumlah Upah Tenaga 425,760.00
Alat bantu Utama:
- Sewa Pompa Beton s/d lt 4 m³ 1.0000 79,349 79,349.00
- Sewa Vibrator jam 1.0000 58,596 58,596.15
- Ember aduk bh 0.0500 5,500 275.00
- Pacul aduk bh 0.0500 52,500 2,625.00
- Sekop bh 0.0500 53,500 2,675.00
Jumlah Upah Tenaga 143,520.15
Jumlah Total 1,489,280.15
Jumlah Total + jasa 10% 1,638,200
9. Beton Ready Mix K.275 / m3
Harga bahan:
- Ready Mix K275 slump 12 m³ 1.1500 790,000 908,500.00
Jumlah Harga Bahan 908,500.00
Upah :
- Pekerja Oh 2.5000 140,000 350,000.00
- Tukang batu Oh 0.4170 160,000 66,720.00
- Kepala Tukang Oh 0.0420 180,000 7,560.00
- Mandor Oh 0.0080 185,000 1,480.00
Jumlah Upah Tenaga 425,760.00
Alat bantu Utama:
- Sewa Pompa Beton s/d lt 4 m³ 1.0000 79,349 79,349.00
- Sewa Vibrator jam 1.0000 58,596 58,596.15
- Ember aduk bh 0.0500 5,500 275.00
- Pacul aduk bh 0.0500 52,500 2,625.00
- Sekop bh 0.0500 53,500 2,675.00
Jumlah Upah Tenaga 143,520.15
Jumlah Total 1,477,780.15
Jumlah Total + jasa 10% 1,625,550
10. Beton Ready Mix K.250 / m3
Harga bahan:
- Ready Mix K250 slump 12 m³ 1.1500 760,000 874,000.00
Jumlah Harga Bahan 874,000.00
Upah :
- Pekerja Oh 2.5000 140,000 350,000.00
210

KUANTI HARGA SAT.


NO. URAIAN SAT SUB TOTAL (Rp) HSP (Rp)
TAS DASAR (Rp)

1 2 3 4 5 6 7

- Tukang batu Oh 0.4170 160,000 66,720.00


- Kepala Tukang Oh 0.0420 180,000 7,560.00
- Mandor Oh 0.0080 185,000 1,480.00
Jumlah Upah Tenaga 425,760.00
Alat bantu Utama:
- Sewa Pompa Beton s/d lt 4 m³ 1.0000 79,349 79,349.00
- Sewa Vibrator jam 1.0000 58,596 58,596.15
- Ember aduk bh 0.0500 5,500 275.00
- Pacul aduk bh 0.0500 52,500 2,625.00
- Sekop bh 0.0500 53,500 2,675.00
Jumlah Upah Tenaga 143,520.15
Jumlah Total 1,443,280.15
Jumlah Total + jasa 10% 1,587,600
11. Beton Ready Mix K.225 / m3
Harga bahan:
- Ready Mix K225 slump 12 m³ 1.1000 730,000 803,000.00
Jumlah Harga Bahan 803,000.00
Upah :
- Pekerja Oh 2.5000 140,000 350,000.00
- Tukang batu Oh 0.4170 160,000 66,720.00
- Kepala Tukang Oh 0.0420 180,000 7,560.00
- Mandor Oh 0.0080 185,000 1,480.00
Jumlah Upah Tenaga 425,760.00
Alat bantu Utama:
- Sewa Pompa Beton s/d lt 4 m³ 1.0000 79,349 79,349.00
- Sewa Vibrator m³ 1.0000 58,596 58,596.15
- Ember aduk bh 0.0500 5,500 275.00
- Pacul aduk bh 0.0500 52,500 2,625.00
- Sekop bh 0.0500 53,500 2,675.00
Jumlah Upah Tenaga 143,520.15
Jumlah Total 1,372,280.15
Jumlah Total + jasa 10% 1,509,500

Palembang, 01 September 2020


PT. MANDALA WANGI

Sahma Sukarta
Direktur Utama
211

ANALISIS BIAYA PERALATAN PER JAM KERJA


WILAYAH PALEMBANG TA. 2020

A. RINGKASAN

BIAYA ALAT/
NO. URAIAN KODE HP KAPASITAS HARGA ALAT KET.
JAM
1 2 3 4 5 6 7 8

A ASPHALT MIXING PLANT (AMP) E01 150 50 Ton/Jam 2,074,469,568 5,024,900.61 Alat baru
B ASPHALT FINISHER E02 47 40 Ton/Jam 446,297,197 211,643.76 Alat baru
1
C ASPHALT SPRAYER E03 15 800 Liter 146,326,950 101,937.72 Alat baru 1
2
D BULLDOZER 140 HP E04 140 - - 1,309,393,937 555,718.77 Alat baru 1
3 Bu
2
3
4 Bu
E AIR COMPRESSOR E05 80 - - 95,112,517 224,249.73 Alat baru
4
5
F CONCRETE MIXER 0,3-0,6 M3 E06 6 350 Liter 10,919,094 59,557.26 Alat baru 5
6
G DUMP TRUCK 3-4 M³ / 6 TON E08 100 6 Ton 315,532,125 297,961.09 Alat baru 6
7
7
8
H DUMP TRUCK 8 TON E09 125 8 Ton 365,817,375 361,969.91 Alat baru 8
9
I EXCAVATOR 150 HP Kobelco SK200 E10 150 0.9 M3 1,009,655,955 508,480.37 Alat baru 9
10
10
11
J GENERATOR SET 125 KVA E12 175 125 KVA 170,508,511 429,043.99 Alat baru 11
12
K GENERATOR SET 2 KVA E12.a 4 2 KVA 7,870,616 57,476.76 Alat baru 12
13
13
14
L MOTOR GRADER 125 HP E13 125 - - 731,634,750 425,348.07 Alat baru 14
15
M WHEEL LOADER 1,0-1,6 M3 E15 105 1.8 M3 792,604,312 383,385.80 Alat baru 15
16
16
17
N THREE WHEEL ROLLER 8-10 TON E16 55 8 Ton 292,653,900 203,528.08 Alat baru
17
18
O TANDEM ROLLER 6-8 TON E17 50 8 Ton 406,057,286 217,574.26 Alat baru 18
19
P PNEUMATIC TYRE ROLLER 8-12 TON E18 60 10 Ton 428,006,328 234,992.48 Alat baru 19
20
20
21
Q VIBRATING ROLLER 6-8 TON E19 75 7 Ton 478,001,370 273,160.55 Alat baru 21
22
R CONCRETE VIBRATOR E20 5 - - 5,581,790 58,596.15 Alat baru 22
23
23
24
S WATER PUMP 70-100 mm E22 8 - - 11,389,593 64,695.22 Alat baru 24
25
T WATER TANK TRUCK 3000-4500 L E23 100 4,000 Liter 160,959,645 273,552.84 Alat baru 25
26
26
27
U PEDESTERIAN ROLLER E24 11 0.980 Ton 100,672,425 84,410.53 Alat baru 27
28
V TAMPER / HAND COMPACTOR E25 4 0.082 Ton 11,462,062 56,996.72 Alat baru 28
29
29
30
W PLATE COMPACTOR E25.a 5.0 0.090 Ton 10,929,318 59,855.81 Alat baru
30
31
31
<SEL
<SEL
Janu
Referensi: Panduan Analisa Harga Satuan No. 028/T/BM/1995 Ditjen Bina Marga Departemen Pekerjaan Umum
Janu
Febr
Catatan: Febr
Mare
1. Tingkat suku bunga sesuai penetapan Lembaga Penjamin Simpanan (LPS) selanjutnya lihat www.lps.go.id - Periode: 15 7.00% Mare
Apri
Apri
Mei
2. Konversi upah orang hari ke upah orang jam sesuai SE Bappenas & DJA Depkeu Nomor 1203/D.II/03/2000 & SE-38/A/2000 tanggal 17 Maret 2000 Mei
Juni
dengan formula: SBOJ = (SBOH / 8) x 1,3 di mana SBOJ = Satuan Biaya Orang Jam; SBOH = Satuan Biaya Orang Hari. Juni
Juli
Juli
Agu
3. Biaya sewa sudah termasuk bahan bakar & pelumas, operator & pembantu operator. Agu
Sept
4. Biaya Umum & Keuntungan 10% diperhitungkan pada lembar Analisis Harga Satuan Pekerjaan. Sept
Okto
Okto
Nov
4. PPN 10% diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan. Nov
Dese
5. Upah Operator / Sopir U1 26,813.00 Rp / Jam Dese
<SEL
<SEL
2008
6. Upah Pembantu Operator U2 19,500.00 Rp / Jam
2008
2007
7. Bahan Bakar Bensin Mb 6,500.00 Rp / Liter 2007
2006
8. Bahan Bakar Solar Ms 10,200.00 Rp / Liter 2006
2005
2005
2004
9. Minyak Pelumas Mp 74,323.00 Rp / Liter 2004
2003
2003
2002
2002
2001
B. URAIAN 2001
2000
2000
<SEL
<SEL
1
1
2 Bu
3 Bu
4
5
212

NO. URAIAN KODE KOEF. SAT. KETERANGAN


1 2 3 4 5 6

A ASPHALT MIXING PLANT (AMP) E01


1. URAIAN PERALATAN
a. Tenaga Pw 150 HP
b. Kapasitas Cp 50 Ton/Jam
c. Alat Baru: 1) Umur Ekonomis A 10 Tahun
2) Jam Kerja dalam 1 Tahun W 1,500 Jam
3) Harga Alat B 2,074,469,568 Rupiah
d. Alat yang D1) Umur Ekonomis A' 10 Tahun Alat baru
2) Jam Kerja dalam 1 Tahun W' 1,500 Jam Alat baru
3) Harga Alat B' 2,074,469,568 Rupiah Alat baru

2. BIAYA PASTI (INITIAL COST / CAPITAL COST) PER JAM KERJA


a. Nilai Sisa Alat = 10% x B C 207,446,957 Rupiah
b. Faktor Angsuran Modal i x (1 + i) ^ A' D 0.14238
(1 + i) ^ A' - 1
c. Biaya Pasti Per Jam:
1) Biaya Pengembalian (B' - C) x D E 177,214.68 Rupiah
W'
2) Asuransi, dll = 0,002 x B' F 2,765.96 Rupiah
W'
Biaya Pasti Per Jam = (E + F) G 179,980.64 Rupiah

3. BIAYA OPERASI & PEMELIHARAAN (DIRECT OPERATIONAL & MAINTENANCE COST) PER JAM KERJA
a. Bahan Baka(0,125-0,175 Ltr/HP/Jam) x Pw x Ms H1 191,250.00 Rupiah
B. Bakar Pemanasan Ma
12 x 0,7Cp x Ms H2 4,284,000.00 Rupiah
b. Pelumas = (0,01-0,02 Ltr/HP/Jam) x Pw x Mp I 111,484.50 Rupiah
c. Perawatan (12,5%-17,5%) x B' K 172,872.46 Rupiah
Perb W'
d. Operator = (1 Orang / Jam) x U1 L 26,813.00 Rupiah
e. Pembantu Operator = (3 Orang / Jam) x U2 M 58,500.00 Rupiah
Biaya Operasi Per Ja (H + I + K + L + M) P 4,844,919.96 Rupiah

4. TOTAL BIAYA SEWA ALAT / JAM = (G + P) S 5,024,900.61 Rupiah

B ASPHALT FINISHER E02


1. URAIAN PERALATAN
a. Tenaga Pw 47 HP
b. Kapasitas Cp 40 Ton/Jam
c. Alat Baru: 1) Umur Ekonomis A 6 Tahun
2) Jam Kerja dalam 1 Tahun W 2,000 Jam
3) Harga Alat B 446,297,197 Rupiah
d. Alat yang D1) Umur Ekonomis A' 6 Tahun Alat baru
2) Jam Kerja dalam 1 Tahun W' 2,000 Jam Alat baru
3) Harga Alat B' 446,297,197 Rupiah Alat baru

2. BIAYA PASTI (INITIAL COST / CAPITAL COST) PER JAM KERJA


a. Nilai Sisa Alat = 10% x B C 44,629,720 Rupiah
b. Faktor Angsuran Modal i x (1 + i) ^ A' D 0.20980
(1 + i) ^ A' - 1
c. Biaya Pasti Per Jam:
1) Biaya Pengembalian (B' - C) x D E 42,134.07 Rupiah
W'
213

1 2 3 4 5 6

2) Asuransi, dll = 0,002 x B' F 446.30 Rupiah


W'
Biaya Pasti Per Jam = (E + F) G 42,580.37 Rupiah

3. BIAYA OPERASI & PEMELIHARAAN (DIRECT OPERATIONAL & MAINTENANCE COST) PER JAM KERJA
a. Bahan Baka(0,125-0,175 Ltr/HP/Jam) x Pw x Ms H 59,925.00 Rupiah
b. Pelumas = (0,01-0,02 Ltr/HP/Jam) x Pw x Mp I 34,931.81 Rupiah
c. Perawatan (12,5%-17,5%) x B' K 27,893.57 Rupiah
Perb W'
d. Operator = (1 Orang / Jam) x U1 L 26,813.00 Rupiah
e. Pembantu Operator = (1 Orang / Jam) x U2 M 19,500.00 Rupiah
Biaya Operasi Per Ja (H + I + K + L + M) P 169,063.38 Rupiah

4. TOTAL BIAYA SEWA ALAT / JAM = (G + P) S 211,643.76 Rupiah

C ASPHALT SPRAYER E03


1. URAIAN PERALATAN
a. Tenaga Pw 15 HP
b. Kapasitas Cp 800 Liter
c. Alat Baru: 1) Umur Ekonomis A 5 Tahun
2) Jam Kerja dalam 1 Tahun W 2,000 Jam
3) Harga Alat B 146,326,950 Rupiah
d. Alat yang D1) Umur Ekonomis A' 5 Tahun Alat baru
2) Jam Kerja dalam 1 Tahun W' 2,000 Jam Alat baru
3) Harga Alat B' 146,326,950 Rupiah Alat baru

