JADWAL WAKTU PELAKSANAAN PEKERJAAN

( KONTRAK AWAL )
INSTANSI : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021

BULAN KE-1 BULAN KE-2 BULAN KE-3 BULAN KE-4


Ming.1 Ming.2 Ming.3 Ming.4 Ming.5 Ming.6 Ming.7 Ming.8 Ming.9 Ming.10 Ming.11 Ming.12 Ming.13 Ming.14 Ming.15 Ming.16 Ming.17 Ming.18 Ming.19 Ming.20 Ming.21 Ming.22
VOLUME HARGA SATUAN JUMLAH HARGA BOBOT
NO JENIS PEKERJAAN SAT. 24/05/21 31/05/21 07/06/21 14/06/21 21/06/21 28/06/21 05/07/21 12/07/21 19/07/21 26/07/21 02/08/21 09/08/21 16/08/21 23/08/21 30/08/21 06/09/21 13/09/21 20/09/21 27/09/21 04/10/21 11/10/21 18/10/21 PROGRES KET.
KONTRAK (Rp) (Rp) (%)
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
30/05/21 06/06/21 13/06/21 20/06/21 27/06/21 04/07/21 11/07/21 18/07/21 25/07/21 01/08/21 08/08/21 15/08/21 22/08/21 29/08/21 05/09/21 12/09/21 19/09/21 26/09/21 03/10/21 10/10/21 17/10/21 20/10/21

I PEKERJAAN PERSIAPAN
1 Pembuatan Papan Nama Pekerjaan bh 1.00 250,000.00 250,000.00 0.04 0.04
2 Pengukuran dan Pemasangan Bouwplank m 28.56 12,198.91 348,400.73 0.05 0.03 0.03
3 Pembuatan bedeng pekerja m2 9.00 383,330.04 3,449,970.32 0.53 0.26 0.26
4 Mobilisasi Demobilisasi Alat Berat ls 1.00 2,500,000.00 2,500,000.00 0.38 0.19 0.19
5 Pembuatan akses menuju badan sungai sementara m2 24.00 113,128.49 2,715,083.64 0.41 0.21 0.21
6 Dewatering dengan pompa air diesel jam 40.00 25,000.00 1,000,000.00 0.15 0.02 0.02 0.02 0.02 0.02 0.02 0.02
7 SMKK ls 1.00 4,325,000.00 4,325,000.00 0.66 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
- - - - - - -
II PEKERJAAN PERBAIKAN TALUD SEGMEN 5 - - - - -
A PEKERJAAN TANAH DAN BETON BERTULANG - - - - -
1 Penggalian 1 M3 Tanah Biasa m3 50.00 67,972.30 3,398,615.01 0.52 0.13 0.13 0.13 0.13
2 Pengurugan Kembali 1 M3 Galian Tanah m3 33.15 49,023.50 1,625,129.04 0.25 0.08 0.08 0.08
3 Bongkaran Pasangan Batu dan Beton Eksisting m3 50.00 71,953.20 3,597,660.02 0.55 0.14 0.14 0.14 0.14
4 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area m3 50.00 19,888.18 994,408.76 0.15 0.04 0.04 0.04 0.04
5 Pemadatan Tanah Eksisting m3 11.84 49,023.50 580,438.24 0.09 0.04 0.04
6 Pengurugan dengan pasir urug m3 5.92 178,388.92 1,056,062.41 0.16 0.16
7 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 m3 2.96 737,396.00 2,182,692.15 0.33 0.17 0.17
8 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 m3 10.00 872,242.00 8,722,419.97 1.33 0.22 0.22 0.22 0.22 0.22 0.22
9 Pekerjaan Beton Dinding Talud Beton - - - - -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 m3 10.00 872,242.00 8,722,419.97 1.33 0.67 0.67
b Pembesian dg Besi Polos atau Besi Ulir kg 1,000.00 11,860.70 11,860,698.15 1.81 0.91 0.91
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 40.00 316,861.88 12,674,475.27 1.94 1.94
10 Pekerjaan Beton Sloof 20x30cm - - - - -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 m3 4.74 872,242.00 4,134,427.07 0.63 0.63
b Pembesian dg Besi Polos atau Besi Ulir kg 400.00 11,860.70 4,744,279.26 0.72 0.72
c Memasang Bekisting untuk Sloof (dipakai 2 kali) m2 47.36 89,375.55 4,232,825.87 0.65 0.32 0.32
11 Pekerjaan Beton Konsul Cantilever - - - - -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 m3 7.75 872,242.00 6,759,875.48 1.03 0.52 0.52
b Pembesian dg Besi Polos atau Besi Ulir kg 700.00 11,860.70 8,302,488.71 1.27 0.63 0.63
c Memasang Bekisting untuk Balok (dipakai 2 kali) m2 40.00 120,181.13 4,807,245.27 0.73 0.73
12 Pekerjaan Plat Beton tebal 12 cm - - - - -
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) m3 10.00 872,242.00 8,722,419.97 1.33 1.33
b Jaring Kawat baja/Wire Mesh M8 2 lapis kg 700.00 10,697.66 7,488,358.68 1.14 0.38 0.38 0.38
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 30.00 316,861.88 9,505,856.45 1.45 0.48 0.48 0.48
13 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm m 13.00 77,312.85 1,005,067.10 0.15 0.15
14 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm m 38.37 86,676.29 3,325,769.35 0.51 0.25 0.25
15 Memasang Stek Besi kg 200.00 11,860.70 2,372,139.63 0.36 0.36
16 Pekerjaan Plat Beton Pot tebal 10 cm - - - - -
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) m3 4.74 872,242.00 4,134,427.07 0.63 0.32 0.32
b Pembesian dg Besi Polos atau Besi Ulir kg 200.00 11,860.70 2,372,139.63 0.36 0.18 0.18
c Bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm m2 30.00 118,158.83 3,544,764.95 0.54 0.27 0.27
- - - - - - -
B PEKERJAAN PASANGAN DINDING - - - - -
1 Pemasangan Dinding Bata Merah Bakar Sekam Tebal 1/2 Bata Camp. 1SP 6PP m2 42.00 116,576.48 4,896,212.34 0.75 0.75
2 Pemasangan Plesteran 1 Pc 6 Pp Tebal 15 mm m2 84.00 54,689.70 4,593,934.71 0.70 0.70
3 Pemasangan Acian m2 210.00 33,411.23 7,016,358.16 1.07 1.07
4 Pemasangan Plesteran Skoning 1 Pc 2Pp lebar 10 cm m 360.00 55,075.90 19,827,324.36 3.03 1.01 1.01 1.01
5 Pemasangan Kepala Kolom bh 10.00 50,000.00 500,000.00 0.08 0.08
- - - - - - -
III PEKERJAAN PENATAAN LINGKUNGAN RW 1 - - - - -
A PEKERJAAN PENGECATAN - - - - -
1 Pengecatan Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Weathershield luar ruangan m2 210.00 11,686.42 2,454,148.34 0.37 0.37
- - - - - - -
B PEKERJAAN RUMAH TERDAMPAK - - - - -
I. PEKERJAAN BONGKARAN - - - - -
1 Membongkar 1 m2 genteng / sirap untuk dipergunakan lagi m2 103.90 3,628.42 376,993.05 0.06 0.03 0.03
2 Membongkar 1 m3 kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi m3 0.46 991,595.91 456,134.12 0.07 0.03 0.03
3 Pembongkaran 1 m3 pasangan bata merah dan membersihkan m3 40.86 185,908.38 7,596,216.24 1.16 0.58 0.58
4 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 m3 9.20 688,832.33 6,337,257.47 0.97 0.48 0.48
II. PEKERJAAN TANAH - - - - -
1 Menggali 1 m3 tanah biasa sedalam 1 meter m3 22.32 67,972.30 1,517,141.74 0.23 0.23
III. PEKERJAAN PONDASI - - - - -
1 Memasang 1 m3 pondasi batu belah, campuran 1 PC 6 PP m2 17.28 665,195.09 11,494,571.24 1.76 1.76
IV. PEKERJAAN BETON - - - - -
1 Membuat 1 m3 Sloof beton bertulang (200 kg besi + bekisting) m3 3.55 3,844,764.87 13,648,915.30 2.08 1.04 1.04
2 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) m3 4.94 7,083,735.01 34,993,650.96 5.35 1.78 1.78 1.78
3 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) m3 5.00 5,659,422.09 28,297,110.46 4.32 1.08 1.08 1.08 1.08
V. PEKERJAAN DINDING - - - - -
1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP m2 127.00 116,576.48 14,805,213.51 2.26 0.57 0.57 0.57 0.57
BULAN KE-1 BULAN KE-2 BULAN KE-3 BULAN KE-4
Ming.1 Ming.2 Ming.3 Ming.4 Ming.5 Ming.6 Ming.7 Ming.8 Ming.9 Ming.10 Ming.11 Ming.12 Ming.13 Ming.14 Ming.15 Ming.16 Ming.17 Ming.18 Ming.19 Ming.20 Ming.21 Ming.22
VOLUME HARGA SATUAN JUMLAH HARGA BOBOT
NO JENIS PEKERJAAN SAT. 24/05/21 31/05/21 07/06/21 14/06/21 21/06/21 28/06/21 05/07/21 12/07/21 19/07/21 26/07/21 02/08/21 09/08/21 16/08/21 23/08/21 30/08/21 06/09/21 13/09/21 20/09/21 27/09/21 04/10/21 11/10/21 18/10/21 PROGRES KET.
KONTRAK (Rp) (Rp) (%)
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
30/05/21 06/06/21 13/06/21 20/06/21 27/06/21 04/07/21 11/07/21 18/07/21 25/07/21 01/08/21 08/08/21 15/08/21 22/08/21 29/08/21 05/09/21 12/09/21 19/09/21 26/09/21 03/10/21 10/10/21 17/10/21 20/10/21
VI PEKERJAAN KAYU - - - - -
1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti m3 0.50 16,443,774.77 8,221,887.38 1.26 0.63 0.63
2 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti m2 12.72 644,715.80 8,200,785.00 1.25 1.25
3 Memasang 1 m3 konstruksi gordeng, kayu glugu m3 0.21 4,450,537.65 934,612.91 0.14 0.07 0.07
VII. PEKERJAAN PLESTERAN - - - - -
1 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm m2 100.00 54,689.70 5,468,969.90 0.84 0.84
2 Memasang 1 m2 acian m2 100.00 33,411.23 3,341,122.93 0.51 0.51
VIII. PEKERJAAN PENGECATAN - - - - -
1 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) m2 100.00 11,686.42 1,168,642.06 0.18 0.18
IX. PEKERJAAN PENUTUP ATAP - - - - -
1 Memasang 1 m2 Atap Galvalum (Paket) m3 78.20 190,000.00 14,858,000.00 2.27 2.27
X. PEKERJAAN PENUTUP LANTAI DAN DINDING - - - - -
1 Memasang 1 m2 lantai keramik (30 x 30) cm m2 8.54 114,193.22 975,210.13 0.15 0.15
XI. PEKERJAAN SANITASI - - - - -
1 Memasang 1 buah Kloset Jongkok Porselen bh 2.00 280,952.58 561,905.16 0.09 0.09
2 Memasang 1 m Pipa PVC tipe AW m2 24.00 19,406.20 465,748.90 0.07 0.07
3 Memasang 1 m Pipa PVC tipe AW 1 m2 24.00 22,254.33 534,103.90 0.08 0.08
4 Memasang 1 m Pipa PVC tipe AW 3 m2 24.00 63,036.61 1,512,878.67 0.23 0.23
5 Memasang 1 buah Kran atau m2 2.00 46,068.18 92,136.37 0.01 0.01
6 Memasang 1 buah Floor Drain m3 2.00 80,836.18 161,672.35 0.02 0.02
7 Memasang 1 buah Pintu Kamar Mandi bh 2.00 650,000.00 1,300,000.00 0.20 0.20
- - - - - - -
III PEKERJAAN PENATAAN LINGKUNGAN RW 1 - - - - -
A PEKERJAAN PEMBERSIHAN SALURAN - - - - -
1 Penggalian Tanah Lumpur dan Endapan Limbah Sedalam 30 cm m3 85.36 109,311.98 9,330,870.22 1.43 0.71 0.71
2 Pembersihan dan Pembuangan Tanah Lumpur dan Limbah Keluar Area m3 85.36 29,796.55 2,543,433.77 0.39 0.19 0.19
3 Pemadatan Tanah Eksisting m3 48.91 49,023.50 2,397,739.40 0.37 0.37
4 Pengurugan dengan pasir urug, 10 cm m3 17.07 178,388.92 3,045,098.87 0.47 0.23 0.23
5 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 m3 17.07 737,396.00 12,587,349.68 1.92 0.96 0.96
6 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 m3 17.07 872,242.00 14,889,170.90 2.27 1.14 1.14
7 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm m 466.40 77,312.85 36,058,714.99 5.51 1.84 1.84 1.84
8 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm m 466.40 86,676.29 40,425,822.86 6.17 1.54 1.54 1.54 1.54
9 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,2m, K.300 bh 65.00 626,150.00 40,699,750.00 6.22 1.55 1.55 1.55 1.55
10 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,8m, K.300 bh 32.00 750,000.00 24,000,000.00 3.67 1.22 1.22 1.22
- - - - - - -
B PEKERJAAN JARINGAN IPAL KOMUNAL - - - - -
1 Pekerjaan Galian Tanah Pipa m3 81.86 67,972.30 5,564,212.49 0.85 0.21 0.21 0.21 0.21
2 Pengurugan dengan pasir urug m3 6.82 178,388.92 1,216,612.43 0.19 0.06 0.06 0.06
3 Pengurugan Kembali 1 M3 Galian Tanah m3 24.56 49,023.50 1,204,017.17 0.18 0.06 0.06 0.06
4 Pemasangan 1 M Pipa PVC tipe AW 4 m 30.00 90,907.55 2,727,226.46 0.42 0.14 0.14 0.14
5 Saluran Pipa Air Limbah SDR - 41, Dia 15 cm , inc. fitting & Assecories m 343.20 133,200.00 45,714,240.00 6.98 1.75 1.75 1.75 1.75
6 Saluran Pipa Air Limbah SDR - 41, Dia 20 cm, , inc. fitting & Assecories m 113.70 203,900.00 23,183,430.00 3.54 1.18 1.18 1.18
7 Pemasangan Clean Out Inc. Fitting & Assecories ttk 17.00 185,000.00 3,145,000.00 0.48 0.16 0.16 0.16
8 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 100 org, 20 m3 / hari unit 1.00 7,500,000.00 7,500,000.00 1.15 1.15
9 Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm unit 4.00 975,000.00 3,900,000.00 0.60 0.30 0.30
10 Pekerjaan Sumur Resapan, Dia 100 cm, Kedalaman 2 m, Inc. Tutup Beton Berlubang ttk 15.00 500,000.00 7,500,000.00 1.15 0.38 0.38 0.38
11 Grill Beton Penutup Sumur Resapan unit 20.00 750,000.00 15,000,000.00 2.29 0.76 0.76 0.76

Rencana Kemajuan Mingguan 654,697,105.06 100.000 0.095 0.718 0.501 0.937 1.803 2.688 2.964 4.087 6.711 6.870 5.876 8.118 7.585 7.477 10.026 10.362 11.178 4.745 4.328 1.218 1.491 0.221
Rencana Komulatif Kemajuan Mingguan - 0.095 0.813 1.314 2.251 4.054 6.742 9.706 13.793 20.504 27.374 33.251 41.368 48.953 56.430 66.457 76.819 87.997 92.742 97.070 98.288 99.779 100.000
Realisasi Kemajuan Mingguan
Realisasi Komulatif Kemajuan Mingguan
Deviasi (+/-)

Yogyakarta 24 Mei 2021


Dibuat Oleh
PEJABAT PEMBUAT KOMITMEN TIM TEKNIS KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA
1. Cicilia Novi hendrawati, M.SC., M.Eng.
NIP. 19781102 200501 2 011

2. Danang Dwi Wahyujati,S.Kom.,M.Eng


NIP. 19761028 199803 1 004

SIGIT SETIAWAN, ST.MT 3. Sudaryanto


NIP. 19690605 199303 1 007 RISMAN WARCHAN ZULIANTO
NIP. 19770623 200501 1 013 Tim Leader Direktur
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : I ( Satu )


Periode : 24 Mei 2021 sampai dengan 30 Mei 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
I PEKERJAAN PERSIAPAN
1 Pembuatan Papan Nama Pekerjaan 1.00 bh 250,000.00 250,000.00 0.038 - - - - - -
2 Pengukuran dan Pemasangan Bouwplank 28.56 m 12,198.91 348,400.73 0.053 - - 28.560 0.053 28.560 0.053
3 Pembuatan bedeng pekerja 9.00 m2 383,330.04 3,449,970.32 0.527 - - - - - -
4 Mobilisasi Demobilisasi Alat Berat 1.00 ls 2,500,000.00 2,500,000.00 0.382 - - - - - -
5 Pembuatan akses menuju badan sungai sementara 24.00 m2 113,128.49 2,715,083.64 0.415 - - - - - -
6 Dewatering dengan pompa air diesel 40.00 jam 25,000.00 1,000,000.00 0.153 - - - - - -
7 SMKK 1.00 ls 4,325,000.00 4,325,000.00 0.661 - - 0.045 0.030 0.045 0.030
14,588,454.69 2.228 - - 28.605 0.083 28.605 0.083
II PEKERJAAN PERBAIKAN TALUD SEGMEN 5
A PEKERJAAN TANAH DAN BETON BERTULANG
1 Penggalian 1 M3 Tanah Biasa 50.00 m3 67,972.30 3,398,615.01 0.519 - - - - - -
2 Pengurugan Kembali 1 M3 Galian Tanah 33.15 m3 49,023.50 1,625,129.04 0.248 - - - - - -
3 Bongkaran Pasangan Batu dan Beton Eksisting 50.00 m3 71,953.20 3,597,660.02 0.550 - - - - - -
4 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area 50.00 m3 19,888.18 994,408.76 0.152 - - - - - -
5 Pemadatan Tanah Eksisting 11.84 m3 49,023.50 580,438.24 0.089 - - - - - -
6 Pengurugan dengan pasir urug 5.92 m3 178,388.92 1,056,062.41 0.161 - - - - - -
7 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 2.96 m3 737,396.00 2,182,692.15 0.333 - - - - - -
8 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 10.00 m3 872,242.00 8,722,419.97 1.332 - - - - - -
9 Pekerjaan Beton Dinding Talud Beton
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 10.00 m3 872,242.00 8,722,419.97 1.332 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 1,000.00 kg 11,860.70 11,860,698.15 1.812 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 40.00 m2 316,861.88 12,674,475.27 1.936 - - - - - -
10 Pekerjaan Beton Sloof 20x30cm
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 4.74 m3 872,242.00 4,134,427.07 0.632 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 400.00 kg 11,860.70 4,744,279.26 0.725 - - - - - -
c Memasang Bekisting untuk Sloof (dipakai 2 kali) 47.36 m2 89,375.55 4,232,825.87 0.647 - - - - - -
11 Pekerjaan Beton Konsul Cantilever
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 7.75 m3 872,242.00 6,759,875.48 1.033 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 700.00 kg 11,860.70 8,302,488.71 1.268 - - - - - -
c Memasang Bekisting untuk Balok (dipakai 2 kali) 40.00 m2 120,181.13 4,807,245.27 0.734 - - - - - -
12 Pekerjaan Plat Beton tebal 12 cm
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 10.00 m3 872,242.00 8,722,419.97 1.332 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis 700.00 kg 10,697.66 7,488,358.68 1.144 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 30.00 m2 316,861.88 9,505,856.45 1.452 - - - - - -
13 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 13.00 m 77,312.85 1,005,067.10 0.154 - - - - - -
14 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 38.37 m 86,676.29 3,325,769.35 0.508 - - - - - -
15 Memasang Stek Besi 200.00 kg 11,860.70 2,372,139.63 0.362 - - - - - -
16 Pekerjaan Plat Beton Pot tebal 10 cm
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 4.74 m3 872,242.00 4,134,427.07 0.632 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 200.00 kg 11,860.70 2,372,139.63 0.362 - - - - - -
c Bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm 30.00 m2 118,158.83 3,544,764.95 0.541 - - - - - -
130,867,103.48 19.989 - - - - - -
B PEKERJAAN PASANGAN DINDING
1 Pemasangan Dinding Bata Merah Bakar Sekam Tebal 1/2 Bata Camp. 1SP 6PP 42.00 m2 116,576.48 4,896,212.34 0.748 - - - - - -
2 Pemasangan Plesteran 1 Pc 6 Pp Tebal 15 mm 84.00 m2 54,689.70 4,593,934.71 0.702 - - - - - -
3 Pemasangan Acian 210.00 m2 33,411.23 7,016,358.16 1.072 - - - - - -
4 Pemasangan Plesteran Skoning 1 Pc 2Pp lebar 10 cm 360.00 m 55,075.90 19,827,324.36 3.028 - - - - - -
5 Pemasangan Kepala Kolom 10.00 bh 50,000.00 500,000.00 0.076 - - - - - -
36,833,829.57 5.626 - - - - - -
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PENGECATAN
1 Pengecatan Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Weathershield luar ruangan 210.00 m2 11,686.42 2,454,148.34 0.375 - - - - - -
2,454,148.34 0.375 - - - - - -

Laporan Progres Mingguan ke-1


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
B PEKERJAAN RUMAH TERDAMPAK
I. PEKERJAAN BONGKARAN
1 Membongkar 1 m2 genteng / sirap untuk dipergunakan lagi 103.90 m2 3,628.42 376,993.05 0.058 - - - - - -
2 Membongkar 1 m3 kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi 0.46 m3 991,595.91 456,134.12 0.070 - - - - - -
3 Pembongkaran 1 m3 pasangan bata merah dan membersihkan 40.86 m3 185,908.38 7,596,216.24 1.160 - - - - - -
4 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 9.20 m3 688,832.33 6,337,257.47 0.968 - - - - - -
II. PEKERJAAN TANAH
1 Menggali 1 m3 tanah biasa sedalam 1 meter 22.32 m3 67,972.30 1,517,141.74 0.232 - - - - - -
III. PEKERJAAN PONDASI
1 Memasang 1 m3 pondasi batu belah, campuran 1 PC 6 PP 17.28 m2 665,195.09 11,494,571.24 1.756 - - - - - -
IV. PEKERJAAN BETON
1 Membuat 1 m3 Sloof beton bertulang (200 kg besi + bekisting) 3.55 m3 3,844,764.87 13,648,915.30 2.085 - - - - - -
2 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) 4.94 m3 7,083,735.01 34,993,650.96 5.345 - - - - - -
3 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) 5 m3 5,659,422.09 28,297,110.46 4.322 - - - - - -
V. PEKERJAAN DINDING
1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP 127.00 m2 116,576.48 14,805,213.51 2.261 - - - - - -
VI PEKERJAAN KAYU
1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.50 m3 16,443,774.77 8,221,887.38 1.256 - - - - - -
2 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti 12.72 m2 644,715.80 8,200,785.00 1.253 - - - - - -
3 Memasang 1 m3 konstruksi gordeng, kayu glugu 0.21 m3 4,450,537.65 934,612.91 0.143 - - - - - -
VII. PEKERJAAN PLESTERAN
1 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm 100.00 m2 54,689.70 5,468,969.90 0.835 - - - - - -
2 Memasang 1 m2 acian 100.00 m2 33,411.23 3,341,122.93 0.510 - - - - - -
VIII. PEKERJAAN PENGECATAN
1 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 100.00 m2 11,686.42 1,168,642.06 0.179 - - - - - -
IX. PEKERJAAN PENUTUP ATAP
1 Memasang 1 m2 Atap Galvalum (Paket) 78.20 m3 190,000.00 14,858,000.00 2.269 - - - - - -
X. PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Memasang 1 m2 lantai keramik (30 x 30) cm 8.54 m2 114,193.22 975,210.13 0.149 - - - - - -
XI. PEKERJAAN SANITASI
1 Memasang 1 buah Kloset Jongkok Porselen 2.00 bh 280,952.58 561,905.16 0.086 - - - - - -
2 Memasang 1 m Pipa PVC tipe AW 24.00 m2 19,406.20 465,748.90 0.071 - - - - - -
3 Memasang 1 m Pipa PVC tipe AW 1 24.00 m2 22,254.33 534,103.90 0.082 - - - - - -
4 Memasang 1 m Pipa PVC tipe AW 3 24.00 m2 63,036.61 1,512,878.67 0.231 - - - - - -
5 Memasang 1 buah Kran atau 2.00 m2 46,068.18 92,136.37 0.014 - - - - - -
6 Memasang 1 buah Floor Drain 2.00 m3 80,836.18 161,672.35 0.025 - - - - - -
7 Memasang 1 buah Pintu Kamar Mandi 2.00 bh 650,000.00 1,300,000.00 0.199 - - - - - -
167,320,879.74 25.557 - - - - - -
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PEMBERSIHAN SALURAN
1 Penggalian Tanah Lumpur dan Endapan Limbah Sedalam 30 cm 85.36 m3 109,311.98 9,330,870.22 1.425 - - - - - -
2 Pembersihan dan Pembuangan Tanah Lumpur dan Limbah Keluar Area 85.36 m3 29,796.55 2,543,433.77 0.388 - - - - - -
3 Pemadatan Tanah Eksisting 48.91 m3 49,023.50 2,397,739.40 0.366 - - - - - -
4 Pengurugan dengan pasir urug, 10 cm 17.07 m3 178,388.92 3,045,098.87 0.465 - - - - - -
5 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 17.07 m3 737,396.00 12,587,349.68 1.923 - - - - - -
6 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 17.07 m3 872,242.00 14,889,170.90 2.274 - - - - - -
7 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 466.40 m 77,312.85 36,058,714.99 5.508 - - - - - -
8 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 466.40 m 86,676.29 40,425,822.86 6.175 - - - - - -
9 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,2m, K.300 65.00 bh 626,150.00 40,699,750.00 6.217 - - - - - -
10 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,8m, K.300 32.00 bh 750,000.00 24,000,000.00 3.666 - - - - - -
185,977,950.68 28.407 - - -

Laporan Progres Mingguan ke-1


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
B PEKERJAAN JARINGAN IPAL KOMUNAL
1 Pekerjaan Galian Tanah Pipa 81.86 m3 67,972.30 5,564,212.49 0.850 - - - - - -
2 Pengurugan dengan pasir urug 6.82 m3 178,388.92 1,216,612.43 0.186 - - - - - -
3 Pengurugan Kembali 1 M3 Galian Tanah 24.56 m3 49,023.50 1,204,017.17 0.184 - - - - - -
4 Pemasangan 1 M Pipa PVC tipe AW 4 30.00 m 90,907.55 2,727,226.46 0.417 - - - - - -
5 Saluran Pipa Air Limbah SDR - 41, Dia 15 cm , inc. fitting & Assecories 343.20 m 133,200.00 45,714,240.00 6.983 - - - - - -
6 Saluran Pipa Air Limbah SDR - 41, Dia 20 cm, , inc. fitting & Assecories 113.70 m 203,900.00 23,183,430.00 3.541 - - - - - -
7 Pemasangan Clean Out Inc. Fitting & Assecories 17.00 ttk 185,000.00 3,145,000.00 0.480 - - - - - -
8 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 100 org, 20 m3 / hari, 1 unit 7,500,000.00 7,500,000.00 1.146 - - - - - -
(Galian, Urugan, Pondasi, Tutup Beton, Penyambungan Instalasi)
9 Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm 4.00 unit 975,000.00 3,900,000.00 0.596 - - - - - -
10 Pekerjaan Sumur Resapan, Dia 100 cm, Kedalaman 2 m, Inc. Tutup Beton Berlubang 15.00 ttk 500,000.00 7,500,000.00 1.146 - - - - - -
11 Grill Beton Penutup Sumur Resapan 20.00 unit 750,000.00 15,000,000.00 2.291 - - - - - -
116,654,738.56 17.818 - - - - - -

JUMLAH 654,697,105.06 100.000 - - - 0.083 - 0.083


PRESTASI MINGGU LALU -
PRESTASI MINGGU INI 0.083
PRESTASI SAMPAI DENGAN MINGGU INI 0.083
PRESTASI MENURUT SCHEDULE 0.095
LEBIH CEPAT(+)/TERLAMBAT(-) (0.012)

Yogyakarta, 31 Mei 2021


di buat oleh,
KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA

Noor Hasan Bambang Erlianto


Pengawas Pelaksana

Laporan Progres Mingguan ke-1


REKAPITULASI
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : I ( Satu )


Periode : 24 Mei 2021 sampai dengan 30 Mei 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO PEKERJAAN PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp (%) BOBOT % BOBOT % BOBOT %

I PEKERJAAN PERSIAPAN 14,588,454.69 2.228 - 0.083 0.083

II PEKERJAAN PERBAIKAN TALUD SEGMEN 5


A PEKERJAAN TANAH DAN BETON BERTULANG 130,867,103.48 19.989 - - -
B PEKERJAAN PASANGAN DINDING 36,833,829.57 5.626 - - -

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PENGECATAN 2,454,148.34 0.375 - - -
B PEKERJAAN RUMAH TERDAMPAK 167,320,879.74 25.557 - - -

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PEMBERSIHAN SALURAN 185,977,950.68 28.407 - - -
B PEKERJAAN JARINGAN IPAL KOMUNAL 116,654,738.56 17.818 - - -

JUMLAH 654,697,105.06 100.000 - 0.083 0.083


PRESTASI MINGGU LALU -
PRESTASI MINGGU INI 0.083
PRESTASI SAMPAI DENGAN MINGGU INI 0.083
PRESTASI MENURUT SCHEDULE 0.095
LEBIH CEPAT (+) / TERLAMBAT (-) (0.012)

Yogyakarta, 31 Mei 2021


di buat oleh,
PEJABAT PEMBUAT KOMITMEN TIM TEKNIS KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA
1. Cicilia Novi hendrawati, M.SC., M.Eng.
NIP. 19781102 200501 2 011 ...........................

2. Danang Dwi Wahyujati,S.Kom.,M.Eng


NIP. 19761028 199803 1 004 ...........................
SIGIT SETIAWAN, ST.MT 3. Sudaryanto
NIP. 19690605 199303 1 007 RISMAN WARCHAN ZULIANTO
NIP. 19770623 200501 1 013 ........................... Tim Leader Direktur
REKAPITULASI
DAFTAR KUANTITAS DAN HARGA

PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN


LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TANHUN ANGGARAN : 2021

NO PEKERJAAN JUMLAH

I PEKERJAAN PERSIAPAN Rp. 16,047,300.16

II PEKERJAAN PERBAIKAN TALUD SEGMEN 5


A PEKERJAAN TANAH DAN BETON BERTULANG Rp. 143,953,813.83
B PEKERJAAN PASANGAN DINDING Rp. 40,517,212.53

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PENGECATAN Rp. 2,699,563.17
B PEKERJAAN RUMAH TERDAMPAK Rp. 184,052,967.72

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PEMBERSIHAN SALURAN Rp. 204,575,745.75
B PEKERJAAN JARINGAN IPAL KOMUNAL Rp. 128,320,212.41

JUMLAH Rp 720,166,815.57
TERBILANG: (Tujuh Ratus Dua Puluh Juta Seratus Enam Puluh Enam Ribu Delapan Ratus Lima Belas 57/100 Rupiah)

PENAWAR,
CV. ALMEERA RAYA

WARCHAN ZULIANTO
Direktur
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : II ( Dua )


Periode : 31 Mei 2021 sampai dengan 06 Juni 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
I PEKERJAAN PERSIAPAN
1 Pembuatan Papan Nama Pekerjaan 1.00 bh 250,000.00 250,000.00 0.038 - - - - - -
2 Pengukuran dan Pemasangan Bouwplank 28.56 m 12,198.91 348,400.73 0.053 28.560 0.053 - - 28.560 0.053
3 Pembuatan bedeng pekerja 9.00 m2 383,330.04 3,449,970.32 0.527 - - - - - -
4 Mobilisasi Demobilisasi Alat Berat 1.00 ls 2,500,000.00 2,500,000.00 0.382 - - - - - -
5 Pembuatan akses menuju badan sungai sementara 24.00 m2 113,128.49 2,715,083.64 0.415 - - - - - -
6 Dewatering dengan pompa air diesel 40.00 jam 25,000.00 1,000,000.00 0.153 - - - - - -
7 SMKK 1.00 ls 4,325,000.00 4,325,000.00 0.661 0.045 0.030 0.045 0.030 0.091 0.060
14,588,454.69 2.228 28.605 0.083 0.045 0.030 28.651 0.113
II PEKERJAAN PERBAIKAN TALUD SEGMEN 5
A PEKERJAAN TANAH DAN BETON BERTULANG
1 Penggalian 1 M3 Tanah Biasa 50.00 m3 67,972.30 3,398,615.01 0.519 - - - - - -
2 Pengurugan Kembali 1 M3 Galian Tanah 33.15 m3 49,023.50 1,625,129.04 0.248 - - - - - -
3 Bongkaran Pasangan Batu dan Beton Eksisting 50.00 m3 71,953.20 3,597,660.02 0.550 - - - - - -
4 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area 50.00 m3 19,888.18 994,408.76 0.152 - - - - - -
5 Pemadatan Tanah Eksisting 11.84 m3 49,023.50 580,438.24 0.089 - - - - - -
6 Pengurugan dengan pasir urug 5.92 m3 178,388.92 1,056,062.41 0.161 - - - - - -
7 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 2.96 m3 737,396.00 2,182,692.15 0.333 - - - - - -
8 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 10.00 m3 872,242.00 8,722,419.97 1.332 - - - - - -
9 Pekerjaan Beton Dinding Talud Beton
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 10.00 m3 872,242.00 8,722,419.97 1.332 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 1,000.00 kg 11,860.70 11,860,698.15 1.812 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 40.00 m2 316,861.88 12,674,475.27 1.936 - - - - - -
10 Pekerjaan Beton Sloof 20x30cm
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 4.74 m3 872,242.00 4,134,427.07 0.632 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 400.00 kg 11,860.70 4,744,279.26 0.725 - - - - - -
c Memasang Bekisting untuk Sloof (dipakai 2 kali) 47.36 m2 89,375.55 4,232,825.87 0.647 - - - - - -
11 Pekerjaan Beton Konsul Cantilever
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 7.75 m3 872,242.00 6,759,875.48 1.033 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 700.00 kg 11,860.70 8,302,488.71 1.268 - - - - - -
c Memasang Bekisting untuk Balok (dipakai 2 kali) 40.00 m2 120,181.13 4,807,245.27 0.734 - - - - - -
12 Pekerjaan Plat Beton tebal 12 cm
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 10.00 m3 872,242.00 8,722,419.97 1.332 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis 700.00 kg 10,697.66 7,488,358.68 1.144 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 30.00 m2 316,861.88 9,505,856.45 1.452 - - - - - -
13 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 13.00 m 77,312.85 1,005,067.10 0.154 - - - - - -
14 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 38.37 m 86,676.29 3,325,769.35 0.508 - - - - - -
15 Memasang Stek Besi 200.00 kg 11,860.70 2,372,139.63 0.362 - - - - - -
16 Pekerjaan Plat Beton Pot tebal 10 cm
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 4.74 m3 872,242.00 4,134,427.07 0.632 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 200.00 kg 11,860.70 2,372,139.63 0.362 - - - - - -
c Bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm 30.00 m2 118,158.83 3,544,764.95 0.541 - - - - - -
130,867,103.48 19.989 - - - - - -
B PEKERJAAN PASANGAN DINDING
1 Pemasangan Dinding Bata Merah Bakar Sekam Tebal 1/2 Bata Camp. 1SP 6PP 42.00 m2 116,576.48 4,896,212.34 0.748 - - - - - -
2 Pemasangan Plesteran 1 Pc 6 Pp Tebal 15 mm 84.00 m2 54,689.70 4,593,934.71 0.702 - - - - - -
3 Pemasangan Acian 210.00 m2 33,411.23 7,016,358.16 1.072 - - - - - -
4 Pemasangan Plesteran Skoning 1 Pc 2Pp lebar 10 cm 360.00 m 55,075.90 19,827,324.36 3.028 - - - - - -
5 Pemasangan Kepala Kolom 10.00 bh 50,000.00 500,000.00 0.076 - - - - - -
36,833,829.57 5.626 - - - - - -
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PENGECATAN
1 Pengecatan Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Weathershield luar ruangan 210.00 m2 11,686.42 2,454,148.34 0.375 - - - - - -
2,454,148.34 0.375 - - - - - -

Laporan Progres Mingguan ke-2


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
B PEKERJAAN RUMAH TERDAMPAK
I. PEKERJAAN BONGKARAN
1 Membongkar 1 m2 genteng / sirap untuk dipergunakan lagi 103.90 m2 3,628.42 376,993.05 0.058 - - - - - -
2 Membongkar 1 m3 kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi 0.46 m3 991,595.91 456,134.12 0.070 - - - - - -
3 Pembongkaran 1 m3 pasangan bata merah dan membersihkan 40.86 m3 185,908.38 7,596,216.24 1.160 - - - - - -
4 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 9.20 m3 688,832.33 6,337,257.47 0.968 - - - - - -
II. PEKERJAAN TANAH
1 Menggali 1 m3 tanah biasa sedalam 1 meter 22.32 m3 67,972.30 1,517,141.74 0.232 - - - - - -
III. PEKERJAAN PONDASI
1 Memasang 1 m3 pondasi batu belah, campuran 1 PC 6 PP 17.28 m2 665,195.09 11,494,571.24 1.756 - - - - - -
IV. PEKERJAAN BETON
1 Membuat 1 m3 Sloof beton bertulang (200 kg besi + bekisting) 3.55 m3 3,844,764.87 13,648,915.30 2.085 - - - - - -
2 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) 4.94 m3 7,083,735.01 34,993,650.96 5.345 - - - - - -
3 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) 5 m3 5,659,422.09 28,297,110.46 4.322 - - - - - -
V. PEKERJAAN DINDING
1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP 127.00 m2 116,576.48 14,805,213.51 2.261 - - - - - -
VI PEKERJAAN KAYU
1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.50 m3 16,443,774.77 8,221,887.38 1.256 - - - - - -
2 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti 12.72 m2 644,715.80 8,200,785.00 1.253 - - - - - -
3 Memasang 1 m3 konstruksi gordeng, kayu glugu 0.21 m3 4,450,537.65 934,612.91 0.143 - - - - - -
VII. PEKERJAAN PLESTERAN
1 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm 100.00 m2 54,689.70 5,468,969.90 0.835 - - - - - -
2 Memasang 1 m2 acian 100.00 m2 33,411.23 3,341,122.93 0.510 - - - - - -
VIII. PEKERJAAN PENGECATAN
1 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 100.00 m2 11,686.42 1,168,642.06 0.179 - - - - - -
IX. PEKERJAAN PENUTUP ATAP
1 Memasang 1 m2 Atap Galvalum (Paket) 78.20 m3 190,000.00 14,858,000.00 2.269 - - - - - -
X. PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Memasang 1 m2 lantai keramik (30 x 30) cm 8.54 m2 114,193.22 975,210.13 0.149 - - - - - -
XI. PEKERJAAN SANITASI
1 Memasang 1 buah Kloset Jongkok Porselen 2.00 bh 280,952.58 561,905.16 0.086 - - - - - -
2 Memasang 1 m Pipa PVC tipe AW 24.00 m2 19,406.20 465,748.90 0.071 - - - - - -
3 Memasang 1 m Pipa PVC tipe AW 1 24.00 m2 22,254.33 534,103.90 0.082 - - - - - -
4 Memasang 1 m Pipa PVC tipe AW 3 24.00 m2 63,036.61 1,512,878.67 0.231 - - - - - -
5 Memasang 1 buah Kran atau 2.00 m2 46,068.18 92,136.37 0.014 - - - - - -
6 Memasang 1 buah Floor Drain 2.00 m3 80,836.18 161,672.35 0.025 - - - - - -
7 Memasang 1 buah Pintu Kamar Mandi 2.00 bh 650,000.00 1,300,000.00 0.199 - - - - - -
167,320,879.74 25.557 - - - - - -
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PEMBERSIHAN SALURAN
1 Penggalian Tanah Lumpur dan Endapan Limbah Sedalam 30 cm 85.36 m3 109,311.98 9,330,870.22 1.425 - - - - - -
2 Pembersihan dan Pembuangan Tanah Lumpur dan Limbah Keluar Area 85.36 m3 29,796.55 2,543,433.77 0.388 - - - - - -
3 Pemadatan Tanah Eksisting 48.91 m3 49,023.50 2,397,739.40 0.366 - - - - - -
4 Pengurugan dengan pasir urug, 10 cm 17.07 m3 178,388.92 3,045,098.87 0.465 - - - - - -
5 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 17.07 m3 737,396.00 12,587,349.68 1.923 - - - - - -
6 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 17.07 m3 872,242.00 14,889,170.90 2.274 - - - - - -
7 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 466.40 m 77,312.85 36,058,714.99 5.508 - - - - - -
8 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 466.40 m 86,676.29 40,425,822.86 6.175 - - - - - -
9 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,2m, K.300 65.00 bh 626,150.00 40,699,750.00 6.217 - - - - - -
10 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,8m, K.300 32.00 bh 750,000.00 24,000,000.00 3.666 - - - - - -
185,977,950.68 28.407 - - -

Laporan Progres Mingguan ke-2


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
B PEKERJAAN JARINGAN IPAL KOMUNAL
1 Pekerjaan Galian Tanah Pipa 81.86 m3 67,972.30 5,564,212.49 0.850 - - - - - -
2 Pengurugan dengan pasir urug 6.82 m3 178,388.92 1,216,612.43 0.186 - - - - - -
3 Pengurugan Kembali 1 M3 Galian Tanah 24.56 m3 49,023.50 1,204,017.17 0.184 - - - - - -
4 Pemasangan 1 M Pipa PVC tipe AW 4 30.00 m 90,907.55 2,727,226.46 0.417 - - - - - -
5 Saluran Pipa Air Limbah SDR - 41, Dia 15 cm , inc. fitting & Assecories 343.20 m 133,200.00 45,714,240.00 6.983 - - - - - -
6 Saluran Pipa Air Limbah SDR - 41, Dia 20 cm, , inc. fitting & Assecories 113.70 m 203,900.00 23,183,430.00 3.541 - - - - - -
7 Pemasangan Clean Out Inc. Fitting & Assecories 17.00 ttk 185,000.00 3,145,000.00 0.480 - - - - - -
8 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 100 org, 20 m3 / hari, 1 unit 7,500,000.00 7,500,000.00 1.146 - - - - - -
(Galian, Urugan, Pondasi, Tutup Beton, Penyambungan Instalasi)
9 Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm 4.00 unit 975,000.00 3,900,000.00 0.596 - - - - - -
10 Pekerjaan Sumur Resapan, Dia 100 cm, Kedalaman 2 m, Inc. Tutup Beton Berlubang 15.00 ttk 500,000.00 7,500,000.00 1.146 - - - - - -
11 Grill Beton Penutup Sumur Resapan 20.00 unit 750,000.00 15,000,000.00 2.291 - - - - - -
116,654,738.56 17.818 - - - - - -

JUMLAH 654,697,105.06 100.000 - 0.083 - 0.030 - 0.113


PRESTASI MINGGU LALU 0.083
PRESTASI MINGGU INI 0.030
PRESTASI SAMPAI DENGAN MINGGU INI 0.113
PRESTASI MENURUT SCHEDULE 0.813
LEBIH CEPAT(+)/TERLAMBAT(-) (0.700)

Yogyakarta, 7 Juni 2021


di buat oleh,
KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA

Noor Hasan Bambang Erlianto


Pengawas Pelaksana

Laporan Progres Mingguan ke-2


REKAPITULASI
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : II ( Dua )


Periode : 31 Mei 2021 sampai dengan 06 Juni 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO PEKERJAAN PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp (%) BOBOT % BOBOT % BOBOT %

I PEKERJAAN PERSIAPAN 14,588,454.69 2.228 0.083 0.030 0.113

II PEKERJAAN PERBAIKAN TALUD SEGMEN 5


A PEKERJAAN TANAH DAN BETON BERTULANG 130,867,103.48 19.989 - - -
B PEKERJAAN PASANGAN DINDING 36,833,829.57 5.626 - - -

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PENGECATAN 2,454,148.34 0.375 - - -
B PEKERJAAN RUMAH TERDAMPAK 167,320,879.74 25.557 - - -

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PEMBERSIHAN SALURAN 185,977,950.68 28.407 - - -
B PEKERJAAN JARINGAN IPAL KOMUNAL 116,654,738.56 17.818 - - -

JUMLAH 654,697,105.06 100.000 0.083 0.030 0.113


PRESTASI MINGGU LALU 0.083
PRESTASI MINGGU INI 0.030
PRESTASI SAMPAI DENGAN MINGGU INI 0.113
PRESTASI MENURUT SCHEDULE 0.813
LEBIH CEPAT (+) / TERLAMBAT (-) (0.700)

Yogyakarta, 7 Juni 2021


di buat oleh,
PEJABAT PEMBUAT KOMITMEN TIM TEKNIS KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA
1. Cicilia Novi hendrawati, M.SC., M.Eng.
NIP. 19781102 200501 2 011 ...........................

2. Danang Dwi Wahyujati,S.Kom.,M.Eng


NIP. 19761028 199803 1 004 ...........................
SIGIT SETIAWAN, ST.MT 3. Sudaryanto
NIP. 19690605 199303 1 007 RISMAN WARCHAN ZULIANTO
NIP. 19770623 200501 1 013 ........................... Tim Leader Direktur
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : III ( Tiga )


Periode : 07 Juni 2021 sampai dengan 13 Juni 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
I PEKERJAAN PERSIAPAN
1 Pembuatan Papan Nama Pekerjaan 1.00 bh 250,000.00 250,000.00 0.038 - - 1.000 0.038 1.000 0.038
2 Pengukuran dan Pemasangan Bouwplank 28.56 m 12,198.91 348,400.73 0.053 28.560 0.053 - - 28.560 0.053
3 Pembuatan bedeng pekerja 9.00 m2 383,330.04 3,449,970.32 0.527 - - 9.000 0.527 9.000 0.527
4 Mobilisasi Demobilisasi Alat Berat 1.00 ls 2,500,000.00 2,500,000.00 0.382 - - - - - -
5 Pembuatan akses menuju badan sungai sementara 24.00 m2 113,128.49 2,715,083.64 0.415 - - - - - -
6 Dewatering dengan pompa air diesel 40.00 jam 25,000.00 1,000,000.00 0.153 - - - - - -
7 SMKK 1.00 ls 4,325,000.00 4,325,000.00 0.661 0.091 0.060 0.045 0.030 0.136 0.090
14,588,454.69 2.228 28.651 0.113 10.045 0.595 38.696 0.708
II PEKERJAAN PERBAIKAN TALUD SEGMEN 5
A PEKERJAAN TANAH DAN BETON BERTULANG
1 Penggalian 1 M3 Tanah Biasa 50.00 m3 67,972.30 3,398,615.01 0.519 - - - - - -
2 Pengurugan Kembali 1 M3 Galian Tanah 33.15 m3 49,023.50 1,625,129.04 0.248 - - - - - -
3 Bongkaran Pasangan Batu dan Beton Eksisting 50.00 m3 71,953.20 3,597,660.02 0.550 - - - - - -
4 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area 50.00 m3 19,888.18 994,408.76 0.152 - - - - - -
5 Pemadatan Tanah Eksisting 11.84 m3 49,023.50 580,438.24 0.089 - - - - - -
6 Pengurugan dengan pasir urug 5.92 m3 178,388.92 1,056,062.41 0.161 - - - - - -
7 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 2.96 m3 737,396.00 2,182,692.15 0.333 - - - - - -
8 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 10.00 m3 872,242.00 8,722,419.97 1.332 - - - - - -
9 Pekerjaan Beton Dinding Talud Beton
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 10.00 m3 872,242.00 8,722,419.97 1.332 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 1,000.00 kg 11,860.70 11,860,698.15 1.812 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 40.00 m2 316,861.88 12,674,475.27 1.936 - - - - - -
10 Pekerjaan Beton Sloof 20x30cm
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 4.74 m3 872,242.00 4,134,427.07 0.632 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 400.00 kg 11,860.70 4,744,279.26 0.725 - - - - - -
c Memasang Bekisting untuk Sloof (dipakai 2 kali) 47.36 m2 89,375.55 4,232,825.87 0.647 - - - - - -
11 Pekerjaan Beton Konsul Cantilever
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 7.75 m3 872,242.00 6,759,875.48 1.033 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 700.00 kg 11,860.70 8,302,488.71 1.268 - - - - - -
c Memasang Bekisting untuk Balok (dipakai 2 kali) 40.00 m2 120,181.13 4,807,245.27 0.734 - - - - - -
12 Pekerjaan Plat Beton tebal 12 cm
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 10.00 m3 872,242.00 8,722,419.97 1.332 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis 700.00 kg 10,697.66 7,488,358.68 1.144 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 30.00 m2 316,861.88 9,505,856.45 1.452 - - - - - -
13 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 13.00 m 77,312.85 1,005,067.10 0.154 - - - - - -
14 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 38.37 m 86,676.29 3,325,769.35 0.508 - - - - - -
15 Memasang Stek Besi 200.00 kg 11,860.70 2,372,139.63 0.362 - - - - - -
16 Pekerjaan Plat Beton Pot tebal 10 cm
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 4.74 m3 872,242.00 4,134,427.07 0.632 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 200.00 kg 11,860.70 2,372,139.63 0.362 - - - - - -
c Bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm 30.00 m2 118,158.83 3,544,764.95 0.541 - - - - - -
130,867,103.48 19.989 - - - - - -
B PEKERJAAN PASANGAN DINDING
1 Pemasangan Dinding Bata Merah Bakar Sekam Tebal 1/2 Bata Camp. 1SP 6PP 42.00 m2 116,576.48 4,896,212.34 0.748 - - - - - -
2 Pemasangan Plesteran 1 Pc 6 Pp Tebal 15 mm 84.00 m2 54,689.70 4,593,934.71 0.702 - - - - - -
3 Pemasangan Acian 210.00 m2 33,411.23 7,016,358.16 1.072 - - - - - -
4 Pemasangan Plesteran Skoning 1 Pc 2Pp lebar 10 cm 360.00 m 55,075.90 19,827,324.36 3.028 - - - - - -
5 Pemasangan Kepala Kolom 10.00 bh 50,000.00 500,000.00 0.076 - - - - - -
36,833,829.57 5.626 - - - - - -
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PENGECATAN
1 Pengecatan Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Weathershield luar ruangan 210.00 m2 11,686.42 2,454,148.34 0.375 - - - - - -
2,454,148.34 0.375 - - - - - -

Laporan Progres Mingguan ke-3


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
B PEKERJAAN RUMAH TERDAMPAK
I. PEKERJAAN BONGKARAN
1 Membongkar 1 m2 genteng / sirap untuk dipergunakan lagi 103.90 m2 3,628.42 376,993.05 0.058 - - - - - -
2 Membongkar 1 m3 kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi 0.46 m3 991,595.91 456,134.12 0.070 - - - - - -
3 Pembongkaran 1 m3 pasangan bata merah dan membersihkan 40.86 m3 185,908.38 7,596,216.24 1.160 - - - - - -
4 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 9.20 m3 688,832.33 6,337,257.47 0.968 - - - - - -
II. PEKERJAAN TANAH
1 Menggali 1 m3 tanah biasa sedalam 1 meter 22.32 m3 67,972.30 1,517,141.74 0.232 - - - - - -
III. PEKERJAAN PONDASI
1 Memasang 1 m3 pondasi batu belah, campuran 1 PC 6 PP 17.28 m2 665,195.09 11,494,571.24 1.756 - - - - - -
IV. PEKERJAAN BETON
1 Membuat 1 m3 Sloof beton bertulang (200 kg besi + bekisting) 3.55 m3 3,844,764.87 13,648,915.30 2.085 - - - - - -
2 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) 4.94 m3 7,083,735.01 34,993,650.96 5.345 - - - - - -
3 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) 5 m3 5,659,422.09 28,297,110.46 4.322 - - - - - -
V. PEKERJAAN DINDING
1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP 127.00 m2 116,576.48 14,805,213.51 2.261 - - - - - -
VI PEKERJAAN KAYU
1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.50 m3 16,443,774.77 8,221,887.38 1.256 - - - - - -
2 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti 12.72 m2 644,715.80 8,200,785.00 1.253 - - - - - -
3 Memasang 1 m3 konstruksi gordeng, kayu glugu 0.21 m3 4,450,537.65 934,612.91 0.143 - - - - - -
VII. PEKERJAAN PLESTERAN
1 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm 100.00 m2 54,689.70 5,468,969.90 0.835 - - - - - -
2 Memasang 1 m2 acian 100.00 m2 33,411.23 3,341,122.93 0.510 - - - - - -
VIII. PEKERJAAN PENGECATAN
1 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 100.00 m2 11,686.42 1,168,642.06 0.179 - - - - - -
IX. PEKERJAAN PENUTUP ATAP
1 Memasang 1 m2 Atap Galvalum (Paket) 78.20 m3 190,000.00 14,858,000.00 2.269 - - - - - -
X. PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Memasang 1 m2 lantai keramik (30 x 30) cm 8.54 m2 114,193.22 975,210.13 0.149 - - - - - -
XI. PEKERJAAN SANITASI
1 Memasang 1 buah Kloset Jongkok Porselen 2.00 bh 280,952.58 561,905.16 0.086 - - - - - -
2 Memasang 1 m Pipa PVC tipe AW 24.00 m2 19,406.20 465,748.90 0.071 - - - - - -
3 Memasang 1 m Pipa PVC tipe AW 1 24.00 m2 22,254.33 534,103.90 0.082 - - - - - -
4 Memasang 1 m Pipa PVC tipe AW 3 24.00 m2 63,036.61 1,512,878.67 0.231 - - - - - -
5 Memasang 1 buah Kran atau 2.00 m2 46,068.18 92,136.37 0.014 - - - - - -
6 Memasang 1 buah Floor Drain 2.00 m3 80,836.18 161,672.35 0.025 - - - - - -
7 Memasang 1 buah Pintu Kamar Mandi 2.00 bh 650,000.00 1,300,000.00 0.199 - - - - - -
167,320,879.74 25.557 - - - - - -
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PEMBERSIHAN SALURAN
1 Penggalian Tanah Lumpur dan Endapan Limbah Sedalam 30 cm 85.36 m3 109,311.98 9,330,870.22 1.425 - - - - - -
2 Pembersihan dan Pembuangan Tanah Lumpur dan Limbah Keluar Area 85.36 m3 29,796.55 2,543,433.77 0.388 - - - - - -
3 Pemadatan Tanah Eksisting 48.91 m3 49,023.50 2,397,739.40 0.366 - - - - - -
4 Pengurugan dengan pasir urug, 10 cm 17.07 m3 178,388.92 3,045,098.87 0.465 - - - - - -
5 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 17.07 m3 737,396.00 12,587,349.68 1.923 - - - - - -
6 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 17.07 m3 872,242.00 14,889,170.90 2.274 - - - - - -
7 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 466.40 m 77,312.85 36,058,714.99 5.508 - - - - - -
8 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 466.40 m 86,676.29 40,425,822.86 6.175 - - - - - -
9 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,2m, K.300 65.00 bh 626,150.00 40,699,750.00 6.217 - - - - - -
10 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,8m, K.300 32.00 bh 750,000.00 24,000,000.00 3.666 - - - - - -
185,977,950.68 28.407 - - -

Laporan Progres Mingguan ke-3


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
B PEKERJAAN JARINGAN IPAL KOMUNAL
1 Pekerjaan Galian Tanah Pipa 81.86 m3 67,972.30 5,564,212.49 0.850 - - - - - -
2 Pengurugan dengan pasir urug 6.82 m3 178,388.92 1,216,612.43 0.186 - - - - - -
3 Pengurugan Kembali 1 M3 Galian Tanah 24.56 m3 49,023.50 1,204,017.17 0.184 - - - - - -
4 Pemasangan 1 M Pipa PVC tipe AW 4 30.00 m 90,907.55 2,727,226.46 0.417 - - - - - -
5 Saluran Pipa Air Limbah SDR - 41, Dia 15 cm , inc. fitting & Assecories 343.20 m 133,200.00 45,714,240.00 6.983 - - - - - -
6 Saluran Pipa Air Limbah SDR - 41, Dia 20 cm, , inc. fitting & Assecories 113.70 m 203,900.00 23,183,430.00 3.541 - - - - - -
7 Pemasangan Clean Out Inc. Fitting & Assecories 17.00 ttk 185,000.00 3,145,000.00 0.480 - - - - - -
8 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 100 org, 20 m3 / hari, 1 unit 7,500,000.00 7,500,000.00 1.146 - - - - - -
(Galian, Urugan, Pondasi, Tutup Beton, Penyambungan Instalasi)
9 Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm 4.00 unit 975,000.00 3,900,000.00 0.596 - - - - - -
10 Pekerjaan Sumur Resapan, Dia 100 cm, Kedalaman 2 m, Inc. Tutup Beton Berlubang 15.00 ttk 500,000.00 7,500,000.00 1.146 - - - - - -
11 Grill Beton Penutup Sumur Resapan 20.00 unit 750,000.00 15,000,000.00 2.291 - - - - - -
116,654,738.56 17.818 - - - - - -

JUMLAH 654,697,105.06 100.000 - 0.113 - 0.595 - 0.708


PRESTASI MINGGU LALU 0.113
PRESTASI MINGGU INI 0.595
PRESTASI SAMPAI DENGAN MINGGU INI 0.708
PRESTASI MENURUT SCHEDULE 1.314
LEBIH CEPAT (+) / TERLAMBAT (-) (0.606)

Yogyakarta, 14 Juni 2021


di buat oleh,
KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA

Noor Hasan Bambang Erlianto


Pengawas Pelaksana

Laporan Progres Mingguan ke-3


REKAPITULASI
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : III ( Tiga )


Periode : 07 Juni 2021 sampai dengan 13 Juni 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO PEKERJAAN PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp (%) BOBOT % BOBOT % BOBOT %

I PEKERJAAN PERSIAPAN 14,588,454.69 2.228 0.113 0.595 0.708

II PEKERJAAN PERBAIKAN TALUD SEGMEN 5


A PEKERJAAN TANAH DAN BETON BERTULANG 130,867,103.48 19.989 - - -
B PEKERJAAN PASANGAN DINDING 36,833,829.57 5.626 - - -

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PENGECATAN 2,454,148.34 0.375 - - -
B PEKERJAAN RUMAH TERDAMPAK 167,320,879.74 25.557 - - -

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PEMBERSIHAN SALURAN 185,977,950.68 28.407 - - -
B PEKERJAAN JARINGAN IPAL KOMUNAL 116,654,738.56 17.818 - - -

JUMLAH 654,697,105.06 100.000 0.113 0.595 0.708


PRESTASI MINGGU LALU 0.113
PRESTASI MINGGU INI 0.595
PRESTASI SAMPAI DENGAN MINGGU INI 0.708
PRESTASI MENURUT SCHEDULE 1.314
LEBIH CEPAT (+) / TERLAMBAT (-) (0.606)

Yogyakarta, 14 Juni 2021


di buat oleh,
PEJABAT PEMBUAT KOMITMEN TIM TEKNIS KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA
1. Cicilia Novi hendrawati, M.SC., M.Eng.
NIP. 19781102 200501 2 011 ...........................

2. Danang Dwi Wahyujati,S.Kom.,M.Eng


NIP. 19761028 199803 1 004 ...........................
SIGIT SETIAWAN, ST.MT 3. Sudaryanto
NIP. 19690605 199303 1 007 RISMAN WARCHAN ZULIANTO
NIP. 19770623 200501 1 013 ........................... Tim Leader Direktur
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : IV ( Empat )


Periode : 14 Juni 2021 sampai dengan 20 Juni 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
I PEKERJAAN PERSIAPAN
1 Pembuatan Papan Nama Pekerjaan 1.00 bh 250,000.00 250,000.00 0.038 1.000 0.038 - - 1.000 0.038
2 Pengukuran dan Pemasangan Bouwplank 28.56 m 12,198.91 348,400.73 0.053 28.560 0.053 - - 28.560 0.053
3 Pembuatan bedeng pekerja 9.00 m2 383,330.04 3,449,970.32 0.527 9.000 0.527 - - 9.000 0.527
4 Mobilisasi Demobilisasi Alat Berat 1.00 ls 2,500,000.00 2,500,000.00 0.382 - - - - - -
5 Pembuatan akses menuju badan sungai sementara 24.00 m2 113,128.49 2,715,083.64 0.415 - - - - - -
6 Dewatering dengan pompa air diesel 40.00 jam 25,000.00 1,000,000.00 0.153 - - - - - -
7 SMKK 1.00 ls 4,325,000.00 4,325,000.00 0.661 0.136 0.090 0.045 0.030 0.182 0.120
14,588,454.69 2.228 38.696 0.708 0.045 0.030 38.742 0.738
II PEKERJAAN PERBAIKAN TALUD SEGMEN 5
A PEKERJAAN TANAH DAN BETON BERTULANG
1 Penggalian 1 M3 Tanah Biasa 50.00 m3 67,972.30 3,398,615.01 0.519 - - - - - -
2 Pengurugan Kembali 1 M3 Galian Tanah 33.15 m3 49,023.50 1,625,129.04 0.248 - - - - - -
3 Bongkaran Pasangan Batu dan Beton Eksisting 50.00 m3 71,953.20 3,597,660.02 0.550 - - - - - -
4 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area 50.00 m3 19,888.18 994,408.76 0.152 - - - - - -
5 Pemadatan Tanah Eksisting 11.84 m3 49,023.50 580,438.24 0.089 - - - - - -
6 Pengurugan dengan pasir urug 5.92 m3 178,388.92 1,056,062.41 0.161 - - - - - -
7 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 2.96 m3 737,396.00 2,182,692.15 0.333 - - - - - -
8 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 10.00 m3 872,242.00 8,722,419.97 1.332 - - - - - -
9 Pekerjaan Beton Dinding Talud Beton
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 10.00 m3 872,242.00 8,722,419.97 1.332 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 1,000.00 kg 11,860.70 11,860,698.15 1.812 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 40.00 m2 316,861.88 12,674,475.27 1.936 - - - - - -
10 Pekerjaan Beton Sloof 20x30cm
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 4.74 m3 872,242.00 4,134,427.07 0.632 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 400.00 kg 11,860.70 4,744,279.26 0.725 - - - - - -
c Memasang Bekisting untuk Sloof (dipakai 2 kali) 47.36 m2 89,375.55 4,232,825.87 0.647 - - - - - -
11 Pekerjaan Beton Konsul Cantilever
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 7.75 m3 872,242.00 6,759,875.48 1.033 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 700.00 kg 11,860.70 8,302,488.71 1.268 - - - - - -
c Memasang Bekisting untuk Balok (dipakai 2 kali) 40.00 m2 120,181.13 4,807,245.27 0.734 - - - - - -
12 Pekerjaan Plat Beton tebal 12 cm
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 10.00 m3 872,242.00 8,722,419.97 1.332 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis 700.00 kg 10,697.66 7,488,358.68 1.144 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 30.00 m2 316,861.88 9,505,856.45 1.452 - - - - - -
13 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 13.00 m 77,312.85 1,005,067.10 0.154 - - - - - -
14 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 38.37 m 86,676.29 3,325,769.35 0.508 - - - - - -
15 Memasang Stek Besi 200.00 kg 11,860.70 2,372,139.63 0.362 - - - - - -
16 Pekerjaan Plat Beton Pot tebal 10 cm
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 4.74 m3 872,242.00 4,134,427.07 0.632 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 200.00 kg 11,860.70 2,372,139.63 0.362 - - - - - -
c Bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm 30.00 m2 118,158.83 3,544,764.95 0.541 - - - - - -
130,867,103.48 19.989 - - - - - -
B PEKERJAAN PASANGAN DINDING
1 Pemasangan Dinding Bata Merah Bakar Sekam Tebal 1/2 Bata Camp. 1SP 6PP 42.00 m2 116,576.48 4,896,212.34 0.748 - - - - - -
2 Pemasangan Plesteran 1 Pc 6 Pp Tebal 15 mm 84.00 m2 54,689.70 4,593,934.71 0.702 - - - - - -
3 Pemasangan Acian 210.00 m2 33,411.23 7,016,358.16 1.072 - - - - - -
4 Pemasangan Plesteran Skoning 1 Pc 2Pp lebar 10 cm 360.00 m 55,075.90 19,827,324.36 3.028 - - - - - -
5 Pemasangan Kepala Kolom 10.00 bh 50,000.00 500,000.00 0.076 - - - - - -
36,833,829.57 5.626 - - - - - -
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PENGECATAN
1 Pengecatan Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Weathershield luar ruangan 210.00 m2 11,686.42 2,454,148.34 0.375 - - - - - -
2,454,148.34 0.375 - - - - - -

Laporan Progres Mingguan ke-4


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
B PEKERJAAN RUMAH TERDAMPAK
I. PEKERJAAN BONGKARAN
1 Membongkar 1 m2 genteng / sirap untuk dipergunakan lagi 103.90 m2 3,628.42 376,993.05 0.058 - - - - - -
2 Membongkar 1 m3 kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi 0.46 m3 991,595.91 456,134.12 0.070 - - - - - -
3 Pembongkaran 1 m3 pasangan bata merah dan membersihkan 40.86 m3 185,908.38 7,596,216.24 1.160 - - - - - -
4 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 9.20 m3 688,832.33 6,337,257.47 0.968 - - - - - -
II. PEKERJAAN TANAH
1 Menggali 1 m3 tanah biasa sedalam 1 meter 22.32 m3 67,972.30 1,517,141.74 0.232 - - - - - -
III. PEKERJAAN PONDASI
1 Memasang 1 m3 pondasi batu belah, campuran 1 PC 6 PP 17.28 m2 665,195.09 11,494,571.24 1.756 - - - - - -
IV. PEKERJAAN BETON
1 Membuat 1 m3 Sloof beton bertulang (200 kg besi + bekisting) 3.55 m3 3,844,764.87 13,648,915.30 2.085 - - - - - -
2 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) 4.94 m3 7,083,735.01 34,993,650.96 5.345 - - - - - -
3 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) 5 m3 5,659,422.09 28,297,110.46 4.322 - - - - - -
V. PEKERJAAN DINDING
1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP 127.00 m2 116,576.48 14,805,213.51 2.261 - - - - - -
VI PEKERJAAN KAYU
1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.50 m3 16,443,774.77 8,221,887.38 1.256 - - - - - -
2 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti 12.72 m2 644,715.80 8,200,785.00 1.253 - - - - - -
3 Memasang 1 m3 konstruksi gordeng, kayu glugu 0.21 m3 4,450,537.65 934,612.91 0.143 - - - - - -
VII. PEKERJAAN PLESTERAN
1 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm 100.00 m2 54,689.70 5,468,969.90 0.835 - - - - - -
2 Memasang 1 m2 acian 100.00 m2 33,411.23 3,341,122.93 0.510 - - - - - -
VIII. PEKERJAAN PENGECATAN
1 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 100.00 m2 11,686.42 1,168,642.06 0.179 - - - - - -
IX. PEKERJAAN PENUTUP ATAP
1 Memasang 1 m2 Atap Galvalum (Paket) 78.20 m3 190,000.00 14,858,000.00 2.269 - - - - - -
X. PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Memasang 1 m2 lantai keramik (30 x 30) cm 8.54 m2 114,193.22 975,210.13 0.149 - - - - - -
XI. PEKERJAAN SANITASI
1 Memasang 1 buah Kloset Jongkok Porselen 2.00 bh 280,952.58 561,905.16 0.086 - - - - - -
2 Memasang 1 m Pipa PVC tipe AW 24.00 m2 19,406.20 465,748.90 0.071 - - - - - -
3 Memasang 1 m Pipa PVC tipe AW 1 24.00 m2 22,254.33 534,103.90 0.082 - - - - - -
4 Memasang 1 m Pipa PVC tipe AW 3 24.00 m2 63,036.61 1,512,878.67 0.231 - - - - - -
5 Memasang 1 buah Kran atau 2.00 m2 46,068.18 92,136.37 0.014 - - - - - -
6 Memasang 1 buah Floor Drain 2.00 m3 80,836.18 161,672.35 0.025 - - - - - -
7 Memasang 1 buah Pintu Kamar Mandi 2.00 bh 650,000.00 1,300,000.00 0.199 - - - - - -
167,320,879.74 25.557 - - - - - -
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PEMBERSIHAN SALURAN
1 Penggalian Tanah Lumpur dan Endapan Limbah Sedalam 30 cm 85.36 m3 109,311.98 9,330,870.22 1.425 - - - - - -
2 Pembersihan dan Pembuangan Tanah Lumpur dan Limbah Keluar Area 85.36 m3 29,796.55 2,543,433.77 0.388 - - - - - -
3 Pemadatan Tanah Eksisting 48.91 m3 49,023.50 2,397,739.40 0.366 - - - - - -
4 Pengurugan dengan pasir urug, 10 cm 17.07 m3 178,388.92 3,045,098.87 0.465 - - - - - -
5 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 17.07 m3 737,396.00 12,587,349.68 1.923 - - - - - -
6 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 17.07 m3 872,242.00 14,889,170.90 2.274 - - - - - -
7 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 466.40 m 77,312.85 36,058,714.99 5.508 - - - - - -
8 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 466.40 m 86,676.29 40,425,822.86 6.175 - - - - - -
9 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,2m, K.300 65.00 bh 626,150.00 40,699,750.00 6.217 - - - - - -
10 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,8m, K.300 32.00 bh 750,000.00 24,000,000.00 3.666 - - - - - -
185,977,950.68 28.407 - - -

Laporan Progres Mingguan ke-4


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
B PEKERJAAN JARINGAN IPAL KOMUNAL
1 Pekerjaan Galian Tanah Pipa 81.86 m3 67,972.30 5,564,212.49 0.850 - - - - - -
2 Pengurugan dengan pasir urug 6.82 m3 178,388.92 1,216,612.43 0.186 - - - - - -
3 Pengurugan Kembali 1 M3 Galian Tanah 24.56 m3 49,023.50 1,204,017.17 0.184 - - - - - -
4 Pemasangan 1 M Pipa PVC tipe AW 4 30.00 m 90,907.55 2,727,226.46 0.417 - - - - - -
5 Saluran Pipa Air Limbah SDR - 41, Dia 15 cm , inc. fitting & Assecories 343.20 m 133,200.00 45,714,240.00 6.983 - - - - - -
6 Saluran Pipa Air Limbah SDR - 41, Dia 20 cm, , inc. fitting & Assecories 113.70 m 203,900.00 23,183,430.00 3.541 - - - - - -
7 Pemasangan Clean Out Inc. Fitting & Assecories 17.00 ttk 185,000.00 3,145,000.00 0.480 - - - - - -
8 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 100 org, 20 m3 / hari, 1 unit 7,500,000.00 7,500,000.00 1.146 - - - - - -
(Galian, Urugan, Pondasi, Tutup Beton, Penyambungan Instalasi)
9 Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm 4.00 unit 975,000.00 3,900,000.00 0.596 - - - - - -
10 Pekerjaan Sumur Resapan, Dia 100 cm, Kedalaman 2 m, Inc. Tutup Beton Berlubang 15.00 ttk 500,000.00 7,500,000.00 1.146 - - - - - -
11 Grill Beton Penutup Sumur Resapan 20.00 unit 750,000.00 15,000,000.00 2.291 - - - - - -
116,654,738.56 17.818 - - - - - -

JUMLAH 654,697,105.06 100.000 - 0.708 - 0.030 - 0.738


PRESTASI MINGGU LALU 0.708
PRESTASI MINGGU INI 0.030
PRESTASI SAMPAI DENGAN MINGGU INI 0.738
PRESTASI MENURUT SCHEDULE 2.251
LEBIH CEPAT (+) / TERLAMBAT (-) (1.512)

Yogyakarta, 21 Juni 2021


di buat oleh,
KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA

Noor Hasan Bambang Erlianto


Pengawas Pelaksana

Laporan Progres Mingguan ke-4


REKAPITULASI
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : IV ( Empat )


Periode : 14 Juni 2021 sampai dengan 20 Juni 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO PEKERJAAN PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp (%) BOBOT % BOBOT % BOBOT %

I PEKERJAAN PERSIAPAN 14,588,454.69 2.228 0.708 0.030 0.738

II PEKERJAAN PERBAIKAN TALUD SEGMEN 5


A PEKERJAAN TANAH DAN BETON BERTULANG 130,867,103.48 19.989 - - -
B PEKERJAAN PASANGAN DINDING 36,833,829.57 5.626 - - -

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PENGECATAN 2,454,148.34 0.375 - - -
B PEKERJAAN RUMAH TERDAMPAK 167,320,879.74 25.557 - - -

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PEMBERSIHAN SALURAN 185,977,950.68 28.407 - - -
B PEKERJAAN JARINGAN IPAL KOMUNAL 116,654,738.56 17.818 - - -

JUMLAH 654,697,105.06 100.000 0.708 0.030 0.738


PRESTASI MINGGU LALU 0.708
PRESTASI MINGGU INI 0.030
PRESTASI SAMPAI DENGAN MINGGU INI 0.738
PRESTASI MENURUT SCHEDULE 2.251
LEBIH CEPAT (+) / TERLAMBAT (-) (1.512)

Yogyakarta, 21 Juni 2021


di buat oleh,
PEJABAT PEMBUAT KOMITMEN TIM TEKNIS KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA
1. Cicilia Novi hendrawati, M.SC., M.Eng.
NIP. 19781102 200501 2 011 ...........................