2. BIAYA PASTI (INITIAL COST / CAPITAL COST) PER JAM KERJA


a. Nilai Sisa Alat = 10% x B C 14,632,695 Rupiah
b. Faktor Angsuran Modal i x (1 + i) ^ A' D 0.24389
(1 + i) ^ A' - 1
c. Biaya Pasti Per Jam:
1) Biaya Pengembalian (B' - C) x D E 16,059.50 Rupiah
W'
2) Asuransi, dll = 0,002 x B' F 146.33 Rupiah
W'
Biaya Pasti Per Jam = (E + F) G 16,205.83 Rupiah

3. BIAYA OPERASI & PEMELIHARAAN (DIRECT OPERATIONAL & MAINTENANCE COST) PER JAM KERJA
a. Bahan Baka(0,125-0,175 Ltr/HP/Jam) x Pw x Ms H 19,125.00 Rupiah
b. Pelumas = (0,01-0,02 Ltr/HP/Jam) x Pw x Mp I 11,148.45 Rupiah
c. Perawatan (12,5%-17,5%) x B' K 9,145.43 Rupiah
Perb W'
d. Operator = (1 Orang / Jam) x U1 L 26,813.00 Rupiah
e. Pembantu Operator = (1 Orang / Jam) x U2 M 19,500.00 Rupiah
Biaya Operasi Per Ja (H + I + K + L + M) P 85,731.88 Rupiah

4. TOTAL BIAYA SEWA ALAT / JAM = (G + P) S 101,937.72 Rupiah

D BULLDOZER 140 HP E04


1. URAIAN PERALATAN
a. Tenaga Pw 140 HP
b. Kapasitas Cp - -
c. Alat Baru: 1) Umur Ekonomis A 5 Tahun
214

1 2 3 4 5 6

2) Jam Kerja dalam 1 Tahun W 2,000 Jam


3) Harga Alat B 1,309,393,937 Rupiah
d. Alat yang D1) Umur Ekonomis A' 5 Tahun Alat baru
2) Jam Kerja dalam 1 Tahun W' 2,000 Jam Alat baru
3) Harga Alat B' 1,309,393,937 Rupiah Alat baru

2. BIAYA PASTI (INITIAL COST / CAPITAL COST) PER JAM KERJA


a. Nilai Sisa Alat = 10% x B C 130,939,394 Rupiah
b. Faktor Angsuran Modal i x (1 + i) ^ A' D 0.24389
(1 + i) ^ A' - 1
c. Biaya Pasti Per Jam:
1) Biaya Pengembalian (B' - C) x D E 143,707.05 Rupiah
W'
2) Asuransi, dll = 0,002 x B' F 1,309.39 Rupiah
W'
Biaya Pasti Per Jam = (E + F) G 145,016.44 Rupiah

3. BIAYA OPERASI & PEMELIHARAAN (DIRECT OPERATIONAL & MAINTENANCE COST) PER JAM KERJA
a. Bahan Baka(0,125-0,175 Ltr/HP/Jam) x Pw x Ms H 178,500.00 Rupiah
b. Pelumas = (0,01-0,02 Ltr/HP/Jam) x Pw x Mp I 104,052.20 Rupiah
c. Perawatan (12,5%-17,5%) x B' K 81,837.12 Rupiah
Perb W'
d. Operator = (1 Orang / Jam) x U1 L 26,813.00 Rupiah
e. Pembantu Operator = (1 Orang / Jam) x U2 M 19,500.00 Rupiah
Biaya Operasi Per Ja (H + I + K + L + M) P 410,702.32 Rupiah

4. TOTAL BIAYA SEWA ALAT / JAM = (G + P) S 555,718.77 Rupiah

E AIR COMPRESSOR E05


1. URAIAN PERALATAN
a. Tenaga Pw 80 HP
b. Kapasitas Cp - -
c. Alat Baru: 1) Umur Ekonomis A 5 Tahun
2) Jam Kerja dalam 1 Tahun W 2,000 Jam
3) Harga Alat B 95,112,517 Rupiah
d. Alat yang D1) Umur Ekonomis A' 5 Tahun Alat baru
2) Jam Kerja dalam 1 Tahun W' 2,000 Jam Alat baru
3) Harga Alat B' 95,112,517 Rupiah Alat baru

2. BIAYA PASTI (INITIAL COST / CAPITAL COST) PER JAM KERJA


a. Nilai Sisa Alat = 10% x B C 9,511,252 Rupiah
b. Faktor Angsuran Modal i x (1 + i) ^ A' D 0.24389
(1 + i) ^ A' - 1
c. Biaya Pasti Per Jam:
1) Biaya Pengembalian (B' - C) x D E 10,438.68 Rupiah
W'
2) Asuransi, dll = 0,002 x B' F 95.11 Rupiah
W'
Biaya Pasti Per Jam = (E + F) G 10,533.79 Rupiah

3. BIAYA OPERASI & PEMELIHARAAN (DIRECT OPERATIONAL & MAINTENANCE COST) PER JAM KERJA
a. Bahan Baka(0,125-0,175 Ltr/HP/Jam) x Pw x Ms H 102,000.00 Rupiah
b. Pelumas = (0,01-0,02 Ltr/HP/Jam) x Pw x Mp I 59,458.40 Rupiah
c. Perawatan (12,5%-17,5%) x B' K 5,944.53 Rupiah
215

1 2 3 4 5 6

Perb W'
d. Operator = (1 Orang / Jam) x U1 L 26,813.00 Rupiah
e. Pembantu Operator = (1 Orang / Jam) x U2 M 19,500.00 Rupiah
Biaya Operasi Per Ja (H + I + K + L + M) P 213,715.93 Rupiah

4. TOTAL BIAYA SEWA ALAT / JAM = (G + P) S 224,249.73 Rupiah

F CONCRETE MIXER 0,3-0,6 M3 E06


1. URAIAN PERALATAN
a. Tenaga Pw 6 HP
b. Kapasitas Cp 350 Liter
c. Alat Baru: 1) Umur Ekonomis A 4 Tahun
2) Jam Kerja dalam 1 Tahun W 2,000 Jam
3) Harga Alat B 10,919,094 Rupiah
d. Alat yang D1) Umur Ekonomis A' 4 Tahun Alat baru
2) Jam Kerja dalam 1 Tahun W' 2,000 Jam Alat baru
3) Harga Alat B' 10,919,094 Rupiah Alat baru

2. BIAYA PASTI (INITIAL COST / CAPITAL COST) PER JAM KERJA


a. Nilai Sisa Alat = 10% x B C 1,091,909 Rupiah
b. Faktor Angsuran Modal i x (1 + i) ^ A' D 0.29523
(1 + i) ^ A' - 1
c. Biaya Pasti Per Jam:
1) Biaya Pengembalian (B' - C) x D E 1,450.63 Rupiah
W'
2) Asuransi, dll = 0,002 x B' F 10.92 Rupiah
W'
Biaya Pasti Per Jam = (E + F) G 1,461.55 Rupiah

3. BIAYA OPERASI & PEMELIHARAAN (DIRECT OPERATIONAL & MAINTENANCE COST) PER JAM KERJA
a. Bahan Baka(0,125-0,175 Ltr/HP/Jam) x Pw x Ms H 7,012.50 Rupiah
b. Pelumas = (0,01-0,02 Ltr/HP/Jam) x Pw x Mp I 4,087.77 Rupiah
c. Perawatan (12,5%-17,5%) x B' K 682.44 Rupiah
Perb W'
d. Operator = (1 Orang / Jam) x U1 L 26,813.00 Rupiah
e. Pembantu Operator = (1 Orang / Jam) x U2 M 19,500.00 Rupiah
Biaya Operasi Per Ja (H + I + K + L + M) P 58,095.71 Rupiah

4. TOTAL BIAYA SEWA ALAT / JAM = (G + P) S 59,557.26 Rupiah

G DUMP TRUCK 3-4 M³ / 6 TON E08


1. URAIAN PERALATAN
a. Tenaga Pw 100 HP
b. Kapasitas Cp 6 Ton
c. Alat Baru: 1) Umur Ekonomis A 6 Tahun
2) Jam Kerja dalam 1 Tahun W 2,000 Jam
3) Harga Alat B 315,532,125 Rupiah
d. Alat yang D1) Umur Ekonomis A' 6 Tahun Alat baru
2) Jam Kerja dalam 1 Tahun W' 2,000 Jam Alat baru
3) Harga Alat B' 315,532,125 Rupiah Alat baru

2. BIAYA PASTI (INITIAL COST / CAPITAL COST) PER JAM KERJA


a. Nilai Sisa Alat = 10% x B C 31,553,213 Rupiah
216

1 2 3 4 5 6

b. Faktor Angsuran Modal i x (1 + i) ^ A' D 0.20980


(1 + i) ^ A' - 1
c. Biaya Pasti Per Jam:
1) Biaya Pengembalian (B' - C) x D E 29,788.79 Rupiah
W'
2) Asuransi, dll = 0,002 x B' F 315.53 Rupiah
W'
Biaya Pasti Per Jam = (E + F) G 30,104.32 Rupiah

3. BIAYA OPERASI & PEMELIHARAAN (DIRECT OPERATIONAL & MAINTENANCE COST) PER JAM KERJA
a. Bahan Baka(0,125-0,175 Ltr/HP/Jam) x Pw x Ms H 127,500.00 Rupiah
b. Pelumas = (0,01-0,02 Ltr/HP/Jam) x Pw x Mp I 74,323.00 Rupiah
c. Perawatan (12,5%-17,5%) x B' K 19,720.76 Rupiah
Perb W'
d. Operator = (1 Orang / Jam) x U1 L 26,813.00 Rupiah
e. Pembantu Operator = (1 Orang / Jam) x U2 M 19,500.00 Rupiah
Biaya Operasi Per Ja (H + I + K + L + M) P 267,856.76 Rupiah

4. TOTAL BIAYA SEWA ALAT / JAM = (G + P) S 297,961.09 Rupiah

H DUMP TRUCK 8 TON E09


1. URAIAN PERALATAN
a. Tenaga Pw 125 HP
b. Kapasitas Cp 8 Ton
c. Alat Baru: 1) Umur Ekonomis A 5 Tahun
2) Jam Kerja dalam 1 Tahun W 2,000 Jam
3) Harga Alat B 365,817,375 Rupiah
d. Alat yang D1) Umur Ekonomis A' 5 Tahun Alat baru
2) Jam Kerja dalam 1 Tahun W' 2,000 Jam Alat baru
3) Harga Alat B' 365,817,375 Rupiah Alat baru

2. BIAYA PASTI (INITIAL COST / CAPITAL COST) PER JAM KERJA


a. Nilai Sisa Alat = 10% x B C 36,581,738 Rupiah
b. Faktor Angsuran Modal i x (1 + i) ^ A' D 0.24389
(1 + i) ^ A' - 1
c. Biaya Pasti Per Jam:
1) Biaya Pengembalian (B' - C) x D E 40,148.75 Rupiah
W'
2) Asuransi, dll = 0,002 x B' F 365.82 Rupiah
W'
Biaya Pasti Per Jam = (E + F) G 40,514.57 Rupiah

3. BIAYA OPERASI & PEMELIHARAAN (DIRECT OPERATIONAL & MAINTENANCE COST) PER JAM KERJA
a. Bahan Baka(0,125-0,175 Ltr/HP/Jam) x Pw x Ms H 159,375.00 Rupiah
b. Pelumas = (0,01-0,02 Ltr/HP/Jam) x Pw x Mp I 92,903.75 Rupiah
c. Perawatan (12,5%-17,5%) x B' K 22,863.59 Rupiah
Perb W'
d. Operator = (1 Orang / Jam) x U1 L 26,813.00 Rupiah
e. Pembantu Operator = (1 Orang / Jam) x U2 M 19,500.00 Rupiah
Biaya Operasi Per Ja (H + I + K + L + M) P 321,455.34 Rupiah

4. TOTAL BIAYA SEWA ALAT / JAM = (G + P) S 361,969.91 Rupiah

I EXCAVATOR 150 HP Kobelco SK200 E10


217

1 2 3 4 5 6

1. URAIAN PERALATAN
a. Tenaga Pw 150 HP
b. Kapasitas Cp 0.9 M3
c. Alat Baru: 1) Umur Ekonomis A 6 Tahun
2) Jam Kerja dalam 1 Tahun W 2,000 Jam
3) Harga Alat B 1,009,655,955 Rupiah
d. Alat yang D1) Umur Ekonomis A' 6 Tahun Alat baru
2) Jam Kerja dalam 1 Tahun W' 2,000 Jam Alat baru
3) Harga Alat B' 1,009,655,955 Rupiah Alat baru

2. BIAYA PASTI (INITIAL COST / CAPITAL COST) PER JAM KERJA


a. Nilai Sisa Alat = 10% x B C 100,965,596 Rupiah
b. Faktor Angsuran Modal i x (1 + i) ^ A' D 0.20980
(1 + i) ^ A' - 1
c. Biaya Pasti Per Jam:
1) Biaya Pengembalian (B' - C) x D E 95,319.71 Rupiah
W'
2) Asuransi, dll = 0,002 x B' F 1,009.66 Rupiah
W'
Biaya Pasti Per Jam = (E + F) G 96,329.37 Rupiah

3. BIAYA OPERASI & PEMELIHARAAN (DIRECT OPERATIONAL & MAINTENANCE COST) PER JAM KERJA
a. Bahan Baka(0,125-0,175 Ltr/HP/Jam) x Pw x Ms H 191,250.00 Rupiah
b. Pelumas = (0,01-0,02 Ltr/HP/Jam) x Pw x Mp I 111,484.50 Rupiah
c. Perawatan (12,5%-17,5%) x B' K 63,103.50 Rupiah
Perb W'
d. Operator = (1 Orang / Jam) x U1 L 26,813.00 Rupiah
e. Pembantu Operator = (1 Orang / Jam) x U2 M 19,500.00 Rupiah
Biaya Operasi Per Ja (H + I + K + L + M) P 412,151.00 Rupiah

4. TOTAL BIAYA SEWA ALAT / JAM = (G + P) S 508,480.37 Rupiah

J GENERATOR SET 125 KVA E12


1. URAIAN PERALATAN
a. Tenaga Pw 175 HP
b. Kapasitas Cp 125 KVA
c. Alat Baru: 1) Umur Ekonomis A 5 Tahun
2) Jam Kerja dalam 1 Tahun W 2,000 Jam
3) Harga Alat B 170,508,511 Rupiah
d. Alat yang D1) Umur Ekonomis A' 5 Tahun Alat baru
2) Jam Kerja dalam 1 Tahun W' 2,000 Jam Alat baru
3) Harga Alat B' 170,508,511 Rupiah Alat baru

2. BIAYA PASTI (INITIAL COST / CAPITAL COST) PER JAM KERJA


a. Nilai Sisa Alat = 10% x B C 17,050,851 Rupiah
b. Faktor Angsuran Modal i x (1 + i) ^ A' D 0.24389
(1 + i) ^ A' - 1
c. Biaya Pasti Per Jam:
1) Biaya Pengembalian (B' - C) x D E 18,713.45 Rupiah
W'
2) Asuransi, dll = 0,002 x B' F 170.51 Rupiah
218

1 2 3 4 5 6

W'
Biaya Pasti Per Jam = (E + F) G 18,883.96 Rupiah

3. BIAYA OPERASI & PEMELIHARAAN (DIRECT OPERATIONAL & MAINTENANCE COST) PER JAM KERJA
a. Bahan Baka(0,125-0,175 Ltr/HP/Jam) x Pw x Ms H 223,125.00 Rupiah
b. Pelumas = (0,01-0,02 Ltr/HP/Jam) x Pw x Mp I 130,065.25 Rupiah
c. Perawatan (12,5%-17,5%) x B' K 10,656.78 Rupiah
Perb W'

d. Operator = (1 Orang / Jam) x U1 L 26,813.00 Rupiah


e. Pembantu Operator = (1 Orang / Jam) x U2 M 19,500.00 Rupiah
Biaya Operasi Per Ja (H + I + K + L + M) P 410,160.03 Rupiah

4. TOTAL BIAYA SEWA ALAT / JAM = (G + P) S 429,043.99 Rupiah

K GENERATOR SET 2 KVA E12.a


1. URAIAN PERALATAN
a. Tenaga Pw 4 HP
b. Kapasitas Cp 2 KVA
c. Alat Baru: 1) Umur Ekonomis A 4 Tahun
2) Jam Kerja dalam 1 Tahun W 1,000 Jam
3) Harga Alat B 7,870,616 Rupiah
d. Alat yang D1) Umur Ekonomis A' 4 Tahun Alat baru
2) Jam Kerja dalam 1 Tahun W' 1,000 Jam Alat baru
3) Harga Alat B' 7,870,616 Rupiah Alat baru

2. BIAYA PASTI (INITIAL COST / CAPITAL COST) PER JAM KERJA


a. Nilai Sisa Alat = 10% x B C 787,062 Rupiah
b. Faktor Angsuran Modal i x (1 + i) ^ A' D 0.29523
(1 + i) ^ A' - 1 `
c. Biaya Pasti Per Jam:
1) Biaya Pengembalian (B' - C) x D E 2,091.26 Rupiah
W'
2) Asuransi, dll = 0,002 x B' F 15.74 Rupiah
W'
Biaya Pasti Per Jam = (E + F) G 2,107.01 Rupiah

3. BIAYA OPERASI & PEMELIHARAAN (DIRECT OPERATIONAL & MAINTENANCE COST) PER JAM KERJA
a. Bahan Baka(0,125-0,175 Ltr/HP/Jam) x Pw x Ms H 5,100.00 Rupiah
b. Pelumas = (0,01-0,02 Ltr/HP/Jam) x Pw x Mp I 2,972.92 Rupiah
c. Perawatan (12,5%-17,5%) x B' K 983.83 Rupiah
Perb W'
d. Operator = (1 Orang / Jam) x U1 L 26,813.00 Rupiah
e. Pembantu Operator = (1 Orang / Jam) x U2 M 19,500.00 Rupiah
Biaya Operasi Per Ja (H + I + K + L + M) P 55,369.75 Rupiah

4. TOTAL BIAYA SEWA ALAT / JAM = (G + P) S 57,476.76 Rupiah

L MOTOR GRADER 125 HP E13


1. URAIAN PERALATAN
a. Tenaga Pw 125 HP
b. Kapasitas Cp - -
c. Alat Baru: 1) Umur Ekonomis A 5 Tahun
2) Jam Kerja dalam 1 Tahun W 2,000 Jam
219

1 2 3 4 5 6

3) Harga Alat B 731,634,750 Rupiah


d. Alat yang D1) Umur Ekonomis A' 5 Tahun Alat baru
2) Jam Kerja dalam 1 Tahun W' 2,000 Jam Alat baru
3) Harga Alat B' 731,634,750 Rupiah Alat baru

2. BIAYA PASTI (INITIAL COST / CAPITAL COST) PER JAM KERJA


a. Nilai Sisa Alat = 10% x B C 73,163,475 Rupiah
b. Faktor Angsuran Modal i x (1 + i) ^ A' D 0.24389
(1 + i) ^ A' - 1
c. Biaya Pasti Per Jam:
1) Biaya Pengembalian (B' - C) x D E 80,297.51 Rupiah
W'
2) Asuransi, dll = 0,002 x B' F 731.63 Rupiah
W'
Biaya Pasti Per Jam = (E + F) G 81,029.14 Rupiah

3. BIAYA OPERASI & PEMELIHARAAN (DIRECT OPERATIONAL & MAINTENANCE COST) PER JAM KERJA
a. Bahan Baka(0,125-0,175 Ltr/HP/Jam) x Pw x Ms H 159,375.00 Rupiah
b. Pelumas = (0,01-0,02 Ltr/HP/Jam) x Pw x Mp I 92,903.75 Rupiah
c. Perawatan (12,5%-17,5%) x B' K 45,727.17 Rupiah
Perb W'
d. Operator = (1 Orang / Jam) x U1 L 26,813.00 Rupiah
e. Pembantu Operator = (1 Orang / Jam) x U2 M 19,500.00 Rupiah
Biaya Operasi Per Ja (H + I + K + L + M) P 344,318.92 Rupiah

4. TOTAL BIAYA SEWA ALAT / JAM = (G + P) S 425,348.07 Rupiah

M WHEEL LOADER 1,0-1,6 M3 E15


1. URAIAN PERALATAN
a. Tenaga Pw 105 HP
b. Kapasitas Cp 1.8 M3
c. Alat Baru: 1) Umur Ekonomis A 6 Tahun
2) Jam Kerja dalam 1 Tahun W 2,000 Jam
3) Harga Alat B 792,604,312 Rupiah

d. Alat yang D1) Umur Ekonomis A' 6 Tahun Alat baru


2) Jam Kerja dalam 1 Tahun W' 2,000 Jam Alat baru
3) Harga Alat B' 792,604,312 Rupiah Alat baru

2. BIAYA PASTI (INITIAL COST / CAPITAL COST) PER JAM KERJA


a. Nilai Sisa Alat = 10% x B C 79,260,431 Rupiah
b. Faktor Angsuran Modal i x (1 + i) ^ A' D 0.20980
(1 + i) ^ A' - 1
c. Biaya Pasti Per Jam:
1) Biaya Pengembalian (B' - C) x D E 74,828.27 Rupiah
W'
2) Asuransi, dll = 0,002 x B' F 792.60 Rupiah
W'
Biaya Pasti Per Jam = (E + F) G 75,620.88 Rupiah

3. BIAYA OPERASI & PEMELIHARAAN (DIRECT OPERATIONAL & MAINTENANCE COST) PER JAM KERJA
a. Bahan Baka(0,125-0,175 Ltr/HP/Jam) x Pw x Ms H 133,875.00 Rupiah
b. Pelumas = (0,01-0,02 Ltr/HP/Jam) x Pw x Mp I 78,039.15 Rupiah
c. Perawatan (12,5%-17,5%) x B' K 49,537.77 Rupiah
Perb W'
220

1 2 3 4 5 6

d. Operator = (1 Orang / Jam) x U1 L 26,813.00 Rupiah


e. Pembantu Operator = (1 Orang / Jam) x U2 M 19,500.00 Rupiah
Biaya Operasi Per Ja (H + I + K + L + M) P 307,764.92 Rupiah

4. TOTAL BIAYA SEWA ALAT / JAM = (G + P) S 383,385.80 Rupiah

N THREE WHEEL ROLLER 8-10 TON E16


1. URAIAN PERALATAN
a. Tenaga Pw 55 HP
b. Kapasitas Cp 8 Ton
c. Alat Baru: 1) Umur Ekonomis A 6 Tahun
2) Jam Kerja dalam 1 Tahun W 2,000 Jam
3) Harga Alat B 292,653,900 Rupiah
d. Alat yang D1) Umur Ekonomis A' 6 Tahun Alat baru
2) Jam Kerja dalam 1 Tahun W' 2,000 Jam Alat baru
3) Harga Alat B' 292,653,900 Rupiah Alat baru

2. BIAYA PASTI (INITIAL COST / CAPITAL COST) PER JAM KERJA


a. Nilai Sisa Alat = 10% x B C 29,265,390 Rupiah
b. Faktor Angsuran Modal i x (1 + i) ^ A' D 0.20980
(1 + i) ^ A' - 1
c. Biaya Pasti Per Jam:
1) Biaya Pengembalian (B' - C) x D E 27,628.90 Rupiah
W'
2) Asuransi, dll = 0,002 x B' F 292.65 Rupiah
W'
Biaya Pasti Per Jam = (E + F) G 27,921.56 Rupiah

3. BIAYA OPERASI & PEMELIHARAAN (DIRECT OPERATIONAL & MAINTENANCE COST) PER JAM KERJA
a. Bahan Baka(0,125-0,175 Ltr/HP/Jam) x Pw x Ms H 70,125.00 Rupiah
b. Pelumas = (0,01-0,02 Ltr/HP/Jam) x Pw x Mp I 40,877.65 Rupiah
c. Perawatan (12,5%-17,5%) x B' K 18,290.87 Rupiah
Perb W'
d. Operator = (1 Orang / Jam) x U1 L 26,813.00 Rupiah
e. Pembantu Operator = (1 Orang / Jam) x U2 M 19,500.00 Rupiah
Biaya Operasi Per Ja (H + I + K + L + M) P 175,606.52 Rupiah

4. TOTAL BIAYA SEWA ALAT / JAM = (G + P) S 203,528.08 Rupiah

O TANDEM ROLLER 6-8 TON E17


1. URAIAN PERALATAN
a. Tenaga Pw 50 HP
b. Kapasitas Cp 8 Ton
c. Alat Baru: 1) Umur Ekonomis A 5 Tahun
2) Jam Kerja dalam 1 Tahun W 2,000 Jam
3) Harga Alat B 406,057,286 Rupiah
d. Alat yang D1) Umur Ekonomis A' 5 Tahun Alat baru
2) Jam Kerja dalam 1 Tahun W' 2,000 Jam Alat baru
3) Harga Alat B' 406,057,286 Rupiah Alat baru

2. BIAYA PASTI (INITIAL COST / CAPITAL COST) PER JAM KERJA


a. Nilai Sisa Alat = 10% x B C 40,605,729 Rupiah
b. Faktor Angsuran Modal i x (1 + i) ^ A' D 0.24389
(1 + i) ^ A' - 1
c. Biaya Pasti Per Jam:
221

1 2 3 4 5 6

1) Biaya Pengembalian (B' - C) x D E 44,565.12 Rupiah


W'
2) Asuransi, dll = 0,002 x B' F 406.06 Rupiah
W'
Biaya Pasti Per Jam = (E + F) G 44,971.17 Rupiah

3. BIAYA OPERASI & PEMELIHARAAN (DIRECT OPERATIONAL & MAINTENANCE COST) PER JAM KERJA
a. Bahan Baka(0,125-0,175 Ltr/HP/Jam) x Pw x Ms H 63,750.00 Rupiah
b. Pelumas = (0,01-0,02 Ltr/HP/Jam) x Pw x Mp I 37,161.50 Rupiah
c. Perawatan (12,5%-17,5%) x B' K 25,378.58 Rupiah
Perb W'
d. Operator = (1 Orang / Jam) x U1 L 26,813.00 Rupiah
e. Pembantu Operator = (1 Orang / Jam) x U2 M 19,500.00 Rupiah
Biaya Operasi Per Ja (H + I + K + L + M) P 172,603.08 Rupiah

4. TOTAL BIAYA SEWA ALAT / JAM = (G + P) S 217,574.26 Rupiah

P PNEUMATIC TYRE ROLLER 8-12 TON E18


1. URAIAN PERALATAN
a. Tenaga Pw 60 HP
b. Kapasitas Cp 10 Ton
c. Alat Baru: 1) Umur Ekonomis A 6 Tahun
2) Jam Kerja dalam 1 Tahun W 2,000 Jam
3) Harga Alat B 428,006,328 Rupiah
d. Alat yang D1) Umur Ekonomis A' 6 Tahun Alat baru
2) Jam Kerja dalam 1 Tahun W' 2,000 Jam Alat baru
3) Harga Alat B' 428,006,328 Rupiah Alat baru

2. BIAYA PASTI (INITIAL COST / CAPITAL COST) PER JAM KERJA


a. Nilai Sisa Alat = 10% x B C 42,800,633 Rupiah
b. Faktor Angsuran Modal i x (1 + i) ^ A' D 0.20980
(1 + i) ^ A' - 1
c. Biaya Pasti Per Jam:
1) Biaya Pengembalian (B' - C) x D E 40,407.27 Rupiah
W'
2) Asuransi, dll = 0,002 x B' F 428.01 Rupiah
W'
Biaya Pasti Per Jam = (E + F) G 40,835.27 Rupiah

3. BIAYA OPERASI & PEMELIHARAAN (DIRECT OPERATIONAL & MAINTENANCE COST) PER JAM KERJA
a. Bahan Baka(0,125-0,175 Ltr/HP/Jam) x Pw x Ms H 76,500.00 Rupiah
b. Pelumas = (0,01-0,02 Ltr/HP/Jam) x Pw x Mp I 44,593.80 Rupiah
c. Perawatan (12,5%-17,5%) x B' K 26,750.40 Rupiah
Perb W'
d. Operator = (1 Orang / Jam) x U1 L 26,813.00 Rupiah
e. Pembantu Operator = (1 Orang / Jam) x U2 M 19,500.00 Rupiah
Biaya Operasi Per Ja (H + I + K + L + M) P 194,157.20 Rupiah