2. Danang Dwi Wahyujati,S.Kom.,M.Eng


NIP. 19761028 199803 1 004 ...........................
SIGIT SETIAWAN, ST.MT 3. Sudaryanto
NIP. 19690605 199303 1 007 RISMAN WARCHAN ZULIANTO
NIP. 19770623 200501 1 013 ........................... Tim Leader Direktur
DAFTAR KUANTITAS DAN HARGA

PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN


LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TANHUN ANGGARAN : 2021

HARGA SATUAN JUMLAH + PAJAK JUMLAH HARGA JUMLAH


NO URAIAN PEKERJAAN VOLUME
Rp 10% Rp Rp
I PEKERJAAN PERSIAPAN
1 Pembuatan Papan Nama Pekerjaan 1.00 bh 250,000.00 25,000.00 275,000.00
2 Pengukuran dan Pemasangan Bouwplank 28.56 m 12,198.91 34,840.07 383,240.80
3 Pembuatan bedeng pekerja 9.00 m2 383,330.04 344,997.03 3,794,967.35
4 Mobilisasi Demobilisasi Alat Berat 1.00 ls 2,500,000.00 250,000.00 2,750,000.00
5 Pembuatan akses menuju badan sungai sementara 24.00 m2 113,128.49 271,508.36 2,986,592.01
6 Dewatering dengan pompa air diesel 40.00 jam 25,000.00 100,000.00 1,100,000.00
7 SMKK 1.00 ls 4,325,000.00 432,500.00 4,757,500.00
16,047,300.16
II PEKERJAAN PERBAIKAN TALUD SEGMEN 5
A PEKERJAAN TANAH DAN BETON BERTULANG
1 Penggalian 1 M3 Tanah Biasa 50.00 m3 67,972.30 339,861.50 3,738,476.51
2 Pengurugan Kembali 1 M3 Galian Tanah 33.15 m3 49,023.50 162,512.90 1,787,641.94
3 Bongkaran Pasangan Batu dan Beton Eksisting 50.00 m3 71,953.20 359,766.00 3,957,426.03
4 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area 50.00 m3 19,888.18 99,440.88 1,093,849.63
5 Pemadatan Tanah Eksisting 11.84 m3 49,023.50 58,043.82 638,482.07
6 Pengurugan dengan pasir urug 5.92 m3 178,388.92 105,606.24 1,161,668.65
7 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 2.96 m3 737,396.00 218,269.22 2,400,961.37
8 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 10.00 m3 872,242.00 872,242.00 9,594,661.97
9 Pekerjaan Beton Dinding Talud Beton
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 10.00 m3 872,242.00 872,242.00 9,594,661.97
b Pembesian dg Besi Polos atau Besi Ulir 1,000.00 kg 11,860.70 1,186,069.82 13,046,767.97
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 40.00 m2 316,861.88 1,267,447.53 13,941,922.80
10 Pekerjaan Beton Sloof 20x30cm
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 4.74 m3 872,242.00 413,442.71 4,547,869.77
b Pembesian dg Besi Polos atau Besi Ulir 400.00 kg 11,860.70 474,427.93 5,218,707.19
13 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 13.00 m 77,312.85 100,506.71 1,105,573.81
14 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 38.37 m 86,676.29 332,576.93 3,658,346.28
15 Memasang Stek Besi 200.00 kg 11,860.70 237,213.96 2,609,353.59
16 Pekerjaan Plat Beton Pot tebal 10 cm
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Mole 4.74 m3 872,242.00 413,442.71 4,547,869.77
b Pembesian dg Besi Polos atau Besi Ulir 200.00 kg 11,860.70 237,213.96 2,609,353.59
c Bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm 30.00 m2 118,158.83 354,476.50 3,899,241.45
143,953,813.83
B PEKERJAAN PASANGAN DINDING
1 Pemasangan Dinding Bata Merah Bakar Sekam Tebal 1/2 Bata Camp. 1SP 6PP 42.00 m2 116,576.48 489,621.23 5,385,833.58
2 Pemasangan Plesteran 1 Pc 6 Pp Tebal 15 mm 84.00 m2 54,689.70 459,393.47 5,053,328.19
3 Pemasangan Acian 210.00 m2 33,411.23 701,635.82 7,717,993.97
4 Pemasangan Plesteran Skoning 1 Pc 2Pp lebar 10 cm 360.00 m 55,075.90 1,982,732.44 21,810,056.79
5 Pemasangan Kepala Kolom 10.00 bh 50,000.00 50,000.00 550,000.00
40,517,212.53
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PENGECATAN
1 Pengecatan Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Weathe 210.00 m2 11,686.42 245,414.83 2,699,563.17
2,699,563.17
B PEKERJAAN RUMAH TERDAMPAK
I. PEKERJAAN BONGKARAN
1 Membongkar 1 m2 genteng / sirap untuk dipergunakan lagi 103.90 m2 3,628.42 37,699.30 414,692.35
2 Membongkar 1 m3 kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan 0.46 m3 991,595.91 45,613.41 501,747.53
3 Pembongkaran 1 m3 pasangan bata merah dan membersihkan 40.86 m3 185,908.38 759,621.62 8,355,837.86
4 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 9.20 m3 688,832.33 633,725.75 6,970,983.21
II. PEKERJAAN TANAH
1 Menggali 1 m3 tanah biasa sedalam 1 meter 22.32 m3 67,972.30 151,714.17 1,668,855.91
III. PEKERJAAN PONDASI
1 Memasang 1 m3 pondasi batu belah, campuran 1 PC 6 PP 17.28 m2 665,195.09 1,149,457.12 12,644,028.36
IV. PEKERJAAN BETON
1 Membuat 1 m3 Sloof beton bertulang (200 kg besi + bekisting) 3.55 m3 3,844,764.87 1,364,891.53 15,013,806.83
2 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) 4.94 m3 7,083,735.01 3,499,365.10 38,493,016.06
3 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) 5 m3 5,659,422.09 2,829,711.05 31126821.510708
V. PEKERJAAN DINDING
1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, camp 127.00 m2 116,576.48 1,480,521.35 16,285,734.87
VI PEKERJAAN KAYU
1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.50 m3 16,443,774.77 822,188.74 9,044,076.12
2 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti 12.72 m2 644,715.80 820,078.50 9,020,863.50
3 Memasang 1 m3 konstruksi gordeng, kayu glugu 0.21 m3 4,450,537.65 93,461.29 1,028,074.20
VII. PEKERJAAN PLESTERAN
1 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm 100.00 m2 54,689.70 546,896.99 6,015,866.89
2 Memasang 1 m2 acian 100.00 m2 33,411.23 334,112.29 3,675,235.23
VIII. PEKERJAAN PENGECATAN
1 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup 100.00 m2 11,686.42 116,864.21 1,285,506.27
IX. PEKERJAAN PENUTUP ATAP
1 Memasang 1 m2 Atap Galvalum (Paket) 78.20 m3 190,000.00 1,485,800.00 16,343,800.00
X. PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Memasang 1 m2 lantai keramik (30 x 30) cm 8.54 m2 114,193.22 97,521.01 1,072,731.14
HARGA SATUAN JUMLAH + PAJAK JUMLAH HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME
Rp 10% Rp Rp
XI. PEKERJAAN SANITASI
1 Memasang 1 buah Kloset Jongkok Porselen 2.00 bh 280,952.58 56,190.52 618,095.68
2 Memasang 1 m Pipa PVC tipe AW 24.00 m2 19,406.20 46,574.89 512,323.79
3 Memasang 1 m Pipa PVC tipe AW 1 24.00 m2 22,254.33 53,410.39 587,514.29
4 Memasang 1 m Pipa PVC tipe AW 3 24.00 m2 63,036.61 151,287.87 1,664,166.53
5 Memasang 1 buah Kran atau 2.00 m2 46,068.18 9,213.64 101,350.00
6 Memasang 1 buah Floor Drain 2.00 m3 80,836.18 16,167.24 177,839.59
7 Memasang 1 buah Pintu Kamar Mandi 2.00 bh 650,000.00 130,000.00 1,430,000.00
184,052,967.72
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PEMBERSIHAN SALURAN
1 Penggalian Tanah Lumpur dan Endapan Limbah Sedalam 30 cm 85.36 m3 109,311.98 933,087.02 10,263,957.24
2 Pembersihan dan Pembuangan Tanah Lumpur dan Limbah Keluar Area 85.36 m3 29,796.55 254,343.38 2,797,777.15
3 Pemadatan Tanah Eksisting 48.91 m3 49,023.50 239,773.94 2,637,513.35
4 Pengurugan dengan pasir urug, 10 cm 17.07 m3 178,388.92 304,509.89 3,349,608.75
5 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 17.07 m3 737,396.00 1,258,734.97 13,846,084.64
6 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 17.07 m3 872,242.00 1,488,917.09 16,378,087.99
7 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 466.40 m 77,312.85 3,605,871.50 39,664,586.49
8 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 466.40 m 86,676.29 4,042,582.29 44,468,405.15
9 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,2m, K.300 65.00 bh 626,150.00 4,069,975.00 44,769,725.00
10 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,8m, K.300 32.00 bh 750,000.00 2,400,000.00 26,400,000.00
204,575,745.75
B PEKERJAAN JARINGAN IPAL KOMUNAL
1 Pekerjaan Galian Tanah Pipa 81.86 m3 67,972.30 556,421.25 6,120,633.74
2 Pengurugan dengan pasir urug 6.82 m3 178,388.92 121,661.24 1,338,273.68
3 Pengurugan Kembali 1 M3 Galian Tanah 24.56 m3 49,023.50 120,401.72 1,324,418.89
4 Pemasangan 1 M Pipa PVC tipe AW 4 30.00 m 90,907.55 272,722.65 2,999,949.10
5 Saluran Pipa Air Limbah SDR - 41, Dia 15 cm , inc. fitting & Assecories 343.20 m 133,200.00 4,571,424.00 50,285,664.00
6 Saluran Pipa Air Limbah SDR - 41, Dia 20 cm, , inc. fitting & Assecories 113.70 m 203,900.00 2,318,343.00 25,501,773.00
7 Pemasangan Clean Out Inc. Fitting & Assecories 17.00 ttk 185,000.00 314,500.00 3,459,500.00
8 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), ka 1 unit 7,500,000.00 750,000.00 8250000
9 Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm 4.00 unit 975,000.00 390,000.00 4,290,000.00
10 Pekerjaan Sumur Resapan, Dia 100 cm, Kedalaman 2 m, Inc. Tutup Beton Berlub 15.00 ttk 500,000.00 750,000.00 8,250,000.00
11 Grill Beton Penutup Sumur Resapan 20.00 unit 750,000.00 1,500,000.00 16,500,000.00
128,320,212.41

Bantul, 22 April 2021


penawar,
CV. ALMEERA RAYA

WARCHAN ZULIANTO
Direktur
JADWAL WAKTU PELAKSANAAN PEKERJAAN
( MUTUAL CHECK 0% )
INSTANSI : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021

BULAN KE-1 BULAN KE-2 BULAN KE-3 BULAN KE-4


KONTRAK MC 0 KONTRAK MC 0
Ming.1 Ming.2 Ming.3 Ming.4 Ming.5 Ming.6 Ming.7 Ming.8 Ming.9 Ming.10 Ming.11 Ming.12 Ming.13 Ming.14 Ming.15 Ming.16 Ming.17 Ming.18 Ming.19 Ming.20 Ming.21 Ming.22
NO JENIS PEKERJAAN 24/05/21 31/05/21 07/06/21 14/06/21 21/06/21 28/06/21 05/07/21 12/07/21 19/07/21 26/07/21 02/08/21 09/08/21 16/08/21 23/08/21 30/08/21 06/09/21 13/09/21 20/09/21 27/09/21 04/10/21 11/10/21 18/10/21 PROGRES KET.
VOLUME HARGA SATUAN JUMLAH HARGA VOLUME JUMLAH HARGA
SAT. BOBOT (%) BOBOT (%) s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
KONTRAK (Rp) (Rp) MC 0 (Rp)
30/05/21 06/06/21 13/06/21 20/06/21 27/06/21 04/07/21 11/07/21 18/07/21 25/07/21 01/08/21 08/08/21 15/08/21 22/08/21 29/08/21 05/09/21 12/09/21 19/09/21 26/09/21 03/10/21 10/10/21 17/10/21 20/10/21

I PEKERJAAN PERSIAPAN
1 Pembuatan Papan Nama Pekerjaan bh 1.00 250,000.00 250,000.00 1.00 250,000.00 0.038 0.038 0.038 -
2 Pengukuran dan Pemasangan Bouwplank m 28.56 12,198.91 348,400.73 28.56 348,400.73 0.053 0.053 0.027 0.027 -
3 Pembuatan bedeng pekerja m2 9.00 383,330.04 3,449,970.32 9.00 3,449,970.32 0.527 0.527 0.263 0.263 -
4 Mobilisasi Demobilisasi Alat Berat ls 1.00 2,500,000.00 2,500,000.00 1.00 2,500,000.00 0.382 0.382 0.191 0.191 0.191
5 Pembuatan akses menuju badan sungai sementara m2 24.00 113,128.49 2,715,083.64 - - 0.415 - 0.207 0.207 -
6 Dewatering dengan pompa air diesel jam 40.00 25,000.00 1,000,000.00 40.00 1,000,000.00 0.153 0.153 0.022 0.022 0.022 0.022 0.022 0.022 0.022
7 SMKK ls 1.00 4,325,000.00 4,325,000.00 1.00 4,325,000.00 0.661 0.661 0.030 0.030 0.030 0.030 0.030 0.030 0.030 0.030 0.030 0.030 0.030 0.030 0.030 0.030 0.030 0.030 0.030 0.030 0.030 0.030 0.030 0.030
- -
II PEKERJAAN PERBAIKAN TALUD SEGMEN 5 - - - - - - -
A PEKERJAAN TANAH DAN BETON BERTULANG - - - - - - -
1 Penggalian 1 M3 Tanah Biasa m3 50.00 67,972.30 3,398,615.01 61.50 4,180,296.46 0.519 0.639 0.160 0.160 0.160 0.160
2 Pengurugan Kembali 1 M3 Galian Tanah m3 33.15 49,023.50 1,625,129.04 29.21 1,431,976.45 0.248 0.219 0.073 0.073 0.073
3 Bongkaran Pasangan Batu dan Beton Eksisting m3 50.00 71,953.20 3,597,660.02 39.18 2,819,126.39 0.550 0.431 0.108 0.108 0.108 0.108
4 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area m3 50.00 19,888.18 994,408.76 39.18 779,218.70 0.152 0.119 0.030 0.030 0.030 0.030
5 Pemadatan Tanah Eksisting m3 11.84 49,023.50 580,438.24 29.21 1,431,976.45 0.089 0.219 0.109 0.109
6 Pengurugan dengan pasir urug m3 5.92 178,388.92 1,056,062.41 1.23 219,418.37 0.161 0.034 0.034
7 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 m3 2.96 737,396.00 2,182,692.15 1.23 906,997.08 0.333 0.139 0.069 0.069
8 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 m3 10.00 872,242.00 8,722,419.97 4.92 4,291,430.63 1.332 0.655 0.109 0.109 0.109 0.109 0.109 0.109
a Pembesian dg Besi Polos atau Besi Ulir 11,860.70 714.10 8,469,724.55 - 1.294 0.216 0.216 0.216 0.216 0.216 0.216
b Bekisting untuk pondasi beton ( dipakai 2 kali ) 89,375.55 8.56 765,054.68 - 0.117 0.019 0.019 0.019 0.019 0.019 0.019
9 Pekerjaan Beton Dinding Talud Beton - - - - - - -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 m3 10.00 872,242.00 8,722,419.97 9.97 8,696,252.71 1.332 1.328 0.664 0.664
b Pembesian dg Besi Polos atau Besi Ulir kg 1,000.00 11,860.70 11,860,698.15 4,675.31 55,452,440.67 1.812 8.470 4.235 4.235
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 40.00 316,861.88 12,674,475.27 10.12 3,206,642.24 1.936 0.490 0.490
10 Pekerjaan Beton Sloof 20x30cm - - - - - - -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 m3 4.74 872,242.00 4,134,427.07 2.26 1,971,266.91 0.632 0.301 0.301
b Pembesian dg Besi Polos atau Besi Ulir kg 400.00 11,860.70 4,744,279.26 671.58 7,965,407.66 0.725 1.217 1.217
c Memasang Bekisting untuk Sloof (dipakai 2 kali) m2 47.36 89,375.55 4,232,825.87 11.34 1,013,518.69 0.647 0.155 0.077 0.077
11 Pekerjaan Beton Konsul Cantilever - - - - - - -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 m3 7.75 872,242.00 6,759,875.48 0.42 366,341.64 1.033 0.056 0.028 0.028
b Pembesian dg Besi Polos atau Besi Ulir kg 700.00 11,860.70 8,302,488.71 194.43 2,306,075.54 1.268 0.352 0.176 0.176
c Memasang Bekisting untuk Balok (dipakai 2 kali) m2 40.00 120,181.13 4,807,245.27 2.10 252,380.38 0.734 0.039 0.039
12 Pekerjaan Plat Beton tebal 12 cm - - - - - - -
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) m3 10.00 872,242.00 8,722,419.97 12.30 10,728,576.57 1.332 1.639 1.639
b Jaring Kawat baja/Wire Mesh M8 2 lapis kg 700.00 10,697.66 7,488,358.68 1,340.41 14,339,244.07 1.144 2.190 0.730 0.730 0.730
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 30.00 316,861.88 9,505,856.45 6.15 1,948,700.57 1.452 0.298 0.099 0.099 0.099
13 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm m 13.00 77,312.85 1,005,067.10 21.00 1,623,569.93 0.154 0.248 0.248
14 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm m 38.37 86,676.29 3,325,769.35 39.46 3,420,246.51 0.508 0.522 0.261 0.261
15 Memasang Stek Besi kg 200.00 11,860.70 2,372,139.63 107.71 1,277,515.80 0.362 0.195 0.195
16 Pekerjaan Plat Beton Pot tebal 10 cm - - - - - - -
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) m3 4.74 872,242.00 4,134,427.07 2.26 1,971,266.91 0.632 0.301 0.151 0.151
b Pembesian dg Besi Polos atau Besi Ulir kg 200.00 11,860.70 2,372,139.63 107.71 1,277,515.80 0.362 0.195 0.098 0.098
c Bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm m2 30.00 118,158.83 3,544,764.95 32.80 3,875,609.68 0.541 0.592 0.296 0.296
- - - - - - - - -
B PEKERJAAN PASANGAN DINDING - - - - - - -
1 Pemasangan Dinding Bata Merah Bakar Sekam Tebal 1/2 Bata Camp. 1SP 6PP m2 42.00 116,576.48 4,896,212.34 45.37 5,289,075.10 0.748 0.808 0.808
2 Pemasangan Plesteran 1 Pc 6 Pp Tebal 15 mm m2 84.00 54,689.70 4,593,934.71 155.38 8,497,685.43 0.702 1.298 1.298
3 Pemasangan Acian m2 210.00 33,411.23 7,016,358.16 155.38 5,191,436.81 1.072 0.793 0.793
4 Pemasangan Plesteran Skoning 1 Pc 2Pp lebar 10 cm m 360.00 55,075.90 19,827,324.36 212.00 11,676,091.01 3.028 1.783 0.594 0.594 0.594
5 Pemasangan Kepala Kolom bh 10.00 50,000.00 500,000.00 14.00 700,000.00 0.076 0.107 0.107
- - - - - - - - -
III PEKERJAAN PENATAAN LINGKUNGAN RW 1 - - - - - - -
A PEKERJAAN PENGECATAN - - - - - - -
1 Pengecatan Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Weathershield luar ruangan m2 210.00 11,686.42 2,454,148.34 155.38 1,815,836.04 0.375 0.277 0.277
- - - - - - - - -
B PEKERJAAN RUMAH TERDAMPAK - - - - - - -
I. PEKERJAAN BONGKARAN - - - - - - -
1 Membongkar 1 m2 genteng / sirap untuk dipergunakan lagi m2 103.90 3,628.42 376,993.05 77.17 280,005.33 0.058 0.043 0.021 0.021
2 Membongkar 1 m3 kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi m3 0.46 991,595.91 456,134.12 0.37 366,890.49 0.070 0.056 0.028 0.028
3 Pembongkaran 1 m3 pasangan bata merah dan membersihkan m3 40.86 185,908.38 7,596,216.24 11.13 2,069,160.22 1.160 0.316 0.158 0.158
4 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 m3 9.20 688,832.33 6,337,257.47 1.80 1,239,898.20 0.968 0.189 0.095 0.095
II. PEKERJAAN TANAH - - - - - - -
1 Menggali 1 m3 tanah biasa sedalam 1 meter m3 22.32 67,972.30 1,517,141.74 26.71 1,815,540.14 0.232 0.277 0.277
III. PEKERJAAN PONDASI - - - - - - -
1 Memasang 1 m3 pondasi batu belah, campuran 1 PC 6 PP m2 17.28 665,195.09 11,494,571.24 16.11 10,716,292.98 1.756 1.637 1.637
IV. PEKERJAAN BETON - - - - - - -
1 Membuat 1 m3 Sloof beton bertulang (200 kg besi + bekisting) m3 3.55 3,844,764.87 13,648,915.30 1.72 6,612,995.58 2.085 1.010 0.505 0.505
BULAN KE-1 BULAN KE-2 BULAN KE-3 BULAN KE-4
KONTRAK MC 0 KONTRAK MC 0
Ming.1 Ming.2 Ming.3 Ming.4 Ming.5 Ming.6 Ming.7 Ming.8 Ming.9 Ming.10 Ming.11 Ming.12 Ming.13 Ming.14 Ming.15 Ming.16 Ming.17 Ming.18 Ming.19 Ming.20 Ming.21 Ming.22
NO JENIS PEKERJAAN 24/05/21 31/05/21 07/06/21 14/06/21 21/06/21 28/06/21 05/07/21 12/07/21 19/07/21 26/07/21 02/08/21 09/08/21 16/08/21 23/08/21 30/08/21 06/09/21 13/09/21 20/09/21 27/09/21 04/10/21 11/10/21 18/10/21 PROGRES KET.
VOLUME HARGA SATUAN JUMLAH HARGA VOLUME JUMLAH HARGA
SAT. BOBOT (%) BOBOT (%) s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
KONTRAK (Rp) (Rp) MC 0 (Rp)
30/05/21 06/06/21 13/06/21 20/06/21 27/06/21 04/07/21 11/07/21 18/07/21 25/07/21 01/08/21 08/08/21 15/08/21 22/08/21 29/08/21 05/09/21 12/09/21 19/09/21 26/09/21 03/10/21 10/10/21 17/10/21 20/10/21
2 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) m3 4.94 7,083,735.01 34,993,650.96 3.92 27,768,241.25 5.345 4.241 1.414 1.414 1.414
3 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) m3 5.00 5,659,422.09 28,297,110.46 9.08 51,387,552.60 4.322 7.849 1.962 1.962 1.962 1.962
BULAN KE-1 BULAN KE-2 BULAN KE-3 BULAN KE-4
KONTRAK MC 0 KONTRAK MC 0
Ming.1 Ming.2 Ming.3 Ming.4 Ming.5 Ming.6 Ming.7 Ming.8 Ming.9 Ming.10 Ming.11 Ming.12 Ming.13 Ming.14 Ming.15 Ming.16 Ming.17 Ming.18 Ming.19 Ming.20 Ming.21 Ming.22
NO JENIS PEKERJAAN 24/05/21 31/05/21 07/06/21 14/06/21 21/06/21 28/06/21 05/07/21 12/07/21 19/07/21 26/07/21 02/08/21 09/08/21 16/08/21 23/08/21 30/08/21 06/09/21 13/09/21 20/09/21 27/09/21 04/10/21 11/10/21 18/10/21 PROGRES KET.
VOLUME HARGA SATUAN JUMLAH HARGA VOLUME JUMLAH HARGA
SAT. BOBOT (%) BOBOT (%) s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
KONTRAK (Rp) (Rp) MC 0 (Rp)
30/05/21 06/06/21 13/06/21 20/06/21 27/06/21 04/07/21 11/07/21 18/07/21 25/07/21 01/08/21 08/08/21 15/08/21 22/08/21 29/08/21 05/09/21 12/09/21 19/09/21 26/09/21 03/10/21 10/10/21 17/10/21 20/10/21
V. PEKERJAAN DINDING - - - - - - -
1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP m2 127.00 116,576.48 14,805,213.51 191.94 22,375,690.41 2.261 3.418 0.854 0.854 0.854 0.854
VI PEKERJAAN KAYU - - - - - - -
1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti m3 0.50 16,443,774.77 8,221,887.38 0.27 4,439,819.19 1.256 0.678 0.339 0.339
2 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti m2 12.72 644,715.80 8,200,785.00 12.08 7,788,166.89 1.253 1.190 1.190
3 Memasang 1 m3 konstruksi gordeng, kayu glugu m3 0.21 4,450,537.65 934,612.91 0.35 1,557,688.18 0.143 0.238 0.119 0.119
VII. PEKERJAAN PLESTERAN - - - - - - -
1 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm m2 100.00 54,689.70 5,468,969.90 75.69 4,139,463.32 0.835 0.632 0.632
2 Memasang 1 m2 acian m2 100.00 33,411.23 3,341,122.93 75.69 2,528,895.95 0.510 0.386 0.386
VIII. PEKERJAAN PENGECATAN - - - - - - -
1 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) m2 100.00 11,686.42 1,168,642.06 75.69 884,545.18 0.179 0.135 0.135
IX. PEKERJAAN PENUTUP ATAP - - - - - - -
1 Memasang 1 m2 Atap Galvalum (Paket) m3 78.20 190,000.00 14,858,000.00 78.24 14,864,806.70 2.269 2.270 2.270
X. PEKERJAAN PENUTUP LANTAI DAN DINDING - - - - - - -
1 Memasang 1 m2 lantai keramik (30 x 30) cm m2 8.54 114,193.22 975,210.13 16.26 1,856,781.81 0.149 0.284 0.284
XI. PEKERJAAN SANITASI - - - - - - -
1 Memasang 1 buah Kloset Jongkok Porselen bh 2.00 280,952.58 561,905.16 2.00 561,905.16 0.086 0.086 0.086
2 Memasang 1 m Pipa PVC tipe AW m2 24.00 19,406.20 465,748.90 24.00 465,748.90 0.071 0.071 0.071
3 Memasang 1 m Pipa PVC tipe AW 1 m2 24.00 22,254.33 534,103.90 24.00 534,103.90 0.082 0.082 0.082
4 Memasang 1 m Pipa PVC tipe AW 3 m2 24.00 63,036.61 1,512,878.67 24.00 1,512,878.67 0.231 0.231 0.231
5 Memasang 1 buah Kran atau m2 2.00 46,068.18 92,136.37 2.00 92,136.37 0.014 0.014 0.014
6 Memasang 1 buah Floor Drain m3 2.00 80,836.18 161,672.35 2.00 161,672.35 0.025 0.025 0.025
7 Memasang 1 buah Pintu Kamar Mandi bh 2.00 650,000.00 1,300,000.00 2.00 1,300,000.00 0.199 0.199 0.199
- - - - - - - - -
III PEKERJAAN PENATAAN LINGKUNGAN RW 1 - - - - - - -
A PEKERJAAN PEMBERSIHAN SALURAN - - - - - - -
1 Penggalian Tanah Lumpur dan Endapan Limbah Sedalam 30 cm m3 85.36 109,311.98 9,330,870.22 65.62 7,173,051.82 1.425 1.096 0.713 0.548 0.548
2 Pembersihan dan Pembuangan Tanah Lumpur dan Limbah Keluar Area m3 85.36 29,796.55 2,543,433.77 65.62 1,955,249.81 0.388 0.299 0.194 0.149 0.149
3 Pemadatan Tanah Eksisting m3 48.91 49,023.50 2,397,739.40 65.62 3,216,922.10 0.366 0.491 0.491
4 Pengurugan dengan pasir urug, 10 cm m3 17.07 178,388.92 3,045,098.87 21.87 3,901,365.68 0.465 0.596 0.298 0.298
5 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 m3 17.07 737,396.00 12,587,349.68 10.93 8,059,738.25 1.923 1.231 0.616 0.616
6 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 m3 17.07 872,242.00 14,889,170.90 21.87 19,075,932.48 2.274 2.914 1.457 1.457
7 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm m 466.40 77,312.85 36,058,714.99 78.60 6,076,790.31 5.508 0.928 0.309 0.309 0.309
8 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm m 466.40 86,676.29 40,425,822.86 642.60 55,698,185.61 6.175 8.507 2.127 2.127 2.127 2.127
9 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,2m, K.300 bh 65.00 626,150.00 40,699,750.00 70.00 43,830,500.00 6.217 6.695 1.674 1.674 1.674 1.674
10 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,8m, K.300 bh 32.00 750,000.00 24,000,000.00 61.00 45,750,000.00 3.666 6.988 2.329 2.329 2.329
- - - - - - - - -
B PEKERJAAN JARINGAN IPAL KOMUNAL - - - - - - -
1 Pekerjaan Galian Tanah Pipa m3 81.86 67,972.30 5,564,212.49 46.07 3,131,483.87 0.850 0.478 0.120 0.120 0.120 0.120
2 Pengurugan dengan pasir urug m3 6.82 178,388.92 1,216,612.43 11.51 2,053,256.47 0.186 0.314 0.105 0.105 0.105
3 Pengurugan Kembali 1 M3 Galian Tanah m3 24.56 49,023.50 1,204,017.17 30.54 1,497,264.55 0.184 0.229 0.076 0.076 0.076
4 Pemasangan 1 M Pipa PVC tipe AW 4 m 30.00 90,907.55 2,727,226.46 64.50 5,863,536.89 0.417 0.896 0.299 0.299 0.299
5 Saluran Pipa Air Limbah SDR - 41, Dia 15 cm , inc. fitting & Assecories m 343.20 133,200.00 45,714,240.00 375.05 49,956,660.00 6.983 7.630 1.908 1.908 1.908 1.908
6 Saluran Pipa Air Limbah SDR - 41, Dia 20 cm, , inc. fitting & Assecories m 113.70 203,900.00 23,183,430.00 - - 3.541 - - - -
7 Pemasangan Clean Out Inc. Fitting & Assecories ttk 17.00 185,000.00 3,145,000.00 43.00 7,955,000.00 0.480 1.215 MC 0 0.405 0.405 0.405
8 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 100 org, 20 m3 / h unit 1.00 7,500,000.00 7,500,000.00 1.00 7,500,000.00 1.146 1.146 1.146
9 Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm unit 4.00 975,000.00 3,900,000.00 4.00 3,900,000.00 0.596 0.596 0.298 0.298
10 Pekerjaan Sumur Resapan, Dia 100 cm, Kedalaman 2 m, Inc. Tutup Beton Berlubang ttk 15.00 500,000.00 7,500,000.00 15.00 7,500,000.00 1.146 1.146 0.382 0.382 0.382
11 Grill Beton Penutup Sumur Resapan unit 20.00 750,000.00 15,000,000.00 15.00 11,250,000.00 2.291 1.718 0.573 0.573 0.573

Rencana Kemajuan Mingguan 654,697,105.06 654,697,105.06 100.000 100.000 0.095 0.718 0.501 0.937 1.803 2.688 2.964 4.087 6.711 6.870 5.876 8.118 7.585 7.477 10.026 10.362 11.178 4.745 4.328 1.218 1.491 0.221
Rencana Komulatif Kemajuan Mingguan - - 0.095 0.813 1.314 2.251 4.054 6.742 9.706 13.793 20.504 27.374 33.251 41.368 48.953 56.430 66.457 76.819 87.997 92.742 97.070 98.288 99.779 100.000
Rencana Kemajuan Mingguan MC 0 - 0.095 0.718 0.501 0.937 1.975 3.416 2.985 3.789 5.102 5.349 7.797 10.416 6.703 8.140 11.146 9.510 11.219 5.659 4.067 0.760 1.009 0.221
Rencana Komulatif Kemajuan Mingguan MC 0 - 0.095 0.813 1.314 2.251 2.713 6.130 9.115 12.904 18.006 23.355 31.152 41.568 48.270 56.410 67.556 77.066 88.284 93.943 98.011 98.770 99.779 100.000
Realisasi Kemajuan Mingguan
Realisasi Komulatif Kemajuan Mingguan
Deviasi (+/-)

0.095 0.718 0.501 0.937


0.095 0.813 1.314 2.251 Yogyakarta, 15 Juni 2021
Dibuat Oleh
PEJABAT PEMBUAT KOMITMEN TIM TEKNIS KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA
1. Cicilia Novi hendrawati, M.SC., M.Eng.
NIP. 19781102 200501 2 011

2. Danang Dwi Wahyujati,S.Kom.,M.Eng


NIP. 19761028 199803 1 004

SIGIT SETIAWAN, ST.MT 3. Sudaryanto


NIP. 19690605 199303 1 007 RISMAN WARCHAN ZULIANTO
NIP. 19770623 200501 1 013 Tim Leader Direktur
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : V ( Lima )


Periode : 21 Juni 2021 sampai dengan 27 Juni 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
NILAI KONTRAK ADDENDUM I : Rp 720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
I PEKERJAAN PERSIAPAN
1 Pembuatan Papan Nama Pekerjaan 1.00 bh 250,000.00 250,000.00 0.038 1.000 0.038 - - 1.000 0.038
2 Pengukuran dan Pemasangan Bouwplank 28.56 m 12,198.91 348,400.73 0.053 28.560 0.053 - - 28.560 0.053
3 Pembuatan bedeng pekerja 9.00 m2 383,330.04 3,449,970.32 0.527 9.000 0.527 - - 9.000 0.527
4 Mobilisasi Demobilisasi Alat Berat 1.00 ls 2,500,000.00 2,500,000.00 0.382 - - - - - -
5 Pembuatan akses menuju badan sungai sementara - m2 113,128.49 - - - - - - - -
6 Dewatering dengan pompa air diesel 40.00 jam 25,000.00 1,000,000.00 0.153 - - - - - -
7 SMKK 1.00 ls 4,325,000.00 4,325,000.00 0.661 0.182 0.120 0.000 0.000 0.182 0.120
11,873,371.04 1.814 0.738 0.000 0.739
II PEKERJAAN PERBAIKAN TALUD SEGMEN 5
A PEKERJAAN TANAH DAN BETON BERTULANG
1 Penggalian 1 M3 Tanah Biasa 61.50 m3 67,972.30 4,180,296.46 0.639 - - - - - -
2 Pengurugan Kembali 1 M3 Galian Tanah 29.21 m3 49,023.50 1,431,976.45 0.219 - - - - - -
3 Bongkaran Pasangan Batu dan Beton Eksisting 39.18 m3 71,953.20 2,819,126.39 0.431 - - - - - -
4 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area 39.18 m3 19,888.18 779,218.70 0.119 - - - - - -
5 Pemadatan Tanah Eksisting 29.21 m3 49,023.50 1,431,976.45 0.219 - - - - - -
6 Pengurugan dengan pasir urug 1.23 m3 178,388.92 219,418.37 0.034 - - - - - -
7 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 1.23 m3 737,396.00 906,997.08 0.139 - - - - - -
8 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 4.92 m3 872,242.00 4,291,430.63 0.655 - - - - - -
a Pembesian dg Besi Polos atau Besi Ulir 714.10 m3 11,860.70 8,469,724.55 1.294 - - - - - -
b Bekisting untuk pondasi beton ( dipakai 2 kali ) 8.56 kg 89,375.55 765,054.68 0.117 - - - - - -
9 Pekerjaan Beton Dinding Talud Beton
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 9.97 m3 872,242.00 8,696,252.71 1.328 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 4,675.31 kg 11,860.70 55,452,440.67 8.470 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 10.12 m2 316,861.88 3,206,642.24 0.490 - - - - - -
10 Pekerjaan Beton Sloof 20x30cm
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 2.26 m3 872,242.00 1,971,266.91 0.301 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 671.58 kg 11,860.70 7,965,407.66 1.217 - - - - - -
c Memasang Bekisting untuk Sloof (dipakai 2 kali) 11.34 m2 89,375.55 1,013,518.69 0.155 - - - - - -
11 Pekerjaan Beton Konsul Cantilever
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 0.42 m3 872,242.00 366,341.64 0.056 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 194.43 kg 11,860.70 2,306,075.54 0.352 - - - - - -
c Memasang Bekisting untuk Balok (dipakai 2 kali) 2.10 m2 120,181.13 252,380.38 0.039 - - - - - -
12 Pekerjaan Plat Beton tebal 12 cm
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 12.30 m3 872,242.00 10,728,576.57 1.639 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis 1,340.41 kg 10,697.66 14,339,244.07 2.190 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 6.15 m2 316,861.88 1,948,700.57 0.298 - - - - - -
13 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 21.00 m 77,312.85 1,623,569.93 0.248 - - - - - -
14 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 39.46 m 86,676.29 3,420,246.51 0.522 - - - - - -
15 Memasang Stek Besi 107.71 kg 11,860.70 1,277,515.80 0.195 - - - - - -
16 Pekerjaan Plat Beton Pot tebal 10 cm
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 2.26 m3 872,242.00 1,971,266.91 0.301 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 107.71 kg 11,860.70 1,277,515.80 0.195 - - - - - -
c Bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm 32.80 m2 118,158.83 3,875,609.68 0.592 - - - - - -
146,987,792.05 22.451 - - -
B PEKERJAAN PASANGAN DINDING
1 Pemasangan Dinding Bata Merah Bakar Sekam Tebal 1/2 Bata Camp. 1SP 6PP 45.37 m2 116,576.48 5,289,075.10 0.808 - - - - - -
2 Pemasangan Plesteran 1 Pc 6 Pp Tebal 15 mm 155.38 m2 54,689.70 8,497,685.43 1.298 - - - - - -
3 Pemasangan Acian 155.38 m2 33,411.23 5,191,436.81 0.793 - - - - - -
4 Pemasangan Plesteran Skoning 1 Pc 2Pp lebar 10 cm 212.00 m 55,075.90 11,676,091.01 1.783 - - - - - -
5 Pemasangan Kepala Kolom 14.00 bh 50,000.00 700,000.00 0.107 - - - - - -
31,354,288.34 4.789 - - -

Laporan Progres Mingguan ke-5


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PENGECATAN
1 Pengecatan Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Weathershield luar ruangan 155.38 m2 11,686.42 1,815,836.04 0.277 - - - - - -
1,815,836.04 0.277 - - - - - -
B PEKERJAAN RUMAH TERDAMPAK
I. PEKERJAAN BONGKARAN
1 Membongkar 1 m2 genteng / sirap untuk dipergunakan lagi 77.17 m2 3,628.42 280,005.33 0.043 - - - - - -
2 Membongkar 1 m3 kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi 0.37 m3 991,595.91 366,890.49 0.056 - - - - - -
3 Pembongkaran 1 m3 pasangan bata merah dan membersihkan 11.13 m3 185,908.38 2,069,160.22 0.316 - - - - - -
4 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 1.80 m3 688,832.33 1,239,898.20 0.189 - - - - - -
II. PEKERJAAN TANAH
1 Menggali 1 m3 tanah biasa sedalam 1 meter 26.71 m3 67,972.30 1,815,540.14 0.277 - - 8.013 0.083 8.013 0.083
III. PEKERJAAN PONDASI
1 Memasang 1 m3 pondasi batu belah, campuran 1 PC 6 PP 16.11 m2 665,195.09 10,716,292.98 1.637 - - 4.833 0.491 4.833 0.491
IV. PEKERJAAN BETON
1 Membuat 1 m3 Sloof beton bertulang (200 kg besi + bekisting) 1.72 m3 3,844,764.87 6,612,995.58 1.010 - - - - - -
2 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) 3.92 m3 7,083,735.01 27,768,241.25 4.241 - - - - - -
3 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) 9.08 m3 5,659,422.09 51,387,552.60 7.849 - - - - - -
V. PEKERJAAN DINDING
1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP 191.94 m2 116,576.48 22,375,690.41 3.418 - - - - - -
VI PEKERJAAN KAYU
1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.27 m3 16,443,774.77 4,439,819.19 0.678 - - - - - -
2 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti 12.08 m2 644,715.80 7,788,166.89 1.190 - - - - - -
3 Memasang 1 m3 konstruksi gordeng, kayu glugu 0.35 m3 4,450,537.65 1,557,688.18 0.238 - - - - - -
VII. PEKERJAAN PLESTERAN
1 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm 75.69 m2 54,689.70 4,139,463.32 0.632 - - - - - -
2 Memasang 1 m2 acian 75.69 m2 33,411.23 2,528,895.95 0.386 - - - - - -
VIII. PEKERJAAN PENGECATAN
1 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 75.69 m2 11,686.42 884,545.18 0.135 - - - - - -
IX. PEKERJAAN PENUTUP ATAP
1 Memasang 1 m2 Atap Galvalum (Paket) 78.24 m3 190,000.00 14,864,806.70 2.270 - - - - - -
X. PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Memasang 1 m2 lantai keramik (30 x 30) cm 16.26 m2 114,193.22 1,856,781.81 0.284 - - - - - -
XI. PEKERJAAN SANITASI
1 Memasang 1 buah Kloset Jongkok Porselen 2.00 bh 280,952.58 561,905.16 0.086 - - - - - -
2 Memasang 1 m Pipa PVC tipe AW 24.00 m2 19,406.20 465,748.90 0.071 - - - - - -
3 Memasang 1 m Pipa PVC tipe AW 1 24.00 m2 22,254.33 534,103.90 0.082 - - - - - -
4 Memasang 1 m Pipa PVC tipe AW 3 24.00 m2 63,036.61 1,512,878.67 0.231 - - - - - -
5 Memasang 1 buah Kran atau 2.00 m2 46,068.18 92,136.37 0.014 - - - - - -
6 Memasang 1 buah Floor Drain 2.00 m3 80,836.18 161,672.35 0.025 - - - - - -
7 Memasang 1 buah Pintu Kamar Mandi 2.00 bh 650,000.00 1,300,000.00 0.199 - - - - - -
167,320,879.74 25.557 - 0.574 0.574
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PEMBERSIHAN SALURAN
1 Penggalian Tanah Lumpur dan Endapan Limbah Sedalam 30 cm 65.62 m3 109,311.98 7,173,051.82 1.096 - - 5.250 0.088 5.250 0.088
2 Pembersihan dan Pembuangan Tanah Lumpur dan Limbah Keluar Area 65.62 m3 29,796.55 1,955,249.81 0.299 - - - - - -
3 Pemadatan Tanah Eksisting 65.62 m3 49,023.50 3,216,922.10 0.491 - - - - - -
4 Pengurugan dengan pasir urug, 10 cm 21.87 m3 178,388.92 3,901,365.68 0.596 - - - - - -
5 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 10.93 m3 737,396.00 8,059,738.25 1.231 - - - - - -
6 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 21.87 m3 872,242.00 19,075,932.48 2.914 - - - - - -
7 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 78.60 m 77,312.85 6,076,790.31 0.928 - - - - - -
8 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 642.60 m 86,676.29 55,698,185.61 8.507 - - - - - -
9 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,2m, K.300 70.00 bh 626,150.00 43,830,500.00 6.695 - - - - - -
10 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,8m, K.300 61.00 bh 750,000.00 45,750,000.00 6.988 - - - - - -
194,737,736.07 29.745 - 0.088 0.088

Laporan Progres Mingguan ke-5


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
B PEKERJAAN JARINGAN IPAL KOMUNAL
1 Pekerjaan Galian Tanah Pipa 46.07 m3 67,972.30 3,131,483.87 0.478 - - - - - -
2 Pengurugan dengan pasir urug 11.51 m3 178,388.92 2,053,256.47 0.314 - - - - - -
3 Pengurugan Kembali 1 M3 Galian Tanah 30.54 m3 49,023.50 1,497,264.55 0.229 - - - - - -
4 Pemasangan 1 M Pipa PVC tipe AW 4 64.50 m 90,907.55 5,863,536.89 0.896 - - - - - -
5 Saluran Pipa Air Limbah SDR - 41, Dia 15 cm , inc. fitting & Assecories 375.05 m 133,200.00 49,956,660.00 7.630 - - - - - -
6 Saluran Pipa Air Limbah SDR - 41, Dia 20 cm, , inc. fitting & Assecories - m 203,900.00 - - - - - - - -
7 Pemasangan Clean Out Inc. Fitting & Assecories 43.00 ttk 185,000.00 7,955,000.00 1.215 - - - - - -
8 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 100 org, 20 m3 / hari, 1.00 unit 7,500,000.00 7,500,000.00 1.146 - - - - - -
(Galian, Urugan, Pondasi, Tutup Beton, Penyambungan Instalasi)
9 Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm 4.00 unit 975,000.00 3,900,000.00 0.596 - - - - - -
10 Pekerjaan Sumur Resapan, Dia 100 cm, Kedalaman 2 m, Inc. Tutup Beton Berlubang 15.00 ttk 500,000.00 7,500,000.00 1.146 - - - - - -
11 Grill Beton Penutup Sumur Resapan 15.00 unit 750,000.00 11,250,000.00 1.718 - - - - - -
100,607,201.77 15.367 - - -

JUMLAH 654,697,105.06 100.000 0.738 0.662 1.401


PRESTASI MINGGU LALU 654,697,105.06 0.738
PRESTASI MINGGU INI 0.662
PRESTASI SAMPAI DENGAN MINGGU INI 1.401
PRESTASI MENURUT SCHEDULE 2.713
LEBIH CEPAT (+) / TERLAMBAT (-) (1.312)

Yogyakarta, 28 Juni 2021


di buat oleh,
KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA

Noor Hasan Bambang Erlianto


Pengawas Pelaksana

Laporan Progres Mingguan ke-5


REKAPITULASI
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : V ( Lima )


Periode : 21 Juni 2021 sampai dengan 27 Juni 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
NILAI KONTRAK ADDENDUM I : Rp 720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO PEKERJAAN PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp (%) BOBOT % BOBOT % BOBOT %

I PEKERJAAN PERSIAPAN 11,873,371.04 1.814 0.738 0.000 0.739

II PEKERJAAN PERBAIKAN TALUD SEGMEN 5


A PEKERJAAN TANAH DAN BETON BERTULANG 146,987,792.05 22.451 - - -
B PEKERJAAN PASANGAN DINDING 31,354,288.34 4.789 - - -

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PENGECATAN 1,815,836.04 0.277 - - -
B PEKERJAAN RUMAH TERDAMPAK 167,320,879.74 25.557 - 0.574 0.574

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PEMBERSIHAN SALURAN 194,737,736.07 29.745 - 0.088 0.088
B PEKERJAAN JARINGAN IPAL KOMUNAL 100,607,201.77 15.367 - - -

JUMLAH 654,697,105.06 100.000 0.738 0.662 1.401


PRESTASI MINGGU LALU 0.738
PRESTASI MINGGU INI 0.662
PRESTASI SAMPAI DENGAN MINGGU INI 1.401
PRESTASI MENURUT SCHEDULE 2.713
LEBIH CEPAT (+) / TERLAMBAT (-) (1.312)

Yogyakarta, 28 Juni 2021


di buat oleh,
PEJABAT PEMBUAT KOMITMEN TIM TEKNIS KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA
1. Cicilia Novi hendrawati, M.SC., M.Eng.
NIP. 19781102 200501 2 011 ...........................

2. Danang Dwi Wahyujati,S.Kom.,M.Eng


NIP. 19761028 199803 1 004 ...........................
SIGIT SETIAWAN, ST.MT 3. Sudaryanto
NIP. 19690605 199303 1 007 RISMAN WARCHAN ZULIANTO
NIP. 19770623 200501 1 013 ........................... Tim Leader Direktur
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : VI ( Enam )


Periode : 28 Juni 2021 sampai dengan 04 Juli 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
NILAI KONTRAK ADDENDUM I : Rp 720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
I PEKERJAAN PERSIAPAN
1 Pembuatan Papan Nama Pekerjaan 1.00 bh 250,000.00 250,000.00 0.038 1.000 0.038 - - 1.000 0.038
2 Pengukuran dan Pemasangan Bouwplank 28.56 m 12,198.91 348,400.73 0.053 28.560 0.053 - - 28.560 0.053
3 Pembuatan bedeng pekerja 9.00 m2 383,330.04 3,449,970.32 0.527 9.000 0.527 - - 9.000 0.527
4 Mobilisasi Demobilisasi Alat Berat 1.00 ls 2,500,000.00 2,500,000.00 0.382 - - - - - -
5 Pembuatan akses menuju badan sungai sementara - m2 113,128.49 - - - - - - - -
6 Dewatering dengan pompa air diesel 40.00 jam 25,000.00 1,000,000.00 0.153 - - - - - -
7 SMKK 1.00 ls 4,325,000.00 4,325,000.00 0.661 0.182 0.120 0.045 0.030 0.228 0.150
11,873,371.04 1.814 0.739 0.030 0.769
II PEKERJAAN PERBAIKAN TALUD SEGMEN 5
A PEKERJAAN TANAH DAN BETON BERTULANG
1 Penggalian 1 M3 Tanah Biasa 61.50 m3 67,972.30 4,180,296.46 0.639 - - - - - -
2 Pengurugan Kembali 1 M3 Galian Tanah 29.21 m3 49,023.50 1,431,976.45 0.219 - - - - - -
3 Bongkaran Pasangan Batu dan Beton Eksisting 39.18 m3 71,953.20 2,819,126.39 0.431 - - - - - -
4 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area 39.18 m3 19,888.18 779,218.70 0.119 - - - - - -
5 Pemadatan Tanah Eksisting 29.21 m3 49,023.50 1,431,976.45 0.219 - - - - - -
6 Pengurugan dengan pasir urug 1.23 m3 178,388.92 219,418.37 0.034 - - - - - -
7 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 1.23 m3 737,396.00 906,997.08 0.139 - - - - - -
8 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 4.92 m3 872,242.00 4,291,430.63 0.655 - - - - - -
a Pembesian dg Besi Polos atau Besi Ulir 714.10 m3 11,860.70 8,469,724.55 1.294 - - - - - -
b Bekisting untuk pondasi beton ( dipakai 2 kali ) 8.56 kg 89,375.55 765,054.68 0.117 - - - - - -
9 Pekerjaan Beton Dinding Talud Beton -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 9.97 m3 872,242.00 8,696,252.71 1.328 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 4,675.31 kg 11,860.70 55,452,440.67 8.470 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 10.12 m2 316,861.88 3,206,642.24 0.490 - - - - - -
10 Pekerjaan Beton Sloof 20x30cm -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 2.26 m3 872,242.00 1,971,266.91 0.301 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 671.58 kg 11,860.70 7,965,407.66 1.217 - - - - - -
c Memasang Bekisting untuk Sloof (dipakai 2 kali) 11.34 m2 89,375.55 1,013,518.69 0.155 - - - - - -
11 Pekerjaan Beton Konsul Cantilever -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 0.42 m3 872,242.00 366,341.64 0.056 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 194.43 kg 11,860.70 2,306,075.54 0.352 - - - - - -
c Memasang Bekisting untuk Balok (dipakai 2 kali) 2.10 m2 120,181.13 252,380.38 0.039 - - - - - -
12 Pekerjaan Plat Beton tebal 12 cm -
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 12.30 m3 872,242.00 10,728,576.57 1.639 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis 1,340.41 kg 10,697.66 14,339,244.07 2.190 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 6.15 m2 316,861.88 1,948,700.57 0.298 - - - - - -
13 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 21.00 m 77,312.85 1,623,569.93 0.248 - - - - - -
14 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 39.46 m 86,676.29 3,420,246.51 0.522 - - - - - -
15 Memasang Stek Besi 107.71 kg 11,860.70 1,277,515.80 0.195 - - - - - -
16 Pekerjaan Plat Beton Pot tebal 10 cm -
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 2.26 m3 872,242.00 1,971,266.91 0.301 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 107.71 kg 11,860.70 1,277,515.80 0.195 - - - - - -
c Bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm 32.80 m2 118,158.83 3,875,609.68 0.592 - - - - - -
146,987,792.05 22.451 - - -
B PEKERJAAN PASANGAN DINDING
1 Pemasangan Dinding Bata Merah Bakar Sekam Tebal 1/2 Bata Camp. 1SP 6PP 45.37 m2 116,576.48 5,289,075.10 0.808 - - - - - -
2 Pemasangan Plesteran 1 Pc 6 Pp Tebal 15 mm 155.38 m2 54,689.70 8,497,685.43 1.298 - - - - - -
3 Pemasangan Acian 155.38 m2 33,411.23 5,191,436.81 0.793 - - - - - -
4 Pemasangan Plesteran Skoning 1 Pc 2Pp lebar 10 cm 212.00 m 55,075.90 11,676,091.01 1.783 - - - - - -
5 Pemasangan Kepala Kolom 14.00 bh 50,000.00 700,000.00 0.107 - - - - - -
31,354,288.34 4.789 - - -

Laporan Progres Mingguan ke-6


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PENGECATAN
1 Pengecatan Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Weathershield luar ruangan 155.38 m2 11,686.42 1,815,836.04 0.277 - - - - - -
1,815,836.04 0.277 - - -
B PEKERJAAN RUMAH TERDAMPAK
I. PEKERJAAN BONGKARAN
1 Membongkar 1 m2 genteng / sirap untuk dipergunakan lagi 77.17 m2 3,628.42 280,005.33 0.043 - - - - - -
2 Membongkar 1 m3 kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi 0.37 m3 991,595.91 366,890.49 0.056 - - - - - -
3 Pembongkaran 1 m3 pasangan bata merah dan membersihkan 11.13 m3 185,908.38 2,069,160.22 0.316 - - - - - -
4 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 1.80 m3 688,832.33 1,239,898.20 0.189 - - - - - -
II. PEKERJAAN TANAH -
1 Menggali 1 m3 tanah biasa sedalam 1 meter 26.71 m3 67,972.30 1,815,540.14 0.277 8.013 0.083 6.678 0.069 14.691 0.153
III. PEKERJAAN PONDASI -
1 Memasang 1 m3 pondasi batu belah, campuran 1 PC 6 PP 16.11 m2 665,195.09 10,716,292.98 1.637 4.833 0.491 2.417 0.246 7.250 0.737
IV. PEKERJAAN BETON -
1 Membuat 1 m3 Sloof beton bertulang (200 kg besi + bekisting) 1.72 m3 3,844,764.87 6,612,995.58 1.010 - - 0.516 0.303 0.516 0.303
2 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) 3.92 m3 7,083,735.01 27,768,241.25 4.241 - - 0.274 0.297 0.274 0.297
3 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) 9.08 m3 5,659,422.09 51,387,552.60 7.849 - - - - - -
V. PEKERJAAN DINDING -
1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP 191.94 m2 116,576.48 22,375,690.41 3.418 - - - - - -
VI PEKERJAAN KAYU -
1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.27 m3 16,443,774.77 4,439,819.19 0.678 - - - - - -
2 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti 12.08 m2 644,715.80 7,788,166.89 1.190 - - - - - -
3 Memasang 1 m3 konstruksi gordeng, kayu glugu 0.35 m3 4,450,537.65 1,557,688.18 0.238 - - - - - -
VII. PEKERJAAN PLESTERAN -
1 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm 75.69 m2 54,689.70 4,139,463.32 0.632 - - - - - -
2 Memasang 1 m2 acian 75.69 m2 33,411.23 2,528,895.95 0.386 - - - - - -
VIII. PEKERJAAN PENGECATAN -
1 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 75.69 m2 11,686.42 884,545.18 0.135 - - - - - -
IX. PEKERJAAN PENUTUP ATAP -
1 Memasang 1 m2 Atap Galvalum (Paket) 78.24 m3 190,000.00 14,864,806.70 2.270 - - - - - -
X. PEKERJAAN PENUTUP LANTAI DAN DINDING -
1 Memasang 1 m2 lantai keramik (30 x 30) cm 16.26 m2 114,193.22 1,856,781.81 0.284 - - - - - -
XI. PEKERJAAN SANITASI -
1 Memasang 1 buah Kloset Jongkok Porselen 2.00 bh 280,952.58 561,905.16 0.086 - - - - - -
2 Memasang 1 m Pipa PVC tipe AW 24.00 m2 19,406.20 465,748.90 0.071 - - - - - -
3 Memasang 1 m Pipa PVC tipe AW 1 24.00 m2 22,254.33 534,103.90 0.082 - - - - - -
4 Memasang 1 m Pipa PVC tipe AW 3 24.00 m2 63,036.61 1,512,878.67 0.231 - - - - - -
5 Memasang 1 buah Kran atau 2.00 m2 46,068.18 92,136.37 0.014 - - - - - -
6 Memasang 1 buah Floor Drain 2.00 m3 80,836.18 161,672.35 0.025 - - - - - -
7 Memasang 1 buah Pintu Kamar Mandi 2.00 bh 650,000.00 1,300,000.00 0.199 - - - - - -
167,320,879.74 25.557 0.574 0.915 1.489
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PEMBERSIHAN SALURAN
1 Penggalian Tanah Lumpur dan Endapan Limbah Sedalam 30 cm 65.62 m3 109,311.98 7,173,051.82 1.096 5.250 0.088 3.281 0.055 8.531 0.142
2 Pembersihan dan Pembuangan Tanah Lumpur dan Limbah Keluar Area 65.62 m3 29,796.55 1,955,249.81 0.299 - - - - - -
3 Pemadatan Tanah Eksisting 65.62 m3 49,023.50 3,216,922.10 0.491 - - - - - -
4 Pengurugan dengan pasir urug, 10 cm 21.87 m3 178,388.92 3,901,365.68 0.596 - - - - - -
5 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 10.93 m3 737,396.00 8,059,738.25 1.231 - - - - - -
6 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 21.87 m3 872,242.00 19,075,932.48 2.914 - - - - - -
7 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 78.60 m 77,312.85 6,076,790.31 0.928 - - - - - -
8 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 642.60 m 86,676.29 55,698,185.61 8.507 - - - - - -
9 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,2m, K.300 70.00 bh 626,150.00 43,830,500.00 6.695 - - - - - -
10 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,8m, K.300 61.00 bh 750,000.00 45,750,000.00 6.988 - - - - - -
194,737,736.07 29.745 0.088 0.055 0.142

Laporan Progres Mingguan ke-6


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
B PEKERJAAN JARINGAN IPAL KOMUNAL
1 Pekerjaan Galian Tanah Pipa 46.07 m3 67,972.30 3,131,483.87 0.478 - - - - - -
2 Pengurugan dengan pasir urug 11.51 m3 178,388.92 2,053,256.47 0.314 - - - - - -
3 Pengurugan Kembali 1 M3 Galian Tanah 30.54 m3 49,023.50 1,497,264.55 0.229 - - - - - -
4 Pemasangan 1 M Pipa PVC tipe AW 4 64.50 m 90,907.55 5,863,536.89 0.896 - - - - - -
5 Saluran Pipa Air Limbah SDR - 41, Dia 15 cm , inc. fitting & Assecories 375.05 m 133,200.00 49,956,660.00 7.630 - - - - - -
6 Saluran Pipa Air Limbah SDR - 41, Dia 20 cm, , inc. fitting & Assecories - m 203,900.00 - - - - - - - -
7 Pemasangan Clean Out Inc. Fitting & Assecories 43.00 ttk 185,000.00 7,955,000.00 1.215 - - - - - -
8 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 100 org, 20 m3 / hari, 1.00 unit 7,500,000.00 7,500,000.00 1.146 - - - - - -
(Galian, Urugan, Pondasi, Tutup Beton, Penyambungan Instalasi) -
9 Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm 4.00 unit 975,000.00 3,900,000.00 0.596 - - - - - -
10 Pekerjaan Sumur Resapan, Dia 100 cm, Kedalaman 2 m, Inc. Tutup Beton Berlubang 15.00 ttk 500,000.00 7,500,000.00 1.146 - - - - - -
11 Grill Beton Penutup Sumur Resapan 15.00 unit 750,000.00 11,250,000.00 1.718 - - - - - -
100,607,201.77 15.367 - - -

JUMLAH 654,697,105.06 100.000 1.401 1.000 2.400


PRESTASI MINGGU LALU 1.401
PRESTASI MINGGU INI 1.000
PRESTASI SAMPAI DENGAN MINGGU INI 2.400
PRESTASI MENURUT SCHEDULE 6.130
LEBIH CEPAT (+) / TERLAMBAT (-) (3.729)

Yogyakarta, 5 Juli 2021


di buat oleh,
KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA

Noor Hasan Bambang Erlianto


Pengawas Pelaksana

Laporan Progres Mingguan ke-6


REKAPITULASI
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : VI ( Enam )


Periode : 28 Juni 2021 sampai dengan 04 Juli 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
NILAI KONTRAK ADDENDUM I : Rp 720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO PEKERJAAN PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp (%) BOBOT % BOBOT % BOBOT %

I PEKERJAAN PERSIAPAN 11,873,371.04 1.814 0.739 0.030 0.769

II PEKERJAAN PERBAIKAN TALUD SEGMEN 5


A PEKERJAAN TANAH DAN BETON BERTULANG 146,987,792.05 22.451 - - -
B PEKERJAAN PASANGAN DINDING 31,354,288.34 4.789 - - -

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PENGECATAN 1,815,836.04 0.277 - - -
B PEKERJAAN RUMAH TERDAMPAK 167,320,879.74 25.557 0.574 0.915 1.489

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PEMBERSIHAN SALURAN 194,737,736.07 29.745 0.088 0.055 0.142
B PEKERJAAN JARINGAN IPAL KOMUNAL 100,607,201.77 15.367 - - -

JUMLAH 654,697,105.06 100.000 1.401 1.000 2.400


PRESTASI MINGGU LALU 1.401
PRESTASI MINGGU INI 1.000
PRESTASI SAMPAI DENGAN MINGGU INI 2.400
PRESTASI MENURUT SCHEDULE 6.130
LEBIH CEPAT (+) / TERLAMBAT (-) (3.729)

Yogyakarta, 5 Juli 2021


di buat oleh,
PEJABAT PEMBUAT KOMITMEN TIM TEKNIS KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA
1. Cicilia Novi hendrawati, M.SC., M.Eng.
NIP. 19781102 200501 2 011 ...........................

2. Danang Dwi Wahyujati,S.Kom.,M.Eng


NIP. 19761028 199803 1 004 ...........................

SIGIT SETIAWAN, ST.MT 3. Sudaryanto


NIP. 19690605 199303 1 007 RISMAN WARCHAN ZULIANTO
NIP. 19770623 200501 1 013 ........................... Tim Leader Direktur
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : VII ( Tujuh )


Periode : 05 Juli 2021 sampai dengan 11 Juli 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
NILAI KONTRAK ADDENDUM I : Rp 720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
I PEKERJAAN PERSIAPAN
1 Pembuatan Papan Nama Pekerjaan 1.00 bh 250,000.00 250,000.00 0.038 1.000 0.038 - - 1.000 0.038
2 Pengukuran dan Pemasangan Bouwplank 28.56 m 12,198.91 348,400.73 0.053 28.560 0.053 - - 28.560 0.053
3 Pembuatan bedeng pekerja 9.00 m2 383,330.04 3,449,970.32 0.527 9.000 0.527 - - 9.000 0.527
4 Mobilisasi Demobilisasi Alat Berat 1.00 ls 2,500,000.00 2,500,000.00 0.382 - - - - - -
5 Pembuatan akses menuju badan sungai sementara - m2 113,128.49 - - - - - - - -
6 Dewatering dengan pompa air diesel 40.00 jam 25,000.00 1,000,000.00 0.153 - - - - - -
7 SMKK 1.00 ls 4,325,000.00 4,325,000.00 0.661 0.228 0.150 0.045 0.030 0.273 0.180
11,873,371.04 1.814 0.769 0.030 0.799
II PEKERJAAN PERBAIKAN TALUD SEGMEN 5
A PEKERJAAN TANAH DAN BETON BERTULANG
1 Penggalian 1 M3 Tanah Biasa 61.50 m3 67,972.30 4,180,296.46 0.639 - - - - - -
2 Pengurugan Kembali 1 M3 Galian Tanah 29.21 m3 49,023.50 1,431,976.45 0.219 - - - - - -
3 Bongkaran Pasangan Batu dan Beton Eksisting 39.18 m3 71,953.20 2,819,126.39 0.431 - - - - - -
4 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area 39.18 m3 19,888.18 779,218.70 0.119 - - - - - -
5 Pemadatan Tanah Eksisting 29.21 m3 49,023.50 1,431,976.45 0.219 - - - - - -
6 Pengurugan dengan pasir urug 1.23 m3 178,388.92 219,418.37 0.034 - - - - - -
7 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 1.23 m3 737,396.00 906,997.08 0.139 - - - - - -
8 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 4.92 m3 872,242.00 4,291,430.63 0.655 - - - - - -
a Pembesian dg Besi Polos atau Besi Ulir 714.10 m3 11,860.70 8,469,724.55 1.294 - - - - - -
b Bekisting untuk pondasi beton ( dipakai 2 kali ) 8.56 kg 89,375.55 765,054.68 0.117 - - - - - -
9 Pekerjaan Beton Dinding Talud Beton -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 9.97 m3 872,242.00 8,696,252.71 1.328 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 4,675.31 kg 11,860.70 55,452,440.67 8.470 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 10.12 m2 316,861.88 3,206,642.24 0.490 - - - - - -
10 Pekerjaan Beton Sloof 20x30cm -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 2.26 m3 872,242.00 1,971,266.91 0.301 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 671.58 kg 11,860.70 7,965,407.66 1.217 - - - - - -
c Memasang Bekisting untuk Sloof (dipakai 2 kali) 11.34 m2 89,375.55 1,013,518.69 0.155 - - - - - -
11 Pekerjaan Beton Konsul Cantilever -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 0.42 m3 872,242.00 366,341.64 0.056 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 194.43 kg 11,860.70 2,306,075.54 0.352 - - - - - -
c Memasang Bekisting untuk Balok (dipakai 2 kali) 2.10 m2 120,181.13 252,380.38 0.039 - - - - - -
12 Pekerjaan Plat Beton tebal 12 cm -
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 12.30 m3 872,242.00 10,728,576.57 1.639 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis 1,340.41 kg 10,697.66 14,339,244.07 2.190 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 6.15 m2 316,861.88 1,948,700.57 0.298 - - - - - -
13 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 21.00 m 77,312.85 1,623,569.93 0.248 - - - - - -
14 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 39.46 m 86,676.29 3,420,246.51 0.522 - - - - - -
15 Memasang Stek Besi 107.71 kg 11,860.70 1,277,515.80 0.195 - - - - - -
16 Pekerjaan Plat Beton Pot tebal 10 cm -
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 2.26 m3 872,242.00 1,971,266.91 0.301 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 107.71 kg 11,860.70 1,277,515.80 0.195 - - - - - -
c Bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm 32.80 m2 118,158.83 3,875,609.68 0.592 - - - - - -
146,987,792.05 22.451 - - -
B PEKERJAAN PASANGAN DINDING
1 Pemasangan Dinding Bata Merah Bakar Sekam Tebal 1/2 Bata Camp. 1SP 6PP 45.37 m2 116,576.48 5,289,075.10 0.808 - - - - - -
2 Pemasangan Plesteran 1 Pc 6 Pp Tebal 15 mm 155.38 m2 54,689.70 8,497,685.43 1.298 - - - - - -
3 Pemasangan Acian 155.38 m2 33,411.23 5,191,436.81 0.793 - - - - - -
4 Pemasangan Plesteran Skoning 1 Pc 2Pp lebar 10 cm 212.00 m 55,075.90 11,676,091.01 1.783 - - - - - -
5 Pemasangan Kepala Kolom 14.00 bh 50,000.00 700,000.00 0.107 - - - - - -
31,354,288.34 4.789 - - -

Laporan Progres Mingguan ke-7


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PENGECATAN
1 Pengecatan Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Weathershield luar ruangan 155.38 m2 11,686.42 1,815,836.04 0.277 - - - - - -
1,815,836.04 0.277 - - -
B PEKERJAAN RUMAH TERDAMPAK
I. PEKERJAAN BONGKARAN
1 Membongkar 1 m2 genteng / sirap untuk dipergunakan lagi 77.17 m2 3,628.42 280,005.33 0.043 - - - - - -
2 Membongkar 1 m3 kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi 0.37 m3 991,595.91 366,890.49 0.056 - - - - - -
3 Pembongkaran 1 m3 pasangan bata merah dan membersihkan 11.13 m3 185,908.38 2,069,160.22 0.316 - - 2.226 0.063 2.226 0.063
4 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 1.80 m3 688,832.33 1,239,898.20 0.189 - - 0.108 0.011 0.108 0.011
II. PEKERJAAN TANAH -
1 Menggali 1 m3 tanah biasa sedalam 1 meter 26.71 m3 67,972.30 1,815,540.14 0.277 14.691 0.153 6.678 0.069 21.368 0.222
III. PEKERJAAN PONDASI -
1 Memasang 1 m3 pondasi batu belah, campuran 1 PC 6 PP 16.11 m2 665,195.09 10,716,292.98 1.637 7.250 0.737 2.417 0.246 9.666 0.982
IV. PEKERJAAN BETON -
1 Membuat 1 m3 Sloof beton bertulang (200 kg besi + bekisting) 1.72 m3 3,844,764.87 6,612,995.58 1.010 0.516 0.303 0.172 0.101 0.688 0.404
2 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) 3.92 m3 7,083,735.01 27,768,241.25 4.241 0.274 0.297 0.784 0.848 1.058 1.145
3 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) 9.08 m3 5,659,422.09 51,387,552.60 7.849 - - 1.362 1.177 1.362 1.177
V. PEKERJAAN DINDING -
1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP 191.94 m2 116,576.48 22,375,690.41 3.418 - - - - - -
VI PEKERJAAN KAYU -
1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.27 m3 16,443,774.77 4,439,819.19 0.678 - - - - - -
2 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti 12.08 m2 644,715.80 7,788,166.89 1.190 - - - - - -
3 Memasang 1 m3 konstruksi gordeng, kayu glugu 0.35 m3 4,450,537.65 1,557,688.18 0.238 - - - - - -
VII. PEKERJAAN PLESTERAN -
1 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm 75.69 m2 54,689.70 4,139,463.32 0.632 - - - - - -
2 Memasang 1 m2 acian 75.69 m2 33,411.23 2,528,895.95 0.386 - - - - - -
VIII. PEKERJAAN PENGECATAN -
1 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 75.69 m2 11,686.42 884,545.18 0.135 - - - - - -
IX. PEKERJAAN PENUTUP ATAP -
1 Memasang 1 m2 Atap Galvalum (Paket) 78.24 m3 190,000.00 14,864,806.70 2.270 - - - - - -
X. PEKERJAAN PENUTUP LANTAI DAN DINDING -
1 Memasang 1 m2 lantai keramik (30 x 30) cm 16.26 m2 114,193.22 1,856,781.81 0.284 - - - - - -
XI. PEKERJAAN SANITASI -
1 Memasang 1 buah Kloset Jongkok Porselen 2.00 bh 280,952.58 561,905.16 0.086 - - - - - -
2 Memasang 1 m Pipa PVC tipe AW 24.00 m2 19,406.20 465,748.90 0.071 - - - - - -
3 Memasang 1 m Pipa PVC tipe AW 1 24.00 m2 22,254.33 534,103.90 0.082 - - - - - -
4 Memasang 1 m Pipa PVC tipe AW 3 24.00 m2 63,036.61 1,512,878.67 0.231 - - - - - -
5 Memasang 1 buah Kran atau 2.00 m2 46,068.18 92,136.37 0.014 - - - - - -
6 Memasang 1 buah Floor Drain 2.00 m3 80,836.18 161,672.35 0.025 - - - - - -
7 Memasang 1 buah Pintu Kamar Mandi 2.00 bh 650,000.00 1,300,000.00 0.199 - - - - - -
167,320,879.74 25.557 1.489 2.516 4.005
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PEMBERSIHAN SALURAN
1 Penggalian Tanah Lumpur dan Endapan Limbah Sedalam 30 cm 65.62 m3 109,311.98 7,173,051.82 1.096 8.531 0.142 13.124 0.219 21.655 0.362
2 Pembersihan dan Pembuangan Tanah Lumpur dan Limbah Keluar Area 65.62 m3 29,796.55 1,955,249.81 0.299 - - 19.686 0.090 19.686 0.090
3 Pemadatan Tanah Eksisting 65.62 m3 49,023.50 3,216,922.10 0.491 - - - - - -
4 Pengurugan dengan pasir urug, 10 cm 21.87 m3 178,388.92 3,901,365.68 0.596 - - - - - -
5 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 10.93 m3 737,396.00 8,059,738.25 1.231 - - - - - -
6 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 21.87 m3 872,242.00 19,075,932.48 2.914 - - - - - -
7 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 78.60 m 77,312.85 6,076,790.31 0.928 - - - - - -
8 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 642.60 m 86,676.29 55,698,185.61 8.507 - - - - - -
9 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,2m, K.300 70.00 bh 626,150.00 43,830,500.00 6.695 - - - - - -
10 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,8m, K.300 61.00 bh 750,000.00 45,750,000.00 6.988 - - - - - -
194,737,736.07 29.745 0.142 0.309 0.451

Laporan Progres Mingguan ke-7


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
B PEKERJAAN JARINGAN IPAL KOMUNAL
1 Pekerjaan Galian Tanah Pipa 46.07 m3 67,972.30 3,131,483.87 0.478 - - - - - -
2 Pengurugan dengan pasir urug 11.51 m3 178,388.92 2,053,256.47 0.314 - - - - - -
3 Pengurugan Kembali 1 M3 Galian Tanah 30.54 m3 49,023.50 1,497,264.55 0.229 - - - - - -
4 Pemasangan 1 M Pipa PVC tipe AW 4 64.50 m 90,907.55 5,863,536.89 0.896 - - - - - -
5 Saluran Pipa Air Limbah SDR - 41, Dia 15 cm , inc. fitting & Assecories 375.05 m 133,200.00 49,956,660.00 7.630 - - - - - -
6 Saluran Pipa Air Limbah SDR - 41, Dia 20 cm, , inc. fitting & Assecories - m 203,900.00 - - - - - - - -
7 Pemasangan Clean Out Inc. Fitting & Assecories 43.00 ttk 185,000.00 7,955,000.00 1.215 - - - - - -
8 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 100 org, 20 m3 / hari, 1.00 unit 7,500,000.00 7,500,000.00 1.146 - - - - - -
(Galian, Urugan, Pondasi, Tutup Beton, Penyambungan Instalasi) -
9 Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm 4.00 unit 975,000.00 3,900,000.00 0.596 - - - - - -
10 Pekerjaan Sumur Resapan, Dia 100 cm, Kedalaman 2 m, Inc. Tutup Beton Berlubang 15.00 ttk 500,000.00 7,500,000.00 1.146 - - - - - -
11 Grill Beton Penutup Sumur Resapan 15.00 unit 750,000.00 11,250,000.00 1.718 - - - - - -
100,607,201.77 15.367 - - -

JUMLAH 654,697,105.06 100.000 2.400 2.855 5.255


PRESTASI MINGGU LALU 2.400
PRESTASI MINGGU INI 2.855
PRESTASI SAMPAI DENGAN MINGGU INI 5.255
PRESTASI MENURUT SCHEDULE 9.115
LEBIH CEPAT (+) / TERLAMBAT (-) (3.860)

Yogyakarta, 12 Juli 2021


di buat oleh,
KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA

Noor Hasan Bambang Erlianto


Pengawas Pelaksana

Laporan Progres Mingguan ke-7


REKAPITULASI
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : VII ( Tujuh )


Periode : 05 Juli 2021 sampai dengan 11 Juli 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
NILAI KONTRAK ADDENDUM I : Rp 720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO PEKERJAAN PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp (%) BOBOT % BOBOT % BOBOT %

I PEKERJAAN PERSIAPAN 11,873,371.04 1.814 0.769 0.030 0.799

II PEKERJAAN PERBAIKAN TALUD SEGMEN 5


A PEKERJAAN TANAH DAN BETON BERTULANG 146,987,792.05 22.451 - - -
B PEKERJAAN PASANGAN DINDING 31,354,288.34 4.789 - - -

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PENGECATAN 1,815,836.04 0.277 - - -
B PEKERJAAN RUMAH TERDAMPAK 167,320,879.74 25.557 1.489 2.516 4.005

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PEMBERSIHAN SALURAN 194,737,736.07 29.745 0.142 0.309 0.451
B PEKERJAAN JARINGAN IPAL KOMUNAL 100,607,201.77 15.367 - - -

JUMLAH 654,697,105.06 100.000 2.400 2.855 5.255


PRESTASI MINGGU LALU 2.400
PRESTASI MINGGU INI 2.855
PRESTASI SAMPAI DENGAN MINGGU INI 5.255
PRESTASI MENURUT SCHEDULE 9.115
LEBIH CEPAT (+) / TERLAMBAT (-) (3.860)

Yogyakarta, 12 Juli 2021


di buat oleh,
PEJABAT PEMBUAT KOMITMEN TIM TEKNIS KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA
1. Cicilia Novi hendrawati, M.SC., M.Eng.
NIP. 19781102 200501 2 011 ...........................

2. Danang Dwi Wahyujati,S.Kom.,M.Eng


NIP. 19761028 199803 1 004 ...........................

SIGIT SETIAWAN, ST.MT 3. Sudaryanto


NIP. 19690605 199303 1 007 RISMAN WARCHAN ZULIANTO
NIP. 19770623 200501 1 013 ........................... Tim Leader Direktur
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : VIII ( Delapan )


Periode : 12 Juli 2021 sampai dengan 18 Juli 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
NILAI KONTRAK ADDENDUM I : Rp 720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
I PEKERJAAN PERSIAPAN
1 Pembuatan Papan Nama Pekerjaan 1.00 bh 250,000.00 250,000.00 0.038 1.000 0.038 - - 1.000 0.038
2 Pengukuran dan Pemasangan Bouwplank 28.56 m 12,198.91 348,400.73 0.053 28.560 0.053 - - 28.560 0.053
3 Pembuatan bedeng pekerja 9.00 m2 383,330.04 3,449,970.32 0.527 9.000 0.527 - - 9.000 0.527
4 Mobilisasi Demobilisasi Alat Berat 1.00 ls 2,500,000.00 2,500,000.00 0.382 - - - - - -
5 Pembuatan akses menuju badan sungai sementara - m2 113,128.49 - - - - - - - -
6 Dewatering dengan pompa air diesel 40.00 jam 25,000.00 1,000,000.00 0.153 - - - - - -
7 SMKK 1.00 ls 4,325,000.00 4,325,000.00 0.661 0.273 0.180 0.045 0.030 0.319 0.210
11,873,371.04 1.814 0.799 0.030 0.829
II PEKERJAAN PERBAIKAN TALUD SEGMEN 5
A PEKERJAAN TANAH DAN BETON BERTULANG
1 Penggalian 1 M3 Tanah Biasa 61.50 m3 67,972.30 4,180,296.46 0.639 - - - - - -
2 Pengurugan Kembali 1 M3 Galian Tanah 29.21 m3 49,023.50 1,431,976.45 0.219 - - - - - -
3 Bongkaran Pasangan Batu dan Beton Eksisting 39.18 m3 71,953.20 2,819,126.39 0.431 - - - - - -
4 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area 39.18 m3 19,888.18 779,218.70 0.119 - - - - - -
5 Pemadatan Tanah Eksisting 29.21 m3 49,023.50 1,431,976.45 0.219 - - - - - -
6 Pengurugan dengan pasir urug 1.23 m3 178,388.92 219,418.37 0.034 - - - - - -
7 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 1.23 m3 737,396.00 906,997.08 0.139 - - - - - -
8 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 4.92 m3 872,242.00 4,291,430.63 0.655 - - - - - -
a Pembesian dg Besi Polos atau Besi Ulir 714.10 m3 11,860.70 8,469,724.55 1.294 - - - - - -
b Bekisting untuk pondasi beton ( dipakai 2 kali ) 8.56 kg 89,375.55 765,054.68 0.117 - - - - - -
9 Pekerjaan Beton Dinding Talud Beton -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 9.97 m3 872,242.00 8,696,252.71 1.328 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 4,675.31 kg 11,860.70 55,452,440.67 8.470 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 10.12 m2 316,861.88 3,206,642.24 0.490 - - - - - -
10 Pekerjaan Beton Sloof 20x30cm -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 2.26 m3 872,242.00 1,971,266.91 0.301 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 671.58 kg 11,860.70 7,965,407.66 1.217 - - - - - -
c Memasang Bekisting untuk Sloof (dipakai 2 kali) 11.34 m2 89,375.55 1,013,518.69 0.155 - - - - - -
11 Pekerjaan Beton Konsul Cantilever -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 0.42 m3 872,242.00 366,341.64 0.056 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 194.43 kg 11,860.70 2,306,075.54 0.352 - - - - - -
c Memasang Bekisting untuk Balok (dipakai 2 kali) 2.10 m2 120,181.13 252,380.38 0.039 - - - - - -
12 Pekerjaan Plat Beton tebal 12 cm -
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 12.30 m3 872,242.00 10,728,576.57 1.639 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis 1,340.41 kg 10,697.66 14,339,244.07 2.190 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 6.15 m2 316,861.88 1,948,700.57 0.298 - - - - - -
13 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 21.00 m 77,312.85 1,623,569.93 0.248 - - - - - -
14 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 39.46 m 86,676.29 3,420,246.51 0.522 - - - - - -
15 Memasang Stek Besi 107.71 kg 11,860.70 1,277,515.80 0.195 - - - - - -
16 Pekerjaan Plat Beton Pot tebal 10 cm -
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 2.26 m3 872,242.00 1,971,266.91 0.301 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 107.71 kg 11,860.70 1,277,515.80 0.195 - - - - - -
c Bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm 32.80 m2 118,158.83 3,875,609.68 0.592 - - - - - -
146,987,792.05 22.451 - - -
B PEKERJAAN PASANGAN DINDING
1 Pemasangan Dinding Bata Merah Bakar Sekam Tebal 1/2 Bata Camp. 1SP 6PP 45.37 m2 116,576.48 5,289,075.10 0.808 - - - - - -
2 Pemasangan Plesteran 1 Pc 6 Pp Tebal 15 mm 155.38 m2 54,689.70 8,497,685.43 1.298 - - - - - -
3 Pemasangan Acian 155.38 m2 33,411.23 5,191,436.81 0.793 - - - - - -
4 Pemasangan Plesteran Skoning 1 Pc 2Pp lebar 10 cm 212.00 m 55,075.90 11,676,091.01 1.783 - - - - - -
5 Pemasangan Kepala Kolom 14.00 bh 50,000.00 700,000.00 0.107 - - - - - -
31,354,288.34 4.789 - - -

Laporan Progres Mingguan ke-8


III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PENGECATAN
1 Pengecatan Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Weathershield luar ruangan 155.38 m2 11,686.42 1,815,836.04 0.277 - - - - - -
1,815,836.04 0.277 - - -
B PEKERJAAN RUMAH TERDAMPAK
I. PEKERJAAN BONGKARAN
1 Membongkar 1 m2 genteng / sirap untuk dipergunakan lagi 77.17 m2 3,628.42 280,005.33 0.043 - - - - - -
2 Membongkar 1 m3 kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi 0.37 m3 991,595.91 366,890.49 0.056 - - - - - -
3 Pembongkaran 1 m3 pasangan bata merah dan membersihkan 11.13 m3 185,908.38 2,069,160.22 0.316 2.226 0.063 0.779 0.022 3.005 0.085
4 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 1.80 m3 688,832.33 1,239,898.20 0.189 0.108 0.011 - - 0.108 0.011
II. PEKERJAAN TANAH -
1 Menggali 1 m3 tanah biasa sedalam 1 meter 26.71 m3 67,972.30 1,815,540.14 0.277 21.368 0.222 - - 21.368 0.222
III. PEKERJAAN PONDASI -
1 Memasang 1 m3 pondasi batu belah, campuran 1 PC 6 PP 16.11 m2 665,195.09 10,716,292.98 1.637 9.666 0.982 - - 9.666 0.982
IV. PEKERJAAN BETON -
1 Membuat 1 m3 Sloof beton bertulang (200 kg besi + bekisting) 1.72 m3 3,844,764.87 6,612,995.58 1.010 0.688 0.404 - - 0.688 0.404
2 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) 3.92 m3 7,083,735.01 27,768,241.25 4.241 1.058 1.145 0.392 0.424 1.450 1.569
3 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) 9.08 m3 5,659,422.09 51,387,552.60 7.849 1.362 1.177 - - 1.362 1.177
V. PEKERJAAN DINDING -
1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP 191.94 m2 116,576.48 22,375,690.41 3.418 - - 19.194 0.342 19.194 0.342
VI PEKERJAAN KAYU -
1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.27 m3 16,443,774.77 4,439,819.19 0.678 - - - - - -
2 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti 12.08 m2 644,715.80 7,788,166.89 1.190 - - - - - -
3 Memasang 1 m3 konstruksi gordeng, kayu glugu 0.35 m3 4,450,537.65 1,557,688.18 0.238 - - - - - -
VII. PEKERJAAN PLESTERAN -
1 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm 75.69 m2 54,689.70 4,139,463.32 0.632 - - - - - -
2 Memasang 1 m2 acian 75.69 m2 33,411.23 2,528,895.95 0.386 - - - - - -
VIII. PEKERJAAN PENGECATAN -
1 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 75.69 m2 11,686.42 884,545.18 0.135 - - - - - -
IX. PEKERJAAN PENUTUP ATAP -
1 Memasang 1 m2 Atap Galvalum (Paket) 78.24 m3 190,000.00 14,864,806.70 2.270 - - - - - -
X. PEKERJAAN PENUTUP LANTAI DAN DINDING -
1 Memasang 1 m2 lantai keramik (30 x 30) cm 16.26 m2 114,193.22 1,856,781.81 0.284 - - - - - -
XI. PEKERJAAN SANITASI -
1 Memasang 1 buah Kloset Jongkok Porselen 2.00 bh 280,952.58 561,905.16 0.086 - - - - - -
2 Memasang 1 m Pipa PVC tipe AW 24.00 m2 19,406.20 465,748.90 0.071 - - - - - -
3 Memasang 1 m Pipa PVC tipe AW 1 24.00 m2 22,254.33 534,103.90 0.082 - - - - - -
4 Memasang 1 m Pipa PVC tipe AW 3 24.00 m2 63,036.61 1,512,878.67 0.231 - - - - - -
5 Memasang 1 buah Kran atau 2.00 m2 46,068.18 92,136.37 0.014 - - - - - -
6 Memasang 1 buah Floor Drain 2.00 m3 80,836.18 161,672.35 0.025 - - - - - -
7 Memasang 1 buah Pintu Kamar Mandi 2.00 bh 650,000.00 1,300,000.00 0.199 - - - - - -
167,320,879.74 25.557 4.005 0.788 4.793
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PEMBERSIHAN SALURAN
1 Penggalian Tanah Lumpur dan Endapan Limbah Sedalam 30 cm 65.62 m3 109,311.98 7,173,051.82 1.096 21.655 0.362 19.686 0.329 41.341 0.690
2 Pembersihan dan Pembuangan Tanah Lumpur dan Limbah Keluar Area 65.62 m3 29,796.55 1,955,249.81 0.299 19.686 0.090 19.686 0.090 39.372 0.179
3 Pemadatan Tanah Eksisting 65.62 m3 49,023.50 3,216,922.10 0.491 - - - - - -
4 Pengurugan dengan pasir urug, 10 cm 21.87 m3 178,388.92 3,901,365.68 0.596 - - - - - -
5 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 10.93 m3 737,396.00 8,059,738.25 1.231 - - - - - -
6 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 21.87 m3 872,242.00 19,075,932.48 2.914 - - - - - -
7 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 78.60 m 77,312.85 6,076,790.31 0.928 - - - - - -
8 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 642.60 m 86,676.29 55,698,185.61 8.507 - - - - - -
9 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,2m, K.300 70.00 bh 626,150.00 43,830,500.00 6.695 - - - - - -
10 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,8m, K.300 61.00 bh 750,000.00 45,750,000.00 6.988 - - - - - -
194,737,736.07 29.745 0.451 0.418 0.869

Laporan Progres Mingguan ke-8


B PEKERJAAN JARINGAN IPAL KOMUNAL
1 Pekerjaan Galian Tanah Pipa 46.07 m3 67,972.30 3,131,483.87 0.478 - - - - - -
2 Pengurugan dengan pasir urug 11.51 m3 178,388.92 2,053,256.47 0.314 - - - - - -
3 Pengurugan Kembali 1 M3 Galian Tanah 30.54 m3 49,023.50 1,497,264.55 0.229 - - - - - -
4 Pemasangan 1 M Pipa PVC tipe AW 4 64.50 m 90,907.55 5,863,536.89 0.896 - - - - - -
5 Saluran Pipa Air Limbah SDR - 41, Dia 15 cm , inc. fitting & Assecories 375.05 m 133,200.00 49,956,660.00 7.630 - - - - - -
6 Saluran Pipa Air Limbah SDR - 41, Dia 20 cm, , inc. fitting & Assecories - m 203,900.00 - - - - - - - -
7 Pemasangan Clean Out Inc. Fitting & Assecories 43.00 ttk 185,000.00 7,955,000.00 1.215 - - - - - -
8 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 100 org, 20 m3 / hari, 1.00 unit 7,500,000.00 7,500,000.00 1.146 - - - - - -
(Galian, Urugan, Pondasi, Tutup Beton, Penyambungan Instalasi) -
9 Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm 4.00 unit 975,000.00 3,900,000.00 0.596 - - - - - -
10 Pekerjaan Sumur Resapan, Dia 100 cm, Kedalaman 2 m, Inc. Tutup Beton Berlubang 15.00 ttk 500,000.00 7,500,000.00 1.146 - - - - - -
11 Grill Beton Penutup Sumur Resapan 15.00 unit 750,000.00 11,250,000.00 1.718 - - - - - -
100,607,201.77 15.367 - - -

JUMLAH 654,697,105.06 100.000 5.255 1.236 6.491


PRESTASI MINGGU LALU 5.255
PRESTASI MINGGU INI 1.236
PRESTASI SAMPAI DENGAN MINGGU INI 6.491
PRESTASI MENURUT SCHEDULE 12.904
LEBIH CEPAT (+) / TERLAMBAT (-) (6.413)

Yogyakarta, 19 Juli 2021


di buat oleh,
KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA

Noor Hasan Bambang Erlianto


Pengawas Pelaksana

Laporan Progres Mingguan ke-8


REKAPITULASI
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : VIII ( Delapan )


Periode : 12 Juli 2021 sampai dengan 18 Juli 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
NILAI KONTRAK ADDENDUM I : Rp 720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO PEKERJAAN PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp (%) BOBOT % BOBOT % BOBOT %

I PEKERJAAN PERSIAPAN 11,873,371.04 1.814 0.799 0.030 0.829

II PEKERJAAN PERBAIKAN TALUD SEGMEN 5


A PEKERJAAN TANAH DAN BETON BERTULANG 146,987,792.05 22.451 - - -
B PEKERJAAN PASANGAN DINDING 31,354,288.34 4.789 - - -

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PENGECATAN 1,815,836.04 0.277 - - -
B PEKERJAAN RUMAH TERDAMPAK 167,320,879.74 25.557 4.005 0.788 4.793

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PEMBERSIHAN SALURAN 194,737,736.07 29.745 0.451 0.418 0.869
B PEKERJAAN JARINGAN IPAL KOMUNAL 100,607,201.77 15.367 - - -

JUMLAH 654,697,105.06 100.000 5.255 1.236 6.491


PRESTASI MINGGU LALU 5.255
PRESTASI MINGGU INI 1.236
PRESTASI SAMPAI DENGAN MINGGU INI 6.491
PRESTASI MENURUT SCHEDULE 12.904
LEBIH CEPAT (+) / TERLAMBAT (-) (6.413)

Yogyakarta, 19 Juli 2021


di buat oleh,
PEJABAT PEMBUAT KOMITMEN TIM TEKNIS KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA
1. Cicilia Novi hendrawati, M.SC., M.Eng.
NIP. 19781102 200501 2 011 ...........................

2. Danang Dwi Wahyujati,S.Kom.,M.Eng


NIP. 19761028 199803 1 004 ...........................