4. TOTAL BIAYA SEWA ALAT / JAM = (G + P) S 234,992.48 Rupiah

Q VIBRATING ROLLER 6-8 TON E19


1. URAIAN PERALATAN
a. Tenaga Pw 75 HP
b. Kapasitas Cp 7 Ton
222

1 2 3 4 5 6

c. Alat Baru: 1) Umur Ekonomis A 6 Tahun


2) Jam Kerja dalam 1 Tahun W 2,000 Jam
3) Harga Alat B 478,001,370 Rupiah
d. Alat yang D1) Umur Ekonomis A' 6 Tahun Alat baru
2) Jam Kerja dalam 1 Tahun W' 2,000 Jam Alat baru
3) Harga Alat B' 478,001,370 Rupiah Alat baru

2. BIAYA PASTI (INITIAL COST / CAPITAL COST) PER JAM KERJA Lebar roda = 2,13 m
a. Nilai Sisa Alat = 10% x B C 47,800,137 Rupiah
b. Faktor Angsuran Modal i x (1 + i) ^ A' D 0.20980
(1 + i) ^ A' - 1
c. Biaya Pasti Per Jam:
1) Biaya Pengembalian (B' - C) x D E 45,127.21 Rupiah
W'
2) Asuransi, dll = 0,002 x B' F 478.00 Rupiah
W'
Biaya Pasti Per Jam = (E + F) G 45,605.21 Rupiah

3. BIAYA OPERASI & PEMELIHARAAN (DIRECT OPERATIONAL & MAINTENANCE COST) PER JAM KERJA
a. Bahan Baka(0,125-0,175 Ltr/HP/Jam) x Pw x Ms H 95,625.00 Rupiah
b. Pelumas = (0,01-0,02 Ltr/HP/Jam) x Pw x Mp I 55,742.25 Rupiah
c. Perawatan (12,5%-17,5%) x B' K 29,875.09 Rupiah
Perb W'
d. Operator = (1 Orang / Jam) x U1 L 26,813.00 Rupiah
e. Pembantu Operator = (1 Orang / Jam) x U2 M 19,500.00 Rupiah
Biaya Operasi Per Ja (H + I + K + L + M) P 227,555.34 Rupiah

4. TOTAL BIAYA SEWA ALAT / JAM = (G + P) S 273,160.55 Rupiah

R CONCRETE VIBRATOR E20


1. URAIAN PERALATAN
a. Tenaga Pw 5 HP
b. Kapasitas Cp - -
c. Alat Baru: 1) Umur Ekonomis A 4 Tahun
2) Jam Kerja dalam 1 Tahun W 1,000 Jam
3) Harga Alat B 5,581,790 Rupiah
d. Alat yang D1) Umur Ekonomis A' 4 Tahun Alat baru
2) Jam Kerja dalam 1 Tahun W' 1,000 Jam Alat baru
3) Harga Alat B' 5,581,790 Rupiah Alat baru

2. BIAYA PASTI (INITIAL COST / CAPITAL COST) PER JAM KERJA


a. Nilai Sisa Alat = 10% x B C 558,179 Rupiah
b. Faktor Angsuran Modal i x (1 + i) ^ A' D 0.29523
(1 + i) ^ A' - 1

c. Biaya Pasti Per Jam:


1) Biaya Pengembalian (B' - C) x D E 1,483.11 Rupiah
W'
2) Asuransi, dll = 0,002 x B' F 11.16 Rupiah
W'
Biaya Pasti Per Jam = (E + F) G 1,494.27 Rupiah

3. BIAYA OPERASI & PEMELIHARAAN (DIRECT OPERATIONAL & MAINTENANCE COST) PER JAM KERJA
a. Bahan Baka(0,125-0,175 Ltr/HP/Jam) x Pw x Ms H 6,375.00 Rupiah
b. Pelumas = (0,01-0,02 Ltr/HP/Jam) x Pw x Mp I 3,716.15 Rupiah
223

1 2 3 4 5 6

c. Perawatan (12,5%-17,5%) x B' K 697.72 Rupiah


Perb W'
d. Operator = (1 Orang / Jam) x U1 L 26,813.00 Rupiah
e. Pembantu Operator = (1 Orang / Jam) x U2 M 19,500.00 Rupiah
Biaya Operasi Per Ja (H + I + K + L + M) P 57,101.87 Rupiah

4. TOTAL BIAYA SEWA ALAT / JAM = (G + P) S 58,596.15 Rupiah

S WATER PUMP 70-100 mm E22


1. URAIAN PERALATAN
a. Tenaga Pw 8 HP
b. Kapasitas Cp - -
c. Alat Baru: 1) Umur Ekonomis A 4 Tahun
2) Jam Kerja dalam 1 Tahun W 2,000 Jam
3) Harga Alat B 11,389,593 Rupiah
d. Alat yang D1) Umur Ekonomis A' 4 Tahun Alat baru
2) Jam Kerja dalam 1 Tahun W' 2,000 Jam Alat baru
3) Harga Alat B' 11,389,593 Rupiah Alat baru

2. BIAYA PASTI (INITIAL COST / CAPITAL COST) PER JAM KERJA


a. Nilai Sisa Alat = 10% x B C 1,138,959 Rupiah
b. Faktor Angsuran Modal i x (1 + i) ^ A' D 0.29523
(1 + i) ^ A' - 1
c. Biaya Pasti Per Jam:
1) Biaya Pengembalian (B' - C) x D E 1,513.14 Rupiah
W'
2) Asuransi, dll = 0,002 x B' F 11.39 Rupiah
W'
Biaya Pasti Per Jam = (E + F) G 1,524.53 Rupiah

3. BIAYA OPERASI & PEMELIHARAAN (DIRECT OPERATIONAL & MAINTENANCE COST) PER JAM KERJA
a. Bahan Baka(0,125-0,175 Ltr/HP/Jam) x Pw x Ms H 10,200.00 Rupiah
b. Pelumas = (0,01-0,02 Ltr/HP/Jam) x Pw x Mp I 5,945.84 Rupiah
c. Perawatan (12,5%-17,5%) x B' K 711.85 Rupiah
Perb W'
d. Operator = (1 Orang / Jam) x U1 L 26,813.00 Rupiah
e. Pembantu Operator = (1 Orang / Jam) x U2 M 19,500.00 Rupiah
Biaya Operasi Per Ja (H + I + K + L + M) P 63,170.69 Rupiah

4. TOTAL BIAYA SEWA ALAT / JAM = (G + P) S 64,695.22 Rupiah


224

1 2 3 4 5 6

T WATER TANK TRUCK 3000-4500 L E23


1. URAIAN PERALATAN
a. Tenaga Pw 100 HP
b. Kapasitas Cp 4,000 Liter
c. Alat Baru: 1) Umur Ekonomis A 6 Tahun
2) Jam Kerja dalam 1 Tahun W 2,000 Jam
3) Harga Alat B 160,959,645 Rupiah
d. Alat yang D1) Umur Ekonomis A' 6 Tahun Alat baru
2) Jam Kerja dalam 1 Tahun W' 2,000 Jam Alat baru
3) Harga Alat B' 160,959,645 Rupiah Alat baru

2. BIAYA PASTI (INITIAL COST / CAPITAL COST) PER JAM KERJA


a. Nilai Sisa Alat = 10% x B C 16,095,965 Rupiah
b. Faktor Angsuran Modal i x (1 + i) ^ A' D 0.20980
(1 + i) ^ A' - 1
c. Biaya Pasti Per Jam:
1) Biaya Pengembalian (B' - C) x D E 15,195.90 Rupiah
W'
2) Asuransi, dll = 0,002 x B' F 160.96 Rupiah
W'
Biaya Pasti Per Jam = (E + F) G 15,356.86 Rupiah

3. BIAYA OPERASI & PEMELIHARAAN (DIRECT OPERATIONAL & MAINTENANCE COST) PER JAM KERJA
a. Bahan Baka(0,125-0,175 Ltr/HP/Jam) x Pw x Ms H 127,500.00 Rupiah
b. Pelumas = (0,01-0,02 Ltr/HP/Jam) x Pw x Mp I 74,323.00 Rupiah
c. Perawatan (12,5%-17,5%) x B' K 10,059.98 Rupiah
Perb W'
d. Operator = (1 Orang / Jam) x U1 L 26,813.00 Rupiah
e. Pembantu Operator = (1 Orang / Jam) x U2 M 19,500.00 Rupiah
Biaya Operasi Per Ja (H + I + K + L + M) P 258,195.98 Rupiah

4. TOTAL BIAYA SEWA ALAT / JAM = (G + P) S 273,552.84 Rupiah

U PEDESTERIAN ROLLER E24


1. URAIAN PERALATAN Istilah lain adalah baby roller, walk-behind roller
a. Tenaga Pw 11 HP
b. Kapasitas Cp 0.980 Ton
c. Alat Baru: 1) Umur Ekonomis A 6 Tahun
2) Jam Kerja dalam 1 Tahun W 2,000 Jam
3) Harga Alat B 100,672,425 Rupiah
d. Alat yang D1) Umur Ekonomis A' 6 Tahun Alat baru
2) Jam Kerja dalam 1 Tahun W' 2,000 Jam Alat baru
3) Harga Alat B' 100,672,425 Rupiah Alat baru

2. BIAYA PASTI (INITIAL COST / CAPITAL COST) PER JAM KERJA


a. Nilai Sisa Alat = 10% x B C 10,067,243 Rupiah
b. Faktor Angsuran Modal i x (1 + i) ^ A' D 0.20980
(1 + i) ^ A' - 1
c. Biaya Pasti Per Jam:
1) Biaya Pengembalian (B' - C) x D E 9,504.29 Rupiah
W'
2) Asuransi, dll = 0,002 x B' F 100.67 Rupiah
W'
Biaya Pasti Per Jam = (E + F) G 9,604.97 Rupiah
225

1 2 3 4 5 6

3. BIAYA OPERASI & PEMELIHARAAN (DIRECT OPERATIONAL & MAINTENANCE COST) PER JAM KERJA
a. Bahan Baka(0,125-0,175 Ltr/HP/Jam) x Pw x Ms H 14,025.00 Rupiah
b. Pelumas = (0,01-0,02 Ltr/HP/Jam) x Pw x Mp I 8,175.53 Rupiah
c. Perawatan (12,5%-17,5%) x B' K 6,292.03 Rupiah
Perb W'
d. Operator = (1 Orang / Jam) x U1 L 26,813.00 Rupiah
e. Pembantu Operator = (1 Orang / Jam) x U2 M 19,500.00 Rupiah
Biaya Operasi Per Ja (H + I + K + L + M) P 74,805.56 Rupiah

4. TOTAL BIAYA SEWA ALAT / JAM = (G + P) S 84,410.53 Rupiah

V TAMPER / HAND COMPACTOR E25


1. URAIAN PERALATAN Istilah lain adalah stamper, vibratory compactor, upright rammers,
a. Tenaga Pw 3.5 HP hand compactor
b. Kapasitas Cp 0.082 Ton
c. Alat Baru: 1) Umur Ekonomis A 6 Tahun
2) Jam Kerja dalam 1 Tahun W 1,000 Jam
3) Harga Alat B 11,462,062 Rupiah
d. Alat yang D1) Umur Ekonomis A' 6 Tahun Alat baru
2) Jam Kerja dalam 1 Tahun W' 1,000 Jam Alat baru
3) Harga Alat B' 11,462,062 Rupiah Alat baru

2. BIAYA PASTI (INITIAL COST / CAPITAL COST) PER JAM KERJA


a. Nilai Sisa Alat = 10% x B C 1,146,206 Rupiah
b. Faktor Angsuran Modal i x (1 + i) ^ A' D 0.20980
(1 + i) ^ A' - 1
c. Biaya Pasti Per Jam:
1) Biaya Pengembalian (B' - C) x D E 2,164.22 Rupiah Honda Gasoline Engine 4 HP or ROBIN Gasoline Engine 4 HP
W' Hit frequency:640-680/min Compact force:17kN jump height:50-60mm
2) Asuransi, dll = 0,002 x B' F 22.92 Rupiah speed:12m/min N.W.:80kgs G.W.:100kgs
W'
Biaya Pasti Per Jam = (E + F) G 2,187.15 Rupiah

3. BIAYA OPERASI & PEMELIHARAAN (DIRECT OPERATIONAL & MAINTENANCE COST) PER JAM KERJA
a. Bahan Baka(0,125-0,175 Ltr/HP/Jam) x Pw x Ms H 4,462.50 Rupiah
b. Pelumas = (0,01-0,02 Ltr/HP/Jam) x Pw x Mp I 2,601.31 Rupiah
c. Perawatan (12,5%-17,5%) x B' K 1,432.76 Rupiah
Perb W'

d. Operator = (1 Orang / Jam) x U1 L 26,813.00 Rupiah


e. Pembantu Operator = (1 Orang / Jam) x U2 M 19,500.00 Rupiah
Biaya Operasi Per Ja (H + I + K + L + M) P 54,809.56 Rupiah

4. TOTAL BIAYA SEWA ALAT / JAM = (G + P) S 56,996.72 Rupiah

W PLATE COMPACTOR E25.a


1. URAIAN PERALATAN Istilah lain adalah vibratory plate compactor, stamper kodok.
a. Tenaga Pw 5.0 HP Power: Gasoline engine ROBIN EY20/Honda copy 5.5 HP
b. Kapasitas Cp 0.090 Ton C-77 Frequency: 5600 VPM Centrifugal Force: 13.5KN
c. Alat Baru: 1) Umur Ekonomis A 6 Tahun Trav.Speed: 15~20 m/menit Plate Size: 57X43 cm NetWeight: 83 kg
2) Jam Kerja dalam 1 Tahun W 1,000 Jam
3) Harga Alat B 10,929,318 Rupiah
d. Alat yang D1) Umur Ekonomis A' 6 Tahun Alat baru
226

1 2 3 4 5 6

2) Jam Kerja dalam 1 Tahun W' 1,000 Jam Alat baru


3) Harga Alat B' 10,929,318 Rupiah Alat baru

2. BIAYA PASTI (INITIAL COST / CAPITAL COST) PER JAM KERJA


a. Nilai Sisa Alat = 10% x B C 1,092,932 Rupiah
b. Faktor Angsuran Modal i x (1 + i) ^ A' D 0.20980
(1 + i) ^ A' - 1
c. Biaya Pasti Per Jam:
1) Biaya Pengembalian (B' - C) x D E 2,063.63 Rupiah
W'
2) Asuransi, dll = 0,002 x B' F 21.86 Rupiah
W'
Biaya Pasti Per Jam = (E + F) G 2,085.49 Rupiah

3. BIAYA OPERASI & PEMELIHARAAN (DIRECT OPERATIONAL & MAINTENANCE COST) PER JAM KERJA
a. Bahan Baka(0,125-0,175 Ltr/HP/Jam) x Pw x Ms H 6,375.00 Rupiah
b. Pelumas = (0,01-0,02 Ltr/HP/Jam) x Pw x Mp I 3,716.15 Rupiah
c. Perawatan (12,5%-17,5%) x B' K 1,366.16 Rupiah
Perb W'
d. Operator = (1 Orang / Jam) x U1 L 26,813.00 Rupiah
e. Pembantu Operator = (1 Orang / Jam) x U2 M 19,500.00 Rupiah
Biaya Operasi Per Ja (H + I + K + L + M) P 57,770.31 Rupiah

4. TOTAL BIAYA SEWA ALAT / JAM = (G + P) S 59,855.81 Rupiah

Palembang, 01 September 2020


PT. MANDALA WANGI

Sahma Sukarta
Direktur Utama
227

DAFTAR HARGA SATUAN DASAR BAHAN, PERALATAN DAN UPAH TENAGA (BASIC PRICE)
WILAYAH PALEMBANG TA. 2020

RATA-RATA
NO. URAIAN SAT HARGA DASAR KET.
2020

1 2 3 4 5

I. URAIAN BAHAN
A PASIR, BATU DAN SEMEN
1. Pasir pasang m³ 178,164
2. Pasir beton m³ 178,164
3. Pasir urug m³ 120,000
4. Sirtu m³ 416,539
5. Tanah merah m³ 95,000
6. Abu batu m³ 607,639
7. Batu kali m³ 385,000
8. Batu belah 15/20 m³ 385,000
9. Batu pecah 5/7 m³ 475,000
10. Batu pecah/split 3/5 m³ 475,000
11. Batu pecah/split 2/3 m³ 475,000
12. Batu pecah/split 1/2 m³ 475,000
13. Batu pecah/split 0,5/1 m³ 475,000
14. Bata merah proses tangan bh 1,500
15. Bata merah bh 660 proses mesin
16. Batako bh 2,800
17. Hebel uk.60x20x10 bh 12,500
18. Hollow block HB. 20 bh 5,250
19. Hollow block HB. 15 bh 3,950
20. Hollow block HB. 10 bh 2,600
21. Roster keramik 30 x 30 x 7 bh 57,500
22. Roster bata merah 12 x 24 x 10 bh 14,818
23. Glass block 20 x 20 x 10 bh 19,500
24. Paving abu-abu segi enam, tebal 8 cm m² 40,100 ex.Internusa type Veta 8 abu
25. Paving abu-abu segi enam, tebal 6 cm m² 33,750 ex.Internusa type Veta 8 abu
26. Paving merah/hitam segi enam, tebal 8 cm m² 225,700 ex.Internusa type Veta 8 warna
27. Grassblock m² 96,400 ex.Internusa
28. Kanstin abu-abu 15 x 25 x 40 bh 55,000 ex.Internusa
29. Kanstin abu-abu saluran 15 x 30 x 40 bh 29,518 ex.Internusa
30. Batu palimanan/andesit m² 165,000
31. Batu paras m² 185,000 Batu paras jogja
228

RATA-RATA
NO. URAIAN SAT HARGA DASAR KET.
2020

1 2 3 4 5

32. Batu tempel m² 145,000 Batu acak Purwakarta


33. Semen portland kg 1,300 Tiga Roda
34. Semen putih Tiga Roda kg 1,300
35. Semen warna kg 2,375
36. Koral beton m³ 435,000
37. Perekat PM-100 (perekat) kg 3,750 Perekat Hebel
38. Perekat PM-200 (plesteran) kg 3,950 Plesteran
39. Perekat PM-300 (acian) kg 3,950 Acian
B BAHAN KAYU
1. Kayu Jati balok m³ 21,537,300
2. Kayu Jati balok kelas II m³ 20,497,350
3. Kayu Ulin balok m³ 6,556,200
4. Kayu Merbau balok m³ 9,290,600
5. Kayu Kamper Samarinda Oven balok m³ 6,564,650
6. Kayu Kamper Samarinda balok m³ 5,564,714
7. Kayu Kamper Singkil balok m³ 5,564,714
8. Kayu Borneo balok m³ 4,500,000
9. Kayu Kamper Medan/Kruing balok m³ 4,500,000
10. Kayu Meranti Palembang balok m³ 4,500,000
11. Kayu Meranti Jambi balok m³ 4,500,000
12. Kayu Meranti Sampit balok m³ 4,500,000
13. Kayu Terentang balok m³ 2,826,516
14. Kayu Kamper Samarinda kaso m³ 5,564,714
15. Kayu Kamper Singkil kaso m³ 5,564,714
16. Kayu Borneo kaso m³ 4,500,000
17. Kayu Kamper Medan/Kruing kaso m³ 5,564,714
18. Kayu Meranti Palembang kaso m³ 4,500,000
19. Kayu Meranti Jambi kaso m³ 4,500,000
20. Kayu Meranti Sampit kaso m³ 4,500,000
21. Kayu Terentang kaso m³ 2,826,516
22. Kayu Kamper Samarinda reng m³ 5,564,714
23. Kayu Kamper Singkil reng m³ 5,564,714
24. Kayu Borneo reng m³ 4,500,000
25. Kayu Kamper Medan/Kruing reng m³ 5,564,714
26. Kayu Meranti Palembang reng m³ 4,500,000
27. Kayu Meranti Jambi reng m³ 4,500,000
28. Kayu Meranti Sampit reng m³ 2,906,000
29. Kayu Jati papan m³ 25,338,000
30. Kayu Jati papan kelas II m³ 20,265,100
31. Kayu Ulin papan m³ 6,556,200
32. Kayu Merbau papan m³ 9,638,950
33. Kayu Kamper Samarinda oven papan m³ 5,564,714
34. Kayu Kamper Samarinda papan m³ 4,500,000
35. Kayu Bengkirai papan m³ 5,564,714
36. Kayu Nyatoh papan m³ 5,564,714
37. Kayu Sungkai papan m³ 5,564,714
229

RATA-RATA
NO. URAIAN SAT HARGA DASAR KET.
2020

1 2 3 4 5

38. Kayu Kamper Singkil papan m³ 5,564,714


39. Kayu Kamper Medan/Kruing papan m³ 4,500,000
40. Kayu Meranti Palembang papan m³ 4,500,000
41. Kayu Meranti Jambi papan m³ 4,500,000
42. Kayu Meranti Sampit papan m³ 4,500,000
43. Kayu Borneo papan 3 cm m³ 2,826,516
44. Kayu Terentang papan 3 cm m³ 2,826,516
45. Kayu dolken Ø 8-10/400 cm btg 11,878
46. Kayu dolken Ø 5-7/400 cm btg 8,114
47. Kayu list profil m' 22,226
48. Bambu panjang 400 cm btg 14,950
C KAYU LAPIS DAN LEMBARAN
1. Teakwood 3x7 ft 3 mm Lbr 108,074
2. Teakwood 4x8 ft 3 mm Lbr 120,983
3. Triplek 4x8 ft 4 mm Lbr 65,000
4. Triplek 4x8 ft 6 mm Lbr 80,000
5. Triplek 4x8 ft 9 mm Lbr 110,000
6. Triplek 3x7 ft 12 mm Lbr 257,500
7. Triplek 4x8 ft 12 mm Lbr 245,100
8. Formika 3x7 ft Lbr 121,650 0.03 mm
9. Formika 4x8 ft Lbr 144,850 0.03 mm
10. Plat asbes 100x100 cm 2,7 mm Lbr 23,100 Flat Harflex
11. Plat asbes 100x100 cm 4 mm Lbr 18,450 Jabesmen
12. Gypsumboard 120x240 cm 9 mm Lbr 75,000 Jayaboard
13. Gypsumboard 120x240 cm 12 mm Lbr 78,300 Jayaboard
14. GRC-board 120x240 cm 4 mm Lbr 68,000
15. GRC-board 120x240 cm 6 mm Lbr 70,000
16. Calsiboard 120x240 cm 4 mm Lbr 60,000
17. Calsiboard 6.0x1220x2440 cm 6 mm Lbr 69,000
18. Kalsiplank 8-jati 8.0x300x30000 Lbr 53,150
19. Akustik 60 x 60 cm Lbr 30,600 Armstrong
20. Akustik 60 x 120 cm Lbr 60,750 Armstrong
21. Hollow 4x4 cm tbl 0.35 mm btg 29,000 0.35 mm
22. Hollow 2x4 cm tbl 0.35 mm btg 22,500 0.35 mm
23. Hollow 4x4 cm tbl 0.5 mm btg 28,500 0.5 mm
24. Hollow 2x4 cm tbl 0.5 mm btg 23,200 0.5 mm
25. Hollow 4x4 cm tbl 0.6 mm btg 46,350 0.6 mm
26. Hollow 2x4 cm tbl 0.6 mm btg 36,050 0.6 mm
27. Metal wall stud 35mm x 40mm m' 15,900 Jayaboard
28. Metal wall track 30mm x 40mm m' 14,350 Jayaboard
29. Profil alumunium "T" (akustik) m' 10,600
30. Profil Allumunium Kusen m' 120,000 3" x 1 1/2" YKK
31. Profil Allumunium Kusen m' 150,000 4" x 1 3/4" YKK
32. Profil Allumunium Rangka Natural m' 100,000
33. Profil Allumunium Rangka Warna m' 100,000
34. List profil cornice gypsum lebar sampai 5 cm m' 8,400
230

RATA-RATA
NO. URAIAN SAT HARGA DASAR KET.
2020

1 2 3 4 5

35. List profil cornice gypsum lebar 5-10 cm m' 10,950


36. List profil cornice gypsum lebih dari 10 cm m' 14,250
37. Paku peluru ramset bh 1,700
38. Paku rivet btg 50
39. Sekrup 6x1-1,5 bh 100
40. Sekrup gypsum bh 130
41. Skrup fixer bh 750
42. Sealant tube 36,950
43. Compound gypsum 20kg/zak 108,000 Jayaboard
44. Compound GRC 20kg/zak 81,250
45. Textile tape 50m/rol 8,400
46. Alkasit kg 15,800
D BAHAN BESI -
1. Besi beton polos kg 12,000
2. Besi beton ulir kg 19,000
3. Kawat beton kg 20,000 10kg/rol
4. Kawat diameter 4 mm kg 9,100
5. Kawat duri (10kg/60m/rol) kg 8,350
6. Kawat harmonika Ø 2 mm spasi 40x40 mm m² 14,750
7. Kawat nyamuk m² 17,900 alumunium
8. Kawat Las listrik kg 19,600 Nikko Steel
9. Kawat kasa (parabola) m² 18,450
10. Besi pelat strip kg 16,111
11. Besi segi empat 3/8"x3/8" (0,83kg/m') kg 7,100
12. Besi profil kg 12,350
13. Besi baja WF kg 14,300
14. Besi Siku kg 10,650
15. Baja Canal kg 9,500
16. Baja CNP kg 12,073
17. Besi Plat baja kg 8,750
18. Besi rangka kg 8,200
19. Plat Bordes kg 10,250
20. Pintu besi baja m² 1,425,250
21. Jendela besi m² 2,159,000
22. Besi wermest dia. 8 mm m² 60,000
23. Baja truss C 75.75.5 m' 15,333
24. Reng U 50 m' 7,833
25. Screw/dynabolt bh 500
26. Breaket Siku/spigot/stifner btg 60,000
27. Paku skrup beton kg 21,600
28. Paku Sekrup kg 21,600
29. Allumunium Composite panel m² 420,500
30. Kawat besi expeded m² 118,403