SIGIT SETIAWAN, ST.MT 3. Sudaryanto


NIP. 19690605 199303 1 007 RISMAN WARCHAN ZULIANTO
NIP. 19770623 200501 1 013 ........................... Tim Leader Direktur
JADWAL WAKTU PELAKSANAAN PEKERJAAN
MUTUAL CHECK ( MC 1 )
INSTANSI : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021

BULAN KE-1 BULAN KE-2 BULAN KE-3 BULAN KE-4


KONTRAK MC 0 MC 1 KONTRAK MC 0 MC 1
Ming.1 Ming.2 Ming.3 Ming.4 Ming.5 Ming.6 Ming.7 Ming.8 Ming.9 Ming.10 Ming.11 Ming.12 Ming.13 Ming.14 Ming.15 Ming.16 Ming.17 Ming.18 Ming.19 Ming.20 Ming.21 Ming.22
NO JENIS PEKERJAAN 24/05/21 31/05/21 07/06/21 14/06/21 21/06/21 28/06/21 05/07/21 12/07/21 19/07/21 26/07/21 02/08/21 09/08/21 16/08/21 23/08/21 30/08/21 06/09/21 13/09/21 20/09/21 27/09/21 04/10/21 11/10/21 18/10/21 KET.
VOLUME HARGA SATUAN JUMLAH HARGA VOLUME JUMLAH HARGA VOLUME JUMLAH HARGA
SAT. BOBOT (%) BOBOT (%) BOBOT (%) s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
KONTRAK (Rp) (Rp) MC 0 (Rp) MC 1 (Rp)
30/05/21 06/06/21 13/06/21 20/06/21 27/06/21 04/07/21 11/07/21 18/07/21 25/07/21 01/08/21 08/08/21 15/08/21 22/08/21 29/08/21 05/09/21 12/09/21 19/09/21 26/09/21 03/10/21 10/10/21 17/10/21 20/10/21

I PEKERJAAN PERSIAPAN
1 Pembuatan Papan Nama Pekerjaan bh 1.00 250,000.00 250,000.00 1.00 250,000.00 1.00 250,000.00 0.038 0.038 0.038 0.038 -
2 Pengukuran dan Pemasangan Bouwplank m 28.56 12,198.91 348,400.73 28.56 348,400.73 28.56 348,400.73 0.053 0.053 0.053 0.027 0.027 -
3 Pembuatan bedeng pekerja m2 9.00 383,330.04 3,449,970.32 9.00 3,449,970.32 9.00 3,449,970.32 0.527 0.527 0.527 0.263 0.263 -
4 Mobilisasi Demobilisasi Alat Berat ls 1.00 2,500,000.00 2,500,000.00 1.00 2,500,000.00 1.00 2,500,000.00 0.382 0.382 0.382 0.191 0.191 0.191 0.191
5 Pembuatan akses menuju badan sungai sementara m2 24.00 113,128.49 2,715,083.64 - - - - 0.415 - - 0.207 0.207 -
6 Dewatering dengan pompa air diesel jam 40.00 25,000.00 1,000,000.00 40.00 1,000,000.00 40.00 1,000,000.00 0.153 0.153 0.153 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022
7 SMKK ls 1.00 4,325,000.00 4,325,000.00 1.00 4,325,000.00 1.00 4,325,000.00 0.661 0.661 0.661 0.030 0.030 0.030 0.030 0.030 0.030 0.030 0.030 0.032 0.032 0.032 0.032 0.032 0.032 0.032 0.032 0.032 0.032 0.032 0.032 0.032 0.032

II PEKERJAAN PERBAIKAN TALUD SEGMEN 5


A PEKERJAAN TANAH DAN BETON BERTULANG
1 Penggalian 1 M3 Tanah Biasa m3 50.00 67,972.30 3,398,615.01 61.50 4,180,296.46 13.50 917,626.05 0.519 0.639 0.140 0.160 0.160 0.160 0.160 0.070 0.070
2 Pengurugan Kembali 1 M3 Galian Tanah m3 33.15 49,023.50 1,625,129.04 29.21 1,431,976.45 6.41 314,240.64 0.248 0.219 0.048 0.073 0.073 0.024 0.024
3 Bongkaran Pasangan Batu dan Beton Eksisting m3 50.00 71,953.20 3,597,660.02 39.18 2,819,126.39 7.92 569,869.35 0.550 0.431 0.087 0.108 0.108 0.108 0.108 0.044 0.044
4 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area m3 50.00 19,888.18 994,408.76 39.18 779,218.70 7.92 157,514.35 0.152 0.119 0.024 0.030 0.030 0.030 0.012 0.012
5 Pemadatan Tanah Eksisting m3 11.84 49,023.50 580,438.24 29.21 1,431,976.45 6.41 314,240.64 0.089 0.219 0.048 0.109 0.109 0.024 0.024
6 Pengurugan dengan pasir urug m3 5.92 178,388.92 1,056,062.41 1.23 219,418.37 0.27 48,165.01 0.161 0.034 0.007 0.034 0.007
7 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 m3 2.96 737,396.00 2,182,692.15 1.23 906,997.08 0.27 199,096.92 0.333 0.139 0.030 0.069 0.030
8 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 m3 10.00 872,242.00 8,722,419.97 4.92 4,291,430.63 1.08 942,021.36 1.332 0.655 0.144 0.109 0.072 0.072
a Pembesian dg Besi Polos atau Besi Ulir kg - 11,860.70 - 714.10 8,469,724.55 156.69 1,858,452.79 - 1.294 0.284 0.216 0.142 0.142
b Bekisting untuk pondasi beton ( dipakai 2 kali ) m2 - 89,375.55 - 8.56 765,054.68 1.92 171,601.05 - 0.117 0.026 0.019 0.013 0.013
c Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 1.92 30,039.93 - - 0.005 0.005
9 Pekerjaan Beton Dinding Talud Beton
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 m3 10.00 872,242.00 8,722,419.97 9.97 8,696,252.71 2.16 1,884,042.71 1.332 1.328 0.288 0.144 0.144
b Pembesian dg Besi Polos atau Besi Ulir kg 1,000.00 11,860.70 11,860,698.15 4,675.31 55,452,440.67 1,026.67 12,177,022.97 1.812 8.470 1.860 0.930 0.930
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 40.00 316,861.88 12,674,475.27 10.12 3,206,642.24 9.02 2,858,094.17 1.936 0.490 0.437 0.218 0.218
d Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 9.02 141,125.10 0.022 0.022
10 Pekerjaan Beton Sloof 20x30cm
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 m3 4.74 872,242.00 4,134,427.07 2.26 1,971,266.91 0.49 427,398.58 0.632 0.301 0.065 0.065
b Pembesian dg Besi Polos atau Besi Ulir kg 400.00 11,860.70 4,744,279.26 671.58 7,965,407.66 147.55 1,750,046.01 0.725 1.217 0.267 0.267
c Memasang Bekisting untuk Sloof (dipakai 2 kali) m2 47.36 89,375.55 4,232,825.87 11.34 1,013,518.69 2.46 219,863.84 0.647 0.155 0.034 0.017 0.017
d Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 2.46 38,488.66 0.006 0.006
11 Pekerjaan Beton Konsul Cantilever
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 m3 7.75 872,242.00 6,759,875.48 0.42 366,341.64 0.09 78,501.78 1.033 0.056 0.012 0.006 0.006
b Pembesian dg Besi Polos atau Besi Ulir kg 700.00 11,860.70 8,302,488.71 194.43 2,306,075.54 47.58 564,332.02 1.268 0.352 0.086 0.043 0.043
c Memasang Bekisting untuk Balok (dipakai 2 kali) m2 40.00 120,181.13 4,807,245.27 2.10 252,380.38 0.45 54,081.51 0.734 0.039 0.008 0.008
d Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 0.45 7,040.61 0.001 0.001
12 Pekerjaan Plat Beton tebal 12 cm
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) m3 10.00 872,242.00 8,722,419.97 12.30 10,728,576.57 2.70 2,355,053.39 1.332 1.639 0.360 0.360
b Jaring Kawat baja/Wire Mesh M8 2 lapis kg 700.00 10,697.66 7,488,358.68 1,340.41 14,339,244.07 294.23 3,147,571.10 1.144 2.190 0.481 0.240 0.240
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 30.00 316,861.88 9,505,856.45 6.15 1,948,700.57 1.35 427,763.54 1.452 0.298 0.065 0.033 0.033
d Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 1.35 21,121.83 0.003 0.003
13 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm m 13.00 77,312.85 1,005,067.10 21.00 1,623,569.93 4.50 347,907.84 0.154 0.248 0.053 0.053
14 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm m 38.37 86,676.29 3,325,769.35 39.46 3,420,246.51 8.67 751,483.46 0.508 0.522 0.115 0.057 0.057
15 Memasang Stek Besi kg 200.00 11,860.70 2,372,139.63 107.71 1,277,515.80 23.67 280,742.73 0.362 0.195 0.043 0.043
16 Pekerjaan Plat Beton Pot tebal 10 cm
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) m3 4.74 872,242.00 4,134,427.07 2.26 1,971,266.91 0.49 427,398.58 0.632 0.301 0.065 0.033 0.033
b Pembesian dg Besi Polos atau Besi Ulir kg 200.00 11,860.70 2,372,139.63 107.71 1,277,515.80 23.67 280,742.73 0.362 0.195 0.043 0.021 0.021
c Bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm m2 30.00 118,158.83 3,544,764.95 32.80 3,875,609.68 7.20 850,743.59 0.541 0.592 0.130 0.065 0.065
d Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 7.20 112,649.75 - - 0.017 0.017
-
B PEKERJAAN PASANGAN DINDING
1 Pemasangan Dinding Bata Merah Bakar Sekam Tebal 1/2 Bata Camp. 1SP 6PP m2 42.00 116,576.48 4,896,212.34 45.37 5,289,075.10 9.97 1,162,267.55 0.748 0.808 0.178 0.178
2 Pemasangan Plesteran 1 Pc 6 Pp Tebal 15 mm m2 84.00 54,689.70 4,593,934.71 155.38 8,497,685.43 34.11 1,865,465.63 0.702 1.298 0.285 0.285
3 Pemasangan Acian m2 210.00 33,411.23 7,016,358.16 155.38 5,191,436.81 34.11 1,139,657.03 1.072 0.793 0.174 0.174
4 Pemasangan Plesteran Skoning 1 Pc 2Pp lebar 10 cm m 360.00 55,075.90 19,827,324.36 212.00 11,676,091.01 46.50 2,561,029.40 3.028 1.783 0.391 0.130 0.130 0.130
5 Pemasangan Kepala Kolom bh 10.00 50,000.00 500,000.00 14.00 700,000.00 3.00 150,000.00 0.076 0.107 0.023 0.023
- -
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PENGECATAN
1 Pengecatan Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Weathershield luar ruangan m2 210.00 11,686.42 2,454,148.34 155.38 1,815,836.04 34.11 398,623.81 0.375 0.277 0.061 0.061
- -
B PEKERJAAN RUMAH TERDAMPAK
I. PEKERJAAN BONGKARAN
1 Membongkar 1 m2 genteng / sirap untuk dipergunakan lagi m2 103.90 3,628.42 376,993.05 77.17 280,005.33 77.17 280,005.33 0.058 0.043 0.043 0.021 0.043
2 Membongkar 1 m3 kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi m3 0.46 991,595.91 456,134.12 0.37 366,890.49 0.37 366,890.49 0.070 0.056 0.056 0.028 0.056
3 Pembongkaran 1 m3 pasangan bata merah dan membersihkan m3 40.86 185,908.38 7,596,216.24 11.13 2,069,160.22 12.72 2,364,754.54 1.160 0.316 0.361 0.158 0.276
4 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 m3 9.20 688,832.33 6,337,257.47 1.80 1,239,898.20 1.50 1,033,248.50 0.968 0.189 0.158 0.095 0.146
II. PEKERJAAN TANAH
1 Menggali 1 m3 tanah biasa sedalam 1 meter m3 22.32 67,972.30 1,517,141.74 26.71 1,815,540.14 27.22 1,850,206.01 0.232 0.277 0.283 0.061
2 Pengurugan Kembali 1 m3 Galian Tanah m3 - 18,745.83 - - - 10.11 189,520.38 - - 0.029 0.029
3 Pengurugan dengan pasir urug m3 - 173,624.00 - - - 1.82 315,995.68 - - 0.048 0.048
4 Peninggian peil lantai m3 - 18,745.83 - 9.18 172,086.75 - - 0.026 0.026
III. PEKERJAAN PONDASI - -
1 Memasang 1 m3 pondasi batu belah, campuran 1 PC 6 PP m2 17.28 665,195.09 11,494,571.24 16.11 10,716,292.98 16.49 10,969,067.11 1.756 1.637 1.675 0.693
IV. PEKERJAAN BETON
1 Membuat 1 m3 Sloof beton bertulang (200 kg besi + bekisting) m3 3.55 3,844,764.87 13,648,915.30 1.72 6,612,995.58 1.06 4,075,450.77 2.085 1.010 0.622 0.109 0.109
2 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) m3 4.94 7,083,735.01 34,993,650.96 3.92 27,768,241.25 2.29 16,221,753.18 5.345 4.241 2.478 0.303 0.303 0.303
3 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) m3 5.00 5,659,422.09 28,297,110.46 9.08 51,387,552.60 3.05 17,261,237.38 4.322 7.849 2.637 0.365 0.365 0.365 0.365
4 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 m3 - 723,713.11 - - - 0.14 101,319.83 - - 0.015 0.015
5 Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting) m3 - 3,127,107.54 0.57 1,782,451.30 - - 0.272 0.272

Jangka Waktu Pelaksanaan


MC1 hal.46
BULAN KE-1 BULAN KE-2 BULAN KE-3 BULAN KE-4
KONTRAK MC 0 MC 1 KONTRAK MC 0 MC 1
Ming.1 Ming.2 Ming.3 Ming.4 Ming.5 Ming.6 Ming.7 Ming.8 Ming.9 Ming.10 Ming.11 Ming.12 Ming.13 Ming.14 Ming.15 Ming.16 Ming.17 Ming.18 Ming.19 Ming.20 Ming.21 Ming.22
NO JENIS PEKERJAAN 24/05/21 31/05/21 07/06/21 14/06/21 21/06/21 28/06/21 05/07/21 12/07/21 19/07/21 26/07/21 02/08/21 09/08/21 16/08/21 23/08/21 30/08/21 06/09/21 13/09/21 20/09/21 27/09/21 04/10/21 11/10/21 18/10/21 KET.
VOLUME HARGA SATUAN JUMLAH HARGA VOLUME JUMLAH HARGA VOLUME JUMLAH HARGA
SAT. BOBOT (%) BOBOT (%) BOBOT (%) s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
KONTRAK (Rp) (Rp) MC 0 (Rp) MC 1 (Rp)
30/05/21 06/06/21 13/06/21 20/06/21 27/06/21 04/07/21 11/07/21 18/07/21 25/07/21 01/08/21 08/08/21 15/08/21 22/08/21 29/08/21 05/09/21 12/09/21 19/09/21 26/09/21 03/10/21 10/10/21 17/10/21 20/10/21
6 Sloof 150 x 200 dengan beton K 225 Tulangan 105 kg m3 - 3,295,166.46 - - - 0.74 2,438,423.18 - - 0.372 0.372
7 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m' - 77,312.85 67.35 5,207,020.70 - - 0.795 0.199 0.199 0.199 0.199
8 Balok 150 x 200 dengan beton K 225 Tulangan 105 kg m3 - 3,705,897.33 1.01 3,742,956.31 - - 0.572 0.143 0.143 0.143 0.143
9 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm m' - 86,676.29 54.15 4,693,521.24 - - 0.717 0.179 0.179 0.179 0.179
10 Membuat 1 m3 Plat Lantai beton bertulang m3 - 3,119,381.73 - - - 2.95 9,202,176.12 - - 1.406 0.351 0.351 0.351 0.351
11 Membuat 1 m3 Plat Tangga beton bertulang m3 - 3,119,381.73 - - - 0.72 2,245,954.85 - - 0.343 0.086 0.086 0.086 0.086
12 Membuat 1 m3 Plat Water torn beton bertulang m3 - 3,119,381.73 - - - 0.42 1,310,140.33 - - 0.200 0.200
V. PEKERJAAN DINDING
1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP m2 127.00 116,576.48 14,805,213.51 191.94 22,375,690.41 161.84 18,866,738.23 2.261 3.418 2.882 0.635 0.635 0.635 0.635
2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP, trap tangga m2 - 250,668.02 6.30 1,579,208.52 - - 0.241 0.060 0.060 0.060 0.060
VI PEKERJAAN KAYU
1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti m3 0.50 16,443,774.77 8,221,887.38 0.27 4,439,819.19 0.27 4,439,819.19 1.256 0.678 0.678 0.339 0.339
Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti m3 - 8,048,535.00 - - - 0.02 160,970.70 - - 0.025 0.012 0.012
2 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti m2 12.72 644,715.80 8,200,785.00 12.08 7,788,166.89 12.32 7,942,898.68 1.253 1.190 1.213 1.213
3 Memasang 1 m3 konstruksi gordeng, kayu glugu m3 0.21 4,450,537.65 934,612.91 0.35 1,557,688.18 - - 0.143 0.238 - - -
VII. PEKERJAAN PLESTERAN
1 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm m2 100.00 54,689.70 5,468,969.90 75.69 4,139,463.32 96.76 5,291,775.27 0.835 0.632 0.808 0.808
2 Memasang 1 m2 acian m2 100.00 33,411.23 3,341,122.93 75.69 2,528,895.95 96.76 3,232,870.55 0.510 0.386 0.494 0.494
3 Pemasangan 1 m2 plesteran ciprat 1SP : 2PP m2 - 45,029.48 - - - 33.50 1,508,487.73 - - 0.230 0.230
VIII. PEKERJAAN PENGECATAN
1 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) m2 100.00 11,686.42 1,168,642.06 75.69 884,545.18 96.76 1,130,778.06 0.179 0.135 0.173 0.173
IX. PEKERJAAN PENUTUP ATAP
1 Memasang 1 m2 Atap Galvalum (Paket) m3 78.20 190,000.00 14,858,000.00 78.24 14,864,806.70 78.51 14,917,137.50 2.269 2.270 2.278 2.278
2 Pemasangan 1 m talang datar Galvalum lebar 60 cm m' 105,483.99 6.00 632,903.97 - - 0.097 0.097
X. PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Memasang 1 m2 lantai keramik (30 x 30) cm m2 8.54 114,193.22 975,210.13 16.26 1,856,781.81 - - 0.149 0.284 - -
2 Membuat rabat beton lantai mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 m3 - 723,713.11 - - - 2.08 1,504,722.31 0.230 0.230
3 Memasang 1 m2 lantai keramik (20 x 20) cm m' - 184,674.28 - - - 4.99 921,524.65 0.141 0.141
XI. PEKERJAAN SANITASI
1 Memasang 1 buah Kloset Jongkok Porselen bh 2.00 280,952.58 561,905.16 2.00 561,905.16 2.00 561,905.16 0.086 0.086 0.086 0.086
2 Memasang 1 m Pipa PVC tipe AW m2 24.00 19,406.20 465,748.90 24.00 465,748.90 16.00 310,499.27 0.071 0.071 0.047 0.047
3 Memasang 1 m Pipa PVC tipe AW 1 m2 24.00 22,254.33 534,103.90 24.00 534,103.90 8.00 178,034.63 0.082 0.082 0.027 0.027
4 Memasang 1 m Pipa PVC tipe AW 3 m2 24.00 63,036.61 1,512,878.67 24.00 1,512,878.67 18.00 1,134,659.00 0.231 0.231 0.173 0.173
5 Memasang 1 buah Kran atau m2 2.00 46,068.18 92,136.37 2.00 92,136.37 2.00 92,136.37 0.014 0.014 0.014 0.014
6 Memasang 1 buah Floor Drain m3 2.00 80,836.18 161,672.35 2.00 161,672.35 2.00 161,672.35 0.025 0.025 0.025 0.025
7 Memasang 1 buah Pintu Kamar Mandi bh 2.00 650,000.00 1,300,000.00 2.00 1,300,000.00 2.00 1,300,000.00 0.199 0.199 0.199 0.199
8 Pemasangan 1 M Pipa PVC tipe D 4 m' - 85,618.17 - - - 12.00 1,027,418.08 - - 0.157 0.157
XII. PEKERJAAN ELEKTRIKAL - - - -
1 Instalasi Penerangan menggunakan kabel NYY 3x2,5mm² dalam pipa conduit Ø 20mm. titik - 105,000.00 - - - 10.00 1,050,000.00 - - 0.160 0.160
2 Instalasi stop kontak dinding, menggunakan kabel NYM 3x2,5mm² titik - 100,000.00 - - - 5.00 500,000.00 - - 0.076 0.076
3 Saklar tunggal inbow, 1 gang 1 way bh - 20,000.00 - - - 4.00 80,000.00 - - 0.012 0.012
4 Saklar seri inbow, 1 gang 2 way bh - 25,000.00 - - - 4.00 100,000.00 - - 0.015 0.015
5 Stop kontak wall type 1ph, 16A, 1 gang bh - 20,000.00 - - - 5.00 100,000.00 - - 0.015 0.015
6 Lampu PLC 18 Watt dengan fitting gantung bh - 75,000.00 - - - 8.00 600,000.00 - - 0.092 0.092
7 Lampu PLC 7 Watt dengan fitting gantung bh - 65,000.00 - - - 2.00 130,000.00 - - 0.020 0.020
8 Penyambungan kabel Ls - 500,000.00 - - - 1.00 500,000.00 - - 0.076 0.076
9 Box MCB + MCB bh - 250,000.00 - - - 2.00 500,000.00 - - 0.076 0.076
XIII. PEKERJAAN LAIN-LAIN
1 Pintu Folding gate m2 - 788,049.93 6.00 4,728,299.56 - - 0.722 0.361 0.361
2 Railling pengaman besi Hollow 40x40 / 40x20 mm, finishing cat m2 - 550,000.00 11.48 6,312,240.00 - - 0.964 0.964
-
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PEMBERSIHAN SALURAN
1 Penggalian Tanah Lumpur dan Endapan Limbah Sedalam 30 cm m3 85.36 109,311.98 9,330,870.22 65.62 7,173,051.82 69.70 7,619,044.68 1.425 1.096 1.164 0.713 0.548 0.548 0.237 0.237
2 Pembersihan dan Pembuangan Tanah Lumpur dan Limbah Keluar Area m3 85.36 29,796.55 2,543,433.77 65.62 1,955,249.81 90.90 2,708,506.67 0.388 0.299 0.414 0.194 0.149 0.149 0.117 0.117
3 Pemadatan Tanah Eksisting m3 48.91 49,023.50 2,397,739.40 65.62 3,216,922.10 69.70 3,416,937.98 0.366 0.491 0.522 0.491 0.522
4 Pengurugan dengan pasir urug, 10 cm m3 17.07 178,388.92 3,045,098.87 21.87 3,901,365.68 21.87 3,901,365.68 0.465 0.596 0.596 0.298 0.298 0.298 0.298
Pengurugan dengan pasir urug, 10 cm m3 - 173,624.00 - - - 1.36 236,128.64 - - 0.036 0.018 0.018
5 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 m3 17.07 737,396.00 12,587,349.68 10.93 8,059,738.25 10.93 8,059,738.25 1.923 1.231 1.231 0.616 0.616 0.616 0.616
Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 m3 - 723,713.11 - - - 0.68 492,124.91 - - 0.075 0.038 0.038
6 Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 m3 17.07 872,242.00 14,889,170.90 21.87 19,075,932.48 23.23 20,262,181.60 2.274 2.914 3.095 1.457 1.457 1.547 1.547
a Jaring Kawat baja/Wire Mesh M5 1 lapis kg - 10,697.66 - - - 375.85 4,020,713.73 - 0.614 0.307 0.307
7 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm m 466.40 77,312.85 36,058,714.99 78.60 6,076,790.31 133.20 10,298,072.12 5.508 0.928 1.573 0.524 0.524 0.524
8 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm m 466.40 86,676.29 40,425,822.86 642.60 55,698,185.61 718.80 62,302,919.11 6.175 8.507 9.516 2.127 2.379 2.379 2.379 2.379
9 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,2m, K.300 bh 65.00 626,150.00 40,699,750.00 70.00 43,830,500.00 - - 6.217 6.695 -
10 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,8m, K.300 bh 32.00 750,000.00 24,000,000.00 61.00 45,750,000.00 - - 3.666 6.988 -
11 Pekerjaan Plat Beton tebal 15 cm - - - - - - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 m3 - 872,242.00 - - - 8.37 7,300,665.52 - - 1.115 0.223 0.223 0.112 0.112 0.112 0.112 0.112 0.112
b Jaring Kawat baja/Wire Mesh M8 2 lapis kg - 10,697.66 - - - 608.09 6,505,137.18 - - 0.994 0.199 0.199 0.099 0.099 0.099 0.099 0.099 0.099
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - 13.95 4,420,223.25 - - 0.675 0.135 0.135 0.068 0.068 0.068 0.068 0.068 0.068
d Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 13.95 218,258.88 - - 0.033 0.033
12 Pekerjaan Plat Beton tebal 10 cm - - - - - - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 m3 - 872,242.00 - - - 17.65 15,395,071.25 - - 2.351 0.470 0.470 0.235 0.235 0.235 0.235 0.235 0.235
b Jaring Kawat baja/Wire Mesh M8 1 lapis kg - 10,697.66 - - - 962.04 10,291,572.26 - - 1.572 0.314 0.314 0.157 0.157 0.157 0.157 0.157 0.157
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - 44.14 13,986,283.46 - - 2.136 0.427 0.427 0.214 0.214 0.214 0.214 0.214 0.214
d Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 44.14 690,605.52 - - 0.105 0.105

B PEKERJAAN JARINGAN IPAL KOMUNAL


1 Pekerjaan Galian Tanah Pipa MC 0 m3 81.86 67,972.30 5,564,212.49 46.07 3,131,483.87 46.07 3,131,483.87 0.850 0.478 0.478 0.120 0.120 0.120 0.120
2 Pengurugan dengan pasir urug m3 6.82 178,388.92 1,216,612.43 11.51 2,053,256.47 11.51 2,053,256.47 0.186 0.314 0.314 0.105 0.105 0.105
3 Pengurugan Kembali 1 M3 Galian Tanah m3 24.56 49,023.50 1,204,017.17 30.54 1,497,264.55 30.54 1,497,264.55 0.184 0.229 0.229 0.076 0.076 0.076
4 Pemasangan 1 M Pipa PVC tipe AW 4 m 30.00 90,907.55 2,727,226.46 64.50 5,863,536.89 - - 0.417 0.896 -
5 Saluran Pipa Air Limbah SDR - 41, Dia 15 cm , inc. fitting & Assecories m 343.20 133,200.00 45,714,240.00 375.05 49,956,660.00 375.05 49,956,660.00 6.983 7.630 7.630 0.848 0.848 0.848 0.848 0.707 0.707 0.707 0.707 0.707 0.707
6 Saluran Pipa Air Limbah SDR - 41, Dia 20 cm, , inc. fitting & Assecories m 113.70 203,900.00 23,183,430.00 - - - - 3.541 - -
7 Pemasangan Clean Out Inc. Fitting & Assecories ttk 17.00 185,000.00 3,145,000.00 43.00 7,955,000.00 43.00 7,955,000.00 0.480 1.215 1.215 0.135 0.135 0.135 0.135 0.113 0.113 0.113 0.113 0.113 0.113
8 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 100 org, 20 m3 / hari, (Galia unit 1.00 7,500,000.00 7,500,000.00 1.00 7,500,000.00 - - 1.146 1.146 -
9 Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm unit 4.00 975,000.00 3,900,000.00 4.00 3,900,000.00 - - 0.596 0.596 - - -
10 Pekerjaan Sumur Resapan, Dia 100 cm, Kedalaman 2 m, Inc. Tutup Beton Berlubang ttk 15.00 500,000.00 7,500,000.00 15.00 7,500,000.00 - - 1.146 1.146 - 0.382 0.382
11 Grill Beton Penutup Sumur Resapan unit 20.00 750,000.00 15,000,000.00 15.00 11,250,000.00 - - 2.291 1.718 -
12 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 m3 - 688,832.33 - - - 13.49 9,292,348.18 - - 1.419 0.237 0.237 0.237 0.237 0.237 0.237
13 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area m3 - 19,888.18 - - - 13.49 268,291.48 - - 0.041 0.007 0.007 0.007 0.007 0.007 0.007
14 Pemasangan 1 M Pipa PVC tipe D 4 m - 85,618.17 - - - 64.50 5,522,372.20 - - 0.844 0.094 0.094 0.094 0.094 0.078 0.078 0.078 0.078 0.078 0.078
15 Pekerjaan Sumur Resapan kedalaman 4 Buis Beton Dia 80 cm ttk - 474,124.46 - - - 15.00 7,111,866.88 - - 1.086 1.086

Jangka Waktu Pelaksanaan


MC1 hal.47
BULAN KE-1 BULAN KE-2 BULAN KE-3 BULAN KE-4
KONTRAK MC 0 MC 1 KONTRAK MC 0 MC 1
Ming.1 Ming.2 Ming.3 Ming.4 Ming.5 Ming.6 Ming.7 Ming.8 Ming.9 Ming.10 Ming.11 Ming.12 Ming.13 Ming.14 Ming.15 Ming.16 Ming.17 Ming.18 Ming.19 Ming.20 Ming.21 Ming.22
NO JENIS PEKERJAAN 24/05/21 31/05/21 07/06/21 14/06/21 21/06/21 28/06/21 05/07/21 12/07/21 19/07/21 26/07/21 02/08/21 09/08/21 16/08/21 23/08/21 30/08/21 06/09/21 13/09/21 20/09/21 27/09/21 04/10/21 11/10/21 18/10/21 KET.
VOLUME HARGA SATUAN JUMLAH HARGA VOLUME JUMLAH HARGA VOLUME JUMLAH HARGA
SAT. BOBOT (%) BOBOT (%) BOBOT (%) s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
KONTRAK (Rp) (Rp) MC 0 (Rp) MC 1 (Rp)
30/05/21 06/06/21 13/06/21 20/06/21 27/06/21 04/07/21 11/07/21 18/07/21 25/07/21 01/08/21 08/08/21 15/08/21 22/08/21 29/08/21 05/09/21 12/09/21 19/09/21 26/09/21 03/10/21 10/10/21 17/10/21 20/10/21
16 Pasang Grill Besi Penutup Sumur Resapan unit - 826,875.00 - - - 15.00 12,403,125.00 - - 1.894 0.947 0.947

C PEKERJAAN PEMASANGAN DAN PENGADAAN INSTALASI IPAL


1 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 50 org, 10 m3 / hari
MC 1
a Pengadaan Unit IPAL kap 50 org, 10 m3 / hari unit - 110,250,000.00 - - - 1.00 110,250,000.00 - - 16.840 3.368 2.245 2.245 2.245 2.245 2.245 2.245
b Galian Tanah m3 - 67,972.30 - - - 57.21 3,888,695.29 - - 0.594 0.198 0.198 0.198
c Pengurugan Kembali 1 M3 Galian Tanah m3 - 49,023.50 - - - 2.39 117,166.17 - - 0.018 0.006 0.006 0.006
d Pengurugan dengan pasir urug m3 - 178,388.92 - - - 1.83 326,254.80 - - 0.050 0.007 0.007 0.007 0.007 0.007 0.007 0.007
e Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Dinding, Lantai dan Tutup m3 - 872,242.00 - - - 11.77 10,266,288.31 - - 1.568 0.523 0.523 0.523
Jaring Kawat baja/Wire Mesh M8 kg - 10,697.66 - - - 713.69 7,634,809.58 - - 1.166 0.389 0.389 0.389
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - 30.14 9,550,217.12 - - 1.459 0.486 0.486 0.486
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 30.14 471,564.35 - - 0.072 0.024 0.024 0.024
f Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Inlet m3 - 872,242.00 - - - 0.30 261,672.60 - - 0.040 0.013 0.013 0.013
Jaring Kawat baja/Wire Mesh M8 kg - 10,697.66 - - - 11.06 118,316.07 - - 0.018 0.006 0.006 0.006
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - 0.66 209,128.84 - - 0.032 0.011 0.011 0.011
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 0.66 10,326.23 - - 0.002 0.001 0.001 0.001
g Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Outlet m3 - 872,242.00 - - - 0.41 357,619.22 - - 0.055 0.018 0.018 0.018
Jaring Kawat baja/Wire Mesh M8 kg - 10,697.66 - - - 14.98 160,250.88 - - 0.024 0.008 0.008 0.008
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - 0.96 304,187.41 - - 0.046 0.015 0.015 0.015
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 0.96 15,019.97 - - 0.002 0.001 0.001 0.001
h Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Kolom 15 x 15 cm m3 - 872,242.00 - - - 0.47 409,953.74 - - 0.063 0.021 0.021 0.021
Pembesian dg Besi Polos atau Besi Ulir kg - 11,860.70 - - - 119.39 1,416,048.75 - - 0.216 0.072 0.072 0.072
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - 1.44 456,281.11 - - 0.070 0.023 0.023 0.023
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 1.44 22,529.95 - - 0.003 0.001 0.001 0.001
i Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Balok 15 x 20 cm m3 - 872,242.00 - - - 0.12 104,669.04 - - 0.016 0.005 0.005 0.005
Pembesian dg Besi Polos atau Besi Ulir kg - 11,860.70 - - - 23.91 283,589.29 - - 0.043 0.014 0.014 0.014
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - 0.55 174,274.03 - - 0.027 MC 0 0.009 0.009 0.009
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 0.55 8,605.19 - - 0.001 0.000 0.000 0.000
j Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, pondasi 60 x 60 x 20 cm m3 - 872,242.00 - - - 0.72 628,014.24 - - 0.096 0.032 0.032 0.032
Pembesian dg Besi Polos atau Besi Ulir kg - 11,860.70 - - - 36.93 438,015.58 - - 0.067 0.022 0.022 0.022
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - 1.20 380,234.26 - - 0.058 0.019 0.019 0.019
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 1.20 18,774.96 - - 0.003 0.001 0.001 0.001
k Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm - - 975,000.00 - - - 4.00 3,900,000.00 - - 0.596 0.298 0.298

Rencana Kemajuan Mingguan 654,697,105.06 654,697,105.06 654,697,105.06 100.000 100.000 100.000 0.095 0.718 0.501 0.937 1.803 2.688 2.964 4.087 6.711 6.870 5.876 8.118 7.585 7.477 10.026 10.362 11.178 4.745 4.328 1.218 1.491 0.221
Rencana Komulatif Kemajuan Mingguan - - - 0.095 0.813 1.314 2.251 4.054 6.742 9.706 13.793 20.504 27.374 33.251 41.368 48.953 56.430 66.457 76.819 87.997 92.742 97.070 98.288 99.779 100.000
Rencana Kemajuan Mingguan MC 0 - - 0.095 0.718 0.501 0.937 1.975 3.416 2.985 3.789 5.109 5.356 7.803 10.422 6.709 8.147 11.152 9.516 11.225 5.666 4.074 0.766 1.015 0.228
Rencana Komulatif Kemajuan Mingguan MC 0 - - 0.095 0.813 1.314 2.251 2.713 6.130 9.115 12.904 17.920 23.276 31.079 41.502 48.211 56.358 67.510 77.026 88.251 93.917 97.991 98.757 99.772 100.000
Rencana Kemajuan Mingguan MC 1 - - 0.095 0.718 0.501 0.937 1.981 3.423 2.992 3.796 7.292 8.567 7.733 7.941 7.753 11.855 7.909 7.598 7.505 5.879 4.353 4.189 3.105 1.829
Rencana Komulatif Kemajuan Mingguan MC 1 - - 0.095 0.813 1.314 2.251 2.601 6.024 9.016 12.812 13.784 22.351 30.084 38.024 45.777 57.632 65.541 73.139 80.644 86.523 90.876 95.065 98.171 100.000
Realisasi Kemajuan Mingguan
Realisasi Komulatif Kemajuan Mingguan
Deviasi (+/-)

Yogyakarta, 19 Juli 2021


Dibuat Oleh
PEJABAT PEMBUAT KOMITMEN TIM TEKNIS KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA
1. Cicilia Novi hendrawati, M.SC., M.Eng.
NIP. 19781102 200501 2 011

2. Danang Dwi Wahyujati,S.Kom.,M.Eng


NIP. 19761028 199803 1 004

SIGIT SETIAWAN, ST.MT 3. Sudaryanto


NIP. 19690605 199303 1 007 RISMAN WARCHAN ZULIANTO
NIP. 19770623 200501 1 013 Tim Leader Direktur

Jangka Waktu Pelaksanaan


MC1 hal.48
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : IX ( Sembilan )


Periode : 19 Juli 2021 sampai dengan 25 Juli 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
ADDENDUM II : 050 / 1909 / VII / 2021, TANGGAL 19 JULI 2021
NILAI KONTRAK ADDENDUM II : Rp 720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
I PEKERJAAN PERSIAPAN
1 Pembuatan Papan Nama Pekerjaan 1.00 bh 250,000.00 250,000.00 0.038 1.000 0.038 - - 1.000 0.038
2 Pengukuran dan Pemasangan Bouwplank 28.56 m 12,198.91 348,400.73 0.053 28.560 0.053 - - 28.560 0.053
3 Pembuatan bedeng pekerja 9.00 m2 383,330.04 3,449,970.32 0.527 9.000 0.527 - - 9.000 0.527
4 Mobilisasi Demobilisasi Alat Berat 1.00 ls 2,500,000.00 2,500,000.00 0.382 - - 0.409 0.156 0.409 0.156
5 Pembuatan akses menuju badan sungai sementara - m2 113,128.49 - - - - - - - -
6 Dewatering dengan pompa air diesel 40.00 jam 25,000.00 1,000,000.00 0.153 - - 16.364 0.062 16.364 0.062
7 SMKK 1.00 ls 4,325,000.00 4,325,000.00 0.661 0.319 0.210 0.090 0.060 0.409 0.270
11,873,371.04 1.814 0.829 0.278 1.107
II PEKERJAAN PERBAIKAN TALUD SEGMEN 5
A PEKERJAAN TANAH DAN BETON BERTULANG
1 Penggalian 1 M3 Tanah Biasa 13.50 m3 67,972.30 917,626.05 0.140 - - - - - -
2 Pengurugan Kembali 1 M3 Galian Tanah 6.41 m3 49,023.50 314,240.64 0.048 - - - - - -
3 Bongkaran Pasangan Batu dan Beton Eksisting 7.92 m3 71,953.20 569,869.35 0.087 - - - - - -
4 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area 7.92 m3 19,888.18 157,514.35 0.024 - - - - - -
5 Pemadatan Tanah Eksisting 6.41 m3 49,023.50 314,240.64 0.048 - - - - - -
6 Pengurugan dengan pasir urug 0.27 m3 178,388.92 48,165.01 0.007 - - - - - -
7 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.27 m3 737,396.00 199,096.92 0.030 - - - - - -
8 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 1.08 m3 872,242.00 942,021.36 0.144 - - - - - -
a Pembesian dg Besi Polos atau Besi Ulir 156.69 kg 11,860.70 1,858,452.79 0.284 - - - - - -
b Bekisting untuk pondasi beton ( dipakai 2 kali ) 1.92 m2 89,375.55 171,601.05 0.026 - - - - - -
c Pembongkaran 1 M2 Bekisting 1.92 m2 15,645.80 30,039.93 0.005 - - - - - -
9 Pekerjaan Beton Dinding Talud Beton
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 2.16 m3 872,242.00 1,884,042.71 0.288 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 1,026.67 kg 11,860.70 12,177,022.97 1.860 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 9.02 m2 316,861.88 2,858,094.17 0.437 - - - - - -
d Pembongkaran 1 M2 Bekisting 9.02 m2 15,645.80 141,125.10 0.022 - - - - - -
10 Pekerjaan Beton Sloof 20x30cm
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 0.49 m3 872,242.00 427,398.58 0.065 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 147.55 kg 11,860.70 1,750,046.01 0.267 - - - - - -
c Memasang Bekisting untuk Sloof (dipakai 2 kali) 2.46 m2 89,375.55 219,863.84 0.034 - - - - - -
d Pembongkaran 1 M2 Bekisting 2.46 m2 15,645.80 38,488.66 0.006 - - - - - -
11 Pekerjaan Beton Konsul Cantilever
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 0.09 m3 872,242.00 78,501.78 0.012 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 47.58 kg 11,860.70 564,332.02 0.086 - - - - - -
c Memasang Bekisting untuk Balok (dipakai 2 kali) 0.45 m2 120,181.13 54,081.51 0.008 - - - - - -
d Pembongkaran 1 M2 Bekisting 0.45 m2 15,645.80 7,040.61 0.001 - - - - - -
12 Pekerjaan Plat Beton tebal 12 cm
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 2.70 m3 872,242.00 2,355,053.39 0.360 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis 294.23 kg 10,697.66 3,147,571.10 0.481 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.35 m2 316,861.88 427,763.54 0.065 - - - - - -
d Pembongkaran 1 M2 Bekisting 1.35 m2 15,645.80 21,121.83 0.003 - - - - - -
13 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 4.50 m 77,312.85 347,907.84 0.053 - - - - - -
14 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 8.67 m 86,676.29 751,483.46 0.115 - - - - - -
15 Memasang Stek Besi 23.67 kg 11,860.70 280,742.73 0.043 - - - - - -
16 Pekerjaan Plat Beton Pot tebal 10 cm
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 0.49 m3 872,242.00 427,398.58 0.065 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 23.67 kg 11,860.70 280,742.73 0.043 - - - - - -
c Bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm 7.20 m2 118,158.83 850,743.59 0.130 - - - - - -
d Pembongkaran 1 M2 Bekisting 7.20 m2 15,645.80 112,649.75 0.017 - - - - - -
34,726,084.58 5.304 - - -
B PEKERJAAN PASANGAN DINDING
1 Pemasangan Dinding Bata Merah Bakar Sekam Tebal 1/2 Bata Camp. 1SP 6PP 9.97 m2 116,576.48 1,162,267.55 0.178 - - - - - -
2 Pemasangan Plesteran 1 Pc 6 Pp Tebal 15 mm 34.11 m2 54,689.70 1,865,465.63 0.285 - - - - - -
3 Pemasangan Acian 34.11 m2 33,411.23 1,139,657.03 0.174 - - - - - -
4 Pemasangan Plesteran Skoning 1 Pc 2Pp lebar 10 cm 46.50 m 55,075.90 2,561,029.40 0.391 - - - - - -
5 Pemasangan Kepala Kolom 3.00 bh 50,000.00 150,000.00 0.023 - - - - - -
Laporan Progres Mingguan ke-9
HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
6,878,419.61 1.051 - - -

Laporan Progres Mingguan ke-9


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PENGECATAN
1 Pengecatan Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Weathershield luar ruangan 34.11 m2 11,686.42 398,623.81 0.061 - - - - - -
398,623.81 0.061 - - -
B PEKERJAAN RUMAH TERDAMPAK
I. PEKERJAAN BONGKARAN
1 Membongkar 1 m2 genteng / sirap untuk dipergunakan lagi 77.17 m2 3,628.42 280,005.33 0.043 - - - - - -
2 Membongkar 1 m3 kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi 0.37 m3 991,595.91 366,890.49 0.056 - - - - - -
3 Pembongkaran 1 m3 pasangan bata merah dan membersihkan 12.72 m3 185,908.38 2,364,754.54 0.361 3.005 0.085 - - 3.005 0.085
4 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 1.50 m3 688,832.33 1,033,248.50 0.158 0.108 0.011 - - 0.108 0.011
II. PEKERJAAN TANAH
1 Menggali 1 m3 tanah biasa sedalam 1 meter 27.22 m3 67,972.30 1,850,206.01 0.283 21.368 0.222 - - 21.368 0.222
2 Pengurugan Kembali 1 m3 Galian Tanah 10.11 m3 18,745.83 189,520.38 0.029 - - 7.987 0.023 7.987 0.023
3 Pengurugan dengan pasir urug 1.82 m3 173,624.00 315,995.68 0.048 - - 1.438 0.038 1.438 0.038
4 Peninggian peil lantai 9.18 m3 18,745.83 172,086.75 0.026 - - - - - -
III. PEKERJAAN PONDASI
1 Memasang 1 m3 pondasi batu belah, campuran 1 PC 6 PP 16.49 m2 665,195.09 10,969,067.11 1.675 9.666 0.982 3.298 0.335 12.964 1.317
IV. PEKERJAAN BETON
1 Membuat 1 m3 Sloof beton bertulang (200 kg besi + bekisting) 1.06 m3 3,844,764.87 4,075,450.77 0.622 0.688 0.404 - - 0.688 0.404
2 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) 2.29 m3 7,083,735.01 16,221,753.18 2.478 1.450 1.569 - - 1.450 1.569
3 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) 3.05 m3 5,659,422.09 17,261,237.38 2.637 1.362 1.177 0.151 0.131 1.513 1.308
4 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.14 m3 723,713.11 101,319.83 0.015 - - 0.105 0.012 0.105 0.012
5 Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting) 0.57 m3 3,127,107.54 1,782,451.30 0.272 - - 0.428 0.204 0.428 0.204
6 Sloof 150 x 200 dengan beton K 225 Tulangan 105 kg 0.74 m3 3,295,166.46 2,438,423.18 0.372 - - - - - -
7 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm 67.35 m' 77,312.85 5,207,020.70 0.795 - - - - - -
8 Balok 150 x 200 dengan beton K 225 Tulangan 105 kg 1.01 m3 3,705,897.33 3,742,956.31 0.572 - - - - - -
9 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm 54.15 m' 86,676.29 4,693,521.24 0.717 - - - - - -
10 Membuat 1 m3 Plat Lantai beton bertulang 2.95 m3 3,119,381.73 9,202,176.12 1.406 - - 2.015 0.960 2.015 0.960
11 Membuat 1 m3 Plat Tangga beton bertulang 0.72 m3 3,119,381.73 2,245,954.85 0.343 - - - - - -
12 Membuat 1 m3 Plat Water torn beton bertulang 0.42 m3 3,119,381.73 1,310,140.33 0.200 - - - - - -
V. PEKERJAAN DINDING
1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP 161.84 m2 116,576.48 18,866,738.23 2.882 19.194 0.342 87.395 1.556 106.589 1.898
2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP, trap tangga 6.30 m2 250,668.02 1,579,208.52 0.241 - - - - - -
VI PEKERJAAN KAYU
1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.27 m3 16,443,774.77 4,439,819.19 0.678 - - 0.081 0.203 0.081 0.203
Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.02 m3 8,048,535.00 160,970.70 0.025 - - - - - -
2 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti 12.32 m2 644,715.80 7,942,898.68 1.213 - - - - - -
3 Memasang 1 m3 konstruksi gordeng, kayu glugu - m3 4,450,537.65 - - - - - - - -
VII. PEKERJAAN PLESTERAN
1 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm 96.76 m2 54,689.70 5,291,775.27 0.808 - - 9.676 0.081 9.676 0.081
2 Memasang 1 m2 acian 96.76 m2 33,411.23 3,232,870.55 0.494 - - - - - -
3 Pemasangan 1 m2 plesteran ciprat 1SP : 2PP 33.50 m2 45,029.48 1,508,487.73 0.230 - - - - - -
VIII. PEKERJAAN PENGECATAN
1 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 96.76 m2 11,686.42 1,130,778.06 0.173 - - - - - -
IX. PEKERJAAN PENUTUP ATAP
1 Memasang 1 m2 Atap Galvalum (Paket) 78.51 m3 190,000.00 14,917,137.50 2.278 - - - - - -
2 Pemasangan 1 m talang datar Galvalum lebar 60 cm 6.00 m' 105,483.99 632,903.97 0.097 - - - - - -
X. PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Memasang 1 m2 lantai keramik (30 x 30) cm - m2 114,193.22 - - - - - - - -
2 Membuat rabat beton lantai mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 2.08 m3 723,713.11 1,504,722.31 0.230 - - - - - -
3 Memasang 1 m2 lantai keramik (20 x 20) cm 4.99 m2 184,674.28 921,524.65 0.141 - - - - - -
XI. PEKERJAAN SANITASI
1 Memasang 1 buah Kloset Jongkok Porselen 2.00 bh 280,952.58 561,905.16 0.086 - - - - - -
2 Memasang 1 m Pipa PVC tipe AW 16.00 m' 19,406.20 310,499.27 0.047 - - - - - -
3 Memasang 1 m Pipa PVC tipe AW 1 8.00 m' 22,254.33 178,034.63 0.027 - - - - - -
4 Memasang 1 m Pipa PVC tipe AW 3 18.00 m' 63,036.61 1,134,659.00 0.173 - - - - - -
5 Memasang 1 buah Kran atau 2.00 bh 46,068.18 92,136.37 0.014 - - - - - -
6 Memasang 1 buah Floor Drain 2.00 bh 80,836.18 161,672.35 0.025 - - - - - -
7 Memasang 1 buah Pintu Kamar Mandi 2.00 bh 650,000.00 1,300,000.00 0.199 - - - - - -
8 Pemasangan 1 M Pipa PVC tipe D 4 12.00 m 85,618.17 1,027,418.08 0.157 - - - - - -
XII. PEKERJAAN ELEKTRIKAL
1 Instalasi Penerangan menggunakan kabel NYY 3x2,5mm² dalam pipa conduit Ø 20mm. 10.00 titik 105,000.00 1,050,000.00 0.160 - - - - - -
2 Instalasi stop kontak dinding, menggunakan kabel NYM 3x2,5mm² 5.00 titik 100,000.00 500,000.00 0.076 - - - - - -
3 Saklar tunggal inbow, 1 gang 1 way 4.00 bh 20,000.00 80,000.00 0.012 - - - - - -
4 Saklar seri inbow, 1 gang 2 way 4.00 bh 25,000.00 100,000.00 0.015 - - - - - -
5 Stop kontak wall type 1ph, 16A, 1 gang 5.00 bh 20,000.00 100,000.00 0.015 - - - - - -
6 Lampu PLC 18 Watt dengan fitting gantung 8.00 bh 75,000.00 600,000.00 0.092 - - - - - -
7 Lampu PLC 7 Watt dengan fitting gantung 2.00 bh 65,000.00 130,000.00 0.020 - - - - - -
8 Penyambungan kabel 1.00 Ls 500,000.00 500,000.00 0.076 - - - - - -
9 Box MCB + MCB 2.00 bh 250,000.00 500,000.00 0.076 - - - - - -
XIII. PEKERJAAN LAIN-LAIN
1 Pintu Folding gate 6.00 m2 788,049.93 4,728,299.56 0.722 - - - - - -
2 Railling pengaman besi Hollow 40x40 / 40x20 mm, finishing cat 11.48 m2 550,000.00 6,312,240.00 0.964 - - - - - -
167,320,879.74 25.557 4.793 3.543 8.336

Laporan Progres Mingguan ke-9


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PEMBERSIHAN SALURAN
1 Penggalian Tanah Lumpur dan Endapan Limbah Sedalam 30 cm 69.70 m3 109,311.98 7,619,044.68 1.164 41.341 0.690 3.485 0.058 44.826 0.748
2 Pembersihan dan Pembuangan Tanah Lumpur dan Limbah Keluar Area 90.90 m3 29,796.55 2,708,506.67 0.414 39.372 0.179 18.180 0.083 57.552 0.262
3 Pemadatan Tanah Eksisting 69.70 m3 49,023.50 3,416,937.98 0.522 - - 27.880 0.209 27.880 0.209
4 Pengurugan dengan pasir urug, 10 cm 21.87 m3 178,388.92 3,901,365.68 0.596 - - 7.609 0.207 7.609 0.207
Pengurugan dengan pasir urug, 10 cm 1.36 m3 173,624.00 236,128.64 0.036 - - - - - -
5 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 10.93 m3 737,396.00 8,059,738.25 1.231 - - 2.186 0.246 2.186 0.246
Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.68 m3 723,713.11 492,124.91 0.075 - - - - - -
6 Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 23.23 m3 872,242.00 20,262,181.60 3.095 - - 4.646 0.619 4.646 0.619
a Jaring Kawat baja/Wire Mesh M5 1 lapis 375.85 kg 10,697.66 4,020,713.73 0.614 - - 75.170 0.123 75.170 0.123
7 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 133.20 m 77,312.85 10,298,072.12 1.573 - - 26.640 0.315 26.640 0.315
8 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 718.80 m 86,676.29 62,302,919.11 9.516 - - 71.880 0.952 71.880 0.952
9 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,2m, K.300 - bh 626,150.00 - - - - - - - -
10 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,8m, K.300 - bh 750,000.00 - - - - - - - -
11 Pekerjaan Plat Beton tebal 15 cm - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 8.37 m3 872,242.00 7,300,665.52 1.115 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis 608.09 kg 10,697.66 6,505,137.18 0.994 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 13.95 m2 316,861.88 4,420,223.25 0.675 - - - - - -
d Pembongkaran 1 M2 Bekisting 13.95 m2 15,645.80 218,258.88 0.033 - - - - - -
12 Pekerjaan Plat Beton tebal 10 cm - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 17.65 m3 872,242.00 15,395,071.25 2.351 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 1 lapis 962.04 kg 10,697.66 10,291,572.26 1.572 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 44.14 m2 316,861.88 13,986,283.46 2.136 - - - - - -
d Pembongkaran 1 M2 Bekisting 44.14 m2 15,645.80 690,605.52 0.105 - - - - - -
182,125,550.71 27.818 0.869 2.811 3.681
B PEKERJAAN JARINGAN IPAL KOMUNAL
1 Pekerjaan Galian Tanah Pipa 46.07 m3 67,972.30 3,131,483.87 0.478 - - - - - -
2 Pengurugan dengan pasir urug 11.51 m3 178,388.92 2,053,256.47 0.314 - - - - - -
3 Pengurugan Kembali 1 M3 Galian Tanah 30.54 m3 49,023.50 1,497,264.55 0.229 - - - - - -
4 Pemasangan 1 M Pipa PVC tipe AW 4 - m 90,907.55 - -
5 Saluran Pipa Air Limbah SDR - 41, Dia 15 cm , inc. fitting & Assecories - m 133,200.00 - - - - - - - -
6 Saluran Pipa Air Limbah SDR - 41, Dia 20 cm, , inc. fitting & Assecories - m 203,900.00 - - - - - - - -
7 Pemasangan Clean Out Inc. Fitting & Assecories 43.00 ttk 185,000.00 7,955,000.00 1.215 - - - - - -
8 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 100 org, 20 m3 / hari, - unit 7,500,000.00 - - - - - - - -
(Galian, Urugan, Pondasi, Tutup Beton, Penyambungan Instalasi)
9 Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm - unit 975,000.00 - - - - - - - -
10 Pekerjaan Sumur Resapan, Dia 100 cm, Kedalaman 2 m, Inc. Tutup Beton Berlubang - ttk 500,000.00 - - - - - - - -
11 Grill Beton Penutup Sumur Resapan - unit 750,000.00 - - - - - - - -
12 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 13.49 m3 688,832.33 9,292,348.18 1.419 - - - - - -
13 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area 13.49 m3 19,888.18 268,291.48 0.041 - - - - - -
14 Pemasangan 1 M Pipa PVC tipe D 6 375.05 m 133,200.00 49,956,660.00 7.630 - - - - - -
15 Pemasangan 1 M Pipa PVC tipe D 4 64.50 m 85,618.17 5,522,372.20 0.844 - - - - - -
16 Pekerjaan Sumur Resapan kedalaman 4 Buis Beton Dia 80 cm 15.00 ttk 474,124.46 7,111,866.88 1.086 - - 13.000 0.941 13.000 0.941
17 Pasang Grill Besi Penutup Sumur Resapan 15.00 unit 826,875.00 12,403,125.00 1.894 - - - - - -

Laporan Progres Mingguan ke-9


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
C PEKERJAAN PEMASANGAN DAN PENGADAAN INSTALASI IPAL
1 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 50 org, 10 m3 / hari
a Pengadaan Unit IPAL kap 50 org, 10 m3 / hari 1.00 unit 110,250,000.00 110,250,000.00 16.840 - - - - - -
b Galian Tanah 57.21 m3 67,972.30 3,888,695.29 0.594 - - - - - -
c Pengurugan Kembali 1 M3 Galian Tanah 2.39 m3 49,023.50 117,166.17 0.018 - - - - - -
d Pengurugan dengan pasir urug 1.83 m3 178,388.92 326,254.80 0.050 - - - - - -
e Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Dinding, Lantai dan Tutup 11.77 m3 872,242.00 10,266,288.31 1.568 - - - - - -
Jaring Kawat baja/Wire Mesh M8 713.69 kg 10,697.66 7,634,809.58 1.166 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 30.14 m2 316,861.88 9,550,217.12 1.459 - - - - - -
Pembongkaran 1 M2 Bekisting 30.14 m2 15,645.80 471,564.35 0.072 - - - - - -
f Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Inlet 0.30 m3 872,242.00 261,672.60 0.040 - - - - - -
Jaring Kawat baja/Wire Mesh M8 11.06 kg 10,697.66 118,316.07 0.018 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.66 m2 316,861.88 209,128.84 0.032 - - - - - -
Pembongkaran 1 M2 Bekisting 0.66 m2 15,645.80 10,326.23 0.002 - - - - - -
g Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Outlet 0.41 m3 872,242.00 357,619.22 0.055 - - - - - -
Jaring Kawat baja/Wire Mesh M8 14.98 kg 10,697.66 160,250.88 0.024 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.96 m2 316,861.88 304,187.41 0.046 - - - - - -
Pembongkaran 1 M2 Bekisting 0.96 m2 15,645.80 15,019.97 0.002 - - - - - -
h Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Kolom 15 x 15 cm 0.47 m3 872,242.00 409,953.74 0.063 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 119.39 kg 11,860.70 1,416,048.75 0.216 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.44 m2 316,861.88 456,281.11 0.070 - - - - - -
Pembongkaran 1 M2 Bekisting 1.44 m2 15,645.80 22,529.95 0.003 - - - - - -
i Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Balok 15 x 20 cm 0.12 m3 872,242.00 104,669.04 0.016 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 23.91 kg 11,860.70 283,589.29 0.043 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.55 m2 316,861.88 174,274.03 0.027 - - - - - -
Pembongkaran 1 M2 Bekisting 0.55 m2 15,645.80 8,605.19 0.001 - - - - - -
j Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, pondasi 60 x 60 x 20 cm 0.72 m3 872,242.00 628,014.24 0.096 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 36.93 kg 11,860.70 438,015.58 0.067 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.20 m2 316,861.88 380,234.26 0.058 - - - - - -
Pembongkaran 1 M2 Bekisting 1.20 m2 15,645.80 18,774.96 0.003 - - - - - -
k Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm 4.00 unit 975,000.00 3,900,000.00 0.596

251,374,175.57 38.395 - 0.941 0.941

JUMLAH 654,697,105.06 654,697,105.06 100.000 6.491 7.574 14.066


PRESTASI MINGGU LALU 6.491
PRESTASI MINGGU INI 7.574
PRESTASI SAMPAI DENGAN MINGGU INI 14.066
PRESTASI MENURUT SCHEDULE 13.784
LEBIH CEPAT (+) / TERLAMBAT (-) 0.282

Yogyakarta, 26 Juli 2021


di buat oleh,
KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA

Noor Hasan Bambang Erlianto


Pengawas Pelaksana

Laporan Progres Mingguan ke-9


REKAPITULASI
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : IX ( Sembilan )


Periode : 19 Juli 2021 sampai dengan 25 Juli 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
ADDENDUM II : 050 / 1909 / VII / 2021, TANGGAL 19 JULI 2021
NILAI KONTRAK ADDENDUM II : Rp 720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO PEKERJAAN PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp (%) BOBOT % BOBOT % BOBOT %

I PEKERJAAN PERSIAPAN 11,873,371.04 1.814 0.829 0.278 1.107

II PEKERJAAN PERBAIKAN TALUD SEGMEN 5


A PEKERJAAN TANAH DAN BETON BERTULANG 34,726,084.58 5.304 - - -
B PEKERJAAN PASANGAN DINDING 6,878,419.61 1.051 - - -

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PENGECATAN 398,623.81 0.061 - - -
B PEKERJAAN RUMAH TERDAMPAK 167,320,879.74 25.557 4.793 3.543 8.336

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PEMBERSIHAN SALURAN 182,125,550.71 27.818 0.869 2.811 3.681
B PEKERJAAN JARINGAN IPAL KOMUNAL 251,374,175.57 38.395 - 0.941 0.941

JUMLAH 654,697,105.06 100.000 6.491 7.574 14.066


PRESTASI MINGGU LALU 6.491
PRESTASI MINGGU INI 7.574
PRESTASI SAMPAI DENGAN MINGGU INI 14.066
PRESTASI MENURUT SCHEDULE 13.784
LEBIH CEPAT (+) / TERLAMBAT (-) 0.282

Yogyakarta, 26 Juli 2021


di buat oleh,
PEJABAT PEMBUAT KOMITMEN TIM TEKNIS KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA
1. Cicilia Novi hendrawati, M.SC., M.Eng.
NIP. 19781102 200501 2 011 ...........................

2. Danang Dwi Wahyujati,S.Kom.,M.Eng


NIP. 19761028 199803 1 004 ...........................

SIGIT SETIAWAN, ST.MT 3. Sudaryanto RISMAN WARCHAN ZULIANTO


NIP. 19690605 199303 1 007
NIP. 19770623 200501 1 013 ........................... Tim Leader Direktur
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : X ( Sepuluh )


Periode : 26 Juli 2021 sampai dengan 01 Agustus 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
ADDENDUM II : 050 / 1909 / VII / 2021, TANGGAL 19 JULI 2021
NILAI KONTRAK ADDENDUM II : Rp 720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
I PEKERJAAN PERSIAPAN
1 Pembuatan Papan Nama Pekerjaan 1.00 bh 250,000.00 250,000.00 0.038 1.000 0.038 - - 1.000 0.038
2 Pengukuran dan Pemasangan Bouwplank 28.56 m 12,198.91 348,400.73 0.053 28.560 0.053 - - 28.560 0.053
3 Pembuatan bedeng pekerja 9.00 m2 383,330.04 3,449,970.32 0.527 9.000 0.527 - - 9.000 0.527
4 Mobilisasi Demobilisasi Alat Berat 1.00 ls 2,500,000.00 2,500,000.00 0.382 0.409 0.156 0.045 0.017 0.455 0.174
5 Pembuatan akses menuju badan sungai sementara - m2 113,128.49 - - - - - - - -
6 Dewatering dengan pompa air diesel 40.00 jam 25,000.00 1,000,000.00 0.153 16.364 0.062 1.818 0.007 18.182 0.069
7 SMKK 1.00 ls 4,325,000.00 4,325,000.00 0.661 0.409 0.270 0.045 0.030 0.455 0.300
11,873,371.04 1.814 1.107 0.054 1.162
II PEKERJAAN PERBAIKAN TALUD SEGMEN 5
A PEKERJAAN TANAH DAN BETON BERTULANG
1 Penggalian 1 M3 Tanah Biasa 13.50 m3 67,972.30 917,626.05 0.140 - - - - - -
2 Pengurugan Kembali 1 M3 Galian Tanah 6.41 m3 49,023.50 314,240.64 0.048 - - - - - -
3 Bongkaran Pasangan Batu dan Beton Eksisting 7.92 m3 71,953.20 569,869.35 0.087 - - - - - -
4 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area 7.92 m3 19,888.18 157,514.35 0.024 - - - - - -
5 Pemadatan Tanah Eksisting 6.41 m3 49,023.50 314,240.64 0.048 - - - - - -
6 Pengurugan dengan pasir urug 0.27 m3 178,388.92 48,165.01 0.007 - - - - - -
7 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.27 m3 737,396.00 199,096.92 0.030 - - - - - -
8 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 1.08 m3 872,242.00 942,021.36 0.144 - - - - - -
a Pembesian dg Besi Polos atau Besi Ulir 156.69 kg 11,860.70 1,858,452.79 0.284 - - - - - -
b Bekisting untuk pondasi beton ( dipakai 2 kali ) 1.92 m2 89,375.55 171,601.05 0.026 - - - - - -
c Pembongkaran 1 M2 Bekisting 1.92 m2 15,645.80 30,039.93 0.005 - - - - - -
9 Pekerjaan Beton Dinding Talud Beton
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 2.16 m3 872,242.00 1,884,042.71 0.288 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 1,026.67 kg 11,860.70 12,177,022.97 1.860 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 9.02 m2 316,861.88 2,858,094.17 0.437 - - - - - -
d Pembongkaran 1 M2 Bekisting 9.02 m2 15,645.80 141,125.10 0.022 - - - - - -
10 Pekerjaan Beton Sloof 20x30cm
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 0.49 m3 872,242.00 427,398.58 0.065 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 147.55 kg 11,860.70 1,750,046.01 0.267 - - - - - -
c Memasang Bekisting untuk Sloof (dipakai 2 kali) 2.46 m2 89,375.55 219,863.84 0.034 - - - - - -
d Pembongkaran 1 M2 Bekisting 2.46 m2 15,645.80 38,488.66 0.006 - - - - - -
11 Pekerjaan Beton Konsul Cantilever
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 0.09 m3 872,242.00 78,501.78 0.012 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 47.58 kg 11,860.70 564,332.02 0.086 - - - - - -
c Memasang Bekisting untuk Balok (dipakai 2 kali) 0.45 m2 120,181.13 54,081.51 0.008 - - - - - -
d Pembongkaran 1 M2 Bekisting 0.45 m2 15,645.80 7,040.61 0.001 - - - - - -
12 Pekerjaan Plat Beton tebal 12 cm
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 2.70 m3 872,242.00 2,355,053.39 0.360 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis 294.23 kg 10,697.66 3,147,571.10 0.481 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.35 m2 316,861.88 427,763.54 0.065 - - - - - -
d Pembongkaran 1 M2 Bekisting 1.35 m2 15,645.80 21,121.83 0.003 - - - - - -
13 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 4.50 m 77,312.85 347,907.84 0.053 - - - - - -
14 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 8.67 m 86,676.29 751,483.46 0.115 - - - - - -
15 Memasang Stek Besi 23.67 kg 11,860.70 280,742.73 0.043 - - - - - -
16 Pekerjaan Plat Beton Pot tebal 10 cm
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 0.49 m3 872,242.00 427,398.58 0.065 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 23.67 kg 11,860.70 280,742.73 0.043 - - - - - -
c Bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm 7.20 m2 118,158.83 850,743.59 0.130 - - - - - -
d Pembongkaran 1 M2 Bekisting 7.20 m2 15,645.80 112,649.75 0.017 - - - - - -
34,726,084.58 5.304 - - -
B PEKERJAAN PASANGAN DINDING
1 Pemasangan Dinding Bata Merah Bakar Sekam Tebal 1/2 Bata Camp. 1SP 6PP 9.97 m2 116,576.48 1,162,267.55 0.178 - - - - - -
2 Pemasangan Plesteran 1 Pc 6 Pp Tebal 15 mm 34.11 m2 54,689.70 1,865,465.63 0.285 - - - - - -
3 Pemasangan Acian 34.11 m2 33,411.23 1,139,657.03 0.174 - - - - - -
4 Pemasangan Plesteran Skoning 1 Pc 2Pp lebar 10 cm 46.50 m 55,075.90 2,561,029.40 0.391 - - - - - -
5 Pemasangan Kepala Kolom 3.00 bh 50,000.00 150,000.00 0.023 - - - - - -
Laporan Progres Mingguan ke-10
HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
6,878,419.61 1.051 - - -

Laporan Progres Mingguan ke-10


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PENGECATAN
1 Pengecatan Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Weathershield luar ruangan 34.11 m2 11,686.42 398,623.81 0.061 - - - - - -
398,623.81 0.061 - - -
B PEKERJAAN RUMAH TERDAMPAK
I. PEKERJAAN BONGKARAN
1 Membongkar 1 m2 genteng / sirap untuk dipergunakan lagi 77.17 m2 3,628.42 280,005.33 0.043 - - - - - -
2 Membongkar 1 m3 kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi 0.37 m3 991,595.91 366,890.49 0.056 - - - - - -
3 Pembongkaran 1 m3 pasangan bata merah dan membersihkan 12.72 m3 185,908.38 2,364,754.54 0.361 3.005 0.085 - - 3.005 0.085
4 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 1.50 m3 688,832.33 1,033,248.50 0.158 0.108 0.011 - - 0.108 0.011
II. PEKERJAAN TANAH - - -
1 Menggali 1 m3 tanah biasa sedalam 1 meter 27.22 m3 67,972.30 1,850,206.01 0.283 21.368 0.222 5.852 0.061 27.220 0.283
2 Pengurugan Kembali 1 m3 Galian Tanah 10.11 m3 18,745.83 189,520.38 0.029 7.987 0.023 2.123 0.006 10.110 0.029
3 Pengurugan dengan pasir urug 1.82 m3 173,624.00 315,995.68 0.048 1.438 0.038 0.382 0.010 1.820 0.048
4 Peninggian peil lantai 9.18 m3 18,745.83 172,086.75 0.026
III. PEKERJAAN PONDASI - - -
1 Memasang 1 m3 pondasi batu belah, campuran 1 PC 6 PP 16.49 m2 665,195.09 10,969,067.11 1.675 12.964 1.317 3.526 0.358 16.490 1.675
IV. PEKERJAAN BETON - - -
1 Membuat 1 m3 Sloof beton bertulang (200 kg besi + bekisting) 1.06 m3 3,844,764.87 4,075,450.77 0.622 0.688 0.404 0.372 0.218 1.060 0.622
2 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) 2.29 m3 7,083,735.01 16,221,753.18 2.478 1.450 1.569 0.138 0.149 1.588 1.718
3 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) 3.05 m3 5,659,422.09 17,261,237.38 2.637 1.513 1.308 0.915 0.791 2.428 2.099
4 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.14 m3 723,713.11 101,319.83 0.015 0.105 0.012 0.035 0.004 0.140 0.015
5 Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting) 0.57 m3 3,127,107.54 1,782,451.30 0.272 0.428 0.204 0.143 0.068 0.570 0.272
6 Sloof 150 x 200 dengan beton K 225 Tulangan 105 kg 0.74 m3 3,295,166.46 2,438,423.18 0.372 - - 0.740 0.372 0.740 0.372
7 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm 67.35 m' 77,312.85 5,207,020.70 0.795 - - 57.248 0.676 57.248 0.676
8 Balok 150 x 200 dengan beton K 225 Tulangan 105 kg 1.01 m3 3,705,897.33 3,742,956.31 0.572 - - 0.859 0.486 0.859 0.486
9 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm 54.15 m' 86,676.29 4,693,521.24 0.717 - - 43.320 0.574 43.320 0.574
10 Membuat 1 m3 Plat Lantai beton bertulang 2.95 m3 3,119,381.73 9,202,176.12 1.406 2.015 0.960 - - 2.015 0.960
11 Membuat 1 m3 Plat Tangga beton bertulang 0.72 m3 3,119,381.73 2,245,954.85 0.343 - - - - - -
12 Membuat 1 m3 Plat Water torn beton bertulang 0.42 m3 3,119,381.73 1,310,140.33 0.200 - - 0.210 0.100 0.210 0.100
V. PEKERJAAN DINDING - - -
1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP 161.84 m2 116,576.48 18,866,738.23 2.882 106.589 1.898 32.368 0.576 138.957 2.474
2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP, trap tangga 6.30 m2 250,668.02 1,579,208.52 0.241 - - - - - -
VI PEKERJAAN KAYU - - -
1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.27 m3 16,443,774.77 4,439,819.19 0.678 0.081 0.203 0.081 0.203 0.162 0.407
Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.02 m3 8,048,535.00 160,970.70 0.025 - - 0.012 0.015 0.012 0.015
2 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti 12.32 m2 644,715.80 7,942,898.68 1.213 - - - - - -
3 Memasang 1 m3 konstruksi gordeng, kayu glugu - m3 4,450,537.65 - - - - - - - -
VII. PEKERJAAN PLESTERAN - - -
1 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm 96.76 m2 54,689.70 5,291,775.27 0.808 9.676 0.081 38.704 0.323 48.380 0.404
2 Memasang 1 m2 acian 96.76 m2 33,411.23 3,232,870.55 0.494 - - - - - -
3 Pemasangan 1 m2 plesteran ciprat 1SP : 2PP 33.50 m2 45,029.48 1,508,487.73 0.230 - - 30.150 0.207 30.150 0.207
VIII. PEKERJAAN PENGECATAN - - -
1 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 96.76 m2 11,686.42 1,130,778.06 0.173 - - - - - -
IX. PEKERJAAN PENUTUP ATAP - - -
1 Memasang 1 m2 Atap Galvalum (Paket) 78.51 m3 190,000.00 14,917,137.50 2.278 - - - - - -
2 Pemasangan 1 m talang datar Galvalum lebar 60 cm 6.00 m' 105,483.99 632,903.97 0.097 - - - - - -
X. PEKERJAAN PENUTUP LANTAI DAN DINDING - - -
1 Memasang 1 m2 lantai keramik (30 x 30) cm - m2 114,193.22 - - - - - - - -
2 Membuat rabat beton lantai mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 2.08 m3 723,713.11 1,504,722.31 0.230 - - - - - -
3 Memasang 1 m2 lantai keramik (20 x 20) cm 4.99 m2 184,674.28 921,524.65 0.141 - - - - - -
XI. PEKERJAAN SANITASI - - -
1 Memasang 1 buah Kloset Jongkok Porselen 2.00 bh 280,952.58 561,905.16 0.086 - - - - - -
2 Memasang 1 m Pipa PVC tipe AW 16.00 m' 19,406.20 310,499.27 0.047 - - - - - -
3 Memasang 1 m Pipa PVC tipe AW 1 8.00 m' 22,254.33 178,034.63 0.027 - - - - - -
4 Memasang 1 m Pipa PVC tipe AW 3 18.00 m' 63,036.61 1,134,659.00 0.173 - - - - - -
5 Memasang 1 buah Kran atau 2.00 bh 46,068.18 92,136.37 0.014 - - - - - -
6 Memasang 1 buah Floor Drain 2.00 bh 80,836.18 161,672.35 0.025 - - - - - -
7 Memasang 1 buah Pintu Kamar Mandi 2.00 bh 650,000.00 1,300,000.00 0.199 - - - - - -
8 Pemasangan 1 M Pipa PVC tipe D 4 12.00 m 85,618.17 1,027,418.08 0.157 - - - - - -
XII. PEKERJAAN ELEKTRIKAL - - -
1 Instalasi Penerangan menggunakan kabel NYY 3x2,5mm² dalam pipa conduit Ø 20mm. 10.00 titik 105,000.00 1,050,000.00 0.160 - - - - - -
2 Instalasi stop kontak dinding, menggunakan kabel NYM 3x2,5mm² 5.00 titik 100,000.00 500,000.00 0.076 - - - - - -
3 Saklar tunggal inbow, 1 gang 1 way 4.00 bh 20,000.00 80,000.00 0.012 - - - - - -
4 Saklar seri inbow, 1 gang 2 way 4.00 bh 25,000.00 100,000.00 0.015 - - - - - -
5 Stop kontak wall type 1ph, 16A, 1 gang 5.00 bh 20,000.00 100,000.00 0.015 - - - - - -
6 Lampu PLC 18 Watt dengan fitting gantung 8.00 bh 75,000.00 600,000.00 0.092 - - - - - -
7 Lampu PLC 7 Watt dengan fitting gantung 2.00 bh 65,000.00 130,000.00 0.020 - - - - - -
8 Penyambungan kabel 1.00 Ls 500,000.00 500,000.00 0.076 - - - - - -
9 Box MCB + MCB 2.00 bh 250,000.00 500,000.00 0.076 - - - - - -
XIII. PEKERJAAN LAIN-LAIN - - -
1 Pintu Folding gate 6.00 m2 788,049.93 4,728,299.56 0.722 - - - - - -
2 Railling pengaman besi Hollow 40x40 / 40x20 mm, finishing cat 11.48 m2 550,000.00 6,312,240.00 0.964 - - - - - -
167,320,879.74 25.557 8.336 5.199 13.535

Laporan Progres Mingguan ke-10


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PEMBERSIHAN SALURAN
1 Penggalian Tanah Lumpur dan Endapan Limbah Sedalam 30 cm 69.70 m3 109,311.98 7,619,044.68 1.164 44.826 0.748 3.485 0.058 48.311 0.807
2 Pembersihan dan Pembuangan Tanah Lumpur dan Limbah Keluar Area 90.90 m3 29,796.55 2,708,506.67 0.414 57.552 0.262 4.545 0.021 62.097 0.283
3 Pemadatan Tanah Eksisting 69.70 m3 49,023.50 3,416,937.98 0.522 27.880 0.209 27.880 0.209 55.760 0.418
4 Pengurugan dengan pasir urug, 10 cm 21.87 m3 178,388.92 3,901,365.68 0.596 7.609 0.207 8.748 0.238 16.357 0.446
Pengurugan dengan pasir urug, 10 cm 1.36 m3 173,624.00 236,128.64 0.036 - - 0.952 0.025 0.952 0.025
5 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 10.93 m3 737,396.00 8,059,738.25 1.231 2.186 0.246 4.372 0.492 6.558 0.739
Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.68 m3 723,713.11 492,124.91 0.075 - - 0.401 0.044 0.401 0.044
6 Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 23.23 m3 872,242.00 20,262,181.60 3.095 4.646 0.619 5.971 0.796 10.617 1.414
a Jaring Kawat baja/Wire Mesh M5 1 lapis 375.85 kg 10,697.66 4,020,713.73 0.614 75.170 0.123 131.548 0.215 206.718 0.338
7 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 133.20 m 77,312.85 10,298,072.12 1.573 26.640 0.315 26.640 0.315 53.280 0.629
8 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 718.80 m 86,676.29 62,302,919.11 9.516 71.880 0.952 71.880 0.952 143.760 1.903
9 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,2m, K.300 - bh 626,150.00 - - - - - - - -
10 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,8m, K.300 - bh 750,000.00 - - - - - - - -
11 Pekerjaan Plat Beton tebal 15 cm - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 8.37 m3 872,242.00 7,300,665.52 1.115 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis 608.09 kg 10,697.66 6,505,137.18 0.994 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 13.95 m2 316,861.88 4,420,223.25 0.675 - - - - - -
d Pembongkaran 1 M2 Bekisting 13.95 m2 15,645.80 218,258.88 0.033 - - - - - -
12 Pekerjaan Plat Beton tebal 10 cm - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 17.65 m3 872,242.00 15,395,071.25 2.351 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 1 lapis 962.04 kg 10,697.66 10,291,572.26 1.572 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 44.14 m2 316,861.88 13,986,283.46 2.136 - - - - - -
d Pembongkaran 1 M2 Bekisting 44.14 m2 15,645.80 690,605.52 0.105 - - - - - -
182,125,550.71 27.818 3.681 3.365 7.045
B PEKERJAAN JARINGAN IPAL KOMUNAL
1 Pekerjaan Galian Tanah Pipa 46.07 m3 67,972.30 3,131,483.87 0.478 - - - - - -
2 Pengurugan dengan pasir urug 11.51 m3 178,388.92 2,053,256.47 0.314 - - - - - -
3 Pengurugan Kembali 1 M3 Galian Tanah 30.54 m3 49,023.50 1,497,264.55 0.229 - - - - - -
4 Pemasangan 1 M Pipa PVC tipe AW 4 - m 90,907.55 - -
5 Saluran Pipa Air Limbah SDR - 41, Dia 15 cm , inc. fitting & Assecories - m 133,200.00 - - - - - - - -
6 Saluran Pipa Air Limbah SDR - 41, Dia 20 cm, , inc. fitting & Assecories - m 203,900.00 - - - - - - - -
7 Pemasangan Clean Out Inc. Fitting & Assecories 43.00 ttk 185,000.00 7,955,000.00 1.215 - - - - - -
8 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 100 org, 20 m3 / hari, - unit 7,500,000.00 - - - - - - - -
(Galian, Urugan, Pondasi, Tutup Beton, Penyambungan Instalasi)
9 Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm - unit 975,000.00 - - - - - - - -
10 Pekerjaan Sumur Resapan, Dia 100 cm, Kedalaman 2 m, Inc. Tutup Beton Berlubang - ttk 500,000.00 - - - - - - - -
11 Grill Beton Penutup Sumur Resapan - unit 750,000.00 - - - - - - - -
12 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 13.49 m3 688,832.33 9,292,348.18 1.419 - - - - - -
13 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area 13.49 m3 19,888.18 268,291.48 0.041 - - - - - -
14 Pemasangan 1 M Pipa PVC tipe D 6 375.05 m 133,200.00 49,956,660.00 7.630
14 Pemasangan 1 M Pipa PVC tipe D 4 64.50 m 85,618.17 5,522,372.20 0.844 - - - - - -
15 Pekerjaan Sumur Resapan kedalaman 4 Buis Beton Dia 80 cm 15.00 ttk 474,124.46 7,111,866.88 1.086 13.000 0.941 - - 13.000 0.941
16 Pasang Grill Besi Penutup Sumur Resapan 15.00 unit 826,875.00 12,403,125.00 1.894 - - - - - -

Laporan Progres Mingguan ke-10


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
C PEKERJAAN PEMASANGAN DAN PENGADAAN INSTALASI IPAL
1 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 50 org, 10 m3 / hari
a Pengadaan Unit IPAL kap 50 org, 10 m3 / hari 1.00 unit 110,250,000.00 110,250,000.00 16.840 - - - - - -
b Galian Tanah 57.21 m3 67,972.30 3,888,695.29 0.594 - - - - - -
c Pengurugan Kembali 1 M3 Galian Tanah 2.39 m3 49,023.50 117,166.17 0.018 - - - - - -
d Pengurugan dengan pasir urug 1.83 m3 178,388.92 326,254.80 0.050 - - - - - -
e Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Dinding, Lantai dan Tutup 11.77 m3 872,242.00 10,266,288.31 1.568 - - - - - -
Jaring Kawat baja/Wire Mesh M8 713.69 kg 10,697.66 7,634,809.58 1.166 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 30.14 m2 316,861.88 9,550,217.12 1.459 - - - - - -
Pembongkaran 1 M2 Bekisting 30.14 m2 15,645.80 471,564.35 0.072 - - - - - -
f Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Inlet 0.30 m3 872,242.00 261,672.60 0.040 - - - - - -
Jaring Kawat baja/Wire Mesh M8 11.06 kg 10,697.66 118,316.07 0.018 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.66 m2 316,861.88 209,128.84 0.032 - - - - - -
Pembongkaran 1 M2 Bekisting 0.66 m2 15,645.80 10,326.23 0.002 - - - - - -
g Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Outlet 0.41 m3 872,242.00 357,619.22 0.055 - - - - - -
Jaring Kawat baja/Wire Mesh M8 14.98 kg 10,697.66 160,250.88 0.024 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.96 m2 316,861.88 304,187.41 0.046 - - - - - -
Pembongkaran 1 M2 Bekisting 0.96 m2 15,645.80 15,019.97 0.002 - - - - - -
h Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Kolom 15 x 15 cm 0.47 m3 872,242.00 409,953.74 0.063 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 119.39 kg 11,860.70 1,416,048.75 0.216 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.44 m2 316,861.88 456,281.11 0.070 - - - - - -
Pembongkaran 1 M2 Bekisting 1.44 m2 15,645.80 22,529.95 0.003 - - - - - -
i Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Balok 15 x 20 cm 0.12 m3 872,242.00 104,669.04 0.016 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 23.91 kg 11,860.70 283,589.29 0.043 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.55 m2 316,861.88 174,274.03 0.027 - - - - - -
Pembongkaran 1 M2 Bekisting 0.55 m2 15,645.80 8,605.19 0.001 - - - - - -
j Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, pondasi 60 x 60 x 20 cm 0.72 m3 872,242.00 628,014.24 0.096 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 36.93 kg 11,860.70 438,015.58 0.067 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.20 m2 316,861.88 380,234.26 0.058 - - - - - -
Pembongkaran 1 M2 Bekisting 1.20 m2 15,645.80 18,774.96 0.003 - - - - - -
k Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm 4.00 unit 975,000.00 3,900,000.00 0.596

251,374,175.57 38.395 0.941 - 0.941

JUMLAH 654,697,105.06 654,697,105.06 100.000 14.066 8.618 22.683


PRESTASI MINGGU LALU 14.066
PRESTASI MINGGU INI 8.618
PRESTASI SAMPAI DENGAN MINGGU INI 22.683
PRESTASI MENURUT SCHEDULE 22.351
LEBIH CEPAT (+) / TERLAMBAT (-) 0.332

Yogyakarta, 2 Agustus 2021


di buat oleh,
KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA

Noor Hasan Bambang Erlianto


Pengawas Pelaksana

Laporan Progres Mingguan ke-10


REKAPITULASI
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : X ( Sepuluh )


Periode : 26 Juli 2021 sampai dengan 01 Agustus 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
ADDENDUM II : 050 / 1909 / VII / 2021, TANGGAL 19 JULI 2021
NILAI KONTRAK ADDENDUM II : Rp 720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO PEKERJAAN PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp (%) BOBOT % BOBOT % BOBOT %

I PEKERJAAN PERSIAPAN 11,873,371.04 1.814 1.107 0.054 1.162

II PEKERJAAN PERBAIKAN TALUD SEGMEN 5


A PEKERJAAN TANAH DAN BETON BERTULANG 34,726,084.58 5.304 - - -
B PEKERJAAN PASANGAN DINDING 6,878,419.61 1.051 - - -

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PENGECATAN 398,623.81 0.061 - - -
B PEKERJAAN RUMAH TERDAMPAK 167,320,879.74 25.557 8.336 5.199 13.535

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PEMBERSIHAN SALURAN 182,125,550.71 27.818 3.681 3.365 7.045
B PEKERJAAN JARINGAN IPAL KOMUNAL 251,374,175.57 38.395 0.941 - 0.941

JUMLAH 654,697,105.06 100.000 14.066 8.618 22.683


PRESTASI MINGGU LALU 654,697,105.06 14.066
PRESTASI MINGGU INI 8.618
PRESTASI SAMPAI DENGAN MINGGU INI 22.683
PRESTASI MENURUT SCHEDULE 22.351
LEBIH CEPAT (+) / TERLAMBAT (-) 0.332

Yogyakarta, 2 Agustus 2021


di buat oleh,
PEJABAT PEMBUAT KOMITMEN TIM TEKNIS KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA
1. Cicilia Novi hendrawati, M.SC., M.Eng.
NIP. 19781102 200501 2 011 ...........................

2. Danang Dwi Wahyujati,S.Kom.,M.Eng


NIP. 19761028 199803 1 004 ...........................