E BAHAN KERAMIK DAN PENUTUP LAIN


1. Ubin pc abu-abu 40 x 40 bh -
231

RATA-RATA
NO. URAIAN SAT HARGA DASAR KET.
2020

1 2 3 4 5

2. Ubin pc abu-abu 30 x 30 bh -
3. Ubin pc abu-abu 20 x 20 bh -
4. Ubin pc warna 40 x 40 bh -
5. Ubin pc warna 30 x 30 bh -
6. Ubin pc warna 20 x 20 bh -
7. Plint ubin pc 10 x 40 bh -
8. Plint ubin pc 10 x 30 bh -
9. Plint ubin pc 15 x 20 bh -
10. Plint ubin pc warna 10 x 40 bh -
11. Plint ubin pc warna 10 x 30 bh -
12. Plint ubin pc warna 10 x 20 bh -
1. Marmer m² 131,667 ex. Bandung uk.20x20x2
2. Plint ubin marmer 10 x 60 bh 17,150
3. Plint ubin marmer 10 x 40 bh 6,233
4. Plint ubin marmer 10 x 30 bh 3,410
5. Granito tile 40x40 cm bh 40,833 Granito Castello
6. Granito tile 60x60 cm bh 81,667
7. Plint granito tile 10x40 cm bh 22,226 Granito Castello
8. Granito tile 30x30 cm bh 37,044 Granito Castello
9. Plint granito tile 10x30 cm bh 4,351
10. Ubin keramik 40 x 40 cm Roman bh 19,500 ex.Roman
11. Ubin keramik 30 x 30 cm Roman bh 9,182
12. Ubin keramik 20 x 20 cm Roman bh 4,400
13. Ubin keramik 20 x 25 cm Roman bh 5,880
14. Ubin keramik 5 x 20 cm Roman bh 1,500
15. Ubin keramik 20 x 60 cm Roman bh 10,344
16. Ubin keramik 20 x 40 cm Roman bh 6,896
17. Ubin keramik 25 x 40 cm KIA bh 8,620
18. Ubin keramik 40 x 40 cm setara mulia bh 12,348 ex.Mulia / Ikad
19. Ubin keramik 30 x 30 cm setara mulia bh 5,292 ex.Mulia type polos / Ikad
20. Ubin keramik 20 x 20 cm setara mulia bh 3,410
21. Ubin keramik 20 x 25 cm setara mulia bh 4,351 ex.Mulia type Postel opera, warna / Ikad
22. Ubin keramik 25 x 25 cm setara KIA bh 5,388 ex.Mulia type Postel opera, warna / Ikad
23. Ubin keramik 5 x 20 cm setara mulia bh 862
24. Plint keramik 10x40 cm bh 6,233 ex.Roman
25. Plint keramik 10x30 cm bh 3,410
26. Plint keramik 10x20 cm bh 2,587 ex.Masterina
27. Stepnosing bh 10,500 ex.Roman
28. Vinyl karet 30 x 30 cm kl 1 bh 5,250 Maxwell
29. Vinyl karet 30 x 30 cm kl 2 bh 4,500
30. Parquet m² 229,050
31. Floor Hardener PM-700 kg 5,000
F BAHAN PENUTUP ATAP
1. Seng gelombang 3x6 ft BJLS 20 (0,2 mm) Lbr 198,744
2. Seng gelombang 3x6 ft BJLS 25 (0,25 mm) Lbr 169,579
3. Seng gelomb.Galvanish 3x6 ft (0,30 mm) Lbr 134,417
232

RATA-RATA
NO. URAIAN SAT HARGA DASAR KET.
2020

1 2 3 4 5

4. Seng gelomb.Zincalume 3x6 ft (0,30 mm) Lbr 145,000 ex.Cahaya Benteng Mas
5. Seng plat 3x6 ft BJLS 20 (0,2 mm) m' 25,284
6. Seng plat 3x6 ft BJLS 25 (0,25 mm) m' 44,570
7. Seng plat 3x6 ft BJLS 28 (0,28 mm) m' 41,630
8. Genteng plentong kecil natural bh 1,800 tidak Glazzur
9. Genteng plentong super/besar bh 3,600 Glazzur
10. Genteng morando natural bh 4,351 tidak Glazzur
11. Genteng morando glazzur bh 4,850 Glazzur
12. Genteng kodok natural bh 3,000 tidak Glazzur
13. Genteng kodok glazzur bh 3,650 Glazzur
14. Genteng keramik Kanmuri natural bh 6,115 ex.Kanmuri Espanica Natural
15. Genteng keramik M Class bh 14,347
16. Genteng beton Monier standar bh 7,997 Monier Albana type warna standar
17. Genteng metal m² 74,980 Multi Roof
18. Spandek m² 77,000
19. Atap Fibreglass m² 17,400
20. Atap Allumunium SWG 28 tebal 0,38 m² 58,050
21. Nok genteng plentong kecil natural bh 4,116
22. Nok genteng plentong super/besar bh 4,500
23. Nok genteng morando natural bh 7,174
24. Nok genteng kodok natural bh 4,116
25. Nok genteng keramik Kanmuri natural bh 10,231 ex.Kanmuri type Espanica
26. Nok genteng keramik M Class bh 55,625
27. Nok genteng beton Monier standar bh 10,114 Albana
28. Nok genteng metal m' 35,000 Multi Roof
29. Nok asbes bh 26,350
30. Genteng sirap bh 179,450 Multi Sirap
31. Asbes gelombang 2,5x,92 m 5 mm Lbr 63,450 Jabesmen
32. Asbes gelombang 2,25x,92 m 5 mm Lbr 68,250
33. Asbes gelombang 2,00x,92 m 5 mm Lbr 49,000
34. Asbes gelombang 1,80x,92 m 5 mm Lbr 48,200
35. Nok stel gelombang Lbr 36,250
36. Flashing m' 25,284
37. Nok spandek standar m' 65,000
38. Nok paten Lbr 57,000 Zinclume 0.35 mm
39. Nok stel rata Lbr 60,750
40. Allumunium foil m² 12,500 standar 1 sided
41. Plastik Cor m² 4,500 standar 1 sided
42. Armafoil NZO HF 405 single sided m2 5,000 1250mm x 60 m
43. Armafoil NZO HF 425 double sided m2 8,250 1250mm x 60 m
44. Armafoil Moistop 737 concrete underlay m2 26,350 90 m2
45. Glasswool BG 50 m2 20,850 (20x1.2x0.05)m ex.malaysia
46. Glasswool IB 3250 m2 48,350 (10x1.2x0.025)m ex.malaysia
47. Glasswool IPB 4825 m2 112,800 (2.3x1.2x0.025)m ex.malaysia
48. Policarbonat m2 253,350
G BAHAN CAT KAYU DAN TEMBOK
233

RATA-RATA
NO. URAIAN SAT HARGA DASAR KET.
2020

1 2 3 4 5

1. Dempul kayu kg 16,699


2. Dempul Duco kg 34,750 Sanpolac
3. Plamir kayu kg 40,870
4. Plamir tembok kg 13,289 Matex
5. Wall sealer jotashield primer kg 62,050
6. Wall sealer jotashiel kg 61,800
6. Cat meni kayu kg 21,991 Nippon / Bango
7. Cat meni besi kg 14,200 Nippon
8. Cat zinchromate kg 50,100 Jotun / Kansai
9. Cat kayu/besi KW 2 (cat dasar) kg 37,162 Glotex
10. Cat kayu/besi KW 2 (cat penutup) kg 50,450 Glotex
11. Cat kayu/besi Mowilex (cat dasar) kg 65,600
12. Cat kayu/besi Mowilex (cat penutup) kg 65,600
13. Cat kayu/besi Glotex kg 56,650
14. Cat tembok KW 2 (cat dasar) kg 37,162 Kanggaro
15. Cat tembok KW 2 (cat penutup) kg 29,350 Kanggaro
16. Cat tembok Metrolite kg 27,250
17. Cat tembok Super Vinilex/ Decolith kg 23,873
18. Cat tembok Catylac (cat dasar) kg 28,000
19. Cat tembok Catylac (cat penutup) kg 28,000
20. Cat tembok Dulux/ICI (cat dasar) kg 48,000
21. Cat tembok Dulux/ICI (cat penutup) kg 48,000
22. Cat tembok jotun jotaplast (cat dasar) kg 89,100
23. Cat tembok jotun jotaplast (cat penurtup) kg 95,000
24. Cat tembok jotun jotashileld kg 89,100
25. Cat tembok Mowiliex kg 65,600
26. Cat Duco Nippe 2000 kg 42,750 Nippe 2000
27. Cat genteng KW 2 kg 35,633 Matex
28. Cat genteng Dulux/ICI kg 37,500
29. Minyak cat/ thinner Ltr 25,284
30. Thinner (High Class) Ltr 32,500
31. Politur Ltr 81,732
32. Politur jadi Ltr 82,500
33. Politur Ultran kg 43,000 P-01
34. Wood filler Ultran kg 51,979
35. Sanding Sealer Impra kg 160,450
36. Cat warna Ultran kg 41,700
37. Melamic Impra kg 29,000
38. Vernis Ltr 81,732 Ultran
39. Residu Ltr 18,581
40. Minyak bekisting Ltr 8,820
41. Amplas Lbr 5,880 Niken
42. Kuas bh 14,818 4"
43. Bak cat bh 15,500 4"
44. Kuas Roll bh 25,000
45. Ijuk m³ 95,000
234

RATA-RATA
NO. URAIAN SAT HARGA DASAR KET.
2020

1 2 3 4 5

46. Ijuk ikatan kg 26,350


47. Lem kayu Ltr 34,800 Fox
48. Lem Vinyl kg 28,700 Fox
49. Lem perekat kg 28,700 Fox
50. Cumoir Waterproofing Coating kg 34,300
51. Waterproofing sika kg 140,000
52. Material primer kg 21,100
53. Aquaproof Waterproofing kg 41,550
54. Wallpaper m2 90,000 Kingston
H PAKU -
1. Paku biasa 2"-5" kg 19,286
2. Paku biasa 1/2"- 1" kg 19,286
3. Paku sekrup 3,5" bh 450
4. Paku sekrup kg 48,569
5. Paku beton kg 21,000
6. Paku asbes bh 75
7. Paku seng kg 37,162
8. Baut dia 12 mm - 1" bh 10,500
9. angkur pengikat atap bh 27,000
I BAHAN PIPA -
1. Pipa galvanis dia 1/2" m' 26,754
2. Pipa galvanis dia 3/4" m' 29,753
3. Pipa galvanis dia 1" m' 38,279
4. Pipa galvanis dia 1 ¼" m' 47,375
5. Pipa galvanis dia 1 ½" m' 55,037
6. Pipa galvanis dia 2" m' 75,382
7. Pipa galvanis hitam dia 2" untuk pagar m' 51,979
8. Pipa galvanis dia 2 ½" m' 98,343
9. Pipa galvanis dia 3" m' 260,249
10. Pipa galvanis dia 4" m' 275,000
11. Pipa PVC dia 1/2" AW m' 5,174
12. Pipa PVC dia 3/4" AW m' 10,466
13. Pipa PVC dia 1" AW m' 21,403
14. Pipa PVC dia 1 ¼" AW m' 28,224
15. Pipa PVC dia 1 ¼" D m' 27,500
16. Pipa PVC dia 1 ½" AW m' 32,222
17. Pipa PVC dia 1 ½" D m' 32,000
18. Pipa PVC dia 2" AW m' 39,043
19. Pipa PVC dia 2" D m' 38,000
20. Pipa PVC dia 2 ½" AW m' 53,038
21. Pipa PVC dia 2 ½" D m' 52,000
22. Pipa PVC dia 3" AW m' 60,682
23. Pipa PVC dia 3" D m' 60,000
24. Pipa PVC dia 4" AW m' 79,733
25. Pipa PVC dia 4" D m' 77,500
26. Pipa PVC dia 6" AW m' 87,500
235

RATA-RATA
NO. URAIAN SAT HARGA DASAR KET.
2020

1 2 3 4 5

27. Pipa PVC dia 6" D m' 85,000


26. Buis beton dia 100 panj. 50 cm bh 409,013 Tanpa tulangan
27. Buis beton dia 80 panj. 50 cm bh 334,690
28. Buis beton dia 60 panj. 100 cm bh 334,690
29. Buis beton dia 50 panj. 100 cm bh 250,000
30. Buis beton dia 40 panj. 100 cm bh 187,500
31. Buis beton dia 30 panj. 100 cm bh 133,829
32. Buis beton dia 20 panj. 100 cm bh 96,667
33. Buis beton 1/2 dia 60 panj. 100 cm bh 167,345
34. Buis beton 1/2 dia 50 panj. 100 cm bh 125,000
35. Buis beton 1/2 dia 40 panj. 100 cm bh 93,750
36. Buis beton 1/2 dia 30 panj. 100 cm bh 66,915
37. Buis beton 1/2 dia 20 panj. 100 cm bh 48,334
38. Saluran air beton dusaspun 40/40 cm m 292,050
39. Saluran air beton dusaspun 30/20 cm m 168,000
40. Doop PVC 1 " bh 950
J BAHAN KACA ASAHIMAS
1. Jendela nako (rangka) daun 23,580
2. Kaca nako polos 5 mm daun 20,580
3. Kaca 3 mm m² 182,515
4. Kaca 5 mm m² 269,069
5. Kaca 8 mm m² 275,000
6. Kaca rayben 5 mm m² 297,528
7. Kaca rayben 8 mm m² 286,591
8. Kaca rayben 10 mm m² 580,100
9. Kaca rayben 12 mm m² 1,114,300
10. Kaca es 3 mm m² 65,450
11. Kaca es 5 mm m² 139,050
12. Kaca Tempered polos 5 mm m² 229,050
13. Kaca Tempered polos 8 mm m² 405,400
14. Kaca Tempered polos 10 mm m² 625,350
15. Kaca cermin tebal 5 mm m² 163,800
16. Kaca patri tebal 5 mm m² 950,150
K BAHAN SANITASI
1. Kloset duduk ex KIA (LUX) bh 3,149,328
2. Kloset duduk setara TOTO (LUX) bh 2,520,050
3. Kloset duduk Toto lengkap (sederhana) bh 1,750,000 Toto CW 420 J
4. Kloset duduk Toto + eco washer lengkap (tidak sederha bh 11,865,600 Toto CW 420 J
5. Kloset duduk Toto lengkap (sedang) bh 9,115,500 Toto CW 420 J
4. Kloset jongkok sederhana bh 267,893 Alindo
5. Kloset jongkok sedang bh 824,376 Toto CE 7
6. Kloset jongkok Toto bh 706,541 Toto CE 6
7. Urinoir muslim Toto lengkap bh 3,091,469 Toto U 57
8. Penyekat Urinoir Toto lengkap bh 335,866 Toto A 100
9. Wastafel Toto lengkap bh 1,078,510 Toto LW 521 V1A
10. Bak fibreglass 0.3 m³ bh 1,169,179 TIG
236