SIGIT SETIAWAN, ST.MT 3. Sudaryanto RISMAN WARCHAN ZULIANTO


NIP. 19690605 199303 1 007
NIP. 19770623 200501 1 013 ........................... Tim Leader Direktur
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : XI ( Sebelas )


Periode : 02 Agustus 2021 sampai dengan 08 Agustus 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
ADDENDUM II : 050 / 1909 / VII / 2021, TANGGAL 19 JULI 2021
NILAI KONTRAK ADDENDUM II : Rp 720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
I PEKERJAAN PERSIAPAN
1 Pembuatan Papan Nama Pekerjaan 1.00 bh 250,000.00 250,000.00 0.038 1.000 0.038 - - 1.000 0.038
2 Pengukuran dan Pemasangan Bouwplank 28.56 m 12,198.91 348,400.73 0.053 28.560 0.053 - - 28.560 0.053
3 Pembuatan bedeng pekerja 9.00 m2 383,330.04 3,449,970.32 0.527 9.000 0.527 - - 9.000 0.527
4 Mobilisasi Demobilisasi Alat Berat 1.00 ls 2,500,000.00 2,500,000.00 0.382 0.455 0.174 0.045 0.017 0.500 0.191
5 Pembuatan akses menuju badan sungai sementara - m2 113,128.49 - - - - - - - -
6 Dewatering dengan pompa air diesel 40.00 jam 25,000.00 1,000,000.00 0.153 18.182 0.069 1.818 0.007 20.000 0.076
7 SMKK 1.00 ls 4,325,000.00 4,325,000.00 0.661 0.455 0.300 0.045 0.030 0.500 0.330
11,873,371.04 1.814 1.162 0.054 1.216
II PEKERJAAN PERBAIKAN TALUD SEGMEN 5
A PEKERJAAN TANAH DAN BETON BERTULANG
1 Penggalian 1 M3 Tanah Biasa 13.50 m3 67,972.30 917,626.05 0.140 - - - - - -
2 Pengurugan Kembali 1 M3 Galian Tanah 6.41 m3 49,023.50 314,240.64 0.048 - - - - - -
3 Bongkaran Pasangan Batu dan Beton Eksisting 7.92 m3 71,953.20 569,869.35 0.087 - - - - - -
4 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area 7.92 m3 19,888.18 157,514.35 0.024 - - - - - -
5 Pemadatan Tanah Eksisting 6.41 m3 49,023.50 314,240.64 0.048 - - - - - -
6 Pengurugan dengan pasir urug 0.27 m3 178,388.92 48,165.01 0.007 - - - - - -
7 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.27 m3 737,396.00 199,096.92 0.030 - - - - - -
8 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 1.08 m3 872,242.00 942,021.36 0.144 - - - - - -
a Pembesian dg Besi Polos atau Besi Ulir 156.69 kg 11,860.70 1,858,452.79 0.284 - - - - - -
b Bekisting untuk pondasi beton ( dipakai 2 kali ) 1.92 m2 89,375.55 171,601.05 0.026 - - - - - -
c Pembongkaran 1 M2 Bekisting 1.92 m2 15,645.80 30,039.93 0.005 - - - - - -
9 Pekerjaan Beton Dinding Talud Beton
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 2.16 m3 872,242.00 1,884,042.71 0.288 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 1,026.67 kg 11,860.70 12,177,022.97 1.860 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 9.02 m2 316,861.88 2,858,094.17 0.437 - - - - - -
d Pembongkaran 1 M2 Bekisting 9.02 m2 15,645.80 141,125.10 0.022 - - - - - -
10 Pekerjaan Beton Sloof 20x30cm
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 0.49 m3 872,242.00 427,398.58 0.065 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 147.55 kg 11,860.70 1,750,046.01 0.267 - - - - - -
c Memasang Bekisting untuk Sloof (dipakai 2 kali) 2.46 m2 89,375.55 219,863.84 0.034 - - - - - -
d Pembongkaran 1 M2 Bekisting 2.46 m2 15,645.80 38,488.66 0.006 - - - - - -
11 Pekerjaan Beton Konsul Cantilever
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 0.09 m3 872,242.00 78,501.78 0.012 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 47.58 kg 11,860.70 564,332.02 0.086 - - - - - -
c Memasang Bekisting untuk Balok (dipakai 2 kali) 0.45 m2 120,181.13 54,081.51 0.008 - - - - - -
d Pembongkaran 1 M2 Bekisting 0.45 m2 15,645.80 7,040.61 0.001 - - - - - -
12 Pekerjaan Plat Beton tebal 12 cm
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 2.70 m3 872,242.00 2,355,053.39 0.360 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis 294.23 kg 10,697.66 3,147,571.10 0.481 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.35 m2 316,861.88 427,763.54 0.065 - - - - - -
d Pembongkaran 1 M2 Bekisting 1.35 m2 15,645.80 21,121.83 0.003 - - - - - -
13 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 4.50 m 77,312.85 347,907.84 0.053 - - - - - -
14 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 8.67 m 86,676.29 751,483.46 0.115 - - - - - -
15 Memasang Stek Besi 23.67 kg 11,860.70 280,742.73 0.043 - - - - - -
16 Pekerjaan Plat Beton Pot tebal 10 cm
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 0.49 m3 872,242.00 427,398.58 0.065 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 23.67 kg 11,860.70 280,742.73 0.043 - - - - - -
c Bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm 7.20 m2 118,158.83 850,743.59 0.130 - - - - - -
d Pembongkaran 1 M2 Bekisting 7.20 m2 15,645.80 112,649.75 0.017 - - - - - -
34,726,084.58 5.304 - - -
B PEKERJAAN PASANGAN DINDING
1 Pemasangan Dinding Bata Merah Bakar Sekam Tebal 1/2 Bata Camp. 1SP 6PP 9.97 m2 116,576.48 1,162,267.55 0.178 - - - - - -
2 Pemasangan Plesteran 1 Pc 6 Pp Tebal 15 mm 34.11 m2 54,689.70 1,865,465.63 0.285 - - - - - -
3 Pemasangan Acian 34.11 m2 33,411.23 1,139,657.03 0.174 - - - - - -
4 Pemasangan Plesteran Skoning 1 Pc 2Pp lebar 10 cm 46.50 m 55,075.90 2,561,029.40 0.391 - - - - - -
5 Pemasangan Kepala Kolom 3.00 bh 50,000.00 150,000.00 0.023 - - - - - -
Laporan Progres Mingguan ke-11
HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
6,878,419.61 1.051 - - -

Laporan Progres Mingguan ke-11


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PENGECATAN
1 Pengecatan Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Weathershield luar ruangan 34.11 m2 11,686.42 398,623.81 0.061 - - - - - -
398,623.81 0.061 - - -
B PEKERJAAN RUMAH TERDAMPAK
I. PEKERJAAN BONGKARAN
1 Membongkar 1 m2 genteng / sirap untuk dipergunakan lagi 77.17 m2 3,628.42 280,005.33 0.043 - - 19.293 0.011 19.293 0.011
2 Membongkar 1 m3 kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi 0.37 m3 991,595.91 366,890.49 0.056 - - 0.093 0.014 0.093 0.014
3 Pembongkaran 1 m3 pasangan bata merah dan membersihkan 12.72 m3 185,908.38 2,364,754.54 0.361 3.005 0.085 1.272 0.036 4.277 0.121
4 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 1.50 m3 688,832.33 1,033,248.50 0.158 0.108 0.011 0.300 0.032 0.408 0.043
II. PEKERJAAN TANAH - - -
1 Menggali 1 m3 tanah biasa sedalam 1 meter 27.22 m3 67,972.30 1,850,206.01 0.283 27.220 0.283 - - 27.220 0.283
2 Pengurugan Kembali 1 m3 Galian Tanah 10.11 m3 18,745.83 189,520.38 0.029 10.110 0.029 - - 10.110 0.029
3 Pengurugan dengan pasir urug 1.82 m3 173,624.00 315,995.68 0.048 1.820 0.048 - - 1.820 0.048
4 Peninggian peil lantai 9.18 m3 18,745.83 172,086.75 0.026 - - - - - -
III. PEKERJAAN PONDASI - - -
1 Memasang 1 m3 pondasi batu belah, campuran 1 PC 6 PP 16.49 m2 665,195.09 10,969,067.11 1.675 16.490 1.675 - - 16.490 1.675
IV. PEKERJAAN BETON - - -
1 Membuat 1 m3 Sloof beton bertulang (200 kg besi + bekisting) 1.06 m3 3,844,764.87 4,075,450.77 0.622 1.060 0.622 - - 1.060 0.622
2 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) 2.29 m3 7,083,735.01 16,221,753.18 2.478 1.588 1.718 0.702 0.760 2.290 2.478
3 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) 3.05 m3 5,659,422.09 17,261,237.38 2.637 2.428 2.099 0.622 0.538 3.050 2.637
4 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.14 m3 723,713.11 101,319.83 0.015 0.140 0.015 - - 0.140 0.015
5 Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting) 0.57 m3 3,127,107.54 1,782,451.30 0.272 0.570 0.272 - - 0.570 0.272
6 Sloof 150 x 200 dengan beton K 225 Tulangan 105 kg 0.74 m3 3,295,166.46 2,438,423.18 0.372 0.740 0.372 - - 0.740 0.372
7 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm 67.35 m' 77,312.85 5,207,020.70 0.795 57.248 0.676 - - 57.248 0.676
8 Balok 150 x 200 dengan beton K 225 Tulangan 105 kg 1.01 m3 3,705,897.33 3,742,956.31 0.572 0.859 0.486 - - 0.859 0.486
9 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm 54.15 m' 86,676.29 4,693,521.24 0.717 43.320 0.574 - - 43.320 0.574
10 Membuat 1 m3 Plat Lantai beton bertulang 2.95 m3 3,119,381.73 9,202,176.12 1.406 2.015 0.960 - - 2.015 0.960
11 Membuat 1 m3 Plat Tangga beton bertulang 0.72 m3 3,119,381.73 2,245,954.85 0.343 - - - - - -
12 Membuat 1 m3 Plat Water torn beton bertulang 0.42 m3 3,119,381.73 1,310,140.33 0.200 0.210 0.100 0.210 0.100 0.420 0.200
V. PEKERJAAN DINDING - - -
1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP 161.84 m2 116,576.48 18,866,738.23 2.882 138.957 2.474 14.566 0.259 153.522 2.734
2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP, trap tangga 6.30 m2 250,668.02 1,579,208.52 0.241 - - - - - -
VI PEKERJAAN KAYU - - -
1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.27 m3 16,443,774.77 4,439,819.19 0.678 0.162 0.407 - - 0.162 0.407
Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.02 m3 8,048,535.00 160,970.70 0.025 0.012 0.015 - - 0.012 0.015
2 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti 12.32 m2 644,715.80 7,942,898.68 1.213 - - - - - -
3 Memasang 1 m3 konstruksi gordeng, kayu glugu - m3 4,450,537.65 - - - - - - - -
VII. PEKERJAAN PLESTERAN - - -
1 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm 96.76 m2 54,689.70 5,291,775.27 0.808 48.380 0.404 19.352 0.162 67.732 0.566
2 Memasang 1 m2 acian 96.76 m2 33,411.23 3,232,870.55 0.494 - - - - - -
3 Pemasangan 1 m2 plesteran ciprat 1SP : 2PP 33.50 m2 45,029.48 1,508,487.73 0.230 30.150 0.207 1.675 0.012 31.825 0.219
VIII. PEKERJAAN PENGECATAN - - -
1 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 96.76 m2 11,686.42 1,130,778.06 0.173 - - - - - -
IX. PEKERJAAN PENUTUP ATAP - - -
1 Memasang 1 m2 Atap Galvalum (Paket) 78.51 m3 190,000.00 14,917,137.50 2.278 - - - - - -
2 Pemasangan 1 m talang datar Galvalum lebar 60 cm 6.00 m' 105,483.99 632,903.97 0.097 - - - - - -
X. PEKERJAAN PENUTUP LANTAI DAN DINDING - - -
1 Memasang 1 m2 lantai keramik (30 x 30) cm - m2 114,193.22 - - - - - - - -
2 Membuat rabat beton lantai mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 2.08 m3 723,713.11 1,504,722.31 0.230 - - - - - -
3 Memasang 1 m2 lantai keramik (20 x 20) cm 4.99 m2 184,674.28 921,524.65 0.141 - - - - - -
XI. PEKERJAAN SANITASI - - -
1 Memasang 1 buah Kloset Jongkok Porselen 2.00 bh 280,952.58 561,905.16 0.086 - - - - - -
2 Memasang 1 m Pipa PVC tipe AW 16.00 m' 19,406.20 310,499.27 0.047 - - - - - -
3 Memasang 1 m Pipa PVC tipe AW 1 8.00 m' 22,254.33 178,034.63 0.027 - - - - - -
4 Memasang 1 m Pipa PVC tipe AW 3 18.00 m' 63,036.61 1,134,659.00 0.173 - - - - - -
5 Memasang 1 buah Kran atau 2.00 bh 46,068.18 92,136.37 0.014 - - - - - -
6 Memasang 1 buah Floor Drain 2.00 bh 80,836.18 161,672.35 0.025 - - - - - -
7 Memasang 1 buah Pintu Kamar Mandi 2.00 bh 650,000.00 1,300,000.00 0.199 - - - - - -
8 Pemasangan 1 M Pipa PVC tipe D 4 12.00 m 85,618.17 1,027,418.08 0.157 - - - - - -
XII. PEKERJAAN ELEKTRIKAL - - -
1 Instalasi Penerangan menggunakan kabel NYY 3x2,5mm² dalam pipa conduit Ø 20mm. 10.00 titik 105,000.00 1,050,000.00 0.160 - - - - - -
2 Instalasi stop kontak dinding, menggunakan kabel NYM 3x2,5mm² 5.00 titik 100,000.00 500,000.00 0.076 - - - - - -
3 Saklar tunggal inbow, 1 gang 1 way 4.00 bh 20,000.00 80,000.00 0.012 - - - - - -
4 Saklar seri inbow, 1 gang 2 way 4.00 bh 25,000.00 100,000.00 0.015 - - - - - -
5 Stop kontak wall type 1ph, 16A, 1 gang 5.00 bh 20,000.00 100,000.00 0.015 - - - - - -
6 Lampu PLC 18 Watt dengan fitting gantung 8.00 bh 75,000.00 600,000.00 0.092 - - - - - -
7 Lampu PLC 7 Watt dengan fitting gantung 2.00 bh 65,000.00 130,000.00 0.020 - - - - - -
8 Penyambungan kabel 1.00 Ls 500,000.00 500,000.00 0.076 - - - - - -
9 Box MCB + MCB 2.00 bh 250,000.00 500,000.00 0.076 - - - - - -
XIII. PEKERJAAN LAIN-LAIN - - -
1 Pintu Folding gate 6.00 m2 788,049.93 4,728,299.56 0.722 - - - - - -
2 Railling pengaman besi Hollow 40x40 / 40x20 mm, finishing cat 11.48 m2 550,000.00 6,312,240.00 0.964 - - - - - -
167,320,879.74 25.557 13.535 1.922 15.457

Laporan Progres Mingguan ke-11


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PEMBERSIHAN SALURAN
1 Penggalian Tanah Lumpur dan Endapan Limbah Sedalam 30 cm 69.70 m3 109,311.98 7,619,044.68 1.164 48.311 0.807 10.455 0.175 58.766 0.981
2 Pembersihan dan Pembuangan Tanah Lumpur dan Limbah Keluar Area 90.90 m3 29,796.55 2,708,506.67 0.414 62.097 0.283 13.635 0.062 75.732 0.345
3 Pemadatan Tanah Eksisting 69.70 m3 49,023.50 3,416,937.98 0.522 55.760 0.418 3.485 0.026 59.245 0.444
4 Pengurugan dengan pasir urug, 10 cm 21.87 m3 178,388.92 3,901,365.68 0.596 16.357 0.446 2.187 0.060 18.544 0.505
Pengurugan dengan pasir urug, 10 cm 1.36 m3 173,624.00 236,128.64 0.036 0.952 0.025 0.204 0.005 1.156 0.031
5 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 10.93 m3 737,396.00 8,059,738.25 1.231 6.558 0.739 2.186 0.246 8.744 0.985
Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.68 m3 723,713.11 492,124.91 0.075 0.401 0.044 0.143 0.016 0.544 0.060
6 Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 23.23 m3 872,242.00 20,262,181.60 3.095 10.617 1.414 6.737 0.898 17.354 2.312
a Jaring Kawat baja/Wire Mesh M5 1 lapis 375.85 kg 10,697.66 4,020,713.73 0.614 206.718 0.338 75.170 0.123 281.888 0.461
7 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 133.20 m 77,312.85 10,298,072.12 1.573 53.280 0.629 33.300 0.393 86.580 1.022
8 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 718.80 m 86,676.29 62,302,919.11 9.516 143.760 1.903 90.451 1.197 234.211 3.101
9 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,2m, K.300 - bh 626,150.00 - - - - - - - -
10 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,8m, K.300 - bh 750,000.00 - - - - - - - -
11 Pekerjaan Plat Beton tebal 15 cm - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 8.37 m3 872,242.00 7,300,665.52 1.115 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis 608.09 kg 10,697.66 6,505,137.18 0.994 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 13.95 m2 316,861.88 4,420,223.25 0.675 - - - - - -
d Pembongkaran 1 M2 Bekisting 13.95 m2 15,645.80 218,258.88 0.033 - - - - - -
12 Pekerjaan Plat Beton tebal 10 cm - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 17.65 m3 872,242.00 15,395,071.25 2.351 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 1 lapis 962.04 kg 10,697.66 10,291,572.26 1.572 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 44.14 m2 316,861.88 13,986,283.46 2.136 - - - - - -
d Pembongkaran 1 M2 Bekisting 44.14 m2 15,645.80 690,605.52 0.105 - - - - - -
182,125,550.71 27.818 7.045 3.201 10.246
B PEKERJAAN JARINGAN IPAL KOMUNAL
1 Pekerjaan Galian Tanah Pipa 46.07 m3 67,972.30 3,131,483.87 0.478 - - - - - -
2 Pengurugan dengan pasir urug 11.51 m3 178,388.92 2,053,256.47 0.314 - - - - - -
3 Pengurugan Kembali 1 M3 Galian Tanah 30.54 m3 49,023.50 1,497,264.55 0.229 - - - - - -
4 Pemasangan 1 M Pipa PVC tipe AW 4 - m 90,907.55 - -
5 Saluran Pipa Air Limbah SDR - 41, Dia 15 cm , inc. fitting & Assecories - m 133,200.00 - - - - - - - -
6 Saluran Pipa Air Limbah SDR - 41, Dia 20 cm, , inc. fitting & Assecories - m 203,900.00 - - - - - - - -
7 Pemasangan Clean Out Inc. Fitting & Assecories 43.00 ttk 185,000.00 7,955,000.00 1.215 - - - - - -
8 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 100 org, 20 m3 / hari, - unit 7,500,000.00 - - - - - - - -
(Galian, Urugan, Pondasi, Tutup Beton, Penyambungan Instalasi)
9 Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm - unit 975,000.00 - - - - - - - -
10 Pekerjaan Sumur Resapan, Dia 100 cm, Kedalaman 2 m, Inc. Tutup Beton Berlubang - ttk 500,000.00 - - - - - - - -
11 Grill Beton Penutup Sumur Resapan - unit 750,000.00 - - - - - - - -
12 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 13.49 m3 688,832.33 9,292,348.18 1.419 - - - - - -
13 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area 13.49 m3 19,888.18 268,291.48 0.041 - - - - - -
14 Pemasangan 1 M Pipa PVC tipe D 6 375.05 m 133,200.00 49,956,660.00 7.630
14 Pemasangan 1 M Pipa PVC tipe D 4 64.50 m 85,618.17 5,522,372.20 0.844 - - - - - -
15 Pekerjaan Sumur Resapan kedalaman 4 Buis Beton Dia 80 cm 15.00 ttk 474,124.46 7,111,866.88 1.086 13.000 0.941 - - 13.000 0.941
16 Pasang Grill Besi Penutup Sumur Resapan 15.00 unit 826,875.00 12,403,125.00 1.894 - - - - - -

Laporan Progres Mingguan ke-11


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
C PEKERJAAN PEMASANGAN DAN PENGADAAN INSTALASI IPAL
1 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 50 org, 10 m3 / hari
a Pengadaan Unit IPAL kap 50 org, 10 m3 / hari 1.00 unit 110,250,000.00 110,250,000.00 16.840 - - - - - -
b Galian Tanah 57.21 m3 67,972.30 3,888,695.29 0.594 - - 14.303 0.148 14.303 0.148
c Pengurugan Kembali 1 M3 Galian Tanah 2.39 m3 49,023.50 117,166.17 0.018 - - - - - -
d Pengurugan dengan pasir urug 1.83 m3 178,388.92 326,254.80 0.050 - - - - - -
e Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Dinding, Lantai dan Tutup 11.77 m3 872,242.00 10,266,288.31 1.568 - - - - - -
Jaring Kawat baja/Wire Mesh M8 713.69 kg 10,697.66 7,634,809.58 1.166 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 30.14 m2 316,861.88 9,550,217.12 1.459 - - - - - -
Pembongkaran 1 M2 Bekisting 30.14 m2 15,645.80 471,564.35 0.072 - - - - - -
f Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Inlet 0.30 m3 872,242.00 261,672.60 0.040 - - - - - -
Jaring Kawat baja/Wire Mesh M8 11.06 kg 10,697.66 118,316.07 0.018 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.66 m2 316,861.88 209,128.84 0.032 - - - - - -
Pembongkaran 1 M2 Bekisting 0.66 m2 15,645.80 10,326.23 0.002 - - - - - -
g Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Outlet 0.41 m3 872,242.00 357,619.22 0.055 - - - - - -
Jaring Kawat baja/Wire Mesh M8 14.98 kg 10,697.66 160,250.88 0.024 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.96 m2 316,861.88 304,187.41 0.046 - - - - - -
Pembongkaran 1 M2 Bekisting 0.96 m2 15,645.80 15,019.97 0.002 - - - - - -
h Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Kolom 15 x 15 cm 0.47 m3 872,242.00 409,953.74 0.063 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 119.39 kg 11,860.70 1,416,048.75 0.216 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.44 m2 316,861.88 456,281.11 0.070 - - - - - -
Pembongkaran 1 M2 Bekisting 1.44 m2 15,645.80 22,529.95 0.003 - - - - - -
i Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Balok 15 x 20 cm 0.12 m3 872,242.00 104,669.04 0.016 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 23.91 kg 11,860.70 283,589.29 0.043 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.55 m2 316,861.88 174,274.03 0.027 - - - - - -
Pembongkaran 1 M2 Bekisting 0.55 m2 15,645.80 8,605.19 0.001 - - - - - -
j Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, pondasi 60 x 60 x 20 cm 0.72 m3 872,242.00 628,014.24 0.096 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 36.93 kg 11,860.70 438,015.58 0.067 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.20 m2 316,861.88 380,234.26 0.058 - - - - - -
Pembongkaran 1 M2 Bekisting 1.20 m2 15,645.80 18,774.96 0.003 - - - - - -
k Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm 4.00 unit 975,000.00 3,900,000.00 0.596 - - - - - -

251,374,175.57 38.395 0.941 0.148 1.090

JUMLAH 654,697,105.06 654,697,105.06 100.000 22.683 5.326 28.009


PRESTASI MINGGU LALU 22.683
PRESTASI MINGGU INI 5.326
PRESTASI SAMPAI DENGAN MINGGU INI 28.009
PRESTASI MENURUT SCHEDULE 30.084
LEBIH CEPAT (+) / TERLAMBAT (-) (2.075)

Yogyakarta, 9 Agustus 2021


di buat oleh,
KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA

Noor Hasan Bambang Erlianto


Pengawas Pelaksana

Laporan Progres Mingguan ke-11


REKAPITULASI
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : XI ( Sebelas )


Periode : 02 Agustus 2021 sampai dengan 08 Agustus 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
ADDENDUM II : 050 / 1909 / VII / 2021, TANGGAL 19 JULI 2021
NILAI KONTRAK ADDENDUM II : Rp 720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO PEKERJAAN PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp (%) BOBOT % BOBOT % BOBOT %

I PEKERJAAN PERSIAPAN 11,873,371.04 1.814 1.162 0.054 1.216

II PEKERJAAN PERBAIKAN TALUD SEGMEN 5


A PEKERJAAN TANAH DAN BETON BERTULANG 34,726,084.58 5.304 - - -
B PEKERJAAN PASANGAN DINDING 6,878,419.61 1.051 - - -

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PENGECATAN 398,623.81 0.061 - - -
B PEKERJAAN RUMAH TERDAMPAK 167,320,879.74 25.557 13.535 1.922 15.457

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PEMBERSIHAN SALURAN 182,125,550.71 27.818 7.045 3.201 10.246
B PEKERJAAN JARINGAN IPAL KOMUNAL 251,374,175.57 38.395 0.941 0.148 1.090

JUMLAH 654,697,105.06 100.000 22.683 5.326 28.009


PRESTASI MINGGU LALU 654,697,105.06 22.683
PRESTASI MINGGU INI 5.326
PRESTASI SAMPAI DENGAN MINGGU INI 28.009
PRESTASI MENURUT SCHEDULE 30.084
LEBIH CEPAT (+) / TERLAMBAT (-) (2.075)

Yogyakarta, 9 Agustus 2021


di buat oleh,
PEJABAT PEMBUAT KOMITMEN TIM TEKNIS KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA
1. Cicilia Novi hendrawati, M.SC., M.Eng.
NIP. 19781102 200501 2 011 ...........................

2. Danang Dwi Wahyujati,S.Kom.,M.Eng


NIP. 19761028 199803 1 004 ...........................
SIGIT SETIAWAN, ST.MT 3. Sudaryanto
NIP. 19690605 199303 1 007 RISMAN WARCHAN ZULIANTO
NIP. 19770623 200501 1 013 ........................... Tim Leader Direktur
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : XII ( Dua belas )


Periode : 09 Agustus 2021 sampai dengan 15 Agustus 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
ADDENDUM II : 050 / 1909 / VII / 2021, TANGGAL 19 JULI 2021
NILAI KONTRAK ADDENDUM II : Rp 720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
I PEKERJAAN PERSIAPAN
1 Pembuatan Papan Nama Pekerjaan 1.00 bh 250,000.00 250,000.00 0.038 1.000 0.038 - - 1.000 0.038
2 Pengukuran dan Pemasangan Bouwplank 28.56 m 12,198.91 348,400.73 0.053 28.560 0.053 - - 28.560 0.053
3 Pembuatan bedeng pekerja 9.00 m2 383,330.04 3,449,970.32 0.527 9.000 0.527 - - 9.000 0.527
4 Mobilisasi Demobilisasi Alat Berat 1.00 ls 2,500,000.00 2,500,000.00 0.382 0.500 0.191 0.045 0.017 0.545 0.208
5 Pembuatan akses menuju badan sungai sementara - m2 113,128.49 - - - - - - - -
6 Dewatering dengan pompa air diesel 40.00 jam 25,000.00 1,000,000.00 0.153 20.000 0.076 1.818 0.007 21.818 0.083
7 SMKK 1.00 ls 4,325,000.00 4,325,000.00 0.661 0.500 0.330 0.045 0.030 0.545 0.360
11,873,371.04 1.814 1.216 0.054 1.270
II PEKERJAAN PERBAIKAN TALUD SEGMEN 5
A PEKERJAAN TANAH DAN BETON BERTULANG
1 Penggalian 1 M3 Tanah Biasa 13.50 m3 67,972.30 917,626.05 0.140 - - - - - -
2 Pengurugan Kembali 1 M3 Galian Tanah 6.41 m3 49,023.50 314,240.64 0.048 - - - - - -
3 Bongkaran Pasangan Batu dan Beton Eksisting 7.92 m3 71,953.20 569,869.35 0.087 - - - - - -
4 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area 7.92 m3 19,888.18 157,514.35 0.024 - - - - - -
5 Pemadatan Tanah Eksisting 6.41 m3 49,023.50 314,240.64 0.048 - - - - - -
6 Pengurugan dengan pasir urug 0.27 m3 178,388.92 48,165.01 0.007 - - - - - -
7 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.27 m3 737,396.00 199,096.92 0.030 - - - - - -
8 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 1.08 m3 872,242.00 942,021.36 0.144 - - - - - -
a Pembesian dg Besi Polos atau Besi Ulir 156.69 kg 11,860.70 1,858,452.79 0.284 - - - - - -
b Bekisting untuk pondasi beton ( dipakai 2 kali ) 1.92 m2 89,375.55 171,601.05 0.026 - - - - - -
c Pembongkaran 1 M2 Bekisting 1.92 m2 15,645.80 30,039.93 0.005 - - - - - -
9 Pekerjaan Beton Dinding Talud Beton
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 2.16 m3 872,242.00 1,884,042.71 0.288 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 1,026.67 kg 11,860.70 12,177,022.97 1.860 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 9.02 m2 316,861.88 2,858,094.17 0.437 - - - - - -
d Pembongkaran 1 M2 Bekisting 9.02 m2 15,645.80 141,125.10 0.022 - - - - - -
10 Pekerjaan Beton Sloof 20x30cm
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 0.49 m3 872,242.00 427,398.58 0.065 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 147.55 kg 11,860.70 1,750,046.01 0.267 - - - - - -
c Memasang Bekisting untuk Sloof (dipakai 2 kali) 2.46 m2 89,375.55 219,863.84 0.034 - - - - - -
d Pembongkaran 1 M2 Bekisting 2.46 m2 15,645.80 38,488.66 0.006 - - - - - -
11 Pekerjaan Beton Konsul Cantilever
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 0.09 m3 872,242.00 78,501.78 0.012 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 47.58 kg 11,860.70 564,332.02 0.086 - - - - - -
c Memasang Bekisting untuk Balok (dipakai 2 kali) 0.45 m2 120,181.13 54,081.51 0.008 - - - - - -
d Pembongkaran 1 M2 Bekisting 0.45 m2 15,645.80 7,040.61 0.001 - - - - - -
12 Pekerjaan Plat Beton tebal 12 cm
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 2.70 m3 872,242.00 2,355,053.39 0.360 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis 294.23 kg 10,697.66 3,147,571.10 0.481 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.35 m2 316,861.88 427,763.54 0.065 - - - - - -
d Pembongkaran 1 M2 Bekisting 1.35 m2 15,645.80 21,121.83 0.003 - - - - - -
13 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 4.50 m 77,312.85 347,907.84 0.053 - - - - - -
14 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 8.67 m 86,676.29 751,483.46 0.115 - - - - - -
15 Memasang Stek Besi 23.67 kg 11,860.70 280,742.73 0.043 - - - - - -
16 Pekerjaan Plat Beton Pot tebal 10 cm
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 0.49 m3 872,242.00 427,398.58 0.065 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 23.67 kg 11,860.70 280,742.73 0.043 - - - - - -
c Bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm 7.20 m2 118,158.83 850,743.59 0.130 - - - - - -
d Pembongkaran 1 M2 Bekisting 7.20 m2 15,645.80 112,649.75 0.017 - - - - - -
34,726,084.58 5.304 - - -
B PEKERJAAN PASANGAN DINDING
1 Pemasangan Dinding Bata Merah Bakar Sekam Tebal 1/2 Bata Camp. 1SP 6PP 9.97 m2 116,576.48 1,162,267.55 0.178 - - - - - -
2 Pemasangan Plesteran 1 Pc 6 Pp Tebal 15 mm 34.11 m2 54,689.70 1,865,465.63 0.285 - - - - - -
3 Pemasangan Acian 34.11 m2 33,411.23 1,139,657.03 0.174 - - - - - -
4 Pemasangan Plesteran Skoning 1 Pc 2Pp lebar 10 cm 46.50 m 55,075.90 2,561,029.40 0.391 - - - - - -
5 Pemasangan Kepala Kolom 3.00 bh 50,000.00 150,000.00 0.023 - - - - - -
Laporan Progres Mingguan ke-12
HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
6,878,419.61 1.051 - - -

Laporan Progres Mingguan ke-12


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PENGECATAN
1 Pengecatan Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Weathershield luar ruangan 34.11 m2 11,686.42 398,623.81 0.061 - - - - - -
398,623.81 0.061 - - -
B PEKERJAAN RUMAH TERDAMPAK
I. PEKERJAAN BONGKARAN
1 Membongkar 1 m2 genteng / sirap untuk dipergunakan lagi 77.17 m2 3,628.42 280,005.33 0.043 19.293 0.011 19.293 0.011 38.585 0.021
2 Membongkar 1 m3 kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi 0.37 m3 991,595.91 366,890.49 0.056 0.093 0.014 0.093 0.014 0.185 0.028
3 Pembongkaran 1 m3 pasangan bata merah dan membersihkan 12.72 m3 185,908.38 2,364,754.54 0.361 4.277 0.121 3.816 0.108 8.093 0.230
4 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 1.50 m3 688,832.33 1,033,248.50 0.158 0.408 0.043 0.450 0.047 0.858 0.090
II. PEKERJAAN TANAH - - - - -
1 Menggali 1 m3 tanah biasa sedalam 1 meter 27.22 m3 67,972.30 1,850,206.01 0.283 27.220 0.283 - - 27.220 0.283
2 Pengurugan Kembali 1 m3 Galian Tanah 10.11 m3 18,745.83 189,520.38 0.029 10.110 0.029 - - 10.110 0.029
3 Pengurugan dengan pasir urug 1.82 m3 173,624.00 315,995.68 0.048 1.820 0.048 - - 1.820 0.048
4 Peninggian peil lantai 9.18 m3 18,745.83 172,086.75 0.026 - - - - - -
III. PEKERJAAN PONDASI - - - - -
1 Memasang 1 m3 pondasi batu belah, campuran 1 PC 6 PP 16.49 m2 665,195.09 10,969,067.11 1.675 16.490 1.675 - - 16.490 1.675
IV. PEKERJAAN BETON - - - - -
1 Membuat 1 m3 Sloof beton bertulang (200 kg besi + bekisting) 1.06 m3 3,844,764.87 4,075,450.77 0.622 1.060 0.622 - - 1.060 0.622
2 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) 2.29 m3 7,083,735.01 16,221,753.18 2.478 2.290 2.478 - - 2.290 2.478
3 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) 3.05 m3 5,659,422.09 17,261,237.38 2.637 3.050 2.637 - - 3.050 2.637
4 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.14 m3 723,713.11 101,319.83 0.015 0.140 0.015 - - 0.140 0.015
5 Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting) 0.57 m3 3,127,107.54 1,782,451.30 0.272 0.570 0.272 - - 0.570 0.272
6 Sloof 150 x 200 dengan beton K 225 Tulangan 105 kg 0.74 m3 3,295,166.46 2,438,423.18 0.372 0.740 0.372 - - 0.740 0.372
7 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm 67.35 m' 77,312.85 5,207,020.70 0.795 57.248 0.676 10.103 0.119 67.350 0.795
8 Balok 150 x 200 dengan beton K 225 Tulangan 105 kg 1.01 m3 3,705,897.33 3,742,956.31 0.572 0.859 0.486 0.152 0.086 1.010 0.572
9 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm 54.15 m' 86,676.29 4,693,521.24 0.717 43.320 0.574 10.830 0.143 54.150 0.717
10 Membuat 1 m3 Plat Lantai beton bertulang 2.95 m3 3,119,381.73 9,202,176.12 1.406 2.015 0.960 0.935 0.445 2.950 1.406
11 Membuat 1 m3 Plat Tangga beton bertulang 0.72 m3 3,119,381.73 2,245,954.85 0.343 - - 0.540 0.257 0.540 0.257
12 Membuat 1 m3 Plat Water torn beton bertulang 0.42 m3 3,119,381.73 1,310,140.33 0.200 0.420 0.200 - - 0.420 0.200
V. PEKERJAAN DINDING - - - - -
1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP 161.84 m2 116,576.48 18,866,738.23 2.882 153.522 2.734 4.855 0.086 158.378 2.820
2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP, trap tangga 6.30 m2 250,668.02 1,579,208.52 0.241 - - - - - -
VI PEKERJAAN KAYU - - - - -
1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.27 m3 16,443,774.77 4,439,819.19 0.678 0.162 0.407 0.068 0.170 0.230 0.576
Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.02 m3 8,048,535.00 160,970.70 0.025 0.012 0.015 0.005 0.006 0.017 0.021
2 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti 12.32 m2 644,715.80 7,942,898.68 1.213 - - - - - -
3 Memasang 1 m3 konstruksi gordeng, kayu glugu - m3 4,450,537.65 - - - - - - - -
VII. PEKERJAAN PLESTERAN - - - - -
1 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm 96.76 m2 54,689.70 5,291,775.27 0.808 67.732 0.566 24.190 0.202 91.922 0.768
2 Memasang 1 m2 acian 96.76 m2 33,411.23 3,232,870.55 0.494 - - 79.206 0.404 79.206 0.404
3 Pemasangan 1 m2 plesteran ciprat 1SP : 2PP 33.50 m2 45,029.48 1,508,487.73 0.230 31.825 0.219 1.005 0.007 32.830 0.226
VIII. PEKERJAAN PENGECATAN - - - - -
1 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 96.76 m2 11,686.42 1,130,778.06 0.173 - - - - - -
IX. PEKERJAAN PENUTUP ATAP - - - - -
1 Memasang 1 m2 Atap Galvalum (Paket) 78.51 m3 190,000.00 14,917,137.50 2.278 - - - - - -
2 Pemasangan 1 m talang datar Galvalum lebar 60 cm 6.00 m' 105,483.99 632,903.97 0.097 - - - - - -
X. PEKERJAAN PENUTUP LANTAI DAN DINDING - - - - -
1 Memasang 1 m2 lantai keramik (30 x 30) cm - m2 114,193.22 - - - - - - - -
2 Membuat rabat beton lantai mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 2.08 m3 723,713.11 1,504,722.31 0.230 - - - - - -
3 Memasang 1 m2 lantai keramik (20 x 20) cm 4.99 m2 184,674.28 921,524.65 0.141 - - - - - -
XI. PEKERJAAN SANITASI - - - - -
1 Memasang 1 buah Kloset Jongkok Porselen 2.00 bh 280,952.58 561,905.16 0.086 - - - - - -
2 Memasang 1 m Pipa PVC tipe AW 16.00 m' 19,406.20 310,499.27 0.047 - - - - - -
3 Memasang 1 m Pipa PVC tipe AW 1 8.00 m' 22,254.33 178,034.63 0.027 - - - - - -
4 Memasang 1 m Pipa PVC tipe AW 3 18.00 m' 63,036.61 1,134,659.00 0.173 - - - - - -
5 Memasang 1 buah Kran atau 2.00 bh 46,068.18 92,136.37 0.014 - - - - - -
6 Memasang 1 buah Floor Drain 2.00 bh 80,836.18 161,672.35 0.025 - - - - - -
7 Memasang 1 buah Pintu Kamar Mandi 2.00 bh 650,000.00 1,300,000.00 0.199 - - - - - -
8 Pemasangan 1 M Pipa PVC tipe D 4 12.00 m 85,618.17 1,027,418.08 0.157 - - - - - -
XII. PEKERJAAN ELEKTRIKAL - - - - -
1 Instalasi Penerangan menggunakan kabel NYY 3x2,5mm² dalam pipa conduit Ø 20mm. 10.00 titik 105,000.00 1,050,000.00 0.160 - - - - - -
2 Instalasi stop kontak dinding, menggunakan kabel NYM 3x2,5mm² 5.00 titik 100,000.00 500,000.00 0.076 - - - - - -
3 Saklar tunggal inbow, 1 gang 1 way 4.00 bh 20,000.00 80,000.00 0.012 - - - - - -
4 Saklar seri inbow, 1 gang 2 way 4.00 bh 25,000.00 100,000.00 0.015 - - - - - -
5 Stop kontak wall type 1ph, 16A, 1 gang 5.00 bh 20,000.00 100,000.00 0.015 - - - - - -
6 Lampu PLC 18 Watt dengan fitting gantung 8.00 bh 75,000.00 600,000.00 0.092 - - - - - -
7 Lampu PLC 7 Watt dengan fitting gantung 2.00 bh 65,000.00 130,000.00 0.020 - - - - - -
8 Penyambungan kabel 1.00 Ls 500,000.00 500,000.00 0.076 - - - - - -
9 Box MCB + MCB 2.00 bh 250,000.00 500,000.00 0.076 - - - - - -
XIII. PEKERJAAN LAIN-LAIN
1 Pintu Folding gate 6.00 m2 788,049.93 4,728,299.56 0.722 - - - - - -
2 Railling pengaman besi Hollow 40x40 / 40x20 mm, finishing cat 11.48 m2 550,000.00 6,312,240.00 0.964 - - - - - -
167,320,879.74 25.557 15.457 2.107 17.564

Laporan Progres Mingguan ke-12


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PEMBERSIHAN SALURAN
1 Penggalian Tanah Lumpur dan Endapan Limbah Sedalam 30 cm 69.70 m3 109,311.98 7,619,044.68 1.164 58.766 0.981 - - 58.766 0.981
2 Pembersihan dan Pembuangan Tanah Lumpur dan Limbah Keluar Area 90.90 m3 29,796.55 2,708,506.67 0.414 75.732 0.345 - - 75.732 0.345
3 Pemadatan Tanah Eksisting 69.70 m3 49,023.50 3,416,937.98 0.522 59.245 0.444 - - 59.245 0.444
4 Pengurugan dengan pasir urug, 10 cm 21.87 m3 178,388.92 3,901,365.68 0.596 18.544 0.505 - - 18.544 0.505
Pengurugan dengan pasir urug, 10 cm 1.36 m3 173,624.00 236,128.64 0.036 1.156 0.031 - - 1.156 0.031
5 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 10.93 m3 737,396.00 8,059,738.25 1.231 8.744 0.985 - - 8.744 0.985
Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.68 m3 723,713.11 492,124.91 0.075 0.544 0.060 - - 0.544 0.060
6 Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 23.23 m3 872,242.00 20,262,181.60 3.095 17.354 2.312 1.162 0.155 18.515 2.467
a Jaring Kawat baja/Wire Mesh M5 1 lapis 375.85 kg 10,697.66 4,020,713.73 0.614 281.888 0.461 18.793 0.031 300.680 0.491
7 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 133.20 m 77,312.85 10,298,072.12 1.573 86.580 1.022 13.320 0.157 99.900 1.180
8 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 718.80 m 86,676.29 62,302,919.11 9.516 234.211 3.101 53.025 0.702 287.235 3.803
9 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,2m, K.300 - bh 626,150.00 - - - - - - - -
10 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,8m, K.300 - bh 750,000.00 - - - - - - - -
11 Pekerjaan Plat Beton tebal 15 cm - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 8.37 m3 872,242.00 7,300,665.52 1.115 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis 608.09 kg 10,697.66 6,505,137.18 0.994 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 13.95 m2 316,861.88 4,420,223.25 0.675 - - - - - -
d Pembongkaran 1 M2 Bekisting 13.95 m2 15,645.80 218,258.88 0.033 - - - - - -
12 Pekerjaan Plat Beton tebal 10 cm - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 17.65 m3 872,242.00 15,395,071.25 2.351 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 1 lapis 962.04 kg 10,697.66 10,291,572.26 1.572 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 44.14 m2 316,861.88 13,986,283.46 2.136 - - - - - -
d Pembongkaran 1 M2 Bekisting 44.14 m2 15,645.80 690,605.52 0.105 - - - - - -
182,125,550.71 27.818 10.246 1.045 11.291
B PEKERJAAN JARINGAN IPAL KOMUNAL
1 Pekerjaan Galian Tanah Pipa 46.07 m3 67,972.30 3,131,483.87 0.478 - - - - - -
2 Pengurugan dengan pasir urug 11.51 m3 178,388.92 2,053,256.47 0.314 - - - - - -
3 Pengurugan Kembali 1 M3 Galian Tanah 30.54 m3 49,023.50 1,497,264.55 0.229 - - - - - -
4 Pemasangan 1 M Pipa PVC tipe AW 4 - m 90,907.55 - -
5 Saluran Pipa Air Limbah SDR - 41, Dia 15 cm , inc. fitting & Assecories - m 133,200.00 - - - - - - - -
6 Saluran Pipa Air Limbah SDR - 41, Dia 20 cm, , inc. fitting & Assecories - m 203,900.00 - - - - - - - -
7 Pemasangan Clean Out Inc. Fitting & Assecories 43.00 ttk 185,000.00 7,955,000.00 1.215 - - - - - -
8 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 100 org, 20 m3 / hari, - unit 7,500,000.00 - - - - - - - -
(Galian, Urugan, Pondasi, Tutup Beton, Penyambungan Instalasi)
9 Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm - unit 975,000.00 - - - - - - - -
10 Pekerjaan Sumur Resapan, Dia 100 cm, Kedalaman 2 m, Inc. Tutup Beton Berlubang - ttk 500,000.00 - - - - - - - -
11 Grill Beton Penutup Sumur Resapan - unit 750,000.00 - - - - - - - -
12 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 13.49 m3 688,832.33 9,292,348.18 1.419 - - - - - -
13 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area 13.49 m3 19,888.18 268,291.48 0.041 - - - - - -
14 Pemasangan 1 M Pipa PVC tipe D 6 375.05 m 133,200.00 49,956,660.00 7.630 - - - - - -
14 Pemasangan 1 M Pipa PVC tipe D 4 64.50 m 85,618.17 5,522,372.20 0.844 - - - - - -
15 Pekerjaan Sumur Resapan kedalaman 4 Buis Beton Dia 80 cm 15.00 ttk 474,124.46 7,111,866.88 1.086 13.000 0.941 - - 13.000 0.941
16 Pasang Grill Besi Penutup Sumur Resapan 15.00 unit 826,875.00 12,403,125.00 1.894 - - - - - -

Laporan Progres Mingguan ke-12


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
C PEKERJAAN PEMASANGAN DAN PENGADAAN INSTALASI IPAL
1 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 50 org, 10 m3 / hari
a Pengadaan Unit IPAL kap 50 org, 10 m3 / hari 1.00 unit 110,250,000.00 110,250,000.00 16.840 - - - - - -
b Galian Tanah 57.21 m3 67,972.30 3,888,695.29 0.594 14.303 0.148 22.884 0.238 37.187 0.386
c Pengurugan Kembali 1 M3 Galian Tanah 2.39 m3 49,023.50 117,166.17 0.018 - - - - - -
d Pengurugan dengan pasir urug 1.83 m3 178,388.92 326,254.80 0.050 - - - - - -
e Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Dinding, Lantai dan Tutup 11.77 m3 872,242.00 10,266,288.31 1.568 - - - - - -
Jaring Kawat baja/Wire Mesh M8 713.69 kg 10,697.66 7,634,809.58 1.166 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 30.14 m2 316,861.88 9,550,217.12 1.459 - - - - - -
Pembongkaran 1 M2 Bekisting 30.14 m2 15,645.80 471,564.35 0.072 - - - - - -
f Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Inlet 0.30 m3 872,242.00 261,672.60 0.040 - - - - - -
Jaring Kawat baja/Wire Mesh M8 11.06 kg 10,697.66 118,316.07 0.018 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.66 m2 316,861.88 209,128.84 0.032 - - - - - -
Pembongkaran 1 M2 Bekisting 0.66 m2 15,645.80 10,326.23 0.002 - - - - - -
g Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Outlet 0.41 m3 872,242.00 357,619.22 0.055 - - - - - -
Jaring Kawat baja/Wire Mesh M8 14.98 kg 10,697.66 160,250.88 0.024 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.96 m2 316,861.88 304,187.41 0.046 - - - - - -
Pembongkaran 1 M2 Bekisting 0.96 m2 15,645.80 15,019.97 0.002 - - - - - -
h Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Kolom 15 x 15 cm 0.47 m3 872,242.00 409,953.74 0.063 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 119.39 kg 11,860.70 1,416,048.75 0.216 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.44 m2 316,861.88 456,281.11 0.070 - - - - - -
Pembongkaran 1 M2 Bekisting 1.44 m2 15,645.80 22,529.95 0.003 - - - - - -
i Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Balok 15 x 20 cm 0.12 m3 872,242.00 104,669.04 0.016 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 23.91 kg 11,860.70 283,589.29 0.043 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.55 m2 316,861.88 174,274.03 0.027 - - - - - -
Pembongkaran 1 M2 Bekisting 0.55 m2 15,645.80 8,605.19 0.001 - - - - - -
j Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, pondasi 60 x 60 x 20 cm 0.72 m3 872,242.00 628,014.24 0.096 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 36.93 kg 11,860.70 438,015.58 0.067 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.20 m2 316,861.88 380,234.26 0.058 - - - - - -
Pembongkaran 1 M2 Bekisting 1.20 m2 15,645.80 18,774.96 0.003 - - - - - -
k Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm 4.00 unit 975,000.00 3,900,000.00 0.596 - - - - - -

251,374,175.57 38.395 1.090 0.238 1.328

JUMLAH 654,697,105.06 654,697,105.06 100.000 28.009 3.443 31.453


PRESTASI MINGGU LALU 28.009
PRESTASI MINGGU INI 3.443
PRESTASI SAMPAI DENGAN MINGGU INI 31.453
PRESTASI MENURUT SCHEDULE 38.024
LEBIH CEPAT (+) / TERLAMBAT (-) (6.572)

Yogyakarta, 16 Agustus 2021


di buat oleh,
KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA

Noor Hasan Bambang Erlianto


Pengawas Pelaksana

Laporan Progres Mingguan ke-12


REKAPITULASI
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : XII ( Dua belas )


Periode : 09 Agustus 2021 sampai dengan 15 Agustus 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
ADDENDUM II : 050 / 1909 / VII / 2021, TANGGAL 19 JULI 2021
NILAI KONTRAK ADDENDUM II : Rp 720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO PEKERJAAN PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp (%) BOBOT % BOBOT % BOBOT %

I PEKERJAAN PERSIAPAN 11,873,371.04 1.814 1.216 0.054 1.270

II PEKERJAAN PERBAIKAN TALUD SEGMEN 5


A PEKERJAAN TANAH DAN BETON BERTULANG 34,726,084.58 5.304 - - -
B PEKERJAAN PASANGAN DINDING 6,878,419.61 1.051 - - -

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PENGECATAN 398,623.81 0.061 - - -
B PEKERJAAN RUMAH TERDAMPAK 167,320,879.74 25.557 15.457 2.107 17.564

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PEMBERSIHAN SALURAN 182,125,550.71 27.818 10.246 1.045 11.291
B PEKERJAAN JARINGAN IPAL KOMUNAL 251,374,175.57 38.395 1.090 0.238 1.328

JUMLAH 654,697,105.06 100.000 28.009 3.443 31.453


PRESTASI MINGGU LALU 654,697,105.06 28.009
PRESTASI MINGGU INI 3.443
PRESTASI SAMPAI DENGAN MINGGU INI 31.453
PRESTASI MENURUT SCHEDULE 38.024
LEBIH CEPAT (+) / TERLAMBAT (-) (6.572)

Yogyakarta, 16 Agustus 2021


di buat oleh,
PEJABAT PEMBUAT KOMITMEN TIM TEKNIS KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA
1. Cicilia Novi hendrawati, M.SC., M.Eng.
NIP. 19781102 200501 2 011 ...........................

2. Danang Dwi Wahyujati,S.Kom.,M.Eng


NIP. 19761028 199803 1 004 ...........................
SIGIT SETIAWAN, ST.MT 3. Sudaryanto
NIP. 19690605 199303 1 007 RISMAN WARCHAN ZULIANTO
NIP. 19770623 200501 1 013 ........................... Tim Leader Direktur
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : XIII ( Tiga belas )


Periode : 16 Agustus 2021 sampai dengan 22 Agustus 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
ADDENDUM II : 050 / 1909 / VII / 2021, TANGGAL 19 JULI 2021
NILAI KONTRAK ADDENDUM II : Rp 720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
I PEKERJAAN PERSIAPAN
1 Pembuatan Papan Nama Pekerjaan 1.00 bh 250,000.00 250,000.00 0.038 1.000 0.038 - - 1.000 0.038
2 Pengukuran dan Pemasangan Bouwplank 28.56 m 12,198.91 348,400.73 0.053 28.560 0.053 - - 28.560 0.053
3 Pembuatan bedeng pekerja 9.00 m2 383,330.04 3,449,970.32 0.527 9.000 0.527 - - 9.000 0.527
4 Mobilisasi Demobilisasi Alat Berat 1.00 ls 2,500,000.00 2,500,000.00 0.382 0.545 0.208 0.045 0.017 0.591 0.226
5 Pembuatan akses menuju badan sungai sementara - m2 113,128.49 - - - - - - - -
6 Dewatering dengan pompa air diesel 40.00 jam 25,000.00 1,000,000.00 0.153 21.818 0.083 1.818 0.007 23.636 0.090
7 SMKK 1.00 ls 4,325,000.00 4,325,000.00 0.661 0.545 0.360 0.045 0.030 0.591 0.390
11,873,371.04 1.814 1.270 0.054 1.325
II PEKERJAAN PERBAIKAN TALUD SEGMEN 5
A PEKERJAAN TANAH DAN BETON BERTULANG
1 Penggalian 1 M3 Tanah Biasa 13.50 m3 67,972.30 917,626.05 0.140 - - - - - -
2 Pengurugan Kembali 1 M3 Galian Tanah 6.41 m3 49,023.50 314,240.64 0.048 - - - - - -
3 Bongkaran Pasangan Batu dan Beton Eksisting 7.92 m3 71,953.20 569,869.35 0.087 - - - - - -
4 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area 7.92 m3 19,888.18 157,514.35 0.024 - - - - - -
5 Pemadatan Tanah Eksisting 6.41 m3 49,023.50 314,240.64 0.048 - - - - - -
6 Pengurugan dengan pasir urug 0.27 m3 178,388.92 48,165.01 0.007 - - - - - -
7 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.27 m3 737,396.00 199,096.92 0.030 - - - - - -
8 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 1.08 m3 872,242.00 942,021.36 0.144 - - - - - -
a Pembesian dg Besi Polos atau Besi Ulir 156.69 kg 11,860.70 1,858,452.79 0.284 - - - - - -
b Bekisting untuk pondasi beton ( dipakai 2 kali ) 1.92 m2 89,375.55 171,601.05 0.026 - - - - - -
c Pembongkaran 1 M2 Bekisting 1.92 m2 15,645.80 30,039.93 0.005 - - - - - -
9 Pekerjaan Beton Dinding Talud Beton
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 2.16 m3 872,242.00 1,884,042.71 0.288 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 1,026.67 kg 11,860.70 12,177,022.97 1.860 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 9.02 m2 316,861.88 2,858,094.17 0.437 - - - - - -
d Pembongkaran 1 M2 Bekisting 9.02 m2 15,645.80 141,125.10 0.022 - - - - - -
10 Pekerjaan Beton Sloof 20x30cm
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 0.49 m3 872,242.00 427,398.58 0.065 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 147.55 kg 11,860.70 1,750,046.01 0.267 - - - - - -
c Memasang Bekisting untuk Sloof (dipakai 2 kali) 2.46 m2 89,375.55 219,863.84 0.034 - - - - - -
d Pembongkaran 1 M2 Bekisting 2.46 m2 15,645.80 38,488.66 0.006 - - - - - -
11 Pekerjaan Beton Konsul Cantilever
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 0.09 m3 872,242.00 78,501.78 0.012 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 47.58 kg 11,860.70 564,332.02 0.086 - - - - - -
c Memasang Bekisting untuk Balok (dipakai 2 kali) 0.45 m2 120,181.13 54,081.51 0.008 - - - - - -
d Pembongkaran 1 M2 Bekisting 0.45 m2 15,645.80 7,040.61 0.001 - - - - - -
12 Pekerjaan Plat Beton tebal 12 cm
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 2.70 m3 872,242.00 2,355,053.39 0.360 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis 294.23 kg 10,697.66 3,147,571.10 0.481 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.35 m2 316,861.88 427,763.54 0.065 - - - - - -
d Pembongkaran 1 M2 Bekisting 1.35 m2 15,645.80 21,121.83 0.003 - - - - - -
13 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 4.50 m 77,312.85 347,907.84 0.053 - - - - - -
14 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 8.67 m 86,676.29 751,483.46 0.115 - - - - - -
15 Memasang Stek Besi 23.67 kg 11,860.70 280,742.73 0.043 - - - - - -
16 Pekerjaan Plat Beton Pot tebal 10 cm
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 0.49 m3 872,242.00 427,398.58 0.065 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 23.67 kg 11,860.70 280,742.73 0.043 - - - - - -
c Bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm 7.20 m2 118,158.83 850,743.59 0.130 - - - - - -
d Pembongkaran 1 M2 Bekisting 7.20 m2 15,645.80 112,649.75 0.017 - - - - - -
34,726,084.58 5.304 - - -
B PEKERJAAN PASANGAN DINDING
1 Pemasangan Dinding Bata Merah Bakar Sekam Tebal 1/2 Bata Camp. 1SP 6PP 9.97 m2 116,576.48 1,162,267.55 0.178 - - - - - -
2 Pemasangan Plesteran 1 Pc 6 Pp Tebal 15 mm 34.11 m2 54,689.70 1,865,465.63 0.285 - - - - - -
3 Pemasangan Acian 34.11 m2 33,411.23 1,139,657.03 0.174 - - - - - -
4 Pemasangan Plesteran Skoning 1 Pc 2Pp lebar 10 cm 46.50 m 55,075.90 2,561,029.40 0.391 - - - - - -
5 Pemasangan Kepala Kolom 3.00 bh 50,000.00 150,000.00 0.023 - - - - - -
Laporan Progres Mingguan ke-13
HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
6,878,419.61 1.051 - - -

Laporan Progres Mingguan ke-13


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PENGECATAN
1 Pengecatan Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Weathershield luar ruangan 34.11 m2 11,686.42 398,623.81 0.061 - - - - - -
398,623.81 0.061 - - -
B PEKERJAAN RUMAH TERDAMPAK
I. PEKERJAAN BONGKARAN
1 Membongkar 1 m2 genteng / sirap untuk dipergunakan lagi 77.17 m2 3,628.42 280,005.33 0.043 38.585 0.021 - - 38.585 0.021
2 Membongkar 1 m3 kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi 0.37 m3 991,595.91 366,890.49 0.056 0.185 0.028 - - 0.185 0.028
3 Pembongkaran 1 m3 pasangan bata merah dan membersihkan 12.72 m3 185,908.38 2,364,754.54 0.361 8.093 0.230 - - 8.093 0.230
4 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 1.50 m3 688,832.33 1,033,248.50 0.158 0.858 0.090 - - 0.858 0.090
II. PEKERJAAN TANAH
1 Menggali 1 m3 tanah biasa sedalam 1 meter 27.22 m3 67,972.30 1,850,206.01 0.283 27.220 0.283 - - 27.220 0.283
2 Pengurugan Kembali 1 m3 Galian Tanah 10.11 m3 18,745.83 189,520.38 0.029 10.110 0.029 - - 10.110 0.029
3 Pengurugan dengan pasir urug 1.82 m3 173,624.00 315,995.68 0.048 1.820 0.048 - - 1.820 0.048
4 Peninggian peil lantai 9.18 m3 18,745.83 172,086.75 0.026
III. PEKERJAAN PONDASI
1 Memasang 1 m3 pondasi batu belah, campuran 1 PC 6 PP 16.49 m2 665,195.09 10,969,067.11 1.675 16.490 1.675 - - 16.490 1.675
IV. PEKERJAAN BETON
1 Membuat 1 m3 Sloof beton bertulang (200 kg besi + bekisting) 1.06 m3 3,844,764.87 4,075,450.77 0.622 1.060 0.622 - - 1.060 0.622
2 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) 2.29 m3 7,083,735.01 16,221,753.18 2.478 2.290 2.478 - - 2.290 2.478
3 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) 3.05 m3 5,659,422.09 17,261,237.38 2.637 3.050 2.637 - - 3.050 2.637
4 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.14 m3 723,713.11 101,319.83 0.015 0.140 0.015 - - 0.140 0.015
5 Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting) 0.57 m3 3,127,107.54 1,782,451.30 0.272 0.570 0.272 - - 0.570 0.272
6 Sloof 150 x 200 dengan beton K 225 Tulangan 105 kg 0.74 m3 3,295,166.46 2,438,423.18 0.372 0.740 0.372 - - 0.740 0.372
7 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm 67.35 m' 77,312.85 5,207,020.70 0.795 67.350 0.795 - - 67.350 0.795
8 Balok 150 x 200 dengan beton K 225 Tulangan 105 kg 1.01 m3 3,705,897.33 3,742,956.31 0.572 1.010 0.572 - - 1.010 0.572
9 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm 54.15 m' 86,676.29 4,693,521.24 0.717 54.150 0.717 - - 54.150 0.717
10 Membuat 1 m3 Plat Lantai beton bertulang 2.95 m3 3,119,381.73 9,202,176.12 1.406 2.950 1.406 - - 2.950 1.406
11 Membuat 1 m3 Plat Tangga beton bertulang 0.72 m3 3,119,381.73 2,245,954.85 0.343 0.540 0.257 0.180 0.086 0.720 0.343
12 Membuat 1 m3 Plat Water torn beton bertulang 0.42 m3 3,119,381.73 1,310,140.33 0.200 0.420 0.200 - - 0.420 0.200
V. PEKERJAAN DINDING
1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP 161.84 m2 116,576.48 18,866,738.23 2.882 158.378 2.820 - - 158.378 2.820
2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP, trap tangga 6.30 m2 250,668.02 1,579,208.52 0.241 - - - - - -
VI PEKERJAAN KAYU
1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.27 m3 16,443,774.77 4,439,819.19 0.678 0.230 0.576 0.041 0.102 0.270 0.678
Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.02 m3 8,048,535.00 160,970.70 0.025 0.017 0.021 0.003 0.004 0.020 0.025
2 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti 12.32 m2 644,715.80 7,942,898.68 1.213 - - 9.856 0.971 9.856 0.971
3 Memasang 1 m3 konstruksi gordeng, kayu glugu - m3 4,450,537.65 - - - - - - - -
VII. PEKERJAAN PLESTERAN
1 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm 96.76 m2 54,689.70 5,291,775.27 0.808 91.922 0.768 4.838 0.040 96.760 0.808
2 Memasang 1 m2 acian 96.76 m2 33,411.23 3,232,870.55 0.494 79.206 0.404 15.824 0.081 95.030 0.485
3 Pemasangan 1 m2 plesteran ciprat 1SP : 2PP 33.50 m2 45,029.48 1,508,487.73 0.230 32.830 0.226 0.670 0.005 33.500 0.230
VIII. PEKERJAAN PENGECATAN
1 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 96.76 m2 11,686.42 1,130,778.06 0.173 - - - - - -
IX. PEKERJAAN PENUTUP ATAP
1 Memasang 1 m2 Atap Galvalum (Paket) 78.51 m3 190,000.00 14,917,137.50 2.278 - - 58.883 1.709 58.883 1.709
2 Pemasangan 1 m talang datar Galvalum lebar 60 cm 6.00 m' 105,483.99 632,903.97 0.097 - - - - - -
X. PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Memasang 1 m2 lantai keramik (30 x 30) cm - m2 114,193.22 - - - - - - - -
2 Membuat rabat beton lantai mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 2.08 m3 723,713.11 1,504,722.31 0.230 - - - - - -
3 Memasang 1 m2 lantai keramik (20 x 20) cm 4.99 m2 184,674.28 921,524.65 0.141 - - - - - -
XI. PEKERJAAN SANITASI - - - - -
1 Memasang 1 buah Kloset Jongkok Porselen 2.00 bh 280,952.58 561,905.16 0.086 - - - - - -
2 Memasang 1 m Pipa PVC tipe AW 16.00 m' 19,406.20 310,499.27 0.047 - - - - - -
3 Memasang 1 m Pipa PVC tipe AW 1 8.00 m' 22,254.33 178,034.63 0.027 - - - - - -
4 Memasang 1 m Pipa PVC tipe AW 3 18.00 m' 63,036.61 1,134,659.00 0.173 - - - - - -
5 Memasang 1 buah Kran atau 2.00 bh 46,068.18 92,136.37 0.014 - - - - - -
6 Memasang 1 buah Floor Drain 2.00 bh 80,836.18 161,672.35 0.025 - - - - - -
7 Memasang 1 buah Pintu Kamar Mandi 2.00 bh 650,000.00 1,300,000.00 0.199 - - - - - -
8 Pemasangan 1 M Pipa PVC tipe D 4 12.00 m 85,618.17 1,027,418.08 0.157 - - - - - -
XII. PEKERJAAN ELEKTRIKAL
1 Instalasi Penerangan menggunakan kabel NYY 3x2,5mm² dalam pipa conduit Ø 20mm. 10.00 titik 105,000.00 1,050,000.00 0.160 - - - - - -
2 Instalasi stop kontak dinding, menggunakan kabel NYM 3x2,5mm² 5.00 titik 100,000.00 500,000.00 0.076 - - - - - -
3 Saklar tunggal inbow, 1 gang 1 way 4.00 bh 20,000.00 80,000.00 0.012 - - - - - -
4 Saklar seri inbow, 1 gang 2 way 4.00 bh 25,000.00 100,000.00 0.015 - - - - - -
5 Stop kontak wall type 1ph, 16A, 1 gang 5.00 bh 20,000.00 100,000.00 0.015 - - - - - -
6 Lampu PLC 18 Watt dengan fitting gantung 8.00 bh 75,000.00 600,000.00 0.092 - - - - - -
7 Lampu PLC 7 Watt dengan fitting gantung 2.00 bh 65,000.00 130,000.00 0.020 - - - - - -
8 Penyambungan kabel 1.00 Ls 500,000.00 500,000.00 0.076 - - - - - -
9 Box MCB + MCB 2.00 bh 250,000.00 500,000.00 0.076 - - - - - -
XIII. PEKERJAAN LAIN-LAIN
1 Pintu Folding gate 6.00 m2 788,049.93 4,728,299.56 0.722 - - - - - -
2 Railling pengaman besi Hollow 40x40 / 40x20 mm, finishing cat 11.48 m2 550,000.00 6,312,240.00 0.964 - - - - - -
167,320,879.74 25.557 17.564 2.996 20.560

Laporan Progres Mingguan ke-13


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PEMBERSIHAN SALURAN
1 Penggalian Tanah Lumpur dan Endapan Limbah Sedalam 30 cm 69.70 m3 109,311.98 7,619,044.68 1.164 58.766 0.981 6.970 0.116 65.736 1.098
2 Pembersihan dan Pembuangan Tanah Lumpur dan Limbah Keluar Area 90.90 m3 29,796.55 2,708,506.67 0.414 75.732 0.345 9.090 0.041 84.822 0.386
3 Pemadatan Tanah Eksisting 69.70 m3 49,023.50 3,416,937.98 0.522 59.245 0.444 - - 59.245 0.444
4 Pengurugan dengan pasir urug, 10 cm 21.87 m3 178,388.92 3,901,365.68 0.596 18.544 0.505 - - 18.544 0.505
Pengurugan dengan pasir urug, 10 cm 1.36 m3 173,624.00 236,128.64 0.036 1.156 0.031 - - 1.156 0.031
5 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 10.93 m3 737,396.00 8,059,738.25 1.231 8.744 0.985 - - 8.744 0.985
Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.68 m3 723,713.11 492,124.91 0.075 0.544 0.060 - - 0.544 0.060
6 Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 23.23 m3 872,242.00 20,262,181.60 3.095 18.515 2.467 - - 18.515 2.467
a Jaring Kawat baja/Wire Mesh M5 1 lapis 375.85 kg 10,697.66 4,020,713.73 0.614 300.680 0.491 - - 300.680 0.491
7 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 133.20 m 77,312.85 10,298,072.12 1.573 99.900 1.180 6.660 0.079 106.560 1.258
8 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 718.80 m 86,676.29 62,302,919.11 9.516 287.235 3.803 215.640 2.855 502.875 6.658
9 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,2m, K.300 - bh 626,150.00 - - - - - - - -
10 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,8m, K.300 - bh 750,000.00 - - - - - - - -
11 Pekerjaan Plat Beton tebal 15 cm - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 8.37 m3 872,242.00 7,300,665.52 1.115 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis 608.09 kg 10,697.66 6,505,137.18 0.994 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 13.95 m2 316,861.88 4,420,223.25 0.675 - - - - - -
d Pembongkaran 1 M2 Bekisting 13.95 m2 15,645.80 218,258.88 0.033 - - - - - -
12 Pekerjaan Plat Beton tebal 10 cm - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 17.65 m3 872,242.00 15,395,071.25 2.351 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 1 lapis 962.04 kg 10,697.66 10,291,572.26 1.572 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 44.14 m2 316,861.88 13,986,283.46 2.136 - - - - - -
d Pembongkaran 1 M2 Bekisting 44.14 m2 15,645.80 690,605.52 0.105 - - - - - -
182,125,550.71 27.818 11.291 3.091 14.382
B PEKERJAAN JARINGAN IPAL KOMUNAL
1 Pekerjaan Galian Tanah Pipa 46.07 m3 67,972.30 3,131,483.87 0.478 - - - - - -
2 Pengurugan dengan pasir urug 11.51 m3 178,388.92 2,053,256.47 0.314 - - - - - -
3 Pengurugan Kembali 1 M3 Galian Tanah 30.54 m3 49,023.50 1,497,264.55 0.229 - - - - - -
4 Pemasangan 1 M Pipa PVC tipe AW 4 - m 90,907.55 - -
5 Saluran Pipa Air Limbah SDR - 41, Dia 15 cm , inc. fitting & Assecories - m 133,200.00 - - - - - - - -
6 Saluran Pipa Air Limbah SDR - 41, Dia 20 cm, , inc. fitting & Assecories - m 203,900.00 - - - - - - - -
7 Pemasangan Clean Out Inc. Fitting & Assecories 43.00 ttk 185,000.00 7,955,000.00 1.215 - - - - - -
8 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 100 org, 20 m3 / hari, - unit 7,500,000.00 - - - - - - - -
(Galian, Urugan, Pondasi, Tutup Beton, Penyambungan Instalasi)
9 Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm - unit 975,000.00 - - - - - - - -
10 Pekerjaan Sumur Resapan, Dia 100 cm, Kedalaman 2 m, Inc. Tutup Beton Berlubang - ttk 500,000.00 - - - - - - - -
11 Grill Beton Penutup Sumur Resapan - unit 750,000.00 - - - - - - - -
12 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 13.49 m3 688,832.33 9,292,348.18 1.419 - - 1.484 0.156 1.484 0.156
13 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area 13.49 m3 19,888.18 268,291.48 0.041 - - 1.484 0.005 1.484 0.005
14 Pemasangan 1 M Pipa PVC tipe D 6 375.05 m 133,200.00 49,956,660.00 7.630 - - 69.637 1.417 69.637 1.417
14 Pemasangan 1 M Pipa PVC tipe D 4 64.50 m 85,618.17 5,522,372.20 0.844 - - - - - -
15 Pekerjaan Sumur Resapan kedalaman 4 Buis Beton Dia 80 cm 15.00 ttk 474,124.46 7,111,866.88 1.086 13.000 0.941 - - 13.000 0.941
16 Pasang Grill Besi Penutup Sumur Resapan 15.00 unit 826,875.00 12,403,125.00 1.894 - - - - - -

Laporan Progres Mingguan ke-13


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
C PEKERJAAN PEMASANGAN DAN PENGADAAN INSTALASI IPAL
1 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 50 org, 10 m3 / hari
a Pengadaan Unit IPAL kap 50 org, 10 m3 / hari 1.00 unit 110,250,000.00 110,250,000.00 16.840 - - - - - -
b Galian Tanah 57.21 m3 67,972.30 3,888,695.29 0.594 37.187 0.386 - - 37.187 0.386
c Pengurugan Kembali 1 M3 Galian Tanah 2.39 m3 49,023.50 117,166.17 0.018 - - 1.315 0.010 1.315 0.010
d Pengurugan dengan pasir urug 1.83 m3 178,388.92 326,254.80 0.050 - - - - - -
e Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Dinding, Lantai dan Tutup 11.77 m3 872,242.00 10,266,288.31 1.568 - - 7.286 0.971 7.286 0.971
Jaring Kawat baja/Wire Mesh M8 713.69 kg 10,697.66 7,634,809.58 1.166 - - 441.766 0.722 441.766 0.722
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 30.14 m2 316,861.88 9,550,217.12 1.459 - - 18.656 0.903 18.656 0.903
Pembongkaran 1 M2 Bekisting 30.14 m2 15,645.80 471,564.35 0.072 - - - - - -
f Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Inlet 0.30 m3 872,242.00 261,672.60 0.040 - - - - - -
Jaring Kawat baja/Wire Mesh M8 11.06 kg 10,697.66 118,316.07 0.018 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.66 m2 316,861.88 209,128.84 0.032 - - - - - -
Pembongkaran 1 M2 Bekisting 0.66 m2 15,645.80 10,326.23 0.002 - - - - - -
g Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Outlet 0.41 m3 872,242.00 357,619.22 0.055 - - - - - -
Jaring Kawat baja/Wire Mesh M8 14.98 kg 10,697.66 160,250.88 0.024 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.96 m2 316,861.88 304,187.41 0.046 - - - - - -
Pembongkaran 1 M2 Bekisting 0.96 m2 15,645.80 15,019.97 0.002 - - - - - -
h Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Kolom 15 x 15 cm 0.47 m3 872,242.00 409,953.74 0.063 - - 0.470 0.063 0.470 0.063
Pembesian dg Besi Polos atau Besi Ulir 119.39 kg 11,860.70 1,416,048.75 0.216 - - 119.390 0.216 119.390 0.216
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.44 m2 316,861.88 456,281.11 0.070 - - 1.440 0.070 1.440 0.070
Pembongkaran 1 M2 Bekisting 1.44 m2 15,645.80 22,529.95 0.003 - - - - - -
i Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Balok 15 x 20 cm 0.12 m3 872,242.00 104,669.04 0.016 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 23.91 kg 11,860.70 283,589.29 0.043 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.55 m2 316,861.88 174,274.03 0.027 - - - - - -
Pembongkaran 1 M2 Bekisting 0.55 m2 15,645.80 8,605.19 0.001 - - - - - -
j Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, pondasi 60 x 60 x 20 cm 0.72 m3 872,242.00 628,014.24 0.096 - - 0.576 0.077 0.576 0.077
Pembesian dg Besi Polos atau Besi Ulir 36.93 kg 11,860.70 438,015.58 0.067 - - 29.544 0.054 29.544 0.054
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.20 m2 316,861.88 380,234.26 0.058 - - 0.960 0.046 0.960 0.046
Pembongkaran 1 M2 Bekisting 1.20 m2 15,645.80 18,774.96 0.003 - - 0.960 0.002 0.960 0.002
k Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm 4.00 unit 975,000.00 3,900,000.00 0.596 - - - - - -

251,374,175.57 38.395 1.328 4.710 6.038

JUMLAH 654,697,105.06 654,697,105.06 100.000 31.453 10.852 42.305


PRESTASI MINGGU LALU 31.453
PRESTASI MINGGU INI 10.852
PRESTASI SAMPAI DENGAN MINGGU INI 42.305
PRESTASI MENURUT SCHEDULE 45.777
LEBIH CEPAT (+) / TERLAMBAT (-) (3.472)

Yogyakarta, 23 Agustus 2021


di buat oleh,
KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA

Noor Hasan Bambang Erlianto


Pengawas Pelaksana

Laporan Progres Mingguan ke-13


REKAPITULASI
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : XIII ( Tiga belas )


Periode : 16 Agustus 2021 sampai dengan 22 Agustus 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
ADDENDUM II : 050 / 1909 / VII / 2021, TANGGAL 19 JULI 2021
NILAI KONTRAK ADDENDUM II : Rp 720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO PEKERJAAN PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp (%) BOBOT % BOBOT % BOBOT %

I PEKERJAAN PERSIAPAN 11,873,371.04 1.814 1.270 0.054 1.325

II PEKERJAAN PERBAIKAN TALUD SEGMEN 5


A PEKERJAAN TANAH DAN BETON BERTULANG 34,726,084.58 5.304 - - -
B PEKERJAAN PASANGAN DINDING 6,878,419.61 1.051 - - -

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PENGECATAN 398,623.81 0.061 - - -
B PEKERJAAN RUMAH TERDAMPAK 167,320,879.74 25.557 17.564 2.996 20.560

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PEMBERSIHAN SALURAN 182,125,550.71 27.818 11.291 3.091 14.382
B PEKERJAAN JARINGAN IPAL KOMUNAL 251,374,175.57 38.395 1.328 4.710 6.038

JUMLAH 654,697,105.06 100.000 31.453 10.852 42.305


PRESTASI MINGGU LALU 654,697,105.06 31.453
PRESTASI MINGGU INI 10.852
PRESTASI SAMPAI DENGAN MINGGU INI 42.305
PRESTASI MENURUT SCHEDULE 45.777
LEBIH CEPAT (+) / TERLAMBAT (-) (3.472)

Yogyakarta, 23 Agustus 2021


di buat oleh,
PEJABAT PEMBUAT KOMITMEN TIM TEKNIS KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA
1. Cicilia Novi hendrawati, M.SC., M.Eng.
NIP. 19781102 200501 2 011 ...........................

2. Danang Dwi Wahyujati,S.Kom.,M.Eng


NIP. 19761028 199803 1 004 ...........................

SIGIT SETIAWAN, ST.MT 3. Sudaryanto RISMAN WARCHAN ZULIANTO


NIP. 19690605 199303 1 007
NIP. 19770623 200501 1 013 ........................... Tim Leader Direktur
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : XIV ( Empat belas )


Periode : 23 Agustus 2021 sampai dengan 29 Agustus 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
ADDENDUM II : 050 / 1909 / VII / 2021, TANGGAL 19 JULI 2021
NILAI KONTRAK ADDENDUM II : Rp 720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
I PEKERJAAN PERSIAPAN
1 Pembuatan Papan Nama Pekerjaan 1.00 bh 250,000.00 250,000.00 0.038 1.000 0.038 - - 1.000 0.038
2 Pengukuran dan Pemasangan Bouwplank 28.56 m 12,198.91 348,400.73 0.053 28.560 0.053 - - 28.560 0.053
3 Pembuatan bedeng pekerja 9.00 m2 383,330.04 3,449,970.32 0.527 9.000 0.527 - - 9.000 0.527
4 Mobilisasi Demobilisasi Alat Berat 1.00 ls 2,500,000.00 2,500,000.00 0.382 0.591 0.226 0.045 0.017 0.636 0.243
5 Pembuatan akses menuju badan sungai sementara - m2 113,128.49 - - - - - - - -
6 Dewatering dengan pompa air diesel 40.00 jam 25,000.00 1,000,000.00 0.153 23.636 0.090 1.818 0.007 25.455 0.097
7 SMKK 1.00 ls 4,325,000.00 4,325,000.00 0.661 0.591 0.390 0.045 0.030 0.636 0.420
11,873,371.04 1.814 1.325 0.054 1.379
II PEKERJAAN PERBAIKAN TALUD SEGMEN 5
A PEKERJAAN TANAH DAN BETON BERTULANG
1 Penggalian 1 M3 Tanah Biasa 13.50 m3 67,972.30 917,626.05 0.140 - - - - - -
2 Pengurugan Kembali 1 M3 Galian Tanah 6.41 m3 49,023.50 314,240.64 0.048 - - - - - -
3 Bongkaran Pasangan Batu dan Beton Eksisting 7.92 m3 71,953.20 569,869.35 0.087 - - - - - -
4 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area 7.92 m3 19,888.18 157,514.35 0.024 - - - - - -
5 Pemadatan Tanah Eksisting 6.41 m3 49,023.50 314,240.64 0.048 - - - - - -
6 Pengurugan dengan pasir urug 0.27 m3 178,388.92 48,165.01 0.007 - - - - - -
7 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.27 m3 737,396.00 199,096.92 0.030 - - - - - -
8 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 1.08 m3 872,242.00 942,021.36 0.144 - - - - - -
a Pembesian dg Besi Polos atau Besi Ulir 156.69 kg 11,860.70 1,858,452.79 0.284 - - - - - -
b Bekisting untuk pondasi beton ( dipakai 2 kali ) 1.92 m2 89,375.55 171,601.05 0.026 - - - - - -
c Pembongkaran 1 M2 Bekisting 1.92 m2 15,645.80 30,039.93 0.005 - - - - - -
9 Pekerjaan Beton Dinding Talud Beton
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 2.16 m3 872,242.00 1,884,042.71 0.288 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 1,026.67 kg 11,860.70 12,177,022.97 1.860 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 9.02 m2 316,861.88 2,858,094.17 0.437 - - - - - -
d Pembongkaran 1 M2 Bekisting 9.02 m2 15,645.80 141,125.10 0.022 - - - - - -
10 Pekerjaan Beton Sloof 20x30cm
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 0.49 m3 872,242.00 427,398.58 0.065 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 147.55 kg 11,860.70 1,750,046.01 0.267 - - - - - -
c Memasang Bekisting untuk Sloof (dipakai 2 kali) 2.46 m2 89,375.55 219,863.84 0.034 - - - - - -
d Pembongkaran 1 M2 Bekisting 2.46 m2 15,645.80 38,488.66 0.006 - - - - - -
11 Pekerjaan Beton Konsul Cantilever
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 0.09 m3 872,242.00 78,501.78 0.012 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 47.58 kg 11,860.70 564,332.02 0.086 - - - - - -
c Memasang Bekisting untuk Balok (dipakai 2 kali) 0.45 m2 120,181.13 54,081.51 0.008 - - - - - -
d Pembongkaran 1 M2 Bekisting 0.45 m2 15,645.80 7,040.61 0.001 - - - - - -
12 Pekerjaan Plat Beton tebal 12 cm
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 2.70 m3 872,242.00 2,355,053.39 0.360 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis 294.23 kg 10,697.66 3,147,571.10 0.481 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.35 m2 316,861.88 427,763.54 0.065 - - - - - -
d Pembongkaran 1 M2 Bekisting 1.35 m2 15,645.80 21,121.83 0.003 - - - - - -
13 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 4.50 m 77,312.85 347,907.84 0.053 - - - - - -
14 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 8.67 m 86,676.29 751,483.46 0.115 - - - - - -
15 Memasang Stek Besi 23.67 kg 11,860.70 280,742.73 0.043 - - - - - -
16 Pekerjaan Plat Beton Pot tebal 10 cm
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 0.49 m3 872,242.00 427,398.58 0.065 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 23.67 kg 11,860.70 280,742.73 0.043 - - - - - -
c Bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm 7.20 m2 118,158.83 850,743.59 0.130 - - - - - -
d Pembongkaran 1 M2 Bekisting 7.20 m2 15,645.80 112,649.75 0.017 - - - - - -
34,726,084.58 5.304 - - -
B PEKERJAAN PASANGAN DINDING
1 Pemasangan Dinding Bata Merah Bakar Sekam Tebal 1/2 Bata Camp. 1SP 6PP 9.97 m2 116,576.48 1,162,267.55 0.178 - - - - - -
2 Pemasangan Plesteran 1 Pc 6 Pp Tebal 15 mm 34.11 m2 54,689.70 1,865,465.63 0.285 - - - - - -
3 Pemasangan Acian 34.11 m2 33,411.23 1,139,657.03 0.174 - - - - - -
4 Pemasangan Plesteran Skoning 1 Pc 2Pp lebar 10 cm 46.50 m 55,075.90 2,561,029.40 0.391 - - - - - -
5 Pemasangan Kepala Kolom 3.00 bh 50,000.00 150,000.00 0.023 - - - - - -
Laporan Progres Mingguan ke-14
HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
6,878,419.61 1.051 - - -

Laporan Progres Mingguan ke-14


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PENGECATAN
1 Pengecatan Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Weathershield luar ruangan 34.11 m2 11,686.42 398,623.81 0.061 - - - - - -
398,623.81 0.061 - - -
B PEKERJAAN RUMAH TERDAMPAK
I. PEKERJAAN BONGKARAN
1 Membongkar 1 m2 genteng / sirap untuk dipergunakan lagi 77.17 m2 3,628.42 280,005.33 0.043 38.585 0.021 - - 38.585 0.021
2 Membongkar 1 m3 kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi 0.37 m3 991,595.91 366,890.49 0.056 0.185 0.028 - - 0.185 0.028
3 Pembongkaran 1 m3 pasangan bata merah dan membersihkan 12.72 m3 185,908.38 2,364,754.54 0.361 8.093 0.230 - - 8.093 0.230
4 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 1.50 m3 688,832.33 1,033,248.50 0.158 0.858 0.090 - - 0.858 0.090
II. PEKERJAAN TANAH
1 Menggali 1 m3 tanah biasa sedalam 1 meter 27.22 m3 67,972.30 1,850,206.01 0.283 27.220 0.283 - - 27.220 0.283
2 Pengurugan Kembali 1 m3 Galian Tanah 10.11 m3 18,745.83 189,520.38 0.029 10.110 0.029 - - 10.110 0.029
3 Pengurugan dengan pasir urug 1.82 m3 173,624.00 315,995.68 0.048 1.820 0.048 - - 1.820 0.048
4 Peninggian peil lantai 9.18 m3 18,745.83 172,086.75 0.026 - - 8.262 0.024 8.262 0.024
III. PEKERJAAN PONDASI
1 Memasang 1 m3 pondasi batu belah, campuran 1 PC 6 PP 16.49 m2 665,195.09 10,969,067.11 1.675 16.490 1.675 - - 16.490 1.675
IV. PEKERJAAN BETON
1 Membuat 1 m3 Sloof beton bertulang (200 kg besi + bekisting) 1.06 m3 3,844,764.87 4,075,450.77 0.622 1.060 0.622 - - 1.060 0.622
2 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) 2.29 m3 7,083,735.01 16,221,753.18 2.478 2.290 2.478 - - 2.290 2.478
3 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) 3.05 m3 5,659,422.09 17,261,237.38 2.637 3.050 2.637 - - 3.050 2.637
4 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.14 m3 723,713.11 101,319.83 0.015 0.140 0.015 - - 0.140 0.015
5 Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting) 0.57 m3 3,127,107.54 1,782,451.30 0.272 0.570 0.272 - - 0.570 0.272
6 Sloof 150 x 200 dengan beton K 225 Tulangan 105 kg 0.74 m3 3,295,166.46 2,438,423.18 0.372 0.740 0.372 - - 0.740 0.372
7 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm 67.35 m' 77,312.85 5,207,020.70 0.795 67.350 0.795 - - 67.350 0.795
8 Balok 150 x 200 dengan beton K 225 Tulangan 105 kg 1.01 m3 3,705,897.33 3,742,956.31 0.572 1.010 0.572 - - 1.010 0.572
9 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm 54.15 m' 86,676.29 4,693,521.24 0.717 54.150 0.717 - - 54.150 0.717
10 Membuat 1 m3 Plat Lantai beton bertulang 2.95 m3 3,119,381.73 9,202,176.12 1.406 2.950 1.406 - - 2.950 1.406
11 Membuat 1 m3 Plat Tangga beton bertulang 0.72 m3 3,119,381.73 2,245,954.85 0.343 0.720 0.343 - - 0.720 0.343
12 Membuat 1 m3 Plat Water torn beton bertulang 0.42 m3 3,119,381.73 1,310,140.33 0.200 0.420 0.200 - - 0.420 0.200
V. PEKERJAAN DINDING
1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP 161.84 m2 116,576.48 18,866,738.23 2.882 158.378 2.820 3.462 0.062 161.840 2.882
2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP, trap tangga 6.30 m2 250,668.02 1,579,208.52 0.241 - - 6.300 0.241 6.300 0.241
VI PEKERJAAN KAYU
1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.27 m3 16,443,774.77 4,439,819.19 0.678 0.270 0.678 - - 0.270 0.678
Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.02 m3 8,048,535.00 160,970.70 0.025 0.020 0.025 - - 0.020 0.025
2 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti 12.32 m2 644,715.80 7,942,898.68 1.213 9.856 0.971 2.464 0.243 12.320 1.213
3 Memasang 1 m3 konstruksi gordeng, kayu glugu - m3 4,450,537.65 - - - - - - - -
VII. PEKERJAAN PLESTERAN
1 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm 96.76 m2 54,689.70 5,291,775.27 0.808 96.760 0.808 - - 96.760 0.808
2 Memasang 1 m2 acian 96.76 m2 33,411.23 3,232,870.55 0.494 95.030 0.485 - - 95.030 0.485
3 Pemasangan 1 m2 plesteran ciprat 1SP : 2PP 33.50 m2 45,029.48 1,508,487.73 0.230 33.500 0.230 - - 33.500 0.230
VIII. PEKERJAAN PENGECATAN
1 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 96.76 m2 11,686.42 1,130,778.06 0.173 - - - - - -
IX. PEKERJAAN PENUTUP ATAP
1 Memasang 1 m2 Atap Galvalum (Paket) 78.51 m3 190,000.00 14,917,137.50 2.278 58.883 1.709 15.702 0.456 74.586 2.165
2 Pemasangan 1 m talang datar Galvalum lebar 60 cm 6.00 m' 105,483.99 632,903.97 0.097 - - - - - -
X. PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Memasang 1 m2 lantai keramik (30 x 30) cm - m2 114,193.22 - - - - - - - -
2 Membuat rabat beton lantai mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 2.08 m3 723,713.11 1,504,722.31 0.230 - - - - - -
3 Memasang 1 m2 lantai keramik (20 x 20) cm 4.99 m2 184,674.28 921,524.65 0.141 - - - - - -
XI. PEKERJAAN SANITASI - - - - -
1 Memasang 1 buah Kloset Jongkok Porselen 2.00 bh 280,952.58 561,905.16 0.086 - - - - - -
2 Memasang 1 m Pipa PVC tipe AW 16.00 m' 19,406.20 310,499.27 0.047 - - 8.000 0.024 8.000 0.024
3 Memasang 1 m Pipa PVC tipe AW 1 8.00 m' 22,254.33 178,034.63 0.027 - - 4.000 0.014 4.000 0.014
4 Memasang 1 m Pipa PVC tipe AW 3 18.00 m' 63,036.61 1,134,659.00 0.173 - - 16.000 0.154 16.000 0.154
5 Memasang 1 buah Kran atau 2.00 bh 46,068.18 92,136.37 0.014 - - - - - -
6 Memasang 1 buah Floor Drain 2.00 bh 80,836.18 161,672.35 0.025 - - - - - -
7 Memasang 1 buah Pintu Kamar Mandi 2.00 bh 650,000.00 1,300,000.00 0.199 - - 1.000 0.099 1.000 0.099
8 Pemasangan 1 M Pipa PVC tipe D 4 12.00 m 85,618.17 1,027,418.08 0.157 - - 10.000 0.131 10.000 0.131
XII. PEKERJAAN ELEKTRIKAL
1 Instalasi Penerangan menggunakan kabel NYY 3x2,5mm² dalam pipa conduit Ø 20mm. 10.00 titik 105,000.00 1,050,000.00 0.160 - - 5.000 0.080 5.000 0.080
2 Instalasi stop kontak dinding, menggunakan kabel NYM 3x2,5mm² 5.00 titik 100,000.00 500,000.00 0.076 - - 3.000 0.046 3.000 0.046
3 Saklar tunggal inbow, 1 gang 1 way 4.00 bh 20,000.00 80,000.00 0.012 - - - - - -
4 Saklar seri inbow, 1 gang 2 way 4.00 bh 25,000.00 100,000.00 0.015 - - - - - -
5 Stop kontak wall type 1ph, 16A, 1 gang 5.00 bh 20,000.00 100,000.00 0.015 - - - - - -
6 Lampu PLC 18 Watt dengan fitting gantung 8.00 bh 75,000.00 600,000.00 0.092 - - - - - -
7 Lampu PLC 7 Watt dengan fitting gantung 2.00 bh 65,000.00 130,000.00 0.020 - - - - - -
8 Penyambungan kabel 1.00 Ls 500,000.00 500,000.00 0.076 - - - - - -
9 Box MCB + MCB 2.00 bh 250,000.00 500,000.00 0.076 - - - - - -
XIII. PEKERJAAN LAIN-LAIN
1 Pintu Folding gate 6.00 m2 788,049.93 4,728,299.56 0.722 - - - - - -
2 Railling pengaman besi Hollow 40x40 / 40x20 mm, finishing cat 11.48 m2 550,000.00 6,312,240.00 0.964 - - - - - -
167,320,879.74 25.557 20.560 1.572 22.133

Laporan Progres Mingguan ke-14


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PEMBERSIHAN SALURAN
1 Penggalian Tanah Lumpur dan Endapan Limbah Sedalam 30 cm 69.70 m3 109,311.98 7,619,044.68 1.164 65.736 1.098 - - 65.736 1.098
2 Pembersihan dan Pembuangan Tanah Lumpur dan Limbah Keluar Area 90.90 m3 29,796.55 2,708,506.67 0.414 84.822 0.386 - - 84.822 0.386
3 Pemadatan Tanah Eksisting 69.70 m3 49,023.50 3,416,937.98 0.522 59.245 0.444 - - 59.245 0.444
4 Pengurugan dengan pasir urug, 10 cm 21.87 m3 178,388.92 3,901,365.68 0.596 18.544 0.505 - - 18.544 0.505
Pengurugan dengan pasir urug, 10 cm 1.36 m3 173,624.00 236,128.64 0.036 1.156 0.031 - - 1.156 0.031
5 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 10.93 m3 737,396.00 8,059,738.25 1.231 8.744 0.985 - - 8.744 0.985
Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.68 m3 723,713.11 492,124.91 0.075 0.544 0.060 - - 0.544 0.060
6 Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 23.23 m3 872,242.00 20,262,181.60 3.095 18.515 2.467 - - 18.515 2.467
a Jaring Kawat baja/Wire Mesh M5 1 lapis 375.85 kg 10,697.66 4,020,713.73 0.614 300.680 0.491 - - 300.680 0.491
7 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 133.20 m 77,312.85 10,298,072.12 1.573 106.560 1.258 - - 106.560 1.258
8 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 718.80 m 86,676.29 62,302,919.11 9.516 502.875 6.658 34.974 0.463 537.849 7.121
9 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,2m, K.300 - bh 626,150.00 - - - - - - - -
10 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,8m, K.300 - bh 750,000.00 - - - - - - - -
11 Pekerjaan Plat Beton tebal 15 cm - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 8.37 m3 872,242.00 7,300,665.52 1.115 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis 608.09 kg 10,697.66 6,505,137.18 0.994 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 13.95 m2 316,861.88 4,420,223.25 0.675 - - - - - -
d Pembongkaran 1 M2 Bekisting 13.95 m2 15,645.80 218,258.88 0.033 - - - - - -
12 Pekerjaan Plat Beton tebal 10 cm - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 17.65 m3 872,242.00 15,395,071.25 2.351 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 1 lapis 962.04 kg 10,697.66 10,291,572.26 1.572 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 44.14 m2 316,861.88 13,986,283.46 2.136 - - - - - -
d Pembongkaran 1 M2 Bekisting 44.14 m2 15,645.80 690,605.52 0.105 - - - - - -
182,125,550.71 27.818 14.382 0.463 14.845
B PEKERJAAN JARINGAN IPAL KOMUNAL
1 Pekerjaan Galian Tanah Pipa 46.07 m3 67,972.30 3,131,483.87 0.478 - - - - - -
2 Pengurugan dengan pasir urug 11.51 m3 178,388.92 2,053,256.47 0.314 - - - - - -
3 Pengurugan Kembali 1 M3 Galian Tanah 30.54 m3 49,023.50 1,497,264.55 0.229 - - - - - -
4 Pemasangan 1 M Pipa PVC tipe AW 4 - m 90,907.55 - -
5 Saluran Pipa Air Limbah SDR - 41, Dia 15 cm , inc. fitting & Assecories - m 133,200.00 - - - - - - - -
6 Saluran Pipa Air Limbah SDR - 41, Dia 20 cm, , inc. fitting & Assecories - m 203,900.00 - - - - - - - -
7 Pemasangan Clean Out Inc. Fitting & Assecories 43.00 ttk 185,000.00 7,955,000.00 1.215 - - 21.500 0.608 21.500 0.608
8 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 100 org, 20 m3 / hari, - unit 7,500,000.00 - - - - - - - -
(Galian, Urugan, Pondasi, Tutup Beton, Penyambungan Instalasi)
9 Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm - unit 975,000.00 - - - - - - - -
10 Pekerjaan Sumur Resapan, Dia 100 cm, Kedalaman 2 m, Inc. Tutup Beton Berlubang - ttk 500,000.00 - - - - - - - -
11 Grill Beton Penutup Sumur Resapan - unit 750,000.00 - - - - - - - -
12 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 13.49 m3 688,832.33 9,292,348.18 1.419 1.484 0.156 - - 1.484 0.156
13 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area 13.49 m3 19,888.18 268,291.48 0.041 1.484 0.005 - - 1.484 0.005
14 Pemasangan 1 M Pipa PVC tipe D 6 375.05 m 133,200.00 49,956,660.00 7.630 69.637 1.417 150.020 3.052 219.657 4.469
14 Pemasangan 1 M Pipa PVC tipe D 4 64.50 m 85,618.17 5,522,372.20 0.844 - - 25.800 0.337 25.800 0.337
15 Pekerjaan Sumur Resapan kedalaman 4 Buis Beton Dia 80 cm 15.00 ttk 474,124.46 7,111,866.88 1.086 13.000 0.941 - - 13.000 0.941
16 Pasang Grill Besi Penutup Sumur Resapan 15.00 unit 826,875.00 12,403,125.00 1.894 - - 5.250 0.663 5.250 0.663

Laporan Progres Mingguan ke-14


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
C PEKERJAAN PEMASANGAN DAN PENGADAAN INSTALASI IPAL
1 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 50 org, 10 m3 / hari
a Pengadaan Unit IPAL kap 50 org, 10 m3 / hari 1.00 unit 110,250,000.00 110,250,000.00 16.840 - - 0.350 5.894 0.350 5.894
b Galian Tanah 57.21 m3 67,972.30 3,888,695.29 0.594 37.187 0.386 2.689 0.028 39.875 0.414
c Pengurugan Kembali 1 M3 Galian Tanah 2.39 m3 49,023.50 117,166.17 0.018 1.315 0.010 0.215 0.002 1.530 0.011
d Pengurugan dengan pasir urug 1.83 m3 178,388.92 326,254.80 0.050 - - - - - -
e Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Dinding, Lantai dan Tutup 11.77 m3 872,242.00 10,266,288.31 1.568 7.286 0.971 1.412 0.188 8.698 1.159
Jaring Kawat baja/Wire Mesh M8 713.69 kg 10,697.66 7,634,809.58 1.166 441.766 0.722 85.643 0.140 527.409 0.862
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 30.14 m2 316,861.88 9,550,217.12 1.459 18.656 0.903 3.617 0.175 22.273 1.078
Pembongkaran 1 M2 Bekisting 30.14 m2 15,645.80 471,564.35 0.072 - - - - - -
f Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Inlet 0.30 m3 872,242.00 261,672.60 0.040 - - - - - -
Jaring Kawat baja/Wire Mesh M8 11.06 kg 10,697.66 118,316.07 0.018 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.66 m2 316,861.88 209,128.84 0.032 - - - - - -
Pembongkaran 1 M2 Bekisting 0.66 m2 15,645.80 10,326.23 0.002 - - - - - -
g Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Outlet 0.41 m3 872,242.00 357,619.22 0.055 - - - - - -
Jaring Kawat baja/Wire Mesh M8 14.98 kg 10,697.66 160,250.88 0.024 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.96 m2 316,861.88 304,187.41 0.046 - - - - - -
Pembongkaran 1 M2 Bekisting 0.96 m2 15,645.80 15,019.97 0.002 - - - - - -
h Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Kolom 15 x 15 cm 0.47 m3 872,242.00 409,953.74 0.063 0.470 0.063 - - 0.470 0.063
Pembesian dg Besi Polos atau Besi Ulir 119.39 kg 11,860.70 1,416,048.75 0.216 119.390 0.216 - - 119.390 0.216
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.44 m2 316,861.88 456,281.11 0.070 1.440 0.070 - - 1.440 0.070
Pembongkaran 1 M2 Bekisting 1.44 m2 15,645.80 22,529.95 0.003 - - - - - -
i Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Balok 15 x 20 cm 0.12 m3 872,242.00 104,669.04 0.016 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 23.91 kg 11,860.70 283,589.29 0.043 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.55 m2 316,861.88 174,274.03 0.027 - - - - - -
Pembongkaran 1 M2 Bekisting 0.55 m2 15,645.80 8,605.19 0.001 - - - - - -
j Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, pondasi 60 x 60 x 20 cm 0.72 m3 872,242.00 628,014.24 0.096 0.576 0.077 - - 0.576 0.077
Pembesian dg Besi Polos atau Besi Ulir 36.93 kg 11,860.70 438,015.58 0.067 29.544 0.054 - - 29.544 0.054
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.20 m2 316,861.88 380,234.26 0.058 0.960 0.046 - - 0.960 0.046
Pembongkaran 1 M2 Bekisting 1.20 m2 15,645.80 18,774.96 0.003 0.960 0.002 - - 0.960 0.002
k Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm 4.00 unit 975,000.00 3,900,000.00 0.596 - - - - - -

251,374,175.57 38.395 6.038 11.087 17.125

JUMLAH 654,697,105.06 654,697,105.06 100.000 42.305 13.176 55.481


PRESTASI MINGGU LALU 42.305
PRESTASI MINGGU INI 13.176
PRESTASI SAMPAI DENGAN MINGGU INI 55.481
PRESTASI MENURUT SCHEDULE 57.632
LEBIH CEPAT (+) / TERLAMBAT (-) (2.151)

Yogyakarta, 30 Agustus 2021


di buat oleh,
KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA

Noor Hasan Bambang Erlianto


Pengawas Pelaksana

Laporan Progres Mingguan ke-14


REKAPITULASI
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : XIV ( Empat belas )


Periode : 23 Agustus 2021 sampai dengan 29 Agustus 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
ADDENDUM II : 050 / 1909 / VII / 2021, TANGGAL 19 JULI 2021
NILAI KONTRAK ADDENDUM II : Rp 720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO PEKERJAAN PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp (%) BOBOT % BOBOT % BOBOT %

I PEKERJAAN PERSIAPAN 11,873,371.04 1.814 1.325 0.054 1.379

II PEKERJAAN PERBAIKAN TALUD SEGMEN 5


A PEKERJAAN TANAH DAN BETON BERTULANG 34,726,084.58 5.304 - - -
B PEKERJAAN PASANGAN DINDING 6,878,419.61 1.051 - - -

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PENGECATAN 398,623.81 0.061 - - -
B PEKERJAAN RUMAH TERDAMPAK 167,320,879.74 25.557 20.560 1.572 22.133

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PEMBERSIHAN SALURAN 182,125,550.71 27.818 14.382 0.463 14.845
B PEKERJAAN JARINGAN IPAL KOMUNAL 251,374,175.57 38.395 6.038 11.087 17.125

JUMLAH 654,697,105.06 100.000 42.305 13.176 55.481


PRESTASI MINGGU LALU 654,697,105.06 42.305
PRESTASI MINGGU INI 13.176
PRESTASI SAMPAI DENGAN MINGGU INI 55.481
PRESTASI MENURUT SCHEDULE 57.632
LEBIH CEPAT (+) / TERLAMBAT (-) (2.151)

Yogyakarta, 30 Agustus 2021


di buat oleh,
PEJABAT PEMBUAT KOMITMEN TIM TEKNIS KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA
1. Cicilia Novi hendrawati, M.SC., M.Eng.
NIP. 19781102 200501 2 011 ...........................

2. Danang Dwi Wahyujati,S.Kom.,M.Eng


NIP. 19761028 199803 1 004 ...........................
SIGIT SETIAWAN, ST.MT 3. Sudaryanto
NIP. 19690605 199303 1 007 RISMAN WARCHAN ZULIANTO
NIP. 19770623 200501 1 013 ........................... Tim Leader Direktur
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : XV ( Lima belas )


Periode : 30 Agustus 2021 sampai dengan 05 September 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
ADDENDUM II : 050 / 1909 / VII / 2021, TANGGAL 19 JULI 2021
NILAI KONTRAK ADDENDUM II : Rp 720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
I PEKERJAAN PERSIAPAN
1 Pembuatan Papan Nama Pekerjaan 1.00 bh 250,000.00 250,000.00 0.038 1.000 0.038 - - 1.000 0.038
2 Pengukuran dan Pemasangan Bouwplank 28.56 m 12,198.91 348,400.73 0.053 28.560 0.053 - - 28.560 0.053
3 Pembuatan bedeng pekerja 9.00 m2 383,330.04 3,449,970.32 0.527 9.000 0.527 - - 9.000 0.527
4 Mobilisasi Demobilisasi Alat Berat 1.00 ls 2,500,000.00 2,500,000.00 0.382 0.636 0.243 0.045 0.017 0.682 0.260
5 Pembuatan akses menuju badan sungai sementara - m2 113,128.49 - - - - - - - -
6 Dewatering dengan pompa air diesel 40.00 jam 25,000.00 1,000,000.00 0.153 25.455 0.097 1.818 0.007 27.273 0.104
7 SMKK 1.00 ls 4,325,000.00 4,325,000.00 0.661 0.636 0.420 0.045 0.030 0.682 0.450
11,873,371.04 1.814 1.379 0.054 1.433
II PEKERJAAN PERBAIKAN TALUD SEGMEN 5
A PEKERJAAN TANAH DAN BETON BERTULANG
1 Penggalian 1 M3 Tanah Biasa 13.50 m3 67,972.30 917,626.05 0.140 - - - - - -
2 Pengurugan Kembali 1 M3 Galian Tanah 6.41 m3 49,023.50 314,240.64 0.048 - - - - - -
3 Bongkaran Pasangan Batu dan Beton Eksisting 7.92 m3 71,953.20 569,869.35 0.087 - - - - - -
4 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area 7.92 m3 19,888.18 157,514.35 0.024 - - - - - -
5 Pemadatan Tanah Eksisting 6.41 m3 49,023.50 314,240.64 0.048 - - - - - -
6 Pengurugan dengan pasir urug 0.27 m3 178,388.92 48,165.01 0.007 - - - - - -
7 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.27 m3 737,396.00 199,096.92 0.030 - - - - - -
8 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 1.08 m3 872,242.00 942,021.36 0.144 - - - - - -
a Pembesian dg Besi Polos atau Besi Ulir 156.69 kg 11,860.70 1,858,452.79 0.284 - - - - - -
b Bekisting untuk pondasi beton ( dipakai 2 kali ) 1.92 m2 89,375.55 171,601.05 0.026 - - - - - -
c Pembongkaran 1 M2 Bekisting 1.92 m2 15,645.80 30,039.93 0.005 - - - - - -
9 Pekerjaan Beton Dinding Talud Beton
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 2.16 m3 872,242.00 1,884,042.71 0.288 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 1,026.67 kg 11,860.70 12,177,022.97 1.860 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 9.02 m2 316,861.88 2,858,094.17 0.437 - - - - - -
d Pembongkaran 1 M2 Bekisting 9.02 m2 15,645.80 141,125.10 0.022 - - - - - -
10 Pekerjaan Beton Sloof 20x30cm
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 0.49 m3 872,242.00 427,398.58 0.065 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 147.55 kg 11,860.70 1,750,046.01 0.267 - - - - - -
c Memasang Bekisting untuk Sloof (dipakai 2 kali) 2.46 m2 89,375.55 219,863.84 0.034 - - - - - -
d Pembongkaran 1 M2 Bekisting 2.46 m2 15,645.80 38,488.66 0.006 - - - - - -
11 Pekerjaan Beton Konsul Cantilever
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 0.09 m3 872,242.00 78,501.78 0.012 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 47.58 kg 11,860.70 564,332.02 0.086 - - - - - -
c Memasang Bekisting untuk Balok (dipakai 2 kali) 0.45 m2 120,181.13 54,081.51 0.008 - - - - - -
d Pembongkaran 1 M2 Bekisting 0.45 m2 15,645.80 7,040.61 0.001 - - - - - -
12 Pekerjaan Plat Beton tebal 12 cm
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 2.70 m3 872,242.00 2,355,053.39 0.360 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis 294.23 kg 10,697.66 3,147,571.10 0.481 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.35 m2 316,861.88 427,763.54 0.065 - - - - - -
d Pembongkaran 1 M2 Bekisting 1.35 m2 15,645.80 21,121.83 0.003 - - - - - -
13 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 4.50 m 77,312.85 347,907.84 0.053 - - - - - -
14 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 8.67 m 86,676.29 751,483.46 0.115 - - - - - -
15 Memasang Stek Besi 23.67 kg 11,860.70 280,742.73 0.043 - - - - - -
16 Pekerjaan Plat Beton Pot tebal 10 cm
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) 0.49 m3 872,242.00 427,398.58 0.065 - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir 23.67 kg 11,860.70 280,742.73 0.043 - - - - - -
c Bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm 7.20 m2 118,158.83 850,743.59 0.130 - - - - - -
d Pembongkaran 1 M2 Bekisting 7.20 m2 15,645.80 112,649.75 0.017 - - - - - -
34,726,084.58 5.304 - - -
B PEKERJAAN PASANGAN DINDING
1 Pemasangan Dinding Bata Merah Bakar Sekam Tebal 1/2 Bata Camp. 1SP 6PP 9.97 m2 116,576.48 1,162,267.55 0.178 - - - - - -
2 Pemasangan Plesteran 1 Pc 6 Pp Tebal 15 mm 34.11 m2 54,689.70 1,865,465.63 0.285 - - - - - -
3 Pemasangan Acian 34.11 m2 33,411.23 1,139,657.03 0.174 - - - - - -
4 Pemasangan Plesteran Skoning 1 Pc 2Pp lebar 10 cm 46.50 m 55,075.90 2,561,029.40 0.391 - - - - - -
5 Pemasangan Kepala Kolom 3.00 bh 50,000.00 150,000.00 0.023 - - - - - -
Laporan Progres Mingguan ke-15
HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
6,878,419.61 1.051 - - -

Laporan Progres Mingguan ke-15


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PENGECATAN
1 Pengecatan Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Weathershield luar ruangan 34.11 m2 11,686.42 398,623.81 0.061 - - - - - -
398,623.81 0.061 - - -
B PEKERJAAN RUMAH TERDAMPAK
I. PEKERJAAN BONGKARAN
1 Membongkar 1 m2 genteng / sirap untuk dipergunakan lagi 77.17 m2 3,628.42 280,005.33 0.043 38.585 0.021 - - 38.585 0.021
2 Membongkar 1 m3 kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi 0.37 m3 991,595.91 366,890.49 0.056 0.185 0.028 - - 0.185 0.028
3 Pembongkaran 1 m3 pasangan bata merah dan membersihkan 12.72 m3 185,908.38 2,364,754.54 0.361 8.093 0.230 - - 8.093 0.230
4 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 1.50 m3 688,832.33 1,033,248.50 0.158 0.858 0.090 - - 0.858 0.090
II. PEKERJAAN TANAH
1 Menggali 1 m3 tanah biasa sedalam 1 meter 27.22 m3 67,972.30 1,850,206.01 0.283 27.220 0.283 - - 27.220 0.283
2 Pengurugan Kembali 1 m3 Galian Tanah 10.11 m3 18,745.83 189,520.38 0.029 10.110 0.029 - - 10.110 0.029
3 Pengurugan dengan pasir urug 1.82 m3 173,624.00 315,995.68 0.048 1.820 0.048 - - 1.820 0.048
4 Peninggian peil lantai 9.18 m3 18,745.83 172,086.75 0.026 8.262 0.024 0.918 0.003 9.180 0.026
III. PEKERJAAN PONDASI
1 Memasang 1 m3 pondasi batu belah, campuran 1 PC 6 PP 16.49 m2 665,195.09 10,969,067.11 1.675 16.490 1.675 - - 16.490 1.675
IV. PEKERJAAN BETON
1 Membuat 1 m3 Sloof beton bertulang (200 kg besi + bekisting) 1.06 m3 3,844,764.87 4,075,450.77 0.622 1.060 0.622 - - 1.060 0.622
2 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) 2.29 m3 7,083,735.01 16,221,753.18 2.478 2.290 2.478 - - 2.290 2.478
3 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) 3.05 m3 5,659,422.09 17,261,237.38 2.637 3.050 2.637 - - 3.050 2.637
4 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.14 m3 723,713.11 101,319.83 0.015 0.140 0.015 - - 0.140 0.015
5 Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting) 0.57 m3 3,127,107.54 1,782,451.30 0.272 0.570 0.272 - - 0.570 0.272
6 Sloof 150 x 200 dengan beton K 225 Tulangan 105 kg 0.74 m3 3,295,166.46 2,438,423.18 0.372 0.740 0.372 - - 0.740 0.372
7 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm 67.35 m' 77,312.85 5,207,020.70 0.795 67.350 0.795 - - 67.350 0.795
8 Balok 150 x 200 dengan beton K 225 Tulangan 105 kg 1.01 m3 3,705,897.33 3,742,956.31 0.572 1.010 0.572 - - 1.010 0.572
9 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm 54.15 m' 86,676.29 4,693,521.24 0.717 54.150 0.717 - - 54.150 0.717
10 Membuat 1 m3 Plat Lantai beton bertulang 2.95 m3 3,119,381.73 9,202,176.12 1.406 2.950 1.406 - - 2.950 1.406
11 Membuat 1 m3 Plat Tangga beton bertulang 0.72 m3 3,119,381.73 2,245,954.85 0.343 0.720 0.343 - - 0.720 0.343
12 Membuat 1 m3 Plat Water torn beton bertulang 0.42 m3 3,119,381.73 1,310,140.33 0.200 0.420 0.200 - - 0.420 0.200
V. PEKERJAAN DINDING
1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP 161.84 m2 116,576.48 18,866,738.23 2.882 161.840 2.882 - - 161.840 2.882
2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP, trap tangga 6.30 m2 250,668.02 1,579,208.52 0.241 6.300 0.241 - - 6.300 0.241
VI PEKERJAAN KAYU
1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.27 m3 16,443,774.77 4,439,819.19 0.678 0.270 0.678 - - 0.270 0.678
Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.02 m3 8,048,535.00 160,970.70 0.025 0.020 0.025 - - 0.020 0.025
2 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti 12.32 m2 644,715.80 7,942,898.68 1.213 12.320 1.213 - - 12.320 1.213
3 Memasang 1 m3 konstruksi gordeng, kayu glugu - m3 4,450,537.65 - - - - - - - -
VII. PEKERJAAN PLESTERAN
1 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm 96.76 m2 54,689.70 5,291,775.27 0.808 96.760 0.808 - - 96.760 0.808
2 Memasang 1 m2 acian 96.76 m2 33,411.23 3,232,870.55 0.494 95.030 0.485 1.730 0.009 96.760 0.494
3 Pemasangan 1 m2 plesteran ciprat 1SP : 2PP 33.50 m2 45,029.48 1,508,487.73 0.230 33.500 0.230 - - 33.500 0.230
VIII. PEKERJAAN PENGECATAN
1 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 96.76 m2 11,686.42 1,130,778.06 0.173 - - - - - -
IX. PEKERJAAN PENUTUP ATAP
1 Memasang 1 m2 Atap Galvalum (Paket) 78.51 m3 190,000.00 14,917,137.50 2.278 74.586 2.165 - - 74.586 2.165
2 Pemasangan 1 m talang datar Galvalum lebar 60 cm 6.00 m' 105,483.99 632,903.97 0.097 - - - - - -
X. PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Memasang 1 m2 lantai keramik (30 x 30) cm - m2 114,193.22 - - - - - - - -
2 Membuat rabat beton lantai mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 2.08 m3 723,713.11 1,504,722.31 0.230 - - 2.079 0.230 2.079 0.230
3 Memasang 1 m2 lantai keramik (20 x 20) cm 4.99 m2 184,674.28 921,524.65 0.141 - - - - - -
XI. PEKERJAAN SANITASI - - - - -
1 Memasang 1 buah Kloset Jongkok Porselen 2.00 bh 280,952.58 561,905.16 0.086
2 Memasang 1 m Pipa PVC tipe AW 16.00 m' 19,406.20 310,499.27 0.047 8.000 0.024 4.800 0.014 12.800 0.038
3 Memasang 1 m Pipa PVC tipe AW 1 8.00 m' 22,254.33 178,034.63 0.027 4.000 0.014 2.400 0.008 6.400 0.022
4 Memasang 1 m Pipa PVC tipe AW 3 18.00 m' 63,036.61 1,134,659.00 0.173 16.000 0.154 - - 16.000 0.154
5 Memasang 1 buah Kran atau 2.00 bh 46,068.18 92,136.37 0.014 - - - - - -
6 Memasang 1 buah Floor Drain 2.00 bh 80,836.18 161,672.35 0.025 - - - - - -
7 Memasang 1 buah Pintu Kamar Mandi 2.00 bh 650,000.00 1,300,000.00 0.199 1.000 0.099 1.000 0.099 2.000 0.199
8 Pemasangan 1 M Pipa PVC tipe D 4 12.00 m 85,618.17 1,027,418.08 0.157 10.000 0.131 - - 10.000 0.131
XII. PEKERJAAN ELEKTRIKAL
1 Instalasi Penerangan menggunakan kabel NYY 3x2,5mm² dalam pipa conduit Ø 20mm. 10.00 titik 105,000.00 1,050,000.00 0.160 5.000 0.080 5.000 0.080 10.000 0.160
2 Instalasi stop kontak dinding, menggunakan kabel NYM 3x2,5mm² 5.00 titik 100,000.00 500,000.00 0.076 3.000 0.046 2.000 0.031 5.000 0.076
3 Saklar tunggal inbow, 1 gang 1 way 4.00 bh 20,000.00 80,000.00 0.012 - - 4.000 0.012 4.000 0.012
4 Saklar seri inbow, 1 gang 2 way 4.00 bh 25,000.00 100,000.00 0.015 - - 4.000 0.015 4.000 0.015
5 Stop kontak wall type 1ph, 16A, 1 gang 5.00 bh 20,000.00 100,000.00 0.015 - - 5.000 0.015 5.000 0.015
6 Lampu PLC 18 Watt dengan fitting gantung 8.00 bh 75,000.00 600,000.00 0.092 - - 8.000 0.092 8.000 0.092
7 Lampu PLC 7 Watt dengan fitting gantung 2.00 bh 65,000.00 130,000.00 0.020 - - 2.000 0.020 2.000 0.020
8 Penyambungan kabel 1.00 Ls 500,000.00 500,000.00 0.076 - - - - - -
9 Box MCB + MCB 2.00 bh 250,000.00 500,000.00 0.076 - - 2.000 0.076 2.000 0.076
XIII. PEKERJAAN LAIN-LAIN
1 Pintu Folding gate 6.00 m2 788,049.93 4,728,299.56 0.722 - - 6.000 0.722 6.000 0.722
2 Railling pengaman besi Hollow 40x40 / 40x20 mm, finishing cat 11.48 m2 550,000.00 6,312,240.00 0.964 - - - - - -
167,320,879.74 25.557 22.133 1.427 23.559

Laporan Progres Mingguan ke-15


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PEMBERSIHAN SALURAN
1 Penggalian Tanah Lumpur dan Endapan Limbah Sedalam 30 cm 69.70 m3 109,311.98 7,619,044.68 1.164 65.736 1.098 - - 65.736 1.098
2 Pembersihan dan Pembuangan Tanah Lumpur dan Limbah Keluar Area 90.90 m3 29,796.55 2,708,506.67 0.414 84.822 0.386 - - 84.822 0.386
3 Pemadatan Tanah Eksisting 69.70 m3 49,023.50 3,416,937.98 0.522 59.245 0.444 - - 59.245 0.444
4 Pengurugan dengan pasir urug, 10 cm 21.87 m3 178,388.92 3,901,365.68 0.596 18.544 0.505 - - 18.544 0.505
Pengurugan dengan pasir urug, 10 cm 1.36 m3 173,624.00 236,128.64 0.036 1.156 0.031 - - 1.156 0.031
5 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 10.93 m3 737,396.00 8,059,738.25 1.231 8.744 0.985 - - 8.744 0.985
Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.68 m3 723,713.11 492,124.91 0.075 0.544 0.060 - - 0.544 0.060
6 Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 23.23 m3 872,242.00 20,262,181.60 3.095 18.515 2.467 - - 18.515 2.467
a Jaring Kawat baja/Wire Mesh M5 1 lapis 375.85 kg 10,697.66 4,020,713.73 0.614 300.680 0.491 - - 300.680 0.491
7 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 133.20 m 77,312.85 10,298,072.12 1.573 106.560 1.258 - - 106.560 1.258
8 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 718.80 m 86,676.29 62,302,919.11 9.516 537.849 7.121 35.940 0.476 573.789 7.596
9 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,2m, K.300 - bh 626,150.00 - - - - - - - -
10 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,8m, K.300 - bh 750,000.00 - - - - - - - -
11 Pekerjaan Plat Beton tebal 15 cm - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 8.37 m3 872,242.00 7,300,665.52 1.115 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis 608.09 kg 10,697.66 6,505,137.18 0.994 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 13.95 m2 316,861.88 4,420,223.25 0.675 - - 6.975 0.338 6.975 0.338
d Pembongkaran 1 M2 Bekisting 13.95 m2 15,645.80 218,258.88 0.033 - - - - - -
12 Pekerjaan Plat Beton tebal 10 cm - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 17.65 m3 872,242.00 15,395,071.25 2.351 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 1 lapis 962.04 kg 10,697.66 10,291,572.26 1.572 - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 44.14 m2 316,861.88 13,986,283.46 2.136 - - 22.070 1.068 22.070 1.068
d Pembongkaran 1 M2 Bekisting 44.14 m2 15,645.80 690,605.52 0.105 - - - - - -
182,125,550.71 27.818 14.845 1.882 16.727
B PEKERJAAN JARINGAN IPAL KOMUNAL
1 Pekerjaan Galian Tanah Pipa 46.07 m3 67,972.30 3,131,483.87 0.478 - - - - - -
2 Pengurugan dengan pasir urug 11.51 m3 178,388.92 2,053,256.47 0.314 - - - - - -
3 Pengurugan Kembali 1 M3 Galian Tanah 30.54 m3 49,023.50 1,497,264.55 0.229 - - - - - -
4 Pemasangan 1 M Pipa PVC tipe AW 4 - m 90,907.55 - -
5 Saluran Pipa Air Limbah SDR - 41, Dia 15 cm , inc. fitting & Assecories - m 133,200.00 - - - - - - - -
6 Saluran Pipa Air Limbah SDR - 41, Dia 20 cm, , inc. fitting & Assecories - m 203,900.00 - - - - - - - -
7 Pemasangan Clean Out Inc. Fitting & Assecories 43.00 ttk 185,000.00 7,955,000.00 1.215 21.500 0.608 - - 21.500 0.608
8 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 100 org, 20 m3 / hari, - unit 7,500,000.00 - - - - - - - -
(Galian, Urugan, Pondasi, Tutup Beton, Penyambungan Instalasi)
9 Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm - unit 975,000.00 - - - - - - - -
10 Pekerjaan Sumur Resapan, Dia 100 cm, Kedalaman 2 m, Inc. Tutup Beton Berlubang - ttk 500,000.00 - - - - - - - -
11 Grill Beton Penutup Sumur Resapan - unit 750,000.00 - - - - - - - -
12 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 13.49 m3 688,832.33 9,292,348.18 1.419 1.484 0.156 - - 1.484 0.156
13 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area 13.49 m3 19,888.18 268,291.48 0.041 1.484 0.005 - - 1.484 0.005
14 Pemasangan 1 M Pipa PVC tipe D 6 375.05 m 133,200.00 49,956,660.00 7.630 219.657 4.469 80.124 1.630 299.781 6.099
15 Pemasangan 1 M Pipa PVC tipe D 4 64.50 m 85,618.17 5,522,372.20 0.844 25.800 0.337 - - 25.800 0.337
16 Pekerjaan Sumur Resapan kedalaman 4 Buis Beton Dia 80 cm 15.00 ttk 474,124.46 7,111,866.88 1.086 13.000 0.941 - - 13.000 0.941
17 Pasang Grill Besi Penutup Sumur Resapan 15.00 unit 826,875.00 12,403,125.00 1.894 5.250 0.663 - - 5.250 0.663

Laporan Progres Mingguan ke-15


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
C PEKERJAAN PEMASANGAN DAN PENGADAAN INSTALASI IPAL
1 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 50 org, 10 m3 / hari
a Pengadaan Unit IPAL kap 50 org, 10 m3 / hari 1.00 unit 110,250,000.00 110,250,000.00 16.840 0.350 5.894 - - 0.350 5.894
b Galian Tanah 57.21 m3 67,972.30 3,888,695.29 0.594 39.875 0.414 2.861 0.030 42.736 0.444
c Pengurugan Kembali 1 M3 Galian Tanah 2.39 m3 49,023.50 117,166.17 0.018 1.530 0.011 - - 1.530 0.011
d Pengurugan dengan pasir urug 1.83 m3 178,388.92 326,254.80 0.050 - - - - - -
e Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Dinding, Lantai dan Tutup 11.77 m3 872,242.00 10,266,288.31 1.568 8.698 1.159 - - 8.698 1.159
Jaring Kawat baja/Wire Mesh M8 713.69 kg 10,697.66 7,634,809.58 1.166 527.409 0.862 - - 527.409 0.862
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 30.14 m2 316,861.88 9,550,217.12 1.459 22.273 1.078 - - 22.273 1.078
Pembongkaran 1 M2 Bekisting 30.14 m2 15,645.80 471,564.35 0.072 - - 22.273 0.053 22.273 0.053
f Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Inlet 0.30 m3 872,242.00 261,672.60 0.040 - - - - - -
Jaring Kawat baja/Wire Mesh M8 11.06 kg 10,697.66 118,316.07 0.018 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.66 m2 316,861.88 209,128.84 0.032 - - - - - -
Pembongkaran 1 M2 Bekisting 0.66 m2 15,645.80 10,326.23 0.002 - - - - - -
g Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Outlet 0.41 m3 872,242.00 357,619.22 0.055 - - - - - -
Jaring Kawat baja/Wire Mesh M8 14.98 kg 10,697.66 160,250.88 0.024 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.96 m2 316,861.88 304,187.41 0.046 - - - - - -
Pembongkaran 1 M2 Bekisting 0.96 m2 15,645.80 15,019.97 0.002 - - - - - -
h Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Kolom 15 x 15 cm 0.47 m3 872,242.00 409,953.74 0.063 0.470 0.063 - - 0.470 0.063
Pembesian dg Besi Polos atau Besi Ulir 119.39 kg 11,860.70 1,416,048.75 0.216 119.390 0.216 - - 119.390 0.216
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.44 m2 316,861.88 456,281.11 0.070 1.440 0.070 - - 1.440 0.070
Pembongkaran 1 M2 Bekisting 1.44 m2 15,645.80 22,529.95 0.003 - - 1.440 0.003 1.440 0.003
i Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Balok 15 x 20 cm 0.12 m3 872,242.00 104,669.04 0.016 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 23.91 kg 11,860.70 283,589.29 0.043 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.55 m2 316,861.88 174,274.03 0.027 - - - - - -
Pembongkaran 1 M2 Bekisting 0.55 m2 15,645.80 8,605.19 0.001 - - - - - -
j Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, pondasi 60 x 60 x 20 cm 0.72 m3 872,242.00 628,014.24 0.096 0.576 0.077 - - 0.576 0.077
Pembesian dg Besi Polos atau Besi Ulir 36.93 kg 11,860.70 438,015.58 0.067 29.544 0.054 - - 29.544 0.054
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.20 m2 316,861.88 380,234.26 0.058 0.960 0.046 - - 0.960 0.046
Pembongkaran 1 M2 Bekisting 1.20 m2 15,645.80 18,774.96 0.003 0.960 0.002 - - 0.960 0.002
k Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm 4.00 unit 975,000.00 3,900,000.00 0.596 - - - - - -

251,374,175.57 38.395 17.125 1.717 18.841

JUMLAH 654,697,105.06 654,697,105.06 100.000 55.481 5.079 60.560


PRESTASI MINGGU LALU 55.481
PRESTASI MINGGU INI 5.079
PRESTASI SAMPAI DENGAN MINGGU INI 60.560
PRESTASI MENURUT SCHEDULE 65.541
LEBIH CEPAT (+) / TERLAMBAT (-) (4.981)

Yogyakarta, 6 September 2021


di buat oleh,
KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA

Noor Hasan Bambang Erlianto


Pengawas Pelaksana

Laporan Progres Mingguan ke-15


REKAPITULASI
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : XV ( Lima belas )


Periode : 30 Agustus 2021 sampai dengan 05 September 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
ADDENDUM II : 050 / 1909 / VII / 2021, TANGGAL 19 JULI 2021
NILAI KONTRAK ADDENDUM II : Rp 720,166,815.57
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO PEKERJAAN PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp (%) BOBOT % BOBOT % BOBOT %

I PEKERJAAN PERSIAPAN 11,873,371.04 1.814 1.379 0.054 1.433

II PEKERJAAN PERBAIKAN TALUD SEGMEN 5


A PEKERJAAN TANAH DAN BETON BERTULANG 34,726,084.58 5.304 - - -
B PEKERJAAN PASANGAN DINDING 6,878,419.61 1.051 - - -

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PENGECATAN 398,623.81 0.061 - - -
B PEKERJAAN RUMAH TERDAMPAK 167,320,879.74 25.557 22.133 1.427 23.559

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PEMBERSIHAN SALURAN 182,125,550.71 27.818 14.845 1.882 16.727
B PEKERJAAN JARINGAN IPAL KOMUNAL 251,374,175.57 38.395 17.125 1.717 18.841

JUMLAH 654,697,105.06 100.000 55.481 5.079 60.560


PRESTASI MINGGU LALU 654,697,105.06 55.481
PRESTASI MINGGU INI 5.079
PRESTASI SAMPAI DENGAN MINGGU INI 60.560
PRESTASI MENURUT SCHEDULE 65.541
LEBIH CEPAT (+) / TERLAMBAT (-) (4.981)

Yogyakarta, 6 September 2021


di buat oleh,
PEJABAT PEMBUAT KOMITMEN TIM TEKNIS KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA
1. Cicilia Novi hendrawati, M.SC., M.Eng.
NIP. 19781102 200501 2 011 ...........................

2. Danang Dwi Wahyujati,S.Kom.,M.Eng


NIP. 19761028 199803 1 004 ...........................
SIGIT SETIAWAN, ST.MT 3. Sudaryanto
NIP. 19690605 199303 1 007 RISMAN WARCHAN ZULIANTO
NIP. 19770623 200501 1 013 ........................... Tim Leader Direktur
JADWAL WAKTU PELAKSANAAN PEKERJAAN
MUTUAL CHECK ( MC 2)
INSTANSI : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021

BULAN KE-1 BULAN KE-2 BULAN KE-3 BULAN KE-4


KONTRAK MC 0 MC 1 MC 2 KONTRAK MC 0 MC 1 MC 2
Ming.1 Ming.2 Ming.3 Ming.4 Ming.5 Ming.6 Ming.7 Ming.8 Ming.9 Ming.10 Ming.11 Ming.12 Ming.13 Ming.14 Ming.15 Ming.16 Ming.17 Ming.18 Ming.19 Ming.20 Ming.21 Ming.22
NO JENIS PEKERJAAN 24/05/21 31/05/21 07/06/21 14/06/21 21/06/21 28/06/21 05/07/21 12/07/21 19/07/21 26/07/21 02/08/21 09/08/21 16/08/21 23/08/21 30/08/21 06/09/21 13/09/21 20/09/21 27/09/21 04/10/21 11/10/21 18/10/21 KET.
VOLUME HARGA SATUAN JUMLAH HARGA VOLUME JUMLAH HARGA VOLUME JUMLAH HARGA VOLUME
SAT. JUMLAH HARGA (Rp) BOBOT (%) BOBOT (%) BOBOT (%) BOBOT (%) s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
KONTRAK (Rp) (Rp) MC 0 (Rp) MC 1 (Rp) MC 2
30/05/21 06/06/21 13/06/21 20/06/21 27/06/21 04/07/21 11/07/21 18/07/21 25/07/21 01/08/21 08/08/21 15/08/21 22/08/21 29/08/21 05/09/21 12/09/21 19/09/21 26/09/21 03/10/21 10/10/21 17/10/21 20/10/21

I PEKERJAAN PERSIAPAN
1 Pembuatan Papan Nama Pekerjaan bh 1.00 250,000.00 250,000.00 1.00 250,000.00 1.00 250,000.00 1.00 250,000.00 0.038 0.038 0.038 0.035 0.038 - (0.003)
2 Pengukuran dan Pemasangan Bouwplank m 28.56 12,198.91 348,400.73 28.56 348,400.73 28.56 348,400.73 28.56 348,400.73 0.053 0.053 0.053 0.049 0.027 0.027 - (0.005)
3 Pembuatan bedeng pekerja m2 9.00 383,330.04 3,449,970.32 9.00 3,449,970.32 9.00 3,449,970.32 9.00 3,449,970.32 0.527 0.527 0.527 0.481 0.263 0.263 - (0.046)
4 Mobilisasi Demobilisasi Alat Berat ls 1.00 2,500,000.00 2,500,000.00 1.00 2,500,000.00 1.00 2,500,000.00 1.00 2,500,000.00 0.382 0.382 0.382 0.349 0.191 0.191 0.191 0.044 0.044
5 Pembuatan akses menuju badan sungai sementara m2 24.00 113,128.49 2,715,083.64 - - - - - - 0.415 - - - 0.207 0.207 -
6 Dewatering dengan pompa air diesel jam 40.00 25,000.00 1,000,000.00 40.00 1,000,000.00 40.00 1,000,000.00 40.00 1,000,000.00 0.153 0.153 0.153 0.139 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.005 0.005 0.005 0.005 0.005 0.005 0.005
7 SMKK ls 1.00 4,325,000.00 4,325,000.00 1.00 4,325,000.00 1.00 4,325,000.00 1.00 4,325,000.00 0.661 0.661 0.661 0.603 0.030 0.030 0.030 0.030 0.030 0.030 0.030 0.030 0.032 0.032 0.032 0.032 0.032 0.032 0.032 0.022 0.022 0.022 0.022 0.022 0.022 0.022
- -
II PEKERJAAN PERBAIKAN TALUD SEGMEN 5 - -
A PEKERJAAN TANAH DAN BETON BERTULANG - -
1 Penggalian 1 M3 Tanah Biasa m3 50.00 67,972.30 3,398,615.01 61.50 4,180,296.46 13.50 917,626.05 - - 0.519 0.639 0.140 - 0.160 0.160 0.160 0.160 0.070 0.070 -
2 Pengurugan Kembali 1 M3 Galian Tanah m3 33.15 49,023.50 1,625,129.04 29.21 1,431,976.45 6.41 314,240.64 - - 0.248 0.219 0.048 - 0.073 0.073 0.024 0.024 -
3 Bongkaran Pasangan Batu dan Beton Eksisting m3 50.00 71,953.20 3,597,660.02 39.18 2,819,126.39 7.92 569,869.35 - - 0.550 0.431 0.087 - 0.108 0.108 0.108 0.108 0.044 0.044 -
4 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area m3 50.00 19,888.18 994,408.76 39.18 779,218.70 7.92 157,514.35 - - 0.152 0.119 0.024 - 0.030 0.030 0.030 0.012 0.012 -
5 Pemadatan Tanah Eksisting m3 11.84 49,023.50 580,438.24 29.21 1,431,976.45 6.41 314,240.64 - - 0.089 0.219 0.048 - 0.109 0.109 0.024 0.024 -
6 Pengurugan dengan pasir urug m3 5.92 178,388.92 1,056,062.41 1.23 219,418.37 0.27 48,165.01 - - 0.161 0.034 0.007 - 0.034 0.007 -
7 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 m3 2.96 737,396.00 2,182,692.15 1.23 906,997.08 0.27 199,096.92 - - 0.333 0.139 0.030 - 0.069 0.030 -
8 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 m3 10.00 872,242.00 8,722,419.97 4.92 4,291,430.63 1.08 942,021.36 - - 1.332 0.655 0.144 - 0.109 0.072 0.072 -
a Pembesian dg Besi Polos atau Besi Ulir kg - 11,860.70 - 714.10 8,469,724.55 156.69 1,858,452.79 - - - 1.294 0.284 - 0.216 0.142 0.142 -
b Bekisting untuk pondasi beton ( dipakai 2 kali ) m2 - 89,375.55 - 8.56 765,054.68 1.92 171,601.05 - - - 0.117 0.026 - 0.019 0.013 0.013 -
c Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 1.92 30,039.93 - - - - 0.005 - 0.005 -
9 Pekerjaan Beton Dinding Talud Beton - - -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 m3 10.00 872,242.00 8,722,419.97 9.97 8,696,252.71 2.16 1,884,042.71 - - 1.332 1.328 0.288 - 0.144 0.144 -
b Pembesian dg Besi Polos atau Besi Ulir kg 1,000.00 11,860.70 11,860,698.15 4,675.31 55,452,440.67 1,026.67 12,177,022.97 - - 1.812 8.470 1.860 - 0.930 0.930 -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 40.00 316,861.88 12,674,475.27 10.12 3,206,642.24 9.02 2,858,094.17 - - 1.936 0.490 0.437 - 0.218 0.218 -
d Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 9.02 141,125.10 - - 0.022 - -
10 Pekerjaan Beton Sloof 20x30cm - - -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 m3 4.74 872,242.00 4,134,427.07 2.26 1,971,266.91 0.49 427,398.58 - - 0.632 0.301 0.065 - 0.065 -
b Pembesian dg Besi Polos atau Besi Ulir kg 400.00 11,860.70 4,744,279.26 671.58 7,965,407.66 147.55 1,750,046.01 - - 0.725 1.217 0.267 - 0.267 -
c Memasang Bekisting untuk Sloof (dipakai 2 kali) m2 47.36 89,375.55 4,232,825.87 11.34 1,013,518.69 2.46 219,863.84 - - 0.647 0.155 0.034 - 0.017 0.017 -
d Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 2.46 38,488.66 - - 0.006 - 0.006 -
11 Pekerjaan Beton Konsul Cantilever - - -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 m3 7.75 872,242.00 6,759,875.48 0.42 366,341.64 0.09 78,501.78 - - 1.033 0.056 0.012 - - -
b Pembesian dg Besi Polos atau Besi Ulir kg 700.00 11,860.70 8,302,488.71 194.43 2,306,075.54 47.58 564,332.02 - - 1.268 0.352 0.086 - 0.043 0.043 -
c Memasang Bekisting untuk Balok (dipakai 2 kali) m2 40.00 120,181.13 4,807,245.27 2.10 252,380.38 0.45 54,081.51 - - 0.734 0.039 0.008 - 0.008 -
d Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 0.45 7,040.61 - - 0.001 - - -
12 Pekerjaan Plat Beton tebal 12 cm - - -
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) m3 10.00 872,242.00 8,722,419.97 12.30 10,728,576.57 2.70 2,355,053.39 - - 1.332 1.639 0.360 - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis kg 700.00 10,697.66 7,488,358.68 1,340.41 14,339,244.07 294.23 3,147,571.10 - - 1.144 2.190 0.481 - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 30.00 316,861.88 9,505,856.45 6.15 1,948,700.57 1.35 427,763.54 - - 1.452 0.298 0.065 - - -
d Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 1.35 21,121.83 - - 0.003 - - -
13 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm m 13.00 77,312.85 1,005,067.10 21.00 1,623,569.93 4.50 347,907.84 - - 0.154 0.248 0.053 - - -
14 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm m 38.37 86,676.29 3,325,769.35 39.46 3,420,246.51 8.67 751,483.46 - - 0.508 0.522 0.115 - - - -
15 Memasang Stek Besi kg 200.00 11,860.70 2,372,139.63 107.71 1,277,515.80 23.67 280,742.73 - - 0.362 0.195 0.043 - - -
16 Pekerjaan Plat Beton Pot tebal 10 cm - - -
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) m3 4.74 872,242.00 4,134,427.07 2.26 1,971,266.91 0.49 427,398.58 - - 0.632 0.301 0.065 - - - -
b Pembesian dg Besi Polos atau Besi Ulir kg 200.00 11,860.70 2,372,139.63 107.71 1,277,515.80 23.67 280,742.73 - - 0.362 0.195 0.043 - - - -
c Bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm m2 30.00 118,158.83 3,544,764.95 32.80 3,875,609.68 7.20 850,743.59 - - 0.541 0.592 0.130 - - - -
d Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 7.20 112,649.75 - - - - 0.017 - - -
- - - -
B PEKERJAAN PASANGAN DINDING - - -
1Pemasangan Dinding Bata Merah Bakar Sekam Tebal 1/2 Bata Camp. 1SP 6PP m2 42.00 116,576.48 4,896,212.34 45.37 5,289,075.10 9.97 1,162,267.55 - - 0.748 0.808 0.178 - - -
2Pemasangan Plesteran 1 Pc 6 Pp Tebal 15 mm m2 84.00 54,689.70 4,593,934.71 155.38 8,497,685.43 34.11 1,865,465.63 - - 0.702 1.298 0.285 - - -
3Pemasangan Acian m2 210.00 33,411.23 7,016,358.16 155.38 5,191,436.81 34.11 1,139,657.03 - - 1.072 0.793 0.174 - - -
4Pemasangan Plesteran Skoning 1 Pc 2Pp lebar 10 cm m 360.00 55,075.90 19,827,324.36 212.00 11,676,091.01 46.50 2,561,029.40 - - 3.028 1.783 0.391 - - - -
5Pemasangan Kepala Kolom bh 10.00 50,000.00 500,000.00 14.00 700,000.00 3.00 150,000.00 - - 0.076 0.107 0.023 - -
- - - -
III PEKERJAAN PENATAAN LINGKUNGAN RW 1 - -
A PEKERJAAN PENGECATAN - -
1Pengecatan Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Weathershield luar ruangan m2 210.00 11,686.42 2,454,148.34 155.38 1,815,836.04 34.11 398,623.81 - - 0.375 0.277 0.061 - -
- - - -
B PEKERJAAN RUMAH TERDAMPAK - -
I. PEKERJAAN BONGKARAN - -
1Membongkar 1 m2 genteng / sirap untuk dipergunakan lagi m2 103.90 3,628.42 376,993.05 77.17 280,005.33 77.17 280,005.33 77.17 280,005.33 0.058 0.043 0.043 0.039 0.021 0.043 0.003 0.003 0.003 0.003 0.003 0.003 0.003
2Membongkar 1 m3 kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi m3 0.46 991,595.91 456,134.12 0.37 366,890.49 0.37 366,890.49 0.37 366,890.49 0.070 0.056 0.056 0.051 0.028 0.056 0.003 0.003 0.003 0.003 0.003 0.003 0.003
3Pembongkaran 1 m3 pasangan bata merah dan membersihkan m3 40.86 185,908.38 7,596,216.24 11.13 2,069,160.22 12.72 2,364,754.54 12.72 2,364,754.54 1.160 0.316 0.361 0.330 0.158 0.276 0.014 0.014 0.014 0.014 0.014 0.014 0.014
4Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 m3 9.20 688,832.33 6,337,257.47 1.80 1,239,898.20 1.50 1,033,248.50 1.50 1,033,248.50 0.968 0.189 0.158 0.144 0.095 0.146 0.008 0.008 0.008 0.008 0.008 0.008 0.008
II. PEKERJAAN TANAH - - -
1Menggali 1 m3 tanah biasa sedalam 1 meter m3 22.32 67,972.30 1,517,141.74 26.71 1,815,540.14 27.22 1,850,206.01 27.22 1,850,206.01 0.232 0.277 0.283 0.258 0.061 (0.025)
2Pengurugan Kembali 1 m3 Galian Tanah m3 - 18,745.83 - - - 10.11 189,520.38 10.11 189,520.38 - - 0.029 0.026 0.029 (0.003)
3Pengurugan dengan pasir urug m3 - 173,624.00 - - - 1.82 315,995.68 1.82 315,995.68 - - 0.048 0.044 0.048 (0.004)
4Peninggian peil lantai m3 - 18,745.83 - 9.18 172,086.75 9.18 172,086.75 - - 0.026 0.024 0.026 (0.002)
III. PEKERJAAN PONDASI - - - - -
1Memasang 1 m3 pondasi batu belah, campuran 1 PC 6 PP m2 17.28 665,195.09 11,494,571.24 16.11 10,716,292.98 16.49 10,969,067.11 16.49 10,969,067.11 1.756 1.637 1.675 1.530 0.693 (0.145)
IV. PEKERJAAN BETON - - -
1Membuat 1 m3 Sloof beton bertulang (200 kg besi + bekisting) m3 3.55 3,844,764.87 13,648,915.30 1.72 6,612,995.58 1.06 4,075,450.77 1.06 4,075,450.77 2.085 1.010 0.622 0.569 0.109 0.109 (0.054)
2Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) m3 4.94 7,083,735.01 34,993,650.96 3.92 27,768,241.25 2.29 16,221,753.18 2.29 16,221,753.18 5.345 4.241 2.478 2.263 0.303 0.303 0.303 (0.215)
3Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) m3 5.00 5,659,422.09 28,297,110.46 9.08 51,387,552.60 3.05 17,261,237.38 3.05 17,261,237.38 4.322 7.849 2.637 2.408 0.365 0.365 0.365 0.365 (0.229)
4Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 m3 - 723,713.11 - - - 0.14 101,319.83 0.14 101,319.83 - - 0.015 0.014 0.015 (0.001)
5Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting) m3 - 3,127,107.54 - - - 0.57 1,782,451.30 0.57 1,782,451.30 - - 0.272 0.249 0.272 (0.024)
6Sloof 150 x 200 dengan beton K 225 Tulangan 105 kg m3 - 3,295,166.46 - - - 0.74 2,438,423.18 0.74 2,438,423.18 - - 0.372 0.340 0.372 (0.032)
7Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m' - 77,312.85 - - - 67.35 5,207,020.70 67.35 5,207,020.70 - - 0.795 0.726 0.199 0.199 0.199 (0.069)
8Balok 150 x 200 dengan beton K 225 Tulangan 105 kg m3 - 3,705,897.33 - - - 1.01 3,742,956.31 1.01 3,742,956.31 - - 0.572 0.522 0.143 (0.050)
9Membuat 1 m’ ring balok beton bertulang (10 x 15) cm m' - 86,676.29 - - - 54.15 4,693,521.24 54.15 4,693,521.24 - - 0.717 0.655 0.179 (0.062)
10 Membuat 1 m3 Plat Lantai beton bertulang m3 - 3,119,381.73 - - - 2.95 9,202,176.12 2.95 9,202,176.12 - - 1.406 1.284 0.351 0.351 0.351 0.351 (0.122)
11 Membuat 1 m3 Plat Tangga beton bertulang m3 - 3,119,381.73 - - - 0.72 2,245,954.85 0.72 2,245,954.85 - - 0.343 0.313 0.086 0.086 0.086 (0.030)
12 Membuat 1 m3 Plat Water torn beton bertulang m3 - 3,119,381.73 - - - 0.42 1,310,140.33 0.42 1,310,140.33 - - 0.200 0.183 0.200 (0.017)
V. PEKERJAAN DINDING - - -
1Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP m2 127.00 116,576.48 14,805,213.51 191.94 22,375,690.41 161.84 18,866,738.23 161.84 18,866,738.23 2.261 3.418 2.882 2.632 0.635 0.635 0.635 (0.250) MC 2
2Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP, trap tangga m2 - 250,668.02 6.30 1,579,208.52 6.30 1,579,208.52 - - 0.241 0.220 0.060 0.060 0.060 (0.021)
VI PEKERJAAN KAYU - - -
1Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti m3 0.50 16,443,774.77 8,221,887.38 0.27 4,439,819.19 0.27 4,439,819.19 0.27 4,439,819.19 1.256 0.678 0.678 0.619 0.339 0.339 (0.059)
Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti m3 - 8,048,535.00 - - - 0.02 160,970.70 0.02 160,970.70 - - 0.025 0.022 0.012 0.012 (0.002)
2 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti m2 12.72 644,715.80 8,200,785.00 12.08 7,788,166.89 12.32 7,942,898.68 12.32 7,942,898.68 1.253 1.190 1.213 1.108 (0.105)
3 Memasang 1 m3 konstruksi gordeng, kayu glugu m3 0.21 4,450,537.65 934,612.91 0.35 1,557,688.18 - - - - 0.143 0.238 - - - -

Jangka Waktu Pelaksanaan


MC2 hal.98
VII. PEKERJAAN PLESTERAN - -
1 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm m2 100.00 54,689.70 5,468,969.90 75.69 4,139,463.32 96.76 5,291,775.27 96.76 5,291,775.27 0.835 0.632 0.808 0.738 0.808 (0.070)
2 Memasang 1 m2 acian m2 100.00 33,411.23 3,341,122.93 75.69 2,528,895.95 96.76 3,232,870.55 96.76 3,232,870.55 0.510 0.386 0.494 0.451 0.494 (0.043)
3 Pemasangan 1 m2 plesteran ciprat 1SP : 2PP m2 - 45,029.48 - - - 33.50 1,508,487.73 33.50 1,508,487.73 - - 0.230 0.210 0.230 (0.020)
VIII. PEKERJAAN PENGECATAN - -
1 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) m2 100.00 11,686.42 1,168,642.06 75.69 884,545.18 96.76 1,130,778.06 96.76 1,130,778.06 0.179 0.135 0.173 0.158 0.158
IX. PEKERJAAN PENUTUP ATAP - -
1 Memasang 1 m2 Atap Galvalum (Paket) m3 78.20 190,000.00 14,858,000.00 78.24 14,864,806.70 78.51 14,917,137.50 78.51 14,917,137.50 2.269 2.270 2.278 2.081 (0.084)
2 Pemasangan 1 m talang datar Galvalum lebar 60 cm m' - 105,483.99 - - - 6.00 632,903.97 - - - - 0.097 - -
3 Pemasangan 1 m talang datar U PVC m' - 73,235.87 - - - - - 8.64 632,903.97 - 0.088 0.088
X. PEKERJAAN PENUTUP LANTAI DAN DINDING - -
1 Memasang 1 m2 lantai keramik (30 x 30) cm m2 8.54 114,193.22 975,210.13 16.26 1,856,781.81 - - - - 0.149 0.284 - - - -
2 Membuat rabat beton lantai mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 m3 - 723,713.11 - - - 2.08 1,504,722.31 2.08 1,504,722.31 0.230 0.210 (0.020)
3 Memasang 1 m2 lantai keramik (20 x 20) cm m' - 184,674.28 - - - 4.99 921,524.65 4.99 921,524.65 0.141 0.129 0.129
XI. PEKERJAAN SANITASI - -
1 Memasang 1 buah Kloset Jongkok Porselen bh 2.00 280,952.58 561,905.16 2.00 561,905.16 2.00 561,905.16 2.00 561,905.16 0.086 0.086 0.086 0.078 0.078
2 Memasang 1 m Pipa PVC tipe AW m2 24.00 19,406.20 465,748.90 24.00 465,748.90 16.00 310,499.27 16.00 310,499.27 0.071 0.071 0.047 0.043 0.047 0.005
3 Memasang 1 m Pipa PVC tipe AW 1 m2 24.00 22,254.33 534,103.90 24.00 534,103.90 8.00 178,034.63 8.00 178,034.63 0.082 0.082 0.027 0.025 0.027 0.003
4 Memasang 1 m Pipa PVC tipe AW 3 m2 24.00 63,036.61 1,512,878.67 24.00 1,512,878.67 18.00 1,134,659.00 18.00 1,134,659.00 0.231 0.231 0.173 0.158 0.173 0.004
5 Memasang 1 buah Kran atau m2 2.00 46,068.18 92,136.37 2.00 92,136.37 2.00 92,136.37 2.00 92,136.37 0.014 0.014 0.014 0.013 0.014 0.013
6 Memasang 1 buah Floor Drain m3 2.00 80,836.18 161,672.35 2.00 161,672.35 2.00 161,672.35 2.00 161,672.35 0.025 0.025 0.025 0.023 0.025 0.023
7 Memasang 1 buah Pintu Kamar Mandi bh 2.00 650,000.00 1,300,000.00 2.00 1,300,000.00 2.00 1,300,000.00 2.00 1,300,000.00 0.199 0.199 0.199 0.181 0.199 (0.017)
8 Pemasangan 1 M Pipa PVC tipe D 4 m' - 85,618.17 - - - 12.00 1,027,418.08 12.00 1,027,418.08 - - 0.157 0.143 0.013
XII. PEKERJAAN ELEKTRIKAL - - - - - - -
1 Instalasi Penerangan menggunakan kabel NYY 3x2,5mm² dalam pipa conduit Ø 20mm. titik - 105,000.00 - - - 10.00 1,050,000.00 10.00 1,050,000.00 - - 0.160 0.146 0.160 (0.014)
2 Instalasi stop kontak dinding, menggunakan kabel NYM 3x2,5mm² titik - 100,000.00 - - - 5.00 500,000.00 5.00 500,000.00 - - 0.076 0.070 0.076 (0.007)
3 Saklar tunggal inbow, 1 gang 1 way bh - 20,000.00 - - - 4.00 80,000.00 4.00 80,000.00 - - 0.012 0.011 0.012 (0.001)
4 Saklar seri inbow, 1 gang 2 way bh - 25,000.00 - - - 4.00 100,000.00 4.00 100,000.00 - - 0.015 0.014 0.015 (0.001)
5 Stop kontak wall type 1ph, 16A, 1 gang bh - 20,000.00 - - - 5.00 100,000.00 5.00 100,000.00 - - 0.015 0.014 0.015 (0.001)
6 Lampu PLC 18 Watt dengan fitting gantung bh - 75,000.00 - - - 8.00 600,000.00 8.00 600,000.00 - - 0.092 0.084 0.092 (0.008)
7 Lampu PLC 7 Watt dengan fitting gantung bh - 65,000.00 - - - 2.00 130,000.00 2.00 130,000.00 - - 0.020 0.018 0.020 (0.002)
8 Penyambungan kabel Ls - 500,000.00 - - - 1.00 500,000.00 1.00 500,000.00 - - 0.076 0.070 0.076 0.070
9 Box MCB + MCB bh - 250,000.00 - - - 2.00 500,000.00 2.00 500,000.00 - - 0.076 0.070 0.076 (0.007)
XIII. PEKERJAAN LAIN-LAIN - -
1 Pintu Folding gate m2 - 788,049.93 - - - 6.00 4,728,299.56 6.00 4,728,299.56 - - 0.722 0.660 (0.063)
2 Railling pengaman besi Hollow 40x40 / 40x20 mm, finishing cat m2 - 550,000.00 - - - 11.48 6,312,240.00 11.48 6,312,240.00 - - 0.964 0.881 0.126 0.126 0.126 0.126 0.126 0.126 0.126
XIV. Rumah Timur sungai - - - -
1 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m' - 77,312.85 - - - - - 4.50 347,907.84 - 0.049 0.007 0.007 0.007 0.007 0.007 0.007 0.007
2 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm m' - 86,676.29 - - - - - 5.70 494,054.87 - 0.069 0.010 0.010 0.010 0.010 0.010 0.010 0.010
3 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP m2 - 116,576.48 - - - - - 3.10 361,387.10 - 0.050 0.007 0.007 0.007 0.007 0.007 0.007 0.007
4 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm m2 - 54,689.70 - - - - - 7.41 405,250.67 - 0.057 0.008 0.008 0.008 0.008 0.008 0.008 0.008
5 Memasang 1 m2 acian m2 - 33,411.23 - - - - - 7.41 247,577.21 - 0.035 0.005 0.005 0.005 0.005 0.005 0.005 0.005
6 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) m2 - 11,686.42 - - - - - 7.41 86,596.38 - 0.012 0.002 0.002 0.002 0.002 0.002 0.002 0.002
7 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti m3 - 8,048,535.00 - - - - - 0.13 1,046,309.55 - 0.146 0.021 0.021 0.021 0.021 0.021 0.021 0.021
8 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti m2 - 644,715.80 - - - - - 4.64 2,991,481.32 - 0.417 0.060 0.060 0.060 0.060 0.060 0.060 0.060
9 Memasang 1 m2 Atap Galvalum (Paket) m2 - 190,000.00 - - - - - 17.55 3,334,500.00 - 0.465 0.066 0.066 0.066 0.066 0.066 0.066 0.066
10 Membuat rabat beton lantai mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 m3 - 723,713.11 - - - - - 1.22 882,929.99 - 0.123 0.018 0.018 0.018 0.018 0.018 0.018 0.018
- - -
III PEKERJAAN PENATAAN LINGKUNGAN RW 1 -
A PEKERJAAN PEMBERSIHAN SALURAN -
1 Penggalian Tanah Lumpur dan Endapan Limbah Sedalam 30 cm m3 85.36 109,311.98 9,330,870.22 65.62 7,173,051.82 69.70 7,619,044.68 70.70 7,728,356.66 1.425 1.096 1.164 1.078 0.713 0.548 0.548 0.237 0.237 (0.003) (0.003) (0.003) (0.003) (0.003) (0.003) (0.003)
2 Pembersihan dan Pembuangan Tanah Lumpur dan Limbah Keluar Area m3 85.36 29,796.55 2,543,433.77 65.62 1,955,249.81 90.90 2,708,506.67 89.07 2,653,978.98 0.388 0.299 0.414 0.370 0.194 0.149 0.149 0.117 0.117 (0.002) (0.002) (0.002) (0.002) (0.002) (0.002) (0.002)
3 Pemadatan Tanah Eksisting m3 48.91 49,023.50 2,397,739.40 65.62 3,216,922.10 69.70 3,416,937.98 70.70 3,465,961.48 0.366 0.491 0.522 0.483 0.491 0.522 0.006 0.006 0.006 0.006 0.006 0.006 0.006
4 Pengurugan dengan pasir urug, 10 cm m3 17.07 178,388.92 3,045,098.87 21.87 3,901,365.68 21.87 3,901,365.68 21.87 3,901,365.68 0.465 0.596 0.596 0.544 0.298 0.298 0.298 0.298 0.006 0.006 0.006 0.006 0.006 0.006 0.006
Pengurugan dengan pasir urug, 10 cm m3 - 173,624.00 - - - 1.36 236,128.64 1.69 293,424.56 - - 0.036 0.041 0.018 0.018 0.001 0.001 0.001 0.001 0.001 0.001 0.001
5 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 m3 17.07 737,396.00 12,587,349.68 10.93 8,059,738.25 10.93 8,059,738.25 10.93 8,059,738.25 1.923 1.231 1.231 1.124 0.616 0.616 0.616 0.616 0.020 0.020 0.020 0.020 0.020 0.020 0.020
Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 m3 - 723,713.11 - - - 0.68 492,124.91 0.85 615,156.14 - - 0.075 0.086 0.038 0.038 0.004 0.004 0.004 0.004 0.004 0.004 0.004
6 Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 m3 17.07 872,242.00 14,889,170.90 21.87 19,075,932.48 23.23 20,262,181.60 23.56 20,550,021.46 2.274 2.914 3.095 2.867 1.457 1.457 1.547 1.547 0.057 0.057 0.057 0.057 0.057 0.057 0.057
a Jaring Kawat baja/Wire Mesh M5 1 lapis kg - 10,697.66 - - - 375.85 4,020,713.73 501.73 5,367,334.57 - 0.614 0.749 0.307 0.307 0.037 0.037 0.037 0.037 0.037 0.037 0.037
7 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm m 466.40 77,312.85 36,058,714.99 78.60 6,076,790.31 133.20 10,298,072.12 158.40 12,246,356.04 5.508 0.928 1.573 1.708 0.524 0.524 0.524 0.064 0.064 0.064 0.064 0.064 0.064 0.064
8 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm m 466.40 86,676.29 40,425,822.86 642.60 55,698,185.61 718.80 62,302,919.11 583.98 50,617,221.34 6.175 8.507 9.516 7.061 2.127 2.379 2.379 2.379 2.379 (0.076) (0.076) (0.076) (0.076) (0.076) (0.076) (0.076)
9 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,2m, K.300 bh 65.00 626,150.00 40,699,750.00 70.00 43,830,500.00 - - - - 6.217 6.695 - - -
10 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,8m, K.300 bh 32.00 750,000.00 24,000,000.00 61.00 45,750,000.00 - - - - 3.666 6.988 - - -
11 Pekerjaan Plat Beton tebal 15 cm - - - - - - - - - - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 m3 - 872,242.00 - - - 8.37 7,300,665.52 6.81 5,939,968.00 - - 1.115 0.829 0.223 0.223 0.112 0.118 0.118 0.118 0.118 0.118 0.118 0.118
b Jaring Kawat baja/Wire Mesh M8 2 lapis kg - 10,697.66 - - - 608.09 6,505,137.18 480.26 5,137,655.91 - - 0.994 0.717 0.199 0.199 0.099 0.102 0.102 0.102 0.102 0.102 0.102 0.102
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - 13.95 4,420,223.25 10.17 3,222,485.34 - - 0.675 0.450 0.135 0.135 0.068 0.016 0.016 0.016 0.016 0.016 0.016 0.016
d Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 13.95 218,258.88 10.17 159,117.77 - - 0.033 0.022 0.022
12 Pekerjaan Plat Beton tebal 10 cm - - - - - - - - - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 m3 - 872,242.00 - - - 17.65 15,395,071.25 22.73 19,826,060.60 - - 2.351 2.766 0.470 0.470 0.235 0.395 0.395 0.395 0.395 0.395 0.395 0.395
b Jaring Kawat baja/Wire Mesh M8 1 lapis kg - 10,697.66 - - - 962.04 10,291,572.26 1,186.92 12,697,260.97 - - 1.572 1.771 0.314 0.314 0.157 0.253 0.253 0.253 0.253 0.253 0.253 0.253
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - 44.14 13,986,283.46 57.68 18,276,593.34 - - 2.136 2.550 0.427 0.427 0.214 0.212 0.212 0.212 0.212 0.212 0.212 0.212
d Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 44.14 690,605.52 57.68 902,449.63 - - 0.105 0.126 0.126
-
B PEKERJAAN JARINGAN IPAL KOMUNAL -
1 Pekerjaan Galian Tanah Pipa m3 81.86 67,972.30 5,564,212.49 46.07 3,131,483.87 46.07 3,131,483.87 31.93 2,170,355.55 0.850 0.478 0.478 0.303 0.120 0.120 0.120 0.120 0.043 0.043 0.043 0.043 0.043 0.043 0.043
2 Pengurugan dengan pasir urug m3 6.82 178,388.92 1,216,612.43 11.51 2,053,256.47 11.51 2,053,256.47 14.41 2,570,584.34 0.186 0.314 0.314 0.359 0.105 0.105 0.105 0.051 0.051 0.051 0.051 0.051 0.051 0.051
3 Pengurugan Kembali 1 M3 Galian Tanah m3 24.56 49,023.50 1,204,017.17 30.54 1,497,264.55 30.54 1,497,264.55 12.97 635,966.29 0.184 0.229 0.229 0.089 0.076 0.076 0.076 0.013 0.013 0.013 0.013 0.013 0.013 0.013
4 Pemasangan 1 M Pipa PVC tipe AW 4 m 30.00 90,907.55 2,727,226.46 64.50 5,863,536.89 - - - - 0.417 0.896 - -
5 Saluran Pipa Air Limbah SDR - 41, Dia 15 cm , inc. fitting & Assecories m 343.20 133,200.00 45,714,240.00 375.05 49,956,660.00 375.05 49,956,660.00 - - 6.983 7.630 7.630 - 0.848 0.848 0.848 0.848 0.707
6 Saluran Pipa Air Limbah SDR - 41, Dia 20 cm, , inc. fitting & Assecories m 113.70 203,900.00 23,183,430.00 - - - - - - 3.541 - - -
7 Pemasangan Clean Out Inc. Fitting & Assecories ttk 17.00 185,000.00 3,145,000.00 43.00 7,955,000.00 43.00 7,955,000.00 43.00 7,955,000.00 0.480 1.215 1.215 1.110 0.135 0.135 0.135 0.135 0.113 0.072 0.072 0.072 0.072 0.072 0.072 0.072
8 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 100 org, 20 m3 / hari, (Gali unit 1.00 7,500,000.00 7,500,000.00 1.00 7,500,000.00 - - - - 1.146 1.146 - -
9 Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm unit 4.00 975,000.00 3,900,000.00 4.00 3,900,000.00 - - - - 0.596 0.596 - - - -
10 Pekerjaan Sumur Resapan, Dia 100 cm, Kedalaman 2 m, Inc. Tutup Beton Berlubang ttk 15.00 500,000.00 7,500,000.00 15.00 7,500,000.00 - - - - 1.146 1.146 - - 0.382 0.382
11 Grill Beton Penutup Sumur Resapan unit 20.00 750,000.00 15,000,000.00 15.00 11,250,000.00 - - - - 2.291 1.718 - -
12 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 m3 - 688,832.33 - - - 13.49 9,292,348.18 7.05 4,856,267.95 - - 1.419 0.677 0.237 0.237 0.237 0.074 0.074 0.074 0.074 0.074 0.074 0.074
13 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area m3 - 19,888.18 - - - 13.49 268,291.48 7.05 140,211.63 - - 0.041 0.020 0.007 0.007 0.007 0.002 0.002 0.002 0.002 0.002 0.002 0.002
14 Pemasangan 1 M Pipa PVC tipe D 6 - - 133,200.00 - - - - - 422.00 56,210,400.00 - - - 7.841 - - - - - 0.249 0.249 0.249 0.249 0.249 0.249 0.249
15 Pemasangan 1 M Pipa PVC tipe D 4 m - 85,618.17 - - - 64.50 5,522,372.20 165.50 14,169,807.73 - - 0.844 1.977 0.094 0.094 0.094 0.094 0.078 0.234 0.234 0.234 0.234 0.234 0.234 0.234
16 Pekerjaan Sumur Resapan kedalaman 4 Buis Beton Dia 80 cm ttk - 474,124.46 - - - 15.00 7,111,866.88 13.00 6,163,617.96 - - 1.086 0.860 1.086 - 0.082
17 Pasang Grill Besi Penutup Sumur Resapan unit - 826,875.00 - - - 15.00 12,403,125.00 15.00 12,403,125.00 - - 1.894 1.730 0.152 0.152 0.152 0.152 0.152 0.152 0.152
C PEKERJAAN PEMASANGAN DAN PENGADAAN INSTALASI IPAL
1 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 50 org, 10 m3 / hari
a Pengadaan Unit IPAL kap 50 org, 10 m3 / hari unit - 110,250,000.00 - - - 1.00 110,250,000.00 1.00 110,250,000.00 - - 16.840 15.380 3.368 2.245 1.355 1.355 1.355 1.355 1.355 1.355 1.355
b Galian Tanah m3 - 67,972.30 - - - 57.21 3,888,695.29 57.21 3,888,695.29 - - 0.594 0.542 0.198 0.198 0.198 0.014 0.014 0.014 0.014 0.014 0.014 0.014
c Pengurugan Kembali 1 M3 Galian Tanah m3 - 49,023.50 - - - 2.39 117,166.17 2.39 117,166.17 - - 0.018 0.016 0.006 0.006 0.006 0.001 0.001 0.001 0.001 0.001 0.001 0.001
d Pengurugan dengan pasir urug m3 - 178,388.92 - - - 1.83 326,254.80 4.98 888,028.96 - - 0.050 0.124 0.007 0.007 0.007 0.007 0.018 0.018 0.018 0.018 0.018 0.018 0.018
e Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Dinding, Lantai dan Tutup m3 - 872,242.00 - - - 11.77 10,266,288.31 11.77 10,266,288.31 - - 1.568 1.432 0.523 0.523 0.523 0.039 0.039 0.039 0.039 0.039 0.039 0.039
Jaring Kawat baja/Wire Mesh M8 kg - 10,697.66 - - - 713.69 7,634,809.58 534.95 5,722,710.68 - - 1.166 0.798 0.389 0.389 0.389 (0.009) (0.009) (0.009) (0.009) (0.009) (0.009) (0.009)
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - 30.14 9,550,217.12 30.14 9,550,217.12 - - 1.459 1.332 0.486 0.486 0.486 0.036 0.036 0.036 0.036 0.036 0.036 0.036
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 30.14 471,564.35 30.14 471,564.35 - - 0.072 0.066 0.024 0.024 0.024 0.002 0.002 0.002 0.002 0.002 0.002 0.002
f Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Inlet m3 - 872,242.00 - - - 0.30 261,672.60 0.30 261,672.60 - - 0.040 0.037 0.013 0.013 0.013 0.005 0.005 0.005 0.005 0.005 0.005 0.005
Jaring Kawat baja/Wire Mesh M8 kg - 10,697.66 - - - 11.06 118,316.07 11.06 118,316.07 - - 0.018 0.017 0.006 0.006 0.006 0.002 0.002 0.002 0.002 0.002 0.002 0.002
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - 0.66 209,128.84 0.66 209,128.84 - - 0.032 0.029 0.011 0.011 0.011 0.004 0.004 0.004 0.004 0.004 0.004 0.004
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 0.66 10,326.23 0.66 10,326.23 - - 0.002 0.001 0.001 0.001 0.001 0.000 0.000 0.000 0.000 0.000 0.000 0.000
g Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Outlet m3 - 872,242.00 - - - 0.41 357,619.22 0.41 357,619.22 - - 0.055 0.050 0.018 0.018 0.018 0.007 0.007 0.007 0.007 0.007 0.007 0.007
Jaring Kawat baja/Wire Mesh M8 kg - 10,697.66 - - - 14.98 160,250.88 14.98 160,250.88 - - 0.024 0.022 0.008 0.008 0.008 0.003 0.003 0.003 0.003 0.003 0.003 0.003
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - 0.96 304,187.41 0.96 304,187.41 - - 0.046 0.042 0.015 0.015 0.015 0.006 0.006 0.006 0.006 0.006 0.006 0.006
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 0.96 15,019.97 0.96 15,019.97 - - 0.002 0.002 0.001 0.001 0.001 0.000 0.000 0.000 0.000 0.000 0.000 0.000
h Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Kolom 15 x 15 cm m3 - 872,242.00 - - - 0.47 409,953.74 0.47 409,953.74 - - 0.063 0.057 0.021 0.021 0.021 (0.001) (0.001) (0.001) (0.001) (0.001) (0.001) (0.001)
Pembesian dg Besi Polos atau Besi Ulir kg - 11,860.70 - - - 119.39 1,416,048.75 119.39 1,416,048.75 - - 0.216 0.198 0.072 0.072 0.072 (0.003) (0.003) (0.003) (0.003) (0.003) (0.003) (0.003)
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - 1.44 456,281.11 1.44 456,281.11 - - 0.070 0.064 0.023 0.023 0.023 (0.001) (0.001) (0.001) (0.001) (0.001) (0.001) (0.001)
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 1.44 22,529.95 1.44 22,529.95 - - 0.003 0.003 0.001 0.001 0.001 (0.000) (0.000) (0.000) (0.000) (0.000) (0.000) (0.000)

Jangka Waktu Pelaksanaan


MC2 hal.99
i Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Balok 15 x 20 cm m3 - 872,242.00 - - - 0.12 104,669.04 0.12 104,669.04 - - 0.016 0.015 0.005 0.005 0.005 0.002 0.002 0.002 0.002 0.002 0.002 0.002
Pembesian dg Besi Polos atau Besi Ulir kg - 11,860.70 - - - 23.91 283,589.29 23.91 283,589.29 - - 0.043 0.040 0.014 0.014 0.014 0.006 0.006 0.006 0.006 0.006 0.006 0.006
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - 0.55 174,274.03 0.55 174,274.03 - - 0.027 0.024 0.009 0.009 0.009 0.003 0.003 0.003 0.003 0.003 0.003 0.003
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 0.55 8,605.19 0.55 8,605.19 - - 0.001 0.001 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
j Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, pondasi 60 x 60 x 20 cm m3 - 872,242.00 - - - 0.72 628,014.24 0.72 628,014.24 - - 0.096 0.088 0.032 0.032 0.032 0.002 0.002 0.002 0.002 0.002 0.002 0.002
Pembesian dg Besi Polos atau Besi Ulir kg - 11,860.70 - - - 36.93 438,015.58 36.93 438,015.58 - - 0.067 0.061 0.022 0.022 0.022 0.001 0.001 0.001 0.001 0.001 0.001 0.001
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - 1.20 380,234.26 1.20 380,234.26 - - 0.058 0.053 0.019 0.019 0.019 0.001 0.001 0.001 0.001 0.001 0.001 0.001
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 1.20 18,774.96 1.20 18,774.96 - - 0.003 0.003 0.001 0.001 0.001 0.000 0.000 0.000 0.000 0.000 0.000 0.000
k Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm unit - 975,000.00 - - - - - 3.00 2,925,000.00 - - - 0.408 0.204 0.204
l Tutup Manhole diameter 40 cm bh - 400,000.00 - - - - - 2.00 800,000.00 - - - 0.112 0.056 0.056

2 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 20 org, 2 m3 / hari
a Pengadaan Unit IPAL kap 20 org, 2 m3 / hari unit - 38,697,750.00 - - - - - 1.00 38,697,750.00 - - - 5.398 0.771 0.771 0.771 0.771 0.771 0.771 0.771
b Galian Tanah m3 - 67,972.30 - - - - - 26.89 1,827,775.15 - - - 0.255 0.036 0.036 0.036 0.036 0.036 0.036 0.036
c Pengurugan Kembali 1 M3 Galian Tanah m3 - 49,023.50 - - - - - 1.33 65,201.26 - - - 0.009 0.001 0.001 0.001 0.001 0.001 0.001 0.001
d Pengurugan dengan pasir urug m3 - 178,388.92 - - - - - 2.16 385,973.86 - - - 0.054 0.008 0.008 0.008 0.008 0.008 0.008 0.008
e Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Dinding, Lantai dan Tutup m3 - 872,242.00 - - - - - 6.37 5,556,181.52 - - - 0.775 0.111 0.111 0.111 0.111 0.111 0.111 0.111
Jaring Kawat baja/Wire Mesh M8 kg - 10,697.66 - - - - - 270.48 2,893,501.79 - - - 0.404 MC 1 0.058 0.058 0.058 0.058 0.058 0.058 0.058
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - - - 8.68 2,750,361.13 - - - 0.384 0.055 0.055 0.055 0.055 0.055 0.055 0.055
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - - - 8.68 135,805.53 - - - 0.019 0.003 0.003 0.003 0.003 0.003 0.003 0.003
f Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Inlet m3 - 872,242.00 - - - - - 0.17 148,281.14 - - - 0.021 0.003 0.003 0.003 0.003 0.003 0.003 0.003
Jaring Kawat baja/Wire Mesh M8 kg - 10,697.66 - - - - - 6.48 69,320.81 - - - 0.010 0.001 0.001 0.001 0.001 0.001 0.001 0.001
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - - - 0.33 104,564.42 - - - 0.015 0.002 0.002 0.002 0.002 0.002 0.002 0.002
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - - - 0.33 5,163.11 - - - 0.001 0.000 0.000 0.000 0.000 0.000 0.000 0.000
g Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Outlet m3 - 872,242.00 - - - - - 0.23 200,615.66 - - - 0.028 0.004 0.004 0.004 0.004 0.004 0.004 0.004
Jaring Kawat baja/Wire Mesh M8 kg - 10,697.66 - - - - - 8.44 90,288.21 - - - 0.013 0.002 0.002 0.002 0.002 0.002 0.002 0.002
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - - - 0.48 152,093.70 - - - 0.021 0.003 0.003 0.003 0.003 0.003 0.003 0.003
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - - - 0.48 7,509.98 - - - 0.001 0.000 0.000 0.000 0.000 0.000 0.000 0.000
h Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Kolom 15 x 15 cm m3 - 872,242.00 - - - - - 0.35 305,284.70 - - - 0.043 0.006 0.006 0.006 0.006 0.006 0.006 0.006
Pembesian dg Besi Polos atau Besi Ulir kg - 11,860.70 - - - - - 89.54 1,062,006.91 - - - 0.148 0.021 0.021 0.021 0.021 0.021 0.021 0.021
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - - - 1.08 342,210.83 - - - 0.048 0.007 0.007 0.007 0.007 0.007 0.007 0.007
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - - - 1.08 16,897.46 - - - 0.002 0.000 0.000 0.000 0.000 0.000 0.000 0.000
i Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Balok 15 x 20 cm m3 - 872,242.00 - - - - - 0.08 69,779.36 - - - 0.010 0.001 0.001 0.001 0.001 0.001 0.001 0.001
Pembesian dg Besi Polos atau Besi Ulir kg - 11,860.70 - - - - - 19.41 230,216.15 - - - 0.032 0.005 0.005 0.005 0.005 0.005 0.005 0.005
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - - - 0.40 126,744.75 - - - 0.018 0.003 0.003 0.003 0.003 0.003 0.003 0.003
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - - - 0.40 6,258.32 - - - 0.001 0.000 0.000 0.000 0.000 0.000 0.000 0.000
j Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, pondasi 60 x 60 x 20 cm m3 - 872,242.00 - - - - - 0.54 471,010.68 - - - 0.066 0.009 0.009 0.009 0.009 0.009 0.009 0.009
Pembesian dg Besi Polos atau Besi Ulir kg - 11,860.70 - - - - - 27.69 328,422.73 - - - 0.046 0.007 0.007 0.007 0.007 0.007 0.007 0.007
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - - - 0.90 285,175.69 - - - 0.040 0.006 0.006 0.006 0.006 0.006 0.006 0.006
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - - - 0.90 14,081.22 - - - 0.002 0.000 0.000 0.000 0.000 0.000 0.000 0.000
k Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm unit - 975,000.00 - - - 4.00 3,900,000.00 2.00 1,950,000.00 - - 0.596 0.272 0.136 0.136
l Tutup Manhole diameter 40 cm bh - 400,000.00 - - - - - 2.00 800,000.00 - - - 0.112 0.056 0.056