RATA-RATA
NO. URAIAN SAT HARGA DASAR KET.
2020

1 2 3 4 5

11. Bak cuci stainless steel bh 824,376 1 lubang


12. Water drain + asesoris set 631,394
13. Bak penampung drum 200 ltr bh 236,200
14. Kran air lokal (sederhana) bh 25,284 INA
15. Kran air stainless Toto bh 51,509 Toto T 23 B13V7N
16. Kran tembok kepala besi Toto bh 188,250 Toto T 23 B13
17. Kran air leher angsa stainless bh 275,000
18. Kran bebek Toto bh 288,200 Toto T 30 AR 13V7N
19. Hand Shower Toto bh 319,750 Toto TX 402 S
20. Shower Dinding Toto bh 786,500 Toto TB 18 R / TX 422 SC
21. Stop Kran Toto T4A bh 122,657 Toto T4A
22. Seal tape bh 14,300
23. Floor drain sederhana bh 45,000
24. Floor drain stainless Toto bh 329,600 Toto TX 1 Bn
25. Tempat sabun Toto bh 180,250 Toto S 156 N
26. Bak reservoir fibreglass 1000 L bh 1,493,500 Penguin
27. Shower tiang (km/wc utama) JB bh 5,407,500
` 28. Shower tiang (km/wc anak + tamu) bh 3,399,000
29. Box shower kaca (km/wc utama) Icepool bh 3,939,500
30. Wastafel kaca + cermin + kran lengkap (km/wc utama) bh 15,398,500
31. Wastafel kaca + cermin + kran lengkap (km/wc anak + t bh 2,549,250
32. Shower tiang (km/wc utama) GBV bh 4,635,000
L BAHAN KUNCI DAN ALAT PENGGANTUNG
1. Kunci tanam sederhana bh 107,839 Binoche
2. Kunci tanam biasa bh 162,053 Belluci
3. Kunci tanam antik bh 270,245 CISA 52120
4. Kunci tanam KM bh 85,000 Cylinder DKS 60mm BK-SN
5. Kunci silinder pintu aluminium bh 112,245 Cylinder DKS 60mm TC-SN
6. Kunci lemari bh 79,800 Cylinder DKS 60mm DC-PB
7. Kunci gembok bh 53,050
8. Engsel pintu biasa/sederhana bh 13,289 3 x 4"
9. Engsel pintu kuningan/stainless 4" bh 31,950 ES BRASS
10. Engsel jendela kuningan/stainless 3" bh 23,750 ES BRASS
11. Engsel pintu nylon bh 21,400 3 x 4"
12. Engsel jendela bh 25,200 Stainless ES-S/S 3x2,5" PN
13. Engsel angin bh 21,100
14. Spring knip DB018BR-SN bh 25,000 DB018 BR
15. Kait angin kuningan bh 21,756 10-20 cm
16. Hak angin DK SS/S8"-SS bh 58,300 DK SS/SB-SS
17. Window Casement bh 79,700 20"
18. Rambuncis bh 43,000
19. Door closer DKS HO-NA/BA bh 262,600 DKS HO-NA/BA
20. Door closer Kend bh 491,950
21. Door closer Cisa bh 393,607 Cisa 60410-02
22. Kunci selot bh 91,846
23. Grendel bh 28,106 RRT
237

RATA-RATA
NO. URAIAN SAT HARGA DASAR KET.
2020

1 2 3 4 5

24. Roll door m² 316,700


25. Pintu aluminium m² 100,250
26. Door holder bh 48,550
27. Door stop Kend 015 GP bh 28,500
28. Door stop DKS 887 bh 39,550 DKS 887
29. Rel pintu dorong bh 140,750
M BAHAN INSTALASI LISTRIK
1. Kabel NYM 3x4 mm² m' 14,500 Eterna
2. Kabel NYM 3x2,5 mm² m' 9,800
3. Kabel NYM 2x2,5 mm² m' 9,707
4. Kabel NYM 2x1,5 mm² m' 6,301
5. Kabel antena TV m' 6,300
6. Kabel telepon m' 3,650
7. Kabel BC 10 mm m' 11,600
8. Kabel BC 50 mm m' 35,850
9. MCB box isi 4 bh 40,000
10. MCB 10 A bh 113,249
11. MCB 6 A bh 105,000
12. Kotak kontak khusus (KKK) bh 125,000
13. Conduit pipa PVC dia ⅝" C m' 9,500
14. Tee dos bh 3,100
15. Inbow doos bh 2,000
16. Sock bh 2,000
17. Klem conduit bh 2,000
18. Klem pipa besi 3/4" bh 1,550
19. Lastdop bh 3,000
20. Flexible pipe m' 1,500
21. Elbow bh 2,000
22. Saklar tunggal Broco bh 30,000 Lokal
23. Saklar tunggal Vimar bh 25,000 Italia
24. Saklar tunggal MK bh 35,850 England
25. Saklar seri Broco bh 45,900 Lokal
26. Saklar seri Vimar bh 42,200 Italia
27. Saklar seri MK bh 51,450 England
28. Saklar triple Broco bh 55,000 Italia
29. Saklar triple Vimar bh 48,550 Italia
30. Saklar triple National bh 58,050 Jepang
31. Saklar triple MK bh 86,950 England
32. Stop kontak Broco bh 45,000
33. Stop kontak Vimar bh 17,650
34. Stop kontak MK bh 32,500
35. Stop kontak AC bh 75,500 Panasonic
36. Lampu TKI 1x18 watt bh 52,750 Philips
37. Lampu TKI 2x18 watt bh 68,600 Philips
38. Lampu PLC 8 watt bh 16,850 Philips
39. Lampu SL 20 watt bh 41,700 Philips
238

RATA-RATA
NO. URAIAN SAT HARGA DASAR KET.
2020

1 2 3 4 5

40. Lampu TL 1x18 watt RM bh 213,444 Philips


41. Lampu TL 2x18 watt RM bh 426,888 Philips
42. Lampu TL 2x36 watt RM bh 500,000 Philips
43. Lampu TL 1x18 watt Balk bh 55,000 Philips
44. Lampu TL 2x18 watt Balk bh 110,000 Philips
45. Lampu TL 2x36 watt Balk bh 205,850 Philips
46. Lampu Baret 11 watt bh 75,500 IDB 181 Cylinder Arcylic PL 11 watt
47. Lampu pijar 25 watt bh 9,290 Philips
48. Lampu LED bh 346,567 IDGL 197 Stendo Essential 18w
49. Exhaust Fan bh 343,100 Maspion
50. Panel listrik 3Phase 31.200 watt - 41.800 watt bh 17,500,000 Maspion
51. Kabel BC 35 mm m' 100,000 Maspion
52. Jarum penangkap (tembaga) unit 500,000 Maspion
53. Klem Penyangga Kabel BC Bh 15,000 Maspion
54. Tembaga dia.1/2"-1.5m btg 850,000 Maspion
55. Panel Genset ATS AMF 33 KVA 3phase DSE 4520 With unit 25,000,000 Maspion
56. Cable Try Type U 200 x 50 x 3000 nn HotDip 2mm unit 450,000 Maspion
57. Ventilator Cyclone 45 cm unit 1,100,000

N LAIN-LAIN
1. Panel beton pracetak 50x400x2130 Lbr 125,000 ex.Hollywood
2. Kolom beton pracetak 170x180x3200 btg 270,000
3. Kolom beton pracetak 160x200x2750 btg 190,450
4. Pintu lipat m² 824,376
5. Pagar BRC tinggi 1,2 m' m' 381,100
6. Pagar BRC tinggi 0,9 m' m' 109,500
7. Tiang pagar BRC tinggi 1,2 m' bh 114,550
8. Tiang pagar BRC tinggi 0,9 m' bh 89,950
9. Bensin Ltr 6,500
10. Solar Ltr 10,200
11. Minyak tanah Ltr 17,758
12. Pelumas Ltr 74,323
13. Aspal Pertamina drum kg 21,500
14. Aspal Alam Asbuton kg 23,100
15. Aspal Polimer Lokal kg 23,500
16. Aspal Emulsi (Teac Coat) kg 22,315 CRS-1
17. Aspal Emulsi (Prime Coat) kg 22,315 CSS-2
18. Aspal Tack Coating Emulsi 2 kg m² 44,630
19. Hotmix ton 1,350,000
20. Filler untuk hotmix (semen) kg 2,380
21. Pompa air listrik 250 W unit 1,500,000 Pompa Semi Deep
22. Ready Mix K225 slump 12 m³ 730,000
23. Ready Mix K250 slump 12 m³ 760,000
24. Ready Mix K275 slump 12 m³ 790,000
25. Ready Mix K300 slump 12 m³ 800,000
26. Ready Mix K350 slump 12 m³ 830,000
239

RATA-RATA
NO. URAIAN SAT HARGA DASAR KET.
2020

1 2 3 4 5

27. Ready Mix K400 slump 12 m³ 860,000


28. Geotekstil non woven m² 13,750
29. U- dit 200x200x120 unit 6,258,000
30. Superdek BMT 0.70 mm m² 159,500
O AlAT BANTU
1. Sewa Scafolding m2 33,000 1 SET
2. Blencong bh 55,500
3. Ember Aduk bh 5,500
4. Mesin Bor unit 1,045,500
5. Mesin Gurinda unit 690,000 Bosch (GWS8-100CE)
6. Pacul Aduk bh 52,500
7. Pahat Besi bh 25,000
8. Pengki bh 12,500
9. Sekop bh 53,500
10. Sendok semen bh 17,500
11. Travo Las unit 1,795,000 NLG (MMA-160)
12. Mata gerinda bh 35,500
13. Mata bor bh 25,000
14. Material Bantu lot 384,375
P TAMBAHAN
1. Ongkos angkut truk kap. 6 m3 jarak s/d 20 km m3 513,236
2. Cetak foto pada kertas lbr 5,500
3. CD / Flesdics bh 75,000
4. Jilid bh 25,000
5. Gebalan rumput m2 70,000
II. HARGA PERALATAN BARU (sebagai dasar perhitungan sewa alat)
1. ASPHALT MIXING PLANT (AMP) unit 2,074,469,568
2. ASPHALT FINISHER unit 446,297,197
3. ASPHALT SPRAYER unit 146,326,950
4. BULLDOZER 140 HP unit 1,309,393,937
5. AIR COMPRESSOR unit 95,112,517
6. CONCRETE MIXER 0,3-0,6 M3 unit 10,919,094
7. DUMP TRUCK 3-4 M³ / 6 TON unit 315,532,125
8. DUMP TRUCK 8 TON unit 365,817,375
9. EXCAVATOR 150 HP Kobelco SK200 unit 1,009,655,955
10. GENERATOR SET 125 KVA unit 170,508,511
11. GENERATOR SET 2 KVA unit 7,870,616
12. MOTOR GRADER 125 HP unit 731,634,750
13. WHEEL LOADER 1,0-1,6 M3 unit 792,604,312
14. THREE WHEEL ROLLER 8-10 TON unit 292,653,900
15. TANDEM ROLLER 6-8 TON unit 406,057,286
16. PNEUMATIC TYRE ROLLER 8-12 TON unit 428,006,328
17. VIBRATING ROLLER 6-8 TON unit 478,001,370
18. CONCRETE VIBRATOR unit 5,581,790
19. WATER PUMP 70-100 mm unit 11,389,593
20. WATER TANK TRUCK 3000-4500 L unit 160,959,645
240

RATA-RATA
NO. URAIAN SAT HARGA DASAR KET.
2020

1 2 3 4 5

21. PEDESTERIAN ROLLER unit 100,672,425


22. TAMPER / HAND COMPACTOR unit 11,462,062
23. PLATE COMPACTOR unit 10,929,318
III. SEWA ALAT BESAR SESUAI BUKU PATOKAN HARGA SATUAN BAHAN & UPAH DKI
1. Asphalt Finisher jam 922,500
2. Asphalt Sprayer 800 liter jam 358,750
3. Bulldozer D7G Caterpilar jam 71,750
4. Compresor Mer Inggresot jam 410,000
5. Mesin pemadat beton Concrete Vibrator jam 64,062
6. Dump Truck Hino, 1993 jam 179,375
7. Excavator Hitachi Ex 200,1990 jam 358,750
8. Generator 125 Kva + BBM & Pelumas jam 261,375
9. Grader Mitsubishi Md 330,1994 jam 230,625
10. Wheel Loader Lx 150 Hitachi 1990 jam 205,000
11. Wheel Loader Lx 150 Hitachi 1990 unit 973,750 Mob Demob
12. Tower Crane (daya angkut 1,5 s/d 7.5 ton) bln 30,750,000
13. Tower Crane (daya angkut 5 s/d 40 ton) bln 41,000,000
14. Tire Roller 8-10 ton jam 563,750
15. Vibrator Roller Ingersol Ran Sp 54 10 ton jam 179,375
16. Stamper/ Compactor Cartepilar jam 973,750
17. Gondola Standar bln 512,500 200x65x100 cm
18. Gondola diluar standar bln 7,687,500 600x65x100 cm
19. Sewa Pompa Beton s/d lt 4 m3 79,349
20. Sewa Pompa Beton lt 5 s/d lt 8 m3 110,000
21. Sewa Alat ukur ( theodolite) m² 5,000
22. Sewa mesin bor jam 300,000
IV. PEKERJAAN LAPISAN HOTMIX LENGKAP PEMADATAN & QUALITY CONTROL
1. Hotmix 97-100% 2,3 ton/m3 tebal 3 cm m² 178,164
2. Hotmix 97-100% 2,3 ton/m3 tebal 5 cm m² 178,164
V. PEKERJAAN TIANG PANCANG JHS (TERPASANG)
A TIANG PANCANG PERSEGI EMPAT JHS (TERPASANG)
1. Ukuran 25x25 cm² panjang s/d 12 m' m' 189,625
2. Ukuran 25x25 cm² panjang 13 s/d 14 m' m' 200,900
3. Ukuran 30x30 cm² panjang s/d 12 m' m' 242,900
4. Ukuran 30x30 cm² panjang 13 s/d 14 m' m' 264,450
5. Ukuran 30x30 cm² panjang 15 s/d 16 m' m' 277,775
6. Ukuran 30x30 cm² panjang 17 s/d 18 m' m' 297,250
B TIANG PANCANG SEGITIGA JHS (TERPASANG)
1. Ukuran 20x20 cm² panjang 3 s/d 6 m' m' 120,950
2. Ukuran 28x28 cm² panjang 3 s/d 6 m' m' 172,200
3. Ukuran 32x32 cm² panjang 3 s/d 6 m' m' 230,625
C PENYAMBUNGAN SEPATU TIANG (JOINT SYSTEM)
1. Ukuran 25x25 cm² set 728,775
2. Ukuran 30x30 cm² set 889,700
D LAS PENYAMBUNGAN TIANG (PER TIANG SAMBUNGAN)
1. Ukuran 25x25 cm² sbg 100,962
241