D PEKERJAAN LAIN - LAIN


1 Pasang Bak Kontrol dengan tutup precast cetak diameter 40 cm bh - 850,000.00 - - - - - 3.00 2,550,000.00 - - - 0.356 0.051 0.051 0.051 0.051 0.051 0.051 0.051
2 Pembersihan dan Pembuangan Bekas Galian Tanah IPAL Keluar Area m3 - 67,972.30 - - - - - 84.10 5,716,470.45 - - - 0.797 MC 0 0.169 0.143 0.143 0.143 0.143 0.032 0.024
3 Pembongkaran 1 M2 Paving Block eksisting m2 - 49,910.10 - - - - - 31.40 1,567,177.00 - - - 0.219 0.031 0.031 0.031 0.031 0.031 0.031 0.031
4 Pemasangan 1 M2 kembali Paving Block eksisting m2 - 64,463.10 - - - - - 31.40 2,024,141.20 - - - 0.282 0.040 0.040 0.040 0.040 0.040 0.040 0.040
5 Pembongkaran dan Pemasangan kembali pipa PDAM yang terdampak galian Ls - 1,500,000.00 - - - - - 1.00 1,500,000.00 - - - 0.209 0.030 0.030 0.030 0.030 0.030 0.030 0.030
6 Check Valve diameter 6 inch+ Reducer diameter 8x6 inch bh - 4,669,087.50 - - - - - 1.00 4,669,087.50 - - - 0.651 0.093 0.093 0.093 0.093 0.093 0.093 0.093
7 Check Valve diameter 6 inch bh - 4,278,582.00 - - - - - 1.00 4,278,582.00 - - - 0.597 0.085 0.085 0.085 0.085 0.085 0.085 0.085
8 Check Valve diameter 4 inch bh - 2,051,002.80 - - - - - 2.00 4,102,005.60 - - - 0.572 0.082 0.082 0.082 0.082 0.082 0.082 0.082
9 Membuat rabat beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 m3 - 723,713.11 - - - - - 1.55 1,121,650.74 - - - 0.156 0.022 0.022 0.022 0.022 0.022 0.022 0.022
10 Grill besi area ipal barat m2 - 828,726.02 - - - - - 1.50 1,243,089.03 - - - 0.173 0.025 0.025 0.025 0.025 0.025 0.025 0.025

Rencana Kemajuan Mingguan 654,697,105.06 654,697,105.06 654,697,105.06 716,855,950.73 100.000 100.000 100.000 100.000 0.095 0.718 0.501 0.937 1.803 2.688 2.964 4.087 6.711 6.870 5.876 8.118 7.585 7.477 10.026 10.362 11.178 4.745 4.328 1.218 1.491 0.221
Rencana Komulatif Kemajuan Mingguan 654,697,105.06 654,697,105.06 716,855,950.73 - - - - 0.095 0.813 1.314 2.251 4.054 6.742 9.706 13.793 20.504 27.374 33.251 41.368 48.953 56.430 66.457 76.819 87.997 92.742 97.070 98.288 99.779 100.000
Rencana Kemajuan Mingguan MC 0 - - - 0.095 0.718 0.501 0.937 1.975 3.416 2.985 3.789 5.109 5.356 7.803 10.422 6.709 8.147 11.152 9.516 11.225 5.666 4.074 0.766 1.015 0.228
Rencana Komulatif Kemajuan Mingguan MC 0 - - - 0.095 0.813 1.314 2.251 2.713 6.130 9.115 12.904 17.920 23.276 31.079 41.502 48.211 56.358 67.510 77.026 88.251 93.917 97.991 98.757 99.772 100.000
Rencana Kemajuan Mingguan MC 1 - - - 0.095 0.718 0.501 0.937 1.981 3.423 2.992 3.796 7.292 8.567 7.733 7.941 7.753 11.855 7.909 7.598 7.505 5.879 4.353 4.189 3.105 1.829
Rencana Komulatif Kemajuan Mingguan MC 1 - - - 0.095 0.813 1.314 2.251 2.601 6.024 9.016 12.812 13.784 22.351 30.084 38.024 45.777 57.632 65.541 73.139 80.644 86.523 90.876 95.065 98.171 100.000
Rencana Kemajuan Mingguan MC 2 - - - 0.095 0.718 0.501 0.937 1.981 3.423 2.992 3.796 7.297 8.572 7.737 7.945 7.757 11.860 7.913 4.055 5.709 5.705 5.833 5.705 6.203 6.229
Rencana Komulatif Kemajuan Mingguan MC 2 - - - 0.095 0.813 1.314 2.251 2.601 6.024 9.016 12.812 13.729 22.300 30.037 37.982 45.739 57.599 65.511 64.616 70.325 76.030 81.863 87.568 93.771 100.000
Realisasi Kemajuan Mingguan
Realisasi Komulatif Kemajuan Mingguan
Deviasi (+/-)

Yogyakarta, 6 September 2021


Dibuat Oleh
PEJABAT PEMBUAT KOMITMEN TIM TEKNIS KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA
1. Cicilia Novi hendrawati, M.SC., M.Eng.
NIP. 19781102 200501 2 011

2. Danang Dwi Wahyujati,S.Kom.,M.Eng


NIP. 19761028 199803 1 004

SIGIT SETIAWAN, ST.MT 3. Sudaryanto


NIP. 19690605 199303 1 007 RISMAN WARCHAN ZULIANTO
NIP. 19770623 200501 1 013 Tim Leader Direktur

Jangka Waktu Pelaksanaan


MC2 hal.100
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : XVI ( Enam belas )


Periode : 06 September 2021 sampai dengan 12 September 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
ADDENDUM II : 050 / 1909 / VII / 2021, TANGGAL 19 JULI 2021
ADDENDUM III : 050 / 0615 / IX / 2021, TANGGAL 6 SEPTEMBER 2021
NILAI KONTRAK ADDENDUM III : Rp 788,541,545.80
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
I PEKERJAAN PERSIAPAN
1 Pembuatan Papan Nama Pekerjaan 1.00 bh 250,000.00 250,000.00 0.035 1.000 0.035 - - 1.000 0.035
2 Pengukuran dan Pemasangan Bouwplank 28.56 m 12,198.91 348,400.73 0.049 28.560 0.049 - - 28.560 0.049
3 Pembuatan bedeng pekerja 9.00 m2 383,330.04 3,449,970.32 0.481 9.000 0.481 - - 9.000 0.481
4 Mobilisasi Demobilisasi Alat Berat 1.00 ls 2,500,000.00 2,500,000.00 0.349 0.682 0.238 0.045 0.016 0.727 0.254
5 Pembuatan akses menuju badan sungai sementara - m2 113,128.49 - - - - - - - -
6 Dewatering dengan pompa air diesel 40.00 jam 25,000.00 1,000,000.00 0.139 27.273 0.095 1.818 0.006 29.091 0.101
7 SMKK 1.00 ls 4,325,000.00 4,325,000.00 0.603 0.682 0.411 0.045 0.027 0.727 0.439
11,873,371.04 1.656 1.309 0.050 1.359
II PEKERJAAN PERBAIKAN TALUD SEGMEN 5
A PEKERJAAN TANAH DAN BETON BERTULANG
1 Penggalian 1 M3 Tanah Biasa - m3 67,972.30 - - - - - - - -
2 Pengurugan Kembali 1 M3 Galian Tanah - m3 49,023.50 - - - - - - - -
3 Bongkaran Pasangan Batu dan Beton Eksisting - m3 71,953.20 - - - - - - - -
4 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area - m3 19,888.18 - - - - - - - -
5 Pemadatan Tanah Eksisting - m3 49,023.50 - - - - - - - -
6 Pengurugan dengan pasir urug - m3 178,388.92 - - - - - - - -
7 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 - m3 737,396.00 - - - - - - - -
8 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 - m3 872,242.00 - - - - - - - -
a Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
b Bekisting untuk pondasi beton ( dipakai 2 kali ) - m2 89,375.55 - - - - - - - -
c Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
9 Pekerjaan Beton Dinding Talud Beton
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 - m3 872,242.00 - - - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) - m2 316,861.88 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
10 Pekerjaan Beton Sloof 20x30cm
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 - m3 872,242.00 - - - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
c Memasang Bekisting untuk Sloof (dipakai 2 kali) - m2 89,375.55 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
11 Pekerjaan Beton Konsul Cantilever
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 - m3 872,242.00 - - - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
c Memasang Bekisting untuk Balok (dipakai 2 kali) - m2 120,181.13 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
12 Pekerjaan Plat Beton tebal 12 cm
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) - m3 872,242.00 - - - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis - kg 10,697.66 - - - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) - m2 316,861.88 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
13 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm - m 77,312.85 - - - - - - - -
14 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm - m 86,676.29 - - - - - - - -
15 Memasang Stek Besi - kg 11,860.70 - - - - - - - -
16 Pekerjaan Plat Beton Pot tebal 10 cm
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) - m3 872,242.00 - - - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
c Bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm - m2 118,158.83 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
- - - - -

Laporan Progres Mingguan ke-16


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
B PEKERJAAN PASANGAN DINDING
1 Pemasangan Dinding Bata Merah Bakar Sekam Tebal 1/2 Bata Camp. 1SP 6PP - m2 116,576.48 - - - - - - - -
2 Pemasangan Plesteran 1 Pc 6 Pp Tebal 15 mm - m2 54,689.70 - - - - - - - -
3 Pemasangan Acian - m2 33,411.23 - - - - - - - -
4 Pemasangan Plesteran Skoning 1 Pc 2Pp lebar 10 cm - m 55,075.90 - - - - - - - -
5 Pemasangan Kepala Kolom - bh 50,000.00 - - - - - - - -
- - - - -
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PENGECATAN
1 Pengecatan Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Weathershield luar ruangan - m2 11,686.42 - - - - - - - -
- - - - -
B PEKERJAAN RUMAH TERDAMPAK
I. PEKERJAAN BONGKARAN
1 Membongkar 1 m2 genteng / sirap untuk dipergunakan lagi 77.17 m2 3,628.42 280,005.33 0.039 38.585 0.020 - - 38.585 0.020
2 Membongkar 1 m3 kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi 0.37 m3 991,595.91 366,890.49 0.051 0.185 0.026 - - 0.185 0.026
3 Pembongkaran 1 m3 pasangan bata merah dan membersihkan 12.72 m3 185,908.38 2,364,754.54 0.330 8.093 0.210 - - 8.093 0.210
4 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 1.50 m3 688,832.33 1,033,248.50 0.144 0.858 0.082 - - 0.858 0.082
II. PEKERJAAN TANAH
1 Menggali 1 m3 tanah biasa sedalam 1 meter 27.22 m3 67,972.30 1,850,206.01 0.258 27.220 0.258 - - 27.220 0.258
2 Pengurugan Kembali 1 m3 Galian Tanah 10.11 m3 18,745.83 189,520.38 0.026 10.110 0.026 - - 10.110 0.026
3 Pengurugan dengan pasir urug 1.82 m3 173,624.00 315,995.68 0.044 1.820 0.044 - - 1.820 0.044
4 Peninggian peil lantai 9.18 m3 18,745.83 172,086.75 0.024 9.180 0.024 - - 9.180 0.024
III. PEKERJAAN PONDASI
1 Memasang 1 m3 pondasi batu belah, campuran 1 PC 6 PP 16.49 m2 665,195.09 10,969,067.11 1.530 16.490 1.530 - - 16.490 1.530
IV. PEKERJAAN BETON
1 Membuat 1 m3 Sloof beton bertulang (200 kg besi + bekisting) 1.06 m3 3,844,764.87 4,075,450.77 0.569 1.060 0.569 - - 1.060 0.569
2 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) 2.29 m3 7,083,735.01 16,221,753.18 2.263 2.290 2.263 - - 2.290 2.263
3 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) 3.05 m3 5,659,422.09 17,261,237.38 2.408 3.050 2.408 - - 3.050 2.408
4 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.14 m3 723,713.11 101,319.83 0.014 0.140 0.014 - - 0.140 0.014
5 Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting) 0.57 m3 3,127,107.54 1,782,451.30 0.249 0.570 0.249 - - 0.570 0.249
6 Sloof 150 x 200 dengan beton K 225 Tulangan 105 kg 0.74 m3 3,295,166.46 2,438,423.18 0.340 0.740 0.340 - - 0.740 0.340
7 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm 67.35 m' 77,312.85 5,207,020.70 0.726 67.350 0.726 - - 67.350 0.726
8 Balok 150 x 200 dengan beton K 225 Tulangan 105 kg 1.01 m3 3,705,897.33 3,742,956.31 0.522 1.010 0.522 - - 1.010 0.522
9 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm 54.15 m' 86,676.29 4,693,521.24 0.655 54.150 0.655 - - 54.150 0.655
10 Membuat 1 m3 Plat Lantai beton bertulang 2.95 m3 3,119,381.73 9,202,176.12 1.284 2.950 1.284 - - 2.950 1.284
11 Membuat 1 m3 Plat Tangga beton bertulang 0.72 m3 3,119,381.73 2,245,954.85 0.313 0.720 0.313 - - 0.720 0.313
12 Membuat 1 m3 Plat Water torn beton bertulang 0.42 m3 3,119,381.73 1,310,140.33 0.183 0.420 0.183 - - 0.420 0.183
V. PEKERJAAN DINDING
1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP 161.84 m2 116,576.48 18,866,738.23 2.632 161.840 2.632 - - 161.840 2.632
2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP, trap tangga 6.30 m2 250,668.02 1,579,208.52 0.220 6.300 0.220 - - 6.300 0.220
VI PEKERJAAN KAYU
1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.27 m3 16,443,774.77 4,439,819.19 0.619 0.270 0.619 - - 0.270 0.619
Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.02 m3 8,048,535.00 160,970.70 0.022 0.020 0.022 - - 0.020 0.022
2 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti 12.32 m2 644,715.80 7,942,898.68 1.108 12.320 1.108 - - 12.320 1.108
3 Memasang 1 m3 konstruksi gordeng, kayu glugu - m3 4,450,537.65 - - - - - - - -
VII. PEKERJAAN PLESTERAN
1 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm 96.76 m2 54,689.70 5,291,775.27 0.738 96.760 0.738 - - 96.760 0.738
2 Memasang 1 m2 acian 96.76 m2 33,411.23 3,232,870.55 0.451 96.760 0.451 - - 96.760 0.451
3 Pemasangan 1 m2 plesteran ciprat 1SP : 2PP 33.50 m2 45,029.48 1,508,487.73 0.210 33.500 0.210 - - 33.500 0.210
VIII. PEKERJAAN PENGECATAN
1 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 96.76 m2 11,686.42 1,130,778.06 0.158 - - - - - -
IX. PEKERJAAN PENUTUP ATAP
1 Memasang 1 m2 Atap Galvalum (Paket) 78.51 m3 190,000.00 14,917,137.50 2.081 74.586 1.977 - - 74.586 1.977
2 Pemasangan 1 m talang datar Galvalum lebar 60 cm - m' 105,483.99 - - - - - - - -
3 Pemasangan 1 m talang datar U PVC 8.64 m' 73,235.87 632,903.97 0.088 - - - - - -
X. PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Memasang 1 m2 lantai keramik (30 x 30) cm - m2 114,193.22 - - - - - - - -
2 Membuat rabat beton lantai mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 2.08 m3 723,713.11 1,504,722.31 0.210 2.079 0.210 - - 2.079 0.210
3 Memasang 1 m2 lantai keramik (20 x 20) cm 4.99 m2 184,674.28 921,524.65 0.129 - - - - - -
XI. PEKERJAAN SANITASI - - - -
1 Memasang 1 buah Kloset Jongkok Porselen 2.00 bh 280,952.58 561,905.16 0.078
2 Memasang 1 m Pipa PVC tipe AW 16.00 m' 19,406.20 310,499.27 0.043 12.800 0.035 3.200 0.009 16.000 0.043
3 Memasang 1 m Pipa PVC tipe AW 1 8.00 m' 22,254.33 178,034.63 0.025 6.400 0.020 1.600 0.005 8.000 0.025
4 Memasang 1 m Pipa PVC tipe AW 3 18.00 m' 63,036.61 1,134,659.00 0.158 16.000 0.141 - - 16.000 0.141
5 Memasang 1 buah Kran atau 2.00 bh 46,068.18 92,136.37 0.013 - - - - - -
6 Memasang 1 buah Floor Drain 2.00 bh 80,836.18 161,672.35 0.023 - - - - - -
7 Memasang 1 buah Pintu Kamar Mandi 2.00 bh 650,000.00 1,300,000.00 0.181 2.000 0.181 - - 2.000 0.181
8 Pemasangan 1 M Pipa PVC tipe D 4 12.00 m 85,618.17 1,027,418.08 0.143 10.000 0.119 - - 10.000 0.119

Laporan Progres Mingguan ke-16


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
XII. PEKERJAAN ELEKTRIKAL
1 Instalasi Penerangan menggunakan kabel NYY 3x2,5mm² dalam pipa conduit Ø 20mm. 10.00 titik 105,000.00 1,050,000.00 0.146 10.000 0.146 - - 10.000 0.146
2 Instalasi stop kontak dinding, menggunakan kabel NYM 3x2,5mm² 5.00 titik 100,000.00 500,000.00 0.070 5.000 0.070 - - 5.000 0.070
3 Saklar tunggal inbow, 1 gang 1 way 4.00 bh 20,000.00 80,000.00 0.011 4.000 0.011 - - 4.000 0.011
4 Saklar seri inbow, 1 gang 2 way 4.00 bh 25,000.00 100,000.00 0.014 4.000 0.014 - - 4.000 0.014
5 Stop kontak wall type 1ph, 16A, 1 gang 5.00 bh 20,000.00 100,000.00 0.014 5.000 0.014 - - 5.000 0.014
6 Lampu PLC 18 Watt dengan fitting gantung 8.00 bh 75,000.00 600,000.00 0.084 8.000 0.084 - - 8.000 0.084
7 Lampu PLC 7 Watt dengan fitting gantung 2.00 bh 65,000.00 130,000.00 0.018 2.000 0.018 - - 2.000 0.018
8 Penyambungan kabel 1.00 Ls 500,000.00 500,000.00 0.070 - - 1.000 0.070 1.000 0.070
9 Box MCB + MCB 2.00 bh 250,000.00 500,000.00 0.070 2.000 0.070 - - 2.000 0.070
XIII. PEKERJAAN LAIN-LAIN
1 Pintu Folding gate 6.00 m2 788,049.93 4,728,299.56 0.660 6.000 0.660 - - 6.000 0.660
2 Railling pengaman besi Hollow 40x40 / 40x20 mm, finishing cat 11.48 m2 550,000.00 6,312,240.00 0.881 - - 5.738 0.440 5.738 0.440
XIV. Rumah Timur sungai
1 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm 4.50 m' 77,312.85 347,907.84 0.049 - - - - - -
2 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm 5.70 m' 86,676.29 494,054.87 0.069 - - - - - -
3 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP 3.10 m2 116,576.48 361,387.10 0.050 - - - - - -
4 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm 7.41 m2 54,689.70 405,250.67 0.057 - - - - - -
5 Memasang 1 m2 acian 7.41 m2 33,411.23 247,577.21 0.035 - - - - - -
6 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 7.41 m2 11,686.42 86,596.38 0.012 - - - - - -
7 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.13 m3 8,048,535.00 1,046,309.55 0.146 - - - - - -
8 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti 4.64 m2 644,715.80 2,991,481.32 0.417 - - - - - -
9 Memasang 1 m2 Atap Galvalum (Paket) 17.55 m2 190,000.00 3,334,500.00 0.465 - - - - - -
10 Membuat rabat beton lantai mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 1.22 m3 723,713.11 882,929.99 0.123 - - - - - -

177,518,874.67 24.764 21.516 0.524 22.040


III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PEMBERSIHAN SALURAN
1 Penggalian Tanah Lumpur dan Endapan Limbah Sedalam 30 cm 70.70 m3 109,311.98 7,728,356.66 1.078 65.736 1.002 - - 65.736 1.002
2 Pembersihan dan Pembuangan Tanah Lumpur dan Limbah Keluar Area 89.07 m3 29,796.55 2,653,978.98 0.370 84.822 0.353 - - 84.822 0.353
3 Pemadatan Tanah Eksisting 70.70 m3 49,023.50 3,465,961.48 0.483 59.245 0.405 - - 59.245 0.405
4 Pengurugan dengan pasir urug, 10 cm 21.87 m3 178,388.92 3,901,365.68 0.544 18.544 0.461 - - 18.544 0.461
Pengurugan dengan pasir urug, 10 cm 1.69 m3 173,624.00 293,424.56 0.041 1.156 0.028 - - 1.156 0.028
5 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 10.93 m3 737,396.00 8,059,738.25 1.124 8.744 0.899 - - 8.744 0.899
Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.85 m3 723,713.11 615,156.14 0.086 0.544 0.055 - - 0.544 0.055
6 Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 23.56 m3 872,242.00 20,550,021.46 2.867 18.515 2.253 - - 18.515 2.253
a Jaring Kawat baja/Wire Mesh M5 1 lapis 501.73 kg 10,697.66 5,367,334.57 0.749 300.680 0.449 - - 300.680 0.449
7 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 158.40 m 77,312.85 12,246,356.04 1.708 106.560 1.149 - - 106.560 1.149
8 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 583.98 m 86,676.29 50,617,221.34 7.061 573.789 6.938 - - 573.789 6.938
9 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,2m, K.300 - bh 626,150.00 - - - - - - - -
10 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,8m, K.300 - bh 750,000.00 - - - - - - - -
11 Pekerjaan Plat Beton tebal 15 cm - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 6.81 m3 872,242.00 5,939,968.00 0.829 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis 480.26 kg 10,697.66 5,137,655.91 0.717 - - 144.078 0.215 144.078 0.215
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 10.17 m2 316,861.88 3,222,485.34 0.450 6.975 0.308 1.526 0.067 8.501 0.376
d Pembongkaran 1 M2 Bekisting 10.17 m2 15,645.80 159,117.77 0.022 - - - - - -
12 Pekerjaan Plat Beton tebal 10 cm - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 22.73 m3 872,242.00 19,826,060.60 2.766 - - 11.365 1.383 11.365 1.383
b Jaring Kawat baja/Wire Mesh M8 1 lapis 1,186.92 kg 10,697.66 12,697,260.97 1.771 - - 454.602 0.678 454.602 0.678
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 57.68 m2 316,861.88 18,276,593.34 2.550 22.070 0.976 18.458 0.816 40.528 1.791
d Pembongkaran 1 M2 Bekisting 57.68 m2 15,645.80 902,449.63 0.126 - - - - - -
181,660,506.72 25.341 15.276 3.160 18.436
B PEKERJAAN JARINGAN IPAL KOMUNAL
1 Pekerjaan Galian Tanah Pipa 31.93 m3 67,972.30 2,170,355.55 0.303 - - - - - -
2 Pengurugan dengan pasir urug 14.41 m3 178,388.92 2,570,584.34 0.359 - - - - - -
3 Pengurugan Kembali 1 M3 Galian Tanah 12.97 m3 49,023.50 635,966.29 0.089 - - - - - -
4 Pemasangan 1 M Pipa PVC tipe AW 4 - m 90,907.55 - -
5 Saluran Pipa Air Limbah SDR - 41, Dia 15 cm , inc. fitting & Assecories - m 133,200.00 - - - - - - - -
6 Saluran Pipa Air Limbah SDR - 41, Dia 20 cm, , inc. fitting & Assecories - m 203,900.00 - - - - - - - -
7 Pemasangan Clean Out Inc. Fitting & Assecories 43.00 ttk 185,000.00 7,955,000.00 1.110 22.000 0.568 - - 22.000 0.568
8 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 100 org, 20 m3 / hari, - unit 7,500,000.00 - - - - - - - -
(Galian, Urugan, Pondasi, Tutup Beton, Penyambungan Instalasi)
9 Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm - unit 975,000.00 - - - - - - - -
10 Pekerjaan Sumur Resapan, Dia 100 cm, Kedalaman 2 m, Inc. Tutup Beton Berlubang - ttk 500,000.00 - - - - - - - -
11 Grill Beton Penutup Sumur Resapan - unit 750,000.00 - - - - - - - -
12 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 7.05 m3 688,832.33 4,856,267.95 0.677 1.484 0.143 - - 1.484 0.143
13 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area 7.05 m3 19,888.18 140,211.63 0.020 1.484 0.004 - - 1.484 0.004
14 Pemasangan 1 M Pipa PVC tipe D 6 422.00 m 133,200.00 56,210,400.00 7.841 299.781 5.570 21.100 0.392 320.881 5.962
15 Pemasangan 1 M Pipa PVC tipe D 4 165.50 m 85,618.17 14,169,807.73 1.977 25.800 0.308 25.322 0.302 51.122 0.611
16 Pekerjaan Sumur Resapan kedalaman 4 Buis Beton Dia 80 cm 13.00 ttk 474,124.46 6,163,617.96 0.860 13.000 0.860 - - 13.000 0.860
17 Pasang Grill Besi Penutup Sumur Resapan 15.00 unit 826,875.00 12,403,125.00 1.730 5.250 0.606 0.750 0.087 6.000 0.692

Laporan Progres Mingguan ke-16


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)

C PEKERJAAN PEMASANGAN DAN PENGADAAN INSTALASI IPAL


1 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 50 org, 10 m3 / hari
a Pengadaan Unit IPAL kap 50 org, 10 m3 / hari 1.00 unit 110,250,000.00 110,250,000.00 15.380 0.350 5.383 0.150 2.307 0.500 7.690
b Galian Tanah 57.21 m3 67,972.30 3,888,695.29 0.542 42.736 0.405 14.474 0.137 57.210 0.542
c Pengurugan Kembali 1 M3 Galian Tanah 2.39 m3 49,023.50 117,166.17 0.016 1.530 0.010 0.860 0.006 2.390 0.016
d Pengurugan dengan pasir urug 4.98 m3 178,388.92 888,028.96 0.124 - - - - - -
e Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Dinding, Lantai dan Tutup 11.77 m3 872,242.00 10,266,288.31 1.432 8.698 1.058 - - 8.698 1.058
Jaring Kawat baja/Wire Mesh M8 534.95 kg 10,697.66 5,722,710.68 0.798 527.409 0.787 - - 527.409 0.787
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 30.14 m2 316,861.88 9,550,217.12 1.332 22.273 0.985 - - 22.273 0.985
Pembongkaran 1 M2 Bekisting 30.14 m2 15,645.80 471,564.35 0.066 22.273 0.049 - - 22.273 0.049
f Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Inlet 0.30 m3 872,242.00 261,672.60 0.037 - - 0.165 0.020 0.165 0.020
Jaring Kawat baja/Wire Mesh M8 11.06 kg 10,697.66 118,316.07 0.017 - - 6.083 0.009 6.083 0.009
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.66 m2 316,861.88 209,128.84 0.029 - - 0.363 0.016 0.363 0.016
Pembongkaran 1 M2 Bekisting 0.66 m2 15,645.80 10,326.23 0.001 - - 0.363 0.001 0.363 0.001
g Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Outlet 0.41 m3 872,242.00 357,619.22 0.050 - - 0.246 0.030 0.246 0.030
Jaring Kawat baja/Wire Mesh M8 14.98 kg 10,697.66 160,250.88 0.022 - - 8.988 0.013 8.988 0.013
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.96 m2 316,861.88 304,187.41 0.042 - - 0.576 0.025 0.576 0.025
Pembongkaran 1 M2 Bekisting 0.96 m2 15,645.80 15,019.97 0.002 - - 0.576 0.001 0.576 0.001
h Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Kolom 15 x 15 cm 0.47 m3 872,242.00 409,953.74 0.057 0.470 0.057 - - 0.470 0.057
Pembesian dg Besi Polos atau Besi Ulir 119.39 kg 11,860.70 1,416,048.75 0.198 119.390 0.198 - - 119.390 0.198
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.44 m2 316,861.88 456,281.11 0.064 1.440 0.064 - - 1.440 0.064
Pembongkaran 1 M2 Bekisting 1.44 m2 15,645.80 22,529.95 0.003 1.440 0.003 - - 1.440 0.003
i Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Balok 15 x 20 cm 0.12 m3 872,242.00 104,669.04 0.015 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 23.91 kg 11,860.70 283,589.29 0.040 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.55 m2 316,861.88 174,274.03 0.024 - - - - - -
Pembongkaran 1 M2 Bekisting 0.55 m2 15,645.80 8,605.19 0.001 - - - - - -
j Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, pondasi 60 x 60 x 20 cm 0.72 m3 872,242.00 628,014.24 0.088 0.576 0.070 - - 0.576 0.070
Pembesian dg Besi Polos atau Besi Ulir 36.93 kg 11,860.70 438,015.58 0.061 29.544 0.049 - - 29.544 0.049
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.20 m2 316,861.88 380,234.26 0.053 0.960 0.042 - - 0.960 0.042
Pembongkaran 1 M2 Bekisting 1.20 m2 15,645.80 18,774.96 0.003 0.960 0.002 - - 0.960 0.002
k Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm 3.00 unit 975,000.00 2,925,000.00 0.408 - - - - - -
l Tutup Manhole diameter 40 cm 2.00 bh 400,000.00 800,000.00 0.112 - - - - - -

2 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 20 org, 2 m3 / hari
a Pengadaan Unit IPAL kap 20 org, 2 m3 / hari 1.00 unit 38,697,750.00 38,697,750.00 5.398 - - - - - -
b Galian Tanah 26.89 m3 67,972.30 1,827,775.15 0.255 - - 26.890 0.255 26.890 0.255
c Pengurugan Kembali 1 M3 Galian Tanah 1.33 m3 49,023.50 65,201.26 0.009 - - - - - -
d Pengurugan dengan pasir urug 2.16 m3 178,388.92 385,973.86 0.054 - - - - - -
e Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Dinding, Lantai dan Tutup 6.37 m3 872,242.00 5,556,181.52 0.775 - - - - - -
Jaring Kawat baja/Wire Mesh M8 270.48 kg 10,697.66 2,893,501.79 0.404 - - 135.240 0.202 135.240 0.202
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 8.68 m2 316,861.88 2,750,361.13 0.384 - - 4.340 0.192 4.340 0.192
Pembongkaran 1 M2 Bekisting 8.68 m2 15,645.80 135,805.53 0.019 - - - - - -
f Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Inlet 0.17 m3 872,242.00 148,281.14 0.021 - - - - - -
Jaring Kawat baja/Wire Mesh M8 6.48 kg 10,697.66 69,320.81 0.010 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.33 m2 316,861.88 104,564.42 0.015 - - - - - -
Pembongkaran 1 M2 Bekisting 0.33 m2 15,645.80 5,163.11 0.001 - - - - - -
g Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Outlet 0.23 m3 872,242.00 200,615.66 0.028 - - - - - -
Jaring Kawat baja/Wire Mesh M8 8.44 kg 10,697.66 90,288.21 0.013 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.48 m2 316,861.88 152,093.70 0.021 - - - - - -
Pembongkaran 1 M2 Bekisting 0.48 m2 15,645.80 7,509.98 0.001 - - - - - -
h Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Kolom 15 x 15 cm 0.35 m3 872,242.00 305,284.70 0.043 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 89.54 kg 11,860.70 1,062,006.91 0.148 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.08 m2 316,861.88 342,210.83 0.048 - - - - - -
Pembongkaran 1 M2 Bekisting 1.08 m2 15,645.80 16,897.46 0.002 - - - - - -
i Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Balok 15 x 20 cm 0.08 m3 872,242.00 69,779.36 0.010 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 19.41 kg 11,860.70 230,216.15 0.032 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.40 m2 316,861.88 126,744.75 0.018 - - - - - -
Pembongkaran 1 M2 Bekisting 0.40 m2 15,645.80 6,258.32 0.001 - - - - - -
j Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, pondasi 60 x 60 x 20 cm 0.54 m3 872,242.00 471,010.68 0.066 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 27.69 kg 11,860.70 328,422.73 0.046 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.90 m2 316,861.88 285,175.69 0.040 - - - - - -
Pembongkaran 1 M2 Bekisting 0.90 m2 15,645.80 14,081.22 0.002 - - - - - -
k Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm 2.00 unit 975,000.00 1,950,000.00 0.272 - - - - - -
l Tutup Manhole diameter 40 cm 2.00 bh 400,000.00 800,000.00 0.112 - - - - - -

Laporan Progres Mingguan ke-16


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)

D PEKERJAAN LAIN - LAIN


1 Pasang Bak Kontrol dengan tutup precast cetak diameter 40 cm 3.00 bh 850,000.00 2,550,000.00 0.356 - - - - - -
2 Pembersihan dan Pembuangan Bekas Galian Tanah IPAL Keluar Area 84.10 m3 67,972.30 5,716,470.45 0.797 - - - - - -
3 Pembongkaran 1 M2 Paving Block eksisting 31.40 m2 49,910.10 1,567,177.00 0.219 - - - - - -
4 Pemasangan 1 M2 kembali Paving Block eksisting 31.40 m2 64,463.10 2,024,141.20 0.282 - - - - - -
5 Pembongkaran dan Pemasangan kembali pipa PDAM yang terdampak galian 1.00 Ls 1,500,000.00 1,500,000.00 0.209 - - - - - -
6 Check Valve diameter 6 inch+ Reducer diameter 8x6 inch 1.00 bh 4,669,087.50 4,669,087.50 0.651 - - - - - -
7 Check Valve diameter 6 inch 1.00 bh 4,278,582.00 4,278,582.00 0.597 - - - - - -
8 Check Valve diameter 4 inch 2.00 bh 2,051,002.80 4,102,005.60 0.572 - - - - - -
9 Membuat rabat beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 1.55 m3 723,713.11 1,121,650.74 0.156 - - - - - -
10 Grill besi area ipal barat 1.50 m2 828,726.02 1,243,089.03 0.173 - - - - - -

345,803,198.30 48.239 17.220 3.996 21.216

JUMLAH 716,855,950.73 716,855,950.73 100.000 55.322 7.729 63.051


PRESTASI MINGGU LALU 716,855,950.73 55.322
PRESTASI MINGGU INI 7.729
PRESTASI SAMPAI DENGAN MINGGU INI 63.051
PRESTASI MENURUT SCHEDULE 64.616
LEBIH CEPAT (+) / TERLAMBAT (-) (1.565)

Yogyakarta, 13 September 2021


di buat oleh,
KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA

Noor Hasan Bambang Erlianto


Pengawas Pelaksana

Laporan Progres Mingguan ke-16


REKAPITULASI
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : XVI ( Enam belas )


Periode : 06 September 2021 sampai dengan 12 September 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
ADDENDUM II : 050 / 1909 / VII / 2021, TANGGAL 19 JULI 2021
ADDENDUM III : 050 / 0615 / IX / 2021, TANGGAL 6 SEPTEMBER 2021
NILAI KONTRAK ADDENDUM III : Rp 788,541,545.80
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO PEKERJAAN PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp (%) BOBOT % BOBOT % BOBOT %

I PEKERJAAN PERSIAPAN 11,873,371.04 1.66 1.309 0.050 1.359

II PEKERJAAN PERBAIKAN TALUD SEGMEN 5


A PEKERJAAN TANAH DAN BETON BERTULANG - - - - -
B PEKERJAAN PASANGAN DINDING - - - - -

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PENGECATAN - - - - -
B PEKERJAAN RUMAH TERDAMPAK 177,518,874.67 24.76 21.516 0.524 22.040

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PEMBERSIHAN SALURAN 181,660,506.72 25.34 15.276 3.160 18.436
B PEKERJAAN JARINGAN IPAL KOMUNAL 345,803,198.30 48.24 17.220 3.996 21.216

JUMLAH 716,855,950.73 100.000 55.322 7.729 63.051


PRESTASI MINGGU LALU 55.322
PRESTASI MINGGU INI 7.729
PRESTASI SAMPAI DENGAN MINGGU INI 63.051
PRESTASI MENURUT SCHEDULE 64.616
LEBIH CEPAT (+) / TERLAMBAT (-) (1.565)

Yogyakarta, 13 September 2021


di buat oleh,
PEJABAT PEMBUAT KOMITMEN TIM TEKNIS KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA
1. Cicilia Novi hendrawati, M.SC., M.Eng.
NIP. 19781102 200501 2 011 ...........................

2. Danang Dwi Wahyujati,S.Kom.,M.Eng


NIP. 19761028 199803 1 004 ...........................
SIGIT SETIAWAN, ST.MT 3. Sudaryanto
NIP. 19690605 199303 1 007 RISMAN WARCHAN ZULIANTO
NIP. 19770623 200501 1 013 ........................... Tim Leader Direktur
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : XVII ( Tujuh belas )


Periode : 13 September 2021 sampai dengan 19 September 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
ADDENDUM II : 050 / 1909 / VII / 2021, TANGGAL 19 JULI 2021
ADDENDUM III : 050 / 0615 / IX / 2021, TANGGAL 6 SEPTEMBER 2021
NILAI KONTRAK ADDENDUM III : Rp 788,541,545.80
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
I PEKERJAAN PERSIAPAN
1 Pembuatan Papan Nama Pekerjaan 1.00 bh 250,000.00 250,000.00 0.035 1.000 0.035 - - 1.000 0.035
2 Pengukuran dan Pemasangan Bouwplank 28.56 m 12,198.91 348,400.73 0.049 28.560 0.049 - - 28.560 0.049
3 Pembuatan bedeng pekerja 9.00 m2 383,330.04 3,449,970.32 0.481 9.000 0.481 - - 9.000 0.481
4 Mobilisasi Demobilisasi Alat Berat 1.00 ls 2,500,000.00 2,500,000.00 0.349 0.727 0.254 0.045 0.016 0.773 0.269
5 Pembuatan akses menuju badan sungai sementara - m2 113,128.49 - - - - - - - -
6 Dewatering dengan pompa air diesel 40.00 jam 25,000.00 1,000,000.00 0.139 29.091 0.101 1.818 0.006 30.909 0.108
7 SMKK 1.00 ls 4,325,000.00 4,325,000.00 0.603 0.727 0.439 0.045 0.027 0.773 0.466
11,873,371.04 1.656 1.359 0.050 1.408
II PEKERJAAN PERBAIKAN TALUD SEGMEN 5
A PEKERJAAN TANAH DAN BETON BERTULANG
1 Penggalian 1 M3 Tanah Biasa - m3 67,972.30 - - - - - - - -
2 Pengurugan Kembali 1 M3 Galian Tanah - m3 49,023.50 - - - - - - - -
3 Bongkaran Pasangan Batu dan Beton Eksisting - m3 71,953.20 - - - - - - - -
4 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area - m3 19,888.18 - - - - - - - -
5 Pemadatan Tanah Eksisting - m3 49,023.50 - - - - - - - -
6 Pengurugan dengan pasir urug - m3 178,388.92 - - - - - - - -
7 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 - m3 737,396.00 - - - - - - - -
8 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 - m3 872,242.00 - - - - - - - -
a Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
b Bekisting untuk pondasi beton ( dipakai 2 kali ) - m2 89,375.55 - - - - - - - -
c Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
9 Pekerjaan Beton Dinding Talud Beton -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 - m3 872,242.00 - - - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) - m2 316,861.88 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
10 Pekerjaan Beton Sloof 20x30cm -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 - m3 872,242.00 - - - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
c Memasang Bekisting untuk Sloof (dipakai 2 kali) - m2 89,375.55 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
11 Pekerjaan Beton Konsul Cantilever -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 - m3 872,242.00 - - - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
c Memasang Bekisting untuk Balok (dipakai 2 kali) - m2 120,181.13 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
12 Pekerjaan Plat Beton tebal 12 cm -
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) - m3 872,242.00 - - - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis - kg 10,697.66 - - - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) - m2 316,861.88 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
13 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm - m 77,312.85 - - - - - - - -
14 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm - m 86,676.29 - - - - - - - -
15 Memasang Stek Besi - kg 11,860.70 - - - - - - - -
16 Pekerjaan Plat Beton Pot tebal 10 cm -
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) - m3 872,242.00 - - - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
c Bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm - m2 118,158.83 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
- - - - -

Laporan Progres Mingguan ke-17


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
B PEKERJAAN PASANGAN DINDING
1 Pemasangan Dinding Bata Merah Bakar Sekam Tebal 1/2 Bata Camp. 1SP 6PP - m2 116,576.48 - - - - - - - -
2 Pemasangan Plesteran 1 Pc 6 Pp Tebal 15 mm - m2 54,689.70 - - - - - - - -
3 Pemasangan Acian - m2 33,411.23 - - - - - - - -
4 Pemasangan Plesteran Skoning 1 Pc 2Pp lebar 10 cm - m 55,075.90 - - - - - - - -
5 Pemasangan Kepala Kolom - bh 50,000.00 - - - - - - - -
- - - - -
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PENGECATAN
1 Pengecatan Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Weathershield luar ruangan - m2 11,686.42 - - - - - - - -
- - - - -
B PEKERJAAN RUMAH TERDAMPAK
I. PEKERJAAN BONGKARAN
1 Membongkar 1 m2 genteng / sirap untuk dipergunakan lagi 77.17 m2 3,628.42 280,005.33 0.039 38.585 0.020 5.479 0.003 44.064 0.022
2 Membongkar 1 m3 kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi 0.37 m3 991,595.91 366,890.49 0.051 0.185 0.026 0.026 0.004 0.211 0.029
3 Pembongkaran 1 m3 pasangan bata merah dan membersihkan 12.72 m3 185,908.38 2,364,754.54 0.330 8.093 0.210 - - 8.093 0.210
4 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 1.50 m3 688,832.33 1,033,248.50 0.144 0.858 0.082 - - 0.858 0.082
II. PEKERJAAN TANAH -
1 Menggali 1 m3 tanah biasa sedalam 1 meter 27.22 m3 67,972.30 1,850,206.01 0.258 27.220 0.258 - - 27.220 0.258
2 Pengurugan Kembali 1 m3 Galian Tanah 10.11 m3 18,745.83 189,520.38 0.026 10.110 0.026 - - 10.110 0.026
3 Pengurugan dengan pasir urug 1.82 m3 173,624.00 315,995.68 0.044 1.820 0.044 - - 1.820 0.044
4 Peninggian peil lantai 9.18 m3 18,745.83 172,086.75 0.024 9.180 0.024 - - 9.180 0.024
III. PEKERJAAN PONDASI -
1 Memasang 1 m3 pondasi batu belah, campuran 1 PC 6 PP 16.49 m2 665,195.09 10,969,067.11 1.530 16.490 1.530 - - 16.490 1.530
IV. PEKERJAAN BETON -
1 Membuat 1 m3 Sloof beton bertulang (200 kg besi + bekisting) 1.06 m3 3,844,764.87 4,075,450.77 0.569 1.060 0.569 - - 1.060 0.569
2 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) 2.29 m3 7,083,735.01 16,221,753.18 2.263 2.290 2.263 - - 2.290 2.263
3 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) 3.05 m3 5,659,422.09 17,261,237.38 2.408 3.050 2.408 - - 3.050 2.408
4 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.14 m3 723,713.11 101,319.83 0.014 0.140 0.014 - - 0.140 0.014
5 Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting) 0.57 m3 3,127,107.54 1,782,451.30 0.249 0.570 0.249 - - 0.570 0.249
6 Sloof 150 x 200 dengan beton K 225 Tulangan 105 kg 0.74 m3 3,295,166.46 2,438,423.18 0.340 0.740 0.340 - - 0.740 0.340
7 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm 67.35 m' 77,312.85 5,207,020.70 0.726 67.350 0.726 - - 67.350 0.726
8 Balok 150 x 200 dengan beton K 225 Tulangan 105 kg 1.01 m3 3,705,897.33 3,742,956.31 0.522 1.010 0.522 - - 1.010 0.522
9 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm 54.15 m' 86,676.29 4,693,521.24 0.655 54.150 0.655 - - 54.150 0.655
10 Membuat 1 m3 Plat Lantai beton bertulang 2.95 m3 3,119,381.73 9,202,176.12 1.284 2.950 1.284 - - 2.950 1.284
11 Membuat 1 m3 Plat Tangga beton bertulang 0.72 m3 3,119,381.73 2,245,954.85 0.313 0.720 0.313 - - 0.720 0.313
12 Membuat 1 m3 Plat Water torn beton bertulang 0.42 m3 3,119,381.73 1,310,140.33 0.183 0.420 0.183 - - 0.420 0.183
V. PEKERJAAN DINDING -
1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP 161.84 m2 116,576.48 18,866,738.23 2.632 161.840 2.632 - - 161.840 2.632
2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP, trap tangga 6.30 m2 250,668.02 1,579,208.52 0.220 6.300 0.220 - - 6.300 0.220
VI PEKERJAAN KAYU -
1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.27 m3 16,443,774.77 4,439,819.19 0.619 0.270 0.619 - - 0.270 0.619
Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.02 m3 8,048,535.00 160,970.70 0.022 0.020 0.022 - - 0.020 0.022
2 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti 12.32 m2 644,715.80 7,942,898.68 1.108 12.320 1.108 - - 12.320 1.108
3 Memasang 1 m3 konstruksi gordeng, kayu glugu - m3 4,450,537.65 - - - - - - - -
VII. PEKERJAAN PLESTERAN -
1 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm 96.76 m2 54,689.70 5,291,775.27 0.738 96.760 0.738 - - 96.760 0.738
2 Memasang 1 m2 acian 96.76 m2 33,411.23 3,232,870.55 0.451 96.760 0.451 - - 96.760 0.451
3 Pemasangan 1 m2 plesteran ciprat 1SP : 2PP 33.50 m2 45,029.48 1,508,487.73 0.210 33.500 0.210 - - 33.500 0.210
VIII. PEKERJAAN PENGECATAN -
1 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 96.76 m2 11,686.42 1,130,778.06 0.158 - - 96.760 0.158 96.760 0.158
IX. PEKERJAAN PENUTUP ATAP -
1 Memasang 1 m2 Atap Galvalum (Paket) 78.51 m3 190,000.00 14,917,137.50 2.081 74.586 1.977 - - 74.586 1.977
2 Pemasangan 1 m talang datar Galvalum lebar 60 cm - m' 105,483.99 - - - - - - - -
3 Pemasangan 1 m talang datar U PVC 8.64 m' 73,235.87 632,903.97 0.088 - - - - - -
X. PEKERJAAN PENUTUP LANTAI DAN DINDING -
1 Memasang 1 m2 lantai keramik (30 x 30) cm - m2 114,193.22 - - - - - - - -
2 Membuat rabat beton lantai mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 2.08 m3 723,713.11 1,504,722.31 0.210 2.079 0.210 - - 2.079 0.210
3 Memasang 1 m2 lantai keramik (20 x 20) cm 4.99 m2 184,674.28 921,524.65 0.129 - - 4.990 0.129 4.990 0.129
XI. PEKERJAAN SANITASI - - - - -
1 Memasang 1 buah Kloset Jongkok Porselen 2.00 bh 280,952.58 561,905.16 0.078 - - 2.000 0.078 2.000 0.078
2 Memasang 1 m Pipa PVC tipe AW 16.00 m' 19,406.20 310,499.27 0.043 16.000 0.043 - - 16.000 0.043
3 Memasang 1 m Pipa PVC tipe AW 1 8.00 m' 22,254.33 178,034.63 0.025 8.000 0.025 - - 8.000 0.025
4 Memasang 1 m Pipa PVC tipe AW 3 18.00 m' 63,036.61 1,134,659.00 0.158 16.000 0.141 - - 16.000 0.141
5 Memasang 1 buah Kran atau 2.00 bh 46,068.18 92,136.37 0.013 - - 2.000 0.013 2.000 0.013
6 Memasang 1 buah Floor Drain 2.00 bh 80,836.18 161,672.35 0.023 - - 2.000 0.023 2.000 0.023
7 Memasang 1 buah Pintu Kamar Mandi 2.00 bh 650,000.00 1,300,000.00 0.181 2.000 0.181 - - 2.000 0.181
8 Pemasangan 1 M Pipa PVC tipe D 4 12.00 m 85,618.17 1,027,418.08 0.143 10.000 0.119 2.000 0.024 12.000 0.143

Laporan Progres Mingguan ke-17


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
XII. PEKERJAAN ELEKTRIKAL -
1 Instalasi Penerangan menggunakan kabel NYY 3x2,5mm² dalam pipa conduit Ø 20mm. 10.00 titik 105,000.00 1,050,000.00 0.146 10.000 0.146 - - 10.000 0.146
2 Instalasi stop kontak dinding, menggunakan kabel NYM 3x2,5mm² 5.00 titik 100,000.00 500,000.00 0.070 5.000 0.070 - - 5.000 0.070
3 Saklar tunggal inbow, 1 gang 1 way 4.00 bh 20,000.00 80,000.00 0.011 4.000 0.011 - - 4.000 0.011
4 Saklar seri inbow, 1 gang 2 way 4.00 bh 25,000.00 100,000.00 0.014 4.000 0.014 - - 4.000 0.014
5 Stop kontak wall type 1ph, 16A, 1 gang 5.00 bh 20,000.00 100,000.00 0.014 5.000 0.014 - - 5.000 0.014
6 Lampu PLC 18 Watt dengan fitting gantung 8.00 bh 75,000.00 600,000.00 0.084 8.000 0.084 - - 8.000 0.084
7 Lampu PLC 7 Watt dengan fitting gantung 2.00 bh 65,000.00 130,000.00 0.018 2.000 0.018 - - 2.000 0.018
8 Penyambungan kabel 1.00 Ls 500,000.00 500,000.00 0.070 1.000 0.070 - - 1.000 0.070
9 Box MCB + MCB 2.00 bh 250,000.00 500,000.00 0.070 2.000 0.070 - - 2.000 0.070
XIII. PEKERJAAN LAIN-LAIN -
1 Pintu Folding gate 6.00 m2 788,049.93 4,728,299.56 0.660 6.000 0.660 - - 6.000 0.660
2 Railling pengaman besi Hollow 40x40 / 40x20 mm, finishing cat 11.48 m2 550,000.00 6,312,240.00 0.881 5.738 0.440 - - 5.738 0.440
XIV. Rumah Timur sungai - -
1 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm 4.50 m' 77,312.85 347,907.84 0.049 - - - - - -
2 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm 5.70 m' 86,676.29 494,054.87 0.069 - - - - - -
3 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP 3.10 m2 116,576.48 361,387.10 0.050 - - - - - -
4 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm 7.41 m2 54,689.70 405,250.67 0.057 - - - - - -
5 Memasang 1 m2 acian 7.41 m2 33,411.23 247,577.21 0.035 - - - - - -
6 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 7.41 m2 11,686.42 86,596.38 0.012 - - - - - -
7 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.13 m3 8,048,535.00 1,046,309.55 0.146 - - - - - -
8 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti 4.64 m2 644,715.80 2,991,481.32 0.417 - - - - - -
9 Memasang 1 m2 Atap Galvalum (Paket) 17.55 m2 190,000.00 3,334,500.00 0.465 - - - - - -
10 Membuat rabat beton lantai mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 1.22 m3 723,713.11 882,929.99 0.123 - - - - - -

177,518,874.67 24.764 22.040 0.430 22.470


III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PEMBERSIHAN SALURAN
1 Penggalian Tanah Lumpur dan Endapan Limbah Sedalam 30 cm 70.70 m3 109,311.98 7,728,356.66 1.078 65.736 1.002 - - 65.736 1.002
2 Pembersihan dan Pembuangan Tanah Lumpur dan Limbah Keluar Area 89.07 m3 29,796.55 2,653,978.98 0.370 84.822 0.353 - - 84.822 0.353
3 Pemadatan Tanah Eksisting 70.70 m3 49,023.50 3,465,961.48 0.483 59.245 0.405 - - 59.245 0.405
4 Pengurugan dengan pasir urug, 10 cm 21.87 m3 178,388.92 3,901,365.68 0.544 18.544 0.461 - - 18.544 0.461
Pengurugan dengan pasir urug, 10 cm 1.69 m3 173,624.00 293,424.56 0.041 1.156 0.028 - - 1.156 0.028
5 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 10.93 m3 737,396.00 8,059,738.25 1.124 8.744 0.899 - - 8.744 0.899
Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.85 m3 723,713.11 615,156.14 0.086 0.544 0.055 - - 0.544 0.055
6 Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 23.56 m3 872,242.00 20,550,021.46 2.867 18.515 2.253 - - 18.515 2.253
a Jaring Kawat baja/Wire Mesh M5 1 lapis 501.73 kg 10,697.66 5,367,334.57 0.749 300.680 0.449 50.173 0.075 350.853 0.524
7 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 158.40 m 77,312.85 12,246,356.04 1.708 106.560 1.149 - - 106.560 1.149
8 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 583.98 m 86,676.29 50,617,221.34 7.061 573.789 6.938 - - 573.789 6.938
9 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,2m, K.300 - bh 626,150.00 - - - - - - - -
10 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,8m, K.300 - bh 750,000.00 - - - - - - - -
11 Pekerjaan Plat Beton tebal 15 cm - - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 6.81 m3 872,242.00 5,939,968.00 0.829 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis 480.26 kg 10,697.66 5,137,655.91 0.717 144.078 0.215 159.116 0.237 303.194 0.452
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 10.17 m2 316,861.88 3,222,485.34 0.450 8.501 0.376 - - 8.501 0.376
d Pembongkaran 1 M2 Bekisting 10.17 m2 15,645.80 159,117.77 0.022 - - - - - -
12 Pekerjaan Plat Beton tebal 10 cm - - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 22.73 m3 872,242.00 19,826,060.60 2.766 11.365 1.383 4.546 0.553 15.911 1.936
b Jaring Kawat baja/Wire Mesh M8 1 lapis 1,186.92 kg 10,697.66 12,697,260.97 1.771 454.602 0.678 296.730 0.443 751.332 1.121
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 57.68 m2 316,861.88 18,276,593.34 2.550 40.528 1.791 11.536 0.510 52.064 2.301
d Pembongkaran 1 M2 Bekisting 57.68 m2 15,645.80 902,449.63 0.126 - - - - - -
181,660,506.72 25.341 18.436 1.818 20.254
B PEKERJAAN JARINGAN IPAL KOMUNAL
1 Pekerjaan Galian Tanah Pipa 31.93 m3 67,972.30 2,170,355.55 0.303 - - - - - -
2 Pengurugan dengan pasir urug 14.41 m3 178,388.92 2,570,584.34 0.359 - - - - - -
3 Pengurugan Kembali 1 M3 Galian Tanah 12.97 m3 49,023.50 635,966.29 0.089 - - - - - -
4 Pemasangan 1 M Pipa PVC tipe AW 4 - m 90,907.55 - -
5 Saluran Pipa Air Limbah SDR - 41, Dia 15 cm , inc. fitting & Assecories - m 133,200.00 - - - - - - - -
6 Saluran Pipa Air Limbah SDR - 41, Dia 20 cm, , inc. fitting & Assecories - m 203,900.00 - - - - - - - -
7 Pemasangan Clean Out Inc. Fitting & Assecories 43.00 ttk 185,000.00 7,955,000.00 1.110 22.000 0.568 - - 22.000 0.568
8 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 100 org, 20 m3 / hari, - unit 7,500,000.00 - - - - - - - -
(Galian, Urugan, Pondasi, Tutup Beton, Penyambungan Instalasi) -
9 Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm - unit 975,000.00 - - - - - - - -
10 Pekerjaan Sumur Resapan, Dia 100 cm, Kedalaman 2 m, Inc. Tutup Beton Berlubang - ttk 500,000.00 - - - - - - - -
11 Grill Beton Penutup Sumur Resapan - unit 750,000.00 - - - - - - - -
12 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 7.05 m3 688,832.33 4,856,267.95 0.677 1.484 0.143 - - 1.484 0.143
13 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area 7.05 m3 19,888.18 140,211.63 0.020 1.484 0.004 - - 1.484 0.004
14 Pemasangan 1 M Pipa PVC tipe D 6 422.00 m 133,200.00 56,210,400.00 7.841 320.881 5.962 - - 320.881 5.962
15 Pemasangan 1 M Pipa PVC tipe D 4 165.50 m 85,618.17 14,169,807.73 1.977 51.122 0.611 59.601 0.712 110.723 1.322
16 Pekerjaan Sumur Resapan kedalaman 4 Buis Beton Dia 80 cm 13.00 ttk 474,124.46 6,163,617.96 0.860 13.000 0.860 - - 13.000 0.860
17 Pasang Grill Besi Penutup Sumur Resapan 15.00 unit 826,875.00 12,403,125.00 1.730 6.000 0.692 7.071 0.816 13.071 1.508

Laporan Progres Mingguan ke-17


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)

C PEKERJAAN PEMASANGAN DAN PENGADAAN INSTALASI IPAL


1 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 50 org, 10 m3 / hari
a Pengadaan Unit IPAL kap 50 org, 10 m3 / hari 1.00 unit 110,250,000.00 110,250,000.00 15.380 0.500 7.690 - - 0.500 7.690
b Galian Tanah 57.21 m3 67,972.30 3,888,695.29 0.542 57.210 0.542 - - 57.210 0.542
c Pengurugan Kembali 1 M3 Galian Tanah 2.39 m3 49,023.50 117,166.17 0.016 2.390 0.016 - - 2.390 0.016
d Pengurugan dengan pasir urug 4.98 m3 178,388.92 888,028.96 0.124 - - - - - -
e Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Dinding, Lantai dan Tutup 11.77 m3 872,242.00 10,266,288.31 1.432 8.698 1.058 0.454 0.055 9.152 1.114
Jaring Kawat baja/Wire Mesh M8 534.95 kg 10,697.66 5,722,710.68 0.798 527.409 0.787 - - 527.409 0.787
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 30.14 m2 316,861.88 9,550,217.12 1.332 22.273 0.985 4.224 0.187 26.498 1.171
Pembongkaran 1 M2 Bekisting 30.14 m2 15,645.80 471,564.35 0.066 22.273 0.049 4.224 0.009 26.498 0.058
f Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Inlet 0.30 m3 872,242.00 261,672.60 0.037 0.165 0.020 0.057 0.007 0.222 0.027
Jaring Kawat baja/Wire Mesh M8 11.06 kg 10,697.66 118,316.07 0.017 6.083 0.009 2.101 0.003 8.184 0.012
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.66 m2 316,861.88 209,128.84 0.029 0.363 0.016 0.125 0.006 0.488 0.022
Pembongkaran 1 M2 Bekisting 0.66 m2 15,645.80 10,326.23 0.001 0.363 0.001 0.125 0.000 0.488 0.001
g Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Outlet 0.41 m3 872,242.00 357,619.22 0.050 0.246 0.030 - - 0.246 0.030
Jaring Kawat baja/Wire Mesh M8 14.98 kg 10,697.66 160,250.88 0.022 8.988 0.013 - - 8.988 0.013
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.96 m2 316,861.88 304,187.41 0.042 0.576 0.025 - - 0.576 0.025
Pembongkaran 1 M2 Bekisting 0.96 m2 15,645.80 15,019.97 0.002 0.576 0.001 - - 0.576 0.001
h Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Kolom 15 x 15 cm 0.47 m3 872,242.00 409,953.74 0.057 0.470 0.057 - - 0.470 0.057
Pembesian dg Besi Polos atau Besi Ulir 119.39 kg 11,860.70 1,416,048.75 0.198 119.390 0.198 - - 119.390 0.198
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.44 m2 316,861.88 456,281.11 0.064 1.440 0.064 - - 1.440 0.064
Pembongkaran 1 M2 Bekisting 1.44 m2 15,645.80 22,529.95 0.003 1.440 0.003 - - 1.440 0.003
i Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Balok 15 x 20 cm 0.12 m3 872,242.00 104,669.04 0.015 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 23.91 kg 11,860.70 283,589.29 0.040 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.55 m2 316,861.88 174,274.03 0.024 - - - - - -
Pembongkaran 1 M2 Bekisting 0.55 m2 15,645.80 8,605.19 0.001 - - - - - -
j Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, pondasi 60 x 60 x 20 cm 0.72 m3 872,242.00 628,014.24 0.088 0.576 0.070 - - 0.576 0.070
Pembesian dg Besi Polos atau Besi Ulir 36.93 kg 11,860.70 438,015.58 0.061 29.544 0.049 - - 29.544 0.049
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.20 m2 316,861.88 380,234.26 0.053 0.960 0.042 - - 0.960 0.042
Pembongkaran 1 M2 Bekisting 1.20 m2 15,645.80 18,774.96 0.003 0.960 0.002 - - 0.960 0.002
k Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm 3.00 unit 975,000.00 2,925,000.00 0.408 - - - - - -
l Tutup Manhole diameter 40 cm 2.00 bh 400,000.00 800,000.00 0.112 - - - - - -

2 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 20 org, 2 m3 / hari
a Pengadaan Unit IPAL kap 20 org, 2 m3 / hari 1.00 unit 38,697,750.00 38,697,750.00 5.398 - - - - - -
b Galian Tanah 26.89 m3 67,972.30 1,827,775.15 0.255 26.890 0.255 - - 26.890 0.255
c Pengurugan Kembali 1 M3 Galian Tanah 1.33 m3 49,023.50 65,201.26 0.009 - - - - - -
d Pengurugan dengan pasir urug 2.16 m3 178,388.92 385,973.86 0.054 - - - - - -
e Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Dinding, Lantai dan Tutup 6.37 m3 872,242.00 5,556,181.52 0.775 - - 5.962 0.725 5.962 0.725
Jaring Kawat baja/Wire Mesh M8 270.48 kg 10,697.66 2,893,501.79 0.404 135.240 0.202 117.929 0.176 253.169 0.378
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 8.68 m2 316,861.88 2,750,361.13 0.384 4.340 0.192 3.784 0.167 8.124 0.359
Pembongkaran 1 M2 Bekisting 8.68 m2 15,645.80 135,805.53 0.019 - - 3.038 0.007 3.038 0.007
f Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Inlet 0.17 m3 872,242.00 148,281.14 0.021 - - - - - -
Jaring Kawat baja/Wire Mesh M8 6.48 kg 10,697.66 69,320.81 0.010 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.33 m2 316,861.88 104,564.42 0.015 - - - - - -
Pembongkaran 1 M2 Bekisting 0.33 m2 15,645.80 5,163.11 0.001 - - - - - -
g Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Outlet 0.23 m3 872,242.00 200,615.66 0.028 - - - - - -
Jaring Kawat baja/Wire Mesh M8 8.44 kg 10,697.66 90,288.21 0.013 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.48 m2 316,861.88 152,093.70 0.021 - - - - - -
Pembongkaran 1 M2 Bekisting 0.48 m2 15,645.80 7,509.98 0.001 - - - - - -
h Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Kolom 15 x 15 cm 0.35 m3 872,242.00 305,284.70 0.043 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 89.54 kg 11,860.70 1,062,006.91 0.148 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.08 m2 316,861.88 342,210.83 0.048 - - - - - -
Pembongkaran 1 M2 Bekisting 1.08 m2 15,645.80 16,897.46 0.002 - - - - - -
i Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Balok 15 x 20 cm 0.08 m3 872,242.00 69,779.36 0.010 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 19.41 kg 11,860.70 230,216.15 0.032 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.40 m2 316,861.88 126,744.75 0.018 - - - - - -
Pembongkaran 1 M2 Bekisting 0.40 m2 15,645.80 6,258.32 0.001 - - - - - -
j Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, pondasi 60 x 60 x 20 cm 0.54 m3 872,242.00 471,010.68 0.066 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 27.69 kg 11,860.70 328,422.73 0.046 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.90 m2 316,861.88 285,175.69 0.040 - - - - - -
Pembongkaran 1 M2 Bekisting 0.90 m2 15,645.80 14,081.22 0.002 - - - - - -
k Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm 2.00 unit 975,000.00 1,950,000.00 0.272 - - - - - -
l Tutup Manhole diameter 40 cm 2.00 bh 400,000.00 800,000.00 0.112 - - - - - -

Laporan Progres Mingguan ke-17


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)

D PEKERJAAN LAIN - LAIN


1 Pasang Bak Kontrol dengan tutup precast cetak diameter 40 cm 3.00 bh 850,000.00 2,550,000.00 0.356 - - - - - -
2 Pembersihan dan Pembuangan Bekas Galian Tanah IPAL Keluar Area 84.10 m3 67,972.30 5,716,470.45 0.797 - - - - - -
3 Pembongkaran 1 M2 Paving Block eksisting 31.40 m2 49,910.10 1,567,177.00 0.219 - - - - - -
4 Pemasangan 1 M2 kembali Paving Block eksisting 31.40 m2 64,463.10 2,024,141.20 0.282 - - - - - -
5 Pembongkaran dan Pemasangan kembali pipa PDAM yang terdampak galian 1.00 Ls 1,500,000.00 1,500,000.00 0.209 - - - - - -
6 Check Valve diameter 6 inch+ Reducer diameter 8x6 inch 1.00 bh 4,669,087.50 4,669,087.50 0.651 - - - - - -
7 Check Valve diameter 6 inch 1.00 bh 4,278,582.00 4,278,582.00 0.597 - - - - - -
8 Check Valve diameter 4 inch 2.00 bh 2,051,002.80 4,102,005.60 0.572 - - - - - -
9 Membuat rabat beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 1.55 m3 723,713.11 1,121,650.74 0.156 - - - - - -
10 Grill besi area ipal barat 1.50 m2 828,726.02 1,243,089.03 0.173 - - - - - -

345,803,198.30 48.239 21.216 2.870 24.086

JUMLAH 716,855,950.73 100.000 63.051 5.168 68.219


PRESTASI MINGGU LALU 716,855,950.73 63.051
PRESTASI MINGGU INI 5.168
PRESTASI SAMPAI DENGAN MINGGU INI 68.219
PRESTASI MENURUT SCHEDULE 70.325
LEBIH CEPAT (+) / TERLAMBAT (-) (2.106)

Yogyakarta, 20 September 2021


di buat oleh,
KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA

Noor Hasan Bambang Erlianto


Pengawas Pelaksana

Laporan Progres Mingguan ke-17


REKAPITULASI
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : XVII ( Tujuh belas )


Periode : 13 September 2021 sampai dengan 19 September 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
ADDENDUM II : 050 / 1909 / VII / 2021, TANGGAL 19 JULI 2021
ADDENDUM III : 050 / 0615 / IX / 2021, TANGGAL 6 SEPTEMBER 2021
NILAI KONTRAK ADDENDUM III : Rp 788,541,545.80
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO PEKERJAAN PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp (%) BOBOT % BOBOT % BOBOT %

I PEKERJAAN PERSIAPAN 11,873,371.04 1.656 1.359 0.050 1.408

II PEKERJAAN PERBAIKAN TALUD SEGMEN 5


A PEKERJAAN TANAH DAN BETON BERTULANG - - - - -
B PEKERJAAN PASANGAN DINDING - - - - -

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PENGECATAN - - - - -
B PEKERJAAN RUMAH TERDAMPAK 177,518,874.67 24.764 22.040 0.430 22.470

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PEMBERSIHAN SALURAN 181,660,506.72 25.341 18.436 1.818 20.254
B PEKERJAAN JARINGAN IPAL KOMUNAL 345,803,198.30 48.239 21.216 2.870 24.086

JUMLAH 716,855,950.73 100.000 63.051 5.168 68.219


PRESTASI MINGGU LALU - 63.051
PRESTASI MINGGU INI 5.168
PRESTASI SAMPAI DENGAN MINGGU INI 68.219
PRESTASI MENURUT SCHEDULE 70.325
LEBIH CEPAT (+) / TERLAMBAT (-) (2.106)

Yogyakarta, 20 September 2021


di buat oleh,
PEJABAT PEMBUAT KOMITMEN TIM TEKNIS KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA
1. Cicilia Novi hendrawati, M.SC., M.Eng.
NIP. 19781102 200501 2 011 ...........................

2. Danang Dwi Wahyujati,S.Kom.,M.Eng


NIP. 19761028 199803 1 004 ...........................
SIGIT SETIAWAN, ST.MT 3. Sudaryanto
NIP. 19690605 199303 1 007 RISMAN WARCHAN ZULIANTO
NIP. 19770623 200501 1 013 ........................... Tim Leader Direktur
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : XVIII ( Delapan belas )


Periode : 20 September 2021 sampai dengan 26 September 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
ADDENDUM II : 050 / 1909 / VII / 2021, TANGGAL 19 JULI 2021
ADDENDUM III : 050 / 0615 / IX / 2021, TANGGAL 6 SEPTEMBER 2021
NILAI KONTRAK ADDENDUM III : Rp 788,541,545.80
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
I PEKERJAAN PERSIAPAN
1 Pembuatan Papan Nama Pekerjaan 1.00 bh 250,000.00 250,000.00 0.035 1.000 0.035 - - 1.000 0.035
2 Pengukuran dan Pemasangan Bouwplank 28.56 m 12,198.91 348,400.73 0.049 28.560 0.049 - - 28.560 0.049
3 Pembuatan bedeng pekerja 9.00 m2 383,330.04 3,449,970.32 0.481 9.000 0.481 - - 9.000 0.481
4 Mobilisasi Demobilisasi Alat Berat 1.00 ls 2,500,000.00 2,500,000.00 0.349 0.773 0.269 0.045 0.016 0.818 0.285
5 Pembuatan akses menuju badan sungai sementara - m2 113,128.49 - - - - - - - -
6 Dewatering dengan pompa air diesel 40.00 jam 25,000.00 1,000,000.00 0.139 30.909 0.108 1.818 0.006 32.727 0.114
7 SMKK 1.00 ls 4,325,000.00 4,325,000.00 0.603 0.773 0.466 0.045 0.027 0.818 0.494
11,873,371.04 1.656 1.408 0.050 1.458
II PEKERJAAN PERBAIKAN TALUD SEGMEN 5
A PEKERJAAN TANAH DAN BETON BERTULANG
1 Penggalian 1 M3 Tanah Biasa - m3 67,972.30 - - - - - - - -
2 Pengurugan Kembali 1 M3 Galian Tanah - m3 49,023.50 - - - - - - - -
3 Bongkaran Pasangan Batu dan Beton Eksisting - m3 71,953.20 - - - - - - - -
4 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area - m3 19,888.18 - - - - - - - -
5 Pemadatan Tanah Eksisting - m3 49,023.50 - - - - - - - -
6 Pengurugan dengan pasir urug - m3 178,388.92 - - - - - - - -
7 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 - m3 737,396.00 - - - - - - - -
8 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 - m3 872,242.00 - - - - - - - -
a Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
b Bekisting untuk pondasi beton ( dipakai 2 kali ) - m2 89,375.55 - - - - - - - -
c Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
9 Pekerjaan Beton Dinding Talud Beton -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 - m3 872,242.00 - - - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) - m2 316,861.88 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
10 Pekerjaan Beton Sloof 20x30cm -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 - m3 872,242.00 - - - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
c Memasang Bekisting untuk Sloof (dipakai 2 kali) - m2 89,375.55 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
11 Pekerjaan Beton Konsul Cantilever -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 - m3 872,242.00 - - - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
c Memasang Bekisting untuk Balok (dipakai 2 kali) - m2 120,181.13 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
12 Pekerjaan Plat Beton tebal 12 cm -
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) - m3 872,242.00 - - - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis - kg 10,697.66 - - - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) - m2 316,861.88 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
13 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm - m 77,312.85 - - - - - - - -
14 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm - m 86,676.29 - - - - - - - -
15 Memasang Stek Besi - kg 11,860.70 - - - - - - - -
16 Pekerjaan Plat Beton Pot tebal 10 cm -
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) - m3 872,242.00 - - - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
c Bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm - m2 118,158.83 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
- - - - -
B PEKERJAAN PASANGAN DINDING
1 Pemasangan Dinding Bata Merah Bakar Sekam Tebal 1/2 Bata Camp. 1SP 6PP - m2 116,576.48 - - - - - - - -
2 Pemasangan Plesteran 1 Pc 6 Pp Tebal 15 mm - m2 54,689.70 - - - - - - - -
3 Pemasangan Acian - m2 33,411.23 - - - - - - - -
4 Pemasangan Plesteran Skoning 1 Pc 2Pp lebar 10 cm - m 55,075.90 - - - - - - - -

Laporan Progres Mingguan ke-18


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
5 Pemasangan Kepala Kolom - bh 50,000.00 - - - - - - - -
- - - - -
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PENGECATAN
1 Pengecatan Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Weathershield luar ruangan - m2 11,686.42 - - - - - - - -
- - - - -
B PEKERJAAN RUMAH TERDAMPAK
I. PEKERJAAN BONGKARAN
1 Membongkar 1 m2 genteng / sirap untuk dipergunakan lagi 77.17 m2 3,628.42 280,005.33 0.039 44.064 0.022 16.206 0.008 60.269 0.031
2 Membongkar 1 m3 kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi 0.37 m3 991,595.91 366,890.49 0.051 0.211 0.029 0.078 0.011 0.289 0.040
3 Pembongkaran 1 m3 pasangan bata merah dan membersihkan 12.72 m3 185,908.38 2,364,754.54 0.330 8.093 0.210 2.671 0.069 10.764 0.279
4 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 1.50 m3 688,832.33 1,033,248.50 0.144 0.858 0.082 0.315 0.030 1.173 0.113
II. PEKERJAAN TANAH -
1 Menggali 1 m3 tanah biasa sedalam 1 meter 27.22 m3 67,972.30 1,850,206.01 0.258 27.220 0.258 - - 27.220 0.258
2 Pengurugan Kembali 1 m3 Galian Tanah 10.11 m3 18,745.83 189,520.38 0.026 10.110 0.026 - - 10.110 0.026
3 Pengurugan dengan pasir urug 1.82 m3 173,624.00 315,995.68 0.044 1.820 0.044 - - 1.820 0.044
4 Peninggian peil lantai 9.18 m3 18,745.83 172,086.75 0.024 9.180 0.024 - - 9.180 0.024
III. PEKERJAAN PONDASI -
1 Memasang 1 m3 pondasi batu belah, campuran 1 PC 6 PP 16.49 m2 665,195.09 10,969,067.11 1.530 16.490 1.530 - - 16.490 1.530
IV. PEKERJAAN BETON -
1 Membuat 1 m3 Sloof beton bertulang (200 kg besi + bekisting) 1.06 m3 3,844,764.87 4,075,450.77 0.569 1.060 0.569 - - 1.060 0.569
2 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) 2.29 m3 7,083,735.01 16,221,753.18 2.263 2.290 2.263 - - 2.290 2.263
3 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) 3.05 m3 5,659,422.09 17,261,237.38 2.408 3.050 2.408 - - 3.050 2.408
4 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.14 m3 723,713.11 101,319.83 0.014 0.140 0.014 - - 0.140 0.014
5 Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting) 0.57 m3 3,127,107.54 1,782,451.30 0.249 0.570 0.249 - - 0.570 0.249
6 Sloof 150 x 200 dengan beton K 225 Tulangan 105 kg 0.74 m3 3,295,166.46 2,438,423.18 0.340 0.740 0.340 - - 0.740 0.340
7 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm 67.35 m' 77,312.85 5,207,020.70 0.726 67.350 0.726 - - 67.350 0.726
8 Balok 150 x 200 dengan beton K 225 Tulangan 105 kg 1.01 m3 3,705,897.33 3,742,956.31 0.522 1.010 0.522 - - 1.010 0.522
9 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm 54.15 m' 86,676.29 4,693,521.24 0.655 54.150 0.655 - - 54.150 0.655
10 Membuat 1 m3 Plat Lantai beton bertulang 2.95 m3 3,119,381.73 9,202,176.12 1.284 2.950 1.284 - - 2.950 1.284
11 Membuat 1 m3 Plat Tangga beton bertulang 0.72 m3 3,119,381.73 2,245,954.85 0.313 0.720 0.313 - - 0.720 0.313
12 Membuat 1 m3 Plat Water torn beton bertulang 0.42 m3 3,119,381.73 1,310,140.33 0.183 0.420 0.183 - - 0.420 0.183
V. PEKERJAAN DINDING -
1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP 161.84 m2 116,576.48 18,866,738.23 2.632 161.840 2.632 - - 161.840 2.632
2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP, trap tangga 6.30 m2 250,668.02 1,579,208.52 0.220 6.300 0.220 - - 6.300 0.220
VI PEKERJAAN KAYU -
1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.27 m3 16,443,774.77 4,439,819.19 0.619 0.270 0.619 - - 0.270 0.619
Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.02 m3 8,048,535.00 160,970.70 0.022 0.020 0.022 - - 0.020 0.022
2 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti 12.32 m2 644,715.80 7,942,898.68 1.108 12.320 1.108 - - 12.320 1.108
3 Memasang 1 m3 konstruksi gordeng, kayu glugu - m3 4,450,537.65 - - - - - - - -
VII. PEKERJAAN PLESTERAN -
1 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm 96.76 m2 54,689.70 5,291,775.27 0.738 96.760 0.738 - - 96.760 0.738
2 Memasang 1 m2 acian 96.76 m2 33,411.23 3,232,870.55 0.451 96.760 0.451 - - 96.760 0.451
3 Pemasangan 1 m2 plesteran ciprat 1SP : 2PP 33.50 m2 45,029.48 1,508,487.73 0.210 33.500 0.210 - - 33.500 0.210
VIII. PEKERJAAN PENGECATAN -
1 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 96.76 m2 11,686.42 1,130,778.06 0.158 96.760 0.158 - - 96.760 0.158
IX. PEKERJAAN PENUTUP ATAP -
1 Memasang 1 m2 Atap Galvalum (Paket) 78.51 m3 190,000.00 14,917,137.50 2.081 74.586 1.977 3.926 0.104 78.511 2.081
2 Pemasangan 1 m talang datar Galvalum lebar 60 cm - m' 105,483.99 - - - - - - - -
3 Pemasangan 1 m talang datar U PVC 8.64 m' 73,235.87 632,903.97 0.088 - - 6.000 0.061 6.000 0.061
X. PEKERJAAN PENUTUP LANTAI DAN DINDING -
1 Memasang 1 m2 lantai keramik (30 x 30) cm - m2 114,193.22 - - - - - - - -
2 Membuat rabat beton lantai mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 2.08 m3 723,713.11 1,504,722.31 0.210 2.079 0.210 - - 2.079 0.210
3 Memasang 1 m2 lantai keramik (20 x 20) cm 4.99 m2 184,674.28 921,524.65 0.129 4.990 0.129 - - 4.990 0.129
XI. PEKERJAAN SANITASI - - - - -
1 Memasang 1 buah Kloset Jongkok Porselen 2.00 bh 280,952.58 561,905.16 0.078 2.000 0.078 - - 2.000 0.078
2 Memasang 1 m Pipa PVC tipe AW 16.00 m' 19,406.20 310,499.27 0.043 16.000 0.043 - - 16.000 0.043
3 Memasang 1 m Pipa PVC tipe AW 1 8.00 m' 22,254.33 178,034.63 0.025 8.000 0.025 - - 8.000 0.025
4 Memasang 1 m Pipa PVC tipe AW 3 18.00 m' 63,036.61 1,134,659.00 0.158 16.000 0.141 1.080 0.009 17.080 0.150
5 Memasang 1 buah Kran atau 2.00 bh 46,068.18 92,136.37 0.013 2.000 0.013 - - 2.000 0.013
6 Memasang 1 buah Floor Drain 2.00 bh 80,836.18 161,672.35 0.023 2.000 0.023 - - 2.000 0.023
7 Memasang 1 buah Pintu Kamar Mandi 2.00 bh 650,000.00 1,300,000.00 0.181 2.000 0.181 - - 2.000 0.181
8 Pemasangan 1 M Pipa PVC tipe D 4 12.00 m 85,618.17 1,027,418.08 0.143 12.000 0.143 - - 12.000 0.143
XII. PEKERJAAN ELEKTRIKAL -
1 Instalasi Penerangan menggunakan kabel NYY 3x2,5mm² dalam pipa conduit Ø 20mm. 10.00 titik 105,000.00 1,050,000.00 0.146 10.000 0.146 - - 10.000 0.146
2 Instalasi stop kontak dinding, menggunakan kabel NYM 3x2,5mm² 5.00 titik 100,000.00 500,000.00 0.070 5.000 0.070 - - 5.000 0.070
3 Saklar tunggal inbow, 1 gang 1 way 4.00 bh 20,000.00 80,000.00 0.011 4.000 0.011 - - 4.000 0.011
4 Saklar seri inbow, 1 gang 2 way 4.00 bh 25,000.00 100,000.00 0.014 4.000 0.014 - - 4.000 0.014
5 Stop kontak wall type 1ph, 16A, 1 gang 5.00 bh 20,000.00 100,000.00 0.014 5.000 0.014 - - 5.000 0.014
6 Lampu PLC 18 Watt dengan fitting gantung 8.00 bh 75,000.00 600,000.00 0.084 8.000 0.084 - - 8.000 0.084
7 Lampu PLC 7 Watt dengan fitting gantung 2.00 bh 65,000.00 130,000.00 0.018 2.000 0.018 - - 2.000 0.018
8 Penyambungan kabel 1.00 Ls 500,000.00 500,000.00 0.070 1.000 0.070 - - 1.000 0.070
9 Box MCB + MCB 2.00 bh 250,000.00 500,000.00 0.070 2.000 0.070 - - 2.000 0.070
XIII. PEKERJAAN LAIN-LAIN -
1 Pintu Folding gate 6.00 m2 788,049.93 4,728,299.56 0.660 6.000 0.660 - - 6.000 0.660
2 Railling pengaman besi Hollow 40x40 / 40x20 mm, finishing cat 11.48 m2 550,000.00 6,312,240.00 0.881 5.738 0.440 5.165 0.396 10.903 0.837
XIV. Rumah Timur sungai - -
1 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm 4.50 m' 77,312.85 347,907.84 0.049 - - - - - -
2 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm 5.70 m' 86,676.29 494,054.87 0.069 - - - - - -

Laporan Progres Mingguan ke-18


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
3 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP 3.10 m2 116,576.48 361,387.10 0.050 - - - - - -
4 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm 7.41 m2 54,689.70 405,250.67 0.057 - - - - - -
5 Memasang 1 m2 acian 7.41 m2 33,411.23 247,577.21 0.035 - - - - - -
6 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 7.41 m2 11,686.42 86,596.38 0.012 - - - - - -
7 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.13 m3 8,048,535.00 1,046,309.55 0.146 - - - - - -
8 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti 4.64 m2 644,715.80 2,991,481.32 0.417 - - - - - -
9 Memasang 1 m2 Atap Galvalum (Paket) 17.55 m2 190,000.00 3,334,500.00 0.465 - - - - - -
10 Membuat rabat beton lantai mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 1.22 m3 723,713.11 882,929.99 0.123 - - - - - -