RATA-RATA
NO. URAIAN SAT HARGA DASAR KET.
2020

1 2 3 4 5

2. Ukuran 30x30 cm² sbg 100,962


E MOB DEMOB TIANG PANCANG (LOKASI sumatera selatan)
1. Termasuk peralatan Crane pancang dan
Sewa Crawler crane jam 350,000
VI. UPAH TENAGA
1. Pekerja Oh 140,000
2. Tukang gali Oh 160,000
3. Tukang kayu Oh 160,000
4. Tukang batu Oh 160,000
5. Tukang besi Oh 160,000
6. Tukang besi konstruksi Oh 160,000
7. Kepala tukang Oh 180,000
8. Tukang las Oh 160,000
9. Tukang cat Oh 160,000
10. Tukang cat Melamic Oh 160,000
11. Kepala tukang cat Melamic Oh 180,000
12. Tukang pasang pipa Oh 180,000
13. Tukang aspal Oh 180,000
14. Tukang gypsum Oh 180,000
15. Tukang alumunium Oh 180,000
16. Instalator Oh 180,000
17. Operator alat berat Oh 165,000
18. Pembantu operator alat berat Oh 120,000
19. Mandor Oh 185,000
20. Operator Genset Oh 110,000

Keterangan:
1. Data harga bahan dan upah diperoleh dari survei pasar, Journal Harga Bahan dan Harga Satuan Bahan & Upah Pemda.
2. Data yang diperoleh dari survei pasar dimasukkan dalam kolom 6 s/d 11.
3. Data yang diperoleh dari Journal Harga Bahan dimasukkan dalam kolom 5.
4. Harga-harga dari kolom 5 s/d 11 tersebut diambil nilai rata-ratanya dan dimasukkan dalam kolom 4.
Nilai harga dalam kolom 4 ini yang dipakai sebagai pedoman.
5. Singkatan:
m' = meter panjang/lari
m² = meter persegi
m³ = meter kubik
dia. = diameter
btg = batang
Ltr = liter
kg = kilogram
bh = buah
Lbr = lembar
zak = karung
Oh = orang hari
BJLS = Baja Lembaran Lapis Seng
242

RATA-RATA
NO. URAIAN SAT HARGA DASAR KET.
2020

1 2 3 4 5

Palembang, 01 September 2020


PT. MANDALA WANGI

Sahma Sukarta
Direktur Utama
HARGA SAT JUMLAH
NO PEKERJAAN VOL SAT
Rp. Rp.
1 2 3 4 5 6
I PEKERJAAN PENDAHULUAN
1 Perencanaan dan pengawasan 1,860.00 m2 150,000.00 279,000,000.00
2 Pek. Zondir 4.00 ttk 7,500,000.00 30,000,000.00
309,000,000.00
II PEK. BANGUNAN LT. I
A PEKERJAAN TANAH
1. Pasang bouwplank 206.00 m1 95,450.00 19,662,700.00
2. Galian tanah pondasi 2,827.22 m3 120,550.00 340,821,371.00
3. Galian pondasi rolag 50.06 m3 120,550.00 6,034,467.79
4. Galian tanah file cap PC.I 9.68 m3 147,750.00 1,430,220.00
5. Galian tanah file cap PC.II 5.88 m3 147,750.00 868,770.00
6. Urugan tanah kembali 954.64 m3 40,150.00 38,328,654.43
7. Urugan pasir urug bawah lantai 10 cm 133.40 m3 206,600.00 27,560,026.80
8. Urugan tanah ke dalam bangunan 30 cm 611.82 m3 173,600.00 106,211,952.00
9. Pemadatan tanah bawah lantai 2,039.40 m3 3,600.00 7,341,840.00
548,260,002.02
B PEKERJAAN PASANGAN PONDASI
1. Pas. Pondasi Batu kali/belah Camp. 1pc : 4ps 173.49 m3 1,236,300.00 214,483,832.55
2. Pas. Pondasi rolag 4 lapis 118.48 m1 156,100.00 18,494,728.00
232,978,560.55
C PEKERJAAN BETON STRUKTUR
1. Pek. Lantai kerja dibawah lantai 101.97 m3 1,187,550.00 121,094,473.50
2. Pek. Lantai Kerja di bawah pile cap 10.76 m3 1,187,550.00 12,773,287.80
3. Pek. Pondasi tiang pancang Uk.∆ 30x30X30 cm kedalaman 6 m' 300.00 m1 485,750.00 145,725,000.00
4. Pek. Pondasi pile cap PC.I 33.79 m3 7,489,550.00 253,086,873.60
5. Pek. Pondasi pile cap PC.II 1.30 m 3
7,489,550.00 9,706,456.80
6. Membuat kolom pedestal beton bertulang (40x40) 7.04 m3 8,942,700.00 62,956,608.00
7. Membuat kolom pedestal beton bertulang (35x35) 0.74 m3 8,942,700.00 6,572,884.50
8. Membuat sloof beton 20x40 cm 44.64 m3 6,172,227.89 275,528,253.01
9. Membuat sloof beton 15x20 cm 32.52 m3 6,172,227.89 200,720,850.98
10. Membuat kolom beton bertulang (12 x 12) 0.78 m3 7,500,600.00 5,832,466.56
11. Membuat kolom beton bertulang (12 x 30) 5.88 m 3
8,942,700.00 52,549,809.16
12. Pas. Besi wermest Ø 8 mm untuk lantai beton 1 lapis 2,039.40 m2 102,280.18 208,590,199.09
13. Membuat lantai beton tebal 10 cm K - 225 203.94 m3 1,509,500.00 307,847,430.00
14. Membuat dak beton bertulang tebal 12 cm 3.36 m3 6,117,500.00 20,554,800.00
15. Membuat ring balok beton bertulang (12 x15) 0.34 m3 5,179,550.00 1,771,406.10

2.
1 2 3 4 5 6
16. Membuat balok latai 0.19 m3 5,179,550.00 964,639.39
17. Membuat pelat meja wastafel beton bertulang tebal 8 0.07 m3 3,644,350.00 244,900.32
1,633,970,529.66
D PEKERJAAN PASANGAN
1. Pas. Dinding 1/2 bata 1,344.14 m2 142,300.00 191,271,691.20
2. Pek. Plesteran 2,688.29 m2 92,200.00 247,860,153.60
3. Pek. Acian 2,688.29 m2 57,050.00 153,366,830.40
592,498,675.20
E PEKERJAAN KONSTRUKSI BAJA + EREKSEN
1. Pek. Kolom baja
a IWF 350 17,587.35 kg 37,500.00 659,525,805.00
g IWF 350 1,395.20 kg 37,500.00 52,320,150.00
711,845,955.00
2. Rafter
a IWF 300 13,177.43 kg 37,500.00 494,153,572.50
494,153,572.50
3. Ring & Floor Beam
a IWF 300 13,872.60 kg 37,500.00 520,222,500.00
520,222,500.00
4. Bracing
a Rod Dia.19 1,370.15 kg 37,500.00 51,380,568.00
b Sagrod Dia.12 845.23 kg 37,500.00 31,696,272.00
83,076,840.00
5. Gording dan Clading
a Gording CNP150.65.20.2,3 9,350.00 kg 34,155.00 319,349,250.00
b Clading besi plat 12 mm 446.76 kg 34,155.00 15,259,087.80
334,608,337.80
6. Sambungan Baja
a Base Plate 732.41 Kg 37,200.00 27,245,466.00
b Cap Plate 1,526.04 Kg 37,200.00 56,768,688.00
c End Plate 5,294.98 Kg 37,200.00 196,973,330.40
d Pelat Stiffener 760.19 Kg 37,200.00 28,279,216.80
e Mur & Baut M19 4,400.00 bh 12,075.00 53,130,000.00
f Mur & Baut M22 440.00 bh 20,700.00 9,108,000.00
g Angkur M22 Type A325 440.00 bh 80,500.00 35,420,000.00
406,924,701.20
F PEKERJAAN KUSEN DAN DAUN PINTU/JENDELA KAYU
1. Pas. kusen besi canal C 125.50.20.3,2 189.42 Kg 34,155.00 6,469,640.10
2. Pas. Pintu panel oven 7.20 M² 870,800.00 6,269,760.00
3. Pas. Pintu kaca tb 10 mm , rangka allumunium 10.40 M² 1,247,700.00 12,976,080.00
4. Pas. BV KM/WC, rangka allumunium 1.12 M² 836,150.00 936,488.00
5. Pasang kusen pintu jendela allumunium 426.50 M' 174,650.00 74,488,225.00
6. Pasang jendela kaca, rangka allumunium 304.05 M² 836,150.00 254,227,226.75
7. Pas. Pintu rolng door 65.19 M² 769,350.00 50,153,926.50
8. Pasang pintu aluminium KM/WC 4.20 M² 836,150.00 3,511,830.00
409,033,176.35
G PEKERJAAN KONSTRUKSI LANGIT-LANGIT/PLAFON
1. Pasang list cornice gypsum lebar sampai 5-10 cm 48.00 M' 45,300.00 2,174,400.00
2. Penutup plafon Gypsumboard 9 mm dgn rangka hollow tebal 0.6 mm 72.00 M² 189,450.00 13,640,400.00
15,814,800.00
H PEKERJAAN PENUTUP ATAP
1. Pasang teras + kolom ACP rangka besi hollow 1031.05 M² 838,600.00 864,638,530.00
2. Pasang listplank ACP rangka besi hollow 59.70 M² 838,600.00 50,064,420.00
3. Pasang atap Spandek 0.30 mm 1990.00 M² 233,900.00 465,461,000.00
4. Pasang nok Spandek 50.00 M' 118,050.00 5,902,500.00

3.
1 2 3 4 5 6
5. Pasang talang datar 200.00 M' 229,350.00 45,870,000.00
6. Pasang ornamen besi hollow di atas dak 189.14 M² 603,700.00 114,180,799.50
7. Pasang pipa galvanis penguat atap ACP Ø 4' 25.30 M' 561,200.00 14,198,360.00
8. Pasang talang PVC Ø 4" 180.00 M' 180,800.00 32,544,000.00
1,592,859,609.50
I PEKERJAAN SANITASI
1. Memasang kloset duduk 6.00 Bh 3,540,055.00 21,240,330.00
2. Memasang pipa PVC tipe AW dia 1/2" 40.00 M' 28,150.00 1,126,000.00
3. Memasang pipa PVC tipe AW dia 3/4" 120.00 M' 37,600.00 4,512,000.00
4. Memasang pipa PVC tipe AW dia 3" 36.00 M' 149,600.00 5,385,600.00
5. Memasang pipa PVC tipe AW dia 4" 36.00 M' 180,800.00 6,508,800.00
6. Memasang jet washer 6.00 Bh 81,350.00 488,100.00
7. Memasang floor drain stainless 6.00 Bh 71,600.00 429,600.00
8. Membuat tanki septik kapasitas (vol. 4,5 m³) 2.00 Bh 10,748,700.00 21,497,400.00
9. Membuat resapan Ø 0,8 m (digali 1 m) 2.00 Bh 1,601,200.00 3,202,400.00
10. Membuat saluran air buis beton ½ Ø 20 cm 202.00 M' 176,100.00 35,572,200.00
11. Pas bak kontrol 45x45 + tutup 6.00 Bh 625,300.00 3,751,800.00
103,714,230.00
J PEKERJAAN KUNCI DAN KACA
1. Pasang kunci silinder allumunium 13.00 Bh 213,250.00 2,772,250.00
2. Pasang engsel pintu kuningan/stainless 39.00 Bh 66,950.00 2,611,050.00
3. Pasang pegangan pintu/door holder 15.00 Bh 159,500.00 2,392,500.00
4. Pasang grendel pintu 15.00 Bh 84,600.00 1,269,000.00
9,044,800.00
K PEKERJAAN PENUTUP LANTAI DAN DINDING
1. Pasang Granit lantai + tangga ukuran 60 x 60 cm 590.00 M² 295,451.68 174,316,490.02
2. Pasang lantai Km/Wc Granit lantai + tangga ukuran 60 x 60 cm 36.00 M² 295,451.68 10,636,260.41
3. Pasang dinding Km/Wc 30 x 60 cm 196.75 M² 295,451.68 58,130,117.65
4. Pasang Granit warna hitam pintu masuk 10.80 M² 418,350.00 4,518,180.00
247,601,048.07
L PEKERJAAN PENGECATAN
1. Pengecatan tembok baru 2688.29 M² 53,150.00 142,882,507.20
2. Pengecatan Plafond 77.76 M² 53,150.00 4,132,944.00
3. Pengecatan waterproofing membran 36.00 M² 191,100.00 6,879,600.00
4. Pengecatan lantai dng epoxy 1404.00 M² 51,450.00 72,235,800.00
5. Pengecatan cycroma baja 844.28 M² 50,700.00 42,804,845.93
268,935,697.13
M PEKERJAAN INSTALASI LISTRIK
1. Pasang Meterisasi listrik 65.000 KVA 1.00 Unit 75,000,000.00 75,000,000.00
2. Pasang instalasi lampu untuk lampu 15.00 Titik 780,050.00 11,700,750.00
3. Pasang instalasi lampu kabel NYM 2x 2,5 mm 44.00 Titik 354,500.00 15,598,000.00
4. Pasang instalasi stop kontak 20.00 Bh 354,100.00 7,082,000.00
5. Pasang Panel Genset ATS AMF 33 KVA 3phase 1.00 Unit 27,517,100.00 27,517,100.00

4.
1 2 3 4 5 6
6. Pasang lampu LED untuk 15.00 Bh 418,000.00 6,270,000.00
7. Pasang lampu SL 44.00 Titik 73,800.00 3,247,200.00
8. Pasang saklar tunggal 7.00 Bh 129,550.00 906,850.00
9. Pasang saklar ganda 15.00 Bh 147,200.00 2,208,000.00
10. Pasang stop kontak 20.00 Bh 146,200.00 2,924,000.00
152,453,900.00

Jumlah 8,357,996,934.98
Ppn 10 % 835,799,693.50
Total jumlah 9,193,796,628.48
Dibulatkan 9,193,796,000.00

Perencana,

Anword studio arsitektur


team work