177,518,874.67 24.764 22.470 0.690 23.160


III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PEMBERSIHAN SALURAN
1 Penggalian Tanah Lumpur dan Endapan Limbah Sedalam 30 cm 70.70 m3 109,311.98 7,728,356.66 1.078 65.736 1.002 - - 65.736 1.002
2 Pembersihan dan Pembuangan Tanah Lumpur dan Limbah Keluar Area 89.07 m3 29,796.55 2,653,978.98 0.370 84.822 0.353 - - 84.822 0.353
3 Pemadatan Tanah Eksisting 70.70 m3 49,023.50 3,465,961.48 0.483 59.245 0.405 - - 59.245 0.405
4 Pengurugan dengan pasir urug, 10 cm 21.87 m3 178,388.92 3,901,365.68 0.544 18.544 0.461 - - 18.544 0.461
Pengurugan dengan pasir urug, 10 cm 1.69 m3 173,624.00 293,424.56 0.041 1.156 0.028 - - 1.156 0.028
5 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 10.93 m3 737,396.00 8,059,738.25 1.124 8.744 0.899 - - 8.744 0.899
Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.85 m3 723,713.11 615,156.14 0.086 0.544 0.055 - - 0.544 0.055
6 Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 23.56 m3 872,242.00 20,550,021.46 2.867 18.515 2.253 - - 18.515 2.253
a Jaring Kawat baja/Wire Mesh M5 1 lapis 501.73 kg 10,697.66 5,367,334.57 0.749 350.853 0.524 - - 350.853 0.524
7 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 158.40 m 77,312.85 12,246,356.04 1.708 106.560 1.149 - - 106.560 1.149
8 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 583.98 m 86,676.29 50,617,221.34 7.061 573.789 6.938 - - 573.789 6.938
9 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,2m, K.300 - bh 626,150.00 - - - - - - - -
10 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,8m, K.300 - bh 750,000.00 - - - - - - - -
11 Pekerjaan Plat Beton tebal 15 cm - - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 6.81 m3 872,242.00 5,939,968.00 0.829 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis 480.26 kg 10,697.66 5,137,655.91 0.717 303.194 0.452 - - 303.194 0.452
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 10.17 m2 316,861.88 3,222,485.34 0.450 8.501 0.376 - - 8.501 0.376
d Pembongkaran 1 M2 Bekisting 10.17 m2 15,645.80 159,117.77 0.022 - - - - - -
12 Pekerjaan Plat Beton tebal 10 cm - - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 22.73 m3 872,242.00 19,826,060.60 2.766 15.911 1.936 - - 15.911 1.936
b Jaring Kawat baja/Wire Mesh M8 1 lapis 1,186.92 kg 10,697.66 12,697,260.97 1.771 751.332 1.121 210.245 0.314 961.577 1.435
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 57.68 m2 316,861.88 18,276,593.34 2.550 52.064 2.301 5.616 0.248 57.680 2.550
d Pembongkaran 1 M2 Bekisting 57.68 m2 15,645.80 902,449.63 0.126 - - - - - -
181,660,506.72 25.341 20.254 0.562 20.816
B PEKERJAAN JARINGAN IPAL KOMUNAL
1 Pekerjaan Galian Tanah Pipa 31.93 m3 67,972.30 2,170,355.55 0.303 - - 25.544 0.242 25.544 0.242
2 Pengurugan dengan pasir urug 14.41 m3 178,388.92 2,570,584.34 0.359 - - 8.646 0.215 8.646 0.215
3 Pengurugan Kembali 1 M3 Galian Tanah 12.97 m3 49,023.50 635,966.29 0.089 - - 6.486 0.044 6.486 0.044
4 Pemasangan 1 M Pipa PVC tipe AW 4 - m 90,907.55 - -
5 Saluran Pipa Air Limbah SDR - 41, Dia 15 cm , inc. fitting & Assecories - m 133,200.00 - - - - - - - -
6 Saluran Pipa Air Limbah SDR - 41, Dia 20 cm, , inc. fitting & Assecories - m 203,900.00 - - - - - - - -
7 Pemasangan Clean Out Inc. Fitting & Assecories 43.00 ttk 185,000.00 7,955,000.00 1.110 22.000 0.568 - - 22.000 0.568
8 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 100 org, 20 m3 / hari, - unit 7,500,000.00 - - - - - - - -
(Galian, Urugan, Pondasi, Tutup Beton, Penyambungan Instalasi) -
9 Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm - unit 975,000.00 - - - - - - - -
10 Pekerjaan Sumur Resapan, Dia 100 cm, Kedalaman 2 m, Inc. Tutup Beton Berlubang - ttk 500,000.00 - - - - - - - -
11 Grill Beton Penutup Sumur Resapan - unit 750,000.00 - - - - - - - -
12 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 7.05 m3 688,832.33 4,856,267.95 0.677 1.484 0.143 - - 1.484 0.143
13 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area 7.05 m3 19,888.18 140,211.63 0.020 1.484 0.004 - - 1.484 0.004
14 Pemasangan 1 M Pipa PVC tipe D 6 422.00 m 133,200.00 56,210,400.00 7.841 320.881 5.962 36.014 0.669 356.895 6.632
15 Pemasangan 1 M Pipa PVC tipe D 4 165.50 m 85,618.17 14,169,807.73 1.977 110.723 1.322 8.250 0.099 118.973 1.421
16 Pekerjaan Sumur Resapan kedalaman 4 Buis Beton Dia 80 cm 13.00 ttk 474,124.46 6,163,617.96 0.860 13.000 0.860 - - 13.000 0.860
17 Pasang Grill Besi Penutup Sumur Resapan 15.00 unit 826,875.00 12,403,125.00 1.730 13.071 1.508 - - 13.071 1.508

C PEKERJAAN PEMASANGAN DAN PENGADAAN INSTALASI IPAL


1 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 50 org, 10 m3 / hari
a Pengadaan Unit IPAL kap 50 org, 10 m3 / hari 1.00 unit 110,250,000.00 110,250,000.00 15.380 0.500 7.690 - - 0.500 7.690
b Galian Tanah 57.21 m3 67,972.30 3,888,695.29 0.542 57.210 0.542 - - 57.210 0.542
c Pengurugan Kembali 1 M3 Galian Tanah 2.39 m3 49,023.50 117,166.17 0.016 2.390 0.016 - - 2.390 0.016
d Pengurugan dengan pasir urug 4.98 m3 178,388.92 888,028.96 0.124 - - - - - -
e Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Dinding, Lantai dan Tutup 11.77 m3 872,242.00 10,266,288.31 1.432 9.152 1.114 - - 9.152 1.114
Jaring Kawat baja/Wire Mesh M8 534.95 kg 10,697.66 5,722,710.68 0.798 527.409 0.787 - - 527.409 0.787
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 30.14 m2 316,861.88 9,550,217.12 1.332 26.498 1.171 - - 26.498 1.171
Pembongkaran 1 M2 Bekisting 30.14 m2 15,645.80 471,564.35 0.066 26.498 0.058 - - 26.498 0.058
f Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Inlet 0.30 m3 872,242.00 261,672.60 0.037 0.222 0.027 - - 0.222 0.027
Jaring Kawat baja/Wire Mesh M8 11.06 kg 10,697.66 118,316.07 0.017 8.184 0.012 - - 8.184 0.012
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.66 m2 316,861.88 209,128.84 0.029 0.488 0.022 - - 0.488 0.022
Pembongkaran 1 M2 Bekisting 0.66 m2 15,645.80 10,326.23 0.001 0.488 0.001 - - 0.488 0.001
g Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Outlet 0.41 m3 872,242.00 357,619.22 0.050 0.246 0.030 - - 0.246 0.030
Jaring Kawat baja/Wire Mesh M8 14.98 kg 10,697.66 160,250.88 0.022 8.988 0.013 - - 8.988 0.013
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.96 m2 316,861.88 304,187.41 0.042 0.576 0.025 - - 0.576 0.025
Pembongkaran 1 M2 Bekisting 0.96 m2 15,645.80 15,019.97 0.002 0.576 0.001 - - 0.576 0.001
h Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Kolom 15 x 15 cm 0.47 m3 872,242.00 409,953.74 0.057 0.470 0.057 - - 0.470 0.057
Pembesian dg Besi Polos atau Besi Ulir 119.39 kg 11,860.70 1,416,048.75 0.198 119.390 0.198 - - 119.390 0.198
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.44 m2 316,861.88 456,281.11 0.064 1.440 0.064 - - 1.440 0.064
Pembongkaran 1 M2 Bekisting 1.44 m2 15,645.80 22,529.95 0.003 1.440 0.003 - - 1.440 0.003
i Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Balok 15 x 20 cm 0.12 m3 872,242.00 104,669.04 0.015 - - - - - -

Laporan Progres Mingguan ke-18


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
Pembesian dg Besi Polos atau Besi Ulir 23.91 kg 11,860.70 283,589.29 0.040 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.55 m2 316,861.88 174,274.03 0.024 - - - - - -
Pembongkaran 1 M2 Bekisting 0.55 m2 15,645.80 8,605.19 0.001 - - - - - -
j Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, pondasi 60 x 60 x 20 cm 0.72 m3 872,242.00 628,014.24 0.088 0.576 0.070 - - 0.576 0.070
Pembesian dg Besi Polos atau Besi Ulir 36.93 kg 11,860.70 438,015.58 0.061 29.544 0.049 - - 29.544 0.049
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.20 m2 316,861.88 380,234.26 0.053 0.960 0.042 - - 0.960 0.042
Pembongkaran 1 M2 Bekisting 1.20 m2 15,645.80 18,774.96 0.003 0.960 0.002 - - 0.960 0.002
k Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm 3.00 unit 975,000.00 2,925,000.00 0.408 - - - - - -
l Tutup Manhole diameter 40 cm 2.00 bh 400,000.00 800,000.00 0.112 - - - - - -

2 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 20 org, 2 m3 / hari
a Pengadaan Unit IPAL kap 20 org, 2 m3 / hari 1.00 unit 38,697,750.00 38,697,750.00 5.398 - - 0.150 0.810 0.150 0.810
b Galian Tanah 26.89 m3 67,972.30 1,827,775.15 0.255 26.890 0.255 - - 26.890 0.255
c Pengurugan Kembali 1 M3 Galian Tanah 1.33 m3 49,023.50 65,201.26 0.009 - - - - - -
d Pengurugan dengan pasir urug 2.16 m3 178,388.92 385,973.86 0.054 - - - - - -
e Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Dinding, Lantai dan Tutup 6.37 m3 872,242.00 5,556,181.52 0.775 5.962 0.725 - - 5.962 0.725
Jaring Kawat baja/Wire Mesh M8 270.48 kg 10,697.66 2,893,501.79 0.404 253.169 0.378 - - 253.169 0.378
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 8.68 m2 316,861.88 2,750,361.13 0.384 8.124 0.359 - - 8.124 0.359
Pembongkaran 1 M2 Bekisting 8.68 m2 15,645.80 135,805.53 0.019 3.038 0.007 5.208 0.011 8.246 0.018
f Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Inlet 0.17 m3 872,242.00 148,281.14 0.021 - - - - - -
Jaring Kawat baja/Wire Mesh M8 6.48 kg 10,697.66 69,320.81 0.010 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.33 m2 316,861.88 104,564.42 0.015 - - - - - -
Pembongkaran 1 M2 Bekisting 0.33 m2 15,645.80 5,163.11 0.001 - - - - - -
g Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Outlet 0.23 m3 872,242.00 200,615.66 0.028 - - - - - -
Jaring Kawat baja/Wire Mesh M8 8.44 kg 10,697.66 90,288.21 0.013 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.48 m2 316,861.88 152,093.70 0.021 - - - - - -
Pembongkaran 1 M2 Bekisting 0.48 m2 15,645.80 7,509.98 0.001 - - - - - -
h Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Kolom 15 x 15 cm 0.35 m3 872,242.00 305,284.70 0.043 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 89.54 kg 11,860.70 1,062,006.91 0.148 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.08 m2 316,861.88 342,210.83 0.048 - - - - - -
Pembongkaran 1 M2 Bekisting 1.08 m2 15,645.80 16,897.46 0.002 - - - - - -
i Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Balok 15 x 20 cm 0.08 m3 872,242.00 69,779.36 0.010 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 19.41 kg 11,860.70 230,216.15 0.032 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.40 m2 316,861.88 126,744.75 0.018 - - - - - -
Pembongkaran 1 M2 Bekisting 0.40 m2 15,645.80 6,258.32 0.001 - - - - - -
j Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, pondasi 60 x 60 x 20 cm 0.54 m3 872,242.00 471,010.68 0.066 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 27.69 kg 11,860.70 328,422.73 0.046 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.90 m2 316,861.88 285,175.69 0.040 - - - - - -
Pembongkaran 1 M2 Bekisting 0.90 m2 15,645.80 14,081.22 0.002 - - - - - -
k Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm 2.00 unit 975,000.00 1,950,000.00 0.272 - - - - - -
l Tutup Manhole diameter 40 cm 2.00 bh 400,000.00 800,000.00 0.112 - - - - - -

D PEKERJAAN LAIN - LAIN


1 Pasang Bak Kontrol dengan tutup precast cetak diameter 40 cm 3.00 bh 850,000.00 2,550,000.00 0.356 - - - - - -
2 Pembersihan dan Pembuangan Bekas Galian Tanah IPAL Keluar Area 84.10 m3 67,972.30 5,716,470.45 0.797 - - - - - -
3 Pembongkaran 1 M2 Paving Block eksisting 31.40 m2 49,910.10 1,567,177.00 0.219 - - - - - -
4 Pemasangan 1 M2 kembali Paving Block eksisting 31.40 m2 64,463.10 2,024,141.20 0.282 - - - - - -
5 Pembongkaran dan Pemasangan kembali pipa PDAM yang terdampak galian 1.00 Ls 1,500,000.00 1,500,000.00 0.209 - - - - - -
6 Check Valve diameter 6 inch+ Reducer diameter 8x6 inch 1.00 bh 4,669,087.50 4,669,087.50 0.651 - - - - - -
7 Check Valve diameter 6 inch 1.00 bh 4,278,582.00 4,278,582.00 0.597 - - - - - -
8 Check Valve diameter 4 inch 2.00 bh 2,051,002.80 4,102,005.60 0.572 - - - - - -
9 Membuat rabat beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 1.55 m3 723,713.11 1,121,650.74 0.156 - - - - - -
10 Grill besi area ipal barat 1.50 m2 828,726.02 1,243,089.03 0.173 - - - - - -

345,803,198.30 48.239 24.086 2.091 26.177

JUMLAH 654,697,105.06 716,855,950.73 100.000 68.219 3.392 71.611


PRESTASI MINGGU LALU 68.219
PRESTASI MINGGU INI 3.392
PRESTASI SAMPAI DENGAN MINGGU INI 71.611
PRESTASI MENURUT SCHEDULE 76.030
LEBIH CEPAT (+) / TERLAMBAT (-) (4.419)

Yogyakarta, 27 September 2021


di buat oleh,
KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA

Noor Hasan Bambang Erlianto


Pengawas Pelaksana

Laporan Progres Mingguan ke-18


REKAPITULASI
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : XVIII ( Delapan belas )


Periode : 20 September 2021 sampai dengan 26 September 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
ADDENDUM II : 050 / 1909 / VII / 2021, TANGGAL 19 JULI 2021
ADDENDUM III : 050 / 0615 / IX / 2021, TANGGAL 6 SEPTEMBER 2021
NILAI KONTRAK ADDENDUM III : Rp 788,541,545.80
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO PEKERJAAN PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp (%) BOBOT % BOBOT % BOBOT %

I PEKERJAAN PERSIAPAN 11,873,371.04 1.656 1.408 0.050 1.458

II PEKERJAAN PERBAIKAN TALUD SEGMEN 5


A PEKERJAAN TANAH DAN BETON BERTULANG - - - - -
B PEKERJAAN PASANGAN DINDING - - - - -

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PENGECATAN - - - - -
B PEKERJAAN RUMAH TERDAMPAK 177,518,874.67 24.764 22.470 0.690 23.160

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PEMBERSIHAN SALURAN 181,660,506.72 25.341 20.254 0.562 20.816
B PEKERJAAN JARINGAN IPAL KOMUNAL 345,803,198.30 48.239 24.086 2.091 26.177

JUMLAH 716,855,950.73 100.000 68.219 3.392 71.611


PRESTASI MINGGU LALU - 68.219
PRESTASI MINGGU INI 3.392
PRESTASI SAMPAI DENGAN MINGGU INI 71.611
PRESTASI MENURUT SCHEDULE 76.030
LEBIH CEPAT (+) / TERLAMBAT (-) (4.419)

Yogyakarta, 27 September 2021


di buat oleh,
PEJABAT PEMBUAT KOMITMEN TIM TEKNIS KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA
1. Cicilia Novi hendrawati, M.SC., M.Eng.
NIP. 19781102 200501 2 011 ...........................

2. Danang Dwi Wahyujati,S.Kom.,M.Eng


NIP. 19761028 199803 1 004 ...........................
SIGIT SETIAWAN, ST.MT 3. Sudaryanto
NIP. 19690605 199303 1 007 RISMAN WARCHAN ZULIANTO
NIP. 19770623 200501 1 013 ........................... Tim Leader Direktur
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : XIX ( Sembilan belas )


Periode : 27 September 2021 sampai dengan 03 Oktober 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
ADDENDUM II : 050 / 1909 / VII / 2021, TANGGAL 19 JULI 2021
ADDENDUM III : 050 / 0615 / IX / 2021, TANGGAL 6 SEPTEMBER 2021
NILAI KONTRAK ADDENDUM III : Rp 788,541,545.80
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
I PEKERJAAN PERSIAPAN
1 Pembuatan Papan Nama Pekerjaan 1.00 bh 250,000.00 250,000.00 0.035 1.000 0.035 - - 1.000 0.035
2 Pengukuran dan Pemasangan Bouwplank 28.56 m 12,198.91 348,400.73 0.049 28.560 0.049 - - 28.560 0.049
3 Pembuatan bedeng pekerja 9.00 m2 383,330.04 3,449,970.32 0.481 9.000 0.481 - - 9.000 0.481
4 Mobilisasi Demobilisasi Alat Berat 1.00 ls 2,500,000.00 2,500,000.00 0.349 0.818 0.285 0.045 0.016 0.864 0.301
5 Pembuatan akses menuju badan sungai sementara - m2 113,128.49 - - - - - - - -
6 Dewatering dengan pompa air diesel 40.00 jam 25,000.00 1,000,000.00 0.139 32.727 0.114 1.818 0.006 34.545 0.120
7 SMKK 1.00 ls 4,325,000.00 4,325,000.00 0.603 0.818 0.494 0.045 0.027 0.864 0.521
11,873,371.04 1.656 1.458 0.050 1.507
II PEKERJAAN PERBAIKAN TALUD SEGMEN 5
A PEKERJAAN TANAH DAN BETON BERTULANG
1 Penggalian 1 M3 Tanah Biasa - m3 67,972.30 - - - - - - - -
2 Pengurugan Kembali 1 M3 Galian Tanah - m3 49,023.50 - - - - - - - -
3 Bongkaran Pasangan Batu dan Beton Eksisting - m3 71,953.20 - - - - - - - -
4 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area - m3 19,888.18 - - - - - - - -
5 Pemadatan Tanah Eksisting - m3 49,023.50 - - - - - - - -
6 Pengurugan dengan pasir urug - m3 178,388.92 - - - - - - - -
7 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 - m3 737,396.00 - - - - - - - -
8 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 - m3 872,242.00 - - - - - - - -
a Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
b Bekisting untuk pondasi beton ( dipakai 2 kali ) - m2 89,375.55 - - - - - - - -
c Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
9 Pekerjaan Beton Dinding Talud Beton -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 - m3 872,242.00 - - - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) - m2 316,861.88 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
10 Pekerjaan Beton Sloof 20x30cm -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 - m3 872,242.00 - - - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
c Memasang Bekisting untuk Sloof (dipakai 2 kali) - m2 89,375.55 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
11 Pekerjaan Beton Konsul Cantilever -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 - m3 872,242.00 - - - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
c Memasang Bekisting untuk Balok (dipakai 2 kali) - m2 120,181.13 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
12 Pekerjaan Plat Beton tebal 12 cm -
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) - m3 872,242.00 - - - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis - kg 10,697.66 - - - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) - m2 316,861.88 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
13 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm - m 77,312.85 - - - - - - - -
14 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm - m 86,676.29 - - - - - - - -
15 Memasang Stek Besi - kg 11,860.70 - - - - - - - -
16 Pekerjaan Plat Beton Pot tebal 10 cm -
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) - m3 872,242.00 - - - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
c Bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm - m2 118,158.83 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
- - - - -

Laporan Progres Mingguan ke-19


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
B PEKERJAAN PASANGAN DINDING
1 Pemasangan Dinding Bata Merah Bakar Sekam Tebal 1/2 Bata Camp. 1SP 6PP - m2 116,576.48 - - - - - - - -
2 Pemasangan Plesteran 1 Pc 6 Pp Tebal 15 mm - m2 54,689.70 - - - - - - - -
3 Pemasangan Acian - m2 33,411.23 - - - - - - - -
4 Pemasangan Plesteran Skoning 1 Pc 2Pp lebar 10 cm - m 55,075.90 - - - - - - - -
5 Pemasangan Kepala Kolom - bh 50,000.00 - - - - - - - -
- - - - -
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PENGECATAN
1 Pengecatan Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Weathershield luar ruangan - m2 11,686.42 - - - - - - - -
- - - - -
B PEKERJAAN RUMAH TERDAMPAK
I. PEKERJAAN BONGKARAN
1 Membongkar 1 m2 genteng / sirap untuk dipergunakan lagi 77.17 m2 3,628.42 280,005.33 0.039 60.269 0.031 1.543 0.001 61.813 0.031
2 Membongkar 1 m3 kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi 0.37 m3 991,595.91 366,890.49 0.051 0.289 0.040 0.007 0.001 0.296 0.041
3 Pembongkaran 1 m3 pasangan bata merah dan membersihkan 12.72 m3 185,908.38 2,364,754.54 0.330 10.764 0.279 0.254 0.007 11.019 0.286
4 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 1.50 m3 688,832.33 1,033,248.50 0.144 1.173 0.113 0.030 0.003 1.203 0.116
II. PEKERJAAN TANAH -
1 Menggali 1 m3 tanah biasa sedalam 1 meter 27.22 m3 67,972.30 1,850,206.01 0.258 27.220 0.258 - - 27.220 0.258
2 Pengurugan Kembali 1 m3 Galian Tanah 10.11 m3 18,745.83 189,520.38 0.026 10.110 0.026 - - 10.110 0.026
3 Pengurugan dengan pasir urug 1.82 m3 173,624.00 315,995.68 0.044 1.820 0.044 - - 1.820 0.044
4 Peninggian peil lantai 9.18 m3 18,745.83 172,086.75 0.024 9.180 0.024 - - 9.180 0.024
III. PEKERJAAN PONDASI -
1 Memasang 1 m3 pondasi batu belah, campuran 1 PC 6 PP 16.49 m2 665,195.09 10,969,067.11 1.530 16.490 1.530 - - 16.490 1.530
IV. PEKERJAAN BETON -
1 Membuat 1 m3 Sloof beton bertulang (200 kg besi + bekisting) 1.06 m3 3,844,764.87 4,075,450.77 0.569 1.060 0.569 - - 1.060 0.569
2 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) 2.29 m3 7,083,735.01 16,221,753.18 2.263 2.290 2.263 - - 2.290 2.263
3 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) 3.05 m3 5,659,422.09 17,261,237.38 2.408 3.050 2.408 - - 3.050 2.408
4 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.14 m3 723,713.11 101,319.83 0.014 0.140 0.014 - - 0.140 0.014
5 Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting) 0.57 m3 3,127,107.54 1,782,451.30 0.249 0.570 0.249 - - 0.570 0.249
6 Sloof 150 x 200 dengan beton K 225 Tulangan 105 kg 0.74 m3 3,295,166.46 2,438,423.18 0.340 0.740 0.340 - - 0.740 0.340
7 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm 67.35 m' 77,312.85 5,207,020.70 0.726 67.350 0.726 - - 67.350 0.726
8 Balok 150 x 200 dengan beton K 225 Tulangan 105 kg 1.01 m3 3,705,897.33 3,742,956.31 0.522 1.010 0.522 - - 1.010 0.522
9 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm 54.15 m' 86,676.29 4,693,521.24 0.655 54.150 0.655 - - 54.150 0.655
10 Membuat 1 m3 Plat Lantai beton bertulang 2.95 m3 3,119,381.73 9,202,176.12 1.284 2.950 1.284 - - 2.950 1.284
11 Membuat 1 m3 Plat Tangga beton bertulang 0.72 m3 3,119,381.73 2,245,954.85 0.313 0.720 0.313 - - 0.720 0.313
12 Membuat 1 m3 Plat Water torn beton bertulang 0.42 m3 3,119,381.73 1,310,140.33 0.183 0.420 0.183 - - 0.420 0.183
V. PEKERJAAN DINDING -
1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP 161.84 m2 116,576.48 18,866,738.23 2.632 161.840 2.632 - - 161.840 2.632
2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP, trap tangga 6.30 m2 250,668.02 1,579,208.52 0.220 6.300 0.220 - - 6.300 0.220
VI PEKERJAAN KAYU -
1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.27 m3 16,443,774.77 4,439,819.19 0.619 0.270 0.619 - - 0.270 0.619
Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.02 m3 8,048,535.00 160,970.70 0.022 0.020 0.022 - - 0.020 0.022
2 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti 12.32 m2 644,715.80 7,942,898.68 1.108 12.320 1.108 - - 12.320 1.108
3 Memasang 1 m3 konstruksi gordeng, kayu glugu - m3 4,450,537.65 - - - - - - - -
VII. PEKERJAAN PLESTERAN -
1 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm 96.76 m2 54,689.70 5,291,775.27 0.738 96.760 0.738 - - 96.760 0.738
2 Memasang 1 m2 acian 96.76 m2 33,411.23 3,232,870.55 0.451 96.760 0.451 - - 96.760 0.451
3 Pemasangan 1 m2 plesteran ciprat 1SP : 2PP 33.50 m2 45,029.48 1,508,487.73 0.210 33.500 0.210 - - 33.500 0.210
VIII. PEKERJAAN PENGECATAN -
1 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 96.76 m2 11,686.42 1,130,778.06 0.158 96.760 0.158 - - 96.760 0.158
IX. PEKERJAAN PENUTUP ATAP -
1 Memasang 1 m2 Atap Galvalum (Paket) 78.51 m3 190,000.00 14,917,137.50 2.081 78.511 2.081 - - 78.511 2.081
2 Pemasangan 1 m talang datar Galvalum lebar 60 cm - m' 105,483.99 - - - - - - - -
3 Pemasangan 1 m talang datar U PVC 8.64 m' 73,235.87 632,903.97 0.088 6.000 0.061 2.506 0.026 8.506 0.087
X. PEKERJAAN PENUTUP LANTAI DAN DINDING -
1 Memasang 1 m2 lantai keramik (30 x 30) cm - m2 114,193.22 - - - - - - - -
2 Membuat rabat beton lantai mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 2.08 m3 723,713.11 1,504,722.31 0.210 2.079 0.210 - - 2.079 0.210
3 Memasang 1 m2 lantai keramik (20 x 20) cm 4.99 m2 184,674.28 921,524.65 0.129 4.990 0.129 - - 4.990 0.129
XI. PEKERJAAN SANITASI - - - - -
1 Memasang 1 buah Kloset Jongkok Porselen 2.00 bh 280,952.58 561,905.16 0.078 2.000 0.078 - - 2.000 0.078
2 Memasang 1 m Pipa PVC tipe AW 16.00 m' 19,406.20 310,499.27 0.043 16.000 0.043 - - 16.000 0.043
3 Memasang 1 m Pipa PVC tipe AW 1 8.00 m' 22,254.33 178,034.63 0.025 8.000 0.025 - - 8.000 0.025
4 Memasang 1 m Pipa PVC tipe AW 3 18.00 m' 63,036.61 1,134,659.00 0.158 17.080 0.150 0.540 0.005 17.620 0.155
5 Memasang 1 buah Kran atau 2.00 bh 46,068.18 92,136.37 0.013 2.000 0.013 - - 2.000 0.013
6 Memasang 1 buah Floor Drain 2.00 bh 80,836.18 161,672.35 0.023 2.000 0.023 - - 2.000 0.023
7 Memasang 1 buah Pintu Kamar Mandi 2.00 bh 650,000.00 1,300,000.00 0.181 2.000 0.181 - - 2.000 0.181
8 Pemasangan 1 M Pipa PVC tipe D 4 12.00 m 85,618.17 1,027,418.08 0.143 12.000 0.143 - - 12.000 0.143

Laporan Progres Mingguan ke-19


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
XII. PEKERJAAN ELEKTRIKAL -
1 Instalasi Penerangan menggunakan kabel NYY 3x2,5mm² dalam pipa conduit Ø 20mm. 10.00 titik 105,000.00 1,050,000.00 0.146 10.000 0.146 - - 10.000 0.146
2 Instalasi stop kontak dinding, menggunakan kabel NYM 3x2,5mm² 5.00 titik 100,000.00 500,000.00 0.070 5.000 0.070 - - 5.000 0.070
3 Saklar tunggal inbow, 1 gang 1 way 4.00 bh 20,000.00 80,000.00 0.011 4.000 0.011 - - 4.000 0.011
4 Saklar seri inbow, 1 gang 2 way 4.00 bh 25,000.00 100,000.00 0.014 4.000 0.014 - - 4.000 0.014
5 Stop kontak wall type 1ph, 16A, 1 gang 5.00 bh 20,000.00 100,000.00 0.014 5.000 0.014 - - 5.000 0.014
6 Lampu PLC 18 Watt dengan fitting gantung 8.00 bh 75,000.00 600,000.00 0.084 8.000 0.084 - - 8.000 0.084
7 Lampu PLC 7 Watt dengan fitting gantung 2.00 bh 65,000.00 130,000.00 0.018 2.000 0.018 - - 2.000 0.018
8 Penyambungan kabel 1.00 Ls 500,000.00 500,000.00 0.070 1.000 0.070 - - 1.000 0.070
9 Box MCB + MCB 2.00 bh 250,000.00 500,000.00 0.070 2.000 0.070 - - 2.000 0.070
XIII. PEKERJAAN LAIN-LAIN -
1 Pintu Folding gate 6.00 m2 788,049.93 4,728,299.56 0.660 6.000 0.660 - - 6.000 0.660
2 Railling pengaman besi Hollow 40x40 / 40x20 mm, finishing cat 11.48 m2 550,000.00 6,312,240.00 0.881 10.903 0.837 0.344 0.026 11.247 0.863
XIV. Rumah Timur sungai - -
1 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm 4.50 m' 77,312.85 347,907.84 0.049 - - - - - -
2 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm 5.70 m' 86,676.29 494,054.87 0.069 - - - - - -
3 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP 3.10 m2 116,576.48 361,387.10 0.050 - - - - - -
4 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm 7.41 m2 54,689.70 405,250.67 0.057 - - - - - -
5 Memasang 1 m2 acian 7.41 m2 33,411.23 247,577.21 0.035 - - - - - -
6 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 7.41 m2 11,686.42 86,596.38 0.012 - - - - - -
7 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.13 m3 8,048,535.00 1,046,309.55 0.146 - - - - - -
8 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti 4.64 m2 644,715.80 2,991,481.32 0.417 - - - - - -
9 Memasang 1 m2 Atap Galvalum (Paket) 17.55 m2 190,000.00 3,334,500.00 0.465 - - - - - -
10 Membuat rabat beton lantai mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 1.22 m3 723,713.11 882,929.99 0.123 - - - - - -

177,518,874.67 24.764 23.160 0.068 23.228


III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PEMBERSIHAN SALURAN
1 Penggalian Tanah Lumpur dan Endapan Limbah Sedalam 30 cm 70.70 m3 109,311.98 7,728,356.66 1.078 65.736 1.002 2.828 0.043 68.564 1.046
2 Pembersihan dan Pembuangan Tanah Lumpur dan Limbah Keluar Area 89.07 m3 29,796.55 2,653,978.98 0.370 84.822 0.353 - - 84.822 0.353
3 Pemadatan Tanah Eksisting 70.70 m3 49,023.50 3,465,961.48 0.483 59.245 0.405 7.070 0.048 66.315 0.454
4 Pengurugan dengan pasir urug, 10 cm 21.87 m3 178,388.92 3,901,365.68 0.544 18.544 0.461 2.187 0.054 20.731 0.516
Pengurugan dengan pasir urug, 10 cm 1.69 m3 173,624.00 293,424.56 0.041 1.156 0.028 0.169 0.004 1.325 0.032
5 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 10.93 m3 737,396.00 8,059,738.25 1.124 8.744 0.899 1.093 0.112 9.837 1.012
Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.85 m3 723,713.11 615,156.14 0.086 0.544 0.055 0.085 0.009 0.629 0.064
6 Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 23.56 m3 872,242.00 20,550,021.46 2.867 18.515 2.253 2.767 0.337 21.283 2.590
a Jaring Kawat baja/Wire Mesh M5 1 lapis 501.73 kg 10,697.66 5,367,334.57 0.749 350.853 0.524 90.311 0.135 441.164 0.658
7 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 158.40 m 77,312.85 12,246,356.04 1.708 106.560 1.149 - - 106.560 1.149
8 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 583.98 m 86,676.29 50,617,221.34 7.061 573.789 6.938 - - 573.789 6.938
9 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,2m, K.300 - bh 626,150.00 - - - - - - - -
10 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,8m, K.300 - bh 750,000.00 - - - - - - - -
11 Pekerjaan Plat Beton tebal 15 cm - - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 6.81 m3 872,242.00 5,939,968.00 0.829 - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis 480.26 kg 10,697.66 5,137,655.91 0.717 303.194 0.452 - - 303.194 0.452
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 10.17 m2 316,861.88 3,222,485.34 0.450 8.501 0.376 - - 8.501 0.376
d Pembongkaran 1 M2 Bekisting 10.17 m2 15,645.80 159,117.77 0.022 - - - - - -
12 Pekerjaan Plat Beton tebal 10 cm - - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 22.73 m3 872,242.00 19,826,060.60 2.766 15.911 1.936 6.819 0.830 22.730 2.766
b Jaring Kawat baja/Wire Mesh M8 1 lapis 1,186.92 kg 10,697.66 12,697,260.97 1.771 961.577 1.435 225.343 0.336 1,186.920 1.771
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 57.68 m2 316,861.88 18,276,593.34 2.550 57.680 2.550 - - 57.680 2.550
d Pembongkaran 1 M2 Bekisting 57.68 m2 15,645.80 902,449.63 0.126 - - - - - -
181,660,506.72 25.341 20.816 1.908 22.725
B PEKERJAAN JARINGAN IPAL KOMUNAL
1 Pekerjaan Galian Tanah Pipa 31.93 m3 67,972.30 2,170,355.55 0.303 25.544 0.242 - - 25.544 0.242
2 Pengurugan dengan pasir urug 14.41 m3 178,388.92 2,570,584.34 0.359 8.646 0.215 - - 8.646 0.215
3 Pengurugan Kembali 1 M3 Galian Tanah 12.97 m3 49,023.50 635,966.29 0.089 6.486 0.044 - - 6.486 0.044
4 Pemasangan 1 M Pipa PVC tipe AW 4 - m 90,907.55 - -
5 Saluran Pipa Air Limbah SDR - 41, Dia 15 cm , inc. fitting & Assecories - m 133,200.00 - - - - - - - -
6 Saluran Pipa Air Limbah SDR - 41, Dia 20 cm, , inc. fitting & Assecories - m 203,900.00 - - - - - - - -
7 Pemasangan Clean Out Inc. Fitting & Assecories 43.00 ttk 185,000.00 7,955,000.00 1.110 22.000 0.568 - - 22.000 0.568
8 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 100 org, 20 m3 / hari, - unit 7,500,000.00 - - - - - - - -
(Galian, Urugan, Pondasi, Tutup Beton, Penyambungan Instalasi) -
9 Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm - unit 975,000.00 - - - - - - - -
10 Pekerjaan Sumur Resapan, Dia 100 cm, Kedalaman 2 m, Inc. Tutup Beton Berlubang - ttk 500,000.00 - - - - - - - -
11 Grill Beton Penutup Sumur Resapan - unit 750,000.00 - - - - - - - -
12 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 7.05 m3 688,832.33 4,856,267.95 0.677 1.484 0.143 - - 1.484 0.143
13 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area 7.05 m3 19,888.18 140,211.63 0.020 1.484 0.004 - - 1.484 0.004
14 Pemasangan 1 M Pipa PVC tipe D 6 422.00 m 133,200.00 56,210,400.00 7.841 356.895 6.632 - - 356.895 6.632
15 Pemasangan 1 M Pipa PVC tipe D 4 165.50 m 85,618.17 14,169,807.73 1.977 118.973 1.421 - - 118.973 1.421
16 Pekerjaan Sumur Resapan kedalaman 4 Buis Beton Dia 80 cm 13.00 ttk 474,124.46 6,163,617.96 0.860 13.000 0.860 - - 13.000 0.860
17 Pasang Grill Besi Penutup Sumur Resapan 15.00 unit 826,875.00 12,403,125.00 1.730 13.071 1.508 - - 13.071 1.508

Laporan Progres Mingguan ke-19


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)

C PEKERJAAN PEMASANGAN DAN PENGADAAN INSTALASI IPAL


1 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 50 org, 10 m3 / hari
a Pengadaan Unit IPAL kap 50 org, 10 m3 / hari 1.00 unit 110,250,000.00 110,250,000.00 15.380 0.500 7.690 - - 0.500 7.690
b Galian Tanah 57.21 m3 67,972.30 3,888,695.29 0.542 57.210 0.542 - - 57.210 0.542
c Pengurugan Kembali 1 M3 Galian Tanah 2.39 m3 49,023.50 117,166.17 0.016 2.390 0.016 - - 2.390 0.016
d Pengurugan dengan pasir urug 4.98 m3 178,388.92 888,028.96 0.124 - - - - - -
e Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Dinding, Lantai dan Tutup 11.77 m3 872,242.00 10,266,288.31 1.432 9.152 1.114 - - 9.152 1.114
Jaring Kawat baja/Wire Mesh M8 534.95 kg 10,697.66 5,722,710.68 0.798 527.409 0.787 - - 527.409 0.787
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 30.14 m2 316,861.88 9,550,217.12 1.332 26.498 1.171 - - 26.498 1.171
Pembongkaran 1 M2 Bekisting 30.14 m2 15,645.80 471,564.35 0.066 26.498 0.058 - - 26.498 0.058
f Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Inlet 0.30 m3 872,242.00 261,672.60 0.037 0.222 0.027 - - 0.222 0.027
Jaring Kawat baja/Wire Mesh M8 11.06 kg 10,697.66 118,316.07 0.017 8.184 0.012 - - 8.184 0.012
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.66 m2 316,861.88 209,128.84 0.029 0.488 0.022 - - 0.488 0.022
Pembongkaran 1 M2 Bekisting 0.66 m2 15,645.80 10,326.23 0.001 0.488 0.001 - - 0.488 0.001
g Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Outlet 0.41 m3 872,242.00 357,619.22 0.050 0.246 0.030 - - 0.246 0.030
Jaring Kawat baja/Wire Mesh M8 14.98 kg 10,697.66 160,250.88 0.022 8.988 0.013 - - 8.988 0.013
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.96 m2 316,861.88 304,187.41 0.042 0.576 0.025 - - 0.576 0.025
Pembongkaran 1 M2 Bekisting 0.96 m2 15,645.80 15,019.97 0.002 0.576 0.001 - - 0.576 0.001
h Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Kolom 15 x 15 cm 0.47 m3 872,242.00 409,953.74 0.057 0.470 0.057 - - 0.470 0.057
Pembesian dg Besi Polos atau Besi Ulir 119.39 kg 11,860.70 1,416,048.75 0.198 119.390 0.198 - - 119.390 0.198
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.44 m2 316,861.88 456,281.11 0.064 1.440 0.064 - - 1.440 0.064
Pembongkaran 1 M2 Bekisting 1.44 m2 15,645.80 22,529.95 0.003 1.440 0.003 - - 1.440 0.003
i Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Balok 15 x 20 cm 0.12 m3 872,242.00 104,669.04 0.015 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 23.91 kg 11,860.70 283,589.29 0.040 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.55 m2 316,861.88 174,274.03 0.024 - - - - - -
Pembongkaran 1 M2 Bekisting 0.55 m2 15,645.80 8,605.19 0.001 - - - - - -
j Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, pondasi 60 x 60 x 20 cm 0.72 m3 872,242.00 628,014.24 0.088 0.576 0.070 - - 0.576 0.070
Pembesian dg Besi Polos atau Besi Ulir 36.93 kg 11,860.70 438,015.58 0.061 29.544 0.049 - - 29.544 0.049
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.20 m2 316,861.88 380,234.26 0.053 0.960 0.042 - - 0.960 0.042
Pembongkaran 1 M2 Bekisting 1.20 m2 15,645.80 18,774.96 0.003 0.960 0.002 - - 0.960 0.002
k Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm 3.00 unit 975,000.00 2,925,000.00 0.408
l Tutup Manhole diameter 40 cm 2.00 bh 400,000.00 800,000.00 0.112

2 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 20 org, 2 m3 / hari
a Pengadaan Unit IPAL kap 20 org, 2 m3 / hari 1.00 unit 38,697,750.00 38,697,750.00 5.398 0.150 0.810 0.350 1.889 0.500 2.699
b Galian Tanah 26.89 m3 67,972.30 1,827,775.15 0.255 26.890 0.255 - - 26.890 0.255
c Pengurugan Kembali 1 M3 Galian Tanah 1.33 m3 49,023.50 65,201.26 0.009 - - - - - -
d Pengurugan dengan pasir urug 2.16 m3 178,388.92 385,973.86 0.054 - - - - - -
e Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Dinding, Lantai dan Tutup 6.37 m3 872,242.00 5,556,181.52 0.775 5.962 0.725 - - 5.962 0.725
Jaring Kawat baja/Wire Mesh M8 270.48 kg 10,697.66 2,893,501.79 0.404 253.169 0.378 - - 253.169 0.378
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 8.68 m2 316,861.88 2,750,361.13 0.384 8.124 0.359 - - 8.124 0.359
Pembongkaran 1 M2 Bekisting 8.68 m2 15,645.80 135,805.53 0.019 8.246 0.018 - - 8.246 0.018
f Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Inlet 0.17 m3 872,242.00 148,281.14 0.021 - - - - - -
Jaring Kawat baja/Wire Mesh M8 6.48 kg 10,697.66 69,320.81 0.010 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.33 m2 316,861.88 104,564.42 0.015 - - - - - -
Pembongkaran 1 M2 Bekisting 0.33 m2 15,645.80 5,163.11 0.001 - - - - - -
g Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Outlet 0.23 m3 872,242.00 200,615.66 0.028 - - - - - -
Jaring Kawat baja/Wire Mesh M8 8.44 kg 10,697.66 90,288.21 0.013 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.48 m2 316,861.88 152,093.70 0.021 - - - - - -
Pembongkaran 1 M2 Bekisting 0.48 m2 15,645.80 7,509.98 0.001 - - - - - -
h Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Kolom 15 x 15 cm 0.35 m3 872,242.00 305,284.70 0.043 - - 0.350 0.043 0.350 0.043
Pembesian dg Besi Polos atau Besi Ulir 89.54 kg 11,860.70 1,062,006.91 0.148 - - 89.540 0.148 89.540 0.148
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.08 m2 316,861.88 342,210.83 0.048 - - 1.080 0.048 1.080 0.048
Pembongkaran 1 M2 Bekisting 1.08 m2 15,645.80 16,897.46 0.002 - - 1.080 0.002 1.080 0.002
i Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Balok 15 x 20 cm 0.08 m3 872,242.00 69,779.36 0.010 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 19.41 kg 11,860.70 230,216.15 0.032 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.40 m2 316,861.88 126,744.75 0.018 - - - - - -
Pembongkaran 1 M2 Bekisting 0.40 m2 15,645.80 6,258.32 0.001 - - - - - -
j Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, pondasi 60 x 60 x 20 cm 0.54 m3 872,242.00 471,010.68 0.066 - - 0.540 0.066 0.540 0.066
Pembesian dg Besi Polos atau Besi Ulir 27.69 kg 11,860.70 328,422.73 0.046 - - 27.690 0.046 27.690 0.046
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.90 m2 316,861.88 285,175.69 0.040 - - 0.900 0.040 0.900 0.040
Pembongkaran 1 M2 Bekisting 0.90 m2 15,645.80 14,081.22 0.002 - - 0.900 0.002 0.900 0.002
k Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm 2.00 unit 975,000.00 1,950,000.00 0.272
l Tutup Manhole diameter 40 cm 2.00 bh 400,000.00 800,000.00 0.112

Laporan Progres Mingguan ke-19


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)

D PEKERJAAN LAIN - LAIN


1 Pasang Bak Kontrol dengan tutup precast cetak diameter 40 cm 3.00 bh 850,000.00 2,550,000.00 0.356 - - 3.000 0.356 3.000 0.356
2 Pembersihan dan Pembuangan Bekas Galian Tanah IPAL Keluar Area 84.10 m3 67,972.30 5,716,470.45 0.797 - - 63.075 0.598 63.075 0.598
3 Pembongkaran 1 M2 Paving Block eksisting 31.40 m2 49,910.10 1,567,177.00 0.219 - - 23.550 0.164 23.550 0.164
4 Pemasangan 1 M2 kembali Paving Block eksisting 31.40 m2 64,463.10 2,024,141.20 0.282 - - 4.746 0.043 4.746 0.043
5 Pembongkaran dan Pemasangan kembali pipa PDAM yang terdampak galian 1.00 Ls 1,500,000.00 1,500,000.00 0.209 - - - - - -
6 Check Valve diameter 6 inch+ Reducer diameter 8x6 inch 1.00 bh 4,669,087.50 4,669,087.50 0.651 - - - - - -
7 Check Valve diameter 6 inch 1.00 bh 4,278,582.00 4,278,582.00 0.597 - - - - - -
8 Check Valve diameter 4 inch 2.00 bh 2,051,002.80 4,102,005.60 0.572 - - - - - -
9 Membuat rabat beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 1.55 m3 723,713.11 1,121,650.74 0.156 - - - - - -
10 Grill besi area ipal barat 1.50 m2 828,726.02 1,243,089.03 0.173 - - - - - -

345,803,198.30 48.239 26.177 3.444 29.621

JUMLAH 654,697,105.06 716,855,950.73 100.000 71.611 5.470 77.081


PRESTASI MINGGU LALU 71.611
PRESTASI MINGGU INI 5.470
PRESTASI SAMPAI DENGAN MINGGU INI 77.081
PRESTASI MENURUT SCHEDULE 81.863
LEBIH CEPAT (+) / TERLAMBAT (-) (4.783)

Yogyakarta, 4 Oktober 2021


di buat oleh,
KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA

Noor Hasan Bambang Erlianto


Pengawas Pelaksana

Laporan Progres Mingguan ke-19


REKAPITULASI
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : XIX ( Sembilan belas )


Periode : 27 September 2021 sampai dengan 03 Oktober 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
ADDENDUM II : 050 / 1909 / VII / 2021, TANGGAL 19 JULI 2021
ADDENDUM III : 050 / 0615 / IX / 2021, TANGGAL 6 SEPTEMBER 2021
NILAI KONTRAK ADDENDUM III : Rp 788,541,545.80
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO PEKERJAAN PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp (%) BOBOT % BOBOT % BOBOT %

I PEKERJAAN PERSIAPAN 11,873,371.04 1.656 1.458 0.050 1.507

II PEKERJAAN PERBAIKAN TALUD SEGMEN 5


A PEKERJAAN TANAH DAN BETON BERTULANG - - - - -
B PEKERJAAN PASANGAN DINDING - - - - -

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PENGECATAN - - - - -
B PEKERJAAN RUMAH TERDAMPAK 177,518,874.67 24.764 23.160 0.068 23.228

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PEMBERSIHAN SALURAN 181,660,506.72 25.341 20.816 1.908 22.725
B PEKERJAAN JARINGAN IPAL KOMUNAL 345,803,198.30 48.239 26.177 3.444 29.621

JUMLAH 716,855,950.73 100.000 71.611 5.470 77.081


PRESTASI MINGGU LALU - 71.611
PRESTASI MINGGU INI 5.470
PRESTASI SAMPAI DENGAN MINGGU INI 77.081
PRESTASI MENURUT SCHEDULE 81.863
LEBIH CEPAT (+) / TERLAMBAT (-) (4.783)

Yogyakarta, 4 Oktober 2021


di buat oleh,
PEJABAT PEMBUAT KOMITMEN TIM TEKNIS KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA
1. Cicilia Novi hendrawati, M.SC., M.Eng.
NIP. 19781102 200501 2 011 ...........................

2. Danang Dwi Wahyujati,S.Kom.,M.Eng


NIP. 19761028 199803 1 004 ...........................
SIGIT SETIAWAN, ST.MT 3. Sudaryanto
NIP. 19690605 199303 1 007 RISMAN WARCHAN ZULIANTO
NIP. 19770623 200501 1 013 ........................... Tim Leader Direktur
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : XX ( Dua puluh )


Periode : 04 Oktober 2021 sampai dengan 10 Oktober 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
ADDENDUM II : 050 / 1909 / VII / 2021, TANGGAL 19 JULI 2021
ADDENDUM III : 050 / 0615 / IX / 2021, TANGGAL 6 SEPTEMBER 2021
NILAI KONTRAK ADDENDUM III : Rp 788,541,545.80
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
I PEKERJAAN PERSIAPAN
1 Pembuatan Papan Nama Pekerjaan 1.00 bh 250,000.00 250,000.00 0.035 1.000 0.035 - - 1.000 0.035
2 Pengukuran dan Pemasangan Bouwplank 28.56 m 12,198.91 348,400.73 0.049 28.560 0.049 - - 28.560 0.049
3 Pembuatan bedeng pekerja 9.00 m2 383,330.04 3,449,970.32 0.481 9.000 0.481 - - 9.000 0.481
4 Mobilisasi Demobilisasi Alat Berat 1.00 ls 2,500,000.00 2,500,000.00 0.349 0.864 0.301 0.045 0.016 0.909 0.317
5 Pembuatan akses menuju badan sungai sementara - m2 113,128.49 - - - - - - - -
6 Dewatering dengan pompa air diesel 40.00 jam 25,000.00 1,000,000.00 0.139 34.545 0.120 1.818 0.006 36.364 0.127
7 SMKK 1.00 ls 4,325,000.00 4,325,000.00 0.603 0.864 0.521 0.045 0.027 0.909 0.548
11,873,371.04 1.656 1.507 0.050 1.557
II PEKERJAAN PERBAIKAN TALUD SEGMEN 5
A PEKERJAAN TANAH DAN BETON BERTULANG
1 Penggalian 1 M3 Tanah Biasa - m3 67,972.30 - - - - - - - -
2 Pengurugan Kembali 1 M3 Galian Tanah - m3 49,023.50 - - - - - - - -
3 Bongkaran Pasangan Batu dan Beton Eksisting - m3 71,953.20 - - - - - - - -
4 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area - m3 19,888.18 - - - - - - - -
5 Pemadatan Tanah Eksisting - m3 49,023.50 - - - - - - - -
6 Pengurugan dengan pasir urug - m3 178,388.92 - - - - - - - -
7 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 - m3 737,396.00 - - - - - - - -
8 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 - m3 872,242.00 - - - - - - - -
a Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
b Bekisting untuk pondasi beton ( dipakai 2 kali ) - m2 89,375.55 - - - - - - - -
c Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
9 Pekerjaan Beton Dinding Talud Beton -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 - m3 872,242.00 - - - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) - m2 316,861.88 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
10 Pekerjaan Beton Sloof 20x30cm -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 - m3 872,242.00 - - - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
c Memasang Bekisting untuk Sloof (dipakai 2 kali) - m2 89,375.55 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
11 Pekerjaan Beton Konsul Cantilever -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 - m3 872,242.00 - - - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
c Memasang Bekisting untuk Balok (dipakai 2 kali) - m2 120,181.13 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
12 Pekerjaan Plat Beton tebal 12 cm -
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) - m3 872,242.00 - - - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis - kg 10,697.66 - - - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) - m2 316,861.88 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
13 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm - m 77,312.85 - - - - - - - -
14 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm - m 86,676.29 - - - - - - - -
15 Memasang Stek Besi - kg 11,860.70 - - - - - - - -
16 Pekerjaan Plat Beton Pot tebal 10 cm -
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) - m3 872,242.00 - - - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
c Bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm - m2 118,158.83 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -

Laporan Progres Mingguan ke-20


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
- - - - -

Laporan Progres Mingguan ke-20


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
B PEKERJAAN PASANGAN DINDING
1 Pemasangan Dinding Bata Merah Bakar Sekam Tebal 1/2 Bata Camp. 1SP 6PP - m2 116,576.48 - - - - - - - -
2 Pemasangan Plesteran 1 Pc 6 Pp Tebal 15 mm - m2 54,689.70 - - - - - - - -
3 Pemasangan Acian - m2 33,411.23 - - - - - - - -
4 Pemasangan Plesteran Skoning 1 Pc 2Pp lebar 10 cm - m 55,075.90 - - - - - - - -
5 Pemasangan Kepala Kolom - bh 50,000.00 - - - - - - - -
- - - - -
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PENGECATAN
1 Pengecatan Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Weathershield luar ruangan - m2 11,686.42 - - - - - - - -
- - - - -
B PEKERJAAN RUMAH TERDAMPAK
I. PEKERJAAN BONGKARAN
1 Membongkar 1 m2 genteng / sirap untuk dipergunakan lagi 77.17 m2 3,628.42 280,005.33 0.039 61.813 0.031 15.357 0.008 77.170 0.039
2 Membongkar 1 m3 kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi 0.37 m3 991,595.91 366,890.49 0.051 0.296 0.041 0.074 0.010 0.370 0.051
3 Pembongkaran 1 m3 pasangan bata merah dan membersihkan 12.72 m3 185,908.38 2,364,754.54 0.330 11.019 0.286 - - 11.019 0.286
4 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 1.50 m3 688,832.33 1,033,248.50 0.144 1.203 0.116 - - 1.203 0.116
II. PEKERJAAN TANAH -
1 Menggali 1 m3 tanah biasa sedalam 1 meter 27.22 m3 67,972.30 1,850,206.01 0.258 27.220 0.258 - - 27.220 0.258
2 Pengurugan Kembali 1 m3 Galian Tanah 10.11 m3 18,745.83 189,520.38 0.026 10.110 0.026 - - 10.110 0.026
3 Pengurugan dengan pasir urug 1.82 m3 173,624.00 315,995.68 0.044 1.820 0.044 - - 1.820 0.044
4 Peninggian peil lantai 9.18 m3 18,745.83 172,086.75 0.024 9.180 0.024 - - 9.180 0.024
III. PEKERJAAN PONDASI -
1 Memasang 1 m3 pondasi batu belah, campuran 1 PC 6 PP 16.49 m2 665,195.09 10,969,067.11 1.530 16.490 1.530 - - 16.490 1.530
IV. PEKERJAAN BETON -
1 Membuat 1 m3 Sloof beton bertulang (200 kg besi + bekisting) 1.06 m3 3,844,764.87 4,075,450.77 0.569 1.060 0.569 - - 1.060 0.569
2 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) 2.29 m3 7,083,735.01 16,221,753.18 2.263 2.290 2.263 - - 2.290 2.263
3 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) 3.05 m3 5,659,422.09 17,261,237.38 2.408 3.050 2.408 - - 3.050 2.408
4 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.14 m3 723,713.11 101,319.83 0.014 0.140 0.014 - - 0.140 0.014
5 Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting) 0.57 m3 3,127,107.54 1,782,451.30 0.249 0.570 0.249 - - 0.570 0.249
6 Sloof 150 x 200 dengan beton K 225 Tulangan 105 kg 0.74 m3 3,295,166.46 2,438,423.18 0.340 0.740 0.340 - - 0.740 0.340
7 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm 67.35 m' 77,312.85 5,207,020.70 0.726 67.350 0.726 - - 67.350 0.726
8 Balok 150 x 200 dengan beton K 225 Tulangan 105 kg 1.01 m3 3,705,897.33 3,742,956.31 0.522 1.010 0.522 - - 1.010 0.522
9 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm 54.15 m' 86,676.29 4,693,521.24 0.655 54.150 0.655 - - 54.150 0.655
10 Membuat 1 m3 Plat Lantai beton bertulang 2.95 m3 3,119,381.73 9,202,176.12 1.284 2.950 1.284 - - 2.950 1.284
11 Membuat 1 m3 Plat Tangga beton bertulang 0.72 m3 3,119,381.73 2,245,954.85 0.313 0.720 0.313 - - 0.720 0.313
12 Membuat 1 m3 Plat Water torn beton bertulang 0.42 m3 3,119,381.73 1,310,140.33 0.183 0.420 0.183 - - 0.420 0.183
V. PEKERJAAN DINDING -
1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP 161.84 m2 116,576.48 18,866,738.23 2.632 161.840 2.632 - - 161.840 2.632
2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP, trap tangga 6.30 m2 250,668.02 1,579,208.52 0.220 6.300 0.220 - - 6.300 0.220
VI PEKERJAAN KAYU -
1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.27 m3 16,443,774.77 4,439,819.19 0.619 0.270 0.619 - - 0.270 0.619
Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.02 m3 8,048,535.00 160,970.70 0.022 0.020 0.022 - - 0.020 0.022
2 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti 12.32 m2 644,715.80 7,942,898.68 1.108 12.320 1.108 - - 12.320 1.108
3 Memasang 1 m3 konstruksi gordeng, kayu glugu - m3 4,450,537.65 - - - - - - - -
VII. PEKERJAAN PLESTERAN -
1 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm 96.76 m2 54,689.70 5,291,775.27 0.738 96.760 0.738 - - 96.760 0.738
2 Memasang 1 m2 acian 96.76 m2 33,411.23 3,232,870.55 0.451 96.760 0.451 - - 96.760 0.451
3 Pemasangan 1 m2 plesteran ciprat 1SP : 2PP 33.50 m2 45,029.48 1,508,487.73 0.210 33.500 0.210 - - 33.500 0.210
VIII. PEKERJAAN PENGECATAN -
1 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 96.76 m2 11,686.42 1,130,778.06 0.158 96.760 0.158 - - 96.760 0.158
IX. PEKERJAAN PENUTUP ATAP -
1 Memasang 1 m2 Atap Galvalum (Paket) 78.51 m3 190,000.00 14,917,137.50 2.081 78.511 2.081 - - 78.511 2.081
2 Pemasangan 1 m talang datar Galvalum lebar 60 cm - m' 105,483.99 - - - - - - - -
3 Pemasangan 1 m talang datar U PVC 8.64 m' 73,235.87 632,903.97 0.088 8.506 0.087 0.136 0.001 8.642 0.088
X. PEKERJAAN PENUTUP LANTAI DAN DINDING -
1 Memasang 1 m2 lantai keramik (30 x 30) cm - m2 114,193.22 - - - - - - - -
2 Membuat rabat beton lantai mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 2.08 m3 723,713.11 1,504,722.31 0.210 2.079 0.210 - - 2.079 0.210
3 Memasang 1 m2 lantai keramik (20 x 20) cm 4.99 m2 184,674.28 921,524.65 0.129 4.990 0.129 - - 4.990 0.129
XI. PEKERJAAN SANITASI - - - - -
1 Memasang 1 buah Kloset Jongkok Porselen 2.00 bh 280,952.58 561,905.16 0.078 2.000 0.078 - - 2.000 0.078
2 Memasang 1 m Pipa PVC tipe AW 16.00 m' 19,406.20 310,499.27 0.043 16.000 0.043 - - 16.000 0.043
3 Memasang 1 m Pipa PVC tipe AW 1 8.00 m' 22,254.33 178,034.63 0.025 8.000 0.025 - - 8.000 0.025
4 Memasang 1 m Pipa PVC tipe AW 3 18.00 m' 63,036.61 1,134,659.00 0.158 17.620 0.155 0.380 0.003 18.000 0.158
5 Memasang 1 buah Kran atau 2.00 bh 46,068.18 92,136.37 0.013 2.000 0.013 - - 2.000 0.013
6 Memasang 1 buah Floor Drain 2.00 bh 80,836.18 161,672.35 0.023 2.000 0.023 - - 2.000 0.023
7 Memasang 1 buah Pintu Kamar Mandi 2.00 bh 650,000.00 1,300,000.00 0.181 2.000 0.181 - - 2.000 0.181
8 Pemasangan 1 M Pipa PVC tipe D 4 12.00 m 85,618.17 1,027,418.08 0.143 12.000 0.143 - - 12.000 0.143

Laporan Progres Mingguan ke-20


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
XII. PEKERJAAN ELEKTRIKAL -
1 Instalasi Penerangan menggunakan kabel NYY 3x2,5mm² dalam pipa conduit Ø 20mm. 10.00 titik 105,000.00 1,050,000.00 0.146 10.000 0.146 - - 10.000 0.146
2 Instalasi stop kontak dinding, menggunakan kabel NYM 3x2,5mm² 5.00 titik 100,000.00 500,000.00 0.070 5.000 0.070 - - 5.000 0.070
3 Saklar tunggal inbow, 1 gang 1 way 4.00 bh 20,000.00 80,000.00 0.011 4.000 0.011 - - 4.000 0.011
4 Saklar seri inbow, 1 gang 2 way 4.00 bh 25,000.00 100,000.00 0.014 4.000 0.014 - - 4.000 0.014
5 Stop kontak wall type 1ph, 16A, 1 gang 5.00 bh 20,000.00 100,000.00 0.014 5.000 0.014 - - 5.000 0.014
6 Lampu PLC 18 Watt dengan fitting gantung 8.00 bh 75,000.00 600,000.00 0.084 8.000 0.084 - - 8.000 0.084
7 Lampu PLC 7 Watt dengan fitting gantung 2.00 bh 65,000.00 130,000.00 0.018 2.000 0.018 - - 2.000 0.018
8 Penyambungan kabel 1.00 Ls 500,000.00 500,000.00 0.070 1.000 0.070 - - 1.000 0.070
9 Box MCB + MCB 2.00 bh 250,000.00 500,000.00 0.070 2.000 0.070 - - 2.000 0.070
XIII. PEKERJAAN LAIN-LAIN -
1 Pintu Folding gate 6.00 m2 788,049.93 4,728,299.56 0.660 6.000 0.660 - - 6.000 0.660
2 Railling pengaman besi Hollow 40x40 / 40x20 mm, finishing cat 11.48 m2 550,000.00 6,312,240.00 0.881 11.247 0.863 0.230 0.018 11.477 0.881
XIV. Rumah Timur sungai - -
1 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm 4.50 m' 77,312.85 347,907.84 0.049 - - - - - -
2 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm 5.70 m' 86,676.29 494,054.87 0.069 - - - - - -
3 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP 3.10 m2 116,576.48 361,387.10 0.050 - - - - - -
4 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm 7.41 m2 54,689.70 405,250.67 0.057 - - - - - -
5 Memasang 1 m2 acian 7.41 m2 33,411.23 247,577.21 0.035 - - - - - -
6 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 7.41 m2 11,686.42 86,596.38 0.012 - - - - - -
7 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.13 m3 8,048,535.00 1,046,309.55 0.146 - - - - - -
8 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti 4.64 m2 644,715.80 2,991,481.32 0.417 - - - - - -
9 Memasang 1 m2 Atap Galvalum (Paket) 17.55 m2 190,000.00 3,334,500.00 0.465 - - - - - -
10 Membuat rabat beton lantai mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 1.22 m3 723,713.11 882,929.99 0.123 - - - - - -

177,518,874.67 24.764 23.228 0.040 23.268


III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PEMBERSIHAN SALURAN
1 Penggalian Tanah Lumpur dan Endapan Limbah Sedalam 30 cm 70.70 m3 109,311.98 7,728,356.66 1.078 68.564 1.046 - - 68.564 1.046
2 Pembersihan dan Pembuangan Tanah Lumpur dan Limbah Keluar Area 89.07 m3 29,796.55 2,653,978.98 0.370 84.822 0.353 - - 84.822 0.353
3 Pemadatan Tanah Eksisting 70.70 m3 49,023.50 3,465,961.48 0.483 66.315 0.454 2.121 0.015 68.436 0.468
4 Pengurugan dengan pasir urug, 10 cm 21.87 m3 178,388.92 3,901,365.68 0.544 20.731 0.516 0.656 0.016 21.387 0.532
Pengurugan dengan pasir urug, 10 cm 1.69 m3 173,624.00 293,424.56 0.041 1.325 0.032 0.051 0.001 1.376 0.033
5 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 10.93 m3 737,396.00 8,059,738.25 1.124 9.837 1.012 1.093 0.112 10.930 1.124
Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.85 m3 723,713.11 615,156.14 0.086 0.629 0.064 0.221 0.022 0.850 0.086
6 Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 23.56 m3 872,242.00 20,550,021.46 2.867 21.283 2.590 2.277 0.277 23.560 2.867
a Jaring Kawat baja/Wire Mesh M5 1 lapis 501.73 kg 10,697.66 5,367,334.57 0.749 441.164 0.658 60.566 0.090 501.730 0.749
7 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 158.40 m 77,312.85 12,246,356.04 1.708 106.560 1.149 51.840 0.559 158.400 1.708
8 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 583.98 m 86,676.29 50,617,221.34 7.061 573.789 6.938 10.191 0.123 583.980 7.061
9 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,2m, K.300 - bh 626,150.00 - - - - - - - -
10 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,8m, K.300 - bh 750,000.00 - - - - - - - -
11 Pekerjaan Plat Beton tebal 15 cm - - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 6.81 m3 872,242.00 5,939,968.00 0.829 - - 4.968 0.604 4.968 0.604
b Jaring Kawat baja/Wire Mesh M8 2 lapis 480.26 kg 10,697.66 5,137,655.91 0.717 303.194 0.452 88.182 0.132 391.376 0.584
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 10.17 m2 316,861.88 3,222,485.34 0.450 8.501 0.376 1.627 0.072 10.128 0.448
d Pembongkaran 1 M2 Bekisting 10.17 m2 15,645.80 159,117.77 0.022 - - - - - -
12 Pekerjaan Plat Beton tebal 10 cm - - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 22.73 m3 872,242.00 19,826,060.60 2.766 22.730 2.766 - - 22.730 2.766
b Jaring Kawat baja/Wire Mesh M8 1 lapis 1,186.92 kg 10,697.66 12,697,260.97 1.771 1,186.920 1.771 - - 1,186.920 1.771
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 57.68 m2 316,861.88 18,276,593.34 2.550 57.680 2.550 - - 57.680 2.550
d Pembongkaran 1 M2 Bekisting 57.68 m2 15,645.80 902,449.63 0.126 - - 57.680 0.126 57.680 0.126
181,660,506.72 25.341 22.725 2.150 24.875
B PEKERJAAN JARINGAN IPAL KOMUNAL
1 Pekerjaan Galian Tanah Pipa 31.93 m3 67,972.30 2,170,355.55 0.303 25.544 0.242 - - 25.544 0.242
2 Pengurugan dengan pasir urug 14.41 m3 178,388.92 2,570,584.34 0.359 8.646 0.215 5.764 0.143 14.410 0.359
3 Pengurugan Kembali 1 M3 Galian Tanah 12.97 m3 49,023.50 635,966.29 0.089 6.486 0.044 5.189 0.035 11.675 0.080
4 Pemasangan 1 M Pipa PVC tipe AW 4 - m 90,907.55 - -
5 Saluran Pipa Air Limbah SDR - 41, Dia 15 cm , inc. fitting & Assecories - m 133,200.00 - - - - - - - -
6 Saluran Pipa Air Limbah SDR - 41, Dia 20 cm, , inc. fitting & Assecories - m 203,900.00 - - - - - - - -
7 Pemasangan Clean Out Inc. Fitting & Assecories 43.00 ttk 185,000.00 7,955,000.00 1.110 22.000 0.568 - - 22.000 0.568
8 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 100 org, 20 m3 / hari, - unit 7,500,000.00 - - - - - - - -
(Galian, Urugan, Pondasi, Tutup Beton, Penyambungan Instalasi) -
9 Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm - unit 975,000.00 - - - - - - - -
10 Pekerjaan Sumur Resapan, Dia 100 cm, Kedalaman 2 m, Inc. Tutup Beton Berlubang - ttk 500,000.00 - - - - - - - -
11 Grill Beton Penutup Sumur Resapan - unit 750,000.00 - - - - - - - -
12 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 7.05 m3 688,832.33 4,856,267.95 0.677 1.484 0.143 5.234 0.503 6.718 0.646
13 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area 7.05 m3 19,888.18 140,211.63 0.020 1.484 0.004 5.234 0.015 6.718 0.019
14 Pemasangan 1 M Pipa PVC tipe D 6 422.00 m 133,200.00 56,210,400.00 7.841 356.895 6.632 16.880 0.314 373.775 6.945
15 Pemasangan 1 M Pipa PVC tipe D 4 165.50 m 85,618.17 14,169,807.73 1.977 118.973 1.421 - - 118.973 1.421
16 Pekerjaan Sumur Resapan kedalaman 4 Buis Beton Dia 80 cm 13.00 ttk 474,124.46 6,163,617.96 0.860 13.000 0.860 - - 13.000 0.860
17 Pasang Grill Besi Penutup Sumur Resapan 15.00 unit 826,875.00 12,403,125.00 1.730 13.071 1.508 - - 13.071 1.508

Laporan Progres Mingguan ke-20


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)

C PEKERJAAN PEMASANGAN DAN PENGADAAN INSTALASI IPAL


1 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 50 org, 10 m3 / hari
a Pengadaan Unit IPAL kap 50 org, 10 m3 / hari 1.00 unit 110,250,000.00 110,250,000.00 15.380 0.500 7.690 0.300 4.614 0.800 12.304
b Galian Tanah 57.21 m3 67,972.30 3,888,695.29 0.542 57.210 0.542 - - 57.210 0.542
c Pengurugan Kembali 1 M3 Galian Tanah 2.39 m3 49,023.50 117,166.17 0.016 2.390 0.016 - - 2.390 0.016
d Pengurugan dengan pasir urug 4.98 m3 178,388.92 888,028.96 0.124 - - - - - -
e Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Dinding, Lantai dan Tutup 11.77 m3 872,242.00 10,266,288.31 1.432 9.152 1.114 - - 9.152 1.114
Jaring Kawat baja/Wire Mesh M8 534.95 kg 10,697.66 5,722,710.68 0.798 527.409 0.787 - - 527.409 0.787
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 30.14 m2 316,861.88 9,550,217.12 1.332 26.498 1.171 - - 26.498 1.171
Pembongkaran 1 M2 Bekisting 30.14 m2 15,645.80 471,564.35 0.066 26.498 0.058 - - 26.498 0.058
f Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Inlet 0.30 m3 872,242.00 261,672.60 0.037 0.222 0.027 - - 0.222 0.027
Jaring Kawat baja/Wire Mesh M8 11.06 kg 10,697.66 118,316.07 0.017 8.184 0.012 - - 8.184 0.012
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.66 m2 316,861.88 209,128.84 0.029 0.488 0.022 - - 0.488 0.022
Pembongkaran 1 M2 Bekisting 0.66 m2 15,645.80 10,326.23 0.001 0.488 0.001 - - 0.488 0.001
g Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Outlet 0.41 m3 872,242.00 357,619.22 0.050 0.246 0.030 - - 0.246 0.030
Jaring Kawat baja/Wire Mesh M8 14.98 kg 10,697.66 160,250.88 0.022 8.988 0.013 - - 8.988 0.013
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.96 m2 316,861.88 304,187.41 0.042 0.576 0.025 - - 0.576 0.025
Pembongkaran 1 M2 Bekisting 0.96 m2 15,645.80 15,019.97 0.002 0.576 0.001 - - 0.576 0.001
h Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Kolom 15 x 15 cm 0.47 m3 872,242.00 409,953.74 0.057 0.470 0.057 - - 0.470 0.057
Pembesian dg Besi Polos atau Besi Ulir 119.39 kg 11,860.70 1,416,048.75 0.198 119.390 0.198 - - 119.390 0.198
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.44 m2 316,861.88 456,281.11 0.064 1.440 0.064 - - 1.440 0.064
Pembongkaran 1 M2 Bekisting 1.44 m2 15,645.80 22,529.95 0.003 1.440 0.003 - - 1.440 0.003
i Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Balok 15 x 20 cm 0.12 m3 872,242.00 104,669.04 0.015 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 23.91 kg 11,860.70 283,589.29 0.040 - - - - - -
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.55 m2 316,861.88 174,274.03 0.024 - - - - - -
Pembongkaran 1 M2 Bekisting 0.55 m2 15,645.80 8,605.19 0.001 - - - - - -
j Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, pondasi 60 x 60 x 20 cm 0.72 m3 872,242.00 628,014.24 0.088 0.576 0.070 - - 0.576 0.070
Pembesian dg Besi Polos atau Besi Ulir 36.93 kg 11,860.70 438,015.58 0.061 29.544 0.049 - - 29.544 0.049
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.20 m2 316,861.88 380,234.26 0.053 0.960 0.042 - - 0.960 0.042
Pembongkaran 1 M2 Bekisting 1.20 m2 15,645.80 18,774.96 0.003 0.960 0.002 - - 0.960 0.002
k Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm 3.00 unit 975,000.00 2,925,000.00 0.408 - - - - - -
l Tutup Manhole diameter 40 cm 2.00 bh 400,000.00 800,000.00 0.112 - - - - - -

2 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 20 org, 2 m3 / hari
a Pengadaan Unit IPAL kap 20 org, 2 m3 / hari 1.00 unit 38,697,750.00 38,697,750.00 5.398 0.500 2.699 0.350 1.889 0.850 4.589
b Galian Tanah 26.89 m3 67,972.30 1,827,775.15 0.255 26.890 0.255 - - 26.890 0.255
c Pengurugan Kembali 1 M3 Galian Tanah 1.33 m3 49,023.50 65,201.26 0.009 - - - - - -
d Pengurugan dengan pasir urug 2.16 m3 178,388.92 385,973.86 0.054 - - - - - -
e Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Dinding, Lantai dan Tutup 6.37 m3 872,242.00 5,556,181.52 0.775 5.962 0.725 - - 5.962 0.725
Jaring Kawat baja/Wire Mesh M8 270.48 kg 10,697.66 2,893,501.79 0.404 253.169 0.378 - - 253.169 0.378
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 8.68 m2 316,861.88 2,750,361.13 0.384 8.124 0.359 - - 8.124 0.359
Pembongkaran 1 M2 Bekisting 8.68 m2 15,645.80 135,805.53 0.019 8.246 0.018 - - 8.246 0.018
f Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Inlet 0.17 m3 872,242.00 148,281.14 0.021 - - 0.162 0.020 0.162 0.020
Jaring Kawat baja/Wire Mesh M8 6.48 kg 10,697.66 69,320.81 0.010 - - 6.156 0.009 6.156 0.009
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.33 m2 316,861.88 104,564.42 0.015 - - 0.314 0.014 0.314 0.014
Pembongkaran 1 M2 Bekisting 0.33 m2 15,645.80 5,163.11 0.001 - - - - - -
g Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Outlet 0.23 m3 872,242.00 200,615.66 0.028 - - 0.219 0.027 0.219 0.027
Jaring Kawat baja/Wire Mesh M8 8.44 kg 10,697.66 90,288.21 0.013 - - 8.018 0.012 8.018 0.012
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.48 m2 316,861.88 152,093.70 0.021 - - 0.456 0.020 0.456 0.020
Pembongkaran 1 M2 Bekisting 0.48 m2 15,645.80 7,509.98 0.001 - - - - - -
h Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Kolom 15 x 15 cm 0.35 m3 872,242.00 305,284.70 0.043 0.350 0.043 - - 0.350 0.043
Pembesian dg Besi Polos atau Besi Ulir 89.54 kg 11,860.70 1,062,006.91 0.148 89.540 0.148 - - 89.540 0.148
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.08 m2 316,861.88 342,210.83 0.048 1.080 0.048 - - 1.080 0.048
Pembongkaran 1 M2 Bekisting 1.08 m2 15,645.80 16,897.46 0.002 1.080 0.002 - - 1.080 0.002
i Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Balok 15 x 20 cm 0.08 m3 872,242.00 69,779.36 0.010 - - - - - -
Pembesian dg Besi Polos atau Besi Ulir 19.41 kg 11,860.70 230,216.15 0.032 - - 14.558 0.024 14.558 0.024
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.40 m2 316,861.88 126,744.75 0.018 - - - - - -
Pembongkaran 1 M2 Bekisting 0.40 m2 15,645.80 6,258.32 0.001 - - - - - -
j Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, pondasi 60 x 60 x 20 cm 0.54 m3 872,242.00 471,010.68 0.066 0.540 0.066 - - 0.540 0.066
Pembesian dg Besi Polos atau Besi Ulir 27.69 kg 11,860.70 328,422.73 0.046 27.690 0.046 - - 27.690 0.046
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.90 m2 316,861.88 285,175.69 0.040 0.900 0.040 - - 0.900 0.040
Pembongkaran 1 M2 Bekisting 0.90 m2 15,645.80 14,081.22 0.002 0.900 0.002 - - 0.900 0.002
k Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm 2.00 unit 975,000.00 1,950,000.00 0.272 - - - - - -
l Tutup Manhole diameter 40 cm 2.00 bh 400,000.00 800,000.00 0.112 - - - - - -

Laporan Progres Mingguan ke-20


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)

D PEKERJAAN LAIN - LAIN


1 Pasang Bak Kontrol dengan tutup precast cetak diameter 40 cm 3.00 bh 850,000.00 2,550,000.00 0.356 3.000 0.356 - - 3.000 0.356
2 Pembersihan dan Pembuangan Bekas Galian Tanah IPAL Keluar Area 84.10 m3 67,972.30 5,716,470.45 0.797 63.075 0.598 - - 63.075 0.598
3 Pembongkaran 1 M2 Paving Block eksisting 31.40 m2 49,910.10 1,567,177.00 0.219 23.550 0.164 - - 23.550 0.164
4 Pemasangan 1 M2 kembali Paving Block eksisting 31.40 m2 64,463.10 2,024,141.20 0.282 4.746 0.043 - - 4.746 0.043
5 Pembongkaran dan Pemasangan kembali pipa PDAM yang terdampak galian 1.00 Ls 1,500,000.00 1,500,000.00 0.209 - - - - - -
6 Check Valve diameter 6 inch+ Reducer diameter 8x6 inch 1.00 bh 4,669,087.50 4,669,087.50 0.651 - - - - - -
7 Check Valve diameter 6 inch 1.00 bh 4,278,582.00 4,278,582.00 0.597 - - - - - -
8 Check Valve diameter 4 inch 2.00 bh 2,051,002.80 4,102,005.60 0.572 - - - - - -
9 Membuat rabat beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 1.55 m3 723,713.11 1,121,650.74 0.156 - - - - - -
10 Grill besi area ipal barat 1.50 m2 828,726.02 1,243,089.03 0.173 - - - - - -

345,803,198.30 48.239 29.621 7.639 37.259

JUMLAH 654,697,105.06 716,855,950.73 100.000 77.081 9.879 86.960


PRESTASI MINGGU LALU 77.081
PRESTASI MINGGU INI 9.879
PRESTASI SAMPAI DENGAN MINGGU INI 86.960
PRESTASI MENURUT SCHEDULE 87.568
LEBIH CEPAT (+) / TERLAMBAT (-) (0.608)

Yogyakarta, 10 Oktober 2021


di buat oleh,
KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA

Noor Hasan Bambang Erlianto


Pengawas Pelaksana

Laporan Progres Mingguan ke-20


REKAPITULASI
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : XX ( Dua puluh )


Periode : 04 Oktober 2021 sampai dengan 10 Oktober 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
ADDENDUM II : 050 / 1909 / VII / 2021, TANGGAL 19 JULI 2021
ADDENDUM III : 050 / 0615 / IX / 2021, TANGGAL 6 SEPTEMBER 2021
NILAI KONTRAK ADDENDUM III : Rp 788,541,545.80
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO PEKERJAAN PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp (%) BOBOT % BOBOT % BOBOT %

I PEKERJAAN PERSIAPAN 11,873,371.04 1.656 1.507 0.050 1.557

II PEKERJAAN PERBAIKAN TALUD SEGMEN 5


A PEKERJAAN TANAH DAN BETON BERTULANG - - - - -
B PEKERJAAN PASANGAN DINDING - - - - -

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PENGECATAN - - - - -
B PEKERJAAN RUMAH TERDAMPAK 177,518,874.67 24.764 23.228 0.040 23.268

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PEMBERSIHAN SALURAN 181,660,506.72 25.341 22.725 2.150 24.875
B PEKERJAAN JARINGAN IPAL KOMUNAL 345,803,198.30 48.239 29.621 7.639 37.259

JUMLAH 716,855,950.73 100.000 77.081 9.879 86.960


PRESTASI MINGGU LALU - 77.081
PRESTASI MINGGU INI 9.879
PRESTASI SAMPAI DENGAN MINGGU INI 86.960
PRESTASI MENURUT SCHEDULE 87.568
LEBIH CEPAT (+) / TERLAMBAT (-) (0.608)

Yogyakarta, 10 Oktober 2021


di buat oleh,
PEJABAT PEMBUAT KOMITMEN TIM TEKNIS KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA
1. Cicilia Novi hendrawati, M.SC., M.Eng.
NIP. 19781102 200501 2 011 ...........................

2. Danang Dwi Wahyujati,S.Kom.,M.Eng


NIP. 19761028 199803 1 004 ...........................
SIGIT SETIAWAN, ST.MT 3. Sudaryanto
NIP. 19690605 199303 1 007 RISMAN WARCHAN ZULIANTO
NIP. 19770623 200501 1 013 ........................... Tim Leader Direktur
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : XXI ( Dua puluh satu )


Periode : 11 Oktober 2021 sampai dengan 17 Oktober 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
ADDENDUM II : 050 / 1909 / VII / 2021, TANGGAL 19 JULI 2021
ADDENDUM III : 050 / 0615 / IX / 2021, TANGGAL 6 SEPTEMBER 2021
NILAI KONTRAK ADDENDUM III : Rp 788,541,545.80
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
I PEKERJAAN PERSIAPAN
1 Pembuatan Papan Nama Pekerjaan 1.00 bh 250,000.00 250,000.00 0.035 1.000 0.035 - - 1.000 0.035
2 Pengukuran dan Pemasangan Bouwplank 28.56 m 12,198.91 348,400.73 0.049 28.560 0.049 - - 28.560 0.049
3 Pembuatan bedeng pekerja 9.00 m2 383,330.04 3,449,970.32 0.481 9.000 0.481 - - 9.000 0.481
4 Mobilisasi Demobilisasi Alat Berat 1.00 ls 2,500,000.00 2,500,000.00 0.349 0.909 0.317 0.091 0.032 1.000 0.349
5 Pembuatan akses menuju badan sungai sementara - m2 113,128.49 - - - - - - - -
6 Dewatering dengan pompa air diesel 40.00 jam 25,000.00 1,000,000.00 0.139 36.364 0.127 3.636 0.013 40.000 0.139
7 SMKK 1.00 ls 4,325,000.00 4,325,000.00 0.603 0.909 0.548 0.091 0.055 1.000 0.603
11,873,371.04 1.656 1.557 0.099 1.656
II PEKERJAAN PERBAIKAN TALUD SEGMEN 5
A PEKERJAAN TANAH DAN BETON BERTULANG
1 Penggalian 1 M3 Tanah Biasa - m3 67,972.30 - - - - - - - -
2 Pengurugan Kembali 1 M3 Galian Tanah - m3 49,023.50 - - - - - - - -
3 Bongkaran Pasangan Batu dan Beton Eksisting - m3 71,953.20 - - - - - - - -
4 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area - m3 19,888.18 - - - - - - - -
5 Pemadatan Tanah Eksisting - m3 49,023.50 - - - - - - - -
6 Pengurugan dengan pasir urug - m3 178,388.92 - - - - - - - -
7 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 - m3 737,396.00 - - - - - - - -
8 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 - m3 872,242.00 - - - - - - - -
a Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
b Bekisting untuk pondasi beton ( dipakai 2 kali ) - m2 89,375.55 - - - - - - - -
c Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
9 Pekerjaan Beton Dinding Talud Beton -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 - m3 872,242.00 - - - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) - m2 316,861.88 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
10 Pekerjaan Beton Sloof 20x30cm -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 - m3 872,242.00 - - - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
c Memasang Bekisting untuk Sloof (dipakai 2 kali) - m2 89,375.55 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
11 Pekerjaan Beton Konsul Cantilever -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 - m3 872,242.00 - - - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
c Memasang Bekisting untuk Balok (dipakai 2 kali) - m2 120,181.13 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
12 Pekerjaan Plat Beton tebal 12 cm -
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) - m3 872,242.00 - - - - - - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis - kg 10,697.66 - - - - - - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) - m2 316,861.88 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -
13 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm - m 77,312.85 - - - - - - - -
14 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm - m 86,676.29 - - - - - - - -
15 Memasang Stek Besi - kg 11,860.70 - - - - - - - -
16 Pekerjaan Plat Beton Pot tebal 10 cm -
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) - m3 872,242.00 - - - - - - - -
b Pembesian dg Besi Polos atau Besi Ulir - kg 11,860.70 - - - - - - - -
c Bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm - m2 118,158.83 - - - - - - - -
d Pembongkaran 1 M2 Bekisting - m2 15,645.80 - - - - - - - -

Laporan Progres Mingguan ke-21


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
- - - - -

Laporan Progres Mingguan ke-21


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
B PEKERJAAN PASANGAN DINDING
1 Pemasangan Dinding Bata Merah Bakar Sekam Tebal 1/2 Bata Camp. 1SP 6PP - m2 116,576.48 - - - - - - - -
2 Pemasangan Plesteran 1 Pc 6 Pp Tebal 15 mm - m2 54,689.70 - - - - - - - -
3 Pemasangan Acian - m2 33,411.23 - - - - - - - -
4 Pemasangan Plesteran Skoning 1 Pc 2Pp lebar 10 cm - m 55,075.90 - - - - - - - -
5 Pemasangan Kepala Kolom - bh 50,000.00 - - - - - - - -
- - - - -
III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PENGECATAN
1 Pengecatan Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Weathershield luar ruangan - m2 11,686.42 - - - - - - - -
- - - - -
B PEKERJAAN RUMAH TERDAMPAK
I. PEKERJAAN BONGKARAN
1 Membongkar 1 m2 genteng / sirap untuk dipergunakan lagi 77.17 m2 3,628.42 280,005.33 0.039 77.170 0.039 - - 77.170 0.039
2 Membongkar 1 m3 kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi 0.37 m3 991,595.91 366,890.49 0.051 0.370 0.051 - - 0.370 0.051
3 Pembongkaran 1 m3 pasangan bata merah dan membersihkan 12.72 m3 185,908.38 2,364,754.54 0.330 11.019 0.286 1.701 0.044 12.720 0.330
4 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 1.50 m3 688,832.33 1,033,248.50 0.144 1.203 0.116 0.297 0.029 1.500 0.144
II. PEKERJAAN TANAH -
1 Menggali 1 m3 tanah biasa sedalam 1 meter 27.22 m3 67,972.30 1,850,206.01 0.258 27.220 0.258 - - 27.220 0.258
2 Pengurugan Kembali 1 m3 Galian Tanah 10.11 m3 18,745.83 189,520.38 0.026 10.110 0.026 - - 10.110 0.026
3 Pengurugan dengan pasir urug 1.82 m3 173,624.00 315,995.68 0.044 1.820 0.044 - - 1.820 0.044
4 Peninggian peil lantai 9.18 m3 18,745.83 172,086.75 0.024 9.180 0.024 - - 9.180 0.024
III. PEKERJAAN PONDASI -
1 Memasang 1 m3 pondasi batu belah, campuran 1 PC 6 PP 16.49 m2 665,195.09 10,969,067.11 1.530 16.490 1.530 - - 16.490 1.530
IV. PEKERJAAN BETON -
1 Membuat 1 m3 Sloof beton bertulang (200 kg besi + bekisting) 1.06 m3 3,844,764.87 4,075,450.77 0.569 1.060 0.569 - - 1.060 0.569
2 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) 2.29 m3 7,083,735.01 16,221,753.18 2.263 2.290 2.263 - - 2.290 2.263
3 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) 3.05 m3 5,659,422.09 17,261,237.38 2.408 3.050 2.408 - - 3.050 2.408
4 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.14 m3 723,713.11 101,319.83 0.014 0.140 0.014 - - 0.140 0.014
5 Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting) 0.57 m3 3,127,107.54 1,782,451.30 0.249 0.570 0.249 - - 0.570 0.249
6 Sloof 150 x 200 dengan beton K 225 Tulangan 105 kg 0.74 m3 3,295,166.46 2,438,423.18 0.340 0.740 0.340 - - 0.740 0.340
7 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm 67.35 m' 77,312.85 5,207,020.70 0.726 67.350 0.726 - - 67.350 0.726
8 Balok 150 x 200 dengan beton K 225 Tulangan 105 kg 1.01 m3 3,705,897.33 3,742,956.31 0.522 1.010 0.522 - - 1.010 0.522
9 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm 54.15 m' 86,676.29 4,693,521.24 0.655 54.150 0.655 - - 54.150 0.655
10 Membuat 1 m3 Plat Lantai beton bertulang 2.95 m3 3,119,381.73 9,202,176.12 1.284 2.950 1.284 - - 2.950 1.284
11 Membuat 1 m3 Plat Tangga beton bertulang 0.72 m3 3,119,381.73 2,245,954.85 0.313 0.720 0.313 - - 0.720 0.313
12 Membuat 1 m3 Plat Water torn beton bertulang 0.42 m3 3,119,381.73 1,310,140.33 0.183 0.420 0.183 - - 0.420 0.183
V. PEKERJAAN DINDING -
1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP 161.84 m2 116,576.48 18,866,738.23 2.632 161.840 2.632 - - 161.840 2.632
2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP, trap tangga 6.30 m2 250,668.02 1,579,208.52 0.220 6.300 0.220 - - 6.300 0.220
VI PEKERJAAN KAYU -
1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.27 m3 16,443,774.77 4,439,819.19 0.619 0.270 0.619 - - 0.270 0.619
Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.02 m3 8,048,535.00 160,970.70 0.022 0.020 0.022 - - 0.020 0.022
2 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti 12.32 m2 644,715.80 7,942,898.68 1.108 12.320 1.108 - - 12.320 1.108
3 Memasang 1 m3 konstruksi gordeng, kayu glugu - m3 4,450,537.65 - - - - - - - -
VII. PEKERJAAN PLESTERAN -
1 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm 96.76 m2 54,689.70 5,291,775.27 0.738 96.760 0.738 - - 96.760 0.738
2 Memasang 1 m2 acian 96.76 m2 33,411.23 3,232,870.55 0.451 96.760 0.451 - - 96.760 0.451
3 Pemasangan 1 m2 plesteran ciprat 1SP : 2PP 33.50 m2 45,029.48 1,508,487.73 0.210 33.500 0.210 - - 33.500 0.210
VIII. PEKERJAAN PENGECATAN -
1 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 96.76 m2 11,686.42 1,130,778.06 0.158 96.760 0.158 - - 96.760 0.158
IX. PEKERJAAN PENUTUP ATAP -
1 Memasang 1 m2 Atap Galvalum (Paket) 78.51 m3 190,000.00 14,917,137.50 2.081 78.511 2.081 - - 78.511 2.081
2 Pemasangan 1 m talang datar Galvalum lebar 60 cm - m' 105,483.99 - - - - - - - -
3 Pemasangan 1 m talang datar U PVC 8.64 m' 73,235.87 632,903.97 0.088 8.642 0.088 - - 8.642 0.088
X. PEKERJAAN PENUTUP LANTAI DAN DINDING -
1 Memasang 1 m2 lantai keramik (30 x 30) cm - m2 114,193.22 - - - - - - - -
2 Membuat rabat beton lantai mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 2.08 m3 723,713.11 1,504,722.31 0.210 2.079 0.210 - - 2.079 0.210
3 Memasang 1 m2 lantai keramik (20 x 20) cm 4.99 m2 184,674.28 921,524.65 0.129 4.990 0.129 - - 4.990 0.129
XI. PEKERJAAN SANITASI - - - - -
1 Memasang 1 buah Kloset Jongkok Porselen 2.00 bh 280,952.58 561,905.16 0.078 2.000 0.078 - - 2.000 0.078
2 Memasang 1 m Pipa PVC tipe AW 16.00 m' 19,406.20 310,499.27 0.043 16.000 0.043 - - 16.000 0.043
3 Memasang 1 m Pipa PVC tipe AW 1 8.00 m' 22,254.33 178,034.63 0.025 8.000 0.025 - - 8.000 0.025
4 Memasang 1 m Pipa PVC tipe AW 3 18.00 m' 63,036.61 1,134,659.00 0.158 18.000 0.158 - - 18.000 0.158
5 Memasang 1 buah Kran atau 2.00 bh 46,068.18 92,136.37 0.013 2.000 0.013 - - 2.000 0.013
6 Memasang 1 buah Floor Drain 2.00 bh 80,836.18 161,672.35 0.023 2.000 0.023 - - 2.000 0.023
7 Memasang 1 buah Pintu Kamar Mandi 2.00 bh 650,000.00 1,300,000.00 0.181 2.000 0.181 - - 2.000 0.181
8 Pemasangan 1 M Pipa PVC tipe D 4 12.00 m 85,618.17 1,027,418.08 0.143 12.000 0.143 - - 12.000 0.143

Laporan Progres Mingguan ke-21


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
XII. PEKERJAAN ELEKTRIKAL -
1 Instalasi Penerangan menggunakan kabel NYY 3x2,5mm² dalam pipa conduit Ø 20mm. 10.00 titik 105,000.00 1,050,000.00 0.146 10.000 0.146 - - 10.000 0.146
2 Instalasi stop kontak dinding, menggunakan kabel NYM 3x2,5mm² 5.00 titik 100,000.00 500,000.00 0.070 5.000 0.070 - - 5.000 0.070
3 Saklar tunggal inbow, 1 gang 1 way 4.00 bh 20,000.00 80,000.00 0.011 4.000 0.011 - - 4.000 0.011
4 Saklar seri inbow, 1 gang 2 way 4.00 bh 25,000.00 100,000.00 0.014 4.000 0.014 - - 4.000 0.014
5 Stop kontak wall type 1ph, 16A, 1 gang 5.00 bh 20,000.00 100,000.00 0.014 5.000 0.014 - - 5.000 0.014
6 Lampu PLC 18 Watt dengan fitting gantung 8.00 bh 75,000.00 600,000.00 0.084 8.000 0.084 - - 8.000 0.084
7 Lampu PLC 7 Watt dengan fitting gantung 2.00 bh 65,000.00 130,000.00 0.018 2.000 0.018 - - 2.000 0.018
8 Penyambungan kabel 1.00 Ls 500,000.00 500,000.00 0.070 1.000 0.070 - - 1.000 0.070
9 Box MCB + MCB 2.00 bh 250,000.00 500,000.00 0.070 2.000 0.070 - - 2.000 0.070
XIII. PEKERJAAN LAIN-LAIN -
1 Pintu Folding gate 6.00 m2 788,049.93 4,728,299.56 0.660 6.000 0.660 - - 6.000 0.660
2 Railling pengaman besi Hollow 40x40 / 40x20 mm, finishing cat 11.48 m2 550,000.00 6,312,240.00 0.881 11.477 0.881 - - 11.477 0.881
XIV. Rumah Timur sungai - - -
1 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm 4.50 m' 77,312.85 347,907.84 0.049 - - 4.500 0.049 4.500 0.049
2 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm 5.70 m' 86,676.29 494,054.87 0.069 - - 5.700 0.069 5.700 0.069
3 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP 3.10 m2 116,576.48 361,387.10 0.050 - - 3.100 0.050 3.100 0.050
4 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm 7.41 m2 54,689.70 405,250.67 0.057 - - 7.410 0.057 7.410 0.057
5 Memasang 1 m2 acian 7.41 m2 33,411.23 247,577.21 0.035 - - 7.410 0.035 7.410 0.035
6 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 7.41 m2 11,686.42 86,596.38 0.012 - - 7.410 0.012 7.410 0.012
7 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti 0.13 m3 8,048,535.00 1,046,309.55 0.146 - - 0.130 0.146 0.130 0.146
8 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti 4.64 m2 644,715.80 2,991,481.32 0.417 - - 4.640 0.417 4.640 0.417
9 Memasang 1 m2 Atap Galvalum (Paket) 17.55 m2 190,000.00 3,334,500.00 0.465 - - 17.550 0.465 17.550 0.465
10 Membuat rabat beton lantai mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 1.22 m3 723,713.11 882,929.99 0.123 - - 1.220 0.123 1.220 0.123

177,518,874.67 24.764 23.268 1.495 24.764


III PEKERJAAN PENATAAN LINGKUNGAN RW 1
A PEKERJAAN PEMBERSIHAN SALURAN
1 Penggalian Tanah Lumpur dan Endapan Limbah Sedalam 30 cm 70.70 m3 109,311.98 7,728,356.66 1.078 68.564 1.046 2.136 0.033 70.700 1.078
2 Pembersihan dan Pembuangan Tanah Lumpur dan Limbah Keluar Area 89.07 m3 29,796.55 2,653,978.98 0.370 84.822 0.353 4.248 0.018 89.070 0.370
3 Pemadatan Tanah Eksisting 70.70 m3 49,023.50 3,465,961.48 0.483 68.436 0.468 2.264 0.015 70.700 0.483
4 Pengurugan dengan pasir urug, 10 cm 21.87 m3 178,388.92 3,901,365.68 0.544 21.387 0.532 0.483 0.012 21.870 0.544
Pengurugan dengan pasir urug, 10 cm 1.69 m3 173,624.00 293,424.56 0.041 1.376 0.033 0.314 0.008 1.690 0.041
5 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 10.93 m3 737,396.00 8,059,738.25 1.124 10.930 1.124 - - 10.930 1.124
Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 0.85 m3 723,713.11 615,156.14 0.086 0.850 0.086 - - 0.850 0.086
6 Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 23.56 m3 872,242.00 20,550,021.46 2.867 23.560 2.867 - - 23.560 2.867
a Jaring Kawat baja/Wire Mesh M5 1 lapis 501.73 kg 10,697.66 5,367,334.57 0.749 501.730 0.749 - - 501.730 0.749
7 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm 158.40 m 77,312.85 12,246,356.04 1.708 158.400 1.708 - - 158.400 1.708
8 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm 583.98 m 86,676.29 50,617,221.34 7.061 583.980 7.061 - - 583.980 7.061
9 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,2m, K.300 - bh 626,150.00 - - - - - - - -
10 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,8m, K.300 - bh 750,000.00 - - - - - - - -
11 Pekerjaan Plat Beton tebal 15 cm - - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 6.81 m3 872,242.00 5,939,968.00 0.829 4.968 0.604 1.842 0.224 6.810 0.829
b Jaring Kawat baja/Wire Mesh M8 2 lapis 480.26 kg 10,697.66 5,137,655.91 0.717 391.376 0.584 88.884 0.133 480.260 0.717
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 10.17 m2 316,861.88 3,222,485.34 0.450 10.128 0.448 0.042 0.002 10.170 0.450
d Pembongkaran 1 M2 Bekisting 10.17 m2 15,645.80 159,117.77 0.022 - - 10.170 0.022 10.170 0.022
12 Pekerjaan Plat Beton tebal 10 cm - - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 22.73 m3 872,242.00 19,826,060.60 2.766 22.730 2.766 - - 22.730 2.766
b Jaring Kawat baja/Wire Mesh M8 1 lapis 1,186.92 kg 10,697.66 12,697,260.97 1.771 1,186.920 1.771 - - 1,186.920 1.771
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 57.68 m2 316,861.88 18,276,593.34 2.550 57.680 2.550 - - 57.680 2.550
d Pembongkaran 1 M2 Bekisting 57.68 m2 15,645.80 902,449.63 0.126 57.680 0.126 - - 57.680 0.126
181,660,506.72 25.341 24.875 0.466 25.341
B PEKERJAAN JARINGAN IPAL KOMUNAL
1 Pekerjaan Galian Tanah Pipa 31.93 m3 67,972.30 2,170,355.55 0.303 25.544 0.242 6.386 0.061 31.930 0.303
2 Pengurugan dengan pasir urug 14.41 m3 178,388.92 2,570,584.34 0.359 14.410 0.359 - - 14.410 0.359
3 Pengurugan Kembali 1 M3 Galian Tanah 12.97 m3 49,023.50 635,966.29 0.089 11.675 0.080 1.297 0.009 12.973 0.089
4 Pemasangan 1 M Pipa PVC tipe AW 4 - m 90,907.55 - -
5 Saluran Pipa Air Limbah SDR - 41, Dia 15 cm , inc. fitting & Assecories - m 133,200.00 - - - - - - - -
6 Saluran Pipa Air Limbah SDR - 41, Dia 20 cm, , inc. fitting & Assecories - m 203,900.00 - - - - - - - -
7 Pemasangan Clean Out Inc. Fitting & Assecories 43.00 ttk 185,000.00 7,955,000.00 1.110 22.000 0.568 21.000 0.542 43.000 1.110
8 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 100 org, 20 m3 / hari, - unit 7,500,000.00 - - - - - - - -
(Galian, Urugan, Pondasi, Tutup Beton, Penyambungan Instalasi) -
9 Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm - unit 975,000.00 - - - - - - - -
10 Pekerjaan Sumur Resapan, Dia 100 cm, Kedalaman 2 m, Inc. Tutup Beton Berlubang - ttk 500,000.00 - - - - - - - -
11 Grill Beton Penutup Sumur Resapan - unit 750,000.00 - - - - - - - -
12 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 7.05 m3 688,832.33 4,856,267.95 0.677 6.718 0.646 0.332 0.032 7.050 0.677
13 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area 7.05 m3 19,888.18 140,211.63 0.020 6.718 0.019 0.332 0.001 7.050 0.020
14 Pemasangan 1 M Pipa PVC tipe D 6 422.00 m 133,200.00 56,210,400.00 7.841 373.775 6.945 48.225 0.896 422.000 7.841
15 Pemasangan 1 M Pipa PVC tipe D 4 165.50 m 85,618.17 14,169,807.73 1.977 118.973 1.421 46.527 0.556 165.500 1.977
16 Pekerjaan Sumur Resapan kedalaman 4 Buis Beton Dia 80 cm 13.00 ttk 474,124.46 6,163,617.96 0.860 13.000 0.860 - - 13.000 0.860
17 Pasang Grill Besi Penutup Sumur Resapan 15.00 unit 826,875.00 12,403,125.00 1.730 13.071 1.508 1.929 0.223 15.000 1.730

Laporan Progres Mingguan ke-21


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)

C PEKERJAAN PEMASANGAN DAN PENGADAAN INSTALASI IPAL


1 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 50 org, 10 m3 / hari
a Pengadaan Unit IPAL kap 50 org, 10 m3 / hari 1.00 unit 110,250,000.00 110,250,000.00 15.380 0.800 12.304 0.200 3.076 1.000 15.380
b Galian Tanah 57.21 m3 67,972.30 3,888,695.29 0.542 57.210 0.542 - - 57.210 0.542
c Pengurugan Kembali 1 M3 Galian Tanah 2.39 m3 49,023.50 117,166.17 0.016 2.390 0.016 - - 2.390 0.016
d Pengurugan dengan pasir urug 4.98 m3 178,388.92 888,028.96 0.124 - - 4.978 0.124 4.978 0.124
e Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Dinding, Lantai dan Tutup 11.77 m3 872,242.00 10,266,288.31 1.432 9.152 1.114 2.618 0.319 11.770 1.432
Jaring Kawat baja/Wire Mesh M8 534.95 kg 10,697.66 5,722,710.68 0.798 527.409 0.787 7.541 0.011 534.950 0.798
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 30.14 m2 316,861.88 9,550,217.12 1.332 26.498 1.171 3.642 0.161 30.140 1.332
Pembongkaran 1 M2 Bekisting 30.14 m2 15,645.80 471,564.35 0.066 26.498 0.058 3.642 0.008 30.140 0.066
f Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Inlet 0.30 m3 872,242.00 261,672.60 0.037 0.222 0.027 0.078 0.009 0.300 0.037
Jaring Kawat baja/Wire Mesh M8 11.06 kg 10,697.66 118,316.07 0.017 8.184 0.012 2.876 0.004 11.060 0.017
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.66 m2 316,861.88 209,128.84 0.029 0.488 0.022 0.172 0.008 0.660 0.029
Pembongkaran 1 M2 Bekisting 0.66 m2 15,645.80 10,326.23 0.001 0.488 0.001 0.172 0.000 0.660 0.001
g Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Outlet 0.41 m3 872,242.00 357,619.22 0.050 0.246 0.030 0.164 0.020 0.410 0.050
Jaring Kawat baja/Wire Mesh M8 14.98 kg 10,697.66 160,250.88 0.022 8.988 0.013 5.992 0.009 14.980 0.022
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.96 m2 316,861.88 304,187.41 0.042 0.576 0.025 0.384 0.017 0.960 0.042
Pembongkaran 1 M2 Bekisting 0.96 m2 15,645.80 15,019.97 0.002 0.576 0.001 0.384 0.001 0.960 0.002
h Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Kolom 15 x 15 cm 0.47 m3 872,242.00 409,953.74 0.057 0.470 0.057 - - 0.470 0.057
Pembesian dg Besi Polos atau Besi Ulir 119.39 kg 11,860.70 1,416,048.75 0.198 119.390 0.198 - - 119.390 0.198
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.44 m2 316,861.88 456,281.11 0.064 1.440 0.064 - - 1.440 0.064
Pembongkaran 1 M2 Bekisting 1.44 m2 15,645.80 22,529.95 0.003 1.440 0.003 - - 1.440 0.003
i Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Balok 15 x 20 cm 0.12 m3 872,242.00 104,669.04 0.015 - - 0.120 0.015 0.120 0.015
Pembesian dg Besi Polos atau Besi Ulir 23.91 kg 11,860.70 283,589.29 0.040 - - 23.910 0.040 23.910 0.040
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.55 m2 316,861.88 174,274.03 0.024 - - 0.550 0.024 0.550 0.024
Pembongkaran 1 M2 Bekisting 0.55 m2 15,645.80 8,605.19 0.001 - - 0.550 0.001 0.550 0.001
j Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, pondasi 60 x 60 x 20 cm 0.72 m3 872,242.00 628,014.24 0.088 0.576 0.070 0.144 0.018 0.720 0.088
Pembesian dg Besi Polos atau Besi Ulir 36.93 kg 11,860.70 438,015.58 0.061 29.544 0.049 7.386 0.012 36.930 0.061
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.20 m2 316,861.88 380,234.26 0.053 0.960 0.042 0.240 0.011 1.200 0.053
Pembongkaran 1 M2 Bekisting 1.20 m2 15,645.80 18,774.96 0.003 0.960 0.002 0.240 0.001 1.200 0.003
k Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm 3.00 unit 975,000.00 2,925,000.00 0.408 - - 3.000 0.408 3.000 0.408
l Tutup Manhole diameter 40 cm 2.00 bh 400,000.00 800,000.00 0.112 - - 2.000 0.112 2.000 0.112

2 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 20 org, 2 m3 / hari
a Pengadaan Unit IPAL kap 20 org, 2 m3 / hari 1.00 unit 38,697,750.00 38,697,750.00 5.398 0.850 4.589 0.150 0.810 1.000 5.398
b Galian Tanah 26.89 m3 67,972.30 1,827,775.15 0.255 26.890 0.255 - - 26.890 0.255
c Pengurugan Kembali 1 M3 Galian Tanah 1.33 m3 49,023.50 65,201.26 0.009 - - 1.330 0.009 1.330 0.009
d Pengurugan dengan pasir urug 2.16 m3 178,388.92 385,973.86 0.054 - - 2.164 0.054 2.164 0.054
e Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Dinding, Lantai dan Tutup 6.37 m3 872,242.00 5,556,181.52 0.775 5.962 0.725 0.408 0.050 6.370 0.775
Jaring Kawat baja/Wire Mesh M8 270.48 kg 10,697.66 2,893,501.79 0.404 253.169 0.378 17.311 0.026 270.480 0.404
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 8.68 m2 316,861.88 2,750,361.13 0.384 8.124 0.359 0.556 0.025 8.680 0.384
Pembongkaran 1 M2 Bekisting 8.68 m2 15,645.80 135,805.53 0.019 8.246 0.018 0.434 0.001 8.680 0.019
f Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Inlet 0.17 m3 872,242.00 148,281.14 0.021 0.162 0.020 0.009 0.001 0.170 0.021
Jaring Kawat baja/Wire Mesh M8 6.48 kg 10,697.66 69,320.81 0.010 6.156 0.009 0.324 0.000 6.480 0.010
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.33 m2 316,861.88 104,564.42 0.015 0.314 0.014 0.017 0.001 0.330 0.015
Pembongkaran 1 M2 Bekisting 0.33 m2 15,645.80 5,163.11 0.001 - - 0.330 0.001 0.330 0.001
g Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Outlet 0.23 m3 872,242.00 200,615.66 0.028 0.219 0.027 0.012 0.001 0.230 0.028
Jaring Kawat baja/Wire Mesh M8 8.44 kg 10,697.66 90,288.21 0.013 8.018 0.012 0.422 0.001 8.440 0.013
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.48 m2 316,861.88 152,093.70 0.021 0.456 0.020 0.024 0.001 0.480 0.021
Pembongkaran 1 M2 Bekisting 0.48 m2 15,645.80 7,509.98 0.001 - - 0.480 0.001 0.480 0.001
h Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Kolom 15 x 15 cm 0.35 m3 872,242.00 305,284.70 0.043 0.350 0.043 - - 0.350 0.043
Pembesian dg Besi Polos atau Besi Ulir 89.54 kg 11,860.70 1,062,006.91 0.148 89.540 0.148 - - 89.540 0.148
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 1.08 m2 316,861.88 342,210.83 0.048 1.080 0.048 - - 1.080 0.048
Pembongkaran 1 M2 Bekisting 1.08 m2 15,645.80 16,897.46 0.002 1.080 0.002 - - 1.080 0.002
i Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Balok 15 x 20 cm 0.08 m3 872,242.00 69,779.36 0.010 - - 0.080 0.010 0.080 0.010
Pembesian dg Besi Polos atau Besi Ulir 19.41 kg 11,860.70 230,216.15 0.032 14.558 0.024 4.853 0.008 19.410 0.032
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.40 m2 316,861.88 126,744.75 0.018 - - 0.400 0.018 0.400 0.018
Pembongkaran 1 M2 Bekisting 0.40 m2 15,645.80 6,258.32 0.001 - - 0.400 0.001 0.400 0.001
j Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, pondasi 60 x 60 x 20 cm 0.54 m3 872,242.00 471,010.68 0.066 0.540 0.066 - - 0.540 0.066
Pembesian dg Besi Polos atau Besi Ulir 27.69 kg 11,860.70 328,422.73 0.046 27.690 0.046 - - 27.690 0.046
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) 0.90 m2 316,861.88 285,175.69 0.040 0.900 0.040 - - 0.900 0.040
Pembongkaran 1 M2 Bekisting 0.90 m2 15,645.80 14,081.22 0.002 0.900 0.002 - - 0.900 0.002
k Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm 2.00 unit 975,000.00 1,950,000.00 0.272 - - 2.000 0.272 2.000 0.272
l Tutup Manhole diameter 40 cm 2.00 bh 400,000.00 800,000.00 0.112 - - 2.000 0.112 2.000 0.112

Laporan Progres Mingguan ke-21


HARGA SATUAN JUMLAH HARGA BOBOT PRESTASI PEKERJAAN
NO URAIAN PEKERJAAN VOLUME PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp Rp (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)

D PEKERJAAN LAIN - LAIN


1 Pasang Bak Kontrol dengan tutup precast cetak diameter 40 cm 3.00 bh 850,000.00 2,550,000.00 0.356 3.000 0.356 - - 3.000 0.356
2 Pembersihan dan Pembuangan Bekas Galian Tanah IPAL Keluar Area 84.10 m3 67,972.30 5,716,470.45 0.797 63.075 0.598 21.025 0.199 84.100 0.797
3 Pembongkaran 1 M2 Paving Block eksisting 31.40 m2 49,910.10 1,567,177.00 0.219 23.550 0.164 7.850 0.055 31.400 0.219
4 Pemasangan 1 M2 kembali Paving Block eksisting 31.40 m2 64,463.10 2,024,141.20 0.282 4.746 0.043 26.654 0.240 31.400 0.282
5 Pembongkaran dan Pemasangan kembali pipa PDAM yang terdampak galian 1.00 Ls 1,500,000.00 1,500,000.00 0.209 - - 1.000 0.209 1.000 0.209
6 Check Valve diameter 6 inch+ Reducer diameter 8x6 inch 1.00 bh 4,669,087.50 4,669,087.50 0.651 - - 1.000 0.651 1.000 0.651
7 Check Valve diameter 6 inch 1.00 bh 4,278,582.00 4,278,582.00 0.597 - - 1.000 0.597 1.000 0.597
8 Check Valve diameter 4 inch 2.00 bh 2,051,002.80 4,102,005.60 0.572 - - 2.000 0.572 2.000 0.572
9 Membuat rabat beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 1.55 m3 723,713.11 1,121,650.74 0.156 - - 1.550 0.156 1.550 0.156
10 Grill besi area ipal barat 1.50 m2 828,726.02 1,243,089.03 0.173 - - 1.500 0.173 1.500 0.173

345,803,198.30 48.239 37.259 10.979 48.239

JUMLAH 654,697,105.06 716,855,950.73 100.000 86.960 13.040 100.000


PRESTASI MINGGU LALU 86.960
PRESTASI MINGGU INI 13.040
PRESTASI SAMPAI DENGAN MINGGU INI 100.000
PRESTASI MENURUT SCHEDULE 93.771
LEBIH CEPAT (+) / TERLAMBAT (-) 6.229

Yogyakarta, 18 Oktober 2021


di buat oleh,
KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA

Noor Hasan Bambang Erlianto


Pengawas Pelaksana

Laporan Progres Mingguan ke-21


REKAPITULASI
LAPORAN PRESTASI PEKERJAAN

Laporan Prestasi Pekerjaan Minggu ke : XXI ( Dua puluh satu )


Periode : 11 Oktober 2021 sampai dengan 17 Oktober 2021
SATUAN KERJA : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021
PENYEDIA JASA : CV. ALMEERA RAYA
KONSULTAN PENGAWAS : CV. POLA PRAKARYA
NO. KONTRAK : 050 / 2407 / V / 2021, TANGGAL 24 MEI 2021
NO. SPMK : 050 / 2408 / V / 2021, TANGGAL 24 MEI 2021
NILAI KONTRAK : Rp 720,166,815.57
ADDENDUM I : 050 / 2407 / VI / 2021, TANGGAL 21 JUNI 2021
ADDENDUM II : 050 / 1909 / VII / 2021, TANGGAL 19 JULI 2021
ADDENDUM III : 050 / 0615 / IX / 2021, TANGGAL 6 SEPTEMBER 2021
NILAI KONTRAK ADDENDUM III : Rp 788,541,545.80
WAKTU PELAKSANAAN : 180 Hari Kalender
PENYERAHAN PERTAMA : 20 Oktober 2021

JUMLAH HARGA BOBOT PRESTASI PEKERJAAN


NO PEKERJAAN PEKERJAAN MINGGU LALU MINGGU INI S/D MINGGU INI
Rp (%) BOBOT % BOBOT % BOBOT %

I PEKERJAAN PERSIAPAN 11,873,371.04 1.656 1.557 0.099 1.656

II PEKERJAAN PERBAIKAN TALUD SEGMEN 5


A PEKERJAAN TANAH DAN BETON BERTULANG - - - - -
B PEKERJAAN PASANGAN DINDING - - - - -

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PENGECATAN - - - - -
B PEKERJAAN RUMAH TERDAMPAK 177,518,874.67 24.764 23.268 1.495 24.764

III PEKERJAAN PENATAAN LINGKUNGAN RW 1


A PEKERJAAN PEMBERSIHAN SALURAN 181,660,506.72 25.341 24.875 0.466 25.341
B PEKERJAAN JARINGAN IPAL KOMUNAL 345,803,198.30 48.239 37.259 10.979 48.239

JUMLAH 716,855,950.73 100.000 86.960 13.040 100.000


PRESTASI MINGGU LALU - 86.960
PRESTASI MINGGU INI 13.040
PRESTASI SAMPAI DENGAN MINGGU INI 100.000
PRESTASI MENURUT SCHEDULE 93.771
LEBIH CEPAT (+) / TERLAMBAT (-) 6.229

Yogyakarta, 18 Oktober 2021


di buat oleh,
PEJABAT PEMBUAT KOMITMEN TIM TEKNIS KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA
1. Cicilia Novi hendrawati, M.SC., M.Eng.
NIP. 19781102 200501 2 011 ...........................

2. Danang Dwi Wahyujati,S.Kom.,M.Eng


NIP. 19761028 199803 1 004 ...........................
SIGIT SETIAWAN, ST.MT 3. Sudaryanto
NIP. 19690605 199303 1 007 RISMAN WARCHAN ZULIANTO
NIP. 19770623 200501 1 013 ........................... Tim Leader Direktur
REALISASI WAKTU PELAKSANAAN PEKERJAAN
MUTUAL CHECK ( MC 2 )
INSTANSI : DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA YOGYAKARTA
KEGIATAN : PENATAAN BANGUNAN DAN LINGKUNGAN
PEKERJAAN : PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN
LOKASI : KELURAHAN KLITREN, KOTA YOGYAKARTA
TAHUN ANGGARAN : 2021

BULAN KE-1 BULAN KE-2 BULAN KE-3 BULAN KE-4


KONTRAK MC 0 MC 1 MC 2 KONTRAK MC 0 MC 1 MC 2
Ming.1 Ming.2 Ming.3 Ming.4 Ming.5 Ming.6 Ming.7 Ming.8 Ming.9 Ming.10 Ming.11 Ming.12 Ming.13 Ming.14 Ming.15 Ming.16 Ming.17 Ming.18 Ming.19 Ming.20 Ming.21 Ming.22
NO JENIS PEKERJAAN 24/05/21 31/05/21 07/06/21 14/06/21 21/06/21 28/06/21 05/07/21 12/07/21 19/07/21 26/07/21 02/08/21 09/08/21 16/08/21 23/08/21 30/08/21 06/09/21 13/09/21 20/09/21 27/09/21 04/10/21 11/10/21 18/10/21 KET.
VOLUME HARGA SATUAN JUMLAH HARGA VOLUME JUMLAH HARGA VOLUME JUMLAH HARGA VOLUME
SAT. JUMLAH HARGA (Rp) BOBOT (%) BOBOT (%) BOBOT (%) BOBOT (%) s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
KONTRAK (Rp) (Rp) MC 0 (Rp) MC 1 (Rp) MC 2
30/05/21 06/06/21 13/06/21 20/06/21 27/06/21 04/07/21 11/07/21 18/07/21 25/07/21 01/08/21 08/08/21 15/08/21 22/08/21 29/08/21 05/09/21 12/09/21 19/09/21 26/09/21 03/10/21 10/10/21 17/10/21 20/10/21

I PEKERJAAN PERSIAPAN
1 Pembuatan Papan Nama Pekerjaan bh 1.00 250,000.00 250,000.00 1.00 250,000.00 1.00 250,000.00 1.00 250,000.00 0.038 0.038 0.038 0.035 0.038 - (0.003)
2 Pengukuran dan Pemasangan Bouwplank m 28.56 12,198.91 348,400.73 28.56 348,400.73 28.56 348,400.73 28.56 348,400.73 0.053 0.053 0.053 0.049 0.027 0.027 - (0.005)
3 Pembuatan bedeng pekerja m2 9.00 383,330.04 3,449,970.32 9.00 3,449,970.32 9.00 3,449,970.32 9.00 3,449,970.32 0.527 0.527 0.527 0.481 0.263 0.263 - (0.046)
4 Mobilisasi Demobilisasi Alat Berat ls 1.00 2,500,000.00 2,500,000.00 1.00 2,500,000.00 1.00 2,500,000.00 1.00 2,500,000.00 0.382 0.382 0.382 0.349 0.191 0.191 0.191 0.044 0.044
5 Pembuatan akses menuju badan sungai sementara m2 24.00 113,128.49 2,715,083.64 - - - - - - 0.415 - - - 0.207 0.207 -
6 Dewatering dengan pompa air diesel jam 40.00 25,000.00 1,000,000.00 40.00 1,000,000.00 40.00 1,000,000.00 40.00 1,000,000.00 0.153 0.153 0.153 0.139 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.005 0.005 0.005 0.005 0.005 0.005 0.005
7 SMKK ls 1.00 4,325,000.00 4,325,000.00 1.00 4,325,000.00 1.00 4,325,000.00 1.00 4,325,000.00 0.661 0.661 0.661 0.603 0.030 0.030 0.030 0.030 0.030 0.030 0.030 0.030 0.032 0.032 0.032 0.032 0.032 0.032 0.032 0.022 0.022 0.022 0.022 0.022 0.022 0.022
- -
II PEKERJAAN PERBAIKAN TALUD SEGMEN 5 - -
A PEKERJAAN TANAH DAN BETON BERTULANG - -
1 Penggalian 1 M3 Tanah Biasa m3 50.00 67,972.30 3,398,615.01 61.50 4,180,296.46 13.50 917,626.05 - - 0.519 0.639 0.140 - 0.160 0.160 0.160 0.160 0.070 0.070 -
2 Pengurugan Kembali 1 M3 Galian Tanah m3 33.15 49,023.50 1,625,129.04 29.21 1,431,976.45 6.41 314,240.64 - - 0.248 0.219 0.048 - 0.073 0.073 0.024 0.024 -
3 Bongkaran Pasangan Batu dan Beton Eksisting m3 50.00 71,953.20 3,597,660.02 39.18 2,819,126.39 7.92 569,869.35 - - 0.550 0.431 0.087 - 0.108 0.108 0.108 0.108 0.044 0.044 -
4 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area m3 50.00 19,888.18 994,408.76 39.18 779,218.70 7.92 157,514.35 - - 0.152 0.119 0.024 - 0.030 0.030 0.030 0.012 0.012 -
5 Pemadatan Tanah Eksisting m3 11.84 49,023.50 580,438.24 29.21 1,431,976.45 6.41 314,240.64 - - 0.089 0.219 0.048 - 0.109 0.109 0.024 0.024 -
6 Pengurugan dengan pasir urug m3 5.92 178,388.92 1,056,062.41 1.23 219,418.37 0.27 48,165.01 - - 0.161 0.034 0.007 - 0.034 0.007 -
7 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 m3 2.96 737,396.00 2,182,692.15 1.23 906,997.08 0.27 199,096.92 - - 0.333 0.139 0.030 - 0.069 0.030 -
8 Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 m3 10.00 872,242.00 8,722,419.97 4.92 4,291,430.63 1.08 942,021.36 - - 1.332 0.655 0.144 - 0.109 0.072 0.072 -
a Pembesian dg Besi Polos atau Besi Ulir kg - 11,860.70 - 714.10 8,469,724.55 156.69 1,858,452.79 - - - 1.294 0.284 - 0.216 0.142 0.142 -
b Bekisting untuk pondasi beton ( dipakai 2 kali ) m2 - 89,375.55 - 8.56 765,054.68 1.92 171,601.05 - - - 0.117 0.026 - 0.019 0.013 0.013 -
c Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 1.92 30,039.93 - - - - 0.005 - 0.005 -
9 Pekerjaan Beton Dinding Talud Beton - - -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 m3 10.00 872,242.00 8,722,419.97 9.97 8,696,252.71 2.16 1,884,042.71 - - 1.332 1.328 0.288 - 0.144 0.144 -
b Pembesian dg Besi Polos atau Besi Ulir kg 1,000.00 11,860.70 11,860,698.15 4,675.31 55,452,440.67 1,026.67 12,177,022.97 - - 1.812 8.470 1.860 - 0.930 0.930 -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 40.00 316,861.88 12,674,475.27 10.12 3,206,642.24 9.02 2,858,094.17 - - 1.936 0.490 0.437 - 0.218 0.218 -
d Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 9.02 141,125.10 - - 0.022 - -
10 Pekerjaan Beton Sloof 20x30cm - - -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 m3 4.74 872,242.00 4,134,427.07 2.26 1,971,266.91 0.49 427,398.58 - - 0.632 0.301 0.065 - 0.065 -
b Pembesian dg Besi Polos atau Besi Ulir kg 400.00 11,860.70 4,744,279.26 671.58 7,965,407.66 147.55 1,750,046.01 - - 0.725 1.217 0.267 - 0.267 -
c Memasang Bekisting untuk Sloof (dipakai 2 kali) m2 47.36 89,375.55 4,232,825.87 11.34 1,013,518.69 2.46 219,863.84 - - 0.647 0.155 0.034 - 0.017 0.017 -
d Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 2.46 38,488.66 - - 0.006 - 0.006 -
11 Pekerjaan Beton Konsul Cantilever - - -
a Membuat Beton mutu fc=21,7 MPa (K250), slum (122)cm, w/c = 0,56 m3 7.75 872,242.00 6,759,875.48 0.42 366,341.64 0.09 78,501.78 - - 1.033 0.056 0.012 - - -
b Pembesian dg Besi Polos atau Besi Ulir kg 700.00 11,860.70 8,302,488.71 194.43 2,306,075.54 47.58 564,332.02 - - 1.268 0.352 0.086 - 0.043 0.043 -
c Memasang Bekisting untuk Balok (dipakai 2 kali) m2 40.00 120,181.13 4,807,245.27 2.10 252,380.38 0.45 54,081.51 - - 0.734 0.039 0.008 - 0.008 -
d Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 0.45 7,040.61 - - 0.001 - - -
12 Pekerjaan Plat Beton tebal 12 cm - - -
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) m3 10.00 872,242.00 8,722,419.97 12.30 10,728,576.57 2.70 2,355,053.39 - - 1.332 1.639 0.360 - - -
b Jaring Kawat baja/Wire Mesh M8 2 lapis kg 700.00 10,697.66 7,488,358.68 1,340.41 14,339,244.07 294.23 3,147,571.10 - - 1.144 2.190 0.481 - - -
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 30.00 316,861.88 9,505,856.45 6.15 1,948,700.57 1.35 427,763.54 - - 1.452 0.298 0.065 - - -
d Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 1.35 21,121.83 - - 0.003 - - -
13 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm m 13.00 77,312.85 1,005,067.10 21.00 1,623,569.93 4.50 347,907.84 - - 0.154 0.248 0.053 - - -
14 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm m 38.37 86,676.29 3,325,769.35 39.46 3,420,246.51 8.67 751,483.46 - - 0.508 0.522 0.115 - - - -
15 Memasang Stek Besi kg 200.00 11,860.70 2,372,139.63 107.71 1,277,515.80 23.67 280,742.73 - - 0.362 0.195 0.043 - - -
16 Pekerjaan Plat Beton Pot tebal 10 cm - - -
a Membuat Beton mutu fc=26,4 MPa (K250), slum (122)cm, w/c = 0,52 (dengan Molen) m3 4.74 872,242.00 4,134,427.07 2.26 1,971,266.91 0.49 427,398.58 - - 0.632 0.301 0.065 - - - -
b Pembesian dg Besi Polos atau Besi Ulir kg 200.00 11,860.70 2,372,139.63 107.71 1,277,515.80 23.67 280,742.73 - - 0.362 0.195 0.043 - - - -
c Bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm m2 30.00 118,158.83 3,544,764.95 32.80 3,875,609.68 7.20 850,743.59 - - 0.541 0.592 0.130 - - - -
d Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 7.20 112,649.75 - - - - 0.017 - - -
- - - -
B PEKERJAAN PASANGAN DINDING - - -
1 Pemasangan Dinding Bata Merah Bakar Sekam Tebal 1/2 Bata Camp. 1SP 6PP m2 42.00 116,576.48 4,896,212.34 45.37 5,289,075.10 9.97 1,162,267.55 - - 0.748 0.808 0.178 - - -
2 Pemasangan Plesteran 1 Pc 6 Pp Tebal 15 mm m2 84.00 54,689.70 4,593,934.71 155.38 8,497,685.43 34.11 1,865,465.63 - - 0.702 1.298 0.285 - - -
3 Pemasangan Acian m2 210.00 33,411.23 7,016,358.16 155.38 5,191,436.81 34.11 1,139,657.03 - - 1.072 0.793 0.174 - - -
4 Pemasangan Plesteran Skoning 1 Pc 2Pp lebar 10 cm m 360.00 55,075.90 19,827,324.36 212.00 11,676,091.01 46.50 2,561,029.40 - - 3.028 1.783 0.391 - - - -
5 Pemasangan Kepala Kolom bh 10.00 50,000.00 500,000.00 14.00 700,000.00 3.00 150,000.00 - - 0.076 0.107 0.023 - -
- - - -
III PEKERJAAN PENATAAN LINGKUNGAN RW 1 - -
A PEKERJAAN PENGECATAN - -
1 Pengecatan Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Weathershield luar ruangan m2 210.00 11,686.42 2,454,148.34 155.38 1,815,836.04 34.11 398,623.81 - - 0.375 0.277 0.061 - -
- - - -
B PEKERJAAN RUMAH TERDAMPAK - -
I. PEKERJAAN BONGKARAN - -
1 Membongkar 1 m2 genteng / sirap untuk dipergunakan lagi m2 103.90 3,628.42 376,993.05 77.17 280,005.33 77.17 280,005.33 77.17 280,005.33 0.058 0.043 0.043 0.039 0.021 0.043 0.003 0.003 0.003 0.003 0.003 0.003 0.003
2 Membongkar 1 m3 kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi m3 0.46 991,595.91 456,134.12 0.37 366,890.49 0.37 366,890.49 0.37 366,890.49 0.070 0.056 0.056 0.051 0.028 0.056 0.003 0.003 0.003 0.003 0.003 0.003 0.003
3 Pembongkaran 1 m3 pasangan bata merah dan membersihkan m3 40.86 185,908.38 7,596,216.24 11.13 2,069,160.22 12.72 2,364,754.54 12.72 2,364,754.54 1.160 0.316 0.361 0.330 0.158 0.276 0.014 0.014 0.014 0.014 0.014 0.014 0.014
4 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 m3 9.20 688,832.33 6,337,257.47 1.80 1,239,898.20 1.50 1,033,248.50 1.50 1,033,248.50 0.968 0.189 0.158 0.144 0.095 0.146 0.008 0.008 0.008 0.008 0.008 0.008 0.008
II. PEKERJAAN TANAH - - -
1 Menggali 1 m3 tanah biasa sedalam 1 meter m3 22.32 67,972.30 1,517,141.74 26.71 1,815,540.14 27.22 1,850,206.01 27.22 1,850,206.01 0.232 0.277 0.283 0.258 0.061 (0.025)
2 Pengurugan Kembali 1 m3 Galian Tanah m3 - 18,745.83 - - - 10.11 189,520.38 10.11 189,520.38 - - 0.029 0.026 0.029 (0.003)
3 Pengurugan dengan pasir urug m3 - 173,624.00 - - - 1.82 315,995.68 1.82 315,995.68 - - 0.048 0.044 0.048 (0.004)
4 Peninggian peil lantai m3 - 18,745.83 - 9.18 172,086.75 9.18 172,086.75 - - 0.026 0.024 0.026 (0.002)
III. PEKERJAAN PONDASI - - - - -
1 Memasang 1 m3 pondasi batu belah, campuran 1 PC 6 PP m2 17.28 665,195.09 11,494,571.24 16.11 10,716,292.98 16.49 10,969,067.11 16.49 10,969,067.11 1.756 1.637 1.675 1.530 0.693 (0.145)
IV. PEKERJAAN BETON - - -
1 Membuat 1 m3 Sloof beton bertulang (200 kg besi + bekisting) m3 3.55 3,844,764.87 13,648,915.30 1.72 6,612,995.58 1.06 4,075,450.77 1.06 4,075,450.77 2.085 1.010 0.622 0.569 0.109 0.109 (0.054)
2 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) m3 4.94 7,083,735.01 34,993,650.96 3.92 27,768,241.25 2.29 16,221,753.18 2.29 16,221,753.18 5.345 4.241 2.478 2.263 0.303 0.303 0.303 (0.215)
3 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) m3 5.00 5,659,422.09 28,297,110.46 9.08 51,387,552.60 3.05 17,261,237.38 3.05 17,261,237.38 4.322 7.849 2.637 2.408 0.365 0.365 0.365 0.365 (0.229)
4 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 m3 - 723,713.11 - - - 0.14 101,319.83 0.14 101,319.83 - - 0.015 0.014 0.015 (0.001)
5 Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting) m3 - 3,127,107.54 0.57 1,782,451.30 0.57 1,782,451.30 - - 0.272 0.249 0.272 (0.024)
6 Sloof 150 x 200 dengan beton K 225 Tulangan 105 kg m3 - 3,295,166.46 - - - 0.74 2,438,423.18 0.74 2,438,423.18 - - 0.372 0.340 0.372 (0.032)
7 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m' - 77,312.85 67.35 5,207,020.70 67.35 5,207,020.70 - - 0.795 0.726 0.199 0.199 0.199 (0.069)
8 Balok 150 x 200 dengan beton K 225 Tulangan 105 kg m3 - 3,705,897.33 1.01 3,742,956.31 1.01 3,742,956.31 - - 0.572 0.522 0.143 (0.050)
9 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm m' - 86,676.29 54.15 4,693,521.24 54.15 4,693,521.24 - - 0.717 0.655 0.179 (0.062)
10 Membuat 1 m3 Plat Lantai beton bertulang m3 - 3,119,381.73 - - - 2.95 9,202,176.12 2.95 9,202,176.12 - - 1.406 1.284 0.351 0.351 0.351 0.351 (0.122)
11 Membuat 1 m3 Plat Tangga beton bertulang m3 - 3,119,381.73 - - - 0.72 2,245,954.85 0.72 2,245,954.85 - - 0.343 0.313 0.086 0.086 0.086 (0.030)
12 Membuat 1 m3 Plat Water torn beton bertulang m3 - 3,119,381.73 - - - 0.42 1,310,140.33 0.42 1,310,140.33 - - 0.200 0.183 0.200 (0.017)
V. PEKERJAAN DINDING - - -
1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP m2 127.00 116,576.48 14,805,213.51 191.94 22,375,690.41 161.84 18,866,738.23 161.84 18,866,738.23 2.261 3.418 2.882 2.632 0.635 0.635 0.635 (0.250) MC 2
2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP, trap tangga m2 - 250,668.02 6.30 1,579,208.52 6.30 1,579,208.52 - - 0.241 0.220 0.060 0.060 0.060 (0.021)
VI PEKERJAAN KAYU - - -
1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti m3 0.50 16,443,774.77 8,221,887.38 0.27 4,439,819.19 0.27 4,439,819.19 0.27 4,439,819.19 1.256 0.678 0.678 0.619 0.339 0.339 (0.059)
Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti m3 - 8,048,535.00 - - - 0.02 160,970.70 0.02 160,970.70 - - 0.025 0.022 0.012 0.012 (0.002)
2 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti m2 12.72 644,715.80 8,200,785.00 12.08 7,788,166.89 12.32 7,942,898.68 12.32 7,942,898.68 1.253 1.190 1.213 1.108 (0.105)
3 Memasang 1 m3 konstruksi gordeng, kayu glugu m3 0.21 4,450,537.65 934,612.91 0.35 1,557,688.18 - - - - 0.143 0.238 - - - -
VII. PEKERJAAN PLESTERAN - -
1 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm m2 100.00 54,689.70 5,468,969.90 75.69 4,139,463.32 96.76 5,291,775.27 96.76 5,291,775.27 0.835 0.632 0.808 0.738 0.808 (0.070)
2 Memasang 1 m2 acian m2 100.00 33,411.23 3,341,122.93 75.69 2,528,895.95 96.76 3,232,870.55 96.76 3,232,870.55 0.510 0.386 0.494 0.451 0.494 (0.043)
3 Pemasangan 1 m2 plesteran ciprat 1SP : 2PP m2 - 45,029.48 - - - 33.50 1,508,487.73 33.50 1,508,487.73 - - 0.230 0.210 0.230 (0.020)
VIII. PEKERJAAN PENGECATAN - -
1 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) m2 100.00 11,686.42 1,168,642.06 75.69 884,545.18 96.76 1,130,778.06 96.76 1,130,778.06 0.179 0.135 0.173 0.158 0.158
IX. PEKERJAAN PENUTUP ATAP - -
1 Memasang 1 m2 Atap Galvalum (Paket) m3 78.20 190,000.00 14,858,000.00 78.24 14,864,806.70 78.51 14,917,137.50 78.51 14,917,137.50 2.269 2.270 2.278 2.081 (0.084)
2 Pemasangan 1 m talang datar Galvalum lebar 60 cm m' - 105,483.99 - - - 6.00 632,903.97 - - - - 0.097 - -
3 Pemasangan 1 m talang datar U PVC m' - 73,235.87 - - - - - 8.64 632,903.97 - 0.088 0.088
X. PEKERJAAN PENUTUP LANTAI DAN DINDING - -
1 Memasang 1 m2 lantai keramik (30 x 30) cm m2 8.54 114,193.22 975,210.13 16.26 1,856,781.81 - - - - 0.149 0.284 - - - -
2 Membuat rabat beton lantai mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 m3 - 723,713.11 - - - 2.08 1,504,722.31 2.08 1,504,722.31 0.230 0.210 (0.020)
3 Memasang 1 m2 lantai keramik (20 x 20) cm m' - 184,674.28 - - - 4.99 921,524.65 4.99 921,524.65 0.141 0.129 0.129
XI. PEKERJAAN SANITASI - -
1 Memasang 1 buah Kloset Jongkok Porselen bh 2.00 280,952.58 561,905.16 2.00 561,905.16 2.00 561,905.16 2.00 561,905.16 0.086 0.086 0.086 0.078 0.078
2 Memasang 1 m Pipa PVC tipe AW m2 24.00 19,406.20 465,748.90 24.00 465,748.90 16.00 310,499.27 16.00 310,499.27 0.071 0.071 0.047 0.043 0.047 0.005
3 Memasang 1 m Pipa PVC tipe AW 1 m2 24.00 22,254.33 534,103.90 24.00 534,103.90 8.00 178,034.63 8.00 178,034.63 0.082 0.082 0.027 0.025 0.027 0.003
4 Memasang 1 m Pipa PVC tipe AW 3 m2 24.00 63,036.61 1,512,878.67 24.00 1,512,878.67 18.00 1,134,659.00 18.00 1,134,659.00 0.231 0.231 0.173 0.158 0.173 0.004
5 Memasang 1 buah Kran atau m2 2.00 46,068.18 92,136.37 2.00 92,136.37 2.00 92,136.37 2.00 92,136.37 0.014 0.014 0.014 0.013 0.014 0.013
6 Memasang 1 buah Floor Drain m3 2.00 80,836.18 161,672.35 2.00 161,672.35 2.00 161,672.35 2.00 161,672.35 0.025 0.025 0.025 0.023 0.025 0.023
7 Memasang 1 buah Pintu Kamar Mandi bh 2.00 650,000.00 1,300,000.00 2.00 1,300,000.00 2.00 1,300,000.00 2.00 1,300,000.00 0.199 0.199 0.199 0.181 0.199 (0.017)
8 Pemasangan 1 M Pipa PVC tipe D 4 m' - 85,618.17 - - - 12.00 1,027,418.08 12.00 1,027,418.08 - - 0.157 0.143 0.013
XII. PEKERJAAN ELEKTRIKAL - - - - - - -
1 Instalasi Penerangan menggunakan kabel NYY 3x2,5mm² dalam pipa conduit Ø 20mm. titik - 105,000.00 - - - 10.00 1,050,000.00 10.00 1,050,000.00 - - 0.160 0.146 0.160 (0.014)
2 Instalasi stop kontak dinding, menggunakan kabel NYM 3x2,5mm² titik - 100,000.00 - - - 5.00 500,000.00 5.00 500,000.00 - - 0.076 0.070 0.076 (0.007)
3 Saklar tunggal inbow, 1 gang 1 way bh - 20,000.00 - - - 4.00 80,000.00 4.00 80,000.00 - - 0.012 0.011 0.012 (0.001)
4 Saklar seri inbow, 1 gang 2 way bh - 25,000.00 - - - 4.00 100,000.00 4.00 100,000.00 - - 0.015 0.014 0.015 (0.001)
5 Stop kontak wall type 1ph, 16A, 1 gang bh - 20,000.00 - - - 5.00 100,000.00 5.00 100,000.00 - - 0.015 0.014 0.015 (0.001)
6 Lampu PLC 18 Watt dengan fitting gantung bh - 75,000.00 - - - 8.00 600,000.00 8.00 600,000.00 - - 0.092 0.084 0.092 (0.008)
7 Lampu PLC 7 Watt dengan fitting gantung bh - 65,000.00 - - - 2.00 130,000.00 2.00 130,000.00 - - 0.020 0.018 0.020 (0.002)
8 Penyambungan kabel Ls - 500,000.00 - - - 1.00 500,000.00 1.00 500,000.00 - - 0.076 0.070 0.076 0.070
9 Box MCB + MCB bh - 250,000.00 - - - 2.00 500,000.00 2.00 500,000.00 - - 0.076 0.070 0.076 (0.007)
XIII. PEKERJAAN LAIN-LAIN - -
1 Pintu Folding gate m2 - 788,049.93 - - - 6.00 4,728,299.56 6.00 4,728,299.56 - - 0.722 0.660 (0.063)
2 Railling pengaman besi Hollow 40x40 / 40x20 mm, finishing cat m2 - 550,000.00 - - - 11.48 6,312,240.00 11.48 6,312,240.00 - - 0.964 0.881 0.126 0.126 0.126 0.126 0.126 0.126 0.126
XIV. Rumah Timur sungai - - - -
1 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m' - 77,312.85 - - - - - 4.50 347,907.84 - 0.049 0.007 0.007 0.007 0.007 0.007 0.007 0.007
2 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm m' - 86,676.29 - - - - - 5.70 494,054.87 - 0.069 0.010 0.010 0.010 0.010 0.010 0.010 0.010
3 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC 6 PP m2 - 116,576.48 - - - - - 3.10 361,387.10 - 0.050 0.007 0.007 0.007 0.007 0.007 0.007 0.007
4 Memasang 1 m2 plesteran 1 PC 6 PP, tebal 15 mm m2 - 54,689.70 - - - - - 7.41 405,250.67 - 0.057 0.008 0.008 0.008 0.008 0.008 0.008 0.008
5 Memasang 1 m2 acian m2 - 33,411.23 - - - - - 7.41 247,577.21 - 0.035 0.005 0.005 0.005 0.005 0.005 0.005 0.005
6 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) m2 - 11,686.42 - - - - - 7.41 86,596.38 - 0.012 0.002 0.002 0.002 0.002 0.002 0.002 0.002
7 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu Meranti m3 - 8,048,535.00 - - - - - 0.13 1,046,309.55 - 0.146 0.021 0.021 0.021 0.021 0.021 0.021 0.021
8 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu Meranti m2 - 644,715.80 - - - - - 4.64 2,991,481.32 - 0.417 0.060 0.060 0.060 0.060 0.060 0.060 0.060
9 Memasang 1 m2 Atap Galvalum (Paket) m2 - 190,000.00 - - - - - 17.55 3,334,500.00 - 0.465 0.066 0.066 0.066 0.066 0.066 0.066 0.066
10 Membuat rabat beton lantai mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 m3 - 723,713.11 - - - - - 1.22 882,929.99 - 0.123 0.018 0.018 0.018 0.018 0.018 0.018 0.018
- - -
III PEKERJAAN PENATAAN LINGKUNGAN RW 1 -
A PEKERJAAN PEMBERSIHAN SALURAN -
1 Penggalian Tanah Lumpur dan Endapan Limbah Sedalam 30 cm m3 85.36 109,311.98 9,330,870.22 65.62 7,173,051.82 69.70 7,619,044.68 70.70 7,728,356.66 1.425 1.096 1.164 1.078 0.713 0.548 0.548 0.237 0.237 (0.003) (0.003) (0.003) (0.003) (0.003) (0.003) (0.003)
2 Pembersihan dan Pembuangan Tanah Lumpur dan Limbah Keluar Area m3 85.36 29,796.55 2,543,433.77 65.62 1,955,249.81 90.90 2,708,506.67 89.07 2,653,978.98 0.388 0.299 0.414 0.370 0.194 0.149 0.149 0.117 0.117 (0.002) (0.002) (0.002) (0.002) (0.002) (0.002) (0.002)
3 Pemadatan Tanah Eksisting m3 48.91 49,023.50 2,397,739.40 65.62 3,216,922.10 69.70 3,416,937.98 70.70 3,465,961.48 0.366 0.491 0.522 0.483 0.491 0.522 0.006 0.006 0.006 0.006 0.006 0.006 0.006
4 Pengurugan dengan pasir urug, 10 cm m3 17.07 178,388.92 3,045,098.87 21.87 3,901,365.68 21.87 3,901,365.68 21.87 3,901,365.68 0.465 0.596 0.596 0.544 0.298 0.298 0.298 0.298 0.006 0.006 0.006 0.006 0.006 0.006 0.006
Pengurugan dengan pasir urug, 10 cm m3 - 173,624.00 - - - 1.36 236,128.64 1.69 293,424.56 - - 0.036 0.041 0.018 0.018 0.001 0.001 0.001 0.001 0.001 0.001 0.001
5 Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 m3 17.07 737,396.00 12,587,349.68 10.93 8,059,738.25 10.93 8,059,738.25 10.93 8,059,738.25 1.923 1.231 1.231 1.124 0.616 0.616 0.616 0.616 0.020 0.020 0.020 0.020 0.020 0.020 0.020
Membuat lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 m3 - 723,713.11 - - - 0.68 492,124.91 0.85 615,156.14 - - 0.075 0.086 0.038 0.038 0.004 0.004 0.004 0.004 0.004 0.004 0.004
6 Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 m3 17.07 872,242.00 14,889,170.90 21.87 19,075,932.48 23.23 20,262,181.60 23.56 20,550,021.46 2.274 2.914 3.095 2.867 1.457 1.457 1.547 1.547 0.057 0.057 0.057 0.057 0.057 0.057 0.057
a Jaring Kawat baja/Wire Mesh M5 1 lapis kg - 10,697.66 - - - 375.85 4,020,713.73 501.73 5,367,334.57 - 0.614 0.749 0.307 0.307 0.037 0.037 0.037 0.037 0.037 0.037 0.037
7 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm m 466.40 77,312.85 36,058,714.99 78.60 6,076,790.31 133.20 10,298,072.12 158.40 12,246,356.04 5.508 0.928 1.573 1.708 0.524 0.524 0.524 0.064 0.064 0.064 0.064 0.064 0.064 0.064
8 Membuat Sloof dan Ring Balok Beton Bertulang (10 x 15) cm m 466.40 86,676.29 40,425,822.86 642.60 55,698,185.61 718.80 62,302,919.11 583.98 50,617,221.34 6.175 8.507 9.516 7.061 2.127 2.379 2.379 2.379 2.379 (0.076) (0.076) (0.076) (0.076) (0.076) (0.076) (0.076)
9 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,2m, K.300 bh 65.00 626,150.00 40,699,750.00 70.00 43,830,500.00 - - - - 6.217 6.695 - - -
10 Pengadaan dan Pemasangan Cover Penutup Beton (Precast) lebar 1,8m, K.300 bh 32.00 750,000.00 24,000,000.00 61.00 45,750,000.00 - - - - 3.666 6.988 - - -
11 Pekerjaan Plat Beton tebal 15 cm - - - - - - - - - - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 m3 - 872,242.00 - - - 8.37 7,300,665.52 6.81 5,939,968.00 - - 1.115 0.829 0.223 0.223 0.112 0.118 0.118 0.118 0.118 0.118 0.118 0.118
b Jaring Kawat baja/Wire Mesh M8 2 lapis kg - 10,697.66 - - - 608.09 6,505,137.18 480.26 5,137,655.91 - - 0.994 0.717 0.199 0.199 0.099 0.102 0.102 0.102 0.102 0.102 0.102 0.102
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - 13.95 4,420,223.25 10.17 3,222,485.34 - - 0.675 0.450 0.135 0.135 0.068 0.016 0.016 0.016 0.016 0.016 0.016 0.016
d Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 13.95 218,258.88 10.17 159,117.77 - - 0.033 0.022 0.022
12 Pekerjaan Plat Beton tebal 10 cm - - - - - - - - - -
a Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 m3 - 872,242.00 - - - 17.65 15,395,071.25 22.73 19,826,060.60 - - 2.351 2.766 0.470 0.470 0.235 0.395 0.395 0.395 0.395 0.395 0.395 0.395
b Jaring Kawat baja/Wire Mesh M8 1 lapis kg - 10,697.66 - - - 962.04 10,291,572.26 1,186.92 12,697,260.97 - - 1.572 1.771 0.314 0.314 0.157 0.253 0.253 0.253 0.253 0.253 0.253 0.253
c Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - 44.14 13,986,283.46 57.68 18,276,593.34 - - 2.136 2.550 0.427 0.427 0.214 0.212 0.212 0.212 0.212 0.212 0.212 0.212
d Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 44.14 690,605.52 57.68 902,449.63 - - 0.105 0.126 0.126
-
B PEKERJAAN JARINGAN IPAL KOMUNAL -
1 Pekerjaan Galian Tanah Pipa m3 81.86 67,972.30 5,564,212.49 46.07 3,131,483.87 46.07 3,131,483.87 31.93 2,170,355.55 0.850 0.478 0.478 0.303 0.120 0.120 0.120 0.120 0.043 0.043 0.043 0.043 0.043 0.043 0.043
2 Pengurugan dengan pasir urug m3 6.82 178,388.92 1,216,612.43 11.51 2,053,256.47 11.51 2,053,256.47 14.41 2,570,584.34 0.186 0.314 0.314 0.359 0.105 0.105 0.105 0.051 0.051 0.051 0.051 0.051 0.051 0.051
3 Pengurugan Kembali 1 M3 Galian Tanah m3 24.56 49,023.50 1,204,017.17 30.54 1,497,264.55 30.54 1,497,264.55 12.97 635,966.29 0.184 0.229 0.229 0.089 0.076 0.076 0.076 0.013 0.013 0.013 0.013 0.013 0.013 0.013
4 Pemasangan 1 M Pipa PVC tipe AW 4 m 30.00 90,907.55 2,727,226.46 64.50 5,863,536.89 - - - - 0.417 0.896 - -
5 Saluran Pipa Air Limbah SDR - 41, Dia 15 cm , inc. fitting & Assecories m 343.20 133,200.00 45,714,240.00 375.05 49,956,660.00 375.05 49,956,660.00 - - 6.983 7.630 7.630 - 0.848 0.848 0.848 0.848 0.707
6 Saluran Pipa Air Limbah SDR - 41, Dia 20 cm, , inc. fitting & Assecories m 113.70 203,900.00 23,183,430.00 - - - - - - 3.541 - - -
7 Pemasangan Clean Out Inc. Fitting & Assecories ttk 17.00 185,000.00 3,145,000.00 43.00 7,955,000.00 43.00 7,955,000.00 43.00 7,955,000.00 0.480 1.215 1.215 1.110 0.135 0.135 0.135 0.135 0.113 0.072 0.072 0.072 0.072 0.072 0.072 0.072
8 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 100 org, 20 m3 / hari, (Gali unit 1.00 7,500,000.00 7,500,000.00 1.00 7,500,000.00 - - - - 1.146 1.146 - -
9 Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm unit 4.00 975,000.00 3,900,000.00 4.00 3,900,000.00 - - - - 0.596 0.596 - - - -
10 Pekerjaan Sumur Resapan, Dia 100 cm, Kedalaman 2 m, Inc. Tutup Beton Berlubang ttk 15.00 500,000.00 7,500,000.00 15.00 7,500,000.00 - - - - 1.146 1.146 - - 0.382 0.382
11 Grill Beton Penutup Sumur Resapan unit 20.00 750,000.00 15,000,000.00 15.00 11,250,000.00 - - - - 2.291 1.718 - -
12 Pembongkaran 1 m3 beton bertulang dan membersihkan 1 m3 m3 - 688,832.33 - - - 13.49 9,292,348.18 7.05 4,856,267.95 - - 1.419 0.677 0.237 0.237 0.237 0.074 0.074 0.074 0.074 0.074 0.074 0.074
13 Pembersihan dan Pembuangan Bekas Bongkaran Keluar Area m3 - 19,888.18 - - - 13.49 268,291.48 7.05 140,211.63 - - 0.041 0.020 0.007 0.007 0.007 0.002 0.002 0.002 0.002 0.002 0.002 0.002
14 Pemasangan 1 M Pipa PVC tipe D 6 - - 133,200.00 - - - - - 422.00 56,210,400.00 - - - 7.841 - - - - - 0.249 0.249 0.249 0.249 0.249 0.249 0.249
15 Pemasangan 1 M Pipa PVC tipe D 4 m - 85,618.17 - - - 64.50 5,522,372.20 165.50 14,169,807.73 - - 0.844 1.977 0.094 0.094 0.094 0.094 0.078 0.234 0.234 0.234 0.234 0.234 0.234 0.234
16 Pekerjaan Sumur Resapan kedalaman 4 Buis Beton Dia 80 cm ttk - 474,124.46 - - - 15.00 7,111,866.88 13.00 6,163,617.96 - - 1.086 0.860 1.086 - 0.082
17 Pasang Grill Besi Penutup Sumur Resapan unit - 826,875.00 - - - 15.00 12,403,125.00 15.00 12,403,125.00 - - 1.894 1.730 0.152 0.152 0.152 0.152 0.152 0.152 0.152
C PEKERJAAN PEMASANGAN DAN PENGADAAN INSTALASI IPAL
1 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 50 org, 10 m3 / hari
a Pengadaan Unit IPAL kap 50 org, 10 m3 / hari unit - 110,250,000.00 - - - 1.00 110,250,000.00 1.00 110,250,000.00 - - 16.840 15.380 3.368 2.245 1.355 1.355 1.355 1.355 1.355 1.355 1.355
b Galian Tanah m3 - 67,972.30 - - - 57.21 3,888,695.29 57.21 3,888,695.29 - - 0.594 0.542 0.198 0.198 0.198 0.014 0.014 0.014 0.014 0.014 0.014 0.014
c Pengurugan Kembali 1 M3 Galian Tanah m3 - 49,023.50 - - - 2.39 117,166.17 2.39 117,166.17 - - 0.018 0.016 0.006 0.006 0.006 0.001 0.001 0.001 0.001 0.001 0.001 0.001
d Pengurugan dengan pasir urug m3 - 178,388.92 - - - 1.83 326,254.80 4.98 888,028.96 - - 0.050 0.124 0.007 0.007 0.007 0.007 0.018 0.018 0.018 0.018 0.018 0.018 0.018
e Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Dinding, Lantai dan Tutup m3 - 872,242.00 - - - 11.77 10,266,288.31 11.77 10,266,288.31 - - 1.568 1.432 0.523 0.523 0.523 0.039 0.039 0.039 0.039 0.039 0.039 0.039
Jaring Kawat baja/Wire Mesh M8 kg - 10,697.66 - - - 713.69 7,634,809.58 534.95 5,722,710.68 - - 1.166 0.798 0.389 0.389 0.389 (0.009) (0.009) (0.009) (0.009) (0.009) (0.009) (0.009)
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - 30.14 9,550,217.12 30.14 9,550,217.12 - - 1.459 1.332 0.486 0.486 0.486 0.036 0.036 0.036 0.036 0.036 0.036 0.036
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 30.14 471,564.35 30.14 471,564.35 - - 0.072 0.066 0.024 0.024 0.024 0.002 0.002 0.002 0.002 0.002 0.002 0.002
f Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Inlet m3 - 872,242.00 - - - 0.30 261,672.60 0.30 261,672.60 - - 0.040 0.037 0.013 0.013 0.013 0.005 0.005 0.005 0.005 0.005 0.005 0.005
Jaring Kawat baja/Wire Mesh M8 kg - 10,697.66 - - - 11.06 118,316.07 11.06 118,316.07 - - 0.018 0.017 0.006 0.006 0.006 0.002 0.002 0.002 0.002 0.002 0.002 0.002
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - 0.66 209,128.84 0.66 209,128.84 - - 0.032 0.029 0.011 0.011 0.011 0.004 0.004 0.004 0.004 0.004 0.004 0.004
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 0.66 10,326.23 0.66 10,326.23 - - 0.002 0.001 0.001 0.001 0.001 0.000 0.000 0.000 0.000 0.000 0.000 0.000
g Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Outlet m3 - 872,242.00 - - - 0.41 357,619.22 0.41 357,619.22 - - 0.055 0.050 0.018 0.018 0.018 0.007 0.007 0.007 0.007 0.007 0.007 0.007
Jaring Kawat baja/Wire Mesh M8 kg - 10,697.66 - - - 14.98 160,250.88 14.98 160,250.88 - - 0.024 0.022 0.008 0.008 0.008 0.003 0.003 0.003 0.003 0.003 0.003 0.003
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - 0.96 304,187.41 0.96 304,187.41 - - 0.046 0.042 0.015 0.015 0.015 0.006 0.006 0.006 0.006 0.006 0.006 0.006
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 0.96 15,019.97 0.96 15,019.97 - - 0.002 0.002 0.001 0.001 0.001 0.000 0.000 0.000 0.000 0.000 0.000 0.000
h Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Kolom 15 x 15 cm m3 - 872,242.00 - - - 0.47 409,953.74 0.47 409,953.74 - - 0.063 0.057 0.021 0.021 0.021 (0.001) (0.001) (0.001) (0.001) (0.001) (0.001) (0.001)
Pembesian dg Besi Polos atau Besi Ulir kg - 11,860.70 - - - 119.39 1,416,048.75 119.39 1,416,048.75 - - 0.216 0.198 0.072 0.072 0.072 (0.003) (0.003) (0.003) (0.003) (0.003) (0.003) (0.003)
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - 1.44 456,281.11 1.44 456,281.11 - - 0.070 0.064 0.023 0.023 0.023 (0.001) (0.001) (0.001) (0.001) (0.001) (0.001) (0.001)
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 1.44 22,529.95 1.44 22,529.95 - - 0.003 0.003 0.001 0.001 0.001 (0.000) (0.000) (0.000) (0.000) (0.000) (0.000) (0.000)
i Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Balok 15 x 20 cm m3 - 872,242.00 - - - 0.12 104,669.04 0.12 104,669.04 - - 0.016 0.015 0.005 0.005 0.005 0.002 0.002 0.002 0.002 0.002 0.002 0.002
Pembesian dg Besi Polos atau Besi Ulir kg - 11,860.70 - - - 23.91 283,589.29 23.91 283,589.29 - - 0.043 0.040 0.014 0.014 0.014 0.006 0.006 0.006 0.006 0.006 0.006 0.006
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - 0.55 174,274.03 0.55 174,274.03 - - 0.027 0.024 0.009 0.009 0.009 0.003 0.003 0.003 0.003 0.003 0.003 0.003
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 0.55 8,605.19 0.55 8,605.19 - - 0.001 0.001 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
j Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, pondasi 60 x 60 x 20 cm m3 - 872,242.00 - - - 0.72 628,014.24 0.72 628,014.24 - - 0.096 0.088 0.032 0.032 0.032 0.002 0.002 0.002 0.002 0.002 0.002 0.002
Pembesian dg Besi Polos atau Besi Ulir kg - 11,860.70 - - - 36.93 438,015.58 36.93 438,015.58 - - 0.067 0.061 0.022 0.022 0.022 0.001 0.001 0.001 0.001 0.001 0.001 0.001
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - 1.20 380,234.26 1.20 380,234.26 - - 0.058 0.053 0.019 0.019 0.019 0.001 0.001 0.001 0.001 0.001 0.001 0.001
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - 1.20 18,774.96 1.20 18,774.96 - - 0.003 0.003 0.001 0.001 0.001 0.000 0.000 0.000 0.000 0.000 0.000 0.000
k Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm unit - 975,000.00 - - - - - 3.00 2,925,000.00 - - - 0.408 0.204 0.204
l Tutup Manhole diameter 40 cm bh - 400,000.00 - - - - - 2.00 800,000.00 - - - 0.112 0.056 0.056

2 Pekerjaan pemasangan dan pengadaan instalasi Pengolahan Air Limbah ( IPAL ), kap 20 org, 2 m3 / hari
a Pengadaan Unit IPAL kap 20 org, 2 m3 / hari unit - 38,697,750.00 - - - - - 1.00 38,697,750.00 - - - 5.398 0.771 0.771 0.771 0.771 0.771 0.771 0.771
b Galian Tanah m3 - 67,972.30 - - - - - 26.89 1,827,775.15 - - - 0.255 0.036 0.036 0.036 0.036 0.036 0.036 0.036
c Pengurugan Kembali 1 M3 Galian Tanah m3 - 49,023.50 - - - - - 1.33 65,201.26 - - - 0.009 0.001 0.001 0.001 0.001 0.001 0.001 0.001
d Pengurugan dengan pasir urug m3 - 178,388.92 - - - - - 2.16 385,973.86 - - - 0.054 0.008 0.008 0.008 0.008 0.008 0.008 0.008
e Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Dinding, Lantai dan Tutup m3 - 872,242.00 - - - - - 6.37 5,556,181.52 - - - 0.775 0.111 0.111 0.111 0.111 0.111 0.111 0.111
Jaring Kawat baja/Wire Mesh M8 kg - 10,697.66 - - - - - 270.48 2,893,501.79 - - - 0.404 MC 1 0.058 0.058 0.058 0.058 0.058 0.058 0.058
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - - - 8.68 2,750,361.13 - - - 0.384 0.055 0.055 0.055 0.055 0.055 0.055 0.055
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - - - 8.68 135,805.53 - - - 0.019 0.003 0.003 0.003 0.003 0.003 0.003 0.003
f Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Inlet m3 - 872,242.00 - - - - - 0.17 148,281.14 - - - 0.021 0.003 0.003 0.003 0.003 0.003 0.003 0.003
Jaring Kawat baja/Wire Mesh M8 kg - 10,697.66 - - - - - 6.48 69,320.81 - - - 0.010 0.001 0.001 0.001 0.001 0.001 0.001 0.001
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - - - 0.33 104,564.42 - - - 0.015 0.002 0.002 0.002 0.002 0.002 0.002 0.002
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - - - 0.33 5,163.11 - - - 0.001 0.000 0.000 0.000 0.000 0.000 0.000 0.000
g Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Bak Outlet m3 - 872,242.00 - - - - - 0.23 200,615.66 - - - 0.028 0.004 0.004 0.004 0.004 0.004 0.004 0.004
Jaring Kawat baja/Wire Mesh M8 kg - 10,697.66 - - - - - 8.44 90,288.21 - - - 0.013 0.002 0.002 0.002 0.002 0.002 0.002 0.002
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - - - 0.48 152,093.70 - - - 0.021 0.003 0.003 0.003 0.003 0.003 0.003 0.003
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - - - 0.48 7,509.98 - - - 0.001 0.000 0.000 0.000 0.000 0.000 0.000 0.000
h Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Kolom 15 x 15 cm m3 - 872,242.00 - - - - - 0.35 305,284.70 - - - 0.043 0.006 0.006 0.006 0.006 0.006 0.006 0.006
Pembesian dg Besi Polos atau Besi Ulir kg - 11,860.70 - - - - - 89.54 1,062,006.91 - - - 0.148 0.021 0.021 0.021 0.021 0.021 0.021 0.021
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - - - 1.08 342,210.83 - - - 0.048 0.007 0.007 0.007 0.007 0.007 0.007 0.007
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - - - 1.08 16,897.46 - - - 0.002 0.000 0.000 0.000 0.000 0.000 0.000 0.000
i Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, Balok 15 x 20 cm m3 - 872,242.00 - - - - - 0.08 69,779.36 - - - 0.010 0.001 0.001 0.001 0.001 0.001 0.001 0.001
Pembesian dg Besi Polos atau Besi Ulir kg - 11,860.70 - - - - - 19.41 230,216.15 - - - 0.032 0.005 0.005 0.005 0.005 0.005 0.005 0.005
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - - - 0.40 126,744.75 - - - 0.018 0.003 0.003 0.003 0.003 0.003 0.003 0.003
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - - - 0.40 6,258.32 - - - 0.001 0.000 0.000 0.000 0.000 0.000 0.000 0.000
j Membuat 1 M3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56, pondasi 60 x 60 x 20 cm m3 - 872,242.00 - - - - - 0.54 471,010.68 - - - 0.066 0.009 0.009 0.009 0.009 0.009 0.009 0.009
Pembesian dg Besi Polos atau Besi Ulir kg - 11,860.70 - - - - - 27.69 328,422.73 - - - 0.046 0.007 0.007 0.007 0.007 0.007 0.007 0.007
Memasang Bekisting dg Papan Phenol Film (dipakai 4 kali) m2 - 316,861.88 - - - - - 0.90 285,175.69 - - - 0.040 0.006 0.006 0.006 0.006 0.006 0.006 0.006
Pembongkaran 1 M2 Bekisting m2 - 15,645.80 - - - - - 0.90 14,081.22 - - - 0.002 0.000 0.000 0.000 0.000 0.000 0.000 0.000
k Penutup Manhole IPAL Komunal Besi Dia 60 cm, tbl 1,5 cm unit - 975,000.00 - - - 4.00 3,900,000.00 2.00 1,950,000.00 - - 0.596 0.272 0.136 0.136
l Tutup Manhole diameter 40 cm bh - 400,000.00 - - - - - 2.00 800,000.00 - - - 0.112 0.056 0.056

D PEKERJAAN LAIN - LAIN


1 Pasang Bak Kontrol dengan tutup precast cetak diameter 40 cm bh - 850,000.00 - - - - - 3.00 2,550,000.00 - - - 0.356 0.051 0.051 0.051 0.051 0.051 0.051 0.051
2 Pembersihan dan Pembuangan Bekas Galian Tanah IPAL Keluar Area m3 - 67,972.30 - - - - - 84.10 5,716,470.45 - - - 0.797 MC 0 0.169 0.143 0.143 0.143 0.143 0.032 0.024
3 Pembongkaran 1 M2 Paving Block eksisting m2 - 49,910.10 - - - - - 31.40 1,567,177.00 - - - 0.219 0.031 0.031 0.031 0.031 0.031 0.031 0.031
4 Pemasangan 1 M2 kembali Paving Block eksisting m2 - 64,463.10 - - - - - 31.40 2,024,141.20 - - - 0.282 0.040 0.040 0.040 0.040 0.040 0.040 0.040
5 Pembongkaran dan Pemasangan kembali pipa PDAM yang terdampak galian Ls - 1,500,000.00 - - - - - 1.00 1,500,000.00 - - - 0.209 0.030 0.030 0.030 0.030 0.030 0.030 0.030
6 Check Valve diameter 6 inch+ Reducer diameter 8x6 inch bh - 4,669,087.50 - - - - - 1.00 4,669,087.50 - - - 0.651 0.093 0.093 0.093 0.093 0.093 0.093 0.093
7 Check Valve diameter 6 inch bh - 4,278,582.00 - - - - - 1.00 4,278,582.00 - - - 0.597 0.085 0.085 0.085 0.085 0.085 0.085 0.085
8 Check Valve diameter 4 inch bh - 2,051,002.80 - - - - - 2.00 4,102,005.60 - - - 0.572 0.082 0.082 0.082 0.082 0.082 0.082 0.082
9 Membuat rabat beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 m3 - 723,713.11 - - - - - 1.55 1,121,650.74 - - - 0.156 0.022 0.022 0.022 0.022 0.022 0.022 0.022
10 Grill besi area ipal barat m2 - 828,726.02 - - - - - 1.50 1,243,089.03 - - - 0.173 0.025 0.025 0.025 0.025 0.025 0.025 0.025

Rencana Kemajuan Mingguan 654,697,105.06 654,697,105.06 654,697,105.06 716,855,950.73 100.000 100.000 100.000 100.000 0.095 0.718 0.501 0.937 1.803 2.688 2.964 4.087 6.711 6.870 5.876 8.118 7.585 7.477 10.026 10.362 11.178 4.745 4.328 1.218 1.491 0.221
Rencana Komulatif Kemajuan Mingguan - - - - 0.095 0.813 1.314 2.251 4.054 6.742 9.706 13.793 20.504 27.374 33.251 41.368 48.953 56.430 66.457 76.819 87.997 92.742 97.070 98.288 99.779 100.000
Rencana Kemajuan Mingguan MC 0 - - - 0.095 0.718 0.501 0.937 1.975 3.416 2.985 3.789 5.109 5.356 7.803 10.422 6.709 8.147 11.152 9.516 11.225 5.666 4.074 0.766 1.015 0.228
Rencana Komulatif Kemajuan Mingguan MC 0 - - - 0.095 0.813 1.314 2.251 2.713 6.130 9.115 12.904 17.920 23.276 31.079 41.502 48.211 56.358 67.510 77.026 88.251 93.917 97.991 98.757 99.772 100.000
Rencana Kemajuan Mingguan MC 1 - - - 0.095 0.718 0.501 0.937 1.976 3.418 2.987 3.791 7.292 8.567 7.733 7.941 7.753 11.855 7.909 7.598 7.505 5.879 4.353 4.189 3.105 1.829
Rencana Komulatif Kemajuan Mingguan MC 1 - - - 0.095 0.813 1.314 2.251 2.685 6.103 9.090 12.881 13.784 22.351 30.084 38.024 45.777 57.632 65.541 73.139 80.644 86.523 90.876 95.065 98.171 100.000
Rencana Kemajuan Mingguan MC 2 - - - 0.095 0.718 0.501 0.937 1.976 3.418 2.987 3.791 7.295 8.569 7.735 7.943 7.755 11.858 7.911 4.055 5.709 5.705 5.833 5.705 6.203 6.229
Rencana Komulatif Kemajuan Mingguan MC 2 - - - 0.095 0.813 1.314 2.251 2.685 6.103 9.090 12.881 13.756 22.326 30.060 38.003 45.758 57.615 65.526 64.616 70.325 76.030 81.863 87.568 93.771 100.000
Realisasi Kemajuan Mingguan 0.083 0.030 0.595 0.030 0.662 1.000 2.855 1.236 7.574 8.618 5.326 3.443 10.852 13.176 5.079 7.729 5.168 3.392 5.470 9.879 13.040 100.000
Realisasi Komulatif Kemajuan Mingguan - 0.083 0.113 0.708 0.738 1.401 2.400 5.255 6.491 14.066 22.683 28.009 31.453 42.305 55.481 60.560 63.051 68.219 71.611 77.081 86.960 100.000 100.000
Deviasi (+/-) (0.012) (0.700) (0.606) (1.512) (1.312) (3.729) (3.860) (6.413) 0.282 0.332 (2.075) (6.572) (3.472) (2.151) (4.981) (1.565) (2.106) (4.419) (4.783) (0.608) 6.229 -

Yogyakarta, 18 Oktober 2021


Dibuat Oleh
PEJABAT PEMBUAT KOMITMEN TIM TEKNIS KONSULTAN PENGAWAS PENYEDIA JASA
CV. POLA PRAKARYA CV. ALMEERA RAYA
1. Cicilia Novi hendrawati, M.SC., M.Eng.
NIP. 19781102 200501 2 011

2. Danang Dwi Wahyujati,S.Kom.,M.Eng


NIP. 19761028 199803 1 004

SIGIT SETIAWAN, ST.MT 3. Sudaryanto


NIP. 19690605 199303 1 007 RISMAN WARCHAN ZULIANTO
NIP. 19770623 200501 1 013 Tim Leader Direktur
LAPORAN MINGGUAN

SATUAN KERJA
DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN
KOTA YOGYAKARTA

KEGIATAN
PENATAAN BANGUNAN DAN LINGKUNGAN

PEKERJAAN
PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN

LOKASI
KELURAHAN KLITREN, KOTA YOGYAKARTA

TAHUN ANGGARAN
2021

PENYEDIA JASA
CV. ALMEERA RAYA
TIME SCHEDULE

SATUAN KERJA
DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN
KOTA YOGYAKARTA

KEGIATAN
PENATAAN BANGUNAN DAN LINGKUNGAN

PEKERJAAN
PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN

LOKASI
KELURAHAN KLITREN, KOTA YOGYAKARTA

TAHUN ANGGARAN
2021

PENYEDIA JASA
CV. ALMEERA RAYA
LAPORAN HARIAN

SATUAN KERJA
DINAS PEKERJAAN UMUM, PERUMAHAN DAN KAWASAN PERMUKIMAN
KOTA YOGYAKARTA

KEGIATAN
PENATAAN BANGUNAN DAN LINGKUNGAN

PEKERJAAN
PENATAAN SARPRAS PERMUKIMAN DAN SANITASI KEL. KLITREN

LOKASI
KELURAHAN KLITREN, KOTA YOGYAKARTA

TAHUN ANGGARAN
2021

PENYEDIA JASA
CV. ALMEERA RAYA